HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 105,000 115,000
10 T u k a n g c a t Hr 135,000 145,000
11 K e p . t k . c a t Hr 140,000 150,000
12 T u k a n g p l i t u r Hr 135,000 145,000
13 T u k a n g j a l a n Hr 105,000 115,000
14 T u k a n g g a l i Hr 105,000 115,000
16 T k . l e i d e n g Hr 135,000 145,000
17 M a s i n i s Hr 175,000 200,000
18 P e m b . M a s i n i s Hr 125,000 150,000
19 P e n j a g a a p i Hr 105,000 115,000
20 P e n j a g a m a l a m Hr 105,000 115,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000 230,000
Bulat Belah m3 337,093 280,000
Pecah 10/15 m3 - 270,000
Pecah 5/7 m3 355,500 270,000
Pecah 3/5 m3 355,700 300,000
2 KERIKIL Timbun m3 - 180,000
Sawur / Koral m3 - 170,000
Beton 0,5/1 m3 - 310,000
Beton 1/2 m3 - 330,000
Beton 2/3 m3 - 320,000
Biasa m3 - 210,000
Tras Giling m3 - 280,000
3 BATU BATA ex lokal bh 664 520
5 Keramik 30 X 30 cm m2 - 67,000
20 X 20 cm m2 - 66,000
33 x 33 cm m2 - 66,000
25 x 25 cm m2 - 65,000
15 x 20 cm m2 - 68,000
2,250 2,500
6 Parquet Jati m2 306,600 260,000
7 Batu Paros m2 115,000 125,000
8 Batu Tempel Hitam m2 120,000 120,000
9 GRANITO 40 x 40 cm m2 - 220,000
30 x 30 cm m2 - 300,000
10 Marmer m2 492,600 475,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh - 35,000
Ø 20 cm - 100 cm bh 56,300 40,000
Ø 30 cm - 100 cm bh 77,200 47,500
Ø 50 cm - 100 cm bh 141,700 120,000
Ø 60 cm - 100 cm bh 202,900 196,000
Ø 70 cm - 100 cm bh 244,400 225,000
U 10 cm - 100 cm bh - 30,000
U 15 cm - 100 cm bh - 35,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 20 cm - 100 cm bh 49,200 43,000
U 30 cm - 100 cm bh 58,700 70,000
U 50 cm - 100 cm bh - -
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 12,000 2,500
20 X 20 cm bh 16,000 10,000
25 X 25 cm bh 20,000 16,500
30 X 30 cm bh 22,000 19,000
15 X 25 cm bh 20,000 18,000
15 X 30 cm bh 22,000 12,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 13,050 10,200
besi beton prestress kg - 14,000
besi beton ulir kg 13,600 13,200
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 27,300 26,500 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 33,800 32,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,700 40,500 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 69,500 70,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 94,500 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 190,700 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 292,600 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 311,900 321,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 535,900 900,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg 907,900 - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg 1,221,100 - panjang 4 m
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 6,200 5,800
30 X 60 lbr 13,900 13,200
60 X 120 lbr - 42,000
List Kayu Profil m' 18,000 4,800
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 64,300 60,000
3 HARD BOARD-uk: 4'X 8' lbr 90,100 51,000
GYPROC uk.120cmx240cmx9mm lbr 60,000 65,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr - 53,500
. 120 X 240 X 3 mm lbr - 62,000
. 90 X 210 X 4 mm lbr 85,000 65,000
. 90 X 210 X 9 mm lbr 125,000 120,000
. 90 X 210 X 12 mm lbr - 170,000
. 90 X 210 X 15 mm lbr - 200,000
. 90 X 210 X 18 mm lbr - 250,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr - 50,000
. 120 X 240 X 4 mm lbr 68,200 65,000
. 120 X 240 X 6 mm lbr - 75,000
Multipleks
. 120 X 240 X 9 mm lbr 131,000 110,000
. 120 X 240 X 12 mm lbr 157,700 154,000
. 120 X 240 X 15 mm lbr - 190,000
. 120 X 240 X 18 mm lbr 237,500 222,500
Formika ukuran pintu lbr 75,000 70,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 28,200 30,000
Dempul plamur kg 32,700 25,000
Ambril/amplas lbr 3,400 3,500
Batu Apung kg - 75,000
Cat dasar kg - 40,000
. Emco kg - 65,000
. Yunior 66 (nippon paint) kg 41,500 40,000
- Koas bh - 17,500
. Deculux kg - 67,000
. Siralax ons - 20,000
. Spiritus ltr - 15,000
. Plitur jadi ltr 54,200 65,000
2 TEMBOK
Kalkarium kg - 4,500
Kapur sirih kg - 4,250
Plamur kg 31,700 25,000
Cat Tembok kg - -
Sintex 5 kg - 80,000
Danabride 5 kg - 130,000
Catylac interior 5 kg - 128,000
Mowilex 2,50 kg 338,000 285,000
3 BESI
Menie kg 28,200 36,000
Cat mengkilat kg 59,800 60,000
Cat kg 50,800 40,000
Thinner A ltr 28,500 20,000
Minyak cat ltr 25,200 10,000
Thinner Super ltr 23,500 17,500
Residu (teer/aspal) drum - 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 783,300 975,000
kapasitas 1100 liter. bh 1,650,000 1,650,000
Lem Aica Aibon kg 28,500 75,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 82,000 70,000
5 mm m2 98,800 75,000
2 ES KABUR 3 mm m2 85,000 110,000
5 mm m2 95,000 130,000
3 RAY BAND 3 mm m2 85,100 95,000
5 mm m2 112,400 105,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 2,200 5,000
2 SKAKELAR
Out bauw . Seri bh - 25,000
. Engkel bh - 20,000
. Engkel bh - 17,500
2 group bh - 40,000
3 group bh - 75,000
Arde bh - 32,500
T Biasa bh - 15,500
Arde IB bh - 35,000
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh - 350,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh - 600,000
Fuji 250 watt bh - 1,450,000
Shimizu . 100 watt bh - 470,000
. 90 watt bh - 350,000
Dab . 125 watt bh - 400,000
. 175 watt bh - 425,000
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 - 77,500
Merah/hitam m2 - 90,000
2 HOLLAND Abu-abu m2 - 77,500
Merah/hitam m2 - 90,000
3 UNIDECOR Abu-abu m2 - 85,000
Merah/hitam m2 - 90,000
4 UNI Abu-abu m2 - 85,000
Merah/hitam m2 - 90,000
5 TRIHEX Abu-abu m2 - 85,000
Merah/hitam m2 - 90,000
6 OLYMPIA HEXA Abu-abu m2 - 85,000
7 HEXAGONAL Abu-abu m2 - 90,000
Merah/hitam m2 - 85,000
8 CASTLE Abu-abu m2 - 90,000
9 TRAPEZ Abu-abu m2 - 85,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 - 85,000
11 STANDARD GRASS BLOCK ABU-ABU BH - 7,500
12 BATACO BH - 3,600
13 KANSTEEN m' 21,500 27,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 - 45,000
2 Sliding Pintu J4 bh - 265,000
3 Naco per Daun bh - 20,000
4 Rolling door Besi m2 - 335,000
Rolling door Almunium m2 - 450,000
5 Awning Almunium m2 - 225,000
6 Kusen Almunium 4" Putih m' - 95,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg - 1,425,000
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum - 950,000
9 KACA
Cermin tebal 5 mm m2 221,400 275,000
A. PEKERJAAN PERSIAPAN :
Harga Jumlah
No. Uraian Pekerjaan Volume Jumlah Rp.
Satuan Rp. Harga Rp.
Harga Jumlah
No. Uraian Pekerjaan Volume Jumlah Rp.
Satuan Rp. Harga Rp.
a. PEKERJAAN STRUKTUR :
1 Beton Sloof (15x20) K-175
- Beton 1.58 m3 669,845.00 1,055,005.88
- Besi 251.17 Kg 14,275.80 3,585,652.69
- Begisting 21.00 m2 221,287.00 4,647,027.00
2 Beton Kolom Praktis (15x15) K-175
- Beton 1.71 m3 669,845.00 1,145,434.95
- Besi 309.15 Kg 14,275.80 4,413,363.57
- Begisting 45.60 m2 436,062.55 19,884,452.28
3 Beton Ring Balk (15x20) K-175
- Beton 1.58 m3 669,845.00 1,055,005.88
- Besi 251.17 Kg 14,275.80 3,585,652.69
- Begisting 21.00 m2 459,476.38 9,649,003.98
4 Beton Kolom Struktur (15x30) K-175
-Beton 0.58 m3 669,845.00 385,830.72
-Besi 62.87 Kg 14,275.80 897,519.55
-Begisting 11.52 m2 436,062.55 5,023,440.58
5 Beton Kolom Struktur (15x50) K-175
-Beton 0.48 m3 669,845.00 321,525.60
-Besi 46.28 Kg 14,275.80 660,684.02
-Begisting 8.32 m2 436,062.55 3,628,040.42
6 Beton plat daak t= 10 cm K-175
- Beton 1.98 m3 669,845.00 1,326,293.10
- Besi 489.90 Kg 14,275.80 6,993,714.42
-Begisting 21.75 m2 436,062.55 9,484,360.46
7 Beton Plat Topi-Topi t=8cm K-175
-Beton 0.08 m3 669,845.00 53,587.60
-Besi 25.28 Kg 14,275.80 360,892.22
-Begisting 1.34 m2 436,062.55 584,323.82
8 Gunungan Beton K-175
-Beton 1.21 m3 669,845.00 810,512.45
-Besi 152.12 Kg 14,275.80 2,171,634.70
-Begisting 24.64 m2 459,476.38 11,321,498.00
9 Balok Latei (15x20) K-175
-Beton 0.78 m3 669,845.00 522,479.10
-Besi 124.08 Kg 14,275.80 1,771,341.26
-Begisting 14.30 m2 459,476.38 6,570,512.23
101,908,789.15
b. PEK. RANGKA ATAP DAN ATAP :
1 Konstruksi Rangka Atap Kayu 2.50 m3 13,149,620.00 32,874,050.00
2 Genteng Kodok Glazur 96.73 m2 150,408.50 14,548,713.39
3 Bubungan Kodok 11.30 m' 105,108.96 1,187,731.25
4 Listplank 39.70 m' 154,852.50 6,147,644.25
a. PEKERJAAN STRUKTUR :
1 Beton Sloof (15x20) K-175
54,758,138.89
112,812,083.42
IV. PEK. PAS. KOSEN DAN PARTISI
a. PEKERJAAN PASANGAN KUSEN
1 Pintu Type KPJ (1 Buah) 1.00 Unit 10,522,507.60 10,522,507.60
2 Pintu Type KP1 (2 Buah) 2.00 Unit 3,153,784.70 6,307,569.40
3 Pintu Type KP2 (2 Buah) 2.00 Unit 3,787,287.47 7,574,574.94
4 Pintu Type KP3 (1 Buah) 1.00 Unit 850,000.00 850,000.00
5 Jendela Type KJ1 (1 Buah) 1.00 Unit 1,743,715.02 1,743,715.02
6 Jendela Type KJ2 (2 Buah) 2.00 Unit 3,094,301.16 6,188,602.32
7 Bouven (1 Buah) 1.00 Unit 252,394.62 252,394.62
33,439,363.90
V PEKERJAAN PLAFOND
1 Plafond Gypsum Board t=9mm Rangka Kayu 57.12 m 2
277,794.22 15,867,605.85
2 Plafond Kalsi Board t=6mm Rangka Kayu 1.88 m2 15,716.14 29,546.34
3 List Plafond Gypsum 61.75 m' 21,334.50 1,317,405.38
17,214,557.56
VI PEKERJAAN PASANGAN LANTAI DAN DINDING
1 Urugan Pasir Dibawah Lantai 7.58 m³ 277,145.00 2,100,759.10
2 Lantai Kerja Beton Rabat 3.79 m³ 567,520.25 2,150,901.75
3 Lantai Keramik UK 60x60 Platinum Lexus Grey REC (Polished) 57.12 m2 284,642.60 16,258,785.31
4 Lantai Keramik UK 40x40 Asia Tile Oscar Black (Unpolished) 16.75 m2 253,842.60 4,251,863.55
5 Lantai Keramik UK 25x25 Asia Tile ALPHA grey (Unpolished) 1.88 m2 245,033.80 460,663.54
6 Dinding Lapis Keramik UK 25x40 Platinum Hayden Purple Decor (Lavatory) 11.00 m2 323,693.87 3,560,632.52
7 Dinding Lapis Keramik UK 30x60 Platinum Tracy REC Grey (Dapur) 1.26 m2 339,049.87 427,202.83
8 Dinding Lapis Batu Alam 5.79 m2 314,521.49 1,821,079.41
31,031,888.01
VII PEKERJAAN SANITAIR
1 Closed Duduk + Jet Spray 1.00 bh 2,077,865.00 2,077,865.00
2 Floor Drain 1.00 bh 58,162.50 58,162.50
3 Kran Air 2.00 bh 102,723.50 205,447.00
2,136,027.50
VIII PEKERJAAN CAT-CATAN
1 Cat Tembok Interior 210.00 m 2
17,871.70 3,753,057.00
2 Cat Tembok Eksterior 152.22 m2 17,871.70 2,720,430.17
3 Cat Plafond 59.00 m2 17,871.70 1,054,430.30
7,527,917.47
a. PEKERJAAN DAYA :
1 PLN 2200 VA
-Perizinan PLN
-Uang Jaminan Langganan (UJL) 2200 VA 141.00 310,200.00
-Biaya Penyambungan 2200 VA 937.30 2,062,060.00
-Administrasi, Keur gambar dan Materai 2200 VA 937.30 2,062,060.00
-SLO Konsuil 2200 VA 50.00 110,000.00
-Jaminan Instalasi 2200 VA 50.00 110,000.00
b. PEKERJAAN PANEL :
1 Pemasanagan MCB 1.00 Unit 529,848.00 529,848.00
529,848.00
c. PEKERJAAN KABEL :
1 Dari KWH meter ke Box MCB NYM 3x6mm 6.00 m' 45,000.00 270,000.00
270,000.00
d. PEKERJAAN PENERANGAN :
1 Bulb LED 10 Watt 2.00 bh 39,600.00 79,200.00
2 Bulb LED 12 Watt 7.00 bh 60,000.00 420,000.00
3 Bulb LED 5 Watt 1.00 bh 37,000.00 37,000.00
4 Saklar Tunggal 3.00 bh 40,000.00 120,000.00
5 Saklar Ganda 3.00 bh 60,000.00 180,000.00
6 Titik Inst. Penerangan (NYM 3x2.5mm) Dalam Conduit High Impact Ø 20mm 10.00 bh 95,480.00 954,800.00 1,791,000.00
f. PEKERJAAN AC :
1 Stop Kontak AC 3 kaki 2.00 bh 75,000.00 150,000.00
2 Titik Inst. Stop Kontak (NYM 3x2.5mm) Dalam Conduit High Impact Ø 20mm 2.00 bh 95,480.00 190,960.00
3 Pemasangan AC 2.00 Unit 8,247,296.20 16,494,592.40
16,835,552.40
f. PEKERJAAN AC : 16,835,552.40
g. PEKERJAAN PLUMBING :
1 Meter Air 1.00 Unit 1,265,000.00 1,265,000.00
2 Pipa dari Septic Tank ke Peresapan PVC Ø4" 1.00 m' 31,856.00 31,856.00
3 Pipa Air Bersih :
- Ø 2" 13.00 m' 18,049.35 234,641.55
- Ø 1.5" 1.00 m' 18,049.35 18,049.35
4 Fitting dan Aksessoris :
- Socket Ø 2" 2.00 bh 15,609.00 31,218.00
- Elbow Ø 1.5" 1.00 bh 17,121.50 17,121.50
- Reducer Ø 2" ke Ø 1.5" 1.00 bh 9,196.00 9,196.00
- Tee Reducer Ø 2" ke Ø 1/2" 1.00 bh 17,666.00 17,666.00
- Tee Reducer Ø 1.5" ke Ø 0.5" 1.00 bh 15,463.80 15,463.80
Jumlah
No. Uraian Pekerjaan
Harga Rp.
1 PEKERJAAN PERSIAPAN : 15,439,785.00
2 PEKERJAAN STRUKTUR DAN ATAP : 156,666,928.04
3 PEKERJAAN FINISHING ARSITEKTUR : 265,696,851.65
4 PEKERJAAN MEKANIKAL ELEKTRIKAL : 31,274,368.60
Jumlah 469,077,933.30
PPN 10% 46,907,793.33
Total Harga 515,985,726.62
(m) (m) (m) (m2)
Panjang Lebar Tinggi Luas Penampang Qty
Pembersihan Lahan
PEMBERSIHAN LAHAN 18.00 15.00 1.00
Galian
PONDASI PAGAR 60.58 1.00 1.10 1.00
ROLLAG 0.40 6.65 1.00
PONDASI RUMAH 52.50 1.00 1.10 1.00
Urugan Kembali
URUGAN KEMBALI GALIAN RUMAH
URUGAN KEMBALI GALIAN PAGAR
Pas. Pondasi
PAS.BATU BELAH RUMAH 52.50 0.44 1.00
PAS.BATU BELAH PAGAR 60.58 0.44 1.00
Aanstamping
AANSTAMPING PONDASI RUMAH 52.50 1.00 0.20 1.00
AANSTAMPING PONDASI PAGAR 60.58 1.00 0.20 1.00
Rollag
ROLLAG BATA 0.30 6.65
SLOOF (15x20)
Beton 52.50 0.15 0.20 1.00
Besi
Bekisting 52.50 0.20
KOLOM (15x15)
Beton 0.15 0.15 4.00 19.00
Besi
Bekisting 4.00 0.60 19.00
KOLOM (15x30)
Beton 0.15 0.30 3.20 4.00
Besi
Bekisting 3.20 0.90 4.00
KOLOM (15x50)
Beton 0.15 0.50 3.20 2.00
Besi
Bekisting 3.20 1.30 2.00
Penutup Atap
GENTENG KODOK GLAZUR 11.30 4.28 2.00
BUBUNGAN KODOK 11.30
LISTPLANK KAYU KELAS 1 11.30 8.55
Pas.Dinding
PAS.DINDING BATA
Vol Total
- 270.00 m3
127.05
66.64 m3
2.66 m3 m3
57.75 m3
41.46
57.75 19.25 m3
66.64 22.21
11.97
0.66 m3
5.25 m3 m3
6.06 m3
49.76
23.10 m3 m3
26.66 m3
22.62
10.50 m3
12.12 m3
26.86 m3
1.99 m3
1.58 m3
251.17 kg
21.00 m2
1.71 m3
309.15 kg
45.60 m2
0.58 m3
62.87 kg
11.52 m2
0.48 m3
46.28 kg
8.32 m2
48.36 m2 96.73 m2
11.30 m'
39.70 m'
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016
1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m' 741,405.89 729,382.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 190,867.60 183,634.00
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 471,385.20 877,112.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 623,930.01 951,087.50
PP
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 99,981.86 94,847.50
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 127,923.02 124,289.00
29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 64,416.00 66,599.50
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 12,408.00 14,762.00
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,905,772.54 1,893,914.27
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50
1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m' 741,405.89 729,382.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 190,867.60 183,634.00
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 471,385.20 877,112.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 623,930.01 951,087.50
PP
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 99,981.86 94,847.50
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 127,923.02 124,289.00
22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 71,186.50 76,648.00
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 12,408.00 14,762.00
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,905,772.54 1,893,914.27
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50
10 A.5.1.1.14 Pemasangan Floor Drain buah 72,050.00 58,162.50
NO Koefisien Satuan
Uraian
SANGAN AC
Unit AC Type Wall Mounted 1 1/2 PK
TENAGA
Pekerja
Tukang Listrik
Kepala Tukang
Mandor
BAHAN
IU & OU AC Wall Mounted 1 PK SAMSUNG AR13 Windfree
SANGAN KERAMIK
m2 Keramik Lantai UK 60x60cm
TENAGA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
BAHAN
Keramik UK 60x60 Platinum Lexus Grey REC
Semen Portland
Pasir Pasang
Semen Warna
(Rp) (Rp)
C PERALATAN
D Jumlah A + B + C 192,606.88 184,525.00
E Overhead & Profit (contah 10%) 10% 19,260.69 18,452.50
F Harga Satuan Pekerjaan (D+E) 211,867.57 202,977.50
6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 471,385.20 877,112.50
A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 149,532.00 494,000.00
1.2 m3 Batu Belah 15/20 - 270,000.00 - 324,000.00
0.17 m3 Kapur Pasang (KP) - 300,000.00 - 51,000.00
0.17 Kg Semen Merah (SM) - 200,000.00 - 34,000.00
0.340 m3 Pasir Pasang 439,800.00 250,000.00 149,532.00 85,000.00
C PERALATAN
D Jumlah A + B + C 428,532.00 797,375.00
E Overhead & Profit (contoh 10%) 10% 42,853.20 79,737.50
F Harga Satuan Pekerjaan (D+E) 471,385.20 877,112.50
24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 99,981.86 94,847.50
A Tenaga 28,810.00 31,405.00
L.01 0.180 OH Pekerja 105,000.00 115,000.00 18,900.00 20,700.00
L.02 0.020 OH Tukang batu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Kayu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Besi 125,000.00 135,000.00 2,500.00 2,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.009 OH Mandor 130,000.00 145,000.00 1,170.00 1,305.00
B Bahan 62,082.60 54,820.00
0.002 m3 Kayu Klas III 2,847,200.00 3,290,000.00 5,694.40 6,580.00
0.01 Kg Paku Biasa 2" - 5" 18,740.00 17,000.00 187.40 170.00
3.0 Kg Besi Beton Polos 13,050.00 10,200.00 39,150.00 30,600.00
0.45 Kg Kawat Beton 20,310.00 19,000.00 9,139.50 8,550.00
4.0 Kg Portland Semen 1,177.50 1,150.00 4,710.00 4,600.00
0.006 m3 Pasir Beton 0.00 270,000.00 - 1,620.00
0.009 m3 Kerikil 355,700.00 300,000.00 3,201.30 2,700.00
C PERALATAN
D Jumlah A + B + C 90,892.60 86,225.00
E Overhead & Profit (contoh 10%) 10% 9,089.26 8,622.50
F Harga Satuan Pekerjaan (D+E) 99,981.86 94,847.50
25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 127,923.02 124,289.00
A Tenaga 47,570.00 51,855.00
L.01 0.297 OH Pekerja 105,000.00 115,000.00 31,185.00 34,155.00
L.02 0.033 OH Tukang batu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Kayu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Besi 125,000.00 135,000.00 4,125.00 4,455.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 68,723.65 61,135.00
0.003 m3 Kayu Klas III 2,847,200.00 3,290,000.00 8,541.60 9,870.00
0.02 Kg Paku Biasa 2" - 5" 18,740.00 17,000.00 374.80 340.00
3.6 Kg Besi Beton Polos 13,050.00 10,200.00 46,980.00 36,720.00
0.05 Kg Kawat Beton 20,310.00 19,000.00 1,015.50 950.00
5.5 Kg Portland Semen 1,177.50 1,150.00 6,476.25 6,325.00
0.009 m3 Pasir Beton 0.00 270,000.00 - 2,430.00
0.015 m3 Kerikil 355,700.00 300,000.00 5,335.50 4,500.00
C PERALATAN
D Jumlah A + B + C 116,293.65 112,990.00
E Overhead & Profit (contoh 10%) 10% 11,629.37 11,299.00
F Harga Satuan Pekerjaan (D+E) 127,923.02 124,289.00
11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 78,309.00 76,985.00
12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 80,536.50 79,170.00
2 1.0000 14 1.134
3 1.0000 15 1.155
4 1.0000 16 1.176
5 1.0000 17 1.197
6 1.0000 18 1.219
7 1.0000 19 1.241
8 1.0180 20 1.264
9 1.0370 21 1.287
10 1.0550 22 1.310
11 1.0750 23 1.334
12 1.0940 24 1.358
1 1.0000 13 1.068
2 1.0000 14 1.080
3 1.0000 15 1.092
4 1.0000 16 1.104
5 1.0000 17 1.116
6 1.0000 18 1.129
7 1.0000 19 1.141
8 1.0110 20 1.154
9 1.0220 21 1.166
10 1.0340 22 1.179
11 1.0450 23 1.192
12 1.0570 24 1.206
2 1.0000 14 1.191
3 1.0000 15 1.221
4 1.0000 16 1.252
5 1.0000 17 1.284
6 1.0000 18 1.318
7 1.0000 19 1.350
8 1.0250 20 1.384
9 1.0510 21 1.419
10 1.0780 22 1.455
11 1.1050 23 1.492
12 1.1330 24 1.530
22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 71,186.50 76,648.00
A Tenaga 64,715.00 69,680.00
L.02 0.367 OH Tukang Batu 135,000.000 145,000.000 49,545.000 53,215.000
L.03 0.074 OH Kepala Tukang 140,000.000 150,000.000 10,360.000 11,100.000
L.04 0.037 OH Mandor 130,000.000 145,000.000 4,810.000 5,365.000
B Bahan - -
C PERALATAN - -
D Jumlah A + B + C 64,715.00 69,680.00
E Overhead & Profit (contoh 10%) 10% 6,471.50 6,968.00
F Harga Satuan Pekerjaan (D+E) 71,186.50 76,648.00
C PERALATAN - -
D Jumlah A + B + C 57,200.00 61,985.00
E Overhead & Profit (contoh 10%) 10% 5,720.00 6,198.50
F Harga Satuan Pekerjaan (D+E) 62,920.00 68,183.50
B Bahan - 450,000.00
1 m2 Rolling Allumunium 0.00 450,000.00 - 450,000.00
C PERALATAN
D Jumlah A + B + C 260,500.00 732,250.00
E Overhead & Profit (contoh 10%) 10% 26,050.00 73,225.00
F Harga Satuan Pekerjaan (D+E) 286,550.00 805,475.00
16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 518,067.22 373,679.90
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 531,504.33 378,114.00
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 406,593.39 298,184.70
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 316,070.35 212,757.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,177.50 1,150.00 26,776.35 26,151.00
0.550 m3 Pasir Pasang 439,800.00 250,000.00 241,890.00 137,500.00
0.280 kg Besi Angkur Ø 8 mm 13,050.00 10,200.00 3,654.00 2,856.00
C PERALATAN
D Jumlah A + B + C 369,630.35 271,077.00
E Overhead & Profit (contoh 10%) 10% 36,963.04 27,107.70
F Harga Satuan Pekerjaan (D+E) 406,593.39 298,184.70
19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 416,193.91 301,241.60
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 324,798.10 215,536.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,177.50 1,150.00 21,430.50 20,930.00
0.582 m3 Pasir Pasang 439,800.00 250,000.00 255,963.60 145,500.00
0.280 kg Besi Angkur Ø 8 mm 13,050.00 10,200.00 3,654.00 2,856.00
C PERALATAN
D Jumlah A + B + C 378,358.10 273,856.00
E Overhead & Profit (contoh 10%) 10% 37,835.81 27,385.60
F Harga Satuan Pekerjaan (D+E) 416,193.91 301,241.60
20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 252,936.31 229,861.50
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 260,622.42 232,628.55
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
C PERALATAN
D Jumlah A + B + C 318,211.40 341,170.05
E Overhead & Profit (contoh 10%) 10% 31,821.14 34,117.01
F Harga Satuan Pekerjaan (D+E) 350,032.54 375,287.06
C PERALATAN
D Jumlah A + B + C 317,578.40 338,726.55
E Overhead & Profit (contoh 10%) 10% 31,757.84 33,872.66
F Harga Satuan Pekerjaan (D+E) 349,336.24 372,599.21
22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 121,671.00 131,076.00
26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 314,521.49 331,471.25
C PERALATAN
D Jumlah A + B + C 70,140.00 160,809.00
E Overhead & Profit (contoh 10%) 10% 7,014.00 16,080.90
F Harga Satuan Pekerjaan (D+E) 77,154.00 176,889.90
29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 64,416.00 66,599.50
Tenaga 31,260.00 33,870.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.12 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
Bahan 27,300.00 26,675.00
0.003 m3 Papan Kayu Klas II 8,850,000.00 8,625,000.00 26,550.00 25,875.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 58,560.00 60,545.00
E Overhead & Profit (contoh 10%) 10% 5,856.00 6,054.50
F Harga Satuan Pekerjaan (D+E) 64,416.00 66,599.50
C PERALATAN
D Jumlah A + B + C 73,227.00 80,235.00
E Overhead & Profit (contoh 10%) 10% 7,322.70 8,023.50
F Harga Satuan Pekerjaan (D+E) 80,549.70 88,258.50
C PERALATAN
D Jumlah A + B + C 65,216.40 67,115.00
E Overhead & Profit (contoh 10%) 10% 6,521.64 6,711.50
F Harga Satuan Pekerjaan (D+E) 71,738.04 73,826.50
8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 12,408.00 14,762.00
A Tenaga 11,280.00 12,370.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan - 1,050.00
0.35 Ltr Residu atau Ter 0.00 3,000.00 - 1,050.00
C PERALATAN
D Jumlah A + B + C 11,280.00 13,420.00
E Overhead & Profit (contoh 10%) 10% 1,128.00 1,342.00
F Harga Satuan Pekerjaan (D+E) 12,408.00 14,762.00
C PERALATAN
D Jumlah A + B + C 79,925.00 97,662.50
E Overhead & Profit (contoh 10%) 10% 7,992.50 9,766.25
F Harga Satuan Pekerjaan (D+E) 87,917.50 107,428.75
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,905,772.54 1,893,914.27
A Tenaga 1,080,900.00 1,174,350.00
L.01 6.00 OH Pekerja 105,000.00 115,000.00 630,000.00 690,000.00
L.02 3.00 OH Tukang Batu 135,000.00 145,000.00 405,000.00 435,000.00
L.03 0.30 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 651,620.49 547,390.24
150.0 bh Batu Bata 664.00 520.00 99,600.00 78,000.00
120 Kg Portland Semen 0.11 1,177.50 1,150.00 141,300.00 138,000.00
0.3 m3 Pasir Pasang 0.0121 439,800.00 250,000.00 131,940.00 75,000.00
360 buah Porselen 11 x 11 cm 82.6446 524.39 512.20 188,780.49 184,390.24
6 Kg Semen Nat 15,000.00 12,000.00 90,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 1,732,520.49 1,721,740.24
E Overhead & Profit (contoh 10%) 10% 173,252.05 172,174.02
F Harga Satuan Pekerjaan (D+E) 1,905,772.54 1,893,914.27
9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 357,280.00 399,987.50
A Tenaga 49,800.00 53,625.00
L.01 0.030 OH Pekerja 105,000.00 115,000.00 3,150.00 3,450.00
L.02 0.300 OH Tukang Batu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.030 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 324,800.00 363,625.00
E Overhead & Profit (contoh 10%) 10% 32,480.00 36,362.50
F Harga Satuan Pekerjaan (D+E) 357,280.00 399,987.50
C PERALATAN
D Jumlah A + B + C 65,500.00 52,875.00
E Overhead & Profit (contoh 10%) 10% 6,550.00 5,287.50
F Harga Satuan Pekerjaan (D+E) 72,050.00 58,162.50
28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 89,749.11 89,815.00
cm
A Tenaga 14,880.00 16,180.00
L.01 0.080 OH Pekerja 105,000.00 115,000.00 8,400.00 9,200.00
L.02 0.040 OH Tukang Batu 135,000.00 145,000.00 5,400.00 5,800.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 66,710.10 65,470.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,177.50 1,150.00 41,212.50 40,250.00
0.014 m3 Pasir Pasang 439,800.00 250,000.00 6,157.20 3,500.00
0.014 m3 Pasir Urug 238,600.00 180,000.00 3,340.40 2,520.00
- -
C PERALATAN
D Jumlah A + B + C 86,800.00 382,680.00
E Overhead & Profit (contoh 10%) 10% 8,680.00 38,268.00
F Harga Satuan Pekerjaan (D+E) 95,480.00 420,948.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 307,340.00 529,848.00
A Tenaga 139,700.00 240,840.00
L.01 100 % Pekerja 139,700.00 240,840.00 139,700.00 240,840.00