REKAPITULASI HASIL SURVEI HARGA SATUAN UPAH DAN BAHAN

BIDANG KONTRUKSI
TAHUN 2018

Sumber Data Harga Satuan ( Rp )


No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13

A. UPAH
1 Pekerja oh 75,000 Rp75,000
2 Tukang oh 100,000 Rp100,000
3 Tukang batu oh 100,000 Rp100,000
4 Tukang kayu oh 100,000 Rp100,000
5 Tukang besi oh 125,000 Rp125,000
6 Tukang pipa oh 100,000 Rp100,000
7 Tukang batu/pipa oh 100,000 Rp100,000
8 Tukang pipa oh 100,000 Rp100,000
9 Tukang Las Konstruksi oh 125,000 Rp125,000
10 Tukang Las Biasa oh 125,000 Rp125,000
11 Tukang Besi Konstruksi oh 125,000 Rp125,000
12 Tukang Vibrator oh Rp100,000
13 Tukang Erection oh Rp125,000
14 Tukang Khusus Alumunium oh Rp125,000
15 Tukang Cat oh 125,000 Rp125,000
16 Kepala tukang oh 150,000 Rp150,000
17 Mandor oh 150,000 Rp150,000
20 Ahli alat berat (Mekanik) oh Rp145,000
21 Operator Alat Berat oh 150,000 Rp150,000
22 Pembantu operator oh 100,000 Rp100,000
23 Supir Truk oh 125,000 Rp125,000
24 Kenek Truk oh 85,000 Rp85,000

B MATERIAL/BAHAN

1 Alat-alat bantu set


2 Abu Batu m³ Rp450,000
4 Acuan/multipleks m³
5 Additive liter
6 Agregat Halus m³ Rp334,489
7 Agregat Kasar m³ Rp334,489
8 Agr.Base Kelas S m³
9 Agr.Base Kelas C2 m³
10 Agregat Pecah Mesin 0-5 mm m³ Rp334,489
11 Agregat Pecah Mesin 5-10 & 10-20 mm m³ Rp362,245
12 Agregat Pecah Mesin 20-30 mm m³ Rp342,245
13 Agregat Lolos # 1 " m³
14 Lolos screen1 ukuran ( 0 - 5) m³
15 Lolos screen2 ukuran ( 0 - 5) m³
16 Lolos screen2 ukuran ( 5 - 9,5) m³
17 Lolos screen2 ukuran ( 9.5 - 19,0) m³
18 F i l l e r Kg Rp1,450
19 Air Ltr
20 Air test (air bersih) Ltr
22 Alat Penyuntik Anti Gravitasi Kg
23 Aluminium foil m²
28 Alluminium strip m'
29 Ampelas lembar 5,600 Rp5,000
30 Amplas Kayu / Besi lembar 5,000 Rp5,000
34 Anchorage
35 - hidup buah

Page 1 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
36 - mati buah
37 Angker Mur Baut, dia. 19 Panjang 80cm buah 15,600 Rp15,500
38 Angkur Kabel Prategang, Tipe............... m²
39 Angkur Kabel Prategang, Tipe............ buah
40 Anti Karat / Panas / Bising, Nippe Underseal Klg (@ 5kg)
41 Anti Karat Besi, Beta Zinc Chlorate Klg/kg 79,000 Rp63,800
42 Anti Stripping Agent liter Rp93,200
45 Anchorage buah
46 Anti strpping agent kg
47 Arbocell kg
48 Assetilline botol
49 Aspal Emulsi kg Rp9,812
50 Aspal Minyak kg Rp12,000
54 Aspal Modifikasi kg
55 Asbuton Halus ton
56 Asbuton yang diproses kg
Atap Alumunium super sheet uk. 1,10 x 6 (m), t = 0,3
57 lembar Rp390,000
(berwarna)
64 Atap asbes gelombang uk. 1,80 x 1,05 (m) tebal 4 mm lembar 72,000 Rp62,000
Atap asbes gelombang uk. 1,80 x 1,05 (m) tebal 4 mm
65 lembar 72,000 Rp72,000
gelombang kecil
80 Atap Fiber Glass Tebal, 80 x 180 cm (Gelombang) lembar 152,000 Rp90,000
81 Atap Fiber Glass Tipis, 80 x 180 cm (Gelombang) lembar 138,000 Rp70,000
82 Atap genteng (standar KIA) buah
83 Atap genteng beton ( jenis press) buah
84 Atap genteng kodok buah
85 Atap genteng soka buah
86 Atap metal polos m² Rp25,000
87 Atap metal berbatuan m² Rp52,000
88 Atap metal polos (eks rainbow roof) m²
89 Atap metal berbatuan (eks rainbow roof) m²
90 Atap metal multi sirap (eks rainbow roof) m²
91 Atap genteng metal (eks rainbow roof) m²
93 Atap Polikarbonat m²
94 Atap Rumbia bh
95 Atap seng fiber transparan lembar Rp75,000
97 Atap seng gelombang BJLS 20 uk. 0,914 x 1,829 (m) lembar 54,000 Rp49,000

98 Atap seng gelombang bjls 20 uk. 0,914 x 1,829 (m) Kualitas 2 lembar 44,000 Rp48,000

99 Atap Alluminium lembar


100 Batu Bara kg
101 Bahan Agregat Base kelas A m³
102 Bahan Agregat Base kelas B m³
103 Bahan Agregat Base kelas C m³
104 Bahan Grouting kg
105 Bahan Tanah Timbunan m³
106 Bahan Tanah Puru m³
107 Bahan pengawet: kreosot liter
108 Bahan Pilihan m³
109 Bahan pengaman tebing galian (kayu) m³
110 Bahan Curing m²
111 Bahan Geosynthetic m²
112 Bahan Baja Profil kg
113 Bahan Baja Profil, Mutu BJ 32 kg
114 Bahan Baja Profil, Mutu BJ 41 kg
115 Bahan Baja Profil, Mutu BJ 52 kg
116 Bahan anti rayap kg
117 Baja Struktur Lantai Ortotropik kg
118 Baja Struktur kg

Page 2 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
119 Besi strip kg
124 Baut Mutu Tinggi buah
125 Baja Profil kg
126 Baja Struktur Titik leleh 2500 kg/cm2 kg
127 Baja Struktur Titik leleh 2800 kg/cm2 kg
128 Baja Struktur Titik leleh 3500 kg/cm2 kg
129 Baja Tulangan BJTP 24 (epoxy coated) kg
130 Baja Prategang kg
131 Baja Tulangan (Ulir) U32 kg Rp9,500
132 Baja Tulangan (Ulir) D39 kg
133 Baja Tulangan (Ulir) D48 kg
134 Baja ringan 0.6 mm m' 15,000 Rp14,000
135 Baja ringan 0.75 mm m' 17,000 Rp18,000
136 Baja ringan 1 mm m' 26,000 Rp26,000
137 Baja Bergelombang kg
138 Baja Tulangan (Polos) U24 kg Rp9,500
139 Baja Tulangan (Ulir) D32 kg
140 Bak cuci piring (sink) stainless steel 1 lobang bh 197,500 Rp200,000
141 Bak cuci piring (sink) stainless steel 2 lobang bh 716,000 Rp790,000
142 Bak Kamar Mandi Fiber 50 x 50 bh Rp325,000
143 Bak Kamar Mandi Segi Empat, 53 x 53 x 60 cm 120 ltr bh 359,500
144 Bak Kamar Mandi Segi Empat, 66 x 66 x 70 cm 200 ltr bh 421,000 Rp410,000
145 Bak mandi fibreglass volume 0,15 m³ bh 300,000 Rp300,000
146 Bak mandi fibreglass volume 0,30 m³ bh
147 Bak fibreglass bh
148 Bak mandi jenis bathtub bh Rp3,650,000
153 Bataco bh 3,500 Rp2,500

155 Batu belah 15-20 cm m³/truk 625.000/m³ Rp300,000


(1.875.000 / truk)

156 Batu Pecah Biasa Uk. 3/5 m³ 330,000 Rp330,000


157 Batu Pecah Mekanis (split) Uk. 1/2-2/3 m³ Rp480,000
158 Batu tempel hitam m² 94,000 Rp94,000
159 Batu Alam, Batu Candi RTM, uk. 10cm x 20xm m² 132,000 Rp132,000
160 Batu Alam, Batu Candi RTM, uk. 15cm x 30xm m²
161 Batu Alam, Batu Merah Tasik RTM, uk. 10cm x 20xm m²
162 Batu Alam, Batu Putih Jogja RTM, uk. 10cm x 20xm m²
163 Batu Alam, Batu Putih Jogja RTM, uk. 20cm x 20xm m²
164 Batu alam kuning uk. 10 x 20 cm m²
165 Batu alam hijau uk. 10 x 20 cm m²
166 Batu alam kuning polos uk. 10 x 20 cm m²
167 Batu alam hitam caber uk. 10 x 20 cm m² 132,000 Rp132,000
168 Batu alam hitam adur uk. 10 x 20 cm m² 132,000 Rp132,000
169 Batu alam bever uk. 15 x 30 cm m²
170 Batu sikat m²
171 Batu apung kg
172 Bata rooster unit
173 Batu Bara kg
174 bata berongga bh
175 Batu bata berongga uk. 20 x 20 bh
176 Bata merah bh Rp900
177 Batu belah 10 - 15 (cm) m³ 625,000 Rp300,000
625.000/m³
178 Batu belah 15 - 20 (cm) m³ (1.875.000 / truk) Rp300,000

179 Batu gunung (quarry) m³


180 Batu kali bulat m³ 312,500 Rp312,250
181 Batu kapur m³
182 Batu kerikil ayak / batu saring / kerai m³ 687,500 Rp687,500
183 Batu kerikil dari galian bukit m³ 625,000 Rp625,000

Page 3 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
184 Batu kerikil sungai (dengan pasir) m³ 625,000 Rp625,000
185 Koral beton m³
186 Kerikil m³ 625,000 Rp625,000
187 Kerikil (Maks 30mm) m³
188 Kerikil (2cm/3cm) m³
189 Batu Koral Sikat, Alor - 10kg kg
190 Batu paras m²
191 Batu pecah 0,5 - 1 (cm) m³ 550,000 Rp390,000
192 Batu pecah 1 - 2 (cm) m³ 480,000 Rp390,000
193 Batu pecah 2 - 3 (cm) m³ 410,000 Rp350,000
194 Batu pecah 3 - 5 (cm) m³ 330,000 Rp330,000
195 Batu pecah 5 - 7 (cm) m³ 300,000 Rp300,000
196 Batu pecah 7 - 10 (cm) m³
197 Batu Spit Non Lokal m³
198 Batu Pecah Mesin (Split), uk. 0-5 mm m³
199 Batu Pecah Mesin (Split), uk. 5-10 mm dan 10-20 mm m³ Rp450,000
200 Batu Pecah Mesin (Split), uk. 20-30mm m³
201 Batu Pecah Mesin / kerikil, uk. 5/7 m³
202 Batu teraso m³
203 Baut / mur baja bh
204 Baut klem bh
205 Bensin premium liter Rp7,000
206 Bensin premium (industri) liter
207 Solar liter Rp10,975
208 Bahan Bakar Solar (Industri) liter
209 Bahan Modifikasi kg
210 Bahan Pengisi (Filler) Tambahan kg
211 Besi ø 8 mm m' 4,250 Rp3,600
212 Besi cor/cetak kg
213 Besi angker ø 8 mm kg
214 Besi Profil kg
215 Besi Baja IWF kg
216 Besi Ulir kg
217 Besi beton kg Rp11,570
218 Besi beton jenis press kg
219 Besi beton ø 12 Batang 121,500 Rp110,000
220 Besi beton ø 10 Batang 81,500 Rp70,000
221 Besi beton ø 8 Batang 57,500 Rp45,000
222 Besi beton ø 6 Batang 40,000 Rp30,000
223 Besi beton ulir ø 10 Batang 125,000
224 Besi beton ulir ø 13 Batang 170,000 Rp135,000
228 Besi Beugeul Kuda-kuda kg
229 Besi jaring kawat baja kg
230 Besi Pipa Hydran Bsp, dia. 1" batang Rp35,000
231 Besi Pipa Hydran Bsp, dia. 1,25" batang Rp45,000
232 Besi Pipa Hydran Bsp, dia. 1,5" batang Rp60,000
233 Besi Pipa Hydran Bsp, dia. 2" batang Rp70,000
234 Besi Pipa Hydran Bsp, dia. 2,5" batang Rp110,000
235 Besi Pipa Hydran Bsp, dia. 3" batang Rp130,000
236 Besi Pipa Hydran Bsp, dia. 4" batang Rp200,000
237 Besi prestressed polos kg
238 Besi strip kg 84,300 Rp84,300
239 Besi strip 2 x 3 m' 86,500 Rp86,500
240 Besi siku L 25.25.3 batang Rp35,000
241 Besi siku L 30.30.3 batang Rp89,000
242 Besi siku L 40.40.3 batang Rp110,000
243 Besi siku L 40.40.4 batang Rp145,000
244 Besi siku L 50.50.5 batang Rp250,000
245 Besi siku L 60.60.6 batang Rp400,000

Page 4 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
246 Besi Plat Baja kg
247 Besi Plat tebal 3 mm batang Rp1,000,000
248 Besi Plat tebal 5 mm batang
249 Beton K-500 m³
250 Beton K-400 m³
251 Beton K-350 m³
252 Beton K-300 m³
253 Beton K-250 m³
254 Beton K-175 m³
255 Beton K-125 m³
256 Bilik bambu kering, uk. 1,5 x 4 (m) bh
257 Bilik Bambu Kulit Dalam 2 x 2,5 cm lembar
258 Bilik Bambu Kulit Luar 2 x 2,5 cm lembar
259 Bingkai Beton (Kansteen), 12/15 x 28 x 40 cm m'
260 Bingkai Beton (Kansteen), 12/15 x 28 x 40 cm bh
261 Bingkai Beton (Kansteen), 9 x 20 x 40 cm m'
262 Bingkai Beton (Kansteen), 9 x 20 x 40 cm bh
263 Bliksem spit penangkal petir bh
264 Bondbeam uk. 40 x 20 x 20 (cm) bh
265 Bondek, 1 m lebar m2 156,200 Rp156,200
266 Bordes Plat kg
267 Box Culvert, 100 x 100 x 100 cm m'
268 Box Culvert, 150 x 150 x 100 cm m'
269 Box Culvert, 80 x 80 x 100 cm m'
270 Box sekering, 1 goup / phase bh 9,500 Rp9,500
271 Box sekering, 2 goup / phase bh 27,500 Rp27,500
272 Box sekering, 3 goup / phase bh 82,500 Rp82,500

273 Bubungan atap (nok) alumunium standar 1,00 x 0,30 (m) lbr Rp18,000

274 Bubungan atap (nok) asbes sepasang lembar 63,500 Rp63,500


275 Bubungan atap (nok) genteng (standar KIA) bh
276 Bubungan atap (nok) genteng beton bh
277 Bubungan atap (nok) genteng kodok bh
278 Bubungan atap (nok) genteng soka bh
279 Bubungan atap (nok) metal polos (eks sakura roof) m'
280 Bubungan atap (nok) metal polos (eks Rainbow) m'

281 Bubungan atap (nok) metal berbatuan (eks Rainbow) m'

282 Bubungan atap (nok) metal multi sirap (eks Rainbow) m'

283 Bubungan atap (nok) metal (biasa / polos) lembar 31,500 Rp25,000
284 Bubungan atap (nok) metal (standar Rainbow) m'
285 Bubungan Genteng Flam Pres Bulat, Ex Jatiwangi bh
286 Bubungan Genteng Glasur bh
287 Bubungan Genteng Keramik bh
288 Bubungan Genteng Natural bh
289 Buis beton bertulang ø 100 cm bh
290 Buis beton bertulang ø 15 cm bh
291 Buis beton bertulang ø 20 cm bh
292 Buis beton bertulang ø 30 cm bh
293 Buis beton bertulang ø 40 cm bh
294 Buis beton bertulang ø 50 cm bh
295 Buis beton bertulang ø 60 cm bh
296 Buis beton bertulang ø 80 cm bh
297 Buis beton tak bertulang ø 100 cm buah 400,000 Rp375,000
298 Buis beton tak bertulang ø 80 cm buah 360,000 Rp360,000
299 Buis beton tak bertulang ø 60 cm buah 300,000 Rp300,000
300 Buis beton tak bertulang ø 65 cm - 75 cm bh
301 Buis beton tak bertulang ø 75 cm - 120 cm bh
302 Bunker Oil liter

Page 5 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
303 Cangkul bh Rp42,000
304 Cairan Perekat (Epoxy Resin) psg Rp165,000
305 Casing m²
306 Casting Plaster, 20 Kg zak
307 Cat anti karat (duco danagloos/ICI) klg Rp65,000
308 Cat Exterior Anti Lumut (precoat Mowilek) 2,5ltr Rp100,000
309 Cat interior (eks Mowilex) kg Rp77,500
310 Cat besi kg 91,000 Rp75,000
311 Cat dasar kg 19,100 Rp13,000
312 Cat Galvanis kg
313 Cat genteng kg
314 Cat jalan kg
315 Cat jembatan kg
316 Cat menie kayu kg 48,000 Rp25,000
317 cat Meni besi kg 50,000 Rp25,000
318 Cat minyak kg 70,000 Rp50,000
319 Cat tembok kg 20,800 Rp23,600
320 Cat vernis kaleng 87,000 Rp67,500
321 Cat marka termoplastic kg Rp35,000
322 Cat marka non termoplastic kg Rp15,000
323 Cerucuk m'
324 Chipping m³
325 Chipping (kg) kg
326 Closed duduk Eks Toto buah 1,064,000 Rp1,950,000
327 Closed duduk (lokal) bh 566,000 Rp500,000
328 Closed jongkok keramik bh 203,000 Rp150,000
329 Closed jongkok porcelaint (lokal) bh 190,000 Rp120,000
330 Closed jongkok terasso bh
333 Conblock tebal 6 cm m²
334 Conblock tebal 8 cm m²
335 Conblock, Segi 6 Tebal 10 cm bh 1,600 Rp1,600
336 Conblok, Persegi Uk. 10 x 20 cm Tebal 10 cm bh 1,600 Rp1,600
337 Conblock, Segi 6 Tebal 6 cm bh 1,700 Rp1,700
338 Conblok, Persegi Uk. 10 x 20 cm Tebal 6 cm bh 1,600 Rp1,600
339 Concrete Grouting kg
340 Curing Compound liter
341 Dempul kg Rp39,000
342 Daun pintu aluminium m'
343 Daun jendela aluminium m'
344 Dempul jadi kg 59,000 Rp35,000
345 Dina bolt / ramset bh 5,000 Rp3,100
346 Door stop bh 64,000 Rp40,000
347 Door closer bh 248,500 Rp190,000
348 Door holder bh
352 Ducting (Kabel prestress) m'
353 Ducting (Strand prestress) m'
354 Elastomer bh
355 Elastomer Alam kg
356 Elastomer Sintesis kg
357 Elastomer jenis 1 bh
358 Elastomer jenis 2 bh
359 Elastomer jenis 3 bh
361 Engsel pintu 4" kuningan pasang Rp42,500
362 Engsel pintu 4" biasa pasang Rp19,000
364 Engsel pintu / jendela 3" bh 22,000 Rp24,000
365 Engsel pintu / jendela 4" bh 29,500 Rp31,600
366 Engsel pintu / jendela 5" bh 45,000 Rp4,400
367 Engsel pintu kaca 10 mm set 12,500
369 Engsel jendela 3" kuningan pasang

Page 6 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
370 Engsel jendela 3" biasa pasang Rp10,000
371 Engsel kupu-kupu bh
372 Eternit asbes uk. 1 x 1 (m), tebal 3 mm m² 29,000 Rp20,000
373 Eternit asbes uk. 1 x 1 (m), tebal 5 mm m² 34,000 Rp34,000
374 Eternit asbes uk. 1 x 1 (m), tebal 6 mm m² 37,500 Rp37,500
381 Expansion Cap m²
382 Expansion Tipe Joint Asphaltic Plug m
383 Expansion Join Tipe Rubber m
384 Expansion Join Baja Siku m
385 Expansion Joint Tipe Torma m'
386 Epoxy Bahan Penutup (sealant) kg
387 Epoxy coated kg
388 Fibre jenis e-glass kg
389 Fibre Plat 0,6 x 1,20 (m), tebal 4 mm m²
390 Fibre Plat 1,20 x 2,40 (m), tebal 4 mm m²/lembar Rp68,000
391 Fibre Plat 1,20 x 2,40 (m), tebal 6 mm m²/lembar
392 Fibre Plat 1,20 x 2,40 (m), tebal 8 mm m²/lembar
395 F i l l e r Kg
396 Floor drain steinless bh 58,000 Rp55,000
398 Formica 4" x 8" lbr
400 Gate valve / stop kran ø 1 (inch) kuningan bh 85,000 Rp85,000
401 Gate valve / stop kran ø 1/2 (inch) kuningan bh 51,000 Rp35,000
402 Gate valve / stop kran ø 1 (inch) kuningan bh 85,000 Rp85,000
403 Gate valve / stop kran ø 3/4 (inch) kuningan bh 65,000 Rp65,000
404 Glass block uk. 20 x 20 (cm) bh 30,000 Rp25,000
405 Glass Bead Kg Rp48,000
406 Grass block uk. 50 x 40 cm tebal 6 cm bh
408 Gebalan Rumput m²
409 Gelagar baja kg
410 G r a v e l M3
411 Geotextile lembar
412 Grease (minyak gemuk) kg 18,000 Rp18,000
413 Grendel (biasa) bh 12,500 Rp10,000
414 Grendel (istimewa) bh 33,500 Rp35,000
416 Gypsum board polos uk. 1.22 x 2.44 (m), tebal 9 mm lembar Rp67,000
417 Gorong-gorong Dia.60 cm buah
418 Gorong- gorong Dia.80 cm buah
419 Gorong- gorong Dia.100 cm buah
420 Handle jendela bh Rp20,000
421 Handle pintu bh Rp160,000
422 Handle untuk meubelair (furniture) + kunci bh Rp210,000
423 Handle untuk pintu kaca lebar set
424 Hollow block (H.B. 10) bh
425 Hollow block (H.B. 15) bh
426 Hollow block (H.B. 20) bh
427 Hook bh
428 Huruf Galvanized-Stainless steel m²
429 Ijuk kg
430 Joint Sealent kg
431 Joint Socket Pile 35x35 set
432 Joint Socket Pile 16x16x16 set
433 Jendela besi m²
434 Jendela nako (kerangka + kaca 5 mm) m²
438 Kabel listrik NYY 4 x 2,5 mm² m' Rp17,000
439 Kabel listrik NYY 4 x 4 mm² m' Rp25,000
440 Kabel listrik NYY 1 x 2,5 mm² m' Rp3,100
441 Kabel listrik NYY 1 x 1,5 mm² m' Rp1,900
442 Kabel listrik NYY 2 x 2,5 mm² m' Rp10,000
443 Kabel listrik NYY 2 x 4 mm² m' Rp16,000

Page 7 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
445 Kabel Prategang Kg
446 - Selongsong m'
447 - Baja Prategang kg
448 - Grouting kg
449 Kaca bening tebal 3 mm m² 181,000 Rp181,000
450 Kaca bening tebal 5 mm m² 238,000 Rp238,000
451 Kaca bening tebal 8 mm m²
452 Kaca bening tebal 10 mm m²
453 Kaca bening tebal 12 mm m²
454 Kaca buram tebal 12 mm m²
455 Kaca cermin tebal 5 mm m²
456 Kaca cermin tebal 6 mm m²
457 Kaca cermin tebal 8 mm m²
458 Kaca gelap (ray band) tebal 3 mm m² Rp130,000
459 Kaca gelap (ray band) tebal 5 mm m² Rp170,000
460 Kaca gelap (ray band) tebal 8 mm m²
461 Kaca gelap (ray band) tebal 10 mm m²
462 Kaca wireglassed 5 mm m²
463 Kaca patri tebal 5 mm m²
464 Kaca wireglass tebal 5 mm m²
465 Kain kassa kg Rp30,000
466 Kait angin (istimewa) bh Rp25,000
467 Kait angin jendela biasa bh Rp12,000
468 Kapur m³ Rp60,000
469 Kapur Padam m³
470 Kapur Pasang / Kapur Tembok m³
472 Karpet talang, lebar 0,60 m' m' Rp10,000
473 Kawat ayam m2 Rp25,000
474 Kawat nyamuk Allumunium m² 33,000 Rp26,000
475 Kawat nyamuk logam m² 33,000 Rp33,000
476 Kawat nyamuk plastik m² 34,000 Rp20,000
477 Kawat berduri kg 146000/roll Rp19,500
478 Kawat beton kg 30,500 Rp25,000
479 Kawat bronjong kg
480 Kawat burung m² Rp20,000
481 Kawat harmonika m² 27,500 Rp30,000
482 Kawat kassa / kawat loket m² 25,000 Rp25,000
483 kawat las kg 47,000 Rp25,000
484 kawat las listrik kg 79,500 Rp79,500
485 Kawat seng polos kg 36,000 Rp36,000
486 Kawat burung m²
487 Kawat seng polos kg
488 Kayu Acuan m³
489 Kayu bakar m³
490 Kasau 4/6 bh Rp18,000
491 Kayu Perancah batang 7,000 Rp5,000
492 Kayu dolken ø 8 - 10 (cm) panjang 4 m batang 22,500 Rp27,000
493 Kayu gergajian kelas II, balok m³ Rp2,500,000
494 Kayu gergajian kelas II, papan m³ Rp1,700,000
495 Kayu gergajian kelas II, profil m³ Rp2,500,000
496 Kayu kelas II, Sugu m³ Rp2,000,000
497 Kayu gergajian kelas III, balok m³ Rp1,500,000
498 Kayu gergajian kelas III, papan m³ Rp1,500,000
499 Kayu gergajian kelas III, profil m³ Rp2,250,000
500 Kayu kelas III m³ Rp1,500,000
501 Kayu kelas III, Sugu m³ Rp1,800,000
502 Kayu gergajian kelas IV, balok m³ Rp1,350,000
503 Kayu gergajian kelas IV, papan m³ Rp1,350,000
504 Kayu kelas IV, sugu m3 Rp1,600,000

Page 8 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
505 Kayu untuk konstruksi jembatan m³
506 Kayu untuk perancah buah 7,000 Rp5,000
509 Keramik 20 x 20 (cm) m²/dus 76,500 Rp57,500
510 Keramik 30 cm x 30 cm m²/dus 77,500 Rp52,000
512 Keramik 40 x 40 (cm) m²/dus 76,000 Rp60,000
513 Keramik 60 x 60 (cm) m²/dus 275,000 Rp150,000
516 Keramik Dinding 20 x 20 (cm) m²/dus 76,500 Rp55,000
517 Keramik Dinding 20 x 25 (cm) m²/dus 77,500 Rp63,500
518 Keramik Dinding 25 x 40 (cm) m²/dus Rp75,000
519 Keramik Lantai Granito 40 x 40 (cm) m² 77,000 Rp77,000
520 Kerb Type A buah
521 Kerb jenis 1 buah
522 Kerb jenis 2 buah
523 Kerb jenis 3 buah
524 Kerosen / Minyak Tanah liter
525 Keramik KM/WC anti slip 20 x 20 (cm) m² 76,500 Rp56,500
529 Knee / elbow PVC 1(inch) bh 11,000 Rp4,500
530 Knee / elbow PVC 1/2 (inch) bh 6,500 Rp2,500
531 Knee / elbow PVC 3/4 (inch) bh 7,500 Rp3,400
532 Kompon gypsum kg 25,200 Rp5,000
533 Kotak sabun keramik bh Rp55,000
534 Kran air uk. 1/2 " Biasa bh 28,500 Rp18,000
535 Kran air uk. 1/2 " stanless bh 81,700 Rp45,000
536 Kran air uk. 3/4" Biasa bh Rp22,000
537 Kuas roll bh Rp30,000
538 Kuas uk. 1" bh Rp5,000
539 Kuas uk. 1,5" bh Rp6,000
540 Kuas uk. 3" bh Rp11,000
541 Kunci jendela (lokal) set 37,500 Rp8,000
542 Kunci lemari bh 21,500 Rp19,000
543 Kunci pintu (biasa) set 148,000 Rp120,000
544 Kunci pintu (istimewa) set 302,500 Rp225,000
545 Kunci pintu untuk meubelair (furniture) set Rp95,000
546 Kunci silinder bh 69,000 Rp70,000
547 Kunci tanam biasa bh 156,500 Rp60,000
548 Kunci tanam antik bh Rp140,000
549 Kunci tanam eklusif bh Rp125,000
550 Kunci tanam kamar mandi bh 73,500 Rp50,000
551 Kunci slot bh Rp8,000
552 Kusen pintu / jendela alumunium 3" m' 106,200 Rp15,000
553 Kusen pintu / jendela alumunium 4" m' 106,200 Rp17,000
554 Lampu downlight SL 25 Watt bh
557 Lampu TL 20 W + aksesoris titik Rp105,000
558 Lampu TL 40 W + aksesoris titik Rp125,000
561 Langit-langit Accoustic board / tile uk. 0,30 x 0,30 (m) m²
562 Langit-langit Accoustic board / tile uk. 0,30 x 0,60 (m) m²

563 Langit-langit Accoustic board / tile uk. 0,60 x 1,20 x 0,14 (m) m²

564 Langit-langit Accoustic board / tile uk. 0,60 x 1,20 x 0,15 (m) m²

566 Lem PVC, 1/2 kg bh Rp45,000


567 Lem (standar Aica Aibond) kg 48,000 Rp60,000
568 Lem (standar Fox) kg 45,800 Rp17,000
569 List gypsum profil m' 221,800 Rp221,800
576 Mata Kucing buah
577 Matras Concrete buah
578 Marmer buah
579 Meter box (terpasang) titik
580 Mikro Pile 16x16x16 m'

Page 9 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
581 Mini Timber Pile buah
582 Minyak bekisting liter
583 Minyak Fluks liter
584 Minyak pelarut cat (solvent) liter 32,500 Rp32,500
585 Minyak pelumas liter
586 Minyak tanah (subsidi) liter
587 Minyak tanah (industri) liter
588 Multiplek tebal 12 mm uk. 1.22 x 2.44 (m) lembar Rp190,000
589 Multiplek tebal 15 mm uk. 1.22 x 2.44 (m) lembar Rp245,000
590 Multiplek tebal 18 mm 4 x 8 (inch) lembar Rp295,000
591 Multiplek tebal 6 mm uk. 1.22 x 2.44 (m) lembar Rp90,000
592 Multiplek tebal 9 mm uk. 1.22 x 2.44 (m) lembar Rp135,000
594 Oxygen botol
595 Paku anti Karat kg 29,500 Rp29,500
596 Paku asbes kg 35,000 Rp35,000
597 Paku berbagai ukuran (1/2" - 1") kg 27,500 Rp23,000
598 Paku berbagai ukuran (2" - 5") kg 19,500 Rp14,000
599 Paku biasa 2” – 5” kg 19,500 Rp15,500
600 Paku 5-7cm kg Rp1,500
601 Paku jembatan kg 29,500 Rp25,300
602 Paku kait bh Rp200
603 Paku sekrup kotak 26,000 Rp22,500
604 Paku seng kg 34,000 Rp35,500
605 Paku hak panj 15cm kg
606 Paku tembok kg 56,500 Rp60,000
608 Panel listrik / MCB, 1 group / fase ktk Rp7,000
609 Panel listrik / MCB, 2 group / fase bh Rp20,000
610 Panel listrik / MCB, 3 group / fase bh Rp32,000
611 Panel listrik / MCB, 4 group / fase bh Rp35,000
612 Parquette lantai m²
613 Pasir ayak untuk beton m³ 52,000 Rp25,000
614 Pasir beton m³ Rp100,820
616 Pasir Halus m³ Rp144,650
617 Pasir pasang m³ Rp81,305
618 Pasir Tailing m³
619 Pasir urug / timbun m³ 65,000 Rp50,000
620 Papan cor bh Rp25,000
621 PCI Girder L=17m buah
622 PCI Girder L=21m buah
623 PCI Girder L=26m buah
624 PCI Girder L=32m buah
625 PCI Girder L=36m buah
626 PCI Girder L=41m buah
627 Pegangan pintu/door holder bh
628 Pelat Baja kg
629 Pelat Baja Galvanis kg
630 Pelat Rambu (Eng. Grade) bh Rp216,000
631 Pelat Rambu (High I. Grade) bh Rp243,000
632 Pemantul cahaya (Reflector) bh Rp19,768
633 Pengencer kg Rp10,000
634 Plint keramik bh
635 Pintu alumunium - swing + door closer m²
636 Pintu alumunium - swing + floorhinge m²
637 Pintu besi m²
638 Pintu besi lipat m²
639 Pintu gulung besi m²
640 Pintu plastik untuk kamar mandi bh Rp220,000
641 Rangka Pintu Aluminium m' Rp1,650,000
642 Pintu alumimium + kaca untuk kamar mandi m²

Page 10 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
643 Pipa Baja kg
644 Pipa besi galvanis ø 0,5 (inch) batang
645 Pipa besi galvanis ø 0,75 (inch) batang
646 Pipa besi galvanis ø 1 (inch) batang
647 Pipa besi galvanis ø 1,25 (inch) batang
648 Pipa besi galvanis ø 1,5 (inch) batang
649 Pipa besi galvanis ø 2 (inch) batang
650 Pipa besi galvanis ø 3 (inch) batang
651 Pipa besi galvanis ø 4 (inch) m'
652 Pipa beton ø 20 cm, panjang 1 m' bh
653 Pipa beton ø 60 cm, panjang 1 m' bh
654 Pipa Galvanis Dia. 1.6" batang
655 Pipa Porus m'
656 Pipa PVC ø 1/2 (inch) AW, panjang 4 m m' 25,500 Rp18,000
657 Pipa PVC ø 3/4 (inch) AW, panjang 4 m m' 33,500 Rp24,000
658 Pipa PVC ø 1(inch) AW, panjang 4 m m' 39,500 Rp33,000
659 Pipa PVC ø 1,5 (inch) AW, panjang 4 m m' 77,500 Rp67,000
660 Pipa PVC ø 2 (inch) AW, panjang 4 m m' 95,000 Rp72,000
661 Pipa PVC ø 2,5 (inch) AW, panjang 4 m m' 126,000 Rp110,000
662 Pipa PVC ø 3 (inch) AW, panjang 4 m m' 159,000 Rp143,000
663 Pipa PVC ø 4 (inch) AW, panjang 4 m m' 264,000 Rp218,000
664 Pipa PVC ø 6 (inch) AW, panjang 4 m m' 643,000 Rp505,000
665 Plameur kg Rp39,000
666 Plat Besi Tebal 5 mm lembar
667 Plat Besi Tebal 3 mm lembar Rp1,000,000
668 Plat Besi Tebal 2 mm lembar Rp700,000
669 Plastik polos m²
670 Plastik Filter m²
671 Plint keramik 10 x 15 cm bh Rp5,000
672 Plint keramik 10 x 20 cm bh 3,500 Rp2,500
673 Plint keramik 10 x 40 cm bh 18,000 Rp13,400
674 Plint ubin abu-abu 15 x 20 cm bh
675 Plint ubin granito 10 x 30 cm bh
676 Plint ubin granito 10 x 40 cm bh
679 Plywood uk. 0,30 x 0,60 (m), tebal 4mm lembar
680 Plywood uk. 0,30 x 0,60 (m), tebal 6mm lembar
682 Plywood uk. 1,22 x 2,440 (m), tebal 6mm lembar Rp80,000
683 Plywood uk. 1,22 x 2,44 (m), tebal 4 mm lembar Rp65,000
684 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lembar Rp145,000
685 Polymer Mortar kg
686 Polytene 125 mikron kg
687 Politur liter 53,000 Rp53,000
688 Politur jadi liter 50,000 Rp50,000
689 Politur Kayu, Woodstain Kaleng/liter 89,000 Rp62,000
690 Porcelaint uk. 11 cm x 11 cm bh
691 Profil aluminium T m'
693 Pompa air (dengan otomatis) Besar buah Rp2,700,000
694 Pompa air (dengan otomatis) Kecil buah Rp500,000
700 Rangka atap baja ringan type limas m² 279,000 Rp185,000
701 Rangka metal hollow 40.40.2 mm m'
703 Reducer PVC dari 1/2 (inch) ke 1 (inch) bh 6,000 Rp5,000
704 Reducer PVC dari 1/2 (inch) ke 3/4 (inch) bh 5,500 Rp4,000
705 Reducer PVC dari 3/4 (inch) ke 1 (inch) bh 6,500 Rp4,500
708 Rel Pengaman m'
709 Residu galon Rp93,000
710 Reng baja ringan 0,6 mm m' Rp38,000
711 Rolling dor - alumunium tebal m²
712 Rolling dor - alumunium tipis m²
713 Rooflight fibreglass uk. 1,8 x 0,9 (m) lembar

Page 11 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
714 Rooster Bata, 12 x 11,5 x 24 cm bh
715 Rooster Beton, 20 x 20 x 7 cm bh
716 Rooster block uk. 12 x 11 x 24 (cm) bh
720 Saklar dobel bh Rp19,000
721 seal tape bh Rp8,000
722 Sealent kg Rp30,000
724 Semen merah kg Rp16,300
725 Semen Portland Sak 86,000 Rp75,000
726 Semen putih kg 27,000 Rp2,300
727 Semen warna kg 20,500 Rp16,875
728 Seng plat BJLS m' Rp30,000
731 Sirtu m³
732 Slot jendela bh 9,000 Rp9,600
733 Slot pintu bh 52,500 Rp25,000
735 Socket PVC ø 1 (inch) bh 5,500 Rp4,000
736 Socket PVC ø 1/2 (inch) bh 4,000 Rp2,800
737 Socket PVC ø 3/4 (inch) bh 5,000 Rp3,000
738 Soda api kg Rp22,500
739 Softboard uk. 1,20 x 2,40 (m), tebal 4 mm lembar
740 Sealtape bh Rp10,000
743 Stone Coating kg
744 Stop kontak + instalasi titik Rp15,000
745 Stop kran ø 0,5 (inch) buah Rp12,000
746 Stop kran ø 0,75 (inch) buah Rp15,000
747 Stop kran ø 1 (inch) buah Rp20,000
749 Strorox – 100 kg
762 Strip Bearing buah
763 Tangki air fiberglass (oranye) 1.000 liter bh 1,800,000 Rp1,700,000
764 Tangki air fiberglass (oranye) 2.000 liter bh 3,750,000 Rp3,400,000
765 Tangki air fiberglass (oranye) 3.000 liter bh
766 Tangki air fiberglass (oranye) 500 liter bh Rp1,050,000
767 Tangki air fiberglass (oranye) 1.500 liter bh 2,750,000 Rp2,600,000
768 Tangki air tanles stail (pranye) 1.000 liter bh
769 Tangki air tanles stail (pranye) 1.500 liter bh
770 Teak wood 0,30 x 0,60 (m), tebal 4 mm lembar
771 Teak wood 0,90 x 2,10 (m), tebal 4 mm lembar
772 Teak wood 1,20 x 2,40 (m), tebal 4 mm lembar
773 Tee all socket PVC ø 100 x 50 (mm) unit
774 Tee all socket PVC ø 225 x 100 (mm) unit
775 Tee all socket PVC ø 50 x 50 (mm) unit
776 Tee all socket PVC ø 80 x 50 (mm) unit
777 Tempat sabun keramik bh Rp55,000
778 Residu/Ter kg Rp90,000
779 Tiang Pancang Baja m'
780 Tiang Pancang Beton Pratekan m³
781 Timbunan biasa m³
782 Timbunan pilihan / tanah puru m³ 110,000 Rp110,000
784 Thinner liter 21,100 Rp20,000
785 Triplek tebal 15 mm uk. 1.22 x 2.44 (m) lembar 367,500 Rp245,000
786 Triplek tebal 12 mm uk. 1.22 x 2.44 (m) lembar 245,500 Rp185,000
787 Triplek tebal 8 mm uk. 1.22 x 2.44 (m) lembar 173,000 Rp125,000
788 Triplek tebal 6 mm uk. 1.22 x 2.44 (m) lembar 111,000 Rp90,000
789 Triplek tebal 4 mm uk. 1.22 x 2.44 (m) lembar 97,500 Rp75,000
790 Ubin abu-abu 20 x 20 (cm) bh 6,870 Rp6,870
791 Ubin berwarna 20 x 20 (cm) bh 68,700
794 Ubin motif (mozaik) m²
795 Ubin wafel bh
796 Urinoir Unit
797 Urinoir Keramik Kwalitas no..2 Unit

Page 12 of 45
Sumber Data Harga Satuan ( Rp )
No. Uraian /Nama/ Jenis Barang Satuan SSHBJ 2018 DIPAKAI
BELTIM
1 2 3 12 13
798 Venetion blinds/Vertical blinds (tirai) m²
799 Vertical blinds m²
800 Wallpaper ukuran 50 cm m'
801 Wallpaper m²
802 Lem Wallpapper kg Rp45,000
803 Lem kayu kg Rp17,000
804 Wastafel bh 507,500 Rp400,000
805 Waterdrain unit

Page 13 of 45
REKAPITULASI ANALISA PEKERJAAN KONSTRUKSI

KELOMPOK PEKERJAAN JENIS PEKERJAAN HARGA SATUAN


LEVEL 1
(LEVEL 2) (SUB LEVEL 2) (Rp.)

Divisi 2 2.2.1

PEKERJAAN PENDAHULUAN

9.     Pembersihan 1 m2 lapangan dan perataan 19,250.00

10.A. Pembuatan 1 Buah papan nama proyek 250,000.00

Divisi 2 2.3.1

PEKERJAAN TANAH

1.     Penggalian tanah biasa sedalam 1 m 86,625.00

9.A.     Pengurugan kembali galian 28,820.00

10.   Pemadatan tanah per 20 cm 63,250.00

11.   Pengurugan dengan pasir urug 127,050.00

12. Timbunan pilihan dari sumber galian 133,889.69

3.2.1
Divisi 3
PEKERJAAN PONDASI

2.     Pemasangan pondasi batu belah 1PC:4PP 1,006,445.00

9.     Pemasangan batu kosong (aanstamping) 581,559.00


4.1.1
Divisi 4
PEKERJAAN BETON

1.    Pembuatan 1 m3 beton mutu fc 7,4 MPa (K100) 1,079,489.09

2.    Pembuatan 1 m3 beton mutu fc 9,8 MPa (K125) 1,129,189.58

3.    Pembuatan 1 m beton mutu fc 12,2 MPa (K150)


3
1,166,967.69

4.    Pembuatan 1 m3 lantai kerja beton mutu fc 7,4 MPa 996,347.82

5.    Pembuatan 1 m3 beton mutu fc 14,5 MPa (K175) 1,213,148.78

7.    Pembuatan 1 m3 beton mutu fc 19,3 MPa (K225) 1,289,611.66

17.  Pembesian 10 Kg dengan besi polos atau ulir 173,332.50

4.2.1
Divisi 4 PEKERJAAN BESI DAN
ALUMINIUM
11   Pemasangan Kusen Pintu Aluminium 45,894.75

19 Pemasangan 1 m talang ½ lingkaran 92,372.50

21 Pemasangan rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon 161,221.50

4.4.1
Divisi 4 PEKERJAAN DINDING
PASANGAN
3      Pemasangan dinding bata merah 1 batu camp. 1PC:4PP 593,153.00

9      Pemasangan dinding bata merah 1/2 batu camp. 1PC:4PP 293,320.50

21.A Pemasangan 1 m² dinding bataco camp. 1PC:4PP 69,924.25

4.4.2
Divisi 4
PEKERJAAN PLESTERAN

3.    Pemasangan plesteran 1PC:3PP tebal 15 mm 73,555.90

4.    Pemasangan plesteran 1PC:4PP tebal 15 mm 71,115.00

4.4.3
Divisi 4 PEKERJAAN PENUTUP LANTAI
DAN DINDING
35.B  Pemasangan 1 m2 lantai keramik 40x40 253,706.75

39.  Pemasangan 1 m2 plint keramik 10x20 66,487.44

54.A  Pemasangan 1 m2 dinding keramik 20x25 304,647.75

4.5.1
Divisi 4
PEKERJAAN PLAFOND

7.    Pemasangan langit-langit gypsum board tebal 9 mm 53,711.17

8.A  Pemasangan list langit-langit gypsum 25,311.00

4.5.2
Divisi 4
PEKERJAAN PENUTUP ATAP

32.   Pemasangan 1 m2 atap genteng metal 129,910.00

36.   Pemasangan 1 m2 nok genteng metal 84,260.00

37.A. Pemasangan 1 m2 Rangka Atap Baja Ringan 203,328.00

4.6.2
Divisi 4
PEKERJAAN KUNCI DAN KACA

1.    Pemasangan 1 buah kunci tanam antik 253,495.00

2.     Pemasangan 1 buah kunci tanam biasa 172,425.00

3.     Pemasangan 1 buah kunci tanam Kamar Mandi 133,045.00

4.     Pemasangan 1 buah kunci tanam silinder 145,695.00

5.     Pemasangan 1 buah engsel pintu 51,282.00

6.     Pemasangan 1 buah engsel jendela kupu-kupu 27,582.50

7.     Pemasangan 1 buah engsel angin 58,382.50

9.     Pemasangan 1 buah kait angin 37,207.50

10.  Pemasangan 1 buah doorcloser 297,495.00

11.  Pemasangan 1 buah slot 38,665.00

17.  Pemasangan 1 m kaca polos tebal 5 mm


2
184,189.50

4.7.1
Divisi 4
PEKERJAAN PENGECATAN

10.  Pengecatan 1 m2 tembok baru tanpa plamir 40,887.00

5.1.1
Divisi 5
PEKERJAAN SANITASI

29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” 55,638.00

33. Pemasangan 1 titik Instalasi Listrik 210,100.00


PEMERINTAH KABUPATEN BELITUNG TIMUR

Komplek Perkantoran Terpadu Pemerintah Kabupaten Belitung Timur 33472  +62.719.9220018


E-mail : pu.beltim@yahoo.com & dpu.beltim@yahoo.co.id

HARGA SATUAN UMUM UPAH, BAHAN DAN PERALATAN


BIDANG KONSTRUKSI BERLAKU DI LINGKUNGAN DINAS PEKERJAAN UMUM DAN PENATAAN RUANG TAHUN 2020

No. Uraian/nama/jenis barang satuan rata rata HSU 2019 SSH 2020 Depot Kayu Putra PT. KMN Toko Asia Toko Melan Jaya Toko Sumber Jaya PT. BHSC PT.SMA Depot 13 Harga Dipakai Th.
Sunda Bangunan 2020

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

A. UPAH
1 Pekerja oh Rp 100,000.00 Rp 100,000.00 Rp 100,000.00 Rp 119,100.00 Rp 100,000.00
2 Tukang oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 135,000.00 Rp 125,000.00
3 Tukang batu oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
4 Tukang kayu oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
5 Tukang besi oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
6 Tukang pipa oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
7 Tukang batu/pipa oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
8 Tukang pipa oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
9 Tukang Las Konstruksi oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
10 Tukang Las Biasa oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
11 Tukang Besi Konstruksi oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
12 Tukang Vibrator oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
13 Tukang Erection oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
14 Tukang Khusus Alumunium oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
15 Tukang Cat oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
16 Kepala tukang oh Rp 150,000.00 Rp 150,000.00 Rp 150,000.00 Rp 165,000.00 Rp 150,000.00
17 Mandor oh Rp 150,000.00 Rp 150,000.00 Rp 150,000.00 Rp 175,000.00 Rp 150,000.00
20 Ahli alat berat (Mekanik) oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 145,000.00 Rp 125,000.00
21 Operator Alat Berat oh Rp 150,000.00 Rp 145,000.00 Rp 150,000.00 Rp 150,000.00 Rp 150,000.00
22 Pembantu operator oh Rp 100,000.00 Rp 100,000.00 Rp 100,000.00 Rp 119,100.00 Rp 100,000.00
23 Supir Truk oh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00 Rp 130,000.00 Rp 125,000.00
24 Kenek Truk oh Rp 85,000.00 Rp 85,000.00 Rp 85,000.00 Rp 119,100.00 Rp 85,000.00
B MATERIAL/BAHAN
1 Alat-alat bantu set Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
2 Abu Batu m³ Rp 208,000.00 Rp 208,000.00 Rp 208,000.00
3 Aspal set Rp 12,000.00 Rp 11,922.00 Rp 13,800.00 Rp 13,500.00 Rp 13,500.00 Rp 12,000.00
4 Agregat Halus m³ Rp 334,500.00 Rp 334,489.00 Rp 375,000.00 Rp 416,000.00 Rp 334,500.00
5 Agregat Kasar m³ Rp 320,000.00 Rp 320,000.00 Rp 353,000.00 Rp 395,000.00 Rp 320,000.00
6 Air Ltr Rp 100.00 Rp 100.00 Rp 100.00
7 Air test (air bersih) Ltr Rp 100.00 Rp 100.00 Rp 100.00
9 Aluminium foil m² Rp 700,000.00 Rp 9,125.00 Rp 700,000.00 Rp 700,000.00
10 Agr. Base Kelas A m³ Rp 301,500.00 Rp 301,500.00 Rp 375,000.00 Rp 416,000.00 Rp 301,500.00
11 Agr. Base Kelas B m³ Rp 301,500.00 Rp 301,500.00 Rp 353,000.00 Rp 395,000.00 Rp 301,500.00
12 Agr. Base Kelas C m³ Rp 362,500.00 Rp 362,500.00 Rp 298,000.00 Rp 375,000.00 Rp 362,500.00
14 Alluminium strip m' Rp 28,500.00 Rp 28,500.00 Rp 28,500.00
15 Ampelas lembar Rp 5,000.00 Rp 3,000.00 Rp 6,000.00 Rp 6,000.00 Rp 3,000.00 Rp 5,000.00
16 Amplas Kayu / Besi lembar Rp 6,000.00 Rp 3,000.00 Rp 8,000.00 Rp 8,000.00 Rp 3,000.00 Rp 5,000.00 Rp 6,000.00
20 Angker Mur Baut, dia. 19 Panjang 80cm bh Rp 30,500.00 Rp 30,500.00 Rp 30,500.00 Rp 30,500.00
21 Anti Karat / Panas / Bising, Nippe Underseal Klg (@ 5kg) Rp 144,000.00 Rp 144,000.00 Rp 144,000.00
22 Anti Karat Besi, Beta Zinc Chlorate Klg/kg Rp 75,500.00 Rp 50,000.00 Rp 75,500.00 Rp 75,500.00
23 Anti Stripping Agent liter Rp 60,000.00 Rp 60,000.00 Rp 60,000.00
26 Aspal Emulsi kg Rp 10,000.00 Rp 10,000.00 Rp 10,450.00 Rp 11,500.00 Rp 10,000.00
27 Aspal Minyak kg Rp 11,922.00 Rp 11,922.00 Rp 11,922.00
31 Atap Alumunium super sheet uk. 1,10 x 6 (m), t = 0 lembar Rp 360,000.00 Rp 360,000.00 Rp 360,000.00
38 Atap asbes gelombang uk. 1,80 x 1,05 (m) tebal 4 lembar Rp 82,500.00 Rp 68,000.00 Rp 82,500.00 Rp 82,500.00
39 Atap asbes gelombang uk. 1,80 x 1,05 (m) tebal 4 lembar Rp 80,000.00 Rp 72,000.00 Rp 80,000.00 Rp 80,000.00
54 Atap Fiber Glass Tebal, 80 x 180 cm (Gelombang) lembar Rp 109,250.00 Rp 87,500.00 Rp 138,500.00 Rp 80,000.00 Rp 109,250.00
55 Atap Fiber Glass Tipis, 80 x 180 cm (Gelombang) lembar Rp 84,750.00 Rp 70,000.00 Rp 109,500.00 Rp 60,000.00 Rp 84,750.00
56 Atap genteng (standar KIA) buah Rp 27,600.00 Rp 27,600.00 Rp 27,600.00
57 Atap genteng beton ( jenis press) buah Rp 5,712.50 Rp 5,712.50 Rp 5,712.50
58 Atap genteng kodok buah Rp 7,800.00 Rp 7,800.00 Rp 7,800.00
59 Atap genteng soka buah Rp 5,200.00 Rp 5,200.00 Rp 5,200.00
60 Atap metal polos m2 Rp 40,500.00 Rp 25,000.00 Rp 40,500.00 Rp 40,500.00
61 Atap metal berbatuan m2 Rp 55,000.00 Rp 52,000.00 Rp 55,000.00 Rp 55,000.00
62 Atap metal polos (eks rainbow roof) m2 Rp 30,000.00 Rp 30,000.00 Rp 30,000.00
63 Atap metal berbatuan (eks rainbow roof) m2 Rp 210,546.60 Rp 210,546.60 Rp 210,546.60
64 Atap metal multi sirap (eks rainbow roof) m2 Rp 231,408.98 Rp 231,408.98 Rp 231,408.98
65 Atap genteng metal (eks rainbow roof) m2 Rp 231,408.98 Rp 231,408.98 Rp 231,408.98
67 Atap Polikarbonat m² Rp 200,000.00 Rp 200,000.00 Rp 200,000.00
68 Atap Rumbia bh Rp 5,750.00 Rp 5,750.00 Rp 5,750.00
69 Atap seng fiber transparan lembar Rp 80,000.00 Rp 75,000.00 Rp 80,000.00 Rp 80,000.00
71 Atap seng gelombang BJLS 20 uk. 0,914 x 1,829 (m) lembar Rp 57,750.00 Rp 49,800.00 Rp 64,500.00 Rp 51,000.00 Rp 57,750.00
72 Atap seng gelombang bjls 20 uk. 0,914 x 1,829 (m) K lembar Rp 51,500.00 Rp 45,333.33 Rp 56,000.00 Rp 47,000.00 Rp 51,500.00
73 Atap Alluminium lembar Rp 48,000.00 Rp 48,000.00 Rp 48,000.00
74 Bahan Agregat Base kelas A m³ Rp 301,075.00 Rp 301,075.00 Rp 301,075.00
75 Bahan Agregat Base kelas B m³ Rp 301,075.00 Rp 301,075.00 Rp 301,075.00
76 Bahan Agregat Base kelas C m³ Rp 362,500.00 Rp 362,500.00 Rp 362,500.00
77 Baja Struktur kg Rp 20,200.00 Rp 20,200.00 Rp 20,200.00
78 Besi strip kg Rp 78,887.50 Rp 78,887.50 Rp 84,300.00 Rp 45,000.00 Rp 78,887.50
83 Baja ringan 0.6 mm m' Rp 74,666.67 Rp 83,000.00 Rp 84,000.00 Rp 65,000.00 Rp 75,000.00 Rp 74,666.67
84 Baja ringan 0.75 mm m' Rp 85,250.00 Rp 135,000.00 Rp 102,000.00 Rp 74,000.00 Rp 80,000.00 Rp 85,000.00 Rp 85,250.00
85 Baja ringan 1 mm m' Rp 156,200.00 Rp 145,600.00 Rp 156,200.00 Rp 156,200.00
86 Bak cuci piring (sink) stainless steel 1 lobang bh Rp 244,750.00 Rp 378,100.00 Rp 439,000.00 Rp 130,000.00 Rp 150,000.00 Rp 260,000.00 Rp 244,750.00
87 Bak cuci piring (sink) stainless steel 2 lobang bh Rp 608,500.00 Rp 703,000.00 Rp 634,000.00 Rp 600,000.00 Rp 750,000.00 Rp 450,000.00 Rp 608,500.00
88 Bak Kamar Mandi Fiber 50 x 50 bh Rp 316,666.67 Rp 238,600.00 Rp 300,000.00 Rp 350,000.00 Rp 300,000.00 Rp 316,666.67
89 Bak Kamar Mandi Segi Empat, 53 x 53 x 60 cm 120 l bh Rp 369,000.00 Rp 264,000.00 Rp 369,000.00 Rp 369,000.00
90 Bak Kamar Mandi Segi Empat, 66 x 66 x 70 cm 200 l bh Rp 421,000.00 Rp 360,000.00 Rp 421,000.00 Rp 421,000.00
91 Bak mandi fibreglass volume 0,15 m³ bh Rp 397,000.00 Rp 300,000.00 Rp 397,000.00 Rp 397,000.00
92 Bak mandi fibreglass volume 0,30 m³ bh Rp 338,400.00 Rp 338,400.00 Rp 338,400.00
93 Bak fibreglass bh Rp 350,000.00 Rp 350,000.00 Rp 350,000.00
94 Bak mandi jenis bathtub bh Rp 3,395,000.00 Rp 2,500,000.00 Rp 3,685,000.00 Rp 3,800,000.00 Rp 2,700,000.00 Rp 3,395,000.00
99 Bataco bh Rp 2,500.00 Rp 2,400.00 Rp 3,250.00 Rp 2,500.00 Rp 2,500.00 Rp 2,500.00
100 Batu belah 15-20 cm m³ Rp 525,000.00 Rp 300,000.00 Rp 625,000.00 Rp 250,000.00 Rp 700,000.00 Rp 525,000.00
101 Batu tempel hitam m² Rp 94,000.00 Rp 94,000.00 Rp 94,000.00
102 Batu Alam, Batu Candi RTM, uk. 10cm x 20xm m² Rp 132,000.00 Rp 132,000.00 Rp 132,000.00
103 Batu Alam, Batu Candi RTM, uk. 15cm x 30xm m² Rp 159,100.00 Rp 159,100.00 Rp 159,100.00
104 Batu Alam, Batu Merah Tasik RTM, uk. 10cm x 20x m² Rp 123,700.00 Rp 123,700.00 Rp 123,700.00
105 Batu Alam, Batu Putih Jogja RTM, uk. 10cm x 20xm m² Rp 128,500.00 Rp 128,500.00 Rp 128,500.00
106 Batu Alam, Batu Putih Jogja RTM, uk. 20cm x 20xm m² Rp 133,300.00 Rp 133,300.00 Rp 133,300.00
114 Batu apung kg Rp 3,000.00 Rp 3,000.00 Rp 3,000.00
115 Bata rooster unit Rp 10,000.00 Rp 10,000.00 Rp 10,000.00
116 Batu Bara kg Rp 1,450.00 Rp 1,450.00 Rp 1,450.00
117 bata berongga bh Rp 5,000.00 Rp 5,000.00 Rp 5,000.00
118 Batu bata berongga uk. 20 x 20 bh Rp 15,000.00 Rp 15,000.00 Rp 15,000.00
119 Bata merah bh Rp 2,850.00 Rp 1,125.00 Rp 4,500.00 Rp 1,200.00 Rp 2,850.00
120 Batu belah 10 - 15 (cm) m³ Rp 300,000.00 Rp 300,000.00 Rp 625,000.00 Rp 300,000.00
121 Batu belah 15 - 20 (cm) m³ Rp 300,000.00 Rp 300,000.00 Rp 625,000.00 Rp 300,000.00
122 Batu gunung (quarry) m³ Rp 417,818.75 Rp 362,887.50 Rp 472,750.00 Rp 417,818.75
123 Batu kali bulat m³ Rp 202,500.00 Rp 312,500.00 Rp 312,500.00 Rp 250,000.00 Rp 210,000.00 Rp 220,000.00 Rp 202,500.00
124 Batu kapur m³ Rp 199,462.50 Rp 148,925.00 Rp 250,000.00 Rp 199,462.50
125 Batu kerikil ayak / batu saring / kerai m³ Rp 252,000.00 Rp 252,000.00 Rp 769,000.00 Rp 252,000.00
126 Batu kerikil dari galian bukit m³ Rp 214,800.00 Rp 214,800.00 Rp 625,000.00 Rp 214,800.00
127 Batu kerikil sungai (dengan pasir) m³ Rp 247,200.00 Rp 247,200.00 Rp 625,000.00 Rp 247,200.00
128 Koral beton m³ Rp 109,375.00 Rp 109,375.00 Rp 109,375.00
129 Kerikil m³ Rp 327,700.00 Rp 327,700.00 Rp 327,700.00
130 Kerikil (Maks 30mm) m³ Rp 433,200.00 Rp 433,200.00 Rp 433,200.00
131 Kerikil (2cm/3cm) m³ Rp 366,500.00 Rp 366,500.00 Rp 366,500.00
132 Batu Koral Sikat, Alor - 10kg kg Rp 109,800.00 Rp 109,800.00 Rp 109,800.00
133 Batu paras m² Rp 342,300.00 Rp 342,300.00 Rp 342,300.00
134 Batu pecah 0,5 - 1 (cm) m³ Rp 615,000.00 Rp 540,000.00 Rp 615,000.00 Rp 615,000.00
135 Batu pecah 1 - 2 (cm) m³ Rp 480,000.00 Rp 468,000.00 Rp 480,000.00 Rp 480,000.00
136 Batu pecah 2 - 3 (cm) m³ Rp 410,000.00 Rp 408,000.00 Rp 410,000.00 Rp 410,000.00
137 Batu pecah 3 - 5 (cm) m³ Rp 330,000.00 Rp 324,000.00 Rp 330,000.00 Rp 330,000.00
138 Batu pecah 5 - 7 (cm) m³ Rp 300,000.00 Rp 300,000.00 Rp 300,000.00 Rp 300,000.00
139 Batu pecah 7 - 10 (cm) m³ Rp 226,500.00 Rp 226,500.00 Rp 226,500.00
140 Batu Spit Non Lokal m³ Rp 487,500.00 Rp 487,500.00 Rp 487,500.00
141 Batu Pecah Mesin (Split), uk. 0-5 mm m³ Rp 671,462.50 Rp 671,462.50 Rp 671,462.50
142 Batu Pecah Mesin (Split), uk. 5-10 mm dan 10-20 m³ Rp 464,375.00 Rp 464,375.00 Rp 464,375.00
143 Batu Pecah Mesin (Split), uk. 20-30mm m³ Rp 548,600.00 Rp 548,600.00 Rp 548,600.00
144 Batu Pecah Mesin / kerikil, uk. 5/7 m³ Rp 211,762.50 Rp 211,762.50 Rp 211,762.50
145 Batu teraso m³ Rp 176,000.00 Rp 176,000.00 Rp 176,000.00
146 Baut / mur baja bh Rp 10,200.00 Rp 10,200.00 Rp 10,200.00
147 Baut klem bh Rp 4,000.00 Rp 4,000.00 Rp 4,000.00
148 Bensin premium liter Rp 6,450.00 Rp 6,500.00 Rp 8,000.00 Rp 6,450.00
149 Bensin premium (industri) liter Rp 9,300.00 Rp 9,300.00 Rp 9,300.00
150 Solar liter Rp 12,000.00 Rp 7,800.00 Rp 14,000.00 Rp 10,200.00 Rp 12,000.00
151 Bahan Bakar Solar (Industri) liter Rp 13,400.00 Rp 13,400.00 Rp 13,400.00
152 Besi ø 8 mm m' Rp 11,000.00 Rp 3,500.00 Rp 11,000.00 Rp 11,000.00
153 Besi cor/cetak kg Rp 11,000.00 Rp 11,000.00 Rp 11,000.00
154 Besi angker ø 8 mm kg Rp 10,000.00 Rp 10,000.00 Rp 10,000.00
155 Besi Profil kg Rp 20,200.00 Rp 17,250.00 Rp 17,250.00
156 Besi Baja IWF kg Rp 20,200.00 Rp 17,250.00 Rp 17,250.00
157 Besi Ulir kg Rp 13,400.00 Rp 9,610.00 Rp 13,400.00 Rp 40,000.00 Rp 13,400.00
158 Besi beton kg Rp 13,000.00 Rp 9,610.00 Rp 13,400.00 Rp 13,400.00
159 Besi beton jenis press kg Rp 10,000.00 Rp 10,000.00 Rp 10,000.00
170 Besi strip kg Rp 84,300.00 Rp 52,800.00 Rp 84,300.00 Rp 84,300.00
171 Besi strip 2 x 3 m' Rp 86,500.00 Rp 50,000.00 Rp 86,500.00 Rp 86,500.00
172 Besi siku L 30.30.3 batang Rp 96,500.00 Rp 30,000.00 Rp 93,000.00 Rp 100,000.00 Rp 96,500.00
173 Besi Plat Baja kg Rp 17,250.00 Rp 17,250.00 Rp 17,250.00
191 Bubungan atap (nok) alumunium standar 1,00 x 0,30 lbr Rp 48,250.00 Rp 48,250.00 Rp 48,250.00
192 Bubungan atap (nok) asbes sepasang lembar Rp 67,500.00 Rp 51,833.33 Rp 67,500.00 Rp 67,500.00
193 Bubungan atap (nok) genteng (standar KIA) bh Rp 12,000.00 Rp 12,000.00 Rp 12,000.00
194 Bubungan atap (nok) genteng beton bh Rp 11,900.00 Rp 11,900.00 Rp 11,900.00
195 Bubungan atap (nok) genteng kodok bh Rp 7,000.00 Rp 7,000.00 Rp 7,000.00
196 Bubungan atap (nok) genteng soka bh Rp 7,100.00 Rp 7,100.00 Rp 7,100.00
197 Bubungan atap (nok) metal polos (eks sakura roof) m' Rp 35,000.00 Rp 35,000.00 Rp 35,000.00
198 Bubungan atap (nok) metal polos (eks Rainbow) m' Rp 31,500.00 Rp 28,000.00 Rp 31,500.00 Rp 31,500.00
199 Bubungan atap (nok) metal berbatuan (eks Rainbo m' Rp 55,000.00 Rp 55,000.00 Rp 55,000.00
200 Bubungan atap (nok) metal multi sirap (eks Rainbo m' Rp 99,853.66 Rp 99,853.66 Rp 99,853.66
204 Bubungan Genteng Glasur bh Rp 10,000.00 Rp 10,000.00 Rp 10,000.00
205 Bubungan Genteng Keramik bh Rp 8,000.00 Rp 8,000.00 Rp 8,000.00
206 Bubungan Genteng Natural bh Rp 8,000.00 Rp 8,000.00 Rp 8,000.00
207 Buis beton bertulang ø 100 cm bh Rp 461,000.00 Rp 437,000.00 Rp 461,000.00 Rp 461,000.00
208 Buis beton bertulang ø 15 cm bh Rp 85,800.00 Rp 85,800.00 Rp 85,800.00
209 Buis beton bertulang ø 20 cm bh Rp 70,000.00 Rp 70,000.00 Rp 70,000.00
210 Buis beton bertulang ø 30 cm bh Rp 95,000.00 Rp 95,000.00 Rp 95,000.00
211 Buis beton bertulang ø 40 cm bh Rp 120,000.00 Rp 120,000.00 Rp 120,000.00
212 Buis beton bertulang ø 50 cm bh Rp 150,000.00 Rp 150,000.00 Rp 150,000.00
213 Buis beton bertulang ø 60 cm bh Rp 300,000.00 Rp 250,000.00 Rp 300,000.00 Rp 300,000.00
214 Buis beton bertulang ø 80 cm bh Rp 430,000.00 Rp 415,000.00 Rp 430,000.00 Rp 430,000.00
215 Buis beton tak bertulang ø 100 cm buah Rp 333,000.00 Rp 333,000.00 Rp 333,000.00
216 Buis beton tak bertulang ø 80 cm buah Rp 151,500.00 Rp 151,500.00 Rp 151,500.00
217 Buis beton tak bertulang ø 60 cm buah Rp 250,000.00 Rp 250,000.00 Rp 250,000.00
218 Buis beton tak bertulang ø 65 cm - 75 cm bh Rp 325,000.00 Rp 325,000.00 Rp 325,000.00
219 Buis beton tak bertulang ø 75 cm - 120 cm bh Rp 350,500.00 Rp 350,500.00 Rp 350,500.00
220 Cangkul bh Rp 61,666.67 Rp 51,580.00 Rp 65,000.00 Rp 75,000.00 Rp 45,000.00 Rp 61,666.67
221 Casting Plaster, 20 Kg zak Rp 48,955.56 Rp 48,955.56 Rp 48,955.56
222 Cat anti karat (duco danagloos/ICI) klg Rp 57,145.83 Rp 57,145.83 Rp 57,145.83
223 Cat Exterior Anti Lumut (precoat Mowilek) kg Rp 110,000.00 Rp 94,300.00 Rp 110,000.00 Rp 110,000.00
224 Cat interior (eks Mowilex) kg Rp 65,000.00 Rp 63,500.00 Rp 65,000.00 Rp 65,000.00
225 Cat besi kg Rp 73,000.00 Rp 51,200.00 Rp 56,000.00 Rp 90,000.00 Rp 73,000.00
226 Cat dasar kg Rp 26,500.00 Rp 14,500.00 Rp 27,500.00 Rp 25,500.00 Rp 26,500.00
227 Cat genteng kg Rp 27,500.00 Rp 27,500.00 Rp 27,500.00
228 Cat jalan kg Rp 49,600.00 Rp 49,600.00 Rp 49,600.00
229 Cat jembatan kg Rp 45,900.00 Rp 45,900.00 Rp 45,900.00
230 Cat menie kayu kg Rp 23,333.33 Rp 23,333.33 Rp 23,333.33
231 cat Meni besi kg Rp 24,375.00 Rp 24,375.00 Rp 24,375.00
232 Cat minyak kg Rp 56,500.00 Rp 52,000.00 Rp 56,000.00 Rp 57,000.00 Rp 56,500.00
233 Cat tembok kg Rp 75,000.00 Rp 33,975.00 Rp 57,500.00 Rp 27,500.00 Rp 25,000.00 Rp 75,000.00
234 Cat vernis kg Rp 70,281.25 Rp 70,281.25 Rp 70,281.25
235 Cat marka termoplastic kg Rp 38,483.33 Rp 38,483.33 Rp 27,000.00 Rp 38,483.33
236 Cat marka non termoplastic kg Rp 23,000.00 Rp 45,900.00 Rp 23,000.00 Rp 23,000.00
237 Closed duduk Eks Toto buah Rp 2,500,000.00 Rp 1,712,500.00 Rp 1,950,000.00 Rp 3,250,000.00 Rp 2,300,000.00 Rp 2,500,000.00
238 Closed duduk (lokal) bh Rp 950,000.00 Rp 725,000.00 Rp 650,000.00 Rp 1,250,000.00 Rp 950,000.00
239 Closed jongkok keramik bh Rp 376,666.67 Rp 194,000.00 Rp 400,000.00 Rp 600,000.00 Rp 130,000.00 Rp 376,666.67
240 Closed jongkok porcelaint (lokal) bh Rp 150,000.00 Rp 130,000.00 Rp 150,000.00 Rp 150,000.00 Rp 150,000.00
241 Closed jongkok terasso bh Rp 300,000.00 Rp 300,000.00 Rp 300,000.00
244 Conblock tebal 6 cm m² Rp 75,750.00 Rp 75,750.00 Rp 75,750.00
245 Conblock tebal 8 cm m² Rp 77,562.50 Rp 77,562.50 Rp 77,562.50
246 Conblock, Segi 6 Tebal 10 cm bh Rp 2,000.00 Rp 1,566.67 Rp 2,000.00 Rp 2,000.00
247 Conblok, Persegi Uk. 10 x 20 cm Tebal 10 cm bh Rp 2,000.00 Rp 1,566.67 Rp 2,000.00 Rp 2,000.00
248 Conblock, Segi 6 Tebal 6 cm bh Rp 1,600.00 Rp 1,700.00 Rp 1,700.00 Rp 1,500.00 Rp 1,600.00
249 Conblok, Persegi Uk. 10 x 20 cm Tebal 6 cm bh Rp 1,500.00 Rp 1,600.00 Rp 1,500.00 Rp 1,500.00
250 Dempul kg Rp 35,750.00 Rp 35,750.00 Rp 35,750.00
251 Daun pintu aluminium m' Rp 103,500.00 Rp 103,500.00 Rp 103,500.00
252 Daun jendela aluminium m' Rp 86,250.00 Rp 86,250.00 Rp 86,250.00
253 Dempul jadi kg Rp 49,216.67 Rp 46,666.67 Rp 67,650.00 Rp 40,000.00 Rp 40,000.00 Rp 49,216.67
254 Dina bolt / ramset bh Rp 6,000.00 Rp 3,562.50 Rp 6,000.00 Rp 6,000.00
255 Door stop bh Rp 34,333.33 Rp 35,000.00 Rp 43,000.00 Rp 35,000.00 Rp 25,000.00 Rp 34,333.33
256 Door closer bh Rp 195,000.00 Rp 145,000.00 Rp 224,500.00 Rp 250,000.00 Rp 200,000.00 Rp 195,000.00 Rp 195,000.00
257 Door holder bh Rp 75,000.00 Rp 75,000.00 Rp 75,000.00
261 Elastomer bh Rp 470,655.00 Rp 470,655.00 Rp 470,655.00
262 Elastomer jenis 1 bh Rp 750,000.00 Rp 750,000.00 Rp 750,000.00
263 Elastomer jenis 2 bh Rp 850,000.00 Rp 850,000.00 Rp 850,000.00
264 Elastomer jenis 3 bh Rp 950,000.00 Rp 950,000.00 Rp 950,000.00
266 Engsel pintu 4" kuningan pasang Rp 41,666.67 Rp 39,000.00 Rp 50,000.00 Rp 40,000.00 Rp 35,000.00 Rp 41,666.67
267 Engsel pintu 4" biasa pasang Rp 24,000.00 Rp 25,380.00 Rp 34,000.00 Rp 18,000.00 Rp 20,000.00 Rp 24,000.00
269 Engsel pintu / jendela 3" bh Rp 21,500.00 Rp 23,666.67 Rp 22,000.00 Rp 14,000.00 Rp 35,000.00 Rp 15,000.00 Rp 21,500.00
270 Engsel pintu / jendela 4" bh Rp 29,250.00 Rp 32,697.22 Rp 34,000.00 Rp 18,000.00 Rp 45,000.00 Rp 20,000.00 Rp 29,250.00
271 Engsel pintu / jendela 5" bh Rp 46,750.00 Rp 43,560.00 Rp 52,000.00 Rp 50,000.00 Rp 55,000.00 Rp 30,000.00 Rp 46,750.00
272 Engsel pintu kaca 10 mm set Rp 500,000.00 Rp 22,416.67 Rp 500,000.00 Rp 500,000.00
274 Engsel jendela 3" kuningan pasang Rp 25,000.00 Rp 25,966.67 Rp 25,000.00 Rp 25,000.00
275 Engsel jendela 3" biasa pasang Rp 15,000.00 Rp 14,425.00 Rp 15,000.00 Rp 15,000.00
276 Engsel kupu-kupu bh Rp 10,000.00 Rp 15,000.00 Rp 10,000.00 Rp 10,000.00
277 Eternit asbes uk. 1 x 1 (m), tebal 4 mm m² Rp 24,000.00 Rp 22,250.00 Rp 25,000.00 Rp 23,000.00 Rp 24,000.00
278 Eternit asbes uk. 1 x 1 (m), tebal 5 mm m² Rp 34,000.00 Rp 30,200.00 Rp 34,000.00 Rp 34,000.00
279 Eternit asbes uk. 1 x 1 (m), tebal 6 mm m² Rp 37,500.00 Rp 37,000.00 Rp 37,500.00 Rp 37,500.00
280 Expansion Joint tipe Baja Siku m Rp 225,300.00 - Rp 225,300.00
281 FASTPEC GRS-1 Uk.330 x 330 x 360 Unit Rp 500,000.00 - Rp 500,000.00
282 FASTPEC GRS-2 Uk.550 x 450 x 500 Unit Rp 850,000.00 - Rp 850,000.00
283 FASTPEC GRS-3 Uk.315 x 380 Unit Rp 450,000.00 - Rp 450,000.00
284 FASTPEC GRS-4 Uk.450 x 430 Unit Rp 750,000.00 - Rp 750,000.00
285 FASTPEC GRS-5 Uk.500 x 430 Unit Rp 850,000.00 - Rp 850,000.00
286 Fibre Plat 0,6 x 1,20 (m), tebal 4 mm m² Rp 68,000.00 Rp 68,000.00 Rp 68,000.00
287 Fibre Plat 1,20 x 2,40 (m), tebal 4 mm m²/lembar Rp 68,333.33 Rp 71,875.00 Rp 65,000.00 Rp 70,000.00 Rp 70,000.00 Rp 68,333.33
288 Fibre Plat 1,20 x 2,40 (m), tebal 6 mm m²/lembar Rp 133,100.00 Rp 133,100.00 Rp 133,100.00
289 Fibre Plat 1,20 x 2,40 (m), tebal 8 mm m²/lembar Rp 131,000.00 Rp 131,000.00 Rp 131,000.00
292 Floor drain steinless bh Rp 77,000.00 Rp 57,200.00 Rp 86,000.00 Rp 90,000.00 Rp 55,000.00 Rp 77,000.00
294 Formica 4" x 8" lbr Rp 91,700.00 Rp 91,700.00 Rp 91,700.00
296 Gate valve / stop kran ø 1 (inch) kuningan bh Rp 82,850.00 Rp 77,233.33 Rp 110,700.00 Rp 55,000.00 Rp 82,850.00
297 Gate valve / stop kran ø 1/2 (inch) kuningan bh Rp 43,833.33 Rp 45,333.33 Rp 61,500.00 Rp 35,000.00 Rp 35,000.00 Rp 43,833.33
298 Gate valve / stop kran ø 1 (inch) kuningan bh Rp 85,350.00 Rp 82,233.33 Rp 110,700.00 Rp 60,000.00 Rp 85,350.00
299 Gate valve / stop kran ø 3/4 (inch) kuningan bh Rp 79,444.44 Rp 62,333.33 Rp 86,000.00 Rp 45,000.00 Rp 45,000.00 Rp 79,444.44
300 Glass block uk. 20 x 20 (cm) bh Rp 26,750.00 Rp 25,400.00 Rp 36,000.00 Rp 24,000.00 Rp 22,000.00 Rp 25,000.00 Rp 26,750.00
301 Glass Bead Kg Rp 48,000.00 Rp 53,562.50 Rp 35,000.00 Rp 48,000.00
302 Grass block uk. 50 x 40 cm tebal 6 cm bh Rp 42,375.00 Rp 42,375.00 Rp 42,375.00
304 Grease (minyak gemuk) kg Rp 70,000.00 Rp 19,000.00 Rp 70,000.00 Rp 70,000.00
305 Grendel (biasa) bh Rp 7,500.00 Rp 8,400.00 Rp 7,500.00 Rp 7,500.00
306 Grendel (istimewa) bh Rp 43,000.00 Rp 28,200.00 Rp 43,000.00 Rp 43,000.00
308 Gypsum board polos uk. 1.22 x 2.44 (m), tebal 9 m lembar Rp 69,333.33 Rp 72,000.00 Rp 83,000.00 Rp 60,000.00 Rp 65,000.00 Rp 69,333.33
309 Gorong-gorong Dia.60 cm buah Rp 325,000.00 Rp 325,000.00 Rp 325,000.00
310 Gorong- gorong Dia.80 cm buah Rp 350,000.00 Rp 350,000.00 Rp 350,000.00
311 Gorong- gorong Dia.100 cm buah Rp 400,000.00 Rp 400,000.00 Rp 400,000.00
312 Handle jendela bh Rp 10,000.00 Rp 17,500.00 Rp 13,000.00 Rp 7,000.00 Rp 10,000.00
313 Handle pintu bh Rp 160,000.00 Rp 178,333.33 Rp 160,000.00 Rp 160,000.00
314 Handle untuk meubelair (furniture) + kunci bh Rp 40,000.00 Rp 74,400.00 Rp 40,000.00 Rp 40,000.00
315 Handle untuk pintu kaca lebar set Rp 246,000.00 Rp 270,000.00 Rp 246,000.00 Rp 246,000.00
316 Hollow block (H.B. 10) bh Rp 23,600.00 Rp 23,600.00 Rp 23,600.00
317 Hollow block (H.B. 15) bh Rp 60,000.00 Rp 60,000.00 Rp 60,000.00
318 Hollow block (H.B. 20) bh Rp 72,000.00 Rp 72,000.00 Rp 72,000.00
319 Hook bh Rp 12,000.00 Rp 12,000.00 Rp 12,000.00
320 Huruf Galvanized-Stainless steel m² Rp 120,000.00 Rp 120,000.00 Rp 120,000.00
321 Ijuk kg Rp 12,200.00 Rp 12,200.00 Rp 12,200.00
322 Jendela besi m² Rp 211,025.00 Rp 211,025.00 Rp 211,025.00
323 Jendela nako (kerangka + kaca 5 mm) m² Rp 86,250.00 Rp 86,250.00 Rp 86,250.00
327 Kabel listrik NYY 4 x 2,5 mm² m' Rp 17,333.33 Rp 21,666.67 Rp 17,000.00 Rp 18,000.00 Rp 17,000.00 Rp 17,333.33
328 Kabel listrik NYY 4 x 4 mm² m' Rp 26,000.00 Rp 28,333.33 Rp 26,000.00 Rp 26,000.00
329 Kabel listrik NYY 1 x 2,5 mm² m' Rp 3,600.00 Rp 4,000.00 Rp 3,300.00 Rp 4,000.00 Rp 3,500.00 Rp 3,600.00
330 Kabel listrik NYY 1 x 1,5 mm² m' Rp 2,516.67 Rp 3,000.00 Rp 2,050.00 Rp 3,000.00 Rp 2,500.00 Rp 2,516.67
331 Kabel listrik NYY 2 x 2,5 mm² m' Rp 10,333.33 Rp 10,000.00 Rp 9,000.00 Rp 12,000.00 Rp 10,000.00 Rp 10,333.33
332 Kabel listrik NYY 2 x 4 mm² m' Rp 16,666.67 Rp 16,750.00 Rp 15,000.00 Rp 20,000.00 Rp 15,000.00 Rp 16,666.67
334 Kaca bening tebal 3 mm m² Rp 120,000.00 Rp 120,000.00 Rp 120,000.00 Rp 120,000.00
335 Kaca bening tebal 5 mm m² Rp 130,000.00 Rp 182,666.67 Rp 130,000.00 Rp 130,000.00
336 Kaca bening tebal 8 mm m² Rp 420,000.00 Rp 420,000.00 Rp 420,000.00
337 Kaca bening tebal 10 mm m² Rp 600,000.00 Rp 600,000.00 Rp 600,000.00
338 Kaca bening tebal 12 mm m² Rp 900,000.00 Rp 900,000.00 Rp 900,000.00
339 Kaca buram tebal 12 mm m² Rp 474,000.00 Rp 474,000.00 Rp 474,000.00
340 Kaca cermin tebal 5 mm m² Rp 188,400.00 Rp 188,400.00 Rp 188,400.00
341 Kaca cermin tebal 6 mm m² Rp 211,200.00 Rp 211,200.00 Rp 211,200.00
342 Kaca cermin tebal 8 mm m² Rp 280,800.00 Rp 280,800.00 Rp 280,800.00
343 Kaca gelap (ray band) tebal 3 mm m² Rp 130,000.00 Rp 130,000.00 Rp 130,000.00
344 Kaca gelap (ray band) tebal 5 mm m² Rp 170,000.00 Rp 170,000.00 Rp 170,000.00
345 Kaca gelap (ray band) tebal 8 mm m² Rp 469,200.00 Rp 469,200.00 Rp 469,200.00
346 Kaca gelap (ray band) tebal 10 mm m² Rp 486,000.00 Rp 486,000.00 Rp 486,000.00
347 Kaca wireglassed 5 mm m² Rp 458,275.00 Rp 458,275.00 Rp 458,275.00
348 Kaca patri tebal 5 mm m² Rp 1,120,100.00 Rp 1,120,100.00 Rp 1,120,100.00
349 Kaca wireglass tebal 5 mm m² Rp 458,275.00 Rp 458,275.00 Rp 458,275.00
350 Kain kassa kg Rp 20,000.00 Rp 30,000.00 Rp 20,000.00 Rp 20,000.00
351 Kait angin (istimewa) bh Rp 26,666.67 Rp 29,100.00 Rp 43,000.00 Rp 25,000.00 Rp 12,000.00 Rp 26,666.67
352 Kait angin jendela biasa bh Rp 10,125.00 Rp 7,900.00 Rp 12,500.00 Rp 5,000.00 Rp 15,000.00 Rp 8,000.00 Rp 10,125.00
353 Kapur bakar m³ Rp 97,000.00 Rp 97,000.00 Rp 97,000.00
354 Kapur Padam m³ Rp 245,000.00 Rp 245,000.00 Rp 245,000.00
355 Kapur Pasang / Kapur Tembok m³ Rp 75,375.00 Rp 75,375.00 Rp 75,375.00
357 Karpet talang, lebar 0,60 m' m' Rp 11,500.00 Rp 10,000.00 Rp 14,000.00 Rp 9,000.00 Rp 11,500.00
358 Kawat ayam m2 Rp 25,000.00 Rp 25,000.00 Rp 1,450,000.00 Rp 25,000.00 Rp 737,500.00
359 Kawat nyamuk Allumunium m² Rp 41,000.00 Rp 29,500.00 Rp 43,000.00 Rp 55,000.00 Rp 25,000.00 Rp 41,000.00
360 Kawat nyamuk logam m² Rp 43,000.00 Rp 32,666.67 Rp 43,000.00 Rp 43,000.00
361 Kawat nyamuk plastik m² Rp 29,000.00 Rp 23,875.00 Rp 29,000.00 Rp 29,000.00
362 Kawat berduri kg Rp 28,000.00 Rp 23,125.00 Rp 36,000.00 Rp 20,000.00 Rp 28,000.00
363 Kawat beton kg Rp 24,500.00 Rp 24,142.86 Rp 33,000.00 Rp 13,500.00 Rp 26,000.00 Rp 25,000.00 Rp 18,000.00 Rp 24,500.00
364 Kawat bronjong kg Rp 245,000.00 Rp 228,800.00 Rp 245,000.00 Rp 245,000.00
365 Kawat burung m² Rp 37,000.00 Rp 20,000.00 Rp 37,000.00 Rp 37,000.00
366 Kawat harmonika m² Rp 35,000.00 Rp 25,000.00 Rp 36,000.00 Rp 29,000.00 Rp 40,000.00 Rp 35,000.00
367 Kawat kassa / kawat loket m² Rp 26,000.00 Rp 21,800.00 Rp 26,000.00 Rp 26,000.00
368 kawat las kg Rp 25,000.00 Rp 38,650.00 Rp 35,000.00 Rp 30,000.00 Rp 25,000.00
369 kawat las listrik kg Rp 118,000.00 Rp 118,000.00 Rp 118,000.00
370 Kawat seng polos kg Rp 28,333.33 Rp 28,333.33 Rp 28,333.33
371 Kawat burung m² Rp 37,000.00 Rp 45,250.00 Rp 37,000.00 Rp 37,000.00
372 Kawat seng polos kg Rp 33,675.00 Rp 33,675.00 Rp 33,675.00
373 Kayu bakar m³ Rp 107,700.00 Rp 107,700.00 Rp 107,700.00
374 Kasau 4/6 bh Rp 18,500.00 Rp 18,500.00 Rp 18,500.00
375 Kayu dolken ø 8 - 10 (cm) panjang 4 m batang Rp 22,750.00 Rp 25,833.33 Rp 18,500.00 Rp 27,000.00 Rp 22,750.00
376 Kayu gergajian kelas II, balok m³ Rp 2,500,000.00 Rp 2,593,333.33 Rp 2,500,000.00 Rp 2,500,000.00
377 Kayu gergajian kelas II, papan m³ Rp 4,166,666.67 Rp 3,237,500.00 Rp 4,166,666.67 Rp 4,166,666.67
378 Kayu gergajian kelas II, profil m³ Rp 2,208,500.00 Rp 2,208,500.00 Rp 2,208,500.00
379 Kayu kelas II, Sugu m3 Rp 2,185,000.00 Rp 2,185,000.00 Rp 2,185,000.00
380 Kayu gergajian kelas III, balok m³ Rp 3,125,000.00 Rp 2,934,666.67 Rp 3,125,000.00 Rp 3,125,000.00
381 Kayu gergajian kelas III, papan m³ Rp 3,472,222.22 Rp 1,920,166.67 Rp 3,472,222.22 Rp 3,472,222.22
382 Kayu gergajian kelas III, profil m' Rp 2,250,000.00 Rp 2,250,000.00 Rp 2,250,000.00
383 Kayu kelas III m³ Rp 2,666,666.67 Rp 1,500,000.00 Rp 2,666,666.67 Rp 2,666,666.67
384 Kayu kelas III, Sugu m³ Rp 1,800,000.00 Rp 1,800,000.00 Rp 1,800,000.00
385 Kayu gergajian kelas IV, balok m³ Rp 2,951,388.89 Rp 1,687,500.00 Rp 2,951,388.89 Rp 2,951,388.89
386 Kayu gergajian kelas IV, papan m³ Rp 1,875,000.00 Rp 1,978,750.00 Rp 1,875,000.00 Rp 1,875,000.00
387 Kayu kelas IV, sugu m3 Rp 1,481,481.48 Rp 2,175,000.00 Rp 1,481,481.48 Rp 1,481,481.48
388 Kayu untuk konstruksi jembatan m³ Rp 2,406,950.00 Rp 2,406,950.00 Rp 2,406,950.00
389 Kayu untuk perancah batang Rp 6,000.00 Rp 5,000.00 Rp 6,000.00 Rp 6,000.00
392 Keramik 20 x 20 (cm) m² / dus Rp 58,333.33 Rp 58,333.33 Rp 58,333.33
393 Keramik 30 cm x 30 cm m² / dus Rp 60,000.00 Rp 68,000.00 Rp 60,000.00 Rp 60,000.00
395 Keramik 40 x 40 (cm) m² / dus Rp 56,000.00 Rp 60,500.00 Rp 54,000.00 Rp 58,000.00 Rp 56,000.00
396 Keramik 60 x 60 (cm) m² / dus Rp 157,500.00 Rp 167,500.00 Rp 150,000.00 Rp 165,000.00 Rp 157,500.00
399 Keramik Dinding 20 x 20 (cm) m² / dus Rp 74,000.00 Rp 55,000.00 Rp 74,000.00 Rp 74,000.00
400 Keramik Dinding 20 x 25 (cm) m² / dus Rp 68,500.00 Rp 65,500.00 Rp 77,000.00 Rp 60,000.00 Rp 68,500.00
401 Keramik Dinding 25 x 40 (cm) m² / dus Rp 72,500.00 Rp 75,000.00 Rp 75,000.00 Rp 70,000.00 Rp 72,500.00
402 Keramik Lantai Granito 40 x 40 (cm) m² / dus Rp 282,500.00 Rp 282,500.00 Rp 282,500.00
403 Keramik KM/WC anti slip 20 x 20 (cm) m² / dus Rp 60,000.00 Rp 59,000.00 Rp 60,000.00 Rp 60,000.00
407 Knee / elbow PVC 1(inch) bh Rp 6,000.00 Rp 4,500.00 Rp 6,000.00 Rp 5,000.00 Rp 7,000.00 Rp 6,000.00
408 Knee / elbow PVC 1/2 (inch) bh Rp 4,166.67 Rp 3,600.00 Rp 4,500.00 Rp 3,000.00 Rp 5,000.00 Rp 4,166.67
409 Knee / elbow PVC 3/4 (inch) bh Rp 4,000.00 Rp 4,300.00 Rp 4,000.00 Rp 4,000.00 Rp 5,000.00 Rp 3,000.00 Rp 4,000.00
410 Kompon gypsum kg Rp 6,000.00 Rp 5,300.00 Rp 7,000.00 Rp 5,000.00 Rp 7,000.00 Rp 5,000.00 Rp 6,000.00
411 Kotak sabun keramik bh Rp 55,000.00 Rp 55,000.00 Rp 55,000.00 Rp 55,000.00
412 Kran air uk. 1/2 " Biasa bh Rp 15,000.00 Rp 22,560.00 Rp 10,000.00 Rp 20,000.00 Rp 15,000.00 Rp 15,000.00
413 Kran air uk. 1/2 " stanless bh Rp 61,666.67 Rp 45,000.00 Rp 70,000.00 Rp 75,000.00 Rp 40,000.00 Rp 61,666.67
414 Kran air uk. 3/4" Biasa bh Rp 22,666.67 Rp 22,840.00 Rp 28,000.00 Rp 25,000.00 Rp 15,000.00 Rp 22,666.67
415 Kuas roll bh Rp 33,000.00 Rp 30,000.00 Rp 35,000.00 Rp 30,000.00 Rp 35,000.00 Rp 32,000.00 Rp 33,000.00
416 Kuas uk. 1" bh Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 4,000.00 Rp 5,000.00 Rp 6,000.00 Rp 5,000.00
417 Kuas uk. 1,5" bh Rp 7,500.00 Rp 6,750.00 Rp 8,000.00 Rp 6,000.00 Rp 7,000.00 Rp 9,000.00 Rp 7,500.00
418 Kuas uk. 3" bh Rp 15,875.00 Rp 13,500.00 Rp 17,500.00 Rp 14,000.00 Rp 20,000.00 Rp 12,000.00 Rp 15,875.00
419 Kunci jendela (lokal) set Rp 24,166.67 Rp 10,000.00 Rp 37,500.00 Rp 25,000.00 Rp 10,000.00 Rp 24,166.67
420 Kunci lemari bh Rp 19,875.00 Rp 16,700.00 Rp 21,500.00 Rp 20,000.00 Rp 20,000.00 Rp 18,000.00 Rp 19,875.00
421 Kunci pintu (biasa) set Rp 68,125.00 Rp 108,250.00 Rp 97,500.00 Rp 90,000.00 Rp 85,000.00 Rp 68,125.00
422 Kunci pintu (istimewa) set Rp 287,850.00 Rp 228,375.00 Rp 473,550.00 Rp 240,000.00 Rp 150,000.00 Rp 287,850.00
423 Kunci pintu untuk meubelair (furniture) set Rp 95,000.00 Rp 95,000.00 Rp 95,000.00
424 Kunci silinder bh Rp 61,500.00 Rp 49,750.00 Rp 73,000.00 Rp 50,000.00 Rp 61,500.00
425 Kunci tanam biasa bh Rp 63,333.33 Rp 63,333.33 Rp 63,333.33
426 Kunci tanam antik bh Rp 140,000.00 Rp 140,000.00 Rp 140,000.00
427 Kunci tanam eklusif bh Rp 125,000.00 Rp 125,000.00 Rp 125,000.00
428 Kunci tanam kamar mandi bh Rp 50,000.00 Rp 50,000.00 Rp 50,000.00
429 Kunci slot bh Rp 5,000.00 Rp 12,000.00 Rp 5,000.00 Rp 5,000.00
430 Kusen pintu / jendela alumunium 3" m' Rp 106,200.00 Rp 106,200.00 Rp 106,200.00 Rp 106,200.00
431 Kusen pintu / jendela alumunium 4" m' Rp 128,000.00 Rp 106,200.00 Rp 128,000.00 Rp 128,000.00
432 Lampu downlight SL 25 Watt bh Rp 55,000.00 Rp 55,000.00 Rp 55,000.00
435 Lampu TL 20 W + aksesoris titik Rp 183,000.00 Rp 12,000.00 Rp 236,000.00 Rp 130,000.00 Rp 183,000.00
436 Lampu TL 40 W + aksesoris titik Rp 219,500.00 Rp 15,000.00 Rp 289,000.00 Rp 150,000.00 Rp 219,500.00
439 Langit-langit Accoustic board / tile uk. 0,30 x 0,30 ( m² Rp 6,000.00 Rp 6,000.00 Rp 6,000.00
440 Langit-langit Accoustic board / tile uk. 0,30 x 0,60 ( m² Rp 11,600.00 Rp 11,600.00 Rp 11,600.00
441 Langit-langit Accoustic board / tile uk. 0,60 x 1,20 x m² Rp 20,800.00 Rp 20,800.00 Rp 20,800.00
442 Langit-langit Accoustic board / tile uk. 0,60 x 1,20 x m² Rp 26,400.00 Rp 26,400.00 Rp 26,400.00
444 Lem PVC, 1/2 kg bh Rp 50,000.00 Rp 45,000.00 Rp 50,000.00 Rp 50,000.00 Rp 50,000.00
445 Lem (standar Aica Aibond) kg Rp 60,000.00 Rp 60,000.00 Rp 65,000.00 Rp 60,000.00
446 Lem (standar Fox) kg Rp 25,000.00 Rp 25,000.00 Rp 25,000.00
447 List gypsum profil m' Rp 24,250.00 Rp 24,250.00 Rp 24,250.00
448 Lolos Screen1 Ukuran (0-5) m³ Rp 325,000.00 Rp 325,000.00 Rp 333,000.00 Rp 333,000.00 Rp 325,000.00
449 Lolos Screen2 Ukuran (0-5) m³ Rp 325,000.00 Rp 325,000.00 Rp 333,000.00 Rp 333,000.00 Rp 325,000.00
450 Lolos Screen2 Ukuran (5-9,5) m³ Rp 325,000.00 Rp 325,000.00 Rp 333,000.00 Rp 333,000.00 Rp 325,000.00
451 Lolos Screen2 Ukuran (9,5-19,0) m³ Rp 325,000.00 Rp 325,000.00 Rp 333,000.00 Rp 333,000.00 Rp 325,000.00
454 Meter box (terpasang) titik Rp 578,450.00 Rp 578,450.00 Rp 578,450.00
455 Minyak bekisting liter Rp 8,000.00 Rp 8,000.00 Rp 8,000.00
456 Minyak pelarut cat (solvent) liter Rp 37,000.00 Rp 31,200.00 Rp 37,000.00 Rp 37,000.00
460 Multiplek tebal 12 mm uk. 1.22 x 2.44 (m) lembar Rp 207,500.00 Rp 192,000.00 Rp 215,000.00 Rp 200,000.00 Rp 207,500.00
461 Multiplek tebal 15 mm uk. 1.22 x 2.44 (m) lembar Rp 267,500.00 Rp 256,250.00 Rp 260,000.00 Rp 275,000.00 Rp 267,500.00
462 Multiplek tebal 18 mm 4 x 8 (inch) lembar Rp 337,333.33 Rp 290,000.00 Rp 412,000.00 Rp 300,000.00 Rp 300,000.00 Rp 337,333.33
463 Multiplek tebal 6 mm uk. 1.22 x 2.44 (m) lembar Rp 123,666.67 Rp 109,200.00 Rp 166,000.00 Rp 105,000.00 Rp 100,000.00 Rp 123,666.67
464 Multiplek tebal 9 mm uk. 1.22 x 2.44 (m) lembar Rp 137,500.00 Rp 135,000.00 Rp 140,000.00 Rp 135,000.00 Rp 137,500.00
466 Paku anti Karat kg Rp 28,800.00 Rp 28,800.00 Rp 28,800.00
467 Paku asbes kg Rp 35,666.67 Rp 35,500.00 Rp 42,000.00 Rp 35,000.00 Rp 30,000.00 Rp 35,666.67
468 Paku berbagai ukuran (1/2" - 1") kg Rp 25,000.00 Rp 23,900.00 Rp 33,000.00 Rp 25,000.00 Rp 20,000.00 Rp 22,000.00 Rp 25,000.00
469 Paku berbagai ukuran (2" - 5") kg Rp 16,000.00 Rp 16,500.00 Rp 21,500.00 Rp 19,000.00 Rp 16,000.00 Rp 15,000.00 Rp 15,000.00 Rp 16,000.00
470 Paku biasa 2” – 5” kg Rp 15,500.00 Rp 15,500.00 Rp 16,000.00 Rp 15,000.00 Rp 15,500.00
471 Paku 5-7cm kg Rp 17,000.00 Rp 15,666.67 Rp 16,000.00 Rp 18,000.00 Rp 17,000.00
472 Paku jembatan kg Rp 26,333.33 Rp 24,925.00 Rp 39,000.00 Rp 20,000.00 Rp 20,000.00 Rp 26,333.33
473 Paku kait bh Rp 2,000.00 Rp 2,000.00 Rp 2,000.00
474 Paku sekrup kotak Rp 53,100.00 Rp 53,100.00 Rp 53,100.00
475 Paku seng kg Rp 35,000.00 Rp 37,200.00 Rp 40,000.00 Rp 35,000.00 Rp 35,000.00 Rp 30,000.00 Rp 35,000.00
477 Paku tembok kg Rp 39,000.00 Rp 47,300.00 Rp 61,000.00 Rp 45,000.00 Rp 50,000.00 Rp 39,000.00
479 Panel listrik / MCB, 1 group / fase bh Rp 50,000.00 Rp 22,593.75 Rp 50,000.00 Rp 50,000.00
480 Panel listrik / MCB, 2 group / fase bh Rp 10,000.00 Rp 21,604.17 Rp 10,000.00 Rp 10,000.00
481 Panel listrik / MCB, 3 group / fase bh Rp 20,000.00 Rp 78,750.00 Rp 20,000.00 Rp 20,000.00
482 Panel listrik / MCB, 4 group / fase bh Rp 40,000.00 Rp 72,370.33 Rp 40,000.00 Rp 40,000.00
483 Parquette lantai m² Rp 285,000.00 Rp 285,000.00 Rp 40,000.00 Rp 285,000.00
484 Pasir ayak untuk beton m³ Rp 87,500.00 Rp 87,500.00 Rp 87,500.00
485 Pasir beton m³ Rp 85,000.00 Rp 87,500.00 Rp 109,000.00 Rp 62,500.00 Rp 100,000.00 Rp 85,000.00 Rp 85,000.00
487 Pasir Halus m³ Rp 90,000.00 Rp 87,500.00 Rp 95,000.00 Rp 75,000.00 Rp 100,000.00 Rp 110,000.00 Rp 90,000.00
488 Pasir pasang m³ Rp 85,000.00 Rp 87,500.00 Rp 112,500.00 Rp 90,000.00 Rp 85,000.00 Rp 85,000.00
489 Pasir urug / timbun m³ Rp 70,000.00 Rp 44,000.00 Rp 65,000.00 Rp 70,000.00 Rp 70,000.00
491 Pegangan pintu/door holder bh Rp 88,500.00 Rp 88,500.00 Rp 88,500.00
492 Pelat Rambu (Eng. Grade) bh Rp 216,000.00 Rp 216,000.00 Rp 300,000.00 Rp 300,000.00 Rp 300,000.00 Rp 216,000.00
493 Pelat Rambu (High I. Grade) bh Rp 243,000.00 Rp 243,000.00 Rp 350,000.00 Rp 350,000.00 Rp 350,000.00 Rp 243,000.00
496 Plint keramik bh Rp 10,000.00 Rp 10,000.00 Rp 10,000.00 Rp 10,000.00
497 Pintu alumunium - swing + door closer unit Rp 2,376,000.00 Rp 2,376,000.00 Rp 2,376,000.00
498 Pintu alumunium - swing + floorhinge unit Rp 2,376,000.00 Rp 2,376,000.00 Rp 2,376,000.00
499 Pintu besi m² Rp 2,046,000.00 Rp 2,046,000.00 Rp 2,046,000.00
500 Pintu besi lipat m² Rp 924,000.00 Rp 924,000.00 Rp 924,000.00
501 Pintu gulung besi m² Rp 300,000.00 Rp 300,000.00 Rp 300,000.00
502 Pintu plastik untuk kamar mandi bh Rp 220,000.00 Rp 220,000.00 Rp 220,000.00
504 Pintu alumimium + kaca untuk kamar mandi m² Rp 900,000.00 Rp 900,000.00 Rp 900,000.00
505 Pipa Baja kg Rp 28,300.00 Rp 28,300.00 Rp 28,300.00
506 Pipa besi galvanis ø 0,5 (inch) batang Rp 63,000.00 Rp 80,000.00 Rp 63,000.00 Rp 63,000.00
507 Pipa besi galvanis ø 0,75 (inch) batang Rp 83,000.00 Rp 105,000.00 Rp 83,000.00 Rp 83,000.00
508 Pipa besi galvanis ø 1 (inch) batang Rp 126,000.00 Rp 125,000.00 Rp 102,000.00 Rp 150,000.00 Rp 126,000.00
509 Pipa besi galvanis ø 1,25 (inch) batang Rp 135,000.00 Rp 155,000.00 Rp 135,000.00 Rp 135,000.00
510 Pipa besi galvanis ø 1,5 (inch) batang Rp 201,000.00 Rp 185,000.00 Rp 182,000.00 Rp 220,000.00 Rp 201,000.00
511 Pipa besi galvanis ø 2 (inch) batang Rp 302,500.00 Rp 250,000.00 Rp 330,000.00 Rp 275,000.00 Rp 302,500.00
512 Pipa besi galvanis ø 3 (inch) batang Rp 525,000.00 Rp 825,000.00 Rp 500,000.00 Rp 550,000.00 Rp 525,000.00
513 Pipa besi galvanis ø 4 (inch) m' Rp 750,000.00 Rp 620,000.00 Rp 750,000.00 Rp 750,000.00
514 Pipa beton ø 20 cm, panjang 1 m' bh Rp 122,800.00 Rp 122,800.00 Rp 122,800.00
515 Pipa beton ø 60 cm, panjang 1 m' bh Rp 201,800.00 Rp 201,800.00 Rp 201,800.00
516 Pipa PVC ø 1/2 (inch) AW, panjang 4 m m' Rp 4,916.67 Rp 5,600.00 Rp 5,000.00 Rp 5,750.00 Rp 4,000.00 Rp 4,916.67
517 Pipa PVC ø 3/4 (inch) AW, panjang 4 m m' Rp 6,666.67 Rp 7,300.00 Rp 6,250.00 Rp 8,000.00 Rp 5,750.00 Rp 6,666.67
518 Pipa PVC ø 1(inch) AW, panjang 4 m m' Rp 9,166.67 Rp 10,000.00 Rp 8,750.00 Rp 11,250.00 Rp 7,500.00 Rp 9,166.67
519 Pipa PVC ø 1,5 (inch) AW, panjang 4 m m' Rp 15,583.33 Rp 18,000.00 Rp 15,000.00 Rp 18,750.00 Rp 13,000.00 Rp 15,583.33
520 Pipa PVC ø 2 (inch) AW, panjang 4 m m' Rp 19,833.33 Rp 22,416.67 Rp 18,750.00 Rp 23,750.00 Rp 17,000.00 Rp 19,833.33
521 Pipa PVC ø 2,5 (inch) AW, panjang 4 m m' Rp 28,333.33 Rp 33,166.67 Rp 27,500.00 Rp 35,000.00 Rp 22,500.00 Rp 28,333.33
522 Pipa PVC ø 3 (inch) AW, panjang 4 m m' Rp 39,583.33 Rp 45,000.00 Rp 37,500.00 Rp 48,750.00 Rp 32,500.00 Rp 39,583.33
523 Pipa PVC ø 4 (inch) AW, panjang 4 m m' Rp 64,583.33 Rp 70,333.33 Rp 60,000.00 Rp 81,250.00 Rp 52,500.00 Rp 64,583.33
524 Pipa PVC ø 6 (inch) AW, panjang 4 m m' Rp 137,500.00 Rp 114,166.67 Rp 125,000.00 Rp 180,000.00 Rp 107,500.00 Rp 137,500.00
525 Plameur kg Rp 37,500.00 Rp 27,666.67 Rp 50,000.00 Rp 25,000.00 Rp 37,500.00
528 Plint keramik 10 x 20 cm bh Rp 6,000.00 Rp 4,750.00 Rp 6,000.00 Rp 6,000.00
529 Plint keramik 10 x 40 cm bh Rp 16,500.00 Rp 11,000.00 Rp 16,500.00 Rp 16,500.00
530 Plint ubin abu-abu 15 x 20 cm bh Rp 4,275.00 Rp 4,275.00 Rp 4,275.00
531 Plint ubin granito 10 x 30 cm bh Rp 5,875.00 Rp 5,875.00 Rp 5,875.00
532 Plint ubin granito 10 x 40 cm bh Rp 6,200.00 Rp 6,200.00 Rp 6,200.00
535 Plywood uk. 0,30 x 0,60 (m), tebal 4mm lembar Rp 86,000.00 Rp 86,000.00 Rp 86,000.00
536 Plywood uk. 0,30 x 0,60 (m), tebal 6mm lembar Rp 71,000.00 Rp 71,000.00 Rp 71,000.00
538 Plywood uk. 1,22 x 2,440 (m), tebal 6mm lembar Rp 80,000.00 Rp 80,000.00 Rp 80,000.00
539 Plywood uk. 1,22 x 2,44 (m), tebal 4 mm lembar Rp 125,000.00 Rp 65,000.00 Rp 125,000.00 Rp 125,000.00
540 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lembar Rp 145,000.00 Rp 145,000.00 Rp 145,000.00
541 Politur liter Rp 67,500.00 Rp 31,200.00 Rp 67,500.00 Rp 67,500.00
542 Politur jadi liter Rp 55,500.00 Rp 50,000.00 Rp 55,500.00 Rp 55,500.00
543 Politur Kayu, Woodstain Kaleng/liter Rp 80,666.67 Rp 60,300.00 Rp 92,000.00 Rp 80,000.00 Rp 70,000.00 Rp 80,666.67
544 Porcelaint uk. 11 cm x 11 cm bh Rp 2,300.00 Rp 2,300.00 Rp 2,300.00
545 Profil aluminium T m' Rp 24,725.00 Rp 24,725.00 Rp 24,725.00
547 Pompa air (dengan otomatis) Besar buah Rp 1,900,000.00 Rp 2,500,000.00 Rp 1,050,000.00 Rp 2,750,000.00 Rp 1,900,000.00
548 Pompa air (dengan otomatis) Kecil buah Rp 540,000.00 Rp 550,000.00 Rp 530,000.00 Rp 550,000.00 Rp 540,000.00
554 Rangka atap baja ringan type limas m² Rp 175,000.00 Rp 185,000.00 Rp 175,000.00 Rp 175,000.00
555 Rangka metal hollow 40.40.2 mm m' Rp 31,250.00 Rp 10,500.00 Rp 31,250.00 Rp 31,250.00
557 Reducer PVC dari 1/2 (inch) ke 1 (inch) bh Rp 5,000.00 Rp 4,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00
558 Reducer PVC dari 1/2 (inch) ke 3/4 (inch) bh Rp 4,333.33 Rp 3,000.00 Rp 4,000.00 Rp 5,000.00 Rp 4,000.00 Rp 4,333.33
559 Reducer PVC dari 3/4 (inch) ke 1 (inch) bh Rp 5,000.00 Rp 4,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00
562 Residu galon Rp 45,000.00 Rp 93,000.00 Rp 45,000.00 Rp 45,000.00
563 Reng baja ringan 0,6 mm m' Rp 42,375.00 Rp 42,375.00 Rp 42,375.00
564 Rolling dor - alumunium tebal m² Rp 487,000.00 Rp 487,000.00 Rp 487,000.00
565 Rolling dor - alumunium tipis m² Rp 605,000.00 Rp 605,000.00 Rp 605,000.00
566 Rooflight fibreglass uk. 1,8 x 0,9 (m) lembar Rp 106,000.00 Rp 106,000.00 Rp 106,000.00
567 Rooster Bata, 12 x 11,5 x 24 cm bh Rp 28,500.00 Rp 21,600.00 Rp 28,500.00 Rp 28,500.00
568 Rooster Beton, 20 x 20 x 7 cm bh Rp 31,500.00 Rp 56,400.00 Rp 31,500.00 Rp 31,500.00
569 Rooster block uk. 12 x 11 x 24 (cm) bh Rp 15,500.00 Rp 21,600.00 Rp 15,500.00 Rp 15,500.00
570 Rooster block uk. 20 x 20 (cm) bh Rp 67,000.00 Rp 53,075.00 Rp 67,000.00 Rp 67,000.00
572 Saklar bh Rp 13,875.00 Rp 13,875.00 Rp 13,875.00
573 Saklar dobel bh Rp 20,000.00 Rp 19,500.00 Rp 20,000.00 Rp 20,000.00 Rp 20,000.00 Rp 20,000.00
574 seal tape bh Rp 7,000.00 Rp 7,400.00 Rp 4,000.00 Rp 4,000.00 Rp 10,000.00 Rp 10,000.00 Rp 7,000.00
575 Sealent kg Rp 36,500.00 Rp 30,000.00 Rp 33,000.00 Rp 40,000.00 Rp 36,500.00
577 Semen merah kg Rp 16,300.00 Rp 16,300.00 Rp 16,300.00
578 Semen Portland kg Rp 1,500.00 Rp 1,500.00 Rp 89,000.00 Rp 75,000.00 Rp 1,500.00
579 Semen putih kg Rp 7,500.00 Rp 4,800.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 15,000.00 Rp 7,500.00
580 Semen warna kg Rp 17,125.00 Rp 16,000.00 Rp 18,500.00 Rp 20,000.00 Rp 15,000.00 Rp 15,000.00 Rp 17,125.00
581 Seng plat BJLS m' Rp 33,600.00 Rp 33,600.00 Rp 33,600.00
584 Sirtu m³ Rp 425,000.00 Rp 425,000.00 Rp 315,000.00 Rp 425,000.00
585 Slot jendela bh Rp 7,500.00 Rp 8,800.00 Rp 5,000.00 Rp 10,000.00 Rp 7,500.00
586 Slot pintu bh Rp 25,000.00 Rp 25,000.00 Rp 25,000.00 Rp 25,000.00
588 Socket PVC ø 1 (inch) bh Rp 5,000.00 Rp 5,100.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00 Rp 5,000.00
589 Socket PVC ø 1/2 (inch) bh Rp 4,000.00 Rp 3,100.00 Rp 4,000.00 Rp 4,000.00 Rp 5,000.00 Rp 3,000.00 Rp 4,000.00
590 Socket PVC ø 3/4 (inch) bh Rp 4,000.00 Rp 4,000.00 Rp 3,000.00 Rp 4,000.00 Rp 5,000.00 Rp 4,000.00 Rp 4,000.00
591 Soda api kg Rp 27,500.00 Rp 25,000.00 Rp 25,000.00 Rp 30,000.00 Rp 27,500.00
592 Softboard uk. 1,20 x 2,40 (m), tebal 4 mm lembar Rp 30,000.00 Rp 55,000.00 Rp 30,000.00 Rp 30,000.00
593 Sealtape bh Rp 8,000.00 Rp 9,000.00 Rp 4,000.00 Rp 10,000.00 Rp 10,000.00 Rp 8,000.00
596 Stone Coating kg Rp 47,000.00 Rp 47,000.00 Rp 47,000.00
597 Stop kontak + instalasi titik Rp 15,000.00 Rp 15,000.00 Rp 15,000.00
598 Stop kran ø 0,5 (inch) buah Rp 17,500.00 Rp 17,500.00 Rp 20,000.00 Rp 15,000.00 Rp 17,500.00
599 Stop kran ø 0,75 (inch) buah Rp 22,500.00 Rp 25,000.00 Rp 25,000.00 Rp 20,000.00 Rp 22,500.00
600 Stop kran ø 1 (inch) buah Rp 33,333.33 Rp 25,000.00 Rp 35,000.00 Rp 35,000.00 Rp 30,000.00 Rp 33,333.33
602 Strorox – 100 kg Rp 6,800.00 Rp 6,800.00 Rp 6,800.00
603 Tangki Septic 0,6 Unit Rp 3,500,000.00 - Rp 3,500,000.00
604 Tangki Septic 0,8 Unit Rp 3,900,000.00 - Rp 3,900,000.00
605 Tangki Septic 1 Unit Rp 4,300,000.00 - Rp 4,300,000.00
606 Tangki Septic 2 Unit Rp 5,300,000.00 - Rp 5,300,000.00
607 Tangki Septic 5 Unit Rp 17,500,000.00 - Rp 17,500,000.00
608 Tangki Komunal 10 Unit Rp 35,000,000.00 - Rp 35,000,000.00
609 Tangki Komunal 25 Unit Rp 90,000,000.00 - Rp 90,000,000.00
610 Tangki Komunal 50 Unit Rp 175,000,000.00 - Rp 175,000,000.00
611 Tangki Komunal 75 Unit Rp 315,000,000.00 - Rp 315,000,000.00
612 Tangki Komunal 100 Unit Rp 400,000,000.00 - Rp 400,000,000.00
613 Tangki Komunal 125 Unit Rp 500,000,000.00 - Rp 500,000,000.00
614 Tangki Komunal 150 Unit Rp 600,000,000.00 - Rp 600,000,000.00
616 Tangki air fiberglass (oranye) 2.000 liter bh Rp 3,533,333.33 Rp 3,100,000.00 Rp 3,400,000.00 Rp 3,500,000.00 Rp 3,700,000.00 Rp 3,533,333.33
617 Tangki air fiberglass (oranye) 3.000 liter bh Rp 5,600,000.00 Rp 7,000,000.00 Rp 5,600,000.00 Rp 5,600,000.00
618 Tangki air fiberglass (oranye) 500 liter bh Rp 1,066,666.67 Rp 1,050,000.00 Rp 1,000,000.00 Rp 1,100,000.00 Rp 1,100,000.00 Rp 1,066,666.67
619 Tangki air fiberglass (oranye) 1.500 liter bh Rp 2,683,333.33 Rp 1,100,000.00 Rp 2,600,000.00 Rp 2,750,000.00 Rp 2,700,000.00 Rp 2,683,333.33
620 Tangki air tanles stail (pranye) 1.000 liter bh - - -
621 Tangki air tanles stail (pranye) 1.500 liter bh - - -
622 Teak wood 0,30 x 0,60 (m), tebal 4 mm lembar Rp 101,000.00 Rp 101,000.00 Rp 101,000.00
623 Teak wood 0,90 x 2,10 (m), tebal 4 mm lembar Rp 138,000.00 Rp 138,000.00 Rp 138,000.00
624 Teak wood 1,20 x 2,40 (m), tebal 4 mm lembar Rp 197,000.00 Rp 197,000.00 Rp 197,000.00
625 Tee all socket PVC ø 100 x 50 (mm) unit - - -
626 Tee all socket PVC ø 225 x 100 (mm) unit - - -
627 Tee all socket PVC ø 50 x 50 (mm) unit - - -
628 Tee all socket PVC ø 80 x 50 (mm) unit - - -
629 Tempat sabun keramik bh Rp 50,000.00 Rp 55,000.00 Rp 45,000.00 Rp 55,000.00 Rp 50,000.00
630 Residu/Ter kg Rp 35,000.00 Rp 90,000.00 Rp 35,000.00 Rp 35,000.00
631 Timbunan biasa m³ Rp 30,000.00 Rp 30,000.00 Rp 30,000.00
632 Timbunan pilihan / tanah puru m³ Rp 30,000.00 Rp 30,000.00 Rp 30,000.00
634 Thinner liter Rp 20,000.00 Rp 23,000.00 Rp 20,000.00 Rp 120,000.00 Rp 25,000.00 Rp 55,000.00
635 Triplek tebal 15 mm uk. 1.22 x 2.44 (m) lembar Rp 268,750.00 Rp 248,040.00 Rp 300,000.00 Rp 260,000.00 Rp 275,000.00 Rp 240,000.00 Rp 268,750.00
636 Triplek tebal 12 mm uk. 1.22 x 2.44 (m) lembar Rp 221,000.00 Rp 214,000.00 Rp 289,000.00 Rp 215,000.00 Rp 200,000.00 Rp 180,000.00 Rp 221,000.00
637 Triplek tebal 8 mm uk. 1.22 x 2.44 (m) lembar Rp 143,000.00 Rp 147,340.00 Rp 172,000.00 Rp 140,000.00 Rp 135,000.00 Rp 125,000.00 Rp 143,000.00
638 Triplek tebal 6 mm uk. 1.22 x 2.44 (m) lembar Rp 98,500.00 Rp 102,400.00 Rp 104,000.00 Rp 105,000.00 Rp 100,000.00 Rp 85,000.00 Rp 98,500.00
639 Triplek tebal 4 mm uk. 1.22 x 2.44 (m) lembar Rp 78,750.00 Rp 80,600.00 Rp 85,000.00 Rp 78,000.00 Rp 80,000.00 Rp 72,000.00 Rp 78,750.00
640 Ubin abu-abu 20 x 20 (cm) bh Rp 3,000.00 Rp 3,000.00 Rp 3,000.00
641 Ubin berwarna 20 x 20 (cm) bh Rp 18,912.50 Rp 18,912.50 Rp 18,912.50
644 Ubin motif (mozaik) m² Rp 89,700.00 Rp 89,700.00 Rp 89,700.00
645 Ubin wafel bh Rp 3,450.00 Rp 3,450.00 Rp 3,450.00
646 Urinoir Unit Rp 1,800,000.00 Rp 815,925.00 Rp 1,800,000.00 Rp 1,800,000.00
647 Urinoir Keramik Kwalitas no..2 Unit Rp 1,943,525.00 Rp 1,943,525.00 Rp 1,943,525.00
648 Venetion blinds/Vertical blinds (tirai) m² Rp 85,000.00 Rp 85,000.00 Rp 85,000.00
649 Vertical blinds m² Rp 36,800.00 Rp 36,800.00 Rp 36,800.00
650 Wallpaper ukuran 50 cm m' Rp 28,000.00 Rp 28,000.00 Rp 28,000.00
651 Wallpaper m² Rp 92,000.00 Rp 92,000.00 Rp 92,000.00
652 Lem Wallpapper kg Rp 45,000.00 Rp 45,000.00 Rp 45,000.00
653 Lem kayu kg Rp 28,333.33 Rp 16,000.00 Rp 10,000.00 Rp 55,000.00 Rp 20,000.00 Rp 28,333.33
654 Wastafel bh Rp 512,500.00 Rp 633,333.33 Rp 1,100,000.00 Rp 250,000.00 Rp 350,000.00 Rp 350,000.00 Rp 512,500.00
655 Kayu perancah m³ Rp 1,800,000.00 Rp 1,800,000.00 Rp 3,500.00 Rp 6,000.00 Rp 5,000.00 Rp 1,800,000.00
656 Waterdrain unit Rp 40,000.00 Rp 40,000.00 Rp 40,000.00

Ditetapkan di Manggar, Maret 2020

Kepala Bidang Kepala Bidang


Kepala Bidang Bina Marga
Sumber Daya Air Cipta Karya

LUKMAN, ST IDWAN FIKRI, ST


SUMARNO, ST NIP. 19731209 200604 1 001
NIP. 19760219 200604 1 004 NIP. 19710215 200604 1 023

Mengetahui/Menyetujui,
Plt. Kepala Dinas Pekerjaan Umum
dan Penataan Ruang

HENDRA JAYA, S.AP


NIP. 19630618 198603 1 008
No. Uraian/nama/jenis barang satuan rata rata HSU 2019 SSH 2020 Depot Kayu PT. KMN Toko Asia Toko Melan Toko Sumber PT. BHSC PT.SMA Depot 13 Harga Dipakai Th. 2020
Putra Sunda Bangunan Jaya Jaya

1 2 3 4 6 7 8 9 10 11 12 13 14 15 16
1 Tangki Septic 0,6 Unit Rp 3,500,000.00 Rp 3,500,000.00
2 Tangki Septic 0,8 Unit Rp 3,900,000.00 Rp 3,900,000.00
3 Tangki Septic 1 Unit Rp 4,300,000.00 Rp 4,300,000.00
4 Tangki Septic 2 Unit Rp 5,300,000.00 Rp 5,300,000.00
5 Tangki Septic 5 Unit Rp 17,500,000.00 Rp 17,500,000.00
6 Tangki Komunal 10 Unit Rp 35,000,000.00 Rp 35,000,000.00
7 Tangki Komunal 25 Unit Rp 90,000,000.00 Rp 90,000,000.00
8 Tangki Komunal 50 Unit Rp 175,000,000.00 Rp 175,000,000.00
9 Tangki Komunal 75 Unit Rp 315,000,000.00 Rp 315,000,000.00
10 Tangki Komunal 100 Unit Rp 400,000,000.00 Rp 400,000,000.00
11 Tangki Komunal 125 Unit Rp 500,000,000.00 Rp 500,000,000.00
12 Tangki Komunal 150 Unit Rp 600,000,000.00 Rp 600,000,000.00
13 FASTPEC GRS-1 Uk.330 x 330 x 3 Unit Rp 500,000.00 Rp 500,000.00
14 FASTPEC GRS-2 Uk.550 x 450 x 5 Unit Rp 850,000.00 Rp 850,000.00
15 FASTPEC GRS-3 Uk.315 x 380 Unit Rp 450,000.00 Rp 450,000.00
16 FASTPEC GRS-4 Uk.450 x 430 Unit Rp 750,000.00 Rp 750,000.00
17 FASTPEC GRS-5 Uk.500 x 430 Unit Rp 850,000.00 Rp 850,000.00
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Pembuatan 1 Bh papan nama proyek A. 2.2.1.10.A 1.00 Bh 250,000 250,000
2 Pembuatan 1 m2 kantor sementara lantai plesteran A. 2.2.1.5 8.81 M2 1,450,024 12,769,934
3 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9 70.00 M2 19,250 1,347,500
Sub Total 14,367,434
II PEKERJAAN TANAH / PONDASI
1 Pek. Galian Tanah A.2.3.1.1 34.03 M3 86,625 2,947,953
2 Pek. Pengurugan dengan pasir urug A.2.3.1.11 4.03 M3 127,050 512,266
3 Pemasangan batu kosong (aanstamping) A.3.2.1.9 4.26 M3 581,559 2,475,115
4 Pek.Pas.Pondasi Batu Gunung Ad 1 : 4 A.3.2.1.2 12.60 M3 1,006,445 12,681,207
5 Pek.Urukan Kembali A.2.3.1.9.A 11.34 M3 28,820 326,926
Sub Total 18,943,467
III PEKERJAAN BETON BERTULANG
1 Pek. Kolom 20/20 ad. 1pc : 2ps : 3kr A.4.1.1.7 1.63 M3 1,289,612 2,104,646
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 218.85 kg 17,333 3,793,360
2 Pek. Kolom 15/15 ad. 1pc : 2ps : 3kr A.4.1.1.7 0.73 M3 1,289,612 940,127
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 166.05 kg 17,333 2,878,269
3 Pek. Balok Sloof 15/20 Ad 1pc : 2ps : 3kr A.4.1.1.7 1.68 M3 1,289,612 2,166,548
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 264.54 kg 17,333 4,585,311
4 Pek. Ring Balok 15/20 ad 1pc : 2ps : 3kr A.4.1.1.7 1.68 M3 1,289,612 2,166,548
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 264.54 kg 17,333 4,585,311
5 Pek. Atap Dak ad 1pc : 2ps : 3kr A.4.1.1.5 1.23 M3 1,213,149 1,495,888
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 162.34 kg 17,333 2,813,836
6 Pek. Pondasi Beton Bertulang A.4.1.1.17 1.84 M 3
1,289,612 2,372,885
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 192.27 kg 17,333 3,332,676
7 Pek. Plat Kanovi Kusen ad 1pc : 2ps : 3kr A.4.1.1.32 0.92 M3 1,213,149 1,111,730
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.32 99.96 kg 17,333 1,732,637
Sub Total 36,079,771
IV PEKERJAAN DINDING
1 Pek.Pas. Dinding Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 109.19 M2 69,924 7,634,973
2 Pek. Plesteran Dinding ad. 1pc : 4ps A.4.4.2.4 218.38 M2 71,115 15,529,980
Sub Total 23,164,953
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 2.00 Unit
a. Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13 6.57 M2 847,198 5,563,041
2 Pintu P2 1.00 Unit
a. Kusen alumunium A.4.2.1.13 2.36 M2 847,198 2,003,115
3 Kusen + Daun Kaca 5 mm Alminium Jendela Type J1 + Aksesoris 2.00 Unit
a. Kusen alumunium A.4.2.1.11 18.36 M1 45,895 842,628
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 1.41 M2 350,724 496,117
4 Kusen Bouvenli Kaca 5 mm Alminium Type BV1 6.00 Unit
a. Kusen alumunium A.4.2.1.11 24.24 M1 45,895 1,112,489
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 1.41 M2 350,724 493,048
5 Kusen Bouvenli Kaca 5 mm Alminium Type BV 1.00 Unit
a. Kusen alumunium A.4.2.1.11 2.78 M 1
45,895 127,587
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.38 M2 350,724 131,522
6 Pemasangan 1 buah engsel pintu A.4.6.2.5 10.00 Unit 51,282 512,820
7 Pas. Kunci Slott / Grendel Pintu A.4.6.2.11 8.00 Unit 38,665 309,320
8 Pas. Door Closer A.4.6.2.10 5.00 Bh 297,495 1,487,475
9 Pemasangan 1 Unit Pintu Kamar Mandi/ WC A.4.2.1.14.A 1.00 Unit 324,995 324,995
10 Pemasangan 1 buah kunci tanam aluminium A.4.6.2.2.A 3.00 Unit 172,425 517,275
Sub Total 13,921,431
VI PEKERJAAN LANTAI
1 Pek.Urugan Tanah Bawah Lantai T.10 cm A.2.3.1.11 6.69 M³ 127,050 849,901
2 Pek Urugan Pasir Bawah Lantai 10 cm A.2.3.1.11 6.69 M³ 127,050 849,901
3 Pek. Cor Lantai Kerja 5 cm A.4.1.1.4 2.96 M³ 996,348 2,945,643
4 Pemasangan 1 m2 dinding keramik 20cm x 25cm Kamar Mandi A.4.4.3.54.A 3.38 M² 304,648 1,028,186
5 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm Kamar Mandi A.4.4.3.36 1.82 M² 255,828 466,247
6 Pemasangan 1m2 lantai keramik ukuran 40cm x 40cm A.4.4.3.35.A 65.07 M² 166,009 10,802,637
Sub Total 16,942,515
VII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik A.5.1.1 32 12.00 Titik 200,778 2,409,330
2 Pas. Lampu 18 Watt, Philips SSH 2020 6.00 Bh 58,500 351,000
3 Pas. Lampu 23 Watt, Philips Tornado SSH 2020 6.00 Bh 70,000 420,000
4 Pas. Sakelar tunggal SSH 2020 1.00 Bh 20,000 20,000
5 Pas. Sakelar Ganda (Panasonic) SSH 2020 3.00 Bh 28,500 85,500
6 Pas. Stop Kontak (National) SSH 2020 2.00 Bh 24,000 48,000
7 Pas. Stop Kontak ac (National) SSH 2020 4.00 Bh 55,000 220,000
Sub Total 3,553,830
VIII PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pas. Pipa Pvc Ø 4 inch A.5.1.1.33 4.00 M' 145,448 581,790
2 Pas. Pipa Pvc Ø 2 inch A.5.1.1.29 4.00 M' 55,638 222,552
3 Pas. Pipa Pvc AW Ø 1/2 inch A.5.1.1.25 7.50 M' 22,292 167,186
4 Pas. Clossed Jongkok A.5.1.1.2 1.00 Unit 543,235 543,235
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19 1.00 Bh 80,245 80,245
6 Pemasangan 1 buah floor drain A.5.1.1 14 1.00 Unit 102,025 102,025
7 Pas. Tedemmond 500 L SSH 2020 1.00 Unit 1,000,000 1,000,000
8 Pemasangan 1 buah bak air fibreglass vol 1 m3 A.5.1.1 10 1.00 Unit 543,983 543,983
9 Pek. Pembuatan Septictank + Resapan A.5.1.1 11.A 1.00 Unit 4,395,622 4,395,622
Sub Total 7,636,639
IX PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja Ringan A.4.5.2.37.A 79.81 M2 166,500 13,288,848
2 Pekerjaan Atap Genteng Metal A.4.5.2.32 79.81 M2 129,910 10,368,494
3 Pekerjaan Bubungan Atap Metal A.4.5.2.36 27.15 M1 96,470 2,619,450
4 Pas. Pipa Pvc Ø 2 inch A.5.1.1 29 16.00 M1 55,638 890,208
5 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm A.4.2.1.19 38.40 M1 92,373 3,547,104
6 Pemasangan 1 m’ lisplank GRC A.4.6.1.22.A 38.40 M1 63,470 2,437,248
Sub Total 33,151,352
X PEK. PLAFOND + RANGKA HOLLOW
1 Pas. Plafond Gypsumboard + Rangka Besi Hollow A.4.2.1.21.A 68.03 M² 161,222 10,968,150
2 Pas. List Plafond Gypsum A.4.5.1.8.A 64.08 M1 25,311 1,621,843
Sub Total 12,589,993
XI PEK. SALURAN TERBUKA
1 PekePekerjaan Galian Tanah A.2.3.1.1 9.54 M3 86,625.00 826,513
2 Pekerjaan Urugan A.2.3.1.9.A 5.75 M3 28,820.00 165,846
3 PekePekerjaan Pas. Batu-bata Ad. 1 : 4 A. 4.4.1.21.A 38.71 M² 69,924.25 2,707,042
4 Pek. Cor Lantai Kerja 5 cm A.4.1.1.4 1.42 M3 996,347.82 1,415,810
5 PekePekerjaan Plesteran Batu bata Ad. 1 : 4 A.4.4.2.4 32.92 M² 71,115.00 2,341,117
Sub Total 7,456,329
XII PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding A.4.7.1.10.A 179.93 M2 40,887.00 7,356,898
Sub Total 7,356,898
XIII PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir A. 2.2.1.9 13.00 M2
19,250 250,250
Sub Total 250,250
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A. 2.2.1.9. Pembersihan 1 m2 lapangan dan perataan

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.100 100,000.00 10,000.00
Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 17,500.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 17,500.00


E Overhead & Profit 10 % 10% x D 1,750.00
F Harga Satuan Pekerjaan (D+E) 19,250.00

A. 2.2.1.10.A Pembuatan 1 Buah papan nama proyek


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.100 100,000.00 10,000.00
Tukang kayu L.02 OH 125,000.00 0.00
Kepala Tukang L.03 OH 150,000.00 0.00
Mandor L.04 OH 150,000.00 0.00
JUMLAH TENAGA KERJA 10,000.00
B BAHAN
Kasau 4/6 Btg 4.708 18,500.00 87,094.28
Paku m 3
0.500 16,000.00 8,000.00
Triplek 6 mm m3 0.672 98,500.00 66,178.45
Banner m2 2.000 28,000.00 56,000.00
JUMLAH HARGA BAHAN 217,272.73
C PERALATAN
JUMLAH
HARGA ALAT
D Jumlah (A+B+C) 227,272.73
E Overhead & Profit 10 % 10% x D 22,727.27
F Harga Satuan Pekerjaan (D+E) 250,000.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.750 100,000.00 75,000.00
Mandor L.04 OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 78,750.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
RAB (RENCANA ANGGARAN BIAYA)

NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembuatan 1 bh papan nama proyek A. 2.2.1.10.A 1.00 Bh 250,000 250,000
JUMLAH I 250,000
II PEKERJAAN TANAH / PONDASI
1 Pek. Galian Tanah A.2.3.1.1 49.52 M3 86,625 4,289,324
2 Pek. Pengurugan dengan pasir urug A.2.3.1.11 5.76 M3 127,050 731,808
3 Pemasangan batu kosong (aanstamping) A.3.2.1.9 6.08 M3 581,559 3,535,879
4 Pek.Pas.Pondasi Batu Gunung Ad 1 : 4 A.3.2.1.2 18.07 M3 1,006,445 18,188,474
5 Pek.Urukan Kembali A.2.3.1.9.A 16.51 M3 28,820 475,684
JUMLAH II 27,221,168
III PEKERJAAN BETON BERTULANG
1 Pek. Kolom 20/20 ad. 1pc : 2ps : 3kr A.4.1.1.7 2.24 M3 1,289,612 2,893,889
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 288.20 kg 17,333 4,995,372
2 Pek. Kolom 15/15 ad. 1pc : 2ps : 3kr A.4.1.1.7 0.37 M3 1,289,612 478,768
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 77.94 kg 17,333 1,350,928
3 Pek. Balok Sloof 15/20 Ad 1pc : 2ps : 3kr A.4.1.1.7 2.40 M3 1,289,612 3,095,068
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 377.63 kg 17,333 6,545,563
4 Pek. Ring Balok 15/20 ad 1pc : 2ps : 3kr A.4.1.1.7 2.40 M3 1,289,612 3,095,068
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 377.63 kg 17,333 6,545,563
5 Pek. Pondasi Beton Bertulang A.4.1.1.2 0.28 M3 4,857,237 1,369,741
JUMLAH III 30,369,958
IV PEKERJAAN DINDING
1 Pemasangan 1 m² dinding bataco campuran 1SP :4PP A. 4.4.1.21.A 120.00 M2 69,924 8,390,910
2 Pek. Plesteran Dinding ad. 1pc : 4ps A.4.4.2.4 240.00 M2 71,115 17,067,600
JUMLAH IV 25,458,510
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 1.00 Unit
a. Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13 3.00 M2 847,198 2,541,594
b. Kusen alumunium (Bouvenli) A.4.2.1.11 3.99 M1 45,895 183,120
c. Daun + kaca 5 mm bingkai alumunium (Bouvenli) A.4.2.1.11.A 0.52 M2 350,724 182,376
2 Kusen Jendela Kaca 5 mm Alminium Type J1 2.00 Unit
a. Kusen alumunium A.4.2.1.11 25.26 M1 45,895 1,159,118
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 3.86 M2 350,724 1,353,514
3 Pemasangan 1 buah engsel pintu A.4.6.2.5 4.00 Unit 51,282 205,128
4 Pas. Kunci Slott / Grendel Pintu A.4.6.2.11 4.00 Unit 38,665 154,660
5 Pas. Door Closer A.4.6.2.10 2.00 Bh 297,495 594,990
6 Pemasangan 1 buah kunci tanam aluminium A.4.6.2.2.A 1.00 Unit 172,425 172,425
7 Pintu Kamar Mandi - 1.00 Unit 250,000 250,000
JUMLAH V 6,546,925
VI PEKERJAAN LANTAI
1 Pek.Urugan Tanah Bawah Lantai T.10 cm A.2.3.1.11 14.90 M³ 127,050 1,893,045
2 Pek Urugan Pasir Bawah Lantai 5 cm A.2.3.1.11 4.65 M³ 127,050 590,783
3 Pek. Cor Lantai Kerja 5 cm A.4.1.1.4 10.25 M³ 996,348 10,212,565
4 Pemasangan 1m2 lantai keramik Dinding Kamar mandi uk.20cm x 25cm A.4.4.3.36 4.50 M² 304,648 1,370,915
5 Pemasangan 1m2 lantai keramik ukuran 40cm x 40cm A.4.4.3.35.B 93.00 M² 253,707 23,594,728
6 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm A.4.4.3.6 4.00 M² 258,519 1,034,077
JUMLAH VII 37,662,035
VII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik A.5.1.1 33 6.00 Titik 210,100 1,260,600
2 Pas. Lampu 18 Watt - 1.00 Bh 58,500 58,500
3 Pas. Lampu 23 Watt - 5.00 Bh 70,000 350,000
4 Pas. Sakelar Ganda - 2.00 Bh 28,500 57,000
5 Pas. Stop Kontak - 2.00 Bh 24,000 48,000
6 Pas. Stop Kontak ac - 2.00 Bh 55,000 110,000
7 Pas. KWH 6 A (1380 V) - 1.00 Unit 1,244,000 1,244,000
8 Pas. MCB 6A - 1.00 Bh 64,500 64,500
JUMLAH VII 1,884,100
VIII PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja Ringan A.4.5.2.37. 323.00 M2 203,328 65,674,943
2 Pekerjaan Atap Spandeck A.4.5.2.32.A 323.00 M2 129,910 41,960,930
3 Pekerjaan Bubungan Atap Spandeck A.4.5.2.36.A 18.00 M1 84,260 1,516,680
4 Pas. Pipa Pvc Ø 2 inch A.5.1.1 29 25.20 M1 55,638 1,402,078
5 Pemasangan 1 m talang ½ lingkaran A.4.2.1.19 41.00 M1 92,373 3,787,273
6 Pemasangan 1 m’ lisplank GRC A.4.6.1.22.A 75.00 M1 63,470 4,760,250
JUMLAH IX 119,102,153
IX PEK. PLAFOND + RANGKA HOLLOW
1 Pas. Plafond Gypsumboard + Rangka Besi Hollow A.4.2.1.21.a 44.00 M² 161,222 7,093,746
2 Pas. List Plafond Gypsum A.4.5.1.8.A 63.00 M1 25,311 1,594,593
JUMLAH X 8,688,339
X PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pas. Pipa Pvc Ø 4 inch A.5.1.1.32 4.00 M' 145,447.50 581,790
2 Pas. Pipa Pvc Ø 2 inch A.5.1.1.29 12.00 M' 55,638.00 667,656
3 Pas. Pipa Pvc AW Ø 1/2 inch A.5.1.1.25 12.00 M' 22,291.50 267,498
4 Pas. Clossed Jongkok A.5.1.1 2 1.00 Bh 543,235.00 543,235
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19 1.00 Bh 80,245.00 80,245
6 Pemasangan 1 buah floor drain Stainless steel A.5.1.1 14 1.00 Unit 102,025.00 102,025
7 Pas. Tedemmond 500 L - 1.00 Unit 1,100,000.00 1,100,000
8 Pek. Pembuatan Septictank + Resapan A.5.1.1 11.A 1.00 Unit 4,395,622.42 4,395,622
9 Pas. Pompa Otomatis - 1.00 Unit 1,900,000.00 1,900,000
JUMLAH XI 9,638,071
XI PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding A.4.7.1.10.A 120.00 M2 40,887.00 4,906,440
JUMLAH XII 4,906,440
XII PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir - 1.00 Ls 500,000 500,000
JUMLAH XIII 500,000

JUMLAH 272,227,701
TOTAL JUMLAH 272,227,701
DIBULATKAN 272,227,000

TERBILANG DUA RATUS TUJUH PULUH DUA JUTA DUA RATUS DUA PULUH TUJUH RIBU RUPIAH
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp 14,367,434.26

II PEKERJAAN TANAH / PONDASI Rp 18,943,466.80

III PEKERJAAN BETON BERTULANG Rp 36,079,770.94

IV PEKERJAAN DINDING Rp 23,164,952.83

V PEKERJAAN PINTU DAN VENTILASI Rp 13,921,431.15

VI PEKERJAAN LANTAI Rp 16,942,514.98

VII PEKERJAAN INSTALASI LISTRIK Rp 3,553,830.00

VIII PEKERJAAN INSTALASI AIR BERSI & AIR KOTOR Rp 7,636,638.67

IX PEKERJAAN ATAP Rp 33,151,351.77

X PEK. PLAFOND + RANGKA HOLLOW Rp 12,589,993.17

XI PEK. SALURAN TERBUKA Rp 7,456,329.05

XII PEKERJAAN PENGECATAN Rp 7,356,897.67

XIII PEKERJAAN LAIN-LAIN Rp 250,250.00

TOTAL Rp Rp195,414,861
x 10 % Rp Rp19,541,486
JUMLAH Rp214,956,347
DI BULATKAN Rp Rp214,956,000
Terbilang: DUA RATUS SEBELAS JUTA TIGA RATUS DUA PULUH SATU RIBU RUPIAH ###
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

HPS (HARGA PERKIRAAN SENDIRI)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME : :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Pembuatan 1 bh papan nama proyek A. 2.2.1.10.A 1.00 Bh 250,000 250,000
2 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9 64.00 M2 19,250 1,232,000
Sub Total 1,482,000
II PEKERJAAN TANAH / PONDASI
1 Pek. Galian Tanah A.2.3.1.1 34.03 M3 86,625 2,947,953
2 Pek. Pengurugan dengan pasir urug A.2.3.1.11 4.03 M3 127,050 512,266
3 Pemasangan batu kosong (aanstamping) A.3.2.1.9 4.26 M3 581,559 2,475,115
4 Pek.Pas.Pondasi Batu Gunung Ad 1 : 4 A.3.2.1.2 12.60 M3 1,006,445 12,681,207
5 Pek.Urukan Kembali A.2.3.1.9.A 11.34 M3 28,820 326,926
Sub Total 18,943,467
III PEKERJAAN BETON BERTULANG
1 Pek. Kolom 20/20 ad. 1pc : 2ps : 3kr A.4.1.1.7 1.60 M3 1,289,612 2,063,379
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 210.00 kg 17,333 3,639,983
2 Pek. Kolom 15/15 ad. 1pc : 2ps : 3kr A.4.1.1.7 0.70 M3 1,289,612 902,728
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 160.00 kg 17,333 2,773,320
3 Pek. Balok Sloof 15/20 Ad 1pc : 2ps : 3kr A.4.1.1.7 2.00 M3 1,289,612 2,579,223
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 250.00 kg 17,333 4,333,313
4 Pek. Ring Balok 15/20 ad 1pc : 2ps : 3kr A.4.1.1.7 2.00 M3 1,289,612 2,579,223
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 250.00 kg 17,333 4,333,313
5 Pek. Atap Dak ad 1pc : 2ps : 3kr A.4.1.1.5 1.50 M3 1,213,149 1,819,723
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 150.00 kg 17,333 2,599,988
6 Pek. Pondasi Beton Bertulang A.4.1.1.17 2.00 M3 1,289,612 2,579,223
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 180.00 kg 17,333 3,119,985
7 Pek. Plat Kanovi Kusen ad 1pc : 2ps : 3kr A.4.1.1.32 1.00 M 3
1,213,149 1,213,149
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.32 80.00 kg 17,333 1,386,660
Sub Total 35,923,209
IV PEKERJAAN DINDING
1 Pek.Pas. Dinding Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 109.45 M2 69,924 7,653,209
2 Pek. Plesteran Dinding ad. 1pc : 4ps A.4.4.2.4 218.90 M2 71,115 15,567,074
Sub Total 23,220,283
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 2.00 Unit
a. Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13 6.50 M2 847,198 5,506,787
2 Pintu P2 1.00 Unit
a. Kusen alumunium A.4.2.1.13 2.30 M2 847,198 1,948,555
3 Kusen + Daun Kaca 5 mm Alminium Jendela Type J1 + Aksesoris 2.00 Unit
a. Kusen alumunium A.4.2.1.11 18.30 M1 45,895 839,874
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 1.41 M2 350,724 496,117
4 Kusen Bouvenli Kaca 5 mm Alminium Type BV1 6.00 Unit
a. Kusen alumunium A.4.2.1.11 24.20 M1 45,895 1,110,653
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 1.40 M2 350,724 491,014
5 Kusen Bouvenli Kaca 5 mm Alminium Type BV 1.00 Unit
a. Kusen alumunium A.4.2.1.11 2.75 M1 45,895 126,211
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.35 M2 350,724 122,753
6 Pemasangan 1 buah engsel pintu SSH 2020 10.00 Unit 34,000 340,000
7 Pas. Kunci Slott / Grendel Pintu SSH 2020 8.00 Unit 23,000 184,000
8 Pas. Door Closer SSH 2020 5.00 Bh 225,000 1,125,000
9 Pemasangan 1 Unit Pintu Kamar Mandi/ WC A.4.2.1.14.A 1.00 Unit 324,995 324,995
10 Pemasangan 1 buah kunci tanam aluminium A.4.6.2.2.A 3.00 Unit 172,425 517,275
Sub Total 13,133,234
VI PEKERJAAN LANTAI
1 Pek.Urugan Tanah Bawah Lantai T.10 cm A.2.3.1.11 7.00 M³ 127,050 889,350
2 Pek Urugan Pasir Bawah Lantai 10 cm A.2.3.1.11 7.00 M³ 127,050 889,350
3 Pek. Cor Lantai Kerja 5 cm A.4.1.1.4 3.00 M³ 996,348 2,989,043
4 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm Kamar Mandi A.4.4.3.36 1.80 M² 255,828 460,491
5 Pemasangan 1m2 lantai keramik ukuran 40cm x 40cm A.4.4.3.35.A 63.62 M² 166,009 10,561,093
Sub Total 15,789,328
VII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik A.5.1.1.33 12.00 Titik 210,100 2,521,200
2 Pas. Lampu 18 Watt, Philips SSH 2020 6.00 Bh 58,500 351,000
3 Pas. Lampu 23 Watt, Philips Tornado SSH 2020 6.00 Bh 70,000 420,000
4 Pas. Sakelar tunggal SSH 2020 1.00 Bh 20,000 20,000
5 Pas. Sakelar Ganda (Panasonic) SSH 2020 3.00 Bh 28,500 85,500
6 Pas. Stop Kontak (National) SSH 2020 2.00 Bh 24,000 48,000
7 Pas. Stop Kontak ac (National) SSH 2020 4.00 Bh 55,000 220,000
Sub Total 3,665,700
VIII PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pas. Pipa Pvc Ø 4 inch A.5.1.1.32 4.00 M' 145,448 581,790
2 Pas. Pipa Pvc Ø 2 inch A.5.1.1.29 4.00 M' 55,638 222,552
3 Pas. Pipa Pvc AW Ø 1/2 inch A.5.1.1.25 6.00 M' 22,292 133,749
4 Pas. Clossed Jongkok SSH 2020 1.00 Bh 258,000 258,000
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19 1.00 Bh 80,245 80,245
6 Pemasangan 1 buah floor drain Stainless steel SSH 2020 1.00 Unit 86,000 86,000
7 Pas. Tedemmond 650 L SSH 2020 1.00 Unit 1,545,000 1,545,000
8 ### SSH 2020 1.00 Unit 421,000 421,000
9 Pek. Pembuatan Septictank + Resapan A.5.1.1 11.A 1.00 Unit 4,395,622 4,395,622
Sub Total 7,723,958
IX PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja Ringan A.4.5.2.37. 79.81 M2 166,500 13,288,848
2 Pekerjaan Atap Genteng Metal A.4.5.2.32 79.81 M2 129,910 10,368,494
3 Pekerjaan Bubungan Atap Metal A.4.5.2.36 27.15 M1 96,470 2,619,450
4 Pas. Pipa Pvc Ø 2 inch A.5.1.1 29 12.00 M1 55,638 667,656
5 Pemasangan 1 m talang ½ lingkaran A.4.2.1.19 38.40 M1 92,373 3,547,104
6 Pemasangan 1 m’ lisplank GRC A.4.6.1.22.A 38.40 M1 63,470 2,437,248
Sub Total 32,928,800
X PEK. PLAFOND + RANGKA HOLLOW
1 Pas. Plafond Gypsumboard + Rangka Besi Hollow A.4.2.1.21.a 88.74 M² 161,222 14,307,199
2 Pas. List Plafond Gypsum A.4.5.1.8.A 64.08 M1 25,311 1,621,843
Sub Total 15,929,042
XI PEK. SALURAN TERBUKA
1 Pekerjaan Galian Tanah A.2.3.1.1 9.00 M3 86,625.00 779,625
2 Pekerjaan Urugan A.2.3.1.9.A 5.75 M3 28,820.00 165,846
3 Pekerjaan Pas. Batu-bata Ad. 1 : 4 A. 4.4.1.21.A 38.71 M² 69,924.25 2,707,042
4 Pek. Cor Lantai Kerja 5 cm A.4.1.1.4 1.40 M3 996,347.82 1,394,887
5 Pekerjaan Plesteran Batu bata Ad. 1 : 4 A.4.4.2.4 32.92 M² 71,115.00 2,341,117
Sub Total 7,388,517
XII PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding A.4.7.1.10.A 180.45 M2 40,887.00 7,378,224
Sub Total 7,378,224
XIII PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir A. 2.2.1.9 8.00 M2 19,250 154,000
Sub Total 154,000

JUMLAH 183,659,762
PPN 10% 18,365,976
TOTAL JUMLAH 202,025,738
DIBULATKAN 202,025,000

TERBILANG SERATUS SEMBILAN PULUH DELAPAN JUTA TIGA RATUS SEMBILAN PULUH RIBU RUPIAH
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

RAB (RENCANA ANGGARAN BIAYA)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Pembuatan 1 bh papan nama proyek A. 2.2.1.10.A 1.00 Bh 250,000 250,000
2 Pembongkaran 1 m3 dinding tembok bata A. 2.2.1.14 1.58 M3 788,315 1,241,596
3 Pembongkaran 1 m2 Lantai keramik A. 2.2.1.15. 312.09 M2 12,650 3,947,986
4 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9. 20.00 M2 19,250 385,000
Sub Total 5,824,582
II PEKERJAAN TANAH / PONDASI
1 Pek. Galian Tanah A.2.3.1.1 7.90 M3 86,625 684,346
2 Pemasangan batu kosong (aanstamping) A.3.2.1.9 0.69 M3 581,559 403,974
3 Pek.Pas.Pondasi Batu Gunung Ad 1 : 4 A.3.2.1.2 2.93 M3 1,006,445 2,943,852
4 Pek.Urukan Kembali A.2.3.1.11.A 2.63 M3 28,820 75,894
Sub Total 4,108,066
III PEKERJAAN BETON BERTULANG
1 Pek. Kolom 15/15 ad. 1pc : 2ps : 3kr A.4.1.1.7 0.18 M3 1,289,612 235,032
Pembesian 28,98 kg dengan besi polos atau besi ulir A.4.1.1.17 38.70 kg 17,333 670,859
2 Pek. Balok Sloof 15/20 Ad 1pc : 2ps : 3kr A.4.1.1.7 0.39 M3 1,289,612 502,949
Pembesian 340,398 kg dengan besi polos atau besi ulir A.4.1.1.17 62.38 kg 17,333 1,081,208
3 Pek. Ring Balok 15/20 ad 1pc : 2ps : 3kr A.4.1.1.7 0.39 M3 1,289,612 502,949
Pembesian 340,398 kg dengan besi polos atau besi ulir A.4.1.1.17 62.38 kg 17,333 1,081,208
4 Pek.Beton Dapur ad 1pc : 2ps : 3kr A.4.1.1.4 0.46 M3 996,348 453,936
Pembesian 15,72 kg dengan besi polos atau besi ulir A.4.1.1.17 15.72 kg 17,333 272,562
Sub Total 4,800,702
IV PEKERJAAN DINDING
1 Pek.Pas. Dinding Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 41.10 M2 69,924 2,873,887
2 Pem. 1 m² dinding terawang (rooster) 12x11x24 campuran 1SP :3PP A.4.4.1.22 0.60 M2 402,298 241,379
3 Pek. Plesteran Dinding ad. 1pc : 4ps A.4.4.2.4 82.20 M2 71,115 5,845,653
Sub Total 8,960,918
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 2.00 Unit
a. Kusen alumunium A.4.2.1.11 17.16 M1 45,895 787,554
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 6.84 M2 350,724 2,400,215
2 Kusen + Daun Kaca 5 mm Alminium Jendela Type J1 + Aksesoris 1.00 Unit
a. Kusen alumunium A.4.2.1.11 9.18 M1 45,895 421,314
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.71 M2 350,724 248,059
3 Kusen Bouvenli Kaca 5 mm Alminium Type BV 1.00 Unit
a. Kusen alumunium A.4.2.1.11 2.78 M1 45,895 127,587
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.38 M2 350,724 131,522
4 Pemasangan 1 buah engsel pintu A.4.6.2.5 2.00 Unit 51,282 102,564
5 Pas. Kunci Slott / Grendel Pintu A.4.6.2.11 1.00 Unit 38,665 38,665
6 Pintu Kamar mandi A.4.2.1.14.A 1.00 Unit 324,995 324,995
7 Pek. Door Closer A.4.6.2.10. 2.00 Bh 297,495 594,990
Sub Total 5,177,464
VI PEKERJAAN LANTAI
1 Pek.Urugan Tanah Bawah Lantai T.10 cm A.2.3.1.11 1.05 M³ 127,050 133,403
2 Pek Urugan Pasir Bawah Lantai 5 cm A.2.3.1.11 0.53 M³ 127,050 66,701
3 Pek. Cor Lantai Kerja 5 cm A.4.1.1.1 0.53 M³ 1,079,489 566,732
4 Pek. Pas. Keramik 10*x 20 cm A.4.4.3.39 93.73 M' 66,487 6,231,825
5 Pek .Pas.Keramik 40 x 40 cm A.4.4.3.35.B 312.09 M² 253,707 79,180,290
Sub Total 86,178,951
VII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik A.5.1.1 33 2.00 Titik 210,100 420,200
3 Pas. Lampu 23 Watt, Philips Tornado SSH 2020 2.00 Bh 70,000 140,000
4 Pas. Sakelar Ganda (Panasonic) SSH 2020 2.00 Bh 28,500 57,000
5 Pas. Stop Kontak (National) SSH 2020 2.00 Bh 24,000 48,000
6 Pas. Stop Kontak ac (National) SSH 2020 1.00 Bh 55,000 55,000
Sub Total 720,200
VIII PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja Ringan A.4.5.2.37. 30.50 M2 166,500 5,078,250
2 Pekerjaan Atap Genteng Metal A.4.5.2.32 30.50 M2 88,506 2,699,433
3 Pas. Pipa Pvc Ø 2 inch A.5.1.1 29 9.40 M1 55,638 522,997
4 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm A.4.2.1.19 12.00 M1 92,373 1,108,470
5 Pekerjaan Lisplank GRC A.4.6.1.22.A 14.00 M1 63,470 888,580
Sub Total 10,297,730
IX PEK. PLAFOND + RANGKA HOLLOW
1 Pas. Plafond Gypsumboard + Rangka Besi Hollow A.4.2.1.21.A 32.75 M² 161,222 5,280,004
2 Pas. List Plafond Gypsum A.4.5.1.8.A 26.00 M1 25,311 658,086
Sub Total 5,938,090
X PEK. DAPUR
1 Pek.Pas. Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 0.84 M² 69,874.75 58,695
2 Pek. Plesteran ad. 1pc : 4ps A.4.4.2.4 1.68 M² 71,115.00 119,473
3 Pek. Wastafel A.5.1.1.5 2.00 bh 1,154,841.60 2,309,683
4 Pek. Bak Cuci Piring A.5.1.15 1.00 bh 765,325.00 765,325
5 Pek. Kran Air SSH 2020 1.00 bh 55,000.00 55,000
6 Pek. Keramik Dinding A.4.4.3.54.A 8.25 M² 312,263 2,576,171
Sub Total 5,884,347
XI PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding A.4.7.1.10.A 82.20 M2 40,887.00 3,360,911
Sub Total 3,360,911
XII PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir A. 2.2.1.9. 20.00 M2 19,250 385,000
Sub Total 385,000
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

RAB (RENCANA ANGGARAN BIAYA)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAAN KODE ANALISA VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9. 525.00 M² 19,250.00 10,106,250.00
JUMLAH I 10,106,250.00
II PEKERJAAN TIMBUNAN
1 Pemadatan tanah per 20 cm A.2.3.1.10 262.50 M3 63,250.00 16,603,125.00
2 Timbunan pilihan / tanah puru A.2.3.1.12 262.50 M3 133,889.69 35,146,042.95
JUMLAH II 35,146,042.95
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

RAB (RENCANA ANGGARAN BIAYA)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAAN KODE ANALISA VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6 7
I PEKERJAAN DRAINASE
1 Pek. Galian tanah A.2.3.1.1 9.80 M³ 86,625.00 848,925.00
2 Pek. Pas. Batu Belah ad. 1 : 4 A.3.2.1.2 9.80 M³ 1,006,445.00 9,863,161.00
JUMLAH II 10,712,086.00
II PEKERJAAN PLAT AKSES KE RUMAH
1 Pembesian 48,16 Kg dengan besi polos atau ulir A.4.1.1.17 48.16 Kg 17,333.25 834,769.32
2 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 2) cm, A. A.4.1.1.5. 4.89 M³ 1,213,148.78 5,934,723.81
3 Pemasangan 1 m² jembatan untuk pengecoran beton A.4.1.1.27 32.56 M² 106,379.97 3,463,731.93
JUMLAH III 10,233,225.06

III PEKERJAAN LAIN-LAIN


Pembersihan Akhir - 1.00 Ls 500,000.00 500,000.00
JUMLAH IV 500,000.00
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

HPS (HARGA PERKIRAAN SENDIRI)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN KODE ANALISA VOLUME SATUAN HARGA SATUAN (RP) JUMLAH HARGA (Rp)

I PEKERJAAN PERSIAPAN
1 Pembuatan 1 bh papan nama proyek A. 2.2.1.10.A 1.00 Bh 250,000 250,00
2 Pembongkaran 1 m3 dinding tembok bata A. 2.2.1.14 1.50 M3 788,315 1,182,47
3 Pembongkaran 1 m2 Lantai keramik A. 2.2.1.15. 312.09 M2 12,650 3,947,98
4 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9. 16.00 M2 19,250 308,00
Sub Total 5,688,45
II PEKERJAAN TANAH / PONDASI
1 Pek. Galian Tanah A.2.3.1.1 7.90 M3 86,625 684,34
2 Pemasangan batu kosong (aanstamping) A.3.2.1.9 0.69 M3 581,559 403,97
3 Pek.Pas.Pondasi Batu Gunung Ad 1 : 4 A.3.2.1.2 2.93 M3 1,006,445 2,943,85
4 Pek.Urukan Kembali A.2.3.1.11.A 2.63 M3 28,820 75,89
Sub Total 4,108,06
III PEKERJAAN BETON BERTULANG
1 Pek. Kolom 15/15 ad. 1pc : 2ps : 3kr A.4.1.1.7 0.18 M3 1,289,612 235,03
Pembesian 28,98 kg dengan besi polos atau besi ulir A.4.1.1.17 38.00 kg 17,333 658,66
2 Pek. Balok Sloof 15/20 Ad 1pc : 2ps : 3kr A.4.1.1.7 0.39 M3 1,289,612 502,94
Pembesian 340,398 kg dengan besi polos atau besi ulir A.4.1.1.17 60.00 kg 17,333 1,039,99
3 Pek. Ring Balok 15/20 ad 1pc : 2ps : 3kr A.4.1.1.7 0.39 M3 1,289,612 502,94
Pembesian 340,398 kg dengan besi polos atau besi ulir A.4.1.1.17 60.00 kg 17,333 1,039,99
4 Pek.Beton Dapur ad 1pc : 2ps : 3kr A.4.1.1.4 0.46 M3 996,348 453,93
Pembesian 15,72 kg dengan besi polos atau besi ulir A.4.1.1.17 15.50 kg 17,333 268,66
Sub Total 4,702,18
IV PEKERJAAN DINDING
1 Pek.Pas. Dinding Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 41.10 M2 69,924 2,873,88
2 Pem. 1 m² dinding terawang (rooster) 12x11x24 campuran 1SP :3PP A.4.4.1.22 0.60 M2 402,298 241,37
3 Pek. Plesteran Dinding ad. 1pc : 4ps A.4.4.2.4 82.20 M2 71,115 5,845,65
Sub Total 8,960,91
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 2.00 Unit
a. Kusen alumunium A.4.2.1.11 17.16 M1 45,895 787,55
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 6.84 M2 350,724 2,400,21
2 Kusen + Daun Kaca 5 mm Alminium Jendela Type J1 + Aksesoris 1.00 Unit
a. Kusen alumunium A.4.2.1.11 9.18 M1 45,895 421,31
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.71 M2 350,724 248,05
3 Kusen Bouvenli Kaca 5 mm Alminium Type BV 1.00 Unit
a. Kusen alumunium A.4.2.1.11 2.78 M1 45,895 127,58
b. Daun + kaca 5 mm bingkai alumunium A.4.2.1.11.A 0.38 M2 350,724 131,52
4 Pemasangan 1 buah engsel pintu SSH 22020 2.00 Unit 34,000 68,00
5 Pas. Kunci Slott / Grendel Pintu SSH 2020 1.00 Unit 23,000 23,00
6 Pintu Kamar mandi A.4.2.1.14.A 1.00 Unit 324,995 324,99
7 Pek. Door Closer SSH 2020 2.00 Bh 225,000 450,00
Sub Total 4,982,24
VI PEKERJAAN LANTAI
1 Pek.Urugan Tanah Bawah Lantai T.10 cm A.2.3.1.11 1.05 M³ 127,050 133,40
2 Pek Urugan Pasir Bawah Lantai 5 cm A.2.3.1.11 0.53 M³ 127,050 66,70
3 Pek. Cor Lantai Kerja 5 cm A.4.1.1.1 0.53 M³ 1,079,489 566,73
4 Pek. Pas. Keramik 10*x 20 cm A.4.4.3.39 90.00 M' 66,487 5,983,86
5 Pek .Pas.Keramik 40 x 40 cm A.4.4.3.35.B 312.09 M² 253,707 79,180,29
Sub Total 85,930,99
VII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik A.5.1.1 33 2.00 Titik 210,100 420,20
3 Pas. Lampu 23 Watt, Philips Tornado SSH 2020 2.00 Bh 70,000 140,00
4 Pas. Sakelar Ganda (Panasonic) SSH 2020 2.00 Bh 28,500 57,00
5 Pas. Stop Kontak (National) SSH 2020 2.00 Bh 24,000 48,00
6 Pas. Stop Kontak ac (National) SSH 2020 1.00 Bh 55,000 55,00
Sub Total 720,20
VIII PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Baja Ringan A.4.5.2.37. 30.50 M2 166,500 5,078,25
2 Pekerjaan Atap Genteng Metal A.4.5.2.32 30.50 M2 88,506 2,699,43
3 Pas. Pipa Pvc Ø 2 inch A.5.1.1 29 9.40 M1 55,638 522,99
4 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm A.4.2.1.19 12.00 M1 92,373 1,108,47
5 Pekerjaan Lisplank GRC A.4.6.1.22.A 14.00 M1 63,470 888,58
Sub Total 10,297,73
IX PEK. PLAFOND + RANGKA HOLLOW
1 Pas. Plafond Gypsumboard + Rangka Besi Hollow A.4.2.1.21.A 32.75 M² 161,222 5,280,00
2 Pas. List Plafond Gypsum A.4.5.1.8.A 26.00 M1 25,311 658,08
Sub Total 5,938,09
X PEK. DAPUR
1 Pek.Pas. Batu Bata Ad 1pc : 4ps A. 4.4.1.21.A 0.84 M² 69,874.75 58,69
2 Pek. Plesteran ad. 1pc : 4ps A.4.4.2.4 1.68 M² 71,115.00 119,47
3 Pek. Wastafel A.5.1.1.5 2.00 bh 1,154,841.60 2,309,68
4 Pek. Bak Cuci Piring A.5.1.15 1.00 bh 765,325.00 765,32
5 Pek. Kran Air SSH 2020 1.00 bh 55,000.00 55,00
6 Pek. Keramik Dinding A.4.4.3.54.A 8.25 M² 312,263 2,576,17
Sub Total 5,884,34
XI PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding A.4.7.1.10.A 82.20 M2 40,887.00 3,360,91
Sub Total 3,360,91
XII PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir A. 2.2.1.9. 16.00 M2 19,250 308,00
Sub Total 308,00

JUMLAH 140,882,14
PPN 10% 14,088,21
TOTAL JUMLAH 154,970,35
DIBULATKAN 154,970,00
TERBILANG SERATUS LIMA PULUH EMPAT JUTA SEMBILAN RATUS TUJUH PULUH RIBU RUPIAH
JUMLAH HARGA (Rp)

250,000
1,182,473
3,947,986
308,000
5,688,458

684,346
403,974
2,943,852
75,894
4,108,066

235,032
658,664
502,949
1,039,995
502,949
1,039,995
453,936
268,665
4,702,184

2,873,887
241,379
5,845,653
8,960,918

787,554
2,400,215

421,314
248,059

127,587
131,522
68,000
23,000
324,995
450,000
4,982,245

133,403
66,701
566,732
5,983,869
79,180,290
85,930,995

420,200
140,000
57,000
48,000
55,000
720,200

5,078,250
2,699,433
522,997
1,108,470
888,580
10,297,730

5,280,004
658,086
5,938,090

58,695
119,473
2,309,683
765,325
55,000
2,576,171
5,884,347

3,360,911
3,360,911

308,000
308,000

140,882,145
14,088,214
154,970,359
154,970,000
PEMERINTAH KABUPATEN BELITUNG TIMUR
OPD / UNIT KERJA
Kompleks Perkantoran Terpadu
Jalan Raya Manggar Gantung Telp/Fax. (0719) 91001

REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN :
PEKERJAAN :
LOKASI :
VOLUME :
SUMBER DANA :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN GEDUNG RKB Rp 272,227,700.75

II RAB PEMBERSIHAN LOKASI & PENIMBUNAN TANAH Rp 45,252,292.95

III PEKERJAAN SALURAN TALUD Rp 21,445,311.06

TOTAL Rp 338,925,305
x 10 % Rp 33,892,530
JUMLAH Rp 372,817,835
DI BULATKAN Rp 372,817,000
Terbilang: TUJUH RATUS JUTA RUPIAH ###