Anda di halaman 1dari 33

RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN REST AREA


PEKERJAAN : PUJASERA (PUSAT JAJANAN SERBA ADA), ANCHOR TENAN & TENAN
LOKASI : KULON PROGO YOGYAKARTA

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT JML. HARGA JML. SUB TOTAL

I PUJASERA (Pusat Jajanan Serba Ada)

A PEKERJAAN PERSIAPAN
1 Pengukuran & Pemasangan Bowplank 808.80 m' 62,118.10 50,241,119.28
50,241,119.28
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 456.00 m3 56,237.50 25,644,300.00
2 Urugan Tanah Kembali 152.00 m3 40,975.00 6,228,200.00
3 Urug Pasir Bawah Pondasi 68.40 m3 211,255.00 14,449,842.00
46,322,342.00
C PEK. RANGKA BAWAH
1 Pas. Pondasi batu kosong 91.20 m3 427,269.30 38,966,960.16
2 Pas. Lantai kerja 22.80 m3 829,773.88 18,918,844.37
3 Pas Pondasi Footplat ( 80 x 80 )
Beton 192.38 m3 987,098.41 189,893,057.14
Pembesian 6,417.82 kg 12,088.42 77,581,320.20
Begesting ( 2 Kali Pakai ) 460.20 m2 125,269.70 57,649,115.94
4 Pekerjaan Sloof ( 15 x 20 )
Beton 71.18 m3 987,098.41 70,259,690.82
Pembesian 8,889.66 kg 12,088.42 107,461,945.32
Begesting ( 2 Kali Pakai ) 1,423.56 m2 125,269.70 178,328,934.13
5 Pekerjaan Umpak Kolom
Beton 9.12 m3 987,098.41 9,002,337.52
Pembesian 874.59 kg 12,088.42 10,572,428.67
Begesting ( 2 Kali Pakai ) 139.80 m2 125,269.70 17,512,704.06
6 Pekerjaan Kolom Praktis
Beton 3.83 m3 987,098.41 3,775,651.43
Pembesian 413.30 kg 12,088.42 4,996,193.72
Begesting ( 2 Kali Pakai ) 51.00 m2 125,269.70 6,388,754.70
7 Pekerjaan Balok Ring
Beton 7.26 m3 987,098.41 7,166,334.48
Pembesian 623.49 kg 12,088.42 7,536,996.56
Begesting ( 2 Kali Pakai ) 48.40 m2 125,269.70 6,063,053.48
812,074,322.70
D PEK. TIANG , LANTAI PAPAN
1 Pekerjaan lantai ruangan keramik 60 x 60 2,914.40 m2 228,467.25 665,844,953.40
2 Urugan pasir bawah lantai 145.72 m3 297,775.00 43,391,773.00
3 Pas. Tiang Kayu Kelas II (ukur) 22.98 m3 13,307,360.00 305,835,070.46
4 Pas. Suai Tiang Kayu Kelas II 5.04 m3 13,307,360.00 67,069,094.40
1,082,140,891.26
E PEK. RANGKA KAP ATAP
1 Kuda-kuda Atap /mander/tumpangsari 9.74 m3 4,176,249.00 40,668,312.76
2 Rangka Atap Lanan 4,054.10 m2 56,787.50 230,222,203.75
3 Atap Genteng Metal 4,054.10 m2 141,897.25 575,265,641.23
4 List Plank 860.30 m1 250,013.50 215,086,614.05
5 Pemuung/Nok 254.00 m' 82,318.50 20,908,899.00
6 Blandar Kayu Kelas II 6.81 m3 13,307,360.00 90,632,702.90
7 Aksesoris Atap 48.00 bh 208,012.86 9,984,617.28
1,182,768,990.97
F PEKERJAAN DINDING DAN PARTISI
1 Pasangan Batu Bata 1:4 991.60 m2 243,976.26 241,926,859.42
2 Plesteran Dinding Batu Bata 1,983.20 m2 71,531.06 141,860,406.12
3 Acian Dinding Batu Bata 1,983.20 m2 30,749.40 60,982,210.08
4 Partisi Dinding Rangka Hollow 660.00 m2 352,952.60 232,948,716.00
677,718,191.62
G PEKERJAAN PENGECATAN
Cat dasar + Cat kilap pada : tiang, suai tiang, lipslank, Pasangan
1 Batu Bata Meja Reservasi dan Pasangan kamar Mandi serta Partisi 5,467.78 m2 37,826.25 206,825,643.49
Dinding
206,825,643.49
H PEKERJAAN KAMAR MANDI
1 Pasangan Dinding Kamar Mandi menggunakan Batu Bata 1:4 209.88 m2 243,976.26 51,205,737.45
2 Plesteran Dinding Kamar Mandi 419.76 m2 71,531.06 30,025,879.42
3 Acian Dinding Kamar Mandi 419.76 m2 30,749.40 12,907,368.14
4 Kloset Jongkok 18.00 unit 511,417.50 9,205,515.00
5 Floordrain 18.00 unit 65,367.50 1,176,615.00
6 Pintu Kamar Mandi/ WC Alumunium 18.00 unit 4,433,137.50 79,796,475.00
7 Boven Light 12.00 unit 393,717.50 4,724,610.00
189,042,200.02
Catatan : - No Electrical Engineering dan Sebagian Mechanical JUMLAH : 4,247,133,701.33
PEMBULATAN : 8,532,726,000.00
UNIT : 2.00
Catatan : - No Electrical Engineering dan Sebagian Mechanical

JUMLAH TOTAL : 17,065,452,000.00


PEMBULATAN : 17,065,452,000.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN REST AREA


PEKERJAAN : TENAN A 1 - A 5
LOKASI : KULON PROGO YOGYAKARTA

NO URAIAN PEKERJAAN VOLUME SAT ANALISA

I TENAN (48 Unit)

A PEKERJAAN PERSIAPAN
1.00 Pengukuran & Pemasangan Bowplank 190.00 m' 2.00

B PEKERJAAN TANAH
1.00 Galian Tanah Pondasi 80.00 m3
2.00 Urugan Tanah Kembali 26.67 m3
3.00 Urug Pasir Bawah Pondasi 12.00 m3

C PEK. RANGKA BAWAH


1.00 Pas. Pondasi batu kosong 16.00 m3
2.00 Pas. Lantai kerja 4.00 m3
3.00 Pas Pondasi Footplat ( 80 x 80 ) 18 buah
Beton 33.75 m3
Pembesian 1,008.23 kg
Begesting ( 2 Kali Pakai ) 51.00 m2
4.00 Pekerjaan Sloof ( 15 x 20 )
Beton 7.20 m3
Pembesian 899.23 kg
Begesting ( 2 Kali Pakai ) 144.00 m2
5.00 Pekerjaan Umpak Kolom
Beton 1.60 m3
Pembesian 166.81 kg
Begesting ( 2 Kali Pakai ) 27.00 m2

D PEK. TIANG , LANTAI PAPAN


1.00 Pekerjaan lantai ruangan keramik 60 x 60 450.00 m2 9.00
2.00 Urugan pasir bawah lantai 22.50 m3
3.00 Pas. Tiang Kayu Kelas II (ukur) 4.03 m3 7.00
4.00 Pas. Suai Tiang Kayu Kelas II 0.59 m3 -

E PEK. RANGKA KAP ATAP


1.00 Kuda-kuda Atap /mander/tumpangsari 2.43 m3 10.00
2.00 Rangka Atap Lanan 708.05 m2 11.00
3.00 Atap Genteng Metal 708.05 m2 12.00
4.00 List Plank 238.00 m1 14.00
5.00 Pemuung/Nok 5.00 m' 13.00
6.00 Blandar Kayu Kelas II 1.68 m3 7.00
7.00 Aksesoris Atap 30.00 bh -

F PEKERJAAN KUSEN

Pekerjaan Kusen Almunium , Daun Pintu, Daun


Jendela , lengkap dengan asesories, sesuai
gambar dan spesifikasi
1.00 Kusen Type PJ 1 5.00 unit
2.00 Kusen Type J1 45.00 unit
3.00 Kusen Type J2 10.00 unit

G PEKERJAAN PENGECATAN
Cat dasar + Cat kilap pada tiang, suai tiang,
1.00 dan lipslank 145.46 m2 15.00

Catatan :
x5

HARGA SAT JML. HARGA JML. SUB TOTAL

62,118.10 11,802,439.00
11,802,439.00

56,237.50 4,499,000.00
40,975.00 1,092,666.67
211,255.00 2,535,060.00
8,126,726.67

427,269.30 6,836,308.80
829,773.88 3,319,095.50

987,098.41 33,314,571.43
12,088.42 12,187,886.88
125,269.70 6,388,754.70

987,098.41 7,107,108.57
12,088.42 10,870,297.09
125,269.70 18,038,836.80

987,098.41 1,579,357.46
12,088.42 2,016,421.54
125,269.70 3,382,281.90
105,040,920.68

228,467.25 102,810,262.50
297,775.00 6,699,937.50
13,307,360.00 53,655,275.52
13,307,360.00 7,824,727.68
170,990,203.20

4,176,249.00 10,148,285.07
56,787.50 40,208,389.38
141,897.25 100,470,347.86
250,013.50 59,503,213.00
82,318.50 411,592.50
13,307,360.00 22,356,364.80
208,012.86 6,240,385.80
239,338,578.41

8,508,273.00 42,541,365.02
6,763,879.42 304,374,573.73
9,573,655.34 95,736,553.41
442,652,492.16

37,826.25 5,502,055.02
5,502,055.02
JUMLAH : 983,453,415.13
PLUS 10% : 1,081,798,756.65
PEMBULATAN : 1,081,798,000.00
UNIT : 5.00
TOTAL : 5,408,993,783.24
RENCANA ANGGARAN BIAYA

KEGIATAN
PEKERJAAN
LOKASI

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT JML. HARGA JML. SUB TOTAL
A PEKERJAAN PERSIAPAN
1 Pengukuran & Pemasangan Bowplank 39.60 m' 62,118.10 2,459,876.76
2,459,876.76
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 16.00 m3 56,237.50 899,800.00
2 Urugan Tanah Kembali 5.33 m3 40,975.00 218,533.33
3 Urug Pasir Bawah Pondasi 2.40 m3 211,255.00 507,012.00
1,625,345.33
C PEK. RANGKA BAWAH
1 Pas. Pondasi batu kosong 3.20 m3 427,269.30 1,367,261.76
2 Pas. Lantai kerja 0.80 m3 829,773.88 663,819.10
3 Pas Pondasi Footplat ( 80 x 80 ) 16 buah
Beton 6.75 m3 987,098.41 6,662,914.29
Pembesian 201.65 kg 12,088.42 2,437,577.38
Begesting ( 2 Kali Pakai ) 10.20 m2 125,269.70 1,277,750.94
4 Pekerjaan Sloof ( 15 x 20 )
Beton 1.80 m3 987,098.41 1,776,777.14
Pembesian 224.81 kg 12,088.42 2,717,574.27
Begesting ( 2 Kali Pakai ) 36.00 m2 125,269.70 4,509,709.20
5 Pekerjaan Umpak Kolom
Beton 0.32 m3 987,098.41 315,871.49
Pembesian 33.36 kg 12,088.42 403,284.31
Begesting ( 2 Kali Pakai ) 4.80 m2 125,269.70 601,294.56
22,733,834.44
D PEK. TIANG , LANTAI PAPAN
1 Pekerjaan lantai ruangan keramik 60 x 60 56.00 m2 228,467.25 12,794,166.00
2 Urugan pasir bawah lantai 2.80 m3 297,775.00 833,770.00
3 Pas. Tiang Kayu Kelas II (ukur) 0.81 m3 13,307,360.00 10,731,055.10
4 Pas. Suai Tiang Kayu Kelas II 0.12 m3 13,307,360.00 1,564,945.54
25,923,936.64
E PEK. RANGKA KAP ATAP
1 Kuda-kuda Atap /mander/tumpangsari 0.49 m3 4,176,249.00 2,029,657.01
2 Rangka Atap Lanan 116.39 m2 56,787.50 6,609,497.13
3 Atap Genteng Metal 116.39 m2 141,897.25 16,515,420.93
4 List Plank 31.90 m1 250,013.50 7,975,430.65
5 Pemuung/Nok 1.00 m' 82,318.50 82,318.50
6 Blandar Kayu Kelas II 0.30 m3 13,307,360.00 3,979,432.93
7 Aksesoris Atap 6.00 bh 208,012.86 1,248,077.16
38,439,834.31
F PEKERJAAN KUSEN

Pekerjaan Kusen Almunium , Daun Pintu, Daun Jendela ,


lengkap dengan asesories, sesuai gambar dan spesifikasi
1 Kusen Type PJ 1 1.00 unit 7,466,400.01 7,466,400.01
2 Kusen Type J1 10.00 unit 3,757,222.96 37,572,229.58
3 Kusen Type J2 1.00 unit 3,778,891.90 3,778,891.90
48,817,521.49
G PEKERJAAN PENGECATAN
1 Cat dasar + Cat kilap pada tiang, suai tiang, dan lipslank 1,087.60 m2 37,826.25 41,139,950.54
41,139,950.54
JUMLAH : 181,140,299.51
PENYEDIA JASA :
NO. KONTRAK :
NO. SPMK :

TAHUN 2019
NILAI PEKERJAAN
NO. URAIAN KEGIATAN BOBOT AGUSTUS SEPTEMBER OKTOBER
(Rp.)
26-31 2-7 9-14 16-21 23-28 30-5 7-12

I PEK. PERSIAPAN
PENGUKURAN DAN PASANG BOUWPLANK 165,855,327.00 1.30 0.14 0.14 0.14 0.14 0.14 0.14 0.14
MOB DAN DEMOB 50,000,000.00 0.39 0.06 0.06 0.06
ADM DAN DOKUMENTASI 80,000,000.00 0.63 0.015 0.015 0.015 0.015 0.015 0.015 0.015

II PEK. PEMB. PUJASERA & TENAN


PEK. TANAH
GALIAN TANAH PONDASI 25,644,300.00 0.20 0.13 0.13 0.13
URUGAN TANAH KEMBALI 6,228,200.00 0.05 0.05 0.05
URUG PASIR BAWAH PONDASI 14,449,842.00 0.11 0.11 0.11
PEK. RANGKA BAWAH
PAS. PONDASI BATU KSONG 38,966,960.16 0.31 0.20 0.20 0.20
PAS. LANTAI KERJA 18,918,844.37 0.15 0.15 0.15
PAS. PONDASI FOOTPLAT ( 80 x 80 ) 325,123,493.28 2.55 0.32 0.60 0.60 0.60 0.60 0.60
PEK. SLOOF ( 15 x 20 ) 356,050,570.28 2.79 0.47 0.77 0.77
PEK UMPAK KOLOM 37,087,470.25 0.29 0.10 0.10
PEK. KOLOM PRAKTIS 15,160,599.85 0.12 0.01
PEK. BALOK RING 20,766,384.51 0.16
PEK. TIANG & LANTAI
PEK. LANTAI RUANGAN KERAMIK 60 X 60 665,844,953.40 5.22
URUGAN PASIR BAWAH TANAH 43,391,773.00 0.34
PAS. TIANG KAYU KELAS 2 (UKUR) 305,835,070.46 2.40
PAS. SUAI TIANG KAYU KELAS II 67,069,094.40 0.53
PEK. RANGKA KAP ATAP
KUDA-KUDA ATAP/MANDER/TUMPANGSARI 40,668,312.76 0.32
RANGKA ATAP LANAN 230,222,203.75 1.81
ATAP GENTENG METAL 575,265,641.23 4.51
LIST PLANK 215,086,614.05 1.69
PEMUUNG/NOK 20,908,899.00 0.16
BLANDAR KAYU KELAS II 90,632,702.90 0.71
AKSESORIS ATAP 9,984,617.28 0.08
PEK. DINDING DAN PRAKTISI
PASANGAN BATU BATA1:4 241,926,859.42 1.90
PLESTERAN DINDING BATU BATA 141,860,406.12 1.11
ACIAN DINDING BATU BATA 60,982,210.08 0.48
PARTISI DINDING RANGKA HOLLOW 232,948,716.00 1.83
PEK. PENGECATAN
CAT DASAR + CAT KILAP PADA :TIANG, SUAI TIANG 206,825,643.49 1.62
LISPLANK, PASANGAN BATU BATA MEJA RESERVASI
DAN PASANGAN KAMAR MANDI SERTA PARTISI
DINDING
PEK. KAMAR MANDI
PASANGAN DINDING KAMAR MANDI MENGGUNAKAN 51,205,737.45 0.40
BATU BATA 1:4
PLESTERAN DINDING KAMAR MANDI 30,025,879.42 0.24
ACIAN DINDING KAMAR MANDI 12,907,368.14 0.10
KLOSET JONGKOK 9,205,515.00 0.07
FLOORDRAIN 1,176,615.00 0.01
PINTU KAMAR MANDI/WC ALUMUNIUM 79,796,475.00 0.63
BOVEN LIGHT 4,724,610.00 0.04

III PEK. LANDSCAPE


PEK PERSIAPAN
PENGUKURAN DAN PEMASANGAN BOUWPLANK 10,000,000.00 0.08 0.030 0.030
PEK. TANAH
TIMBUNAN TANAH PEMATANGAN LAHAN 45,916,146.62 0.36 0.05 0.05 0.05 0.05
LANTAI KERJA BETON COR K-150 21,330,185.54 0.17 0.01 0.01 0.01 0.01
PAS. BATU/TALUD PENGAMAN LANDSCAPE 512,250,618.88 4.02 0.50
PEK.RIGID BETON
RIGID BETON ZONA A 3,773,565,806.92 29.6 1.39
RIGID BETON ZONA B 54,128,759.02 0.42
PEK. TAMAN DAN LANDSCAPE 56,034,557.63 0.44
PEK. PEDESTRIAN 37,638,373.71 0.30
PEK. DRAINASE 136,063,635.59 1.07

IV PEK. POWER HOUSE


PEK. PONDASI DAN STRUKTUR BAWAH 136,077,089.04 1.07
PEK STRUKTUR ATAS 113,922,910.96 0.89

V PEK. MEKANIKAL ELEKTRIKAL


PEK. ELEKTRIKAL 2,113,540,000.00 16.6 1.39 1.39 1.39

VI PEK. BANGUNAN PENUNJANG


PEK. PEMBUATAN PAGAR LOKASI 500,000,000.00 3.92 0.25 0.25 0.25 0.25 0.25 0.25
PEK. PEMBUATAN DRAINASE 750,000,000.00 5.88 0.26 0.26 0.26 0.26 0.26

JUMLAH 12,753,215,992.97 100.00


PROGRESS/MINGGU 0.29 1.11 1.91 1.82 3.26 3.63 5.54
RENCANA
KOMULATIF 0.29 1.39 3.31 5.12 8.39 12.02 17.56
PROGRESS/MINGGU
REALISASI
KOMULATIF
Chart Title

TAHUN 2019 TAHUN 2020


OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI
14-19 21-26 28-2 4-9 11-16 18-23 25-30 2-7 9-14 16-21 23-28 30-4 6-11 13-18 20-25 27-1 3-8 10-15 17-22

0.06
0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015

0.60 0.60
0.77 0.77 0.77
0.10 0.10 0.10 0.10
0.01 0.01 0.01 0.01 0.01
0.02 0.02 0.02 0.02 0.02 0.02

0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93


0.17 0.24
0.60 1.20 1.20 1.20
0.26 0.42

0.16 0.40
0.45 0.80 0.80 0.80
1.59 1.59 1.59 1.59 1.60
0.56 1.16 1.16
0.16
0.36 0.82
0.04 0.20

0.47 0.36 0.36 0.36


0.56 0.42
0.24 0.18
0.61 0.46 0.46

0.54 0.41 0.41

0.20 0.15

0.06 0.06 0.06


0.04 0.04
0.07
0.01
0.31 0.24
0.04

0.05 0.06
0.01 0.01 0.01 0.01 0.01
0.50 0.50 0.50 0.50 0.50

1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.07 0.07 0.07 0.07 0.07
0.04 0.04 0.04 0.04 0.04 0.04
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04

0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07


0.10 0.10

1.39 1.39 1.39 1.39 1.39 1.39

0.25 0.25 0.25 0.25 0.25 0.25


0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26

5.47 5.45 4.79 6.06 6.98 5.83 4.05 6.20 7.80 9.04 7.16 4.63 1.88 1.52 1.52 0.13 0.13 0.22 0.22
23.03 28.48 33.27 39.33 46.30 52.14 56.19 62.39 70.19 79.23 86.39 91.02 92.90 94.42 95.94 96.07 96.20 96.42 96.65

Mengetahui Disetujui,
PT. PERUMDA ANEKA USAHA
(…………………………….) (…………………………….)
AHUN 2020
FEBRUARI MARET KET.
24-29 2-7 9-14 16-21 23-28

0.08
0.015 0.015 0.015 0.015 0.015

0.04

0.07 0.07 0.07


0.10 0.10 0.10 0.10 0.10

0.22 0.18 0.18 0.11 0.19


96.87 97.06 97.24 97.35 97.54

Dibuat,
PT. AVICENA PERKASA
(…………………………….)
DAFTAR ANALISA

A. 2.2.1.9 (K3) Pembersihan 1 m2 lapangan dan peralatan


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.100 65,000.00 6,500.00
Mandor L.04 OH 0.005 95,000.00 475.00
Jumlah Tenaga Kerja 6,975.00
B BAHAN
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 6,975.00
E Overhead & Profit (10%) 4% x D 279.00
F Harga Satuan Pekerjaan (D+E) 7,254.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A. 2.3.1.1 Penggalian 1 m3 Tanah Biasa sedalam 1 m


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.750 65,000.00 48,750.00
Mandor L.04 OH 0.025 95,000.00 2,375.00
Jumlah Tenaga Kerja 51,125.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 51,125.00
E Overhead & Profit (10%) 4% x D 2,045.00
F Harga Satuan Pekerjaan (D+E) 53,170.00
A. 2.3.1.11 Pengurugan 1 m3 dengan pasir urug
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.300 65,000.00 19,500.00
Mandor L.04 OH 0.010 95,000.00 950.00
Jumlah Tenaga Kerja 20,450.00
B BAHAN
Pasir Urug m3 1.200 103,300.00 123,960.00
Jumlah Harga Bahan 123,960.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 144,410.00
E Overhead & Profit (10%) 4% x D 5,776.40
F Harga Satuan Pekerjaan (D+E) 150,186.40

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A. 3.2.1.2 Pemasangan 1m3 pondasi batu belah campuran 1SP : 4PP


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.500 65,000.00 97,500.00
Tukang batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 100,000.00 7,500.00
Mandor L.04 OH 0.075 95,000.00 7,125.00
Jumlah Tenaga Kerja 179,625.00
B BAHAN
Batu Belah/ Kali m3 1.200 265,640.00 318,768.00
Semen Portland Kg 163.000 1,523.30 248,297.90
Pasir Pasang m3 0.520 92,820.00 48,266.40
Jumlah Harga Bahan 615,332.30
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 794,957.30
E Overhead & Profit (10%) 4% x D 31,798.29
F Harga Satuan Pekerjaan (D+E) 826,755.59

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Catatan : Bobot isi pasir = 1400 kg/m3 , Bobot isi kerikil = 1350 kg/m3
A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12.2 Mpa (K 150),slump (12 ± 2) cm, w/c = 0.72
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 95,000.00 7,885.00
Jumlah Tenaga Kerja 142,685.00
B BAHAN
Semen Portland kg 299 1,523.30 455,466.70
Pasir Beton kg 799 112.82 90,143.18
Kerikil (Maks 30 mm) kg 1,017 112.82 114,737.94
Air Liter 215 50.00 10,750.00
Jumlah Harga Bahan 671,097.82
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 813,782.82
E Overhead & Profit (10%) 4% x D 32,551.31
F Harga Satuan Pekerjaan (D+E) 846,334.13
A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 95,000.00 7,885.00
Jumlah Tenaga Kerja 142,685.00
B BAHAN
Semen Portland kg 352 1,523.30 536,201.60
Pasir Beton kg 731 112.82 82,471.42
Kerikil (Maks 30 mm) kg 1,031 112.82 116,317.42
Air Liter 215 50.00 10,750.00
Jumlah Harga Bahan 745,740.44
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 888,425.44
E Overhead & Profit (10%) 4% x D 35,537.02
F Harga Satuan Pekerjaan (D+E) 923,962.46

A. 4.1.1.17 Pembesian 10 kg dengan besi polos


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.070 65,000.00 4,550.00
Tukang besi L.02 OH 0.070 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.007 100,000.00 700.00
Mandor L.04 OH 0.004 95,000.00 380.00
Jumlah Tenaga Kerja 11,930.00
B BAHAN
Besi Beton Polos kg 10.500 9,800.00 102,900.00
Kawat Beton kg 0.150 24,880.00 3,732.00
Jumlah Harga Bahan 106,632.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 118,562.00
E Overhead & Profit (10%) 4% x D 4,742.48
F Harga Satuan Pekerjaan (D+E) 123,304.48
G Harga Satuan per kg besi F : 10 kg 12,330.45

A. 4.1.1.21 Pemasangan 1m2 bekesting untuk sloof


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.520 65,000.00 33,800.00
Tukang kayu L.02 OH 0.260 90,000.00 23,400.00
Kepala Tukang L.03 OH 0.026 100,000.00 2,600.00
Mandor L.04 OH 0.026 95,000.00 2,470.00
Jumlah Tenaga Kerja 62,270.00
B BAHAN
Kayu Klas III m3 0.045 3,598,000.00 161,910.00
Paku 5 - 10 cm kg 0.300 16,660.00 4,998.00
Minyak Bekesting liter 0.100 26,500.00 2,650.00
Jumlah Harga Bahan 169,558.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 231,828.00
E Overhead & Profit (10%) 4% x D 9,273.12
F Harga Satuan Pekerjaan (D+E) 241,101.12
G Pemakaian Bekisting 3 x Pakai 80,367.04
A. 4.1.1.23 Pemasangan 1m2 bekesting untuk balok
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang kayu L.02 OH 0.330 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.033 100,000.00 3,300.00
Mandor L.04 OH 0.033 95,000.00 3,135.00
Jumlah Tenaga Kerja 79,035.00
B BAHAN
Kayu Klas III m3 0.040 0.00 0.00
Paku 5 - 10 cm kg 0.400 16,660.00 6,664.00
Minyak Bekesting liter 0.200 26,500.00 5,300.00
Balok Kayu Klas II m3 0.018 3,002,800.00 54,050.40
Plywood tebal 9 mm Lbr 0.350 156,300.00 54,705.00
Dolken kayu ᴓ 8 - 10 cm - panjang 4
Batang 2.000 0.00 0.000
m
Jumlah Harga Bahan 120,719.40
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 199,754.40
E Overhead & Profit (10%) 4% x D 7,990.18
F Harga Satuan Pekerjaan (D+E) 207,744.58
G Pemakaian Bekisting 3 x Pakai 69,248.19

A. 4.1.1.24 Pemasangan 1m2 bekesting untuk Plat Penutup saluran


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang kayu L.02 OH 0.330 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.033 100,000.00 3,300.00
Mandor L.04 OH 0.033 95,000.00 3,135.00
Jumlah Tenaga Kerja 79,035.00
B BAHAN

Paku 5 - 10 cm kg 0.400 16,660.00 6,664.00


Minyak Bekesting liter 0.200 26,500.00 5,300.00
Balok Kayu Klas IV m3 0.015 3,002,800.00 45,042.00
Plywood tebal 9 mm Lbr 0.350 156,300.00 54,705.00

Jumlah Harga Bahan 111,711.00


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 190,746.00
E Overhead & Profit (10%) 4% x D 7,629.84
F Harga Satuan Pekerjaan (D+E) 198,375.84
A. 4.1.1.25 Pemasangan 1m2 bekesting untuk dinding saluran
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang kayu L.02 OH 0.330 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.033 100,000.00 3,300.00
Mandor L.04 OH 0.033 95,000.00 3,135.00
Jumlah Tenaga Kerja 79,035.00
B BAHAN

Paku 5 - 10 cm kg 0.400 16,660.00 6,664.00


Minyak Bekesting liter 0.200 26,500.00 5,300.00
Balok Kayu Klas IV m3 0.020 3,002,800.00 60,056.00
Plywood tebal 9 mm Lbr 0.350 156,300.00 54,705.00

Jumlah Harga Bahan 126,725.00


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 205,760.00
E Overhead & Profit (10%) 4% x D 8,230.40
F Harga Satuan Pekerjaan (D+E) 213,990.40
G Bekisting 3 x Pakai 71,330.13

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A. 4.4.1.7 Pemasangan 1 m2 dinding bata merah (5 x11x 22) cm tebal 1/2 batu campuran 1SP : 2PP
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.300 65,000.00 19,500.00
Tukang batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.015 95,000.00 1,425.00
Jumlah Tenaga Kerja 30,925.00
B BAHAN
Bata Merah bh 70.000 600.00 42,000.00
Semen Portland kg 18.950 1,523.30 28,866.54
Pasir Pasang m3 0.038 92,820.00 3,527.16
Jumlah Harga Bahan 74,393.70
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 105,318.70
E Overhead & Profit (10%) 4% x D 4,212.75
F Harga Satuan Pekerjaan (D+E) 109,531.44
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A. 4.4.2.2 Pemasangan 1 m2 Plesteran 1SP : 2PP tebal 15 mm


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.300 65,000.00 19,500.00
Tukang batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 100,000.00 1,500.00
Mandor L.04 OH 0.015 95,000.00 1,425.00
Jumlah Tenaga Kerja 35,925.00
B BAHAN
Semen Portland kg 10.224 1,523.30 15,574.22
Pasir Pasang m3 0.020 92,820.00 1,856.40
Jumlah Harga Bahan 17,430.62
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 53,355.62
E Overhead & Profit (10%) 4% x D 2,134.22
F Harga Satuan Pekerjaan (D+E) 55,489.84

A. 4.4.3.66 Pemasangan 1 m2 paving block berwarna tebal 6 cm


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.25 65,000.00 16,250.00
Tukang batu L.02 OH 0.50 90,000.00 45,000.00
Kepala tukang L.03 OH 0.05 100,000.00 5,000.00
Mandor L.04 OH 0.0013 95,000.00 123.50

Jumlah Tenaga Kerja 66,373.50


B BAHAN
Paving block 6 cm berwarna m2 1.01 96,520.00 97,485.20
Pasir beton m3 0.05 92,820.00 4,641.00

Jumlah Harga Bahan 102,126.20


C PERALATAN
Peralatan % 10

Jumlah Harga Alat


D Jumlah (A + B + C) 168,499.70
E Overhead & Profit (10%) 4% x D 6,739.99
F Harga Satuan Pekerjaan (D+E) 175,239.69
ANALISA HARGA SATUAN KUSEN

Harga Satuan Harga Bahan Jumlah + Profit 10% TOTAL BIAYA


No. Uraian Pekerjaan Analisa/ Satuan Upah Kerja (Rp) Jumlah (Rp) VOLUME
(Rp) (Rp) (Rp) (Rp)
A B C D E F G H I J
1 Unit KUSEN PJ 1
A Pasang Kusen pintu/jendela allumunium
natural 4" BAHAN
1.1000 m1 Alumunium profil natural 4" 180,000.00 198,000.00
2.0000 bh Skrup fixer 301.83 603.67
1.0000 m1 Sealant 8,640.00 8,640.00
UPAH
0.0850 OH Pekerja 65,000.00 5,525.00
0.0850 OH Tukang Alumunium 90,000.00 7,650.00
0.0085 OH Kepala Tukang 100,000.00 850.00
0.0050 OH Mandor 95,000.00 475.00
JUMLAH 14,500.00 207,243.67 221,743.67 243,918.03 14.70 3,585,595.09
B Pemasangan Kaca (M2)
BAHAN
1.1000 M2 Kaca 6 mm 154,700.00 170,170.00
UPAH
0.0150 OH Pekerja 65,000.00 975.00
0.1500 OH Tukang Alumunium 90,000.00 13,500.00
0.0150 OH Kepala Tukang 100,000.00 1,500.00
0.0008 OH Mandor 95,000.00 71.25
JUMLAH 16,046.25 170,170.00 186,216.25 204,837.88 10.80 2,212,249.05
C Pasang Pintu Alluminium Natural (M2)
BAHAN
1.0000 M2 Pintu Alluminium Natural 250,000.00 250,000.00
UPAH
1.0500 OH Tukang Alumunium 90,000.00 94,500.00
1.0500 OH Pekerja 65,000.00 68,250.00
0.1050 OH Kepala Tukang 100,000.00 10,500.00
0.0052 OH Mandor 95,000.00 494.00
JUMLAH 173,744.00 250,000.00 423,744.00 466,118.40 3.96 1,845,828.86
D 1 Buah Pasang Engsel
BAHAN
1.0000 bh Engsel 81,000.00 81,000.00
UPAH
0.0150 OH Pekerja 65,000.00
0.1500 OH Tukang 90,000.00
0.0150 OH Kepala Tukang 100,000.00
0.0008 OH Mandor 95,000.00
JUMLAH - 81,000.00 81,000.00 89,100.00 6.00 534,600.00
E Handle Plus Kunci
BAHAN
1.0000 bh Handle 300,000.00 300,000.00
JUMLAH - 300,000.00 300,000.00 330,000.00 1.00 330,000.00
JUMLAH 8,508,273.00
1 Unit KUSEN J1
A Pasang Kusen pintu/jendela allumunium
natural 4" BAHAN
1.1000 m1 Alumunium profil natural 4" 180,000.00 198,000.00
2.0000 bh Skrup fixer 301.83 603.67
1.0000 m1 Sealant 8,640.00 8,640.00
UPAH
0.0850 OH Pekerja 65,000.00 5,525.00
0.0850 OH Tukang Alumunium 90,000.00 7,650.00
0.0085 OH Kepala Tukang 100,000.00 850.00
0.0050 OH Mandor 95,000.00 475.00
JUMLAH 14,500.00 207,243.67 221,743.67 243,918.03 20.55 5,012,515.59
B Pemasangan Kaca (M2)
BAHAN
1.1000 M2 Kaca 6 mm 154,700.00 170,170.00
ANALISA HARGA SATUAN KUSEN

Harga Satuan Harga Bahan Jumlah + Profit 10% TOTAL BIAYA


No. Uraian Pekerjaan Analisa/ Satuan Upah Kerja (Rp) Jumlah (Rp) VOLUME
(Rp) (Rp) (Rp) (Rp)
A B C D E F G H I J
UPAH
0.0150 OH Pekerja 65,000.00 975.00
0.1500 OH Tukang Alumunium 90,000.00 13,500.00
0.0150 OH Kepala Tukang 100,000.00 1,500.00
0.0008 OH Mandor 95,000.00 71.25
JUMLAH 16,046.25 170,170.00 186,216.25 204,837.88 8.55 1,751,363.83
JUMLAH 6,763,879.42
1 Unit KUSEN J2
A Pasang Kusen pintu/jendela allumunium
natural 4" BAHAN
1.1000 m1 Alumunium profil natural 4" 180,000.00 198,000.00
2.0000 bh Skrup fixer 301.83 603.67
1.0000 m1 Sealant 8,640.00 8,640.00
UPAH
0.0850 OH Pekerja 65,000.00 5,525.00
0.0850 OH Tukang Alumunium 90,000.00 7,650.00
0.0085 OH Kepala Tukang 100,000.00 850.00
0.0050 OH Mandor 95,000.00 475.00
JUMLAH 14,500.00 207,243.67 221,743.67 243,918.03 29.55 7,207,777.89
B Pemasangan Kaca (M2)
BAHAN
1.1000 M2 Kaca 6 mm 154,700.00 170,170.00
UPAH
0.0150 OH Pekerja 65,000.00 975.00
0.1500 OH Tukang Alumunium 90,000.00 13,500.00
0.0150 OH Kepala Tukang 100,000.00 1,500.00
0.0008 OH Mandor 95,000.00 71.25
JUMLAH 16,046.25 170,170.00 186,216.25 204,837.88 11.55 2,365,877.46
JUMLAH 9,573,655.34
HARGA UPAH DAN BAHAN

No. Nama Jenis Barang Satuan Harga


A. UPAH
Mandor Orang 95,000.00
Kepala Tukang Orang 100,000.00
Tukang Orang 90,000.00
Pekerja Orang 65,000.00

B. HARGA BAHAN
Air Ltr 50.00
Kayu Kelas 1 m3 5,130,000.00
Kayu Kelas 2 m3 4,464,000.00
Kayu Kelas 3 m3 3,598,000.00
Kayu kelas 4 m3 3,002,800.00
List Eternit Kayu m1 14,928.00
Batu Kali / Belah m3 265,640.00
Papan Kayu Lembar 155,500.00
Paku Beton 4 Inchi kotak 31,100.00
Paku Seng kg 18,880.00
Paku Kayu kg 16,660.00
Pasir Urug m3 103,300.00
Pasir Beton m3 112,820.00
Kerikil Beton m3 112,820.00
Semen Portland kg 1,523.30
Semen 40 kg Zak 60,932.00
Semen Warna Zak 186,600.00
Besi Polos kg 9,800.00
Keramik 40x40 Bh 9,774.24
Kawat Beton kg 24,880.00
Paku Kayu kg 18,660.00
Paku Beton kg 31,100.00
Pasir Pasang m3 92,820.00
Paving Block m2 96,520.00
Batu Bata buah 600.00
Tanah Timbunan m3 82,640.00
Multiplex 3 mm Lembar 78,000.00
Minyak Bekisting Ltr 26,500.00
Pipa PVC 3" m1 67,855.00
Tanah Timbun m3 82,640.00
Pipa PVC 1" m1 49,760.00
Multiplex 9mm M2 156,300.00
Dolken kayu ᴓ 8 - 10 cm - panjang 4 m Btg 20,000.00
Beton K-250 (Ready Mix) M3 1,125,000.00
Pembesian Wiremesh Ø 8 Kg 9,800.00
Plastik Alas Cor Rigid Kg 2,000.00
Paving Block m2 96,520.00
REKAPITULASI

PEKERJAAN : PERENCANAAN REST & RESORT AREA PANDAWA MAETALA


LOKASI : KULON PROGO, YOGYAKARTA
PROVINSI : YOGYAKARTA
TAHUN : 2019

No. Uraian Pekerjaan Jumlah Harga


1 2 3
A PEKERJAAN PEMBANGUNAN PUJASERA & TENAN Rp 8,532,726,000.00
D PEKERJAAN LANDSCAPE Rp 4,646,928,083.92
E PEKERJAAN POWER HOUSE Rp 250,000,000.00
F PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 2,113,540,000.00
G PEKERJAAN BANGUNAN PENUNJANG
I PEK. PEMBUATAN PAGAR LOKASI Rp 500,000,000.00
II PEK. DRAINASE Rp 750,000,000.00
JUMLAH Rp 16,793,194,083.92
Ppn 10% Rp 1,679,319,408.39
TOTAL Rp 18,472,513,492.31
DIBULATKAN Rp 18,472,513,000.00
Terbilang : Delapan Belas Milyar Empat Ratus Tujuh Puluh Dua Juta Lima Ratus Tiga Belas Ribu Rupiah
Dibuat,
PT.AVICENA PERKASA

(………………….)
RENCANA ANGGARAN BIAYA
PEKERJAAN : PERENCANAAN REST & RESORT AREA PANDAWA MAETALA
LOKASI : KULON PROGO, YOGYAKARTA
PROVINSI : YOGYAKARTA
TAHUN : 2019

No. Uraian Pekerjaan Volume/Sat Analisa Harga Satuan Jumlah Harga


1 2 3 4 5 6
A Pekerjaan Persiapan
1 Pembersihan Lapangan 42,920.00 m2 Taksir 1,000.00 42,920,000.00
2 Pengukuran dan Pemasangan Bowplank 1.00 Ls Taksir 10,000,000.00 10,000,000.00
3 Papan Nama Proyek 1.00 Ls Taksir 1,500,000.00 1,500,000.00
4 Direksi Keet / Gudang Material 1.00 Ls Taksir 5,000,000.00 5,000,000.00
Sub-Total 59,420,000.00
B Pekerjaan Tanah
1 Timbunan Tanah Pematangan Lahan 8,584.00 m3 Analisa EI-321 131,489.54 1,128,706,192.92
2 Lantai Kerja Beton Cor K-150 25.60 m3 A. 4.1.1.3 833,210.37 21,330,185.54
3 Pas. Batu/Talud Pengaman Landscape 640.00 m3 A. 3.2.1.2 800,391.59 512,250,618.88
Sub-Total 1,662,286,997.35
C Pekerjaan Rigid Beton
a. Rigid Beton Zona A
1 Lapisan Aggregat A 7,008.00 m3 Analisa EI-511 484,184.34 3,393,163,833.82
2 Pembesian Wiremesh Ø 8 7,116.13 kg Taksir 9,800.00 69,738,076.45
3 Plastik Alas Cor Rigid 1,335.00 m2 Taksir 2,000.00 2,670,000.00
4 Beton K-250 (Ready Mix) 266.82 m3 Taksir 1,125,000.00 300,166,875.00
5 Bekisting Untuk Beton 41.91 m2 A. 4.1.1.24 186,775.68 7,827,021.65

b. Rigid Beton Zona B


1 Urugan Pasir 26.60 m3 A. 2.3.1.11 149,354.40 3,972,827.04
2 Beton K-250 (Ready Mix) 38.00 m3 Taksir 1,250,000.00 47,500,000.00
3 Bekisting Untuk Rigid Beton 4.02 m2 A. 4.1.1.24 186,775.68 750,838.23

4 Cetakan Tali Air 1,524.08 m1 Taksir 1,250.00 1,905,093.75


Sub-Total 3,827,694,565.94
D Pekerjaan Taman Dan Landscape
1 Galian Tanah Bawah Beton Kerb 8.07 m3 A. 2.3.1.1 51,090.00 412,500.66
2 Urugan Pasir Bawah Beton Kerb 4.04 m3 A. 2.3.1.11 149,354.40 602,943.71
3 Beton Kerb (K-150) 11.75 m3 A. 4.1.1.3 833,210.37 9,786,055.83
4 Tanah Humus Timbunan Taman + Pupuk NPK 53.04 m3 Taksir 90,000.00 4,773,600.00
5 Penanaman Pohon Tanjung (T=1m) + Tertanam 1.00 Btg Taksir 600,000.00 600,000.00
6 Penanaman Pohon Cemara Laut (T=1m) + Tertanam 14.00 Btg Taksir 450,000.00 6,300,000.00
7 Penanaman Pohon Ketapang (T=1m) + Tertanam 4.00 Btg Taksir 600,000.00 2,400,000.00
8 Penanaman Pohon Palem Putri (T=1m) + Tertanam 4.00 Btg Taksir 600,000.00 2,400,000.00
10 Penanaman Bunga Asoka + Tertanam 16.00 Btg Taksir 55,000.00 880,000.00
11 Rumput Taman + Tertanam 186.25 m2 Taksir 85,250.00 15,877,812.50
12 Galian Tanah Sloof (Bangku Taman) 2.54 m3 A. 2.3.1.1 51,090.00 129,551.47
13 Urugan Pasir Bawah Sloof 1.10 m3 A. 2.3.1.11 149,354.40 164,663.23

14 Timbunan Tanah (Bangku Taman) 3.24 m3 Taksir 120,000.00 388,500.00


15 Sloof 13/13 (Bangku duduk taman)
a. Beton Cor K-150 0.58 m3 A. 4.1.1.3 833,210.37 487,211.43
b. Pembesian 114.91 kg A. 4.1.1.17 12,105.18 1,390,953.43
c. Bekisting 9.00 m2 A. 4.1.1.21 77,320.53 695,575.52
d. Menyiram beton dan membongkar bekisting 0.58 m3 Taksir 63,000.00 36,838.62

16 Balok 13/13 (Bangku duduk taman)


a. Beton Cor K-150 0.58 m3 A. 4.1.1.3 833,210.37 487,211.43
b. Pembesian 114.91 kg A. 4.1.1.17 12,105.18 1,390,953.43
c. Bekisting 9.00 m2 A. 4.1.1.23 65,381.47 588,171.72
d. Menyiram beton dan membongkar bekisting 0.58 m3 Taksir 63,000.00 36,838.62

17 Pasangan Dinding Bata 1Pc : 2 Ps (Bangku dan dinding tama 30.10 m2 A. 4.4.1.7 105,704.24 3,181,909.12
18 Plasteran Dinding Bata 1PC : 2Ps (Bangku dan dinding taman 60.20 m2 A. 4.4.2.2 50,217.04 3,023,266.92
Sub-Total 56,034,557.63
No. Uraian Pekerjaan Volume/Sat Analisa Harga Satuan Jumlah Harga
1 2 3 4 5 6
E Pekerjaan Pedestrian
1 Galian Tanah Bawah Beton Kansteen 2.27 m3 A. 2.3.1.1 51,090.00 115,769.94
2 Urugan Pasir Bawah Beton Kansteen 2.27 m3 A. 2.3.1.11 149,354.40 338,437.07
3 Kansteen Pedestrian (bagian Luar Pedestrian Samping Jalan) 262.00 unit Taksir 45,000.00 11,790,000.00
4 Timbunan Tanah Bawah Pedestrian 21.17 m3 Analisa EI-321 131,489.54 2,783,173.30
5 Pemasangan Paving Block (pedestrian) 141.11 m2 A. 4.4.3.66 160,236.65 22,610,993.40
Sub-Total 37,638,373.71
F Pekerjaan Drainase
1 Galian Tanah Drainase 51.52 m3 A. 2.3.1.1 51,090.00 2,632,156.80
2 Urugan Pasir Bawah Saluran Drainase 6.44 m3 A. 2.3.1.11 149,354.40 961,842.34
3 Beton Cor K-150 (Lantai Drainase Landscape)
a. Beton Cor K-150 11.90 m3 A. 4.1.1.3 833,210.37 9,915,203.44
b. Pembesian 506.29 kg A. 4.1.1.17 12,105.18 6,128,748.74

3 Beton Cor K-150 (Dinding Drainase Landscape)


a. Beton Cor K-150 23.80 m3 A. 4.1.1.3 833,210.37 19,830,406.87
b. Pembesian 1,013.47 kg A. 4.1.1.17 12,105.18 12,268,255.96
c. Bekisting 476.56 m2 A. 4.1.1.25 67,463.41 32,150,364.26
d. Menyiram beton dan membongkar bekisting 23.80 m3 Taksir 63,000.00 1,499,400.00

4 Beton Cor K-150 (Penutup Drainase Landscape)


a. Beton Cor K-150 11.90 m3 A. 4.1.1.3 833,210.37 9,915,203.44
b. Pembesian 506.29 kg A. 4.1.1.17 12,105.18 6,128,748.74
c. Bekisting 102.12 m2 A. 4.1.1.24 186,775.68 19,073,532.44
d. Menyiram beton dan membongkar bekisting 11.90 m3 Taksir 63,000.00 749,700.00

5 Box Culvert (Pintu Masuk dan Keluar dari Parkir Truck)


a. Beton Cor K-200 2.77 m3 A. 4.1.1.6 910,838.70 2,524,844.87
b. Pembesian 614.09 kg A. 4.1.1.17 12,105.18 7,433,645.33
c. Bekisting 49.68 m2 A. 4.1.1.25 67,463.41 3,351,582.37

5 Pipa Drainhole Ø1 inch 1.00 Ls Taksir 1,500,000.00 1,500,000.00


Sub-Total 136,063,635.59
HARGA PERKIRAAN SENDIRI (HPS)
RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN GEDUNG POWER HOUSE
REST AREA KULON PROGO ,YOGYAKARTA
LOKASI :
TH. ANGGARAN : 2019

NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA


01 02 03 05 06

I PEKERJAAN PERSIAPAN
1 Bowplank 48.00 m' 65,398.77 3,139,140.96
2 Air kerja & Listrik 1.00 Ls 1,500,000.00 1,500,000.00
Sub Jumlah 4,639,140.96

II PEKERJAAN TANAH
1 Peninggian Elevasi Tanah 35.15 m3 192,352.50 6,760,344.02
2 Pemadatan Tanah 35.15 m3 20,865.00 733,312.94
Sub Jumlah 7,493,656.97

III PEKERJAAN PONDASI


PEKERJAAN PONDASI FOOTPLAT
1 Galian Tanah Foot Plat 9.00 m3 35,158.50 316,426.50
2 Urugan Pasir 0.30 m3 150,053.00 45,015.90
3 Lantai Kerja 0.30 m3 686,597.57 205,979.27
4 Beton Bertulang Foot Plat :
Footplat Type FP.1
a. Beton K - 225 1.20 m3 902,177.96 1,082,613.55
b. Tulangan 144.45 kg 13,427.67 1,939,600.08
c. Bekisting 4.80 m2 80,123.00 384,590.40
5 Urugan tanah kembali 5.40 m3 11,719.50 63,285.30

PEKERJAAN PONDASI PASANGAN BATU


1 Galian pondasi Batu belah 50.16 m3 35,158.50 1,763,550.36
2 Urugan pasir bawah pondasi batu belah 2.28 m3 150,053.00 342,120.84
3 Pasang batu kosong 9.12 m3 272,965.20 2,489,442.62
4 Pasang batu kali, 1 Pc : 6 Ps 20.95 m3 537,137.70 11,251,691.97
5 Urugan tanah kembali Pondasi batu belah 15.05 m3 11,719.50 176,355.04

PEKERJAAN PONDASI GENSET


1 Galian Tanah 17.68 m3 35,158.50 621,602.28
2 Urugan Pasir 1.04 m3 150,053.00 156,055.12
3 Pasang batu kosong 3.12 m3 272,965.20 851,651.42
4 Pasang batu kali, 1 Pc : 6 Ps 6.24 m3 537,137.70 3,351,739.25
5 Beton Bertulang Foot Plat :
a. Beton K - 225 3.12 m3 902,177.96 2,814,795.22
b. Tulangan 99.56 kg 13,427.67 1,336,894.63
c. Bekisting 4.32 m2 80,123.00 346,131.36
Sub Jumlah 29,539,541.11

IV PEKERJAAN STRUKTUR
Beton Bertulang Sloof
1 Sloof Type SP 15 x 20
a. Beton K - 175 1.71 m3 838,939.62 1,434,586.75
b. Tulangan 229.47 kg 13,427.67 3,081,255.49
c. Bekisting 22.80 m2 87,456.33 1,994,004.21
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
01 02 03 05 06
Beton Bertulang Kolom
1 Kolom Type K1 25 x 25
a. Beton K - 225 3.51 m3 902,177.96 3,166,644.62
b. Tulangan 430.75 kg 13,427.67 5,783,931.26
c. Bekisting 46.80 m2 146,605.28 6,861,126.87
2 Kolom Type KP 15 x 15
a. Beton K - 175 1.80 m3 838,939.62 1,510,091.32
b. Tulangan 290.62 kg 13,427.67 3,902,403.17
c. Bekisting 48.00 m2 146,605.28 7,037,053.20

Beton Bertulang Balok & Plat


ELV +2.70; +2.80
1 Balok Type BP 15 x 20
a. Beton K - 175 0.39 m3 838,939.62 323,411.22
b. Tulangan 58.46 kg 13,427.67 785,047.79
c. Bekisting 7.07 m2 151,005.27 1,067,229.75

2 Plat Type Parapet


a. Beton K - 225 0.38 m3 902,177.96 340,662.40
b. Tulangan 35.38 kg 13,427.67 475,083.34
c. Bekisting 12.28 m2 169,605.28 2,083,081.28

ELV +3.20; +4.50


1 Balok Type B1 20 x 50
a. Beton K - 225 0.68 m3 902,177.96 608,970.12
b. Tulangan 105.29 kg 13,427.67 1,413,839.39
c. Bekisting 8.10 m2 151,005.27 1,223,142.69
2 Balok Type B2 20 x 30
a. Beton K - 225 1.37 m3 902,177.96 1,239,592.51
b. Tulangan 235.37 kg 13,427.67 3,160,468.86
c. Bekisting 18.32 m2 151,005.27 2,766,416.55
3 Balok Type B3 15 x 30
a. Beton K - 225 0.81 m3 902,177.96 730,764.14
b. Tulangan 153.18 kg 13,427.67 2,056,802.15
c. Bekisting 13.50 m2 151,005.27 2,038,571.15
4 Balok Type BP 15 x 20
a. Beton K - 175 0.52 m3 838,939.62 436,982.68
b. Tulangan 79.00 kg 13,427.67 1,060,730.91
c. Bekisting 9.55 m2 151,005.27 1,442,005.95

5 Plat Type S1
a. Beton K - 225 3.75 m3 902,177.96 3,384,069.51
b. Tulangan 400.97 kg 13,427.67 5,384,051.16
c. Bekisting 52.51 m2 169,605.28 8,906,651.41

ELV +5.50
1 Balok Type BP 15 x 20
a. Beton K - 175 0.99 m3 838,939.62 830,550.23
b. Tulangan 150.14 kg 13,427.67 2,016,076.03
c. Bekisting 18.15 m2 151,005.27 2,740,745.65

2 Plat Type S1
a. Beton K - 225 1.64 m3 902,177.96 1,479,571.85
b. Tulangan 175.31 kg 13,427.67 2,353,997.31
c. Bekisting 22.96 m2 169,605.28 3,894,137.11
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
01 02 03 05 06

Pekerjaan Waterproofing
1 Pekerjaan Waterproofing Plat 53.91 m2 100,000.00 5,391,000.00
Sub Jumlah 94,404,750.00

V PEKERJAAN ATAP
1 Pekerjaaan Rangka Atap Baja Konvensional (termasuk kuda-kuda, g 319.92 kg 21,692.90 6,939,983.89
track stang ,ikatan angin, plendes dan mur baut)
2 Pasang Penutup Asbes Gelombang 35.84 m2 37,649.50 1,349,358.08
3 Pekerjaan Talang Galvalume 11.20 m' 196,923.50 2,205,543.20
Pekerjaan Listplank :
a. Rangka Listplank, baja konvensional 75.92 kg 21,692.90 1,646,968.35
b. Kalsiboard penutup 23.34 m2 140,086.45 3,269,617.63
c. Pengecatan 23.34 m2 33,247.90 776,005.99
Sub Jumlah 16,187,477.14

VI PEKERJAAN DINDING, KUSEN PINTU DAN JENDELA


Pekerjaan Dinding
1 Pasangan bata merah, 1 PC : 6 PS 164.53 m2 93,554.44 15,392,669.18
2 Pasangan bata merah, 1 PC : 3 PS 41.13 m2 101,186.24 4,162,085.52
3 Plesteran 1 PC : 6 PS 329.06 m2 30,574.23 10,060,859.51
4 Plesteran 1 PC : 3 PS 82.27 m2 34,974.15 2,877,177.99
5 Acian 411.33 m2 18,109.50 7,448,966.15
6 Balok latiu 15 x 15
a. Beton K - 175 0.48 m3 838,939.62 399,419.15
b. Tulangan 72.21 kg 13,427.67 969,549.29
c. Bekisting 8.73 m2 151,005.27 1,318,049.50
7 Sponengan 86.21 m' 27,638.30 2,382,559.65
8 Pekerjaan Ducting :
a. Pasangan bata 1:6 14.20 m2 93,554.44 1,328,473.05
b. Plesteran 1 : 6 14.20 m2 30,574.23 434,154.09
c. Acian 14.20 m2 18,109.50 257,154.90
d. Plat Penutup :
- Beton 0.43 m3 838,939.62 357,388.28
- Tulangan 45.54 kg 13,427.67 611,465.15
- Bekisting 7.10 m2 169,605.28 1,204,197.45

Pekerjaan Kusen
Pekerjaan Kusen Almunium , Daun Pintu, Daun Jendela ,
lengkap dengan asesories, sesuai gambar dan spesifikasi
1 Kusen Type P1 1.00 unit 5,576,940.51 5,576,940.51
2 Kusen Type P2 2.00 unit 4,757,709.26 9,515,418.52
3 Kusen Type LV 2.00 unit 1,328,250.00 2,656,500.00
4 Kusen Type LV1 2.00 unit 3,093,300.00 6,186,600.00
Sub Jumlah 73,139,627.90

VII PEKERJAAN PLAFOND


1 Plafon Plat Ekspose 40.95 m2 32,923.80 1,348,229.61
Sub Jumlah 1,348,229.61

VIII PEKERJAAN KERAMIK LANTAI DAN DINDING


1 Urugan pasir bawah lantai 3.66 m3 150,053.00 549,344.03
2 Rabat lantai 8.79 m3 686,597.57 6,032,720.92
3 Finishing Lantai Acian 73.22 m2 18,109.50 1,325,977.59
Sub Jumlah 7,908,042.55
Sub Jumlah Pekerjaan Struktur & Arsitektur 234,660,466.24

IX PEKERJAAN MEKANIKAL ELEKTRIKAL


NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
01 02 03 05 06
A PEKERJAAN PENERANGAN
Panel Penerangan 1
1 Instalasi listrik dan stop kontak, NYM 3 x 2.5 mm2 + Pipa Conduit 14.00 Titik 200,000.00 2,800,000.00
2 Lampu Ess 14W 7.00 Unit 69,000.00 483,000.00
3 Exhaust Fan 200 W termasuk Ducting 2.00 Unit 1,000,000.00 2,000,000.00
4 Exhaust Fan 500 W termasuk Ducting 2.00 Unit 1,500,000.00 3,000,000.00
5 Stop Kontak 200 W 3.00 Unit 50,000.00 150,000.00
6 Saklar Ganda 3.00 Unit 50,000.00 150,000.00
6 Saklar Tunggal 1.00 Unit 45,000.00 45,000.00

MCB Box Penerangan


1 MCB Box 1.00 unit 350,000.00 350,000.00
2 MCB 6A / 5KA 2.00 bh 73,000.00 146,000.00
3 MCB 10A / 5KA 3.00 bh 173,000.00 519,000.00
4 MCB 25A / 5KA 1.00 bh 215,000.00 215,000.00
5 NYM 3 X 4 mm2 dari SDP 120.00 m 34,720.00 4,166,400.00
Sub Jumlah 14,024,400.00

B PEKERJAAN PLUMBING
Pekerjaan Air Hujan
1 Roof Drain 3.00 buah 150,000.00 450,000.00
2 Pipa PVC Type AW 3" 16.50 m' 42,257.18 697,243.47
3 Fitting dan Accessories 1.00 Ls 167,890.29 167,890.29
Sub jumlah 1,315,133.76
Sub Jumlah Pekerjaan Mekanikal Elektrikal & Plumbing 15,339,533.76
JUMLAH TOTAL 250,000,000.00
PRA - RENCANA KESELAMATAN DAN KESEHATAN
KERJA KONTRAK

PRA - RK3K

1. KEBIJAKAN K3
Saya yang bertanda tangan dibawah ini :
Nama :
Jabatan :
Alamat :

Dengan ini menyatakan bahwa dalam melaksanakan kegiatan konstruksi bila dipercayai menjadi pelaksana pekerjaan ini akan mnerapkan sistem keselamatan
dan kesehatan kerja (K3) bagi semua karyawan maupun pekerja dalam melaksanakan pekerjaan baik dilapangan maupun dikantor.
Demikian Pernyataan ini saya perbuat dengan sesunguh - sungguhnya dan akan dilaksanakan di lapangan.

2. PERENCANAAN
1) Identifikasi Bahaya dan Pengendalian Resiko Bahaya

Identifikasi
No. Jenis/Type Pekerjaan Pengendalain Resiko K3
Jenis Bahaya dan Resiko K3
1. 2. 3. 4.
A Pekerjaan Persiapan
Pembersihan Lapangan Jenis Bahaya dan Resiko Pengendalian Resiko K3
Pengukuran dan Pemasangan Bowplank a) Tertimpa Kayu -> Luka Berat a) Memakai Alat Pelindung Diri (APD)
Papan Nama Proyek b) Tergelincir -> Luka Ringan b) Melakukan pekerjaan dengan hati - hati
Direksi Keet / Gudang Material c) Terkena Peralatan Kerja -> Luka Berat c) Menggunakan Peralatan dengan baik
### d) Terkena Benda Tajam -> Luka Berat

B Pekerjaan Tanah Jenis Bahaya dan Resiko Pengendalian Resiko K3


Timbunan Tanah Pematangan Lahan a) Tertimbun longsoran -> Luka Berat a) Membuat pagar pengaman
Lantai Kerja Beton Cor K-150 b) Terjatuh ke lubang -> Luka Berat b) Menggunakan Peralatan dengan baik
Pas. Batu/Talud Pengaman Landscape c) Terkena Peralatan Kerja -> Luka Berat c) Memakai Alat Pelindung Diri (APD)

C Pekerjaan Rigid Beton Jenis Bahaya dan Resiko Pengendalian Resiko K3


a. Rigid Beton Zona A a) Tertimbun longsoran -> Luka Berat a) Membuat pagar pengaman
Lapisan Aggregat A b) Tergelincir -> Luka Ringan b) Melakukan pekerjaan dengan hati - hati
Pembesian Wiremesh Ø 8 c) Terkena Peralatan Kerja -> Luka Berat c) Menggunakan Peralatan dengan baik
Plastik Alas Cor Rigid d) Terkena Benda Tajam -> Luka Berat d) Melakukan pekerjaan dengan hati - hati
Beton K-250 (Ready Mix)
Bekisting Untuk Beton

b. Rigid Beton Zona B


Urugan Pasir
Beton K-250 (Ready Mix)
Bekisting Untuk Rigid Beton

D Pekerjaan Taman Dan Landscape Jenis Bahaya dan Resiko Pengendalian Resiko K3
Galian Tanah Bawah Beton Kerb a) Tertimbun longsoran -> Luka Berat a) Membuat pagar pengaman
Urugan Pasir Bawah Beton Kerb b) Tergelincir -> Luka Ringan b) Melakukan pekerjaan dengan hati - hati
Beton Kerb (K-150) c) Terkena Peralatan Kerja -> Luka Berat c) Menggunakan Peralatan dengan baik
Tanah Humus Timbunan Taman + Pupuk NPK d) Terkena Benda Tajam -> Luka Berat d) Melakukan pekerjaan dengan hati - hati
Penanaman Pohon Tanjung (T=1m) + Tertanam
Penanaman Pohon Cemara Laut (T=1m) + Tertanam
Penanaman Pohon Ketapang (T=1m) + Tertanam
Penanaman Pohon Palem Putri (T=1m) + Tertanam
Penanaman Bunga Asoka + Tertanam
Rumput Taman + Tertanam
Galian Tanah Sloof (Bangku Taman)
Timbunan Tanah (Bangku Taman)
Sloof 13/13 (Bangku duduk taman)
Balok 13/13 (Bangku duduk taman)
Pasangan Dinding Bata 1Pc : 2 Ps (Bangku dan dinding taman)
Plasteran Dinding Bata 1PC : 2Ps (Bangku dan dinding taman)

E Pekerjaan Pedestrian
Galian Tanah Bawah Beton Kansteen Jenis Bahaya dan Resiko Pengendalian Resiko K3
Urugan Pasir Bawah Beton Kansteen a) Tertimpa Material -> Luka Berat a) Memakai Alat Pelindung Diri (APD)
Kansteen Pedestrian (bagian Luar Pedestrian Samping Jalan) b) Tergelincir -> Luka Ringan b) Melakukan pekerjaan dengan hati - hati
Timbunan Tanah Bawah Pedestrian c) Terkena Peralatan Kerja -> Luka Berat c) Menggunakan Peralatan dengan baik
Pemasangan Paving Block (pedestrian) d) Terkena Benda Tajam -> Luka Berat d) Melakukan pekerjaan dengan hati - hati

Jenis Bahaya dan Resiko Pengendalian Resiko K3


2.
F Pekerjaan Drainase a) Tertimpa Material -> Luka Berat a) Memakai Alat Pelindung Diri (APD)
Galian Tanah Drainase b) Tergelincir -> Luka Ringan b) Melakukan pekerjaan dengan hati - hati
G
Urugan Pasir Bawah Saluran Drainase
al c) Terkena Peralatan Kerja -> Luka Berat c) Menggunakan Peralatan dengan baik
ia
Beton Cor K-150 (Lantai Drainase Landscape) d) Terkena Benda Tajam -> Luka Berat d) Melakukan pekerjaan dengan hati - hati
n
Beton Cor K-150 (Dinding Drainase Landscape)
T
Beton
a Cor K-150 (Penutup Drainase Landscape)
Box Culvert (Pintu Masuk dan Keluar dari Parkir Truck)
n
a
h
B
ia
s
a
2) Pemenuhan Perundang-Undangan dan Persyaratan Lainnya
(
Daftar
M Peraturan Perundang-undangan dan Persyaratan K3 yang wajib dipunyai dan dipenuhi dalam melaksanakan paket pekerjaan ini adalah :
P UU No. 1 Tahun 1970 Tentang Keselamatan Kerja
a.
)b. UU No. 18 Tahun 199 Tentang Jasa Konstruksi
c. Peraturan Mentri PU No. 09/PRT/M/2008 tentang Pedoman Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) Konstruksi Bidang PU
d. dst

3) Sasaran K3 dan Program K3


Sasaran K3
(Sasaran dan Program K3 yang akan dilaksanakan, harus disusun berdasarkan hasil identifikasi bahaya dan penetapan pengendalian Risiko. Sasaran harus
terukur secara kualitatif maupun kuantitatif)
a. Tidak ada kecelakaan kerja yang berdampak korban jiwa ( Zero Fatal Accident)
b. Tingkat penerapan elemen SMK3 minila 80%
c. Semua pekerja wajib memakai APD yang sesuai bahaya dan resiko pekerjaan masing-masing.
d. dst

Program K3
a. Melaksanakan Rencana K3 dengan menyediakan sumber daya K3 (APD,rambu-rambu,spanduk,poster,pagar pengaman) secara konsiten.
b. Melakukan inspeksi secara rutin terhadap kondisi dan cara kerja berbahaya
c. Memastikan semua pekerja untuk mematuhi peraturan yang telah ditetapkan dalam pelaksanaan proyek.
d. dst

Organisasi K3
Menyediakan petugas K3 sesuai dengan struktur organisasi yang diusulkan.

Note :
Kelengkapan Alat Pelindung Diri (APD) Sebagai Berikut :
1 Sabuk Pengaman (Safety Belt) dan Tali Pengaman untuk mencegah cedera yang lebih parah pada pekerja yang bekerja di ketinggian (tinggi > 2m).
2 Sarung Tangan (Bahan Kulit) digunakan untuk pekerjaan pengelasan, pemindahan pipa dll.
3 Sarung Tangan (Bahan Karet) untuk pekerjaan listrik yang dijaga agar tidak ada yang dirobek supaya tidak terjadi bahaya kena arus listrik.
4 Sarung Tangan (Bahan Katun) digunakan pada pekerja besi beton, pekerjaan bobokan dan batu, pelindung pada waktu harus menaiki tangga untuk
5 pekerjaan ketinggian. (Safety Booth) untuk menghindari kecelakaan yang diakibatkan tersandung bahan keras seperti logam atau kayu, terinjak atau
Sepatu Keselamatan
6 terhimpit
Helm/Topibeban berat atau
Keselamatan mencegah
(Safety lukauntuk
Helmet) bakarbekerja
pada waktu mengelas.
di tempat Sepatu
beresiko boot
karena karetjatuh
benda bila bekerja pada pekerjaan
atau melayang, tanah dan
dan dilengkapi pengecoran
dengan beton. untuk
ikatan kedagu
7 menghalangi terlepasnya
Pelindung Pernapasan helmet dari kepala
(Masker)adalah akibat menunduk
alat perlindungan untukatau karena benda
melindungi jatuh. dari gas beracun dan berdebu.
pernafasan
8 Masker pelindung pengelasan yang dilengkapi kaca pengaman (shade of lens) yang disesuaikan dengan diameter las (welding rod). Untuk welding rod
1/16” sampai
9 Kaca 5/32 gunakan
Mata Pelindung shade No.
(Protective 10. untuk welding
Goggles)untuk rod 3/16”
melindungi sampai
meta dari 1/4 “ gunakan
percikan logamshade
cair,No. 13
percikan bahan kimia, seta kacamata pelindung untuk
10 pekerjaan
Pelindung menggerinda
pendengaran dan pekejaan
untuk mencegahberdebu.
rusaknya pendengaran akibat suara bising di atas ambang aman seperti pekerjaan plat logam.

Kelengkapan Kotak P3K


1 Obat merah, perban, plester dan obat-obat generic

Anda mungkin juga menyukai