Anda di halaman 1dari 57

REKAPITULASI

RENCANA ANGGARAN BIAYA


PEKERJAAN : PEMBANGUNAN SPA
LOKASI : CASANEMO
TAHUN : 2015

NO URAIAN JUMLAH HARGA


I PEKERJAAN PERSIAPAN 6,504,000.00

II LANTAI I
A PEKERJAAN TANAH DAN PONDASI 32,773,939.51
B PEKERJAAN BETON BERTULANG 172,598,273.10
C PEKERJAAN PASANGAN 44,003,467.30
D PEKERJAAN PLAFOND 16,785,077.64
E PEKERJAAN LANTAI 38,270,946.10
F PEKERJAAN PENGECATAN 9,266,352.41
G PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA 10,770,000.00
H PEKERJAAN MEKANIKAL ELEKTRIKAL 4,610,000.00
I PEKERJAAN INSTALASI AIR BERSIH 8,467,650.00
J PEKERJAAN INSTALASI AIR KOTOR 15,656,180.00
K PEKERJAAN TANGGA LT 1 4,405,070.90

III LANTAI II
A PEKERJAAN BETON BERTULANG 36,555,028.50
B PEKERJAAN PASANGAN 37,569,923.85
C PEKERJAAN PLAFOND 21,590,000.00
D PEKERJAAN LANTAI 13,853,137.51
E PEKERJAAN PENGECATAN 4,890,498.60
F PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA 13,010,000.00
G PEKERJAAN MEKANIKAL ELEKTRIKAL 4,220,000.00
H PEKERJAAN INSTALASI AIR BERSIH 7,357,100.00
I PEKERJAAN INSTALASI AIR KOTOR 11,206,180.00
J PEKERJAAN ATAP 16,874,014.84

JUMLAH 531,236,840.26
PPN 10% 53,123,684.03
JUMLAH TOTAL 584,360,524.29
DIBULATKAN 584,360,000.00

Terbilang : Lima Ratus Delapan Puluh Empat Juta Tiga Ratus Enam Puluh Ribu Rupiah
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN SPA
LOKASI : CASANEMO
TAHUN : 2015

NO URAIAN PEKERJAAN VOLUME SAT ANALISA HARGA SATUAN JUMLAH HARGA


(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 143.00 M2 Taksir 4,000.00 572,000.00
2 Pemasangan Bouwplank 48.00 M' Taksir 9,000.00 432,000.00
3 Direksi Keet/Barak Kerja (Sewa) 1.00 LS Taksir 2,500,000.00 2,500,000.00
4 Pengadaan Air Kerja 1.00 LS Taksir 1,000,000.00 1,000,000.00
5 Pengadaan Listrik Kerja 1.00 LS Taksir 1,000,000.00 1,000,000.00
6 Dokumentasi Dan Administrasi 1.00 LS Taksir 1,000,000.00 1,000,000.00
Sub Jumlah 6,504,000.00
II LANTAI I
A PEKERJAAN TANAH DAN PONDASI
Pondasi Tapak
1 Galian Tanah Pondasi Tapak 16.20 M3 SNI.2835.2008-6.1 51,000.00 826,200.00
2 Urugan Pasir Alas Pondasi Tapak tebal 5 cm 0.60 M3 SNI.2835.2008-6.11 140,400.00 84,240.00
3 Pasangan Batu Kosong 1.20 M3 SNI.2836.2008.69 289,875.00 347,850.00
4 Urugan Tanah Kembali 4.05 M3 SNI.2835.2008-6.9 17,000.00 68,850.00
Pondasi Menerus Batu Gunung
1 Galian Tanah Pondasi Batu Gunung 54.00 M3 SNI.2835.2008-6.1 51,000.00 2,753,836.80
2 Urugan pasir Alas Pondasi Menerus 3.76 M3 SNI.2835.2008-6.11 140,400.00 527,735.52
3 Pas. Aanstamping tebal 10 cm 7.52 M3 SNI.2836.2008.69 289,875.00 2,179,164.30
4 Pas. Pondasi Batu Gunung 1pc : 4ps 41.35 M3 SNI.2836.2008.6.2 607,275.00 25,108,877.97
5 Angchor stik dia 10-100 mm 46.38 Kg SNI.7394.2008-6.17a 13,401.00 621,586.52
6 Urugan Tanah Kembali 15.04 M3 SNI.2835.2008-6.9 17,000.00 255,598.40
Sub Jumlah 32,773,939.51
B PEKERJAAN BETON BERTULANG
1 Pondasi Tapak TP1 (100 X 100 cm)
-Beton Cor K-250 2.40 M3 SNI.7394.2008-6.7 804,566.27 1,930,959.05
-Besi Beton Polos (Ø14-170 mm) ; (Ø14-210 mm) 316.28 Kg SNI.7394.2008-6.20 13,401.00 4,238,419.55
-Bekisting 3.20 M2 SNI.7394.2008-6.20 189,360.00 605,952.00
-Pekerjaan Lain-lain 2.40 Ls Taksir 5,000.00 12,000.00

2 Sloof Beton Type S.1 cm


-Beton Cor K-250 5.64 M3 SNI.7394.2008-6.7 804,566.27 4,536,305.54
-Besi Beton Polos (7Ø14 mm) 794.61 Kg SNI.7394.2008-6.17a 13,401.00 10,648,572.90
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 104.31 Kg SNI.7394.2008-6.17a 13,401.00 1,397,814.09
-Bekisting 37.59 M2 SNI.7394.2008-6.21 206,860.00 7,775,453.68
-Pekerjaan Lain-lain 5.64 Ls Taksir 5,000.00 28,191.00

3 Kolom Beton Tipe K1 Uk. 30 x 30 cm


-Beton Cor K-250 4.32 M3 SNI.7394.2008-6.7 804,566.27 3,475,726.29
-Besi Beton Polos (7Ø14 mm) 463.87 Kg SNI.7394.2008-6.17a 13,401.00 6,216,348.67
-Besi Beton Polos (ø6-100 mm) 127.87 Kg SNI.7394.2008-6.17a 13,401.00 1,713,612.67
-Bekisting 19.20 M2 SNI.7394.2008-6.22 346,175.00 6,646,560.00
-Pekerjaan Lain-lain 4.32 Ls Taksir 5,000.00 21,600.00

4 Kolom Beton Tipe K2 Uk. 13 x 13 cm


-Beton Cor K-250 0.46 M3 SNI.7394.2008-6.7 804,566.27 367,123.59
-Besi Beton Polos (4Ø14mm) 130.46 Kg SNI.7394.2008-6.17a 13,401.00 1,748,348.06
-Besi Beton Polos (ø6-100 mm) 31.17 Kg SNI.7394.2008-6.17a 13,401.00 417,693.09
-Bekisting 4.68 M2 SNI.7394.2008-6.22 346,175.00 1,620,099.00
-Pekerjaan Lain-lain 0.46 Ls Taksir 5,000.00 2,281.50

6 Balok Tipe B.1 Uk. 20 x 30 cm


-Beton Cor K-250 3.55 M3 SNI.7394.2008-6.7 804,566.27 2,853,860.92
-Besi Beton Polos (7Ø14 mm) 833.17 Kg SNI.7394.2008-6.17a 13,401.00 11,165,306.88
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 110.83 Kg SNI.7394.2008-6.17a 13,401.00 1,485,186.52
-Bekisting 19.05 M2 SNI.7394.2008-6.23 355,175.00 6,765,775.93
-Pekerjaan Lain-lain 3.55 Ls Taksir 5,000.00 17,735.40

5 Plat Lantai Tebal 12 cm


-Beton Cor K-250 13.95 M3 SNI.7394.2008-6.7 804,566.27 11,221,276.11
-Besi Beton Polos (ø10-100 mm) 2,866.11 Kg SNI.7394.2008-6.17a 13,401.00 38,408,686.96
-Bekisting 116.22 M2 SNI.7394.2008-6.24 406,175.00 47,207,648.76
-Pekerjaan Lain-lain 13.95 Ls Taksir 5,000.00 69,734.94

Sub Jumlah 172,598,273.10


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
C PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 1:4 180.83 M2 SNI.6897.2008-6.9 106,525.00 19,262,873.14
2 Pasangan Pagar Kayu 1.00 ls Taksir 2,500,000.00 2,500,000.00
3 Plesteran Dinding Bata 1:4 361.66 M2 SNI..2837.2008.6.15 61,496.00 22,240,594.16
Sub Jumlah 44,003,467.30
D PEKERJAAN PLAFOND
1 Rangka Plafond 108.33 M2 Taksir 90,000.00 9,749,907.00
2 Pasangan Plafond Gypsum 9 mm 108.33 M2 SNI.2839.2008-6.7 48,091.00 5,209,808.64
3 Pemasangan List Plafond 75.60 M' SNI.2839.2008-6.8 24,145.00 1,825,362.00
Sub Jumlah 16,785,077.64
E PEKERJAAN LANTAI
1 Tanah Timbun 41.55 M3 SNI.2835.2008-6.9 97,000.00 4,030,419.84
2 Urugan pasir Alas lantai T = 10 cm 13.85 M3 SNI.2835.2008-6.11 140,400.00 1,944,573.70
3 Beton Cor Alas lantai T = 8 cm 11.08 M3 SNI.7394,2008-6.4 589,728.00 6,534,299.47
4 Pas. Lantai keramik 40 x 40 cm 134.75 M2 SNI.7395.2008.6.9a 161,869.00 21,812,398.10
5 Pas. keramik 20 x 20 cm (Toilet) 3.75 M2 SNI.7395.2008.6.9c 195,369.00 732,438.38
6 Pas. keramik 20 x 25 cm (Dinding KM/WC) 14.15 M2 SNI.7395.2008.6.9d 227,369.00 3,216,816.61
Sub Jumlah 38,270,946.10
F PEKERJAAN PENGECATAN
1 Pengecatan Dinding 361.66 M2 Anl.SNI.6.14-2002 19,716.00 7,130,472.79
2 Pengecatan Plafond 108.33 M2 Anl.SNI.6.14-2002 19,716.00 2,135,879.63
Sub Jumlah 9,266,352.41
G PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA
1 Pintu Tipe PJ1
Pintu & Jendela Blockboard + Frame Alumunium + Accessories 1.00 Unit Taksir 2,300,000.00 2,300,000.00

2 Pintu Tipe P2
Pintu Blockboard + Frame Alumunium + Accessories 5.00 Unit Taksir 1,050,000.00 5,250,000.00

3 Pintu Tipe P3
Pintu Kayu + Kusen Kayu + Accessories 1.00 Unit Taksir 850,000.00 850,000.00

4 Jendela Tipe J1
Jendela + Frame Alumunium + Accessories 1.00 Unit Taksir 600,000.00 600,000.00

5 Jendela Tipe J2
Jendela + Frame Alumunium + Accessories 1.00 Unit Taksir 360,000.00 360,000.00

6 Jendela Tipe J3
Jendela + Frame Alumunium + Accessories 1.00 Unit Taksir 690,000.00 690,000.00

6 Jendela Tipe J4
Jendela + Frame Alumunium + Accessories 2.00 Unit Taksir 360,000.00 720,000.00

Sub Jumlah 10,770,000.00


H PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Panel Kontrol
a Panel MCB 1.00 Unit Taksir 250,000.00 250,000.00

2 Titik Instalasi
a Instalasi Titik Panel SDP 3.00 Titik Taksir 30,000.00 90,000.00
b Instalasi Titik Penerangan (Termasuk Pembobokan dan Perapian) 33.00 Titik Taksir 20,000.00 660,000.00
c Instalasi Titik Stop Kontak (Termasuk Pembobokan dan Perapian) 25.00 Titik Taksir 20,000.00 500,000.00

3 Kabel + Accessories
a Kabel GL 2,5 mm NYA 40.00 M' Taksir 10,000.00 400,000.00
b Isolasi 3.00 Bh Taksir 5,000.00 15,000.00

5 Lampu Penerangan
a Lampu Dinding 18 watt + Accessories 28.00 Unit Taksir 65,000.00 1,820,000.00
b Lampu HE 18 watt + Accessories 5.00 Unit Taksir 35,000.00 175,000.00
c Saklar Double + Kelengkapan 10.00 Unit Taksir 20,000.00 200,000.00
d Stop Kontak Setara Panasonic 25.00 Unit Taksir 20,000.00 500,000.00

Sub Jumlah 4,610,000.00


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
I PEKERJAAN INSTALASI AIR BERSIH
1 Pipa Air Bersih PVC Ø 3/4" 50.00 M1 SNI T-15-2002-B.26 13,925.00 696,250.00
2 Instalasi Air Bersih (termasuk galian, pembobokan, 50.00 M1 Taksir 35,000.00 1,750,000.00
penyambungan koneksi)
3 Kran Air Stainless Ø 1/2" 2.00 Bh SNI T-15-2002-B.35 45,700.00 91,400.00
4 Floor drain 2.00 Bh Taksir 40,000.00 80,000.00
5 Wastafel 7.00 Bh Taksir 550,000.00 3,850,000.00
6 Water Heater 1.00 Bh Taksir 2,000,000.00 2,000,000.00
Sub Jumlah 8,467,650.00
J PEKERJAAN INSTALASI AIR KOTOR
1 Pipa Air Kotor PVC Ø 2" 50.00 M1 SNI T-15-2002-6.29 38,618.00 1,930,900.00
2 Pipa Kotoran PVC Ø 4" 40.00 M1 SNI T-15-2002-B.32 84,382.00 3,375,280.00
3 Instalasi Air Kotor (termasuk galian, pembobokan, 50.00 M1 Taksir 25,000.00 1,250,000.00
penyambungan koneksi)
4 Kloset Duduk 2.00 Bh Taksir 1,550,000.00 3,100,000.00
5 Septictank dan resapan 2.00 ls Taksir 3,000,000.00 6,000,000.00
Sub Jumlah 15,656,180.00
K PEKERJAAN TANGGA LT 1
1 Plat Beton Bordes
-Beton Cor K-250 0.10 M3 SNI.7394.2008-6.7 804,566.27 77,238.36
-Besi Beton Polos (ø10-200 mm) 2.47 Kg SNI.7394.2008-6.17a 13,401.00 33,073.67
-Bekisting 0.55 M2 SNI.3435.2002-6.34 310,875.00 172,432.00
-Pekerjaan Lain-lain 0.10 Ls Taksir 5,000.00 480.00

2 Plat Lantai Tangga


-Beton Cor K-250 0.55 M3 SNI.7394.2008-6.7 804,566.27 444,120.58
-Besi Beton Polos (ø10-200 mm) 12.90 Kg SNI.7394.2008-6.17a 13,401.00 172,885.08
-Bekisting 2.43 M2 SNI.3435.2002-6.34 310,875.00 755,219.00
-Pekerjaan Lain-lain 0.55 Ls Taksir 5,000.00 2,760.00

3 Tangga Beton
-Beton Cor K-250 0.45 M3 SNI.7394.2008-6.7 804,566.27 362,054.82
-Besi Beton Polos (ø10-200 mm) 20.94 Kg SNI.7394.2008-6.17a 13,401.00 280,602.39
-Bekisting 2.50 M2 SNI.7394.2008-6.23 355,175.00 887,937.50
-Pekerjaan Lain-lain 0.45 Ls Taksir 5,000.00 2,250.00

4 Pasangan Keramik Tangga 7.50 M2 SNI.7395.2008.6.9a 161,869.00 1,214,017.50

Sub Jumlah 4,405,070.90


II LANTAI II
A PEKERJAAN BETON BERTULANG
1 Kolom Beton Tipe K1 Uk. 30 x 30 cm
-Beton Cor K-250 2.70 M3 SNI.7394.2008-6.7 804,566.27 2,172,328.93
-Besi Beton Polos (8Ø14 mm) 289.92 Kg SNI.7394.2008-6.17a 13,401.00 3,885,217.92
-Besi Beton Polos (ø6-100 mm) 79.92 Kg SNI.7394.2008-6.17a 13,401.00 1,071,007.92
-Bekisting 12.00 M2 SNI.7394.2008-6.22 346,175.00 4,154,100.00
-Pekerjaan Lain-lain 2.70 Ls Taksir 5,000.00 13,500.00

2 Kolom Beton Tipe K2 Uk. 13 x 13 cm


-Beton Cor K-250 0.91 M3 SNI.7394.2008-6.7 804,566.27 734,247.18
-Besi Beton Polos (4Ø14mm) 133.27 Kg SNI.7394.2008-6.17a 13,401.00 1,785,978.07
-Besi Beton Polos (ø6-100 mm) 31.17 Kg SNI.7394.2008-6.17a 13,401.00 417,693.09
-Bekisting 9.36 M2 SNI.7394.2008-6.22 346,175.00 3,240,198.00
-Pekerjaan Lain-lain 0.91 Ls Taksir 5,000.00 4,563.00

3 Ring Balk Tipe B.1 Uk. 20 x 30 cm


-Beton Cor K-250 0.42 M3 SNI.7394.2008-6.7 804,566.27 334,249.01
-Besi Beton Polos (7Ø14mm) 97.58 Kg SNI.7394.2008-6.17a 16,026.00 1,563,852.98
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 9.74 Kg SNI.7394.2008-6.17a 13,401.00 130,460.66
-Bekisting 1.38 M2 SNI.7394.2008-6.23 355,175.00 491,846.34
-Pekerjaan Lain-lain 0.42 Ls Taksir 5,000.00 2,077.20

4 Ring Balk Tipe B.1 Uk. 15 x 20 cm


-Beton Cor K-250 0.59 M3 SNI.7394.2008-6.7 804,566.27 472,891.87
-Besi Beton Polos (6Ø14mm) 355.01 Kg SNI.7394.2008-6.17a 16,026.00 5,689,342.82
-Besi Beton Polos Tumpuan Ø8-100 ; Lapangan Ø8-150 44.50 Kg SNI.7394.2008-6.17a 13,401.00 596,322.12
-Bekisting 2.61 M2 SNI.7394.2008-6.23 355,175.00 927,811.81
-Pekerjaan Lain-lain 0.59 Ls Taksir 5,000.00 2,938.80
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
5 Plat Lantai Tebal 2x12 cm Bawah Bak Air
-Beton Cor K-250 2.00 Ls SNI.7394.2008-6.7 804,566.27 1,606,596.55
-Besi Beton Polos (ø10-200 mm) 95.51 Kg SNI.7394.2008-6.17a 13,401.00 1,279,904.80
-Bekisting 6.01 M2 SNI.7394.2008-6.24 406,175.00 2,440,461.87
-Pekerjaan Lain-lain 2.00 M3 Taksir 5,000.00 9,984.24

6 Kolom Beton Tipe K1 Uk. 30 x 30 cm T.1 m


-Beton Cor K-250 0.36 M3 SNI.2839.2008-6.7 804,566.27 289,643.86
-Besi Beton Polos (8Ø14 mm) 38.66 Kg SNI.7394.2008-6.17a 13,401.00 518,029.06
-Besi Beton Polos (ø6-100 mm) 5.33 Kg SNI.7394.2008-6.17a 406,175.00 2,164,100.40
-Bekisting 1.60 M2 SNI.7394.2008-6.22 346,175.00 553,880.00
-Pekerjaan Lain-lain 0.36 Ls Taksir 5,000.00 1,800.00

Sub Jumlah 36,555,028.50


B PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 1:4 118.25 M2 SNI.6897.2008-6.9 106,525.00 12,596,964.74
2 Pasangan Bata Pada Bak Air Bawah Atap 11.54 M2 SNI.6897.2008-6.9 106,525.00 1,229,298.50
3 Pasangan Dinding Kayu 33.96 M2 Taksir 250,000.00 8,489,750.00
4 Plesteran Dinding Bata 1:4 248.05 M2 SNI..2837.2008.6.15 61,496.00 15,253,910.61
Sub Jumlah 37,569,923.85
D PEKERJAAN PLAFOND
1 Plafond Papan Meranti + Rangka 107.95 M2 Taksir 200,000.00 21,590,000.00
Sub Jumlah 21,590,000.00
C PEKERJAAN LANTAI
1 Pas. Lantai keramik 40 x 40 cm 85.58 M2 SNI.7395.2008.6.9a 161,869.00 13,853,137.51
Sub Jumlah 13,853,137.51
D PEKERJAAN PENGECATAN
1 Pengecatan Dinding 248.05 M2 Anl.SNI.6.14-2002 19,716.00 4,890,498.60
Sub Jumlah 4,890,498.60
E PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA
1 Pintu Tipe P2
Pintu Blockboard + Frame Alumunium + Accessories 1.00 Unit Taksir 1,050,000.00 1,050,000.00

2 Pintu Tipe P3
Pintu Kayu + Kusen Kayu + Accessories 3.00 Unit Taksir 850,000.00 2,550,000.00

3 Jendela Tipe J5
Jendela + Frame Alumunium + Accessories 3.00 Unit Taksir 2,200,000.00 6,600,000.00

4 Jendela Tipe J6
Jendela + Frame Alumunium + Accessories 1.00 Unit Taksir 1,035,000.00 1,035,000.00

5 Jendela Tipe J7
Jendela + Frame Alumunium + Accessories 1.00 Unit Taksir 950,000.00 950,000.00

6 Ventilasi Tipe V1
Ventilasi + Frame Alumunium + Accessories 1.00 Unit Taksir 160,000.00 160,000.00

7 Ventilasi Tipe V2
Ventilasi + Frame Alumunium + Accessories 1.00 Unit Taksir 350,000.00 350,000.00

8 Ventilasi Tipe V3
Ventilasi + Frame Alumunium + Accessories 3.00 Unit Taksir 105,000.00 315,000.00

Sub Jumlah 13,010,000.00


F PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Panel Kontrol
a Panel MCB 1.00 Unit Taksir 250,000.00 250,000.00

2 Titik Instalasi
a Instalasi Titik Panel SDP 3.00 Titik Taksir 30,000.00 90,000.00
b Instalasi Titik Penerangan (Termasuk Pembobokan dan Perapian) 27.00 Titik Taksir 20,000.00 540,000.00
c Instalasi Titik Stop Kontak (Termasuk Pembobokan dan Perapian) 23.00 Titik Taksir 20,000.00 460,000.00

2 Kabel + Accessories
a Kabel GL 2,5 mm NYA 52.00 M' Taksir 10,000.00 520,000.00
b Isolasi 3.00 Bh Taksir 5,000.00 15,000.00

3 Lampu Penerangan
a Lampu Dinding 18 watt + Accessories 24.00 Unit Taksir 65,000.00 1,560,000.00
b Lampu HE 18 watt + Accessories 3.00 Unit Taksir 35,000.00 105,000.00
c Saklar Double + Kelengkapan 11.00 Unit Taksir 20,000.00 220,000.00
d Stop Kontak Setara Panasonic 23.00 Unit Taksir 20,000.00 460,000.00
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)

Sub Jumlah 4,220,000.00


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
G PEKERJAAN INSTALASI AIR BERSIH
1 Pipa Air Bersih PVC Ø 3/4" 50.00 M1 SNI T-15-2002-B.26 13,925.00 696,250.00
2 Instalasi Air Bersih (termasuk galian, pembobokan, 50.00 M1 Taksir 35,000.00 1,750,000.00
penyambungan koneksi)
3 Kran Air Stainless Ø 1/2" 3.00 M1 SNI T-15-2002-B.35 45,700.00 137,100.00
4 Floor drain 3.00 Bh Taksir 40,000.00 120,000.00
5 Wastafel 2.00 Bh Taksir 550,000.00 1,100,000.00
6 Water Heater 3.00 Bh Taksir 2,000,000.00 6,000,000.00
Sub Jumlah 7,357,100.00
H PEKERJAAN INSTALASI AIR KOTOR
1 Pipa Air Kotor PVC Ø 2" 50.00 M1 SNI T-15-2002-6.29 38,618.00 1,930,900.00
2 Pipa Kotoran PVC Ø 4" 40.00 M1 SNI T-15-2002-B.32 84,382.00 3,375,280.00
3 Instalasi Air Kotor (termasuk galian, pembobokan, 50.00 M1 Taksir 25,000.00 1,250,000.00
penyambungan koneksi)
4 Kloset Duduk 3.00 Bh Taksir 1,550,000.00 4,650,000.00
Sub Jumlah 11,206,180.00
I PEKERJAAN ATAP
1 Pengadaan dan pemasangan atap rumbia 168.74 M2 Taksir 45,000.00 7,593,306.68
2 Rangka atap kayu 168.74 M2 Taksir 55,000.00 9,280,708.16
Sub Jumlah 16,874,014.84
DAFTAR ANALISA HARGA SATUAN BAHAN DAN UPAH

PEKERJAAN : PEMBANGUNAN SPA


LOKASI : CASANEMO
TAHUN : 2015

ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA


(Rp)

PEKERJAAN PERSIAPAN
B. PEKERJAAN TANAH DAN PONDASI
SNI.2835.2008-6.1
1 M3 Galian Tanah Biasa
Pekerja 0.7500 OH @Rp 65,000.00 Rp 48,750.00
Mandor 0.0250 OH @Rp 90,000.00 Rp 2,250.00
Jumlah Rp 51,000.00
Dibulatkan Rp 51,000.00
SNI.2835.2008-6.2
1 M3 Galian Tanah Biasa Sedalam 2 Meter
Pekerja 0.9000 OH @Rp 65,000.00 Rp 58,500.00
Mandor 0.0450 OH @Rp 90,000.00 Rp 4,050.00
Jumlah Rp 62,550.00
Dibulatkan Rp 62,550.00
SNI.2835.2008-6.9
1 M3 Urugan Kembali
Pekerja 0.2500 OH @Rp 65,000.00 Rp 16,250.00
Mandor 0.0083 OH @Rp 90,000.00 Rp 750.00
Jumlah Rp 17,000.00
Dibulatkan Rp 17,000.00
SNI.2835.2008-6.11
1 M3 Urugan Pasir
Pasir Urug 1.2000 M3 @Rp 100,000.00 Rp 120,000.00
Pekerja 0.3000 OH @Rp 65,000.00 Rp 19,500.00
Mandor 0.0100 OH @Rp 90,000.00 Rp 900.00
Jumlah Rp 140,400.00
Dibulatkan Rp 140,400.00
SNI.2835.2008-6.9
1 M3 Urugan Tanah
Tanah Timbun 1.2000 M3 @Rp 50,000.00 Rp 60,000.00
Pekerja 0.5000 OH @Rp 65,000.00 Rp 32,500.00
Mandor 0.0500 OH @Rp 90,000.00 Rp 4,500.00
Jumlah Rp 97,000.00
Dibulatkan Rp 97,000.00
SNI.2835.2008-6.10
1 M3 Pemadatan Tanah (per 20 cm)
Pekerja 0.5000 OH @Rp 65,000.00 Rp 32,500.00
Mandor 0.0500 OH @Rp 90,000.00 Rp 4,500.00
Jumlah Rp 37,000.00
Dibulatkan Rp 37,000.00
SNI.2836.2008.69
1 M3 Pasangan Pondasi Batu Kosong/Aanstamping
Batu Kali/Batu Belah 1.2000 M3 @Rp 130,000.00 Rp 156,000.00
Pasir Urug 0.4320 M3 @Rp 100,000.00 Rp 43,200.00
Pekerja 0.7800 OH @Rp 65,000.00 Rp 50,700.00
Tukang (Kayu/Besi/Batu) 0.3900 OH @Rp 85,000.00 Rp 33,150.00
Kepala Tukang (Kayu/Besi/Batu) 0.0390 OH @Rp 85,000.00 Rp 3,315.00
Mandor 0.0390 OH @Rp 90,000.00 Rp 3,510.00
Jumlah Rp 289,875.00
Dibulatkan Rp 289,875.00
SNI.2836.2008.6.2
1 M3 Pasangan Batu Belah/Batu Kali/Batu Gunung 1 PC : 4 PS
Batu Kali/Batu Belah 1.2000 M3 @Rp 130,000.00 Rp 156,000.00
Semen PC @ 40 kg 163.00 Kg @Rp 1,300.00 Rp 211,900.00
Pasir Pasang 0.5200 M3 @Rp 125,000.00 Rp 65,000.00
Pekerja 1.5000 OH @Rp 65,000.00 Rp 97,500.00
Tukang (Kayu/Besi/Batu) 0.7500 OH @Rp 85,000.00 Rp 63,750.00
Kepala Tukang (Kayu/Besi/Batu) 0.0750 OH @Rp 85,000.00 Rp 6,375.00
Mandor 0.0750 OH @Rp 90,000.00 Rp 6,750.00
Jumlah Rp 607,275.00
Dibulatkan Rp 607,275.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
PEKERJAAN PASANGAN DINDING, PLASTERAN DAN PENGECATAN
SNI.6897.2008-6.7
1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 PC : 2 PS
Batu Bata Merah 70.0000 bh @Rp 800.00 Rp 56,000.00
Semen PC @ 40 kg 18.9500 Kg @Rp 1,300.00 Rp 24,635.00
Pasir Pasang 0.0380 M3 @Rp 125,000.00 Rp 4,750.00
Pekerja 0.3000 OH @Rp 65,000.00 Rp 19,500.00
Tukang (Kayu/Besi/Batu) 0.1000 OH @Rp 85,000.00 Rp 8,500.00
Kepala Tukang (Kayu/Besi/Batu) 0.0100 OH @Rp 85,000.00 Rp 850.00
Mandor 0.0150 OH @Rp 90,000.00 Rp 1,350.00
Jumlah Rp 115,585.00
Dibulatkan Rp 115,585.00
SNI.6897.2008-6.9
1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 PC : 4 PS
Batu Bata Merah 70.0000 bh @Rp 800.00 Rp 56,000.00
Semen PC @ 40 kg 11.5000 Kg @Rp 1,300.00 Rp 14,950.00
Pasir Pasang 0.0430 M3 @Rp 125,000.00 Rp 5,375.00
Pekerja 0.3000 OH @Rp 65,000.00 Rp 19,500.00
Tukang (Kayu/Besi/Batu) 0.1000 OH @Rp 85,000.00 Rp 8,500.00
Kepala Tukang (Kayu/Besi/Batu) 0.0100 OH @Rp 85,000.00 Rp 850.00
Mandor 0.0150 OH @Rp 90,000.00 Rp 1,350.00
Jumlah Rp 106,525.00
Dibulatkan Rp 106,525.00
SNI..2837.2008.6.15
1 M2 Plesteran 1 PC : 4 PS, tebal 20 mm
Semen PC @ 40 kg 8.3200 Kg @Rp 1,300.00 Rp 10,816.00
Pasir Pasang 0.0320 M3 @Rp 125,000.00 Rp 4,000.00
Pekerja 0.4000 OH @Rp 65,000.00 Rp 26,000.00
Tukang (Kayu/Besi/Batu) 0.2000 OH @Rp 85,000.00 Rp 17,000.00
Kepala Tukang (Kayu/Besi/Batu) 0.0200 OH @Rp 85,000.00 Rp 1,700.00
Mandor 0.0220 OH @Rp 90,000.00 Rp 1,980.00
Jumlah Rp 61,496.00
Dibulatkan Rp 61,496.00

SNI.2837.2008.6.13
1 M2 Plesteran 1 PC : 2 PS, tebal 20 mm
Semen PC @ 40 kg 13.6320 Kg @Rp 1,300.00 Rp 17,721.60
Pasir Pasang 0.0270 M3 @Rp 125,000.00 Rp 3,375.00
Pekerja 0.4000 OH @Rp 65,000.00 Rp 26,000.00
Tukang (Kayu/Besi/Batu) 0.2000 OH @Rp 85,000.00 Rp 17,000.00
Kepala Tukang (Kayu/Besi/Batu) 0.2000 OH @Rp 85,000.00 Rp 17,000.00
Mandor 0.2200 OH @Rp 90,000.00 Rp 19,800.00
Jumlah Rp 100,896.60
Dibulatkan Rp 100,897.00

SNI 2837-2008.6.27
Membuat 1 m2 Acian
Semen PC @ 40 kg 3.250 Kg @Rp 1,300.00 Rp 4,225.00
Pekerja 0.200 OH @Rp 65,000.00 Rp 13,000.00
Mandor 0.010 OH @Rp 90,000.00 Rp 900.00
Tukang (Kayu/Besi/Batu) 0.100 OH @Rp 85,000.00 Rp 8,500.00
Kepala Tukang (Kayu/Besi/Batu) 0.010 OH @Rp 85,000.00 Rp 850.00
Jumlah Rp 27,475.00
Dibulatkan Rp 27,475.00

PEKERJAAN KERAMIK DINDING DAN LANTAI


SNI.7394,2008-6.4
1 M3 Lantai Kerja Beton Tumbuk 1:3:5 (K-100)
Semen PC @ 40 kg 230.000 Kg @Rp 1,300.00 Rp 299,000.00
Pasir Pasang 0.638 m3 @Rp 125,000.00 Rp 79,732.14
Batu Kali/Batu Belah 0.761 m3 @Rp 130,000.00 Rp 98,896.30
Air 200.000 Ltr @Rp 50.00 Rp 10,000.00
Pekerja 1.200 Oh @Rp 65,000.00 Rp 78,000.00
Tukang (Kayu/Besi/Batu) 0.200 Oh @Rp 85,000.00 Rp 17,000.00
Kepala Tukang (Kayu/Besi/Batu) 0.020 Oh @Rp 85,000.00 Rp 1,700.00
Mandor 0.060 Oh @Rp 90,000.00 Rp 5,400.00
Jumlah Rp 589,728.44
Dibulatkan Rp 589,728.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
SNI.7395.2008.6.9a
1 M2 Pasangan Lantai Keramik 40 x 40 cm
Keramik 40 x 40 cm 6.2500 Bh @Rp 10,000.00 Rp 62,500.00
Semen PC @ 40 kg 11.3800 Kg @Rp 1,300.00 Rp 14,794.00
Pasir Pasang 0.0420 M3 @Rp 125,000.00 Rp 5,250.00
Semen Putih @ 50 Kg 1.5000 Kg @Rp 2,400.00 Rp 3,600.00
Pekerja 0.6200 OH @Rp 65,000.00 Rp 40,300.00
Tukang (Kayu/Besi/Batu) 0.3500 OH @Rp 85,000.00 Rp 29,750.00
Kepala Tukang (Kayu/Besi/Batu) 0.0350 OH @Rp 85,000.00 Rp 2,975.00
Mandor 0.0300 OH @Rp 90,000.00 Rp 2,700.00
Jumlah Rp 161,869.00
Dibulatkan Rp 161,869.00
SNI.7395.2008.6.9b
1 M2 Pasangan Lantai Keramik 40 x 40 cm (Anti Slip)
Keramik 40 x 40 cm (Anti Slip) 6.2500 Bh @Rp 10,000.00 Rp 62,500.00
Semen PC @ 40 kg 11.3800 Kg @Rp 1,300.00 Rp 14,794.00
Pasir Pasang 0.0420 M3 @Rp 125,000.00 Rp 5,250.00
Semen Putih @ 50 Kg 1.5000 Kg @Rp 2,400.00 Rp 3,600.00
Pekerja 0.6200 OH @Rp 65,000.00 Rp 40,300.00
Tukang (Kayu/Besi/Batu) 0.3500 OH @Rp 85,000.00 Rp 29,750.00
Kepala Tukang (Kayu/Besi/Batu) 0.0350 OH @Rp 85,000.00 Rp 2,975.00
Mandor 0.0300 OH @Rp 90,000.00 Rp 2,700.00
Jumlah Rp 161,869.00
Dibulatkan Rp 161,869.00

SNI.7395.2008.6.9c
1 M2 Pasangan Lantai Keramik 20 x 20 cm (Anti Slip)
Keramik 20 x 20 cm 16.0000 Bh @Rp 6,000.00 Rp 96,000.00
Semen PC @ 40 kg 11.3800 Kg @Rp 1,300.00 Rp 14,794.00
Pasir Pasang 0.0420 M3 @Rp 125,000.00 Rp 5,250.00
Semen Putih @ 50 Kg 1.5000 Kg @Rp 2,400.00 Rp 3,600.00
Pekerja 0.6200 OH @Rp 65,000.00 Rp 40,300.00
Tukang (Kayu/Besi/Batu) 0.3500 OH @Rp 85,000.00 Rp 29,750.00
Kepala Tukang (Kayu/Besi/Batu) 0.0350 OH @Rp 85,000.00 Rp 2,975.00
Mandor 0.0300 OH @Rp 90,000.00 Rp 2,700.00
Jumlah Rp 195,369.00
Dibulatkan Rp 195,369.00

SNI.7395.2008.6.9d
1 M2 Pasangan Dinding Keramik 20 x 25 cm
Keramik 20 x 25 cm (Anti Slip) 16.0000 Bh @Rp 8,000.00 Rp 128,000.00
Semen PC @ 40 kg 11.3800 Kg @Rp 1,300.00 Rp 14,794.00
Pasir Pasang 0.0420 M3 @Rp 125,000.00 Rp 5,250.00
Semen Putih @ 50 Kg 1.5000 Kg @Rp 2,400.00 Rp 3,600.00
Pekerja 0.6200 OH @Rp 65,000.00 Rp 40,300.00
Tukang (Kayu/Besi/Batu) 0.3500 OH @Rp 85,000.00 Rp 29,750.00
Kepala Tukang (Kayu/Besi/Batu) 0.0350 OH @Rp 85,000.00 Rp 2,975.00
Mandor 0.0300 OH @Rp 90,000.00 Rp 2,700.00
Jumlah Rp 227,369.00
Dibulatkan Rp 227,369.00
SNI.7394.2008.6.1
1 M3 Beton Mutu fc = 7,4 Mpa (K100), Slump (12 ± 2) cm, w/c = 0.87
Semen PC @ 40 kg 247.0000 Kg @Rp 1,300.00 Rp 321,100.00
Pasir Beton 0.5200 M3 @Rp 125,000.00 Rp 65,000.00
Kerikil Beton/Batu Pecah 0.8700 M3 @Rp 120,000.00 Rp 104,400.00
Pekerja 1.6500 OH @Rp 65,000.00 Rp 107,250.00
Tukang (Kayu/Besi/Batu) 0.2500 OH @Rp 85,000.00 Rp 21,250.00
Kepala Tukang (Kayu/Besi/Batu) 0.0250 OH @Rp 85,000.00 Rp 2,125.00
Mandor 0.0800 OH @Rp 90,000.00 Rp 7,200.00
Jumlah Rp 628,325.00
Dibulatkan Rp 628,325.00

PEKERJAAN BETON BERTULANG


SNI.7394.2008-6.5 1 M3 Membuat Beton Bertulang (K-175) 1Pc : 2 Ps : 3 Kr
Semen PC @ 40 kg 326.00 kg @Rp 1,300.00 Rp 423,800.00
Pasir Beton 0.54 M3 @Rp 125,000.00 Rp 67,857.14
Kerikil Beton/Batu Pecah 0.76 M3 @Rp 120,000.00 Rp 91,466.67
Air 215.00 Ltr @Rp 50.00 Rp 10,750.00
Pekerja 1.65 OH @Rp 65,000.00 Rp 107,250.00
Tukang (Kayu/Besi/Batu) 0.28 OH @Rp 85,000.00 Rp 23,375.00
Kepala Tukang (Kayu/Besi/Batu) 0.03 OH @Rp 85,000.00 Rp 2,380.00
Mandor 0.08 OH @Rp 90,000.00 Rp 7,470.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
Jumlah Rp 734,348.81
Dibulatkan Rp 734,349.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
SNI.7394.2008-6.7 1 M3 Membuat Beton Bertulang (K-250)
Semen PC @ 40 kg 384.000 kg @Rp 1,300.00 Rp 499,200.00
Pasir Beton 0.494 M3 @Rp 125,000.00 Rp 61,785.71
Kerikil Beton/Batu Pecah 0.770 M3 @Rp 120,000.00 Rp 92,355.56
Air 215.000 Ltr @Rp 50.00 Rp 10,750.00
Pekerja 1.650 OH @Rp 65,000.00 Rp 107,250.00
Tukang (Kayu/Besi/Batu) 0.275 OH @Rp 85,000.00 Rp 23,375.00
Kepala Tukang (Kayu/Besi/Batu) 0.028 OH @Rp 85,000.00 Rp 2,380.00
Mandor 0.083 OH @Rp 90,000.00 Rp 7,470.00
Jumlah Rp 804,566.27

SNI.7394.2008-6.20 1 M2 Pasang Bekisting untuk Pondasi


Kayu Kelas II (Kamper/Kruing/dll) 0.0400 M3 @Rp 3,500,000.00 Rp 140,000.00
Paku Kayu 0.3000 Kg @Rp 15,000.00 Rp 4,500.00
Minyak Bekisting/Oil 0.1000 Ltr @Rp 6,000.00 Rp 600.00
Pekerja 0.3000 OH @Rp 65,000.00 Rp 19,500.00
Tukang (Kayu/Besi/Batu) 0.2600 OH @Rp 85,000.00 Rp 22,100.00
Kepala Tukang (Kayu/Besi/Batu) 0.0260 OH @Rp 85,000.00 Rp 2,210.00
Mandor 0.0050 OH @Rp 90,000.00 Rp 450.00
Jumlah Rp 189,360.00
Dibulatkan Rp 189,360.00
SNI.7394.2008-6.21 1 M2 Pasang Bekisting untuk Sloof
Kayu Kelas II (Kamper/Kruing/dll) 0.0450 M3 @Rp 3,500,000.00 Rp 157,500.00
Paku Kayu 0.3000 Kg @Rp 15,000.00 Rp 4,500.00
Minyak Bekisting/Oil 0.1000 Ltr @Rp 6,000.00 Rp 600.00
Pekerja 0.3000 OH @Rp 65,000.00 Rp 19,500.00
Tukang (Kayu/Besi/Batu) 0.2600 OH @Rp 85,000.00 Rp 22,100.00
Kepala Tukang (Kayu/Besi/Batu) 0.0260 OH @Rp 85,000.00 Rp 2,210.00
Mandor 0.0050 OH @Rp 90,000.00 Rp 450.00
Jumlah Rp 206,860.00
Dibulatkan Rp 206,860.00

SNI.7394.2008-6.22 1 M2 Pasang Bekisting untuk Kolom


Kayu Kelas II (Kamper/Kruing/dll) 0.0400 M3 @Rp 3,500,000.00 Rp 140,000.00
Paku Kayu 0.4000 Kg @Rp 15,000.00 Rp 6,000.00
Minyak Bekisting/Oil 0.2000 Ltr @Rp 6,000.00 Rp 1,200.00
Kayu Klas III (Borneo/dll) 0.0150 M3 @Rp 3,000,000.00 Rp 45,000.00
Plywood 9 mm 0.3500 Lmbr @Rp 135,000.00 Rp 47,250.00
Kayu Perancah 2.0000 Btg @Rp 15,000.00 Rp 30,000.00
Pekerja 0.6600 OH @Rp 65,000.00 Rp 42,900.00
Tukang (Kayu/Besi/Batu) 0.3300 OH @Rp 85,000.00 Rp 28,050.00
Kepala Tukang (Kayu/Besi/Batu) 0.0330 OH @Rp 85,000.00 Rp 2,805.00
Mandor 0.0330 OH @Rp 90,000.00 Rp 2,970.00
Jumlah Rp 346,175.00
Dibulatkan Rp 346,175.00

SNI.7394.2008-6.23 1 M2 Pasang Bekisting untuk Balok


Kayu Kelas II (Kamper/Kruing/dll) 0.0400 M3 @Rp 3,500,000.00 Rp 140,000.00
Paku Kayu 0.4000 Kg @Rp 15,000.00 Rp 6,000.00
Minyak Bekisting/Oil 0.2000 Ltr @Rp 6,000.00 Rp 1,200.00
Kayu Klas III (Borneo/dll) 0.0180 M3 @Rp 3,000,000.00 Rp 54,000.00
Plywood 9 mm 0.350 Lmbr @Rp 135,000.00 Rp 47,250.00
Kayu Perancah 2.0000 Btg @Rp 15,000.00 Rp 30,000.00
Pekerja 0.6600 OH @Rp 65,000.00 Rp 42,900.00
Tukang (Kayu/Besi/Batu) 0.3300 OH @Rp 85,000.00 Rp 28,050.00
Kepala Tukang (Kayu/Besi/Batu) 0.0330 OH @Rp 85,000.00 Rp 2,805.00
Mandor 0.0330 OH @Rp 90,000.00 Rp 2,970.00
Jumlah Rp 355,175.00
Dibulatkan Rp 355,175.00

SNI.7394.2008-6.24 1 M2 Pasang Bekisting untuk Plat Lantai


Kayu Kelas II (Kamper/Kruing/dll) 0.0400 M3 @Rp 3,500,000.00 Rp 140,000.00
Paku Kayu 0.4000 Kg @Rp 15,000.00 Rp 6,000.00
Minyak Bekisting/Oil 0.2000 Ltr @Rp 6,000.00 Rp 1,200.00
Kayu Klas III (Borneo/dll) 0.0150 M3 @Rp 3,000,000.00 Rp 45,000.00
Plywood 9 mm 0.3500 Lmbr @Rp 135,000.00 Rp 47,250.00
Kayu Perancah 6.0000 Btg @Rp 15,000.00 Rp 90,000.00
Pekerja 0.6600 OH @Rp 65,000.00 Rp 42,900.00
Tukang (Kayu/Besi/Batu) 0.3300 OH @Rp 85,000.00 Rp 28,050.00
Kepala Tukang (Kayu/Besi/Batu) 0.0330 OH @Rp 85,000.00 Rp 2,805.00
Mandor 0.0330 OH @Rp 90,000.00 Rp 2,970.00
Jumlah Rp 406,175.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
Dibulatkan Rp 406,175.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
SNI.3435.2002-6.34 1 M2 Pasang Bekisting untuk Tangga
Kayu Kelas II (Kamper/Kruing/dll) 0.0300 M3 @Rp 3,500,000.00 Rp 105,000.00
Paku Kayu 0.4000 Kg @Rp 15,000.00 Rp 6,000.00
Minyak Bekisting/Oil 0.1500 Ltr @Rp 6,000.00 Rp 900.00
Kayu Klas III (Borneo/dll) 0.0150 M3 @Rp 3,000,000.00 Rp 45,000.00
Plywood 9 mm 0.3500 Lmbr @Rp 135,000.00 Rp 47,250.00
Kayu Perancah 2.0000 Btg @Rp 15,000.00 Rp 30,000.00
Pekerja 0.6600 OH @Rp 65,000.00 Rp 42,900.00
Tukang (Kayu/Besi/Batu) 0.3300 OH @Rp 85,000.00 Rp 28,050.00
Kepala Tukang (Kayu/Besi/Batu) 0.0330 OH @Rp 85,000.00 Rp 2,805.00
Mandor 0.0330 OH @Rp 90,000.00 Rp 2,970.00
Jumlah Rp 310,875.00
Dibulatkan Rp 310,875.00

SNI.7394.2008-6.17a 1 Kg Pembesian dengan Besi Polos


Besi Beton Polos 1.0500 Kg @Rp 11,500.00 Rp 12,075.00
Kawat Beton 0.0150 Kg @Rp 12,000.00 Rp 180.00
Pekerja 0.0070 OH @Rp 65,000.00 Rp 455.00
Tukang (Kayu/Besi/Batu) 0.0070 OH @Rp 85,000.00 Rp 595.00
Kepala Tukang (Kayu/Besi/Batu) 0.0007 OH @Rp 85,000.00 Rp 59.50
Mandor 0.0004 OH @Rp 90,000.00 Rp 36.00
Jumlah Rp 13,400.50
Dibulatkan Rp 13,401.00

SNI.7394.2008-6.17 b 1 Kg Pembesian dengan Besi Ulir


Besi Beton Ulir 1.0500 Kg @Rp 14,000.00 Rp 14,700.00
Kawat Beton 0.0150 Kg @Rp 12,000.00 Rp 180.00
Pekerja 0.0070 OH @Rp 65,000.00 Rp 455.00
Tukang (Kayu/Besi/Batu) 0.0070 OH @Rp 85,000.00 Rp 595.00
Kepala Tukang (Kayu/Besi/Batu) 0.0007 OH @Rp 85,000.00 Rp 59.50
Mandor 0.0004 OH @Rp 90,000.00 Rp 36.00
Jumlah Rp 16,025.50
Dibulatkan Rp 16,026.00

Anl. Taksir Membongkar dan Menyiram Beton


Membongkar/Menyiram Beton 1.00 Ls @Rp 5,000.00 Rp 5,000.00
Jumlah Rp 5,000.00
Dibulatkan Rp 5,000.00

PEKERJAAN LANGIT -LANGIT


SNI.2839.2008-6.7
Memasang 1 M2 Langit-langit Gypsum 9 mm
Pekerja 0.1000 Org @Rp 65,000.00 Rp 6,500.00
Tukang (Kayu/Besi/Batu) 0.0500 Org @Rp 85,000.00 Rp 4,250.00
Kepala Tukang (Kayu/Besi/Batu) 0.0050 Org @Rp 85,000.00 Rp 425.00
Mandor 0.0050 Org @Rp 90,000.00 Rp 450.00
Screw 0.1100 Kg @Rp 600.00 Rp 66.00
Gypsum board 9 mm 0.3640 Lbr @Rp 100,000.00 Rp 36,400.00
Jumlah Rp 48,091.00
Dibulatkan Rp 48,091.00
SNI.2839.2008-6.7a
Memasang 1 M2 Langit-langit Gypsum 9 mm (Motif)
Pekerja 0.1000 Org @Rp 65,000.00 Rp 6,500.00
Tukang (Kayu/Besi/Batu) 0.0500 Org @Rp 85,000.00 Rp 4,250.00
Kepala Tukang (Kayu/Besi/Batu) 0.0050 Org @Rp 85,000.00 Rp 425.00
Mandor 0.0050 Org @Rp 90,000.00 Rp 450.00
Screw 0.1400 Kg @Rp 600.00 Rp 84.00
Gypsum board 9 mm 0.4240 Lbr @Rp 100,000.00 Rp 42,400.00
Jumlah Rp 54,109.00
Dibulatkan Rp 54,109.00
SNI.2839.2008-6.8
1 M' List Plafond Gypsum Profil
List Gypsum Profil 1.0500 M' @Rp 11,000.00 Rp 11,550.00
Dempul gypsum 0.1500 Kg @Rp 25,000.00 Rp 3,750.00
Pekerja 0.0600 Org @Rp 65,000.00 Rp 3,900.00
Tukang (Kayu/Besi/Batu) 0.0500 Org @Rp 85,000.00 Rp 4,250.00
Kepala Tukang (Kayu/Besi/Batu) 0.0050 Org @Rp 85,000.00 Rp 425.00
Mandor 0.0030 Org @Rp 90,000.00 Rp 270.00
Jumlah Rp 24,145.00
Dibulatkan Rp 24,145.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
Anl.SNI.6.14-2002 1 M2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Tukang (Kayu/Besi/Batu) 0.0630 Oh @Rp 85,000.00 Rp 5,355.00
Kepala Tukang (Kayu/Besi/Batu) 0.0063 Oh @Rp 85,000.00 Rp 535.50
Mandor 0.0025 Oh @Rp 90,000.00 Rp 225.00
Pekerja 0.0200 Oh @Rp 65,000.00 Rp 1,300.00
Cat Tembok 0.2600 kg @Rp 30,000.00 Rp 7,800.00
Cat Tembok Dasar 0.1000 kg @Rp 30,000.00 Rp 3,000.00
Plamir Tembok 0.1000 kg @Rp 15,000.00 Rp 1,500.00
Jumlah Rp 19,715.50
Dibulatkan Rp 19,716.00

Anl. Cat.3 1 m2 Cat Kayu (2 Lapis) termasuk pekerjaan plamur, Mengamplas


Cat Kayu Dasar 0.125 kg @Rp 30,000.00 Rp 3,750.00
Kertas Amplas 0.500 Lbr @Rp 10,000.00 Rp 5,000.00
Cat Kayu Mengkilat 0.200 kg @Rp 55,000.00 Rp 11,000.00
Kuas Roda 0.015 bh @Rp 20,000.00 Rp 300.00
Pekerja 0.160 OH @Rp 65,000.00 Rp 10,400.00
Mandor 0.010 OH @Rp 90,000.00 Rp 900.00
Tukang (Kayu/Besi/Batu) 0.280 OH @Rp 85,000.00 Rp 23,800.00
Kepala Tukang (Kayu/Besi/Batu) 0.030 OH @Rp 85,000.00 Rp 2,550.00
Jumlah Rp 57,700.00
Dibulatkan Rp 57,700.00

PEKERJAAN SANITASI DAN PLUMBING


SNI T-15-2002-6.25
Memasang 1 M' Pipa PVC tipe AW Ø 1/2"
Pipa PVC Ø 1/2" 1.200 M' @Rp 6,000.00 Rp 7,200.00
Harga pipa utk Perlengkapan 35.000 % @Rp 2,100.00 Rp 735.00
Pekerja 0.036 Org @Rp 65,000.00 Rp 2,340.00
Tukang (Kayu/Besi/Batu) 0.060 Org @Rp 85,000.00 Rp 5,100.00
Kepala Tukang (Kayu/Besi/Batu) 0.006 Org @Rp 85,000.00 Rp 510.00
Mandor 0.002 Org @Rp 90,000.00 Rp 162.00
Jumlah Rp 16,047.00
Dibulatkan Rp 16,047.00

SNI T-15-2002-6.29
Memasang 1 M' Pipa PVC tipe AW 2"
Pipa PVC Ø 2" 1.200 M' @Rp 20,000.00 Rp 24,000.00
Harga pipa utk Perlengkapan 35.000 % @Rp 7,000.00 Rp 2,450.00
Pekerja 0.054 Org @Rp 65,000.00 Rp 3,510.00
Tukang (Kayu/Besi/Batu) 0.090 Org @Rp 85,000.00 Rp 7,650.00
Kepala Tukang (Kayu/Besi/Batu) 0.009 Org @Rp 85,000.00 Rp 765.00
Mandor 0.003 Org @Rp 90,000.00 Rp 243.00
Jumlah Rp 38,618.00
Dibulatkan Rp 38,618.00

SNI T-15-2002-B.26
Memasang 1 M' Pipa PVC tipe AW 3/4"
Pipa PVC Ø 3/4" 1.100 M' @Rp 5,000.00 Rp 5,500.00
Harga pipa utk Perlengkapan 25.000 % @Rp 1,250.00 Rp 312.50
Pekerja 0.036 Org @Rp 65,000.00 Rp 2,340.00
Tukang (Kayu/Besi/Batu) 0.060 Org @Rp 85,000.00 Rp 5,100.00
Kepala Tukang (Kayu/Besi/Batu) 0.006 Org @Rp 85,000.00 Rp 510.00
Mandor 0.002 Org @Rp 90,000.00 Rp 162.00
Jumlah Rp 13,924.50
Dibulatkan Rp 13,925.00

SNI T-15-2002-B.32
Memasang 1 M' Pipa PVC tipe AW 4"
Pipa PVC Ø 4" 1.200 M' @Rp 50,000.00 Rp 60,000.00
Harga pipa utk Perlengkapan 35.000 % @Rp 17,500.00 Rp 6,125.00
Pekerja 0.081 Org @Rp 65,000.00 Rp 5,265.00
Tukang (Kayu/Besi/Batu) 0.135 Org @Rp 85,000.00 Rp 11,475.00
Kepala Tukang (Kayu/Besi/Batu) 0.014 Org @Rp 85,000.00 Rp 1,147.50
Mandor 0.004 Org @Rp 90,000.00 Rp 369.00
Jumlah Rp 84,381.50
Dibulatkan Rp 84,382.00
ANALISA KEGIATAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA
(Rp)
SNI T-15-2002-B.35
Memasang 1 Buah Kran Ø ¾" atau Ø ½"
Kran Air 1.000 Buah @Rp 35,000.00 Rp 35,000.00
Seal Tape 0.025 Buah @Rp 10,000.00 Rp 250.00
Pekerja 0.010 Org @Rp 65,000.00 Rp 650.00
Tukang (Kayu/Besi/Batu) 0.100 Org @Rp 85,000.00 Rp 8,500.00
Kepala Tukang (Kayu/Besi/Batu) 0.010 Org @Rp 85,000.00 Rp 850.00
Mandor 0.005 Org @Rp 90,000.00 Rp 450.00
Jumlah Rp 45,700.00
Dibulatkan Rp 45,700.00

Anl. H.8
1 m2 Penutup Atap Celulos Beitumen
Penutup Atap Celulos Bitumen 0.556 Lbr @Rp 120,000.00 Rp 66,720.00
Paku Atap Seng 9.000 bh @Rp 1,200.00 Rp 10,800.00
Pekerja 0.100 OH @Rp 65,000.00 Rp 6,500.00
Tukang (Kayu/Besi/Batu) 0.005 OH @Rp 85,000.00 Rp 425.00
Kepala Tukang (Kayu/Besi/Batu) 0.200 OH @Rp 85,000.00 Rp 17,000.00
Mandor 0.020 OH @Rp 90,000.00 Rp 1,800.00
Rp 103,245.00
Rp 103,245.00

Anl. H.10a
1 m2 Bubungan Celulos Beitumen
Penutup Rabung Celulos Beitumen 1.000 Lbr @Rp 70,000.00 Rp 70,000.00
Paku / Baut Ulir Atap 9.000 bh @Rp 350.00 Rp 3,150.00
Pekerja 0.350 OH @Rp 65,000.00 Rp 22,750.00
Tukang (Kayu/Besi/Batu) 0.250 OH @Rp 85,000.00 Rp 21,250.00
Kepala Tukang (Kayu/Besi/Batu) 0.030 OH @Rp 85,000.00 Rp 2,550.00
Rp 119,700.00
Rp 119,700.00

-
-
-

0
0
DAFTAR HARGA SATUAN BAHAN DAN UPAH

PEKERJAAN : PEMBANGUNAN SPA


LOKASI : CASANEMO
TAHUN : 2015

NO. KOMPONEN MATERIAL/BAHAN HARGA (Rp) SAT

1 Air 50 Ltr
2 Batu Bata Merah 800 Bh
3 Batu Kali/Batu Belah 130,000 M3
4 Besi Angel Bracket (to concrete) 11,000 Bh
5 Besi Beton Polos 11,500 kg
6 Besi Beton Ulir 14,000 kg
7 Cat Kayu Dasar 30,000 kg
8 Cat Kayu Mengkilat 55,000 kg
9 Cat Tembok 30,000 kg
10 Cat Tembok Dasar 30,000 kg
11 Dempul gypsum 25,000 Kg
12 Gypsum board 9 mm 100,000 Lbr
13 Kran Air 35,000 Bh
14 Kawat Beton 12,000 kg
15 Kawat Tembaga Drat/BC 16 mm 70,000 Kg
16 Kayu Kelas I 4,500,000 M3
17 Kayu Kelas II (Kamper/Kruing/dll) 3,500,000 M3
18 Kayu Klas III (Borneo/dll) 3,000,000 M3
19 Kayu Perancah 15,000 Btg
20 Keramik 40 x 40 cm 10,000 Bh
21 Keramik 40 x 40 cm (Anti Slip) 10,000 Bh
22 Keramik 20 x 20 cm 6,000 Bh
23 Keramik 20 x 25 cm (Anti Slip) 8,000 Bh
24 Kerikil Beton/Batu Pecah 120,000 M3
25 Kertas Amplas 10,000 Lbr
26 Kuas Roda 20,000 Buah
27 List Gypsum Profil 11,000 M'
28 Membongkar/Menyiram Beton 5,000 Ls
29 Minyak Bekisting/Oil 6,000 Ltr
30 Paku beton 300 Bh
31 Paku Atap Seng 1,200 Bh
32 Paku Kayu 15,000 Kg
33 Paku / Baut Ulir Atap 350 Bh
34 Papan Kayu 3,000,000 M3
35 Pasir Beton 125,000 M3
36 Pasir Pasang 125,000 M3
37 Pasir Urug 100,000 M3
38 Penutup Atap Celulos Bitumen 120,000 Lbr
NO. KOMPONEN MATERIAL/BAHAN HARGA (Rp) SAT

39 Penutup Rabung Celulos Beitumen 70,000 Lbr


40 Pipa PVC Ø 1/2" 6,000 M'
41 Pipa PVC Ø 2" 20,000 M'
42 Pipa PVC Ø 3/4" 5,000 M'
43 Pipa PVC Ø 4" 50,000 M'
44 Plamir Tembok 15,000 Kg
45 Plywood 9 mm 135,000 Lbr
46 Screw 600 Kg
47 Seal Tape 10,000 Bh
48 Semen PC @ 40 kg 1,300 kg
49 Semen Putih @ 50 Kg 2,400 kg
50 Tanah Timbun 50,000 M3
NO. TENAGA KERJA HARGA (Rp) SAT

1 Pekerja 65,000 OH
2 Tukang (Kayu/Besi/Batu) 85,000 OH
3 Kepala Tukang (Kayu/Besi/Batu) 85,000 OH
4 Mandor 90,000 OH

-
-
-

0
0
RINCIAN PERHITUNGAN VOLUME PEKERJAAN

Bj
NO URAIAN PEKERJAAN TYPE JLH VOLUME SAT
(P) (L) (L) (T) (M²) (kg/m)
1 2 3 4 5 6 7 8 9 10
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 11.00 13.00 143.000 M2
2 Pemasangan Bouwplank 48.000 M'
3 Direksi Keet/Barak Kerja (Sewa) 1.00 1.00 LS
4 Papan Nama Proyek 1.00 1.00 LS
5 Pengadaan Air Kerja 1.00 1.00 LS
6 Pengadaan Listrik Kerja 1.00 1.00 LS
7 Dokumentasi Dan Administrasi 1.00 1.00 LS

II LANTAI 1
A PEKERJAAN TANAH DAN PONDASI
Pondasi Tapak/Sumuran
1 Galian Tanah Pondasi Tapak (TP 1) 12 1.00 1.00 1.35 16.200 M3
16.200 M3
2 Urugan Pasir Alas Pondasi Tapak tebal 5 cm 12 1.00 1.00 0.05 0.600 M3
0.600 M3

3 Pasangan Batu Kosong 12 1.00 1.00 0.10 1.20 M3


1.20 M3

4 Urugan Tanah Kembali 4.05 M3

Pondasi Menerus Batu Gunung


1 Galian Tanah Pondasi Batu Gunung 93.97 0.80 0.80 60.14
12.00 0.80 0.80 (0.80) (6.14)
54.00 M3

2 Urugan pasir Alas Pondasi Menerus 93.97 0.80 0.05 3.76


3.76 M3

3 Pas. Aanstamping tebal 10 cm 93.97 0.80 0.10 7.52


7.52 M3

4 Pas. Pondasi Batu Gunung 1pc : 4ps 93.97 0.80 0.30 0.80 0.44 41.35
41.35 M3

5 Angchor stik dia 10-100 mm 93.97 0.80 0.62 46.38 Kg

6 Urugan Tanah Kembali 15.04 M3

B PEKERJAAN BETON BERTULANG


1 Pondasi Tapak TP1 (100 X 100 cm)
-Beton Cor K-250 12 1.00 1.00 0.20 2.40 M3
-Besi Beton Polos (Ø14-170 mm) ; (Ø14-210 mm) 12 10.91 10.91 1.21 316.28 Kg

-Bekisting 12 0.40 0.40 3x penggunaan 3.20 M2


-Pekerjaan Lain-lain 2.40 Ls

2 Sloof Beton Type S.1 cm


-Beton Cor K-250 93.97 0.20 0.30 5.64 M3
-Besi Beton Polos (7Ø14 mm) 7 93.97 1.21 794.61 Kg
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 469.85 1.00 0.22 104.31 Kg
-Bekisting 93.97 0.60 3x penggunaan 37.59 M2
-Pekerjaan Lain-lain 5.64 Ls
3 Kolom Beton Tipe K1 Uk. 30 x 30 cm
-Beton Cor K-250 12 0.30 0.30 4.00 4.32 M3
-Besi Beton Polos (8Ø14 mm) 96 4.00 1.21 463.87 Kg
-Besi Beton Polos (ø6-100 mm) 480 1.20 0.22 127.87 Kg
-Bekisting 12 4.00 1.20 3x penggunaan 19.20 M2
-Pekerjaan Lain-lain 4.32 Ls

4 Kolom Beton Tipe K2 Uk. 13 x 13 cm


-Beton Cor K-250 9 0.13 0.13 3.00 0.46 M3
-Besi Beton Polos (4Ø14mm) 36 3.00 1.21 130.46 Kg
-Besi Beton Polos (ø6-100 mm) 270 0.52 0.22 31.17 Kg
-Bekisting 9 3.00 0.52 3x penggunaan 4.68 M2
-Pekerjaan Lain-lain 0.46 Ls

5 Balok Tipe B.1 Uk. 20 x 30 cm


-Beton Cor K-250 98.53 0.20 0.18 3.55 M3
-Besi Beton Polos (7Ø14 mm) 7 98.53 1.21 833.17 Kg
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 656.87 0.76 0.22 110.83 Kg
-Bekisting 98.53 0.58 3x penggunaan 19.05 M2
-Pekerjaan Lain-lain 3.55 Ls

6 Plat Lantai Tebal 12 cm


12.73 9.13 116.2249
-Beton Cor K-250 0.12 116.22 13.95 M3
-Besi Beton Polos (ø10-100 mm) 0.62 2,866.11 Kg

-Bekisting 116.22 M2
-Pekerjaan Lain-lain 13.95 Ls

C PEKERJAAN PASANGAN

1 Pasangan Dinding Bata 1:4 1 75.60 2.70 204.120


PJ1 -1 1.72 2.10 -3.612
-2 0.96 0.86 -1.651
P2 -5 0.92 2.10 -9.660
P3 -1 0.82 2.10 -1.722
J1 -1 1.02 1.58 -1.612
J2 -1 1.42 0.72 -1.022
J3 -1 0.92 2.12 -1.950
J4 -2 1.12 0.92 -2.061
180.830 M2

2 Plesteran Dinding Bata 1:4 361.659 M2


D PEKERJAAN PLAFOND

1 Rangka Plafond 1 8.51 12.73 108.33


108.33 M2

2 Pasangan Plafond Gypsum 9 mm 1 8.51 12.73 108.33


108.33 M2

3 Pemasangan List Plafond 1 75.60 75.60


75.60 M'

E PEKERJAAN LANTAI
1 Tanah Timbun 1 10.88 12.73 0.30 41.551
41.551 M3

2 Urugan pasir Alas lantai T = 10 cm 1 10.88 12.73 0.10 13.850 M3


13.850 M3

3 Beton Cor Alas lantai T = 8 cm 1 10.88 12.73 0.08 11.080 M3


11.080 M3

4 Pas. Lantai keramik 40 x 40 cm 1 10.88 12.73 138.502


KM/WC -1 1.63 2.30 -3.749
134.753 M2

5 Pas. keramik 20 x 20 cm (Toilet) 1 1.63 2.30 3.749

6 Pas. keramik 20 x 25 cm (Dinding KM/WC) 1 7.86 1.80 14.148


14.15 M2

F PEKERJAAN PENGECATAN
1 Pengecatan Dinding
Pengecatan Dinding 1:4 361.66 M2
361.66 M2

2 Pengecatan Plafond 108.33 M2

G PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA


1 Pintu Tipe PJ1
Pintu & Jendela Blockboard + Frame Alumunium + Accessories 1 1.00 Unit

2 Pintu Tipe P2
Pintu Blockboard + Frame Alumunium + Accessories 5 5.00 Unit

3 Pintu Tipe P3
Pintu Kayu + Kusen Kayu + Accessories 1 1.00 Unit

4 Jendela Tipe J1
Jendela + Frame Alumunium + Accessories 1 1.00 Unit

5 Jendela Tipe J2
Jendela + Frame Alumunium + Accessories 1 1.00 Unit

6 Jendela Tipe J3
Jendela + Frame Alumunium + Accessories 1 1.00 Unit

7 Jendela Tipe J4
Jendela + Frame Alumunium + Accessories 2 2.00 Unit

H PEKERJAAN MEKANIKAL ELEKTRIKAL

1 Panel Kontrol
a Panel MCB 1 1.00 Unit
b Panel AC 1 1.00 Unit

2 Titik Instalasi
a Instalasi Titik Panel SDP 3 3.00 Titik
b Instalasi Titik Penerangan (Termasuk Pembobokan dan Perapian) 33 33.00 Titik
c Instalasi Titik Stop Kontak (Termasuk Pembobokan dan Perapian) 25 25.00 Titik
3 Kabel + Accessories
a Kabel GL 2,5 mm NYA 50 50.00 M'
b Isolasi 3 3.00 Bh

5 Lampu Penerangan
a Lampu Dinding 18 watt + Accessories 28 28.00 Unit
b Lampu HE 18 watt + Accessories 5 5.00 Unit
c Saklar Double + Kelengkapan 10 10.00 Unit
d Stop Kontak Setara Panasonic 25 25.00 Unit

I PEKERJAAN INSTALASI AIR BERSIH


1 Pipa Air Bersih PVC Ø 3/4" 1 50.00 50.00 M1
2 Instalasi Air Bersih (termasuk galian, pembobokan, 50.00 50.00 M1
penyambungan koneksi)
3 Kran Air Stainless Ø 1/2" 2 2.00 M1
4 Floor drain 2 2.00 Bh
5 Wastafel 7 7.00 Bh
6 Water Heater 1 1.00 Bh

J PEKERJAAN INSTALASI AIR KOTOR


1 Pipa Air Kotor PVC Ø 2" 1 50.00 50.00 M1
2 Pipa Kotoran PVC Ø 4" 1 40.00 40.00 M1
3 Instalasi Air Kotor (termasuk galian, pembobokan, 1 50.00 50.00 M1
penyambungan koneksi)
4 Kloset Duduk 2 2.00 Bh

M PEKERJAAN TANGGA LT 1

1 Plat Beton Bordes


-Beton Cor K-250 1 0.8 1.00 0.12 0.80 0.10 M3
-Besi Beton Polos (ø10-200 mm) 1 4.00 0.62 2.47 Kg
-Bekisting 3x penggunaan 0.55 M2
-Pekerjaan Lain-lain 0.10 Ls

2 Plat Lantai Tangga


-Beton Cor K-250 1 4.60 1.00 0.12 4.60 0.55 M3
-Besi Beton Polos (ø10-200 mm) 1 20.91 0.62 12.90 Kg
-Bekisting 3x penggunaan 2.43 M2
-Pekerjaan Lain-lain 0.55 Ls

3 Tangga Beton
-Beton Cor K-250 15 1.00 0.20 0.30 0.45
0.45 M3
-Besi Beton Polos (ø10-200 mm) 68 1.00 0.62 20.94
20.94 Kg
-Bekisting 7.50
3x penggunaan 2.50 M2
-Pekerjaan Lain-lain 0.45 Ls

4 Pasangan Keramik Tangga 15 1.00 0.20 0.30 7.50


7.50 M2
LANTAI 2
A PEKERJAAN BETON BERTULANG
1 Kolom Beton Tipe K1 Uk. 30 x 30 cm
-Beton Cor K-250 10 0.30 0.30 3.00 2.70 M3
-Besi Beton Polos (8Ø14 mm) 80 3.00 1.21 289.92 Kg
-Besi Beton Polos (ø6-100 mm) 300 1.20 0.22 79.92 Kg
-Bekisting 10 1.80 1.80 3x penggunaan 12.00 M2
-Pekerjaan Lain-lain 2.70 Ls

2 Kolom Beton Tipe K2 Uk. 13 x 13 cm


-Beton Cor K-250 18 0.13 0.13 3.00 0.91 M3
-Besi Beton Polos (4Ø14mm) 72 3.00 0.62 133.27 Kg
-Besi Beton Polos (ø6-100 mm) 270 0.52 0.22 31.17 Kg
-Bekisting 18 0.78 0.78 3x penggunaan 9.36 M2
-Pekerjaan Lain-lain 0.91 Ls

3 Ring Balk Tipe B.1 Uk. 20 x 30 cm


-Beton Cor K-250 11.54 0.20 0.18 0.42 M3
-Besi Beton Polos (7Ø14mm) 7 11.54 1.21 97.58 Kg
-Besi Beton Polos Tumpuan Ø6-100 ; Lapangan Ø6-150 57.70 0.76 0.22 9.74 Kg
-Bekisting 11.54 3x penggunaan 1.38 M2
-Pekerjaan Lain-lain 0.42 Ls

4 Ring Balk Tipe B.1 Uk. 15 x 20 cm


-Beton Cor K-250 48.98 0.15 0.08 0.59 M3
-Besi Beton Polos (6Ø14mm) 6 48.98 1.21 355.01 Kg
-Besi Beton Polos Tumpuan Ø8-100 ; Lapangan Ø8-150 244.90 0.46 0.40 44.50 Kg
-Bekisting 48.98 3x penggunaan 2.61 M2
-Pekerjaan Lain-lain 0.59 Ls

5 Plat Lantai Tebal 2x12 cm Bawah Bak Air


2 2.83 2.94 16.6404
-Beton Cor K-250 0.12 16.64 2.00 M3
-Besi Beton Polos (ø10-200 mm) 2 77.40 0.62 95.51 Kg

-Bekisting 3x penggunaan 6.01 M2


-Pekerjaan Lain-lain 2.00 Ls

6 Kolom Beton Tipe K1 Uk. 30 x 30 cm T.1 m


-Beton Cor K-250 4 0.30 0.30 1.00 0.36 M3
-Besi Beton Polos (8Ø14 mm) 32 1.00 1.21 38.66 Kg
-Besi Beton Polos (ø6-100 mm) 20 1.20 0.22 5.33 Kg
-Bekisting 4 0.60 0.60 3x penggunaan 1.60 M2
-Pekerjaan Lain-lain 0.36 Ls

B PEKERJAAN PASANGAN

1 Pasangan Dinding Bata 1:4 1 48.27 2.70 130.329


P2 -1 0.92 2.10 -1.932
P3 -3 0.82 2.10 -5.166
J7 -1 1.30 2.03 -2.639
V1 -1 0.72 0.62 -0.446
V2 -1 0.62 1.60 -0.992
V3 -3 0.30 1.00 -0.900
118.254 M2

2 Pasangan Bata Pada Bak Air Bawah Atap 1 11.54 1.00 11.540 M2

2 Plesteran Dinding Bata 1:4 248.047 M2

3 Pasangan Dinding Kayu 1 20.44 2.70 55.188


J5 -3 2.90 2.10 -18.270
J6 -1 2.69 1.10 -2.959
33.959 M2

D PEKERJAAN LANTAI
1 Pas. Lantai keramik 40 x 40 cm 1 12.73 6.88 87.582
85.582 M2

E PEKERJAAN PENGECATAN
1 Pengecatan Dinding
Pengecatan Dinding 1:4 248.05 M2
Pengecatan Kolom & Balok
248.05 M2

F PEKERJAAN PENGADAAN DAN PEMASANGAN KUSEN, PINTU, DAN JENDELA

1 Pintu Tipe P2
Pintu Blockboard + Frame Alumunium + Accessories 1 1.00 Unit

2 Pintu Tipe P3
Pintu Kayu + Kusen Kayu + Accessories 3 3.00 Unit

3 Jendela Tipe J5
Jendela + Frame Alumunium + Accessories 3 3.00 Unit

4 Jendela Tipe J6
Jendela + Frame Alumunium + Accessories 1 1.00 Unit

5 Jendela Tipe J7
Jendela + Frame Alumunium + Accessories 1 1.00 Unit

6 Ventilasi Tipe V1
Ventilasi + Frame Alumunium + Accessories 1 1.00 Unit

7 Ventilasi Tipe V2
Ventilasi + Frame Alumunium + Accessories 1 1.00 Unit

8 Ventilasi Tipe V3
Ventilasi + Frame Alumunium + Accessories 3 3.00 Unit

G PEKERJAAN MEKANIKAL ELEKTRIKAL

1 Panel Kontrol
a Panel MCB 1 1.00 Unit
b Panel AC 1 1.00 Unit

2 Titik Instalasi
a Instalasi Titik Panel SDP 3 3.00 Titik
b Instalasi Titik Penerangan (Termasuk Pembobokan dan Perapian) 27 27.00 Titik
c Instalasi Titik Stop Kontak (Termasuk Pembobokan dan Perapian) 23 23.00 Titik

3 Kabel + Accessories
a Kabel GL 2,5 mm NYA 52 52.00 M'
b Isolasi 3 3.00 Bh

5 Lampu Penerangan
a Lampu Dinding 18 watt + Accessories 24 24.00 Unit
b Lampu HE 18 watt + Accessories 3 3.00 Unit
c Saklar Double + Kelengkapan 11 11.00 Unit
d Stop Kontak Setara Panasonic 23 23.00 Unit
I PEKERJAAN INSTALASI AIR BERSIH
1 Pipa Air Bersih PVC Ø 3/4" 1 50.00 50.00 M1
2 Instalasi Air Bersih (termasuk galian, pembobokan, 50.00 50.00 M1
penyambungan koneksi)
3 Kran Air Stainless Ø 1/2" 3 3.00 M1
4 Floor drain 3 3.00 Bh
5 Wastafel 2 2.00 Bh
6 Water Heater 3 3.00 Bh

J PEKERJAAN INSTALASI AIR KOTOR


1 Pipa Air Kotor PVC Ø 2" 1 50.00 50.00 M1
2 Pipa Kotoran PVC Ø 4" 1 40.00 40.00 M1
3 Instalasi Air Kotor (termasuk galian, pembobokan, 1 50.00 50.00 M1
penyambungan koneksi)
4 Kloset Duduk 3 3.00 Bh

PEKERJAAN ATAP
1 Pengadaan dan pemasangan atap rumbia 12.72 10.88 138.39 168.74 M2
cos a = 4,15/5,06
= 0.8201581
2 Rangka atap kayu 168.74 m2
Y = BESI UTAMA
R = BESI SENGKANG

LOCATION Size of Structure Diameter No Jumlah Besi x Total of


Tinggi Lebar Panjang Off Bar
SM
1.5 3.14 0.21231423 Y10 1 21 1 21
Y10 1 10 1 10
Y10 1 8 1 8
Y10 1 2 1 2

LOCATION Size of Structure Diameter No Jumlah Besi x Total of


Tinggi Lebar Panjang Off Bar
T1
1.5 1.8 0.37037037 Y14 2 9 1 17
Y14 2 9 1 18
Y16 1 3 1 3

S1
3 0.5 0.666666667 Y16 1 11 1 11
Y12 1 2 1 2
R10 1 6 1 6
R10 1 4 1 4

S.2
0.25 0.4 10 Y12 1 8 1 8

R10 1 100 1 100


S.3
0.18 0.25 22.22222222 Y12 1 5 1 5
0 1 0 1 -
R10 1 185 1 185

S.4
0.13 0.15 51.28205128 Y12 1 4 1 4
R10 1 427 1 427

K.1
0.3 0.3 11.11 Y13 1 6 1 6
Y13 1 4 1 4
Y10 1 111 1 111
Y10 1 22 1 22

K.2
0.45 0.45 4.94 Y16 1 8 1 8
Y14 1 4 1 4
Y12 1 41 1 41
Y12 1 10 1 10

K.3
0.45 0.5 4.44 Y16 1 8 1 8
Y14 1 4 1 4
Y12 1 37 1 37
Y12 1 9 1 9
K.4
0.5 0.5 4.00 Y16 1 16 1 16
R10 1 40 1 40
R10 1 10 1 10

K.5
0.13 0.13 59.17 R10 1 4 1 4
R8 1 394 1 394

BALOK LANTAI B.1


0.3 0.5 6.67 Y16 1 11 1 11
Y12 1 2 1 2
R10 1 67 1 67

BALOK LANTAI B.2


0.25 0.4 10.00 Y16 1 7 1 7
Y12 1 2 1 2
R10 1 83 1 83

BALOK LANTAI B.3


0.18 0.25 22.22 Y12 1 5 1 5
R10 1 185 1 185
BALOK LANTAI B.4
0.13 0.4 19.23 Y12 1 4 1 4
Y12 1 2 1 2
R10 1 160 1 160

BALOK BORDES TANGGA B.5


0.13 0.4 19.23 Y12 1 6 1 6
Y12 1 2 1 2
R10 1 160 1 160

BALOK BORDES TANGGA B.6


0.13 0.3 25.64 Y12 1 4 1 4
Y12 1 2 1 2
R10 1 214 1 214

BALOK LATAI BL.1


0.13 0.2 38.46 R10 1 4 1 4
R8 1 256 1 256

BALOK LATAI BL.2


0.13 0.13 59.17 R10 1 4 1 4
R8 1 394 1 394
BALOK LATAI BL.2
0.13 0.15 51.28 R10 1 4 1 4
R8 1 342 1 342

PLAT Tangga
0.12 1.9 4.38596491 Y14 2 9.5 1 19
R10 2 22 1 44

PLAT lantai
0.12 1 8.33333333 R10 2 6.666666666667 1 13
R10 2 56 1 111

PLAT Atap Dag


0.1 1 10 Y10 2 6.666666666667 1 13
R10 2 67 1 133

PLAT Sunwearing
0.1 1 10 Y10 2 5 1 10
R10 2 50 1 100

PLAT beton t 12 cm
0.12 1 8.33333333 Y10 1 6.666666666667 1 7
R10 1 56 1 56

RB.1
0.3 0.5 6.67 Y14 1 8 1 8
R10 1 56 1 56
R10 1 2 1 2

RB.2
0.25 0.4 10.00 Y14 1 7 1 7
R10 1 83 1 83
R10 1 2 1 2

RB.3
0.18 0.25 22.22 R12 1 7 1 7
R10 1 185 1 185
0 1 2 1 2
RB.4
0.13 0.4 19.23 R12 1 4 1 4
R10 1 160 1 160
R12 1 2 1 2

RB.5
0.15 0.55 12.12 R12 1 4 1 4
R10 1 101 1 101
R12 1 2 1 2

RB.6
0.15 1 6.67 R12 1 10 1 10
R10 1 56 1 56
R12 1 6 1 6

RB.7
0.15 0.2 33.33 R12 1 4 1 4
R8 1 278 1 278
R12 1 - 1 -
PERHITUNGAN BESI

Length Total Y10 Y12 Y13 Y14


(a) (b) (c) Length mm mm mm mm

3.80 3.80 79.55 - - -


7.08 7.08 70.80 - - -
3.14 3.14 25.12 - - -
1.50 1.50 3.00 - - -
Sub-Total (m) : 150.35 - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : 92.76 - - -
BESI UTAMA
SENGKANG
TOTAL
Length Total Y10 Y12 Y13 Y14
(a) (b) (c) Length mm mm mm mm

3.60 3.60 - - - 61.71


4.20 4.20 - - - 74.12
1.50 1.50 - - - -
Sub-Total (m) : - - - 135.83
Conversion m/Kg : 0.617 0.888 1.042 1.208
Total Weight (Kg) : - - - 164.08
BESI UTAMA
SENGKANG
TOTAL

0.67 0.67 - - - -
0.33 0.33 - 0.67 - -
7.00 7.00 - - - -
0.67 0.67 - - - -
Sub-Total (m) : - 0.67 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 0.59 - -
Besi ulir
Besi polos
TOTAL

10.00 10.00 - 80.00 - -

1.30 1.30 - - - -
Sub-Total (m) : - 80.00 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 71.04 - -
Besi ulir
Besi polos
TOTAL

22.22 22.22 - 111.11 - -


5.00 5.00 - - - -
0.86 0.86 - - - -
Sub-Total (m) : - 111.11 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 98.67 - -
Besi ulir
Besi polos
TOTAL

51.28 51.28 - 205.13 - -


0.56 0.56 - - - -
Sub-Total (m) : - 205.13 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 182.15 - -
Besi ulir
Besi polos
TOTAL

11.11 11.11 - - 66.67 -


1.20 1.20 - - 4.80 -
1.20 1.20 133.33 - - -
2.00 2.00 44.44 - - -
Sub-Total (m) : 133.33 - 71.47 -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : 82.27 - 86.33 -
Besi ulir
Besi polos
TOTAL

4.94 4.94 - - - -
4.94 4.94 - - - 19.75
1.80 1.80 - 74.07 - -
2.00 2.00 - 19.75 - -
Sub-Total (m) : - 93.83 - 19.75
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 83.32 - 23.86
Besi ulir
Besi polos
TOTAL

4.44 4.44 - - - -
4.44 4.44 - - - 17.78
1.90 1.90 - 70.37 - -
1.22 1.22 - 10.84 - -
Sub-Total (m) : - 81.21 - 17.78
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 72.12 - 21.48
Besi ulir
Besi polos
TOTAL

4.00 4.00 - - - -
2.00 2.00 - - - -
0.60 0.60 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

59.17 59.17 - - - -
0.52 0.52 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

6.67 6.67 - - - -
6.67 6.67 - 13.33 - -
1.60 1.60 - - - -
Sub-Total (m) : - 13.33 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 11.84 - -
Besi ulir
Besi polos
TOTAL

10.00 10.00 - - - -
10.00 10.00 - 20.00 - -
1.30 1.30 - - - -
Sub-Total (m) : - 20.00 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 17.76 - -
Besi ulir
Besi polos
TOTAL

22.22 22.22 - 111.11 - -


0.86 0.86 - - - -
Sub-Total (m) : - 111.11 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 98.67 - -
Besi ulir
Besi polos
TOTAL

19.23 19.23 - 76.92 - -


19.23 19.23 - 38.46 - -
1.06 1.06 - - - -
Sub-Total (m) : - 115.38 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 102.46 - -
Besi ulir
Besi polos
TOTAL

19.23 19.23 - 115.38 - -


19.23 19.23 - 38.46 - -
1.06 1.06 - - - -
Sub-Total (m) : - 153.85 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 136.62 - -
Besi ulir
Besi polos
TOTAL

25.64 25.64 - 102.56 - -


25.64 25.64 - 51.28 - -
0.86 0.86 - - - -
Sub-Total (m) : - 153.85 - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - 136.62 - -
Besi ulir
Besi polos
TOTAL

38.46 38.46 - - - -
0.66 0.66 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

59.17 59.17 - - - -
0.52 0.52 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

51.28 51.28 - - - -
0.56 0.56 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

4.39 4.39 - - - 83.33


1.90 1.90 - - - -
Sub-Total (m) : - - - 83.33
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - 100.67
BESI UTAMA
SENGKANG
TOTAL

8.33 8.33 - - - -
1.00 1.00 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
BESI UTAMA
SENGKANG
TOTAL

10.00 10.00 133.33 - - -


1.00 1.00 - - - -
Sub-Total (m) : 133.33 - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : 82.27 - - -
BESI UTAMA
SENGKANG
TOTAL
10.00 10.00 100.00 - - -
1.00 1.00 - - - -
Sub-Total (m) : 100.00 - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : 61.70 - - -
BESI UTAMA
SENGKANG
TOTAL

8.33 8.33 55.56 - - -


1.00 1.00 - - - -
Sub-Total (m) : 55.56 - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : 34.28 - - -
BESI UTAMA
SENGKANG
TOTAL

6.67 6.67 - - - 53.33


1.60 1.60 - - - -
6.67 6.67 - - - -
Sub-Total (m) : - - - 53.33
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - 64.43
Besi ulir
Besi polos
TOTAL

10.00 10.00 - - - 70.00


1.30 1.30 - - - -
10.00 10.00 - - - -
Sub-Total (m) : - - - 70.00
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - 84.56
Besi ulir
Besi polos
TOTAL

22.22 22.22 - - - -
0.86 0.86 - - - -
22.22 22.22 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

19.23 19.23 - - - -
1.06 1.06 - - - -
19.23 19.23 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

12.12 12.12 - - - -
1.40 1.40 - - - -
12.12 12.12 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

6.67 6.67 - - - -
2.30 2.30 - - - -
6.67 6.67 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL

33.33 33.33 - - - -
0.70 0.70 - - - -
33.33 33.33 - - - -
Sub-Total (m) : - - - -
Conversion m/Kg : 0.617 0.888 1.208 1.208
Total Weight (Kg) : - - - -
Besi ulir
Besi polos
TOTAL
Y16 Y19 Y20 Y25 Y32 R6 R7 R8 R10
mm mm mm mm mm mm mm mm mm

- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - -

Y16 Y19 Y20 Y25 Y32 R6 R7 R8 R10


mm mm mm mm mm mm mm mm mm

- - - - - - - - -
- - - - - - - - -
4.50 - - - - - - - -
4.50 - - - - - - - -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
7.10 - - - - - - - -

7.33 - - - - - - - -
- - - - - - - - -
- - - - - - - - 38.89
- - - - - - - - 2.67
7.33 - - - - - - - 41.56
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
11.57 - - - - - - - 25.64

- - - - - - - - -

- - - - - - - - 130.00
- - - - - - - - 130.00
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 80.21

- - - - - - - - -
- - - - - - - - -
- - - - - - - - 159.26
- - - - - - - - 159.26
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 98.26

- - - - - - - - -
- - - - - - - - 239.32
- - - - - - - - 239.32
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 147.66

- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - -

39.51 - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
39.51 - - - - - - - -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
62.34 - - - - - - - -

35.56 - - - - - - - -
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
35.56 - - - - - - - -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
56.11 - - - - - - - -

64.00 - - - - - - - -
- - - - - - - - 80.00
- - - - - - - - 6.00
64.00 - - - - - - - 86.00
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
100.99 - - - - - - - 53.06

- - - - - - - - 236.69
- - - - - - - 205.13 -
- - - - - - - 205.13 236.69
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - 81.03 146.04

73.33 - - - - - - - -
- - - - - - - - -
- - - - - - - - 106.67
73.33 - - - - - - - 106.67
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
115.72 - - - - - - - 65.81

70.00 - - - - - - - -
- - - - - - - - -
- - - - - - - - 108.33
70.00 - - - - - - - 108.33
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
110.46 - - - - - - - 66.84

- - - - - - - - -
- - - - - - - - 159.26
- - - - - - - - 159.26
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 98.26

- - - - - - - - -
- - - - - - - - -
- - - - - - - - 169.87
- - - - - - - - 169.87
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 104.81

- - - - - - - - -
- - - - - - - - -
- - - - - - - - 169.87
- - - - - - - - 169.87
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 104.81

- - - - - - - - -
- - - - - - - - -
- - - - - - - - 183.76
- - - - - - - - 183.76
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 113.38

- - - - - - - - 153.85
- - - - - - - 169.23 -
- - - - - - - 169.23 153.85
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - 66.85 94.92

- - - - - - - - 236.69
- - - - - - - 205.13 -
- - - - - - - 205.13 236.69
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - 81.03 146.04

- - - - - - - - 205.13
- - - - - - - 191.45 -
- - - - - - - 191.45 205.13
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - 75.62 126.56

- - - - - - - - -
- - - - - - - - 83.33
- - - - - - - - 83.33
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 51.42

- - - - - - - - 111.11
- - - - - - - - 111.11
- - - - - - - - 222.22
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 137.11

- - - - - - - - -
- - - - - - - - 133.33
- - - - - - - - 133.33
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 82.27
- - - - - - - - -
- - - - - - - - 100.00
- - - - - - - - 100.00
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 61.70

- - - - - - - - -
- - - - - - - - 55.56
- - - - - - - - 55.56
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 34.28

- - - - - - - - -
- - - - - - - - 88.89
- - - - - - - - 13.33
- - - - - - - - 102.22
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 63.07

- - - - - - - - -
- - - - - - - - 108.33
- - - - - - - - 20.00
- - - - - - - - 128.33
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 79.18

- - - - - - - - -
- - - - - - - - 159.26
- - - - - - - - -
- - - - - - - - 159.26
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 98.26
- - - - - - - - -
- - - - - - - - 169.87
- - - - - - - - -
- - - - - - - - 169.87
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 104.81

- - - - - - - - -
- - - - - - - - 141.41
- - - - - - - - -
- - - - - - - - 141.41
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 87.25

- - - - - - - - -
- - - - - - - - 127.78
- - - - - - - - -
- - - - - - - - 127.78
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - - 78.84

- - - - - - - - -
- - - - - - - 194.44 -
- - - - - - - - -
- - - - - - - 194.44 -
1.578 2.226 2.466 3.853 6.313 0.222 0.302 0.395 0.617
- - - - - - - 76.81 -
92.76
-
92.76

171.19
-
171.19

12.16
25.64
37.80
71.04
80.21
151.25

98.67
98.26
196.93

182.15
147.66
329.81

86.33
82.27
168.60

86.20
83.32
169.52
77.58
72.12
149.70

100.99
53.06
154.05

-
227.06
227.06

115.72
193.37
309.09

110.46
195.06
305.52
98.67
196.93
295.60

102.46
104.81
207.27

136.62
104.81
241.43

136.62
113.38
250.00

161.77
161.77
227.06
227.06

202.19
202.19

100.67
51.42
152.08

-
137.11
137.11

82.27
82.27
164.53
61.70
61.70
123.40

34.28
34.28
68.56

64.43
63.07
127.50

84.56
79.18
163.74
-
98.26
98.26

-
104.81
104.81

-
87.25
87.25

-
78.84
78.84

-
76.81
76.81
HITUNGAN CETAKAN

TINGGI LEBAR PANJANG


STRUKTUR
m m m (Utk 1m3)
k.1 0.40 0.40 6.25
K2 0.45 0.45 4.94
K3 0.45 0.50 4.44
K4 0.50 0.50 4.00
K5 0.13 0.13 59.17
K6 0.00 0.25 #DIV/0!
K7 0.00 0.25 #DIV/0!

B1 0.35 0.50 5.71


B2 0.25 0.40 10.00
B3 0.18 0.25 22.22
B4 0.14 0.40 17.86
BL.1 0.13 0.20 38.46
BL.2 0.13 0.13 59.17
BL.3 0.13 0.15 51.28
RB.1 0.30 0.50 6.67
RB.2 0.25 0.40 10.00
RB.3 0.18 0.25 22.22
RB.4 0.13 0.40 19.23
RB.5 0.15 0.55 12.12
RB.6 0.15 1.00 6.67
RB.7 0.15 0.20 33.33
RBA 0.00 0.35 #DIV/0!
0.00 0.35 #DIV/0!
0.00 0.00 #DIV/0!
S2 0.25 0.50 8.00
0.00 0.40 #DIV/0!
0.00 0.30 #DIV/0!
0.00 0.15 #DIV/0!
0.00 0.40 #DIV/0!
PLAT BORDES A 0.12 4.00 2.08
PLAT BORDES B 0.12 2.12 3.93
PLAT LANTAI TANGGA 0.12 1.80 4.63
0.20 0.15 33.33

PLAT (LANTAI) 0.12 1.00 8.33


PLAT (ATAP DAG) 0.10 1.00 10.00

PLAT (WAERING) 0.13 1.00 7.69

8.80 1.50 0.08


0.00 1.60 #DIV/0!
0.00 1.80 #DIV/0!
0.00 2.00 #DIV/0!
pondasi 0.00 1.00 #DIV/0!
N CETAKAN

JUMLAH BETON CETAKAN CETAKAN UNTUK


no m3 m2 ANALISA
1.00 1.00 10.00 5.00
1.00 1.00 8.89 4.44
1.00 1.00 8.44 4.22
1.00 1.00 8.00 4.00
1.00 1.00 30.77 10.26
2.00 #DIV/0! #DIV/0! #DIV/0!
3.00 #DIV/0! #DIV/0! #DIV/0!

1.00 1.00 9.71 3.24


1.00 1.00 13.00 4.33
1.00 1.00 19.11 4.78
1.00 1.00 19.29 6.43
2.00 2.00 50.77 6.35
2.00 2.00 61.54 7.69
2.00 2.00 57.44 7.18
1.00 1.00 10.67 5.33
1.00 1.00 13.00 6.50
1.00 1.00 19.11 9.56
1.00 1.00 10.19 5.10
1.00 1.00 16.97 5.66
1.00 1.00 15.33 5.11
1.00 1.00 23.33 7.78
1.00 #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0!
1.00 1.00 8.00 4.00
1.00 #DIV/0! #DIV/0! #DIV/0!
2.00 #DIV/0! #DIV/0! #DIV/0!
3.00 #DIV/0! #DIV/0! #DIV/0!
4.00 #DIV/0! #DIV/0! #DIV/0!
1.00 1.00 9.54 3.18
2.00 2.00 9.31 3.10
1.00 1.00 9.32 3.11
1.00 1.00 11.67 2.92

1.00 1.00 8.33 4.17


1.00 1.00 10.00 10.00

1.00 1.00 7.69 7.69

1.00 1.00 1.45 1.45


2.00 #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0!
2.00 #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0!

Anda mungkin juga menyukai