REKAPITULASI

NAMA PEKERJAAN : PEMBANGUNAN GEDUNG KIOS PASAR KOTA PINANG


LOKASI : KOTA PINANG
TAHUN : 2015

TOTAL HARGA
NO URAIAN PEKERJAAN
(Rp)

A PEKERJAAN PERSIAPAN 9,800,000.00

B PEKERJAAN GEDUNG
I PEKERJAAN TANAH 10,353,893.10
II PEKERJAAN PONDASI, SLOOF, KOLOM, RINGBALK 1,040,121,929.71
III PEKERJAAN PARTISI 67,024,908.00
IV PEKERJAAN ATAP 804,188,636.31
V PEKERJAAN ELEKTRIKAL 12,164,826.00
VI PEKERJAAN PENGECATAN -
VII PEKERJAAN SALURAN AIR 60,993,469.90
TOTAL B 1,994,847,663.02

C PEKERJAAN TANAH
I PEKERJAAN TANAH 115,738,604.14
II PEKERJAAN PONDASI 106,916,905.92
III PEKERJAAN BETON 183,594,386.48
IV PEKERJAAN DINDING 373,368,441.60
V PEKERJAAN LANTAI 86,172,960.00
VI PEKERJAAN PINTU 458,965,634.40
VII PEKERJAAN PLAFOND 429,408,000.00
VIII PEKERJAAN PENGECATAN 66,497,583.69
IX PEKERJAAN ELEKTRIKAL 19,260,000.00
TOTAL C 1,839,922,516.23

D PEMBERSIHAN AKHIR 2,500,000.00

JUMLAH 3,847,070,179.25
DIBULATKAN 3,847,070,000.00
Terbilang : Tiga Milyar Delapan Ratus Empat Puluh Tujuh Juta Tujuh Puluh Ribu Rupiah
RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : PEMBANGUNAN GEDUNG KIOS PASAR KOTA PINANG


LOKASI : KOTA PINANG
TAHUN : 2015

SA- HARGA JUMLAH


NO URAIAN PEKERJAAN VOLUME TUAN ANALISA SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 Pembersihan awal 1.000 ls Taksir 1,000,000.00 1,000,000.00
2 Biaya photo dokumentasi 1.00 ls Taksir 500,000.00 500,000.00
3 Gudang alat kerja 1.00 ls Taksir 5,000,000.00 5,000,000.00
4 Biaya pembuatan/pemasangan plank nama kegiatan 1.00 ls Taksir 300,000.00 300,000.00
5 Listrik dan air kerja 1.00 ls Taksir 3,000,000.00 3,000,000.00
TOTAL A 9,800,000.00

B PEKERJAAN GEDUNG
I PEKERJAAN TANAH
1 Pengukuran dan pemasangan bowplank 156.00 m` RSNI T-12-2002:6.4 21,200.00 3,307,200.00
2 Galian Tanah 93.92 m3 SNI 2835:2008.6.1 59,250.00 5,564,760.00
3 Urug kembali galian 31.30 m3 SNI 2835:2008.6.9a 19,750.00 618,175.00
4 Urugan pasir bawah pondasi 2.30 m3 SNI 2835:2008.6.11 375,547.00 863,758.10
TOTAL I 10,353,893.10

II PEKERJAAN PONDASI, SLOOF, KOLOM, RINGBALK


1 Cor rabat beton bawah pondasi 120 cm x 120 cm x 10 c 4.60 m3 SNI 7394:2008.6.4 1,027,365.00 4,725,879.00
2 Pondasi setempat 120 cm x 120 cm x 30 cm 13.82 m3 SNI 7394:2008.6.28a 6,765,078.00 93,493,377.96
3 Cor kolom 40 cm x 40 cm 12.80 m3 SNI 7394:2008.6.30a 6,450,988.00 82,572,646.40
4 Cor sloof 20/30 24.80 m3 SNI 7394:2008.6.29a 4,949,608.00 122,750,278.40
5 Angker Ø18 mm + baut 192.00 bh Dihitung 30,000.00 5,760,000.00
6 Mur + baut pengikat buhul Ø18 mm' 96.00 bh Dihitung 20,000.00 1,920,000.00
7 Tiang baja H 250.250.9.14 13,321.60 kg Dihitung2 40,585.00 540,657,136.00
8 Ringbalk baja WF 200.100.5,5.8 3,108.00 kg Dihitung2 40,585.00 126,138,180.00
9 Plat buhul kolom #10 mm 307.72 kg Dihitung4 40,685.00 12,519,588.20
10 Plat pengaku kolom #10 mm 949.53 kg Dihitung4 40,685.00 38,631,628.05
11 Plat pengaku ringbalk + plat buhul #6 mm 269.22 kg Dihitung4 40,685.00 10,953,215.70
TOTAL II 1,040,121,929.71

III PEKERJAAN PARTISI


2 Dinding partisi GRC rangka alluminium 199.80 m2 Dihitung1 335,460.00 67,024,908.00
TOTAL III 67,024,908.00

IV PEKERJAAN ATAP
1 Kaki kuda-kuda baja WF 200.100.5,5.8 4,095.36 kg Dihitung2 40,585.00 166,210,185.60
2 Kaki kuda-kuda baja WF 100.50.5.7 1,097.40 kg Dihitung2 40,585.00 44,537,979.00
3 Plat pengaku & plat buhul kuda-kuda atap # 6 mm 613.24 kg Dihitung4 40,685.00 24,949,669.40
4 Plat pengaku & plat buhul kuda-kuda atap # 5 mm 115.39 kg Dihitung4 40,685.00 4,694,642.15
5 Gording C 125.50.20.2,3 8,933.40 kg Dihitung3 40,685.00 363,455,379.00
6 tupai-tupai gording besi L 110.110.10 75.36 kg Dihitung2 40,585.00 3,058,485.60
7 Pengikat angin ø14 mm + klem 553.28 kg SNI 7394:2008.6.17 31,252.00 17,291,106.56
8 Atap zinkalum 0,3 mm 1,648.40 m2 Taksir 93,320.00 153,828,688.00
9 Rabung atap zinkalum #0,3 mm 101.20 m` Taksir 38,850 3,931,620.00
10 Mur + baut pengikatu buhul ø18 mm 448.00 bh Taksir 15000 6,720,000.00
11 Talang jurai dalam zinkalum #0,30 mm 55.00 m` XII.18 (SNI-2008) 80,795.00 4,443,725.00
12 Talang air seng 60.00 m` XII.18 (SNI-2008) 80,795.00 4,847,700.00
13 Pipa penyalur air hujan PVC Ø35 mm 96.00 m` RSNI T-15-2002 : 6.25 64,786.00 6,219,456.00
TOTAL IV 804,188,636.31
V PEKERJAAN ELEKTRIKAL
1 Instalasi titik nyala 12.00 titik Harga satuan 130,000.00 1,560,000.00
2 saklar tunggal 6.00 bh Harga satuan 5,000.00 30,000.00
3 Lampu mercury 160 watt 12.00 bh Harga satuan 120,000.00 1,440,000.00
4 Pipa PVC 1/2" 141.00 m` RSNI T-15-2002 : 6.25 64,786.00 9,134,826.00
TOTAL V 12,164,826.00

VI PEKERJAAN PENGECATAN
1 Cat partisi GRC 199.80 m2 XIV.8 (SNI-2002) 31,401.00 6,273,919.80
2 Cat besi 839.60 m2 XIV.4 (SNI-2002) 68,730.00 57,705,708.00
TOTAL VI

VII PEKERJAAN SALURAN AIR


1 Pengukuran & pemasangan bowplang 167.00 m3 RSNI T-12-2002:6.4 21,200.00 3,540,400.00
2 Galian tanah 51.87 m3 SNI 2835:2008.6.1 59,250.00 3,073,297.50
3 Pasir urug 4.71 m3 SNI 2835:2008.6.11 375,547.00 1,768,826.37
4 Rabat beton 9.43 m3 SNI 7394:2008.6.4 1,027,365.00 9,688,051.95
5 Pas. 1/2 bata trassraam 1:2 125.76 m2 SNI 6897:2008.6.7 131,431.00 16,528,762.56
6 Plesteran 1:2 125.76 m2 SNI 2837:2008.6.2 63,927.00 8,039,459.52
7 Acian 125.76 m2 SNI 2837:2008.6.27 33,450.00 4,206,672.00
8 Jerjak besi strip 47.16 m2 Taksir 300,000.00 14,148,000.00
TOTAL VII 60,993,469.90
TOTAL B 1,994,847,663.02

C PEKERJAAN KIOS
I PEKERJAAN TANAH
1 Pengukuran dan pemasangan bowplank 360.00 M` RSNI T-12-2002:6.4 21,200.00 7,632,000.00
2 Galian Tanah Biasa 119.04 m3 SNI 2835:2008.6.1 59,250.00 7,053,120.00
3 Timbun kembali tanah galian 39.68 m3 SNI 2835:2008.6.9a 19,750.00 783,680.00
4 Urugan pasir bawah pondasi 9.92 m3 SNI 2835:2008.6.11 375,547.00 3,725,426.24
5 Tanah timbun meninggikan pile lantai 380.70 m3 SNI 2835:2008.6.15a 253,597.00 96,544,377.90
TOTAL I 115,738,604.14
II PEKERJAAN PONDASI
1 Rollag 1/2 bata camp 1:4 (tangga selasar) 306.24 SNI 6897:2008.6.9 122,567.00 37,534,918.08
2 Pondasi menerus pas. Batu kali 54.56 m3 SNI 2836:2008.6.2 1,271,664.00 69,381,987.84
TOTAL II 106,916,905.92

III PEKERJAAN BETON


1 Sloof 11 cm/20 cm 10.91 m3 SNI 7394:2008.6.29a 4,949,608.00 54,000,223.28
2 Kolom praktis 11 cm x 11 cm 326.40 m` SNI 7394:2008.6.35 119,578.00 39,030,259.20
3 Ringbalk 10 cm/15 cm 576.00 m` SNI 7394:2008.6.36 157,229.00 90,563,904.00
TOTAL III 183,594,386.48

IV PEKERJAAN DINDING
1 Dinding pas.1/2 Bata camp. 1:4 1,209.60 m2 SNI 6897:2008.6.9 122,567.00 148,257,043.20
2 Plesteran 1:4 2,419.20 m2 SNI 2837:2008.6.4 59,602.00 144,189,158.40
3 Acian 2,419.20 m2 SNI 2837:2008.6.27 33,450.00 80,922,240.00
TOTAL IV 373,368,441.60

V PEKERJAAN LANTAI
1 Pasir urug bawah lantai 69.88 m3 SNI 2835:2008.6.11 375,547.00 26,243,224.36
2 Rabat beton #8 cm, cor 1:2:3 11.18 m3 SNI 7394:2008.6.5 1,178,623.00 13,177,005.14
3 Acian 1,397.69 m2 SNI 2837:2008.6.27 33,450.00 46,752,730.50
TOTAL V 86,172,960.00
VI PEKERJAAN PINTU
1 Kusen pintu aluminium 904.80 m` 6.11 96,153.00 86,999,234.40
2 Daun pintu rolling door aluminium + bingkai 748.80 m2 6.10 496,750.00 371,966,400.00
TOTAL VI 458,965,634.40

VII PEKERJAAN PLAFOND


1 Plafond multipleks #12 mm ex. Garuda fom 720.00 m2 SNI 2839:2008.6.5a 96,400.00 69,408,000.00
2 Jerjak besi rangka plafond 720.00 m2 Taksir 500,000.00 360,000,000.00
TOTAL VI 429,408,000.00

VIII PEKERJAAN PENGECATAN


1 Cat tembok baru 1,397.69 m2 XIV.8 (SNI-2002) 31,401.00 43,888,863.69
2 Cat plafond 720.00 m2 XIV.8 (SNI-2002) 31,401.00 22,608,720.00
TOTAL VII 66,497,583.69

IX PEKERJAAN ELEKTRIKAL
1 Instalasi titik nyala 60.00 titik Harga satuan 130,000.00 7,800,000.00
2 Instalasi stop kontak 60.00 titik Harga satuan 130,000.00 7,800,000.00
3 Saklar tunggal 60.00 bh Harga satuan 5,000.00 300,000.00
4 Stop kontak 60.00 bh Harga satuan 6,000.00 360,000.00
5 Lampu sl 23 watt 60.00 bh Harga satuan 50,000.00 3,000,000.00
TOTAL VIII 19,260,000.00
TOTAL C 1,839,922,516.23

D PEMBERSIHAN AKHIR
1 Pembersihan akhir dan penyempurnaan pekerjaan 1.00 ls Taksir 2,500,000.00
TOTAL D 2,500,000.00

TOTAL A+B+C+D 3,847,070,179.25


DIBULATKAN 3,847,070,000.00
Terbilang : Tiga Milyar Delapan Ratus Empat Puluh Tujuh Juta Tujuh Puluh Ribu Rupiah
REKAPITULASI HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2014

NO. NOMOR ANALISA JENIS PEKERJAAN SATUAN HARGA SATUAN


( Rp )
1 2 3 4 5

I. RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
1 RSNI T-12-2002:6.4 1.00 M` Pekerjaan Pengukuran dan Pemasangan Bowplank M` 21,200.00
2 RSNI T-12-2002:6.8 1.00 M² Pekerjaan Membersihkan Lapangan dan Peralatan M² 8,100.00
3 RSNI T-12-2002:6.14 1.00 M3 Pekerjaan Membongkar Dinding Tembok Batu Bata Merah M3 540,210.00

I. SNI 2835:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Tanah Untuk Bangunan Gedung dan Perumahan
1 SNI 2835:2008.6.1 1.00 M³ Pekerjaan Galian Tanah Biasa sedalam 1 meter M³ 59,250.00
2 SNI 2835:2008.6.9a 1.00 M³ Pekerjaan Mengurug kembali 1 m³ bekas galian M³ 19,750.00
3 SNI 2835:2008.6.11 1.00 M³ Pekerjaan Mengurug 1 m³ pasir urug M³ 375,547.00
4 SNI 2835:2008.6.15a 1.00 M³ Pek. Mengurug 1 m3 Tanah Timbun M³ 253,597.00

II. SNI 2836:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Pondasi untuk Konstruksi Bangunan Gedung dan Perumahan
1 SNI 2836:2008.6.2 1.00 M³ Pekerjaan Memasang Pondasi Batu Kali Camp. 1 Semen : 4 Pasir Pasang M³ 1,271,664.00
2 SNI 2836:2008.6.9 1.00 M³ Pekerjaan Memasang Batu Kosong (anstamping) M³ 903,222.00
3 SNI 2836:2008.6.10 1.00 M³ Pekerjaan Memasang Pondasi Siklop, 60% beton camp. 1 : 2 : 3 dan 40% Batu Kali M³ 4,828,509.00

III. SNI 6897:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Dinding untuk Konstruksi Bangunan Gedung dan Perumahan
1 SNI 6897:2008.6.1 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal 1 bata, camp. Spesi 1 M² 271,956.00
Semen : 2 Pasir Pasang
2 SNI 6897:2008.6.3 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal 1 bata, camp. Spesi 1 M² 252,298.00
Semen : 4 Pasir Pasang
1 SNI 6897:2008.6.7 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal ½ bata, camp. Spesi 1 M² 131,431.00
Semen : 2 Pasir Pasang
2 SNI 6897:2008.6.9 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal ½ bata, camp. Spesi 1 M² 122,567.00
Semen : 4 Pasir Pasang

IV. SNI 2837:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Plesteran untuk Konstruksi Bangunan Gedung dan Perumahan
1 SNI 2837:2008.6.2 1.00 M² Pekerjaan Membuat Plesteran 1 Semen : 2 PP, tebal 15 mm M² 63,927.00
2 SNI 2837:2008.6.4 1.00 M² Pekerjaan Membuat Plesteran 1 Semen : 4 PP, tebal 15 mm M² 59,602.00
3 SNI 2837:2008.6.27 1.00 M² Pekerjaan Membuat Acian M² 33,450.00

V. SNI 03-3436-2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Penutup Atap untuk Konstruksi Bangunan Gedung dan Perumahan
1 Taksir 1.00 M² Pekerjaan Memasang atap genteng metal zincalume type prima roof M² #VALUE!
1 Taksir 1.00 M² Pekerjaan Memasang atap zincalume M² 93,320.00
2 SNI 03-3436-2002.6.9 1.00 M² Pekerjaan Memasang Atap Seng Gelombang BJLS M² 52,740.00
3 Taksir 1.00 M' Pekerjaan Memasang Rabung genteng metal zincalume type prima roof M' 11,350.00
3 Taksir 1.00 M' Pekerjaan Memasang Rabung atap zincalume M' 38,850.00

VI. SNI 3434:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Kayu untuk Konstruksi Bangunan Gedung dan Perumahan
1 SNI 3434:2008.6.1 1.00 M³ Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas III M³ #VALUE!
2 SNI 3434:2008.6.5 1.00 M² Membuat dan Memasang Daun Pintu Panel, Kayu Kelas III M² #VALUE!
3 SNI 3434:2008.6.6 1.00 M² Pekerjaan Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas III M² #VALUE!
NO. NOMOR ANALISA JENIS PEKERJAAN SATUAN HARGA SATUAN
( Rp )
1 2 3 4 5
4 SNI 3434:2008.6.8 1.00 M² Pekerjaan Membuat Daun Pintu Kayu Lapis (Triplek) rangkap, rangka tertutup kayu Kelas II M² #VALUE!
(lebar sampai 90 cm)
4 SNI 3434:2008.6.10 1.00 M² Pekerjaan Memasang Jalusi Kusen, Kayu Kelas III M² 887,450.00
5 SNI 3434:2008.6.13 1.00 M³ Pekerjaan Memasang Konstruksi Kuda-Kuda Konvensional, Kayu Kelas II bentang 6 meter M³ 15,160,000.00
6 SNI 3434:2008.6.14 1.00 M³ Pekerjaan Memasang Konstruksi Kuda-Kuda Ekspose, Kayu Kelas II M³ 17,607,400.00
6 SNI 3434:2008.6.15 1.00 M³ Pekerjaan Memasang Konstruksi Gording, Kayu Kelas II M³ 14,368,800.00
7 SNI 3434:2008.6.16 1.00 M² Pekerjaan Memasang Rangka Atap Genteng Keramik, Kayu Kelas II M² 226,200.00
7 SNI 3434:2008.6.19a 1.00 M² Pekerjaan Memasang Rangka Langit-Langit (100 x 100) cm, Kayu Kelas II M² 230,350.00
8 SNI 3434:2008.6.20 1.00 M² Pekerjaan Memasang Rangka Langit-Langit (60 x 60) cm, Kayu Kelas II M² 254,900.00
NO. NOMOR ANALISA JENIS PEKERJAAN SATUAN HARGA SATUAN
( Rp )
1 2 3 4 5
8 SNI 3434:2008.6.21 1.00 M' Pekerjaan Memasang Listplank Ukuran (3 x 20) cm, Kayu Kelas III M' 132,700.00
9 SNI 3434:2008.6.23 1.00 M² Pekerjaan Memasang Rangka Dinding Pemisah (60 x 120) cm Kayu Kelas II M² 408,360.00
10 SNI 3434:2008.6.24 1.00 M² Pekerjaan Memasang Dinding Pemisah Triplek rangkap, rangka kayu kelas II M² 494,600.00

VII. RSNI-T-13-2002 DAN Tata Cara Perhitungan Harga Satuan Pekerjaan Beton untuk Konstruksi Bangunan Gedung dan Perumahan
SNI 7394:2008
1 SNI 7394:2008.6.4 1.00 M³ Pek Membuat Lantai Kerja Beton Mutu (K-100) - Setara Campuran ( 1 Semen : 3,5 PP : 4 Kr ) M³ 1,027,365.00
2 SNI 7394:2008.6.5 1.00 M³ Pek Beton Mutu f'c=14,5 Mpa (K-175) Setara Campuran ( 1 Semen : 2 PP : 3 Kr ) M³ 1,178,623.00
3 SNI 7394:2008.6.17 1.00 Kg Pekerjaan Pembesian dengan besi polos atau besi ulir Kg 31,252.00
4 SNI 7394:2008.6.28a 1.00 M3 Pekerjaan Membuat Pondasi Beton Bertulang ( 165 Kg Besi + Bekisting ) Uk 1,2 x 1,2 m M3 6,765,078.00
2 SNI 7394:2008.6.29a 1.00 M3 Pekerjaan Membuat Sloof Beton Bertulang ( 100 Kg Besi + Bekisting ) M3 4,949,608.00
3 SNI 7394:2008.6.30a 1.00 M3 Pekerjaan Membuat Kolom Beton Bertulang ( 100 Kg Besi + Bekisting ) M3 6,450,988.00
4 SNI 7394:2008.6.31a 1.00 M3 Pekerjaan Membuat Balok Beton Bertulang ( 100 Kg Besi + Bekisting ) M3 6,036,888.00
5 SNI 7394:2008.6.32a 1.00 M3 Pekerjaan Membuat Plat Beton Bertulang ( 140 Kg Besi + Bekisting )untuk plat Lantai M3 7,534,778.00
6 SNI 7394:2008.6.35 1.00 M' Pekerjaan Membuat Kolom Praktis Beton Bertulang (11 x 11) cm M' 119,578.00
7 SNI 7394:2008.6.36 1.00 M' Pekerjaan Membuat Ring Balok Beton Bertulang (10 x 15) cm M' 157,229.00

VIII. SNI XII (2002) Tata Cara Perhitungan Harga Satuan Pekerjaan Besi dan Alumunium untuk Konstruksi Bangunan Gedung dan Perumahan

1 XII.18 (SNI-2008) 1.00 M² Memasang talang datar / jural seng bjls 28 lebar 90 cm M² 80,795.00

IX. SNI 7395:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Penutup Lantai dan Dinding untuk Konstruksi Bangunan Gedung dan Perumahan

1 SNI 7395:2008.6.35 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (30 x 30) cm M² 133,744.00
2 SNI 7395:2008.6.35a 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (40 x 40) cm M² 133,744.00
3 SNI 7395:2008.6.36 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (20 x 20) cm M² 134,664.00
4 SNI 7395:2008.6.39 1.00 M' Pekerjaan Memasang Plint Keramik Ukuran (10 x 20) cm M' 21,390.00
5 SNI 7395:2008.6.46 1.00 M² Pekerjaan Memasang Lantai Parquet Kayu M² #VALUE!
5 SNI 7395:2008.6.54 1.00 M² Pekerjaan Memasang Dinding Keramik Ukuran (20 x 25) cm M² 154,527.00

X. SNI 2839:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Langit-Langit untuk Konstruksi Bangunan Gedung dan Perumahan
1 SNI 2839:2008.6.1 1.00 M² Pekerjaan Memasang Langit-Langit Asbes Semen, tebal 4 mm, 5 mm, dan 6 mm M² #VALUE!
2 SNI 2839:2008.6.5 1.00 M² Pekerjaan Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 3 mm, 4 mm, dan 6 M² 58,900.00
mm
3 SNI 2839:2008.6.7 1.00 M² Pekerjaan Memasang Langit-Langit Gypsum Board Ukuran (1200 x 2400 x 9) mm M² 335,460.00
4 SNI 2839:2008.6.8 1.00 M' Pekerjaan Memasang List Plafond Gypsum Profil M' #VALUE!
5 SNI 2839:2008.6.10 1.00 M' Pekerjaan Memasang List Langit-Langit Kayu Profil M' #VALUE!

XI. SNI XIV 2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Pengecatan dan Finishing Dinding untuk Bangunan Rumah dan Gedung
1 XIV.3 (SNI-2002) 1.00 M² Pengecatan bidang kayu lama M² 39,080.00
2 XIV.4 (SNI-2002) 1.00 M² Pengecatan bidang kayu baru ( 1 lapis Plamir) 1 lapis Cat Dasar dan 2 lapis cat penutup M² 68,730.00
3 XIV.7 (SNI-2002) 1.00 M² Pelaburan Bidang kayu vernis M² 42,820.00
3 XIV.8 (SNI-2002) 1.00 M² Pengecetan Tembok Baru ( 1 lapis plamir, 1 lapis cat dasar dan 2 lapis cat penutup) M² 31,401.00
4 XIV.9 (SNI-2002) 1.00 M² Pengecetan Tembok Lama ( 1 lapis plamir, 1 lapis cat dasar dan 2 lapis cat penutup) M² 27,117.00
5 XIV.10 (SNI-2002) 1.00 M² Pekerjaan Melapis dengan Cat Meni pada Permukaan Baja M² 20,980.00
6 XIV.11 (SNI-2002) 1.00 M² Pekerjaan Mengecat Penutup 2 Lapis Pada Permukaan Baja Secara Manual M² 47,960.00
NO. NOMOR ANALISA JENIS PEKERJAAN SATUAN HARGA SATUAN
( Rp )
1 2 3 4 5

XII. RSNI T-15-2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
1 RSNI T-15-2002:6.1 1.00 Bh Pekerjaan Memasang 1 Bh Closed Duduk/ Monoblok Bh 390,050.00
1 RSNI T-15-2002:6.2 1.00 Bh Pekerjaan Memasang 1 Bh Closed Jongkok Porselen Bh #VALUE!
2 RSNI T-15-2002:6.4 1.00 Bh Pekerjaan Memasang 1 Bh Urinoir Bh 225,532.00
3 RSNI T-15-2002:6.5 1.00 Bh Pekerjaan Memasang 1 Bh Wastafel Bh 308,032.00
4 RSNI T-15-2002:6.14 1.00 M Pekerjaan Memasang 1 M Pipa Beton Ø 15 cm - 20 cm M #VALUE!
5 RSNI T-15-2002:6.15 1.00 M Pekerjaan Memasang 1 M Pipa Beton Ø 30 cm - 100 cm M #VALUE!
6 RSNI T-15-2002:6.16 1.00 Bh Pekerjaan Memasang 1 Bh Bak Kontrol Pas. Batu Bata Uk. 30 cm x 30 cm tinggi 50 cm Bh 635,766.00
2 RSNI T-15-2002 : 6.25 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø ½" M 64,786.00
3 RSNI T-15-2002 : 6.26 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø ¾" M 88,036.00
4 RSNI T-15-2002 : 6.27 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 1" M 95,786.00
5 RSNI T-15-2002 : 6.28 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 1½" M 134,536.00
6 RSNI T-15-2002 : 6.29 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 2" M 170,804.00
5 RSNI T-15-2002 : 6.31 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 3" M 351,937.00
6 RSNI T-15-2002 : 6.32 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 4" M 41,937.00
7 RSNI T-15-2002 : 6.35 1.00 Bh Pekerjaan Memasang 1 Bh Kran Air Ø ¾ atau ½ Bh #VALUE!
8 RSNI T-15-2002 : 6.36 1.00 Bh Pekerjaan Memasang 1 Bh Floor Drain Bh 12,700.00

XIII. NI XI 2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Kunci, Alat Gantungan dan Kaca untuk Bangunan Rumah dan Gedung
1 XI.2 (SNI-2002) 1.00 bh Pasang kunci tanam biasa bh #VALUE!
2 XI.5 (SNI-2002) 1.00 bh Pasang engsel pintu bh #VALUE!
3 XI.6 (SNI-2002) 1.00 bh Pasang engsel jendela bh 20,265.00
4 XI.7 (SNI-2002) 1.00 bh Pasang kait angin bh #VALUE!
5 XI.8 (SNI-2002) 1.00 bh Pasang Kunci Selot bh 27,020.00
6 Pt T.30-2000-C.I.12 1.00 bh Pasang pegangan pintu / door holder bh #VALUE!
7 Pt T.30-2000-C.I.13 1.00 bh Pasang rel pintu dorong bh #VALUE!
7 Pt T.30-2000-C.II.1 1.00 m2 Pasang kaca, tebal 3 mm m2 #VALUE!

XV. TAKSIR
1 @ Anl. Taksir 1.00 m2 Pasang conblock tipe segi-enam warna 6 cm m2 #VALUE!
2 @ Anl. Taksir 1.00 m2 Pasang paving block persegi m2 #VALUE!

Dihitung2 1 kg Memotong dan mengelas besi profil WF kg 40,585.00


DAFTAR UPAH DAN BAHAN
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

Volume Hrg.Material
No. Bahan / Material Satuan Sampai ke Keterangan
Lokasi Pekerjaan
1 2 3 4 5
A. UPAH
1 Mandor Lapangan OH 120,000
2 Kepala Tukang OH 145,000
3 Tukang OH 105,000
4 Pekerja OH 70,000

B. BATU-BATUAN / TANAH
1 Batu bata Buah 800 ###
2 Batu belah 10 - 15 cm m3 513,206 Query Hutagodang
###
3 Batu kali bulat m3 553,206 Query Hutagodang
###
4 Batu padas m3 413,206 Query Hutagodang
###
5 Kerikil tidak tersaring m3 503,206 Query Hutagodang
###
6 Sirtu m3 463,206 Query Hutagodang
###
7 Pasir pasangan / Beton m3 313,206 Query Hutagodang
###
8 Pasir urug m3 293,206 Query Hutagodang
###
9 Tanah timbun m3 193,206 Query Hutagodang
###

C. BESI / BAJA
1 Besi tulangan beton kg 28,000 ###
2 Kawat beton kg 26,000 ###
3 Kawat nyamuk m ###
4 Paku 0,5" - 1" kg 20,000.00 ###
3 Paku 2" - 5" kg 20,000 ###
4 Paku Seng RRT kg 19,000 ###
5 Paku Sekrup kg 25,000.00 ###
6 Kawat Las kg dsdg ###
Baja profil kg 33,000.00
Besi plat kg 33,000.00
Rolling door alluminium m2 300,000.00
Profil alluminium m` 75,000.00
Rangka Metal Sud (MS 75) m` 15,000.00
Rangka U Runner (UR 76) m` 15,000.00
Skrup fixer bh 2,000.00

D. CAT
1 Cat dasar kg 50,000 ###
2 Cat kilat / Cat minyak kg 70,000 ###
3 Cat menie kayu kg 120,000 ###
4 Cat Tembok kg 60,000 ###
Kertas pasir Lbr 3,000.00
5 Plamir kg 10,000.00 ###
Tepung gypsum kg 27,000.00
6 Thiner kg 20,000.00 ###
7 Kuas 5" Bh 35,000 ###
Kuas 4" 30,000 ###
Kuas 3" 20,000
8 Kertas pasir Lbr 7,000
9 Dempul Kayu kg 10,000.00 ###

Sealant tube 20,000.00

E. SEMEN
1 Semen PC kg 1,400.00 56000
###
2 Semen Putih kg 3,000.00 ###
3 Semen Warna kg 3,000.00 ###
###
6 Parquet kayu m2 a
5 Bonbon Keramik 10 cm / m' m' a
7 Conblock warna Bh a ###
8 Paving Block persegi Bh a ###
Volume Hrg.Material
No. Bahan / Material Satuan Sampai ke Keterangan
Lokasi Pekerjaan
1 2 3 4 5
###
2 Kayu kuat kelas III m3 9,000,000.00 ###
3 Kayu kuat kelas II m3 12,000,000.00 ###
5 Tripleks 4 mm Lembar 100,000.00
6 Tripleks 6 mm Lembar 130,000
4 Tripleks 9 mm Lembar 175,000 ###
Tripleks 12 mm Lembar 200,000
5 Kayu Bulat dia. 5 cm Batang 30,000.00 ###
6 Asbes Lembar a ###
###
H. KONSTRUKSI ATAP ###
1 Kuda-kuda & rangka baja system truss (Upah+bahan) m2 a ###
2 Atap Seng gelombang 9 kaki Lbr 50,000.00 ###
3 Atap Zincalume teb. 0,3 mm Kaki 15,000.00
4 Atap Genteng Metal m2 a
4 Rabung Zincalume m' 25,000 ###
5 Seng Plat m' 15,000.00 ###
###
I. PLAFOND / PARTISI ###
1 Rangka furing plafond (upah+bahan) m2 a ###
2 Papan Gypsum Lbr a
Papan GRC Lbe 120,000.00
Volume Hrg.Material
No. Bahan / Material Satuan Sampai ke Keterangan
Lokasi Pekerjaan
1 2 3 4 5
3 Tepung Gypsum kg a
4 Lem Kayu Ltr a ###
5 Lat Asbes Btg a ###
1 Pipa PVC Ø 1/2" m' 35,000 ###
2 Pipa PVC Ø 3/4" m' 50,000 ###
3 Pipa PVC Ø 1" m' 55,000
4 Pipa PVC Ø 1,5" m' 80,000 ###
5 Pipa PVC Ø 2" m' 100,000 ###
3 Pipa PVC Ø 3" m' 200,000 ###
8 Closet Jongkok Unit a ###
12 Bak Fiber Unit a
9 Pintu PVC Unit a
11 Riol Dia. 20 cm Bh a ###
12 Riol Dia. 30 cm Bh a ###
###
1 Minyak Pelumas Ltr a ###
1 Minyak Bekisting Ltr 25,000.00 ###
2 Kunci Tanam Bh a ###
4 Engsel 5" Bh a ###
4 Pegangan Jendela Bh a ###
5 Hak Angin Bh a ###
7 Seltape Bh a ###
7 Kaca Polos / Reyben m2 a ###
8 Isntalasi Titik Lampu Titik 130,000.00 ###
10 Lampu SL 40 Watt Unit 50,000.00
Lampu mercury Unit 120,000.00
11 Saklar Tunggal Unit 5,000.00
12 Saklar Seri Unit 6,000.00
14 Saklar Triple Unit 7,000.00
13 Stop Kontak Unit 6,000.00

Aceton, Oxygen unit 275,000.00


Mesin las Jam 40,000.00
Kawat las Kg 25,000.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan

RSNI T-12-2002:6.4 1.00 M` Pekerjaan Pengukuran dan Pemasangan Bowplank


0.0120 M³ Kayu 5/7 Kelas IV @ Rp. - -
0.0200 Kg Paku Biasa @ Rp. 20,000.00 400.00
0.0070 M³ Kayu Papan 3/20 Kelas IV @ Rp. - -
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Kayu @ Rp. 112,000.00 11,200.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
JUMLAH 20,800.00 400.00 21,200.00
DIBULATKAN 20,800.00 400.00 21,200.00
RSNI T-12-2002:6.8 1.00 M² Pekerjaan Membersihkan Lapangan dan Peralatan
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
JUMLAH 8,100.00 - 8,100.00
DIBULATKAN 8,100.00 - 8,100.00
RSNI T-12-2002:6.14 1.00 M3 Pekerjaan Membongkar Dinding Tembok Batu Bata Merah
0.3330 org Mandor @ Rp. 120,000.00 39,960.00
6.6700 org Pekerja @ Rp. 75,000.00 500,250.00
JUMLAH 540,210.00 - 540,210.00
DIBULATKAN 540,210.00 - 540,210.00

SNI 2835:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Tanah Untuk Bangunan Gedung dan Perumahan

RSNI T.12.2002.6.14 1.00 M³ Pekerjaan Membongkar Dinding Tembok Batu Bata Merah
0.3330 org Mandor @ Rp. 120,000.00 39,960.00
6.6670 org Pekerja @ Rp. 75,000.00 500,025.00
JUMLAH 539,985.00 - 539,985.00
DIBULATKAN 539,985.00 - 539,985.00
SNI 2835:2008.6.1 1.00 M³ Pekerjaan Galian Tanah Biasa sedalam 1 meter
0.0250 org Mandor @ Rp. 120,000.00 3,000.00
0.7500 org Pekerja @ Rp. 75,000.00 56,250.00
JUMLAH 59,250.00 - 59,250.00
DIBULATKAN 59,250.00 - 59,250.00
SNI 2835:2008.6.9a 1.00 M³ Pekerjaan Mengurug kembali 1 m³ bekas galian
Mengurug kembali 1 m³ bekas galian dihitung dari 1/3 kali dari indeks pekerjaan galian
1/3 x Galian Tanah Biasa sedalam 1 @ Rp. 19,750.00 19,750.00
JUMLAH 19,750.00 - 19,750.00
DIBULATKAN 19,750.00 - 19,750.00
SNI 2835:2008.6.11 1.00 M³ Pekerjaan Mengurug 1 m³ pasir urug
1.2000 M³ Pasir Urug @ Rp. 293,206.00 351,847.20
0.0100 org Mandor @ Rp. 120,000.00 1,200.00
0.3000 org Pekerja @ Rp. 75,000.00 22,500.00
JUMLAH 23,700.00 351,847.20 375,547.20
DIBULATKAN 23,700.00 351,847.00 375,547.00
SNI 2835:2008.6.15a 1.00 M³ Pek. Mengurug 1 m3 Tanah Timbun
0.0250 org Mandor @ Rp. 120,000.00 3,000.00
0.2500 org Pekerja @ Rp. 75,000.00 18,750.00
1.2000 M³ Tanah Timbun @ Rp. 193,206.00 - 231,847.20
JUMLAH 21,750.00 231,847.20 253,597.20
DIBULATKAN 21,750.00 231,847.00 253,597.00
SNI 2836:2008.6.2 1.00 M³ Pekerjaan Memasang Pondasi Batu Kali Camp. 1 Semen : 4 Pasir Pasang
1.2000 M³ Batu Kali Bulat @ Rp. 553,206.00 663,847.20
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
163.0000 Kg Semen @ Rp. 1,400.00 228,200.00
0.5200 M³ Pasir Pasang @ Rp. 313,206.00 162,867.12
0.0750 org Mandor @ Rp. 120,000.00 9,000.00
0.0750 org Kepala Tukang @ Rp. 150,000.00 11,250.00
0.7500 org Tukang Batu @ Rp. 112,000.00 84,000.00
1.5000 org Pekerja @ Rp. 75,000.00 112,500.00
JUMLAH 216,750.00 1,054,914.32 1,271,664.32
DIBULATKAN 216,750.00 1,054,914.00 1,271,664.00
SNI 2836:2008.6.9 1.00 M³ Pekerjaan Memasang Batu Kosong (anstamping)
1.2000 M³ Batu Kali Bulat @ Rp. 553,206.00 663,847.20
0.4320 M³ Pasir Urug @ Rp. 293,206.00 126,664.99
0.0390 org Mandor @ Rp. 120,000.00 4,680.00
0.0390 org Kepala Tukang @ Rp. 150,000.00 5,850.00
0.3900 org Tukang Batu @ Rp. 112,000.00 43,680.00
0.7800 org Pekerja @ Rp. 75,000.00 58,500.00
JUMLAH 112,710.00 790,512.19 903,222.19
DIBULATKAN 112,710.00 790,512.00 903,222.00
SNI 2836:2008.6.10 1.00 M³ Pekerjaan Memasang Pondasi Siklop, 60% beton camp. 1 : 2 : 3 dan 40% Batu Kali
0.4800 M³ Batu Kali Bulat @ Rp. 553,206.00 265,538.88
194.0000 Kg Semen @ Rp. 1,400.00 271,600.00
0.3120 M³ Pasir Beton @ Rp. 313,206.00 97,720.27
0.4680 M³ Kerikil @ Rp. 503,206.00 235,500.41
126.0000 Kg Besi Beton @ Rp. 28,000.00 3,528,000.00
1.8000 Kg Kawat Beton @ Rp. 26,000.00 46,800.00
0.1700 org Mandor @ Rp. 120,000.00 20,400.00
0.0850 org Kepala Tukang @ Rp. 150,000.00 12,750.00
0.8500 org Tukang Batu @ Rp. 112,000.00 95,200.00
3.4000 org Pekerja @ Rp. 75,000.00 255,000.00
JUMLAH 383,350.00 4,445,159.56 4,828,509.56
DIBULATKAN 383,350.00 4,445,159.00 4,828,509.00

SNI 6897:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Dinding untuk Konstruksi Bangunan Gedung dan Perumahan

SNI 6897:2008.6.1 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal 1 bata, camp. Spesi 1 Semen : 2 Pasir Pasang
140.0000 Bh Batu bata @ Rp. 800.00 112,000.00
43.5000 Kg Semen @ Rp. 1,400.00 60,900.00
0.0800 M³ Pasir Pasang @ Rp. 313,206.00 25,056.48
0.0300 org Mandor @ Rp. 120,000.00 3,600.00
0.0200 org Kepala Tukang @ Rp. 150,000.00 3,000.00
0.2000 org Tukang Batu @ Rp. 112,000.00 22,400.00
0.6000 org Pekerja @ Rp. 75,000.00 45,000.00
JUMLAH 74,000.00 197,956.48 271,956.48
DIBULATKAN 74,000.00 197,956.00 271,956.00
SNI 6897:2008.6.3 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal 1 bata, camp. Spesi 1 Semen : 4 Pasir Pasang
140.0000 Bh Batu bata @ Rp. 800.00 112,000.00
26.5500 Kg Semen @ Rp. 1,400.00 37,170.00
0.0930 M³ Pasir Pasang @ Rp. 313,206.00 29,128.16
0.0300 org Mandor @ Rp. 120,000.00 3,600.00
0.0200 org Kepala Tukang @ Rp. 150,000.00 3,000.00
0.2000 org Tukang Batu @ Rp. 112,000.00 22,400.00
0.6000 org Pekerja @ Rp. 75,000.00 45,000.00
JUMLAH 74,000.00 178,298.16 252,298.16
DIBULATKAN 74,000.00 178,298.00 252,298.00
SNI 6897:2008.6.7 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal ½ bata, camp. Spesi 1 Semen : 2 Pasir Pasang
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
70.0000 Bh Batu bata @ Rp. 800.00 56,000.00
18.9500 Kg Semen @ Rp. 1,400.00 26,530.00
0.0380 M³ Pasir Pasang @ Rp. 313,206.00 11,901.83
0.0150 org Mandor @ Rp. 120,000.00 1,800.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Batu @ Rp. 112,000.00 11,200.00
0.3000 org Pekerja @ Rp. 75,000.00 22,500.00
JUMLAH 37,000.00 94,431.83 131,431.83
DIBULATKAN 37,000.00 94,431.00 131,431.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 6897:2008.6.9 1.00 M² Pekerjaan Memasang dinding batu bata ukuran (5 x 11 x 22) cm tebal ½ bata, camp. Spesi 1 Semen : 4 Pasir Pasang
70.0000 Bh Batu bata @ Rp. 800.00 56,000.00
11.5000 Kg Semen @ Rp. 1,400.00 16,100.00
0.0430 M³ Pasir Pasang @ Rp. 313,206.00 13,467.86
0.0150 org Mandor @ Rp. 120,000.00 1,800.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Batu @ Rp. 112,000.00 11,200.00
0.3000 org Pekerja @ Rp. 75,000.00 22,500.00
JUMLAH 37,000.00 85,567.86 122,567.86
DIBULATKAN 37,000.00 85,567.00 122,567.00
SNI 2837:2008.6.4 1.00 M² Pekerjaan Membuat Plesteran 1 Semen : 4 PP, tebal 15 mm
6.2400 Kg Semen @ Rp. 1,400.00 8,736.00
0.0240 M³ Pasir Pasang @ Rp. 313,206.00 7,516.94
0.0150 org Mandor @ Rp. 120,000.00 1,800.00
0.0150 org Kepala Tukang @ Rp. 150,000.00 2,250.00
0.1500 org Tukang Batu @ Rp. 112,000.00 16,800.00
0.3000 org Pekerja @ Rp. 75,000.00 22,500.00
JUMLAH 43,350.00 16,252.94 59,602.94
DIBULATKAN 43,350.00 16,252.00 59,602.00
SNI 2837:2008.6.27 1.00 M² Pekerjaan Membuat Acian
3.2500 Kg Semen @ Rp. 1,400.00 4,550.00
0.0100 org Mandor @ Rp. 120,000.00 1,200.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Batu @ Rp. 112,000.00 11,200.00
0.2000 org Pekerja @ Rp. 75,000.00 15,000.00
JUMLAH 28,900.00 4,550.00 33,450.00
DIBULATKAN 28,900.00 4,550.00 33,450.00

SNI 03-3436-2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Penutup Atap untuk Konstruksi Bangunan Gedung dan Perumahan

Taksir 1.00 M² Pekerjaan Memasang atap genteng metal zincalume type prima roof
1.0200 M² Genteng metal @ Rp. a #VALUE!
0.2000 kg Paku anti karat @ Rp. 19,000.00 3,800.00
0.0060 org Mandor @ Rp. 120,000.00 720.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Kayu @ Rp. 112,000.00 6,720.00
0.1200 org Pekerja @ Rp. 75,000.00 9,000.00
JUMLAH 17,340.00 #VALUE! #VALUE!
DIBULATKAN 17,340.00 #VALUE! #VALUE!
Taksir 1.00 M² Pekerjaan Memasang atap zincalume
5.0400 Kaki Atap Zincalume @ Rp. 15,000.00 75,600.00
0.0200 kg Paku anti karat @ Rp. 19,000.00 380.00
0.0060 org Mandor @ Rp. 120,000.00 720.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Kayu @ Rp. 112,000.00 6,720.00
0.1200 org Pekerja @ Rp. 75,000.00 9,000.00
JUMLAH 17,340.00 75,980.00 93,320.00
DIBULATKAN 17,340.00 75,980.00 93,320.00
SNI 03-3436-2002.6.9 1.00 M² Pekerjaan Memasang Atap Seng Gelombang BJLS
0.7000 Lbr Seng Gelombang BJLS @ Rp. 50,000.00 35,000.00
0.0200 kg Paku 1/2" - 1 " @ Rp. 20,000.00 400.00
0.0060 org Mandor @ Rp. 120,000.00 720.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Kayu @ Rp. 112,000.00 6,720.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
0.1200 org Pekerja @ Rp. 75,000.00 9,000.00
JUMLAH 17,340.00 35,400.00 52,740.00
DIBULATKAN 17,340.00 35,400.00 52,740.00
Taksir 1.00 M' Pekerjaan Memasang Rabung genteng metal zincalume type prima roof
1.1000 Lbr Rabung Genteng metal @ Rp. - -
0.0500 kg Paku anti karat @ Rp. 19,000.00 950.00
0.0025 org Mandor @ Rp. 120,000.00 300.00
0.0050 org Kepala Tukang @ Rp. 150,000.00 750.00
0.0500 org Tukang Kayu @ Rp. 112,000.00 5,600.00
0.0500 org Pekerja @ Rp. 75,000.00 3,750.00
JUMLAH 10,400.00 950.00 11,350.00
DIBULATKAN 10,400.00 950.00 11,350.00
Taksir 1.00 M' Pekerjaan Memasang Rabung atap zincalume
1.1000 Lbr Rabung Zincalume @ Rp. 25,000.00 27,500.00
0.0500 kg Paku anti karat @ Rp. 19,000.00 950.00
0.0025 org Mandor @ Rp. 120,000.00 300.00
0.0050 org Kepala Tukang @ Rp. 150,000.00 750.00
0.0500 org Tukang Kayu @ Rp. 112,000.00 5,600.00
0.0500 org Pekerja @ Rp. 75,000.00 3,750.00
JUMLAH 10,400.00 28,450.00 38,850.00
DIBULATKAN 10,400.00 28,450.00 38,850.00

SNI 3434:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Kayu untuk Konstruksi Bangunan Gedung dan Perumahan

SNI 3434:2008.6.1 1.00 M³ Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas III
1.2000 M³ Balok Kayu Kelas II @ Rp. 9,000,000.00 10,800,000.00
1.2500 Kg Paku 10 cm @ Rp. 20,000.00 25,000.00
1.0000 Kg Lem Kayu @ Rp. a #VALUE!
0.3000 org Mandor @ Rp. 120,000.00 36,000.00
1.8000 org Kepala Tukang @ Rp. 150,000.00 270,000.00
18.0000 org Tukang Kayu @ Rp. 112,000.00 2,016,000.00
6.0000 org Pekerja @ Rp. 75,000.00 450,000.00
JUMLAH 2,772,000.00 #VALUE! #VALUE!
DIBULATKAN 2,772,000.00 #VALUE! #VALUE!
SNI 3434:2008.6.5 1.00 M² Membuat dan Memasang Daun Pintu Panel, Kayu Kelas III
0.0400 M³ Papan Kayu Kelas II @ Rp. 9,000,000.00 360,000.00
0.5000 Kg Lem Kayu @ Rp. a #VALUE!
0.0500 org Mandor @ Rp. 120,000.00 6,000.00
0.3000 org Kepala Tukang @ Rp. 150,000.00 45,000.00
3.0000 org Tukang Kayu @ Rp. 112,000.00 336,000.00
1.0000 org Pekerja @ Rp. 75,000.00 75,000.00
JUMLAH (TERMASUK PPN 10%) 462,000.00 #VALUE! #VALUE!
DIBULATKAN 462,000.00 #VALUE! #VALUE!
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 3434:2008.6.6 1.00 M² Pekerjaan Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas III
0.0240 M³ Papan Kayu Kelas II @ Rp. 9,000,000.00 216,000.00
0.3000 Kg Lem Kayu @ Rp. a #VALUE!
0.8000 M2 Kaca 5 mm @ Rp. a #VALUE!
0.0400 org Mandor @ Rp. 120,000.00 4,800.00
0.2400 org Kepala Tukang @ Rp. 150,000.00 36,000.00
2.4000 org Tukang Kayu @ Rp. 112,000.00 268,800.00
0.8000 org Pekerja @ Rp. 75,000.00 60,000.00
JUMLAH 369,600.00 #VALUE! #VALUE!
DIBULATKAN 369,600.00 #VALUE! #VALUE!
SNI 3434:2008.6.10 1.00 M² Pekerjaan Memasang Jalusi Kusen, Kayu Kelas III
0.0600 M³ Papan Kayu Kelas II @ Rp. 9,000,000.00 540,000.00
0.1500 Kg Paku 1 cm - 2,5 cm @ Rp. 20,000.00 3,000.00
0.3350 org Mandor @ Rp. 120,000.00 40,200.00
0.2000 org Kepala Tukang @ Rp. 150,000.00 30,000.00
2.0000 org Tukang Kayu @ Rp. 112,000.00 224,000.00
0.6700 org Pekerja @ Rp. 75,000.00 50,250.00
JUMLAH 344,450.00 543,000.00 887,450.00
DIBULATKAN 344,450.00 543,000.00 887,450.00
SNI 3434:2008.6.13 1.00 M³ Pekerjaan Memasang Konstruksi Kuda-Kuda Konvensional, Kayu Kelas II bentang 6 meter
1.1000 M³ Balok Kayu Kelas II @ Rp. 12,000,000.00 13,200,000.00
15.0000 Kg Besi strip tebal 5 mm @ Rp. - -
5.6000 Kg Paku 12 cm @ Rp. 20,000.00 112,000.00
0.2000 org Mandor @ Rp. 120,000.00 24,000.00
1.2000 org Kepala Tukang @ Rp. 150,000.00 180,000.00
12.0000 org Tukang Kayu @ Rp. 112,000.00 1,344,000.00
4.0000 org Pekerja @ Rp. 75,000.00 300,000.00
JUMLAH 1,848,000.00 13,312,000.00 15,160,000.00
DIBULATKAN 1,848,000.00 13,312,000.00 15,160,000.00
SNI 3434:2008.6.14 1.00 M³ Pekerjaan Memasang Konstruksi Kuda-Kuda Ekspose, Kayu Kelas II
1.2000 M³ Balok Kayu Kelas II @ Rp. 12,000,000.00 14,400,000.00
15.0000 Kg Besi strip tebal 5 mm @ Rp. - -
5.6000 Kg Paku 12 cm @ Rp. 20,000.00 112,000.00
0.3350 org Mandor @ Rp. 120,000.00 40,200.00
2.0100 org Kepala Tukang @ Rp. 150,000.00 301,500.00
20.1000 org Tukang Kayu @ Rp. 112,000.00 2,251,200.00
6.7000 org Pekerja @ Rp. 75,000.00 502,500.00
JUMLAH 3,095,400.00 14,512,000.00 17,607,400.00
DIBULATKAN 3,095,400.00 14,512,000.00 17,607,400.00
SNI 3434:2008.6.15 1.00 M³ Pekerjaan Memasang Konstruksi Gording, Kayu Kelas II
1.1000 M³ Balok Kayu Kelas II @ Rp. 12,000,000.00 13,200,000.00
15.0000 Kg Besi strip tebal 5 mm @ Rp. - -
3.0000 Kg Paku 12 cm @ Rp. 20,000.00 60,000.00
0.1200 org Mandor @ Rp. 120,000.00 14,400.00
0.7200 org Kepala Tukang @ Rp. 150,000.00 108,000.00
7.2000 org Tukang Kayu @ Rp. 112,000.00 806,400.00
2.4000 org Pekerja @ Rp. 75,000.00 180,000.00
JUMLAH 1,108,800.00 13,260,000.00 14,368,800.00
DIBULATKAN 1,108,800.00 13,260,000.00 14,368,800.00
SNI 3434:2008.6.16 1.00 M² Pekerjaan Memasang Rangka Atap Genteng Keramik, Kayu Kelas II
0.0140 M³ Kaso-kaso (5 x 7) cm Kelas II @ Rp. 12,000,000.00 168,000.00
0.0036 M³ Reng (2 x 3) cm Kelas III @ Rp. 9,000,000.00 32,400.00
0.2500 Kg Paku 5 cm dan 10 cm @ Rp. 20,000.00 5,000.00
0.0050 org Mandor @ Rp. 120,000.00 600.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Kayu @ Rp. 112,000.00 11,200.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
JUMLAH 20,800.00 205,400.00 226,200.00
DIBULATKAN 20,800.00 205,400.00 226,200.00
SNI 3434:2008.6.19a 1.00 M² Pekerjaan Memasang Rangka Langit-Langit (100 x 100) cm, Kayu Kelas II
0.0140 M³ Kaso-kaso (5 x 7) cm Kelas II @ Rp. 12,000,000.00 168,000.00
0.2000 Kg Paku 7 cm - 10 cm @ Rp. 20,000.00 4,000.00
0.0750 org Mandor @ Rp. 120,000.00 9,000.00
0.0300 org Kepala Tukang @ Rp. 150,000.00 4,500.00
0.3000 org Tukang Kayu @ Rp. 112,000.00 33,600.00
0.1500 org Pekerja @ Rp. 75,000.00 11,250.00
JUMLAH 58,350.00 172,000.00 230,350.00
DIBULATKAN 58,350.00 172,000.00 230,350.00
SNI 3434:2008.6.20 1.00 M² Pekerjaan Memasang Rangka Langit-Langit (60 x 60) cm, Kayu Kelas II
0.0163 M³ Kaso-kaso (5 x 7) cm Kelas II @ Rp. 12,000,000.00 195,600.00
0.2500 Kg Paku 7 cm - 10 cm @ Rp. 20,000.00 5,000.00
0.0100 org Mandor @ Rp. 120,000.00 1,200.00
0.0300 org Kepala Tukang @ Rp. 150,000.00 4,500.00
0.3000 org Tukang Kayu @ Rp. 112,000.00 33,600.00
0.2000 org Pekerja @ Rp. 75,000.00 15,000.00
JUMLAH 54,300.00 200,600.00 254,900.00
DIBULATKAN 54,300.00 200,600.00 254,900.00
SNI 3434:2008.6.21 1.00 M' Pekerjaan Memasang Listplank Ukuran (3 x 20) cm, Kayu Kelas III
0.0108 M³ Papan Kayu Kelas II @ Rp. 9,000,000.00 97,200.00
0.1000 Kg Paku 5 cm dan 7 cm @ Rp. 20,000.00 2,000.00
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.0200 org Kepala Tukang @ Rp. 150,000.00 3,000.00
0.2000 org Tukang Kayu @ Rp. 112,000.00 22,400.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
JUMLAH 33,500.00 99,200.00 132,700.00
DIBULATKAN 33,500.00 99,200.00 132,700.00
SNI 7394:2008.6.4 1.00 M³ Pek Membuat Lantai Kerja Beton Mutu (K-100) - Setara Campuran ( 1 Semen : 3,5 PP : 4 Kr )
230.0000 Kg Semen @ Rp. 1,400.00 322,000.00
0.6380 M³ Pasir beton @ Rp. 313,206.00 199,825.43
0.7610 M³ Kerikil beton @ Rp. 503,206.00 382,939.77
200.0000 Ltr Air
0.0600 org Mandor @ Rp. 120,000.00 7,200.00
0.0200 org Kepala Tukang @ Rp. 150,000.00 3,000.00
0.2000 org Tukang Batu @ Rp. 112,000.00 22,400.00
1.2000 org Pekerja @ Rp. 75,000.00 90,000.00
JUMLAH 122,600.00 904,765.19 1,027,365.19
DIBULATKAN 122,600.00 904,765.00 1,027,365.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 7394:2008.6.5 1.00 M³ Pek Beton Mutu f'c=14,5 Mpa (K-175) Setara Campuran ( 1 Semen : 2 PP : 3 Kr )
326.0000 Kg Semen @ Rp. 1,400.00 456,400.00
0.5430 M³ Pasir beton @ Rp. 313,206.00 170,070.86
0.7620 M³ Kerikil beton @ Rp. 503,206.00 383,442.97
215.0000 Ltr Air
0.0830 org Mandor @ Rp. 120,000.00 9,960.00
0.0280 org Kepala Tukang @ Rp. 150,000.00 4,200.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.6500 org Pekerja @ Rp. 75,000.00 123,750.00
JUMLAH 168,710.00 1,009,913.83 1,178,623.83
DIBULATKAN 168,710.00 1,009,913.00 1,178,623.00
SNI 7394:2008.6.17 1.00 Kg Pekerjaan Pembesian dengan besi polos atau besi ulir
10.5000 Kg Besi beton (polos) @ Rp. 28,000.00 294,000.00
0.1500 Kg Kawat Beton @ Rp. 26,000.00 3,900.00
0.0040 org Mandor @ Rp. 120,000.00 480.00
0.0070 org Kepala Tukang @ Rp. 150,000.00 1,050.00
0.0700 org Tukang Besi @ Rp. 112,000.00 7,840.00
0.0700 org Pekerja @ Rp. 75,000.00 5,250.00
JUMLAH 14,620.00 297,900.00 312,520.00
PEMBESIAN 1 KG 1,462.00 29,790.00 31,252.00
DIBULATKAN 1,462.00 29,790.00 31,252.00
SNI 7394:2008.6.28a 1.00 M3 Pekerjaan Membuat Pondasi Beton Bertulang ( 165 Kg Besi + Bekisting ) Uk 1,2 x 1,2 m
0.2000 m3 Kayu Kelas IV @ Rp. - -
1.5000 kg Paku 2" - 5" @ Rp. 20,000.00 30,000.00
0.4000 liter Minyak Bekisting @ Rp. 25,000.00 10,000.00
173.2500 kg Besi tulangan beton polos @ Rp. 28,000.00 4,851,000.00
2.4750 kg Kawat Beton @ Rp. 26,000.00 64,350.00
336.0000 kg Semen PC @ Rp. 1,400.00 470,400.00
0.5400 m3 Pasir Beton @ Rp. 313,206.00 169,131.24
0.8100 m3 Batu Kerikil Tersaring @ Rp. 503,206.00 407,596.86
5.3000 org Pekerja @ Rp. 75,000.00 397,500.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.3000 org Tukang Kayu @ Rp. 112,000.00 145,600.00
1.0500 org Tukang Besi @ Rp. 112,000.00 117,600.00
0.2620 org Kepala Tukang @ Rp. 150,000.00 39,300.00
0.2650 org Mandor @ Rp. 120,000.00 31,800.00
JUMLAH 762,600.00 6,002,478.10 6,765,078.10
DIBULATKAN 762,600.00 6,002,478.00 6,765,078.00
SNI 7394:2008.6.29a 1.00 M3 Pekerjaan Membuat Sloof Beton Bertulang ( 100 Kg Besi + Bekisting )
0.2700 m3 Kayu Kelas IV @ Rp. - -
2.0000 kg Paku 2" - 5" @ Rp. 20,000.00 40,000.00
0.6000 liter Minyak Bekisting @ Rp. 25,000.00 15,000.00
105.0000 kg Besi Beton Polos @ Rp. 28,000.00 2,940,000.00
1.5000 kg Kawat Beton @ Rp. 26,000.00 39,000.00
336.0000 kg Semen PC @ Rp. 1,400.00 470,400.00
0.5400 m3 Pasir Beton @ Rp. 313,206.00 169,131.24
0.8100 m3 Kerikil beton @ Rp. 503,206.00 407,596.86
5.6500 org Pekerja @ Rp. 75,000.00 423,750.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.5600 org Tukang Kayu @ Rp. 112,000.00 174,720.00
1.4000 org Tukang Besi @ Rp. 112,000.00 156,800.00
0.3230 org Kepala Tukang @ Rp. 150,000.00 48,450.00
0.2830 org Mandor @ Rp. 120,000.00 33,960.00
JUMLAH 868,480.00 4,081,128.10 4,949,608.10
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
DIBULATKAN 868,480.00 4,081,128.00 4,949,608.00
SNI 7394:2008.6.30a 1.00 M3 Pekerjaan Membuat Kolom Beton Bertulang ( 100 Kg Besi + Bekisting )
0.4000 m3 Kayu Kelas IV @ Rp. - -
4.0000 kg Paku 2" - 5" @ Rp. 20,000.00 80,000.00
2.0000 liter Minyak Bekisting @ Rp. 25,000.00 50,000.00
105.0000 kg Besi Beton Polos @ Rp. 28,000.00 2,940,000.00
1.5000 kg Kawat Beton @ Rp. 26,000.00 39,000.00
336.0000 kg Semen PC @ Rp. 1,400.00 470,400.00
0.5400 m3 Pasir Beton @ Rp. 313,206.00 169,131.24
0.8100 m3 Kerikil beton @ Rp. 503,206.00 407,596.86
0.1500 m3 Kayu Kelas IV Balok @ Rp. - -
3.5000 lbr Triplek 9 mm @ Rp. 175,000.00 612,500.00
20.0000 btg Kayu Bulat Ø (8-10) cm, 4 m' @ Rp. 30,000.00 600,000.00
7.0500 org Pekerja @ Rp. 75,000.00 528,750.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.6500 org Tukang Kayu @ Rp. 112,000.00 184,800.00
2.1000 org Tukang Besi @ Rp. 112,000.00 235,200.00
0.4030 org Kepala Tukang @ Rp. 150,000.00 60,450.00
0.3530 org Mandor @ Rp. 120,000.00 42,360.00
JUMLAH 1,082,360.00 5,368,628.10 6,450,988.10
DIBULATKAN 1,082,360.00 5,368,628.00 6,450,988.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 7394:2008.6.31a 1.00 M3 Pekerjaan Membuat Balok Beton Bertulang ( 100 Kg Besi + Bekisting )
0.3200 m3 Kayu Kelas IV @ Rp. - -
3.2000 kg Paku 2" - 5" @ Rp. 20,000.00 64,000.00
1.6000 liter Minyak Bekisting @ Rp. 25,000.00 40,000.00
105.0000 kg Besi Beton Polos @ Rp. 28,000.00 2,940,000.00
1.5000 kg Kawat Beton @ Rp. 26,000.00 39,000.00
336.0000 kg Semen PC @ Rp. 1,400.00 470,400.00
0.5400 m3 Pasir Beton @ Rp. 313,206.00 169,131.24
0.8100 m3 Kerikil beton @ Rp. 503,206.00 407,596.86
0.1400 m3 Kayu Kelas IV Balok @ Rp. - -
2.8000 lbr Triplek 9 mm @ Rp. 175,000.00 490,000.00
16.0000 btg Kayu Bulat Ø (8-10) cm, 4 m' @ Rp. 30,000.00 480,000.00
6.3500 org Pekerja @ Rp. 75,000.00 476,250.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.6500 org Tukang Kayu @ Rp. 112,000.00 184,800.00
1.4000 org Tukang Besi @ Rp. 112,000.00 156,800.00
0.3330 org Kepala Tukang @ Rp. 150,000.00 49,950.00
0.3180 org Mandor @ Rp. 120,000.00 38,160.00
JUMLAH 936,760.00 5,100,128.10 6,036,888.10
DIBULATKAN 936,760.00 5,100,128.00 6,036,888.00
SNI 7394:2008.6.32a 1.00 M3 Pekerjaan Membuat Plat Beton Bertulang ( 140 Kg Besi + Bekisting )untuk plat Lantai
0.3200 m3 Kayu Kelas IV @ Rp. - -
3.2000 kg Paku 2" - 5" @ Rp. 20,000.00 64,000.00
1.6000 liter Minyak Bekisting @ Rp. 25,000.00 40,000.00
147.0000 kg Besi Beton Polos @ Rp. 28,000.00 4,116,000.00
2.1000 kg Kawat Beton @ Rp. 26,000.00 54,600.00
336.0000 kg Semen PC @ Rp. 1,400.00 470,400.00
0.5400 m3 Pasir Beton @ Rp. 313,206.00 169,131.24
0.8100 m3 Kerikil beton @ Rp. 503,206.00 407,596.86
0.1200 m3 Kayu Kelas IV Balok @ Rp. - -
2.8000 lbr Triplek 9 mm @ Rp. 175,000.00 490,000.00
32.0000 btg Kayu Bulat Ø (8-10) cm, 4 m' @ Rp. 30,000.00 960,000.00
5.3000 org Pekerja @ Rp. 75,000.00 397,500.00
0.2750 org Tukang Batu @ Rp. 112,000.00 30,800.00
1.3000 org Tukang Kayu @ Rp. 112,000.00 145,600.00
1.0500 org Tukang Besi @ Rp. 112,000.00 117,600.00
0.2650 org Kepala Tukang @ Rp. 150,000.00 39,750.00
0.2650 org Mandor @ Rp. 120,000.00 31,800.00
JUMLAH 763,050.00 6,771,728.10 7,534,778.10
DIBULATKAN 763,050.00 6,771,728.00 7,534,778.00
SNI 7394:2008.6.35 1.00 M' Pekerjaan Membuat Kolom Praktis Beton Bertulang (11 x 11) cm
0.0020 M³ Kayu Kelas IV @ Rp. - -
0.0100 Kg Paku Biasa @ Rp. 20,000.00 200.00
3.0000 Kg Besi beton polos @ Rp. 28,000.00 84,000.00
0.0450 Kg Kawat Beton @ Rp. 26,000.00 1,170.00
4.0000 Kg Semen @ Rp. 1,400.00 5,600.00
0.0060 M³ Pasir Beton @ Rp. 313,206.00 1,879.24
0.0090 M³ Kerikil @ Rp. 503,206.00 4,528.85
0.0090 org Mandor @ Rp. 120,000.00 1,080.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0200 org Tukang Batu @ Rp. 112,000.00 2,240.00
0.0200 org Tukang Kayu @ Rp. 112,000.00 2,240.00
0.0200 org Tukang Besi @ Rp. 112,000.00 2,240.00
0.1800 org Pekerja @ Rp. 75,000.00 13,500.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
JUMLAH 22,200.00 97,378.09 119,578.09
DIBULATKAN 22,200.00 97,378.00 119,578.00
SNI 7394:2008.6.36 1.00 M' Pekerjaan Membuat Ring Balok Beton Bertulang (10 x 15) cm
0.0030 M³ Kayu Kelas IV @ Rp. - -
0.0200 Kg Paku Biasa @ Rp. 20,000.00 400.00
3.6000 Kg Besi beton polos @ Rp. 28,000.00 100,800.00
0.0500 Kg Kawat Beton @ Rp. 26,000.00 1,300.00
5.5000 Kg Semen @ Rp. 1,400.00 7,700.00
0.0090 M³ Pasir Beton @ Rp. 313,206.00 2,818.85
0.0150 M³ Kerikil @ Rp. 503,206.00 7,548.09
0.0150 org Mandor @ Rp. 120,000.00 1,800.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.0330 org Tukang Batu @ Rp. 112,000.00 3,696.00
0.0330 org Tukang Kayu @ Rp. 112,000.00 3,696.00
0.0330 org Tukang Besi @ Rp. 112,000.00 3,696.00
0.2970 org Pekerja @ Rp. 75,000.00 22,275.00
JUMLAH 36,663.00 120,566.94 157,229.94
DIBULATKAN 36,663.00 120,566.00 157,229.00

SNI XII (2002) Tata Cara Perhitungan Harga Satuan Pekerjaan Besi dan Alumunium untuk Konstruksi Bangunan Gedung dan Perumahan

XII.18 (SNI-2008) 1.00 M² Memasang talang datar / jural seng bjls 28 lebar 90 cm
1.0500 m1 Seng plat @ Rp. 15,000.00 15,750.00
0.0150 kg Paku Skrup 1 cm - 2,5 cm @ Rp. 25,000.00 375.00
- m3 papan kayu kelas III @ Rp. 9,000,000.00 -
0.2000 Oh Pekerja @ Rp. 75,000.00 15,000.00
0.4000 Oh Tukang @ Rp. 112,000.00 44,800.00
0.0250 Oh Kepala Tukang @ Rp. 150,000.00 3,750.00
0.0100 Oh Mandor @ Rp. 112,000.00 1,120.00
JUMLAH 64,670.00 16,125.00 80,795.00
DIBULATKAN 64,670.00 16,125.00 80,795.00

SNI 7395:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Penutup Lantai dan Dinding untuk Konstruksi Bangunan Gedung dan Perumahan

SNI 7395:2008.6.35 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (30 x 30) cm
11.8700 Bh Ubin Keramik (30 x 30) cm @ Rp. - -
10.0000 Kg Semen @ Rp. 1,400.00 14,000.00
0.0450 M³ Pasir Pasang @ Rp. 313,206.00 14,094.27
1.5000 Kg Semen Warna @ Rp. 3,000.00 4,500.00
0.0350 org Mandor @ Rp. 120,000.00 4,200.00
0.0350 org Kepala Tukang @ Rp. 150,000.00 5,250.00
0.3500 org Tukang Batu @ Rp. 112,000.00 39,200.00
0.7000 org Pekerja @ Rp. 75,000.00 52,500.00
JUMLAH 101,150.00 32,594.27 133,744.27
DIBULATKAN 101,150.00 32,594.00 133,744.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 7395:2008.6.35a 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (40 x 40) cm
6.2500 Bh Ubin Keramik (40 x 40) cm @ Rp. - -
10.0000 Kg Semen @ Rp. 1,400.00 14,000.00
0.0450 M³ Pasir Pasang @ Rp. 313,206.00 14,094.27
1.5000 Kg Semen Warna @ Rp. 3,000.00 4,500.00
0.0350 org Mandor @ Rp. 120,000.00 4,200.00
0.0350 org Kepala Tukang @ Rp. 150,000.00 5,250.00
0.3500 org Tukang Batu @ Rp. 112,000.00 39,200.00
0.7000 org Pekerja @ Rp. 75,000.00 52,500.00
JUMLAH 101,150.00 32,594.27 133,744.27
DIBULATKAN 101,150.00 32,594.00 133,744.00
SNI 7395:2008.6.36 1.00 M² Pekerjaan Memasang Lantai Keramik Ukuran (20 x 20) cm
26.5000 Bh Ubin Keramik (20 x 20) cm @ Rp. - -
10.4000 Kg Semen @ Rp. 1,400.00 14,560.00
0.0450 M³ Pasir Pasang @ Rp. 313,206.00 14,094.27
1.6200 Kg Semen Warna @ Rp. 3,000.00 4,860.00
0.0350 org Mandor @ Rp. 120,000.00 4,200.00
0.0350 org Kepala Tukang @ Rp. 150,000.00 5,250.00
0.3500 org Tukang Batu @ Rp. 112,000.00 39,200.00
0.7000 org Pekerja @ Rp. 75,000.00 52,500.00
JUMLAH 101,150.00 33,514.27 134,664.27
DIBULATKAN 101,150.00 33,514.00 134,664.00
SNI 7395:2008.6.54 1.00 M² Pekerjaan Memasang Dinding Keramik Ukuran (20 x 25) cm
20.0000 Bh Keramik @ Rp. - -
9.3000 Kg Semen @ Rp. 1,400.00 13,020.00
0.0180 M³ Pasir Pasang @ Rp. 313,206.00 5,637.71
1.9400 Kg Semen Warna @ Rp. 3,000.00 5,820.00
0.0450 org Mandor @ Rp. 120,000.00 5,400.00
0.0450 org Kepala Tukang @ Rp. 150,000.00 6,750.00
0.4500 org Tukang Batu @ Rp. 112,000.00 50,400.00
0.9000 org Pekerja @ Rp. 75,000.00 67,500.00
JUMLAH 130,050.00 24,477.71 154,527.71
DIBULATKAN 130,050.00 24,477.00 154,527.00

SNI 2839:2008 Tata Cara Perhitungan Harga Satuan Pekerjaan Langit-Langit untuk Konstruksi Bangunan Gedung dan Perumahan

SNI 2839:2008.6.1 1.00 M² Pekerjaan Memasang Langit-Langit Asbes Semen, tebal 4 mm, 5 mm, dan 6 mm
1.1000 M² Asbes Semen @ Rp. a #VALUE!
0.0100 Kg Paku Tripleks @ Rp. 20,000.00 200.00
0.0040 org Mandor @ Rp. 120,000.00 480.00
0.0070 org Kepala Tukang @ Rp. 150,000.00 1,050.00
0.0700 org Tukang Kayu @ Rp. 112,000.00 7,840.00
0.0300 org Pekerja @ Rp. 75,000.00 2,250.00
JUMLAH 11,620.00 #VALUE! #VALUE!
DIBULATKAN 11,620.00 #VALUE! #VALUE!
SNI 2839:2008.6.5 1.00 M² Pekerjaan Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 3 mm, 4 mm, dan 6 mm
0.3750 Lbr Tripleks tebal 3 mm @ Rp. 100,000.00 37,500.00
0.0300 Kg Paku Tripleks @ Rp. 20,000.00 600.00
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Kayu @ Rp. 112,000.00 11,200.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
JUMLAH 20,800.00 38,100.00 58,900.00
DIBULATKAN 20,800.00 38,100.00 58,900.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 2839:2008.6.5a 1.00 M² Pekerjaan Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 12 mm
0.3750 Lbr Tripleks tebal 12 mm @ Rp. 200,000.00 75,000.00
0.0300 Kg Paku Tripleks @ Rp. 20,000.00 600.00
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Kayu @ Rp. 112,000.00 11,200.00
0.1000 org Pekerja @ Rp. 75,000.00 7,500.00
20,800.00 75,600.00 96,400.00
20,800.00 75,600.00 96,400.00
SNI 2839:2008.6.7 1.00 M² Pekerjaan Memasang Langit-Langit Gypsum Board Ukuran (1200 x 2400 x 9) mm
0.3640 Lbr Gypsum Board @ Rp. a #VALUE!
0.1100 Kg Paku Sekrup @ Rp. 25,000.00 2,750.00
0.0050 org Mandor @ Rp. 120,000.00 600.00
0.0050 org Kepala Tukang @ Rp. 150,000.00 750.00
0.0600 org Tukang Kayu @ Rp. 112,000.00 6,720.00
0.0600 org Pekerja @ Rp. 75,000.00 4,500.00
JUMLAH 12,570.00 #VALUE! #VALUE!

Dihitung1 1.0000 m2 Pekerjaan memasang partisi GRC board ukuran (1200 x 2400 x 9) mm
0.3640 Lbr GRC board @ Rp. 120,000.00 43,680.00
2.0000 Rangka Metal Sud (Ms 75) 15,000.00 30,000.00
0.7500 Rangka U Runner (UR 76) 15,000.00 11,250.00
8.0000 Sekrup Fisher 2,000.00 16,000.00
6.0500 Kg Paku Sekrup @ Rp. 25,000.00 151,250.00
0.0100 org Mandor @ Rp. 120,000.00 1,200.00
0.0540 org Kepala Tukang @ Rp. 150,000.00 8,100.00
0.5400 org Tukang @ Rp. 112,000.00 60,480.00
0.1800 org Pekerja @ Rp. 75,000.00 13,500.00
JUMLAH 83,280.00 252,180.00 335,460.00
DIBULATKAN 12,570.00 252,180.00 335,460.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
SNI 2839:2008.6.8 1.00 M' Pekerjaan Memasang List Plafond Gypsum Profil
1.0500 M' List Profil Gypsum @ Rp. - -
0.1500 Kg Tepung Gypsum @ Rp. a #VALUE!
0.0030 org Mandor @ Rp. 120,000.00 360.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Kayu @ Rp. 112,000.00 6,720.00
0.0600 org Pekerja @ Rp. 75,000.00 4,500.00
JUMLAH 12,480.00 #VALUE! #VALUE!
DIBULATKAN 12,480.00 #VALUE! #VALUE!
SNI 2839:2008.6.10 1.00 M' Pekerjaan Memasang List Langit-Langit Kayu Profil
1.0500 M' List Kayu Profil @ Rp. a #VALUE!
0.0100 Kg Paku @ Rp. 20,000.00 200.00
0.0030 org Mandor @ Rp. 120,000.00 360.00
0.0050 org Kepala Tukang @ Rp. 150,000.00 750.00
0.0500 org Tukang Kayu @ Rp. 112,000.00 5,600.00
0.0500 org Pekerja @ Rp. 75,000.00 3,750.00
JUMLAH 10,460.00 #VALUE! #VALUE!
DIBULATKAN 10,460.00 #VALUE! #VALUE!

SNI XIV 2002 Tata Cara Perhitungan Harga Satuan Pekerjaan Pengecatan dan Finishing Dinding untuk Bangunan Rumah dan Gedung

XIV.3 (SNI-2002) 1.00 M² Pengecatan bidang kayu lama


0.0800 kg Dempul jadi @ Rp. 10,000.00 10,000.00
0.0200 kg Minyak Cat @ Rp. 20,000.00 20,000.00
0.0100 kg Cat penutup @ Rp. 70,000.00 700.00
0.0400 Oh Pekerja @ Rp. 75,000.00 3,000.00
0.0400 Oh Tukang Cat @ Rp. 112,000.00 4,480.00
0.0040 Oh Kepala Tukang @ Rp. 150,000.00 600.00
0.0025 Oh Mandor @ Rp. 120,000.00 300.00
JUMLAH 8,380.00 30,700.00 39,080.00
DIBULATKAN 8,380.00 30,700.00 39,080.00
XIV.4 (SNI-2002) 1.00 M² Pengecatan bidang kayu baru ( 1 lapis Plamir) 1 lapis Cat Dasar dan 2 lapis cat penutup
0.2000 kg Cat Meni @ Rp. 120,000.00 24,000.00
0.1500 kg Plamir @ Rp. 10,000.00 1,500.00
0.1700 kg Cat dasar @ Rp. 50,000.00 8,500.00
0.2600 kg Cat Penutup 2 kali @ Rp. 70,000.00 18,200.00
0.0700 Oh Pekerja @ Rp. 75,000.00 5,250.00
0.0900 Oh Tukang Cat @ Rp. 112,000.00 10,080.00
0.0060 Oh Kepala Tukang @ Rp. 150,000.00 900.00
0.0025 Oh Mandor @ Rp. 120,000.00 300.00
JUMLAH 16,530.00 52,200.00 68,730.00
DIBULATKAN 16,530.00 52,200.00 68,730.00
XIV.8 (SNI-2002) 1.00 M² Pengecetan Tembok Baru ( 1 lapis plamir, 1 lapis cat dasar dan 2 lapis cat penutup)
0.1000 kg Plamir @ Rp. 10,000.00 1,000.00
0.1000 kg Cat dasar @ Rp. 50,000.00 5,000.00
0.2600 kg Cat Penutup 2 kali @ Rp. 60,000.00 15,600.00
0.0200 Bh Pekerja @ Rp. 75,000.00 1,500.00
0.0630 Oh Tukang Cat @ Rp. 112,000.00 7,056.00
0.0063 Oh Kepala Tukang @ Rp. 150,000.00 945.00
0.0025 Oh Mandor @ Rp. 120,000.00 300.00
JUMLAH 9,801.00 21,600.00 31,401.00
DIBULATKAN 9,801.00 21,600.00 31,401.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
RSNI T-15-2002:6.2 1.00 Bh Pekerjaan Memasang 1 Bh Closed Jongkok Porselen
1.0000 Bh Closed Jongkok Porselen @ Rp. a #VALUE!
6.0000 Kg Semen @ Rp. 1,400.00 8,400.00
0.0100 M³ Pasir Pasang @ Rp. 313,206.00 3,132.06
0.1600 org Mandor @ Rp. 120,000.00 19,200.00
0.1500 org Kepala Tukang @ Rp. 150,000.00 22,500.00
1.5000 org Tukang Kayu @ Rp. 112,000.00 168,000.00
1.0000 org Pekerja @ Rp. 75,000.00 75,000.00
JUMLAH 284,700.00 #VALUE! #VALUE!
DIBULATKAN 284,700.00 #VALUE! #VALUE!
RSNI T-15-2002 : 6.25 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø ½"
1.2000 M Pipa PVC tipe AW Ø ½" @ Rp. 35,000.00 42,000.00
Accessories (35 % Harga Pipa) @ Rp. 12,250.00 12,250.00
0.0018 org Mandor @ Rp. 120,000.00 216.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Batu @ Rp. 112,000.00 6,720.00
0.0360 org Pekerja @ Rp. 75,000.00 2,700.00
JUMLAH 10,536.00 54,250.00 64,786.00
DIBULATKAN 10,536.00 54,250.00 64,786.00
RSNI T-15-2002 : 6.26 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø ¾"
1.2000 M Pipa PVC tipe AW Ø ¾" @ Rp. 50,000.00 60,000.00
Accessories (35 % Harga Pipa) @ Rp. 17,500.00 17,500.00
0.0018 org Mandor @ Rp. 120,000.00 216.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Batu @ Rp. 112,000.00 6,720.00
0.0360 org Pekerja @ Rp. 75,000.00 2,700.00
JUMLAH 10,536.00 77,500.00 88,036.00
DIBULATKAN 10,536.00 77,500.00 88,036.00
RSNI T-15-2002 : 6.27 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 1"
1.2000 M Pipa PVC tipe AW Ø 1" @ Rp. 55,000.00 66,000.00
Accessories (35 % Harga Pipa) @ Rp. 19,250.00 19,250.00
0.0018 org Mandor @ Rp. 120,000.00 216.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Batu @ Rp. 112,000.00 6,720.00
0.0360 org Pekerja @ Rp. 75,000.00 2,700.00
JUMLAH 10,536.00 85,250.00 95,786.00
DIBULATKAN 10,536.00 85,250.00 95,786.00
RSNI T-15-2002 : 6.28 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 1½"
1.2000 M Pipa PVC tipe AW Ø 1½" @ Rp. 80,000.00 96,000.00
Accessories (35 % Harga Pipa) @ Rp. 28,000.00 28,000.00
0.0018 org Mandor @ Rp. 120,000.00 216.00
0.0060 org Kepala Tukang @ Rp. 150,000.00 900.00
0.0600 org Tukang Batu @ Rp. 112,000.00 6,720.00
0.0360 org Pekerja @ Rp. 75,000.00 2,700.00
JUMLAH 10,536.00 124,000.00 134,536.00
DIBULATKAN 10,536.00 124,000.00 134,536.00
RSNI T-15-2002 : 6.31 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 3"
1.2000 M Pipa PVC tipe AW Ø 3" @ Rp. 200,000.00 240,000.00
Accessories (35 % Harga Pipa) @ Rp. 70,000.00 70,000.00
0.0041 org Mandor @ Rp. 120,000.00 492.00
0.1350 org Kepala Tukang @ Rp. 150,000.00 20,250.00
0.1350 org Tukang Batu @ Rp. 112,000.00 15,120.00
0.0810 org Pekerja @ Rp. 75,000.00 6,075.00
JUMLAH 41,937.00 310,000.00 351,937.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
DIBULATKAN 41,937.00 310,000.00 351,937.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
RSNI T-15-2002 : 6.32 1.00 M Pekerjaan Memasang 1 M Pipa PVC tipe AW Ø 4"
1.2000 M Pipa PVC tipe AW Ø 4" @ Rp. - -
Accessories (35 % Harga Pipa) @ Rp. - -
0.0041 org Mandor @ Rp. 120,000.00 492.00
0.1350 org Kepala Tukang @ Rp. 150,000.00 20,250.00
0.1350 org Tukang Batu @ Rp. 112,000.00 15,120.00
0.0810 org Pekerja @ Rp. 75,000.00 6,075.00
JUMLAH 41,937.00 - 41,937.00
DIBULATKAN 41,937.00 - 41,937.00
RSNI T-15-2002 : 6.35 1.00 Bh Pekerjaan Memasang 1 Bh Kran Air Ø ¾ atau ½
1.0000 Bh Kran Air Ø ¾ @ Rp. - -
0.0250 Bh Seal tipe @ Rp. a #VALUE!
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Batu @ Rp. 112,000.00 11,200.00
JUMLAH 12,700.00 #VALUE! #VALUE!
DIBULATKAN 12,700.00 #VALUE! #VALUE!
RSNI T-15-2002 : 6.36 1.00 Bh Pekerjaan Memasang 1 Bh Floor Drain
1.0000 Bh Floor Drain @ Rp. - -
0.0100 org Kepala Tukang @ Rp. 150,000.00 1,500.00
0.1000 org Tukang Batu @ Rp. 112,000.00 11,200.00
JUMLAH 12,700.00 - 12,700.00
DIBULATKAN 12,700.00 - 12,700.00
XI.2 (SNI-2002) 1.0000 bh Pasang kunci tanam biasa
1.0000 bh Kunci tanam biasa @ Rp. a #VALUE!
0.6000 org Tukang kayu @ Rp. 112,000.00 67,200.00
0.0600 org Kepala tukang kayu @ Rp. 150,000.00 9,000.00
0.0600 org Pekerja @ Rp. 75,000.00 4,500.00
0.0030 org Mandor @ Rp. 120,000.00 360.00
JUMLAH 81,060.00 #VALUE! #VALUE!
DIBULATKAN 81,060.00 #VALUE! #VALUE!
XI.5 (SNI-2002) 1.0000 bh Pasang engsel pintu
1.0000 bh Engsel pintu @ Rp. a #VALUE!
0.1500 org Tukang kayu @ Rp. 112,000.00 16,800.00
0.0150 org Kepala tukang kayu @ Rp. 150,000.00 2,250.00
0.0150 org Pekerja @ Rp. 75,000.00 1,125.00
0.0008 org Mandor @ Rp. 120,000.00 90.00
JUMLAH 20,265.00 #VALUE! #VALUE!
DIBULATKAN 20,265.00 #VALUE! #VALUE!
XI.6 (SNI-2002) 1.0000 bh Pasang engsel jendela
1.0000 bh Engsel jendela @ Rp. - -
0.1500 org Tukang kayu @ Rp. 112,000.00 16,800.00
0.0150 org Kepala tukang kayu @ Rp. 150,000.00 2,250.00
0.0150 org Pekerja @ Rp. 75,000.00 1,125.00
0.0008 org Mandor @ Rp. 120,000.00 90.00
JUMLAH 20,265.00 - 20,265.00
DIBULATKAN 20,265.00 - 20,265.00
XI.7 (SNI-2002) 1.0000 bh Pasang kait angin
1.0000 bh Kait angin @ Rp. a #VALUE!
0.1500 org Tukang kayu @ Rp. 112,000.00 16,800.00
0.0150 org Kepala tukang kayu @ Rp. 150,000.00 2,250.00
0.0150 org Pekerja @ Rp. 75,000.00 1,125.00
0.0008 org Mandor @ Rp. 120,000.00 90.00
JUMLAH 20,265.00 #VALUE! #VALUE!
DIBULATKAN 20,265.00 #VALUE! #VALUE!
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
XI.8 (SNI-2002) 1.0000 bh Pasang Kunci Selot
1.0000 bh Kunci Selot @ Rp. - -
0.2000 org Tukang kayu @ Rp. 112,000.00 22,400.00
0.0200 org Kepala tukang kayu @ Rp. 150,000.00 3,000.00
0.0200 org Pekerja @ Rp. 75,000.00 1,500.00
0.0010 org Mandor @ Rp. 120,000.00 120.00
JUMLAH 27,020.00 - 27,020.00
DIBULATKAN 27,020.00 - 27,020.00
Pt T.30-2000-C.II.1 1.0000 m2 Pasang kaca, tebal 3 mm
1.1000 m2 Kaca polos @ Rp. a #VALUE!
0.1500 org Tukang kayu @ Rp. 112,000.00 16,800.00
0.0150 org Kepala tukang kayu @ Rp. 150,000.00 2,250.00
0.0150 org Pekerja @ Rp. 75,000.00 1,125.00
0.0008 org Mandor @ Rp. 120,000.00 90.00
JUMLAH 20,265.00 #VALUE! #VALUE!
DIBULATKAN 20,265.00 #VALUE! #VALUE!

Pembuatan Besi/Baja
Dihitung2 (a) 1.0000 kg Memotong dan mengelas besi profil WF
0.0090 org/hr Pekerja @ Rp. 70,000.00 630.00
0.0090 org/hr Tukang @ Rp. 105,000.00 945.00
0.0090 org/hr Kepala Tukang @ Rp. 145,000.00 1,305.00
0.0040 org/hr Mandor @ Rp. 120,000.00 480.00
1.1000 kg besi profil WF @ Rp. 33,000.00 36,300.00
0.0010 unit Aceton, Oxygen @ Rp. 275,000.00 275.00
0.0100 Jam Mesin las @ Rp. 40,000.00 400.00
0.0100 Kg Kawat las @ Rp. 25,000.00 250.00
JUMLAH 3,360.00 37,225.00 40,585.00
DIBULATKAN 3,360.00 37,225.00 40,585.00

Dihitung3 (b) 1.0000 kg Memotong dan mengelas besi Gording


0.0090 org/hr Pekerja @ Rp. 70,000.00 630
0.0090 org/hr Tukang @ Rp. 105,000.00 945
0.0090 org/hr Kepala Tukang @ Rp. 145,000.00 1305
0.0040 org/hr Mandor @ Rp. 145,000.00 580
1.1000 kg besi profil C Gording @ Rp. 33,000.00 36,300.00
0.0010 unit Aceton, Oxygen @ Rp. 275,000.00 275.00
0.0100 Jam Mesin las @ Rp. 40,000.00 400.00
0.0100 Kg Kawat las @ Rp. 25,000.00 250.00
JUMLAH 3460 37,225.00 40,685.00
DIBULATKAN 3,460.00 37,225.00 40,685.00

Dihitung4 (c) 1.0000 kg Memotong dan mengelas besi Buhul


0.0090 org/hr Pekerja @ Rp. 70,000.00 630
0.0090 org/hr Tukang @ Rp. 105,000.00 945
0.0090 org/hr Kepala Tukang @ Rp. 145,000.00 1305
0.0040 org/hr Mandor @ Rp. 145,000.00 580
1.1000 kg besi plat @ Rp. 33,000.00 36,300.00
0.0010 unit Aceton, Oxygen @ Rp. 275,000.00 275.00
0.0100 Jam Mesin las @ Rp. 40,000.00 400.00
0.0100 Kg Kawat las @ Rp. 25,000.00 250.00
JUMLAH 3460 37,225.00 40,685.00
DIBULATKAN 3,460.00 37,225.00 40,685.00

6.10 1.0000 m2 Memasang roling door alluminium #0,m mm


1.0000 Rolling door alluminium #0,8 mm 300,000.00 300000
1.0000 Pekerja 70,000.00 70,000.00
1.0000 Tukang besi 105,000.00 105,000.00
0.1000 Kepala tukang 145,000.00 14,500.00
0.0500 Mandor 145,000.00 7,250.00
ANALISA BIAYA KONSTRUKSI (ABK) SNI
PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH
KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

No. Uraian Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

RSNI T-12-2002 Analisa Biaya Konstruksi (ABK) Bangunan Gedung dan Perumahan Pekerjaan Persiapan
300000 196,750.00 496,750.00
300,000.00 196,750.00 496,750.00
6.11 1.0000 m` Memasang kosen alluminium
1.1000 Profil alluminium 75,000.00 82500
2.0000 Skrup fixer 2,000.00 4000
0.0600 Sealant 20,000.00 1200
0.0430 Pekerja 70,000.00 3,010.00
0.0430 Tukang besi konstruksi 105,000.00 4,515.00
0.0043 Kepala tukang 145,000.00 623.50
0.0021 Mandor 145,000.00 304.50
87700 8,453.00 96,153.00
87,700.00 8,453.00 96,153.00
DAFTAR SATUAN UPAH

UPAH
NO. PEKERJAAN KETERANGAN
Rp. / Hari

1 Mandor Lapangan 120,000.00

2 Kepala Tukang 150,000.00

3 Tukang 112,000.00

4 Pekerja 75,000.00
BACK UP DATA
PEMBANGUNAN TEMPAT PENGOLAHAN SAMPAH AKHIR
KABUPATEN LABUHAN BATU SELATAN PROVINSI SUMATRA UTARA

JUMLAH KOEFISIEN VOLUME


NO URAIAN P L T Ø
Baris Berat Toleran
Luas Unit VIAS Jarak Dimensi Luas Isi Berat(Kg) Unit Panjang
X Y Jumlah Jenis si

I PEKERJAAN PERSIAPAN
- Pegukuran Kembali & Bowplank 32.00 12.00 1.00 44.00
- Pembuatan Gudang Sementara & Direksikeet 6.00 5.00 30.00
- Listrik & air kerja 1.00
- Pembuatan Plank Proyek 1.00
- Mobilisasi & Demobilisasi 1.00

II PEKERJAAN TANAH
- Galian pondasi (P1) 100x100x100cm 1.00 1.00 1.00 28.00 28.00
- Urugan Tanah kembali 9.33

III PEKERJAAN BETON


PEK. PONDASI (P1)
- Pasir Urug 1.00 1.00 0.05 28.00 1.40
- Cor Lantai Kerja 1:3:5 1.00 1.00 0.05 28.00 1.40
- Cor Pondasi (P1) 1:2:3 1.00 1.00 0.30 28.00 8.40
- Bekisting 1.00 0.30 28.00 4.00 33.60
- Besi Beton Ø 16 1.30 16.00 28.00 24.00 0.0062 86.66

PEK. SLOOF 1520


- Cor Sloof 15x20, 1:2:3 80.00 0.20 0.25 4.00
- Bekisting 80.00 0.25 2.00 40.00
- Besi Beton Ø 10 80.00 10.00 4.00 0.0062 19.84
Beguel Ø 7 - 10 80.00 7.00 1.00 0.20 400.00 0.0062 277.76

PEK. KOLOM PRAKTIS 13x13cm


- Cor Kolom 15x15, 1:2:3 0.13 0.13 1.50 12.00 0.30
- Bekisting 0.15 2.00 21.00 4.00 25.20
- Besi Beton Ø 10 2.55 10.00 21.00 4.00 0.0062 13.28
Beguel Ø 7 -10 2.50 7.00 21.00 0.20 12.50 0.0062 5.70

PEK. STIK KOLOM 25x25cm


- Cor Stik 30x30, 1:2:3 0.30 0.30 1.00 28.00 2.52
- Bekisting 0.30 1.00 28.00 4.00 33.60
- Besi Beton Ø 16 1.50 16.00 28.00 8.00 0.0062 33.33
Besi Beton Ø 8-10 1.25 8.00 28.00 0.20 6.25 0.0062 2.17

IV PEKERJAAN DINDING & PLESTERAN


- Pas. Dinding Bata 86.76 1.00 86.76
- Plesteran Dinding Bata 86.76 2.00 173.51

V PEKERJAAN LANTAI
- Timbunan Lantai 30.00 10.00 0.20 60.00
- Pasir Urug Dibawah Lantai t:5cm 30.00 10.00 0.05 15.00
- Pembesian Lantai 30.00 10.00 300.00
- Cor Rabat Beton 1:2:3 30.00 10.00 0.07 21.00

VI PEKERJAAN ATAP
- Pas. Atap Spandeck 0.30mm 33.00 7.00 2.00 462.00
- Pas. Rabung Atap 33.00
- Pas. Lisplank GRC 66.00

VII PEKERJAAN BAJA


- Pas. Baja WF 200x100x5,5x8 10.00 14.00 21.333 2,986.62
- Pas. Baja WF 125x60x8x7 4.175 7.00 2.00 13.200 771.54
- Pas. Puring CNP 75x35x15x1,6 33.00 16.00 2.067 1,091.38
- Pas. Plat Buhul
- Pas. Besi Plat Polos 10mm 0.25 0.25 28.00 23.33 40.83
- Pas. Baut Anger Ø 5/8"- 8" 28.00 6.00 168.00
- Pas. Trackstang CNP Ø8 7.50 7.00 2.00 105
- Baut Pisher 7.00 30.00 210.00

VIII PEKERJAAN SANITASI


PEMBUATAN SALURAN PARIT
- Galian Tanah 40.00 0.25 0.30 3.00
- Cor Dinding Parit 40.00 0.08 0.30 0.90
- Cor Lantai Parit 40.00 0.05 0.20 0.40
- Pas. Floor Drain 20
- Pas. Besi Penutup Parit 60

IX PEKERJAAN LAIN-LAIN
- Pembersihan Akhir 1.00
- Foto Dokumentasi & Laporan 1.00
PERHITUNGAN BIAYA ANGKUTAN

PERENCANAAN PENGADAAN KONTRUKSI BANGUNAN PENGOLAHAN SAMPAH


KABUPATEN LABUHANBATU SELATAN PROVINSI SUMATRA UTARA

Perhitungan sekali angku: Batu Kerikil


Quary : Hutagodang

Biaya Operasi truck (kapasitas) 3,00 M3


1 Truck disewa Rp. 250,000.00 / Jam (An.E.212)
1 Orang supir @ Rp. 187,000.00 /5 Jam Rp. 37,400.00
2 Orang kerne @ Rp. 75,000.00 /5 Jam Rp. 30,000.00
Rp. 317,400.00
Pengunaan Waktu
- Muat = 5.00 Menit
- Bongkar = 3.00 Menit
- Pergi dengan panjang jalan terdiri dari :

= 20 Km
Hotmix 20 Km Waktu Tempuh x 60 Menit = 26.67 Menit
45 Km / Jam

= 0 Km
Lapen 0 Km Waktu Tempuh x 60 Menit = - Menit
40 Km / Jam

= 0 Km
Kerikil 0 Km Waktu Tempuh x 60 Menit = - Menit
35 Km / Jam

= 2 Km
Tanah 2 Km Waktu Tempuh x 60 Menit = 4.00 Menit
30 Km / Jam
Pulang dengan panjang jalan terdiri dari :
= 20 Km
Hotmix 20 Km Waktu Tempuh x 60 Menit = 21.82 Menit
55 Km / Jam

= 0 Km
Lapen 0 Km Waktu Tempuh x 60 Menit = - Menit
50 Km / Jam

= 0 Km
Kerikil 0 Km Waktu Tempuh x 60 Menit = - Menit
40 Km / Jam

= 2 Km
Tanah 2 Km Waktu Tempuh x 60 Menit = 3.43 Menit
35 Km / Jam

Jumlah ......... = 63.92 Menit


= 1.07 Jam
1.07 Jam X Rp. 317,400
=Rp. 113,206.00
Maka Ongkos angkut material/M3 = 3

=Rp. 113,206.00

###
-
-

-
-