REKAPITULASI

RENCANA ANGGARAN BIAYA

NO URAIAN PEKERJAAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN 289,680,000.00


B PEKERJAAN GUDANG
B.I PEKERJAAN STRUKTUR BAWAH 831,594,360.00
B.II PEKERJAAN STRUKTUR
B.II a PEKERJAAN BETON 627,556,473.71
B.II b PEKERJAAN BAJA 1,224,601,033.37
B.II c PEKERJAAN TANGGA 32,849,958.50
C PEKERJAAN SIPIL
C.I.a PEKERJAAN DINDING DAN KOLOM 695,594,400.00
D PEKERJAAN INSTALASI LISTRIK, AIR DAN PENANGKAL PETIR
D.Ia INSTALASI LISTRIK 88,430,000.00
D.I.b INSTALASI AIR DAN ASESORIES 105,327,500.00
F PEKERJAAN LUAR
0 PEKERJAAN PAGAR,SALURAN,GERBANG MASUK, AKSES JALAN 226,928,000.00

TOTAL NILAI PEKERJAAN SEBELUM PAJAK 4,122,561,725.58


PPn 11% 453,481,789.81
PPh 1.75% 72,144,830.20

TOTAL NILAI PEKERJAAN SETELAH PAJAK 4,648,188,345.60


NILAI HARGA PEMBULATAN 4,648,188,000.00

Terbilang
Empat Miliar Enam Ratus Empat Rpuluh Delapan Juta Seratus Delapan puluh Delapan Ribu rupiah

By Retrohome Design
Retrohome Design
RENCANA ANGGARAN BIAYA
PEKJAAN PEMBANGUNAN GUDANG
KOTA TANGERANG

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI BAHAN VOLUME SAT
SATUAN HARGA

A PEKERJAAN PERSIAPAN
1 Pekerjaan Landcrearing -Exavator PC 200 1,860.00 M2 38,500.00 71,610,000.00
2 MobIlisasi Tenaga dan Alat 1.00 Lot 10,000,000.00 10,000,000.00
3 Pembuatan Bedeng Pekerja dan MCK -Bahan Kayu dan Triplek 20.00 M2 2,150,000.00 43,000,000.00
4 Pek. Instalasi Listrik Direksi Keet -Listrik PLN 10.00 Ttk 245,000.00 2,450,000.00
5 Pek. Air dan Listrik Kerja 1.00 Lot 15,000,000.00 15,000,000.00
6 Pek. Sumur Bor termasuk Tandon & Pompa - Sarana Air Kerja 1.00 Ttk 35,000,000.00 35,000,000.00
7 Pengukuran dan Bouwplank 1,092.00 M2 35,000.00 38,220,000.00
8 Dokumentasi dan Pelaporan 1.00 Lot 3,500,000.00 3,500,000.00
9 Kebutuhan K3 (Banner K3, Kotak K3, Sarung Tangan, -Merk Standar SNI 1.00 Lot 8,000,000.00 8,000,000.00
Tabung Damkar, Helm, Sepatu Safety, dll)
10 Pembuatan Gerbang Proyek dan Cor Jalan Akses Masuk - Seng dan Hollow 1.00 Ls 35,000,000.00 35,000,000.00
11 Pek. Pembersihan dan Buang Puing 1,860.00 M2 15,000.00 27,900,000.00
Sub Total A 289,680,000.00
B PEKERJAAN GUDANG
B.I PEKERJAAN STRUKTUR BAWAH
1 Mob dan Demobilisasi Alat Pancang -HSPD - 80 TON 1.00 Lot 23,500,000.00 23,500,000.00
2 Pemancangan Pondasi L = 16 Meter -Pancang kotak 20 X 20 - P 6 Meter Dan 3 Meter = K 400 1,216.00 Ml 172,500.00 209,760,000.00
3 Handling -Manual 1,216.00 Ml 68,500.00 83,296,000.00
4 Joint Las -Kaawat LB 76.00 Ttk 75,000.00 5,700,000.00
5 Bobok Pancang -Manual 76.00 Bh 85,000.00 6,460,000.00
6 PDA Test 2 Titik 2.00 Ttk 6,000,000.00 12,000,000.00
7 Galian Tanah PileCap P1 -Exavator PC 75 14.40 M3 95,000.00 1,368,000.00
8 Galian Tanah PileCap P2 -Exavator PC 75 16.13 M3 95,000.00 1,532,160.00
9 Galian Tanah Sloof -Exavator PC 75 58.56 M3 95,000.00 5,563,200.00
10 Pemadatan Tanah Sub Grade CBR 6% .-Padat Vibrator Mini 58.56 M3 75,000.00 4,392,000.00
11 Urugan Lime Stone Sub Base Padat CBR 30% -Hanya Area rencana Gudang - Tebal 30 Cm 327.60 M3 285,000.00 93,366,000.00
12 Pemadatan Basecourse -Hanya Area rencana Gudang - Tebal 15 Cm 163.80 M3 315,000.00 51,597,000.00
13 Pek. Wiremesh Ø10mm -Hanya Area rencana Gudang - 1 Lapis 1,092.00 M2 87,500.00 95,550,000.00
14 Pek. Beton Untuk Lantai Dasar K.350 -Hanya Area rencana Gudang - Tebal 15 Cm 163.80 M3 1,450,000.00 237,510,000.00
Sub Total B.I 831,594,360.00
Retrohome Design
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI BAHAN VOLUME SAT
SATUAN HARGA
B.II PEKERJAAN STRUKTUR
B.II a PEKERJAAN BETON
1 Begisting Pilecap dan Sloof -Batako press 336.00 M2 115,000.00 38,640,000.00
2 Urugan Pasir dibawah pilecap dan sloof -Pasir Urug tebal 10 Cm 5.60 M3 350,000.00 1,960,000.00
3 Lantai kerja dibawah Pilecap dan Sloof -Semen + Pasir campuran 1 : 4 Tebal 5 Cm 2.80 M2 825,000.00 2,310,000.00
4 Pekerjaan Pilecap P1 Besi Tulangan Baawah Dia 19 MM Tulangan Atas dia 13 9.02 M3 7,450,000.00 67,228,800.00
5 Pekerjaan Pilecap P2 Besi Tulangan Baawah Dia 19 MM Tulangan Atas dia 13 9.02 M3 7,450,000.00 67,228,800.00
6 Pekerjaan Pilecap P3 Besi Tulangan Baawah Dia 19 MM Tulangan Atas dia 13 1.73 M3 7,450,000.00 12,873,600.00
7 Pekerjaan Sloof Beton - 250 X 500 -Mutu Beton K 350 28.00 M3 7,450,000.00 208,600,000.00
8 Pekerjaan Kolom Pedestal P1 Besi Tulangan Utama 19 MM, sengkang Besi 10 MM 3.07 M3 7,450,000.00 22,886,400.00
9 Pekerjaan Kolom Pedestal P2 Besi Tulangan Utama 19 MM, sengkang Besi 10 MM 1.92 M3 7,450,000.00 14,304,000.00
10 Pekerjaan Kolom Pedestal P3 Besi Tulangan Utama 19 MM, sengkang Besi 10 MM 1.15 M3 7,450,000.00 8,582,400.00
11 Pekerjaan Plat Bondex t. 0,75mm Lantai 2 ( Mezanine ) -Plat Bondex t. 0,75mm 324.00 M2 107,037.00 34,679,988.00
12 Pekerjaan Wiremesh Ø10mm + Shear Conector -Wiremesh Ø10mm + Shear Conector 324.00 M2 155,266.93 50,306,485.71
13 Pekerjaan Beton Untuk Lantai Mizanine -K.350 include bekisting samping 38.88 M3 1,450,000.00 56,376,000.00
14 Pekerjaan Floor Hardener 1,080.00 M2 38,500.00 41,580,000.00
Sub Total B. II.A 627,556,473.71
B.II b PEKERJAAN BAJA
1 Angkur Pondasi ke Kolom K1 - Diameter 19 MM - L 120 96.00 Bh 105,000.00 10,080,000.00
2 Angkur Pondasi ke Kolom K2 - Diameter 19 MM 16.00 Bh 105,000.00 1,680,000.00
3 Angkur Pondasi ke Kolom K3 - Diameter 16 MM 28.00 Bh 95,000.00 2,660,000.00
3 BasePlat -Plat Hitam 12 MM 264.44 Kg 27,000.00 7,140,000.00
4 Kolom K1 -WF 300 X 150 MM 5,280.48 Kg 27,000.00 142,572,960.00
5 Kolom K2.1 -WF 250 X 125 MM 609.35 Kg 27,000.00 16,452,396.00
6 Kolom K2 -WF 200 X 150 MM 1,927.80 Kg 27,000.00 52,050,600.00
7 Kolom Mezanine K1 -WF 300 X 150 MM 880.08 Kg 27,000.00 23,762,160.00
8 Balok Mezanine B1 -WF 300 X 150 MM 3,960.36 Kg 27,000.00 106,929,720.00
9 Balok Mezanine B2 -WF 250 X 125 MM 4,259.52 Kg 27,000.00 115,007,040.00
10 Rafter 1 -WF 300 X 150 MM 5,380.22 Kg 27,000.00 145,266,004.80
11 Rafter 2 -WF 200 X 150 MM 1,909.44 Kg 27,000.00 51,554,880.00
12 Pekerjaan Ringbalok -WF 200 X 100 MM 2,349.44 Kg 27,000.00 63,434,826.00
13 Pekerjaan Purlins C 150 -C 150 X 50 X 20 *2.3 MM 3,851.35 Kg 27,000.00 103,986,504.00
14 Pekerjaan Purlins C 125 -C 125 X 50 X 20 *2.3 MM 1,362.05 Kg 27,000.00 36,775,242.00
15 Pekerjaan Stiffener -Plat Hitam 9 MM 1,102.50 Kg 27,000.00 29,767,500.00
16 Pekerjaan Haunch - 1/2 WF 300 646.72 Kg 27,000.00 17,461,440.00
17 Pekerjaan Haunch - 1/2 WF 250 473.28 Kg 27,000.00 12,778,560.00
18 Pek. Mur Baut 8.8 M16 -M16 1,520.00 Bh 22,500.00 34,200,000.00
19 Ikatan Angin - Besi 16 MM 132.00 Kg 27,000.00 3,564,000.00
Retrohome Design
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI BAHAN VOLUME SAT
SATUAN HARGA
20 Trekstang - Besi 12 MM 489.50 Kg 27,000.00 13,216,500.00
21 Pekerjaan Zynchromate secara keseluruhan 34,878.53 Kg 2,450.00 85,452,400.57
22 Pekerjaan Penutup Atap - Spandek Zincallum tebal 035 1,270.56 M2 105,000.00 133,408,800.00
23 Pekerjaan Talang -Zincallum 52.80 ML 115,000.00 6,072,000.00
24 Pekerjaan Nok Atap -Zincallum 45.50 ML 205,000.00 9,327,500.00
Sub Total B. II.b 1,224,601,033.37
B.II c PEKERJAAN TANGGA
1 Struktur Tangga -CNP 200.75.20.3,2mm 263.08 Kg 22,500.00 5,919,358.50
2 Struktur Anak Tangga -Hollow 40x40mm 183.74 Kg 22,500.00 4,134,240.00
3 Pelapis Trap Tangga -Conwood 25mm 8.40 M2 345,000.00 2,898,000.00
4 Railling Tangga -Besi Hollow 20/20 & Besi 12mm Cat Duco 18.29 ML 925,000.00 16,916,400.00
5 Hand Railling -Kayu 1,5inch 20.32 ML 146,750.00 2,981,960.00

Sub Total B. II.c 32,849,958.50


C PEKERJAAN SIPIL
C.I.a PEKERJAAN DINDING DAN KOLOM
1 Pemasangan Kolom beton 15 X 30 -Sitemix 1.04 M3 3,450,000.00 3,601,800.00
2 Pemasangan Kolom Praktis 15 X 15 -Sitemix 6.93 M3 3,450,000.00 23,908,500.00
3 Pemasangan Ringbalok beton 15 X 20 -Sitemix 4.95 M2 3,450,000.00 17,077,500.00
4 Pekerjaan pemasangan dinding -Bata ringan tebal 10 Cm 1,849.50 M2 142,000.00 262,629,000.00
5 Pekerjaan Plesteran dinding -Mortar pasangan 1,996.80 M2 67,500.00 134,784,000.00
6 Pekerjaan Acian dinding -Mortar Acian 3,993.60 M2 35,000.00 139,776,000.00
7 Pekerjaan Pengecatan 3,993.60 M2 28,500.00 113,817,600.00
Sub Total C. I.a 695,594,400.00
D PEKERJAAN INSTALASI LISTRIK, AIR DAN PENANGKAL PETIR
D.Ia INSTALASI LISTRIK
1 Instalasi Penerangan -Include Asesoris + Lampu TL@40 Watt, Kabel 2X1,5 MM 72.00 Titk 325,000.00 23,400,000.00
2 Instalasi Stopkontak -Include Asesoris + Lampu TL@40 Watt, Kabel 3X1,5 MM 20.00 Titk 445,000.00 8,900,000.00
3 Panel 3 Phase -Breaker Merlin Gerin 2.00 Unit 15,750,000.00 31,500,000.00
4 Gantungan Lampu -Pipa 1/2 Inci Galvanis 72.00 Bh 165,000.00 11,880,000.00
5 Pemasangan Penangkal Petir -Kurn R-150 1.00 Lot 12,750,000.00 12,750,000.00
Sub Total D. I.a -
88,430,000.00
D.I.b INSTALASI AIR DAN ASESORIES
1 Pekerjaan instalasi air kotor -Pipa 4 Inci AW - Ex Wavin / Setara 15.00 ML 262,500.00 3,937,500.00
2 Pekerjaan instalasi air bekas -Pipa 4 Inci AW - Ex Wavin / Setara 30.00 ML 262,500.00 7,875,000.00
3 Pekerjaan Instalasi air hujan -Pipa 4 Inci AW - Ex Wavin / Setara + Dari Talang 102.00 ML 262,500.00 26,775,000.00
Retrohome Design
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI BAHAN VOLUME SAT
SATUAN HARGA
4 Pekerjaan Instalasi Air Bersih -Pipa 2- 1- 1/2 Inci AW - Ex Wavin / Setara 10.00 ML 195,000.00 1,950,000.00
5 Pekerjaan pembuatan STP -Biotek Kap 6M3 1.00 Unit 11,750,000.00 11,750,000.00
6 Pekerjaan Pemasangan Tandon Air - 7500 Ltr - Merk Pinguin/Mpoin Setara 1.00 Unit 23,000,000.00 23,000,000.00
7 Pemasangan Closet -Ex Ameican Standar 2.00 Unit 2,750,000.00 5,500,000.00
8 Pemasangan Shower -Ek Onda 2.00 Unit 1,725,000.00 3,450,000.00
9 Pemanagan Kran Air -Ek Onda 4.00 M2 75,000.00 300,000.00
10 Pemasangan keramik Lantai k.mandi - 20 X20 Ex Mulia/Setara 14.00 M2 195,000.00 2,730,000.00
11 Pemasangan keramik dinding k.mandi - 20 X25 Ex Mulia/Setara 84.00 M2 215,000.00 18,060,000.00
Sub Total D. I.b 105,327,500.00
E PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pemasangan pintu Utama -Aluuminium - Kaca 12 mm Tempered 1.00 Unit 17,500,000.00 17,500,000.00
2 Pemasangan Pintu Kmandi -PVC 4.00 Unit 650,000.00 2,600,000.00
3 Pemasangan BV Kamar Mandi -PVC 4.00 Unit 450,000.00 1,800,000.00
4 Pemasangan Jendela Lt Mezanine 180 X 2.00 -Aluuminium - Kaca 8 mm 8.00 Unit 3,250,000.00 26,000,000.00
Sub Total E. -
47,900,000.00
F PEKERJAAN LUAR
PEKERJAAN PAGAR,SALURAN,GERBANG MASUK, AKSES JALAN
1 Pemasangan pagal panel -Tinggi 2.8 Meter - Mutu Beton K225 134.00 ML 792,000.00 106,128,000.00
2 Pekerjaan Saluran Dalam -Udicth 60 X 60X 1200 CM - K 400 120.00 ML 716,666.67 86,000,000.00
3 Pekerjaan Gerbang Utama 12 X 2 -Baja + Holo + Plat 24.00 M2 1,450,000.00 34,800,000.00

Sub Total E. I. 226,928,000.00