REKAPITULASI
II Pekerjaan Struktur
TOTAL 2,976,188,412.22
Dibulatkan 3,601,187,000.00
Wie Min
BILL OF QUANTITY
PROYEK : STM (MR.BREND)
LOKASI : MEDAN
2 Lantai kerja balok sloof dan pile cap 6.03 m³ 750,000 60,000 4,522,669 361,814 4,884,482
4 Balok sloop
- Beton = K-300 24.94 m3 985,000 60,000 24,562,797 1,496,211 26,059,008
- Besi beton SNI U39 3,890.60 kg 9,500 2,500 36,960,661 9,726,490 46,687,150
- Bekesting 136.69 m2 75,000 65,000 10,251,750 8,884,850 19,136,600
13 Pelat lantai 2
- Beton = K-300 44.90 m3 985,000 60,000 44,229,849 2,694,204 46,924,053
- Besi beton SNI U39 3,977.24 kg 9,500 2,500 37,783,776 9,943,099 47,726,876
- Bekesting 390.00 m2 75,000 65,000 29,249,925 25,349,935 54,599,860
14 Balok lantai 2
- Beton = K-300 47.20 m3 985,000 60,000 46,489,352 2,831,839 49,321,191
- Besi beton SNI U39 8,273.42 kg 9,500 2,500 78,597,449 20,683,539 99,280,988
- Bekesting 316.67 m2 75,000 65,000 23,749,890 20,583,238 44,333,128
II. BAGIAN PEKERJAAN : STRUKTUR ATAS
32 Lift
Pit lift
- Beton = K-300 4.83 m3 985,000 60,000 4,759,520 289,920 5,049,440
- Besi beton SNI U39 303.00 kg 9,500 2,500 2,878,460 757,489 3,635,949
- Bekesting 38.72 m2 75,000 65,000 2,904,000 2,516,800 5,420,800
Water Stop
- WaterStop PVC 20 cm 18.40 m' 125,000 15,000 2,300,000 276,000 2,576,000
Kolom Lift
- Beton = K-300 5.34 m3 985,000 60,000 5,262,264 320,544 5,582,808
- Besi beton SNI U39 782.58 kg 9,500 2,500 7,434,465 1,956,438 9,390,903
- Bekesting 80.14 m2 75,000 65,000 6,010,200 5,208,840 11,219,040
Balok Lift
- Beton = K-300 3.96 m3 985,000 60,000 3,900,600 237,600 4,138,200
- Besi beton SNI U39 571.21 kg 9,500 2,500 5,426,505 1,428,028 6,854,533
- Bekesting 52.80 m2 75,000 65,000 3,960,000 3,432,000 7,392,000