MAKASSAR
BILL OF QUANTITY
TOTAL 1,287,801,758.0
DIBULATKAN 1,287,801,000.0
PPn 10% 128,780,100.0
GRAND TOTAL 1,416,581,100.0
LUAS BANGUNAN (M2) 317.0
HARGA PER M2 4,062,463.7
Diajukan oleh ;
Kontraktor
PT. AMTA UTAMA KONTRAKTOR
I PEKERJAAN PERSIAPAN
1 Pengukuran, perataan tanah dan pemasangan bowplank m2 126.0 35,790.00 4,509,540.0
2 Direksi kit, & gudang ls 1.0 992,622.5 992,622.5
3 Jaminan Pelaksanaan (Asuransi) ls 1.0 5,000,000.0 5,000,000.0
4 Mobilisasi & Demobilisasi pekerja & peralatan ls 1.0 1,020,000.0 1,020,000.0
5 Listrik & air kerja bln 10.0 200,000.0 2,000,000.0
6 Shop Drawing ls 1.0 1,800,000.0 1,800,000.0
7 As built drawing ls 1.0 1,800,000.0 1,800,000.0
8 Kebersihan proyek bln 10.0 50,000.0 500,000.0
9 Keamanan proyek bln 10.0 50,000.0 500,000.0
10 Pengadaan Alat Safety Ls 1.0 5,000,000.0 5,000,000.0
SUB TOTAL PEK. PERSIAPAN 23,122,162.5
II PEKERJAAN TANAH
1 Galian tanah pondasi m3 37.86 51,300.00 1,941,961.6
2 Urug kembali sisi pondasi m3 16.29 28,400.0 462,515.7
3 Pemadatan tanah bawah lantai + Perataan sisa galian m2 183.29 52,000.0 9,531,277.6
4 Urugan pasir bawah pondasi 10 CM m3 3.04 172,400.0 524,357.6
5 Urugan pasir bawah lantai 5 CM m3 8.58 100,400.0 861,532.4
SUB TOTAL PEK. TANAH 13,321,645.0
III PEKERJAAN BETON
III C, 1 BALOK BETON & PLAT LANTAI ATAS Elv. + 3,70 ( K 225. )
1 Balok B 1 15 x 20 ( tul. 4 d 13 , sk. 8 - 200 ) m3 0.105 6,892,560.9 723,718.9
2 Balok B 2 15 x 25 ( tul.5 d 13 , sk. 8 - 100/200 ) m3 0.881 6,531,268.3 5,755,680.2
3 Balok B 3 15 x 30 ( tul 5 d 13 , sk. 8 - 100/200 ) m3 1.442 6,142,315.7 8,858,754.9
4 Balok B 4 15 x 35 ( tul 6 d 13 , sk. 8 - 100/150 ) m3 1.391 5,910,103.2 8,222,431.0
5 Balok B 5 15 x 40 ( tul 6 d 13 , sk. 8 - 100/150 ) m3 1.395 5,744,265.6 8,013,250.5
6 Balok B 6 15 x 50 ( tul 9 d 13 , sk. 8 - 100 ) m3 0.375 6,957,100.9 2,608,912.8
7 Balok B 7 20 x 50 ( tul 9 d 16 , sk. 10 - 125/200 ) m3 0.954 6,947,880.9 6,628,278.3
8 Balok B 8 20 x 50 ( tul 9 d 16 sk. 10 - 100/150 ) m3 0.550 7,113,840.9 3,912,612.5
9 Balok B 2 A 13 x 25 ( tul 5 d 13 , sk. 8 - 100/200) m3 0.083 7,270,580.9 602,549.4
10 Balok B 3 A 13 x 30 ( tul 5 d 13 , sk. 8 - 100/200 ) m3 0.156 6,984,760.9 1,089,622.7
11 Balok B 3 B 15 x 30 ( tul 5 d 13 , sk. 8 - 100 ) m3 0.146 7,003,200.9 1,024,218.1
12 Balok B 4 B 13 x 35 ( tul 6 d 13 , sk. 8 - 100/150 ) m3 0.093 7,067,740.9 659,243.5
13 Balok B 5 A 15 x 40 ( tul 9 d 13 , sk. 8 - 100 ) m3 0.680 7,289,020.9 4,956,534.2
14 Balok B 5 B 15 x 40 ( tul 6 d 13 , sk. 8 - 100 ) m3 0.180 5,891,663.2 1,060,499.4
15 Balok B 6 A 15 x 53 ( tul 9 d 13 , sk. 10 - 100 ) m3 0.517 7,252,140.9 3,747,543.8
16 Balok B 7 A 13 x 50 ( tul 6 d 13 , sk. 8 - 100 ) m3 0.390 5,548,810.6 2,164,036.1
17 Balok B 8 A 20 x 50 ( tul 8 d 16 , sk. 10 - 100 ) m3 0.350 7,141,500.9 2,499,525.3
18 Balok B 8 B 20 x 40 ( tul 6 d 16 , sk. 10 - 200 ) m3 0.204 5,456,610.6 1,113,148.6
19 Balok Rb 1 13 x 15 ( tul 4 d 8 , sk. 6 - 200 ) m3 0.585 4,995,365.7 2,922,289.0
20 Balok C B 2 13 x 30 ( tul 6 d 13 , sk. 8 - 100 ) m3 0.242 7,491,860.9 1,810,408.2
21 Balok C B 1 15 x 35 ( tul 6 d 13 , sk. 8 - 100 ) m3 0.263 6,066,965.6 1,592,578.5
22 Balok B C 3 13 x 35 ( tul 8 d 13 , sk. 8 - 100 ) m3 0.319 6,433,440.9 2,049,050.9
23 Balok B C 4 13 x 40 ( tul 8 d 13 , sk. 8 - 100 ) m3 0.312 7,408,880.9 2,311,570.8
24 Janggutan 13 x35 ( tul 8 d 13 , sk. 8 - 100 ) m3 0.035 7,657,820.9 268,023.7
25 Plat Lantai tebal 12 , ( tul . 8 # 20 dobel ) elv. 3,78 m3 14.703 4,143,149.6 60,915,237.5
26 Plat kanopi tebal 10 cm , ( tul . 8 # 20 dobel ) m3 2.400 4,367,590.0 10,480,032.2
27 Balok latai 13 x 15 ( tul . 4 d 10 , sk . Dia 8 - 150 ) m3 0.380 7,104,620.9 2,701,532.1
28 Balok latai 13 x 20 ( tul . 5 d 12 , sk . Dia 8 - 150 ) m3 0.338 7,408,880.9 2,504,201.7
PROJECT : WATERFRONT CITY 2, PROJECT BILL OF
No. PROYEK
PEKERJAAN : RUMAH TINGGAL GRAND TRIVIAL L16 x 20 QUANTITY
LOKASI : PREMIER RESIDENCE
2016
VI PEKERJAAN ATAP
1 Pas. Kuda - kuda baja ringan m2 187.77 185,300.0 34,794,475.9
2 Pas. lisplang GRC 20 x 300 mm ml 54.80 131,760.0 7,220,448.0
3 Pasang genteng beton flat eks Monier m2 187.77 133,210.0 25,013,341.2
4 Aluminium foil woven double side m2 187.77 58,925.0 11,064,568.2
5 Pas. genteng beton nok cabang tiga bh 3.00 114,805.0 344,415.0
6 Pasng genteng bubungan & karpusan jurai ml 45.00 104,515.0 4,703,175.0
7 Pas. genteng nok ujung jurai bh 5.00 69,875.0 349,375.0
IX b LANTAI ATAS
1 Lantai HT 80 x 80 ex INDOGRESS Crystal White (F1) m2 102.31 391,636.8 40,066,397.7
2 Lantai Kmd. Utama Keramik 80 x 80 ex PLATINUM Nino (F3) m2 8.41 370,286.8 3,114,111.6
3 Lantai balkon HT 40 x 40 ex Platinum Lagos Grey ( F 2 ) m2 3.08 311,977.5 960,890.7
4 Dinding kamar mandi Utama 30 x 80 eks PLATINUM Dali m2 32.70 130,286.8 4,260,376.7
5 Plint dalam HT 10 x 80 cm ( keramik di potong sesuai ukuran plint ) ml 61.40 91,115.8 5,594,507.1
6 Lantai kamar mandi Anak 40 x 40 eks PLATINUM Nevada ( F 4 ) m2 3.14 311,977.5 978,049.5
7 Dinding kamar mandi Anak 25 x 40 eks PLATINUM BALKAN m2 29.20 399,908.8 11,677,335.5
SUB TOTAL PEK. KERAMIK 160,908,078.9
X PEKERJAAN SANITARY
Xa PEK. SANITARY L. BAWAH
1 Closet duduk TOTO CW 421 J / SW420 bh 1.0 2,562,403.0 2,562,403.0
2 Closet jongkok TOTO C 7 bh 1.0 762,225.0 762,225.0
3 Jet washer TOTO THX 20 MCRB bh 1.0 337,800.0 337,800.0
4 Shower set TOTO, TX 432 SHBR set 1.0 2,660,605.0 2,660,605.0
5 Wast TOTO L W 220 J + TX 109 LH unt 1.0 1,418,005.0 1,418,005.0
6 Kaca wastafel 70 x 100 tbl 6 mm + bavel + skrup kusus unt 1.0 298,985.0 298,985.0
7 Pas. Shoap Holder S 156 N TOTO bh 2.0 103,800.0 207,600.0
8 Towel rack TOTO TS 113 A 2 bh 1.0 236,800.0 236,800.0
9 Floor drain TOTO TX 1 AVI bh 2.0 338,800.0 677,600.0
10 Kran Taman ONDA bh 2.0 44,800.0 89,600.0
PROJECT : WATERFRONT CITY 2, PROJECT BILL OF
No. PROYEK
PEKERJAAN : RUMAH TINGGAL GRAND TRIVIAL L16 x 20 QUANTITY
LOKASI : PREMIER RESIDENCE
2016
1 Ls Mess Pekerja
BAHAN :
Dolken Kayu 1.25 Batang 25000.00 31250.00
Kayu Terentang 0.19 M³ 1900000.00 353400.00
Paku Biasa 2"-5" 0.30 Kg 17000.00 5100.00
Semen Portland 18.00 Kg 987.50 17775.00
Pasir Beton 0.30 M³ 140000.00 42000.00
Koral Beton 0.05 M³ 250000.00 12500.00
Seng Plat 1.50 Lembar 42000.00 63000.00
Playwood 4 mm 1.35 Lembar 54000.00 72900.00
Jumlah Bahan 597925.00
UPAH :
Pekerja 1.00 Oh 90000.00 90000.00
Tukang Kayu 2.00 Oh 110000.00 220000.00
Kepala Tukang Kayu 0.20 Oh 125000.00 25000.00
Mandor 0.05 Oh 140000.00 7000.00
Jumlah Upah 342000.00
1 M³ GALIAN TANAH
BAHAN :
Jumlah Bahan
UPAH :
Pekerja 0.50 Oh 90000.00 45000.00
Mandor 0.05 Oh 140000.00 6300.00
Jumlah Upah 51300.00
1 M³ PENGURUNGAN KEMBALI
BAHAN :
PERALATAN :
Alat Bantu 1.00 Ls 125000.00 125000.00
Jumlah Peralatan 125000.00
1 M³ Pond. PC1 50 x 50x50 cm , tul bwh . Dia 13 # 100 , ats dia 10 # 100
BAHAN :
Beton K 225 1.00 M³ 700000.00 700000.00
Besi Polos 240.00 Kg 9220.00 2212800.00
Bekisting 15.33 M² 165390.00 2535428.70
Jumlah Bahan 5448228.70
HARGA SATUAN PEKERJAAN 5448228.70
1 M³ Pond. PC 3 120 x 110 x 50 cm , tul bwh . Dia 13 # 150 , ats dia 16 # 150
BAHAN :
Beton K 225 1.00 M³ 700000.00 700000.00
Besi Polos 275.00 Kg 9220.00 2535500.00
Bekisting 15.33 M² 165390.00 2535428.70
Jumlah Bahan 5770928.70
HARGA SATUAN PEKERJAAN 5770928.70
1 M³ Plat kanopi tebal 10 cm , ( tul . 8 # 20 dobel ) /Plat atap tebal 10 , ( tul . 8 # 20 dobel ) elv. 7,08
BAHAN :
Beton K 225 1.00 M³ 735000.00 735000.00
Besi Polos 62.00 Kg 9220.00 571640.00
Bekisting 10.00 M² 306095.00 3060950.00
Jumlah Bahan 4367590.00
HARGA SATUAN PEKERJAAN 4367590.00
1 M³ Balok latai 13 x 15 ( tul . 4 d 10 , sk . Dia 8 - 150 )
BAHAN :
Beton K 225 1.00 M³ 735000.00 735000.00
Besi Polos 215.00 Kg 9220.00 1982300.00
Bekisting 14.33 M² 306095.00 4387320.85
Jumlah Bahan 7104620.85
HARGA SATUAN PEKERJAAN 7104620.85
1 M³ Tangga Utama
BAHAN :
Beton K 225 1.00 M³ 735000.00 735000.00
Besi Polos 150.00 Kg 9220.00 1383000.00
Bekisting 10.33 M² 280245.00 2895827.63
Jumlah Bahan 5013827.63
HARGA SATUAN PEKERJAAN 5013827.63
1 M² Water Profing
BAHAN :
Water Profing 1.05 M² 34000.00 35700.00
Alat Bantu 1.00 Kg 10000.00 10000.00
Jumlah Bahan 45700.00
UPAH :
Pekerja 0.30 Oh 90000.00 27000.00
Tukang 1/2 Terampil 0.30 Oh 110000.00 33000.00
Kepala Tukang 0.03 Oh 125000.00 3750.00
Mandor 0.03 Oh 140000.00 3500.00
Jumlah Upah 67250.00
1 M' Pipa PVC klas AW dia 3/4" ( instl. Diatas plafond ring sistem )
BAHAN :
Pipa PVC tipe AW Ø 3/4" 1.20 M' 10000.00 12000.00
Jumlah Bahan 12000.00
UPAH :
Pekerja 0.04 Oh 90000.00 3240.00
Tukang Pipa 0.06 Oh 110000.00 6600.00
Kepala Tukang Pipa 0.01 Oh 125000.00 750.00
Mandor 0.00 Oh 140000.00 280.00
Jumlah Upah 10870.00
1 Titik Pipa air kotor PVC klas D dia 1 " ( sparing drain AC )
BAHAN :
Pipa PVC Klas D Ø 1" 1.20 M' 12500.00 15000.00
Perlengkapan 0.35 Ls 4375.00 1531.25
Jumlah Bahan 16531.25
UPAH :
Pekerja 0.04 Oh 90000.00 3240.00
Tukang Pipa 0.06 Oh 110000.00 6600.00
Kepala Tukang Pipa 0.01 Oh 125000.00 750.00
Mandor 0.00 Oh 140000.00 280.00
Jumlah Upah 10870.00
1 M' Pipa PVC klas D dia 1 1/4 " ( afur wstfl & pipa udara Sptnk)
BAHAN :
Pipa PVC Klas D Ø 1¼" 1.20 M' 13000.00 15600.00
Perlengkapan 0.35 Ls 4550.00 1592.50
Jumlah Bahan 17192.50
UPAH :
Pekerja 0.04 Oh 90000.00 3240.00
Tukang Pipa 0.06 Oh 110000.00 6600.00
Kepala Tukang Pipa 0.01 Oh 125000.00 750.00
Mandor 0.00 Oh 140000.00 280.00
Jumlah Upah 10870.00
314.00
volume koefisien durasi unit
0.25 1.00 5.00 0.25
0.25 240.00 5.00 60.00
0.25 15.33 5.00 3.83
#REF!
volume koefisien durasi unit
0.69 1.00 7.00 0.69
0.69 133.00 7.00 92.17
0.69 12.67 7.00 8.78
volume koefisien durasi unit
0.75 1.00 7.00 0.75
0.75 235.00 7.00 176.43
0.75 13.33 7.00 10.01
Kontraktor
PT. AMTA UTAMA KONTRAKTOR
Kontraktor
PT. AMTA UTAMA KONTRAKTOR
TOTAL BOBOT SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI JULI
NO. URAIAN PEKERJAAN
HARGA (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
III PEKERJAAN BETON 311,511,191 24.19 3.46 3.46 3.46 3.46 3.46 3.46 3.46
IV PEKERJAAN DINDING 239,308,681 18.58 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
VI PEKERJAAN ATAP 83,489,798 6.48 0.93 0.93 0.93 0.93 0.93 0.93 0.93
VII PEKERJAAN PLAFOND 89,197,820 6.93 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69
PEKERJAAN PENGUNCI /
VIII 20,648,755 1.60 0.32 0.32 0.32 0.32 0.32
PENGGANTUNG
RENCANA
RENCANA
IX PEKERJAAN LANTAI & DINDING KERAM 160,908,079 12.49 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83
X PEKERJAAN SANITARY 55,247,349 4.29 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54
XI PEKERJAAN PENGECATAN 54,293,039 4.22 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
XII PEKERJAAN PLUMBING 33,493,000 2.60 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
XIII PEKERJAAN LISTRIK 45,153,833 3.51 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27
XIV PEKERJAAN LAIN - LAIN 13,971,406 1.08 0.27 0.27 0.27 0.27
XV 0.00 - - - -
US 2016
RAKTOR
CH, ST
Balok B1 15 x 20 ( tul. 4 d 13 , sk. 8 - 200 )
sloef 0.15 0.20
panjang 33.33 kg 33.33
besi tulangan 4.00 dia 13.00 12.51 1.04 kg
Besi Begel dia 8.00 4.74 0.39 kg
Panjang Begel 0.80 m
Jumlah Begel 166.65
P. Kesel Begel 133.32 m