REKAPITULASI

RENCANA ANGGARAN BIAYA BAHAN & UPAH


PROYEK : PERANCANGAN & PERENCANAAN RUMAH TINGGAL 2 UNIT
LOKASI : PERUMAHAN CITRALAND CLUSTER TOSCA TREE BLOK HE/07 DAN H5/1

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN
(Rp.) (Rp.)
A PEKERJAAN BANGUNAN 1
I PENGUKURAN UNTUK SURVEY DATA RENCANA KE DUA BANGUNAN
3,500,000.00
II BONGKARAN ATAP DAN LAINNYA 6,798,410.00
III PEKERJAAN ARSITEKTUR BANGUNAN 1 33,815,739.18
IV PEKERJAAN PERBAIKAN PLAFOND 9,914,935.70
V PEKERJAAN PINTU DAN JENDELA 20,856,000.00
VI PEKERJAAN PENGECEKAN AIR KOTOR 1,829,500.00
VII PEKERJAAN ATAP 13,336,853.78
SUB TOTAL A 90,051,438.66 90,051,438.66
B PEKERJAAN BANGUNAN 2
PENGUKURAN UNTUK SURVEY DATA RENCANA KE DUA BANGUNAN
3,500,000.00
VIII PEKERJAAN ARSITEKTUR BANGUNAN 2 15,932,350.82
IX PEKERJAAN PLAFOND 9,421,851.25
X PEKERJAAN PINTU DAN JENDELA 18,595,795.00
XI PEKERJAAN MEKANIKAL & ELEKTRIKAL Bangunan 2 6,630,000.00
XII PEKERJAAN LAIN - LAIN DEKAT POHON KETAPANG KENCANA
3,770,212.25
XIII PEKERJAAN PENGECEKAN AIR KOTOR 1,829,500.00
XIV PEKERJAAN ATAP 13,336,853.78
SUB TOTAL B 73,016,563.09 73,016,563.09
JUMLAH A + B KEDUA BANGUNAN 163,068,001.75
DIBULATKAN 163,068,000.00
TERBILANG :

Seratus Enam Puluh Tiga Juta Enam Puluh Delapan Ribu Rupiah

Samarinda, 19 Januari 2023


Dibuat Oleh :

-
Estimator
RENCANA ANGGARAN BIAYA
PROYEK : PERANCANGAN & PERENCANAAN RUMAH TINGGAL 2 UNIT
LOKASI : PERUMAHAN CITRALAND CLUSTER TOSCA TREE BLOK HE/07 DAN H5/1

HARGA SATUAN JUMLAH HARGA TOTAL HARGA


NO. URAIAN PEKERJAAN SAT. VOLUME
(Rp) (Rp) (Rp)
I PEKERJAAN PENDAHULUAN KEDUA BANGUNAN
1 PENGUKURAN UNTUK SURVEY DATA RENCANA KE DUA BANGUNAN
m' 110.00 63,636.36 7,000,000.00
Sub Total 7,000,000.00 7,000,000.00
II PEKERJAAN BONGKARAN KEDUA BANGUNAN
1 Bongkaran Atap dan Lainya m2 63.76 106,625.00 6,798,410.00
Sub Total 6,798,410.00 6,798,410.00
III PEKERJAAN ARSITEKTUR BANGUNAN 1
PEKERJAAN DINDING
1 Pasangan Bataringan 1 : 2 Trasraam m2 45.36 147,249.00 6,679,214.64
3 Plesteran + Aci dinding 1 : 2 Trasraam m2 90.72 111,685.80 10,132,135.78
5 Pek. Cat dinding luar, setara Mowilex Weathercoat m2 112.17 65,621.00 7,360,379.47
6 Pek. Cat Dinding Dalam, setara Catylac m2 122.74 52,361.00 6,426,789.14
7 Pek. Cat Duco daun pintu m2 18.48 174,092.00 3,217,220.16
Sub Total 33,815,739.18 33,815,739.18
IV PEKERJAAN PERBAIKAN PLAFOND
1 Plafond Gipsumboard 9 mm + rangka hollow, Elephant m2 22.50 115,000.00 2,587,500.00
2 Plafond Kalsiboard 4mm + rangka hollow, Nusaboard WC m2 2.88 115,000.00 331,200.00
3 List plafond Gipsum m 78.32 20,000.00 1,566,400.00
4 Pek. Cat Plafond Gipsum dan Plafond exposed m2 103.70 52,361.00 5,429,835.70
Sub Total 9,914,935.70 9,914,935.70
V PEKERJAAN PINTU DAN JENDELA
1 Pintu Tipe P1 unit 1.00 4,083,450.00 4,083,450.00
2 Pintu Tipe P2 unit 1.00 3,420,950.00 3,420,950.00
3 Pintu Tipe P3 unit 1.00 2,314,700.00 2,314,700.00
4 Pintu Tipe P4 unit 2.00 1,942,200.00 3,884,400.00
5 Jendela Tipe J1 unit 2.00 2,758,450.00 5,516,900.00
6 Bouventlight BV1 unit 1.00 435,600.00 435,600.00
7 Roaster beton unit 24.00 50,000.00 1,200,000.00
Sub Total 20,856,000.00 20,856,000.00
VI PEKERJAAN PENGECEKAN AIR KOTOR
1 Pasang Pipa Air Kotor PVC AW Ø4" m' 13 56,500.00 734,500.00
2 Pasang Pipa Air Bekas PVC AW Ø3" m' 7 35,000.00 245,000.00
3 Pasang Pipa Air Hujan/ Bekas PVC AW Ø2" m' 20 35,000.00 700,000.00
4 Floor Drain dia. 3", Stainless unit 1 150,000.00 150,000.00
Sub Total 1,829,500.00 1,829,500.00
VII PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan m2 43 130,000.00 5,631,600.00
2 Pasang Atap Seng Metal setara "Multiroof" m2 43 117,707.14 5,099,073.43
3 Pasang Bubungan Metal m' 20 66,396.00 1,314,640.80
4 Pasang Listplank GRC m' 25 26,952.80 673,820.00
5 Cat Minyak Listplank GRC m2 5 123,543.91 617,719.55
Sub Total 13,336,853.78 13,336,853.78
TOTAL BANGUNAN 1 90,051,438.66
VIII PEKERJAAN ARSITEKTUR BANGUNAN 2
PEKERJAAN DINDING
1 Pasangan Bataringan 1 : 2 Trasraam m2 12.49 147,249.00 1,838,933.86
3 Plesteran + Aci dinding 1 : 2 Trasraam m2 24.98 111,685.80 2,789,598.56
6 Pek. Cat dinding luar, setara Mowilex Weathercoat m2 84.09 65,621.00 5,518,050.20
7 Pek. Cat Dinding Dalam, setara Catylac m2 78.38 52,361.00 4,104,039.47
8 Pek. Cat Duco daun pintu, setara Dana Gloss m2 9.66 174,092.00 1,681,728.72
Sub Total 15,932,350.82 15,932,350.82
IX PEKERJAAN PLAFOND
1 Plafond Gipsumboard 9 mm + rangka hollow, Elephant m2 45.25 115,000.00 5,203,750.00
2 Plafond Kalsiboard 4mm + rangka hollow, Nusa Board di wc m2 6.00 115,000.00 690,000.00
3 List plafond Gipsum m 42.23 20,000.00 844,600.00
4 Pek. Cat Plafond, setara Catylac m2 51.25 52,361.00 2,683,501.25
Sub Total 9,421,851.25 9,421,851.25
X PEKERJAAN PINTU DAN JENDELA
1 Pintu Tipe P3 unit 2.00 2,314,700.00 4,629,400.00
2 Pintu Tipe P4 unit 1.00 1,942,200.00 1,942,200.00
3 Jendela Tipe J2 unit 2.00 4,105,212.00 8,210,424.00
4 Jendela Tipe J3 unit 1.00 2,852,200.00 2,852,200.00
5 Jendela Tipe J4 unit 1.00 729,421.00 729,421.00
6 Bouven Light BV2 unit 1.00 232,150.00 232,150.00
Harga Untuk Mengganti atau finising ahkir
Sub Total 18,595,795.00 18,595,795.00
XI PEKERJAAN MEKANIKAL & ELEKTRIKAL Bangunan 2
PEKERJAAN AIR BERSIH
1 Pasang Pipa Air Bersih PVC AW Ø1/2" m' 45.00 5,000.00 225,000.00
2 Pasang Closet Duduk + Acc "Toto" unit 2.00 1,950,000.00 3,900,000.00
3 Pasang Kran Air + Shower unit 2.00 435,000.00 870,000.00
4 Pasang Kitchen Zinc + Acc unit 1.00 250,000.00 250,000.00
5 Pasang Kran Taman Ǿ1/2" unit 1.00 100,000.00 100,000.00
6 Pasang Pompa air (Shimitzu) + Acc unit 1.00 850,000.00 850,000.00
7 Pasang Kran Leher Angsa ls 1.00 435,000.00 435,000.00
Sub Total 6,630,000.00 6,630,000.00
XII PEKERJAAN LAIN - LAIN DEKAT POHON KETAPANG KENCANA
1 Pekerjaan Rumput Taman, Gajah Mini m2 8.00 50,000.00 400,000.00
2 Pekerjaan pembersihan akhir m2 127.50 12,117.50 1,544,981.25
3 Pekerjaan Meja dapur, Beton bertulang Ls 1.00 1,000,000.00 1,000,000.00
4 Pekerjaan Keramik Meja dapur 30x60 m2 1.80 140,072.05 252,129.69
5 Pekerjaan Keramik Meja dapur 60x60 m2 2.10 140,072.05 294,151.31
6 Pekerjaan Water proofing dak m2 7.97 35,000.00 278,950.00
Sub Total 3,770,212.25 3,770,212.25
XIII PEKERJAAN PENGECEKAN AIR KOTOR
1 Pasang Pipa Air Kotor PVC AW Ø4" m' 13.00 56,500.00 734,500.00
2 Pasang Pipa Air Bekas PVC AW Ø3" m' 7.00 35,000.00 245,000.00
3 Pasang Pipa Air Hujan/ Bekas PVC AW Ø2" m' 20.00 35,000.00 700,000.00
4 Floor Drain dia. 3", Stainless unit 1.00 150,000.00 150,000.00
Sub Total 1,829,500.00 1,829,500.00
XIV PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan m2 43.32 130,000.00 5,631,600.00
2 Pasang Atap Seng Metal setara "Multiroof" m2 43.32 117,707.14 5,099,073.43
3 Pasang Bubungan Metal m' 19.80 66,396.00 1,314,640.80
4 Pasang Listplank GRC m' 25.00 26,952.80 673,820.00
5 Cat Minyak Listplank GRC m2 5.00 123,543.91 617,719.55
Sub Total 13,336,853.78 13,336,853.78
TOTAL BANGUNAN 2 73,016,563.09
163,068,001.75
JADWAL PELAKSANAAN PEKERJAAN
( KURVA S )
PEKERJAAN : PERANCANGAN & PERENCANAAN RUMAH TINGGAL 2 UNIT
LOKASI : PERUMAHAN CITRALAND CLUSTER TOSCA TREE BLOK HE/07 DAN H5/1
ANGGARAN BIAYA : Rp. 163,068,001.75
WAKTU PELAKSANAAN : 90 hari kalender

MINGGU KE
BOBOT
FEBUARI 2023 MARET 2023 APRIL 2023
NO URAIAN PEKERJAAN NILAI PEKERJAAN PEKERJA KETERANGAN
12-18 19-25 26-2 3-9 10-16 17-23 24-30 31-6 7-13 14-20 21-27 28-4
AN (%)
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6
I PENGUKURAN UNTUK SURVEY DATA RENCANA KE DUA BANGUNAN Rp 7,000,000.00 4.3 4.293
II BONGKARAN ATAP DAN LAINNYA Rp 6,798,410.00 4.2 4.169
III PEKERJAAN ARSITEKTUR BANGUNAN 1 Rp 33,815,739.18 20.7 6.912 6.912 6.912
IV PEKERJAAN PERBAIKAN PLAFOND Rp 9,914,935.70 6.1 1.520 1.520 1.520 1.520
V PEKERJAAN PINTU DAN JENDELA Rp 20,856,000.00 12.8 2.558 2.558 2.558 2.558 2.558
VI PEKERJAAN PENGECEKAN AIR KOTOR Rp 1,829,500.00 1.1 0.561 0.561
VII PEKERJAAN ATAP Rp 13,336,853.78 8.2 2.726 2.726 2.726
VIII PEKERJAAN ARSITEKTUR BANGUNAN 2 Rp 15,932,350.82 9.8 9.770
IX PEKERJAAN PLAFOND Rp 9,421,851.25 5.8 5.778
X PEKERJAAN PINTU DAN JENDELA Rp 18,595,795.00 11.4 11.404
XI PEKERJAAN MEKANIKAL & ELEKTRIKAL Bangunan 2 Rp 6,630,000.00 4.1 4.066
XII PEKERJAAN LAIN - LAIN DEKAT POHON KETAPANG KENCANA Rp 3,770,212.25 2.3 2.312
XIII PEKERJAAN PENGECEKAN AIR KOTOR Rp 1,829,500.00 1.1 0.561 0.561
XIV PEKERJAAN ATAP Rp 13,336,853.78 8.2 8.179
JUMLAH TOTAL Rp 163,068,001.75 100.0
JUMLAH 4.29 11.08 6.91 9.47 4.08 4.08 4.08 7.93 3.85 12.50 19.49 12.24
PROGRESS RENCANA
KUMULATIF 4.3 15.4 22.3 32 36 40 44 52 56 68 88 100
GODEX

Samarinda, 19 Januari 2023

Estimator
0852 4797 1448
DAFTAR HARGA SATUAN UPAH DAN BAHAN TH.2022
PEKERJAAN : PERANCANGAN & PERENCANAAN RUMAH TINGGAL 2 UNIT
LOKASI : PERUMAHAN CITRALAND CLUSTER TOSCA TREE BLOK HE/07 DAN H5/1

H. SATUAN
NO. URAIAN SATUAN KETERANGAN
Rp.
I. UPAH:
1 Mandor Hari 200,000.00 Standar Kota SMD 2022
2 Kepala Tukang Hari 190,000.00 Standar Kota SMD 2022
3 Tukang Kayu Hari 185,000.00 Standar Kota SMD 2022
4 Tukang Batu Hari 185,000.00 Standar Kota SMD 2022
5 Tukang Besi Hari 185,000.00 Standar Kota SMD 2022
6 Tukang Cat Hari 175,000.00 Standar Kota SMD 2022
7 Tukang Keramik Hari 175,000.00 Standar Kota SMD 2022
8 Tukang Listrik Hari 175,000.00 Standar Kota SMD 2022
9 Pekerja Hari 135,500.00 Standar Kota SMD 2022

II. BAHAN
1 Semen PC ( @ 50 Kg ) Zak 73,000.00 Standar Kota SMD 2022
2 Semen Putih ( @ 50 Kg) Zak 152,250.00 Standar Kota SMD 2022
3 Pasir Urug Putih M³ 64,500.00 Standar Kota SMD 2022
4 Pasir Mahakam ( Rp. 600.000 / Rit / 2 M3 ) M³ 594,000.00 Standar Kota SMD 2022
5 Pasir Tenggarong ( Rp 800.000 / Rit / 2 M3 ) M³ 753,000.00 Standar Kota SMD 2022
6 Kerikil Beton ( Rp 1.0380.000 / Rit / 3 M3 ) M³ 1,038,000.00 Standar Kota SMD 2022
7 Batu Gunung ( Rp. 750.000 / Rit / 2 M3 ) M³ 96,250.00 Standar Kota SMD 2022
8 Batu Padas ( Rp.750.000 / Rit / 3 M3 ) M³ 166,666.67 Standar Kota SMD 2022
9 Batu Bata Bh 950.00 Standar Kota SMD 2022
10 Marmer Bakar 10 x 20 M² 185,000.00 Standar Kota SMD 2022
11 Batu Alam M² 185,000.00 Standar Kota SMD 2022
12 Paving Block m2 84,000.00 Standar Kota SMD 2022
13 Besi Beton Polos Ex KS Kg 9,215.77 Standar Kota SMD 2022
14 Kawat Beton Kg 20,000.00 Standar Kota SMD 2022
15 Paku 2 - 6 Kg 16,000.00 Standar Kota SMD 2022
16 Pipa Sambungan Pancang Bh 20,000.00 Standar Kota SMD 2022
17 Kayu Balok klas IV ( bekesting ) M³ 2,000,000.00 Standar Kota SMD 2022
18 Kayu Papan klas IV ( bekesting ) M³ 2,000,000.00 Standar Kota SMD 2022
19 Kayu Balok Meranti M³ 2,000,000.00 Standar Kota SMD 2022
20 Kayu Papan Kruing M³ 2,000,000.00 Standar Kota SMD 2022
21 Kayu Papan Ulin M³ 4,000,000.00 Standar Kota SMD 2022
22 Kayu Balok Ulin M³ 3,800,000.00 Standar Kota SMD 2022
23 Kusen Alumunium Putih 4" setara "alexindo" M' 125,000.00 Standar Kota SMD 2022
24 Kusen Ulin M' 75,000.00 Standar Kota SMD 2022
25 Daun Pintu Panil Bengkirai 80 x 210 Unt 950,000.00 Standar Kota SMD 2022
26 Daun Pintu Pabrikasi Unt 2,500,000.00 Standar Kota SMD 2022
27 Daun Pintu Double Plywood Unt 850,000.00 Standar Kota SMD 2022
28 Daun Pintu KM / WC Siring Ulin Unit 850,000.00 Standar Kota SMD 2022
29 Daun Jendela Alumunium Putih Unit 750,000.00 Standar Kota SMD 2022
30 Daun Jendela Besar Unit 400,000.00 Standar Kota SMD 2022
31 Engsel Pintu 4" Set 75,000.00 Standar Kota SMD 2022
32 Engsel Jendela 3" Set 30,000.00 Standar Kota SMD 2022
33 Kunci Putar Set 90,000.00 Standar Kota SMD 2022
34 Kunci Pelor setara SES Set 125,000.00 Standar Kota SMD 2022
35 Kunci Tanam 2 slag setara SES Set 350,000.00 Standar Kota SMD 2022
36 Hak Angin Set 15,000.00 Standar Kota SMD 2022
37 Hand vatten Set 10,000.00 Standar Kota SMD 2022
38 Handle Pintu Bh 250,000.00 Standar Kota SMD 2022
39 Rel Pintu Geser Set 250,000.00 Standar Kota SMD 2022
40 Grendel Pintu Set 40,000.00 Standar Kota SMD 2022
41 Grendel Tanam Set 42,500.00 Standar Kota SMD 2022
42 Kaca bening 5mm M² 115,000.00 Standar Kota SMD 2022
43 Kaca bening 8mm M² 750,000.00 Standar Kota SMD 2022
44 Kaca Es 5 mm M² 125,000.00 Standar Kota SMD 2022
45 Genteng Metal setara Sakura Roof lbr 60,000.00 Standar Kota SMD 2022
47 Bubungan bh 34,000.00 Standar Kota SMD 2022
51 Mortar Compound bh 26,000.00 Standar Kota SMD 2022
52 Pigment bh 38,500.00 Standar Kota SMD 2022
53 Aluminium Foil 1 Sisi M² 7,819.67 Standar Kota SMD 2022
54 Triplek 4 mm Lbr 32,500.00 Standar Kota SMD 2022
55 Triplek 6 mm Lbr 44,500.00 Standar Kota SMD 2022
56 Paku Genteng Kg 200.00 Standar Kota SMD 2022
57 Cat Minyak Kg 60,000.00 Standar Kota SMD 2022
58 Cat Dasar Kg 15,000.00 Standar Kota SMD 2022
59 Glass Block Bh 20,000.00 Standar Kota SMD 2022
60 Cat Tembok Interior Kg 23,000.00 Standar Kota SMD 2022
61 Cat Tembok Eksterior Kg 74,000.00 Standar Kota SMD 2022
62 Cat Tembok EMCO Eksterior Kg 60,000.00 Standar Kota SMD 2022
63 Dempol Kayu Kg 55,000.00 Standar Kota SMD 2022
64 Amplas Lbr 3,500.00 Standar Kota SMD 2022
65 Menie Kayu Kg 5,000.00 Standar Kota SMD 2022
66 Residu Kg 5,500.00 Standar Kota SMD 2022
67 Wood Filler ( Cat Dasar/ Dempul ) Kg 25,000.00 Standar Kota SMD 2022
68 Wood Stain Kg 50,000.00 Standar Kota SMD 2022
69 Pelitur Kg 36,000.00 Standar Kota SMD 2022
70 Sainding Sailler Kg 35,000.00 Standar Kota SMD 2022
71 Thinner A Spesial Ltr 16,000.00 Standar Kota SMD 2022
72 Clear Dof Kg 33,500.00 Standar Kota SMD 2022
73 Paku Gipsum Kg 11,000.00 Standar Kota SMD 2022
74 Keramik 40x40 roman M² 120,000.00 Standar Kota SMD 2022
75 Keramik 60x60 roman M² 135,000.00 Standar Kota SMD 2022
76 Keramik setara Roman 30x30 M² 115,000.00 Standar Kota SMD 2022
77 Keramik setara Roman 25x25 ( Utk KM/WC ) M² 100,000.00 Standar Kota SMD 2022
78 Keramik setara Roman 25x40 cm ( Motif ) M² 115,000.00 Standar Kota SMD 2022
79 Roaster beton Bh 50,000.00 Standar Kota SMD 2022
80 List Keramik Bh 8,000.00 Standar Kota SMD 2022
81 Gipsum Polos 9 mm M² 65,000.00 Standar Kota SMD 2022
82 List plafon gipsum 10Cm M' 25,000.00 Standar Kota SMD 2022
83 Closed Duduk Set 1,950,000.00 Standar Kota SMD 2022
84 Closed Jongkok Bh 250,000.00 Standar Kota SMD 2022
85 Bak Mandi fiber Bh 500,000.00 Standar Kota SMD 2022
86 Bathtube + Acc Setara TOTO Bh 3,000,000.00 Standar Kota SMD 2022
87 Pompa Shimitzu 135 watt Bh 850,000.00 Standar Kota SMD 2022
88 Tangki Air Fiber glass 750 Liter Bh 1,000,000.00 Standar Kota SMD 2022
89 Washtafel + Meja Bh 425,000.00 Standar Kota SMD 2022
90 Shower Screen+ Kran + Aksesoris Bh 1,250,000.00 Standar Kota SMD 2022
91 Shower untuk Closed (bidet) Bh 60,000.00 Standar Kota SMD 2022
92 Kitchen Sink 1 Lubang Bh 250,000.00 Standar Kota SMD 2022
93 Kitchen Sink 2 Lubang Kecil Bh 450,000.00 Standar Kota SMD 2022
94 Kitchen Sink 2 Lubang Besar Bh 550,000.00 Standar Kota SMD 2022
95 Pipa PVC Dia 4 " M1 56,500.00 Standar Kota SMD 2022
96 Pipa PVC Dia 3 " M1 35,000.00 Standar Kota SMD 2022
97 Pipa PVC Dia 2" M1 19,500.00 Standar Kota SMD 2022
98 Pipa PVC Dia 1/2" M1 5,000.00 Standar Kota SMD 2022
99 Pipa PVC Dia 1 1/2" M1 16,250.00 Standar Kota SMD 2022
100 Pipa Galvanis Dia 3/4" M1 6,000.00 Standar Kota SMD 2022
101 Pasang Stop Kran 1/2" + instalasi Bh 100,000.00 Standar Kota SMD 2022
102 Pasang Stop kran Leher angsa untuk Kitchen Zinc + instalasi Bh 435,000.00 Standar Kota SMD 2022
103 Floor Drain Bh 150,000.00 Standar Kota SMD 2022
104 Roof Drain Bh 85,000.00 Standar Kota SMD 2022
105 Kalsiboard Grc Lbr 65,000.00 Standar Kota SMD 2022
106 Lampu Downlight 4" bh 45,000.00 Standar Kota SMD 2022
107 Lampu Downlight 3" bh 38,500.00 Standar Kota SMD 2022
108 Stop kontak bh 35,000.00 Standar Kota SMD 2022
109 Saklar tunggal bh 15,000.00 Standar Kota SMD 2022
110 Saklar ganda bh 18,000.00 Standar Kota SMD 2022
111 Tee Doz bh 5,000.00 Standar Kota SMD 2022
112 Pipa conduit Btg 7,000.00 Standar Kota SMD 2022
113 Kabel NYM 3 X 2.5 MM Rol 700,000.00 Standar Kota SMD 2022
114 fitting lampu bh 10,000.00 Standar Kota SMD 2022

Samarinda, 19 Januari 2023


Dibuat oleh,

-
Estimator
ANALISA HARGA SATUAN PEKERJAAN
PROYEK : PERANCANGAN & PERENCANAAN RUMAH TINGGAL 2 UNIT
LOKASI : PERUMAHAN CITRALAND CLUSTER TOSCA TREE BLOK HE/07 DAN H5/1

HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)

1 10 M² Pembersihan Lapangan
0.850 OH Pekerja 135,500.00 115,175.00
0.030 OH Mandor 200,000.00 6,000.00
1 m2 = 1/10 x JUMLAH 121,175.00 12,117.50
2 10 M' Pasang Bowplank
0.060 m3 Papan 2,000,000.00 120,000.00
0.025 m3 Tiang 5/7 2,000,000.00 50,000.00
0.100 kg Paku 185,000.00 18,500.00
0.400 OH Tk. Kayu 185,000.00 74,000.00
0.080 OH Kepala Tukang 190,000.00 15,200.00
0.280 OH Pekerja 135,500.00 37,940.00
0.014 OH Mandor 200,000.00 2,800.00
1 m2 = 1/10 x JUMLAH 129,940.00 188,500.00 26,350.00
3 1 M³ Galian Tanah
0.750 OH Pekerja 135,500.00 101,625.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 106,625.00 106,625.00
4 1 M³ Urugan Tanah Kembali
0.500 OH Pekerja 135,500.00 67,750.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 72,750.00 72,750.00
5 1 M3 Urugan Pasir
1.000 m3 Pasir Urug 64,500.00 64,500.00
0.300 OH Pekerja 135,500.00 40,650.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 42,650.00 64,500.00 107,150.00
6 1 M3 Urugan Tanah
1.000 m3 Tanah Urug 45,000.00 45,000.00
0.500 OH Pekerja 135,500.00 67,750.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 30,000.00 45,000.00 75,000.00
7 1 M3 Pasang Aanstamping
1.100 m3 Bt. Gunung 96,250.00 105,875.00
0.500 m3 Pasir 64,500.00 32,250.00
1.530 OH Pekerja 135,500.00 207,315.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 222,315.00 138,125.00 360,440.00
8 1 M³ Pasangan Batu Gunung (1:4)
1.100 m3 Bt. Gunung 166,666.67 183,333.33
3.000 zak Semen Pc @ 50kg 73,000.00 219,000.00
0.600 m3 Pasir pasang 594,000.00 356,400.00
1.750 OH Pekerja 135,500.00 237,125.00
0.100 OH Mandor 200,000.00 20,000.00
0.300 OH Tk. Batu 185,000.00 55,500.00
0.050 OH Kep. tukang 190,000.00 9,500.00
JUMLAH 322,125.00 758,733.33 1,080,858.33
9 1 Titik Tiang Pancang 10/10 - 1m
0.010 m3 Ky. Balok ulin 3,800,000.00 38,000.00
0.105 OH Tk. Kayu 185,000.00 19,425.00
0.011 OH Kep. Tukang 190,000.00 2,090.00
0.580 OH Pekerja 135,500.00 78,590.00
0.015 OH Mandor 200,000.00 3,000.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 113,105.00 38,000.00 151,105.00
10 1 Titik Tiang Pancang 10/10 - 2m
0.020 m3 Ky. Balok ulin 3,800,000.00 76,000.00
0.145 OH Tk. Kayu 185,000.00 26,825.00
0.020 OH Kep. Tukang 190,000.00 3,800.00
0.400 OH Pekerja 135,500.00 54,200.00
0.025 OH Mandor 200,000.00 5,000.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 99,825.00 76,000.00 175,825.00
11 1 Titik Tiang Pancang Ulin 10/10 - 4m
0.040 m3 Ky. Balok ulin 3,800,000.00 152,000.00
0.100 OH Tk. Kayu 185,000.00 18,500.00
0.029 OH Kep. Tukang 190,000.00 5,510.00
0.500 OH Pekerja 135,500.00 67,750.00
0.039 OH Mandor 200,000.00 7,800.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 109,560.00 152,000.00 261,560.00
12 1 Titik Tiang Pancang Ulin 10/10 - 8m
0.080 m3 Ky. Balok ulin 3,800,000.00 104,000.00
0.100 OH Tk. Kayu 185,000.00 18,500.00
0.029 OH Kep. Tukang 190,000.00 5,510.00
0.500 OH Pekerja 135,500.00 67,750.00
0.039 OH Mandor 200,000.00 7,800.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 20,000.00 104,000.00 124,000.00

Analisa hal 1 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
13 1 M3 Beton 1 : 3 : 5
4.000 zak Semen Pc @ 50kg 73,000.00 292,000.00
0.950 m3 Kerikil 1,038,000.00 986,100.00
0.570 m3 Pasir beton 594,000.00 338,580.00
0.500 OH Tk. Batu 185,000.00 92,500.00
0.050 OH Kepala tukang 190,000.00 9,500.00
1.500 OH Pekerja 135,500.00 203,250.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 300,000.00 1,616,680.00 1,916,680.00
14 1 M3 Beton 1 : 2 : 3
6.000 zak Semen Pc @ 50 Kg 73,000.00 238,000.00
0.700 m3 Kerikil 838,000.00 386,600.00
0.540 m3 Pasir beton 594,000.00 270,760.00
1.500 OH Pekerja 135,500.00 203,250.00
0.250 OH Mandor 200,000.00 50,000.00
0.600 OH Tukang Batu 185,000.00 111,000.00
0.030 OH Kepala Tukang 190,000.00 5,700.00
Catatan :
1.000 jam Molen 30,000.00 30,000.00
1.000 jam Vibrator 25,000.00 25,000.00
1.000 Alat Bantu 10,000.00 10,000.00
JUMLAH 300,000.00 960,360.00 1,260,360.00
15 1 M3 Stuut Werk
0.220 m3 Kayu Stuut 1,800,000.00 396,000.00
2.000 kg Paku 16,000.00 32,000.00
2.000 OH Tukang kayu 185,000.00 370,000.00
0.400 OH Kepala tukang 190,000.00 76,000.00
3.000 OH Pekerja 135,500.00 406,500.00
0.020 OH Mandor 200,000.00 4,000.00
JUMLAH 856,500.00 428,000.00 1,284,500.00
16 100 kg besi
100.000 kg Besi beton 9,215.77 921,576.79
2.000 kg Kawat 20,000.00 40,000.00
0.850 OH Tukang besi 185,000.00 157,250.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.750 OH Pekerja 135,500.00 101,625.00
287,375.00 961,576.79 1,248,951.79
1 kg besi = 1/100 x JUMLAH 2,873.75 12,489.52
17 10 m2 Begisting (dipakai 2x)
0.400 m3 Kayu 1,800,000.00 720,000.00
1.100 m2 plywood 6 mm 44,500.00 48,950.00
4.000 kg Paku 16,000.00 64,000.00
4.000 OH Tukang kayu 185,000.00 740,000.00
0.500 OH Kepala tukang 190,000.00 95,000.00
2.000 OH Pekerja 135,500.00 271,000.00
0.100 OH Mandor 200,000.00 20,000.00
Bongkar Siram
3.000 OH Pekerja 135,500.00 406,500.00
1,532,500.00 832,950.00 2,365,450.00
1 m2 = 1/20 x JUMLAH 76,625.00 41,647.50 118,272.50
18 1 M2 Pasangan batu bata 1:4
55.000 bh Batu bata 950.00 52,250.00
0.230 zak PC semen @ 50 kg 73,000.00 16,790.00
0.043 m3 Pasir pasang 594,000.00 25,542.00
0.100 OH Tukang batu 185,000.00 18,500.00
0.320 OH Pekerja 135,500.00 43,360.00
0.015 OH Mandor 200,000.00 3,000.00
0.010 OH Kepala tukang 190,000.00 1,900.00
JUMLAH 66,760.00 94,582.00 161,342.00
19 1 M2 Pasangan batu bata 1:2
55.000 bh Batu bata 950.00 40,250.00
0.379 zak PC semen @ 50 kg 73,000.00 17,667.00
0.038 m3 Pasir pasang 594,000.00 22,572.00
0.100 OH Tukang batu 185,000.00 18,500.00
0.320 OH Pekerja 135,500.00 43,360.00
0.015 OH Mandor 200,000.00 3,000.00
0.010 OH Kepala tukang 190,000.00 1,900.00
JUMLAH 66,760.00 80,489.00 147,249.00
20 1 M' Parit Pasangan batu bata 1:4
30.000 bh Batu bata 950.00 28,500.00
0.120 zak PC semen @ 50 kg 73,000.00 8,760.00
0.120 m3 Pasir pasang 594,000.00 71,280.00
0.150 OH Tukang batu 185,000.00 27,750.00
0.400 OH Pekerja 135,500.00 54,200.00
0.020 OH Mandor 200,000.00 4,000.00
0.015 OH Kepala tukang 190,000.00 2,850.00
JUMLAH 88,800.00 108,540.00 197,340.00
21 1 M2 Plasteran t. = 25 mm 1:4
0.174 zak PC semen @ 50 kg 73,000.00 12,672.80
0.028 m3 Pasir pasang 594,000.00 16,632.00
0.200 OH Tukang batu 185,000.00 37,000.00
0.020 OH Kepala tukang 190,000.00 3,800.00
0.250 OH Pekerja 135,500.00 33,875.00
0.013 OH Mandor 200,000.00 2,500.00
JUMLAH 77,175.00 29,304.80 106,479.80
22 1 M2 Plasteran t = 25mm 1:2
0.286 zak PC semen @ 50 kg 73,000.00 20,848.80

Analisa hal 2 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
0.023 m3 Pasir pasang 594,000.00 13,662.00
0.200 OH Tukang batu 185,000.00 37,000.00
0.020 OH Kepala tukang 190,000.00 3,800.00
0.250 OH Pekerja 135,500.00 33,875.00
0.013 OH Mandor 200,000.00 2,500.00
JUMLAH 77,175.00 34,510.80 111,685.80
23 1 M2 Pasangan Glass Block

Analisa hal 3 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
0.168 zak PC semen @ 50 kg 73,000.00 12,264.00
0.140 m3 Pasir pasang 594,000.00 83,160.00
25.000 bh Glass Block 20,000.00 500,000.00
0.200 OH Tukang batu 185,000.00 37,000.00
0.100 OH Kepala tukang 190,000.00 19,000.00
0.400 OH Pekerja 135,500.00 54,200.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 115,200.00 595,424.00 710,624.00
24 1 M2 Afwerking beton
0.192 zak PC semen @ 50 kg 73,000.00 14,016.00
0.009 m3 Pasir pasang 594,000.00 5,346.00
0.200 OH Tukang batu 185,000.00 37,000.00
0.020 OH Kepala tukang 190,000.00 3,800.00
0.400 OH Pekerja 135,500.00 54,200.00
0.020 OH Mandor 200,000.00 4,000.00
JUMLAH 99,000.00 19,362.00 118,362.00
25 1 M2 Atap genteng metal
1.400 lbr Genteng 60,000.00 84,000.00
10.000 bh paku 200.00 2,000.00
0.200 OH Tukang kayu 185,000.00 37,000.00
0.022 OH Kepala tukang 190,000.00 4,180.00
0.150 OH Pekerja 135,500.00 20,325.00
0.005 OH Mandor 200,000.00 1,000.00
JUMLAH 62,505.00 86,000.00 148,505.00
26 1 M' Bubungan
0.769 lbr Bubungan/nok metal 34,000.00 26,146.00
5.000 bh paku 200.00 1,000.00
73,000.00 -
0.010 OH Kepala tukang 190,000.00 1,900.00
0.050 OH Tukang batu 185,000.00 9,250.00
0.200 OH Pekerja 135,500.00 27,100.00
0.005 OH Mandor 200,000.00 1,000.00
JUMLAH 39,250.00 27,146.00 66,396.00
27 1 Unit Pintu P1
8.850 m' Kusen Alum putih 4" 125,000.00 1,106,250.00
2.000 unit Daun pintu 950,000.00 1,900,000.00
3.000 set Engsel pintu 75,000.00 225,000.00
1.000 set Kunci pelor 2 slag setara SES 125,000.00 125,000.00
2.000 set Handle pintu 250,000.00 500,000.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 3,856,250.00 4,083,450.00
28 1 Unit Pintu P2
7.950 m' Kusen Alum putih 4" 125,000.00 993,750.00
1.000 unit Daun pintu 950,000.00 950,000.00
1.000 unit Daun Jendela Alum. 750,000.00 750,000.00
2.000 set Engsel pintu 75,000.00 150,000.00
1.000 set Kunci 2 slag setara SES 350,000.00 350,000.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 3,193,750.00 3,420,950.00
29 1 Unit Pintu P3
5.100 m' Kusen Alum putih 4" 125,000.00 637,500.00
1.000 unit Daun pintu 950,000.00 950,000.00
1.000 set Kunci 2 slag setara SES 350,000.00 350,000.00
2.000 set Engsel pintu 75,000.00 150,000.00

Analisa hal 4 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 2,087,500.00 2,314,700.00
30 1 Unit Pintu P4
5.000 m' Kusen Alum putih 4" 125,000.00 625,000.00
1.000 unit Daun pintu siring ulin 850,000.00 850,000.00
2.000 set Engsel pintu 75,000.00 150,000.00
1.000 set Kunci bulat 90,000.00 90,000.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 1,715,000.00 1,942,200.00
33 1 Unit J1
8.250 m' Kusen Alum putih 4" 125,000.00 1,031,250.00
2.000 unit Slimar Daun jendela 750,000.00 1,500,000.00
- m2 Kaca bening 5 mm 250,000.00 -
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 2,531,250.00 2,758,450.00
34 1 Unit J2
8.900 m' Kusen Alum putih 4" 125,000.00 1,112,500.00
2.000 unit Slimar Daun jendela 1,250,000.00 2,500,000.00
2.309 m2 Kaca bening 5 mm 115,000.00 265,512.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 3,878,012.00 4,105,212.00
35 1 Unit J3
9.000 m' Kusen Alum putih 4" 125,000.00 1,125,000.00
2.000 unit Slimar Daun jendela 750,000.00 1,500,000.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 2,625,000.00 2,852,200.00
36 1 Unit J4
3.700 m' Kusen Alum putih 4" 125,000.00 462,500.00
0.345 m2 Kaca bening 5 mm 115,000.00 39,721.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 502,221.00 729,421.00
38 1 Unit BV 1
1.600 m' Kusen Alum putih 4" 125,000.00 200,000.00
0.168 m2 Kaca es 5 mm 50,000.00 8,400.00
0.700 OH Tukang kayu 185,000.00 129,500.00
0.150 OH Kepala tukang 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 208,400.00 435,600.00
39 1 Stoper
- -
0.099 m2 Trasport 50,000.00 4,950.00
0.700 OH Tukang Batu 185,000.00 129,500.00
0.150 OH Buruh Angkat 190,000.00 28,500.00
0.400 OH Pekerja 135,500.00 54,200.00
0.075 OH Mandor 200,000.00 15,000.00
JUMLAH 227,200.00 4,950.00 232,150.00

Analisa hal 5 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
40 1 M' lisplank, Calsy 20x250/1cm
0.014 m3 Kayu Bengkirai 24,500.00 352.80
0.100 kg Paku 16,000.00 1,600.00
0.200 OH Tukang kayu 185,000.00 37,000.00
0.050 OH Kepala Tukang 190,000.00 9,500.00
0.100 OH Pekerja 135,500.00 13,550.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 25,000.00 1,952.80 26,952.80
41 10 M2 Pek. Menie kayu 2x jalan
2.400 kg Menie kayu 5,000.00 12,000.00
1.500 OH Tukang cat 175,000.00 262,500.00
0.050 OH Kepala Tukang 190,000.00 9,500.00
0.500 OH Pekerja 135,500.00 67,750.00
0.005 OH Mandor 200,000.00 1,000.00
340,750.00
340,750.00 12,000.00 352,750.00
1 m2 = 1/10 x JUMLAH 35,275.00
42 1 M2 Pek. Cat dinding dalam/plafond
dengan cat tembok Mowilex
Upah cat / menggosok
0.260 kg Cat tembok 23,000.00 5,980.00
0.260 kg Plamir 36,000.00 9,360.00
0.500 lbr Amplas 3,500.00 1,750.00
0.280 OH Tukang cat 175,000.00 49,000.00
0.030 OH kepala tukang 190,000.00 5,700.00
0.160 OH Pekerja 135,500.00 21,680.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 35,271.00 17,090.00 52,361.00
43 1 M2 Pek. cat dinding Luar
dengan cat tembok Mowilex Watercoat
Upah cat / menggosok
0.260 kg Cat tembok 74,000.00 19,240.00
0.260 kg Plamir 36,000.00 9,360.00
0.500 lbr Amplas 3,500.00 1,750.00
0.280 OH Tukang cat 175,000.00 49,000.00
0.030 OH kepala tukang 190,000.00 5,700.00
0.160 OH Pekerja 135,500.00 21,680.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 35,271.00 30,350.00 65,621.00
44 1 M2 Melamik Kusen, Daun Pintu dan Lumbersering
dengan melamik kayu setara Ultran Lazur
Upah cat / menggosok
0.287 kg Cat Minyak 60,000.00 17,202.00
0.080 kg Dempul 55,000.00 4,400.00
0.060 ltr Thinner 16,000.00 960.00
0.150 lbr Amplas 3,500.00 525.00
0.030 ltr Thinner A Spesial 16,000.00 480.00
0.150 lbr Amplas 3,500.00 525.00
0.510 OH Tukang cat - -
0.045 OH kepala tukang - -
0.300 OH Pekerja - -
0.150 OH Mandor - -
JUMLAH 150,000.00 24,092.00 174,092.00
45 1 M2 Pek. cat minyak
dengan cat minyak Altec
0.287 kg Cat Minyak 30,000.00 8,601.00
0.080 kg Dempul 55,000.00 4,400.00
0.060 ltr Thinner 16,000.00 960.00
0.150 lbr Amplas 175,000.00 26,250.00
0.340 OH Tukang cat 175,000.00 59,500.00
0.030 OH Kepala tukang 190,000.00 5,700.00
0.200 OH Pekerja 135,500.00 27,100.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 83,332.91 40,211.00 123,543.91
46 1 M2 memasang keramik
setara Roman 30x30
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 Keramik 30x30 115,000.00 115,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
upahx0,35 JUMLAH 88,790.00 131,282.05 220,072.05

Analisa hal 6 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
47 1 M2 memasang keramik
setara Roman 25x25
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 Keramik 100,000.00 100,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 88,790.00 116,282.05 205,072.05
48 1 M2 memasang keramik
setara Roman 25x40
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 Keramik 115,000.00 115,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 88,790.00 131,282.05 220,072.05
49 1 M2 memasang keramik
setara Granite 40x40
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 Keramik 120,000.00 120,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 88,790.00 136,282.05 225,072.05
50 1 M' memasang keramik List
setara Roman
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
5.000 Bh Keramik 8,000.00 40,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 22,197.50 56,282.05 78,479.55
51 1 M2 memasang kERAMIK
60 x 60 setara ROMAN
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 keramik 135,000.00 35,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 88,790.00 51,282.05 140,072.05
61 1 M2 memasang keramik
setara Roman 25x45 (Motif)
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak Semen putih 152,250.00 3,045.00
1.000 m2 Keramik 115,000.00 115,000.00
0.450 OH Tukang Keramik 175,000.00 78,750.00
0.050 OH Kepala tukang 190,000.00 9,500.00
0.950 OH Pekerja 135,500.00 128,725.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 76,581.38 131,282.05 207,863.43
62 1 M' Pasang Plint Lantai Kayu
1.000 m' Kayu Plint Lantai 10,000.00 10,000.00
0.010 kg Paku 16,000.00 160.00
0.500 OH Pekerja 135,500.00 67,750.00
0.100 OH Tukang kayu 185,000.00 18,500.00
0.015 OH Kepala Tukang 190,000.00 2,850.00
0.005 OH Mandor 200,000.00 1,000.00
JUMLAH 44,428.31 10,160.00 54,588.31
52 1 M' Pasang Plint Lantai Keramik
1.000 m' Keramik 60x60/6 10,000.00 10,000.00
0.010 kg Paku 12,500.00 125.00
0.500 OH Pekerja 135,500.00 67,750.00
0.100 OH Tukang kayu 185,000.00 18,500.00
0.015 OH Kepala Tukang 190,000.00 2,850.00
0.005 OH Mandor 200,000.00 1,000.00
JUMLAH 10,000.00 10,125.00 20,125.00

Analisa hal 7 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
53 1 M2 Pasang Paving Block
1.000 m2 Paving block 84,000.00 84,000.00
0.035 m3 Pasir pasang 594,000.00 20,790.00
0.600 OH Pekerja 135,500.00 81,300.00
0.100 OH Tukang Batu 185,000.00 18,500.00
JUMLAH 99,800.00 104,790.00 204,590.00
54 1 M2 Pasang Batu Alam
0.025 m3 Spesi 1 : 4 529,482.00 13,237.05
0.020 zak PC semen @ 50 kg 73,000.00 1,460.00
1.000 m2 Batu Alam 185,000.00 185,000.00
0.250 OH Tukang Keramik 175,000.00 43,750.00
0.025 OH Kepala tukang 190,000.00 4,750.00
0.500 OH Pekerja 135,500.00 67,750.00
0.025 OH Mandor 200,000.00 5,000.00
JUMLAH 143,075.00 199,697.05 342,772.05
55 1 M3 Spesi 1 : 4
7.250 zak PC semen @ 50 kg 73,000.00 529,250.00
1.160 m3 Pasir pasang 200.00 232.00
JUMLAH - 529,482.00 529,482.00
56 1 M2 Plafond Gypsum Polos 9 mm + rangka
0.011 m3 Kayu rangka 2,000,000.00 22,000.00
0.347 lbr Gypsum Polos 65,000.00 22,569.44
0.020 kg Paku 16,000.00 320.00
0.200 OH Tukang kayu 185,000.00 37,000.00
0.050 OH Kepala Tukang 190,000.00 9,500.00
0.100 OH Pekerja 135,500.00 13,550.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 71,326.48 44,889.44 116,215.92
57 1 M2 Plafond Calsiboard 4mm+ rangka
0.011 m3 Kayu rangka 2,000,000.00 22,000.00
0.347 m2 Calsiboard 65,000.00 22,555.00
0.020 kg Paku 16,000.00 320.00
0.200 OH Tukang kayu 185,000.00 37,000.00
0.050 OH Kepala Tukang 190,000.00 9,500.00
0.100 OH Pekerja 135,500.00 13,550.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 71,326.48 44,875.00 116,201.48
58 1 M2 Plafond Lumbersering + Rangka
0.013 m3 Kayu rangka 2,000,000.00 26,028.80
3.150 btg Lumbersering - -
0.020 kg Paku 16,000.00 320.00
0.200 OH Tukang kayu 185,000.00 37,000.00
0.050 OH Kepala Tukang 190,000.00 9,500.00
0.100 OH Pekerja 135,500.00 13,550.00
0.010 OH Mandor 200,000.00 2,000.00
JUMLAH 105,485.00 26,348.80 131,833.80
59 1 M3 Sloof S1 (20/30)
1.000 m3 Beton 1:2:3 1,060,360.00 910,360.00
10.000 m2 Begisting 118,272.50 1,032,725.00
150.000 kg Besi 12,489.52 973,427.68
JUMLAH - 2,916,512.68 2,916,512.68
60 1 M3 Sloof S2 (15/25)
1.000 m3 Beton 1:2:3 1,060,360.00 1,000,360.00
13.333 m2 Begisting 118,272.50 1,186,966.67
125.000 kg Besi 12,489.52 1,161,189.73
JUMLAH - 3,348,516.40 3,348,516.40
61 1 M3 Kolom K1 (13 / 40)
1.000 m3 Beton 1:2:3 1,060,360.00 1,060,360.00
20.385 m2 Begisting 118,272.50 2,160,939.42
0.200 m3 Kayu Perancah 1,284,500.00 256,900.00
200.000 kg Besi 12,489.52 2,297,903.58
JUMLAH - 5,776,103.00 5,776,103.00
62 1 M3 Kolom K2 (15 / 50)
1.000 m3 Beton 1:2:3 1,060,360.00 1,060,360.00
17.333 m2 Begisting 118,272.50 2,050,056.67
0.200 m3 Kayu Perancah 1,284,500.00 256,900.00
200.000 kg Besi 12,489.52 2,497,903.58
JUMLAH - 5,865,220.24 5,865,220.24
65 1 M3 Kolom praktis (13/13)
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
30.769 m2 Begisting 118,272.50 3,639,153.85
0.200 m3 Kayu Perancah 1,284,500.00 256,900.00
125.000 kg Besi 12,489.52 1,561,189.73
JUMLAH - 6,317,603.58 6,317,603.58
67 1 M3 Ring Balok (13 / 25)
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
15.385 m2 Begisting 118,272.50 1,819,576.92
0.350 m3 Kayu Skor 1,284,500.00 449,575.00
125.000 kg Besi 12,489.52 1,561,189.73
JUMLAH - 4,690,701.66 4,690,701.66

Analisa hal 8 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
68 1 M3 Balok Latei (13 / 20)
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
15.385 m2 Begisting 118,272.50 1,819,576.92
0.350 m3 Kayu Skor 1,284,500.00 449,575.00
125.000 kg Besi 12,489.52 1,561,189.73
JUMLAH - 4,690,701.66 4,690,701.66
69 1 M3 Balok B1 (15 / 35)
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
13.333 m2 Begisting 118,272.50 1,576,966.67
0.350 m3 Kayu Skor 1,284,500.00 449,575.00
200.000 kg Besi 12,489.52 2,497,903.58
JUMLAH - 5,384,805.24 5,384,805.24
70 1 M3 Balok B2 (15 / 25)
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
13.333 m2 Begisting 118,272.50 1,576,966.67
0.350 m3 Kayu Skor 1,284,500.00 449,575.00
175.000 kg Besi 12,489.52 2,185,665.63
JUMLAH - 5,072,567.30 5,072,567.30
73 1 M' List Plank & Talang Beton
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
3.371 m2 Begisting 118,272.50 398,720.25
0.010 m3 Stuut werk 1,284,500.00 -
10.000 kg Besi 12,489.52 124,895.18
JUMLAH - 1,383,975.43 1,383,975.43
74 1 M3 Plat Beton Bertulang, t= 12cm
1.000 m3 Beton 1:2:3 860,360.00 460,360.00
10.500 m2 Begisting 118,272.50 941,861.25
Upah Anal. F.8 76,625.00 76,625.00
0.450 m3 Kayu Mal 2,000,000.00 700,000.00
m3 Kayu Perancah 2,000,000.00 -
5.000 kg Paku 16,000.00 80,000.00
112.294 kg Besi 12,489.52 1,102,497.92
JUMLAH 76,625.00 3,284,719.17 3,361,344.17
75 1 M3 Plat Beton Bertulang, t= 10cm
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
10.000 m2 Begisting 118,272.50 982,725.00
Upah Anal. F.8 66,760.00 66,760.00
0.450 m3 Kayu Mal 2,000,000.00 900,000.00
m3 Kayu Perancah 2,000,000.00 -
5.000 kg Paku 16,000.00 80,000.00
80.827 kg Besi 12,489.52 1,009,490.26
JUMLAH 66,760.00 3,832,575.26 3,899,335.26
76 1 M3 Foot plate 100x100x30
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
4.000 m2 Begisting 118,272.50 473,090.00
175.000 kg Besi 12,489.52 1,785,665.63
JUMLAH - 3,119,115.63 3,119,115.63
77 1 M3 Foot plate 60x60x25
1.000 m3 Beton 1:2:3 860,360.00 860,360.00
6.667 m2 Begisting 118,272.50 788,483.33
130.000 kg Besi 12,489.52 1,423,637.32
JUMLAH - 3,072,480.66 3,072,480.66
79 1 Unit Septic tank
1.500 m3 Galian Tanah 106,625.00 159,937.50
- m3 Pas. Bt gunung,t=20cm 1,080,858.33 -
0.150 m3 Cor lantai, t=10cm 1,916,680.00 287,502.00
- m3 Urugan bt kali, t=55cm 96,250.00 -
0.650 m3 Pas. Bata trasraam 1:2 147,249.00 95,711.85
6.500 m2 Plesteran + acian 1:2 111,685.80 725,957.70
- m3 Ring balk 15/20 4,690,701.66 -
0.150 m3 Plat Dak beton, t=10cm 3,899,335.26 584,900.29
- m3 Urugan pasir 594,000.00 -
- ls Ijuk 50,000.00 -
JUMLAH - 1,854,009.34 1,854,009.34
80 1 Unit Sumur Resapan
2.860 m3 Galian Tanah 106,625.00 304,947.50
0.316 m3 Pas. Bt gunung,t=20cm 1,080,858.33 341,551.23
0.396 m3 Urugan kerikil 1,038,000.00 411,048.00
0.132 m3 Urugan pasir 594,000.00 78,408.00
0.343 m3 Pas. Bata trasraam 1:4 197,340.00 67,687.62
0.457 m2 Plesteran + acian 1:4 106,479.80 48,661.27
64.000 bh Bata 950.00 60,800.00
0.132 m3 Plat Dak beton, t=10cm 3,899,335.26 514,712.25
1.000 - Ijuk 50,000.00 50,000.00
JUMLAH - 1,877,815.88 1,877,815.88
81 1 Buah Bak Mandi Pas. Bata (vol. 0,45 m3)
0.104 m3 Pas. Bata 1:2 147,249.00 15,313.90
2.720 m2 Pas. Keramik 20/25 207,863.43 565,388.52
1.000 oh Tukang 185,000.00 185,000.00
0.300 oh Kepala Tukang 190,000.00 57,000.00
0.300 oh Mandor 200,000.00 60,000.00
1.000 oh Pekerja 135,500.00 135,500.00
JUMLAH 218,750.00 580,702.41 799,452.41

Analisa hal 9 / 10
HARGA
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (Rp.) UPAH (Rp.) BAHAN (Rp.) (Rp.)
82 1 Buah Bak Kontrol (40x40)
0.360 m2 Bata 197,340.00 71,042.40
0.480 m2 Plesteran 106,479.80 51,110.30
0.008 m3 Cor rabat 1:3:5 1,916,680.00 15,333.44
JUMLAH - 137,486.14 137,486.14
83 1 M' Parit Pas. Bata diplester
0.600 m2 Bata 197,340.00 118,404.00
1.000 m2 Plesteran 106,479.80 106,479.80
0.010 m3 Cor rabat 1:3:5 1,916,680.00 19,166.80
JUMLAH - 244,050.60 244,050.60
84 1 Unit Resevoir, vol 2,5m3
2.501 m3 Galian Tanah 106,625.00 266,690.45
0.169 m3 Cor lantai, t=10cm 1,916,680.00 323,918.92
0.650 m3 Pas. Bata trasraam 1:2 147,249.00 95,711.85
6.710 m2 Pas Keramik 20/20 140,072.05 939,883.46
0.169 m3 Plat Dak beton, t=10cm 3,899,335.26 658,987.66
- m2 Plesteran Acian 106,479.80 -
1.000 Bh Pelampung 150,000.00 150,000.00
JUMLAH - 2,435,192.33 2,435,192.33
85 1 titik instalasi stop kontak
0.0500 Kabel NYM 2.5x3 mm 700,000.00 35,000.00
1.00 T Dos 5,000.00 5,000.00
1.00 Pipa conduit 7,000.00 7,000.00
1.00 stop kontak 15,000.00 15,000.00
1.00 Tukang 175,000.00 175,000.00
JUMLAH 175,000.00 62,000.00 237,000.00
86 1 titik instalasi lampu biasa
0.0500 Kabel NYM 2.5x3 mm 700,000.00 35,000.00
- T Dos 5,000.00 0.00
- Pipa conduit 7,000.00 0.00
1.00 fiting lampu 10,000.00 10,000.00
1.00 Tukang 175,000.00 175,000.00
JUMLAH 175,000.00 45,000.00 220,000.00
87 1 titik instalasi lampu downligth
0.0500 Kabel NYM 2.5x3 mm - 35,000.00
- T Dos 5,000.00 0.00
- Pipa conduit 7,000.00 0.00
1.00 fiting lampu 45,000.00 45,000.00
1.00 Tukang 175,000.00 175,000.00
JUMLAH 175,000.00 80,000.00 255,000.00
88 1 titik instalasi saklar
0.10 Kabel NYM 2.5x3 mm 700,000.00 70,000.00
2.00 T Dos 5,000.00 10,000.00
2.00 Pipa conduit 7,000.00 14,000.00
1.00 saklar 18,000.00 18,000.00
1.00 Tukang 175,000.00 175,000.00
JUMLAH 175,000.00 112,000.00 287,000.00