ANALISA HARGA SATUAN BETON

(KHUSUS) BUNKER K-500 Density 2,35 grm/cm³ ANTIRADIASI


1 1m3 Beton Readymix K-500 Koef Sat Harga Satuan Total Harga
Bahan
Beton readymix K-500 1.05 m3 x Rp 1,650,000.00 = Rp 1,732,500.00
- Batu Split Skrening 10/20,20/30
- Pasir Kandungan Besi
- Beton Non Flyash (FS)
Jumlah (I) = Rp 1,732,500.00
Tenaga
Pekerja 1.20 OH x Rp 100,000.00 = Rp 120,000.00
Tukang batu 0.42 OH x Rp 125,000.00 = Rp 52,083.33
Kepala tukang 0.04 OH x Rp 140,000.00 = Rp 5,833.33
Mandor 0.01 OH x Rp 150,000.00 = Rp 1,250.00
Jumlah (II) = Rp 179,166.67
Alat bantu
Pompa beton (2 alat Running) 1.00 m3 x Rp 150,000.00 = Rp 150,000.00
Vibrator (4 Alat Running) 1.00 m3 x Rp 80,000.00 = Rp 80,000.00
Ember aduk 0.05 bh x Rp 6,000.00 = Rp 300.00
Pacul aduk 0.05 bh x Rp 35,000.00 = Rp 1,750.00
Sekop 0.05 bh x Rp 40,000.00 = Rp 2,000.00
Jumlah (III) = Rp 234,050.00
Jumlah per m³ = Rp 2,145,716.67
ANALISA HARGA NON PPN-10%

A Beton readymix K-500 (WAJIB)

- Agregat A/Batu Split menggunakan Skrening khusus uk. 10/20mm atau


20/30mm

- Agregat A/Batu Split bebas dari lumpur, Tanah, & batu apung

- Pasir Cor menggunakan Jenis Pasir Besi

- Mixdesign dengan perbandingan tertentu sampai mencapai Density


2,35grm/cm³

- Perawatan Beton dengan Adittive Bonding Agent selama 7 hari berturut-


turut

- Penanaman Thermocople pada setiap sisi bagian beton, untuk mengecek


suhu dan memastikan suhu tidak lebih dari 60˚ selama 7 hari

B Alat bantu (WAJIB)

- Pompa Beton Minimal 2 unit, Karena pada saat pelaksanan pengecoran


tidak boleh terputus/Berhenti sebelum batas slab yang di izinkan

- 2 Pompa beton juga mencegah pengecoran dengan kapasitas besar, tidak


mengeras sebelum lajur pengecoran area berikutnya.

- Vibrator Minimal 5 Unit pada saat sekali waktu pelaksanaan pengecoran,


untuk mencapai target density yg baik & benar