PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TAHUN : -
NO LINGKUP PEKERJAAN BESERTA GAMBAR SKET URAIAN PERHITUNGAN VOLUME PEKERJAAN VOLUME
I PEKERJAAN PERSIAPAN
0.30
0.70
3. Pek. Aanstampang / Batu Kosong 14.58 M3
0.90 Luas penampang = 0.20 x 0.90
= 0.180 m2
Panjang Rencana Pondasi : Jml Volume = 0.18 x 81.00
Arah Horizontal = 18.00 x 3 = 54.00 m = 14.58 m3
Arah Vertikal = 9.00 x 3 = 27.00 m
Panjang total pondasi = 81.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 28.35 M3
Luas penampang = 1/2 x 0.30 + 0.70 x 0.70
= 0.350 m2
Volume = 0.35 x 81.00
= 28.35 m3
- Tulangan utama : 4 Ø 10
- Tulangan sengkang : Ø 8 - 150 = 20.16 m2
5. Selimut beton : 2.5 cm
Bentang L = 1.80 m
Lebar sloof = 0.15 m
Panjang Rencana Sloof : Jml Tinggi sloof = 0.20 m
Bentang L = 2.80 m 2.80 x 18 = 50.40 m Panjang sloof = 1.80 m
Bentang L = 1.80 m 1.80 x 3 = 5.40 m Jumlah sloof = 3.00 bh
Bentang L = 6.80 m 6.80 x 3 = 20.40 m
Total panjang sloof = 76.20 m Luas bekistin = 2 x 0.20 x 1.80 x 3.00
= 2.16 m2
Bentang L = 6.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 6.80 m
Jumlah sloof = 3.00 bh
Total Bekisting
= 20.16 + 2.16 + 8.16
= 30.48 m2
b. Pembesian 366.70 Kg
Bentang L = 2.80 m ---------------> Total volume pembesian = 246.91 kg
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 2.80 m
Jumlah sloof = 18.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
Total Pembesian
= 246.91 + 28.40 + 91.39
= 366.7 Kg
Bentang L = 1.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 1.80 m
Jumlah sloof = 3.00 bh
Bentang L = 6.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 6.80 m
Jumlah sloof = 3.00 bh
Total Beton
= 1.512 + 0.162 + 0.612
= 2.286 m3
- Tulangan utama : 4 Ø 12
- Tulangan sengkang : Ø 8 - 150
5. Selimut beton : 2.5 cm
KODE DETAIL KETERANGAN
SKALA 1 : 10
0.20 1. Ukuran : 20 x 20 cm
2. Bahan : Beton bertulang
3. Beton : K-200
KS - 20/20 4. Tulangan : U24 (polos) Lebar bekistin = 2.00 x 0.20 + 2.00 x 0.20
0.20
- Tulangan utama : 4 Ø 12
- Tulangan sengkang : Ø 8 - 150 = 0.80 m
5. Selimut beton : 2.5 cm Luas bekistin = 0.80 x 4.00 x 21.00
= 67.20 m2
a. Tulangan Pokok ( Ø 12 mm )
- Diameter tulangan (Ø) = 12mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 10.63 kg
- Berat besi per-1 m' = 0.89 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.48 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
Total Pembesian
= 536.35 + +
= 536.35 Kg
Total Beton
= 3.36 + +
= 3.36 m3
b. Tulangan Sengkang/begol ( Ø 6 mm )
- Diameter tulangan (Ø) = 6mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 2.66 kg
- Berat besi per-1 m' = 0.22 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
Total Pembesian
= 55.67 + +
= 55.675 Kg
Total Beton
= 0.3888 + +
= 0.3888 m3
a. Tulangan Pokok ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.32 m
b. Tulangan Sengkang/begol ( Ø 6 mm )
- Diameter tulangan (Ø) = 6mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 2.66 kg
- Berat besi per-1 m' = 0.22 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
Total Pembesian
= 89.73 + +
= 89.726 Kg
Total Beton
= 0.6048 + +
= 0.6048 m3
- Tulangan utama : 4 Ø 10
- Tulangan sengkang : Ø 8 - 150 Lebar bekisting RB 01 = 1.00 x 0.04 + 2.00 x 0.20
5. Selimut beton : 2.5 cm
= 0.44 m
Luas bekisting RB 01 = 0.44 x 2.80 x 12.00
= 14.78 m2
Panjang Rencana Ring Balok : Jml
Bentang L = 2.80 m 2.80 x 12 = 33.60 m Lebar bekisting RB 02 = 1.00 x 0.15 + 2.00 x 0.20
2.80 x 6 = 16.80 m = 0.55 m
Bentang L = 1.80 m 1.80 x 7 = 12.60 m Luas bekisting RB 02 = 0.55 x 2.80 x 6.00
Bentang L = 6.80 m 6.80 x 3 = 20.40 m = 9.24 m2
Total panjang ring balok = 83.40 m
Total bekistin = 14.78 + 9.24
= 24.02 m2
Bentang L = 1.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 1.80 m
Jumlah RB = 7.00 bh
Bentang L = 6.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 6.80 m
Jumlah RB = 3.00 bh
b. Pembesian 404.56 Kg
Bentang L = 2.80 m ---------------> Total volume pembesian = 246.91 kg
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 2.80 m
Jumlah RB = 18.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m
b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m
Total Pembesian
= 246.91 + 66.26 + 91.39
= 404.56 Kg
Bentang L = 1.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 1.80 m
Jumlah RB = 7.00 bh
Bentang L = 6.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 6.80 m
Jumlah RB = 3.00 bh
Total Beton
= 1.512 + 0.378 + 0.612
= 2.502 m3
IV PEKERJAAN DINDING
1. Pek. Pasangan Dinding Bata Tebal 1/2 Batu Spesi 1Pc : 4Ps 142.94 M2
Luas Bruto Pas. Dinding Bata
Tinggi dinding - 01 = 3.45 m
Panjang dinding - 01 = 2.80 x 12.00 = 33.60 m
Luas dinding - 01 = 3.45 x 33.60 = 115.92 m2
Total - 03 = 6.48 m2
Total - 04 = 10.08 m2
Total - 05 = 3.44 m2
0.50
0.50
Dimensi kayu kuzen = 0.05 m
= 0.15 m
Panjang kayu kuzen
Arah horizontal = 1.70 + 1.60 + + = 3.30 m
Arah vertikal = 2.65 + 0.50 + 2.65 + = 5.80 m
Total = 3.30 + 5.80 = 9.10 m
2.70
Volume - a = 2.00 x 0.05 x 0.15 x 9.10 = 0.14 m3
2.10
1.90
2.10
Jendela J3
Jumlah unit = 10.00unit
Dimensi kayu kuzen = 0.05 m
= 0.15 m
Panjang kayu kuzen
Pintu Panil Pintu Panil
Arah horizontal = 2.00 + 1.80 + 2.00 + = 5.80 m
Elv. ± 0.00
Arah vertikal = 1.60 + 1.60 + 1.60 + 1.60 = 6.40 m
1.70 Spesifikasi : Total = 5.80 + 6.40 = 12.20 m
- Kuzen kayu uk. 5/15 cm
0.80 0.80
- Pintu panil (2 bh) tebal 3 cm Volume - b = 10.00 x 0.05 x 0.15 x 12.20 = 0.92 m3
- Ventilasi
- Jelusi kayu uk. 2/15 cm
0.50
0.95
1.05
1.07
Jelusi
Elv. + 4.85
Luas - a = 10.00 x 2.00 x 0.62 x 1.07 = 13.27 m2
0.70 Spesifikasi :
- Kuzen kayu uk. 5/15 cm
Total Luas Jendela Kaca
0.60
- Ventilasi
- Jelusi kayu uk. 2/15 cm
Luas = 13.27 + + +
= 13.27 m2
Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 3.00 bh
Lebar = 0.60 m
Tinggi = 0.50 m
Luas - b = 10.00 x 3.00 x 0.60 x 0.50 = 9.00 m2
Ventilasi V1
Jumlah unit = 4.00unit
Jumlah dalam 1 unit = 1.00 bh
Lebar = 0.60 m
Tinggi = 0.50 m
Luas - c = 4.00 x 1.00 x 0.60 x 0.50 = 1.20 m2
Jumlah Total
Jumlah = 2.00 + + +
= 2.00 bh
Jumlah Total
Jumlah = 12.00 + + +
= 12.00 bh
Jumlah Total
Jumlah = 4.00 + + +
= 4.00 bh
Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh
Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh
Jumlah Total
Jumlah = 20.00 + + +
= 20.00 bh
Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh
VI PEKERJAAN ATAP
PERHITUNGAN VOLUME PEKERJAAN
PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TAHUN : -
NO LINGKUP PEKERJAAN BESERTA GAMBAR SKET URAIAN PERHITUNGAN VOLUME PEKERJAAN VOLUME
0.30
0.70 3. Pek. Aanstampang / Batu Kosong 10.26 M3
0.90 Luas penampang = 0.20 x 0.90
= 0.180 m2
Panjang Rencana Pondasi : Volume = 0.18 x 57.00
Arah horizontal = 18.00 x 2.00 = 36.00 m = 10.26 m3
Arah vertikal = 7.00 x 3.00 = 21.00 m
Panjang total pondasi = 57.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 19.95 M3
Luas penampang = 1/2 x 0.30 + 0.70 x 0.70
= 0.350 m2
Volume = 0.35 x 57.00
= 19.95 m3
Gambar Penampang Pondasi Batu Kali - Tipe 02 : 1. Pek. Galian Tanah Biasa Sedalam 1 m 15.36 M3
Luas penampang = 0.80 x 0.80
= 0.640 m2
0.05 Volume = 0.64 x 24.00
= 15.36 m3
Urugan Tanah Kembali
0.55
Pas. Batu Kali Spesi 1Pc : 4Ps 2. Pek. Urugan Pasir Tbl. 5 cm 0.96 M3
0.80
Luas penampang = 0.05 x 0.80
Aanstampang = 0.040 m2
0.20
Urugan Pasir Tbl. 5 cm Volume = 0.04 x 24.00
0.05
= 0.96 m3
0.30
0.60 3. Pek. Aanstampang / Batu Kosong 3.84 M3
0.80
Luas penampang = 0.20 x 0.80
= 0.160 m2
Panjang Rencana Pondasi : Volume = 0.16 x 24.00
Arah horizontal = 18.00 x 1.00 = 18.00 m = 3.84 m3
Arah vertikal = 2.00 x 3.00 = 6.00 m
Panjang total pondasi = 24.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 6.48 M3
Luas penampang = 1/2 x 0.30 + 0.60 x 0.60
= 0.270 m2
Volume = 0.27 x 24.00
= 6.48 m3