PERHITUNGAN VOLUME PEKERJAAN

PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TAHUN : -

NO LINGKUP PEKERJAAN BESERTA GAMBAR SKET URAIAN PERHITUNGAN VOLUME PEKERJAAN VOLUME

I PEKERJAAN PERSIAPAN

II PEKERJAAN PONDASI BATU KALI


Gambar Penampang Pondasi Batu Kali - Tipe 01 : 1. Pek. Galian Tanah Biasa Sedalam 1 m 65.61 M3
Luas penampang = 0.90 x 0.90
= 0.810 m2
0.05 Volume = 0.81 x 81.00
= 65.61 m3
Urugan Tanah Kembali

0.65 Pas. Batu Kali Spesi 1Pc : 4Ps


2. Pek. Urugan Pasir Tbl. 5 cm 3.65 M3
0.90
Luas penampang = 0.05 x 0.90
= 0.045 m2
Aanstampang
0.20 Volume = 0.045 x 81.00
Urugan Pasir Tbl. 5 cm
0.05 = 3.65 m3

0.30
0.70
3. Pek. Aanstampang / Batu Kosong 14.58 M3
0.90 Luas penampang = 0.20 x 0.90
= 0.180 m2
Panjang Rencana Pondasi : Jml Volume = 0.18 x 81.00
Arah Horizontal = 18.00 x 3 = 54.00 m = 14.58 m3
Arah Vertikal = 9.00 x 3 = 27.00 m
Panjang total pondasi = 81.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 28.35 M3
Luas penampang = 1/2 x 0.30 + 0.70 x 0.70
= 0.350 m2
Volume = 0.35 x 81.00
= 28.35 m3

5. Urugan Tanah Kembali 21.06 M3


Luas penampang = 2 x 1/2 x 0.10 + 0.30 x 0.65
= 0.260 m2
Volume = 0.26 x 81.00
= 21.06 m3

III PEKERJAAN STRUKTUR BETON BERTULANG


1. Pek. Sloof Uk. 15 x 20 Cm a. Bekisting Sloof 30.48 M2
TABEL PENULANGAN SLOOF (S) Bentang L = 2.80 m
KODE DETAIL KETERANGAN
Lebar sloof = 0.15 m
SKALA 1 : 10
Tinggi sloof = 0.20 m
Panjang sloof = 2.80 m
0.15 1. Ukuran : 15 x 20 cm Jumlah sloof = 18.00 bh
2. Bahan : Beton bertulang
3. Beton : K-200
S - 15/20 4. Tulangan : U24 (polos) Luas bekistin = 2 x 0.20 x 2.80 x 18.00
0.20

- Tulangan utama : 4 Ø 10
- Tulangan sengkang : Ø 8 - 150 = 20.16 m2
5. Selimut beton : 2.5 cm

Bentang L = 1.80 m
Lebar sloof = 0.15 m
Panjang Rencana Sloof : Jml Tinggi sloof = 0.20 m
Bentang L = 2.80 m 2.80 x 18 = 50.40 m Panjang sloof = 1.80 m
Bentang L = 1.80 m 1.80 x 3 = 5.40 m Jumlah sloof = 3.00 bh
Bentang L = 6.80 m 6.80 x 3 = 20.40 m
Total panjang sloof = 76.20 m Luas bekistin = 2 x 0.20 x 1.80 x 3.00
= 2.16 m2

Bentang L = 6.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 6.80 m
Jumlah sloof = 3.00 bh

Luas bekistin = 2 x 0.20 x 6.80 x 3.00


= 8.16 m2

Total Bekisting
= 20.16 + 2.16 + 8.16
= 30.48 m2
b. Pembesian 366.70 Kg
Bentang L = 2.80 m ---------------> Total volume pembesian = 246.91 kg
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 2.80 m
Jumlah sloof = 18.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 2.80 + 0.40


= 3.60 m
- Panjang total tulangan pokok = 4.00 x 3.60
= 14.40 m
- Volume tulangan = 14.40 x 0.62
= 8.856 kg
- Total volume tulangan = 8.856 x 18.00
= 159.41 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 2.80 / 0.15
= 18.67 bh Pembulatan = 19.00 bh
- Volume tulangan = 19.00 x 0.65 x 0.39
= 4.86 kg
- Total volume tulangan = 4.86 x 18.00
= 87.50 kg

Bentang L = 1.80 m ---------------> Total volume pembesian = 28.40 kg


Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 1.80 m
Jumlah sloof = 3.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 1.80 + 0.40


= 2.60 m
- Panjang total tulangan pokok = 4.00 x 2.60
= 10.40 m
- Volume tulangan = 10.40 x 0.62
= 6.396 kg
- Total volume tulangan = 6.396 x 3.00
= 19.188 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 1.80 / 0.15
= 12.00 bh Pembulatan = 12.00 bh
- Volume tulangan = 12.00 x 0.65 x 0.39
= 3.07 kg
- Total volume tulangan = 3.07 x 3.00
= 9.21 kg
Bentang L = 6.80 m ---------------> Total volume pembesian = 91.39 kg
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 6.80 m
Jumlah sloof = 3.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 6.80 + 0.40


= 7.60 m
- Panjang total tulangan pokok = 4.00 x 7.60
= 30.40 m
- Volume tulangan = 30.40 x 0.62
= 18.696 kg
- Total volume tulangan = 18.696 x 3.00
= 56.088 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 6.80 / 0.15
= 45.33 bh Pembulatan = 46.00 bh
- Volume tulangan = 46.00 x 0.65 x 0.39
= 11.77 kg
- Total volume tulangan = 11.77 x 3.00
= 35.31 kg

Total Pembesian
= 246.91 + 28.40 + 91.39
= 366.7 Kg

c. Beton K-200 2.29 M3


Bentang L = 2.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 2.80 m
Jumlah sloof = 18.00 bh

Volume Beton = 0.15 x 0.20 x 2.80 x 18.00


= 1.512 m3

Bentang L = 1.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 1.80 m
Jumlah sloof = 3.00 bh

Volume Beton = 0.15 x 0.20 x 1.80 x 3.00


= 0.162 m3

Bentang L = 6.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 6.80 m
Jumlah sloof = 3.00 bh

Volume Beton = 0.15 x 0.20 x 6.80 x 3.00


= 0.612 m3

Total Beton
= 1.512 + 0.162 + 0.612
= 2.286 m3

2. Pek. Kolom Struktur Uk. 20 x 20 Cm a. Bekisting Kolom 67.20 M2


TABEL PENULANGAN KOLOM STRUKTUR (KS)
Tinggi T = 4.00 m
Lebar 01 = 0.20 m
KODE DETAIL KETERANGAN
Lebar 02 = 0.20 m
SKALA 1 : 10
Tinggi kolom = 4.00 m
0.20 1. Ukuran : 20 x 20 cm Jumlah kolom = 21.00 bh
2. Bahan : Beton bertulang
3. Beton : K-200
KS - 20/20 4. Tulangan : U24 (polos)
0.20

- Tulangan utama : 4 Ø 12
- Tulangan sengkang : Ø 8 - 150
5. Selimut beton : 2.5 cm
KODE DETAIL KETERANGAN
SKALA 1 : 10

0.20 1. Ukuran : 20 x 20 cm
2. Bahan : Beton bertulang
3. Beton : K-200
KS - 20/20 4. Tulangan : U24 (polos) Lebar bekistin = 2.00 x 0.20 + 2.00 x 0.20

0.20
- Tulangan utama : 4 Ø 12
- Tulangan sengkang : Ø 8 - 150 = 0.80 m
5. Selimut beton : 2.5 cm Luas bekistin = 0.80 x 4.00 x 21.00
= 67.20 m2

Rencana Kolom Struktur : Jml b. Pembesian 536.35 Kg


Tinggi T = 4.00 m 4.00 x 21 = 84.00 m Tinggi T = 4.00 m ---------------> Total volume pembesian = 536.35 kg
Lebar 01 = 0.20 m
Lebar 02 = 0.20 m
Tinggi kolom = 4.00 m
Jumlah kolom = 21.00 bh

a. Tulangan Pokok ( Ø 12 mm )
- Diameter tulangan (Ø) = 12mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 10.63 kg
- Berat besi per-1 m' = 0.89 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.48 m

- Panjang 1 bh tulangan pokok = 0.48 + 4.00 + 0.48


= 4.96 m
- Panjang total tulangan pokok = 4.00 x 4.96
= 19.84 m
- Volume tulangan = 19.84 x 0.89
= 17.57 kg
- Total volume tulangan = 17.57 x 21.00
= 368.98 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.15 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.75 m
- Banyak tulangan sengkang = 4.00 / 0.15
= 26.67 bh Pembulatan = 27.00 bh
- Volume tulangan = 27.00 x 0.75 x 0.39
= 7.97 kg
- Total volume tulangan = 7.97 x 21.00
= 167.38 kg

Total Pembesian
= 536.35 + +
= 536.35 Kg

c. Beton K-200 3.36 M3


Tinggi T = 4.00 m
Lebar 01 = 0.20 m
Lebar 02 = 0.20 m
Tinggi kolom = 4.00 m
Jumlah kolom = 21.00 bh

Volume Beton = 0.20 x 0.20 x 4.00 x 21.00


= 3.36 m3

Total Beton
= 3.36 + +
= 3.36 m3

3. Pek. Kolom Praktis Uk. 12 x 15 Cm a. Bekisting Kolom 6.48 M2


Tinggi T = 3.60 m
KODE DETAIL KETERANGAN Lebar 01 = 0.12 m
SKALA 1 : 10 Lebar 02 = 0.15 m
Tinggi kolom = 3.60 m
1. Ukuran : 12 x 15 cm
0.12 Jumlah kolom = 6.00 bh
2. Bahan : Beton bertulang
3. Beton : K-200
KP - 12/15 4. Tulangan : U24 (polos)
Lebar bekistin = x + 2.00 x 0.15
0.15

- Tulangan utama :4Ø8


- Tulangan sengkang : Ø 6 - 150 = 0.30 m
5. Selimut beton : 2.5 cm
Luas bekistin = 0.30 x 3.60 x 6.00
= 6.48 m2

Rencana Kolom Praktis : Jml b. Pembesian 55.67 Kg


Tinggi T = 3.60 m 3.60 x 6 = 21.60 m Tinggi T = 3.60 m ---------------> Total volume pembesian = 55.67 kg
Lebar 01 = 0.12 m
Lebar 02 = 0.15 m
Tinggi kolom = 3.60 m
Jumlah kolom = 6.00 bh
a. Tulangan Pokok ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.32 m

- Panjang 1 bh tulangan pokok = 0.32 + 3.60 + 0.32


= 4.24 m
- Panjang total tulangan pokok = 4.00 x 4.24
= 16.96 m
- Volume tulangan = 16.96 x 0.39
= 6.6755 kg
- Total volume tulangan = 6.6755 x 6.00
= 40.053 kg

b. Tulangan Sengkang/begol ( Ø 6 mm )
- Diameter tulangan (Ø) = 6mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 2.66 kg
- Berat besi per-1 m' = 0.22 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.07 m


- Tinggi tulangan sengkang = 0.10 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.49 m
- Banyak tulangan sengkang = 3.60 / 0.15
= 24.00 bh Pembulatan = 24.00 bh
- Volume tulangan = 24.00 x 0.49 x 0.22
= 2.60 kg
- Total volume tulangan = 2.60 x 6.00
= 15.62 kg

Total Pembesian
= 55.67 + +
= 55.675 Kg

c. Beton K-200 0.39 M3


Tinggi T = 3.60 m
Lebar 01 = 0.12 m
Lebar 02 = 0.15 m
Tinggi kolom = 3.60 m
Jumlah kolom = 6.00 bh

Volume Beton = 0.12 x 0.15 x 3.60 x 6.00


= 0.3888 m3

Total Beton
= 0.3888 + +
= 0.3888 m3

4. Pek. Balok Latei Uk. 12 x 15 Cm a. Bekisting Balok 10.08 M2


Bentang L = 2.80 m
KODE DETAIL KETERANGAN Lebar balok = 0.12 m
SKALA 1 : 10 Tinggi balok = 0.15 m
Panjang balok = 2.80 m
1. Ukuran : 12 x 15 cm
0.12
2. Bahan : Beton bertulang Jumlah balok = 12.00 bh
3. Beton : K-200
BL - 12/15 4. Tulangan : U24 (polos)
0.15

- Tulangan utama : 4 Ø 8 Lebar bekistin = x + 2.00 x 0.15


- Tulangan sengkang : Ø 6 - 150 = 0.30 m
5. Selimut beton : 2.5 cm
Luas bekistin = 0.30 x 2.80 x 12.00
= 10.08 m2

Panjang Rencana Balok Latei : Jml b. Pembesian 89.73 Kg


Bentang L = 2.80 m 2.80 x 12 = 33.60 m Bentang L = 2.80 m ---------------> Total volume pembesian = 89.73 kg
Lebar balok = 0.12 m
Tinggi balok = 0.15 m
Panjang balok = 2.80 m
Jumlah balok = 12.00 bh

a. Tulangan Pokok ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.32 m

- Panjang 1 bh tulangan pokok = 0.32 + 2.80 + 0.32


= 3.44 m
- Panjang total tulangan pokok = 4.00 x 3.44
= 13.76 m
- Volume tulangan = 13.76 x 0.39
= 5.4159 kg
- Total volume tulangan = 5.4159 x 12.00
= 64.991 kg

b. Tulangan Sengkang/begol ( Ø 6 mm )
- Diameter tulangan (Ø) = 6mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 2.66 kg
- Berat besi per-1 m' = 0.22 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.07 m


- Tinggi tulangan sengkang = 0.10 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.49 m
- Banyak tulangan sengkang = 2.80 / 0.15
= 18.67 bh Pembulatan = 19.00 bh
- Volume tulangan = 19.00 x 0.49 x 0.22
= 2.06 kg
- Total volume tulangan = 2.06 x 12.00
= 24.73 kg

Total Pembesian
= 89.73 + +
= 89.726 Kg

c. Beton K-200 0.60 M3


Bentang L = 2.80 m
Lebar balok = 0.12 m
Tinggi balok = 0.15 m
Panjang balok = 2.80 m
Jumlah balok = 12.00 bh

Volume Beton = 0.12 x 0.15 x 2.80 x 12.00


= 0.6048 m3

Total Beton
= 0.6048 + +
= 0.6048 m3

5. Pek. Ring Balok Uk. 15 x 20 Cm a. Bekisting Balok 39.93 M2


Bentang L = 2.80 m
KODE DETAIL KETERANGAN Lebar RB = 0.15 m
SKALA 1 : 10 Tinggi RB = 0.20 m
Panjang RB = 2.80 m
0.15 1. Ukuran : 15 x 20 cm
2. Bahan : Beton bertulang
Jumlah RB 01 = 12.00 bh
3. Beton : K-200 Jumlah RB 02 = 6.00 bh
RB - 15/20 4. Tulangan : U24 (polos)
0.20

- Tulangan utama : 4 Ø 10
- Tulangan sengkang : Ø 8 - 150 Lebar bekisting RB 01 = 1.00 x 0.04 + 2.00 x 0.20
5. Selimut beton : 2.5 cm
= 0.44 m
Luas bekisting RB 01 = 0.44 x 2.80 x 12.00
= 14.78 m2
Panjang Rencana Ring Balok : Jml
Bentang L = 2.80 m 2.80 x 12 = 33.60 m Lebar bekisting RB 02 = 1.00 x 0.15 + 2.00 x 0.20
2.80 x 6 = 16.80 m = 0.55 m
Bentang L = 1.80 m 1.80 x 7 = 12.60 m Luas bekisting RB 02 = 0.55 x 2.80 x 6.00
Bentang L = 6.80 m 6.80 x 3 = 20.40 m = 9.24 m2
Total panjang ring balok = 83.40 m
Total bekistin = 14.78 + 9.24
= 24.02 m2

Bentang L = 1.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 1.80 m
Jumlah RB = 7.00 bh

Lebar bekistin = 1.00 x 0.15 + 2.00 x 0.20


= 0.55 m
Luas bekistin = 0.55 x 1.80 x 7.00
= 6.93 m2

Bentang L = 6.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 6.80 m
Jumlah RB = 3.00 bh

Lebar bekistin = 1.00 x 0.04 + 2.00 x 0.20


= 0.44 m
Luas bekistin = 0.44 x 6.80 x 3.00
= 8.98 m2
Total Bekisting
= 24.02 + 6.93 + 8.98
= 39.93 m2

b. Pembesian 404.56 Kg
Bentang L = 2.80 m ---------------> Total volume pembesian = 246.91 kg
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 2.80 m
Jumlah RB = 18.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 2.80 + 0.40


= 3.60 m
- Panjang total tulangan pokok = 4.00 x 3.60
= 14.40 m
- Volume tulangan = 14.40 x 0.62
= 8.856 kg
- Total volume tulangan = 8.856 x 18.00
= 159.41 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 2.80 / 0.15
= 18.67 bh Pembulatan = 19.00 bh
- Volume tulangan = 19.00 x 0.65 x 0.39
= 4.86 kg
- Total volume tulangan = 4.86 x 18.00
= 87.50 kg

Bentang L = 1.80 m ---------------> Total volume pembesian = 66.26 kg


Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 1.80 m
Jumlah RB = 7.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 1.80 + 0.40


= 2.60 m
- Panjang total tulangan pokok = 4.00 x 2.60
= 10.40 m
- Volume tulangan = 10.40 x 0.62
= 6.396 kg
- Total volume tulangan = 6.396 x 7.00
= 44.772 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 1.80 / 0.15
= 12.00 bh Pembulatan = 12.00 bh
- Volume tulangan = 12.00 x 0.65 x 0.39
= 3.07 kg
- Total volume tulangan = 3.07 x 7.00
= 21.49 kg

Bentang L = 6.80 m ---------------> Total volume pembesian = 91.39 kg


Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 6.80 m
Jumlah RB = 3.00 bh

a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø) = 10mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 7.38 kg
- Berat besi per-1 m' = 0.62 kg
- Jumlah tulangan pokok = 4.00 bh
- Overlap untuk sambungan (40d= 0.40 m

- Panjang 1 bh tulangan pokok = 0.40 + 6.80 + 0.40


= 7.60 m
- Panjang total tulangan pokok = 4.00 x 7.60
= 30.40 m
- Volume tulangan = 30.40 x 0.62
= 18.696 kg
- Total volume tulangan = 18.696 x 3.00
= 56.088 kg

b. Tulangan Sengkang/begol ( Ø 8 mm )
- Diameter tulangan (Ø) = 8mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.72 kg
- Berat besi per-1 m' = 0.39 kg
- Selimut beton = 0.025 m
- Jarak spasi tulangan = 0.15 m

- Lebar tulangan sengkang = 0.10 m


- Tinggi tulangan sengkang = 0.15 m
- Pembengkokan 135° (6d) = 0.075 m
- Panjang 1 bh tul. Sengkang = 0.65 m
- Banyak tulangan sengkang = 6.80 / 0.15
= 45.33 bh Pembulatan = 46.00 bh
- Volume tulangan = 46.00 x 0.65 x 0.39
= 11.77 kg
- Total volume tulangan = 11.77 x 3.00
= 35.31 kg

Total Pembesian
= 246.91 + 66.26 + 91.39
= 404.56 Kg

c. Beton K-200 2.50 M3


Bentang L = 2.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 2.80 m
Jumlah RB = 18.00 bh

Volume Beton = 0.15 x 0.20 x 2.80 x 18.00


= 1.512 m3

Bentang L = 1.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 1.80 m
Jumlah RB = 7.00 bh

Volume Beton = 0.15 x 0.20 x 1.80 x 7.00


= 0.378 m3

Bentang L = 6.80 m
Lebar RB = 0.15 m
Tinggi RB = 0.20 m
Panjang RB = 6.80 m
Jumlah RB = 3.00 bh

Volume Beton = 0.15 x 0.20 x 6.80 x 3.00


= 0.612 m3

Total Beton
= 1.512 + 0.378 + 0.612
= 2.502 m3

IV PEKERJAAN DINDING
1. Pek. Pasangan Dinding Bata Tebal 1/2 Batu Spesi 1Pc : 4Ps 142.94 M2
Luas Bruto Pas. Dinding Bata
Tinggi dinding - 01 = 3.45 m
Panjang dinding - 01 = 2.80 x 12.00 = 33.60 m
Luas dinding - 01 = 3.45 x 33.60 = 115.92 m2

Tinggi dinding - 02 = 3.60 m


Panjang dinding - 02 = 6.50 x 3.00 = 19.50 m
Luas dinding - 02 = 3.60 x 19.50 = 70.20 m2

Jumlah = 115.92 + 70.20 = 186.12 m2

Luas Pas. Kuzen


Kuzen Pintu P2 = 1.70 x 2.70 x 2.00 = 9.18 m2
Kuzen Jendela J3 = 2.00 x 1.70 x 10.00 = 34.00 m2
Jumlah = 43.18 m2

Luas Netto / Bersih Pas. Dinding Bata


= 186.12 - 43.18 = 142.94 m2

2. Pek. Plesteran Spesi 1Pc : 4Ps, Tebal 20 mm 285.88 M2


Luas Plesteran = 2 x Luas pasangan dinding bata
= 2 x 142.94
= 285.88 m2

3. Pek. Acian 285.88 M2


Luas Acian = Luas Plesteran
= 285.88 m2

4. Pek. Afwerking Permukaan Beton 72.24 M2


Sloof uk. 15 x 20 cm
Panjang sloof (afwerking) = 6.80 m
Jumlah = 2.00 bh
Bagian yg di afwerking = 0.10 m
Luas - a = 6.80 x 2.00 x 0.10 = 1.36 m2

Panjang sloof (afwerking) = 2.80 m


Jumlah = 6.00 bh
Bagian yg di afwerking = 0.10 m
Luas - b = 2.80 x 6.00 x 0.10 = 1.68 m2

Total - 01 = 1.36 + 1.68 = 3.04 m2

Kolom Struktur uk. 20 x 20 cm


Tinggi kolom (afwerking) = 4.00 m
Jumlah = 7.00 bh
Bagian yg di afwerking = 0.80 m
Luas - a = 4.00 x 7.00 x 0.80 = 22.40 m2

Tinggi kolom (afwerking) = 4.00 m


Jumlah = 12.00 bh
Bagian yg di afwerking = 0.50 m
Luas - b = 4.00 x 12.00 x 0.50 = 24.00 m2

Tinggi kolom (afwerking) = 4.00 m


Jumlah = 2.00 bh
Bagian yg di afwerking = 0.35 m
Luas - c = 4.00 x 2.00 x 0.35 = 2.80 m2

Total - 02 = 22.40 + 24.00 + 2.80 = 49.20 m2

Kolom Prakis uk. 12 x 15 cm


Tinggi kolom (afwerking) = 3.60 m
Jumlah = 6.00 bh
Bagian yg di afwerking = 0.30 m
Luas - a = 3.60 x 6.00 x 0.30 = 6.48 m2

Total - 03 = 6.48 m2

Balok Latei uk. 12 x 15 cm


Panjang BL (afwerking) = 2.80 m
Jumlah = 12.00 bh
Bagian yg di afwerking = 0.30 m
Luas - a = 2.80 x 12.00 x 0.30 = 10.08 m2

Total - 04 = 10.08 m2

Ring Balok uk. 15 x 20 cm


Panjang RB (afwerking) = 8.60 m
Jumlah = 2.00 bh
Bagian yg di afwerking = 0.20 m
Luas - a = 8.60 x 2.00 x 0.20 = 3.44 m2

Total - 05 = 3.44 m2

Jumlah Total Afwerking Permukaan Beton


Luas = 3.04 + 49.20 + 6.48 + 10.08 + 3.44
= 72.24 m2

V PEKERJAAN KUZEN, PINTU, JENDELA DAN VENTILASI


1. Pek. Kuzen Pintu, Jendela dan Ventilasi 1.12 M3
Elv. + 2.70
Pintu P2
Jumlah unit = 2.00unit
Jelusi Jelusi

0.50
0.50
Dimensi kayu kuzen = 0.05 m
= 0.15 m
Panjang kayu kuzen
Arah horizontal = 1.70 + 1.60 + + = 3.30 m
Arah vertikal = 2.65 + 0.50 + 2.65 + = 5.80 m
Total = 3.30 + 5.80 = 9.10 m

2.70
Volume - a = 2.00 x 0.05 x 0.15 x 9.10 = 0.14 m3

2.10
1.90
2.10
Jendela J3
Jumlah unit = 10.00unit
Dimensi kayu kuzen = 0.05 m
= 0.15 m
Panjang kayu kuzen
Pintu Panil Pintu Panil
Arah horizontal = 2.00 + 1.80 + 2.00 + = 5.80 m
Elv. ± 0.00
Arah vertikal = 1.60 + 1.60 + 1.60 + 1.60 = 6.40 m
1.70 Spesifikasi : Total = 5.80 + 6.40 = 12.20 m
- Kuzen kayu uk. 5/15 cm
0.80 0.80
- Pintu panil (2 bh) tebal 3 cm Volume - b = 10.00 x 0.05 x 0.15 x 12.20 = 0.92 m3
- Ventilasi
- Jelusi kayu uk. 2/15 cm

Aksesoris untuk 1 Unit Pintu P2 : Ventilasi V1


0.61 0.61 - Kunci Tanam (1 bh)
0.81 0.81 - Merk. SES (Setara) - 2 Slaag Jumlah unit = 4.00unit
- Engsel Pintu (6 bh)
- Grendel Pintu (2 bh) Dimensi kayu kuzen = 0.05 m
= 0.15 m
DETAIL PINTU P2 (2 UNIT) Panjang kayu kuzen
®
SKALA 1 : 25 Arah horizontal = 0.70 + 0.70 + + = 1.40 m
Arah vertikal = 0.50 + 0.50 + + = 1.00 m
Total = 1.40 + 1.00 = 2.40 m
Elv. + 2.70 Volume - c = 4.00 x 0.05 x 0.15 x 2.40 = 0.07 m3
0.50

0.50

Jelusi Jelusi Jelusi


Total Volume Kuzen
Volume = 0.14 + 0.92 + 0.07 +
= 1.12 m3
1.70

0.95
1.05

1.07

2. Pek. Pintu Panil 6.80 M2


Pintu P2
Jendela Kaca Kaca Mati Jendela Kaca Jumlah unit = 2.00unit
Elv. + 1.00
Jumlah dalam 1 unit = 2.00 bh
2.00 Spesifikasi : Lebar pintu = 0.81 m
- Kuzen kayu uk. 5/15 cm
0.60 0.60 0.60
- Kaca mati tebal 5 mm Tinggi pintu = 2.10 m
- Jendela kaca
- Rangka kayu uk. 3/6 cm Luas - a = 2.00 x 2.00 x 0.81 x 2.10 = 6.80 m2
- Kaca tebal 3 mm
- Ventilasi
0.50 0.50 - Jelusi kayu uk. 2/15 cm
0.62 0.62 0.62
Total Luas Pintu
Aksesoris untuk 1 Unit Jendela J3 :
- Engsel Jendela (4 bh)
- Kait Angin Jendela (4 bh)
Luas = 6.80 + + +
- Tangan-tangan Jendela (2 bh)
- Gerendel Jendela (4 bh)
= 6.80 m2
DETAIL JENDELA J3 (10 UNIT)
®
SKALA 1 : 25

3. Pek. Jendela Kaca Rangka Kayu 13.27 M2


Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 2.00 bh
Elv. + 5.45
Lebar jendela kaca = 0.62 m
Tinggi jendela kaca = 1.07 m
0.60
0.50

Jelusi

Elv. + 4.85
Luas - a = 10.00 x 2.00 x 0.62 x 1.07 = 13.27 m2

0.70 Spesifikasi :
- Kuzen kayu uk. 5/15 cm
Total Luas Jendela Kaca
0.60
- Ventilasi
- Jelusi kayu uk. 2/15 cm
Luas = 13.27 + + +
= 13.27 m2

4. Pek. Pasang Kaca Mati Tebal 5 mm 6.63 M2


DETAIL VENTILASI V1 (4 UNIT)
SKALA 1 : 25
® Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 1.00 bh
Lebar kaca = 0.62 m
Tinggi kaca = 1.07 m
Luas - a = 10.00 x 1.00 x 0.62 x 1.07 = 6.63 m2

Total Luas Kaca Mati


Luas = 6.63 + + +
= 6.63 m2

5. Pek. Jelusi Kuzen / Papan Ventilasi 11.76 M2


Pintu P2
Jumlah unit = 2.00unit
Jumlah dalam 1 unit = 2.00 bh
Lebar = 0.78 m
Tinggi = 0.50 m
Luas - a = 2.00 x 2.00 x 0.78 x 0.50 = 1.56 m2

Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 3.00 bh
Lebar = 0.60 m
Tinggi = 0.50 m
Luas - b = 10.00 x 3.00 x 0.60 x 0.50 = 9.00 m2

Ventilasi V1
Jumlah unit = 4.00unit
Jumlah dalam 1 unit = 1.00 bh
Lebar = 0.60 m
Tinggi = 0.50 m
Luas - c = 4.00 x 1.00 x 0.60 x 0.50 = 1.20 m2

Total Luas Ventilasi


Luas = 1.56 + 9.00 + 1.20 +
= 11.76 m2

6. Pas. Kunci Tanam Merk. SES (Setara) - 2 Slaag 2.00 Bh


Pintu P2
Jumlah unit = 2.00unit
Jumlah dalam 1 unit = 1.00 bh
Volume - a = 2.00 x 1.00 = 2.00 bh

Jumlah Total
Jumlah = 2.00 + + +
= 2.00 bh

7. Pas. Engsel Pintu 12.00 Bh


Pintu P2
Jumlah unit = 2.00unit
Jumlah dalam 1 unit = 6.00 bh
Volume - a = 2.00 x 6.00 = 12.00 bh

Jumlah Total
Jumlah = 12.00 + + +
= 12.00 bh

8. Pas. Grendel Pintu 4.00 Bh


Pintu P2
Jumlah unit = 2.00unit
Jumlah dalam 1 unit = 2.00 bh
Volume - a = 2.00 x 2.00 = 4.00 bh

Jumlah Total
Jumlah = 4.00 + + +
= 4.00 bh

9. Pas. Engsel Jendela 40.00 Bh


Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 4.00 bh
Volume - a = 10.00 x 4.00 = 40.00 bh

Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh

10. Pas. Kait Angin Jendela 40.00 Bh


Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 4.00 bh
Volume - a = 10.00 x 4.00 = 40.00 bh

Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh

11. Pas. Tangan-tangan Jendela 20.00 Bh


Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 2.00 bh
Volume - a = 10.00 x 2.00 = 20.00 bh

Jumlah Total
Jumlah = 20.00 + + +
= 20.00 bh

12. Pas. Grendel Jendela 40.00 Bh


Jendela J3
Jumlah unit = 10.00unit
Jumlah dalam 1 unit = 4.00 bh
Volume - a = 10.00 x 4.00 = 40.00 bh

Jumlah Total
Jumlah = 40.00 + + +
= 40.00 bh
VI PEKERJAAN ATAP
PERHITUNGAN VOLUME PEKERJAAN

PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TAHUN : -

NO LINGKUP PEKERJAAN BESERTA GAMBAR SKET URAIAN PERHITUNGAN VOLUME PEKERJAAN VOLUME

II PEKERJAAN PONDASI BATU KALI


Gambar Penampang Pondasi Batu Kali - Tipe 01 : 1. Pek. Galian Tanah Biasa Sedalam 1 m 46.17 M3
Luas penampang = 0.90 x 0.90
= 0.810 m2
0.05 Volume = 0.81 x 57.00
= 46.17 m3
Urugan Tanah Kembali

0.65 Pas. Batu Kali Spesi 1Pc : 4Ps


2. Pek. Urugan Pasir Tbl. 5 cm 2.57 M3
0.90
Luas penampang = 0.05 x 0.90
= 0.045 m2
Aanstampang
0.20 Volume = 0.05 x 57.00
Urugan Pasir Tbl. 5 cm
0.05 = 2.57 m3

0.30
0.70 3. Pek. Aanstampang / Batu Kosong 10.26 M3
0.90 Luas penampang = 0.20 x 0.90
= 0.180 m2
Panjang Rencana Pondasi : Volume = 0.18 x 57.00
Arah horizontal = 18.00 x 2.00 = 36.00 m = 10.26 m3
Arah vertikal = 7.00 x 3.00 = 21.00 m
Panjang total pondasi = 57.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 19.95 M3
Luas penampang = 1/2 x 0.30 + 0.70 x 0.70
= 0.350 m2
Volume = 0.35 x 57.00
= 19.95 m3

5. Urugan Tanah Kembali 14.82 M3


Luas penampang = 2.00 x 1/2 x 0.10 + 0.30 x 0.65
= 0.260 m2
Volume = 0.26 x 57.00
= 14.82 m3

Gambar Penampang Pondasi Batu Kali - Tipe 02 : 1. Pek. Galian Tanah Biasa Sedalam 1 m 15.36 M3
Luas penampang = 0.80 x 0.80
= 0.640 m2
0.05 Volume = 0.64 x 24.00
= 15.36 m3
Urugan Tanah Kembali

0.55
Pas. Batu Kali Spesi 1Pc : 4Ps 2. Pek. Urugan Pasir Tbl. 5 cm 0.96 M3
0.80
Luas penampang = 0.05 x 0.80
Aanstampang = 0.040 m2
0.20
Urugan Pasir Tbl. 5 cm Volume = 0.04 x 24.00
0.05
= 0.96 m3
0.30
0.60 3. Pek. Aanstampang / Batu Kosong 3.84 M3
0.80
Luas penampang = 0.20 x 0.80
= 0.160 m2
Panjang Rencana Pondasi : Volume = 0.16 x 24.00
Arah horizontal = 18.00 x 1.00 = 18.00 m = 3.84 m3
Arah vertikal = 2.00 x 3.00 = 6.00 m
Panjang total pondasi = 24.00 m 4. Pek. Pasangan Batu Kali Spesi 1Pc : 4Ps 6.48 M3
Luas penampang = 1/2 x 0.30 + 0.60 x 0.60
= 0.270 m2
Volume = 0.27 x 24.00
= 6.48 m3

5. Urugan Tanah Kembali 4.62 M3


Luas penampang = 2.00 x 1/2 x 0.10 + 0.25 x 0.55
= 0.193 m2
Volume = 0.19 x 24.00
= 4.62 m3