RAB Paving Block Kantor Desa New
RAB Paving Block Kantor Desa New
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 160.20 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
0.15 m
Volume Galian (V) = 2.88 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 92.00 M
Jumlah Galian (n) = 2.00 buah 0.15 m
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 1.66 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 65.00 M
Jumlah Galian (n) = 2.00 buah 0.15 m
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 1.17 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 65.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 1.17 M³ ;AxnxL
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 175.00 M
Jumlah Galian (n) = 2.00 buah 0.15 m
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 3.15 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 175.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 3.15 M³ ;AxnxL
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 234.00 M
Jumlah Galian (n) = 2.00 buah 0.15 m
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 4.21 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 234.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 4.21 M³ ;AxnxL
Kabupaten : Serang Jenis Pekerjaan : Galian Timbunan Kabupate
Kecamatan : Waringin Kurung Lokasi : Kp. Nagreg 1 Kecamat
Desa : Sukadalem
TAKE OF SHEET Volume : 125 M x 2.50 M Desa
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 125.00 M
0.15 m
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 2.25 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 125.00 M
Jumlah Timbunan (n)= 2.00 buah
B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 2.25 M³ ;AxnxL
Kabupaten : Serang Jenis Pekerjaan : Galian Timbunan
Kecamatan : Waringin Kurung Lokasi : Kp. Begog Jaya
Desa : Sukadalem
TAKE OF SHEET Volume : 59 M x 5.00 M
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 m 0.06 M
Total Panjang (L) = 112.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 2.02 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.06 m 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 69.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 1.24 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
Lebar Bawah (B2) = 0.06 m 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 47.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 0.85 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 47.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 0.85 M³ ;AxnxL
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.40 M
0.06 m
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 32.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 0.58 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 32.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 0.58 M³ ;AxnxL
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.06 m 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 110.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 1.98 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 110.00 M
Jumlah Timbunan (n)= 2.00 buah B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 1.98 M³ ;AxnxL
Kabupaten : Serang Jenis Pekerjaan : Galian Timbunan
Kecamatan : Waringin Kurung Lokasi : Kp. Nagreg 2
Desa : Sukadalem
TAKE OF SHEET Volume : 30 M x 2.50 M
GALIAN
Lokasi Galian =
Lebar Atas (B1) = 0.06 m 0.40 M
Lebar Bawah (B2) = 0.15 M
Tinggi (H) = 0.06 M
Total Panjang (L) = 30.00 M
Jumlah Galian (n) = 2.00 buah
Luas Galian (A) = 0.01 M² ; ( B2 x H )
Volume Galian (V) = 0.54 M³ ;AxnxL
TIMBUNAN
Lokasi Timbunan =
Lebar (B) = 0.30 M
Tinggi (H) = 0.060 M H= 0.06m
Total Panjang (L) = 30.00 M
Jumlah Timbunan (n)= 2.00 buah
B= 0.30 m
Luas Timbunan (A)= 0.01 M² ;BxH/2
Volume Timbunan (V) = 0.54 M³ ;AxnxL
Kemendesa
Sub Total 2) 0 0
3. UPAH
3.1 Pekerja 5.00 0.00 5.00 HOK 90,000 0 450,000
3.2 Tukang 1.00 0.00 1.00 HOK 110,000 0 110,000
( …………………………………… ) ( ……………………………………… )
PDPM Gerbang Utama
BAHAN
1 Paving model segi empat t 6 cm M2 78,000
2 Semen Zak 63,000
3 Batu Belah M3 165,000
4 Pasir Pasang Zak 220,000
5 Pasir Beton M3 220,000
6 Kansteen Bh 16,000
7 Cat Genteng M3 110,000
3
8 Scroop M 210,000
9 Kerikil / Spleet M3 250,000
10 Besi Beton Ø 10mm Btg 60,000
11 Kawat Beton Kg 20,000
12 Kayu Kelas IV M3 3,000,000
13 Paku Kg 21,000
14 Kayu Dolken Btg 23,000
15 Sendok Semen Bh 15,000
16 Selang Water pas M 5,000
17 Benang Rol 5,000
18 Three Whell Roller 6-8T Jam 250,000
19 Mobilisasi Alat (PP) Ls 1,000,000
20 Pipa PVC 2" Btg 100,000
ALAT
1 Papan Nama Proyek Bh 150,000
2 Prasasti Marmer Bh 500,000
3 Kuas Bh 10,000
4 Pengki Bh 15,000
5 Ember Bh 15,000
6 Sapu Lidi Bh 15,000
7 Sekop Bh 100,000
8 Meteran 5 M Bh 20,000
9 Cangkul Bh 100,000
10 Gerobak bh 750,000
UPAH
1 Pekerja HOK 90,000
2 Tukang HOK 110,000
3 Kepala Tukang HOK 120,000
4 Mandor HOK 120,000
Kabupaten : Serang Jenis Prasarana : Perkerasan
Kecamatan : Waringin Kurung Lokasi : Halaman Kantor Desa
TAKE OF SHEET
Desa : Sukadalem Volume : Variatif
Jenis Kerusakan : Jalan masih tanah Jenis Kerusakan : Badan Jalan berlobang
Tingkat Kerusakan : Berat Tingkat Kerusakan : Sedang
Bahan : Agregat B Bahan : Agregat A
P0 P0
1.00 50.00 0.10 5.00 -
P1 P1
1.00 50.00 0.10 5.00 -
P2 P2
1.00 50.00 0.10 5.00 -
P3 P3
1.00 50.00 0.10 5.00 -
P4 P4
1.00 50.00 0.10 5.00 -
P5 P5
1.00 16.50 0.10 1.65 -
P6 P6
2.50 50.00 0.10 12.50 -
P7 P7
2.50 12.60 0.10 3.15 -
P8 P8
2.50 - 0.10 - -
P9 P9
2.50 - 0.10 - -
P10 P10
-
329.10 42.30 - -
0.1 M
1.00 M
0.1 M
2.50 M
1 Volume
Panjang : L : L : 37.80 M
Lebar : B : 12.30 M
Tebal : t : 0.10 M
Luas : 464.94 M²
V total = V1 x n = 46.49 M³
2 Volume
Panjang : L : L : 13.20 M
Lebar : B : 1.80 M
Tebal : t : 0.10 M
Luas : 23.76 M²
V total = V1 x n = 2.38 M³
3 Total Volume
Panjang : L : L : 51.00 M
Lebar : B : (1.00 - 2.5 ) M M
Tebal : t : 0.10 M
Luas : 488.70 M²
V total = V1 x n = 48.87 M³
E VK1 = (2xP1)+(2xL1)
VK1 = 100.20 M'
VK2 = (2xP2)+(2xL2)
VK2 = 30.00 M'
VK3 = (2xP3)+(2xL3)
VK3 = 30.00 M'
D LUASAN PENGECATAN
Luasan Pengecatan = 1/4 Luasan Paving Block
= 129.22 M²
PDPM Gerbang Utama
HARGA SATUAN PEKERJAAN PAVING BLOK
Kabupaten : Serang Jenis Prasarana : Paving Blok
Kecamatan : Waringin Kurung Volume : Variatif
Desa : Sukadalem
3 PEKERJAAN KANSTEEN
Memasang 1 m' Kanstin Jepit lokal, 10.20.40, K-300 M1 160.20 7,722,793
2.5000 Bh Kanstin Jepit Lokal, 10.20.40., K-300 400.50 16,000 6,408,000
0.7200 Kg Semen 50 kg 115.34 1,260 145,333
0.0050 M3 Pasir Pasang PU Cipta Karya 0.80 220,000 176,220
0.0500 Hok Pekerja Thn. 2014 8.01 90,000 720,900
0.0100 Hok Tukang 1.60 110,000 176,220
0.0010 Hok Kepala Tukang 0.16 120,000 19,224
0.0040 Hok Mandor 0.64 120,000 76,896
4 PEKERJAAN PENGECATAN
1 m2 Pengecatan baru M2 129.22 632,772
0.1000 Kg Cat Dasar 12.92 110,000 1,421,365
0.2600 Kg Cat Penutup Permen PUPR 28 33.60 110,000 3,695,549
0.0200 Hok Pekerja TH 2016 2.58 90,000 232,587
0.0630 Hok Tukang 8.14 110,000 895,460
0.0030 Hok Mandor 0.39 120,000 46,517
PDPM Gerbang Utama
REKAPITULASI KEBUTUHAN BAHAN, ALAT DAN UPAH
segi empat t 6
Paving model
Kanstin Jepit
Pasir Pasang
Semen 50 kg
10.20.40., K-
Cat Ekterior
Pasir Beton
Cat Dasar
Pekerja
Tukang
K-250
Lokal,
300
Pekerjaan
TOTAL 522.03 25.84 0.80 400.50 12.92 33.60 2.31 142.38 268.17
: Paving Blok
: Variatif
Kepala Tukang
Mandor
HOK HOK
0.26
25.84 0.67
0.16 0.64
0.39
26.00 1.96
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
Jenis Kerusakan : Jalan masih tanah Jenis Kerusakan : Badan Jalan berlobang
Tingkat Kerusakan : Berat Tingkat Kerusakan : Sedang
Bahan : Agregat B Bahan : Agregat A
P0 P0
2.50 50.00 0.10 12.50 -
P1 P1
2.50 50.00 0.10 12.50 -
P2 P2
2.50 3.40 0.10 0.85 -
P3 P3
2.50 - 0.10 - -
P4 P4
2.50 - 0.10 - -
P5 P5
2.50 - 0.10 - -
P6 P6
2.50 - 0.10 - -
P7 P7
2.50 - 0.10 - -
P8 P8
2.50 - 0.10 - -
P9 P9
2.50 - 0.10 - -
P10 P10
-
103.40 25.85 - -
0.1 M
2.50 M
2 Volume
Panjang : L : L : 103.40 M
Lebar : B : 2.50 M
Tebal : t : 0.10 M
Luas : 258.50 M²
V total = V1 x n = 25.85 M³
233 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 224.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = - M²
0.100 M'
70.00
V total = V1 x n = 1.40 M³
2 VOLUME BEKESTING
pb : Panjang : 2L + B x ( n + 1 ) = - M
tb : Lebar : t = - M
Volume : pb x tb = - M²
3 x pakai, V = - M²
3 PLASTIK CORAN
L1 = P x ( B + 2t ) = - M²
32,788,962.96
192,070.00
1 hari = 11.88 M³
Sewa alat = 0.00 Hari
PDPM Gerbang Utama
HARGA SATUAN PEKERJAAN PAVING BLOK
Kabupaten : Serang Jenis Prasarana : Paving Blok
Kecamatan : Waringin Kurung Volume : Kp. Begog Jaya
Desa : Sukadalem Referensi : SNI 2007, SNI 2008 Brebes
3 PEKERJAAN KANSTEEN
Memasang 1 m' Kanstin Jepit lokal, 10.20.40, K-300 M1 224.00 10,798,413
2.5000 Bh Kanstin Jepit Lokal, 10.20.40., K-300 560.00 16,000 8,960,000
0.7200 Kg Semen 50 kg 161.28 1,260 203,213
0.0050 M3 Pasir Pasang PU Cipta Karya 1.12 220,000 246,400
0.0500 Hok Pekerja Thn. 2014 11.20 90,000 1,008,000
0.0100 Hok Tukang 2.24 110,000 246,400
0.0010 Hok Kepala Tukang 0.22 120,000 26,880
0.0040 Hok Mandor 0.90 120,000 107,520
JUMLAH 59,542,322
Kepala Tukang
segi empat t 6
Paving model
Kanstin Jepit
Pasir Pasang
Semen 50 kg
10.20.40., K-
Pasir Beton
Mandor
Pekerja
Tukang
K-250
Lokal,
300
Pekerjaan
III PEKERJAAN KANSTEEN 1.12 3.23 560.00 11.20 2.24 0.22 0.90
2,00
1,50
0,05
TOTAL 282.80 14.00 1.12 3.23 560.00 83.00 142.24 14.22 1.44
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
Jenis Kerusakan : Jalan masih tanah Jenis Kerusakan : Badan Jalan berlobang
Tingkat Kerusakan : Berat Tingkat Kerusakan : Sedang
Bahan : Agregat B Bahan : Agregat A
P0 P0
3.00 21.00 0.10 6.30 -
P1 P1
3.00 - 0.10 - -
P2 P2
3.00 - 0.10 - -
P3 P3
3.00 - 0.10 - -
P4 P4
3.00 - 0.10 - -
P5 P5
3.00 - 0.10 - -
P6 P6
2.50 - 0.10 - -
P7 P7
2.50 - 0.10 - -
P8 P8
2.50 - 0.10 - -
P9 P9
2.50 - 0.10 - -
P10 P10
-
21.00 6.30 - -
0.1 M
3.00 M
2 Volume
Panjang : L : L : 21.00 M
Lebar : B : 3.00 M
Tebal : t : 0.10 M
Luas : 63.00 M²
V total = V1 x n = 6.30 M³
86 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 184.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 18.40 M²
69 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 138.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 13.80 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
65 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 130.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 13.00 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
47 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 94.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 9.40 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
175 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 350.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 35.00 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
32 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 64.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 6.40 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
Jenis Kerusakan : Jalan masih tanah Jenis Kerusakan : Badan Jalan berlobang
Tingkat Kerusakan : Berat Tingkat Kerusakan : Sedang
Bahan : Agregat B Bahan : Agregat A
P0 P0
1.30 50.00 0.10 6.50 -
P1 P1
1.30 50.00 0.10 6.50 -
P2 P2
1.30 50.00 0.10 6.50 -
P3 P3
1.30 50.00 0.10 6.50 -
P4 P4
1.30 34.00 0.10 4.42 -
P5 P5
1.30 - 0.10 - -
P6 P6
1.30 - 0.10 - -
P7 P7
1.30 - 0.10 - -
P8 P8
1.30 - 0.10 - -
P9 P9
1.30 - 0.10 - -
P10 P10
-
234.00 30.42 - -
0.1 M
1.30 M
2 Volume
Panjang : L : L : 234.00 M
Lebar : B : 1.30 M
Tebal : t : 0.10 M
Luas : 304.20 M²
V total = V1 x n = 30.42 M³
234 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 468.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 46.80 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
125 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 250.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 25.00 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
30 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 60.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 6.00 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK
30 m
C VOLUME KANSTEEN
Volume Kansten = Vk : L x 2 = 220.00 M'
D VOLUME PENGECATAN
Panjang Kansteen = Pk = 0.40 M
Lebar Kansteen = Lk = 0.10 M
Volume Pengecatan = Vp : Lk x L x 2 = 22.00 M²
RENCANA ANGGARAN BIAYA ( RAB ) PAVING BLOCK