I. PEKERJAAN PERSIAPAN
A. Pembersian Lapangan
Lebar = 13.00 m
Panjang = 23.00 m
Luas = (PxL)
= 23 x 13 m 299.00 M²
9.00
B. Pemasangan Bouwplank
Lebar = 11.00 m
Panjang = 21.00 m
Keliling = 2x(P+L)
= 2*(11+21) m 64.00 M¹
HALAMAN 1
NO PERHITUNGAN VOLUME SATUAN
Volume = ( P x L x T ) x Unit
= (1.2 x 1.2 x 1,32) x 23 43.72 M³
Volume = ( P x L x T ) x Unit
= (1.2 x 1.2 x 0,05 ) x 23
= 0,72 x 23 1.66 M³
HALAMAN 2
NO PERHITUNGAN VOLUME SATUAN
1.d aanstamping
Tinggi = 0.10 m
Lebar = 1.20 m
Panjang = 1.20 m
Jumlah = 23.00 Unit
Volume = ( P x L x T ) x Unit
= (1.2 x 1.2 x 0.10) x 23
= 0.144 X 23 3.31 M³
volume = ( P x L x T ) x Unit
= (0.3 x 0.3 x 1.6) x 23
= 1.44 x 23 3.31 M³
volume = ( P x L x T ) x Unit
= (1,2 x 1,2 x 0,225) x 23
= 1.44 x 23 7.45 M³
HALAMAN 3
NO PERHITUNGAN VOLUME SATUAN
Volume = P x (1/2*(a+b)*t)
= 82.3 x (1/2 x (0.80+1.12) x 0.72)
= 82.3 x 0.69 56.89 M³ Ker
Spe
Bet
Pas
2.b alas pasir pondasi menerus
Tinggi = 0.05 m
Lebar Bawah = 0.80 m
Panjang = 107.50 m
75
Tanahuru
Volume = (P x L x T)
= (107.5 x 0.80 x 0.05) 4.30 M³
2.c Aanstamping
Tinggi = 0.10 m
Lebar Bawah = 0.80 m 72
Panjang = 107.50 m
10
5
Volume = (P x L x T)
= (107.50 x 0.80 x 0.10) 8.60 M³
HALAMAN 4
NO PERHITUNGAN VOLUME SATUAN
Lebar Atas =
Panjang = 107.50 m
SLOOF25/ 30
3.50
SLOOF25/ 30
SLOOF25/ 30
3.50 TANGGA
SLOOF25/ 30
SLOOF25/ 30
2.00
HALAMAN 5
NO PERHITUNGAN VOLUME SATUAN
Volume = PxLxT
= 0,15 x 1,12 x 10,40 1.747 M3
Volume = PxLxT
= 0,05 x 1,12 x 10,40 2.881 M3
18
C. Aanstamping Tangga Depan
Tinggi = 0.10 m 18
Lebar = 5.54 m
Panjang = 10.40 m 18
Volume = PxLxT 16
= 0,10 x 1,12 x 10,40 5.762 M 3
10
5
HALAMAN 6
NO PERHITUNGAN VOLUME SATUAN
Volume = PxLxT
= 9,88 x 0,60 x 0,52 3.083 M3
Volume = PxLxT
18
= 9,88 x 0,70 x 0,50 2.964 M3
HALAMAN 7
NO PERHITUNGAN VOLUME SATUAN
Luas = TxP
= 1,52 x 10,40 15.808 M2
H. Plasteran 1 : 2
Luas = 2 x Pas. Dinding Trasram
= 2 x 15.81 31.616 M2
18
18
10
Luas = PxL
5
= 10.40 x 1.82 18.928 M2
HALAMAN 8
NO PERHITUNGAN VOLUME SATUAN
4 PEKERJAAN BETON
1 2
panjang = 107.50 m
SLOOF25/ 30
3.50
lebar = 0.25 m
tinggi = 0.30 m
volume = (p x l x t) 8.06 M³
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
3.50 TANGGA
SLOOF25/ 30 SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
2.00
SLOOF25/ 30 SLOOF25/ 30
Kolo
= (0.3X0.3X7,80)X23 16.15 M³
Kolom30/30 Kolo
3.50 TANGGA
Kolom30/30 Kolo
2.00
Kolom30/30 Kolo
HALAMAN 9
NO PERHITUNGAN VOLUME SATUAN
Kolom30/30 Kolom30/
= (107,50x0.3x0.4) 12.90 M³
Kolom30/30 Kolom30/
2.00
D BALOK LATAI
Kolom30/30 Kolom30/
Panjang = 3.70
Lebar = 0.13
Tinggi = 0.13
= 8.00
0.13
Unit
Volume = PxTxLxT
= 3,70 x 0,13 x 0,13 x 8 0.50
E RING BALK
PANJANG = 126.5 m
LEBAR = 0.2 m
TINGGI = 0.3 m
VOLUME = (P X L X T)
= (169x0.2x0.3) 7.59 M³
Tinggi = 3.62 m
29.60 m A 2.70
=
BORDES
Panjang (16-(0.3X4))X2 KA
Volume = PxT
3.50
- Pintu p1
2.00 1.70 NAIK
Tinggi = 2.10 m
Panjang = 0.90 m
Unit = 4.00 m
Volume = P x T x Unit
= 2.10 x 0,9 x 4 7.56 M2
NO PERHITUNGAN VOLUME SATUAN
- Jendela J1
Tinggi = 1.48 m
Panjang = 2.17 m
Unit = 4.00 m
Volume = P x T x Unit
= 2.17 x 1,48 x 4 12.85 M2
- Jendela J2
Tinggi = 1.48 m
Panjang = 1.51 m
Unit = 4.00 m
Volume = P x T x Unit
= 1,51 x 1,48 x 4 8.94 M2
- Jumlah Volume Pasangan Dinding Bata - Volume Pintu dan Jendela 193.65 M2
Panjang = 29.60 m
Volume = PxT 3.50
Horizontal 3.50
Tinggi = 3.55 m
Panjang = 19.20 m
= PxT
2.00 TURUN
Volume
= 3,55 x 19,20 68.16 M2
HALAMAN 7
NO PERHITUNGAN VOLUME SATUAN
Pintu p1
Tinggi = 2.10 m
Panjang = 0.90 m
Unit = 2.00 m
Volume = P x T x Unit
= 2.10 x 0,9 x 2 3.78 M2
1 2
Jendela J1
Tinggi = 1.48 m 3.00
Panjang = 2.17 m
Unit = 8.00 m 3.50
HALAMAN 8
NO PERHITUNGAN VOLUME SATUAN
lantai 2
luas = (2 x luas lantai 2 dinding bata 1 : 4)
= (2 x 143.77) 287.53 M2
Luas = (L x T) x unit
= (0.3 x 7.8) x 20 46.80
lebar = 0.30 m
tinggi = 6.90 m
jumlah = 3.00 unit
Luas = (L x T) x unit
= (0.30 x 6.90) x 3 6.21 M³
HALAMAN 9
NO PERHITUNGAN VOLUME SATUAN
Luas = (L x T)
= (0.30 x 107.50) 32.25 M2
6 PEKERJAAN LANTAI
6.a Tanah urug bawah lantai bagian a
RUANG A
PANJANG = 6.75 m
LEBAR = 3.75 m
TINGGI = 0.20 m 1 2
3.00 4.15
VOLUME = (P X L X T)
= (6.75X3.75X0.20) 5.06 M³
3.50
RUANG B RUANG
PANJANG = 6.75 m
LEBAR = 3.75 m 3.50 BAGIAN A
TINGGI = 0.20 m
= (P X L X T) BAGIAN B BAGIAN
VOLUME
2.00
= (6.75X3.75X0.20) 5.06 M³
3.00 4.00
HALAMAN 10
NO PERHITUNGAN VOLUME SATUAN
Ruang C
PANJANG = 6.75 m
LEBAR = 3.75 m
TINGGI = 0.20 m
VOLUME = (P X L X T)
= (6.75x3.75x0.20) 5.06 M³
1 2
Ruang D
PANJANG = 6.75 m
3.00 4.15
LEBAR = 3.75 m
TINGGI = 0.20 m
3.50
VOLUME = (P X L X T) RUANG
= (6.75x3.75x0.20) 5.06 M³
3.50 BAGIAN A
Bagian A
Panjang = 3.25 m
BAGIAN B BAGIAN
=
2.00
Lebar 2.75 m
Tinggi = 0.2 m
M2
3.00 4.00
Volume = (P X L X T)
= (3.25 x 2.75 x 0.20) 1.79 M³
Bagian B
Panjang = 1.75 m
Lebar = 2.75 m
Tinggi = 0.2 m
Volume = (P X L X T)
= (1.75 x 2.75 x 0.20) 0.96 M³
HALAMAN 11
NO PERHITUNGAN VOLUME SATUAN
Bagian C
Panjang = 1.75 m
Lebar = 3.75 m
Tinggi = 0.2 m
Volume = (P X L X T)
= (1.75 x 3.75 x 0.20) 1.31 M³
Bagian D M³
Panjang = 1.75 m
Lebar = 3.75 m 1 2
Tinggi = 0.2 m
3.00 4.15
Volume = (P X L X T)
= (1.75 x 3.75 x 0.20) 1.31 M³ 3.50
RUANG
Bagian E M³
Panjang = 1.75 m
3.50 BAGIAN A
Lebar = 3.75 m
Tinggi = 0.2 m
2.00 BAGIAN B BAGIAN
Volume = (P X L X T)
= (1.75 x 3.75 x 0.20) 1.31 M³
3.00 4.00
Bagian F M³
Panjang = 1.75 m
Lebar = 3.75 m
Tinggi = 0.2 m
Volume = (P X L X T)
= (1.75 x 3.75 x 0.20) 1.31 M³
HALAMAN 12
NO PERHITUNGAN VOLUME SATUAN
volume = (P x L x T) x unit 1 2
= (6.82 x 3.49 x 0.53) x 4 50.46 M³
3.00 4.15
bagian A 3.50
Tinggi = 0.33 m
Lebar = 0.08 m RUANG
panjang = 2.98 m
BAGIAN A
sisi = 4 sisi
3.50
bagian B
Tinggi = 0.33 m
Lebar = 0.08 m
panjang = 1.48 m
sisi = 4 sisi
volume = (P x L x T) x unit
= (1.48 x 0.08 x 0.33) x 4 0.16 M³
HALAMAN 13
NO PERHITUNGAN VOLUME SATUAN
bagian C
Tinggi = 0.33 m M³
Lebar = 0.08 m
panjang = 1.48 m
sisi = 4 sisi
volume = (P x L x T) x unit 1 2
= (1.48 x 0.08 x 0.33) x 4 0.16 M³
3.00 4.15
bagian D
Tinggi = 0.33 m
3.50
Lebar = 0.08 m
panjang = 1.48 m RUANG
sisi = 4 sisi
3.50 BAGIAN A
Tinggi = 0.33 m
Lebar = 0.08 m M³
panjang = 1.48 m
sisi = 4 sisi
volume = (P x L x T) x unit
= (1.48 x 0.08 x 0.33) x 4 0.16
HALAMAN 14
NO PERHITUNGAN VOLUME SATUAN
bagian F
Tinggi = 0.33 m M³
Lebar = 0.08 m
panjang = 1.48 m
sisi = 4 sisi
volume = (P x L x T) x unit
= (1.48 x 0.08 x 0.33) x 4 0.16 M³
M²
total tanah urug bawah lantai bagian b
volume = R.A ,B,C,D + B.A + B.B +B.C + B.D + B.E + B.F 1 2
Bagian A M²
Panjang = 3.50 m
Lebar = 3.00 m
Tinggi = 0.1 m
Volume = (P X L X T)
= (3.50 x 3.00 x 0.10) 1.05 M³
HALAMAN 15
NO PERHITUNGAN VOLUME SATUAN
Bagian B
Panjang = 2.00 m
Lebar = 3.00 m
Tinggi = 0.1 m
Volume = (P X L X T)
= (2.00 x 3.00 x 0.10) 0.6 M³
1 2
Panjang = 2.00 m
Lebar = 4.00 m 3.50
Tinggi = 0.1 m
jumlah = 4.00 bagian RUANG
Ruang A, B, C, dan D
Lebar = 4m 3.50
panjang = 7.00 m M³
RUANG
jumlah = 4 ruang
3.50 BAGIAN A
LUAS = (P x L ) x byk ruangan
= (7.00x4.00) x 4 112 M²
2.00 BAGIAN B BAGIAN
Bagian A
Lebar = 3m
panjang = 3.50 m M³ 3.00 4.00
LUAS = (P x L)
= (3.50x3.00) 10.5 M²
HALAMAN 17
NO PERHITUNGAN VOLUME SATUAN
Bagian B
Lebar = 3m
panjang = 2.00 m
= (P x L)
1 2
LUAS
= (2.00x3.00) 6 M²
3.00 4.15
Bagian C,D,E,F M³
Lebar = 4m 3.50
4.00
6.G PLAT BETON LANTAI 2
PLAT BETON
Ruang A,B
Tinggi = 0.12 m
Lebar = 8m
BAGIAN A
panjang = 7.00 m
jumlah = 2 ruang
HALAMAN 18
NO PERHITUNGAN VOLUME SATUAN
Bagian B
Tinggi = 0.12 m
Lebar = 3m M²
panjang = 2.00 m
volume = (P x L x T)
= (2.00x3.00x 0.12) 0.72 M³
bagian C,D,E,F M³
Tinggi = 0.12 m
Lebar = 4m 8.00
panjang = 2.00 m M³
4.00
jumlah 4 bagian
Bagian B
Tinggi = 0.05 m
Lebar = 3.00 m
Panjang = 2.00 m
Volume = (PxLxT)
= ( 2 x 3 x 0,05 ) 0.3 M³
8.00
Tinggi = 0.05 m
Lebar = 4.00 m
Panjang = 2.00 m
jumlah = 3 bagian
BAGIAN A
Volume = ( P x L x T ) xbagian
= ( 2 x 4 x 0,05 )x3 1.2 M³
Bagian F
Tinggi = 0.05 m
Lebar = 4.00 m
Panjang = 2.00 m
Volume = (PxLxT)
= ( 2 x 4 x 0,05 ) 0.4 M³
HALAMAN 20
NO PERHITUNGAN VOLUME SATUAN
Bagian B
Lebar = 3m 8.00
LUAS = (P x L)
= (2x3.00) 6 M²
Bagian C,D,E
BAGIAN A
Lebar = 4m
panjang = 2.00 m
jumlah = 3 bagian
M³
LUAS = (P x L)x bagian
= (2.00x4.00) x3 24 M²
Bagian F
Lebar = 4m
panjang = 2.00 m
LUAS = (P x L)
= (2x4.00) 8 M²
7 Pekerjaan plafond
7.A Lantai 1
Rangka Plafond Kayu 150 M²
Pemasangan Plafond Multiplek 4 mm 150 M²
pemasangan list plafond 300 M²
7.B Lantai 2
Rangka Plafond 144 M²
Pemasangan Plafond Kayu 144 M²
pemasangan list plafond 365 M
8 PEKERJAAN ATAP
Lebar = 18.4 m
Panjang = 11.4 m
LUAS = (P x L)
= (11.4x18.4) 209.76 M²
9 PEKERJAAN TANGGA
9.A plat tangga
Tinggi = 0.15 m
Lebar = 1.45 m
Panjang = 8.13 m
1.20 0.69 1.20 1.20 1.20
Volume = (PxLxT)
= (8.13 x 1,45 x 0,15 ) 1.768 M³
Volume = (PxLxT)
Besi Hollow2/2
= ( 3 x 1,15 x 0,15 ) 0.52 M³ Besi Hollow4/2
175
9.C Balok Bordes 20/35
Bordes T=15cm95
Tinggi = 0.35 m
Lebar = 0.20 m Balok20/3
15
Panjang = 3.00 m 390
Ø12- 120
115
Volume = (PxLxT)
= ( 3 x 0,2 x 0,35 ) 0.210 M³ 200
HALAMAN 22
NO PERHITUNGAN VOLUME SATUAN
9.E Keramik
Keramik di Bordes
Panjang = 3.00 m
Lebar = 1.15 m
Luas = (PxL)
= ( 3 x 1,15 ) 3.45 M² 350
HALAMAN 23
NO PERHITUNGAN VOLUME SATUAN
10 Pekerjaan Kusen
10.A Pintu P1
Tinggi = 0.13 m
Lebar = 0.06 m
Panjang = 7.28 m
jumlah = 6 unit
Volume = ( P x L x T ) xunit
= ( 7.28 x 0.06 x 0,06 )x6 0.34 M³
Daun Pintu P1
Tinggi = 2.10 m
Panjang = 0.82 m
jumlah = 6 unit
272
Luas = ( P x L )xunit
= ( 0.82 x 2.10 )x6 10.33 M³
HALAMAN 28
NO PERHITUNGAN VOLUME SATUAN
10.B jendela J1
Kusen jendela
Tinggi = 0.13 m
Lebar = 0.06 m
Panjang = 199.28 m
jumlah = 12 unit
Volume = ( P x L x T ) xunit
= (199.28 x 0.06 x 0,13 )x12 18.65 M³
Daun Jendela J1
Panjang = 0.80 m
Lebar = 0.60 m
jumlah = 3 unit
148
3,5/ 8 3,
kaca Jendela J1
Panjang = 0.64 m
Lebar = 0.44 m 6 6 60 6
10.C jendela J2
Kusen jendela
Tinggi = 0.13 m
Lebar = 0.06 m 148
Panjang = 7.22 m
jumlah = 4 unit
Volume = ( P x L x T ) xunit
= (7.22 x 0.06 x 0,13 )x4 0.23 M³
jumlah = 2 unit
kaca Jendela J2
Panjang = 0.64 m
Lebar = 0.44 m
jumlah = 2 unit
11 PEKERJAAN PENGECATAN
11.A DINDING
Lantai 1 = plasteran bata 1:4 387.53 M²
Lantai 2 = plasteran bata 1:4 287.77 M²
HALAMAN 31
NO PERHITUNGAN VOLUME SATUAN
HALAMAN 32
GAMBAR
19.00
GAMBAR
4
7
23
63
TanahUrug
TanahUrug
TanahUrug
137
Pond. Tapak 20
Aastamping 10
5
30
1.20
GAMBAR
PENDESTAL
POOR
GAMBAR
2 3 4 5 6
19.00
C B 3.50
9.00
3.50
2.00
Keramik40x40 Keramik40x40
Spesi T=4cm Spesi T=4cm
Betoncor 1:3:5, T=5cm Betoncor 1:3: 5, T=5cm
Pasir urug Pasir urug
±0.00 ±0.00
4 1
7
10
Sloof 25/ 30
Tanahurug
53
Tanahurug
72
Pondasi BatuKali
10 Anstamping
5 LapisanPasir
25
80
GAMBAR
2 3 4 5 6
19.00
3.00 4.00 4.00 4.00 4.00
D
SLOOF25/30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
SLOOF25/ 30
SLOOF25/30
SLOOF25/ 30
SLOOF25/ 30
3.50
C
SLOOF25/30
9.00
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/30
SLOOF25/ 30
SLOOF25/ 30
TANGGA 3.50
B
SLOOF25/30 SLOOF25/30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/30
SLOOF25/ 30
SLOOF25/ 30
2.00
A
SLOOF25/30 SLOOF25/30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
19.00
GAMBAR
6.70 3.70
10
Spesi T=4cm
18 20
Pasir urug
18 20 Tanahurug 15
18 20 15
32
16 5 14
6
10
GAMBAR
10
Spesi T=4cm
8 20
Pasir urug
8 20 Tanahurug 15
8 20 15
32
6 5 14
6
0
GAMBAR
10
Spesi T=4cm
8 20
Pasir urug
8 20 Tanahurug 15
8 20 15
32
6 5 14
6
0
GAMBAR
3 4 5 6
19.00
4.00 4.00 4.00 4.00
D
SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
3.50
9.00
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
3.50
B
SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
SLOOF25/ 30
2.00
A
SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30 SLOOF25/ 30
19.00
2 3 4 5 6
19.00
0 4.00 4.00 4.00 4.00
3.50
9.00
GGA 3.50
2.00
19.00
GAMBAR
2 3 4 5 6
19.00
3.00 4.00 4.00 4.00 4.00
D
Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30
3.50
C
30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30
9.00
NGGA 3.50
B
30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30
2.00
A
30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30 Kolom30/30
19.00
3.70
0.13
apDaagT=12cm
RengBalk20/ 30
Balok18/35 Balok18/35
3.00 0.20
B
2 3 4 5 6
19.00
4.00 4.00 4.00 4.00
3.70
D
3.20 3.50
9.00
3.50
19.00
B DENAHLANTAI 1
SKALA 1:100
GAMBAR
B
2 3 4 5 6
19.00
4.00 4.00 4.00 4.00
3.50
RUANGBELAJAR RUANGBELAJAR C
A
+3.90 +3.90
9.00
3.50
19.00
B DENAHLANTAI 2
SKALA 1: 100
GAMBAR
B
2 3 4 5 6
19.00
4.00 4.00 4.00 4.00
3.50
RUANGBELAJAR RUANGBELAJAR C
A
+3.90 +3.90
9.00
3.50
19.00
B DENAHLANTAI 2
SKALA 1: 100
GAMBAR
GAMBAR
3 4 5 6
19.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
3 4 5 6
19.00
3.50
9.00
3.50
3 4 5 6
19.00
4.15 4.00 4.00 4.00
3.50
9.00
3.50
8.00 8.00
3.50
3.50
GAMBAR
8.00 8.00
3.50
3.50
GAMBAR
8.00 8.00
3.50
3.50
GAMBAR
8.00 8.00
3.50
3.50
GAMBAR
18.40
1.14
1.14
1.14
1.14
1.14
1.14
1.14
1.14
1.14
1.14
1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 0.91 1.20
30
30
30
30
30
30
30
30
30
30
Be30
si Hollow4/2
Balok30/40
30 Besi Hollow2/2
30
18
18
18
18
15
18
Kolom30/ 30
18
m95
30 Besi Hollow2/2
30
Balok20/35
Y-Y 30
Besi Hollow4/2
30
18 30
30
Ø12- 120 18 Besi Hollow2/2
Ø12- 120 Besi Hollow4/2
115 18
18
Ø12- 120
18
15
18
18
Ø12- 120 18
Ø12- 120 18
GAMBAR
145 10 145
15 BORDES 115
+2.16
+2.34
+1.98
+2.52
+1.62
+2.70
+1.44
+2.88
+1.26
50 +3.06 350
+1.08
+3.24
+0.90
+3.42
+0.72
+3.60
+0.54 +3.78
+0.36
+3.90
+0.18
00
NAIK 200
300
GAMBAR
92 +2,72
50
+2,16
PANEL
210
3,5/7
20
±0,00
3,5/8 Panel 13
13
DETAILP1(4UNIT)
6 80 6 SKALA 1:20
GAMBAR
205 13
6
50
Kaca 5MM
80
3,5/8
6
13
6 60 6 60 6 6
DETAILJ1(4UNIT)
SKALA 1: 20
GAMBAR
139 13
6
50
Kaca 5MM
80
3,5/8
6
13
DETAILJ2(4UNIT)
SKALA 1:20
0 6 60 6 6
GAMBAR
GAMBAR
DAFTAR PERHITUNGAN BESI DAN
PEKERJAAN : PEMBANGUNAN ASRAMA & RKB PUTRI JAMAAH AMALIAH
SUB PEKERJAAN : PANDRAH KEUDE KECAMATAN PANDRAH KAB.BIREUN
LOKASI : 2014
b.
c.
b.
3 Sloof (SL.1) Tum ( 0.25 x 0.30 )
b.
4 Sloof (SL.2) Lap ( 0.25 x 0.30 )
b.
b.
6 Beton Cor Bertulang Balok B.1B ( 0.30 x 0.40 )
b.
7 Beton Cor Bertulang Balok Tangga ( 0.20 x 0.35 )
b.
b.
Bidang X = 19.00 m 1
Bidang Y = 7.00 m
Tebal Pengecoran = 0.12 m
Dia. Tulangan = 10.00 mm
Jarak Tulangan = 0.15 m
b.
b.
12 Beton Cor Bertulang Plat Dack ( 7.75 x 0.15 )
tebal 10 cm
Bidang Arah X Tikar Bawah = 7.75 m 1
Bidang Arah Y Tikar Bawah = 0.86 m
Bidang Arah X Tikar Atas = 7.75 m
Bidang Arah Y Tikar Atas = 0.86 m
Tebal Pengecoran = 0.12 m
Dia. Tulangan = 10.00 mm
Jarak Tulangan = 0.20 m 2
13 ( 3.00 x 0.12 )
Beton Cor Bertulang Plat Bordes
3
4
PERHITUNGAN VOLUME
Panjang untuk 1 m3 = 1/ ( b x h )
= 0.69 m' Bidang Y
Pembesian Tulangan Arah X
Panjang Tulangan (Pjg) = 4.80 m'
Jumlah Tulang (jlh) = 5.00 btg
= 1/ ( b x h )
Panjang Plat untuk 1 m3
Panjang Plat untuk 1 m3
= 0.01 m'
Bidang X = 19.00 m'
Jumlah Baris (jb) = 126.67 brs
Jumlah Lapis (Jl) = 2.00 Lapis
Berat Besi = Pjg x jb x berat Jenis
= 296.60 kg
= 1/ ( b x h )
Panjang untuk 1 m3
= 16.67 m'
Pembesian Untuk 1 m3 Beton adalah
Tul. Pokok = Pjg x byk tul x 0,006165 x dia2
dia. Tul. Pokok (Polos) = 131.520 kg Tulangan. Ulir
Tul. Pinggang = Pjg x byk tul x 0,006165 x dia2
dia. Tul. Pinggang = 40.278 kg Tulangan. Ulir
dia. Tul. Begel
Panjang Begel = 1.00 m'
Banyak Begel = Panjang Balok 1 m3 / Jarak Begel
= 111.00 btg
dia. Tul. Begel = 43.80 kg Tulangan. Polos
= 1/ ( b x h )
Panjang Balok Latai untuk 1 m3
= 2.78 m'
Bidang Arah X Tikar Bawah = 3.00 m'
Jumlah Baris (jb) = 4.00 brs
A. UPAH KERJA
B. BAHAN
C. BALAT
Jenis Pekerjaan : Membuat Beton Mutu F'C = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c =
Satuan / Unit : M3
Analisa : AHSP PU A.1.1.1
Jenis Pekerjaan : Beton Mutu F'C = 14,5 Mpa ( K 175 ), Slump (12 ± 2 ) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.1.1.5
Jenis Pekerjaan : Beton Mutu F'C =19,3 Mpa ( K 225 ), Slump (12 ± 2 ) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.1.1.7
Jenis Pekerjaan : Beton Mutu F'C =24,0 Mpa ( K 275 ), Slump (12 ± 2 ) cm, W/c = 0,53
Satuan / Unit : M3
Analisa : AHSP PU A.1.1.8
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 2PP.
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.1
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP.
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.8
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP.
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.10
Jenis Pekerjaan : Memasang Langit-langit Tripleks Ukuran ( 120 x 240 ) cm, Tebal 4 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
Jenis Pekerjaan : Membuat dan Memasang Daun Pintu Panel Kayu Kelas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.5
Jenis Pekerjaan : Pengecetan Tembok Baru (1 x Plamir, 1 x cat dasar, 2x cat Penutup )
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
Jumlah Harga
Rp 8,500.00
Rp 5,000.00
Rp 13,500.00
Rp 13,500.00
Rp 1,350.00
Rp 14,850.00
Jumlah Harga
Rp 8,500.00
Rp 11,000.00
Rp 1,200.00
Rp 500.00
Rp 21,200.00
Rp 46,200.00
Rp 350.00
Rp 22,750.00
Rp 69,300.00
Rp 90,500.00
Rp 9,050.00
Rp 99,550.00
Jumlah Harga
Rp 34,000.00
Rp 4,000.00
Rp 38,000.00
Rp 38,000.00
Rp 3,800.00
Rp 41,800.00
Jumlah Harga
Rp 62,475.00
Rp 7,400.00
Rp 69,875.00
Rp 69,875.00
Rp 6,987.50
Rp 76,862.50
Jumlah Harga
Rp 21,250.00
Rp 8,330.00
Rp 29,580.00
Rp 29,580.00
Rp 2,958.00
Rp 32,538.00
mbunan Tanah di Datangkan Termasuk Perataan dan Pemadatan
Jumlah Harga
Rp 42,500.00
Rp 5,000.00
Rp 47,500.00
Rp 78,000.00
Rp 78,000.00
Rp 1,250.00
Rp 1,250.00
Rp 126,750.00
Rp 12,675.00
Rp 139,425.00
Jumlah Harga
Rp 25,500.00
Rp 1,000.00
Rp 26,500.00
Rp 144,000.00
Rp 144,000.00
Rp 145,000.00
Rp 14,500.00
Rp 159,500.00
Jumlah Harga
Rp 25,500.00
Rp 1,000.00
Rp 26,500.00
Rp 144,000.00
Rp 144,000.00
Rp 145,000.00
Rp 14,500.00
Rp 159,500.00
Jumlah Harga
Rp 56,100.00
Rp 36,300.00
Rp 3,960.00
Rp 3,300.00
Rp 99,660.00
Rp 115,500.00
Rp 7,000.00
Rp 1,500.00
Rp 90,000.00
Rp 49,000.00
Rp 195,000.00
Rp -
Rp 458,000.00
Rp 557,660.00
Rp 55,766.00
Rp 613,426.00
Jumlah Harga
Rp 56,100.00
Rp 36,300.00
Rp 3,960.00
Rp 3,300.00
Rp 99,660.00
Rp 115,500.00
Rp 7,000.00
Rp 1,125.00
Rp 67,500.00
Rp 49,000.00
Rp 130,000.00
Rp 370,125.00
Rp 469,785.00
Rp 46,978.50
Rp 516,763.50
Jumlah Harga
Rp 56,100.00
Rp 6,600.00
Rp 720.00
Rp 300.00
Rp 63,720.00
Rp 4,427,500.00
Rp 4,427,500.00
Rp 4,491,220.00
Rp 449,122.00
Rp 4,940,342.00
Jumlah Harga
Rp 127,500.00
Rp 82,500.00
Rp 9,000.00
Rp 7,500.00
Rp 226,500.00
Rp 222,000.00
Rp 224,125.00
Rp 91,000.00
Rp 537,125.00
Rp 763,625.00
Rp 76,362.50
Rp 839,987.50
Jumlah Harga
Rp 66,300.00
Rp 42,900.00
Rp 4,680.00
Rp 3,900.00
Rp 117,780.00
Rp 222,000.00
Rp 51,840.00
Rp 273,840.00
Rp 391,620.00
Rp 39,162.00
Rp 430,782.00
mbuat Beton Mutu F'C = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c = 0
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 339,625.00
Rp 114,832.14
Rp 136,900.00
Rp 25,800.00
Rp 617,157.14
Rp 799,317.14
Rp 79,931.71
Rp 879,248.86
mbuat Beton Mutu F'C = 9,8 Mpa (K 125), Slump (12 ± 2) cm, W/c = 0
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 379,500.00
Rp 109,414.29
Rp 133,728.57
Rp 25,800.00
Rp 648,442.86
Rp 830,602.86
Rp 83,060.29
Rp 913,663.14
ton Mutu F'C = 14,5 Mpa ( K 175 ), Slump (12 ± 2 ) cm, W/c = 0,66
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 448,250.00
Rp 100,428.57
Rp 141,011.11
Rp 25,800.00
Rp 715,489.68
Rp 897,649.68
Rp 89,764.97
Rp 987,414.65
ton Mutu F'C =16,9 Mpa ( K 200 ), Slump (12 ± 2 ) cm, W/c = 0,61
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 448,250.00
Rp 100,428.57
Rp 141,011.11
Rp 25,800.00
Rp 715,489.68
Rp 897,649.68
Rp 89,764.97
Rp 987,414.65
ton Mutu F'C =19,3 Mpa ( K 225 ), Slump (12 ± 2 ) cm, W/c = 0,58
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 510,125.00
Rp 92,235.71
Rp 143,477.78
Rp 2,580,000.00
Rp 3,325,838.49
Rp 3,507,998.49
Rp 350,799.85
Rp 3,858,798.34
ton Mutu F'C =21,7 Mpa ( K 250 ), Slump (12 ± 2 ) cm, W/c = 0,56
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 528,000.00
Rp 91,442.86
Rp 142.38
Rp 25,800.00
Rp 645,385.24
Rp 827,545.24
Rp 82,754.52
Rp 910,299.76
ton Mutu F'C =24,0 Mpa ( K 275 ), Slump (12 ± 2 ) cm, W/c = 0,53
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 558,250.00
Rp 90,385.71
Rp 140.60
Rp 25,800.00
Rp 674,576.31
Rp 856,736.31
Rp 85,673.63
Rp 942,409.95
ton Mutu F'C =26,4 Mpa ( K 300 ), Slump (12 ± 2 ) cm, W/c = 0,52
Jumlah Harga
Rp 140,250.00
Rp 30,250.00
Rp 3,360.00
Rp 8,300.00
Rp 182,160.00
Rp 567,875.00
Rp 89,989.29
Rp 139.91
Rp 25,800.00
Rp 683,804.20
Rp 865,964.20
Rp 86,596.42
Rp 952,560.62
Jumlah Harga
Rp 595.00
Rp 770.00
Rp 84.00
Rp 40.00
Rp 1,489.00
Rp 13,650.00
Rp 270.00
Rp 13,920.00
Rp 15,409.00
Rp 1,540.90
Rp 16,949.90
Jumlah Harga
Rp 595.00
Rp 770.00
Rp 84.00
Rp 400.00
Rp 1,849.00
Rp 16,800.00
Rp 270.00
Rp 17,070.00
Rp 18,919.00
Rp 1,891.90
Rp 20,810.90
Jumlah Harga
Rp 2,125.00
Rp 2,750.00
Rp 240.00
Rp 100.00
Rp 5,215.00
Rp 25,500.00
Rp 900.00
Rp 26,400.00
Rp 31,615.00
Rp 3,161.50
Rp 34,776.50
Jumlah Harga
Rp 2,125.00
Rp 28,600.00
Rp 3,120.00
Rp 2,600.00
Rp 36,445.00
Rp 154,000.00
Rp 5,250.00
Rp 750.00
Rp 160,000.00
Rp 196,445.00
Rp 19,644.50
Rp 216,089.50
Jumlah Harga
Rp 44,200.00
Rp 28,600.00
Rp 3,120.00
Rp 2,600.00
Rp 78,520.00
Rp 173,250.00
Rp 5,250.00
Rp 750.00
Rp 179,250.00
Rp 257,770.00
Rp 25,777.00
Rp 283,547.00
Jumlah Harga
Rp 56,100.00
Rp 36,300.00
Rp 3,960.00
Rp 3,300.00
Rp 99,660.00
Rp 154,000.00
Rp 7,000.00
Rp 1,500.00
Rp 67,500.00
Rp 74,200.00
Rp 130,000.00
Rp 434,200.00
Rp 533,860.00
Rp 53,386.00
Rp 587,246.00
Jumlah Harga
Rp 56,100.00
Rp 36,300.00
Rp 3,960.00
Rp 3,300.00
Rp 99,660.00
Rp 154,000.00
Rp 7,000.00
Rp 1,500.00
Rp 81,000.00
Rp 74,200.00
Rp 30,000.00
Rp 347,700.00
Rp 447,360.00
Rp 44,736.00
Rp 492,096.00
Jumlah Harga
Rp 56,100.00
Rp 36,300.00
Rp 3,960.00
Rp 3,300.00
Rp 99,660.00
Rp 154,000.00
Rp 7,000.00
Rp 1,500.00
Rp 67,500.00
Rp 74,200.00
Rp 390,000.00
Rp 694,200.00
Rp 793,860.00
Rp 79,386.00
Rp 873,246.00
Jumlah Harga
Rp 5,100.00
Rp 6,600.00
Rp 720.00
Rp 300.00
Rp 12,720.00
Rp 17,250.00
Rp 17,250.00
Rp 29,970.00
Rp 2,997.00
Rp 32,967.00
Jumlah Harga
Rp 3,655.00
Rp 4,730.00
Rp 516.00
Rp 210.00
Rp 9,111.00
Rp -
Rp 1,000.00
Rp 900.00
Rp 1,900.00
Rp 11,011.00
Rp 1,101.10
Rp 12,112.10
Jumlah Harga
Rp 51,000.00
Rp 22,000.00
Rp 2,400.00
Rp 3,000.00
Rp 78,400.00
Rp 880.00
Rp 2,750.00
Rp 10,500.00
Rp 14,130.00
Rp 92,530.00
Rp 9,253.00
Rp 101,783.00
sangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 2 PP.
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 56,000.00
Rp 26,056.25
Rp 6,650.00
Rp 88,706.25
Rp 127,906.25
Rp 12,790.63
Rp 140,696.88
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 56,000.00
Rp 19,758.75
Rp 7,000.00
Rp 82,758.75
Rp 121,958.75
Rp 12,195.88
Rp 134,154.63
sangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 4 PP.
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 56,000.00
Rp 15,812.50
Rp 7,525.00
Rp 79,337.50
Rp 118,537.50
Rp 11,853.75
Rp 130,391.25
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 56,000.00
Rp 13,310.00
Rp 7,525.00
Rp 76,835.00
Rp 116,035.00
Rp 11,603.50
Rp 127,638.50
sangan Dinding Kerawang ( Roster ) Camp. 1Pc : 3 PP.
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 24,000.00
Rp 15,125.00
Rp 6,125.00
Rp 45,250.00
Rp 84,450.00
Rp 8,445.00
Rp 92,895.00
Jumlah Harga
Rp 25,500.00
Rp 11,000.00
Rp 1,200.00
Rp 1,500.00
Rp 39,200.00
Rp 24,000.00
Rp 15,125.00
Rp 6,125.00
Rp 45,250.00
Rp 84,450.00
Rp 8,445.00
Rp 92,895.00
Jumlah Harga
Rp 25,500.00
Rp 16,500.00
Rp 1,800.00
Rp 1,500.00
Rp 45,300.00
Rp 21,318.00
Rp 2,800.00
Rp 24,118.00
Rp 69,418.00
Rp 6,941.80
Rp 76,359.80
Jumlah Harga
Rp 25,500.00
Rp 16,500.00
Rp 1,800.00
Rp 1,500.00
Rp 45,300.00
Rp 14,058.00
Rp 3,500.00
Rp 17,558.00
Rp 62,858.00
Rp 6,285.80
Rp 69,143.80
Jumlah Harga
Rp 25,500.00
Rp 16,500.00
Rp 1,800.00
Rp 1,500.00
Rp 45,300.00
Rp 10,692.00
Rp 4,025.00
Rp 14,717.00
Rp 60,017.00
Rp 6,001.70
Rp 66,018.70
Jumlah Harga
Rp 25,500.00
Rp 16,500.00
Rp 1,800.00
Rp 1,500.00
Rp 45,300.00
Rp 8,580.00
Rp 4,200.00
Rp 12,780.00
Rp 58,080.00
Rp 5,808.00
Rp 63,888.00
Jumlah Harga
Rp 25,500.00
Rp 16,500.00
Rp 1,800.00
Rp 1,500.00
Rp 45,300.00
Rp 7,128.00
Rp 4,550.00
Rp 11,678.00
Rp 56,978.00
Rp -
Rp 56,978.00
Jumlah Harga
Rp 17,000.00
Rp 11,000.00
Rp 1,200.00
Rp 1,000.00
Rp 30,200.00
Rp 4,468.75
Rp 4,468.75
Rp 34,668.75
Rp -
Rp 34,668.75
Jumlah Harga
Rp 59,500.00
Rp 38,500.00
Rp 4,200.00
Rp 3,500.00
Rp 105,700.00
Rp 72,930.00
Rp 13,475.00
Rp 5,200.00
Rp 7,875.00
Rp 99,480.00
Rp 205,180.00
Rp -
Rp 205,180.00
Jumlah Harga
Rp 59,500.00
Rp 38,500.00
Rp 4,200.00
Rp 3,500.00
Rp 105,700.00
Rp 77,155.00
Rp 13,750.00
Rp 6,000.00
Rp 7,875.00
Rp 104,780.00
Rp 210,480.00
Rp -
Rp 210,480.00
Jumlah Harga
Rp 59,500.00
Rp 38,500.00
Rp 4,200.00
Rp 3,500.00
Rp 105,700.00
Rp 106,000.00
Rp 14,300.00
Rp 6,480.00
Rp 7,875.00
Rp 134,655.00
Rp 240,355.00
Rp -
Rp 240,355.00
Jumlah Harga
Rp 7,650.00
Rp 9,900.00
Rp 4,200.00
Rp 3,500.00
Rp 25,250.00
Rp 42,400.00
Rp 1,567.50
Rp 200.00
Rp 525.00
Rp 44,692.50
Rp 69,942.50
Rp -
Rp 69,942.50
Jumlah Harga
Rp 7,650.00
Rp 49,500.00
Rp 5,400.00
Rp 500.00
Rp 63,050.00
Rp 84,800.00
Rp 12,787.50
Rp 7,760.00
Rp 3,150.00
Rp 108,497.50
Rp 171,547.50
Rp -
Rp 171,547.50
Jumlah Harga
Rp 8,500.00
Rp 11,000.00
Rp 1,200.00
Rp 500.00
Rp 21,200.00
Rp 31,875.00
Rp 510.00
Rp 32,385.00
Rp 53,585.00
Rp -
Rp 53,585.00
Jumlah Harga
Rp 8,500.00
Rp 5,500.00
Rp 600.00
Rp 500.00
Rp 15,100.00
Rp 30,940.00
Rp 1,870.00
Rp 32,810.00
Rp 47,910.00
Rp -
Rp 47,910.00
Jumlah Harga
Rp 4,250.00
Rp 5,500.00
Rp 600.00
Rp 300.00
Rp 10,650.00
Rp 7,350.00
Rp 175.00
Rp 7,525.00
Rp 18,175.00
Rp -
Rp 18,175.00
Jumlah Harga
Rp 17,000.00
Rp 11,000.00
Rp 1,200.00
Rp 100.00
Rp 29,300.00
Rp 68,250.00
Rp 3,900.00
Rp 72,150.00
Rp 101,450.00
Rp -
Rp 101,450.00
Jumlah Harga
Rp 12,750.00
Rp 7,700.00
Rp 840.00
Rp 2,000.00
Rp 23,290.00
Rp 13,500.00
Rp 4,212.00
Rp 17,712.00
Rp 41,002.00
Rp -
Rp 41,002.00
mbuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas 1
Jumlah Harga
Rp 595,000.00
Rp 2,310,000.00
Rp 252,000.00
Rp 35,000.00
Rp 3,192,000.00
Rp 5,500,000.00
Rp 21,875.00
Rp 18,000.00
Rp 5,539,875.00
Rp 8,731,875.00
Rp -
Rp 8,731,875.00
Jumlah Harga
Rp 85,000.00
Rp 330,000.00
Rp 36,000.00
Rp 5,000.00
Rp 456,000.00
Rp 180,000.00
Rp 9,000.00
Rp 189,000.00
Rp 645,000.00
Rp -
Rp 645,000.00
Jumlah Harga
Rp 68,000.00
Rp 264,000.00
Rp 28,800.00
Rp 4,000.00
Rp 364,800.00
Rp 108,000.00
Rp 5,400.00
Rp 113,400.00
Rp 478,200.00
Rp -
Rp 478,200.00
Jumlah Harga
Rp 56,950.00
Rp 220,000.00
Rp 24,000.00
Rp 33,500.00
Rp 334,450.00
Rp 300,000.00
Rp 2,700.00
Rp 302,700.00
Rp 637,150.00
Rp -
Rp 637,150.00
Jumlah Harga
Rp 56,950.00
Rp 220,000.00
Rp 24,000.00
Rp 33,500.00
Rp 334,450.00
Rp 6,000,000.00
Rp 217,500.00
Rp 100,800.00
Rp 6,318,300.00
Rp 6,652,750.00
Rp -
Rp 6,652,750.00
Jumlah Harga
Rp 204,000.00
Rp 792,000.00
Rp 86,400.00
Rp 12,000.00
Rp 1,094,400.00
Rp 4,950,000.00
Rp 217,500.00
Rp 54,000.00
Rp 5,221,500.00
Rp 6,315,900.00
Rp -
Rp 6,315,900.00
Jumlah Harga
Rp 17,000.00
Rp 33,000.00
Rp 3,600.00
Rp 1,000.00
Rp 54,600.00
Rp 52,160.00
Rp 4,500.00
Rp 56,660.00
Rp 111,260.00
Rp -
Rp 111,260.00
Jumlah Harga
Rp 8,500.00
Rp 22,000.00
Rp 2,400.00
Rp 500.00
Rp 33,400.00
Rp 34,560.00
Rp 1,800.00
Rp 36,360.00
Rp 69,760.00
Rp -
Rp 69,760.00
Jumlah Harga
Rp 425.00
Rp 55,000.00
Rp 6,000.00
Rp 300.00
Rp 61,725.00
Rp 125,000.00
Rp 125,000.00
Rp 186,725.00
Rp -
Rp 186,725.00
Jumlah Harga
Rp 1,275.00
Rp 16,500.00
Rp 1,800.00
Rp 80.00
Rp 19,655.00
Rp 24,000.00
Rp 24,000.00
Rp 43,655.00
Rp -
Rp 43,655.00
Jumlah Harga
Rp 1,275.00
Rp 16,500.00
Rp 1,800.00
Rp 80.00
Rp 19,655.00
Rp 24,000.00
Rp 24,000.00
Rp 43,655.00
Rp -
Rp 43,655.00
Jumlah Harga
Rp 1,275.00
Rp 16,500.00
Rp 1,800.00
Rp 80.00
Rp 19,655.00
Rp 15,000.00
Rp 15,000.00
Rp 34,655.00
Rp -
Rp 34,655.00
Jumlah Harga
Rp 1,275.00
Rp 16,500.00
Rp 1,800.00
Rp 80.00
Rp 19,655.00
Rp 7,500.00
Rp 7,500.00
Rp 27,155.00
Rp -
Rp 27,155.00
Jumlah Harga
Rp 85,000.00
Rp 165,000.00
Rp 180,000.00
Rp 16,000.00
Rp 446,000.00
Rp 400,000.00
Rp 8,250.00
Rp 1,750.00
Rp 410,000.00
Rp 856,000.00
Rp -
Rp 856,000.00
Jumlah Harga
Rp 85,000.00
Rp 110,000.00
Rp 12,000.00
Rp 5,000.00
Rp 212,000.00
Rp 2,350,000.00
Rp 8,250.00
Rp 1,750.00
Rp -
Rp 2,360,000.00
Rp 2,572,000.00
Rp -
Rp 2,572,000.00
Jumlah Harga
Rp 850.00
Rp 11,000.00
Rp 1,200.00
Rp 500.00
Rp 13,550.00
Rp 20,000.00
Rp 20,000.00
Rp 33,550.00
Rp -
Rp 33,550.00
Jumlah Harga
Rp 850.00
Rp 11,000.00
Rp 1,200.00
Rp 500.00
Rp 13,550.00
Rp 14,000.00
Rp 14,000.00
Rp 27,550.00
Rp -
Rp 27,550.00
Jumlah Harga
Rp 1,275.00
Rp 16,500.00
Rp 1,800.00
Rp 80.00
Rp 19,655.00
Rp 110,000.00
Rp 750.00
Rp 110,750.00
Rp 130,405.00
Rp -
Rp 130,405.00
Jumlah Harga
Rp 5,950.00
Rp 990.00
Rp 720.00
Rp 300.00
Rp 7,960.00
Rp 720.00
Rp 9,350.00
Rp 10,070.00
Rp 18,030.00
Rp -
Rp 18,030.00
t Bidang Kayu Baru ( 1 x Plamir 1 x cat dasar, 2x cat penutup
Jumlah Harga
Rp 5,950.00
Rp 990.00
Rp 720.00
Rp 300.00
Rp 7,960.00
Rp 6,000.00
Rp 5,250.00
Rp 7,650.00
Rp 14,300.00
Rp 150.00
Rp 720.00
Rp 500.00
Rp 34,570.00
Rp 42,530.00
Rp -
Rp 42,530.00
Jumlah Harga
Rp 1,700.00
Rp 6,930.00
Rp 756.00
Rp 250.00
Rp 9,636.00
Rp 3,000.00
Rp 2,500.00
Rp 10,400.00
Rp 15,900.00
Rp 25,536.00
Rp -
Rp 25,536.00
ngecetan Tembok Lama ( 1 x cat dasar, 2x cat Penutup )
Jumlah Harga
Rp 2,380.00
Rp 4,620.00
Rp 504.00
Rp 250.00
Rp 7,754.00
Rp 3,000.00
Rp 4,500.00
Rp 7,500.00
Rp 15,254.00
Rp -
Rp 15,254.00
DAFTAR KUANTITAS DAN HARGA
HARGA SATUAN
NO. URAIAN PEKERJAAN SAT VOLUME ANALISA ( RP)
I PEKERJAAN PERSIAPAN
A. Pembersihan Lapangan M² 299.0 AHSP PU.A.2.2.1.9 14,850.00
B. Pengukuran/Pemasangan Bowplank M¹ 64 AHSP PU.A.2.2.1.4 99,550.00
JUMLAH
B KOLOM 30/30 cm
Beton K-200 M³ 16.146 AHSP PU A.1.1.6 987,414.65
Besi Tulangan Pokok 6 D 16 Kg 1698.818 AHSP PU A.1.1.17.a 20,810.90
Besi Tulangan Sengkang ∅ 8-150 Kg 848.553 AHSP PU A.1.1.17 16,949.90
Besi Tulangan Pinggang 2 ∅ 14 Kg 433.55 AHSP PU A.1.1.17 16,949.90
Bekisting + Perawatan Beton M² 215.280 AHSP PU A.1.1.22 587,246.00
JUMLAH
E Ring Balok
Beton K-200 M³ 7.59 AHSP PU A.1.1.6 987,414.65
Besi Tulangan Pokok 5 D 16 Kg 998.24 AHSP PU A.1.1.17.a 20,810.90
Besi Tulangan Sengkang ∅ 8-100 Kg 500.120 AHSP PU A.1.1.17 16,949.90
Besi Tulangan Sengkang ∅ 8-150 Kg 332.412 AHSP PU A.1.1.17 16,949.90
Besi Tulangan Pinggang 4 ∅ 14 Kg 305.710 AHSP PU A.1.1.17 16,949.90
Bekisting + Perawatan Beton M² 101.200 AHSP PU A.1.1.23 492096
JUMLAH
LANTAI 1
LANTAI 2
TOTAL
B LANTAI 2
Pas. Dinding Bata 1Pc : 4Ps lantai 2 M² 143.767 AHSP PU A.4.4.1.9 130,391.25
Plasteran Pas. Dinding Bata 1Pc : 4Ps lantai 2 M² 287.534 AHSP PU A.4.4.2.4 63,888.00
C PLASTERAN KOLOM M² 53.01 AHSP PU A.4.4.2.4 63,888.00
B LANTAI 2
Plafond Triplek 4 mm / Memasang Langit-Langit M² 144 AHSP PU A.4.5.1.5 53,585.00
Rangka Plafond M² 144 AHSP PU A.4.5.1.5 53,585.00
List Plafond M 365 AHSP PU A.4.5.1.9 18,175.00
JUMLAH
TOTAL
B Plat Bordes
Beton K-300 M³ 0.518 AHSP PU A.1.1.8 952,560.62
Besi Tulangan Pokok ∅ 12-120 Kg 43.815 AHSP PU A.1.1.17 16,949.90
Bekisting + Perawatan Beton M² 4.14 AHSP PU A.4.1.1.26 516,763.50
C Keramik
Keramik Bordes 40x40 M² 3.450 AHSP PU A.4.4.3.34.a 205,180.00
Keramik Anak Tangga 30x30 M² 1.080 AHSP PU A.4.4.3.35 210,480.00
JUMLAH
LANTAI 1
LANTAI 2
JUMLAH
XI PEKERJAAN PENGECATAN
A Dinding
Lantai 1 M² 387.530 AHSP PU A.4.7.1.10 25,536.00
Lantai 2 M² 287.770 AHSP PU A.4.7.1.10 25,536.00
B Plafond
Lantai 1 M² 150.000 AHSP PU A.4.7.1.4 42,530.00
Lantai 2 M² 144.000 AHSP PU A.4.7.1.4 42,530.00
C Kusen
Pintu M² 18.650 AHSP PU A.4.7.1.4 42,530.00
Jendela J1 M² 18.650 AHSP PU A.4.7.1.4 42,530.00
Jendela J2 M² 0.230 AHSP PU A.4.7.1.4 42,530.00
LANTAI 1
LANTAI 2
JUMLAH
UANTITAS DAN HARGA
RAN BIAYA
ANDRAH KAB.BIREUN
JUMLAH BIAYA
( RP)
4,440,150.00
6,371,200.00
10,811,350.00
3,360,305.52
1,850,948.86
264,132.00
14,124,824.84
10,628,531.30
15,638,774.79
10,575,489.28
56,443,006.59
4,372,381.73
462,737.21
685,850.00
3,704,725.20
46,729,554.61
55,955,248.75
107,538,115.78
73,032.96
459,487.60
2,481,993.57
100,300.34
472,758.00
2,224,136.20
2,186,050.38
3,984,386.40
11,982,145.45
7,961,030.62
17,653,969.71
14,378,667.97
5,278,710.54
7,244,270.73
18,288,781.50
70,805,431.07
15,942,796.95
35,353,921.86
14,378,667.97
7,348,669.69
126,422,318.88
199,446,375.35
12,737,649.00
24,715,557.60
14,378,667.97
6,763,833.87
8,806,934.13
64,991,821.71
132,394,464.27
493,944.30
2,187,453.03
685,418.38
5,680,756.22
9,047,571.94
7,494,477.20
20,774,206.22
8,476,988.73
5,634,344.06
5,181,754.27
49,800,115.20
97,361,885.68
411,693,842.63
305,855,832.97
717,549,675.60
25,249,796.15
24,743,362.41
18,745,984.92
18,369,997.75
3,386,702.88
2,060,388.00
55,440,249.44
40,502,685.54
95,942,934.98
11,127,509.25
2,559,975.00
155,316.00
32,931,390.00
46,774,190.25
17,146,091.17
102,774,159.26
130,986,900.00
288,750.00
30,777,000.00
281,972,900.43
328,747,090.680
8,037,750.00
8,037,750.00
5,452,500.00
21,528,000.00
7,716,240.00
7,716,240.00
6,633,875.00
22,066,355.00
43,594,355.000
57,684,000.00
21,280,152.00
12,092,840.00
91,056,992.000
1,684,389.13
1,447,082.21
2,741,339.93
492,950.12
742,662.79
2,139,400.89
707,871.00
227,318.40
10,183,014.477
2,974,984.74
6,664,140.00
1,529,160.00
714,000.00
308,000.00
180,000.00
12,370,284.74
162,872,241.48
688,608.00
6,460,701.00
1,521,000.00
3,143,160.00
2,484,000.00
2,495,160.00
977,580.00
180,642,450.48
1,966,977.09
459,072.00
764,580.00
1,521,000.00
698,480.00
552,000.00
554,480.00
217,240.00
6,733,829.09
199,746,564.31
193,012,735.22
392,759,299.530
9,895,966.08
7,348,494.72
6,379,500.00
6,124,320.00
793,184.50
793,184.50
9,781.90
17,871,616.980
15,059,183.720
32,930,800.700
REKAPITULISASI DAFTAR KUANTITAS DAN HARGA
JUMLAH HARGA
No. URAIAN PEKERJAAN (Rp.)
LANTAI I
A PEKERJAAN PERSIAPAN 10,811,350.00
B PEKERJAAN TANAH DAN PONDASI 107,538,115.78
C PEKERJAAN BETON BERTULANG 411,693,842.63
D PEKERJAAN PASANGAN DAN PLASTERAN 55,440,249.44
E PEKERJAAN LANTAI 46,774,190.25
F PEKERJAAN TANGGA DEPAN 11,982,145.45
G PEKERJAAN TANGGA DALAM 10,183,014.48
H PEKERJAAN PLAFOND 21,528,000.00
I PEKERJAAN PINTU, JENDELA & VENTILASI + Kunci 199,746,564.31
H PEKERJAAN PENGECATAN 17,871,616.98
LANTAI II
A PEKERJAAN BETON BERTULANG 305,855,832.97
B PEKERJAAN PASANGAN DAN PLASTERAN 40,502,685.54
C PEKERJAAN LANTAI 46,774,190.25
D PEKERJAAN PLAFOND 22,066,355.00
E PEKERJAAN ATAP 91,056,992.00
F PEKERJAAN PINTU, JENDELA & VENTILASI + Kunci 193,012,735.22
G PEKERJAAN PENGECATAN 15,059,183.72
JUMLAH 1,607,897,064.02
DIBULATKAN 1,607,897,000.00
Terbilang : Satu Milyar Enam Ratus Tujuh Juta Delapan Ratus Sembilan Puluh Tujuh Ribu Rupiah
..................................
NIM : .........................