A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan
Lebar = 5 m (3+1+1)
Panjang = 8 m (6+1+1)
Luas = (PxL)
= 40.00 M²
2 Pemasangan Bouwplank
Lebar = 5 m (3+1+1)
Panjang = 8 m (6+1+1)
Keliling = 2 (P + L )
= 26.00 M¹
B PEKERJAAN TANAH DAN PONDASI
3 Galian Pondasi Menerus
Vertikal = 12 m
Horizontal = 6 m
18 m 18 m
Tinggi = 0.80 m
Lebar = 0.80 m
Panjang = 18.00 m
Volume = (PxLxT) 11.52 M³
b Pasir Alas
Tinggi = 0.05 m
Lebar = 0.80 m
Panjang = 18.00 m
Volume = (PxLxT) 0.72 M³
b B ( Stick Tapak 1 )
Tinggi = 1.55 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 12 Unit
Volume = ( P x L x T ) x Unit 2.976 M³
Volume Total Pondasi Tapak Tipe 1
= (A+B) 12.70 M³
2 Pondasi Tapak 2
a A ( Tapak 2 )
Tinggi = 0.25 m
Lebar = 1.2 m
Panjang = 1.2 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit 2.16 M³
b B ( Stick Tapak 2 )
Tinggi = 1.55 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit 1.488 M³
Volume Total Pondasi Tapak Tipe 1
= (A+B) 3.65 M³
Panjang = 8.84 m
Tinggi = 3.50 m
PxT 30.94 M²
a Pintu P1
Panjang = 2.24 m
Lebar = 1.88 m
Jumlah = 1.00 unit
= PxLxU 4.21 M²
b Pintu P3
Panjang = 2.15 m
Lebar = 0.90 m
Jumlah = 5.00 unit
= PxLxU 9.68 M²
c Pintu P4
Panjang = 2.15 m
Lebar = 0.80 m
Jumlah = 1.00 unit
= PxLxU 1.72 M²
d Ventilasi BV1
Panjang = 0.98 m
Lebar = 0.60 m
Jumlah = 6.00 unit
PxLxU 3.528 M²
e Ventilasi BV2
Panjang = 1.92 m
Lebar = 0.60 m
Jumlah = 1.00 unit
PxLxU 1.152 M²
f Jendela J1
Panjang = 1.66 m
Lebar = 1.14 m
Jumlah = 9.00 unit
PxLxU 17.03 M²
3 Beton Cor
Ruang Kamar ( + 0.00 )
Tinggi = 0.12 m
Lebar = 5.85 m
Panjang = 5.85 m
Jumlah = 5.00 unit
Luas = (PxLxTxU) 20.53 M³
J PEKERJAN SANITASI
1 Pemasangan Pipa PVC AW 3/4 Air Bersih 35.58 M
2 Pemasangan Pipa PVC AW 4" Air Kotor 4.95 M
3 Pemasangan Kran air 5.00 Unit
4 Septicktank+Resapan+Box Kontrol 1.00 Unit
5 kloset jongkok 2.00 Unit
6 Pemasangan Floor Drain 13.00 Unit
7 Pemasangan Bak Mandi Viber 10.00 Unit
8 Wastafel 2.00 Unit
9 Pipa Buangan Air Hujan 10.00 M
10 Kloset duduk 1.00 Unit
PEKERJAAN LANTAI 2
A Pekerjaan Beton Bertulang
1 Kolom K1 (40/40) Lantai 2
Tinggi = 3.50 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 19 Unit
Volume = ( P x L x T ) x Unit 10.64 M³
6 Plat Lantai
Luasan A
Tinggi = 0.12 m
Lebar = 5.75 m
Panjang = 17.50 m
Unit = 1.00
Volume = (PxLxT)xU 12.08 M³
Luasan B
Tinggi = 0.12 m
Lebar = 8.15 m
Panjang = 11.61 m
Unit = 1.00
Volume = (PxLxT)xU 11.35 M³
Luasan C
Tinggi = 0.12 m
Lebar = 5.27 m
Panjang = 8.50 m
Unit = 1.00
Volume = (PxLxT)xU 5.38 M³
E PEKERJAAN PLAFOND
Plafond Lantai 2
Volume Plafond = Volume Keramik 243.25 M2
F PEKERJAAN ATAP
RANGKA BAJA RINGAN
PANJANG = 8.13
LEBAR = 5.13
PXL 41.71 M2
ATAP SENG
PANJANG = 8.13
LEBAR = 5.13
PXL 41.71 M2
RABUNG
PANJANG 8.13 8.13 M'
LISTPLANK
PANJANG = 8.13
LEBAR = 5.13
2(PXL) 83.41 M2
I PEKERJAN SANITASI
1 Pemasangan Pipa PVC AW 3/4 Air Bersih 35.58 M
2 Pemasangan Pipa PVC AW 4" Air Kotor 4.95 M
3 Pemasangan Kran air 5.00 Unit
4 Septicktank+Resapan+Box Kontrol 1.00 Unit
5 kloset jongkok 2.00 Unit
6 Pemasangan Floor Drain 13.00 Unit
7 Pemasangan Bak Mandi Viber 10.00 Unit
8 Wastafel 2.00 Unit
9 Pipa Buangan Air Hujan 10.00 M
10 Kloset duduk 1.00 Unit
PONDASI TAPAK
Bekisting = (2 x P) + (2 x L) x T x U = 54
Bekisting = (2 x P) + (2 x L) x T x U = 11.18
Anak Tangga = 12 cm
Bidang X = #NAME? M
Bidang Y = #NAME? M
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm
Jarak Tulangan = 0.15 M
Unit = 20.00
#REF! = Pjg*Jb*Jl*0.006162*d*d
= #NAME? Kg
Total Berat Besi = #NAME? Kg
B =
=
To =
B =
L =
B =
=
To =
B =
L =
B =
=
4. Pa =
=
To =
P =
PEMBESIAN
Luasan B
Sumbu X 10.00 0.62 0.06
PEMBESIAN
Sumbu Y 10.00 0.62 0.06
Luasan C
Sumbu X 10.00 0.62 0.06
Sumbu Y 10.00 0.62 0.06
PANJANG
LEBAR TINGGI
No. URAIAN PEKERJAAN
(M) (M) T1
#NAME?
Bekisting = (2 x P) + (2 x L) x T x U = ###
#NAME?
Bekisting = (2 x P) + (2 x L) x T x U = ###
2
m2
btg
m2
btg
btg
Kg/m
Kg/m
m2
m2
m2
m
btg
Kg/m
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
3.75
m
btg
Kg/m
m
m
btg
Kg/m
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
Untuk Bidang 1.00 Meter
#NAME? M
#NAME? M
2.00 Lapis
10.00 mm
Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg
Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg
#NAME? Kg
### Kg / M3 Beton
### M2 / M3 Beton
Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg
Untuk Bidang 2.00 Meter
#NAME? M
#NAME? M
2.00 Lapis
10.00 mm
Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg
#NAME? Kg
### Kg / M3 Beton
### M2 / M3 Beton
### Kg
### M2
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
m2
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
m2
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
TINGGI
VOL
T2
402.5
189.243
44.795
OTAL 636.538
3.75
m
btg
Kg/m
m
m
btg
Kg/m
m2
m
btg
Kg/m
m
m
btg
Kg/m
m2
28.75
87.5
40.75
58.05
0.2
26.35
42.5
REKAPITULASI
ENGINEER ESTIMATE (EE)
NO URAIAN PEKERJAAN
I PEKERJAAN PERSIAPAN
II LANTAI 1
DAL
JUMLAH HARGA
Rp 9,075,449.00
#NAME?
Rp 202,235,162.16
Rp 4,654,860.55
#NAME?
#NAME?
#NAME?
Rp 1,000,000.00
#NAME?
Rp 72,698
#NAME?
Rp -
Rp -
#NAME?
#NAME?
Rp 10,290,000.00
Rp -
#NAME?
#NAME?
#NAME?
Rp 800,000,000.00
a Rupiah
Pekerjaan Lantai 1
1 2 3 4
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 40.00 M2
2 Pengukuran / Pemasangan Bouplank 89.00 M1
3 Administrasi dan Dokumentasi 1.00 Ls
4 K3 dan Lain-lain 1.00 Ls
5 Papan Nama Proyek 1.00 Ls
F PEKERJAAN TANGGA
1 Plat Tangga
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2
2 Anak Tangga
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2
3 Plat Bordes
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2
2 Jendela
Kusen Jendela J1 #NAME? M
Daun Jendela J1 #NAME? M2
- Hak Angin / Gagang Jendela 16.00 Buah
- Engsel Jendela #NAME? Buah
- Pacok Jendela #NAME? Buah
3 Ventilasi
Kusen Ventilasi V1 2.56 M
Daun Ventilasi 0.31 M2
I PEKERJAAN PLAFOND
1 Pemasangan Plafond PVC + Rangka dan List #NAME? M2
J PEKERJAAN PENGECATAN
3 Cat Dinding Luar Dan Dalam ( Dulux ) 2.00 M2
Pekerjaan Lantai 2
A PEKERJAAN BETON BERTULANG
1 Kolom K1 (40/40) Lantai 2
Beton K-250 10.64 M3
Besi Tulangan Pokok Ø16 5.69 kg
Besi Tulangan Sengkang Ø10 - 10 cm 0.67 kg
Bekisting + Perawatan Beton 2.96 M2
4 Plat Lantai
Beton K-250 28.80 M3
Besi Tulangan Pokok Ø10 11963.88 kg
Bekisting + Perawatan Beton 636.54 M2
5 #NAME?
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø16 #NAME? Kg
Besi Tulangan Sengkang Ø10 - 10 cm #NAME? Kg
Bekisting + Perawatan Beton #NAME? M2
6 #NAME?
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø16 #NAME? Kg
Besi Tulangan Sengkang Ø10 - 10 cm #NAME? Kg
Bekisting + Perawatan Beton #NAME? M2
2 Jendela
Kusen Jendela J1 #NAME? M
Daun Jendela J1 #NAME? M2
- Hak Angin / Gagang Jendela 16.00 Buah
- Engsel Jendela #NAME? Buah
- Pacok Jendela #NAME? Buah
3 Ventilasi
Kusen Ventilasi V1 2.56 M
Daun Ventilasi 0.31 M2
G PEKERJAAN PENGECATAN
1 Cat Dinding Luar Dan Dalam 0.00 M2
R ESTIMATE (EE)
5 6 7
jaan Lantai 2
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Pasir beton
Koral beton
Kayu 5/7
Paku biasa
Residu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Seng gelombang
Pasir beton
Koral beton
Kayu 5/7
Paku biasa
Meni besi
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Kawat duri
Pasir beton
Koral beton
Paku biasa 2” - 5”
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu balok 5/7
Paku 2”-3”
Kayu papan 3/20
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Tukang batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu balok 5/7
Paku biasa
Besi strip
Semen portland
Pasir pasang
Pasir beton
Koral beton
Bata merah
Seng plat
Jendela naco
Kaca polos
Kunci tanam
Plywood 4 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Seng gelombang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Semen portland
Pasir beton
Koral beton
Seng gelombang
Seng plat
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Semen portland
Pasir beton
Koral beton
Seng gelombang
Plywood 4 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bambu diameter 6 - 8 / 600 cm
Tali ijuk
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Tukang Kayu L.02.04
Kepala Tukang L.03.01
B BAHAN
Kayu papan kelas III
Kayu balok 5/7 kelas III
Paku biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Batu belah
Batu pecah
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kawat jaring
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Panel Beton Pracetak
Kolom Benton Pracetak
Semen portland
Pasir beton
Koral
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Jenis Pekerjaan : Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedal
Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.9.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Pasir urug
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pengurugan 1 m3 dengan Tanah Timbun Biasa
Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.11b.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Tanah Timbun
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kapur
Pasir Pasang
Tanah Liat
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Ijuk
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Sirtu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Kapur
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Pasir urug
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : (K3) Pemasangan 1 m3 pondasi siklop, 60% beton campu
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.3.2.1.10.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Beton
Kerikil
Besi beton (polos/ulir)
Kawat beton
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Beton
Kerikil (Maks. 30 mm)
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.2
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling fa
Jenis Pekerjaan : Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.4
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.5.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (12
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.6
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 21,7 MPa (K 250), slump (12
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.8.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.10.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.11.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.12.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan penambahan bahan tambahan s
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Bahan tambahan kimia
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
CATATAN: Bobot isi pasir = 1400 kg/m3, Bobot isi kerikil = 1350 kg/m3, Buckling factor pasir = 20%
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Strorox - 100
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Pipa L.02.13
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Waterstop lebar 150 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m’ PVC Waterstop lebar 200 mm
Satuan / Unit : 1 M1
Analisa : AHSP - PU - A.4.1.1.15
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Pipa L.02.13
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Waterstop lebar 200 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Waterstop lebar 230 mm - 320 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Besi beton polos
Kawat beton
C PERALATAN
D Jumlah (A+B+C)
Untuk Harga 1Kg Besi
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Besi Beton Ulir
Kawat Beton
C PERALATAN
D Jumlah (A+B+C)
Untuk Harga 1Kg Besi
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Besi beton (polos/ulir)
Kawat beton
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 10 kg jaring kawat baja (wiremesh)
Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.1.1.19
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Jaring kawat baja dilas
Kawat beton
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 10 cm
Minyak bekisting
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 10 cm
Minyak bekisting
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
Penjaga jarak bekisting / spacer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III (papan)
Paku 5 - 12 cm
Dolken kayu Ø 8-10/400 cm
Jumlah Bahan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : (K3) Pembuatan 1 m2 lahan produksi tebal 8cm beton f’c 1
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.1.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Lantai kerja tebal 10cm
Besi hollow 50.50.3
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Dynabol dia 12 x 120 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Dynabol dia 12 x 120 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Paku Biasa
Dynabol dia 12 x 120 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Solar
C PERALATAN
Sewa crane
Sewa pipe support
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Solar
C PERALATAN
Sewa crane
Sewa pipe support
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Solar
C PERALATAN
Sewa crane
Sewa pipe support
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02
B BAHAN
Solar
C PERALATAN
Sewa crane
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02
B BAHAN
Solar
C PERALATAN
Sewa crane
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02
B BAHAN
Solar
C PERALATAN
Sewa crane
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
B BAHAN
Semen grout
Screening
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
B BAHAN
Semen grout
Air
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kaso 5/7
Kayu papan kelas III
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Tukang besi L.02.05
Mandor L.04.01
B BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las Konstruksi L.02.10
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Besi Profil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las Konstruksi L.02.10
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Besi IWF
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi Konstruksi L.02.06
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Solar
Minyak pelumas
C PERALATAN
Sewa alat Perakitan Baja IWF
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Besi siku L 30.30.3
Besi plat baja
Kawat las
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi Konstruksi L.02.06
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kawat las listrik
Solar
Minyak pelumas
C PERALATAN
Sewa alat Las Listrik
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Besi scuare tube
Besi lis kaca (1 x 1) cm
Pengelasan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pintu gulung besi
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pintu lipat
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Sunscreen alluminium
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Rolling dor alluminium
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Profil alluminium
Skrup fixer
Sealant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Profil alluminium
Aluminium strip
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pintu alluminium
Profil kaca
Sealant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Venetions blinds dan vertical blinds (tirai)
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Besi strip
Pengelasan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kawat nyamuk
Pengelasan
Baja strip (0,2 x 2) cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Jendela nako (rangka + kaca 5 mm)
Paku skrup
Besi strip
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Seng plat
Paku Biasa
Kayu Papan kelas II
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 M' Talang ½ Lingkaran D-15 cm, Seng Pla
Satuan / Unit : 1 M'
Analisa : AHSP - PU - A.4.2.1.19.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Seng plat
Paku Biasa
Besi strip
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Rangka metal hollow 40.40.2 mm
Assesoris (perkuatan, las dll)
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Rangka metal hollow 40.40.2 mm
Assesoris (perkuatan, las dll)
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Baja ringan canai dingin C75
C PERALATAN
Alat Rangka Atap Baja Canai Dingin
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai d
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.23.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Baja ringan canai dingin C75
C PERALATAN
Alat Rangka Atap Baja Canai Dingin
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 M2 PASANG KUDA-KUDA BAJA RINGAN
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.24.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Baja ringan canai dingin C75
Baut (Srew driver)
Dynabol dia 12 x 120 mm
Reng Canai Dingin
Talang / Jurai Canai Dingin
C PERALATAN
Alat Rangka Atap Baja Canai Dingin
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.8.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen Merah
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-20
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-20
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-15
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-15
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-10
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
HB-10
Semen portland
Pasir Pasang
Besi angker dia 8
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata Rooster
Semen Portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata Berongga
Semen Portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 cm2 dinding bata berongga ekspose 12x11
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.24.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata Rooster
Semen Portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata ringan tebal 7,5 cm
Mortar siap pakai
C PERALATAN
Peralatan Pasang Dinding Bata Ringan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata ringan tebal 7,5 cm
Mortar siap pakai
C PERALATAN
Peralatan Pasang Dinding Bata Ringan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.3.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.6.
1 m2 plesteran 1SP : 6PP tebal 15 mm.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.7.
1 m2 plesteran 1SP : 7PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.8.
1 m2 plesteran 1SP : 8PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
AHSP - PU - A.4.4.2.9.
1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.10.
1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.11.
1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.12.
1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.13.
1 m2 plesteran 1SP : 1PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.14.
1 m2 plesteran 1SP : 3PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.15.
1 m2 plesteran 1SP : 4PP tebal 20 mm.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.16.
1 m2 plesteran 1SP : 5PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.17.
1 m2 plesteran 1SP : 6PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.18.
1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSPPemasangan
- PU - A.4.4.2.19.
1 m2 berapen 1SP : 5PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.20.
1 m’ plesteran skoning 1SP : 3PP lebar 10 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.21.
1 m2 plesteran granit 1SP : 2 granit tebal 1cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Batu granit
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.22.
1 m2 plesteran traso 1SP : 2 traso tebal 1cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Batu traso
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP -Pemasangan
PU - A.4.4.2.23.
1 m2 plesteran ciprat 1SP : 2PP
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.24
1 m2 finishing siar pasangan bata merah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.25.
1 m2 finishing siar pasangan conblock ekspose
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
AHSP -1PU
m2- finishing
A.4.4.2.26.
siar pasangan batu kali, campuran 1SP : 2PP.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP - PU - A.4.4.2.27.
Pemasangan 1 m2 acian.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
AHSP - PU - A.4.4.2.28.
1 m2 plesteran dengan mortar siap pakai (MSP)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen mortar pasangan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.29.
1 m2 Acian dengan mortar siap pakai (MSP)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen mortar Acian
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Granit uk. 60 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit ukuran 60 x 60 cm (Unpol
Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.4.3.54a
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Granit uk. 60 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Granit uk. 30 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.1.
1m2 lantai ubin PC abu-abu ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin PC abu-abu ukuran 40cm x40cm
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.2.
1m2 lantai ubin PC abu-abu ukuran 30cm x30 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin PC abu-abu ukuran 30cm x30 cm
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.3.
1m2 lantai ubin PC abu-abu ukuran 20cm x20 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin PC abu-abu ukuran 20cm x20 cm
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.4.
1m2 lantai ubin warna ukuran 40cm x40 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin warna ukuran 40cm x40 cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.5.1m2 lantai ubin warna ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin warna ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.6.1m2 lantai ubin warna ukuran 20cm x20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin warna ukuran 20cm x20cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.7.1m2 lantai ubin teraso ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teraso ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.8.1m2 lantai ubin teraso ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teraso ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.9.1m2 lantai ubin granit ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin granit ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.10.
1m2 lantai ubin granit ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin granit ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.11.
1m2 lantai ubin teralux marmer ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teralux marmer ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.12.
1m2 lantai ubin teralux ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teralux ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.13.
1m2 lantai ubin teralux marmer ukuran 60cm x60cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teralux marmer ukuran 60cm x60cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.14.
1m2 lantai ubin teralux marmer ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teralux marmer ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.15.
1m2 lantai ubin teralux marmer ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teralux marmer ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.16.
1 m’ plint ubin Pc abu-abu ukuran 15cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin Pc abu-abu ukuran 15cm x 20cm
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.17.
1 m’ plint ubin Pc abu-abu ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin Pc abu-abu ukuran 10cm x 30cm
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.18.
1 m’ plint ubin Pc abu-abu ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin Pc abu-abu ukuran 10cm x 40cm
Semen portland
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.19.1 m’ plint ubin warna ukuran 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin warna ukuran 10cm x 20cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.20.1 m’ plint ubin warna ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin warna ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.21.1 m’ plint ubin warna ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin warna ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.22.1 m’ plint ubin teraso ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.03.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teraso ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.23.1 m’ plint ubin teraso ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teraso ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.24.1 m’ plint ubin granit ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin granit ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.25.1 m’ plint ubin granit ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin granit ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.26.
1 m’ plint ubin teralux kerang ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teralux kerang ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.27.
1 m’ plint ubin teralux kerang ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teralux kerang ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.28.
1 m’ plint ubin teralux marmer ukuran 10cm x 60cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
plint ubin teralux marmer ukuran 10cm x 60cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.29.
1 m’ plint ubin teralux marmer ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teralux marmer ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.30.
1 m’ plint ubin teralux marmer ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin teralux marmer ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.31.1m2 lantai teraso cor di tempat, tebal 3cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Teraso cor di tempat, tebal 3cm
Semen warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.32.1m2 lantai keramik artistik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik artistik 10cm x 20cm
Semen portland
Pasir pasang
Semen warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.4.3.33.
1m2 lantai keramik artistik 10cm x 10cm atau 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik artistik 10cm x 10cm atau 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.34.1m2 lantai keramik ukuran 33cm x 33cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik ukuran 33cm x 33cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.35.1m2 lantai keramik ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik ukuran 30cm x 30cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.36.1m2 lantai keramik ukuran 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Keramik ukuran 20cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
keramik
A.4.4.3.37.
ukuran 10cm x 33cm untuk variasi/border
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Ubin keramik
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.38.
1m2 lantai keramik mozaik ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Keramik mozaik ukuran 30cm x 30cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.39. 1 m’ plint keramik ukuran 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint keramik ukuran 10cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.40. 1 m’ plint keramik ukuran 10cm x 10cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint keramik ukuran 10cm x 10cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.41. 1 m’ plint keramik ukuran 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint keramik ukuran 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.42.
1 m’ plint internal cove artistik 5cm x 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint internal cove artistik 5cm x 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.43.
1 m2 lantai marmer ukuran 100cm x 100cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
marmer ukuran 100cm x 100cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.44.
Pemasangan 1 m2 lantai karpet
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
lantai karpet
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.45.1 m2 underlayer (pelapis bawah karpet)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
underlayer (pelapis bawah karpet)
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.46.
Pemasangan 1 m2 lantai parquet kayu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Parquet kayu
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.47.
Pemasangan 1 m2 lantai kayu gymfloor
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Parquet kayu gymfloor
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.48. 1 m2 dinding porslen 11cm x 11cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Porselen Dinding 11x11
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.49. 1 m2 dinding porslen 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Porselen Dinding 10x20
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.50. 1 m2 dinding porslen 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Porselen Dinding 20x20
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.51.
1 m2 dinding keramik artistik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Keramik Dinding artistik
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.52.1 m2 dinding keramik artistik 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik Dinding artistik 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.53. 1 m2 dinding keramik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik Dinding 10cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.54. 1 m2 dinding keramik 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
keramik Dinding 20cm x 20cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.55. 1 m2 dinding marmer 100cm x 100cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
marmer Dinding 100cm x 100cm
Semen portland
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.56.
1 m2 dinding bata pelapis 3cm x 7cm x 24cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bata pelapis Dinding 3cm x 7cm x 24cm
Semen portland
Pasir Pasang
Semen Warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.57.
Pemasangan 1 m2 dinding batu paras
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Batu paras Dinding
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.58.
Pemasangan 1 m2 dinding batu tempel hitam
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
dinding batu tempel hitam
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.59. 1 m2 lantai vynil ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Vynil ukuran 30cm x 30cm
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.60.
Pemasangan 1 m2 wallpaper lebar 50 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
wallpaper lebar 50 cm
Lem Putih
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.61.
Pemasangan 1m2 floor harderner
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
floor harderner
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.62.
Pemasangan 1 m’ plint vynil 15cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
plint vynil 15cm x 30cm
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.63. 1 m’ plint kayu tebal 2 cm lebar 10 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan kelas I
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.64. 1 m2 paving block natural tebal 6 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Paving block 6 cm
Pasir beton
C PERALATAN
Peralatan Kerja Paving Blok
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.65. 1 m2 paving block natural tebal 8 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Paving block 8 cm natural
Pasir beton
C PERALATAN
Peralatan Kerja Paving Blok
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.66. 1 m2 paving block berwarna tebal 6 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Paving block 6cm berwarna
Pasir beton
C PERALATAN
Peralatan Kerja Paving Blok
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.67. 1 m2 paving block berwarna tebal 8 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Paving block 8 cm berwarna
Pasir beton
C PERALATAN
Peralatan Kerja Paving Blok
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.68.
Pemasangan 1 M2 Aluminium Composite Panel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Aluminium Composite Panel
Screw
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.1
HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
Pemasangan 1A.4.5.1.1.
m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes semen
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.1.2.
1 m2 langit-langit akustik ukuran (30 x 30) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Akustik ukuran 30 x 30 cm
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.1.3.
1 m2 langit-langit akustik ukuran (30 x 60) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Akustik ukuran 30 x 60 cm
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.1.4.
1 m2 langit-langit akustik ukuran (60 x 120) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Akustik 60 x 120
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 A.4.5.1.5.
langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Tripleks
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.1.6.
1 m2 langit-langit lambrisering kayu, tebal 9 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu papan
Paku tripleks
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2A.4.5.1.7.
langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Gypsum board 9 mm (1200 x 2400 mm)
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 langit-langit
A.4.5.1.8. akustik ukuran (60 x 120) cm berikut rangka alluminium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Profil Allum"T"
Kawat dia 4 mm
Ramset
Akustik 60 x 120
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.1.9.
Pemasangan 1 m’ list langit-langit kayu profil
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
List kayu profil
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.1.10 Pemasangan 1 m2 Rangka langit-langit besi hollow 40.40
Lihat pada kelompok Pekerjaan Besi dan Alumunium ( A.9.21)
A.4.5.1.10. Pemasangan 1 m2 Plafond PVC
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plafond PVC (setara Shunda Plafon, Flat Gloss Half
Screw
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
List PVC (setara Shunda Plafon,LS 301-1 Min.Silver
Screw
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Genteng palentong
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.2. 1 m2 atap genteng kodok glazuur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng kodok
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.3.1 m2 atap genteng palentong besar/super
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng kodok
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.4.
Pemasangan 1 m’ bubung genteng palentong
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng bubung
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.5. 1 m’ bubung genteng kodok glazuur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng bubung
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.6. 1 m’ bubung genteng palentong besar
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng bubung
Semen portland
Pasir Pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.7. 1 m2 roof light fibreglass 90x180
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Rooflight 90x180
Paku biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.8.
1 m2 atap asbes gelombang 0,92mx2,5m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.9.
1 m2 atap asbes gelombang 0,92mx2,25m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.10.
1 m2 atap asbes gelombang 0,92mx2,00m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.11.
1 m2 atap asbes gelombang 0,92mx1.80m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.12.
1 m2 atap asbes gelombang 1.05mx3.00m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.13.
1 m2 atap asbes gelombang 1.05mx2.70m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.14.
1 m2 atap asbes gelombang 1.05mx2.40m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.15.
1 m2 atap asbes gelombang 1.05mx2.10m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.16.
1 m2 atap asbes gelombang 1.05mx1.50m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.17.
1 m2 atap asbes gelombang 1.08mx3.00m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.18.
1 m2 atap asbes gelombang 1.08mx2.70m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.19.
1 m2 atap asbes gelombang 1.08mx2.40m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.20.
1 m2 atap asbes gelombang 1.08mx2.10m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.21.
1 m2 atap asbes gelombang 1.08mx1.80m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.22. 1 m’ bubung stel gelombang 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bubung stel gel.
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.23. 1 m’ bubung stel gelombang 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bubung stel gel.
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.24. 1 m’ bubung stel gelombang 1,08m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bubung stel gel.
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.25.
Pemasangan 1 m’ nok paten 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok paten 92cm
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.26.
Pemasangan 1 m’ nok paten 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok paten 92cm
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.27.
Pemasangan 1 m’ nok paten 1,08m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok paten 92cm
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.28.
Pemasangan 1 m’ nok stel rata 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok paten 92cm
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.29.
Pemasangan 1 m’ nok stel rata 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok paten 92cm
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.30.
Pemasangan 1 m2 genteng beton
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng beton
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.31.
Pemasangan 1 m2 genteng aspal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng aspal
Plywood 6 mm
Paku biasa
Plastic aerator
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.32.
1 m2 genteng metal ukuran 80 x 100 atap pelana
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng metal
Paku biasa ½”-1”
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.33.
1 m2 genteng metal ukuran 80 x 100 atap Jurai
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Genteng metal
Paku biasa ½”-1”
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.34.
Pemasangan 1 m2 atap sirap kayu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Sirap kayu
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.35.
Pemasangan 1 m’ nok genteng beton
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok genteng beton
Paku Biasa
Semen portland
Pasir Pasang
Semen warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.36.
Pemasangan 1 m’ nok genteng aspal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok genteng aspal
Paku Biasa
Kayu balok borneo
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.37.
Pemasangan 1 m’ nok genteng metal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok genteng metal
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Seng plat
Paku Biasa
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.39.
Pemasangan 1 m2 atap seng gelombang
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Seng gelombang
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.40.
Pemasangan 1 m’nok atap seng
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Seng plat
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.41.
Pemasangan 1 m2 atap alumunium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Alumunium gel tbl 0,55
Paku hak panj 15cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.42.
Pemasangan 1 m’ nok alumunium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Nok standar 40x18
Paku hak panj 15cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.2.43.
Pemasangan 1 m2 alumunium foil/sisalation
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Alumunium foil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
Pembuatan dan A.4.6.1.1.
pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu
Paku Biasa
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Balok kayu
Paku Biasa
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
PembuatanA.4.6.1.3.
dan pemasangan 1 m2 pintu klamp standar, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pembuatan dan
A.4.6.1.4.
pemasangan 1 m2 pintu klamp sederhana, kayu kelas III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pembuatan dan
A.4.6.1.5.
pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
kayu Papan
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pembuatan danA.4.6.1.7.
pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pembuatan 1 m2
A.4.6.1.8.
daun pintu plywood rangkap, rangka kayu kelas II tertutup
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Paku Biasa
Lem Kayu/Karet
Plywood 4 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pembuatan 1 m2
A.4.6.1.9.
pintu plywood rangkap, rangka expose kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Paku Biasa
Lem Kayu/Karet
Plywood 4 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.10. 1 m2 jalusi kusen, kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.11.
1 m2 teakwood rangkap, rangka expose kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
Lem Kayu/Karet
Teakwood 4 mm 90 x 220 cm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2
A.4.6.1.12.
teakwood rangkap lapis formika, rangka expose kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
Lem Kayu/Karet
Teakwood 4 mm 90 x 220 cm
Formika
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m3 konstruksi
A.4.6.1.13.
kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu
Besi strip
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.14.
1 m3 konstruksi kuda-kuda expose, kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu
Besi strip
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.15. 1 m3 konstruksi gordeng, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu
Besi strip
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.16.
1 m2 rangka atap genteng keramik, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu 5/7
Reng 2 x 3 cm
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.17.
1 m2 rangka atap genteng beton, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu 5/7
Reng (3 x 4) cm
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.18. 1 m2 rangka atap sirap, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas II
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1A.4.6.1.19.
m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu 5/7
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1A.4.6.1.20.
m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu 5/7
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.6.1.21.
1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.6.1.22.
1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 A.4.6.1.23.
m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1A.4.6.1.24.
m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu, 6 x 12
Paku Biasa
Teakwood 4 mm, 120 x 240
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.6.1.25.
1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Balok kayu, 6 x 12
Paku Biasa
Plywood 4 mm
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.26.
1 m2 dinding lambrisering dari Kayu Papan kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu Papan
Paku Biasa
Paku skrup
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1A.4.6.1.27.
m2 dinding lambrisering dari plywood ukuran (120 x 240) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plywood 4 mm
Paku Biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.28.
1 m2 dinding bilik, rangka kayu kelas III atau IV
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bilik bambu
Kayu 5/7
Paku Biasa
List kayu 2/4
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Kunci tanam antik
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.2.
Pemasangan 1 buah kunci tanam biasa
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kunci tanam biasa
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.3.
Pemasangan 1 buah kunci kamar mandi
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kunci tanam KM
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.4.
Pemasangan 1 buah kunci silinder
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kunci silinder
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.5.
Pemasangan 1 buah engsel pintu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Engsel pintu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.2.6. 1 buah engsel jendela kupu-kupu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Engsel kupu-kupu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.7.
Pemasangan 1 buah engsel angin
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Engsel angin
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.8.
Pemasangan 1 buah spring knip
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Spring knip
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.9.
Pemasangan 1 buah kait angin
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kait angin
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.10.
Pemasangan 1 buah door closer
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Door closer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.11.
Pemasangan 1 buah kunci slot
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kunci slot
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.12.
Pemasangan 1 buah Door holder
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Door holder
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.13.
Pemasangan 1 buah door stop
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Door stop
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.14.
Pemasangan 1 buah Rrel pintu sorong
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Rel pintu sorong
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.15.
Pemasangan 1 buah kunci lemari
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kunci lemari
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.16.
Pemasangan 1 m2 kaca tebal 3 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca tebal 3mm
SEalant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Kaca tebal 5 mm
SEalant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.18.
Pemasangan 1 m2 kaca tebal 8 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca tebal 8 mm
SEalant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Kaca buram 12 mm
SEalant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.20.
Pemasangan 1 m2 kaca cermin tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca cermin 5 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.21.
Pemasangan 1 m2 kaca cermin tebal 8 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca cermin 8 mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.2.22. 1 m2 kaca wireglassed tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca wireglassed 5mm
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.6.2.23.
Pemasangan 1 m2 kaca patri tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kaca patri 5mm
Sealant
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Soda api
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
1 m2 Pencucian
A.4.7.1.2.bidang permukaan tembok yang pernah dicat
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Sabun
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
1 m2 A.4.7.1.3.
Pengerokan karat pada permukaan baja cara manual
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Sabun
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
1 m2 Pengecatan bidang
A.4.7.1.4.
kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat menie
Plamuur
Cat dasar Kayu
Cat Penutup Kayu
Kuas
Pengencer
Ampelas
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan 1 m2 bidang
A.4.7.1.5.
kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat Penutup)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat menie
Plamuur
Cat dasar Kayu
Cat Penutup Kayu
Kuas
Pengencer
Ampelas
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.6.
Pelaburan 1 m2 bidang kayu dengan teak oil
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Teak oil
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.7.
Pelaburan 1 m2 bidang kayu dengan politur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Politur
Politur jadi
Ampelas
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pelaburan
A.4.7.1.8.
1 m2 bidang kayu dengan cat residu dan ter
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Residu atau ter
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.9.
Pelaburan 1 m2 bidang kayu dengan vernis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Vernis
Dempul
Ampelas
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plamuur
Cat dasar Tembok
Cat Penutup Tembok
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat dasar Tembok
Cat Penutup Tembok
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.12.
Pelaburan 1 m2 tembok dengan kalkarium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kalkarium
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.13.
Pelaburan 1 m2 tembok dengan kapur sirih
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kapur sirih
Ampelas
Alang-alang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pelaburan
A.4.7.1.14.
1 m2 tembok lama dengan kapur sirih (pemeliharaan)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kapur sirih
Ampelas
Alang-alang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.15.Pemasangan 1 m2 wallpaper
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Wallpaper
Lem Kayu/Karet
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan
A.4.7.1.16.1 m2 permukaan baja dengan menie besi
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Menie besi
Kuas
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PengecatanA.4.7.1.17.
1 m2 permukaan baja dengan menie besi dengan perancah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Menie besi
Pengencer
Kuas
Perancah kayu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan
A.4.7.1.18.
1 m2 permukaan baja galvanis secara manual 4 lapis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Menie A
Menie B
Cat Besi
Kuas
Pengencer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan 1 m2 A.4.7.1.19.
permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat Besi
Kuas
Pengencer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PengecatanA.4.7.1.20.
1 m2 permukaan baja galvanis secara manual sistem 3 lapis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat dasar Besi
Cat antara
Cat Besi
Kuas
Pengencer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan 1 m2 A.4.7.1.21.
permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat Besi
Pengencer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.4.7.1.22.
Plituran 10 m2 dengan plitur melamic
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Cat Dasar Kayu
Pengencer
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
(K3)
A.5.1.1.1.
Pemasangan 1 buah closet duduk/monoblock
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Closet duduk
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Closet jongkok
Semen portland
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
3. 1 buah closet jongkok teraso
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Closet jongkok
Semen portland
Pasir pasang
Bata merah
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1 (K3)
4. Pemasangan 1 buah urinoir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Urinoir
Semen portland
Pasir pasang
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1(K3)
5. Pemasangan 1 buah wastafel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Wastafel
Semen portland
Pasir pasang
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
(K3) Pemasangan
6. 1 buah bathcuip porselen
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bathcuip
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.5.1.1
Pemasangan
7. 1 buah bak fibreglass vol 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bak fibreglass
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Pemasangan
A.5.1.1 8. 1 buah bak mandi batu bata vol 0,30 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir pasang
Porselen 11x11
Semen warna
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 9. 1 buah bak mandi teraso vol 0,30 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bak fibreglass
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
10. 1 buah bak air fibreglass vol 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bak fibreglass
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
11. 1 buah bak beton volume 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Beton 1:2:3
Baja tulangan
Kayu bekisting
Ubin porselen
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 12. 1 buah bak cuci piring stainlessteel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bak cuci piring
Waterdrain
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
13. 1 buah bak cuci piring teraso
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bak cuci piring
Waterdrain
Semen portland
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1 14.
Pemasangan 1 buah floor drain
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Floor drain
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1
1 buah
15. bak kontrol pasangan bata 30x30 tinggi 35 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.5.1.1
1 buah16.
bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.5.1.1
1 buah17.
bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
18. 1 m’ pipa galvanis diameter ½”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis ½”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
19. 1 buah kran diameter ½” atau 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kran air
Sealtape
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
20. 1 m’ pipa galvanis diameter 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis 3/4”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
21. 1 m’ pipa galvanis diameter 1”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis 1”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
22. 1 m’ pipa galvanis diameter 1 ½”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis 11/2”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
23. 1 m’ pipa galvanis diameter 3”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis 3”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.5.1.1
Pemasangan
24. 1 m’ pipa galvanis diameter 4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa galvanis 4”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 25. 1 m’ pipa PVC tipe AW diameter 1/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 1/2”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 26. 1 m’ pipa PVC tipe AW diameter 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 3/4”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 27. 1 m’ pipa PVC tipe AW diameter 1”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 1”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 28. 1 m’ pipa PVC tipe AW diameter 11/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 11/2”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 29. 1 m’ pipa PVC tipe AW diameter 2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 2”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 30. 1 m’ pipa PVC tipe AW diameter 21/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 21/2”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 31. 1 m’ pipa PVC tipe AW diameter 3”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 3”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 32. 1 m’ pipa PVC tipe AW diameter 4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 4”
Perlengkapan
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 33. 1 m’ pipa air limbah jenis pipa tanah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa tanah
Semen portland
Pasir pasang
Pasir urug
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1
1 m’
34.pipa air limbah jenis pipa tanah diameter 15 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa tanah
Semen portland
Pasir pasang
Pasir urug
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 35. 1 m’ pipa beton diameter 15 - 20 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa Beton
Bata merah
Semen portland
Pasir pasang
Pasir urug
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1.36. 1 m’ pipa beton diameter 30 - 100 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa Beton
Bata merah
Semen portland
Pasir pasang
Pasir urug
PVC Ø 63
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Pipa PVC Ø 63 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Catatan:
Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang t
Apabila ada tambahan peralatan yang digunakan, harus disesuaikan deng
gambar kerja.
A.8.4.1.2
(K3) Pemasangan 1 m pipa PVC Ø 90 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 90 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.3
(K3) Pemasangan 1 m pipa PVC Ø 110 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 110 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.4
(K3) Pemasangan 1 m pipa PVC Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.5
(K3) Pemasngan 1 m pipa PVC Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.6
(K3) Pemasangan 1 m pipa PVC Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.7
(K3) Pemasangan 1 m pipa PVC Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.8
(K3) Pemasangan 1 m pipa PVC Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 400 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.9
(K3) Pemasangan 1 m pipa PVC Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 450 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.10
(K3) Pemasangan 1 m pipa PVC Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.11
(K3) Pemasangan 1 m pipa PVC Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 600 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.12
(K3) Pemasangan 1 m pipa PVC Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 800 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.13
(K3) Pemasangan 1 m pipa PVC Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 900 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.14
(K3) Pemasangan 1 m pipa PVC Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.15
(K3) Pemasangan 1 m pipa PVC Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.16
(K3) Pemasangan 1 m pipa PVC Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.17
(K3) Pemasangan 1 m pipa HDPE Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 63 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.18
(K3) Pemasangan 1 m pipa HDPE Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.19
(K3) Pemasangan 1 m pipa HDPE Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 125 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.20
(K3) Pemasangan 1 m pipa HDPE Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.21
(K3) Pemasangan 1 m pipa HDPE Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.22
(K3) Pemasangan 1 m pipa HDPE Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.23
(K3) Pemasangan 1 m pipa HDPE Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.24
(K3) Pemasangan 1 m pipa HDPE Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 400 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.25
(K3) Pemasangan 1 m pipa HDPE Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 450 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.26
(K3) Pemasangan 1 m pipa HDPE Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.27
(K3) Pemasangan 1 m pipa HDPE Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.28
(K3) Pemasangan 1 m pipa HDPE Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 800 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.29
(K3) Pemasangan 1 m pipa HDPE Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 900 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.30
(K3) Pemasangan 1 m pipa HDPE Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.31
(K3) Pemasangan 1 m pipa HDPE Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 1100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.32
(K3) Pemasangan 1 m pipa HDPE Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 1200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.33
(K3) Pemasangan 1 m pipa GIP Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 63 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.34
(K3) Pemasangan 1 m pipa GIP Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.35
(K3) Pemasangan 1 m pipa GIP Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 125 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.36
(K3) Pemasangan 1 m pipa GIP Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.37
(K3) Pemasangan 1 m pipa GIP Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.38
(K3) Pemasangan 1 m pipa GIP Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.39
(K3) Pemasangan 1 m pipa GIP Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.40
(K3) Pemasangan 1 m pipa GIP Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 400 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.41
(K3) Pemasangan 1 m pipa GIP Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 450 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.42
(K3) Pemasangan 1 m pipa GIP Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.43
(K3) Pemasangan 1 m pipa GIP Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 600 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.44
(K3) Pemasangan 1 m pipa GIP Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 800 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.45
(K3) Pemasangan 1 m pipa GIP Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 900 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.46
(K3) Pemasangan 1 m pipa GIP Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.47
(K3) Pemasangan 1 m pipa GIP Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.48
(K3) Pemasangan 1 m pipa GIP Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.49
(K3) Pemasangan 1 m pipa DCI Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.50
(K3) Pemasangan 1 m pipa DCI Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 125 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.51
(K3) Pemasangan 1 m pipa DCI Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.52
(K3) Pemasangan 1 m pipa DCI Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.53
(K3) Pemasangan 1 m pipa DCI Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.54
(K3) Pemasangan 1 m pipa DCI Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.55
(K3) Pemasangan 1 m pipa DCI Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 400 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.56
(K3) Pemasangan 1 m pipa DCI Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 450 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.57
(K3) Pemasangan 1 m pipa DCI Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 500 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.58
(K3) Pemasangan pipa 1 m DCI Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 600 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.59
(K3) Pemasangan 1 m pipa DCI Ø800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 800 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.60
(K3) Pemasangan 1 m pipa DCI Ø900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 900 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.61
(K3) Pemasangan 1 m pipa DCI Ø1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1000 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.62
(K3) Pemasangan 1 m pipa DCI Ø1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1100 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.63
(K3) Pemasangan 1 m pipa DCI Ø1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1200 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.64
(K3) Pemasangan 1 m pipa baja Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 63 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.65
(K3) Pemasangan 1 m pipa baja Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.66
(K3) Pemasangan 1 m pipa baja Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 125 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.67
(K3) Pemasangan 1 m pipa baja Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.68
(K3) Pemasangan 1 m pipa baja Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.69
(K3) Pemasangan pipa baja Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.70
(K3) Pemasangan 1 m pipa baja Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.71
(K3) Pemasangan 1 m pipa baja Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 400 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.72
(K3) Pemasangan 1 m pipa baja Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 450 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.73
(K3) Pemasangan 1 m pipa baja Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 500 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.74
(K3) Pemasangan 1 m pipa baja Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 600 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.75
(K3) Pemasangan 1 m pipa baja Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 800 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.76
(K3) Pemasangan 1 m pipa baja Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 900 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.77
(K3) Pemasangan 1 m pipa baja Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1000 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.78
(K3) Pemasangan 1 m pipa baja Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1100 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.79
(K3) Pemasangan 1 m pipa baja Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1200 mm
C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2
HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
A.8.4.2.1
(K3) Pemotongan 1 buah pipa PVC Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 63 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.2
(K3) Pemotongan 1 m pipa PVC Ø 90 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 90 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.3
Pemotongan 1 buah pipa PVC Ø 110 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 110 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.4
Pemotongan 1 buah pipa PVC Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 150 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.5
Pemotongan 1 buah pipa PVC Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 200 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.6
Pemotongan 1 buah pipa PVC Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 250 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.7
Pemotongan 1 buah pipa PVC Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 300 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.8
Pemotongan 1 buah pipa PVC Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 400 mm
C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.9
Pemotongan 1 buah pipa PVC Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.10
(K3) Pemotongan 1 buah pipa PVC Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.11
(K3) Pemotongan 1 buah pipa PVC Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.12
(K3) Pemotongan 1 buah pipa PVC Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.13
(K3) Pemotongan 1 buah pipa PVC Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 900 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.14
Pemotongan 1 buah pipa PVC Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1000 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.15
Pemotongan 1 buah pipa PVC Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.16
Pemotongan 1 buah pipa PVC Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 1200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.17
(K3) Pemotongan 1 buah pipa HDPE Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 63 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.18
Pemotongan 1 buah pipa HDPE Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.19
Pemotongan 1 buah pipa HDPE Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 125 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.20
Pemotongan 1 buah pipa HDPE Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 150 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.21
Pemotongan 1 buah pipa HDPE Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.22
(K3) Pemotongan 1 buah pipaHDPE Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 250 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.23
Pemotongan 1 buah pipa HDPE Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 300 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.24
Pemotongan 1 buah pipa HDPE Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 400 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.25
Pemotongan 1 buah pipa HDPE Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.26
Pemotongan 1 buah pipa HDPE Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.27
Pemotongan 1 buah pipa HDPE Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.28
Pemotongan 1 buah pipa HDPE Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.29
Pemotongan 1 buah pipa HDPE Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 900 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.30
Pemotongan 1 buah pipa HDPE Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 1000
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.31
Pemotongan 1 buah pipa HDPE Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 1100
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.32
Pemotongan 1 buah pipa HDPE Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 1200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.33
(K3) Pemotongan 1 buah pipa GIP Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 63 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.34
(K3) Pemotongan 1 buah pipa GIP Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.35
(K3) Pemotongan 1 buah pipa GIP Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 125 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.36
(K3) Pemotongan 1 buah pipa GIP Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 150 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.37
(K3) Pemotongan 1 buah pipa GIP Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.38
(K3) Pemotongan 1 buah pipa GIP Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 250 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.39
(K3) Pemotongan 1 buah pipa GIP Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 300 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.40
(K3) Pemotongan 1 buah pipa GIP Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 400 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.41
(K3) Pemotongan 1 buah pipa GIP Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.42
(K3) Pemotongan 1 buah pipa GIP Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.43
(K3) Pemotongan1 buah pipa GIP Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.44
(K3) Pemotongan 1 buah pipa GIP Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.45
(K3) Pemotongan 1 buah pipa GIP Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 900 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.46
(K3) Pemotongan 1 buah pipa GIP Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1000 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.47
(K3) Pemotongan 1 buah pipa GIP Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.48
(K3) Pemotongan 1 buah pipa GIP Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 1200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.49
(K3) Pemotongan 1 buah pipa DCI Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.50
(K3) Pemotongan 1 buah pipa DCI Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 125 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.51
(K3) Pemotongan 1 buah pipa DCI Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.52
(K3) Pemotongan 1 buah pipa DCI Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.53
(K3) Pemotongan 1 buah pipa DCI Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.54
(K3) Pemotongan 1 buah pipa DCI Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.55
(K3) Pemotongan 1 buah pipa DCI Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 400 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.56
(K3) Pemotongan 1 buah pipa DCI Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.57
(K3) Pemotongan 1 buah pipa DCI Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.58
(K3) Pemotongan 1 buah pipa DCI Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.59
(K3) Pemotongan 1 buah pipa DCI Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.60
(K3) Pemotongan 1 buah pipa DCI Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 900 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.61
(K3) Pemotongan 1 buah pipa DCI Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1000 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.62
(K3) Pemotongan 1 buah pipa DCI Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.63
(K3) Pemotongan 1 buah pipa DCI Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.64
(K3) Pemotongan 1 buah pipa baja Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 63 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.65
(K3) Pemotongan 1 buah pipa baja Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.66
(K3) Pemotongan 1 buah pipa baja Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 125 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.67
(K3) Pemotongan 1 buah pipa baja Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 150 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.68
(K3) Pemotongan 1 buah pipa baja Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.69
(K3) Pemotongan 1 buah pipa baja Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 250 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.70
(K3) Pemotongan 1 buah pipa baja Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 300 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.71
(K3) Pemotongan 1 buah pipa baja Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 400 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.72
(K3) Pemotongan 1 buah pipa baja Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.73
(K3) Pemotongan 1 buah pipa baja Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.74
(K3) Pemotongan 1 buah pipa baja Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.75
(K3) Pemotongan 1 buah pipa baja Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.76
(K3) Pemotongan 1 buah pipa baja Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 900 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.77
(K3) Pemotongan 1 buah pipa baja Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1000 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.78
(K3) Pemotongan 1 buah pipa baja Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.79
(K3) Pemotongan 1 buah pipa baja Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA
A.8.4.3SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
A.8.4.3.1
(K3) Pemasangan 1 buah Valve Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.2
(K3) Pemasangan 1 buah Valve Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.3
(K3) Pemasangan 1 buah Valve Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.4
(K3) Pemasangan 1 buah Valve Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.5
(K3) Pemasangan 1 buah Valve Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 400 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.6
(K3) Pemasangan 1 buah Valve Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 450 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.7
(K3) Pemasangan 1 buah Valve Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.8
(K3) Pemasangan 1 buah Valve Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 600 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.9
(K3) Pemasangan 1 buah Valve Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 700 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.10
(K3) Pemasangan 1 buah Valve Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 800 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.11
(K3) Pemasangan 1 buah Valve Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 900 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.12
(K3) Pemasangan 1 buah Valve Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.13
(K3) Pemasangan 1 buah Valve Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 1100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.14
(K3) Pemasangan 1 buah Valve Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 1200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.15
(K3) Pemasangan 1 buah Tee Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 150 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.16
(K3) Pemasangan 1 buah Tee Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.17
(K3) Pemasangan 1 buah Tee Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.18
(K3) Pemasangan 1 buah Tee Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.19
(K3) Pemasangan 1 buah Tee Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 400 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.20
(K3) Pemasangan 1 buah Tee Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 450 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.21
(K3) Pemasangan 1 buah Tee Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 500 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.22
(K3) Pemasangan 1 buah Tee Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 600 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.23
(K3) Pemasangan 1 buah Tee Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 700 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.24
(K3) Pemasangan 1 buah Tee Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 800 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.25
(K3) Pemasangan 1 buah Tee Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 900 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.26
(K3) Pemasangan 1 buah Tee Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.27
(K3) Pemasangan 1 buah Tee Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 1100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.28
(K3) Pemasangan 1 buah Tee Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 1200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA A.8.4.4
SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
(K3) Penyambungan
A.8.4.4.1 1 buah pipa baru ke pipa yang ada Ø 80 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 80 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.2 1 buah pipa baru ke pipa yang ada Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 100 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.3 1 buah pipa baru ke pipa yang ada Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 150 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.4 1 buah pipa baru ke pipa yang ada Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.5 1 buah pipa baru ke pipa yang ada Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 250 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.6 1 buah pipa baru ke pipa yang ada Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 300 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.7 1 buah pipa baru ke pipa yang ada Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 400 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.8 1 buah pipa baru ke pipa yang ada Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 450 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.9 1 buah pipa baru ke pipa yang ada Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.10 1 buah pipa baru ke pipa yang ada Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 600 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.11 1 buah pipa baru ke pipa yang ada Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 700 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3) Penyambungan
A.8.4.4.12
1 buah 1 buah pipa baru ke pipa yang ada Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Ø 800 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5
HARGA SATUAN PEKERJAAN PENGETESAN PIPA
A.8.4.5.1
(K3) Pengetesan 1 m pipa Ø 50 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.2
(K3) Pengetesan 1 m pipa Ø 75 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.3
(K3) Pengetesan 1 m pipa Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.4
(K3) Pengetesan 1 m pipa Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.5
(K3) Pengetesan 1 m pipa Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.6
(K3) Pengetesan 1 m pipa Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.7
(K3) Pengetesan 1 m pipa Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.8
(K3) Pengetesan 1 m pipa Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.9
(K3) Pengetesan 1 m pipa Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.10
(K3) Pengetesan 1 m pipa Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Pipa listrik 5/8”
Kabel NYM 3x2,5 mm2
Tee Doos
L.Bow
Las Dop
Klem Pipa Listrik
Mongkok (Listrik)
Saklar (standar)
Fitting Lampu
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.6.2
Memasang 1 Titik Instalasi Penerangan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kabel NYM 3x2,5 mm2
Pipa Conduit
Socket Pipa
Tee Doos
Klem Pipa
Fhiser
Las Dop
Sealtape Listrik
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
ALISA HARGA SATUAN 2021
AN PERSIAPAN
agar sementara dari kayu tinggi 2 meter
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Batang 1.2500 -
Kg 5.0000 -
m3 0.0050 -
m3 0.0090 -
m3 0.0720 -
Kg 0.0600 -
Liter 0.4000 -
JUMLAH HARGA BAHAN -
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Batang 1.2500 -
Kg 2.5000 -
Lbr 1.2000 -
m3 0.0050 -
m3 0.0090 -
m3 0.0720 -
Kg 0.0600 -
Liter 0.4500 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
59,500.00
10% 5,950.00
- 65,450.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 1.0000 78,500.00 78,500.00
OH 1.5000 100,000.00 150,000.00
OH 0.1500 100,000.00 15,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 248,000.00
Batang 3.0000 -
m3 0.2760 -
Kg 0.7000 -
Lbr 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 248,000.00
10% 24,800.00
- 272,800.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Batang 1.7000 -
m3 0.2100 -
Kg 0.3000 -
Kg 10.5000 -
m3 0.0300 -
m3 0.0500 -
Lbr 1.5000 -
Lbr 0.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 303,000.00
10% 30,300.00
- 333,300.00
edeng pekerja
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Batang 1.2500 -
Kg 0.1860 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 303,000.00
10% 30,300.00
- 333,300.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
RJAAN TANAH
biasa sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
biasa sedalam 2 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
asa sedalam 3 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
ras sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
das sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
mpur sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
erjaan galian
3 galian tanah Tanah Biasa Sedalam 1 M
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
RJAAN PONDASI
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 1.5000 78,500.00 117,750.00
OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
kosong (anstamping)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
RJAAN BETON
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
ja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
tu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
tu f’= 21,7 MPa (K 250), slump (120 ± 20) mm, w/c = 0,56
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
tu f’c = 26,4 MPa (K 300), slump (120 ± 20) mm, w/c = 0,52
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
tu f’c = 28,8 MPa (K 325), slump (120 ± 20) mm, w/c = 0,49
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
tu f’c = 31,2 MPa (K 350), slump (120 ± 20) mm, w/c = 0,48
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 2.1000 78,500.00 164,850.00
OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.1050 90,000.00 9,450.00
JUMLAH TENAGA KERJA 212,800.00
kg 400.0000 -
m3 0.4800 -
m3 0.8000 -
kg 1.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 212,800.00
10% 21,280.00
- 234,080.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,280.00
10% 828.00
- 9,108.00
Waterstop lebar 200 mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,025.00
10% 1,002.50
- 11,027.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,040.00
10% 1,104.00
- 12,144.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
l presstressed polos/strands
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
kg 10.2000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,052.50
10% 705.25
- 7,757.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
207,530.00
10% 20,753.00
228,283.00
3 X Pemakaian 76,094.33
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
222,530.00
10% 22,253.00
244,783.00
3 X Pemakaian 81,594.33
-
JUMLAH HARGA ALAT -
456,590.00
10% 45,659.00
502,249.00
3 X Pemakaian 167,416.33
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
467,090.00
10% 46,709.00
513,799.00
3 X Pemakaian 171,266.33
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
696,590.00
10% 69,659.00
766,249.00
3 X Pemakaian 255,416.33
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
511,880.00
10% 51,188.00
563,068.00
3 X Pemakaian 187,689.33
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
426,515.00
10% 42,651.50
469,166.00
3 X Pemakaian 156,388.67
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
#REF!
10% #REF!
#REF!
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
1,359,200.00
10% 135,920.00
1,495,120.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.2700 -
kg 2.0000 -
Liter 0.6000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
824,795.00
10% 82,479.50
907,274.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.4000 -
kg 4.0000 -
Liter 2.0000 -
kg 315.0000 -
kg 4.5000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
M3 0.1500 -
Lbr 3.5000 -
Batang 20.0000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
1,027,995.00
10% 102,799.50
1,130,794.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.3200 -
kg 3.2000 -
Liter 1.6000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1400 -
Lembar 2.8000 -
Batang 16.0000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
892,895.00
10% 89,289.50
982,184.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
728,900.00
10% 72,890.00
801,790.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.2400 -
kg 3.2000 -
Liter 1.6000 -
kg 157.5000 -
kg 2.2500 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1600 -
Lembar 2.8000 -
Batang 24.0000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
354,155.00
10% 35,415.50
389,570.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.2500 -
kg 3.0000 -
Liter 1.2000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1050 -
Lembar 2.5000 -
Batang 14.0000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
824,795.00
10% 82,479.50
907,274.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.0020 -
kg 0.0100 -
Liter 1.2000 -
kg 3.0000 -
kg 0.4500 -
kg 4.0000 -
m3 0.0060 -
m3 0.0090 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
21,540.00
10% 2,154.00
23,694.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.0030 -
kg 0.0200 -
Liter 1.2000 -
kg 3.6000 -
kg 0.0500 -
kg 5.5000 -
m3 0.0090 -
m3 0.0150 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
35,564.50
10% 3,556.45
39,120.00
AN BETON PRACETAK
han produksi tebal 8cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 26.0800 -
Kg 60.8000 -
Kg 82.3200 -
L 17.2000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
13,392.00
10% 1,339.20
14,731.00
han produksi tebal 10 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 32.6000 -
Kg 76.0000 -
Kg 102.9000 -
L 21.5000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
16,772.50
10% 1,677.25
18,449.00
han produksi tebal 12 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 32.1200 -
Kg 91.2000 -
Kg 123.4800 -
L 25.8000 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
20,043.00
10% 2,004.30
22,047.00
han produksi tebal 15 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 48.9000 -
Kg 114.0000 -
Kg 154.3500 -
L 32.2500 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
25,138.00
10% 2,513.80
27,651.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
83,507.26
10% 8,350.73
91,857.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.0050 -
Lbr 0.0430 -
L 0.2000 -
Bh 0.6930 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
4,604.00
10% 460.40
5,064.00
m3 0.0040 -
Lbr 0.0480 -
L 0.2000 -
Kg 0.0460 -
Bh 0.6930 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
4,604.00
10% 460.40
5,064.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
6,410.50
10% 641.05
7,051.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
10,436.50
10% 1,043.65
11,480.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA ALAT -
8,423.50
10% 842.35
9,265.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
52,194.00
10% 5,219.40
57,413.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
53,686.50
10% 5,368.65
59,055.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
48,158.50
10% 4,815.85
52,974.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
L 6.676 -
JUMLAH HARGA BAHAN -
s kenaikan lantai
untuk balok pracetak
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
L 6.11 -
JUMLAH HARGA BAHAN -
unit hari 0.061 -
Buah hari 1.1 -
JUMLAH HARGA ALAT -
Err:502
10% Err:502
Err:502
s kenaikan lantai
ereksi Balok
L 8.277 -
JUMLAH HARGA BAHAN -
s kenaikan lantai
ereksi Kolom
nen plat pracetak ( ± 20 m)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
L 1.8970 -
JUMLAH HARGA BAHAN -
UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
L 1.8970 -
JUMLAH HARGA BAHAN -
UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
L 1.8970 -
JUMLAH HARGA BAHAN -
UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.0120 -
m3 0.0040 -
Kg 0.2640 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 28,189.50
10% 2,818.95
- 31,008.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 1.1500 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
11,580.00
10% 1,158.00
12,738.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
rjaan perakitan
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.1000 78,500.00 7,850.00
OH 0.1000 100,000.00 10,000.00
OH 0.0010 100,000.00 100.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 18,400.00
Liter 1.0000 -
Liter 0.1000 -
JUMLAH HARGA BAHAN -
Jam 0.8000 -
JUMLAH HARGA ALAT -
- 18,400.00
10% 1,840.00
- 20,240.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 15.0000 -
Kg 32.8000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
Kg 0.4000 -
Liter 0.3000 -
Liter 0.0400 -
JUMLAH HARGA BAHAN -
Jam 0.1700 -
JUMLAH HARGA ALAT -
- 5,520.00
10% 552.00
- 6,072.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 4.7600 -
m 4.5220 -
cm 20.0000 5,520.00 110,400.00
JUMLAH HARGA BAHAN 110,400.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.0000 -
JUMLAH HARGA BAHAN -
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 84,920.00
10% 8,492.00
- 93,412.00
creen alluminium
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 94,640.00
10% 9,464.00
- 104,104.00
g door alluminium
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 193,000.00
10% 19,300.00
- 212,300.00
pintu alluminium
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.1000 -
buah 2.0000 -
Tube 0.0600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,294.50
10% 829.45
- 9,123.00
m 4.4000 -
m 14.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,400.50
10% 1,640.05
- 18,040.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 4.4000 -
m 4.5000 -
Tube 0.2700 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,522.50
10% 1,652.25
- 18,174.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 67,595.00
10% 6,759.50
- 74,354.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
kg 6.1770 -
cm 27.0800 5,520.00 149,481.60
JUMLAH HARGA BAHAN 149,481.60
- -
JUMLAH HARGA ALAT -
- 471,746.60
10% 47,174.66
- 518,921.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m2 1.1000 -
cm 11.1100 5,520.00 61,327.20
kg 1.7160 -
JUMLAH HARGA BAHAN 61,327.20
- -
JUMLAH HARGA ALAT -
- 80,627.20
10% 8,062.72
- 88,689.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.2000 78,500.00 15,700.00
OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 37,790.00
m2 1.1000 -
buah 10.0000 -
m 7.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,790.00
10% 3,779.00
- 41,569.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.0500 -
kg 0.0150 -
m3 0.0190 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,790.00
10% 3,779.00
- 41,569.00
g ½ Lingkaran D-15 cm, Seng Plat bjls 30 Lebar 45 cm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m 1.0500 -
kg 0.0100 -
kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 45,495.00
10% 4,549.50
- 50,044.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
M1 4.0000 -
Ls 1.0000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 67,595.00
10% 6,759.50
- 74,354.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.7604 78,500.00 59,691.40
OH 0.7604 100,000.00 76,040.00
OH 0.0760 100,000.00 7,600.00
OH 0.0380 90,000.00 3,420.00
JUMLAH TENAGA KERJA 146,751.40
kg 4.0500 -
JUMLAH HARGA BAHAN -
- -
0.1000 -
JUMLAH HARGA ALAT -
- 146,751.40
10% 14,675.14
- 161,426.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
kg 4.0500 -
JUMLAH HARGA BAHAN -
0.1000 -
JUMLAH HARGA ALAT -
- 141,649.00
10% 14,164.90
- 155,813.00
ANG KUDA-KUDA BAJA RINGAN + RENG UNTUK ATAP GENTENG BIASA/METAL
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
M' 3.7200 -
bh 28.0000 -
bh 2.0000 -
M' 5.4000 -
M' 0.1240 -
JUMLAH HARGA BAHAN -
0.1000 -
JUMLAH HARGA ALAT -
- 66,200.00
10% 6,620.00
- 72,820.00
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
m3 0.1 -
Kg 4.4 -
JUMLAH HARGA BAHAN -
Ls 0.1000 - -
JUMLAH HARGA ALAT -
- 42,045.00
10% 4,204.50
- 46,249.00
RJAAN PLESTERAN
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
Kg 5.1840 -
m3 0.0260 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00
Kg 3.9360 -
m3 0.0280 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00
Kg 3.4560 -
m3 0.0290 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00
Kg 5.7600 -
m3 0.0030 -
m3 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00
Kg 3.0000 -
m3 0.0050 -
m3 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m3 0.0090 -
m3 0.0090 -
m3 0.0090 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00
m3 0.0070 -
m3 0.0070 -
m3 0.0150 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00
Kg 13.6320 -
m3 0.0270 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00
Kg 10.3680 -
m3 0.0310 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,580.00
10% 4,358.00
- 47,938.00
Kg 8.3200 -
m3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00
Kg 6.9120 -
m3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00
Kg 5.8880 -
m3 0.0360 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00
m3 0.0090 -
m3 0.0090 -
m3 0.0180 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 60,720.00
10% 6,072.00
- 66,792.00
Kg 5.1840 -
m3 0.0260 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00
Kg 0.5000 -
m3 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 50,640.00
10% 5,064.00
- 55,704.00
Kg 10.0000 -
Kg 15.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 62,195.00
10% 6,219.50
- 68,414.00
Kg 10.0000 -
Kg 15.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 62,195.00
10% 6,219.50
- 68,414.00
Kg 4.3200 -
m3 0.0060 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,900.00
10% 3,590.00
- 39,490.00
Kg 1.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 9,755.00
10% 975.50
- 10,730.00
Kg 6.3400 -
m3 0.0120 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00
Kg 3.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00
Kg 16.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00
Kg 3.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00
Bh 6.6300 -
kg 9.8000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 11.8700 -
kg 10.0000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 26.5000 -
kg 10.4000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,355.00
10% 3,735.50
- 41,090.00
Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00
Bh 26.5000 -
kg 10.4000 -
Kg 1.6200 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,355.00
10% 3,735.50
- 41,090.00
Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00
Bh 3.1000 -
kg 9.6000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 33,120.00
10% 3,312.00
- 36,432.00
Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00
Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00
Bh 5.3000 -
kg 1.6500 -
M3 0.0040 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.2400 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.2400 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 1.7000 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00
M3 0.0360 -
Kg 0.1000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 49,680.00
10% 4,968.00
- 54,648.00
Bh 53.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Bh 106.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 3.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 10.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 1.6200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Bh 11.8700 -
Kg 10.0000 -
M3 0.0450 -
Kg 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 26.5000 -
Kg 10.4000 -
M3 0.0450 -
Kg 1.6200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 33.0000 -
Kg 9.8000 -
M3 0.0450 -
Kg 4.3700 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,995.00
10% 14,499.50
- 159,494.00
Bh 11.8700 -
Kg 14.1500 -
M3 0.0390 -
Kg 2.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 5.3000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.0250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00
Bh 10.6000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00
Bh 5.3000 -
Kg 0.5700 -
M3 0.0015 -
Kg 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00
Bh 5.3000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.1000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,795.00
10% 14,479.50
- 159,274.00
Bh 1.0600 -
Kg 8.1900 -
M3 0.0450 -
Kg 0.6500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
m2 1.0500 -
Kg 0.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 32,855.00
10% 3,285.50
- 36,140.00
m2 1.0500 -
Kg 0.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
m2 1.0500 -
Kg 0.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 86.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 138,000.00
10% 13,800.00
- 151,800.00
Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 26.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.9400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 106.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.9000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 26.5000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.9400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00
Bh 1.0600 -
Kg 12.4400 -
M3 0.0250 -
Kg 0.6500 -
Bh 3.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 179,400.00
10% 17,940.00
- 197,340.00
Bh 63.0000 -
Kg 12.4400 -
M3 0.0250 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 138,000.00
10% 13,800.00
- 151,800.00
Bh 1.1000 -
Kg 11.7500 -
M3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Bh 1.1000 -
Kg 11.7500 -
M3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Bh 11.8700 -
Kg 0.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 28,995.00
10% 2,899.50
- 31,894.00
m 2.2000 -
Kg 0.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,855.00
10% 4,685.50
- 51,540.00
Kg 5.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00
Bh 1.7600 -
Kg 0.0800 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 15,440.00
10% 1,544.00
- 16,984.00
M3 0.0030 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00
M2 1.0100 -
M3 0.0500 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00
M2 1.01 -
M3 0.07 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00
M2 1.0100 -
M 3
0.0500 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
M2 1.0100 -
M3 0.0700 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00
Lbr 0.3650 -
bh 20.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00
m2 1.1000 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,415.00
10% 1,041.50
- 11,456.00
Lembar 12.0000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00
Lembar 5.8000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00
Lembar 1.5000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00
Lembar 0.3750 -
kg 0.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00
m3 0.0150 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 154,400.00
10% 15,440.00
- 169,840.00
Lembar 0.3640 -
kg 0.1100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 3.6000 -
kg 0.1500 -
Buah 1.0500 -
Lembar 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,500.00
10% 9,650.00
- 106,150.00
m 1.0500 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 9,695.00
10% 969.50
- 10,664.00
angit-langit besi hollow 40.40
an Alumunium ( A.9.21)
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m2 1.0500 -
bh 18.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,025.00
10% 4,602.50
- 50,627.00
M' 1.0500 -
bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00
Bh 25.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,745.00
10% 2,074.50
- 22,819.00
Bh 25.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00
Bh 12.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00
Bh 5.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00
Bh 5.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00
Bh 4.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00
Lbr 0.6000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,020.00
10% 1,902.00
- 20,922.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Lbr 0.5000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,010.00
10% 2,001.00
- 22,011.00
Lbr 0.6000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,010.00
10% 2,001.00
- 22,011.00
Lbr 0.6000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.7500 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.3500 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.4200 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.4400 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.5100 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.8000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.3700 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.3800 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.4900 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 0.5700 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00
Lbr 2.4000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Lbr 2.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Lbr 2.0500 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Lbr 1.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 24,510.00
10% 2,451.00
- 26,961.00
Lbr 1.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Bh 11.0000 -
Kg 0.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00
Bh 6.9000 -
Lbr 0.3500 -
Kg 0.0300 -
Bh 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,900.00
10% 4,690.00
- 51,590.00
Bh 1.3000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 26,790.00
10% 2,679.00
- 29,469.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Bh 2.0000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 26,790.00
10% 2,679.00
- 29,469.00
Bh 30.0000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,251.00
10% 4,125.10
- 45,376.00
Bh 3.5000 -
Kg 0.0500 -
Kg 10.8000 -
M3 0.0320 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,200.00
10% 5,520.00
- 60,720.00
Bh 2.0000 -
Kg 0.0500 -
M3 0.0035 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,852.50
10% 3,785.25
- 41,637.00
Bh 1.1000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,295.00
10% 3,729.50
- 41,024.00
Lbr 0.4000 -
Kg 0.0500 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,852.50
10% 3,785.25
- 41,637.00
- -
OH 0.1200 78,500.00 9,420.00
OH 0.0600 100,000.00 6,000.00
OH 0.0060 100,000.00 600.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 16,560.00
Lbr 0.7000 -
Kg 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,560.00
10% 1,656.00
- 18,216.00
Lbr 0.3000 -
Kg 0.0400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00
Lbr 1.0500 -
Kg 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 95,315.00
10% 9,531.50
- 104,846.00
Bh 1.2000 -
Kg 0.0400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 122,350.00
10% 12,235.00
- 134,585.00
M2 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,995.00
10% 1,799.50
- 19,794.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m3 1.1000 -
Kg 1.2500 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,891,000.00
10% 289,100.00
- 3,180,100.00
m3 1.2000 -
Kg 1.2500 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,478,000.00
10% 247,800.00
- 2,725,800.00
m3 0.0400 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,595.00
10% 14,459.50
- 159,054.00
m3 0.0400 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,595.00
10% 14,459.50
- 159,054.00
m3 0.0400 -
Kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 413,000.00
10% 41,300.00
- 454,300.00
m3 0.0240 -
Kg 0.3000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00
m3 0.0640 -
Kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 413,000.00
10% 41,300.00
- 454,300.00
m3 0.0250 -
kg 0.0300 -
kg 0.5000 -
Lembar 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 289,100.00
10% 28,910.00
- 318,010.00
m3 0.0256 -
kg 0.0300 -
kg 0.5000 -
Lembar 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00
m3 0.06 -
kg 0.15 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 302,745.00
10% 30,274.50
- 333,019.00
m3 0.025 -
kg 0.03 -
kg 0.3 -
Lembar 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00
m3 0.025 -
kg 0.03 -
kg 0.8 -
Lembar 1.000 -
Lembar 0.5 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 351,095.00
10% 35,109.50
- 386,204.00
m3 1.100 -
kg 15.000 -
kg 5.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 1,652,000.00
10% 165,200.00
- 1,817,200.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m3 1.200 -
kg 15.000 -
kg 5.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,767,100.00
10% 276,710.00
- 3,043,810.00
m3 1.100 -
kg 15.000 -
kg 3.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 32,886,950.00
10% 3,288,695.00
- 36,175,645.00
m3 0.014 -
m3 0.036 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00
m3 0.014 -
m3 0.057 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00
m3 0.014 -
m3 0.057 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00
m3 0.0154 -
kg 0.2 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 51,525.00
10% 5,152.50
- 56,677.00
m3 0.0163 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 49,600.00
10% 4,960.00
- 54,560.00
m3 0.0108 -
kg 0.1 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,300.00
10% 3,030.00
- 33,330.00
m3 0.011 -
kg 0.05 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,300.00
10% 3,030.00
- 33,330.00
m3 0.028 -
kg 0.15 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,995.00
10% 6,199.50
- 68,194.00
m3 0.028 -
kg 0.15 -
Lembar 0.86 -
kg 0.56 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,995.00
10% 6,199.50
- 68,194.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m3 0.028 -
kg 0.15 -
Lembar 0.86 -
kg 0.56 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 82,600.00
10% 8,260.00
- 90,860.00
m3 0.007 -
kg 0.100 -
kg 0.150 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 247,800.00
10% 24,780.00
- 272,580.00
m3 0.400 -
kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,352.50
10% 1,035.25
- 11,387.00
m2 1.500 -
m3 0.014 -
kg 0.012 -
m3 0.003 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 70,980.00
10% 7,098.00
- 78,078.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 56,235.00
10% 5,623.50
- 61,858.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,662.50
10% 5,566.25
- 61,228.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,662.50
10% 5,566.25
- 61,228.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,749.50
10% 1,774.95
- 19,524.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,830.00
10% 1,183.00
- 13,013.00
- -
OH 0.100 78,500.00 7,850.00
OH 0.200 100,000.00 20,000.00
OH 0.020 100,000.00 2,000.00
OH 0.001 90,000.00 45.00
JUMLAH TENAGA KERJA 29,895.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,895.00
10% 2,989.50
- 32,884.00
- -
OH 0.015 78,500.00 1,177.50
OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 18,397.50
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00
set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 59,195.00
10% 5,919.50
- 65,114.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,660.00
10% 2,366.00
- 26,026.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 59,195.00
10% 5,919.50
- 65,114.00
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,235.00
10% 1,223.50
- 13,458.00
Set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 70,980.00
10% 7,098.00
- 78,078.00
Set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,579.50
10% 2,957.95
- 32,537.00
m2 1.100 -
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,749.50
10% 1,774.95
- 19,524.00
m2 1.100 -
Kg 0.070 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,115.50
10% 2,011.55
- 22,127.00
m2 1.100 -
Kg 0.070 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,579.50
10% 2,957.95
- 32,537.00
m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00
m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,844.50
10% 2,084.45
- 22,928.00
m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00
m2 1.100 -
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 22,747.50
10% 2,274.75
- 25,022.00
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,045.00
10% 1,204.50
- 13,249.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,045.00
10% 1,204.50
- 13,249.00
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,495.00
10% 1,249.50
- 13,744.00
Kg 0.200 -
Kg 0.150 -
Kg 0.170 -
Kg 0.260 -
Bh 0.010 -
Kg 0.030 -
Lbr 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,265.00
10% 726.50
- 7,991.00
Kg 0.200 -
Kg 0.150 -
Kg 0.170 -
Kg 0.350 -
Bh 0.010 -
Kg 0.030 -
Lbr 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,665.00
10% 1,666.50
- 18,331.00
L 0.360 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,010.00
10% 1,601.00
- 17,611.00
L 0.150 -
L 0.372 -
Lbr 2.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,010.00
10% 1,101.00
- 12,111.00
L 0.350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,390.00
10% 839.00
- 9,229.00
L 0.150 -
Kg 0.050 -
Lbr 0.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,430.00
10% 3,043.00
- 33,473.00
Kg 0.150 -
Lbr 0.100 -
Ikat 0.250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,110.00
10% 1,211.00
- 13,321.00
Kg 0.300 -
Lbr 0.200 -
Ikat 0.250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 3,915.00
10% 391.50
- 4,306.00
m2 1.200 -
Kg 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,795.00
10% 2,379.50
- 26,174.00
Kg 0.100 -
Bh 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,795.00
10% 2,379.50
- 26,174.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Kg 0.100 -
L 0.010 -
Bh 0.010 -
m3 0.002 333,300.00 666.60
JUMLAH HARGA BAHAN 666.60
- -
JUMLAH HARGA ALAT -
- 45,716.60
10% 4,571.66
- 50,288.00
Kg 0.100 -
Kg 0.100 -
Kg 0.080 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 47,242.00
10% 4,724.20
- 51,966.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Kg 0.300 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,180.00
10% 1,218.00
- 13,398.00
Kg 0.110 -
Kg 0.170 -
Kg 0.080 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 121,200.00
10% 12,120.00
- 133,320.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
Kg 0.300 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 110,200.00
10% 11,020.00
- 121,220.00
Kg 0.300 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 110,200.00
10% 11,020.00
- 121,220.00
Unit 1.000 -
% 0.060 - -
JUMLAH HARGA BAHAN - -
- -
JUMLAH HARGA ALAT -
- 384,450.00
10% 38,445.00
- 422,895.00
Unit 1.000 -
Kg 6.000 -
M3 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 257,900.00
10% 25,790.00
- 283,690.00
Unit 1.000 -
Kg 6.000 -
M3 0.010 -
% 30.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 193,000.00
10% 19,300.00
- 212,300.00
Unit 1.200 -
Kg 6.000 -
M3 0.010 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 259,600.00
10% 25,960.00
- 285,560.00
Unit 1.000 -
% 20.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 88,657.50
10% 8,865.75
- 97,523.00
Unit 1.000 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 771,500.00
10% 77,150.00
- 848,650.00
M3 150.000 -
Kg 120.000 -
M3 0.300 -
bh 360.000 -
Kg 6.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 803,700.00
10% 80,370.00
- 884,070.00
Unit 1.000 -
% 0.120 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 771,500.00
10% 77,150.00
- 848,650.00
Unit 1.000 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 74,400.00
10% 7,440.00
- 81,840.00
Unit 1.000 -
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 36,705.00
10% 3,670.50
- 40,375.00
Unit 1.000 -
Bh 1.000 -
Kg 20.000 -
M3 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,175.00
10% 6,117.50
- 67,292.00
Unit 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,235.00
10% 1,223.50
- 13,458.00
bh 40.000 -
Kg 44.000 -
M3 0.070 -
M3 0.060 -
M3 0.070 -
Kg 1.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 249,750.00
10% 24,975.00
- 274,725.00
bh 70.000 -
Kg 77.000 -
M3 0.130 -
M3 0.090 -
M3 0.020 -
Kg 2.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 368,740.00
10% 36,874.00
- 405,614.00
bh 123.000 -
Kg 114.000 -
M3 0.184 -
M3 0.120 -
M3 0.033 -
Kg 4.850 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 368,740.00
10% 36,874.00
- 405,614.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,569.00
10% 1,656.90
- 18,225.00
M 1.000 -
Buah 0.025 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 45,235.00
10% 4,523.50
- 49,758.00
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,569.00
10% 1,656.90
- 18,225.00
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Bh 1.600 -
Kg 35.000 -
M3 0.014 -
M3 0.014 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,040.00
10% 1,104.00
- 12,144.00
Bh 1.600 -
Kg 0.680 -
M3 0.013 -
M3 0.011 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Bh 1.100 -
M3 0.027 -
Kg 3.920 -
M3 0.056 -
M3 0.024 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Bh 1.100 -
M3 0.550 -
Kg 10.300 -
M3 0.061 -
M3 0.069 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.006 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
da A.8.4.1 ini adalah seperti yang tercantum pada tabel.
digunakan, harus disesuaikan dengan spesifi -
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.008 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.012 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.024 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.034 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.040 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.080 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.122 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.145 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.250 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.262 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.294 -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
- -
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.327 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.359 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.065 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.152 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.200 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.251 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.307 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.573 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.883 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 1.093 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 1.205 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 1.584 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.058 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.058 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.000 -
JUMLAH HARGA BAHAN -
hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
M 1.000 -
JUMLAH HARGA BAHAN -
hari 0.050 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.071 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.023 -
hari 0.031 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.029 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.034 -
hari 0.045 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.058 -
hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.084 -
hari 0.225 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.093 -
hari 0.248 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.112 -
hari 0.298 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.152 -
hari 0.304 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.180 -
hari 0.360 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.027 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.026 -
hari 0.037 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.029 -
hari 0.045 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.027 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.046 -
hari 0.098 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.052 -
hari 0.115 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.058 -
hari 0.133 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.064 -
hari 0.150 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.070 -
hari 0.167 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.017 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.030 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.037 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.054 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.069 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.160 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.168 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.191 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.213 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.236 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.005 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.006 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.009 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.017 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.023 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0300 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0550 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0700 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1790 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2700 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3320 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3650 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.4770 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.0170 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0170 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0340 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0340 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0030 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0180 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0540 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0730 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0790 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1580 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1760 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1920 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1920 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3810 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.4410 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5060 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5760 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0370 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0400 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0420 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0450 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0600 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0720 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1050 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1070 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1070 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.1130 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1660 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1830 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2180 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2360 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.4000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.6000 -
hari 0.3000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.7500 -
hari 0.7500 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0280 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0290 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0390 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.6000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.1930 -
hari 0.0960 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2250 -
hari 0.1130 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.2570 -
hari 0.1290 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3210 -
hari 0.1610 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3660 -
hari 0.1830 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3860 -
hari 0.1930 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.4500 -
hari 0.2250 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.6060 -
hari 0.0750 -
hari 0.9680 -
hari 0.8650 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
hari 0.6500 -
hari 0.1590 -
hari 1.0780 -
hari 0.9110 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.7600 -
hari 0.3690 -
hari 1.3530 -
hari 1.0260 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.8700 -
hari 0.5790 -
hari 1.6280 -
hari 1.1410 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.9800 -
hari 0.7890 -
hari 1.9030 -
hari 1.2560 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0900 -
hari 0.9990 -
hari 2.1780 -
hari 1.3710 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.3100 -
hari 1.4190 -
hari 2.7280 -
hari 1.6010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.4200 -
hari 1.6290 -
hari 3.0030 -
hari 1.7160 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.5300 -
hari 1.8390 -
hari 3.2780 -
hari 1.8310 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.7500 -
hari 2.2590 -
hari 3.8280 -
hari 2.0610 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.9700 -
hari 2.6790 -
hari 4.3780 -
hari 2.2910 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 2.1900 -
hari 3.0990 -
hari 4.9280 -
hari 2.5210 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.0020 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.0040 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
m3 0.0080 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.0180 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.0490 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.0710 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.1260 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.1580 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
m3 0.2830 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
% 1.0000 - -
JUMLAH TENAGA KERJA -
btg 0.2830 -
m 24.0000 -
bh 3.0000 -
bh 4.0000 -
bh 3.0000 -
bh 24.0000 -
bh 1.0000 -
bh 1.0000 -
bh 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- -
10% -
- -
OH 0.1500 -
OH 0.1500 -
OH 0.0300 -
OH 0.0300 -
JUMLAH TENAGA KERJA -
M' 11.00 -
M' 11.00 -
bh 1.00 -
bh 2.00 -
bh 3.00 -
bh 6.00 -
bh 2.00 -
bh 0.25 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
-
10% -
-
DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN
HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN
(Rp)
1 Pekerja Hari Rp 80,000.00
2 Tukang Hari Rp 100,000.00
3 Tukang Batu/ Besi Hari Rp 120,000.00
4 Keapal Tukang Bati / Besi Hari Rp 150,000.00
5 Tukang Kayu/ Cat Hari Rp 120,000.00
6 Kepala Tukang Kayu/ Cat Hari Rp 150,000.00
7 Mandor Hari Rp 180,000.00
8 Pekerja Galian Tanah Hari Rp 120,000.00
HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN
(Rp)
1 2 3 4
1 Air Ltr Rp 1,200.00
2 Asbes Gelombang Lembar Rp 77,500.00
3 Batu Bata Buah Rp 700.00
4 Baut Beton/ Hiltybolt Buah Rp 5,000.00
5 Batu Pecah Uk 2-3 cm m3 Rp 450,000.00
6 Batu Kali / Batu Belah / Batu Gunung m3 Rp 275,000.00
7 Besi Beton Polos Kg Rp 18,000.00
8 Besi Beton Ulir Kg Rp 23,000.00
9 Reng Baja Ringan 40.45 Btg Rp 65,000.00
10 Baja Ringan Kanai C 100 Btg Rp 160,000.00
11 Besi Profil Kg Rp 15,000.00
12 Closet Duduk Unit Rp 4,000,000.00
13 Closet Jongkok Unit Rp 425,000.00
14 Wastafel + Kaca Cermin Terpasang Unit Rp 2,000,000.00
15 Floor Drain Stainless Unit Rp 70,000.00
16 Kran Air Stainless 1/4 '' atau 1/2 '' Unit Rp 110,000.00
17 Seal Tape bh Rp 3,000.00
18 Kawat Beton Kg Rp 30,000.00
19 Semen @ 40 kg Zak Rp 74,000.00
20 Semen / kg Kg Rp 1,850.00
21 Semen Putih @ 50 kg Zak Rp 150,000.00
22 Semen Warna / kg kKg Rp 3,000.00
23 Pasir Pasang m3 Rp 200,000.00
24 Pasir Urung m3 Rp 175,000.00
25 Pasir Beton m3 Rp 230,000.00
26 Pasir Beton m3 Rp 210,000.00
27 Kerikil Beton m3 Rp 175,000.00
28 Pasir Beton Kg Rp 150.00
29 Kerikil Beton Kg Rp 12,962.00
30 Kayu Kelas I ( Seumantok, ulin ) m3 Rp 6,000,000.00
31 Kayu Kelas II ( Kamper , Kruing ) m3 Rp 4,300,000.00
32 Kayu Balok Kelas III ( Borneo ) m3 Rp 3,300,000.00
33 Kayu Kasoi 5/7 untuk Bouwplank Kelas III m3 Rp 3,300,000.00
34 Papan Kayu Bouwplank 3/20 Klas IV m3 Rp 2,800,000.00
35 Dolken Kayu Ø 10 Cm Batang Rp 22,000.00
36 Multiplexs 9 mm Lbr Rp 150,000.00
37 Multiplexs 4 mm Lbr Rp 120,000.00
38 Seng Plat B jls 30 M2 Rp 130,000.00
39 Granit ukuran 30 x 30 cm Buah Rp 25,000.00
40 Granit Ukuran 40 x 40 cm Buah Rp 35,000.00
41 Keramik Uk 40 x 40 cm Buah Rp 25,000.00
42 Keramik Uk 30 c 20 cm Buah Rp 20,000.00
43 Keramik Uk 20 x 30 cm Buah Rp 17,000.00
44 Keramik 10 x 30 cm Buah Rp 15,000.00
45 Keramik 11 x x11 cm Buah Rp 2,500.00
46 Plamir Tembok Kg Rp 20,000.00
47 Dempul Kayu Kg Rp 30,000.00
48 Cat Dasar Kg Rp 90,000.00
49 Cat Menie Kg Rp 60,000.00
50 Cat Menie Besi Kg Rp 50,000.00
51 Cat Kayu / Cat Minyak Kg Rp 80,000.00
52 Cat Tembok Kg Rp 120,000.00
53 Paku Kayu 2''- 5'' Kg Rp 22,000.00
54 Paku Genteng Metal Kg Rp 28,000.00
55 Paku 8 Inchi Kg Rp 30,000.00
56 Paku Seng Kg Rp 27,000.00
57 Paku Asbes Kg Rp 21,000.00
58 Minyak Cat Kg Rp 55,000.00
59 Minyak Bekesting Liter Rp 16,000.00
60 Kertas Amplas Lembar Rp 7,000.00
61 Residu Liter Rp 10,000.00
62 Kuas Cat 4'' Buah Rp 25,000.00
63 Lem Kayu Kg Rp 70,000.00
64 Seal Tape Buah Rp 3,000.00
65 Pipa PVC Ø 1'' Batang Rp 115,000.00
66 Pipa PVC Ø 1/2'' Batang Rp 55,000.00
67 Pipa PVC Ø 3/4'' Batang Rp 90,000.00
68 Pipa Galvanis Ø 1,5 ''tebal 3,2 mm Batang Rp 320,000.00
69 Pipa Galvanis Ø 2'' tebal 3,2 mm Batang Rp 450,000.00
70 Pipa Galvanis Ø 3'' tebal 3,2 mm Batang Rp 500,000.00
71 Tanah Timbun M3 Rp 80,000.00
72 Penjaga Jarak Bekisting Bh Rp 5,000.00
73 Gypsum ( 120 x 240 ) tebal 9 mm Lembar Rp 102,000.00
74 GRC Board , t = 4 mm Lembar Rp 85,000.00
75 Plafond PVC Uk, 20 x 4000 cm, Tebal 8 mm Lembar Rp 105,000.00
76 Paku Skrup Kg Rp 25,000.00
77 Atap Genteng Metal 0,4 M2 Rp 180,000.00
78 Atap Spandek 0,35 mm M2 Rp 100,000.00
79 Nok Genteng Metal M' Rp 65,000.00
80 Seng Gelombang BJLS 30 Cat Pabrik M2 Rp 99,000.00
81 Seng Plat B jls 30 M2 Rp 135,000.00
82 Sealant Tube Rp 60,000.00
83 Solar Liter Rp 14,000.00
84 Talang Jurai M' Rp 45,000.00
85 Minyak Pelumas / Oli Liter Rp 55,000.00
86 Metal Furing 40 mm M' Rp 4,000.00
87 Atap Spandek 0,35 mm M2 Rp 100,000.00
88 Nok Genteng Metal M' Rp 65,000.00
89 Seng Gelombang BJLS 30 Cat Prabrik M2 Rp 99,000.00
90 Seng Plat Bjls 30 M2 Rp 135,000.00
91 Sealant Tube Rp 60,000.00
92 Solar Liter Rp 14,000.00
93 Talang Jurai M' Rp 45,000.00
94 Minyak Pelumas / Oli Liter Rp 55,000.00
95 Metal Furing 40 mm M' Rp 4,000.00
96 Kawat Las Listrik Kg Rp 45,000.00
97 Profil Aluminium M' Rp 435,000.00
98 List Profil Gypsum M' Rp 7,000.00
99 List Profil PVC M' Rp 25,000.00
100 Paku Beton Kg Rp 28,000.00
101 Skrup Fixer Buah Rp 900.00
102 Baut Dinaboll Buah Rp 5,000.00
103 Kaca Bening 3 mm M2 Rp 90,000.00
104 Kaca Bening 5 mm M2 Rp 110,000.00
105 Kaca Rayben 5 mm M2 Rp 235,000.00
106 Kaca Timpered 5 mm M2 Rp 40,000.00
107 Pipa Stainless Steel Ø 2 mm M' Rp 102,000.00
108 Pipa Stainless Stell Ø 3 mm M' Rp 160,000.00
109 Pipa Stailess Stell Ø 3/4 mm M' Rp 30,000.00
110 Baut Skrup Baja Ringan Dus Rp 200,000.00
111 Daun Pintu Panel Kayu Jati Buah Rp 4,500,000.00
112 Steel Grating M2 Rp 9,750,000.00
113 Baja Ringan IWF 200x 100 x5,5 X 88mm Kg Rp 9,000.00
114 Besi Hollow Uk 100x 50 x 2,5 mm M' Rp 130,000.00
115 Besi Hollow Uk. 40 x 40 x 2 mm M' Rp 65,000.00
116 Besi Hollow Uk 30 x 340 x 2 mm M' Rp 28,000.00
117 List Stainless Batang Rp 67,000.00
118 Besi Siku 40 x 40 x 4 mm M' Rp 25,000.00
119 Besi Siku 40 x 40 x 5 mm M' Rp 30,000.00
120 PVC Board 18 mm M2 Rp 300,000.00
121 Besi Strip Tebal 15 cm Kg Rp 8,000.00
Catatan : Bila Bahan yang tidak tercantum dalam tabel ini boleh ditambah sendiri.