BACK UP DATA VOLUME PEKERJAAN

NO PERHITUNGAN VOLUME SATUAN

A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan
Lebar = 5 m (3+1+1)
Panjang = 8 m (6+1+1)
Luas = (PxL)
= 40.00 M²

2 Pemasangan Bouwplank
Lebar = 5 m (3+1+1)
Panjang = 8 m (6+1+1)
Keliling = 2 (P + L )
= 26.00 M¹
B PEKERJAAN TANAH DAN PONDASI
3 Galian Pondasi Menerus
Vertikal = 12 m
Horizontal = 6 m
18 m 18 m

Tinggi = 0.80 m
Lebar = 0.80 m
Panjang = 18.00 m
Volume = (PxLxT) 11.52 M³

a Urugan Tanah Kembali


Volume = 1/4 x Volume Galian Menerus
= 1/4 x11.52 2.88 M³

b Pasir Alas
Tinggi = 0.05 m
Lebar = 0.80 m
Panjang = 18.00 m
Volume = (PxLxT) 0.72 M³

4 Pas. Batu Gunung


Tinggi = 0.70 m
Lebar a = 0.28 m
Lebar b = 0.60 m
Panjang = 18.00 m
Volume = (( a + b )/2 x P x T )
= (( 0,28 + 0,60)/2 x 18,0 x 0,70) 5.54 M³
PEKERJAAN LANTAI 1
C Pekerjaan Beton Bertulang
1 Pondasi Tapak 1
a A (Tapak 1 )
Tinggi = 0.25 m
Lebar = 1.8 m
Panjang = 1.8 m
Jumlah = 12 Unit
Volume = ( P x L x T ) x Unit 9.72 M³

b B ( Stick Tapak 1 )
Tinggi = 1.55 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 12 Unit
Volume = ( P x L x T ) x Unit 2.976 M³
Volume Total Pondasi Tapak Tipe 1
= (A+B) 12.70 M³

2 Pondasi Tapak 2
a A ( Tapak 2 )
Tinggi = 0.25 m
Lebar = 1.2 m
Panjang = 1.2 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit 2.16 M³

b B ( Stick Tapak 2 )
Tinggi = 1.55 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit 1.488 M³
Volume Total Pondasi Tapak Tipe 1
= (A+B) 3.65 M³

3.a Sloof SL1 (25/50)


Tinggi = 0.50 m
Lebar = 0.25 m
Panjang = 18.00 m
Volume = (PxLxT) 2.25 M³

b Sloof SL2 (20/30)


Tinggi = 0.30 m
Lebar = 0.22 m
Panjang = 37.20 m
Volume = (PxLxT) 2.46 M³
4.a Balok BL1 (25/50)
Tinggi = 0.50 m
Lebar = 0.25 m
Panjang = 16.20 m
Volume = (PxLxT) 2.03 M³

b Balok BL2 (20/35)


Tinggi = 0.35 m
Lebar = 0.20 m
Panjang = 44.40 m
Volume = (PxLxT) 3.11 M³

c Balok BL3 (30/60)


Tinggi = 0.35 m
Lebar = 0.20 m
Panjang = 21.00 m
Volume = (PxLxT) 1.47 M³

5.a Kolom K1 (40/40) Lantai 1


Tinggi = 3.50 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 19 Unit
Volume = ( P x L x T ) x Unit 10.64 M³

b Kolom Kp (13/13) Lantai 1


Tinggi = 3.50 m
Lebar = 0.13 m
Panjang = 0.13 m
Jumlah = 12 Unit
Volume = ( P x L x T ) x Unit 0.7098 M³

D Pekerjan Dinding lantai 1


1 Dinding Bata 1:4
Panjang dinding = 18.00 m
k1 x unit = 7.60 m
kp x unit = 1.56 m
Panjang dinding-(k1 x unit)-(kp x unit) 8.84 M

Panjang = 8.84 m
Tinggi = 3.50 m
PxT 30.94 M²
a Pintu P1
Panjang = 2.24 m
Lebar = 1.88 m
Jumlah = 1.00 unit
= PxLxU 4.21 M²
b Pintu P3
Panjang = 2.15 m
Lebar = 0.90 m
Jumlah = 5.00 unit
= PxLxU 9.68 M²
c Pintu P4
Panjang = 2.15 m
Lebar = 0.80 m
Jumlah = 1.00 unit
= PxLxU 1.72 M²
d Ventilasi BV1
Panjang = 0.98 m
Lebar = 0.60 m
Jumlah = 6.00 unit
PxLxU 3.528 M²
e Ventilasi BV2
Panjang = 1.92 m
Lebar = 0.60 m
Jumlah = 1.00 unit
PxLxU 1.152 M²

f Jendela J1
Panjang = 1.66 m
Lebar = 1.14 m
Jumlah = 9.00 unit
PxLxU 17.03 M²

Luas Dinding Bata 1:4 -6.38 M²


2 Plasteran Dinding Bata 2 x Luas Dinding 1:4 -12.76 M²

E PEKERJAAN TIMBUNAN DAN LANTAI 1


1 Timbunan Tanah
Ruang Kamar ( + 0.00 )
Tinggi = 1.00 m
Lebar = 5.78 m
Panjang = 5.78 m
Jumlah = 5.00 unit
Luas = (PxLxTxU) 167.04 M³

Ruang Koridor ( + 0.00 )


Tinggi = 1.00 m
Lebar = 2.18 m
Panjang = 20.78 m
Luas = (PxLxT) 45.30 M³
Ruang Selasar ( + 0.00 )
Tinggi = 1.00 m
Lebar = 2.78 m
Panjang = 8.78 m
Luas = (PxLxT) 24.41 M³
Total Keseluruhan 236.75 M³

2 Lapisan Pasir Urug


Ruang Kamar ( + 0.00 )
Tinggi = 0.10 m
Lebar = 5.78 m
Panjang = 5.78 m
Jumlah = 5.00 unit
Luas = (PxLxTxU) 16.70 M³

Ruang Koridor ( + 0.00 )


Tinggi = 0.10 m
Lebar = 2.18 m
Panjang = 20.78 m
Luas = (PxLxT) 4.53 M³

Ruang Selasar ( + 0.00 )


Tinggi = 0.10 m
Lebar = 2.78 m
Panjang = 8.78 m
Luas = (PxLxT) 2.44 M³
Total Keseluruhan 23.68 M³

3 Beton Cor
Ruang Kamar ( + 0.00 )
Tinggi = 0.12 m
Lebar = 5.85 m
Panjang = 5.85 m
Jumlah = 5.00 unit
Luas = (PxLxTxU) 20.53 M³

Ruang Koridor ( + 0.00 )


Tinggi = 0.12 m
Lebar = 2.25 m
Panjang = 20.85 m
Luas = (PxLxT) 5.63 M³

Ruang Selasar ( + 0.00 )


Tinggi = 0.12 m
Lebar = 2.85 m
Panjang = 8.85 m
Luas = (PxLxT) 3.03
Total Keseluruhan 29.19 M³
4 Pemasangan Keramik Lantai 1
Ruang Kamar ( + 0.00 )
Lebar = 5.85 m
Panjang = 5.85 m
Jumlah = 5 unit
Luas = (PxL xU) 171.11 M²

Ruang Koridor ( + 0.00 )


Lebar = 2.25 m
Panjang = 20.85 m
Luas = (PxL) 46.91 M²

Ruang Selasar ( + 0.00 )


Lebar = 2.85 m
Panjang = 8.85 m
Luas = (PxL) 25.22 M²

Total Keseluruhan 243.25 M²

F PEKERJAAN KUSEN DAN DAUN PINTU LANTAI 1


1 Pintu Aluminium (P1)
Kusen = 6.36 m
Jumlah = 1.00 unit
Volume = 6.36 m

Pintu P1 = 1.00 unit

2 Pintu Aluminium (P3)


Kusen = 5.20 m
Jumlah = 5.00 unit
Volume = 26.00 m

Pintu P3 = 5.00 unit

3 Pintu Aluminium (P4)


Kusen = 5.10 m
Jumlah = 1.00 unit
Volume = 5.10 m

Pintu P4 = 1.00 unit

4 Jendela Aluminium (J1)


Kusen = 9.90 m
Jumlah = 9.00 unit
Volume = 89.10 m

Jendela 1 = 9.00 unit


5 Ventilasi Aluminium (BV1)
Kusen = 3.00 m
Jumlah = 6.00 unit
Volume = 18.00 m

Ventilasi 1 = 6.00 unit

6 Ventilasi Aluminium (BV2)


Kusen = 4.88 m
Jumlah = 1.00 unit
Volume = 4.88 m

Ventilasi 1 = 1.00 1.00 unit

G PEKERJAAN PLAFOND LANTAI 1


1 Plafond Lantai 1
Volume Plafond = Volume Keramik 243.25 M²

2 Pegecatan Plafond 243.25 M²

H PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


1 Penghubung Daya 33.000 VA 1.00 Titik
2 Instalasi Titik Penerangan 32.00 Titik
3 Instalasi Stopkontak 17.00 Titik
4 Panel MDV 33.000 VA 1.00 Titik
5 Saklar Seri isi 1 4.00 buah
6 Saklar Seri isi 2 3.00 buah
7 Stopkontak 17.00 buah
8 Lampu TL 16.00 buah
9 Lampu Philips10w 16.00 buah

I PEKERJAAN PENGECATAN DINDING


Volume -12.76 M²

J PEKERJAN SANITASI
1 Pemasangan Pipa PVC AW 3/4 Air Bersih 35.58 M
2 Pemasangan Pipa PVC AW 4" Air Kotor 4.95 M
3 Pemasangan Kran air 5.00 Unit
4 Septicktank+Resapan+Box Kontrol 1.00 Unit
5 kloset jongkok 2.00 Unit
6 Pemasangan Floor Drain 13.00 Unit
7 Pemasangan Bak Mandi Viber 10.00 Unit
8 Wastafel 2.00 Unit
9 Pipa Buangan Air Hujan 10.00 M
10 Kloset duduk 1.00 Unit
PEKERJAAN LANTAI 2
A Pekerjaan Beton Bertulang
1 Kolom K1 (40/40) Lantai 2
Tinggi = 3.50 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 19 Unit
Volume = ( P x L x T ) x Unit 10.64 M³

2 Kolom Kp (13/13) Lantai 2


Tinggi = 3.50 m
Lebar = 0.13 m
Panjang = 0.13 m
Jumlah = 12 Unit
Volume = ( P x L x T ) x Unit 0.7098 M³

3 Ring Balok RB1 (25/40)


Tinggi = 0.40 m
Lebar = 0.25 m
Panjang = 128.4 m
Volume = (PxLxT) 12.84 M³

4 Ring Balok RB2 (20/30)


Tinggi = 0.30 m
Lebar = 0.20 m
Panjang = 4.8 m
Volume = (PxLxT) 0.29 M³

5 Ring Balok RB1 (13/15)


Tinggi = 0.15 m
Lebar = 0.13 m
Panjang = 8.00 m
Volume = (PxLxT) 0.16 M³

6 Plat Lantai
Luasan A
Tinggi = 0.12 m
Lebar = 5.75 m
Panjang = 17.50 m
Unit = 1.00
Volume = (PxLxT)xU 12.08 M³

Luasan B
Tinggi = 0.12 m
Lebar = 8.15 m
Panjang = 11.61 m
Unit = 1.00
Volume = (PxLxT)xU 11.35 M³
Luasan C
Tinggi = 0.12 m
Lebar = 5.27 m
Panjang = 8.50 m
Unit = 1.00
Volume = (PxLxT)xU 5.38 M³

Total Keseluruhan Plat Lantai 28.80 M³

B PEKERJAAN DINDING Lantai 2


1 Dinding Bata 1:4
Panjang = 8.84 m
Tinggi = 3.50 m
PxT 30.94 M²
2 Pintu P3
Panjang = 2.15 m
Lebar = 0.90 m
Jumlah = 5.00 unit
= PxLxU 9.68 M²
3 Pintu P4
Panjang = 2.15 m
Lebar = 0.80 m
Jumlah = 1.00 unit
= PxLxU 1.72 M²
4 Ventilasi BV1
Panjang = 0.98 m
Lebar = 0.60 m
Jumlah = 5.00 unit
PxLxU 2.94 M²
5 Ventilasi BV2
Panjang = 1.92 m
Lebar = 0.60 m
Jumlah = 1.00 unit
PxLxU 1.152 M²
6 Jendela J1
Panjang = 1.66 m
Lebar = 1.14 m
Jumlah = 6.00 unit
PxLxU 11.35 M²

Luas Dinding Bata 1:4 4.10 M²


Plasteran Dinding Bata 2 x Luas Dinding 1:4 8.20 M²
C Pemasangan Keramik Lantai 2
Ruang Kamar ( + 4.00 )
Lebar = 5.85 m
Panjang = 5.85 m
Jumlah = 5 unit
Luas = (PxL xU) 171.11 M²

Ruang Koridor ( + 4.00 )


Lebar = 2.25 m
Panjang = 20.85 m
Luas = (PxL) 46.91 M²

Ruang Selasar ( +40.00 )


Lebar = 2.85 m
Panjang = 8.85 m
Luas = (PxL) 25.22 M²

Total Keseluruhan 243.25 M²

D PEKERJAAN KUSEN DAN DAUN PINTU


1 Pintu Aluminium (P3)
Kusen = 5.20 m
Jumlah = 5.00 unit
Volume = 26.00 m

Pintu P3 = 5.00 unit

Pintu Aluminium (P4)


Kusen = 5.10 m
Jumlah = 1.00 unit
Volume = 5.10 m

Pintu P4 = 1.00 unit

2 Jendela Aluminium (J1)


Kusen = 9.90 m
Jumlah = 6.00 unit
Volume = 59.40 m

Jendela 1 = 6.00 unit

3 Ventilasi Aluminium (BV1)


Kusen = 3.00 m
Jumlah = 5.00 unit
Volume = 15.00 m

Ventilasi 1 = 5.00 unit


4 Ventilasi Aluminium (BV2)
Kusen = 4.88 m
Jumlah = 1.00 unit
Volume = 24.40 m

Ventilasi 1 = 5.00 unit

E PEKERJAAN PLAFOND
Plafond Lantai 2
Volume Plafond = Volume Keramik 243.25 M2

Pegecatan Plafond 243.25 M2

F PEKERJAAN ATAP
RANGKA BAJA RINGAN
PANJANG = 8.13
LEBAR = 5.13
PXL 41.71 M2

ATAP SENG
PANJANG = 8.13
LEBAR = 5.13
PXL 41.71 M2

RABUNG
PANJANG 8.13 8.13 M'

LISTPLANK
PANJANG = 8.13
LEBAR = 5.13
2(PXL) 83.41 M2

G PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


1 Penghubung Daya 33.000 VA 1.00 Titik
2 Instalasi Titik Penerangan 32.00 Titik
3 Instalasi Stopkontak 17.00 Titik
4 Panel MDV 33.000 VA 1.00 Titik
5 Saklar Seri isi 1 4.00 buah
6 Saklar Seri isi 2 3.00 buah
7 Stopkontak 17.00 buah
8 Lampu TL 16.00 buah
9 Lampu Philips10w 16.00 buah
H PEKERJAAN PENGECATAN DINDING
Volume 8.20 M²

I PEKERJAN SANITASI
1 Pemasangan Pipa PVC AW 3/4 Air Bersih 35.58 M
2 Pemasangan Pipa PVC AW 4" Air Kotor 4.95 M
3 Pemasangan Kran air 5.00 Unit
4 Septicktank+Resapan+Box Kontrol 1.00 Unit
5 kloset jongkok 2.00 Unit
6 Pemasangan Floor Drain 13.00 Unit
7 Pemasangan Bak Mandi Viber 10.00 Unit
8 Wastafel 2.00 Unit
9 Pipa Buangan Air Hujan 10.00 M
10 Kloset duduk 1.00 Unit
PONDASI TAPAK

Tinggi Tapak = 1.80 m


Lebar Tapak = 1.8 m
Panjang Tapak = 1.8 m
Jarak tulangan = 0.1 m
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Selimut Beton = 0.05 m
Unit = 12.00 m
Panjang Kait = 0.1 m

Panjang Besi = (Lebar x 2)+(Tinggi x 2)-(Selimut) = 7.1


Jumlah Batang 1.8 / 0.1 + 1 = 19

Panjang Besi = (Panjang x 2)+(Tinggi x 2)-(Selimut) = 7.1


Jumlah Batang = 1.8 / 0.1 + 1 = 19

Jumlah Besi = 38 x 12.00 = 456


Berat Besi = 14.2 x 38 x 1.58 = 852.568
= 852.568 x 12.00 = 10231

Bekisting = (Lebar x 2)+(Panjangg x 2)x Tinggi = 10.08


= 10.08 x 12.00 = 120.96
SLOOF 30/40

Panjang Sloof = 18.00 m


Lebar Sloof = 0.3 m Lebar - selimut = 0.2
Tinggi Sloof = 0.4 m Tinggi - selimut = 0.3
Banyak Besi Pokok (bk) = 5 btg
Banyak Besi Pinggang (bp) = 4 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Besi D13 = 1.04 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 1 m
Panjang Kait = 0.1 m

Luas Tulangan = 0.2 x 0.3 = 0.06


Panjang Tulangan = 18 x 5 = 90
Jumlah Batang 90 / 12 = 7.5 = 127
Berat Besi Tulangan 90 x 1.58 = 142.2

Luas Tulangan = 0.2 x 0.3 = 0.06


Panjang Tulangan = 18 x 4 = 72
Jumlah Batang 72 / 12 = 6 = 32
Berat Besi Tulangan 72 x 1.04 = 74.88

Panjang 1 Begel pokok = 0.2 x 2 + 0.3 x 2


= 1 + 0.1 = 1.1
Panjang Batang = 18 x 1.1 = 19.8
Jumlah Btaang = 19.8 / 12 = 1.65 = 23
Berat Besi Tulangan = 19.8 x 0.62 = 12.276

Bekisting = 18 x 0.4 x 2 = 14.4

Kolom K1 (40/40) Lantai 1

Tinggi Kolom = 3.50 m


Lebar Kolom = 0.40 m Lebar - selimut = 0.3
Panjang Kolom = 0.40 m Panjang - selimut = 0.3
Banyak Besi Pokok (bk) = 8 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.8 m
Panjang Kait = 0.1 m
Unit = 19 unit

Panjang Tulangan = 8 x 3.5 x 19 = 532


Jumlah Batang 532 / 12 = 44.33 = 140
Berat Besi Tulangan 532 x 1.58 = 840.56

Panjang 1 Begel pokok = 0.3 x 2 + 0.3 x 2


= 1.2 + 0.1 = 1.3
Panjang Batang = 3.5 x 1.3 x 19 = 86.45
Jumlah Btaang = 86.45 / 12 = 7.204 = 17
Berat Besi Tulangan = 86.45 x 0.62 = 53.599

Bekisting = (2 x P) + (2 x L) x T x U = 54

Kolom Kp (13/13) Lantai 1

Tinggi Kolom = 3.50 m


Lebar Kolom = 0.13 m Lebar - selimut = 0.03
Panjang Kolom = 0.13 m Panjang - selimut = 0.03
Banyak Besi Pokok (bk) = 6 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi Ø12 = 0.89 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.7 m
Panjang Kait = 0.1 m
Unit = 12 unit

Panjang Tulangan = 6 x 3.5 x 12 = 252


Jumlah Batang 252 / 12 = 21 = 5
Berat Besi Tulangan 252 x 0.89 = 224.28

Panjang 1 Begel pokok = 0.0 x 2 + 0.03 x 2


= 0.12 + 0.1 = 0.22
Panjang Batang = 3.5 x 0.22 x 12 = 9.24
Jumlah Btaang = 9.24 / 12 = 0.77 = 1
Berat Besi Tulangan = 9.24 x 0.62 = 5.7288

Bekisting = (2 x P) + (2 x L) x T x U = 11.18

Anak Tangga = 12 cm

Bidang X = #NAME? M
Bidang Y = #NAME? M
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm
Jarak Tulangan = 0.15 M
Unit = 20.00

1. Untuk Bidang 1.40 Meter


Panjang Besi (Pjb) = #NAME? M
Jumlah Baris Besi (Jb) = #NAME? M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat Besi = Pjg*Jb*Jl*0.006162*d*d


= #NAME? Kg

2. Untuk Bidang 2.80 Meter


Panjang Besi (Pjb) = #NAME? M
Jumlah Baris Besi (Jb) = #NAME? M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm

#REF! = Pjg*Jb*Jl*0.006162*d*d
= #NAME? Kg
Total Berat Besi = #NAME? Kg

Berat Besi Untuk 1 m3 = #NAME? Kg / M3 Beton

Luas Bekisting Untuk 1 = #NAME? M2 / M3 Beton

PERHITUNGAN 1. Untuk Bidang 1.00 Meter


4 Plat Tangga = 12 cm P =
J =
Bidang X = #NAME? M J =
Bidang Y = #NAME? M D =
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm B =
Jarak Tulangan = 0.15 M =

2. Untuk Bidang 6.49 Meter


P =
J =
J =
D =

B =
=

To =

B =

L =

PERHITUNGAN 1. Untuk Bidang 1.30 Meter


5 Plat bordes = 12 cm P =
J =
Bidang X = #NAME? M J =
Bidang Y = #NAME? M D =
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm B =
Jarak Tulangan = 0.15 M =
2. Untuk Bidang 2.00 Meter
P =
J =
J =
D =

B =
=

To =

B =

L =

PERHITUNGAN Panjang balok untuk 1 m3


1 Balok Bordes ( #NAME? x #NAME? ) M =
=
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m3 bet
Ø Tul. Pokok = 10.00 mm 1. Tu =
Jumlah Tul. Pinggang = - Batang B =
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 8.00 mm 2. Tu =
Jarak Begel = 0.100 M B =
Luas Permukaan Papan = #NAME? M2
3. Tulangan Begel Besi Ø 8,
P =
B =
=

B =
=

4. Pa =
=

To =
P =

Kolom K1 (40/40) Lantai 2

Panjang Balok = 0.40 m


Lebar Balok = 0.40 m Lebar - selimut = 0.3
Tinggi Balok = 3.50 m Tinggi - selimut = 3.4
Banyak Besi Pokok (bk) = 9 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.7 m
Panjang Kait = 0.1 m

Luas Tulangan = 0.3 x 3.4 = 1.02


Panjang Tulangan = 0.4 x 9 = 3.6
Jumlah Batang 3.6 / 12 = 0.3 = 20
Berat Besi Tulangan 3.6 x 1.58 = 5.688

Panjang 1 Begel pokok = 0.3 x 0.7 + 3.4 x 0.7


= 2.59 + 0.1 = 2.69
Panjang Batang = 0.4 x 2.69 = 1.076
Jumlah Btaang = 1.076 / 12 = 0.09 = 3
Berat Besi Tulangan = 1.076 x 0.62 = 0.66712

Bekisting = 0.4 x 3.50 x 2 = 2.8


Bekisting = 0.4 x 0.40 x 1 = 0.16

Kolom Kp (13/13) Lantai 2

Panjang Balok = 0.13 m


Lebar Balok = 0.13 m Lebar - selimut = 0.03
Tinggi Balok = 3.50 m Tinggi - selimut = 3.4
Banyak Besi Pokok (bk) = 9 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.9 m
Panjang Kait = 0.1 m
Luas Tulangan = 0.03 x 3.4 = 0.102
Panjang Tulangan = 0.13 x 9 = 1.17
Jumlah Batang 1.17 / 12 = 0.097 = 20
Berat Besi Tulangan 1.17 x 1.58 = 1.8486

Panjang 1 Begel pokok = 0.03 x 0.9 + 3.4 x 0.9


= 3.087 + 0.1 = 3.187
Panjang Batang = 0.13 x 3.187 = 0.41431
Jumlah Btaang = 0.41431 / 12 = 0.035 = 3
Berat Besi Tulangan = 0.41431 x 0.62 = 0.25687

Bekisting = 0.13 x 3.50 x 2 = 0.91


Bekisting = 0.13 x 0.13 x 1 = 0.0169

Ring Balok RB1 (25/40)

Panjang Balok = 128.40 m


Lebar Balok = 0.25 m Lebar - selimut = 0.15
Tinggi Balok = 0.40 m Tinggi - selimut = 0.3
Banyak Besi Pokok (bk) = 4 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi Ø12 = 0.88 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 1 m
Panjang Kait = 0.1 m

Luas Tulangan = 0.15 x 0.3 = 0.045


Panjang Tulangan = 128.4 x 4 = 513.6
Jumlah Batang 513.6 / 12 = 42.8 = 44
Berat Besi Tulangan 513.6 x 0.88 = 451.968

Panjang 1 Begel pokok = 0.15 x 1 + 0.3 x 1


= 0.45 + 0.1 = 0.55
Panjang Batang = 128.4 x 0.55 = 70.62
Jumlah Btaang = 70.62 / 12 = 5.885 = 4
Berat Besi Tulangan = 70.62 x 0.62 = 43.7844

Bekisting = 128.4 x 0.4 x 2 = 102.72

Dia.Berat Jenis PANJAN


No. URAIAN PEKERJAAN
(mm) (Kg/m) a
Luasan A
Sumbu X 10.00 0.62 0.06
Sumbu Y 10.00 0.62 0.06

PEMBESIAN
Luasan B
Sumbu X 10.00 0.62 0.06
PEMBESIAN
Sumbu Y 10.00 0.62 0.06

Luasan C
Sumbu X 10.00 0.62 0.06
Sumbu Y 10.00 0.62 0.06

PANJANG
LEBAR TINGGI
No. URAIAN PEKERJAAN
(M) (M) T1

BEKISTING PLAT LANTAI A


17.50 5.75

BEKISTING BEKISTING PLAT LANTAI B


11.61 8.15

BEKISTING PLAT LANTAI C


8.50 5.27
TOTAL

#NAME?

Tinggi Kolom = #NAME? m


Lebar Kolom = #NAME? m Lebar - selimut = ###
Panjang Kolom = #NAME? m Panjang - selimut = ###
Banyak Besi Pokok (bk) = 8 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi D16 = 1.58 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.8 m
Panjang Kait = 0.1 m
Unit = #NAME? unit

Panjang Tulangan = 8 x #NAME? x ### = ###


Jumlah Batang #NAME? / 12 = ### = 140
Berat Besi Tulangan #NAME? x 1.58 = ###

Panjang 1 Begel pokok = #NAME? x 2 + ### x 2


= #NAME? + 0.1 = ###
Panjang Batang = #NAME? x #NAME? x ### = ###
Jumlah Btaang = #NAME? / 12 = ### = 17
Berat Besi Tulangan = #NAME? x 0.62 = ###

Bekisting = (2 x P) + (2 x L) x T x U = ###

#NAME?

Tinggi Kolom = #NAME? m


Lebar Kolom = #NAME? m Lebar - selimut = ###
Panjang Kolom = #NAME? m Panjang - selimut = ###
Banyak Besi Pokok (bk) = 6 btg
Panjang 1 Batang Besi (p1) = 12 m
Besi Ø12 = 0.89 kg/m
Berat Besi Ø10 = 0.62 kg/m
Panjang 1 begel pokok (b1) = 0.7 m
Panjang Kait = 0.1 m
Unit = #NAME? unit

Panjang Tulangan = 6 x #NAME? x ### = ###


Jumlah Batang #NAME? / 12 = ### = 5
Berat Besi Tulangan #NAME? x 0.89 = ###

Panjang 1 Begel pokok = #NAME? x 2 + ### x 2


= #NAME? + 0.1 = ###
Panjang Batang = #NAME? x #NAME? x ### = ###
Jumlah Btaang = #NAME? / 12 = ### = 1
Berat Besi Tulangan = #NAME? x 0.62 = ###

Bekisting = (2 x P) + (2 x L) x T x U = ###
2

m2
btg

m2
btg

btg
Kg/m
Kg/m

m2
m2

m2
m
btg
Kg/m

m2
m
btg
Kg/m

m
m
btg
Kg/m

m2

3.75

m
btg
Kg/m

m
m
btg
Kg/m

m2
m
btg
Kg/m

m
m
btg
Kg/m

m2
Untuk Bidang 1.00 Meter
#NAME? M
#NAME? M
2.00 Lapis
10.00 mm

Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg

Untuk Bidang 6.49 Meter


#NAME? M
#NAME? M
2.00 Lapis
10.00 mm

Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg

#NAME? Kg

### Kg / M3 Beton

### M2 / M3 Beton

Untuk Bidang 1.30 Meter


#NAME? M
#NAME? M
2.00 Lapis
10.00 mm

Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg
Untuk Bidang 2.00 Meter
#NAME? M
#NAME? M
2.00 Lapis
10.00 mm

Pjg*Jb*Jl*0.006162*d*d
#NAME? Kg

#NAME? Kg

### Kg / M3 Beton

### M2 / M3 Beton

njang balok untuk 1 m3


1/( b x h)
#NAME? m'
embesian untuk 1 m beton adalah
3

Pjg balok x byk tul x 0.006165 x dia.2


#NAME? kg

Pjg balok x byk tul x 0.006165 x dia.2


#NAME? kg

ulangan Begel Besi Ø 8,


#NAME? m'
Pjg balok untuk 1 m3 beton/jarak begel
#NAME? ± -------> ### Btg
#NAME? btg

Byk begel x Pjg begel x 0.006165 x dia.2


#NAME? kg

Pjg balok untuk 1 m3 beton x luas permukaan papan


#NAME? m2 -------> 50%

### Kg
### M2

m2
m
btg
Kg/m

m
m
btg
Kg/m

m2
m2
m2
m
btg
Kg/m

m
m
btg
Kg/m

m2
m2

m2
m
btg
Kg/m

m
m
btg
Kg/m

m2

PANJANG Jumlah Pot. UNIT Tot. Panjang


VOL. SAT.
b c P Tot. (Btg) Bh/n (m)

5.75 0.06 5.87 28.75 2.00 337.53 832.39 5.75


17.50 0.06 17.62 87.50 2.00 3,083.50 7,604.37 17.50
8.15 0.06 8.27 40.75 2.00 674.01 831.10
11.61 0.06 11.73 58.05 2.00 1,361.85 1,679.27 8.15
11.61

5.27 0.06 5.39 26.35 2.00 284.05 284.05


8.50 0.06 8.62 42.50 2.00 732.70 732.70 5.27
Kg 8.50

JUMLAH TOTAL 11,963.88 Kg

TINGGI
VOL
T2

402.5

189.243

44.795
OTAL 636.538

3.75

m
btg
Kg/m

m
m
btg
Kg/m

m2

m
btg
Kg/m

m
m
btg
Kg/m

m2
28.75
87.5
40.75
58.05
0.2

26.35
42.5
REKAPITULASI
ENGINEER ESTIMATE (EE)

PEMBANGUNAN MAKO LANUDAL


GAMPOENG COT BA'U
SABANG

NO URAIAN PEKERJAAN
I PEKERJAAN PERSIAPAN
II LANTAI 1

A PEKERJAAN TANAH DAN PONDASI


B PEKERJAAN BETON BERTULANG
C PEKERJAAN PASANGAN DAN PLESTERAN
D PEKERJAAN PENUTUP LANTAI & DINDING
F PEKERJAAN TANGGA
G PEKERJAAN PINTU, JENDELA DAN KUNCI
H PEKERJAAN INSTALASI LISTRIK
I PEKERJAAN PLAFOND
J PEKERJAAN PENGECATAN
III LANTAI 2
A PEKERJAAN BETON BERTULANG
B PEKERJAAN PASANGAN DAN PLESTERAN
C PEKERJAAN LANTAI
D PEKERJAAN PINTU, JENDELA DAN KUNCI
E PEKERJAAN ATAP DAN PLAFOND
F PEKERJAAN INSTALASI LISTRIK
G PEKERJAAN PENGECATAN
JUMLAH
PPN 10%
JUMLAH TOTAL + PPN 10%
DIBULATKAN
TERBILANG : Delapan Ratus Juta Rupiah
EE)

DAL

JUMLAH HARGA
Rp 9,075,449.00

#NAME?
Rp 202,235,162.16
Rp 4,654,860.55
#NAME?
#NAME?
#NAME?
Rp 1,000,000.00
#NAME?
Rp 72,698

#NAME?
Rp -
Rp -
#NAME?
#NAME?
Rp 10,290,000.00
Rp -
#NAME?
#NAME?
#NAME?
Rp 800,000,000.00
a Rupiah

Banda Aceh , Juli 2023


Uus
NIM __________
ENGINEER ESTIMATE (EE)

PEMBANGUNAN GEDUNG ASRAMA KELAS BARU DAY

Pekerjaan Lantai 1

NO. URAIAN PEKERJAAN VOLUME SAT.

1 2 3 4
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 40.00 M2
2 Pengukuran / Pemasangan Bouplank 89.00 M1
3 Administrasi dan Dokumentasi 1.00 Ls
4 K3 dan Lain-lain 1.00 Ls
5 Papan Nama Proyek 1.00 Ls

B PEKERJAAN TANAH DAN PONDASI


1 Galian Tanah Pondasi Tapak 1 93.60 M3
Urugan Kembali Galian Pondasi Tapak 17.20 M3
Lantai Kerja 1.18 M3

2 Galian Pondasi Menerus 11.52 M3


Urugan Tanah Kembali 2.88 M3
Urugan Pasir 0.72 M3
Pas. Batu Kosong / Aanstamping #NAME? M3
Pas. Pondasi Batu Gunung 5.54 M3

C PEKERJAAN BETON BERTULANG


1 Pondasi Tapak 1
Beton K-250 12.70 M3
Besi Tulangan Pokok Ø16 10230.82 kg
Bekisting + Perawatan Beton 120.96 M2

2 Sloof SL1 (25/50)


Beton K-250 2.25 M3
Besi Tulangan Pokok Ø16 142.2 kg
Tulangan Pinggang Ø13 74.88 kg
Besi Tulangan Sengkang Ø10 - 10 cm 12.28 kg
Bekisting + Perawatan Beton 14.40 M2

3 Kolom K1 (40/40) Lantai 1


Beton K-250 10.64 M3
Besi Tulangan Pokok Ø16 840.56 kg
Besi Tulangan Sengkang Ø10 - 10 cm 53.60 kg
Bekisting + Perawatan Beton 54.00 M2

4 Kolom Kp (13/13) Lantai 1


Beton K-250 0.7098 M3
Besi Tulangan Pokok Ø12 224.28 kg
Besi Tulangan Sengkang Ø10 - 10 cm 5.73 kg
Bekisting + Perawatan Beton 11.18 M2

D. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasangan Trasram Bata 1 PC : 2 PP LT 1 16.1168 M2
2 Plesteran 1 PC : 2 PP LT 1 32.2336 M2
3 Pasangan Trasram Bata 1 PC : 4 PP LT 1 -6.3778 M2
4 Plesteran 1 PC : 4 PP LT 1 -12.7556 M2

E PEKERJAAN PENUTUP LANTAI & DINDING


1 Timbunan Tanah 236.75 M3
2 Lapisan Pasir Urug 23.68 M3
3 Beton Cor #NAME? M3
4 Keramik Lantai 1 40x40 243.25 M2

F PEKERJAAN TANGGA
1 Plat Tangga
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2

2 Anak Tangga
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2

3 Plat Bordes
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø10 #NAME? kg
Bekisting + Perawatan Beton #NAME? M2

G PEKERJAAN PINTU, JENDELA DAN KUNCI


1 Pintu
Kusen Pintu Utama (UPVC) 14.720 M
Daun Pintu PJ #NAME? M2
Kunci Pintu (Standar) #NAME? Buah
Engsel Pintu #NAME? Buah

2 Jendela
Kusen Jendela J1 #NAME? M
Daun Jendela J1 #NAME? M2
- Hak Angin / Gagang Jendela 16.00 Buah
- Engsel Jendela #NAME? Buah
- Pacok Jendela #NAME? Buah

3 Ventilasi
Kusen Ventilasi V1 2.56 M
Daun Ventilasi 0.31 M2

H PEKERJAAN INSTALASI LISTRIK


1 Zekering Kast Lokal 6 Group + Box Panel Elektrikal 1.00 Unit
2 Saklar Seri isi 1 0 Bh
3 Saklar Tunggal 0 Bh
4 Stop Kontak 0 Bh

I PEKERJAAN PLAFOND
1 Pemasangan Plafond PVC + Rangka dan List #NAME? M2

J PEKERJAAN PENGECATAN
3 Cat Dinding Luar Dan Dalam ( Dulux ) 2.00 M2

Pekerjaan Lantai 2
A PEKERJAAN BETON BERTULANG
1 Kolom K1 (40/40) Lantai 2
Beton K-250 10.64 M3
Besi Tulangan Pokok Ø16 5.69 kg
Besi Tulangan Sengkang Ø10 - 10 cm 0.67 kg
Bekisting + Perawatan Beton 2.96 M2

2 Kolom Kp (13/13) Lantai 2


Beton K-250 0.71 M3
Besi Tulangan Pokok Ø16 1.85 kg
Besi Tulangan Sengkang Ø10 - 10 cm 0.26 kg
Bekisting + Perawatan Beton 0.02 M2

3 Ring Balok RB1 (25/40)


Beton K-250 12.84 M3
Besi Tulangan Pokok Ø12 451.97 kg
Besi Tulangan Sengkang Ø10 - 10 cm 43.78 kg
Bekisting + Perawatan Beton 102.72 M2

4 Plat Lantai
Beton K-250 28.80 M3
Besi Tulangan Pokok Ø10 11963.88 kg
Bekisting + Perawatan Beton 636.54 M2

5 #NAME?
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø16 #NAME? Kg
Besi Tulangan Sengkang Ø10 - 10 cm #NAME? Kg
Bekisting + Perawatan Beton #NAME? M2

6 #NAME?
Beton K-250 #NAME? M3
Besi Tulangan Pokok Ø16 #NAME? Kg
Besi Tulangan Sengkang Ø10 - 10 cm #NAME? Kg
Bekisting + Perawatan Beton #NAME? M2

B PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasangan Dinding Bata 1 PC : 2 PP LT 2 #NAME? M2
2 Plesteran Dinding Bata 1 PC : 2 PP LT 2 #NAME? M2
3 Pasangan Dinding Bata 1 PC : 4 PP LT 2 0.00 M2
4 Plesteran Dinding Bata 1 PC : 4 PP LT 2 0.00 M2
C PEKERJAAN LANTAI
1 Keramik Lantai 2 40x40 0.00 M2

D PEKERJAAN PINTU, JENDELA DAN KUNCI


1 Pintu
Kusen Pintu Utama (UPVC) 14.720 M
Daun Pintu PJ #NAME? M2
Kunci Pintu (Standar) #NAME? Buah
Engsel Pintu #NAME? Buah

2 Jendela
Kusen Jendela J1 #NAME? M
Daun Jendela J1 #NAME? M2
- Hak Angin / Gagang Jendela 16.00 Buah
- Engsel Jendela #NAME? Buah
- Pacok Jendela #NAME? Buah

3 Ventilasi
Kusen Ventilasi V1 2.56 M
Daun Ventilasi 0.31 M2

E PEKERJAAN ATAP DAN PLAFOND


1 Pekerjaan Atap Baja Ringan #NAME? M2
2 Pemasangan Plafond PVC + Rangka dan List #NAME? M2

F PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan Lightning Protection 1.00 Ls
2 Saklar Seri isi 1 0 Bh
3 Saklar Tunggal 3 Bh
4 Stop Kontak 2 Bh

G PEKERJAAN PENGECATAN
1 Cat Dinding Luar Dan Dalam 0.00 M2
R ESTIMATE (EE)

KELAS BARU DAYAH DARUL MUSTARIK

HARGA SATUAN JUMLAH HARGA


ANALISA
(RP) SATUAN (RP)

5 6 7

AHSP PU A.2.2.1.9. Rp 18,700.00 Rp 748,000.00


AHSP PU A.2.2.1.4. Rp 54,241.00 Rp 4,827,449.00
Taksir Rp 1,000,000.00 Rp 1,000,000.00
Taksir Rp 2,000,000.00 Rp 2,000,000.00
Taksir Rp 500,000.00 Rp 500,000.00
Sub Jumlah Rp 9,075,449.00

AHSP PU A.2.3.1.3. Rp 105,666.00 Rp 9,890,337.60


AHSP PU A.2.3.1.9. Rp 26,950.00 Rp 463,513.05
AHSP PU A.4.1.1.4 Rp 930,847.00 Rp 1,094,676.07

AHSP PU A.2.3.1.1. Rp 70,950.00 Rp 817,344.00


AHSP PU A.2.3.1.9. Rp 26,950.00 Rp 77,616.00
AHSP PU A.2.3.1.11. Rp 930,847.00 Rp 670,209.84
AHSP PU A.3.2.1.9. Rp 412,902.00 #NAME?
AHSP PU A.3.2.1.2. Rp 745,049 Rp 4,130,551.66
Sub Jumlah #NAME?

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 15,366,273.50


AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 110,646,275.04
AHSP PU A.4.1.1.20 Rp 76,094.33 Rp 9,204,370.16

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 2,723,229.00


AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 1,537,893.00
AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 809,827.20
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 118,586.16
AHSP PU A.4.1.1.21 Rp 244,783.00 Rp 3,524,875.20

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 12,877,847.36


AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 9,090,656.40
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 517,766.34
AHSP - PU - A.4.1.1.22 Rp 502,249.00 Rp 27,121,446.00

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 859,087.98


AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 2,166,544.80
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 55,340.21
AHSP - PU - A.4.1.1.22 Rp 502,249.00 Rp 5,615,143.82
Sub Jumlah Rp 202,235,162.16

AHSP PU A.4.4.1.1 Rp 310,255.00 Rp 5,000,317.78


AHSP PU A.4.4.2.2 Rp 71,374.00 Rp 2,300,640.97
AHSP PU A.4.4.1.3 Rp 284,146.00 Rp (1,812,226.36)
AHSP PU A.4.4.2.4 Rp 65,373.00 Rp (833,871.84)
Sub Jumlah Rp 4,654,860.55

AHSP PU - T.14 E Rp 143,550.00 Rp 33,985,577.34


AHSP PU A.2.3.1.11. Rp 930,847.00 Rp 22,037,877.19
AHSP PU A.2.3.1.11b. Rp 114,180.00 #NAME?
AHSP PU A.4.4.3.54a Rp 196,240.00 Rp 47,734,889.40
Sub Jumlah #NAME?

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 #NAME?


AHSP PU A.4.1.1.17 Rp 9,660.00 #NAME?
AHSP - PU - A.4.1.1.26 Rp 469,166.00 #NAME?

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 #NAME?


AHSP PU A.4.1.1.17 Rp 9,660.00 #NAME?
AHSP - PU - A.4.1.1.26 Rp 469,166.00 #NAME?
AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 #NAME?
AHSP PU A.4.1.1.17 Rp 9,660.00 #NAME?
AHSP - PU - A.4.1.1.26 Rp 469,166.00 #NAME?
Sub Jumlah #NAME?

Taksir Rp 350,000.00 Rp 5,152,000.00


AHSP. 4.6.2.17 Rp 141,453.00 #NAME?
Taksir Rp 35,000.00 #NAME?
Taksir Rp 25,000.00 #NAME?

Taksir Rp 350,000.00 #NAME?


AHSP. 4.6.2.17 Rp 141,453.00 #NAME?
Taksir Rp 40,000.00 Rp 640,000.00
Taksir Rp 20,000.00 #NAME?
Taksir Rp 15,000.00 #NAME?

Taksir Rp 350,000.00 Rp 896,000.00


AHSP. 4.6.2.17 Rp 141,453.00 Rp 43,850.43
Sub Jumlah #NAME?

Taksir Rp 1,000,000.00 Rp 1,000,000.00


Taksir Rp 100,000.00 Rp -
Taksir Rp 50,000.00 Rp -
Taksir Rp 70,000.00 Rp -
Sub Jumlah Rp 1,000,000.000

Taksir Rp 240,000.00 #NAME?


` Sub Jumlah #NAME?

AHSP PU A.4.7.1.10 Rp 36,349.00 Rp 72,698.00


Sub Jumlah Rp 72,698.00

jaan Lantai 2

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 12,877,847.36


AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 61,515.72
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 6,444.38
AHSP - PU - A.4.1.1.23 Rp 513,799.00 Rp 1,520,845.04

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 859,087.98


AHSP PU A.4.1.1.17.a Rp 10,815.00 Rp 19,992.61
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 2,481.39
AHSP - PU - A.4.1.1.23 Rp 513,799.00 Rp 8,683.20

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 15,540,560.16


AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 4,366,010.88
AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 422,957.30
AHSP - PU - A.4.1.1.23 Rp 513,799.00 Rp 52,777,433.28

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 Rp 34,863,358.61


AHSP PU A.4.1.1.17 Rp 9,660.00 Rp 115,571,085.07
AHSP - PU - A.4.1.1.24 Rp 766,249.00 Rp 487,746,605.96

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 #NAME?


AHSP PU A.4.1.1.17.a Rp 10,815.00 #NAME?
AHSP PU A.4.1.1.17 Rp 9,660.00 #NAME?
AHSP - PU - A.4.1.1.22 Rp 502,249.00 #NAME?

AHSP - PU - A.4.1.1.8. Rp 1,210,324.00 #NAME?


AHSP PU A.4.1.1.17.a Rp 10,815.00 #NAME?
AHSP PU A.4.1.1.17 Rp 9,660.00 #NAME?
AHSP - PU - A.4.1.1.22 Rp 502,249.00 #NAME?

Sub Jumlah #NAME?

AHSP PU A.4.4.1.1 Rp 310,255.00 #NAME?


AHSP PU A.4.4.2.2 Rp 71,374.00 #NAME?
AHSP PU A.4.4.1.3 Rp 284,146.00 Rp -
AHSP PU A.4.4.2.4 Rp 65,373.00 Rp -
Sub Jumlah Rp -

AHSP PU A.4.4.3.54a Rp 196,240.00 Rp -


Sub Jumlah Rp -

Taksir Rp 350,000.00 Rp 5,152,000.00


AHSP. 4.6.2.17 Rp 141,453.00 #NAME?
Taksir Rp 35,000.00 #NAME?
Taksir Rp 25,000.00 #NAME?

Taksir Rp 350,000.00 #NAME?


AHSP. 4.6.2.17 Rp 141,453.00 #NAME?
Taksir Rp 40,000.00 Rp 640,000.00
Taksir Rp 20,000.00 #NAME?
Taksir Rp 15,000.00 #NAME?

Taksir Rp 350,000.00 Rp 896,000.00


AHSP. 4.6.2.17 Rp 141,453.00 Rp 43,850.43

Sub Jumlah #NAME?

AHSP - PU - A.4.2.1.2. Rp 35,656.00 #NAME?


Taksir Rp 240,000.00 #NAME?
Sub Jumlah #NAME?

Taksir Rp 10,000,000.00 Rp 10,000,000.00


Taksir Rp 100,000.00 Rp -
Taksir Rp 50,000.00 Rp 150,000.000
Taksir Rp 70,000.00 Rp 140,000.000
Sub Jumlah Rp 10,290,000.000

AHSP PU A.4.7.1.10 Rp 36,349.00 Rp -


Sub Jumlah Rp -
Sub Total #NAME?
ANALISA HARGA SATUAN

AHSP - PU - A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


Jenis Pekerjaan : (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 m
Satuan / Unit : 1 M2
Analisa : AHSP PU A.2.2.1.1.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Pasir beton
Koral beton
Kayu 5/7
Paku biasa
Residu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 pagar sementara dari seng gelomb


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.2
No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Seng gelombang
Pasir beton
Koral beton
Kayu 5/7
Paku biasa
Meni besi

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.3.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Semen portland
Kawat duri
Pasir beton
Koral beton
Paku biasa 2” - 5”

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengukuran dan pemasangan 1 M' Bouwplank


Satuan / Unit : 1 M'
Analisa : AHSP PU A.2.2.1.4.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu balok 5/7
Paku 2”-3”
Kayu papan 3/20

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 kantor sementara lantai plesteran


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.5.
No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Tukang batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu balok 5/7
Paku biasa
Besi strip
Semen portland
Pasir pasang
Pasir beton
Koral beton
Bata merah
Seng plat
Jendela naco
Kaca polos
Kunci tanam
Plywood 4 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu )


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.6.

No. Uraian Kode


A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Seng gelombang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 gudang semen dan peralatan


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.7.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Semen portland
Pasir beton
Koral beton
Seng gelombang
Seng plat
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 bedeng pekerja


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.8.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Dolken kayu Ø 8-10/400 cm
Kayu
Paku biasa
Semen portland
Pasir beton
Koral beton
Seng gelombang
Plywood 4 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

ANALISA HARGA SATUAN


Jenis Pekerjaan : (K3) Pembersihan 1 m2 lapangan dan perataan
Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.9.

No. Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 steger/perancah dari bambu


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bambu diameter 6 - 8 / 600 cm
Tali ijuk

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 Buah Kotak Adukan Ukuran 40cm x 50cm x 2


Satuan / Unit : 1 Buah
Analisa : AHSP PU A.2.2.1.11.

No Uraian Kode

A TENAGA
Tukang Kayu L.02.04
Kepala Tukang L.03.01

B BAHAN
Kayu papan kelas III
Kayu balok 5/7 kelas III
Paku biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 jalan sementara


Satuan / Unit : 1 M2
Analisa : AHSP PU A.2.2.1.12.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Batu belah
Batu pecah
Pasir pasang
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembongkaran 1 m3 beton bertulang


Satuan / Unit : 1 M3
Analisa : AHSP PU A.2.2.1.13.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembongkaran 1 M3 Dinding Tembok Bata


Satuan / Unit : 1 M3
Analisa : AHSP PU A.2.2.1.14.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 pagar kawat jaring galvanis panjang 24


Satuan / Unit : 1M2
Analisa : AHSP - PU - A.2.2.1.15.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kawat jaring

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 panel beton pracetak 5x50x240 cm


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.2.1.16.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Panel Beton Pracetak
Kolom Benton Pracetak
Semen portland
Pasir beton
Koral

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 1 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.1.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 2 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.2.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Menggali 1 M3 tanah biasa sedalam 3 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.3.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Menggali 1 m3 tanah keras sedalam 1 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.4.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Menggali 1 m3 tanah cadas sedalam 1 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.5.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Menggali 1 m3 tanah lumpur sedalam 1 m


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.6.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.3.1.7.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuangan 1 m3 tanah sejauh 30 meter


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.8.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Jenis Pekerjaan : Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedal
Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm)


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengurugan 1 m3 dengan pasir urug


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.11.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Pasir urug

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pengurugan 1 m3 dengan Tanah Timbun Biasa
Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.11b.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Tanah Timbun

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7T


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.12.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kapur
Pasir Pasang
Tanah Liat

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang re


Satuan / Unit : 1M2
Analisa : AHSP PU A.2.3.1.13.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Ijuk

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengurugan 1 m3 sirtu padat


Satuan / Unit : 1M3
Analisa : AHSP PU A.2.3.1.14.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Sirtu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3P


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.1.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4P


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.2.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5P


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.3.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6P


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.4.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8P


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.5.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1K


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.6.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Kapur
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.7.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran ¼ SP : 1


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.8.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 batu kosong (anstamping)


Satuan / Unit : 1M3
Analisa : AHSP PU A.3.2.1.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Pasir urug

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : (K3) Pemasangan 1 m3 pondasi siklop, 60% beton campu
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.3.2.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Batu belah
Semen portland
Pasir Beton
Kerikil
Besi beton (polos/ulir)
Kawat beton

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m3 pondasi sumuran, diameter 100 cm


Satuan / Unit : 1M3
Analisa : AHSP - PU - A.3.2.1.11.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Batu belah
Semen portland
Pasir Beton
Kerikil (Maks. 30 mm)

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)


Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.1

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.2

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 12,2 MPa (K 150)


Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.3

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling fa

Jenis Pekerjaan : Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.4

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.5.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (12
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.6

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (1


Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.7.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’= 21,7 MPa (K 250), slump (12
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.8.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’ = 24,0 MPa (K 275), slump (1


Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.11.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (1
Satuan / Unit : 1M3
Analisa : AHSP - PU - A.4.1.1.12.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Air
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan penambahan bahan tambahan s

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Bahan tambahan kimia
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

CATATAN: Bobot isi pasir = 1400 kg/m3, Bobot isi kerikil = 1350 kg/m3, Buckling factor pasir = 20%

Jenis Pekerjaan : Membuat 1 m3 beton kedap air dengan strorox - 100


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.13

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Beton
Kerikil (Maks 30 mm)
Strorox - 100

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m’ PVC Waterstop lebar 150 mm


Satuan / Unit : 1 M1
Analisa : AHSP - PU - A.4.1.1.14

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Pipa L.02.13
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Waterstop lebar 150 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m’ PVC Waterstop lebar 200 mm
Satuan / Unit : 1 M1
Analisa : AHSP - PU - A.4.1.1.15

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Pipa L.02.13
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Waterstop lebar 200 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m’ PVC Waterstop lebar 230 mm - 320 mm


Satuan / Unit : 1 M1
Analisa : AHSP - PU - A.4.1.1.16

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Waterstop lebar 230 mm - 320 mm

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembesian 1 kg dengan besi polos


Satuan / Unit : 1 Kg
Analisa : AHSP PU A.4.1.1.17

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Besi beton polos
Kawat beton

C PERALATAN

D Jumlah (A+B+C)
Untuk Harga 1Kg Besi
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembesian 1 kg dengan Besi Ulir


Satuan / Unit : 1 Kg
Analisa : AHSP PU A.4.1.1.17.a

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Besi Beton Ulir
Kawat Beton

C PERALATAN

D Jumlah (A+B+C)
Untuk Harga 1Kg Besi
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 10 kg kabel presstressed polos/strands


Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.1.1.18

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Besi beton (polos/ulir)
Kawat beton

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 10 kg jaring kawat baja (wiremesh)
Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.1.1.19

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Jaring kawat baja dilas
Kawat beton

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk pondasi


Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.1.1.20

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 10 cm
Minyak bekisting

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk sloof


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.21

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 10 cm
Minyak bekisting

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 Bekisting untuk Kolom


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.22

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk balok


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.23

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk lantai


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.24

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk dinding


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.25

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm
Penjaga jarak bekisting / spacer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk tangga


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.26
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku 5 - 12 cm
Minyak bekisting
Balok kayu kelas II
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan

Jenis Pekerjaan : Pemasangan 1 m2 jembatan untuk pengecoran beton


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.1.27

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III (papan)
Paku 5 - 12 cm
Dolken kayu Ø 8-10/400 cm

Jumlah Bahan
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 M3 pondasi beton bertulang (150 kg besi + bek


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.28

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisti


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.29

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 kolom beton bertulang (300 kg besi + bekis


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.30
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 balok beton bertulang (200 kg besi + bekis


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.31

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 kolom beton bertulang (150 kg besi + bekist


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.32

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 dinding beton bertulang (150 kg besi + beki


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.33

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m3 dinding beton bertulang (200 kg besi + beki


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.1.34

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil
Kayu kelas II balok
Plywood 9 mm
Dolken kayu Ø 8-10/400 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm


Satuan / Unit : 1 M'
Analisa : AHSP - PU - A.4.1.1.35

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Membuat 1 m’ ring balok beton bertulang (10 x 15) cm


Satuan / Unit : 1 M'
Analisa : AHSP - PU - A.4.1.1.36

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang kayu L.02.04
Tukang besi L.02.05
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas III
Paku Biasa
Minyak bekisting
Besi beton (polos/ulir)
Kawat beton
Semen portland
Pasir Beton
Kerikil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Jenis Pekerjaan : (K3) Pembuatan 1 m2 lahan produksi tebal 8cm beton f’c 1
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.1.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.2.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.3.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.4.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir beton
Kerikil (Maks 30 mm)
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 bekisting untuk plat beton pracetak ( 5 ka


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.5.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Lantai kerja tebal 10cm
Besi hollow 50.50.3
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Dynabol dia 12 x 120 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 bekisting untuk balok beton pracetak ( 10


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.6.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Dynabol dia 12 x 120 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.1.2.7.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kaso 5/7
Phenol film 12mm
Minyak bekisting
Paku Biasa
Dynabol dia 12 x 120 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan dan membuka bekisting 1 buah komponen pl


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.8.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01

B BAHAN

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan dan membuka bekisting 1 buah komponen ba


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan dan membuka bekisting 1 buah komponen Ko


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Mandor L.04.01
B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Penuangan/menebar beton untuk 1 buah komponen plat p


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.11.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Penuangan/menebar beton untuk 1 buah komponen balok


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.12.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Penuangan/menebar beton untuk 1 buah komponen kolom


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.13.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Tukang vibrator L.02.14
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Ereksi 1 buah komponen untuk pelat pracetak


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.14.

No Uraian Kode

A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Solar

C PERALATAN
Sewa crane
Sewa pipe support

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk pelat pracetak

Lantai Indeks kenaikan lantai


ereksi pelat
1 1
2 1
3 1
4 1
5 1
6 1
7 1
8 1.018
9 1.037
10 1.055
11 1.075
12 1.094
13 1.114
14 1.134
15 1.155
16 1.176
17 1.197
18 1.219
19 1.241
20 1.264
21 1.287
22 1.31
23 1.334
24 1.358

Jenis Pekerjaan : Ereksi 1 buah komponen untuk balok pracetak


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.15.

No Uraian Kode

A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Solar
C PERALATAN
Sewa crane
Sewa pipe support

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk Balok pracetak

Lantai Indeks kenaikan lantai


ereksi Balok
1.000 1.000
2.000 1.000
3.000 1.000
4.000 1.000
5.000 1.000
6.000 1.000
7.000 1.000
8.000 1.011
9.000 1.022
10.000 1.034
11.000 1.045
12.000 1.057
13.000 1.068
14.000 1.080
15.000 1.092
16.000 1.104
17.000 1.116
18.000 1.129
19.000 1.141
20.000 1.154
21.000 1.166
22.000 1.179
23.000 1.192
24.000 1.206

Jenis Pekerjaan : Ereksi 1 buah komponen untuk Kolom pracetak


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.16.

No Uraian Kode

A TENAGA
Operator crane L.10.01
Pembantu operator crane L.10.02
Pekerja L.01.01
Tukang batu L.02.03
Tukang ereksi L.02.09
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Solar

C PERALATAN
Sewa crane
Sewa pipe support

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk Kolom pracetak

Lantai Indeks kenaikan lantai


ereksi Kolom
1.000 1.000
2.000 1.000
3.000 1.000
4.000 1.000
5.000 1.000
6.000 1.000
7.000 1.000
8.000 1.011
9.000 1.022
10.000 1.034
11.000 1.045
12.000 1.057
13.000 1.068
14.000 1.080
15.000 1.092
16.000 1.104
17.000 1.116
18.000 1.129
19.000 1.141
20.000 1.154
21.000 1.166
22.000 1.179
23.000 1.192
24.000 1.206

Jenis Pekerjaan : Melangsir 1 buah komponen plat pracetak ( ± 20 m)


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.17.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02

B BAHAN
Solar

C PERALATAN
Sewa crane

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Melangsir 1 buah komponen balok pracetak ( ± 20 m)


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.18.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02

B BAHAN
Solar

C PERALATAN
Sewa crane

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Melangsir 1 buah komponen kolom pracetak ( ± 20 m)


Satuan / Unit : 1 Bh
Analisa : AHSP - PU - A.4.1.2.19.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Operator crane L.10.01
Pembantu operator crane L.10.02

B BAHAN
Solar

C PERALATAN
Sewa crane
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Bahan 1 m3 grouting campuran


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.2.20.

No Uraian Kode

A TENAGA

B BAHAN
Semen grout
Screening
Air

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Bahan 1 m3 grouting tidak campuran


Satuan / Unit : 1 M3
Analisa : AHSP - PU - A.4.1.2.21.

No Uraian Kode

A TENAGA

B BAHAN
Semen grout
Air

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Upah Melakukan 1 Titik Grouting Pada Join Pracetak


Satuan / Unit : 1 Titik
Analisa : AHSP - PU - A.4.1.2.22.

No Uraian Kode

A TENAGA
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 titik Bekisting join pracetak


Satuan / Unit : 1 Titik
Analisa : AHSP - PU - A.4.1.2.23.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kaso 5/7
Kayu papan kelas III
Paku Biasa
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Upah 1 titik Join dengan Sling


Satuan / Unit : 1 Titik
Analisa : AHSP - PU - A.4.1.2.24.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Tukang besi L.02.05
Mandor L.04.01

B BAHAN

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Jenis Pekerjaan : Pemasangan 1 kg besi profil


Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.2.1.1.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las Konstruksi L.02.10
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Besi Profil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 kg rangka kuda-kuda baja IWF


Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.2.1.2.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las Konstruksi L.02.10
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Besi IWF

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengerjaan 100 kg pekerjaan perakitan


Satuan / Unit : 1 Kg
Analisa : AHSP - PU - A.4.2.1.3.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi Konstruksi L.02.06
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Solar
Minyak pelumas

C PERALATAN
Sewa alat Perakitan Baja IWF

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap,


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.4.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Besi siku L 30.30.3
Besi plat baja
Kawat las

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pengerjaan 10 cm pengelasan dengan las listrik


Satuan / Unit : 1 Cm
Analisa : AHSP - PU - A.4.2.1.5.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi Konstruksi L.02.06
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kawat las listrik
Solar
Minyak pelumas

C PERALATAN
Sewa alat Las Listrik

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pembuatan 1 m2 rangka jendela besi scuare tube (25 x 5)


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.6.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Besi scuare tube
Besi lis kaca (1 x 1) cm
Pengelasan
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 pintu rolling door besi


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.7.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pintu gulung besi

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/P


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.8.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pintu lipat

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 sunscreen alluminium


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Sunscreen alluminium

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 rolling door alluminium


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Rolling dor alluminium

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m kusen pintu alluminium


Satuan / Unit : 1M
Analisa : AHSP - PU - A.4.2.1.11.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Profil alluminium
Skrup fixer
Sealant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 pintu alluminium strip lebar 8 cm


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.12.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Profil alluminium
Aluminium strip

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 pintu kaca rangka alluminium


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.13.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Alumunium L.02.02
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pintu alluminium
Profil kaca
Sealant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Venetions Blinds dan Vertical Blinds


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.14.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Venetions blinds dan vertical blinds (tirai)

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Terali Besi Strip (2 x 3) mm


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.15.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Las L.02.11
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Besi strip
Pengelasan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Kawat Nyamuk


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.16.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kawat nyamuk
Pengelasan
Baja strip (0,2 x 2) cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Jendela Nako & Tralis


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.17.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Jendela nako (rangka + kaca 5 mm)
Paku skrup
Besi strip

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M’ Talang Datar/ Jurai Seng BJLS 28 Lebar


Satuan / Unit : 1 M'
Analisa : AHSP - PU - A.4.2.1.18.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Seng plat
Paku Biasa
Kayu Papan kelas II

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 M' Talang ½ Lingkaran D-15 cm, Seng Pla
Satuan / Unit : 1 M'
Analisa : AHSP - PU - A.4.2.1.19.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang L.02.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Seng plat
Paku Biasa
Besi strip

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Rangka Besi Hollow 1x40.40.2 mm, Mo


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.20.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Rangka metal hollow 40.40.2 mm
Assesoris (perkuatan, las dll)

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Rangka Besi Hollow 1 x 40.40.2 mm, M


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.21.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Rangka metal hollow 40.40.2 mm
Assesoris (perkuatan, las dll)

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pemasangan 1 M2 Atap Pelana Rangka Atap Baja Ca


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.22.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Baja ringan canai dingin C75

C PERALATAN
Alat Rangka Atap Baja Canai Dingin

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai d
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.23.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Baja ringan canai dingin C75

C PERALATAN
Alat Rangka Atap Baja Canai Dingin

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 M2 PASANG KUDA-KUDA BAJA RINGAN
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.2.1.24.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Baja ringan canai dingin C75
Baut (Srew driver)
Dynabol dia 12 x 120 mm
Reng Canai Dingin
Talang / Jurai Canai Dingin

C PERALATAN
Alat Rangka Atap Baja Canai Dingin

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.1.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.2.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.3.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.4.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.5.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.6.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.4.1.7

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.8.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.9.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.10.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.11.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.12.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.13.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.14.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen Merah
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.15.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Kapur
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding conblock HB20 campuran 1SP


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.16.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-20
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding conblock HB20 campuran 1SP:


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.17.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-20
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1m2 dinding conblock HB15 campuran 1SP


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.18.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-15
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 dinding conblock HB15 campuran 1SP


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.19.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-15
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 dinding conblock HB10 campuran 1SP


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.20.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-10
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 dinding conblock HB10 campuran 1SP


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.21.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
HB-10
Semen portland
Pasir Pasang
Besi angker dia 8

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Dinding Terawang (Rooster) 12 x 11 x 2


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.22.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata Rooster
Semen Portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 M2 Dinding Terawang (Rooster) 12 x 11 x 2


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.23.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata Berongga
Semen Portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 cm2 dinding bata berongga ekspose 12x11
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.24.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata Rooster
Semen Portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.25.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata ringan tebal 7,5 cm
Mortar siap pakai
C PERALATAN
Peralatan Pasang Dinding Bata Ringan

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.1.26.

No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Bata ringan tebal 7,5 cm
Mortar siap pakai

C PERALATAN
Peralatan Pasang Dinding Bata Ringan

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm.


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.1.
No Uraian Kode

A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm.


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.2.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.
Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.3.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.4.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Satuan / Unit : 1 M2
Analisa : AHSP - PU - A.4.4.2.5.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.6.
1 m2 plesteran 1SP : 6PP tebal 15 mm.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.7.
1 m2 plesteran 1SP : 7PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.8.
1 m2 plesteran 1SP : 8PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
AHSP - PU - A.4.4.2.9.
1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.10.
1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
AHSP
Pemasangan
- PU - A.4.4.2.11.
1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.12.
1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.13.
1 m2 plesteran 1SP : 1PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.14.
1 m2 plesteran 1SP : 3PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.15.
1 m2 plesteran 1SP : 4PP tebal 20 mm.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.16.
1 m2 plesteran 1SP : 5PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.17.
1 m2 plesteran 1SP : 6PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.18.
1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Kapur Pasang
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSPPemasangan
- PU - A.4.4.2.19.
1 m2 berapen 1SP : 5PP tebal 15 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.20.
1 m’ plesteran skoning 1SP : 3PP lebar 10 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.21.
1 m2 plesteran granit 1SP : 2 granit tebal 1cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Batu granit

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.22.
1 m2 plesteran traso 1SP : 2 traso tebal 1cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Batu traso

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP -Pemasangan
PU - A.4.4.2.23.
1 m2 plesteran ciprat 1SP : 2PP
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.24
1 m2 finishing siar pasangan bata merah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01
B BAHAN
Semen portland

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.25.
1 m2 finishing siar pasangan conblock ekspose
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
AHSP -1PU
m2- finishing
A.4.4.2.26.
siar pasangan batu kali, campuran 1SP : 2PP.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP - PU - A.4.4.2.27.
Pemasangan 1 m2 acian.
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen portland

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
AHSP - PU - A.4.4.2.28.
1 m2 plesteran dengan mortar siap pakai (MSP)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen mortar pasangan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

AHSP
Pemasangan
- PU - A.4.4.2.29.
1 m2 Acian dengan mortar siap pakai (MSP)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Semen mortar Acian

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LAN

Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit ukuran 60 x 60 cm (Polish


Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.4.3.54

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Granit uk. 60 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit ukuran 60 x 60 cm (Unpol
Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.4.3.54a

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Granit uk. 60 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit ukuran 30 x 60 cm (Unpol


Satuan / Unit : 1 M2
Analisa : AHSP PU A.4.4.3.54b

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Granit uk. 30 cm x 60 cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.1.
1m2 lantai ubin PC abu-abu ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin PC abu-abu ukuran 40cm x40cm
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.2.
1m2 lantai ubin PC abu-abu ukuran 30cm x30 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin PC abu-abu ukuran 30cm x30 cm
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.3.
1m2 lantai ubin PC abu-abu ukuran 20cm x20 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin PC abu-abu ukuran 20cm x20 cm
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.4.
1m2 lantai ubin warna ukuran 40cm x40 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin warna ukuran 40cm x40 cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.5.1m2 lantai ubin warna ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin warna ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.6.1m2 lantai ubin warna ukuran 20cm x20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin warna ukuran 20cm x20cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.7.1m2 lantai ubin teraso ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teraso ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.8.1m2 lantai ubin teraso ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
ubin teraso ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.9.1m2 lantai ubin granit ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin granit ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.10.
1m2 lantai ubin granit ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin granit ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.11.
1m2 lantai ubin teralux marmer ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teralux marmer ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.12.
1m2 lantai ubin teralux ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teralux ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.13.
1m2 lantai ubin teralux marmer ukuran 60cm x60cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teralux marmer ukuran 60cm x60cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.14.
1m2 lantai ubin teralux marmer ukuran 40cm x40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teralux marmer ukuran 40cm x40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.15.
1m2 lantai ubin teralux marmer ukuran 30cm x30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
ubin teralux marmer ukuran 30cm x30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.16.
1 m’ plint ubin Pc abu-abu ukuran 15cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Plint ubin Pc abu-abu ukuran 15cm x 20cm
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.17.
1 m’ plint ubin Pc abu-abu ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin Pc abu-abu ukuran 10cm x 30cm
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.18.
1 m’ plint ubin Pc abu-abu ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin Pc abu-abu ukuran 10cm x 40cm
Semen portland
Pasir pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.19.1 m’ plint ubin warna ukuran 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin warna ukuran 10cm x 20cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.20.1 m’ plint ubin warna ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin warna ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.21.1 m’ plint ubin warna ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin warna ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.22.1 m’ plint ubin teraso ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.03.01
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teraso ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.23.1 m’ plint ubin teraso ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teraso ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.24.1 m’ plint ubin granit ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin granit ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.25.1 m’ plint ubin granit ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin granit ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.26.
1 m’ plint ubin teralux kerang ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teralux kerang ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.27.
1 m’ plint ubin teralux kerang ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teralux kerang ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.28.
1 m’ plint ubin teralux marmer ukuran 10cm x 60cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
plint ubin teralux marmer ukuran 10cm x 60cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.29.
1 m’ plint ubin teralux marmer ukuran 10cm x 40cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teralux marmer ukuran 10cm x 40cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.30.
1 m’ plint ubin teralux marmer ukuran 10cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint ubin teralux marmer ukuran 10cm x 30cm
Semen portland
Semen Warna
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.31.1m2 lantai teraso cor di tempat, tebal 3cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Teraso cor di tempat, tebal 3cm
Semen warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.32.1m2 lantai keramik artistik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik artistik 10cm x 20cm
Semen portland
Pasir pasang
Semen warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.4.3.33.
1m2 lantai keramik artistik 10cm x 10cm atau 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik artistik 10cm x 10cm atau 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.34.1m2 lantai keramik ukuran 33cm x 33cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik ukuran 33cm x 33cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.35.1m2 lantai keramik ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik ukuran 30cm x 30cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.36.1m2 lantai keramik ukuran 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Keramik ukuran 20cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

keramik
A.4.4.3.37.
ukuran 10cm x 33cm untuk variasi/border
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Ubin keramik
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.38.
1m2 lantai keramik mozaik ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Keramik mozaik ukuran 30cm x 30cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.39. 1 m’ plint keramik ukuran 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint keramik ukuran 10cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.40. 1 m’ plint keramik ukuran 10cm x 10cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint keramik ukuran 10cm x 10cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.41. 1 m’ plint keramik ukuran 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint keramik ukuran 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.42.
1 m’ plint internal cove artistik 5cm x 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plint internal cove artistik 5cm x 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.43.
1 m2 lantai marmer ukuran 100cm x 100cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
marmer ukuran 100cm x 100cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.44.
Pemasangan 1 m2 lantai karpet
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
lantai karpet
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.45.1 m2 underlayer (pelapis bawah karpet)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
underlayer (pelapis bawah karpet)
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.46.
Pemasangan 1 m2 lantai parquet kayu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Parquet kayu
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.47.
Pemasangan 1 m2 lantai kayu gymfloor
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Parquet kayu gymfloor
Lem Kayu/Karet

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.48. 1 m2 dinding porslen 11cm x 11cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Porselen Dinding 11x11
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.49. 1 m2 dinding porslen 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Porselen Dinding 10x20
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.50. 1 m2 dinding porslen 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Porselen Dinding 20x20
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.51.
1 m2 dinding keramik artistik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Keramik Dinding artistik
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.52.1 m2 dinding keramik artistik 5cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik Dinding artistik 5cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.53. 1 m2 dinding keramik 10cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik Dinding 10cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.54. 1 m2 dinding keramik 20cm x 20cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
keramik Dinding 20cm x 20cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.55. 1 m2 dinding marmer 100cm x 100cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
marmer Dinding 100cm x 100cm
Semen portland
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.56.
1 m2 dinding bata pelapis 3cm x 7cm x 24cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bata pelapis Dinding 3cm x 7cm x 24cm
Semen portland
Pasir Pasang
Semen Warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.57.
Pemasangan 1 m2 dinding batu paras
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Batu paras Dinding
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.4.3.58.
Pemasangan 1 m2 dinding batu tempel hitam
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
dinding batu tempel hitam
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.59. 1 m2 lantai vynil ukuran 30cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Vynil ukuran 30cm x 30cm
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.60.
Pemasangan 1 m2 wallpaper lebar 50 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
wallpaper lebar 50 cm
Lem Putih

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.61.
Pemasangan 1m2 floor harderner
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
floor harderner

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.62.
Pemasangan 1 m’ plint vynil 15cm x 30cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
plint vynil 15cm x 30cm
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.63. 1 m’ plint kayu tebal 2 cm lebar 10 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan kelas I
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.64. 1 m2 paving block natural tebal 6 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Paving block 6 cm
Pasir beton

C PERALATAN
Peralatan Kerja Paving Blok
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.65. 1 m2 paving block natural tebal 8 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Paving block 8 cm natural
Pasir beton

C PERALATAN
Peralatan Kerja Paving Blok

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.4.3.66. 1 m2 paving block berwarna tebal 6 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Paving block 6cm berwarna
Pasir beton

C PERALATAN
Peralatan Kerja Paving Blok

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.4.3.67. 1 m2 paving block berwarna tebal 8 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Paving block 8 cm berwarna
Pasir beton

C PERALATAN
Peralatan Kerja Paving Blok

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.68.
Pemasangan 1 M2 Aluminium Composite Panel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Besi L.02.05
Kepala Tukang L.03.01
Mandor L.04.01

B BAHAN
Aluminium Composite Panel
Screw

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.1
HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
Pemasangan 1A.4.5.1.1.
m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes semen
Paku tripleks

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.1.2.
1 m2 langit-langit akustik ukuran (30 x 30) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Akustik ukuran 30 x 30 cm
Paku tripleks

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.1.3.
1 m2 langit-langit akustik ukuran (30 x 60) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Akustik ukuran 30 x 60 cm
Paku tripleks

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.1.4.
1 m2 langit-langit akustik ukuran (60 x 120) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Akustik 60 x 120
Paku tripleks

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 A.4.5.1.5.
langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Tripleks
Paku tripleks
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.1.6.
1 m2 langit-langit lambrisering kayu, tebal 9 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu papan
Paku tripleks

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2A.4.5.1.7.
langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Gypsum board 9 mm (1200 x 2400 mm)
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 langit-langit
A.4.5.1.8. akustik ukuran (60 x 120) cm berikut rangka alluminium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Profil Allum"T"
Kawat dia 4 mm
Ramset
Akustik 60 x 120

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.1.9.
Pemasangan 1 m’ list langit-langit kayu profil
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
List kayu profil
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.5.1.10 Pemasangan 1 m2 Rangka langit-langit besi hollow 40.40
Lihat pada kelompok Pekerjaan Besi dan Alumunium ( A.9.21)
A.4.5.1.10. Pemasangan 1 m2 Plafond PVC
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plafond PVC (setara Shunda Plafon, Flat Gloss Half
Screw

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.1.10. Pemasangan 1 m2 Plafond PVC


No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
List PVC (setara Shunda Plafon,LS 301-1 Min.Silver
Screw

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.HARGA SATUAN PEKERJAAN PENUTUP ATAP


Pemasangan
A.4.5.2.1. 1 m2 atap genteng palentong kecil
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng palentong

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.2. 1 m2 atap genteng kodok glazuur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng kodok

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.3.1 m2 atap genteng palentong besar/super
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng kodok
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.4.
Pemasangan 1 m’ bubung genteng palentong
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng bubung
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.5. 1 m’ bubung genteng kodok glazuur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng bubung
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.6. 1 m’ bubung genteng palentong besar
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng bubung
Semen portland
Pasir Pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.7. 1 m2 roof light fibreglass 90x180
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Rooflight 90x180
Paku biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.8.
1 m2 atap asbes gelombang 0,92mx2,5m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.9.
1 m2 atap asbes gelombang 0,92mx2,25m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.10.
1 m2 atap asbes gelombang 0,92mx2,00m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.11.
1 m2 atap asbes gelombang 0,92mx1.80m x 5mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.12.
1 m2 atap asbes gelombang 1.05mx3.00m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.13.
1 m2 atap asbes gelombang 1.05mx2.70m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.14.
1 m2 atap asbes gelombang 1.05mx2.40m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.15.
1 m2 atap asbes gelombang 1.05mx2.10m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.16.
1 m2 atap asbes gelombang 1.05mx1.50m x 4mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.17.
1 m2 atap asbes gelombang 1.08mx3.00m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.18.
1 m2 atap asbes gelombang 1.08mx2.70m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.19.
1 m2 atap asbes gelombang 1.08mx2.40m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.20.
1 m2 atap asbes gelombang 1.08mx2.10m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.21.
1 m2 atap asbes gelombang 1.08mx1.80m x 6mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Asbes gelombang 92x250
Paku pancing 6x23

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.22. 1 m’ bubung stel gelombang 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bubung stel gel.
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.23. 1 m’ bubung stel gelombang 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bubung stel gel.
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.24. 1 m’ bubung stel gelombang 1,08m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bubung stel gel.
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.25.
Pemasangan 1 m’ nok paten 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok paten 92cm
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.26.
Pemasangan 1 m’ nok paten 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok paten 92cm
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.27.
Pemasangan 1 m’ nok paten 1,08m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok paten 92cm
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.28.
Pemasangan 1 m’ nok stel rata 0,92m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok paten 92cm
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.29.
Pemasangan 1 m’ nok stel rata 1,05m
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok paten 92cm
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.30.
Pemasangan 1 m2 genteng beton
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng beton
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.31.
Pemasangan 1 m2 genteng aspal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng aspal
Plywood 6 mm
Paku biasa
Plastic aerator

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.5.2.32.
1 m2 genteng metal ukuran 80 x 100 atap pelana
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng metal
Paku biasa ½”-1”

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.5.2.33.
1 m2 genteng metal ukuran 80 x 100 atap Jurai
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Genteng metal
Paku biasa ½”-1”

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.34.
Pemasangan 1 m2 atap sirap kayu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Sirap kayu
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.35.
Pemasangan 1 m’ nok genteng beton
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok genteng beton
Paku Biasa
Semen portland
Pasir Pasang
Semen warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.36.
Pemasangan 1 m’ nok genteng aspal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok genteng aspal
Paku Biasa
Kayu balok borneo

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.37.
Pemasangan 1 m’ nok genteng metal
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok genteng metal
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.38.Pemasangan 1 m’ nok sirap


No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Seng plat
Paku Biasa
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.39.
Pemasangan 1 m2 atap seng gelombang
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Seng gelombang
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.40.
Pemasangan 1 m’nok atap seng
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Seng plat
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.41.
Pemasangan 1 m2 atap alumunium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Alumunium gel tbl 0,55
Paku hak panj 15cm
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.42.
Pemasangan 1 m’ nok alumunium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Nok standar 40x18
Paku hak panj 15cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

A.4.5.2.43.
Pemasangan 1 m2 alumunium foil/sisalation
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang Kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Alumunium foil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
Pembuatan dan A.4.6.1.1.
pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Paku Biasa
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan pemasangan


A.4.6.1.2.1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Paku Biasa
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

PembuatanA.4.6.1.3.
dan pemasangan 1 m2 pintu klamp standar, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan
A.4.6.1.4.
pemasangan 1 m2 pintu klamp sederhana, kayu kelas III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan
A.4.6.1.5.
pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
kayu Papan
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan A.4.6.1.6.


pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pembuatan danA.4.6.1.7.
pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Lem Kayu/Karet
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2
A.4.6.1.8.
daun pintu plywood rangkap, rangka kayu kelas II tertutup
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Paku Biasa
Lem Kayu/Karet
Plywood 4 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2
A.4.6.1.9.
pintu plywood rangkap, rangka expose kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
kayu Papan
Paku Biasa
Lem Kayu/Karet
Plywood 4 mm

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.10. 1 m2 jalusi kusen, kayu kelas I atau II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.11.
1 m2 teakwood rangkap, rangka expose kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa
Lem Kayu/Karet
Teakwood 4 mm 90 x 220 cm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2
A.4.6.1.12.
teakwood rangkap lapis formika, rangka expose kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa
Lem Kayu/Karet
Teakwood 4 mm 90 x 220 cm
Formika

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m3 konstruksi
A.4.6.1.13.
kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Besi strip
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.4.6.1.14.
1 m3 konstruksi kuda-kuda expose, kayu kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Besi strip
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.15. 1 m3 konstruksi gordeng, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Besi strip
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.16.
1 m2 rangka atap genteng keramik, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu 5/7
Reng 2 x 3 cm
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.17.
1 m2 rangka atap genteng beton, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu 5/7
Reng (3 x 4) cm
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.18. 1 m2 rangka atap sirap, kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu kelas II
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1A.4.6.1.19.
m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu 5/7
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1A.4.6.1.20.
m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu 5/7
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

PemasanganA.4.6.1.21.
1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

PemasanganA.4.6.1.22.
1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 A.4.6.1.23.
m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1A.4.6.1.24.
m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu, 6 x 12
Paku Biasa
Teakwood 4 mm, 120 x 240
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PemasanganA.4.6.1.25.
1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Balok kayu, 6 x 12
Paku Biasa
Plywood 4 mm
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.26.
1 m2 dinding lambrisering dari Kayu Papan kelas I
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kayu Papan
Paku Biasa
Paku skrup

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1A.4.6.1.27.
m2 dinding lambrisering dari plywood ukuran (120 x 240) cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plywood 4 mm
Paku Biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.1.28.
1 m2 dinding bilik, rangka kayu kelas III atau IV
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bilik bambu
Kayu 5/7
Paku Biasa
List kayu 2/4

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2HARGA SATUAN PEKERJAAN KUNCI DAN KACA


A.4.6.2.1.
Pemasangan 1 buah kunci tanam antik
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci tanam antik

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.2.
Pemasangan 1 buah kunci tanam biasa
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci tanam biasa

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.3.
Pemasangan 1 buah kunci kamar mandi
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci tanam KM
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.4.
Pemasangan 1 buah kunci silinder
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci silinder

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.5.
Pemasangan 1 buah engsel pintu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Engsel pintu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.2.6. 1 buah engsel jendela kupu-kupu
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Engsel kupu-kupu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.7.
Pemasangan 1 buah engsel angin
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Engsel angin

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.8.
Pemasangan 1 buah spring knip
No Uraian Kode
A TENAGA
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Spring knip

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.9.
Pemasangan 1 buah kait angin
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kait angin

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.10.
Pemasangan 1 buah door closer
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Door closer

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.11.
Pemasangan 1 buah kunci slot
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci slot

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.12.
Pemasangan 1 buah Door holder
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Door holder

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.13.
Pemasangan 1 buah door stop
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Door stop

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.14.
Pemasangan 1 buah Rrel pintu sorong
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Rel pintu sorong

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.15.
Pemasangan 1 buah kunci lemari
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kunci lemari
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.16.
Pemasangan 1 m2 kaca tebal 3 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca tebal 3mm
SEalant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm


No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca tebal 5 mm
SEalant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.18.
Pemasangan 1 m2 kaca tebal 8 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca tebal 8 mm
SEalant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.19. Pemasangan 1 m2 kaca buram tebal 12 mm


No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca buram 12 mm
SEalant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.20.
Pemasangan 1 m2 kaca cermin tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca cermin 5 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.21.
Pemasangan 1 m2 kaca cermin tebal 8 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca cermin 8 mm

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.4.6.2.22. 1 m2 kaca wireglassed tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca wireglassed 5mm
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.23.
Pemasangan 1 m2 kaca patri tebal 5 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang kayu L.02.04
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kaca patri 5mm
Sealant

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


1 A.4.7.1.1.
m2 Pengikisan/pengerokan permukaan cat lama
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Soda api

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
1 m2 Pencucian
A.4.7.1.2.bidang permukaan tembok yang pernah dicat
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Sabun

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

1 m2 A.4.7.1.3.
Pengerokan karat pada permukaan baja cara manual
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Sabun

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

1 m2 Pengecatan bidang
A.4.7.1.4.
kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat menie
Plamuur
Cat dasar Kayu
Cat Penutup Kayu
Kuas
Pengencer
Ampelas

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pengecatan 1 m2 bidang
A.4.7.1.5.
kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat Penutup)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat menie
Plamuur
Cat dasar Kayu
Cat Penutup Kayu
Kuas
Pengencer
Ampelas

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.6.
Pelaburan 1 m2 bidang kayu dengan teak oil
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Teak oil

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.7.
Pelaburan 1 m2 bidang kayu dengan politur
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Politur
Politur jadi
Ampelas

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pelaburan
A.4.7.1.8.
1 m2 bidang kayu dengan cat residu dan ter
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Residu atau ter

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.9.
Pelaburan 1 m2 bidang kayu dengan vernis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Vernis
Dempul
Ampelas

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis ca


Satuan / Unit 1 M2
Analisa AHSP PU A.4.7.1.10

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Plamuur
Cat dasar Tembok
Cat Penutup Tembok
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Jenis Pekerjaan Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis c


Satuan / Unit 1 M2
Analisa AHSP PU A.4.7.1.11.

No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat dasar Tembok
Cat Penutup Tembok

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.12.
Pelaburan 1 m2 tembok dengan kalkarium
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kalkarium

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.13.
Pelaburan 1 m2 tembok dengan kapur sirih
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kapur sirih
Ampelas
Alang-alang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pelaburan
A.4.7.1.14.
1 m2 tembok lama dengan kapur sirih (pemeliharaan)
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kapur sirih
Ampelas
Alang-alang

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.15.Pemasangan 1 m2 wallpaper
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Wallpaper
Lem Kayu/Karet

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pengecatan
A.4.7.1.16.1 m2 permukaan baja dengan menie besi
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Menie besi
Kuas

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
PengecatanA.4.7.1.17.
1 m2 permukaan baja dengan menie besi dengan perancah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Menie besi
Pengencer
Kuas
Perancah kayu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pengecatan
A.4.7.1.18.
1 m2 permukaan baja galvanis secara manual 4 lapis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Menie A
Menie B
Cat Besi
Kuas
Pengencer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pengecatan 1 m2 A.4.7.1.19.
permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat Besi
Kuas
Pengencer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

PengecatanA.4.7.1.20.
1 m2 permukaan baja galvanis secara manual sistem 3 lapis
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat dasar Besi
Cat antara
Cat Besi
Kuas
Pengencer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pengecatan 1 m2 A.4.7.1.21.
permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat Besi
Pengencer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.4.7.1.22.
Plituran 10 m2 dengan plitur melamic
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang cat L.02.08
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Cat Dasar Kayu
Pengencer

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
(K3)
A.5.1.1.1.
Pemasangan 1 buah closet duduk/monoblock
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Closet duduk
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen


No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Closet jongkok
Semen portland
Pasir pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
3. 1 buah closet jongkok teraso
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Closet jongkok
Semen portland
Pasir pasang
Bata merah

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 (K3)
4. Pemasangan 1 buah urinoir
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Urinoir
Semen portland
Pasir pasang
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1(K3)
5. Pemasangan 1 buah wastafel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Wastafel
Semen portland
Pasir pasang
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
(K3) Pemasangan
6. 1 buah bathcuip porselen
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bathcuip
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.5.1.1
Pemasangan
7. 1 buah bak fibreglass vol 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bak fibreglass
Perlengkapan

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Pemasangan
A.5.1.1 8. 1 buah bak mandi batu bata vol 0,30 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir pasang
Porselen 11x11
Semen warna

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 9. 1 buah bak mandi teraso vol 0,30 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bak fibreglass
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
10. 1 buah bak air fibreglass vol 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bak fibreglass
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
11. 1 buah bak beton volume 1 m3
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Beton 1:2:3
Baja tulangan
Kayu bekisting
Ubin porselen
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Pemasangan
A.5.1.1 12. 1 buah bak cuci piring stainlessteel
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bak cuci piring
Waterdrain

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
13. 1 buah bak cuci piring teraso
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bak cuci piring
Waterdrain
Semen portland
Pasir pasang

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 14.
Pemasangan 1 buah floor drain
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Floor drain

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1
1 buah
15. bak kontrol pasangan bata 30x30 tinggi 35 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

PemasanganA.5.1.1
1 buah16.
bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

PemasanganA.5.1.1
1 buah17.
bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Bata merah
Semen portland
Pasir pasang
Pasir beton
Kerikil
Baja tulangan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
18. 1 m’ pipa galvanis diameter ½”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis ½”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
19. 1 buah kran diameter ½” atau 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kran air
Sealtape

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
20. 1 m’ pipa galvanis diameter 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis 3/4”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
21. 1 m’ pipa galvanis diameter 1”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis 1”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
22. 1 m’ pipa galvanis diameter 1 ½”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis 11/2”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
23. 1 m’ pipa galvanis diameter 3”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis 3”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.5.1.1
Pemasangan
24. 1 m’ pipa galvanis diameter 4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa galvanis 4”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 25. 1 m’ pipa PVC tipe AW diameter 1/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 1/2”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 26. 1 m’ pipa PVC tipe AW diameter 3/4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 3/4”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 27. 1 m’ pipa PVC tipe AW diameter 1”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 1”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 28. 1 m’ pipa PVC tipe AW diameter 11/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 11/2”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 29. 1 m’ pipa PVC tipe AW diameter 2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01
B BAHAN
Pipa PVC 2”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 30. 1 m’ pipa PVC tipe AW diameter 21/2”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 21/2”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 31. 1 m’ pipa PVC tipe AW diameter 3”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 3”
Perlengkapan
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 32. 1 m’ pipa PVC tipe AW diameter 4”
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa PVC 4”
Perlengkapan

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 33. 1 m’ pipa air limbah jenis pipa tanah
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa tanah
Semen portland
Pasir pasang
Pasir urug

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1
1 m’
34.pipa air limbah jenis pipa tanah diameter 15 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa tanah
Semen portland
Pasir pasang
Pasir urug

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1 35. 1 m’ pipa beton diameter 15 - 20 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa Beton
Bata merah
Semen portland
Pasir pasang
Pasir urug

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Pemasangan
A.5.1.1.36. 1 m’ pipa beton diameter 30 - 100 cm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Pipa Beton
Bata merah
Semen portland
Pasir pasang
Pasir urug
PVC Ø 63
C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA


A.8.4.1.1
(K3) Pemasangan 1 m pipa PVC Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 63 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Catatan:
Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang t
Apabila ada tambahan peralatan yang digunakan, harus disesuaikan deng
gambar kerja.

A.8.4.1.2
(K3) Pemasangan 1 m pipa PVC Ø 90 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 90 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.3
(K3) Pemasangan 1 m pipa PVC Ø 110 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 110 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.4
(K3) Pemasangan 1 m pipa PVC Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.5
(K3) Pemasngan 1 m pipa PVC Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.6
(K3) Pemasangan 1 m pipa PVC Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 250 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.7
(K3) Pemasangan 1 m pipa PVC Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.8
(K3) Pemasangan 1 m pipa PVC Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 400 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.9
(K3) Pemasangan 1 m pipa PVC Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 450 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.10
(K3) Pemasangan 1 m pipa PVC Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.11
(K3) Pemasangan 1 m pipa PVC Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 600 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.12
(K3) Pemasangan 1 m pipa PVC Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 800 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.13
(K3) Pemasangan 1 m pipa PVC Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 900 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.14
(K3) Pemasangan 1 m pipa PVC Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1000 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.15
(K3) Pemasangan 1 m pipa PVC Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.16
(K3) Pemasangan 1 m pipa PVC Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.17
(K3) Pemasangan 1 m pipa HDPE Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 63 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.18
(K3) Pemasangan 1 m pipa HDPE Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 100 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.19
(K3) Pemasangan 1 m pipa HDPE Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 125 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.20
(K3) Pemasangan 1 m pipa HDPE Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.21
(K3) Pemasangan 1 m pipa HDPE Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.22
(K3) Pemasangan 1 m pipa HDPE Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.23
(K3) Pemasangan 1 m pipa HDPE Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa HDPE Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.24
(K3) Pemasangan 1 m pipa HDPE Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 400 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.25
(K3) Pemasangan 1 m pipa HDPE Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 450 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.26
(K3) Pemasangan 1 m pipa HDPE Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.27
(K3) Pemasangan 1 m pipa HDPE Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.28
(K3) Pemasangan 1 m pipa HDPE Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 800 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.29
(K3) Pemasangan 1 m pipa HDPE Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 900 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.30
(K3) Pemasangan 1 m pipa HDPE Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 1000 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.31
(K3) Pemasangan 1 m pipa HDPE Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 1100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.32
(K3) Pemasangan 1 m pipa HDPE Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa HDPE Ø 1200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.33
(K3) Pemasangan 1 m pipa GIP Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 63 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.34
(K3) Pemasangan 1 m pipa GIP Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.35
(K3) Pemasangan 1 m pipa GIP Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 125 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.36
(K3) Pemasangan 1 m pipa GIP Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.37
(K3) Pemasangan 1 m pipa GIP Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.38
(K3) Pemasangan 1 m pipa GIP Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.39
(K3) Pemasangan 1 m pipa GIP Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.40
(K3) Pemasangan 1 m pipa GIP Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 400 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.41
(K3) Pemasangan 1 m pipa GIP Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 450 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.42
(K3) Pemasangan 1 m pipa GIP Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.43
(K3) Pemasangan 1 m pipa GIP Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 600 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.44
(K3) Pemasangan 1 m pipa GIP Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 800 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.45
(K3) Pemasangan 1 m pipa GIP Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 900 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.46
(K3) Pemasangan 1 m pipa GIP Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1000 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.47
(K3) Pemasangan 1 m pipa GIP Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.48
(K3) Pemasangan 1 m pipa GIP Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.49
(K3) Pemasangan 1 m pipa DCI Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.50
(K3) Pemasangan 1 m pipa DCI Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 125 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.51
(K3) Pemasangan 1 m pipa DCI Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.52
(K3) Pemasangan 1 m pipa DCI Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.53
(K3) Pemasangan 1 m pipa DCI Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.54
(K3) Pemasangan 1 m pipa DCI Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.55
(K3) Pemasangan 1 m pipa DCI Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 400 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.56
(K3) Pemasangan 1 m pipa DCI Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 450 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.57
(K3) Pemasangan 1 m pipa DCI Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 500 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.58
(K3) Pemasangan pipa 1 m DCI Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 600 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.59
(K3) Pemasangan 1 m pipa DCI Ø800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 800 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.60
(K3) Pemasangan 1 m pipa DCI Ø900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 900 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.61
(K3) Pemasangan 1 m pipa DCI Ø1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 1000 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.62
(K3) Pemasangan 1 m pipa DCI Ø1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01

B BAHAN
Pipa DCI Ø 1100 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.63
(K3) Pemasangan 1 m pipa DCI Ø1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Operator alat berat L.08.01
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1200 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.64
(K3) Pemasangan 1 m pipa baja Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 63 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.65
(K3) Pemasangan 1 m pipa baja Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.66
(K3) Pemasangan 1 m pipa baja Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 125 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.67
(K3) Pemasangan 1 m pipa baja Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.68
(K3) Pemasangan 1 m pipa baja Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.69
(K3) Pemasangan pipa baja Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.70
(K3) Pemasangan 1 m pipa baja Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 300 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.71
(K3) Pemasangan 1 m pipa baja Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 400 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.72
(K3) Pemasangan 1 m pipa baja Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 450 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.73
(K3) Pemasangan 1 m pipa baja Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 500 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.74
(K3) Pemasangan 1 m pipa baja Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 600 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.75
(K3) Pemasangan 1 m pipa baja Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 800 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.76
(K3) Pemasangan 1 m pipa baja Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 900 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.77
(K3) Pemasangan 1 m pipa baja Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 1000 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.78
(K3) Pemasangan 1 m pipa baja Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 1100 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.79
(K3) Pemasangan 1 m pipa baja Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 1200 mm

C PERALATAN
Sewa excavator type 225 kap 0,5 -1,0 m3
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2
HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
A.8.4.2.1
(K3) Pemotongan 1 buah pipa PVC Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 63 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.2
(K3) Pemotongan 1 m pipa PVC Ø 90 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 90 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
(K3)
A.8.4.2.3
Pemotongan 1 buah pipa PVC Ø 110 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 110 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.4
Pemotongan 1 buah pipa PVC Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 150 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.5
Pemotongan 1 buah pipa PVC Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa PVC Ø 200 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.6
Pemotongan 1 buah pipa PVC Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 250 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.7
Pemotongan 1 buah pipa PVC Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 300 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.8
Pemotongan 1 buah pipa PVC Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 400 mm

C PERALATAN
Peralatan potong pipa T1/manual (gergaji) /saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.9
Pemotongan 1 buah pipa PVC Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.10
(K3) Pemotongan 1 buah pipa PVC Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 500 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.11
(K3) Pemotongan 1 buah pipa PVC Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.12
(K3) Pemotongan 1 buah pipa PVC Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.13
(K3) Pemotongan 1 buah pipa PVC Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 900 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.14
Pemotongan 1 buah pipa PVC Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1000 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.15
Pemotongan 1 buah pipa PVC Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.16
Pemotongan 1 buah pipa PVC Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa PVC Ø 1200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.17
(K3) Pemotongan 1 buah pipa HDPE Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01
B BAHAN
Pipa HDPE Ø 63 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.18
Pemotongan 1 buah pipa HDPE Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.19
Pemotongan 1 buah pipa HDPE Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 125 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.20
Pemotongan 1 buah pipa HDPE Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 150 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.21
Pemotongan 1 buah pipa HDPE Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.22
(K3) Pemotongan 1 buah pipaHDPE Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 250 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.23
Pemotongan 1 buah pipa HDPE Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 300 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.24
Pemotongan 1 buah pipa HDPE Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 400 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.25
Pemotongan 1 buah pipa HDPE Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.26
Pemotongan 1 buah pipa HDPE Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.27
Pemotongan 1 buah pipa HDPE Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.28
Pemotongan 1 buah pipa HDPE Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.29
Pemotongan 1 buah pipa HDPE Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 900 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.30
Pemotongan 1 buah pipa HDPE Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 1000

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.31
Pemotongan 1 buah pipa HDPE Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 1100

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3)
A.8.4.2.32
Pemotongan 1 buah pipa HDPE Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
Operator Alat Pipa L.11.01

B BAHAN
Pipa HDPE Ø 1200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.33
(K3) Pemotongan 1 buah pipa GIP Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa GIP Ø 63 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.34
(K3) Pemotongan 1 buah pipa GIP Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.35
(K3) Pemotongan 1 buah pipa GIP Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 125 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.36
(K3) Pemotongan 1 buah pipa GIP Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 150 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.37
(K3) Pemotongan 1 buah pipa GIP Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.38
(K3) Pemotongan 1 buah pipa GIP Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 250 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.39
(K3) Pemotongan 1 buah pipa GIP Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 300 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.40
(K3) Pemotongan 1 buah pipa GIP Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 400 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.41
(K3) Pemotongan 1 buah pipa GIP Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.42
(K3) Pemotongan 1 buah pipa GIP Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 500 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.43
(K3) Pemotongan1 buah pipa GIP Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.44
(K3) Pemotongan 1 buah pipa GIP Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.45
(K3) Pemotongan 1 buah pipa GIP Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 900 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.46
(K3) Pemotongan 1 buah pipa GIP Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1000 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.47
(K3) Pemotongan 1 buah pipa GIP Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.48
(K3) Pemotongan 1 buah pipa GIP Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa GIP Ø 1200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.49
(K3) Pemotongan 1 buah pipa DCI Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.50
(K3) Pemotongan 1 buah pipa DCI Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 125 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.51
(K3) Pemotongan 1 buah pipa DCI Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.52
(K3) Pemotongan 1 buah pipa DCI Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.53
(K3) Pemotongan 1 buah pipa DCI Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.54
(K3) Pemotongan 1 buah pipa DCI Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.55
(K3) Pemotongan 1 buah pipa DCI Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 400 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.56
(K3) Pemotongan 1 buah pipa DCI Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.57
(K3) Pemotongan 1 buah pipa DCI Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 500 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.58
(K3) Pemotongan 1 buah pipa DCI Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.59
(K3) Pemotongan 1 buah pipa DCI Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.60
(K3) Pemotongan 1 buah pipa DCI Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 900 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.61
(K3) Pemotongan 1 buah pipa DCI Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 1000 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.62
(K3) Pemotongan 1 buah pipa DCI Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa DCI Ø 1100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.63
(K3) Pemotongan 1 buah pipa DCI Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa DCI Ø 1200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.64
(K3) Pemotongan 1 buah pipa baja Ø 63 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 63 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.65
(K3) Pemotongan 1 buah pipa baja Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.66
(K3) Pemotongan 1 buah pipa baja Ø 125 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 125 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.67
(K3) Pemotongan 1 buah pipa baja Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 150 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.68
(K3) Pemotongan 1 buah pipa baja Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 200 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.69
(K3) Pemotongan 1 buah pipa baja Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 250 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.70
(K3) Pemotongan 1 buah pipa baja Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 300 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.71
(K3) Pemotongan 1 buah pipa baja Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 400 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.72
(K3) Pemotongan 1 buah pipa baja Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.73
(K3) Pemotongan 1 buah pipa baja Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 500 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.74
(K3) Pemotongan 1 buah pipa baja Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Pipa Baja Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.75
(K3) Pemotongan 1 buah pipa baja Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.76
(K3) Pemotongan 1 buah pipa baja Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 900 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.77
(K3) Pemotongan 1 buah pipa baja Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 1000 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.78
(K3) Pemotongan 1 buah pipa baja Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 1100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.79
(K3) Pemotongan 1 buah pipa baja Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Baja Ø 1100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

HARGA
A.8.4.3SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
A.8.4.3.1
(K3) Pemasangan 1 buah Valve Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.2
(K3) Pemasangan 1 buah Valve Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 200 mm
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.3
(K3) Pemasangan 1 buah Valve Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.4
(K3) Pemasangan 1 buah Valve Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.5
(K3) Pemasangan 1 buah Valve Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 400 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.6
(K3) Pemasangan 1 buah Valve Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 450 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.7
(K3) Pemasangan 1 buah Valve Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Valve Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.8
(K3) Pemasangan 1 buah Valve Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 600 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.9
(K3) Pemasangan 1 buah Valve Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 700 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.10
(K3) Pemasangan 1 buah Valve Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 800 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.11
(K3) Pemasangan 1 buah Valve Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 900 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.3.12
(K3) Pemasangan 1 buah Valve Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 1000 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.13
(K3) Pemasangan 1 buah Valve Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 1100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.14
(K3) Pemasangan 1 buah Valve Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Valve Ø 1200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.15
(K3) Pemasangan 1 buah Tee Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 150 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.16
(K3) Pemasangan 1 buah Tee Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.17
(K3) Pemasangan 1 buah Tee Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 250 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.18
(K3) Pemasangan 1 buah Tee Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 300 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.19
(K3) Pemasangan 1 buah Tee Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 400 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.20
(K3) Pemasangan 1 buah Tee Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 450 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.21
(K3) Pemasangan 1 buah Tee Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 500 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.22
(K3) Pemasangan 1 buah Tee Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 600 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.23
(K3) Pemasangan 1 buah Tee Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 700 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.24
(K3) Pemasangan 1 buah Tee Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 800 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.25
(K3) Pemasangan 1 buah Tee Ø 900 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 900 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.26
(K3) Pemasangan 1 buah Tee Ø 1000 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 1000 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.27
(K3) Pemasangan 1 buah Tee Ø 1100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Tee Ø 1100 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.28
(K3) Pemasangan 1 buah Tee Ø 1200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01
B BAHAN
Tee Ø 1200 mm

C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T
Mobile crane =< 3 ton

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

HARGA A.8.4.4
SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
(K3) Penyambungan
A.8.4.4.1 1 buah pipa baru ke pipa yang ada Ø 80 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 80 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.2 1 buah pipa baru ke pipa yang ada Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 100 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.3 1 buah pipa baru ke pipa yang ada Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 150 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.4 1 buah pipa baru ke pipa yang ada Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 200 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.5 1 buah pipa baru ke pipa yang ada Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 250 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.6 1 buah pipa baru ke pipa yang ada Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 300 mm
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.7 1 buah pipa baru ke pipa yang ada Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 400 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.8 1 buah pipa baru ke pipa yang ada Ø 450 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 450 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.9 1 buah pipa baru ke pipa yang ada Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 500 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.10 1 buah pipa baru ke pipa yang ada Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 600 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.11 1 buah pipa baru ke pipa yang ada Ø 700 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 700 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

(K3) Penyambungan
A.8.4.4.12
1 buah 1 buah pipa baru ke pipa yang ada Ø 800 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang pipa L.02.13
Mandor L.04.01

B BAHAN
Pipa Ø 800 mm

C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw
Sewa Genset 1500 watt
Sewa Pompa Submersible 3m3/h
Sewa Tripot/Tackel & handle crane 2 T

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5
HARGA SATUAN PEKERJAAN PENGETESAN PIPA
A.8.4.5.1
(K3) Pengetesan 1 m pipa Ø 50 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.2
(K3) Pengetesan 1 m pipa Ø 75 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.8.4.5.3
(K3) Pengetesan 1 m pipa Ø 100 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.4
(K3) Pengetesan 1 m pipa Ø 150 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.5
(K3) Pengetesan 1 m pipa Ø 200 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01
B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.6
(K3) Pengetesan 1 m pipa Ø 250 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.7
(K3) Pengetesan 1 m pipa Ø 300 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.8
(K3) Pengetesan 1 m pipa Ø 400 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.9
(K3) Pengetesan 1 m pipa Ø 500 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.10
(K3) Pengetesan 1 m pipa Ø 600 mm
No Uraian Kode
A TENAGA
Pekerja L.01.01
Mandor L.04.01

B BAHAN
Air test (air bersih)
Bahan bakar
Oli

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL


A.8.4.6.1
(K3) Pemasangan 1 buah titik lampu
No Uraian Kode
A TENAGA
Upah

B BAHAN
Pipa listrik 5/8”
Kabel NYM 3x2,5 mm2
Tee Doos
L.Bow
Las Dop
Klem Pipa Listrik
Mongkok (Listrik)
Saklar (standar)
Fitting Lampu

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.8.4.6.2
Memasang 1 Titik Instalasi Penerangan
No Uraian Kode
A TENAGA
Pekerja L.01.01
Tukang batu L.02.03
Kepala tukang L.03.01
Mandor L.04.01

B BAHAN
Kabel NYM 3x2,5 mm2
Pipa Conduit
Socket Pipa
Tee Doos
Klem Pipa
Fhiser
Las Dop
Sealtape Listrik

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
ALISA HARGA SATUAN 2021

AN PERSIAPAN
agar sementara dari kayu tinggi 2 meter

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0200 90,000.00 1,800.00
JUMLAH TENAGA KERJA 55,200.00

Batang 1.2500 -
Kg 5.0000 -
m3 0.0050 -
m3 0.0090 -
m3 0.0720 -
Kg 0.0600 -
Liter 0.4000 -
JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


55,200.00
10% 5,520.00
- 60,720.00

pagar sementara dari seng gelombang tinggi 2 meter

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.4000 100,000.00 40,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0200 90,000.00 1,800.00
JUMLAH TENAGA KERJA 59,500.00

Batang 1.2500 -
Kg 2.5000 -
Lbr 1.2000 -
m3 0.0050 -
m3 0.0090 -
m3 0.0720 -
Kg 0.0600 -
Liter 0.4500 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
59,500.00
10% 5,950.00
- 65,450.00

sementara dari kawat duri tinggi 1,8 meter

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.3000 100,000.00 30,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0200 90,000.00 1,800.00
JUMLAH TENAGA KERJA 49,500.00
- -
Batang 1.0000 -
Kg 2.0000 -
M’ 25.0000 -
m3 0.0050 -
m3 0.0090 -
Kg 0.0600 -
JUMLAH HARGA BAHAN 49,500.00
- -
JUMLAH HARGA ALAT -
- 74,250.00
10% 7,425.00
- 81,675.00

angan 1 M' Bouwplank

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1000 80,000.00 8,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0050 180,000.00 900.00
JUMLAH TENAGA KERJA 22,400.00
- -
m3 0.1200 60,000.00 7,200.00
Kg 0.0200 20,000.00 400.00
m3 0.0070 130,000.00 910.00
JUMLAH HARGA BAHAN 45,310.00
- -
JUMLAH HARGA ALAT -
- 49,310.00
10% 4,931.00
- 54,241.00

ntor sementara lantai plesteran


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 2.0000 78,500.00 157,000.00


OH 2.0000 100,000.00 200,000.00
OH 1.0000 100,000.00 100,000.00
OH 0.3000 100,000.00 30,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 491,500.00
- -
Batang 1.2500 -
m3 0.1800 -
Kg 0.0800 -
Kg 1.1000 -
Kg 35.0000 -
m3 0.1500 -
m3 0.1000 -
m3 0.1500 -
Bh 30.0000 -
Lbr 0.2500 -
Bh 0.2000 -
m2 0.0800 -
Bh 0.1500 -
Lbr 0.0600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 491,500.00
10% 49,150.00
- 540,650.00

mah jaga (konstruksi kayu )

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 1.0000 78,500.00 78,500.00
OH 1.5000 100,000.00 150,000.00
OH 0.1500 100,000.00 15,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 248,000.00

Batang 3.0000 -
m3 0.2760 -
Kg 0.7000 -
Lbr 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 248,000.00
10% 24,800.00
- 272,800.00

udang semen dan peralatan

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 2.0000 100,000.00 200,000.00
OH 0.2000 100,000.00 20,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 303,000.00

Batang 1.7000 -
m3 0.2100 -
Kg 0.3000 -
Kg 10.5000 -
m3 0.0300 -
m3 0.0500 -
Lbr 1.5000 -
Lbr 0.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 303,000.00
10% 30,300.00
- 333,300.00

edeng pekerja

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 2.0000 100,000.00 200,000.00
OH 0.2000 100,000.00 20,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 303,000.00
-
Batang 1.2500 -
m3 0.1860 -
Kg 0.3000 -
Kg 18.0000 -
m3 0.0300 -
m3 0.0500 -
Lbr 1.5000 -
Lbr 1.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 303,000.00
10% 30,300.00
- 333,300.00

ALISA HARGA SATUAN 2021


apangan dan perataan

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1000 80,000.00 8,000.00


OH 0.0500 180,000.00 9,000.00
JUMLAH TENAGA KERJA 17,000.00
-
JUMLAH HARGA BAHAN
- -
JUMLAH HARGA ALAT -
- 17,000.00
10% 1,700.00
- 18,700.00

eger/perancah dari bambu

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 2.0000 100,000.00 200,000.00
OH 0.2000 100,000.00 20,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 303,000.00

Batang 1.2500 -
Kg 0.1860 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 303,000.00
10% 30,300.00
- 333,300.00

k Adukan Ukuran 40cm x 50cm x 25cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 100,000.00 30,000.00


OH 0.0300 100,000.00 3,000.00
JUMLAH TENAGA KERJA 33,000.00
- -
m3 0.0360 -
m3 0.0210 -
kg 0.0800 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 33,000.00
10% 3,300.00
- 36,300.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 78,950.00
- -
m3 0.1500 -
m3 0.0900 -
m3 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 78,950.00
10% 7,895.00
- 86,845.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.3334 78,500.00 104,671.90


OH 0.6660 90,000.00 59,940.00
JUMLAH TENAGA KERJA 164,611.90
- -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 164,611.90
10% 16,461.19
- 181,073.00

ding Tembok Bata

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6667 78,500.00 52,335.95


OH 0.3330 90,000.00 29,970.00
JUMLAH TENAGA KERJA 82,305.95
- -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 82,305.95
10% 8,230.60
- 90,536.00

ar kawat jaring galvanis panjang 240 cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0420 78,500.00 3,297.00


OH 0.0040 100,000.00 400.00
OH 0.0020 100,000.00 200.00
OH 0.0420 90,000.00 3,780.00
JUMLAH TENAGA KERJA 7,677.00
- -
Lbr 0.1434 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,677.00
10% 767.70
- 8,444.00

beton pracetak 5x50x240 cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3750 78,500.00 29,437.50


OH 0.1250 100,000.00 12,500.00
OH 0.0120 100,000.00 1,200.00
OH 0.0190 90,000.00 1,710.00
JUMLAH TENAGA KERJA 44,847.50
- -
Lbr 0.9860 -
Batang 0.5250 -
Kg 45.0000 -
m3 0.0740 -
m3 0.1460 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 44,847.50
10% 4,484.75
- 49,332.00

RJAAN TANAH

biasa sedalam 1 m

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.7500 80,000.00 60,000.00


OH 0.0250 180,000.00 4,500.00
JUMLAH TENAGA KERJA 64,500.00

JUMLAH HARGA BAHAN -


-
JUMLAH HARGA ALAT -
64,500.00
10% 6,450.00
70,950.00

biasa sedalam 2 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 74,700.00
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
74,700.00
10% 7,470.00
82,170.00

asa sedalam 3 m

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0500 80,000.00 84,000.00


OH 0.0670 180,000.00 12,060.00
JUMLAH TENAGA KERJA 96,060.00
-
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
96,060.00
10% 9,606.00
105,666.00

ras sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 0.0320 90,000.00 2,880.00
JUMLAH TENAGA KERJA 81,380.00

JUMLAH HARGA BAHAN -


-
JUMLAH HARGA ALAT -
81,380.00
10% 8,138.00
89,518.00

das sedalam 1 m

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.0600 90,000.00 5,400.00
JUMLAH TENAGA KERJA 123,150.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


123,150.00
10% 12,315.00
135,465.00

mpur sedalam 1 m
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.2000 78,500.00 94,200.00


OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 98,250.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


98,250.00
10% 9,825.00
108,075.00

2 tanah tebing setinggi 1 meter

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0500 78,500.00 3,925.00


OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 4,375.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


4,375.00
10% 437.50
4,812.00

tanah sejauh 30 meter

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3300 78,500.00 25,905.00


OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 26,805.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


26,805.00
10% 2,680.50
29,485.00

erjaan galian
3 galian tanah Tanah Biasa Sedalam 1 M

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2500 80,000.00 20,000.00


OH 0.0250 180,000.00 4,500.00
JUMLAH TENAGA KERJA 24,500.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


24,500.00
10% 2,450.00
26,950.00

m3 tanah ( per 20 cm)


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
- -
OH 0.5000 78,500.00 39,250.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 43,750.00

JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


- 43,750.00
10% 4,375.00
- 48,125.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.0100 180,000.00 1,800.00
JUMLAH TENAGA KERJA 25,800.00
-
M3 1.2000 128,000.00 153,600.00
JUMLAH HARGA BAHAN 153,600.00
-
JUMLAH HARGA ALAT -
179,400.00
10% 17,940.00
197,340.00
n Tanah Timbun Biasa

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.0100 180,000.00 1,800.00
JUMLAH TENAGA KERJA 25,800.00

M3 1.2000 65,000.00 78,000.00


JUMLAH HARGA BAHAN 78,000.00

JUMLAH HARGA ALAT -


103,800.00
10% 10,380.00
114,180.00

an pudel campuran 1KP : 3PP : 7TL

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.8000 78,500.00 62,800.00


OH 0.4000 100,000.00 40,000.00
OH 0.0400 100,000.00 4,000.00
OH 0.0800 90,000.00 7,200.00
JUMLAH TENAGA KERJA 114,000.00

m3 0.1350 9,838.00 1,328.13


m3 0.4000 110,000.00 44,000.00
m3 0.9480 40,000.00 37,920.00
JUMLAH HARGA BAHAN 83,248.13

JUMLAH HARGA ALAT -


- 197,248.13
10% 19,724.81
- 216,972.00

an ijuk tebal 10 cm untuk bidang resapan

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 13,125.00

m3 6.0000 35,000.00 210,000.00


JUMLAH HARGA BAHAN 210,000.00

JUMLAH HARGA ALAT -


- 223,125.00
10% 22,312.50
- 245,437.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.0250 90,000.00 2,250.00
JUMLAH TENAGA KERJA 21,875.00

m3 1.2000 250,000.00 300,000.00


JUMLAH HARGA BAHAN 300,000.00

JUMLAH HARGA ALAT -


321,875.00
10% 32,187.50
354,062.00

RJAAN PONDASI

dasi batu belah campuran 1SP : 3PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 202.0000 1,300.00 262,600.00
m3 0.4850 110,000.00 53,350.00
JUMLAH HARGA BAHAN 447,950.00

JUMLAH HARGA ALAT -


654,950.00
10% 65,495.00
720,445.00

dasi batu belah campuran 1SP : 4PP


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 80,000.00 120,000.00


OH 0.7500 120,000.00 90,000.00
OH 0.0750 150,000.00 11,250.00
OH 0.0750 180,000.00 13,500.00
JUMLAH TENAGA KERJA 234,750.00

m3 1.2000 165,000.00 198,000.00


Kg 163.0000 1,500.00 244,500.00
m3 0.5200 130.00 67.60
JUMLAH HARGA BAHAN 442,567.60

JUMLAH HARGA ALAT -


677,317.60
10% 67,731.76
745,049.00

dasi batu belah campuran 1SP : 5PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 136.0000 1,300.00 176,800.00
m3 0.5440 110,000.00 59,840.00
JUMLAH HARGA BAHAN 368,640.00

JUMLAH HARGA ALAT -


575,640.00
10% 57,564.00
633,204.00

dasi batu belah campuran 1SP : 6PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 117.0000 1,300.00 152,100.00
m3 0.5610 110,000.00 61,710.00
JUMLAH HARGA BAHAN 345,810.00
-
JUMLAH HARGA ALAT -
552,810.00
10% 55,281.00
608,091.00

dasi batu belah campuran 1SP : 8PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 1.5000 78,500.00 117,750.00
OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 91.0000 1,300.00 118,300.00
m3 0.5840 110,000.00 64,240.00
JUMLAH HARGA BAHAN 314,540.00
-
JUMLAH HARGA ALAT -
521,540.00
10% 52,154.00
573,694.00

dasi batu belah campuran 1SP : 1KP : 2PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


m3 0.1700 9,838.00 1,672.46
Kg 170.0000 1,300.00 221,000.00
m3 0.3400 110,000.00 37,400.00
JUMLAH HARGA BAHAN 392,072.46
-
JUMLAH HARGA ALAT -
599,072.46
10% 59,907.25
658,979.00

dasi batu belah campuran 1 SP : 3 KP : 10 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 61.0000 1,300.00 79,300.00
m3 0.1470 9,838.00 1,446.19
m3 0.4920 110,000.00 54,120.00
JUMLAH HARGA BAHAN 266,866.19
-
JUMLAH HARGA ALAT -
473,866.19
10% 47,386.62
521,252.00

dasi batu belah campuran ¼ SP : 1 KP : 4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.5000 78,500.00 117,750.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 207,000.00

m3 1.2000 110,000.00 132,000.00


Kg 41.0000 1,300.00 53,300.00
m3 0.1310 9,838.00 1,288.78
m3 0.5230 110,000.00 57,530.00
JUMLAH HARGA BAHAN 244,118.78
-
JUMLAH HARGA ALAT -
451,118.78
10% 45,111.88
496,230.00

kosong (anstamping)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.7800 80,000.00 62,400.00


OH 0.3900 120,000.00 46,800.00
OH 0.0390 150,000.00 5,850.00
OH 0.0390 180,000.00 7,020.00
JUMLAH TENAGA KERJA 122,070.00

m3 1.2000 165,000.00 198,000.00


m3 0.4320 128,000.00 55,296.00
JUMLAH HARGA BAHAN 253,296.00
-
JUMLAH HARGA ALAT -
375,366.00
10% 37,536.60
412,902.00
pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 3.4000 78,500.00 266,900.00


OH 0.8500 100,000.00 85,000.00
OH 0.0850 100,000.00 8,500.00
OH 0.1700 90,000.00 15,300.00
JUMLAH TENAGA KERJA 375,700.00

m3 0.4800 110,000.00 52,800.00


Kg 194.0000 1,300.00 252,200.00
m3 0.3120 190,000.00 59,280.00
m3 0.4680 350,000.00 163,800.00
Kg 126.0000 4,500.00 567,000.00
Kg 1.8000 20,000.00 36,000.00
JUMLAH HARGA BAHAN 1,131,080.00
-
JUMLAH HARGA ALAT -
1,506,780.00
10% 150,678.00
1,657,458.00

asi sumuran, diameter 100 cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 2.4000 78,500.00 188,400.00


OH 0.8000 100,000.00 80,000.00
OH 0.0800 100,000.00 8,000.00
OH 0.1190 90,000.00 10,710.00
JUMLAH TENAGA KERJA 287,110.00

m3 0.4500 110,000.00 49,500.00


Kg 194.0000 1,300.00 252,200.00
m3 0.3120 190,000.00 59,280.00
m3 0.4680 350,000.00 163,800.00
JUMLAH HARGA BAHAN 524,780.00
-
JUMLAH HARGA ALAT -
811,890.00
10% 81,189.00
893,079.00

RJAAN BETON

tu f’c = 7,4 MPa (K 100)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 247.0000 1,300.00 321,100.00


kg 869.0000 135.71 117,935.71
kg 999.0000 259.26 259,000.00
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 719,535.71
-
JUMLAH HARGA ALAT -
886,830.71
10% 88,683.07
975,513.00
tu f’= 9,8 MPa (K 125)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 276.0000 1,300.00 358,800.00


kg 828.0000 135.71 112,371.43
kg 1012.0000 259.26 262,370.37
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 755,041.80
-
JUMLAH HARGA ALAT -
922,336.80
10% 92,233.68
1,014,570.00

tu f’= 12,2 MPa (K 150)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 299.0000 1,300.00 388,700.00


kg 799.0000 135.71 108,435.71
kg 1017.0000 259.26 263,666.67
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 782,302.38
-
JUMLAH HARGA ALAT -
949,597.38
10% 94,959.74
1,044,557.00

i kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

ja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.2000 80,000.00 96,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0600 180,000.00 10,800.00
JUMLAH TENAGA KERJA 133,800.00

kg 230.0000 1,500.00 345,000.00


kg 893.0000 150.00 133,950.00
kg 1027.0000 225.00 231,075.00
Liter 200.0000 12.00 2,400.00
JUMLAH HARGA BAHAN 712,425.00
-
JUMLAH HARGA ALAT -
846,225.00
10% 84,622.50
930,847.00
tu f’ = 14,5 MPa (K 175), slump (12 ±2) cm, w/c = 0,66

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 326.0000 1,300.00 423,800.00


kg 760.0000 135.71 103,142.86
kg 1029.0000 259.26 266,777.78
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 815,220.63
-
JUMLAH HARGA ALAT -
982,515.63
10% 98,251.56
1,080,767.00

tu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 352.0000 1,300.00 457,600.00


kg 731.0000 135.71 99,207.14
kg 1031.0000 259.26 267,296.30
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 845,603.44
- -
JUMLAH HARGA ALAT -
- 1,012,898.44
10% 101,289.84
- 1,114,188.00

tu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 371.0000 1,300.00 482,300.00


kg 698.0000 135.71 94,728.57
kg 1047.0000 259.26 271,444.44
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 869,973.02
-
JUMLAH HARGA ALAT -
1,037,268.02
10% 103,726.80
1,140,994.00

tu f’= 21,7 MPa (K 250), slump (120 ± 20) mm, w/c = 0,56
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 80,000.00 132,000.00


OH 0.2750 120,000.00 33,000.00
OH 0.0280 150,000.00 4,200.00
OH 0.0830 180,000.00 14,940.00
JUMLAH TENAGA KERJA 184,140.00

kg 384.0000 1,500.00 576,000.00


kg 692.0000 150.00 103,800.00
kg 1039.0000 225.00 233,775.00
Liter 215.0000 12.00 2,580.00
JUMLAH HARGA BAHAN 916,155.00
-
JUMLAH HARGA ALAT -
1,100,295.00
10% 110,029.50
1,210,324.00

tu f’ = 24,0 MPa (K 275), slump (120 ± 20) mm, w/c = 0,53

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 406.0000 1,300.00 527,800.00


kg 684.0000 135.71 92,828.57
kg 1026.0000 259.26 266,000.00
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 908,128.57
- -
JUMLAH HARGA ALAT -
- 1,075,423.57
10% 107,542.36
- 1,182,965.00

tu f’c = 26,4 MPa (K 300), slump (120 ± 20) mm, w/c = 0,52

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6500 78,500.00 129,525.00


OH 0.2750 100,000.00 27,500.00
OH 0.0280 100,000.00 2,800.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 167,295.00

kg 413.0000 1,300.00 536,900.00


kg 681.0000 135.71 92,421.43
kg 1021.0000 259.26 264,703.70
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 915,525.13
- -
JUMLAH HARGA ALAT -
- 1,082,820.13
10% 108,282.01
- 1,191,102.00

tu f’c = 28,8 MPa (K 325), slump (120 ± 20) mm, w/c = 0,49
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 2.1000 78,500.00 164,850.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.1050 90,000.00 9,450.00
JUMLAH TENAGA KERJA 212,800.00

kg 439.0000 1,300.00 570,700.00


kg 670.0000 135.71 90,928.57
kg 1006.0000 259.26 260,814.81
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 943,943.39
- -
JUMLAH HARGA ALAT -
- 1,156,743.39
10% 115,674.34
- 1,272,417.00

tu f’c = 31,2 MPa (K 350), slump (120 ± 20) mm, w/c = 0,48

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 2.1000 78,500.00 164,850.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.1050 90,000.00 9,450.00
JUMLAH TENAGA KERJA 212,800.00

kg 448.0000 1,300.00 582,400.00


kg 667.0000 135.71 90,521.43
kg 1000.0000 259.26 259,259.26
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 953,680.69
- -
JUMLAH HARGA ALAT -
- 1,166,480.69
10% 116,648.07
- 1,283,128.00

an penambahan bahan tambahan sesuai Tabel berikut:

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 2.1000 78,500.00 164,850.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.1050 90,000.00 9,450.00
JUMLAH TENAGA KERJA 212,800.00

kg 448.0000 1,300.00 582,400.00


kg 667.0000 135.71 90,521.43
kg 1000.0000 259.26 259,259.26
Liter 4.5000 65,000.00 292,500.00
Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,246,180.69
- -
JUMLAH HARGA ALAT -
- 1,458,980.69
10% 145,898.07
- 1,604,878.00

Buckling factor pasir = 20%

dap air dengan strorox - 100

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 2.1000 78,500.00 164,850.00
OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.1050 90,000.00 9,450.00
JUMLAH TENAGA KERJA 212,800.00

kg 400.0000 -
m3 0.4800 -
m3 0.8000 -
kg 1.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 212,800.00
10% 21,280.00
- 234,080.00

Waterstop lebar 150 mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0600 78,500.00 4,710.00


OH 0.0300 100,000.00 3,000.00
OH 0.0030 100,000.00 300.00
OH 0.0030 90,000.00 270.00
JUMLAH TENAGA KERJA 8,280.00

m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,280.00
10% 828.00
- 9,108.00
Waterstop lebar 200 mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0700 78,500.00 5,495.00


OH 0.0350 100,000.00 3,500.00
OH 0.0040 100,000.00 400.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 10,025.00

m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,025.00
10% 1,002.50
- 11,027.00

erstop lebar 230 mm - 320 mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0800 78,500.00 6,280.00


OH 0.0400 100,000.00 4,000.00
OH 0.0040 100,000.00 400.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 11,040.00

m 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,040.00
10% 1,104.00
- 12,144.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0070 80,000.00 560.00


OH 0.0070 120,000.00 840.00
OH 0.0007 150,000.00 105.00
OH 0.0004 180,000.00 72.00
JUMLAH TENAGA KERJA 1,577.00
0.0151
kg 10.5000 8,000.00 84,000.00
kg 0.1500 15,000.00 2,250.00
JUMLAH HARGA BAHAN 86,250.00
-
JUMLAH HARGA ALAT -
87,827.00
8,782.70
10% 878.27
9,660.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0070 80,000.00 560.00


OH 0.0070 120,000.00 840.00
OH 0.0007 150,000.00 105.00
OH 0.0004 180,000.00 72.00
JUMLAH TENAGA KERJA 1,577.00

kg 10.5000 9,000.00 94,500.00


kg 0.1500 15,000.00 2,250.00
JUMLAH HARGA BAHAN 96,750.00
-
JUMLAH HARGA ALAT -
98,327.00
9,832.70
10% 983.27
10,815.00

l presstressed polos/strands

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0500 78,500.00 3,925.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0030 90,000.00 270.00
JUMLAH TENAGA KERJA 9,695.00

kg 10.5000 12,000.00 126,000.00


kg 0.1000 20,000.00 2,000.00
JUMLAH HARGA BAHAN 128,000.00
-
JUMLAH HARGA ALAT -
137,695.00
10% 13,769.50
151,464.00
g kawat baja (wiremesh)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0250 78,500.00 1,962.50


OH 0.0250 100,000.00 2,500.00
OH 0.0250 100,000.00 2,500.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 7,052.50

kg 10.2000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,052.50
10% 705.25
- 7,757.00

bekisting untuk pondasi

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.5200 80,000.00 41,600.00


OH 0.2600 120,000.00 31,200.00
OH 0.0260 150,000.00 3,900.00
OH 0.0260 180,000.00 4,680.00
JUMLAH TENAGA KERJA 81,380.00

m3 0.0400 3,000,000.00 120,000.00


kg 0.3000 20,000.00 6,000.00
Liter 0.1000 1,500.00 150.00
JUMLAH HARGA BAHAN 126,150.00

-
JUMLAH HARGA ALAT -
207,530.00
10% 20,753.00
228,283.00
3 X Pemakaian 76,094.33

bekisting untuk sloof

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.5200 80,000.00 41,600.00


OH 0.2600 120,000.00 31,200.00
OH 0.0260 150,000.00 3,900.00
OH 0.0260 180,000.00 4,680.00
JUMLAH TENAGA KERJA 81,380.00

m3 0.0450 3,000,000.00 135,000.00


kg 0.3000 20,000.00 6,000.00
Liter 0.1000 1,500.00 150.00
JUMLAH HARGA BAHAN 141,150.00

-
JUMLAH HARGA ALAT -
222,530.00
10% 22,253.00
244,783.00
3 X Pemakaian 81,594.33

Bekisting untuk Kolom


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6600 80,000.00 52,800.00


OH 0.3300 120,000.00 39,600.00
OH 0.0330 150,000.00 4,950.00
OH 0.0330 180,000.00 5,940.00
JUMLAH TENAGA KERJA 103,290.00

m3 0.0400 3,000,000.00 120,000.00


kg 0.4000 20,000.00 8,000.00
Liter 0.2000 1,500.00 300.00
m3 0.0150 3,500,000.00 52,500.00
Lbr 0.3500 150,000.00 52,500.00
btg 2.0000 60,000.00 120,000.00
JUMLAH HARGA BAHAN 353,300.00

-
JUMLAH HARGA ALAT -
456,590.00
10% 45,659.00
502,249.00
3 X Pemakaian 167,416.33

bekisting untuk balok

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6600 80,000.00 52,800.00


OH 0.3300 120,000.00 39,600.00
OH 0.0330 150,000.00 4,950.00
OH 0.0330 180,000.00 5,940.00
JUMLAH TENAGA KERJA 103,290.00

m3 0.0400 3,000,000.00 120,000.00


kg 0.4000 20,000.00 8,000.00
Liter 0.2000 1,500.00 300.00
m3 0.0180 3,500,000.00 63,000.00
Lbr 0.3500 150,000.00 52,500.00
Batang 2.0000 60,000.00 120,000.00
JUMLAH HARGA BAHAN 363,800.00

-
JUMLAH HARGA ALAT -
467,090.00
10% 46,709.00
513,799.00
3 X Pemakaian 171,266.33

bekisting untuk lantai

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6600 80,000.00 52,800.00


OH 0.3300 120,000.00 39,600.00
OH 0.0330 150,000.00 4,950.00
OH 0.0330 180,000.00 5,940.00
JUMLAH TENAGA KERJA 103,290.00

m3 0.0400 3,000,000.00 120,000.00


kg 0.4000 20,000.00 8,000.00
Liter 0.2000 1,500.00 300.00
m3 0.0150 3,500,000.00 52,500.00
Lbr 0.3500 150,000.00 52,500.00
Btg 6.0000 60,000.00 360,000.00
JUMLAH HARGA BAHAN 593,300.00

-
JUMLAH HARGA ALAT -
696,590.00
10% 69,659.00
766,249.00
3 X Pemakaian 255,416.33

bekisting untuk dinding

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6600 78,500.00 51,810.00


OH 0.3300 100,000.00 33,000.00
OH 0.0330 100,000.00 3,300.00
OH 0.0330 90,000.00 2,970.00
JUMLAH TENAGA KERJA 91,080.00

m3 0.0300 3,000,000.00 90,000.00


kg 0.4000 20,000.00 8,000.00
Liter 0.2000 1,500.00 300.00
m3 0.0200 3,500,000.00 70,000.00
Lbr 0.3500 150,000.00 52,500.00
Batang 3.0000 60,000.00 180,000.00
Buah 4.0000 5,000.00 20,000.00
JUMLAH HARGA BAHAN 420,800.00

-
JUMLAH HARGA ALAT -
511,880.00
10% 51,188.00
563,068.00
3 X Pemakaian 187,689.33

bekisting untuk tangga

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6600 80,000.00 52,800.00


OH 0.3300 120,000.00 39,600.00
OH 0.0330 150,000.00 4,950.00
OH 0.0330 180,000.00 5,940.00
JUMLAH TENAGA KERJA 103,290.00

m3 0.0300 3,000,000.00 90,000.00


kg 0.4000 20,000.00 8,000.00
Liter 0.1500 1,500.00 225.00
m3 0.0150 3,500,000.00 52,500.00
Lbr 0.3500 150,000.00 52,500.00
Batang 2.0000 60,000.00 120,000.00
JUMLAH HARGA BAHAN 323,225.00

-
JUMLAH HARGA ALAT -
426,515.00
10% 42,651.50
469,166.00
3 X Pemakaian 156,388.67

batan untuk pengecoran beton

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 17,995.00

m3 0.0264 3,000,000.00 79,200.00


kg 0.6000 20,000.00 12,000.00
Batang 0.5000 60,000.00 30,000.00
JUMLAH HARGA BAHAN 121,200.00
#REF! X Pemakaian #REF!

-
JUMLAH HARGA ALAT -
#REF!
10% #REF!
#REF!

beton bertulang (150 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 5.3000 78,500.00 416,050.00


OH 0.2750 100,000.00 27,500.00
OH 1.3000 100,000.00 130,000.00
OH 1.0500 100,000.00 105,000.00
OH 0.2620 100,000.00 26,200.00
OH 0.2650 90,000.00 23,850.00
JUMLAH TENAGA KERJA 728,600.00

m3 0.2000 3,000,000.00 600,000.00


kg 1.5000 20,000.00 30,000.00
Liter 0.4000 1,500.00 600.00
kg 157.5000 -
kg 2.2500 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
JUMLAH HARGA BAHAN 630,600.00

-
JUMLAH HARGA ALAT -
1,359,200.00
10% 135,920.00
1,495,120.00

on bertulang (200 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 5.6500 78,500.00 443,525.00


OH 0.2750 100,000.00 27,500.00
OH 1.5600 100,000.00 156,000.00
OH 1.4000 100,000.00 140,000.00
OH 0.3230 100,000.00 32,300.00
OH 0.2830 90,000.00 25,470.00
JUMLAH TENAGA KERJA 824,795.00

m3 0.2700 -
kg 2.0000 -
Liter 0.6000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
824,795.00
10% 82,479.50
907,274.00

eton bertulang (300 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 7.0500 78,500.00 553,425.00


OH 0.2750 100,000.00 27,500.00
OH 1.6500 100,000.00 165,000.00
OH 2.1000 100,000.00 210,000.00
OH 0.4030 100,000.00 40,300.00
OH 0.3530 90,000.00 31,770.00
JUMLAH TENAGA KERJA 1,027,995.00

m3 0.4000 -
kg 4.0000 -
Liter 2.0000 -
kg 315.0000 -
kg 4.5000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
M3 0.1500 -
Lbr 3.5000 -
Batang 20.0000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
1,027,995.00
10% 102,799.50
1,130,794.00

eton bertulang (200 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 6.3500 78,500.00 498,475.00


OH 0.2750 100,000.00 27,500.00
OH 1.6500 100,000.00 165,000.00
OH 1.4000 100,000.00 140,000.00
OH 0.3330 100,000.00 33,300.00
OH 0.3180 90,000.00 28,620.00
JUMLAH TENAGA KERJA 892,895.00

m3 0.3200 -
kg 3.2000 -
Liter 1.6000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1400 -
Lembar 2.8000 -
Batang 16.0000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
892,895.00
10% 89,289.50
982,184.00

ton bertulang (150 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 5.3000 78,500.00 416,050.00


OH 0.2750 100,000.00 27,500.00
OH 1.3000 100,000.00 130,000.00
OH 1.0500 100,000.00 105,000.00
OH 0.2650 100,000.00 26,500.00
OH 0.2650 90,000.00 23,850.00
JUMLAH TENAGA KERJA 728,900.00
m3 0.3200 -
kg 3.2000 -
Liter 1.6000 -
kg 157.5000 -
kg 2.2500 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1200 -
Lembar 2.8000 -
Batang 32.0000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
728,900.00
10% 72,890.00
801,790.00

eton bertulang (150 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.5300 78,500.00 41,605.00


OH 0.2750 100,000.00 27,500.00
OH 1.3000 100,000.00 130,000.00
OH 1.0500 100,000.00 105,000.00
OH 0.2620 100,000.00 26,200.00
OH 0.2650 90,000.00 23,850.00
JUMLAH TENAGA KERJA 354,155.00

m3 0.2400 -
kg 3.2000 -
Liter 1.6000 -
kg 157.5000 -
kg 2.2500 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1600 -
Lembar 2.8000 -
Batang 24.0000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
354,155.00
10% 35,415.50
389,570.00

eton bertulang (200 kg besi + bekisting)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 5.6500 78,500.00 443,525.00


OH 0.2750 100,000.00 27,500.00
OH 1.5600 100,000.00 156,000.00
OH 1.4000 100,000.00 140,000.00
OH 0.3230 100,000.00 32,300.00
OH 0.2830 90,000.00 25,470.00
JUMLAH TENAGA KERJA 824,795.00

m3 0.2500 -
kg 3.0000 -
Liter 1.2000 -
kg 210.0000 -
kg 3.0000 -
kg 336.0000 -
m3 0.5400 -
m3 0.8100 -
m3 0.1050 -
Lembar 2.5000 -
Batang 14.0000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
824,795.00
10% 82,479.50
907,274.00

aktis beton bertulang (11 x 11) cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1800 78,500.00 14,130.00


OH 0.0200 100,000.00 2,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0060 100,000.00 600.00
OH 0.0090 90,000.00 810.00
JUMLAH TENAGA KERJA 21,540.00

m3 0.0020 -
kg 0.0100 -
Liter 1.2000 -
kg 3.0000 -
kg 0.4500 -
kg 4.0000 -
m3 0.0060 -
m3 0.0090 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
21,540.00
10% 2,154.00
23,694.00

beton bertulang (10 x 15) cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2970 78,500.00 23,314.50


OH 0.0330 100,000.00 3,300.00
OH 0.0330 100,000.00 3,300.00
OH 0.0330 100,000.00 3,300.00
OH 0.0100 100,000.00 1,000.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 35,564.50

m3 0.0030 -
kg 0.0200 -
Liter 1.2000 -
kg 3.6000 -
kg 0.0500 -
kg 5.5000 -
m3 0.0090 -
m3 0.0150 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
35,564.50
10% 3,556.45
39,120.00

AN BETON PRACETAK

han produksi tebal 8cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1320 78,500.00 10,362.00


OH 0.0220 100,000.00 2,200.00
OH 0.0020 100,000.00 200.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 13,392.00

Kg 26.0800 -
Kg 60.8000 -
Kg 82.3200 -
L 17.2000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
13,392.00
10% 1,339.20
14,731.00

han produksi tebal 10 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1650 78,500.00 12,952.50


OH 0.0280 100,000.00 2,800.00
OH 0.0030 100,000.00 300.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 16,772.50

Kg 32.6000 -
Kg 76.0000 -
Kg 102.9000 -
L 21.5000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
16,772.50
10% 1,677.25
18,449.00

han produksi tebal 12 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1980 78,500.00 15,543.00


OH 0.0330 100,000.00 3,300.00
OH 0.0030 100,000.00 300.00
OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 20,043.00

Kg 32.1200 -
Kg 91.2000 -
Kg 123.4800 -
L 25.8000 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
20,043.00
10% 2,004.30
22,047.00

han produksi tebal 15 cm beton f’c 14,5 Mpa (K 175) slump (120 ± 20) mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2480 78,500.00 19,468.00


OH 0.0410 100,000.00 4,100.00
OH 0.0040 100,000.00 400.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 25,138.00

Kg 48.9000 -
Kg 114.0000 -
Kg 154.3500 -
L 32.2500 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
25,138.00
10% 2,513.80
27,651.00

ng untuk plat beton pracetak ( 5 kali pakai)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0070 78,500.00 549.50


OH 0.0760 100,000.00 7,600.00
OH 0.0080 100,000.00 800.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 9,039.50

m3 0.0800 930,847.00 74,467.76


Kg 9.3940 -
m3 0.0050 -
Lbr 0.0800 -
L 0.2000 -
Bh 3.8820 -
JUMLAH HARGA BAHAN 74,467.76

-
JUMLAH HARGA ALAT -
83,507.26
10% 8,350.73
91,857.00

ng untuk balok beton pracetak ( 10-12 kali pakai)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0040 78,500.00 314.00


OH 0.0380 100,000.00 3,800.00
OH 0.0040 100,000.00 400.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 4,604.00

m3 0.0050 -
Lbr 0.0430 -
L 0.2000 -
Bh 0.6930 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
4,604.00
10% 460.40
5,064.00

ng untuk kolom beton pracetak (10-12 kali pakai)


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0040 78,500.00 314.00


OH 0.0380 100,000.00 3,800.00
OH 0.0040 100,000.00 400.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 4,604.00

m3 0.0040 -
Lbr 0.0480 -
L 0.2000 -
Kg 0.0460 -
Bh 0.6930 -
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
4,604.00
10% 460.40
5,064.00

uka bekisting 1 buah komponen plat beton pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0530 78,500.00 4,160.50


OH 0.0180 100,000.00 1,800.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 6,410.50

-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
6,410.50
10% 641.05
7,051.00

uka bekisting 1 buah komponen balok beton pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0890 78,500.00 6,986.50


OH 0.0300 100,000.00 3,000.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 10,436.50

-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
10,436.50
10% 1,043.65
11,480.00

uka bekisting 1 buah komponen Kolom beton pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0710 78,500.00 5,573.50


OH 0.0240 100,000.00 2,400.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 8,423.50
-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
8,423.50
10% 842.35
9,265.00

on untuk 1 buah komponen plat pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0640 78,500.00 5,024.00


OH 0.2440 100,000.00 24,400.00
OH 0.1280 100,000.00 12,800.00
OH 0.0340 100,000.00 3,400.00
OH 0.0730 90,000.00 6,570.00
JUMLAH TENAGA KERJA 52,194.00

-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
52,194.00
10% 5,219.40
57,413.00

on untuk 1 buah komponen balok pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0690 78,500.00 5,416.50


OH 0.2420 100,000.00 24,200.00
OH 0.1380 100,000.00 13,800.00
OH 0.0370 100,000.00 3,700.00
OH 0.0730 90,000.00 6,570.00
JUMLAH TENAGA KERJA 53,686.50

-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
53,686.50
10% 5,368.65
59,055.00

on untuk 1 buah komponen kolom pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0610 78,500.00 4,788.50


OH 0.2130 100,000.00 21,300.00
OH 0.1220 100,000.00 12,200.00
OH 0.0330 100,000.00 3,300.00
OH 0.0730 90,000.00 6,570.00
JUMLAH TENAGA KERJA 48,158.50

-
JUMLAH HARGA BAHAN -

-
JUMLAH HARGA ALAT -
48,158.50
10% 4,815.85
52,974.00

untuk pelat pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.067 Err:502 Err:502


OH 0.067 Err:502 Err:502
OH 0.067 Err:502 Err:502
OH 0.067 Err:502 Err:502
OH 0.134 Err:502 Err:502
OH 0.067 Err:502 Err:502
OH 0.067 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 6.676 -
JUMLAH HARGA BAHAN -

unit hari 0.067 -


Buah hari 1.1 -
JUMLAH HARGA ALAT -
Err:502
10% Err:502
Err:502

s kenaikan lantai
untuk balok pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.061 Err:502 Err:502


OH 0.061 Err:502 Err:502
OH 0.061 Err:502 Err:502
OH 0.061 Err:502 Err:502
OH 0.122 Err:502 Err:502
OH 0.061 Err:502 Err:502
OH 0.061 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 6.11 -
JUMLAH HARGA BAHAN -
unit hari 0.061 -
Buah hari 1.1 -
JUMLAH HARGA ALAT -
Err:502
10% Err:502
Err:502

s kenaikan lantai
ereksi Balok

untuk Kolom pracetak


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.083 Err:502 Err:502


OH 0.083 Err:502 Err:502
OH 0.083 Err:502 Err:502
OH 0.083 Err:502 Err:502
OH 0.166 Err:502 Err:502
OH 0.083 Err:502 Err:502
OH 0.083 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 8.277 -
JUMLAH HARGA BAHAN -

unit hari 0.083 -


Buah hari 2.2 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

s kenaikan lantai
ereksi Kolom
nen plat pracetak ( ± 20 m)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0190 Err:502 Err:502


OH 0.0380 Err:502 Err:502
OH 0.0190 Err:502 Err:502
OH 0.0190 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 1.8970 -
JUMLAH HARGA BAHAN -

UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

nen balok pracetak ( ± 20 m)


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0190 Err:502 Err:502


OH 0.0380 Err:502 Err:502
OH 0.0190 Err:502 Err:502
OH 0.0190 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 1.8970 -
JUMLAH HARGA BAHAN -

UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

nen kolom pracetak ( ± 20 m)

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0190 Err:502 Err:502


OH 0.0380 Err:502 Err:502
OH 0.0190 Err:502 Err:502
OH 0.0190 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

L 1.8970 -
JUMLAH HARGA BAHAN -

UH 0.0190 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

JUMLAH TENAGA KERJA -


- -
Kg 1200.0000 -
Kg 650.0000 -
L 350.0000 -
JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


- -
10% -
- -

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

JUMLAH TENAGA KERJA -


- -
Kg 1850.0000 -
L 400.0000 -
JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


- -
10% -
- -

Grouting Pada Join Pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3670 100,000.00 36,700.00


OH 0.0740 100,000.00 7,400.00
OH 0.0370 90,000.00 3,330.00
JUMLAH TENAGA KERJA 47,430.00
- -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 47,430.00
10% 4,743.00
- 52,173.00

sting join pracetak

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1470 78,500.00 11,539.50


OH 0.1470 100,000.00 14,700.00
OH 0.0150 100,000.00 1,500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 28,189.50

m3 0.0120 -
m3 0.0040 -
Kg 0.2640 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 28,189.50
10% 2,818.95
- 31,008.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2200 78,500.00 17,270.00


OH 0.2200 100,000.00 22,000.00
OH 0.2200 100,000.00 22,000.00
OH 0.0110 90,000.00 990.00
JUMLAH TENAGA KERJA 62,260.00

JUMLAH HARGA BAHAN -


- -
JUMLAH HARGA ALAT -
- 62,260.00
10% 6,226.00
- 68,486.00

RJAAN BESI DAN ALUMUNIUM

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0600 78,500.00 4,710.00


OH 0.0600 100,000.00 6,000.00
OH 0.0060 100,000.00 600.00
OH 0.0030 90,000.00 270.00
JUMLAH TENAGA KERJA 11,580.00

Kg 1.1500 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
11,580.00
10% 1,158.00
12,738.00

a kuda-kuda baja IWF

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0600 80,000.00 4,800.00


OH 0.0600 120,000.00 7,200.00
OH 0.0060 150,000.00 900.00
OH 0.0030 180,000.00 540.00
JUMLAH TENAGA KERJA 13,440.00

Kg 1.1500 16,500.00 18,975.00


JUMLAH HARGA BAHAN 18,975.00

JUMLAH HARGA ALAT -


- 32,415.00
10% 3,241.50
- 35,656.00

rjaan perakitan

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.1000 78,500.00 7,850.00
OH 0.1000 100,000.00 10,000.00
OH 0.0010 100,000.00 100.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 18,400.00

Liter 1.0000 -
Liter 0.1000 -
JUMLAH HARGA BAHAN -

Jam 0.8000 -
JUMLAH HARGA ALAT -
- 18,400.00
10% 1,840.00
- 20,240.00

esi plat baja tebal 2 mm rangkap, rangka baja siku

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0500 78,500.00 82,425.00


OH 1.0500 100,000.00 105,000.00
OH 0.1050 100,000.00 10,500.00
OH 0.0520 90,000.00 4,680.00
JUMLAH TENAGA KERJA 202,605.00

Kg 15.0000 -
Kg 32.8000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


- 202,605.00
10% 20,260.50
- 222,865.00

elasan dengan las listrik


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0400 78,500.00 3,140.00


OH 0.0200 100,000.00 2,000.00
OH 0.0020 100,000.00 200.00
OH 0.0020 90,000.00 180.00
JUMLAH TENAGA KERJA 5,520.00

Kg 0.4000 -
Liter 0.3000 -
Liter 0.0400 -
JUMLAH HARGA BAHAN -

Jam 0.1700 -
JUMLAH HARGA ALAT -
- 5,520.00
10% 552.00
- 6,072.00

a jendela besi scuare tube (25 x 5) cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6500 78,500.00 51,025.00


OH 0.6500 100,000.00 65,000.00
OH 0.0650 100,000.00 6,500.00
OH 0.0320 90,000.00 2,880.00
JUMLAH TENAGA KERJA 125,405.00

m 4.7600 -
m 4.5220 -
cm 20.0000 5,520.00 110,400.00
JUMLAH HARGA BAHAN 110,400.00

JUMLAH HARGA ALAT -


- 235,805.00
10% 23,580.50
- 259,385.00

rolling door besi

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.2000 78,500.00 94,200.00


OH 1.2000 100,000.00 120,000.00
OH 0.1200 100,000.00 12,000.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 226,740.00

m2 1.0000 -
JUMLAH HARGA BAHAN -

JUMLAH HARGA ALAT -


- 226,740.00
10% 22,674.00
- 249,414.00

lipat (folding door) bahan plastik/PVC

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.4400 78,500.00 34,540.00


OH 0.4400 100,000.00 44,000.00
OH 0.0440 100,000.00 4,400.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 84,920.00

m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 84,920.00
10% 8,492.00
- 93,412.00

creen alluminium

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0800 78,500.00 6,280.00


OH 0.8000 100,000.00 80,000.00
OH 0.0800 100,000.00 8,000.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 94,640.00

m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 94,640.00
10% 9,464.00
- 104,104.00

g door alluminium

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 1.0000 100,000.00 100,000.00
OH 0.1000 100,000.00 10,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 193,000.00

m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 193,000.00
10% 19,300.00
- 212,300.00

pintu alluminium

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0430 78,500.00 3,375.50


OH 0.0430 100,000.00 4,300.00
OH 0.0043 100,000.00 430.00
OH 0.0021 90,000.00 189.00
JUMLAH TENAGA KERJA 8,294.50

m 1.1000 -
buah 2.0000 -
Tube 0.0600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,294.50
10% 829.45
- 9,123.00

u alluminium strip lebar 8 cm


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0850 78,500.00 6,672.50


OH 0.0850 100,000.00 8,500.00
OH 0.0085 100,000.00 850.00
OH 0.0042 90,000.00 378.00
JUMLAH TENAGA KERJA 16,400.50

m 4.4000 -
m 14.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,400.50
10% 1,640.05
- 18,040.00

u kaca rangka alluminium

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.0850 78,500.00 6,672.50


OH 0.0850 100,000.00 8,500.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 16,522.50

m 4.4000 -
m 4.5000 -
Tube 0.2700 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,522.50
10% 1,652.25
- 18,174.00

etions Blinds dan Vertical Blinds

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3500 78,500.00 27,475.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 67,595.00

m2 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 67,595.00
10% 6,759.50
- 74,354.00

ali Besi Strip (2 x 3) mm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 1.6700 78,500.00 131,095.00


OH 1.6700 100,000.00 167,000.00
OH 0.1670 100,000.00 16,700.00
OH 0.0830 90,000.00 7,470.00
JUMLAH TENAGA KERJA 322,265.00

kg 6.1770 -
cm 27.0800 5,520.00 149,481.60
JUMLAH HARGA BAHAN 149,481.60
- -
JUMLAH HARGA ALAT -
- 471,746.60
10% 47,174.66
- 518,921.00

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 19,300.00

m2 1.1000 -
cm 11.1100 5,520.00 61,327.20
kg 1.7160 -
JUMLAH HARGA BAHAN 61,327.20
- -
JUMLAH HARGA ALAT -
- 80,627.20
10% 8,062.72
- 88,689.00

dela Nako & Tralis

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.2000 78,500.00 15,700.00
OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 37,790.00

m2 1.1000 -
buah 10.0000 -
m 7.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,790.00
10% 3,779.00
- 41,569.00

g Datar/ Jurai Seng BJLS 28 Lebar 90 cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 37,790.00

m 1.0500 -
kg 0.0150 -
m3 0.0190 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,790.00
10% 3,779.00
- 41,569.00
g ½ Lingkaran D-15 cm, Seng Plat bjls 30 Lebar 45 cm

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.3000 100,000.00 30,000.00
OH 0.0300 100,000.00 3,000.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 45,495.00

m 1.0500 -
kg 0.0100 -
kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 45,495.00
10% 4,549.50
- 50,044.00

ka Besi Hollow 1x40.40.2 mm, Modul 60 x 120 cm, Dinding Partisi

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 48,295.00
M1 3.5000 -
Ls 1.0000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 48,295.00
10% 4,829.50
- 53,124.00

gka Besi Hollow 1 x 40.40.2 mm, Modul 60 x 60 cm, Plafon

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3500 78,500.00 27,475.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 67,595.00

M1 4.0000 -
Ls 1.0000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 67,595.00
10% 6,759.50
- 74,354.00

Atap Pelana Rangka Atap Baja Canai Dingin Profil C75

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)
OH 0.7604 78,500.00 59,691.40
OH 0.7604 100,000.00 76,040.00
OH 0.0760 100,000.00 7,600.00
OH 0.0380 90,000.00 3,420.00
JUMLAH TENAGA KERJA 146,751.40

kg 4.0500 -
JUMLAH HARGA BAHAN -
- -
0.1000 -
JUMLAH HARGA ALAT -
- 146,751.40
10% 14,675.14
- 161,426.00

atap jurai rangka atap baja canai dingin profil C75

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.7340 78,500.00 57,619.00


OH 0.7340 100,000.00 73,400.00
OH 0.0730 100,000.00 7,300.00
OH 0.0370 90,000.00 3,330.00
JUMLAH TENAGA KERJA 141,649.00

kg 4.0500 -
JUMLAH HARGA BAHAN -

0.1000 -
JUMLAH HARGA ALAT -
- 141,649.00
10% 14,164.90
- 155,813.00
ANG KUDA-KUDA BAJA RINGAN + RENG UNTUK ATAP GENTENG BIASA/METAL

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.4500 100,000.00 45,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 66,200.00

M' 3.7200 -
bh 28.0000 -
bh 2.0000 -
M' 5.4000 -
M' 0.1240 -
JUMLAH HARGA BAHAN -

0.1000 -
JUMLAH HARGA ALAT -
- 66,200.00
10% 6,620.00
- 72,820.00

RJAAN PASANGAN DINDING

g bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 2 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 43.5000 1,500.00 65,250.00
m3 0.0800 130,000.00 10,400.00
JUMLAH HARGA BAHAN 201,650.00
-
JUMLAH HARGA ALAT -
282,050.00
10% 28,205.00
310,255.00

g bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 3 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 32.9500 1,500.00 49,425.00
m3 0.0910 130,000.00 11,830.00
JUMLAH HARGA BAHAN 187,255.00
-
JUMLAH HARGA ALAT -
267,655.00
10% 26,765.50
294,420.00

ng bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 26.5500 1,500.00 39,825.00
m3 0.0930 130,000.00 12,090.00
JUMLAH HARGA BAHAN 177,915.00
-
JUMLAH HARGA ALAT -
258,315.00
10% 25,831.50
284,146.00

ng bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 5 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 22.2000 1,500.00 33,300.00
m3 0.1020 130,000.00 13,260.00
JUMLAH HARGA BAHAN 172,560.00
-
JUMLAH HARGA ALAT -
252,960.00
10% 25,296.00
278,256.00

ng Bata Merah (5x11x22) cm tebal 1 batu campuran 1 SP : 6 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 18.5000 1,500.00 27,750.00
m3 0.1220 130,000.00 15,860.00
JUMLAH HARGA BAHAN 169,610.00
-
JUMLAH HARGA ALAT -
250,010.00
10% 25,001.00
275,011.00

ng bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.2000 120,000.00 24,000.00
OH 0.0200 150,000.00 3,000.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 80,400.00

m3 140.0000 900.00 126,000.00


Kg 10.0800 1,500.00 15,120.00
m3 0.0275 9,838.00 270.55
m3 0.0925 130,000.00 12,025.00
JUMLAH HARGA BAHAN 153,415.55
-
JUMLAH HARGA ALAT -
233,815.54
10% 23,381.55
257,197.00

g bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 18.9500 1,500.00 28,425.00
m3 0.0380 130,000.00 4,940.00
JUMLAH HARGA BAHAN 96,365.00
-
JUMLAH HARGA ALAT -
136,565.00
10% 13,656.50
150,221.00
g bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 14.3700 1,500.00 21,555.00
m3 0.0400 130,000.00 5,200.00
JUMLAH HARGA BAHAN 89,755.00
-
JUMLAH HARGA ALAT -
129,955.00
10% 12,995.50
142,950.00

g bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00
m3 70.0000 900.00 63,000.00
Kg 11.5000 1,500.00 17,250.00
m3 0.0430 130,000.00 5,590.00
JUMLAH HARGA BAHAN 85,840.00
-
JUMLAH HARGA ALAT -
126,040.00
10% 12,604.00
138,644.00

g bata merah (5x11x22)cm tebal ½ batu campuran 1 SP : 5 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 9.6800 1,500.00 14,520.00
m3 0.0450 130,000.00 5,850.00
JUMLAH HARGA BAHAN 83,370.00
-
JUMLAH HARGA ALAT -
123,570.00
10% 12,357.00
135,927.00

ng bata merah (5x11x22)cm tebal ½ batu campuran 1 SP : 6 PP


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 8.3200 1,500.00 12,480.00
m3 0.0490 130,000.00 6,370.00
JUMLAH HARGA BAHAN 81,850.00
-
JUMLAH HARGA ALAT -
122,050.00
10% 12,205.00
134,255.00

g bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 8 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 6.5000 1,500.00 9,750.00
m3 0.0500 130,000.00 6,500.00
JUMLAH HARGA BAHAN 79,250.00
-
JUMLAH HARGA ALAT -
119,450.00
10% 11,945.00
131,395.00

ng bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 3KP :10PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 4.5000 1,500.00 6,750.00
m3 0.0150 9,838.00 147.57
m3 0.0500 130,000.00 6,500.00
JUMLAH HARGA BAHAN 76,397.57
-
JUMLAH HARGA ALAT -
116,597.57
10% 11,659.76
128,257.00

g bata merah (5x11x22)cm tebal ½ batu campuran 1SM : 1KP :1PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 0.0180 1,500.00 27.00
m3 0.0180 9,838.00 177.08
m3 0.0180 130,000.00 2,340.00
JUMLAH HARGA BAHAN 65,544.08
-
JUMLAH HARGA ALAT -
105,744.08
10% 10,574.41
116,318.00

g bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 70.0000 900.00 63,000.00


Kg 0.0140 1,500.00 21.00
m3 0.0140 9,838.00 137.73
m3 0.0280 130,000.00 3,640.00
JUMLAH HARGA BAHAN 66,798.73
-
JUMLAH HARGA ALAT -
106,998.73
10% 10,699.87
117,698.00

g conblock HB20 campuran 1SP : 3PP


Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3500 80,000.00 28,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0180 180,000.00 3,240.00
JUMLAH TENAGA KERJA 51,490.00

m3 12.5000 200,000.00 2,500,000.00


Kg 30.3200 1,500.00 45,480.00
m3 0.7280 130,000.00 94,640.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 2,642,780.00
-
JUMLAH HARGA ALAT -
2,694,270.00
10% 269,427.00
2,963,697.00

g conblock HB20 campuran 1SP:4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3500 80,000.00 28,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0180 180,000.00 3,240.00
JUMLAH TENAGA KERJA 51,490.00

m3 12.5000 200,000.00 2,500,000.00


Kg 24.2600 1,500.00 36,390.00
m3 0.7720 130,000.00 100,360.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 2,639,410.00
-
JUMLAH HARGA ALAT -
2,690,900.00
10% 269,090.00
2,959,990.00

g conblock HB15 campuran 1SP :3PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3200 80,000.00 25,600.00


OH 0.1200 120,000.00 14,400.00
OH 0.0120 150,000.00 1,800.00
OH 0.0160 180,000.00 2,880.00
JUMLAH TENAGA KERJA 44,680.00

m3 12.5000 200,000.00 2,500,000.00


Kg 22.7400 1,500.00 34,110.00
m3 0.5500 130,000.00 71,500.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 2,608,270.00
-
JUMLAH HARGA ALAT -
2,652,950.00
10% 265,295.00
2,918,245.00

ng conblock HB15 campuran 1SP :4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3200 80,000.00 25,600.00


OH 0.1200 120,000.00 14,400.00
OH 0.0120 150,000.00 1,800.00
OH 0.0160 180,000.00 2,880.00
JUMLAH TENAGA KERJA 44,680.00

m3 12.5000 200,000.00 2,500,000.00


Kg 18.2000 1,500.00 27,300.00
m3 0.5820 130,000.00 75,660.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 2,605,620.00
-
JUMLAH HARGA ALAT -
2,650,300.00
10% 265,030.00
2,915,330.00

ng conblock HB10 campuran 1SP :3PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 12.5000 150,000.00 1,875,000.00


Kg 15.1600 1,500.00 22,740.00
m3 0.3640 130,000.00 47,320.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 1,947,720.00
- -
JUMLAH HARGA ALAT -
- 1,987,920.00
10% 198,792.00
- 2,186,712.00

ng conblock HB10 campuran 1SP :4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

m3 12.5000 150,000.00 1,875,000.00


Kg 12.1300 1,500.00 18,195.00
m3 0.3880 130,000.00 50,440.00
Kg 0.2800 9,500.00 2,660.00
JUMLAH HARGA BAHAN 1,946,295.00
-
JUMLAH HARGA ALAT -
1,986,495.00
10% 198,649.50
2,185,144.00

ng Terawang (Rooster) 12 x 11 x 24 Campuran 1SP : 3PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

Buah 30.0000 6,000.00 180,000.00


Kg 11.0000 1,500.00 16,500.00
m3 0.0350 130,000.00 4,550.00
JUMLAH HARGA BAHAN 201,050.00
-
JUMLAH HARGA ALAT -
241,250.00
10% 24,125.00
265,375.00

ng Terawang (Rooster) 12 x 11 x 24 Campuran 1SP : 4PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1000 120,000.00 12,000.00
OH 0.0100 150,000.00 1,500.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 40,200.00

Bh 30.0000 6,000.00 180,000.00


Kg 11.0000 1,500.00 16,500.00
M3 0.0350 130,000.00 4,550.00
JUMLAH HARGA BAHAN 201,050.00
-
JUMLAH HARGA ALAT -
241,250.00
10% 24,125.00
265,375.00
ing bata berongga ekspose 12x11x24 campuran 1 SP : 3 PP

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 46,950.00

m3 70.0000 3,249.99 227,499.00


Kg 14.0000 1,500.00 21,000.00
m3 0.0320 130,000.00 4,160.00
JUMLAH HARGA BAHAN 252,659.00
-
JUMLAH HARGA ALAT -
299,609.00
10% 29,960.90
329,569.00

ng bata ringan tebal 7,5 cm dengan mortar siap pakai B.

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.350 78,500.00 27,475.00


OH 0.130 100,000.00 13,000.00
OH 0.013 100,000.00 1,300.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 42,045.00

m3 0.075 15,000,000.00 1,125,000.00


Kg 2.772 350,000.00 970,200.00
JUMLAH HARGA BAHAN 2,095,200.00

Ls 0.1000 2,095,200.00 209,520.00


JUMLAH HARGA ALAT -
2,242,005.00
10% 224,200.50
2,466,205.00

ng bata ringan tebal 10 cm dengan mortar siap pakai

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.350 78,500.00 27,475.00


OH 0.130 100,000.00 13,000.00
OH 0.013 100,000.00 1,300.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 42,045.00

m3 0.1 -
Kg 4.4 -
JUMLAH HARGA BAHAN -

Ls 0.1000 - -
JUMLAH HARGA ALAT -
- 42,045.00
10% 4,204.50
- 46,249.00

RJAAN PLESTERAN

eran 1SP : 1PP tebal 15 mm.

Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp.) (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 15.5040 1,500.00 23,256.00


m3 0.0160 130,000.00 2,080.00
JUMLAH HARGA BAHAN 25,336.00
-
JUMLAH HARGA ALAT -
66,736.00
10% 6,673.60
73,409.00

eran 1SP : 2PP tebal 15 mm.

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 46,950.00

Kg 10.2240 1,500.00 15,336.00


m3 0.0200 130,000.00 2,600.00
JUMLAH HARGA BAHAN 17,936.00
-
JUMLAH HARGA ALAT -
64,886.00
10% 6,488.60
71,374.00
eran 1SP : 3PP tebal 15mm.

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 46,950.00

Kg 7.7760 1,500.00 11,664.00


m3 0.0230 130,000.00 2,990.00
JUMLAH HARGA BAHAN 14,654.00
-
JUMLAH HARGA ALAT -
61,604.00
10% 6,160.40
67,764.00

eran 1SP : 4PP tebal 15 mm

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 80,000.00 24,000.00


OH 0.1500 120,000.00 18,000.00
OH 0.0150 150,000.00 2,250.00
OH 0.0150 180,000.00 2,700.00
JUMLAH TENAGA KERJA 46,950.00

Kg 6.2400 1,500.00 9,360.00


m3 0.0240 130,000.00 3,120.00
JUMLAH HARGA BAHAN 12,480.00
-
JUMLAH HARGA ALAT -
59,430.00
10% 5,943.00
65,373.00

eran 1SP : 5PP tebal 15 mm

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 5.1840 -
m3 0.0260 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00
Kg 4.4160 -
m3 0.0270 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 3.9360 -
m3 0.0280 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 3.4560 -
m3 0.0290 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3600 78,500.00 28,260.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 43,080.00

Kg 5.7600 -
m3 0.0030 -
m3 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3600 78,500.00 28,260.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 43,080.00

Kg 3.0000 -
m3 0.0050 -
m3 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3600 78,500.00 28,260.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 43,080.00

m3 0.0090 -
m3 0.0090 -
m3 0.0090 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3600 78,500.00 28,260.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 43,080.00

m3 0.0070 -
m3 0.0070 -
m3 0.0150 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,080.00
10% 4,308.00
- 47,388.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.4000 78,500.00 31,400.00
OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 55,380.00

Kg 13.6320 -
m3 0.0270 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 43,580.00

Kg 10.3680 -
m3 0.0310 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 43,580.00
10% 4,358.00
- 47,938.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 55,380.00

Kg 8.3200 -
m3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 55,380.00

Kg 6.9120 -
m3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 55,380.00

Kg 5.8880 -
m3 0.0360 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,380.00
10% 5,538.00
- 60,918.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4400 78,500.00 34,540.00


OH 0.2200 100,000.00 22,000.00
OH 0.0220 100,000.00 2,200.00
OH 0.0220 90,000.00 1,980.00
JUMLAH TENAGA KERJA 60,720.00

m3 0.0090 -
m3 0.0090 -
m3 0.0180 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 60,720.00
10% 6,072.00
- 66,792.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,795.00

Kg 5.1840 -
m3 0.0260 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0800 78,500.00 6,280.00


OH 0.4000 100,000.00 40,000.00
OH 0.0400 100,000.00 4,000.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 50,640.00

Kg 0.5000 -
m3 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 50,640.00
10% 5,064.00
- 55,704.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4500 78,500.00 35,325.00


OH 0.2250 100,000.00 22,500.00
OH 0.0230 100,000.00 2,300.00
OH 0.0230 90,000.00 2,070.00
JUMLAH TENAGA KERJA 62,195.00

Kg 10.0000 -
Kg 15.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 62,195.00
10% 6,219.50
- 68,414.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.4500 78,500.00 35,325.00
OH 0.2250 100,000.00 22,500.00
OH 0.0230 100,000.00 2,300.00
OH 0.0230 90,000.00 2,070.00
JUMLAH TENAGA KERJA 62,195.00

Kg 10.0000 -
Kg 15.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 62,195.00
10% 6,219.50
- 68,414.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 35,900.00

Kg 4.3200 -
m3 0.0060 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,900.00
10% 3,590.00
- 39,490.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,795.00
Kg 3.1080 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0700 78,500.00 5,495.00


OH 0.0350 100,000.00 3,500.00
OH 0.0040 100,000.00 400.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 9,755.00

Kg 1.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 9,755.00
10% 975.50
- 10,730.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 6.3400 -
m3 0.0120 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 27,600.00

Kg 3.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3000 78,500.00 23,550.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0150 90,000.00 1,350.00
JUMLAH TENAGA KERJA 41,400.00

Kg 16.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,400.00
10% 4,140.00
- 45,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 27,600.00

Kg 3.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00

UAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

ai Granit ukuran 60 x 60 cm (Polished)

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.6000 78,500.00 47,100.00


OH 0.3000 100,000.00 30,000.00
OH 0.0300 100,000.00 3,000.00
OH 0.0300 90,000.00 2,700.00
JUMLAH TENAGA KERJA 82,800.00

Bh 3.1000 55,000.00 170,500.00


kg 9.6000 1,300.00 12,480.00
Kg 1.5000 3,689.18 5,533.77
M3 0.0450 110,000.00 4,950.00
JUMLAH HARGA BAHAN 193,463.77
-
JUMLAH HARGA ALAT -
276,263.77
10% 27,626.38
303,890.00
ai Granit ukuran 60 x 60 cm (Unpolished)

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.6000 80,000.00 48,000.00


OH 0.3000 120,000.00 36,000.00
OH 0.0300 150,000.00 4,500.00
OH 0.0300 180,000.00 5,400.00
JUMLAH TENAGA KERJA 93,900.00

Bh 3.1000 20,000.00 62,000.00


kg 9.6000 1,500.00 14,400.00
Kg 1.5000 1,500.00 2,250.00
M3 0.0450 130,000.00 5,850.00
JUMLAH HARGA BAHAN 84,500.00
-
JUMLAH HARGA ALAT -
178,400.00
10% 17,840.00
196,240.00

ai Granit ukuran 30 x 60 cm (Unpolished)

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00 0.52


OH 0.1300 100,000.00 13,000.00 0.26
OH 0.0130 100,000.00 1,300.00 0.026
OH 0.0130 90,000.00 1,170.00 0.026
JUMLAH TENAGA KERJA 35,880.00

Bh 5.5000 40,000.00 220,000.00 5.55555556


kg 10.0000 1,300.00 13,000.00 20
Kg 1.5000 3,689.18 5,533.77 3
M3 0.0450 110,000.00 4,950.00 0.09
JUMLAH HARGA BAHAN 243,483.77
-
JUMLAH HARGA ALAT -
279,363.77
10% 27,936.38
307,300.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.2500 78,500.00 19,625.00
OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 11.8700 -
kg 10.0000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2700 78,500.00 21,195.00


OH 0.1350 100,000.00 13,500.00
OH 0.0140 100,000.00 1,400.00
OH 0.0140 90,000.00 1,260.00
JUMLAH TENAGA KERJA 37,355.00

Bh 26.5000 -
kg 10.4000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,355.00
10% 3,735.50
- 41,090.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.1300 100,000.00 13,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 35,880.00

Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2700 78,500.00 21,195.00


OH 0.1350 100,000.00 13,500.00
OH 0.0140 100,000.00 1,400.00
OH 0.0140 90,000.00 1,260.00
JUMLAH TENAGA KERJA 37,355.00

Bh 26.5000 -
kg 10.4000 -
Kg 1.6200 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,355.00
10% 3,735.50
- 41,090.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.1300 100,000.00 13,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 35,880.00
Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.1300 100,000.00 13,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 35,880.00
Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.1300 100,000.00 13,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 35,880.00

Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2400 78,500.00 18,840.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0120 90,000.00 1,080.00
JUMLAH TENAGA KERJA 33,120.00

Bh 3.1000 -
kg 9.6000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 33,120.00
10% 3,312.00
- 36,432.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 34,595.00

Bh 6.6300 -
kg 9.8000 -
Kg 1.3000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 34,595.00
10% 3,459.50
- 38,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2600 78,500.00 20,410.00


OH 0.1300 100,000.00 13,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 35,880.00

Bh 11.8700 -
kg 10.0000 -
Kg 1.5000 -
M3 0.0450 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 35,880.00
10% 3,588.00
- 39,468.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 5.3000 -
kg 1.6500 -
M3 0.0040 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


-
OH 0.0900 78,500.00 7,065.00
OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.2400 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.2400 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 1.7000 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 2.6500 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0090 100,000.00 900.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 17,415.00

Bh 3.5300 -
kg 1.1400 -
Kg 0.1000 -
M3 0.0030 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,415.00
10% 1,741.50
- 19,156.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3600 78,500.00 28,260.00


OH 0.1800 100,000.00 18,000.00
OH 0.0180 100,000.00 1,800.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 49,680.00

M3 0.0360 -
Kg 0.1000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 49,680.00
10% 4,968.00
- 54,648.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 53.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 106.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 3.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 10.0000 -
Kg 8.1900 -
M3 0.0450 -
Kg 1.6200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 11.8700 -
Kg 10.0000 -
M3 0.0450 -
Kg 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 26.5000 -
Kg 10.4000 -
M3 0.0450 -
Kg 1.6200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 1.0500 78,500.00 82,425.00
OH 0.5250 100,000.00 52,500.00
OH 0.0530 100,000.00 5,300.00
OH 0.0530 90,000.00 4,770.00
JUMLAH TENAGA KERJA 144,995.00

Bh 33.0000 -
Kg 9.8000 -
M3 0.0450 -
Kg 4.3700 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,995.00
10% 14,499.50
- 159,494.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 11.8700 -
Kg 14.1500 -
M3 0.0390 -
Kg 2.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.0900 78,500.00 7,065.00
OH 0.0900 100,000.00 9,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 20,015.00

Bh 5.3000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.0250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 20,015.00

Bh 10.6000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 78,500.00 7,065.00


OH 0.0900 100,000.00 9,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 20,015.00

Bh 5.3000 -
Kg 0.5700 -
M3 0.0015 -
Kg 0.0130 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7500 78,500.00 58,875.00


OH 0.7500 100,000.00 75,000.00
OH 0.0750 100,000.00 7,500.00
OH 0.0380 90,000.00 3,420.00
JUMLAH TENAGA KERJA 144,795.00

Bh 5.3000 -
Kg 1.1400 -
M3 0.0030 -
Kg 0.1000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,795.00
10% 14,479.50
- 159,274.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 1.0600 -
Kg 8.1900 -
M3 0.0450 -
Kg 0.6500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1700 78,500.00 13,345.00


OH 0.1700 100,000.00 17,000.00
OH 0.0170 100,000.00 1,700.00
OH 0.0090 90,000.00 810.00
JUMLAH TENAGA KERJA 32,855.00

m2 1.0500 -
Kg 0.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 32,855.00
10% 3,285.50
- 36,140.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1200 78,500.00 9,420.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00
m2 1.0500 -
Kg 0.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

m2 1.0500 -
Kg 0.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

m2 1.0500 -
Kg 0.6000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 0.5000 100,000.00 50,000.00
OH 0.0500 100,000.00 5,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 138,000.00

Bh 86.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 138,000.00
10% 13,800.00
- 151,800.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 26.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.9400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 106.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.9000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 53.0000 -
Kg 9.3000 -
M3 0.0180 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9000 78,500.00 70,650.00


OH 0.4500 100,000.00 45,000.00
OH 0.0450 100,000.00 4,500.00
OH 0.0450 90,000.00 4,050.00
JUMLAH TENAGA KERJA 124,200.00

Bh 26.5000 -
Kg 9.3000 -
M3 0.0180 -
Kg 1.9400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 124,200.00
10% 12,420.00
- 136,620.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.3000 78,500.00 102,050.00


OH 0.6500 100,000.00 65,000.00
OH 0.0650 100,000.00 6,500.00
OH 0.0650 90,000.00 5,850.00
JUMLAH TENAGA KERJA 179,400.00

Bh 1.0600 -
Kg 12.4400 -
M3 0.0250 -
Kg 0.6500 -
Bh 3.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 179,400.00
10% 17,940.00
- 197,340.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 0.5000 100,000.00 50,000.00
OH 0.0500 100,000.00 5,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 138,000.00

Bh 63.0000 -
Kg 12.4400 -
M3 0.0250 -
Kg 2.7500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 138,000.00
10% 13,800.00
- 151,800.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 1.1000 -
Kg 11.7500 -
M3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 0.3500 100,000.00 35,000.00
OH 0.0350 100,000.00 3,500.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 96,600.00

Bh 1.1000 -
Kg 11.7500 -
M3 0.0350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,600.00
10% 9,660.00
- 106,260.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 28,995.00

Bh 11.8700 -
Kg 0.3500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 28,995.00
10% 2,899.50
- 31,894.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3500 78,500.00 27,475.00


OH 0.1750 100,000.00 17,500.00
OH 0.0170 100,000.00 1,700.00
OH 0.0020 90,000.00 180.00
JUMLAH TENAGA KERJA 46,855.00

m 2.2000 -
Kg 0.2500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,855.00
10% 4,685.50
- 51,540.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1200 78,500.00 9,420.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00

Kg 5.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0800 78,500.00 6,280.00


OH 0.0800 100,000.00 8,000.00
OH 0.0080 100,000.00 800.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 15,440.00

Bh 1.7600 -
Kg 0.0800 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 15,440.00
10% 1,544.00
- 16,984.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1200 78,500.00 9,420.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00

M3 0.0030 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0025 90,000.00 225.00
JUMLAH TENAGA KERJA 47,350.00

M2 1.0100 -
M3 0.0500 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0025 90,000.00 225.00
JUMLAH TENAGA KERJA 47,350.00

M2 1.01 -
M3 0.07 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0025 90,000.00 225.00
JUMLAH TENAGA KERJA 47,350.00

M2 1.0100 -
M 3
0.0500 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0025 90,000.00 225.00
JUMLAH TENAGA KERJA 47,350.00

M2 1.0100 -
M3 0.0700 -
JUMLAH HARGA BAHAN -
-
% 0.1000 - -
JUMLAH HARGA ALAT -
- 47,350.00
10% 4,735.00
- 52,085.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,795.00

Lbr 0.3650 -
bh 20.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.0300 78,500.00 2,355.00
OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 10,415.00

m2 1.1000 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,415.00
10% 1,041.50
- 11,456.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1200 78,500.00 9,420.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00

Lembar 12.0000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1200 78,500.00 9,420.00


OH 0.1200 100,000.00 12,000.00
OH 0.0120 100,000.00 1,200.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00

Lembar 5.8000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 19,300.00

Lembar 1.5000 -
kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 19,300.00

Lembar 0.3750 -
kg 0.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8000 78,500.00 62,800.00


OH 0.8000 100,000.00 80,000.00
OH 0.0800 100,000.00 8,000.00
OH 0.0400 90,000.00 3,600.00
JUMLAH TENAGA KERJA 154,400.00

m3 0.0150 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 154,400.00
10% 15,440.00
- 169,840.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 13,800.00

Lembar 0.3640 -
kg 0.1100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.5000 78,500.00 39,250.00


OH 0.5000 100,000.00 50,000.00
OH 0.0500 100,000.00 5,000.00
OH 0.0250 90,000.00 2,250.00
JUMLAH TENAGA KERJA 96,500.00

m 3.6000 -
kg 0.1500 -
Buah 1.0500 -
Lembar 1.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 96,500.00
10% 9,650.00
- 106,150.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0500 78,500.00 3,925.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0030 90,000.00 270.00
JUMLAH TENAGA KERJA 9,695.00

m 1.0500 -
kg 0.0100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 9,695.00
10% 969.50
- 10,664.00
angit-langit besi hollow 40.40
an Alumunium ( A.9.21)
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0750 90,000.00 6,750.00
JUMLAH TENAGA KERJA 46,025.00

m2 1.0500 -
bh 18.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,025.00
10% 4,602.50
- 50,627.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0050 90,000.00 450.00
JUMLAH TENAGA KERJA 13,800.00

M' 1.0500 -
bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0075 100,000.00 750.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,745.00

Bh 25.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,745.00
10% 2,074.50
- 22,819.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,795.00

Bh 25.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,795.00

Bh 12.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,795.00
10% 2,079.50
- 22,874.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0020 90,000.00 180.00
JUMLAH TENAGA KERJA 53,580.00

Bh 5.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0020 90,000.00 180.00
JUMLAH TENAGA KERJA 53,580.00

Bh 5.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4000 78,500.00 31,400.00


OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0020 90,000.00 180.00
JUMLAH TENAGA KERJA 53,580.00

Bh 4.0000 -
Kg 8.0000 -
M3 0.0320 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 53,580.00
10% 5,358.00
- 58,938.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0670 100,000.00 6,700.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,020.00

Lbr 0.6000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,020.00
10% 1,902.00
- 20,922.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,010.00

Lbr 0.5000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,010.00
10% 2,001.00
- 22,011.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0750 100,000.00 7,500.00
OH 0.0080 100,000.00 800.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 20,010.00

Lbr 0.6000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,010.00
10% 2,001.00
- 22,011.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.6000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.7500 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.3500 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.4200 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.4400 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.5100 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.8000 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.1400 78,500.00 10,990.00
OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.3700 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.3800 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00
Lbr 0.4600 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.4900 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1400 78,500.00 10,990.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0070 90,000.00 630.00
JUMLAH TENAGA KERJA 19,320.00

Lbr 0.5700 -
Kg 0.1200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,320.00
10% 1,932.00
- 21,252.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 2.4000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 2.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 2.0500 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 1.2000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 0.1500 100,000.00 15,000.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 24,510.00

Lbr 1.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 24,510.00
10% 2,451.00
- 26,961.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0840 78,500.00 6,594.00


OH 0.1250 100,000.00 12,500.00
OH 0.0130 100,000.00 1,300.00
OH 0.0040 90,000.00 360.00
JUMLAH TENAGA KERJA 20,754.00

Lbr 1.1000 -
Bh 6.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,754.00
10% 2,075.40
- 22,829.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 27,600.00

Bh 11.0000 -
Kg 0.0300 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 27,600.00
10% 2,760.00
- 30,360.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.3000 100,000.00 30,000.00
OH 0.0030 100,000.00 300.00
OH 0.0100 90,000.00 900.00
JUMLAH TENAGA KERJA 46,900.00

Bh 6.9000 -
Lbr 0.3500 -
Kg 0.0300 -
Bh 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 46,900.00
10% 4,690.00
- 51,590.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 26,790.00

Bh 1.3000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 26,790.00
10% 2,679.00
- 29,469.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2000 78,500.00 15,700.00


OH 0.1000 100,000.00 10,000.00
OH 0.0100 100,000.00 1,000.00
OH 0.0010 90,000.00 90.00
JUMLAH TENAGA KERJA 26,790.00

Bh 2.0000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 26,790.00
10% 2,679.00
- 29,469.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1660 78,500.00 13,031.00


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 41,251.00

Bh 30.0000 -
Kg 0.2000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 41,251.00
10% 4,125.10
- 45,376.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.4000 78,500.00 31,400.00
OH 0.2000 100,000.00 20,000.00
OH 0.0200 100,000.00 2,000.00
OH 0.0200 90,000.00 1,800.00
JUMLAH TENAGA KERJA 55,200.00

Bh 3.5000 -
Kg 0.0500 -
Kg 10.8000 -
M3 0.0320 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,200.00
10% 5,520.00
- 60,720.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1250 78,500.00 9,812.50


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 37,852.50

Bh 2.0000 -
Kg 0.0500 -
M3 0.0035 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,852.50
10% 3,785.25
- 41,637.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2500 78,500.00 19,625.00


OH 0.1500 100,000.00 15,000.00
OH 0.0150 100,000.00 1,500.00
OH 0.0130 90,000.00 1,170.00
JUMLAH TENAGA KERJA 37,295.00

Bh 1.1000 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,295.00
10% 3,729.50
- 41,024.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1250 78,500.00 9,812.50


OH 0.2500 100,000.00 25,000.00
OH 0.0250 100,000.00 2,500.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 37,852.50

Lbr 0.4000 -
Kg 0.0500 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 37,852.50
10% 3,785.25
- 41,637.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

- -
OH 0.1200 78,500.00 9,420.00
OH 0.0600 100,000.00 6,000.00
OH 0.0060 100,000.00 600.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 16,560.00

Lbr 0.7000 -
Kg 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,560.00
10% 1,656.00
- 18,216.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0700 100,000.00 7,000.00
OH 0.0070 100,000.00 700.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 20,015.00

Lbr 0.3000 -
Kg 0.0400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,015.00
10% 2,001.50
- 22,016.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.7500 100,000.00 75,000.00
OH 0.0800 100,000.00 8,000.00
OH 0.0060 90,000.00 540.00
JUMLAH TENAGA KERJA 95,315.00

Lbr 1.0500 -
Kg 0.0200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 95,315.00
10% 9,531.50
- 104,846.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1000 78,500.00 7,850.00


OH 1.0000 100,000.00 100,000.00
OH 0.1000 100,000.00 10,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 122,350.00

Bh 1.2000 -
Kg 0.0400 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 122,350.00
10% 12,235.00
- 134,585.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 78,500.00 11,775.00


OH 0.0500 100,000.00 5,000.00
OH 0.0050 100,000.00 500.00
OH 0.0080 90,000.00 720.00
JUMLAH TENAGA KERJA 17,995.00

M2 1.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,995.00
10% 1,799.50
- 19,794.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 7.0000 78,500.00 549,500.00


OH 21.0000 100,000.00 2,100,000.00
OH 2.1000 100,000.00 210,000.00
OH 0.3500 90,000.00 31,500.00
JUMLAH TENAGA KERJA 2,891,000.00

m3 1.1000 -
Kg 1.2500 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,891,000.00
10% 289,100.00
- 3,180,100.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.0000 78,500.00 471,000.00


OH 18.0000 100,000.00 1,800,000.00
OH 1.8000 100,000.00 180,000.00
OH 0.3000 90,000.00 27,000.00
JUMLAH TENAGA KERJA 2,478,000.00

m3 1.2000 -
Kg 1.2500 -
Kg 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,478,000.00
10% 247,800.00
- 2,725,800.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.3500 78,500.00 27,475.00
OH 1.0500 100,000.00 105,000.00
OH 0.1050 100,000.00 10,500.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 144,595.00

m3 0.0400 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,595.00
10% 14,459.50
- 159,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3500 78,500.00 27,475.00


OH 1.0500 100,000.00 105,000.00
OH 0.1050 100,000.00 10,500.00
OH 0.0180 90,000.00 1,620.00
JUMLAH TENAGA KERJA 144,595.00

m3 0.0400 -
Kg 0.0500 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 144,595.00
10% 14,459.50
- 159,054.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 3.0000 100,000.00 300,000.00
OH 0.3000 100,000.00 30,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 413,000.00

m3 0.0400 -
Kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 413,000.00
10% 41,300.00
- 454,300.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8000 78,500.00 62,800.00


OH 2.4000 100,000.00 240,000.00
OH 0.2400 100,000.00 24,000.00
OH 0.0400 90,000.00 3,600.00
JUMLAH TENAGA KERJA 330,400.00

m3 0.0240 -
Kg 0.3000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.0000 78,500.00 78,500.00


OH 3.0000 100,000.00 300,000.00
OH 0.3000 100,000.00 30,000.00
OH 0.0500 90,000.00 4,500.00
JUMLAH TENAGA KERJA 413,000.00

m3 0.0640 -
Kg 0.5000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 413,000.00
10% 41,300.00
- 454,300.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7000 78,500.00 54,950.00


OH 2.1000 100,000.00 210,000.00
OH 0.2100 100,000.00 21,000.00
OH 0.0350 90,000.00 3,150.00
JUMLAH TENAGA KERJA 289,100.00

m3 0.0250 -
kg 0.0300 -
kg 0.5000 -
Lembar 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 289,100.00
10% 28,910.00
- 318,010.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8000 78,500.00 62,800.00


OH 2.4000 100,000.00 240,000.00
OH 0.2400 100,000.00 24,000.00
OH 0.0400 90,000.00 3,600.00
JUMLAH TENAGA KERJA 330,400.00

m3 0.0256 -
kg 0.0300 -
kg 0.5000 -
Lembar 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.67 78,500.00 52,595.00


OH 2.000 100,000.00 200,000.00
OH 0.2 100,000.00 20,000.00
OH 0.335 90,000.00 30,150.00
JUMLAH TENAGA KERJA 302,745.00

m3 0.06 -
kg 0.15 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 302,745.00
10% 30,274.50
- 333,019.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8 78,500.00 62,800.00


OH 2.400 100,000.00 240,000.00
OH 0.24 100,000.00 24,000.00
OH 0.04 90,000.00 3,600.00
JUMLAH TENAGA KERJA 330,400.00

m3 0.025 -
kg 0.03 -
kg 0.3 -
Lembar 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 330,400.00
10% 33,040.00
- 363,440.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.85 78,500.00 66,725.00


OH 2.550 100,000.00 255,000.00
OH 0.255 100,000.00 25,500.00
OH 0.043 90,000.00 3,870.00
JUMLAH TENAGA KERJA 351,095.00

m3 0.025 -
kg 0.03 -
kg 0.8 -
Lembar 1.000 -
Lembar 0.5 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 351,095.00
10% 35,109.50
- 386,204.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.000 78,500.00 314,000.00


OH 12.000 100,000.00 1,200,000.00
OH 1.200 100,000.00 120,000.00
OH 0.2 90,000.00 18,000.00
JUMLAH TENAGA KERJA 1,652,000.00

m3 1.100 -
kg 15.000 -
kg 5.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 1,652,000.00
10% 165,200.00
- 1,817,200.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.700 78,500.00 525,950.00


OH 20.100 100,000.00 2,010,000.00
OH 2.010 100,000.00 201,000.00
OH 0.335 90,000.00 30,150.00
JUMLAH TENAGA KERJA 2,767,100.00

m3 1.200 -
kg 15.000 -
kg 5.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 2,767,100.00
10% 276,710.00
- 3,043,810.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.700 78,500.00 525,950.00


OH 20.100 100,000.00 2,010,000.00
OH 2.010 100,000.00 201,000.00
OH 0,335 90,000.00 30,150,000.00
JUMLAH TENAGA KERJA 32,886,950.00

m3 1.100 -
kg 15.000 -
kg 3.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 32,886,950.00
10% 3,288,695.00
- 36,175,645.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.1 78,500.00 7,850.00
OH 0.1 100,000.00 10,000.00
OH 0.01 100,000.00 1,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 19,300.00

m3 0.014 -
m3 0.036 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1 78,500.00 7,850.00


OH 0.1 100,000.00 10,000.00
OH 0.01 100,000.00 1,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 19,300.00

m3 0.014 -
m3 0.057 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 19,300.00
10% 1,930.00
- 21,230.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.12 78,500.00 9,420.00


OH 0.12 100,000.00 12,000.00
OH 0.012 100,000.00 1,200.00
OH 0.006 90,000.00 540.00
JUMLAH TENAGA KERJA 23,160.00

m3 0.014 -
m3 0.057 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,160.00
10% 2,316.00
- 25,476.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.15 78,500.00 11,775.00


OH 0.3 100,000.00 30,000.00
OH 0.03 100,000.00 3,000.00
OH 0.075 90,000.00 6,750.00
JUMLAH TENAGA KERJA 51,525.00

m3 0.0154 -
kg 0.2 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 51,525.00
10% 5,152.50
- 56,677.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2 78,500.00 15,700.00


OH 0.3 100,000.00 30,000.00
OH 0.03 100,000.00 3,000.00
OH 0.01 90,000.00 900.00
JUMLAH TENAGA KERJA 49,600.00

m3 0.0163 -
kg 0.25 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 49,600.00
10% 4,960.00
- 54,560.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1 78,500.00 7,850.00


OH 0.2 100,000.00 20,000.00
OH 0.02 100,000.00 2,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 30,300.00

m3 0.0108 -
kg 0.1 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,300.00
10% 3,030.00
- 33,330.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1 78,500.00 7,850.00


OH 0.2 100,000.00 20,000.00
OH 0.02 100,000.00 2,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 30,300.00

m3 0.011 -
kg 0.05 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,300.00
10% 3,030.00
- 33,330.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.15 78,500.00 11,775.00


OH 0.45 100,000.00 45,000.00
OH 0.045 100,000.00 4,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 61,995.00

m3 0.028 -
kg 0.15 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,995.00
10% 6,199.50
- 68,194.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.15 78,500.00 11,775.00


OH 0.45 100,000.00 45,000.00
OH 0.045 100,000.00 4,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 61,995.00

m3 0.028 -
kg 0.15 -
Lembar 0.86 -
kg 0.56 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,995.00
10% 6,199.50
- 68,194.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2 78,500.00 15,700.00


OH 0.6 100,000.00 60,000.00
OH 0.06 100,000.00 6,000.00
OH 0.01 90,000.00 900.00
JUMLAH TENAGA KERJA 82,600.00

m3 0.028 -
kg 0.15 -
Lembar 0.86 -
kg 0.56 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 82,600.00
10% 8,260.00
- 90,860.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.600 78,500.00 47,100.00


OH 1.800 100,000.00 180,000.00
OH 0.180 100,000.00 18,000.00
OH 0.030 90,000.00 2,700.00
JUMLAH TENAGA KERJA 247,800.00

m3 0.007 -
kg 0.100 -
kg 0.150 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 247,800.00
10% 24,780.00
- 272,580.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.025 78,500.00 1,962.50
OH 0.075 100,000.00 7,500.00
OH 0.008 100,000.00 800.00
OH 0.001 90,000.00 90.00
JUMLAH TENAGA KERJA 10,352.50

m3 0.400 -
kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 10,352.50
10% 1,035.25
- 11,387.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.100 78,500.00 7,850.00


OH 0.050 100,000.00 5,000.00
OH 0.005 100,000.00 500.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 13,800.00

m2 1.500 -
m3 0.014 -
kg 0.012 -
m3 0.003 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 13,800.00
10% 1,380.00
- 15,180.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.060 78,500.00 4,710.00


OH 0.600 100,000.00 60,000.00
OH 0.060 100,000.00 6,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 70,980.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 70,980.00
10% 7,098.00
- 78,078.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.010 78,500.00 785.00


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 56,235.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 56,235.00
10% 5,623.50
- 61,858.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.005 78,500.00 392.50


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 55,662.50

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,662.50
10% 5,566.25
- 61,228.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.005 78,500.00 392.50


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 55,662.50

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 55,662.50
10% 5,566.25
- 61,228.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.015 78,500.00 1,177.50


OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.001 90,000.00 72.00
JUMLAH TENAGA KERJA 17,749.50

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,749.50
10% 1,774.95
- 19,524.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.010 78,500.00 785.00


OH 0.100 100,000.00 10,000.00
OH 0.010 100,000.00 1,000.00
OH 0.001 90,000.00 45.00
JUMLAH TENAGA KERJA 11,830.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,830.00
10% 1,183.00
- 13,013.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

- -
OH 0.100 78,500.00 7,850.00
OH 0.200 100,000.00 20,000.00
OH 0.020 100,000.00 2,000.00
OH 0.001 90,000.00 45.00
JUMLAH TENAGA KERJA 29,895.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,895.00
10% 2,989.50
- 32,884.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

- -
OH 0.015 78,500.00 1,177.50
OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 18,397.50

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.015 78,500.00 1,177.50


OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 18,397.50

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.050 78,500.00 3,925.00


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 59,195.00

set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 59,195.00
10% 5,919.50
- 65,114.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.020 78,500.00 1,570.00


OH 0.200 100,000.00 20,000.00
OH 0.020 100,000.00 2,000.00
OH 0.001 90,000.00 90.00
JUMLAH TENAGA KERJA 23,660.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,660.00
10% 2,366.00
- 26,026.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.050 78,500.00 3,925.00


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 59,195.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 59,195.00
10% 5,919.50
- 65,114.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.010 78,500.00 785.00
OH 0.100 100,000.00 10,000.00
OH 0.010 100,000.00 1,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 12,235.00

Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,235.00
10% 1,223.50
- 13,458.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.060 78,500.00 4,710.00


OH 0.600 100,000.00 60,000.00
OH 0.060 100,000.00 6,000.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 70,980.00

Set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 70,980.00
10% 7,098.00
- 78,078.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.025 78,500.00 1,962.50


OH 0.250 100,000.00 25,000.00
OH 0.025 100,000.00 2,500.00
OH 0.001 90,000.00 117.00
JUMLAH TENAGA KERJA 29,579.50

Set 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,579.50
10% 2,957.95
- 32,537.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.015 78,500.00 1,177.50


OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.001 90,000.00 72.00
JUMLAH TENAGA KERJA 17,749.50

m2 1.100 -
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 17,749.50
10% 1,774.95
- 19,524.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.015 80,000.00 1,200.00


OH 0.150 120,000.00 18,000.00
OH 0.015 150,000.00 2,250.00
OH 0.001 180,000.00 144.00
JUMLAH TENAGA KERJA 21,594.00

m2 1.100 95,000.00 104,500.00


Kg 0.050 50,000.00 2,500.00
JUMLAH HARGA BAHAN 107,000.00
- -
JUMLAH HARGA ALAT -
- 128,594.00
10% 12,859.40
- 141,453.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.017 78,500.00 1,334.50


OH 0.170 100,000.00 17,000.00
OH 0.017 100,000.00 1,700.00
OH 0.001 90,000.00 81.00
JUMLAH TENAGA KERJA 20,115.50

m2 1.100 -
Kg 0.070 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,115.50
10% 2,011.55
- 22,127.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.025 78,500.00 1,962.50


OH 0.250 100,000.00 25,000.00
OH 0.025 100,000.00 2,500.00
OH 0.001 90,000.00 117.00
JUMLAH TENAGA KERJA 29,579.50

m2 1.100 -
Kg 0.070 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 29,579.50
10% 2,957.95
- 32,537.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.015 78,500.00 1,177.50
OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 18,397.50

m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.017 78,500.00 1,334.50


OH 0.170 100,000.00 17,000.00
OH 0.017 100,000.00 1,700.00
OH 0.009 90,000.00 810.00
JUMLAH TENAGA KERJA 20,844.50

m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 20,844.50
10% 2,084.45
- 22,928.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.015 78,500.00 1,177.50


OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 18,397.50

m2 1.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 18,397.50
10% 1,839.75
- 20,237.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.075 78,500.00 5,887.50


OH 0.150 100,000.00 15,000.00
OH 0.015 100,000.00 1,500.00
OH 0.004 90,000.00 360.00
JUMLAH TENAGA KERJA 22,747.50

m2 1.100 -
Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 22,747.50
10% 2,274.75
- 25,022.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.150 78,500.00 11,775.00


OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 12,045.00

Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,045.00
10% 1,204.50
- 13,249.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.150 78,500.00 11,775.00


OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 12,045.00

Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,045.00
10% 1,204.50
- 13,249.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.150 78,500.00 11,775.00


OH 0.008 90,000.00 720.00
JUMLAH TENAGA KERJA 12,495.00

Kg 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,495.00
10% 1,249.50
- 13,744.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.070 78,500.00 5,495.00


OH 0.009 100,000.00 900.00
OH 0.006 100,000.00 600.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 7,265.00

Kg 0.200 -
Kg 0.150 -
Kg 0.170 -
Kg 0.260 -
Bh 0.010 -
Kg 0.030 -
Lbr 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,265.00
10% 726.50
- 7,991.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.070 78,500.00 5,495.00


OH 0.105 100,000.00 10,500.00
OH 0.004 100,000.00 400.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 16,665.00

Kg 0.200 -
Kg 0.150 -
Kg 0.170 -
Kg 0.350 -
Bh 0.010 -
Kg 0.030 -
Lbr 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,665.00
10% 1,666.50
- 18,331.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.040 78,500.00 3,140.00


OH 0.063 100,000.00 6,300.00
OH 0.063 100,000.00 6,300.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 16,010.00

L 0.360 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,010.00
10% 1,601.00
- 17,611.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.040 78,500.00 3,140.00


OH 0.060 100,000.00 6,000.00
OH 0.016 100,000.00 1,600.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 11,010.00

L 0.150 -
L 0.372 -
Lbr 2.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,010.00
10% 1,101.00
- 12,111.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.100 78,500.00 7,850.00


OH 0.006 90,000.00 540.00
JUMLAH TENAGA KERJA 8,390.00

L 0.350 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 8,390.00
10% 839.00
- 9,229.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.160 78,500.00 12,560.00


OH 0.160 100,000.00 16,000.00
OH 0.016 100,000.00 1,600.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 30,430.00

L 0.150 -
Kg 0.050 -
Lbr 0.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 30,430.00
10% 3,043.00
- 33,473.00

ok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.020 80,000.00 1,600.00


OH 0.063 120,000.00 7,560.00
OH 0.006 150,000.00 945.00
OH 0.003 180,000.00 540.00
JUMLAH TENAGA KERJA 10,645.00

Kg 0.100 20,000.00 2,000.00


Kg 0.100 35,000.00 3,500.00
Kg 0.260 65,000.00 16,900.00
JUMLAH HARGA BAHAN 22,400.00
-
JUMLAH HARGA ALAT -
33,045.00
10% 3,304.50
36,349.00

k lama ( 1 lapis cat dasar, 2 lapis cat penutup)

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.028 78,500.00 2,198.00


OH 0.042 100,000.00 4,200.00
OH 0.004 100,000.00 420.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 7,088.00

Kg 0.120 35,000.00 4,200.00


Kg 0.180 65,000.00 11,700.00
JUMLAH HARGA BAHAN 15,900.00
-
JUMLAH HARGA ALAT -
22,988.00
10% 2,298.80
25,286.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.028 78,500.00 2,198.00


OH 0.042 100,000.00 4,200.00
OH 0.004 100,000.00 420.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 7,088.00
Kg 0.100 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 7,088.00
10% 708.80
- 7,796.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.150 78,500.00 11,775.00


OH 0.001 100,000.00 100.00
OH 0.000 100,000.00 10.00
OH 0.003 90,000.00 225.00
JUMLAH TENAGA KERJA 12,110.00

Kg 0.150 -
Lbr 0.100 -
Ikat 0.250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,110.00
10% 1,211.00
- 13,321.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.040 78,500.00 3,140.00


OH 0.005 100,000.00 500.00
OH 0.001 100,000.00 50.00
OH 0.003 90,000.00 225.00
JUMLAH TENAGA KERJA 3,915.00

Kg 0.300 -
Lbr 0.200 -
Ikat 0.250 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 3,915.00
10% 391.50
- 4,306.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.020 78,500.00 1,570.00


OH 0.200 100,000.00 20,000.00
OH 0.020 100,000.00 2,000.00
OH 0.003 90,000.00 225.00
JUMLAH TENAGA KERJA 23,795.00

m2 1.200 -
Kg 0.200 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,795.00
10% 2,379.50
- 26,174.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.020 78,500.00 1,570.00


OH 0.200 100,000.00 20,000.00
OH 0.020 100,000.00 2,000.00
OH 0.003 90,000.00 225.00
JUMLAH TENAGA KERJA 23,795.00

Kg 0.100 -
Bh 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 23,795.00
10% 2,379.50
- 26,174.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.250 78,500.00 19,625.00


OH 0.225 100,000.00 22,500.00
OH 0.023 100,000.00 2,250.00
OH 0.008 90,000.00 675.00
JUMLAH TENAGA KERJA 45,050.00

Kg 0.100 -
L 0.010 -
Bh 0.010 -
m3 0.002 333,300.00 666.60
JUMLAH HARGA BAHAN 666.60
- -
JUMLAH HARGA ALAT -
- 45,716.60
10% 4,571.66
- 50,288.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.250 78,500.00 19,625.00


OH 0.250 100,000.00 25,000.00
OH 0.025 100,000.00 2,500.00
OH 0.001 90,000.00 117.00
JUMLAH TENAGA KERJA 47,242.00

Kg 0.100 -
Kg 0.100 -
Kg 0.080 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 47,242.00
10% 4,724.20
- 51,966.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.060 78,500.00 4,710.00


OH 0.060 100,000.00 6,000.00
OH 0.012 100,000.00 1,200.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 12,180.00

Kg 0.300 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,180.00
10% 1,218.00
- 13,398.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.400 78,500.00 31,400.00


OH 0.800 100,000.00 80,000.00
OH 0.080 100,000.00 8,000.00
OH 0.020 90,000.00 1,800.00
JUMLAH TENAGA KERJA 121,200.00

Kg 0.110 -
Kg 0.170 -
Kg 0.080 -
Bh 0.010 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 121,200.00
10% 12,120.00
- 133,320.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.400 78,500.00 31,400.00


OH 0.700 100,000.00 70,000.00
OH 0.070 100,000.00 7,000.00
OH 0.020 90,000.00 1,800.00
JUMLAH TENAGA KERJA 110,200.00

Kg 0.300 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 110,200.00
10% 11,020.00
- 121,220.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.400 78,500.00 31,400.00


OH 0.700 100,000.00 70,000.00
OH 0.070 100,000.00 7,000.00
OH 0.020 90,000.00 1,800.00
JUMLAH TENAGA KERJA 110,200.00

Kg 0.300 -
L 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 110,200.00
10% 11,020.00
- 121,220.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.300 78,500.00 259,050.00


OH 1.100 100,000.00 110,000.00
OH 0.010 100,000.00 1,000.00
OH 0.160 90,000.00 14,400.00
JUMLAH TENAGA KERJA 384,450.00

Unit 1.000 -
% 0.060 - -
JUMLAH HARGA BAHAN - -
- -
JUMLAH HARGA ALAT -
- 384,450.00
10% 38,445.00
- 422,895.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.000 78,500.00 78,500.00


OH 1.500 100,000.00 150,000.00
OH 0.150 100,000.00 15,000.00
OH 0.160 90,000.00 14,400.00
JUMLAH TENAGA KERJA 257,900.00

Unit 1.000 -
Kg 6.000 -
M3 0.010 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 257,900.00
10% 25,790.00
- 283,690.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.000 78,500.00 78,500.00


OH 1.500 100,000.00 150,000.00
OH 0.150 100,000.00 15,000.00
OH 0.050 90,000.00 4,500.00
JUMLAH TENAGA KERJA 248,000.00
Unit 1.000 -
Kg 6.000 -
M3 0.010 -
Bh 7.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 248,000.00
10% 24,800.00
- 272,800.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.000 78,500.00 78,500.00


OH 1.000 100,000.00 100,000.00
OH 0.100 100,000.00 10,000.00
OH 0.050 90,000.00 4,500.00
JUMLAH TENAGA KERJA 193,000.00

Unit 1.000 -
Kg 6.000 -
M3 0.010 -
% 30.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 193,000.00
10% 19,300.00
- 212,300.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.200 78,500.00 94,200.00


OH 1.450 100,000.00 145,000.00
OH 0.150 100,000.00 15,000.00
OH 0.060 90,000.00 5,400.00
JUMLAH TENAGA KERJA 259,600.00

Unit 1.200 -
Kg 6.000 -
M3 0.010 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 259,600.00
10% 25,960.00
- 285,560.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.075 78,500.00 5,887.50


OH 0.750 100,000.00 75,000.00
OH 0.075 100,000.00 7,500.00
OH 0.003 90,000.00 270.00
JUMLAH TENAGA KERJA 88,657.50

Unit 1.000 -
% 20.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 88,657.50
10% 8,865.75
- 97,523.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.000 78,500.00 235,500.00


OH 4.500 100,000.00 450,000.00
OH 0.050 100,000.00 5,000.00
OH 0.900 90,000.00 81,000.00
JUMLAH TENAGA KERJA 771,500.00

Unit 1.000 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 771,500.00
10% 77,150.00
- 848,650.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.000 78,500.00 471,000.00


OH 3.000 100,000.00 300,000.00
OH 0.300 100,000.00 30,000.00
OH 0.030 90,000.00 2,700.00
JUMLAH TENAGA KERJA 803,700.00

M3 150.000 -
Kg 120.000 -
M3 0.300 -
bh 360.000 -
Kg 6.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 803,700.00
10% 80,370.00
- 884,070.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.000 78,500.00 235,500.00


OH 4.500 100,000.00 450,000.00
OH 0.050 100,000.00 5,000.00
OH 0.900 90,000.00 81,000.00
JUMLAH TENAGA KERJA 771,500.00

Unit 1.000 -
% 0.120 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 771,500.00
10% 77,150.00
- 848,650.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.300 78,500.00 23,550.00


OH 0.450 100,000.00 45,000.00
OH 0.045 100,000.00 4,500.00
OH 0.015 90,000.00 1,350.00
JUMLAH TENAGA KERJA 74,400.00

Unit 1.000 -
% 12.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 74,400.00
10% 7,440.00
- 81,840.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.500 78,500.00 274,750.00


OH 4.500 100,000.00 450,000.00
OH 0.050 100,000.00 5,000.00
OH 0.018 90,000.00 1,620.00
JUMLAH TENAGA KERJA 731,370.00

M3 0.900 1,044,557.00 940,101.30


Kg 180.000 -
M2 8.000 -
Bh 500.000 -
% 10.000 9,401.01 94,010.13
JUMLAH HARGA BAHAN 1,034,111.43
- -
JUMLAH HARGA ALAT -
- 1,765,481.43
10% 176,548.14
- 1,942,029.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.030 78,500.00 2,355.00


OH 0.300 100,000.00 30,000.00
OH 0.030 100,000.00 3,000.00
OH 0.015 90,000.00 1,350.00
JUMLAH TENAGA KERJA 36,705.00

Unit 1.000 -
Bh 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 36,705.00
10% 3,670.50
- 40,375.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.050 78,500.00 3,925.00


OH 0.500 100,000.00 50,000.00
OH 0.050 100,000.00 5,000.00
OH 0.025 90,000.00 2,250.00
JUMLAH TENAGA KERJA 61,175.00

Unit 1.000 -
Bh 1.000 -
Kg 20.000 -
M3 0.050 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 61,175.00
10% 6,117.50
- 67,292.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.010 78,500.00 785.00
OH 0.100 100,000.00 10,000.00
OH 0.010 100,000.00 1,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 12,235.00

Unit 1.000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 12,235.00
10% 1,223.50
- 13,458.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.160 78,500.00 169,560.00


OH 0.720 100,000.00 72,000.00
OH 0.072 100,000.00 7,200.00
OH 0.011 90,000.00 990.00
JUMLAH TENAGA KERJA 249,750.00

bh 40.000 -
Kg 44.000 -
M3 0.070 -
M3 0.060 -
M3 0.070 -
Kg 1.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 249,750.00
10% 24,975.00
- 274,725.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.200 78,500.00 251,200.00


OH 1.150 100,000.00 115,000.00
OH 0.011 100,000.00 1,100.00
OH 0.016 90,000.00 1,440.00
JUMLAH TENAGA KERJA 368,740.00

bh 70.000 -
Kg 77.000 -
M3 0.130 -
M3 0.090 -
M3 0.020 -
Kg 2.600 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 368,740.00
10% 36,874.00
- 405,614.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.200 78,500.00 251,200.00


OH 1.150 100,000.00 115,000.00
OH 0.011 100,000.00 1,100.00
OH 0.016 90,000.00 1,440.00
JUMLAH TENAGA KERJA 368,740.00

bh 123.000 -
Kg 114.000 -
M3 0.184 -
M3 0.120 -
M3 0.033 -
Kg 4.850 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 368,740.00
10% 36,874.00
- 405,614.00
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.054 78,500.00 4,239.00


OH 0.090 100,000.00 9,000.00
OH 0.009 100,000.00 900.00
OH 0.027 90,000.00 2,430.00
JUMLAH TENAGA KERJA 16,569.00

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,569.00
10% 1,656.90
- 18,225.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.010 78,500.00 785.00


OH 0.400 100,000.00 40,000.00
OH 0.040 100,000.00 4,000.00
OH 0.005 90,000.00 450.00
JUMLAH TENAGA KERJA 45,235.00

M 1.000 -
Buah 0.025 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 45,235.00
10% 4,523.50
- 49,758.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.054 78,500.00 4,239.00


OH 0.090 100,000.00 9,000.00
OH 0.009 100,000.00 900.00
OH 0.027 90,000.00 2,430.00
JUMLAH TENAGA KERJA 16,569.00

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 16,569.00
10% 1,656.90
- 18,225.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.054 Err:502 Err:502


OH 0.090 Err:502 Err:502
OH 0.009 Err:502 Err:502
OH 0.027 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.108 Err:502 Err:502


OH 0.180 Err:502 Err:502
OH 0.018 Err:502 Err:502
OH 0.005 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.135 Err:502 Err:502


OH 0.225 Err:502 Err:502
OH 0.023 Err:502 Err:502
OH 0.007 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.135 Err:502 Err:502


OH 0.225 Err:502 Err:502
OH 0.023 Err:502 Err:502
OH 0.007 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.036 Err:502 Err:502


OH 0.060 Err:502 Err:502
OH 0.006 Err:502 Err:502
OH 0.002 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.036 Err:502 Err:502


OH 0.060 Err:502 Err:502
OH 0.006 Err:502 Err:502
OH 0.002 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.036 Err:502 Err:502
OH 0.060 Err:502 Err:502
OH 0.006 Err:502 Err:502
OH 0.002 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.054 Err:502 Err:502


OH 0.090 Err:502 Err:502
OH 0.009 Err:502 Err:502
OH 0.003 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.054 Err:502 Err:502


OH 0.090 Err:502 Err:502
OH 0.009 Err:502 Err:502
OH 0.003 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.081 Err:502 Err:502


OH 0.135 Err:502 Err:502
OH 0.014 Err:502 Err:502
OH 0.004 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.081 Err:502 Err:502


OH 0.135 Err:502 Err:502
OH 0.014 Err:502 Err:502
OH 0.004 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.081 Err:502 Err:502


OH 0.135 Err:502 Err:502
OH 0.014 Err:502 Err:502
OH 0.004 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.200 -
% 35.000 - -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.080 78,500.00 6,280.00


OH 0.040 100,000.00 4,000.00
OH 0.004 100,000.00 400.00
OH 0.004 90,000.00 360.00
JUMLAH TENAGA KERJA 11,040.00

Bh 1.600 -
Kg 35.000 -
M3 0.014 -
M3 0.014 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- 11,040.00
10% 1,104.00
- 12,144.00

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.060 Err:502 Err:502


OH 0.030 Err:502 Err:502
OH 0.003 Err:502 Err:502
OH 0.003 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

Bh 1.600 -
Kg 0.680 -
M3 0.013 -
M3 0.011 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.140 Err:502 Err:502


OH 0.070 Err:502 Err:502
OH 0.007 Err:502 Err:502
OH 0.007 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

Bh 1.100 -
M3 0.027 -
Kg 3.920 -
M3 0.056 -
M3 0.024 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.380 Err:502 Err:502


OH 0.190 Err:502 Err:502
OH 0.019 Err:502 Err:502
OH 0.019 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

Bh 1.100 -
M3 0.550 -
Kg 10.300 -
M3 0.061 -
M3 0.069 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.081 Err:502 Err:502


OH 0.041 Err:502 Err:502
OH 0.008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.006 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
da A.8.4.1 ini adalah seperti yang tercantum pada tabel.
digunakan, harus disesuaikan dengan spesifi -

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.094 Err:502 Err:502


OH 0.047 Err:502 Err:502
OH 0.009 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.008 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.105 Err:502 Err:502


OH 0.053 Err:502 Err:502
OH 0.011 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.118 Err:502 Err:502
OH 0.059 Err:502 Err:502
OH 0.012 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.012 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.189 Err:502 Err:502


OH 0.095 Err:502 Err:502
OH 0.019 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.024 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.256 Err:502 Err:502


OH 0.128 Err:502 Err:502
OH 0.026 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.034 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.294 Err:502 Err:502


OH 0.147 Err:502 Err:502
OH 0.029 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.040 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.544 Err:502 Err:502


OH 0.272 Err:502 Err:502
OH 0.054 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.080 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.669 Err:502 Err:502


OH 0.335 Err:502 Err:502
OH 0.067 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.809 Err:502 Err:502


OH 0.405 Err:502 Err:502
OH 0.081 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.122 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.957 Err:502 Err:502


OH 0.479 Err:502 Err:502
OH 0.096 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.145 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.618 Err:502 Err:502


OH 0.809 Err:502 Err:502
OH 0.162 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.250 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.691 Err:502 Err:502


OH 0.846 Err:502 Err:502
OH 0.169 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.262 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.895 Err:502 Err:502


OH 0.948 Err:502 Err:502
OH 0.190 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.294 -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

- -
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.099 Err:502 Err:502


OH 1.050 Err:502 Err:502
OH 0.210 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.327 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 2.303 Err:502 Err:502
OH 1.152 Err:502 Err:502
OH 0.230 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.359 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.035 Err:502 Err:502


OH 0.017 Err:502 Err:502
OH 0.003 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.040 Err:502 Err:502


OH 0.020 Err:502 Err:502
OH 0.004 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.045 Err:502 Err:502


OH 0.023 Err:502 Err:502
OH 0.005 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.062 Err:502 Err:502


OH 0.031 Err:502 Err:502
OH 0.006 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.102 Err:502 Err:502


OH 0.051 Err:502 Err:502
OH 0.010 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.019 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.133 Err:502 Err:502


OH 0.067 Err:502 Err:502
OH 0.013 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.170 Err:502 Err:502


OH 0.085 Err:502 Err:502
OH 0.017 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.065 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.290 Err:502 Err:502


OH 0.145 Err:502 Err:502
OH 0.029 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.152 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.359 Err:502 Err:502


OH 0.180 Err:502 Err:502
OH 0.036 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.200 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.433 Err:502 Err:502


OH 0.216 Err:502 Err:502
OH 0.043 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.251 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.512 Err:502 Err:502


OH 0.256 Err:502 Err:502
OH 0.051 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.307 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.893 Err:502 Err:502
OH 0.446 Err:502 Err:502
OH 0.089 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.573 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.353 Err:502 Err:502


OH 0.677 Err:502 Err:502
OH 0.135 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.883 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.659 Err:502 Err:502


OH 0.830 Err:502 Err:502
OH 0.166 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -
hari 1.093 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.818 Err:502 Err:502


OH 0.909 Err:502 Err:502
OH 0.182 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 1.205 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.370 Err:502 Err:502


OH 1.185 Err:502 Err:502
OH 0.237 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 1.584 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.345 Err:502 Err:502


OH 0.172 Err:502 Err:502
OH 0.034 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.400 Err:502 Err:502


OH 0.200 Err:502 Err:502
OH 0.040 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.448 Err:502 Err:502


OH 0.224 Err:502 Err:502
OH 0.045 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.038 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.506 Err:502 Err:502


OH 0.253 Err:502 Err:502
OH 0.051 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.796 Err:502 Err:502


OH 0.398 Err:502 Err:502
OH 0.080 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.949 Err:502 Err:502


OH 0.475 Err:502 Err:502
OH 0.095 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.958 Err:502 Err:502


OH 0.479 Err:502 Err:502
OH 0.096 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.042 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


-
OH 1.212 Err:502 Err:502
OH 0.606 Err:502 Err:502
OH 0.121 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.058 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.353 Err:502 Err:502


OH 0.676 Err:502 Err:502
OH 0.135 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.058 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.469 Err:502 Err:502


OH 0.735 Err:502 Err:502
OH 0.147 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -
hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.327 Err:502 Err:502


OH 0.664 Err:502 Err:502
OH 0.133 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.327 Err:502 Err:502


OH 1.163 Err:502 Err:502
OH 0.233 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.623 Err:502 Err:502


OH 1.312 Err:502 Err:502
OH 0.262 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.911 Err:502 Err:502


OH 1.456 Err:502 Err:502
OH 0.291 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.200 Err:502 Err:502


OH 1.600 Err:502 Err:502
OH 0.320 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.349 Err:502 Err:502


OH 1.744 Err:502 Err:502
OH 0.349 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.489 Err:502 Err:502


OH 0.098 Err:502 Err:502
OH 0.049 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.547 Err:502 Err:502


OH 0.109 Err:502 Err:502
OH 0.055 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.613 Err:502 Err:502


OH 0.123 Err:502 Err:502
OH 0.061 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.855 Err:502 Err:502


OH 0.171 Err:502 Err:502
OH 0.085 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.000 -
JUMLAH HARGA BAHAN -

hari 0.380 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.951 Err:502 Err:502


OH 0.190 Err:502 Err:502
OH 0.095 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

M 1.000 -
JUMLAH HARGA BAHAN -

hari 0.050 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.973 Err:502 Err:502


OH 0.195 Err:502 Err:502
OH 0.097 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.071 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.545 Err:502 Err:502


OH 0.309 Err:502 Err:502
OH 0.093 Err:502 Err:502
OH 0.154 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.023 -
hari 0.031 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.813 Err:502 Err:502


OH 0.363 Err:502 Err:502
OH 0.143 Err:502 Err:502
OH 0.181 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.029 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.047 Err:502 Err:502


OH 0.409 Err:502 Err:502
OH 0.193 Err:502 Err:502
OH 0.205 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.034 -
hari 0.045 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.011 Err:502 Err:502


OH 0.402 Err:502 Err:502
OH 0.293 Err:502 Err:502
OH 0.201 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.058 -
hari 0.077 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.859 Err:502 Err:502


OH 0.772 Err:502 Err:502
OH 0.493 Err:502 Err:502
OH 0.386 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.084 -
hari 0.225 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.995 Err:502 Err:502


OH 0.999 Err:502 Err:502
OH 0.593 Err:502 Err:502
OH 0.499 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.093 -
hari 0.248 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 5.931 Err:502 Err:502


OH 1.186 Err:502 Err:502
OH 0.793 Err:502 Err:502
OH 0.693 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.112 -
hari 0.298 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.949 Err:502 Err:502


OH 1.390 Err:502 Err:502
OH 0.793 Err:502 Err:502
OH 0.695 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.152 -
hari 0.304 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 8.056 Err:502 Err:502


OH 1.611 Err:502 Err:502
OH 0.893 Err:502 Err:502
OH 0.806 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.180 -
hari 0.360 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.499 Err:502 Err:502


OH 0.100 Err:502 Err:502
OH 0.050 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.579 Err:502 Err:502


OH 0.116 Err:502 Err:502
OH 0.058 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.648 Err:502 Err:502


OH 0.130 Err:502 Err:502
OH 0.065 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.708 Err:502 Err:502


OH 0.142 Err:502 Err:502
OH 0.071 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 1.113 Err:502 Err:502
OH 0.223 Err:502 Err:502
OH 0.111 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.325 Err:502 Err:502


OH 0.265 Err:502 Err:502
OH 0.133 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.415 Err:502 Err:502


OH 0.283 Err:502 Err:502
OH 0.141 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.366 Err:502 Err:502


OH 0.473 Err:502 Err:502
OH 0.237 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.027 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.231 Err:502 Err:502


OH 0.446 Err:502 Err:502
OH 0.223 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.026 -
hari 0.037 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.432 Err:502 Err:502


OH 0.486 Err:502 Err:502
OH 0.243 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.029 -
hari 0.045 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.208 Err:502 Err:502


OH 0.442 Err:502 Err:502
OH 0.221 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.027 -
hari 0.039 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 3.897 Err:502 Err:502
OH 0.779 Err:502 Err:502
OH 0.390 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.046 -
hari 0.098 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.403 Err:502 Err:502


OH 0.081 Err:502 Err:502
OH 0.440 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.052 -
hari 0.115 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.895 Err:502 Err:502


OH 0.979 Err:502 Err:502
OH 0.489 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.058 -
hari 0.133 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 5.387 Err:502 Err:502


OH 1.077 Err:502 Err:502
OH 0.539 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.064 -
hari 0.150 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 5.897 Err:502 Err:502


OH 1.176 Err:502 Err:502
OH 0.588 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m 1.000 -
JUMLAH HARGA BAHAN -

hari 0.070 -
hari 0.167 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.005 Err:502 Err:502


OH 0.002 Err:502 Err:502
OH 0.001 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.014 Err:502 Err:502


OH 0.007 Err:502 Err:502
OH 0.001 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.022 Err:502 Err:502


OH 0.011 Err:502 Err:502
OH 0.002 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.031 Err:502 Err:502


OH 0.015 Err:502 Err:502
OH 0.003 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.003 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.081 Err:502 Err:502


OH 0.040 Err:502 Err:502
OH 0.008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.017 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.128 Err:502 Err:502


OH 0.064 Err:502 Err:502
OH 0.013 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.030 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.155 Err:502 Err:502


OH 0.077 Err:502 Err:502
OH 0.015 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.037 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.331 Err:502 Err:502


OH 0.166 Err:502 Err:502
OH 0.033 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.420 Err:502 Err:502


OH 0.210 Err:502 Err:502
OH 0.042 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.054 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.518 Err:502 Err:502


OH 0.259 Err:502 Err:502
OH 0.052 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.069 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.623 Err:502 Err:502


OH 0.311 Err:502 Err:502
OH 0.062 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.086 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.089 Err:502 Err:502


OH 0.545 Err:502 Err:502
OH 0.109 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -
hari 0.160 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.141 Err:502 Err:502


OH 0.571 Err:502 Err:502
OH 0.114 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.168 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.285 Err:502 Err:502


OH 0.643 Err:502 Err:502
OH 0.129 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.191 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.429 Err:502 Err:502


OH 0.715 Err:502 Err:502
OH 0.143 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.213 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.573 Err:502 Err:502


OH 0.787 Err:502 Err:502
OH 0.157 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.236 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.002 Err:502 Err:502


OH 0.001 Err:502 Err:502
OH 0.000 Err:502 Err:502
OH 0.034 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.004 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.006 Err:502 Err:502


OH 0.003 Err:502 Err:502
OH 0.001 Err:502 Err:502
OH 0.071 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.005 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.009 Err:502 Err:502


OH 0.005 Err:502 Err:502
OH 0.001 Err:502 Err:502
OH 0.096 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.006 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.016 Err:502 Err:502


OH 0.008 Err:502 Err:502
OH 0.002 Err:502 Err:502
OH 0.121 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.009 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.044 Err:502 Err:502


OH 0.022 Err:502 Err:502
OH 0.004 Err:502 Err:502
OH 0.171 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.017 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.067 Err:502 Err:502


OH 0.033 Err:502 Err:502
OH 0.007 Err:502 Err:502
OH 0.221 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.000 -
JUMLAH HARGA BAHAN -

hari 0.023 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0900 Err:502 Err:502


OH 0.0450 Err:502 Err:502
OH 0.0090 Err:502 Err:502
OH 0.2710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0300 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1770 Err:502 Err:502


OH 0.0880 Err:502 Err:502
OH 0.0180 Err:502 Err:502
OH 0.3710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0550 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2250 Err:502 Err:502


OH 0.1130 Err:502 Err:502
OH 0.0230 Err:502 Err:502
OH 0.4210 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0700 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2770 Err:502 Err:502


OH 0.1390 Err:502 Err:502
OH 0.0280 Err:502 Err:502
OH 0.4710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3330 Err:502 Err:502


OH 0.1670 Err:502 Err:502
OH 0.0330 Err:502 Err:502
OH 0.5710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.6010 Err:502 Err:502


OH 0.3010 Err:502 Err:502
OH 0.0600 Err:502 Err:502
OH 0.7710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1790 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9130 Err:502 Err:502


OH 0.4560 Err:502 Err:502
OH 0.0910 Err:502 Err:502
OH 0.8710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2700 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.1250 Err:502 Err:502


OH 0.5620 Err:502 Err:502
OH 0.1120 Err:502 Err:502
OH 0.9710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3320 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 1.2380 Err:502 Err:502
OH 0.6190 Err:502 Err:502
OH 0.1240 Err:502 Err:502
OH 1.0710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3650 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.6190 Err:502 Err:502


OH 0.8090 Err:502 Err:502
OH 0.1620 Err:502 Err:502
OH 1.1710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.4770 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0190 Err:502 Err:502


OH 0.0100 Err:502 Err:502
OH 0.0020 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0170 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0580 Err:502 Err:502


OH 0.0290 Err:502 Err:502
OH 0.0060 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0170 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0920 Err:502 Err:502


OH 0.0460 Err:502 Err:502
OH 0.0090 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0340 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1310 Err:502 Err:502


OH 0.0660 Err:502 Err:502
OH 0.0130 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0340 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3400 Err:502 Err:502


OH 0.1700 Err:502 Err:502
OH 0.0340 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4750 Err:502 Err:502


OH 0.2370 Err:502 Err:502
OH 0.0470 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.5040 Err:502 Err:502


OH 0.2520 Err:502 Err:502
OH 0.0500 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0510 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7380 Err:502 Err:502


OH 0.3690 Err:502 Err:502
OH 0.0740 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8480 Err:502 Err:502


OH 0.4240 Err:502 Err:502
OH 0.0850 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.9410 Err:502 Err:502


OH 0.4710 Err:502 Err:502
OH 0.0940 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8640 Err:502 Err:502


OH 0.4320 Err:502 Err:502
OH 0.0860 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.5670 Err:502 Err:502


OH 0.7830 Err:502 Err:502
OH 0.1570 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7700 Err:502 Err:502


OH 0.8850 Err:502 Err:502
OH 0.1770 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0850 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.9740 Err:502 Err:502


OH 0.9870 Err:502 Err:502
OH 0.1970 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.1780 Err:502 Err:502


OH 1.0890 Err:502 Err:502
OH 0.2180 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.3820 Err:502 Err:502


OH 1.1910 Err:502 Err:502
OH 0.2380 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1020 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0710 Err:502 Err:502


OH 0.0140 Err:502 Err:502
OH 0.0070 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0030 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1120 Err:502 Err:502


OH 0.0220 Err:502 Err:502
OH 0.0110 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1590 Err:502 Err:502


OH 0.0320 Err:502 Err:502
OH 0.0160 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0180 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3660 Err:502 Err:502


OH 0.0730 Err:502 Err:502
OH 0.0370 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0540 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4760 Err:502 Err:502


OH 0.0950 Err:502 Err:502
OH 0.0480 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0730 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.5120 Err:502 Err:502


OH 0.1020 Err:502 Err:502
OH 0.0510 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0790 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.9410 Err:502 Err:502
OH 0.1880 Err:502 Err:502
OH 0.0940 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1580 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.1370 Err:502 Err:502


OH 0.2270 Err:502 Err:502
OH 0.1140 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1760 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.3120 Err:502 Err:502


OH 0.2620 Err:502 Err:502
OH 0.1310 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1920 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.3090 Err:502 Err:502


OH 0.2620 Err:502 Err:502
OH 0.1310 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1920 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.5980 Err:502 Err:502


OH 0.5200 Err:502 Err:502
OH 0.2600 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3100 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.3700 Err:502 Err:502


OH 0.6740 Err:502 Err:502
OH 0.3370 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3810 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.0210 Err:502 Err:502


OH 0.8040 Err:502 Err:502
OH 0.4020 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.4410 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.7310 Err:502 Err:502


OH 0.9460 Err:502 Err:502
OH 0.4730 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5060 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 5.5020 Err:502 Err:502


OH 1.1000 Err:502 Err:502
OH 0.5500 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5760 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0280 Err:502 Err:502


OH 0.0060 Err:502 Err:502
OH 0.0030 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0370 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0850 Err:502 Err:502


OH 0.0170 Err:502 Err:502
OH 0.0080 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0400 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1330 Err:502 Err:502


OH 0.0270 Err:502 Err:502
OH 0.0130 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0420 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.1840 Err:502 Err:502
OH 0.0370 Err:502 Err:502
OH 0.0180 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0450 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4760 Err:502 Err:502


OH 0.0950 Err:502 Err:502
OH 0.0480 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0600 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.6630 Err:502 Err:502


OH 0.1330 Err:502 Err:502
OH 0.0660 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0680 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7450 Err:502 Err:502


OH 0.1490 Err:502 Err:502
OH 0.0740 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0720 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4400 Err:502 Err:502


OH 0.2880 Err:502 Err:502
OH 0.1440 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1050 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.3990 Err:502 Err:502


OH 0.2800 Err:502 Err:502
OH 0.1400 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1070 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.5580 Err:502 Err:502


OH 0.3120 Err:502 Err:502
OH 0.1560 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1070 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4370 Err:502 Err:502


OH 0.2870 Err:502 Err:502
OH 0.1440 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1130 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.6240 Err:502 Err:502


OH 0.5250 Err:502 Err:502
OH 0.2620 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1660 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.9710 Err:502 Err:502


OH 0.5940 Err:502 Err:502
OH 0.2970 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1830 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.3190 Err:502 Err:502


OH 0.6640 Err:502 Err:502
OH 0.3320 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.6670 Err:502 Err:502


OH 0.7330 Err:502 Err:502
OH 0.3670 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2180 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.0150 Err:502 Err:502


OH 0.8030 Err:502 Err:502
OH 0.4020 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2360 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4290 Err:502 Err:502


OH 0.7150 Err:502 Err:502
OH 0.1430 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7140 Err:502 Err:502


OH 0.8570 Err:502 Err:502
OH 0.1710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.3000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7140 Err:502 Err:502


OH 0.8570 Err:502 Err:502
OH 0.1710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.4000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.0000 Err:502 Err:502


OH 1.0000 Err:502 Err:502
OH 0.2000 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.4290 Err:502 Err:502


OH 1.7150 Err:502 Err:502
OH 0.3430 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.4290 Err:502 Err:502


OH 1.7150 Err:502 Err:502
OH 0.3430 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.0000 Err:502 Err:502


OH 2.0000 Err:502 Err:502
OH 0.4000 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4210 Err:502 Err:502


OH 0.7110 Err:502 Err:502
OH 0.1420 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.6000 -
hari 0.3000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4290 Err:502 Err:502


OH 0.7150 Err:502 Err:502
OH 0.1430 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7860 Err:502 Err:502


OH 0.8930 Err:502 Err:502
OH 0.1790 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7140 Err:502 Err:502


OH 0.8570 Err:502 Err:502
OH 0.1710 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.7500 -
hari 0.7500 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.5710 Err:502 Err:502


OH 1.2860 Err:502 Err:502
OH 0.2570 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.0000 Err:502 Err:502


OH 1.5000 Err:502 Err:502
OH 0.3000 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.0000 Err:502 Err:502


OH 1.5000 Err:502 Err:502
OH 0.3000 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.0000 -
hari 1.0000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1060 Err:502 Err:502


OH 0.0530 Err:502 Err:502
OH 0.0110 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0280 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.2160 Err:502 Err:502


OH 0.1080 Err:502 Err:502
OH 0.0220 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 0.0290 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.3260 Err:502 Err:502


OH 0.1630 Err:502 Err:502
OH 0.0330 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.0390 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.4360 Err:502 Err:502


OH 0.2180 Err:502 Err:502
OH 0.0440 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.6560 Err:502 Err:502


OH 0.3280 Err:502 Err:502
OH 0.0660 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.7660 Err:502 Err:502


OH 0.3830 Err:502 Err:502
OH 0.0770 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.5000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.8760 Err:502 Err:502


OH 0.4380 Err:502 Err:502
OH 0.0880 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.6000 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.0960 Err:502 Err:502


OH 0.5480 Err:502 Err:502
OH 0.1100 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.1930 -
hari 0.0960 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.3160 Err:502 Err:502


OH 0.6580 Err:502 Err:502
OH 0.1320 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2250 -
hari 0.1130 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.5360 Err:502 Err:502


OH 0.7680 Err:502 Err:502
OH 0.1540 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.2570 -
hari 0.1290 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.7560 Err:502 Err:502


OH 0.8780 Err:502 Err:502
OH 0.1760 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3210 -
hari 0.1610 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.9760 Err:502 Err:502


OH 0.9880 Err:502 Err:502
OH 0.1980 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3660 -
hari 0.1830 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.1960 Err:502 Err:502


OH 1.0980 Err:502 Err:502
OH 0.2200 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.3860 -
hari 0.1930 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.4160 Err:502 Err:502


OH 1.2080 Err:502 Err:502
OH 0.2420 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.4500 -
hari 0.2250 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.4660 Err:502 Err:502


OH 0.7330 Err:502 Err:502
OH 0.1470 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.6060 -
hari 0.0750 -
hari 0.9680 -
hari 0.8650 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 1.6460 Err:502 Err:502


OH 0.8230 Err:502 Err:502
OH 0.1650 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.6500 -
hari 0.1590 -
hari 1.0780 -
hari 0.9110 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.0960 Err:502 Err:502


OH 1.0480 Err:502 Err:502
OH 0.2100 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.7600 -
hari 0.3690 -
hari 1.3530 -
hari 1.0260 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.5460 Err:502 Err:502


OH 1.2730 Err:502 Err:502
OH 0.2550 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.8700 -
hari 0.5790 -
hari 1.6280 -
hari 1.1410 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 2.9960 Err:502 Err:502


OH 1.4980 Err:502 Err:502
OH 0.3000 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 0.9800 -
hari 0.7890 -
hari 1.9030 -
hari 1.2560 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 3.4460 Err:502 Err:502


OH 1.7230 Err:502 Err:502
OH 0.3450 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.0900 -
hari 0.9990 -
hari 2.1780 -
hari 1.3710 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.3460 Err:502 Err:502


OH 2.1730 Err:502 Err:502
OH 0.4350 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.3100 -
hari 1.4190 -
hari 2.7280 -
hari 1.6010 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 4.7960 Err:502 Err:502


OH 2.3980 Err:502 Err:502
OH 0.4800 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -
hari 1.4200 -
hari 1.6290 -
hari 3.0030 -
hari 1.7160 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 5.2460 Err:502 Err:502


OH 2.6230 Err:502 Err:502
OH 0.5250 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.5300 -
hari 1.8390 -
hari 3.2780 -
hari 1.8310 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 6.1460 Err:502 Err:502


OH 3.0730 Err:502 Err:502
OH 0.6150 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.7500 -
hari 2.2590 -
hari 3.8280 -
hari 2.0610 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 7.0460 Err:502 Err:502


OH 3.5230 Err:502 Err:502
OH 0.7050 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 1.9700 -
hari 2.6790 -
hari 4.3780 -
hari 2.2910 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 7.9460 Err:502 Err:502


OH 3.9730 Err:502 Err:502
OH 0.7950 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

bh 1.0000 -
JUMLAH HARGA BAHAN -

hari 2.1900 -
hari 3.0990 -
hari 4.9280 -
hari 2.5210 -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0020 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0040 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502
Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0080 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0180 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502
m3 0.0310 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0490 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.0710 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.1260 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.0080 Err:502 Err:502


OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.1580 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)


OH 0.0080 Err:502 Err:502
OH 0.0008 Err:502 Err:502
JUMLAH TENAGA KERJA Err:502

m3 0.2830 -
liter 0.0600 -
liter 0.0020 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- Err:502
10% Err:502
- Err:502

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

% 1.0000 - -
JUMLAH TENAGA KERJA -

btg 0.2830 -
m 24.0000 -
bh 3.0000 -
bh 4.0000 -
bh 3.0000 -
bh 24.0000 -
bh 1.0000 -
bh 1.0000 -
bh 1.0000 -
JUMLAH HARGA BAHAN -
- -
JUMLAH HARGA ALAT -
- -
10% -
- -

Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

OH 0.1500 -
OH 0.1500 -
OH 0.0300 -
OH 0.0300 -
JUMLAH TENAGA KERJA -

M' 11.00 -
M' 11.00 -
bh 1.00 -
bh 2.00 -
bh 3.00 -
bh 6.00 -
bh 2.00 -
bh 0.25 -
JUMLAH HARGA BAHAN -
-
JUMLAH HARGA ALAT -
-
10% -
-
DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN

1. Daftar Harga Upah Tenaga Kerja

HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN
(Rp)
1 Pekerja Hari Rp 80,000.00
2 Tukang Hari Rp 100,000.00
3 Tukang Batu/ Besi Hari Rp 120,000.00
4 Keapal Tukang Bati / Besi Hari Rp 150,000.00
5 Tukang Kayu/ Cat Hari Rp 120,000.00
6 Kepala Tukang Kayu/ Cat Hari Rp 150,000.00
7 Mandor Hari Rp 180,000.00
8 Pekerja Galian Tanah Hari Rp 120,000.00

2. Daftar Harga Material/ Bahan

HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN
(Rp)
1 2 3 4
1 Air Ltr Rp 1,200.00
2 Asbes Gelombang Lembar Rp 77,500.00
3 Batu Bata Buah Rp 700.00
4 Baut Beton/ Hiltybolt Buah Rp 5,000.00
5 Batu Pecah Uk 2-3 cm m3 Rp 450,000.00
6 Batu Kali / Batu Belah / Batu Gunung m3 Rp 275,000.00
7 Besi Beton Polos Kg Rp 18,000.00
8 Besi Beton Ulir Kg Rp 23,000.00
9 Reng Baja Ringan 40.45 Btg Rp 65,000.00
10 Baja Ringan Kanai C 100 Btg Rp 160,000.00
11 Besi Profil Kg Rp 15,000.00
12 Closet Duduk Unit Rp 4,000,000.00
13 Closet Jongkok Unit Rp 425,000.00
14 Wastafel + Kaca Cermin Terpasang Unit Rp 2,000,000.00
15 Floor Drain Stainless Unit Rp 70,000.00
16 Kran Air Stainless 1/4 '' atau 1/2 '' Unit Rp 110,000.00
17 Seal Tape bh Rp 3,000.00
18 Kawat Beton Kg Rp 30,000.00
19 Semen @ 40 kg Zak Rp 74,000.00
20 Semen / kg Kg Rp 1,850.00
21 Semen Putih @ 50 kg Zak Rp 150,000.00
22 Semen Warna / kg kKg Rp 3,000.00
23 Pasir Pasang m3 Rp 200,000.00
24 Pasir Urung m3 Rp 175,000.00
25 Pasir Beton m3 Rp 230,000.00
26 Pasir Beton m3 Rp 210,000.00
27 Kerikil Beton m3 Rp 175,000.00
28 Pasir Beton Kg Rp 150.00
29 Kerikil Beton Kg Rp 12,962.00
30 Kayu Kelas I ( Seumantok, ulin ) m3 Rp 6,000,000.00
31 Kayu Kelas II ( Kamper , Kruing ) m3 Rp 4,300,000.00
32 Kayu Balok Kelas III ( Borneo ) m3 Rp 3,300,000.00
33 Kayu Kasoi 5/7 untuk Bouwplank Kelas III m3 Rp 3,300,000.00
34 Papan Kayu Bouwplank 3/20 Klas IV m3 Rp 2,800,000.00
35 Dolken Kayu Ø 10 Cm Batang Rp 22,000.00
36 Multiplexs 9 mm Lbr Rp 150,000.00
37 Multiplexs 4 mm Lbr Rp 120,000.00
38 Seng Plat B jls 30 M2 Rp 130,000.00
39 Granit ukuran 30 x 30 cm Buah Rp 25,000.00
40 Granit Ukuran 40 x 40 cm Buah Rp 35,000.00
41 Keramik Uk 40 x 40 cm Buah Rp 25,000.00
42 Keramik Uk 30 c 20 cm Buah Rp 20,000.00
43 Keramik Uk 20 x 30 cm Buah Rp 17,000.00
44 Keramik 10 x 30 cm Buah Rp 15,000.00
45 Keramik 11 x x11 cm Buah Rp 2,500.00
46 Plamir Tembok Kg Rp 20,000.00
47 Dempul Kayu Kg Rp 30,000.00
48 Cat Dasar Kg Rp 90,000.00
49 Cat Menie Kg Rp 60,000.00
50 Cat Menie Besi Kg Rp 50,000.00
51 Cat Kayu / Cat Minyak Kg Rp 80,000.00
52 Cat Tembok Kg Rp 120,000.00
53 Paku Kayu 2''- 5'' Kg Rp 22,000.00
54 Paku Genteng Metal Kg Rp 28,000.00
55 Paku 8 Inchi Kg Rp 30,000.00
56 Paku Seng Kg Rp 27,000.00
57 Paku Asbes Kg Rp 21,000.00
58 Minyak Cat Kg Rp 55,000.00
59 Minyak Bekesting Liter Rp 16,000.00
60 Kertas Amplas Lembar Rp 7,000.00
61 Residu Liter Rp 10,000.00
62 Kuas Cat 4'' Buah Rp 25,000.00
63 Lem Kayu Kg Rp 70,000.00
64 Seal Tape Buah Rp 3,000.00
65 Pipa PVC Ø 1'' Batang Rp 115,000.00
66 Pipa PVC Ø 1/2'' Batang Rp 55,000.00
67 Pipa PVC Ø 3/4'' Batang Rp 90,000.00
68 Pipa Galvanis Ø 1,5 ''tebal 3,2 mm Batang Rp 320,000.00
69 Pipa Galvanis Ø 2'' tebal 3,2 mm Batang Rp 450,000.00
70 Pipa Galvanis Ø 3'' tebal 3,2 mm Batang Rp 500,000.00
71 Tanah Timbun M3 Rp 80,000.00
72 Penjaga Jarak Bekisting Bh Rp 5,000.00
73 Gypsum ( 120 x 240 ) tebal 9 mm Lembar Rp 102,000.00
74 GRC Board , t = 4 mm Lembar Rp 85,000.00
75 Plafond PVC Uk, 20 x 4000 cm, Tebal 8 mm Lembar Rp 105,000.00
76 Paku Skrup Kg Rp 25,000.00
77 Atap Genteng Metal 0,4 M2 Rp 180,000.00
78 Atap Spandek 0,35 mm M2 Rp 100,000.00
79 Nok Genteng Metal M' Rp 65,000.00
80 Seng Gelombang BJLS 30 Cat Pabrik M2 Rp 99,000.00
81 Seng Plat B jls 30 M2 Rp 135,000.00
82 Sealant Tube Rp 60,000.00
83 Solar Liter Rp 14,000.00
84 Talang Jurai M' Rp 45,000.00
85 Minyak Pelumas / Oli Liter Rp 55,000.00
86 Metal Furing 40 mm M' Rp 4,000.00
87 Atap Spandek 0,35 mm M2 Rp 100,000.00
88 Nok Genteng Metal M' Rp 65,000.00
89 Seng Gelombang BJLS 30 Cat Prabrik M2 Rp 99,000.00
90 Seng Plat Bjls 30 M2 Rp 135,000.00
91 Sealant Tube Rp 60,000.00
92 Solar Liter Rp 14,000.00
93 Talang Jurai M' Rp 45,000.00
94 Minyak Pelumas / Oli Liter Rp 55,000.00
95 Metal Furing 40 mm M' Rp 4,000.00
96 Kawat Las Listrik Kg Rp 45,000.00
97 Profil Aluminium M' Rp 435,000.00
98 List Profil Gypsum M' Rp 7,000.00
99 List Profil PVC M' Rp 25,000.00
100 Paku Beton Kg Rp 28,000.00
101 Skrup Fixer Buah Rp 900.00
102 Baut Dinaboll Buah Rp 5,000.00
103 Kaca Bening 3 mm M2 Rp 90,000.00
104 Kaca Bening 5 mm M2 Rp 110,000.00
105 Kaca Rayben 5 mm M2 Rp 235,000.00
106 Kaca Timpered 5 mm M2 Rp 40,000.00
107 Pipa Stainless Steel Ø 2 mm M' Rp 102,000.00
108 Pipa Stainless Stell Ø 3 mm M' Rp 160,000.00
109 Pipa Stailess Stell Ø 3/4 mm M' Rp 30,000.00
110 Baut Skrup Baja Ringan Dus Rp 200,000.00
111 Daun Pintu Panel Kayu Jati Buah Rp 4,500,000.00
112 Steel Grating M2 Rp 9,750,000.00
113 Baja Ringan IWF 200x 100 x5,5 X 88mm Kg Rp 9,000.00
114 Besi Hollow Uk 100x 50 x 2,5 mm M' Rp 130,000.00
115 Besi Hollow Uk. 40 x 40 x 2 mm M' Rp 65,000.00
116 Besi Hollow Uk 30 x 340 x 2 mm M' Rp 28,000.00
117 List Stainless Batang Rp 67,000.00
118 Besi Siku 40 x 40 x 4 mm M' Rp 25,000.00
119 Besi Siku 40 x 40 x 5 mm M' Rp 30,000.00
120 PVC Board 18 mm M2 Rp 300,000.00
121 Besi Strip Tebal 15 cm Kg Rp 8,000.00

Catatan : Bila Bahan yang tidak tercantum dalam tabel ini boleh ditambah sendiri.
DAFTAR UPAH KERJA
DALAM DAERAH BANDA ACEH

NO NAMA JENIS BARANG SATUAN HARGA


A. UPAH
1 Pekerja Hari 80,000.00
2 Tukang Hari 100,000.00
3 Tukang Batu/Besi Hari 120,000.00
4 Kepala Tukang Batu/Besi Hari 150,000.00
5 Tukang Kayu/Cat Hari 120,000.00
6 Kepala Tukang Kayu/Cat Hari 150,000.00
7 Mandor Hari 180,000.00
8 Pekerjaan Galian Tanah Hari 120,000.00
B. HARGA BAHAN
1 Air Liter 12.00
2 Atap Genteng Multiroof uk. 0,80 x 0,80 m M² 218,000.00
3 Batu Bata Buah 900.00
4 Batu Gunung/Batu Kali Mᶟ 165,000.00
5 Besi Beton Polos Kg 8,000.00
6 Besi Beton Ulir Kg 9,000.00
7 Besi Baja IWF Kg 16,500.00
8 Besi Strip Tebal 15 mm M 7,500.00
9 Bubungan Genteng (rabung) M 35,000.00
10 Bubungan Seng (rabung) M 30,000.00
11 Batako Bh 5,000.00
12 Cat Dasar Tembok/Sealer Setara Vinilex Kg 35,000.00
13 Cat Kayu Dasar Kg 40,000.00
14 Cat Kayu Mengkilap Kg 35,000.00
15 Cat Menie Besi Kg 50,000.00
16 Cat Tembok Setara Vinilex Kg 65,000.00
17 Kusen UPVC M 300,000.00
18 Dempul Kayu Kg 35,000.00
19 Dolken Kayu Ø 8-10/400 cm M 60,000.00
20 Door Holder M 18,000.00
21 Engsel Jendela Bh 35,000.00
22 Engsel Pintu Bh 40,000.00
23 Floor Drain Bh 10,000.00
24 Grandel Pintu Bh 20,000.00
25 Gypsum Board Tebal 9 mm M² 12,500.00
26 Jaring Kawat Baja Bh 30,000.00
27 Hak Angin Bh 15,000.00
28 Kaca Bening Uk. 3 mm M² 45,000.00
29 Kaca Bening Uk. 5 mm M² 60,000.00
30 Kaca Rayband Uk. 3 mm M² 80,000.00
31 Kaca Rayband Uk. 5 mm M² 95,000.00
32 Kaso-kaso (5x7) cm M³ 2,600,000.00
33 Kawat Beton Kg 15,000.00
34 Kawat Nyamuk/Kasa Plastik M² 30,000.00
35 Kayu Bakau 10 cm Btg 35,000.00
36 Kayu Kelas I ( Seumantok / Ulim / dll ) M³ 4,000,000.00
37 Kayu Kelas II ( Kamper / Kruing / dll ) M³ 3,500,000.00
38 Kayu Kelas III ( Borneo / dll ) M³ 3,000,000.00
39 Kayu Kelas IV ( Sengon / dll ) M³ 2,750,000.00
40 Keramik Uk. 20x20 cm Buah 2,500.00
41 Keramik Uk. 20x25 cm Buah 10,000.00
42 Keramik Uk. 30x30 cm Buah 15,000.00
43 Keramik Uk. 40x40 cm Buah 20,000.00
44 Keramik Uk. 50 x 50 cm Buah 30,000.00
45 Keramik Uk. 60 x 60 cm Buah 38,000.00
46 Kertas Amplas Lembar 4,000.00
47 Kloset Duduk Keramik Setara Toto + Tabung Buah 1,500,000.00
48 Kloset Jongkok keramik Setara Toto Buah 350,000.00
49 Keran Air 3/4" Buah 5,000.00
50 Kuas Cat Buah 12,000.00
51 Kunci Pintu (Standar) Buah 120,000.00
52 Kunci Pintu Biasa Buah 100,000.00
53 Kusen Pintu UPVC M 380,000.00
54 Kusen Jendela UPVC M 250,000.00
55 Lampu Hemat Energi 18 watt Setara Hannochs Buah 32,000.00
56 Lampu Hemat Energi 20 watt Setara Hannochs Buah 33,000.00
57 Lem Kayu Kg 12,000.00
58 List Eternit Kayu M 12,000.00
59 Marmer M2 50,000.00
60 Minyak Cat Liter 30,000.00
61 Minyak Bekisting Liter 1,500.00
62 Multipleks 3 mm Lembar 55,000.00
63 Multipleks 4 mm Lembar 95,000.00
64 Multipleks 6 mm Lembar 120,000.00
65 Multipleks 9 mm Lembar 130,000.00
66 Pacok Jendela Dan Ventilasi Pasang 8,000.00
67 Paku Asbes Kg 25,000.00
68 Paku Beton 8 inchi Kotak 42,000.00
69 Paku Kait Buah 1,000.00
70 Paku kayu Kg 20,000.00
71 Paku Triplek Kg 22,000.00
72 Paku Seng Kg 28,000.00
73 Paku Sumbat Buah 1,200.00
74 Paku Sekrup Bh 100.00
75 Kerikil Kg 225.00
75 Kerikil M3 225,000.00
76 Pasir Beton Kg 150.00
76 Pasir Beton M3 150,000.00
77 Pasir Pasang Kg 130.00
77 Pasir Pasang M3 130,000.00
78 Pasir Urug Kg 128.00
78 Pasir Urug M3 128,000.00
79 Pelumas/Oli Liter 75,000.00
80 Pipa leading Ø 1" Galvanis Tebal 3,2 mm Batang 35,000.00
81 Pipa leading Ø 2" Galvanis Tebal 3,2 mm Batang 75,000.00
82 Pipa leading Ø 3" Galvanis Tebal 3,2 mm Batang 90,000.00
83 Pipa PVC Ø 1" Batang 20,000.00
84 Pipa PVC Ø 2" Batang 35,000.00
85 Pipa PVC Ø 3" Batang 45,000.00
86 Pipa PVC Ø 4" Batang 60,000.00
87 Pelamur Tembok Kg 20,000.00
88 Plin Keramik Buah 5,000.00
89 plywood Tebal 9 mm Lembar 150,000.00
90 Pemasangan Atap Baja Ringan M² 275,000.00
91 Residu Kg 5,000.00
92 Reservoir Air 500 Ltr Buah 1,800,000.00
93 Reservoir Air 1000 Ltr Buah 2,500,000.00
94 Reservoir Air 500 Ltr Stainless steel Buah 2,000,000.00
95 Saklar Buah 20,000.00
96 Semen @ 40 Kg Zak 60,000.00
97 Semen @ 40 Kg Kg 1,500.00
98 Semen Putih @ 50 Kg Zak 90,000.00
99 Semen Putih @ 50 Kg Kg 1,800.00
100 Semen Warna Kg 1,500.00
101 Seng Genteng Metal M² 50,000.00
102 Seng BJLS 0,20 Cat Pabrik M² 50,000.00
103 Seng Gelombang BJLS 30 M² 60,000.00
104 Seng Gelombang BJLS 30 Cat Pabrik M² 55,000.00
105 Seng Plat BJLS 20 M² 50,000.00
106 Seng Plat BJLS 30 M² 65,000.00
107 Solar ( Industri ) Liter 9,500.00
108 Stut Werk (Ska Folding) M³ 3,000,000.00
109 Sekrup Fixer Buah 900.00
110 Sealant Kg 50,000.00
111 Sumur + Pompa Tangan Terpasang Unit 1,500,000.00
112 Tanah Timbun M³ 65,000.00
113 Tiang Pancang M' 300,000.00
114 Tralis Besi M² 385,000.00
115 Titik Lampu + Instalasi Titik 150,000.00
116 Urinoir Keramik Unit 1,000,000.00
117 Vinyl M² 25,000.00
118 WireMesh (Ulir) Kg 175,000.00
119 Zakering ( Kast Lokal 1 Zakering ) Unit 30,000.00
120 Zakering ( Kast Lokal 2 Zakering ) Unit 50,000.00
121 Besi Strip Tebal 5 mm Kg 15,000.00
122 Jendela UPVC M² 120,000.00
123 Kerawang(roster) M² 275,000.00
124 Reiling Pagar Hollow (Di Cat Putih) M² 950,000.00
125 Fiber M 350,000.00
126 Dempul Tembok M² 25,000.00
C. ALAT
1 Stamper Hari-Sewa 125,000.00
2 Dump Truck Jam 225,000.00
3 Molen Jam 25,000.00
Catatan : bila bahan tidak tercantum di tabel ini boleh ditambah