Anda di halaman 1dari 40

PERHITUNGAN VOLUME

PROYEK GYM AREA 2 LANTAI


I. Pekerjaan Persiapan
No Pekerjaan Perhitungan Volume
.
1 Pembersihan Lahan

Panjang = 20 m
Lebar = 12 m
Luas = Panjang x Lebar 240 m²
= 20 m x 12 m
= 240 m²

2 Pembuatan Papan Nama Proyek

Kebutuhan Bahan
 Papan nama kayu dengan ukuran
0,75 m x 0,4 m sejumlah 1 lembar
 Kayu ukuran panjang 2 m
sejumlah 2 lembar 1 ls
 Papan kayu horizontal, panjang 0,5
m sejumlah 1 lembar

3 Pemagaran
Keliling Lapangan = (22x2) + (16x2)
= 76 m

Kebutuhan Bahan
 Seng Ukuran 2 m x 1 m, t = 2 mm
Seng di pasang dengan posisi tegak
Kebuthan seng = 76 : 1 m
= 76 lembar 76 m
 Kayu 5/7 (panjang 4m)
Arah vertikal dipasang setiap
jarak 2 m
Kebutuhan = (76:2) = 38 buah
Arah horisontal dipasang 2 tingkat
Kebutuhan = (76:4) x 2 = 38 buah

Kebutuhan kayu total = 38 + 38


= 76 buah

PERHITUNGAN VOLUME 1
4 Pemasangan Bowplank Keliling bowplank
= 2(12+2) + 2(16+2)
= 64 m

Kebutuhan Bahan
 Banyak Patok = 64:2 = 32 Unit
Ukuran tiang (5/7)
= 0.05m x 0.07m
Panjang = 1 m
Volume = ( 0.05 x 0.07 x 1 x 32 )
= 0.112 m³
 Ukuran Papan (3/20) 64 m
= 0.03 m x 0.20 m
Panjang = 4m
Banyak Papan = 64:4 = 16 Lembar
Volume = (0.03 x 0.2 x 4 x 16)
= 0.384 m ³

Volume Total
= Volume Patok + Volume Papan
= 0.112 + 0.384
= 0.496 m³

5 Direksi Keet Panjang = 4 m


Lebar = 4 m
Luas = Panjang x Lebar 16 m²
= 4 m x 4 m = 16 m²

6 Gudang Material Panjang = 4 m


Lebar = 4 m
Luas = Panjang x Lebar 16 m²
= 4 m x 4 m = 16 m²

7 Air dan Listrik Kerja Volume = 1 Ls 1 Ls


II. Pekerjaan Tanah
No Pekerjaan Perhitungan Volume
.
1. Galian Tanah
a Galian Tanah Pondasi Foot Plat (F1)
Luas Galian 1 Pondasi Foot Plat (F1)
P = 1.7 m
L = 1.7 m
Tinggi = 2.55 m
Jumlah = 12 unit 88.434 m³
Volume = P x L x Tinggi
= 1.7 m x 1.7 m x 2.55 m
= 7.369 m³

Volume Total = 7.369 m³ x 12


= 88.434 m³

PERHITUNGAN VOLUME 2
b Galian Tanah Pondasi Batu Kali (P1)
Panjang Galian = 74 m
Lebar Galian = 1.2 m
Tinggi Galian = 1.15 m
Volume Galian = 74x1.2x1.15 102.12 m³
= 102.12 m³

c Galian Tanah Pondasi Batu Kali (P2)


Panjang Galian = 48 m
Lebar Galian = 0.7 m
Tinggi Galian = 1.15 m 38.64 m³
Volume Galian = 48x1.15x0.7
= 38.64 m³

2. Urugan Pasir
a Urugan Pasir Dasar Pondasi Foot
Plate (F1) Volume Urugan Pasir 1 Pondasi (F1)
= 1.702 x 0.1 = 0.289 m³
Volume 12 Pondasi (F1) = 0.289 x 12 3.468 m³
= 3.468 m³

b Urugan Pasir Dasar Pondasi Batu


Kali (P1) Luas Urugan Pasir Batu Kali (P1)
= 1.2x0.1 = 0.12 m²
Volume Urugan Pasir Batu Kali (P1) 8.88 m3
= 0.12 x 74 = 8.88 m3

c Urugan Pasir Dasar Pondasi Batu


Kali (P2) Luas Urugan Pasir Batu Kali (P2)
= 0.7 x 0.1 = 0.07 m2
Volume Urugan Pasir Batu Kali (P2) 3.36 m3
= 0.07 x 48 = 3.36 m3

3. Urugan Tanah
a Urugan Tanah Pondasi Foot Plat (F1)
Volume Galian Tanah
= 7.369 m³
Volume Urugan Pasir
= 1.702 x 0.1 = 0.289 m³
Volume Lantai Kerja
= 1.72 x 0.15 = 0.4335 m³
Volume Pondasi FootPlat 66.542 m3
= (1.5x1.5x0.25) + (0.42x0.25)
+4(1/2x0.25x0.55x0.40)
+4(1/3x0.552x0.25) + (0.4x0.4x1.8)
= 1.10133 m³
Volume Urugan 12 FootPlat
= 12(7.369-0.289-0.4335-1.10133)
= 66.542 m3

PERHITUNGAN VOLUME 3
b Urugan Tanah Pondasi Batu Kali
(P1)
Luas Urugan Tanah P1
= 2((0.10+0.44)/2x0.9) = 0.486 m2
Volume Batu Kali P1 35.964 m³
= 0.486 x 74
= 35.964 m³

c Urugan Tanah Pondasi Batu Kali


(P2)
Luas Urugan Tanah P2
= (0.10+0.50)/2x0.9 = 0.27 m2
Volume Batu Kali P2 12.96 m³
= 0.27 x 48
= 12.96 m³

III. Pekerjaan Pondasi


No Pekerjaan Perhitungan Volume
.
1. Pondasi Footplate
a Lantai Kerja (F1)
Volume Lantai Kerja (F1)
= 1.72 x 0.15 6.75 m³
= 0.4335 m³
Volume 30 Pondasi (F1) = 0.225 x30
= 6.75 m³

b Penulangan
Jumlah Footplat = 30 buah

 Tulangan Pedestal
Pedestal 30x30/K1

PERHITUNGAN VOLUME 4
o Tulangan longitudinal = 8D25
D25, berat = 3.853 kg/m
Panjang tulangan longitudinal
= h + 40D
= 2.4+(40x0.016) 2835 kg
= 3.04 m
Berat tulangan longitudinal
= 3.04 x 8 x 3.853
= 93.705 kg

o Begel Ø10-100
Ø10-100, berat = 0.617 kg/m
Panjang Begel :
= 2(b+h+6D)
= 2[(0.4-2x0.04)
+ (0.4-2x0.04)+(6x0.010)]
= 1.4 m
Jumlah sengkang = (2.4/0.10) + 1
= 25 buah
Panjang total begel = 1.4x25 = 35 m
Berat total begel = 35 x 0.617
= 21.595 kg

 Tulangan Footplate
Jarak antara tulangan = 0.15 m
Jumlah Footplat F1 = 30 buah
o Tulangan Atas
Jumlah Tulangan Atas (Ø12-100)
= ((1./0.15+1) x 2) = 22 buah
Panjang Tulangan
= ((1.5-(2x0.05))
+(2x(0.25-(2x0.05)))
+(2x6x0.016))x22
= 41.624 m
o Tulangan Bawah
Jumlah Tulangan Bawah (Ø16-150)
= ((1.5/0.15+1) x 2) = 22 buah
Panjang Tulangan
= ((1.5-(2x0.05))
+(2x6x0.016))x22
= 35.024 m

Berat total tulangan atas dan bawah:


= (41.624 + 35.024) x 1.578
= 120.95 kg

Berat Total 12 Tulangan


Footplate (F1):
= 12 (93.705+21.595+ 120.95)
= 2835 kg

PERHITUNGAN VOLUME 5
c Bekisting

Bekisting 1
= 4 (1.50 x 0.25) = 1.5 m²
Bekisting 2
= 4 x ((0.4+1.5)/2 x (0.552+0.252)1/2)
= 2.2957 m² 82.029 m²
Bekisting 3
= 4 (1.90 x 0.40) = 3.04 m²
Luas total bekisting 12 Footplat (F1)
= 12 ( 1.5 + 2.2957 + 3.04 )
= 82.0293 m²

d Pengecoran
Volume 1
= 1.5x1.5x0.25
= 0.5625 m³
Volume 2
= (0.42x0.25)+4(1/2x0.25x0.55x0.40)
+4(1/3x0.552x0.25)
= 0.25083 m³
Volume 3
= 0.4x0.4x1.53
= 0.304 m³
Volume total 1 Footplat
= 0.5625 + 0.25083 + 0.304 13.046 m³
= 1.11733 m³
Volume 12 Foot Plat (F1)
= 1.11733 x 12
= 13.41 m³

Vol Tulangan
= Berat Tulangan : Berat jenis baja
= 2835 kg : 7850 kg/m³
= 0.3611 m³
Volume Pengecoran
= Vol Total - Vol Tulangan
= 13.41 - 0.3611
= 13.0469 m³

2. Pondasi Batu Kali


a.1 Aanstamping (P1)
Luas Aanstamping Batu Kali (P1)
= 1.2 x 0.15 = 0.18 m² 13.32 m3
Volume Aanstamping Batu Kali (P1)
= 0.18 x 74 = 13.32 m3

a.2 Aanstamping (P2)

PERHITUNGAN VOLUME 6
Luas Aanstamping Batu Kali (P2)
= 0.7 x 0.15 = 0.105 m2 5.04 m3
Volume Aanstamping Batu Kali (P2)
= 0.105 x 48 = 5.04 m3

b.1 Pondasi Batu Kali (P1)

Luas Batu Kali P1


= (0.25+1)/2 x 1 = 0.625 m2
Volume Batu Kali P1 46.25 m³
= 0.625 x 74
= 46.25 m³

b.2 Pondasi Batu Kali (P2)

Luas Batu Kali P2


= (0.15+0.6)/2 x 1 = 0.375 m2
Volume Batu Kali P2 18 m³
= 0.375 x 48
= 18 m³

IV. Pekerjaan Struktur Beton Bertulang


No. Pekerjaan Perhitungan Volume
1. Sloof
a.1 Penulangan (S1)
L = 68 m
Jumlah = 17 batang @ 4m
Tulangan Pokok 6D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 6 (4+2x40x0.025)
= 36 m
Panjang Total Tulangan Pokok 2820.231
= 17 x 36 kg
= 612 m
Berat Total Tulangan Pokok
= 612 x 3.853 = 2358.036 kg

Jumlah Begel (Ø10-100)


= (68/0.1) + 1
= 681 buah
Panjang Begel
= 2 ( b + h + 6Ø)

PERHITUNGAN VOLUME 7
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 681 x 1.1 = 749.1 m
Berat Total Begel
= 749.1 x 0.617 = 462.1947 kg

Berat Total Penulangan Sloof (S1)


= 2358.04+462.1947 = 2820.231 kg

a.2 Penulangan (S2)


L = 54 m
Jumlah = 27 batang @ 2m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 4 (2+2x40x0.012)
= 11.84 m
Panjang Total Tulangan Pokok 517.534
= 27 x 11.84 kg
= 319.68 m
Berat Total Tulangan Pokok
= 319.68 x 0.888 = 283.876 kg

Jumlah Begel (Ø10-100)


= (54/0.1) + 1
= 541 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.2-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.7 m
Panjang Total begel
= 541 x 0.7 = 378.7 m
Berat Total Begel
= 378.7 x 0.617 = 233.658 kg

Berat Total Penulangan Sloof (S2)


= 283.876 +233.658 = 517.534 kg

b.1 Bekisting (S1)


L = 68 m
H = 0.4 m

PERHITUNGAN VOLUME 8
54.4 m²
Luas Bekisting
= 2 x 68 x 0.4
= 54.4 m²

b.2 Bekisting (S2)


L = 54 m
H = 0.2 m
21.6 m²
Luas Bekisting
= 2 x 54 x 0.2
= 21.6 m²

c.1 Pengecoran (S1)


Volume Total = 68 x 0.4 x 0.25
= 6.8 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 6.441 m³
= 2820.231 kg : 7850 kg/m³
= 0.359 m³

Volume pengecoran = 6.8 – 0.3092


= 6.441 m³

c.2 Pengecoran (S2)


Volume Total = 54 x 0.2 x 0.15
= 1.62 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 1.554 m³
= 517.534 kg: 7850 kg/m³
= 0.06593 m³

Volume pengecoran = 1.62 – 0.06593


= 1.554 m³

2. Kolom Lantai 1
a.1 Penulangan (K1)
 Tulangan pokok diteruskan L = 52.80 m
dari FootPlat, berakhir di balok Jumlah = 12 batang @ 4.40 m
Tulangan Pokok 8D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 8 (4.40+40x0.025)
= 43.2 m
Panjang Total Tulangan Pokok
= 12 x 43.2 2441.29

PERHITUNGAN VOLUME 9
= 518.4 m kg
Berat Total Tulangan Pokok
= 518.4 x 3.853 = 1997.395 kg

Jumlah Begel (Ø10-100)


= (52.80 /0.1) + 1
= 529 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.4-(2x0.04))
+ (6x0.01)]
= 1.36 m

Panjang Total begel


= 529 x 1.36 = 719.44 m
Berat Total Begel
= 719.44 x 0.617 = 443.8945 kg

Berat Total Penulangan Kolom (K1)


= 1997.395+443.8945= 2441.29 kg

a.2 Penulangan (K2 di Bangunan


Utama) L = 17.6 m
 Untuk lantai 1, tulangan Jumlah
pokok dimulai dari sloof, 4 batang di lantai 1 @ 4.40 m
berakhir di balok.
Panjang bentang
= 4.40 m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 4 (4.40+2x40x0.012) 185.26 kg
= 21.44 m
Panjang Total Tulangan Pokok
= 8 x 21.44
= 171.52 m
Berat Total Tulangan Pokok
= 171.52 x 0.888 = 152.31 kg

Jumlah Begel (Ø10-200)


= (17.6 /0.2) + 1
= 89 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.15-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.6 m
Panjang Total begel

PERHITUNGAN VOLUME 10
= 89 x 0.6 = 53.4 m
Berat Total Begel
= 53.4 x 0.617 = 32.95 kg

Berat Total Penulangan Kolom (K2)


= 152.31 + 32.95 = 185.26 kg

a.3 Penulangan (K2 di Pagar)


 Tulangan pokok dimulai dari L = 69 m
sloop S2 Jumlah = 23 batang di sekeliling
taman @ 3.00 m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 8 (3.00+40x0.012)
= 27.84 m
Panjang Total Tulangan Pokok
= 23 x 27.84
= 640.32 m
Berat Total Tulangan Pokok
= 640.32 x 0.888 = 568.604 kg
696.693
Jumlah Begel (Ø10-200) kg
= (69/0.2) + 1
= 346 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.15-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.6 m
Panjang Total begel
= 346 x 0.6 = 207.6 m
Berat Total Begel
= 207.6 x 0.617 = 128.089 kg

Berat Total Penulangan Kolom (K2)


= 568.604 +128.089 = 696.693 kg

b.1 Bekisting (K1)


L = 52.80 m
B = 0.4 m
H = 0.4 m
84.48 m²
Luas Bekisting
= 4 x 52.80 x 0.4
= 84.48 m²

PERHITUNGAN VOLUME 11
b.2 Bekisting (K2 di Bangunan Utama)
L = 17.6 m
B = 0.15 m
H = 0.15 m
10.56 m²
Luas Bekisting
= 4 x 17.6 x 0.15
= 10.56 m²

b.3 Bekisting (K2 di Pagar)


L = 69 m
B = 0.15 m
H = 0.15 m
41.4 m²
Luas Bekisting
= 4 x 69 x 0.15
= 41.4 m²

c.1 Pengecoran (K1)


Volume Total = 52.80 x 0.4 x 0.4
= 8.448 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 2441.29 kg: 7850 kg/m³ 8.137 m³
= 0.31099 m³

Volume pengecoran = 8.448–0.31099


= 8.137 m³

c.2 Pengecoran (K2 di Bangunan


Utama) Volume Total = 17.6 x 0.15 x 0.15
= 0.396 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 0.3724 m³
= 185.26 kg : 7850 kg/m³
= 0.0236 m³

Volume pengecoran = 0.396 – 0.0236


= 0.3724 m³

c.3 Pengecoran (K2 di Pagar)


Volume Total = 69 x 0.15 x 0.15
= 1.5525 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 1.464 m³
= 696.693 kg : 7850 kg/m³
= 0.08875 m³

PERHITUNGAN VOLUME 12
Volume pengecoran = 1.553–0.08875
= 1.464 m³

3. Balok Lantai
a.1 Penulangan (B1)
L =6m
Jumlah = 3 batang @ 2.00 m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 4 (2.00+2x40x0.012)
= 11.84 m
Panjang Total Tulangan Pokok
= 3 x 11.84
= 35.52 m 65.415 kg
Berat Total Tulangan Pokok
= 35.52 x 0.888 = 31.5418 kg

Jumlah Begel (Ø10-100)


= (6 /0.1) + 1
= 61 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.3-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.9 m
Panjang Total begel
= 61 x 0.9 = 54.9 m
Berat Total Begel
= 54.9 x 0.617 = 33.8733 kg
Berat Total Penulangan Balok (B1)
= 31.5418 +33.8733 = 65.415kg

a.2 Penulangan (B2 Tumpuan)


L = 34 m
Jumlah = 34 bagian; 2 bagian tiap
balok B2 @ 1.00 m

Tulangan Pokok 5D25


Berat = 3.853 kg/m
Begel Ø10-50
Berat = 0.617 kg/m

Panjang Tulangan Pokok 1182.706


= 5x1 + 1x20x0.025 kg
= 5.5 m
Panjang Total Tulangan Pokok
= 34 x 5.5

PERHITUNGAN VOLUME 13
= 187 m
Berat Total Tulangan Pokok
= 187 x 3.853 = 720.511 kg
Jumlah Begel (Ø10-50)
= (34/0.05) + 1
= 681 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 681 x 1.1 = 749.1 m
Berat Total Begel
= 749.1 x 0.617 = 462.195 kg

Berat Total Penulangan


Balok (B2) Tumpuan
= 720.511 +462.195 = 1182.706 kg

a.3 Penulangan (B2 Lapangan) L = 34 m


Jumlah = 34 bagian; 1 bagian tiap
balok B2 @ 2.00 m
Tulangan Pokok 5D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 5x1 + 2x20x0.025
=6m
Panjang Total Tulangan Pokok
= 34 x 6
= 204 m 1017.45
Berat Total Tulangan Pokok kg
= 204 x 3.853 = 786.012 kg

Jumlah Begel (Ø10-100)


= (34/0.1) + 1
= 341 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 341 x 1.1 = 375.1 m
Berat Total Begel
= 375.1 x 0.617 = 231.437 kg
Berat Total Penulangan
Balok (B2) Lapangan

PERHITUNGAN VOLUME 14
= 786.012+231.437 = 1017.45 kg

a.4 Penulangan (B2 Kantilever)


L = 14 m
Jumlah = 14 bagian berada di tepi
sekeliling bangunan utama
@ 1.00 m
Tulangan Pokok 5D25
Berat = 3.853 kg/m
Begel Ø10-50
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 5x1 + 5x20x0.025
= 7.5 m
Panjang Total Tulangan Pokok
= 14 x 7.5 594.601
= 105 m kg
Berat Total Tulangan Pokok
= 105 x 3.853 = 404.565 kg

Jumlah Begel (Ø10-50)


= (14/0.05) + 1
= 281 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 281 x 1.1 = 308 m
Berat Total Begel
= 308x 0.617 = 190.036 kg

Berat Total Penulangan


Balok (B2) Kantilever
= 404.565 +190.036 = 594.601 kg

b.1 Bekisting (B1)

L =6m
B = 0.15 m
H = 0.18 m 3.06 m²

Luas Bekisting
= 6 (2 x 0.18 + 0.15)
= 3.06 m²

b.2 Bekisting (B2)


L total = 82 m

PERHITUNGAN VOLUME 15
B = 0.25 m
H = 0.28 m

69.26 m²
Luas Bekisting
= 82(2x0.28+0.25)+14(0.25x0.4)
+12x0.12
= 69.26 m²

c.1 Pengecoran (B1)


Volume Total = 6 x 0.3 x 0.15
= 0.27 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 65.415kg: 7850 kg/m³ 0.2617 m³
= 0.008333 m³

Volume pengecoran = 0.27 – 0.00833


= 0.2617 m³

c.2 Pengecoran (B2)


Volume Total = 82 x 0.25 x 0.4
= 8.2 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= (1182.706 + 1017.45 + 594.601) 7.844 m³
: 7850 kg/m³
= 0.356 m³

Volume pengecoran = 8.2 – 0.356


= 7.844 m³

4. Plat Lantai
a.1 Penulangan (Tipe 4x4)
Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 5

Arah X
Panjang Tulangan 2094.61
= 4 + 2 x 6 x 0.01 = 4.12 m kg
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah X
= 4.12 x 41 x 0.62 x 2 = 209.461 kg

PERHITUNGAN VOLUME 16
Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah Y
= 4.12 x 41 x 0.62 x 2 = 209.461 kg

Berat Total Tulangan


= 5 (209.461 + 209.461)
= 2094.61 kg

a.2 Penulangan (Tipe 2x2)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 2

Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 2.12 x 21 x 0.62 x 2 = 55.205 kg

Arah Y 220.82 kg
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 2.12 x 21 x 0.62 x 2 = 55.205 kg

Berat Total Tulangan


= 2 (55.205 + 55.205)
= 220.82 kg
a.3 Penulangan (Tipe 1x4)
Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 10

Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan 1131.378
= 4 / 0.1 + 1 = 41 kg
Berat Tulangan Arah X
= 1.12 x 41 x 0.62 x 2 = 56.941 kg

Arah Y

PERHITUNGAN VOLUME 17
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 4.12 x 11 x 0.62 x 2 = 56.197 kg

Berat Total Tulangan


= 10 (56.941 + 56.197)
= 1131.378 kg

a.4 Penulangan (Tipe 1x1)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 4
Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah X
= 1.12 x 11 x 0.62 x 2 = 15.277 kg
122.2144
Arah Y kg
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 1.12 x 11 x 0.62 x 2 = 15.277 kg

Berat Total Tulangan


= 4 (15.277 + 15.277)
= 122.2144 kg

b.1 Bekisting (Tipe 4x4)

Luas Total Bekisting 80 m2


= 5 (4 x 4) = 80 m2

b.2 Bekisting (Tipe 2x2)

Luas Total Bekisting 8 m2


= 2 (2 x 2) = 8 m2

PERHITUNGAN VOLUME 18
b.3 Bekisting
(Tipe 1x4)
Luas Total Bekisting
= 10 (4 x 1) + 10 (4 x 0.12) 44.8 m2
= 44.8 m2

b.4 Bekisting (Tipe 1x1)

Luas Total Bekisting


= 4 (1 x 1) + 4 x 2 (1 x 0.12) 4.96 m2
= 4.96 m2

c.1 Pengecoran (Tipe 4x4)

Volume Total = 5 (4 x 4 x 0.12)


= 9.6 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 2094.61 kg : 7850 kg/m³ 9.333 m³
= 0.2668 m³

Volume pengecoran = 9.6 – 0.2668


= 9.333 m³

c.2 Pengecoran (Tipe 2x2)


Volume Total = 2 (2 x 2 x 0.12)
= 0.96 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 220.82 kg : 7850 kg/m³ 0.9319 m³
= 0.02813 m³

Volume pengecoran = 0.96 – 0.02813


= 0.9319 m³

c.3 Pengecoran (Tipe 1x4)


Volume Total = 10 (1 x 4 x 0.12)
= 4.8 m³

PERHITUNGAN VOLUME 19
Volume Tulangan
= Berat tulangan : Berat jenis baja 4.656 m³
= 1131.378 kg : 7850 kg/m³
= 0.144 m³

Volume pengecoran = 4.8 – 0.144


= 4.656 m³

c.4 Pengecoran (Tipe 1x1)


Volume Total = 4 (1 x 1 x 0.12)
= 0.48 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 122.2144 kg : 7850 kg/m³ 0.4644 m³
= 0.01557 m³

Volume pengecoran = 0.48 – 0.01557


= 0.4644 m³

5. Tangga
a.1 Penulangan (2 Kolom K2)
L =4m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 8 (2+40x0.012)
= 19.84 m
Panjang Total Tulangan Pokok
= 2 x 19.84
= 39.68 m 43.01 kg
Berat Total Tulangan Pokok
= 39.68 x 0.888 = 35.236 kg

Jumlah Begel (Ø10-200)


= (4/0.2) + 1
= 21 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.15-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.6 m
Panjang Total begel
= 21 x 0.6 = 12.6 m
Berat Total Begel

PERHITUNGAN VOLUME 20
= 12.6 x 0.617 = 7.774 kg

Berat Total Penulangan Kolom (K2)


= 35.236 + 7.774 = 43.01 kg

a.2 Penulangan (4 Balok B1)


2 batang @ 2 m L =6m
2 batang @ 1 m Panjang Batang ± 1.5 m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 4 (1.5+2x40x0.012)
= 9.84 m
Panjang Total Tulangan Pokok
= 4 x 9.84
= 39.36 m 68.825 kg
Berat Total Tulangan Pokok
= 39.36 x 0.888 = 34.952 kg

Jumlah Begel (Ø10-100)


= (6 /0.1) + 1
= 61 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.3-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.9 m
Panjang Total begel
= 61 x 0.9 = 54.9 m
Berat Total Begel
= 54.9 x 0.617 = 33.8733 kg
Berat Total Penulangan Balok (B1)
= 34.952 +33.8733 = 68.825 kg

a.3 Penulangan (Plat Bordes 2 x 1)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 1

Arah X
Panjang Tulangan 58.082 kg
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 1.12 x 21 x 0.62 x 2 = 29.165 kg

Arah Y

PERHITUNGAN VOLUME 21
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 2.12 x 11 x 0.62 x 2 = 28.917 kg

Berat Total Tulangan


= 29.165 + 28.917
= 58.082 kg

a.4 Penulangan (Plat Tangga 0.9 x 3.6)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 2

Arah X
Panjang Tulangan
= 0.9 + 2 x 6 x 0.01 = 1.02 m
Jumlah Tulangan
= 3.6 / 0.1 + 1 = 37 185.852
Berat Tulangan Arah X kg
= 1.02 x 37 x 0.62 x 2 = 46.798 kg

Arah Y
Panjang Tulangan
= 3.6 + 2 x 6 x 0.01 = 3.72 m
Jumlah Tulangan
= 0.9 / 0.1 + 1 = 10
Berat Tulangan Arah Y
= 3.72 x 10 x 0.62 x 2 = 46.128 kg

Berat Total Tulangan


= 2 (46.798 + 46.128)
= 185.852 kg

a.5 Penulangan (Anak Tangga)


Uptrade = 20 cm Ukuran tulangan = D10 – 200
Antrade = 30 cm Berat tulangan = 0.62 kg/m
Jumlah anak tangga = 18

Arah X
Panjang Tulangan 87.041 kg
= 0.3 + 0.2 + 2 x 6 x 0.01 = 0.62 m
Jumlah Tulangan
= 0.9 / 0.2 + 1 = 6
Berat Tulangan Arah X
= 0.62 x 6 x 0.62 = 2.306 kg

Arah Y
Panjang Tulangan

PERHITUNGAN VOLUME 22
= 0.9 + 2 x 6 x 0.01 = 1.02 m
Jumlah Tulangan
= 0.5 / 0.2 + 1 = 4
Berat Tulangan Arah Y
= 1.02 x 4 x 0.62 = 2.53 kg

Berat Total Tulangan


= 18 (2.306 + 2.53)
= 87.041 kg

b.1 Bekisting (2 Kolom K2)

Luas Bekisting
= 4 x 4 x 0.15 2.4 m²
= 2.4 m²

b.2 Bekisting (4 Balok B1)

Luas Bekisting
= 6 (2 x 0.18 + 0.15) 3.06 m²
= 3.06 m²

b.3 Bekisting (Plat Bordes 2 x 1)

Luas Total Bekisting 2 m2


= 2 x 1 = 2 m2

b.4 Bekisting
(Plat Tangga
0.9 x 3.6) Luas Total Bekisting
= 2 (0.9 x 3.6) + 2 (2 x 3.6 x 0.12)
= 8.208 m2 8.208 m2

b.5 Bekisting
(Anak Tangga) Luas Total Bekisting
= 18 (0.2 x 0.9) + 36 (0.2 x 0.3 / 2) 4.32 m2
= 4.32 m2

c.1 Pengecoran (2 Kolom K2) Volume Total = 4 x 0.15 x 0.15


PERHITUNGAN VOLUME 23
= 0.09 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 43.01 kg : 7850 kg/m³ 0.0845 m³
= 0.0055 m³

Volume pengecoran = 0.09 – 0.0055


= 0.0845 m³

c.2 Pengecoran (4 Balok B1) Volume Total = 6 x 0.3 x 0.15


= 0.27 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 0.261 m³
= 68.825 kg : 7850 kg/m³
= 0.008768 m³

Volume pengecoran = 0.27 – 0.00877


= 0.261 m³

c.3 Pengecoran (Plat Bordes 2 x 1) Volume Total = 2 x 1 x 0.12


= 0.24 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 58.082 kg : 7850 kg/m³ 0.2326 m³
= 0.0074 m³

Volume pengecoran = 0.24 – 0.0074


= 0.2326 m³

c.4 Pengecoran (Plat Tangga 0.9 x 3.6) Volume Total = 2 (0.9 x 3.6 x 0.12)
= 0.778 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 185.852 kg : 7850 kg/m³ 0.7543 m³
= 0.02368 m³

Volume pengecoran = 0.778 – 0.0237


= 0.7543 m³

c.5 Pengecoran (Anak Tangga) Volume Total = 18 (0.9 x 0.3 x 0.2 / 2)


= 0.486 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 0.475 m³
= 87.041 kg : 7850 kg/m³
= 0.0111 m³

PERHITUNGAN VOLUME 24
Volume pengecoran = 0.486 – 0.0111
= 0.475 m³

6. Kolom Lantai 2
a.1 Penulangan (K1)
 Tulangan pokok dimulai dari L = 50.40 m
balok, berakhir di balok atap Jumlah = 3 batang @ 4.00 m
3 batang @ 4.13 m
3 batang @ 4.27 m
3 batang @ 4.40 m
Panjang bentang ± 4.20 m
Tulangan Pokok 8D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 8 (4.20+2x40x0.025) 2717.06
= 49.6 m kg
Panjang Total Tulangan Pokok
= 12 x 49.6
= 595.2 m
Berat Total Tulangan Pokok
= 595.2 x 3.853 = 2293.306 kg

Jumlah Begel (Ø10-100)


= (50.40/0.1) + 1
= 505 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.4-(2x0.04))
+ (6x0.01)]
= 1.36 m
Panjang Total begel
= 505 x 1.36 = 686.8 m
Berat Total Begel
= 686.8 x 0.617 = 423.756 kg

Berat Total Penulangan Kolom (K1)


= 2293.306+423.756 = 2717.06 kg

a.2 Penulangan (K2 di Bangunan


Utama) L = 16.195 m
 Untuk lantai 2, tulangan Jumlah

PERHITUNGAN VOLUME 25
pokok dimulai dari balok, 3 batang di lantai 2 @ 4.065 m
berakhir di balok atap. 1 batang di lantai 2 @ 4.00 m
Panjang bentang
= (3x4.065 + 1x4.00)/4
± 4.05 m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 8 (4.05 +2x40x0.012)
= 40.08 m 172.72 kg
Panjang Total Tulangan Pokok
= 4 x 40.08
= 160.32 m
Berat Total Tulangan Pokok
= 160.32 x 0.888 = 142.36 kg

Jumlah Begel (Ø10-200)


= (16.195 /0.2) + 1
= 82 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.15-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.6 m
Panjang Total begel
= 82 x 0.6 = 49.2 m
Berat Total Begel
= 49.2 x 0.617 = 30.36 kg

Berat Total Penulangan Kolom (K2)


= 142.36 + 30.36 = 172.72 kg

b.1 Bekisting (K1)


L = 50.40 m
B = 0.4 m
H = 0.4 m
80.64 m²
Luas Bekisting
= 4 x 50.40 x 0.4
= 80.64 m²

PERHITUNGAN VOLUME 26
b.2 Bekisting (K2 di Bangunan Utama)
L = 16.195 m
B = 0.15 m
H = 0.15 m
9.717 m²
Luas Bekisting
= 4 x 16.195 x 0.15
= 9.717 m²

c.1 Pengecoran (K1)


Volume Total = 50.40 x 0.4 x 0.4
= 8.064 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 7.7179 m3
= 2717.06 kg : 7850 kg/m³
= 0.3461 m³

Volume pengecoran = 8.064 – 0.3461


= 7.7179 m³

c.2 Pengecoran (K2 di Bangunan


Utama) Volume Total = 16.195 x 0.15 x 0.15
= 0.36 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 0.338 m³
= 172.72 kg : 7850 kg/m³
= 0.022 m³

Volume pengecoran = 0.36 – 0.022


= 0.338 m³

V. Pekerjaan Atap
No. Pekerjaan Perhitungan Volume
1. Balok Atap
a.1 Penulangan (B1)
L =6m
Jumlah = 3 batang @ 2.00 m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok 65.415 kg


= 4 (2.00+2x40x0.012)
= 11.84 m
Panjang Total Tulangan Pokok
= 3 x 11.84

PERHITUNGAN VOLUME 27
= 35.52 m
Berat Total Tulangan Pokok
= 35.52 x 0.888 = 31.5418 kg

Jumlah Begel (Ø10-100)


= (6 /0.1) + 1
= 61 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.3-(2x0.015))
+ (0.15-(2x0.015)) + (6x0.01)]
= 0.9 m
Panjang Total begel
= 61 x 0.9 = 54.9 m
Berat Total Begel
= 54.9 x 0.617 = 33.8733 kg
Berat Total Penulangan Balok (B1)
= 31.5418 +33.8733 = 65.415kg

a.2 Penulangan (B2 Tumpuan)


L = 34 m
Jumlah = 34 bagian; 2 bagian tiap
balok B2 @ 1.00 m

Tulangan Pokok 5D25


Berat = 3.853 kg/m
Begel Ø10-50
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 5x1 + 1x20x0.025
= 5.5 m
Panjang Total Tulangan Pokok
= 34 x 5.5 1182.706
= 187 m kg
Berat Total Tulangan Pokok
= 187 x 3.853 = 720.511 kg
Jumlah Begel (Ø10-50)
= (34/0.05) + 1
= 681 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 681 x 1.1 = 749.1 m
Berat Total Begel
= 749.1 x 0.617 = 462.195 kg

Berat Total Penulangan

PERHITUNGAN VOLUME 28
Balok (B2) Tumpuan
= 720.511 +462.195 = 1182.706 kg
a.3 Penulangan (B2 Lapangan) L = 34 m
Jumlah = 34 bagian; 1 bagian tiap
balok B2 @ 2.00 m
Tulangan Pokok 5D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m

Panjang Tulangan Pokok


= 5x1 + 2x20x0.025
=6m
Panjang Total Tulangan Pokok
= 34 x 6
= 204 m 1017.45
Berat Total Tulangan Pokok kg
= 204 x 3.853 = 786.012 kg

Jumlah Begel (Ø10-100)


= (34/0.1) + 1
= 341 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 341 x 1.1 = 375.1 m
Berat Total Begel
= 375.1 x 0.617 = 231.437 kg
Berat Total Penulangan
Balok (B2) Lapangan
= 786.012+231.437 = 1017.45 kg

a.4 Penulangan (B2 Kantilever)


L = 14 m
Jumlah = 14 bagian berada di tepi
sekeliling bangunan utama
@ 1.00 m
Tulangan Pokok 5D25
Berat = 3.853 kg/m
Begel Ø10-50
Berat = 0.617 kg/m
594.601
Panjang Tulangan Pokok kg
= 5x1 + 5x20x0.025
= 7.5 m
Panjang Total Tulangan Pokok
= 14 x 7.5
= 105 m

PERHITUNGAN VOLUME 29
Berat Total Tulangan Pokok
= 105 x 3.853 = 404.565 kg

Jumlah Begel (Ø10-50)


= (14/0.05) + 1
= 281 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 281 x 1.1 = 308 m
Berat Total Begel
= 308x 0.617 = 190.036 kg

Berat Total Penulangan


Balok (B2) Kantilever
= 404.565 +190.036 = 594.601 kg

b.1 Bekisting (B1)

L =6m
B = 0.15 m
H = 0.18 m 3.06 m²

Luas Bekisting
= 6 (2 x 0.18 + 0.15)
= 3.06 m²

b.2 Bekisting (B2)


L total = 82 m
B = 0.25 m
H = 0.28 m

69.26 m²
Luas Bekisting
= 82(2x0.28+0.25)+14(0.25x0.4)
+12x0.12
= 69.26 m²

c.1 Pengecoran (B2)


Volume Total = 82 x 0.6 x 0.4
= 8.2 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= (1182.706 + 1017.45 + 594.601) 7.844 m³
: 7850 kg/m³

PERHITUNGAN VOLUME 30
= 0.356 m³

Volume pengecoran = 8.2 – 0.356


= 7.844 m³

2. Plat Atap
a.1 Penulangan (Tipe 4x4)
Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 5

Arah X
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41 2094.61
Berat Tulangan Arah X kg
= 4.12 x 41 x 0.62 x 2 = 209.461 kg

Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah Y
= 4.12 x 41 x 0.62 x 2 = 209.461 kg

Berat Total Tulangan


= 5 (209.461 + 209.461)
= 2094.61 kg

a.2 Penulangan (Tipe 2x2)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 2

Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m 220.82 kg
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 2.12 x 21 x 0.62 x 2 = 55.205 kg

Arah Y
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan

PERHITUNGAN VOLUME 31
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 2.12 x 21 x 0.62 x 2 = 55.205 kg

Berat Total Tulangan


= 2 (55.205 + 55.205)
= 220.82 kg

a.3 Penulangan (Tipe 1x4)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 10

Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah X 1131.378
= 1.12 x 41 x 0.62 x 2 = 56.941 kg kg

Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 4.12 x 11 x 0.62 x 2 = 56.197 kg

Berat Total Tulangan


= 10 (56.941 + 56.197)
= 1131.378 kg

a.4 Penulangan (Tipe 1x1)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 4
Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m 122.2144
Jumlah Tulangan kg
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah X
= 1.12 x 11 x 0.62 x 2 = 15.277 kg

Arah Y
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y

PERHITUNGAN VOLUME 32
= 1.12 x 11 x 0.62 x 2 = 15.277 kg

Berat Total Tulangan


= 4 (15.277 + 15.277)
= 122.2144 kg

a.5 Penulangan (Tipe 2x4)


Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 1

Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41 215.065
Berat Tulangan Arah X kg
= 2.12 x 41 x 0.62 x 2 = 107.78 kg

Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 4.12 x 21 x 0.62 x 2 = 107.285 kg

Berat Total Tulangan


= 107.78 + 107.285
= 215.065 kg

b.1 Bekisting (Tipe 4x4)

Luas Total Bekisting


= 5 (4 x 4) = 80 m2 80 m2

b.2 Bekisting (Tipe 2x2)

Luas Total Bekisting 8 m2


= 2 (2 x 2) = 8 m2

PERHITUNGAN VOLUME 33
b.3 Bekisting
(Tipe 1x4)
Luas Total Bekisting
= 10 (4 x 1) + 10 (4 x 0.12) 44.8 m2
= 44.8 m2

b.4 Bekisting (Tipe 1x1)

Luas Total Bekisting


= 4 (1 x 1) + 4 x 2 (1 x 0.12) 4.96 m2
= 4.96 m2

b.5 Bekisting
(Tipe 2x4)
Luas Total Bekisting
= 4 x 2 = 8 m2 8 m2

c.1 Pengecoran (Tipe 4x4)


Volume Total = 5 (4 x 4 x 0.12)
= 9.6 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 9.333 m³
= 2094.61 kg : 7850 kg/m³
= 0.2668 m³

Volume pengecoran = 9.6 – 0.2668


= 9.333 m³

c.2 Pengecoran (Tipe 2x2)


Volume Total = 2 (2 x 2 x 0.12)
= 0.96 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 220.82 kg : 7850 kg/m³ 0.9319 m³
= 0.02813 m³

Volume pengecoran = 0.96 – 0.02813


= 0.9319 m³

c.3 Pengecoran (Tipe 1x4)


Volume Total = 10 (1 x 4 x 0.12)

PERHITUNGAN VOLUME 34
= 4.8 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 4.656 m³
= 1131.378 kg : 7850 kg/m³
= 0.144 m³

Volume pengecoran = 4.8 – 0.144


= 4.656 m³

c.4 Pengecoran (Tipe 1x1)


Volume Total = 4 (1 x 1 x 0.12)
= 0.48 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja
= 122.2144 kg : 7850 kg/m³ 0.4644 m³
= 0.01557 m³

Volume pengecoran = 0.48 – 0.01557


= 0.4644 m³

c.5 Pengecoran (Tipe 2x4)


Volume Total = 4 x 2 x 0.12
= 0.96 m³

Volume Tulangan
= Berat tulangan : Berat jenis baja 0.933 m³
= 215.065 kg : 7850 kg/m³
= 0.0274 m³

Volume pengecoran = 0.96 – 0.0274


= 0.933 m³

VI.
Pekerjaan Dinding
No. Pekerjaan Perhitungan Volume
1 Pasangan Batu Bata Lantai 1
Luas Pasangan Batu Bata
Luas Lt. 1 = 50 x 3.65 = 182.5 m²
Pagar = 48 x 3 = 144 m²
Luas Total = 182.5 + 144 = 326.5 m2
247.22 m²
Luas Lubang
Kusen type P1 (1 Unit)
Luas = 0.92 x 2.16 x 1 = 1.9872 m²
Kusen type P2 (1 Unit)
Luas = 0.8 x 2.15 x 1 = 1.72 m²
Kusen type P3 (2 unit)
Luas = 3.05 x 3.6 x 2 = 21.96 m²
Kusen type J1 (6 Unit)

PERHITUNGAN VOLUME 35
Luas = 2.15 x 2.6 x 6 = 33.54 m²
Angin Angin (68 Unit)
Luas = 0.25 x 0.15 x 68 = 2.55 m2
Kolom (12 Unit)
Luas = 0.4 x 3.65 x 12 = 17.52 m2

Luas Lubang Total


= 1.9872 + 1.72 + 21.96 + 33.54
+ 2.55 + 17.52
= 79.28 m2

Luas Total Dinding


= 326.5 - 79.28
= 247.22 m²

2 Pasangan Batu Bata Lantai 2


Luas Pasangan Batu Bata
Luas Lt. 2 = 60 x 3.85 = 231 m²

Luas Lubang
Kusen type P1 (2 Unit)
Luas = 0.92 x 2.16 x 2 = 3.975 m²
Kusen type P2 (1 Unit)
Luas = 0.8 x 2.15 x 1 = 1.72 m²
Kusen type J1 (8 Unit)
Luas = 2.15 x 2.6 x 8 = 44.72 m²
Angin Angin (62 Unit) 159.78 m²
Luas = 0.25 x 0.15 x 62 = 2.325 m2
Kolom (12 Unit)
Luas = 0.4 x 3.85 x 12 = 18.48 m2

Luas Lubang Total


= 3.975 + 1.72 + 44.72 + 2.325
+ 18.48
= 71.22 m2

Luas Total Dinding


= 231- 71.22
= 159.78 m²

VII.Pekerjaan Plafond
No. Pekerjaan Perhitungan Volume
1. Plafond

Luas plafond lt.1 = 88 m²


Luas plafond lt.2 = 96 m² 184 m2
Total luas plafond = 184 m2

VIII. Pekerjaan Kusen


No. Pekerjaan Perhitungan Volume

PERHITUNGAN VOLUME 36
1. Kusen Pintu dan Jendela
a Pintu P1 (3 Unit)
1. Kusen Dimensi kayu = 12 cm x 6 cm
Panjang Kusen
= 3 (0.92 + 2 x 2.16) = 15.72 m
Volume kayu 0.113 m3
= 15.72 (0.12 x 0.06)
= 0.113 m3
 Bahan kayu jati

2. Pintu
Tebal = 3 cm
Luas Pintu
= 0.80 x 2.10 x 3 = 5.04 m2 0.1512 m3
Volume kayu
= 0.03 x 5.04 = 0.1512 m3
 Bahan kayu jati

b Pintu P2 (2 Unit)

Kebutuhan kusen dan pintu = 2 unit 2 buah


 Bahan PVC

c Pintu P3 (2 Unit)
1. Kusen Panjang Kusen
= 2 (2 x 3.05 + 3.6) = 19.4 m
Panjang Rel
= 2 x 3.6 = 7.2 m 1.33 m2
Luas Besi
= 0.05 (19.4 + 7.2)
= 1.33 m2
 Bahan besi
2. Pintu

Luas Pintu
= 3 x 3.5 x 2 = 21 m2 21 m2
 Bahan besi

d Jendela J1 (14 Unit)

PERHITUNGAN VOLUME 37
1. Kusen dan Bingkai Panjang Kusen
= 14 (2 x 2.15 + 3 x 2.6) = 169.4 m
 Bahan aluminium
Panjang Bingkai
= 14 ((1 x 4) + (2.5 x 3)) = 161 m 330.4 m
 Bahan aluminium
Panjang Total Aluminium
= 169.4 + 161 = 330.4 m
2. Jendela

Luas Jendela
= 14 ( 2 (1 x 2.5)) = 70 m2 70 m2
 Bahan kaca 5mm

e Engsel Pintu Jumlah Engsel Pintu = 10 unit 10 unit


f Engsel Jendela Jumlah Engsel Jendela = 56 unit 56 unit
g Kunci Tanam Jumlah Kunci Tanam = 3 unit 3 unit
h Kunci Kamar Mandi Jumlah Kunci Kamar Mandi = 2 unit 2 unit
IX. Pekerjaan Sanitasi
No. Pekerjaan Perhitungan Volume
1. Sanitasi
a Septictank Jumlah = 1 buah 1 ls
b Sumur Resapan Jumlah = 1 buah 1 ls
c Kloset Jongkok Jumlah = 2 buah 2 buah
d Kran Air Jumlah = 3 buah 3 buah
e Pompa Air Jumlah = 1 buah 1 ls
f Floor Drain Jumlah = 2 buah 2 buah
e Wastafel Stainless Steel Jumlah = 1 buah 1 buah
2. Pemipaan Air Kotor
a Pipa Diameter 20 cm Pipa Tanah Jumlah = 29 m 29 m
b Pipa Diameter 4” PVC Jumlah = 24 m 24 m
3. Pemipaan Air Bersih
a Pipa Diameter ¾” PVC Jumlah = 30 m 30 m
X. Pekerjaan Instalasi Listrik
No. Pekerjaan Perhitungan Volume
1. Instalasi Listrik
a Fitting Lampu Jumlah = 21 buah 21 buah
b Lampu
1. Lampu LED 6 watt Jumlah = 11 buah 11 buah
2. Lampu LED 12 watt Jumlah = 10 buah 10 buah
c Saklar
1. Saklar Tunggal Jumlah = 10 buah 10 buah
2. Saklar Ganda Jumlah = 1 buah 1 buah
d Stop Kontak Jumlah = 13 buah 13 buah
XI. Pekerjaan Penutup Lantai
No. Pekerjaan Perhitungan Volume
1. Pasangan Lantai Keramik Lantai 1
a Lantai (30 cm x 30 cm)

PERHITUNGAN VOLUME 38
Luas Keramik 30cm x 30cm (Tangga)
= 20 (0.9 x 0.5) + 1 x 2
= 11 m2 99 m²
Luas Keramik 30cm x 30cm (Lantai)
= 12 x 8 – 8
= 88 m2
Luas Total = 11 + 88 = 99 m2

b Kamar Mandi (20cm x 20cm)


Luas Keramik 20cm x 20cm 4 m²
= 2 x 2 = 4 m²

2. Pasangan Lantai Keramik Lantai 2


a Lantai (30 cm x 30 cm)
Luas Keramik 30cm x 30cm (Lantai)
= 12 x 8 – 2 x 4 – 8 80 m2
= 80 m2

b Kamar Mandi (20cm x 20cm)


Luas Keramik 20cm x 20cm 4 m²
= 2 x 2 = 4 m²

XII.Pekerjaan Penutup Dinding


No. Pekerjaan Perhitungan Volume
1. Pasangan Dinding Keramik Lantai 1
Panjang Dinding
= (2 (2 + 2) – 0.80
= 7.2 m 10.8 m2
Tinggi = 1.5 m
Luas Keramik 20cm x 20cm
= 7.2 x 1.5
= 10.8 m2

2. Pasangan Dinding Keramik Lantai 2


Panjang Dinding
= (2 (2 + 2) – 0.80
= 7.2 m 10.8 m2
Tinggi = 1.5 m
Luas Keramik 20cm x 20cm
= 7.2 x 1.5
= 10.8 m2

XIII. Pekerjaan Finishing


No. Pekerjaan Perhitungan Volume
1. Plesteran
Luas Total Dinding
= 247.22 + 159.78 814 m2
= 407 m²

Luas Plesteran
= 407 x 2

PERHITUNGAN VOLUME 39
= 814 m2

2. Acian
Luas Plesteran
= 814 m2
Panjang dinding tertutup plafond
= 140 m
Luas tertutup plafond
= 140 m x 0.1 m
= 14 m2 984 m2
Luas Acian Dinding
= 814 – 14
= 800 m2
Luas Acian Plafond
= 184 m2

Luas Total Acian


= 800 + 184
= 984 m2

3. Pengecatan
Luas Pengecatan Total
= Luas Total Acian 984 m2
= 984 m2

PERHITUNGAN VOLUME 40