Panjang = 20 m
Lebar = 12 m
Luas = Panjang x Lebar 240 m²
= 20 m x 12 m
= 240 m²
Kebutuhan Bahan
Papan nama kayu dengan ukuran
0,75 m x 0,4 m sejumlah 1 lembar
Kayu ukuran panjang 2 m
sejumlah 2 lembar 1 ls
Papan kayu horizontal, panjang 0,5
m sejumlah 1 lembar
3 Pemagaran
Keliling Lapangan = (22x2) + (16x2)
= 76 m
Kebutuhan Bahan
Seng Ukuran 2 m x 1 m, t = 2 mm
Seng di pasang dengan posisi tegak
Kebuthan seng = 76 : 1 m
= 76 lembar 76 m
Kayu 5/7 (panjang 4m)
Arah vertikal dipasang setiap
jarak 2 m
Kebutuhan = (76:2) = 38 buah
Arah horisontal dipasang 2 tingkat
Kebutuhan = (76:4) x 2 = 38 buah
PERHITUNGAN VOLUME 1
4 Pemasangan Bowplank Keliling bowplank
= 2(12+2) + 2(16+2)
= 64 m
Kebutuhan Bahan
Banyak Patok = 64:2 = 32 Unit
Ukuran tiang (5/7)
= 0.05m x 0.07m
Panjang = 1 m
Volume = ( 0.05 x 0.07 x 1 x 32 )
= 0.112 m³
Ukuran Papan (3/20) 64 m
= 0.03 m x 0.20 m
Panjang = 4m
Banyak Papan = 64:4 = 16 Lembar
Volume = (0.03 x 0.2 x 4 x 16)
= 0.384 m ³
Volume Total
= Volume Patok + Volume Papan
= 0.112 + 0.384
= 0.496 m³
PERHITUNGAN VOLUME 2
b Galian Tanah Pondasi Batu Kali (P1)
Panjang Galian = 74 m
Lebar Galian = 1.2 m
Tinggi Galian = 1.15 m
Volume Galian = 74x1.2x1.15 102.12 m³
= 102.12 m³
2. Urugan Pasir
a Urugan Pasir Dasar Pondasi Foot
Plate (F1) Volume Urugan Pasir 1 Pondasi (F1)
= 1.702 x 0.1 = 0.289 m³
Volume 12 Pondasi (F1) = 0.289 x 12 3.468 m³
= 3.468 m³
3. Urugan Tanah
a Urugan Tanah Pondasi Foot Plat (F1)
Volume Galian Tanah
= 7.369 m³
Volume Urugan Pasir
= 1.702 x 0.1 = 0.289 m³
Volume Lantai Kerja
= 1.72 x 0.15 = 0.4335 m³
Volume Pondasi FootPlat 66.542 m3
= (1.5x1.5x0.25) + (0.42x0.25)
+4(1/2x0.25x0.55x0.40)
+4(1/3x0.552x0.25) + (0.4x0.4x1.8)
= 1.10133 m³
Volume Urugan 12 FootPlat
= 12(7.369-0.289-0.4335-1.10133)
= 66.542 m3
PERHITUNGAN VOLUME 3
b Urugan Tanah Pondasi Batu Kali
(P1)
Luas Urugan Tanah P1
= 2((0.10+0.44)/2x0.9) = 0.486 m2
Volume Batu Kali P1 35.964 m³
= 0.486 x 74
= 35.964 m³
b Penulangan
Jumlah Footplat = 30 buah
Tulangan Pedestal
Pedestal 30x30/K1
PERHITUNGAN VOLUME 4
o Tulangan longitudinal = 8D25
D25, berat = 3.853 kg/m
Panjang tulangan longitudinal
= h + 40D
= 2.4+(40x0.016) 2835 kg
= 3.04 m
Berat tulangan longitudinal
= 3.04 x 8 x 3.853
= 93.705 kg
o Begel Ø10-100
Ø10-100, berat = 0.617 kg/m
Panjang Begel :
= 2(b+h+6D)
= 2[(0.4-2x0.04)
+ (0.4-2x0.04)+(6x0.010)]
= 1.4 m
Jumlah sengkang = (2.4/0.10) + 1
= 25 buah
Panjang total begel = 1.4x25 = 35 m
Berat total begel = 35 x 0.617
= 21.595 kg
Tulangan Footplate
Jarak antara tulangan = 0.15 m
Jumlah Footplat F1 = 30 buah
o Tulangan Atas
Jumlah Tulangan Atas (Ø12-100)
= ((1./0.15+1) x 2) = 22 buah
Panjang Tulangan
= ((1.5-(2x0.05))
+(2x(0.25-(2x0.05)))
+(2x6x0.016))x22
= 41.624 m
o Tulangan Bawah
Jumlah Tulangan Bawah (Ø16-150)
= ((1.5/0.15+1) x 2) = 22 buah
Panjang Tulangan
= ((1.5-(2x0.05))
+(2x6x0.016))x22
= 35.024 m
PERHITUNGAN VOLUME 5
c Bekisting
Bekisting 1
= 4 (1.50 x 0.25) = 1.5 m²
Bekisting 2
= 4 x ((0.4+1.5)/2 x (0.552+0.252)1/2)
= 2.2957 m² 82.029 m²
Bekisting 3
= 4 (1.90 x 0.40) = 3.04 m²
Luas total bekisting 12 Footplat (F1)
= 12 ( 1.5 + 2.2957 + 3.04 )
= 82.0293 m²
d Pengecoran
Volume 1
= 1.5x1.5x0.25
= 0.5625 m³
Volume 2
= (0.42x0.25)+4(1/2x0.25x0.55x0.40)
+4(1/3x0.552x0.25)
= 0.25083 m³
Volume 3
= 0.4x0.4x1.53
= 0.304 m³
Volume total 1 Footplat
= 0.5625 + 0.25083 + 0.304 13.046 m³
= 1.11733 m³
Volume 12 Foot Plat (F1)
= 1.11733 x 12
= 13.41 m³
Vol Tulangan
= Berat Tulangan : Berat jenis baja
= 2835 kg : 7850 kg/m³
= 0.3611 m³
Volume Pengecoran
= Vol Total - Vol Tulangan
= 13.41 - 0.3611
= 13.0469 m³
PERHITUNGAN VOLUME 6
Luas Aanstamping Batu Kali (P2)
= 0.7 x 0.15 = 0.105 m2 5.04 m3
Volume Aanstamping Batu Kali (P2)
= 0.105 x 48 = 5.04 m3
PERHITUNGAN VOLUME 7
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 681 x 1.1 = 749.1 m
Berat Total Begel
= 749.1 x 0.617 = 462.1947 kg
PERHITUNGAN VOLUME 8
54.4 m²
Luas Bekisting
= 2 x 68 x 0.4
= 54.4 m²
Volume Tulangan
= Berat tulangan : Berat jenis baja 6.441 m³
= 2820.231 kg : 7850 kg/m³
= 0.359 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 1.554 m³
= 517.534 kg: 7850 kg/m³
= 0.06593 m³
2. Kolom Lantai 1
a.1 Penulangan (K1)
Tulangan pokok diteruskan L = 52.80 m
dari FootPlat, berakhir di balok Jumlah = 12 batang @ 4.40 m
Tulangan Pokok 8D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 9
= 518.4 m kg
Berat Total Tulangan Pokok
= 518.4 x 3.853 = 1997.395 kg
PERHITUNGAN VOLUME 10
= 89 x 0.6 = 53.4 m
Berat Total Begel
= 53.4 x 0.617 = 32.95 kg
PERHITUNGAN VOLUME 11
b.2 Bekisting (K2 di Bangunan Utama)
L = 17.6 m
B = 0.15 m
H = 0.15 m
10.56 m²
Luas Bekisting
= 4 x 17.6 x 0.15
= 10.56 m²
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 2441.29 kg: 7850 kg/m³ 8.137 m³
= 0.31099 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 0.3724 m³
= 185.26 kg : 7850 kg/m³
= 0.0236 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 1.464 m³
= 696.693 kg : 7850 kg/m³
= 0.08875 m³
PERHITUNGAN VOLUME 12
Volume pengecoran = 1.553–0.08875
= 1.464 m³
3. Balok Lantai
a.1 Penulangan (B1)
L =6m
Jumlah = 3 batang @ 2.00 m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 13
= 187 m
Berat Total Tulangan Pokok
= 187 x 3.853 = 720.511 kg
Jumlah Begel (Ø10-50)
= (34/0.05) + 1
= 681 buah
Panjang Begel
= 2 ( b + h + 6Ø)
= 2 [(0.4-(2x0.04))+ (0.25-(2x0.04))
+ (6x0.01)]
= 1.1 m
Panjang Total begel
= 681 x 1.1 = 749.1 m
Berat Total Begel
= 749.1 x 0.617 = 462.195 kg
PERHITUNGAN VOLUME 14
= 786.012+231.437 = 1017.45 kg
L =6m
B = 0.15 m
H = 0.18 m 3.06 m²
Luas Bekisting
= 6 (2 x 0.18 + 0.15)
= 3.06 m²
PERHITUNGAN VOLUME 15
B = 0.25 m
H = 0.28 m
69.26 m²
Luas Bekisting
= 82(2x0.28+0.25)+14(0.25x0.4)
+12x0.12
= 69.26 m²
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 65.415kg: 7850 kg/m³ 0.2617 m³
= 0.008333 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= (1182.706 + 1017.45 + 594.601) 7.844 m³
: 7850 kg/m³
= 0.356 m³
4. Plat Lantai
a.1 Penulangan (Tipe 4x4)
Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 5
Arah X
Panjang Tulangan 2094.61
= 4 + 2 x 6 x 0.01 = 4.12 m kg
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah X
= 4.12 x 41 x 0.62 x 2 = 209.461 kg
PERHITUNGAN VOLUME 16
Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah Y
= 4.12 x 41 x 0.62 x 2 = 209.461 kg
Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 2.12 x 21 x 0.62 x 2 = 55.205 kg
Arah Y 220.82 kg
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 2.12 x 21 x 0.62 x 2 = 55.205 kg
Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan 1131.378
= 4 / 0.1 + 1 = 41 kg
Berat Tulangan Arah X
= 1.12 x 41 x 0.62 x 2 = 56.941 kg
Arah Y
PERHITUNGAN VOLUME 17
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 4.12 x 11 x 0.62 x 2 = 56.197 kg
PERHITUNGAN VOLUME 18
b.3 Bekisting
(Tipe 1x4)
Luas Total Bekisting
= 10 (4 x 1) + 10 (4 x 0.12) 44.8 m2
= 44.8 m2
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 2094.61 kg : 7850 kg/m³ 9.333 m³
= 0.2668 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 220.82 kg : 7850 kg/m³ 0.9319 m³
= 0.02813 m³
PERHITUNGAN VOLUME 19
Volume Tulangan
= Berat tulangan : Berat jenis baja 4.656 m³
= 1131.378 kg : 7850 kg/m³
= 0.144 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 122.2144 kg : 7850 kg/m³ 0.4644 m³
= 0.01557 m³
5. Tangga
a.1 Penulangan (2 Kolom K2)
L =4m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 20
= 12.6 x 0.617 = 7.774 kg
Arah X
Panjang Tulangan 58.082 kg
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 1.12 x 21 x 0.62 x 2 = 29.165 kg
Arah Y
PERHITUNGAN VOLUME 21
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 2.12 x 11 x 0.62 x 2 = 28.917 kg
Arah X
Panjang Tulangan
= 0.9 + 2 x 6 x 0.01 = 1.02 m
Jumlah Tulangan
= 3.6 / 0.1 + 1 = 37 185.852
Berat Tulangan Arah X kg
= 1.02 x 37 x 0.62 x 2 = 46.798 kg
Arah Y
Panjang Tulangan
= 3.6 + 2 x 6 x 0.01 = 3.72 m
Jumlah Tulangan
= 0.9 / 0.1 + 1 = 10
Berat Tulangan Arah Y
= 3.72 x 10 x 0.62 x 2 = 46.128 kg
Arah X
Panjang Tulangan 87.041 kg
= 0.3 + 0.2 + 2 x 6 x 0.01 = 0.62 m
Jumlah Tulangan
= 0.9 / 0.2 + 1 = 6
Berat Tulangan Arah X
= 0.62 x 6 x 0.62 = 2.306 kg
Arah Y
Panjang Tulangan
PERHITUNGAN VOLUME 22
= 0.9 + 2 x 6 x 0.01 = 1.02 m
Jumlah Tulangan
= 0.5 / 0.2 + 1 = 4
Berat Tulangan Arah Y
= 1.02 x 4 x 0.62 = 2.53 kg
Luas Bekisting
= 4 x 4 x 0.15 2.4 m²
= 2.4 m²
Luas Bekisting
= 6 (2 x 0.18 + 0.15) 3.06 m²
= 3.06 m²
b.4 Bekisting
(Plat Tangga
0.9 x 3.6) Luas Total Bekisting
= 2 (0.9 x 3.6) + 2 (2 x 3.6 x 0.12)
= 8.208 m2 8.208 m2
b.5 Bekisting
(Anak Tangga) Luas Total Bekisting
= 18 (0.2 x 0.9) + 36 (0.2 x 0.3 / 2) 4.32 m2
= 4.32 m2
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 43.01 kg : 7850 kg/m³ 0.0845 m³
= 0.0055 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 0.261 m³
= 68.825 kg : 7850 kg/m³
= 0.008768 m³
c.4 Pengecoran (Plat Tangga 0.9 x 3.6) Volume Total = 2 (0.9 x 3.6 x 0.12)
= 0.778 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 185.852 kg : 7850 kg/m³ 0.7543 m³
= 0.02368 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 0.475 m³
= 87.041 kg : 7850 kg/m³
= 0.0111 m³
PERHITUNGAN VOLUME 24
Volume pengecoran = 0.486 – 0.0111
= 0.475 m³
6. Kolom Lantai 2
a.1 Penulangan (K1)
Tulangan pokok dimulai dari L = 50.40 m
balok, berakhir di balok atap Jumlah = 3 batang @ 4.00 m
3 batang @ 4.13 m
3 batang @ 4.27 m
3 batang @ 4.40 m
Panjang bentang ± 4.20 m
Tulangan Pokok 8D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 25
pokok dimulai dari balok, 3 batang di lantai 2 @ 4.065 m
berakhir di balok atap. 1 batang di lantai 2 @ 4.00 m
Panjang bentang
= (3x4.065 + 1x4.00)/4
± 4.05 m
Tulangan Pokok 8D12
Berat = 0.888 kg/m
Begel Ø10-200
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 26
b.2 Bekisting (K2 di Bangunan Utama)
L = 16.195 m
B = 0.15 m
H = 0.15 m
9.717 m²
Luas Bekisting
= 4 x 16.195 x 0.15
= 9.717 m²
Volume Tulangan
= Berat tulangan : Berat jenis baja 7.7179 m3
= 2717.06 kg : 7850 kg/m³
= 0.3461 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 0.338 m³
= 172.72 kg : 7850 kg/m³
= 0.022 m³
V. Pekerjaan Atap
No. Pekerjaan Perhitungan Volume
1. Balok Atap
a.1 Penulangan (B1)
L =6m
Jumlah = 3 batang @ 2.00 m
Tulangan Pokok 4D12
Berat = 0.888 kg/m
Begel Ø10-100
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 27
= 35.52 m
Berat Total Tulangan Pokok
= 35.52 x 0.888 = 31.5418 kg
PERHITUNGAN VOLUME 28
Balok (B2) Tumpuan
= 720.511 +462.195 = 1182.706 kg
a.3 Penulangan (B2 Lapangan) L = 34 m
Jumlah = 34 bagian; 1 bagian tiap
balok B2 @ 2.00 m
Tulangan Pokok 5D25
Berat = 3.853 kg/m
Begel Ø10-100
Berat = 0.617 kg/m
PERHITUNGAN VOLUME 29
Berat Total Tulangan Pokok
= 105 x 3.853 = 404.565 kg
L =6m
B = 0.15 m
H = 0.18 m 3.06 m²
Luas Bekisting
= 6 (2 x 0.18 + 0.15)
= 3.06 m²
69.26 m²
Luas Bekisting
= 82(2x0.28+0.25)+14(0.25x0.4)
+12x0.12
= 69.26 m²
Volume Tulangan
= Berat tulangan : Berat jenis baja
= (1182.706 + 1017.45 + 594.601) 7.844 m³
: 7850 kg/m³
PERHITUNGAN VOLUME 30
= 0.356 m³
2. Plat Atap
a.1 Penulangan (Tipe 4x4)
Ukuran tulangan = D10 – 100
Berat tulangan = 0.62 kg/m
Jumlah Plat = 5
Arah X
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41 2094.61
Berat Tulangan Arah X kg
= 4.12 x 41 x 0.62 x 2 = 209.461 kg
Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah Y
= 4.12 x 41 x 0.62 x 2 = 209.461 kg
Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m 220.82 kg
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah X
= 2.12 x 21 x 0.62 x 2 = 55.205 kg
Arah Y
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
PERHITUNGAN VOLUME 31
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 2.12 x 21 x 0.62 x 2 = 55.205 kg
Arah X
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41
Berat Tulangan Arah X 1131.378
= 1.12 x 41 x 0.62 x 2 = 56.941 kg kg
Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
= 4.12 x 11 x 0.62 x 2 = 56.197 kg
Arah Y
Panjang Tulangan
= 1 + 2 x 6 x 0.01 = 1.12 m
Jumlah Tulangan
= 1 / 0.1 + 1 = 11
Berat Tulangan Arah Y
PERHITUNGAN VOLUME 32
= 1.12 x 11 x 0.62 x 2 = 15.277 kg
Arah X
Panjang Tulangan
= 2 + 2 x 6 x 0.01 = 2.12 m
Jumlah Tulangan
= 4 / 0.1 + 1 = 41 215.065
Berat Tulangan Arah X kg
= 2.12 x 41 x 0.62 x 2 = 107.78 kg
Arah Y
Panjang Tulangan
= 4 + 2 x 6 x 0.01 = 4.12 m
Jumlah Tulangan
= 2 / 0.1 + 1 = 21
Berat Tulangan Arah Y
= 4.12 x 21 x 0.62 x 2 = 107.285 kg
PERHITUNGAN VOLUME 33
b.3 Bekisting
(Tipe 1x4)
Luas Total Bekisting
= 10 (4 x 1) + 10 (4 x 0.12) 44.8 m2
= 44.8 m2
b.5 Bekisting
(Tipe 2x4)
Luas Total Bekisting
= 4 x 2 = 8 m2 8 m2
Volume Tulangan
= Berat tulangan : Berat jenis baja 9.333 m³
= 2094.61 kg : 7850 kg/m³
= 0.2668 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 220.82 kg : 7850 kg/m³ 0.9319 m³
= 0.02813 m³
PERHITUNGAN VOLUME 34
= 4.8 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 4.656 m³
= 1131.378 kg : 7850 kg/m³
= 0.144 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja
= 122.2144 kg : 7850 kg/m³ 0.4644 m³
= 0.01557 m³
Volume Tulangan
= Berat tulangan : Berat jenis baja 0.933 m³
= 215.065 kg : 7850 kg/m³
= 0.0274 m³
VI.
Pekerjaan Dinding
No. Pekerjaan Perhitungan Volume
1 Pasangan Batu Bata Lantai 1
Luas Pasangan Batu Bata
Luas Lt. 1 = 50 x 3.65 = 182.5 m²
Pagar = 48 x 3 = 144 m²
Luas Total = 182.5 + 144 = 326.5 m2
247.22 m²
Luas Lubang
Kusen type P1 (1 Unit)
Luas = 0.92 x 2.16 x 1 = 1.9872 m²
Kusen type P2 (1 Unit)
Luas = 0.8 x 2.15 x 1 = 1.72 m²
Kusen type P3 (2 unit)
Luas = 3.05 x 3.6 x 2 = 21.96 m²
Kusen type J1 (6 Unit)
PERHITUNGAN VOLUME 35
Luas = 2.15 x 2.6 x 6 = 33.54 m²
Angin Angin (68 Unit)
Luas = 0.25 x 0.15 x 68 = 2.55 m2
Kolom (12 Unit)
Luas = 0.4 x 3.65 x 12 = 17.52 m2
Luas Lubang
Kusen type P1 (2 Unit)
Luas = 0.92 x 2.16 x 2 = 3.975 m²
Kusen type P2 (1 Unit)
Luas = 0.8 x 2.15 x 1 = 1.72 m²
Kusen type J1 (8 Unit)
Luas = 2.15 x 2.6 x 8 = 44.72 m²
Angin Angin (62 Unit) 159.78 m²
Luas = 0.25 x 0.15 x 62 = 2.325 m2
Kolom (12 Unit)
Luas = 0.4 x 3.85 x 12 = 18.48 m2
VII.Pekerjaan Plafond
No. Pekerjaan Perhitungan Volume
1. Plafond
PERHITUNGAN VOLUME 36
1. Kusen Pintu dan Jendela
a Pintu P1 (3 Unit)
1. Kusen Dimensi kayu = 12 cm x 6 cm
Panjang Kusen
= 3 (0.92 + 2 x 2.16) = 15.72 m
Volume kayu 0.113 m3
= 15.72 (0.12 x 0.06)
= 0.113 m3
Bahan kayu jati
2. Pintu
Tebal = 3 cm
Luas Pintu
= 0.80 x 2.10 x 3 = 5.04 m2 0.1512 m3
Volume kayu
= 0.03 x 5.04 = 0.1512 m3
Bahan kayu jati
b Pintu P2 (2 Unit)
c Pintu P3 (2 Unit)
1. Kusen Panjang Kusen
= 2 (2 x 3.05 + 3.6) = 19.4 m
Panjang Rel
= 2 x 3.6 = 7.2 m 1.33 m2
Luas Besi
= 0.05 (19.4 + 7.2)
= 1.33 m2
Bahan besi
2. Pintu
Luas Pintu
= 3 x 3.5 x 2 = 21 m2 21 m2
Bahan besi
PERHITUNGAN VOLUME 37
1. Kusen dan Bingkai Panjang Kusen
= 14 (2 x 2.15 + 3 x 2.6) = 169.4 m
Bahan aluminium
Panjang Bingkai
= 14 ((1 x 4) + (2.5 x 3)) = 161 m 330.4 m
Bahan aluminium
Panjang Total Aluminium
= 169.4 + 161 = 330.4 m
2. Jendela
Luas Jendela
= 14 ( 2 (1 x 2.5)) = 70 m2 70 m2
Bahan kaca 5mm
PERHITUNGAN VOLUME 38
Luas Keramik 30cm x 30cm (Tangga)
= 20 (0.9 x 0.5) + 1 x 2
= 11 m2 99 m²
Luas Keramik 30cm x 30cm (Lantai)
= 12 x 8 – 8
= 88 m2
Luas Total = 11 + 88 = 99 m2
Luas Plesteran
= 407 x 2
PERHITUNGAN VOLUME 39
= 814 m2
2. Acian
Luas Plesteran
= 814 m2
Panjang dinding tertutup plafond
= 140 m
Luas tertutup plafond
= 140 m x 0.1 m
= 14 m2 984 m2
Luas Acian Dinding
= 814 – 14
= 800 m2
Luas Acian Plafond
= 184 m2
3. Pengecatan
Luas Pengecatan Total
= Luas Total Acian 984 m2
= 984 m2
PERHITUNGAN VOLUME 40