TIME SCHEDULE/RENCANA

KEGIATAN : P3MD
PEKERJAAN : JALAN RABAT BETON LABUR ASPAL
LOKASI : KECAMATAN TARERAN DESA RUMOONG ATAS
TAHUN ANGGARAN : 2018

BOBOT BULAN KE I
NO URAIAN PEKERJAAN (%) 1 2

I PEKERJAAN PEMBERSIHAN 33.27% 16.63% 16.63%


33.27%
II PEKERJAAN URUGAN SIRTU 7.49% 7.49%

III PEKERJAAN PASANG BEKISTING COR JALAN 56.58% 14.15%

IV PEKERJAAN COR BETON MUTU K175 Manual 0.00%

V PEKERJAAN LABURAN ASPAL 0.00%

VI PEKERJAAN PRASASTI 2.67%

Jumlah 100%
Rencana 16.63% 38.27%
Rencana Kumulatif 0 16.63% 54.90%

Realisasi 0.00% 33.27%


Realisasi Kumulatif 0 0.00% 33.27%
Deviasi 16.63% 21.63%

Menegtahui,
Hukum Tua

......................
LE/RENCANA KERJA
PELAKSANA
BULAN KE-I
TANGGAL ...

BULAN KE I BULAN KE II
KETERANGAN
3 4 1 2 3 4

JANGKA WAKTU
PELAKSANAAN
60 HARI KALENDER
14.15% 14.15% 14.15%

0.00% 0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00%

2.67%

14.15% 14.15% 14.15% 0.00% 0.00% 2.67%


69.04% 83.19% 97.33% 97.33% 97.33% 100.00%
RENCANA
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% REALISASI
33.27% 33.27% 33.27% 33.27% 33.27% 33.27%
35.78% 49.92% 64.07% 64.07% 64.07% 66.73%

dibuat Diperiksa,
Kader Teknik Desa PDTI

............................... .................
PEMERINTAH DESA PINAMORONGAN
KECAMATAN TARERAN
KABUPATEN MINAHASA SELATAN

RAB OPS KEGIATAN


1 Bidang : PEMBANGUNAN DESA
2 Kegiatan : JALAN AKSES LAHAN/RABAT BETON ASPAL
Rincian Pendanaan : Rp 10,835,000

NO URAIAN VOLUME

~ BELANJA BARANG DAN JASA


I HONOR PELAKSANA KEGIATAN
1 KETUA 1 x 1
2 SEKRETARIS 1 x 1
3 ANGGOTA 1 x 1
II BIAYA PENYUSUNAN DESAIN DAN RAB
1 BIAYA PENYUSUNAN 1 x 1
III TRANSPORTASI SURVEY & SERTIFIKASI
1 TRANSPORTASI SURVEY LOKASI KEGIATAN 7 x 1
2 TRANSPORTASI SURVEY HARGA SATUAN BAHAN & ALAT 7 x 1
3 TRANSPORTASI SERTIFIKASI 5 x 1
4 TRANSPORTASI MONITORING PELAKSANA KEGIATAN 3 x 3
IV BIAYA KONSUMSI RAPAT
1 SNACK RAPAT PRA PELAKSANAAN 20 x 1
2 MAKAN SIANG RAPAT PRA PELAKSANAAN 20 x 1
3 SNACK RAPAT PERTANGGUNG JAWABAN PK 20 x 1
4 MAKAN SIANG RAPAT PERTANGGUNG JAWABAN PK 20 x 1

~ BELANJA MODAL
I ATK TP2K
1 BUKU BIMBINGAN PELAKSANA KEGIATAN 1
2 BUKU KAS PELAKSANA KEGIATAN 1
3 BUKU MATERIAL 1
4 KERTAS HVS 2
5 PULPEN 2
II PENGGANDAAN DOKUMEN DLL
1 CETAK DOKUMEN PBJ DESA 200
2 CETAK DOKUMEN RKS (DESAIN DAN RAB) 220
3 FOTO COPY DOKUMEN PBJ DESA 200
4 FOTO COPY DOKUMEN RKS (DESAIN DAN RAB) 220
5 JILID DOKUMEN 14 x 2
III DOKUMENTASI & INFORMASI
1 CETAK BALIHO APBDES 1
2

TOTA

Terbilang : TUJUH JUTA DELAPAN RATUS EMPAT PULUH DUA RIBU RUPIAH

Diverifikasi oleh :
Sekretaris Desa/PPKD

.......................

Disetujui oleh :
Kepala Desa/PKPKD

.......................
NAMORONGAN
ERAN
SELATAN

GIATAN

HARGA
SATUAN

SATUAN TOTAL BIAYA (Rp)


(Rp)

KEG 1,000,000 1,000,000


KEG 750,000 750,000
KEG 500,000 500,000

KEG 2,167,000 2,167,000

ORG/KEG 100,000 700,000


ORG/KEG 100,000 700,000
ORG/KEG 100,000 500,000
ORG/KEG 100,000 900,000

ORG/KEG 15,000 300,000


ORG/KEG 40,000 800,000
ORG/KEG 15,000 300,000
ORG/KEG 40,000 800,000

(Sub Total I) Rp 9,417,000


BH 25,000 25,000
BH 25,000 25,000
BH 25,000 25,000
RIM 50,000 100,000
BH 13,500 27,000

LBR 1,000 200,000


LBR 1,000 220,000
LBR 300 60,000
LBR 300 66,000
JLD/DOKM 15,000 420,000

LBR 250,000 250,000

(Sub Total II) Rp 1,418,000


TOTAL JUMLAH Rp Rp 10,835,000 - 0

DUA RIBU RUPIAH

Dibuat,
Pelaksana Kegiatan

.......................
XIV. FORMAT REKAPITULASI RENCANA BIAYA

REKAPITULASI R
T
Desa : PINAMORONGAN
Kecamatan : Tareran

Bidang/ Jenis Kegiatan


No
Bidang Jenis Kegiatan

a b c
Penyelenggaraan a.
1 Pemerintahan b.
Desa c.
Jumlah Per Bid
a. JALAN AKSES LAHAN/RABAT BETON ASPAL
OPERASIONAL KEGIATAN
Pembangunan
2 b. DRAINASE
Desa
c. TEMBOK PENAHAN TANAH
d. WISATA WATU LEYLEY
Jumlah Per Bid
a.
Pembinaan
3 b.
Kemasyarakatan
c.
Jumlah Per Bid
a.
Pemberdayaan b.
4
Masyarakat c.
d.
Jumlah Per Bid

JUMLAH T

Menyetujui
Hukum Tua,

(..........................)
JALAN AKSES LAHAN/RABAT BETON ASPAL
OPERASIONAL KEGIATAN
DRAINASE
TEMBOK PENAHAN TANAH
WISATA WATU LEYLEY
REKAPITULASI RENCANA ANGGARAN BIAYA
TAHUN :2019
Kabupaten : Minahasa Selatan
Provinsi : Sulawesi utara

Biaya dan Sumber Pembiayaan


Lokasi Volume
Dana Desa
Jumlah (Rp) ADD (Rp)
(Rp)

d e f g h

281,720,700
Jumlah Per Bidang 1 -
NIT / (400X 3M) (30 X 3M) 270,885,700 270,885,700
10,835,000 10,835,000
1 UNIT / (82 x 0.8 x 0.8 M) 110,866,500 110,866,500
3 UNIT/ 76M x 1.25M 43,559,500 43,559,500
224,104,250 224,104,250
Jumlah Per Bidang 2 660,250,950

Jumlah Per Bidang 3 -


-

Jumlah Per Bidang 4 -

JUMLAH TOTAL 660,250,950


KONTROL
PAGU 795,970,000
SISA 135,719,050

281,720,700
270,885,700
10,835,000
110,866,500
43,559,500 52,000,000 (8,440,500)
224,104,250

pemb 668,691,450
pemberdayaan 152,278,550
820,970,000
(25,000,000) 27,000,000 rab pembersihan dan galian tanah salur
asa Selatan
esi utara

an Sumber Pembiayaan

Pemerintah
Swadaya (Rp) Pihak Ketiga
Pusat/ Daerah

i j k

Desa…..,tanggal….,….,……..
Pelaksana Kegiatan ………………………..
Ketua

(...............................................)
mbersihan dan galian tanah saluran
PEMERINTAH DESA PINAMORONGAN
KECAMATAN TARERAN
KABUPATEN MINAHASA SELATAN

RENCANA ANGGARAN BIAYA / RAB


1 Bidang : 2.2 PELAKSANAAN PEMBANGUNAN DESA
2 Kegiatan : 2.2.1 JALAN AKSES LAHAN/RABAT BETON ASPAL
3 Waktu Pelaksanaan : 1 bulan
4 Volume : 2 UNIT / (400X 3M) (30 X 3M) 645
Rincian Pendanaan : Rp 270,885,700

HARGA

SATUAN
Jumlah (Rp)
NO URAIAN VOLUME SATUAN
(Rp) DD

~ BELANJA BARANG DAN JASA


I UPAH
1 Pekerja 540.00 HOK 120,000 64,800,000 81,480,000 679.00
2 Tukang 65.00 HOK 150,000 9,750,000 17,100,000 114.00
3 Kepala Tukang 7.00 HOK 160,000 1,120,000 1,920,000 12.00
4 Mandor 65.00 HOK 100,000 6,500,000 20,400,000 204.00
PKT
(Sub Total II) 82,170,000 29.17% 120,900,000
~ BELANJA MODAL
BAHAN & ALAT
1 Kaso 5/7 cm ky kls III 1.00 M³ 1,672,500 1,672,500 1,672,500 2,508,750 2 Kaso 5/7 cm ky kls III
2 Papan 3/20 ky kls III 2.00 M³ 1,672,500 3,345,000 1,672,500 5,017,500 3 Papan 3/20 ky kls III
3 Paku 5 cm dan 7 cm 13.00 KG 22,500 292,500 22,500 517,500 23 Paku 5 cm dan 7 cm
4 Semen @50Kg 868.00 Zak 70,500 61,194,000 70,500 69,160,500 981 Semen @50Kg
5 Pasir Beton 113.00 M³ 211,500 23,899,500 212,000 26,231,500 124 Pasir Beton
6 Batu belah 2/3 121.00 M³ 335,000 40,535,000 335,000 44,890,000 134 Batu belah 2/3
7 Sirtu 142.00 M³ 168,000 23,856,000 23,856,000 142.00 Sirtu
8 Air 33,282.00 L 100 3,328,200 100 3,692,200 36,922.00 air
9 Aspal 1,449.00 KG 15,000 21,735,000 21,735,000 1,449.00 Aspal
10 Kayu Bakar 5.00 M³ 223,000 1,115,000 1,115,000 5.00 Kayu Bakar
11 Solar 400.00 Ltr 7,000 2,800,000 2,800,000 400.00 Solar
12 Gerobak Artcho 4.00 bh 613,500 2,454,000 557,500 892,000 4 Pasir Halus
13 Sekop 4.00 bh 72,500 290,000 3,569,000 6.00 Gerobak Artcho
14 Ember Cor 12.00 bh 17,000 204,000 17,000 290,000.00 4.00 Sekop
15 Terpal 3.00 bh 335,000 1,005,000 335,000 408,000 24.00 Ember Cor
16 Benang nylon 4.00 roll 22,500 90,000 22,500 1,675,000 5.00 Terpal
17 Papan proyek 1.00 bh 150,000 150,000 150,000 135,000 6.00 Benang nylon
18 Prasasti 1.00 bh 750,000 750,000 750,000 18,000 3 Sarung tangan
300,000 2.00 Papan proyek
(Sub Total II) 188,715,700 1,500,000 2.00 Prasasti

Total Pekerjaan Rabat Beton Aspal Rp 270,885,700


Operasional Kegiatan Rp 10,835,000
Total Pekerjaan + Operasional Rp 281,720,700
210,310,950
Kabupaten : MINAHASA SELATAN
Kecamatan : TARERAN Take Off Sheet (TOS)
Desa : PINAMORONGAN
URAIAN PEKERJAAN & SKETSA PEK VOLUME PEKERJAAN
1.PEKERJAAN PEMBERSIHAN L= 400 x 3 = 1200 M²
30 x 3 = 90 M²
0 x 3 = 0 M²
0.00 M²
2. PEKERJAAN URUGAN SIRTU V= 334 x 3 x 0.1 = 100.20 M³

Jalan Baru VsirtuDasar= 30 x 3 x 0.1 = 9.00 M³


VsirtuPenutup= 30 x 3 x 0.1 = 9.00 M³
118.20 M³

3.PEKERJAAN PASANG BEKISTING COR JALAN L= 430 x 0.2 x 1 = 86.00 M²

775.00
930.00

4.PEKERJAAN COR BETON MUTU K125 Manual BADAN JALAN


V= 400 x 3 x 0.12 = 144.00 M³
30 x 3 x 0.12 = 10.80 M³
0 x 0 x 0 = 0.00 M³
154.80 M³
Kabupaten : MINAHASA SELATAN
Kecamatan : TARERAN Take Off Sheet (TOS)
Desa : PINAMORONGAN
URAIAN PEKERJAAN & SKETSA PEK VOLUME PEKERJAAN

20.20

5.PEKERJAAN LABURAN ASPAL L1= 400 x 3 = 1200 M²


30 x 3 = 90 M²
0 x 0 = 0 M²
1290.0 M²

6.PEKERJAAN GALIAN TANAH V= 430 x 0.3 x 0.3 x 2 = 77.40 M³

7.PEKERJAAN PASANGAN BATU MORTAR BADAN PONDASI 1:4 V= 11 x 0.25 + 0.5 x 1 = 4.13 M³
2
Kabupaten : MINAHASA SELATAN
Kecamatan : TARERAN Take Off Sheet (TOS)
Desa : PINAMORONGAN
URAIAN PEKERJAAN & SKETSA PEK VOLUME PEKERJAAN

8.PEKERJAAN PASANG BATU DASAR/TELASAH V= 30 x 3 x 0.2 = 18.00 M³

Tanggal Survei : 21 januari 2019 Keterangan:


Jenis Prasarana : JALAN AKSES LAHAN/RABAT BETON ASPAL
Lokasi : JALAN KEBUN MAKESOT
Volume/Dimensi : 2 UNIT / (400X 3M) (30 X 3M)
ANALISA/ KOEFISIEN (Permen PUPR no.28 thn 2016)
T.01.a 1 m2 pembersihan dan striping/kosrekan
Pekerja = 0.06 x 0.00 = - HOK
Mandor = 0.006 x 0.00 = - HOK

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


Pekerja = 0.250 x 118.20 = 29.55 HOK
Mandor = 0.025 x 118.20 = 2.96 HOK
Sirtu = 1.200 x 118.20 = 141.84 M³

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi


Pekerja = 0.5200 x 86.00 = 44.72 HOK
Tukang = 0.2600 x 86.00 = 22.36 HOK
Kepala Tukang = 0.0260 x 86.00 = 2.24 HOK
Mandor = 0.0260 x 86.00 = 2.24 HOK
Kaso 5/7 cm ky kls III = 0.0160 x 86.00 = 1.38 M³
Papan 3/20 ky kls III = 0.0280 x 86.00 = 2.41 M³
Paku 5 cm dan 7 cm = 0.1500 x 86.00 = 12.90 KG

B.03 1 m³ Beton mutu, f’c = 9,8 MPa (K125), slump (12±2) cm, w/c = 0,78
B.03.a Manual
Pekerja = 1.650 x 154.80 = 255.42 HOK
Tukang = 0.275 x 154.80 = 42.57 HOK
Kepala Tukang = 0.028 x 154.80 = 4.33 HOK
Jenis Prasarana : JALAN AKSES LAHAN/RABAT BETON ASPAL
Lokasi : JALAN KEBUN MAKESOT
Volume/Dimensi : 2 UNIT / (400X 3M) (30 X 3M)
ANALISA/ KOEFISIEN (Permen PUPR no.28 thn 2016)
Mandor = 0.165 x 154.80 = 25.54 HOK
Semen @50Kg = 5.520 x 154.80 = 854.50 zak
Pasir Beton = 0.613 x 154.80 = 94.94 M³
Batu belah 2/3 = 0.778 x 154.80 = 120.51 M³
Air = 215.000 x 154.80 = 33,282.00 LITER

BURAS (LABUR ASPAL) 1,00 KG / M2 Dalam 10M2


Pekerja = 1.6000 x 129.00 = 206.40 HOK
Mandor = 0.2640 x 129.00 = 34.06 HOK
Aspal = 11.0000 x 129.00 = 1,419.00 kg
Kayu Bakar = 0.0400 x 129.00 = 5.16 M³
Pasir Beton = 0.1200 x 129.00 = 15.48 M³
Solar = 3.1000 x 129.00 = 399.90 Ltr

T.06.a.1) 1 m3 galian tanah biasa sedalam ≤ 1 m


Pekerja = 0.5630 x 7.74 = 4.36 HOK
Mandor = 0.0563 x 7.74 = 0.44 HOK

P.01 Pasangan batu dengan mortar jenis PC-PP (1 m3)


P.01.a Mortar tipe n (setara campuran 1 PC:4 PP)
P.01.a.1) Manual
Pekerja = 2.7000 x 4.13 = 11.14 HOK
Tukang = 0.9000 x 4.13 = 3.71 HOK
Mandor = 0.2700 x 4.13 = 1.11 HOK
Batu belah 15/20 = 1.2000 x 4.13 = 4.95 M³
Jenis Prasarana : JALAN AKSES LAHAN/RABAT BETON ASPAL
Lokasi : JALAN KEBUN MAKESOT
Volume/Dimensi : 2 UNIT / (400X 3M) (30 X 3M)
ANALISA/ KOEFISIEN (Permen PUPR no.28 thn 2016)
Pasir Beton = 0.5200 x 4.13 = 2.15 M³
Semen @50Kg = 3.2600 x 4.13 = 13.45 zak

A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)


Pekerja = 0.7800 x 18.00 = 14.04 HOK
Tukang = 0.3900 x 18.00 = 7.02 HOK
Kepala Tukang = 0.0390 x 18.00 = 0.70 HOK
Mandor = 0.0390 x 18.00 = 0.70 HOK
Batu belah 20/30 = 1.2000 x 18.00 = 21.60 M³
Pasir Urug = 0.4320 x 18.00 = 7.78 M³

Dibuat oleh :
Jenis Prasarana : JALAN AKSES LAHAN/RABAT BETON ASPAL
e Off Sheet (TOS) Lokasi : JALAN KEBUN MAKESOT
Volume/Dimensi : 2 UNIT / (400X 3M) (30 X 3M)
VOLUME PEKERJAAN ANALISA/ KOEFISIEN (Permen PUPR no.28 thn 2016)

REKAP BAHAN/MATERIAL
1 Kaso 5/7 cm ky kls III = 1.38 M³ ˷˷ 1.00 M³
2 Papan 3/20 ky kls III
3 Paku 5 cm dan 7 cm
=
=
2.41 M³
12.90 KG ˷˷ 2.00 M³
13.00 KG
4 Semen @50Kg
5 Pasir Beton
=
=
867.94 Zak
112.57 M³ ˷˷ 868.00 Zak
113.00 M³
6 Batu belah 2/3
7 Batu belah 15/20
=
=
120.51 M³
4.95 M³ ˷˷ 121.00 M³
5.00 M³
8 Batu belah 20/30
9 Pasir Urug
=
=
21.60 M³
7.78 M³ ˷˷ 22.00 M³
8.00 M³
10 Sirtu
11 Air
=
=
141.84 M³
33,282.00 L ˷˷ 142.00 M³
33,282 L
12 Aspal
13 Kayu Bakar
=
=
1,449.00 KG
5.16 M³ ˷˷ 1,449 KG
5.00 M³
14 Solar = 399.90 Ltr 400.00 Ltr

REKAP UPAH
Pekerja = 540.45 HOK ˷˷ 540.00 HOK
Tukang
Kepala Tukang
=
=
64.93 HOK
6.57 HOK ˷˷ 65.00 HOK
7.00 HOK
Mandor = 65.22 HOK 65.00 HOK
PERMEN PUPR NO.28 TAHUN 2016

T.01.a 1 m2 pembersihan dan striping/kosrekan


URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 7,800.00 1200.00
Pekerja L.01 OH 0.06 120,000 7,200.00
Mandor L.04 OH 0.006 100,000 600.00
B. Bahan -
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 7,800.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m² (D+E) 7,800.00

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 32,500.00 9
Pekerja L.01 OH 0.25 120,000 30,000.00
Mandor L.04 OH 0.025 100,000 2,500.00
B. Bahan 201,600.00
Sirtu m³ 1.2 168,000 201,600.00
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 234,100.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m² (D+E) 234,100.00

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi


URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 108,160.00 86.00
Pekerja L.01 OH 0.52 120,000 62,400.00
Tukang L.02 OH 0.26 150,000 39,000.00
Kepala Tukang L.03 OH 0.026 160,000 4,160.00
Mandor L.04 OH 0.026 100,000 2,600.00
B. Bahan 76,965.00
Kaso 5/7 cm ky kls III M.37.b m³ 0.016 1,672,500 26,760.00
Papan 3/20 ky kls III M.35.e m³ 0.028 1,672,500 46,830.00
Paku 5 cm dan 7 cm M.71.b kg 0.15 22,500 3,375.00
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 185,125.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m² (D+E) 185,125.00
B.03 1 m³ Beton mutu, f’c = 9,8 MPa (K125), slump (12±2) cm, w/c = 0,78
B.03.a Manual
URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 260,230.00 0.00
Pekerja L.01 OH 1.65 120,000 198,000.00
Tukang L.02 OH 0.275 150,000 41,250.00
Kepala Tukang L.03 OH 0.028 160,000 4,480.00
Mandor L.04 OH 0.165 100,000 16,500.00
B. Bahan 801,164.62
Semen @50Kg M.15 Zak 5.52 70,500 389,160.00
Pasir Beton M.14.a M³ 0.61333333 211,500 129,720.00
Batu belah 2/3 M.12 M³ 0.77846154 335,000 260,784.62
Air M.02 Ltr 215 100 21,500.00
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 1,061,394.62
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - M³ (D+E) 1,061,394.62

BURAS (LABUR ASPAL) 1,00 KG / M2 VOLUME


VOLUME : 10 M2 0.00
PEKERJA HOK 1.6000 120,000 192,000.00
MANDOR HOK 0.2640 100,000 26,400.00
ASPAL Kg 11.0000 15,000 165,000.00
KAYU BAKAR M3 0.0400 223,000 8,920.00
PASIR BETON M3 0.1200 211,500 25,380.00
Solar Ltr 3.1000 7,000 21,700.00
SET ALAT BANTU Ls 0.4000
COMPRESOR Jam 0.0500
THREE WHEEL ROLLER Jam 0.0200
OVERHEAD, KEUNTUNGAN DLL.
BIAYA UNTUK 1 M2 43,940.00

T.06.a.1) 1 m3 galian tanah biasa sedalam ≤ 1 m


URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 73,190.00 Err:509
Pekerja L.01 OH 0.563 120,000 67,560.00
Mandor L.04 OH 0.0563 100,000 5,630.00
B. Bahan -
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 73,190.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m³ (D+E) 73,190.00
P.01 Pasangan batu dengan mortar jenis PC-PP (1 m3)
P.01.a Mortar tipe n (setara campuran 1 PC:4 PP)
P.01.a.1) Manual
URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 486,000.00 Err:508
Pekerja L.01 OH 2.7 120,000 324,000.00
Tukang L.02 OH 0.9 150,000 135,000.00
Mandor L.04 OH 0.27 100,000 27,000.00
B. Bahan 594,210.00
Batu belah 15/20 M.05 m³ 1.2 212,000 254,400.00
Pasir Beton M.14.b m³ 0.52 211,500 109,980.00
Semen @50kg M.15 zak 3.26 70,500 229,830.00
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 1,080,210.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m³ (D+E) 1,080,210.00

A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)


URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA VOLUME
A. Tenaga Kerja 162,240.00 0.00
Pekerja L.01 OH 0.78 120,000 93,600.00
Tukang L.02 OH 0.39 150,000 58,500.00
Kepala Tukang L.03 OH 0.039 160,000 6,240.00
Mandor L.04 OH 0.039 100,000 3,900.00
B. Bahan 344,688.00
Batu belah 20/30 m³ 1.2 212,000 254,400.00
Pasir Urug M.14.b m³ 0.432 209,000 90,288.00
C. Peralatan -
D. Jumlah Tenaga Kerja+Bahan+Peralatan (A+B+C) 506,928.00
E. Overhead + Profit -
F. Harga Satuan Pekerjaan per - m³ (D+E) 506,928.00

PEKERJAAN PASANG PRASASTI


HSP TOTAL HARGA PEKERJAAN BOBOT
7,800.00 9,360,000 33.27%

HSP TOTAL HARGA PEKERJAAN BOBOT


234,100.00 2,106,900 7.49%

HSP TOTAL HARGA PEKERJAAN BOBOT


185,125.00 15,920,750 56.58%
HSP TOTAL HARGA PEKERJAAN BOBOT
1,061,394.62 - 0.00%

8.333333

22,660,775 0.12
0.66 33.12 kg 13.04% 14.94% 1 326 kg
0.07 99.36 kg 39.13% 39.72% 2.331288 760 kg
0.09 121.44 kg 47.83% 45.33% 3.156442 1029 kg
254 100.00%

HSP TOTAL HARGA PEKERJAAN BOBOT


43,940.00 - 0.00%

HSP TOTAL HARGA PEKERJAAN BOBOT


73,190.00 Err:509 Err:509
HSP TOTAL HARGA PEKERJAAN BOBOT
1,080,210.00 Err:508 Err:508

1.00
500,000 /M

HSP TOTAL HARGA PEKERJAAN BOBOT


506,928.00 - #DIV/0!

750,000 2.67%

TOTAL BIAYA 28,137,650 100%


6.52 sak
116.5644 kg
157.8221 kg
Daftar Harga Bahan &
KEGIATAN : P3MD KAB. MINAHASA SELATAN
PEKERJAAN : RABAT BETON
LOKASI : DESA PINAMORONGAN - KEC.TARERAN
T. A. : 2019

NO. NAMA BARANG/JENIS SAT

1 2 3

A BAHAN
contoh 1 Kaso 5/7 cm ky kls III M³
2 Papan 3/20 ky kls III M³
3 Paku 5 cm dan 7 cm KG
4 Semen @50Kg Zak
5 Pasir Beton M³
6 Batu Belah 2/3 M³
7 Air LTR
8 Batu belah 15/20 M³
9 Batu belah 20/30 M³
10 Paving Block 8cm natural bh
11 Pasir Halus M³
12 Pasir Urug M³
13 Besi Beton Ø16 stf
14 Besi Beton Ø12 stf
15 Besi Beton Ø10 stf
16 Besi Beton Ø8 stf
17 Besi Beton Ø6 stf
18 Bendrat Kg
19 Bata Merah bh
20 Cat Tembok Kg
21 Cat Minyak Kg
22 Tinner L
23 Pipa Galvanis Ø3" ujg
24 Bambu Ø8-10cm M
25 Aspal kg
26 Solar LTR
27 Kayu Bakar M³
28 Tanah urug M³
29 Sirtu M³
B ALAT
1 Benang nylon roll
2 gerobak artcho bh
3 Sekop bh
4 Ember cor bh
5 Terpal bh
6 Mata gergaji besi bh
7 Gergaji besi bh
8 Papan proyek bh
9 Prasasti bh
10 Stamper sewa hari
11 Pakoel bh

C UPAH
1 Pekerja HOK
2 Tukang HOK
3 Kepala Tukang HOK
4 Mandor HOK
5

PELAKSANA KEGIATAN

......................................
Bahan & Upah

HARGA DIISI BERDASARKAN SURVEY HARGA TERENDAH


KETERANGAN
SATUAN (Rp) HASIL REKONSILIASI DENGAN TOKO/SUPL
4 5

DPP ppn+pph22
1,672,500 1,500,000 172,500
1,672,500 1,500,000 172,500
22,500 20,000 2,300
70,500 63,228.70 7,271
211,500 190,000 21,850
335,000 300,000 34,500
100
212,000 190,000 21,850
212,000 180,000 20,700
2,800 2,511 289
223,000 200,000 23,000
209,000 190,000 21,850
195,500 175,000 20,125
106,000 95,000 10,925
72,500 65,000 7,475
50,500 45,000 5,175
33,500 30,000 3,450
30,000 25,000 2,875
2,500 2,000 230
13,500 12,000 1,380
67,000 60,000 6,900
51,000 45,000 5,175
725,000 650,000 74,750
2,500 2,000 230
15,000 13,800 1,587
7,000 7,000 -
223,000 200,000 23,000
111,500 100,000 11,500
168,000 150,000 17,250
-

22,500 20,000 2,300


613,500 550,000 63,250
72,500 65,000 7,475
17,000 15,000 1,725
335,000 300,000 34,500
11,500 10,000 1,150
139,500 125,000 14,375
150,000 150,000 17,250
750,000 750,000 86,250
500,000 -
250,000 -
-
-
120,000
150,000 B CONTOH
160,000 SATUAN UPAH DIISI
100,000 BERDASARKAN KESEPAKATAN UPAH
DALAM MUS-DES DENGAN Berita Acara

KOORD PPKD

...........................
RVEY HARGA TERENDAH, KETERSEDIAAN STOK, KUALITAS BARANG DARI SURVEY 3 TOKO/SUPLIER
I DENGAN TOKO/SUPLIER

harga trmasuk
1,672,500 -
1,672,500 -
22,300 200
70,500 -
211,850 (350)
334,500 500
100
211,850 150
200,700 11,300
2,800 -
223,000 -
211,850 (2,850)
195,125 375
105,925 75
72,475 25
50,175 325
33,450 50
27,875 2,125
2,230 270
13,380 120
66,900 100
50,175 825
724,750 250
2,230 270
15,387 (387)
7,000 -
223,000 -
111,500 -
167,250 750
- -
-
22,300 200
613,250 250
72,475 25
16,725 275
334,500 500
11,150 350
139,375 125
167,250 (17,250)
836,250 (86,250)
- 500,000
- 250,000
- -
-

N Berita Acara
Rekonsiliasi Harga Baha
KEGIATAN : P3MD KAB.MINAHASA SELATAN
PEKERJAAN : ...................................................................
LOKASI : DESA ............................................... - KEC.TARERAN
T. A. : 2019

SURVEY TPK
NO. NAMA BARANG/JENIS SAT
CV. A
1 2 3 4

A BAHAN
1 Kaso 5/7 cm ky kls III M³ 1,500,000
2 Papan 3/20 ky kls III M³ 1,500,000
3 Paku 5 cm dan 7 cm KG 20,000
4 Semen Tonasa @50Kg Zak 70,000
5 Pasir Beton M³ 250,000
6 Krikil M³ 300,000
7
8
9
10

B ALAT
1 Benang nylon roll 20,000
2 gerobak artco bh 550,000
3 Sekop bh 70,000
4 Ember cor bh 16,000
5
6
7
8
9
10
11

PELAKSANA KEGIATAN
......................................
rga Bahan & Upah

SURVEY TPK
KETERANGAN
UD. B UD. C
5 6 7

1,750,000 1,750,000 disepakati


1,750,000 1,750,000 oleh Tim dan
20,000 20,000 tertuang dlm
70,000 72,000 BA kesepakatan
235,000 250,000 membeli dari UD.C
275,000 300,000

20,000 20,000
550,000 500,000
70,000 65,000
15,000 15,000

Mengetahui,
KOORD PPKD
...........................
aftar Survey Harga Bahan & Upa
KEGIATAN : P3MD KAB. MINAHASA SELATAN
PEKERJAAN : ...................................................................
LOKASI : KEC.TARERAN
T. A. : 2018
NAMA TOKO/SUPLIER :
TANGGAL SURVEY :

HARGA
NO. NAMA BARANG/JENIS SAT KETERANGAN
TOKO
1 2 3 4 5

A BAHAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30

B ALAT
1
2
3
4
5
6
7
8
9
10
11
12
13

SUPLIER/PEMILIK TOKO

cap dan ttd

...........................
Daftar Survey Harga Bahan &
KEGIATAN : P3MD KAB. MINAHASA SELATAN
PEKERJAAN : ...................................................................
LOKASI : DESA ............................................... - KEC.TARERAN
T. A. : 2019
NAMA TOKO/SUPLIER :
TANGGAL SURVEY :

NO. NAMA BARANG/JENIS SAT

1 2 3

A BAHAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75

B ALAT
1
2
3
4
5
6
7
8
9
10
11
12
13

PELAKSANA KEGIATAN

......................................
Bahan & Upah

HARGA
KETERANGAN
TOKO
4 5
SUPLIER/PEMILIK TOKO

...........................
XXIV. FORMAT PEMERIKSAAN DOKUMEN PROPOSAL TEKNIS DAN RAB

PEMERIKSAAN DOKUMEN PROPOSAL TEKNIS DAN RAB

Desa : …...………………………………………… Lokasi


Kecamatan :………………………………………………. Bidang
Kabupaten :………………………………………………. Kegiatan
Provinsi : ………………………………………………. Volume

Ada Memenuhi
Jenis Dokumen yang Diperiksa
Syarat

1 Sketsa lokasi kegiatan


2 Dokumen survey teknis
3 Gambar desain
4 Perhitungan volume
5 Survey harga bahan dan alat
6 Kesepakatan pembayaran upah kerja
7 Perhitungan RAB
8 Kajian sederhana mengenai dampak lingkungan
9 Pernyataan hibah lahan dari masyarakat
10 Pernyataan kesanggupan tidak minta ganti rugi
11 Kesanggupan swadaya dan gotong royong
12 Rencana penggunaan alat berat/bila ada
13 Pernyataan kesiapan warga untuk mengerjakan
14 Data pemanfaat

Diperiksa Tanggal :
Hasil Pemeriksaan dinyatakan : Layak / Tidak Layak

Tim Verifikasi
1 Wakil Masyarakat : 1…………………………………..
2 Pendamping Profesional : 2. ……………………………………
3 Dinas Instansi Terkait : 3……………………………………
4 ………………………………. : 4. …………………………………
EKNIS DAN RAB

: ……………………………………
: ……………………………………
: ……………………………………
: ……………………………………

Ada & Tidak


Memenuhi Tidak Ada
Syarat

2. ……………………………………..

4. …………………………………….
P3MD MINSEL

PEMERIKSAAN DESAIN
Lokasi :: Jenis Prasarana :
Dibuat oleh :: Hasil Pemeriksaan ke :
Jabatan : Tanggal diserahkan :

Jenis Desain dan Dokumen yang diperiksa :


1. Lokasi jelas di peta 6. Dimensi dan spesifikasi lengkap
2. Lokasi prasarana tepat 7. Pemilihan jenis konstruksi
3. Lokasi perlengkapan jelas 8. Volume sesuai
4. Perhitungan teknis jelas dan tepat 9. Harga wajar
5. Gambar detail cukup 10. Penggunan peralatan wajar

Hal-hal yang harus diperhatikan/diperbaiki :


Diperiksa oleh PDTI:

Tanggal :
Penilaian :

(_________________)
Form.25

imensi dan spesifikasi lengkap


emilihan jenis konstruksi
olume sesuai

enggunan peralatan wajar


Diperiksa oleh PDTI:

Layak / Tidak layak

(_________________)
PDTI

Anda mungkin juga menyukai