Halaman 2
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
43 Semen putih Kg 3,740.00
44 Semen Adhesive Kg 4,675.00
45 Perekat / Lem vinyl Ltr 74,800.00
46 Kapur padam M3 125,800.00
47 Semen Plesteran Dinding Bata Ringan (PM - 200) Kg 3,230.00
48 Semen Acian Dinding Bata Ringan (PM - 300) Kg 4,930.00
49 Semen Perekat Dinding Bata Ringan (PM -110) Kg 4,250.00
50 Floor Hardener (MU 700) Kg 7,310.00
51 Compound Zak 79,050.00
52 Panel Beton Pracetak Uk.5 x 40 x 240 cm K.250 Lbr 163,200.00
53 Kolom Beton Pracetak Panjang 3 M' K.250 Btg 462,400.00
54 Kolom Beton Pracetak Sudut Panjang 3 M' K.250 Btg 577,150.00
Halaman 3
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
41 Multiplex laminated 2 sisi 15 mm Lbr 268,600.00
42 Multiplex laminated 2 sisi 12 mm Lbr 215,050.00
43 Blockboard 18 mm Lbr 170,000.00
44 Blockboard 24 mm Lbr 227,800.00
45 Triplek 3 mm Lbr 62,050.00
46 Triplek 4 mm Lbr 79,050.00
47 Triplek 5 mm Lbr 88,400.00
48 Triplek 6 mm Lbr 104,550.00
49 Triplek 8 mm Lbr 145,000.00
50 Triplek 9 mm Lbr 155,000.00
51 Lambresering M2 187,000.00
Halaman 4
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
42 Hollow Hitam 20.20.2 ( 6 m) Btg 73,100.00
43 Hollow Hitam 20.40.2 ( 6 m) Btg 107,100.00
44 Hollow Hitam 25.25.2 ( 6 m) Btg 68,000.00
45 Hollow Hitam 30.30.2 ( 6 m) Btg 107,950.00
46 Hollow Hitam 30.60.2 ( 6 m) Btg 175,950.00
47 Hollow Hitam 40.40.2 ( 6 m) Btg 149,600.00
48 Hollow Hitam 40.60.2 ( 6 m) Btg 211,650.00
49 Hollow Galvalum 2 x 4 Btg 20,000.00
50 Hollow Galvalum 4 x 4 Btg 25,000.00
51 Rangka Hollow 40 x 40 x 0,8 mm M' 56,100.00
52 Rangka Hollow 40 x 40 x 0,25 mm M' 23,800.00
53 Rangka Hollow 40 x 40 x 0,3 mm M' 28,900.00
54 Rangka Hollow 40 x 40 x 0,4 mm M' 28,050.00
55 Rangka Hollow 40 x 20 x 0,8 mm M' 45,050.00
56 Rangka Hollow 40 x 20 x 0,25 mm M' 18,700.00
57 Rangka Hollow 40 x 20 x 0,4 mm M' 28,900.00
58 Spandrell uk. 11 cm x 6 m Lbr 107,950.00
59 UNP 50.50 (6 m) Btg 192,950.00
60 UNP 100.100 (6 m) Btg 574,600.00
61 UNP 150.150 (6 m) Btg 1,132,200.00
62 UNP 200.200 (6 m) Btg 1,713,600.00
63 CNP 125.50.20 tebal 2,2 mm (6 m) Btg 460,700.00
64 CNP 125.50.20 tebal 3 mm (6 m) Btg 489,600.00
65 CNP 100.50.20 tebal 2,2 mm (6 m) Btg 518,500.00
66 CNP 100.50.20 tebal 3 mm (6 m) Btg 551,650.00
67 CNP 75.35.20 tebal 2 mm (6 m) Btg 322,150.00
68 CNP 75.45.20 tebal 2,2 mm (6 m) Btg 316,200.00
69 CNP 75.45.15 tebal 2,2 mm (6 m) Btg 284,750.00
70 CNP 75.45.15 tebal 1,8 mm (6 m) Btg 252,450.00
71 CNP 75.35.15 tebal 1,5 mm (6 m) Btg 220,150.00
72 Canal 100 MMI (6 m) Btg 101,150.00
73 Canal 75 MMI (6 m) Btg 90,950.00
74 Canal 75 Polos (6 m) Btg 90,950.00
75 Canal 75 JP (6 m) Btg 94,350.00
76 Canal 75 GG (6 m) Btg 66,300.00
77 Canal 72 MMI (6 m) Btg 68,000.00
78 Canal 72 Polos (6 m) Btg 67,150.00
79 Reng 32 MMI Btg 58,650.00
80 Reng 30 MMI Btg 51,850.00
81 Reng 28 MMI Btg 47,600.00
82 Reng 32 JP Btg 51,850.00
83 Reng 30 JP Btg 47,600.00
84 Plat Aluminium ( 90 x 200 ) cm Lbr 123,250.00
85 Aluminium Composit Panel (ACP) (Indoor) M2 306,850.00
86 Aluminium Composit Panel (ACP) (Outdoor) M2 453,050.00
87 Besi tempa untuk teralis pagar (rangkap) M2 1,028,500.00
88 Kawat beton Kg 30,600.00
89 Kawat F4, t. 4 mm (Penggantung Plafond) Btg 1,870.00
90 Kawat harmonika M2 31,450.00
91 Kawat nyamuk (Ram nyamuk hijau) M2 24,650.00
92 Kawat duri M' 16,150.00
93 Kawat Bronjong Galvanis Uk. 2 x 1 x 0,5 M3 269,450.00
94 Karung Plastik Kap. 50 kg Bh 6,800.00
95 Ram kawat hitam (saringan) M2 26,350.00
Halaman 5
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
96 Paku sekrup Bh 297.50
97 Paku triplek Kg 26,350.00
98 Paku asbes Kg 39,950.00
99 Paku pancing Kg 1,870.00
100 Paku payung asbes Kg 35,700.00
101 Paku payung Sekrup Kg 1,190.00
102 Paku biasa 2"-5" Kg 18,700.00
103 Paku biasa 1/2" - 1" Kg 22,100.00
104 Paku gypsum Kg 33,150.00
105 Paku beton ( 2 cm s/d 12 cm) Kg 42,500.00
106 Timbal t. 3 mm (Uk. 1 x 10 m) Lbr 16,128,750.00
107 Skrup Fixer Bh 935.00
108 Baud D.12 mm Bh 5,610.00
109 Baud D.16 mm Bh 7,480.00
110 Baud D.19 mm Bh 8,415.00
111 Dina Bolt M 12 P. 6 - 12 cm Bh 6,545.00
112 Kawat las listrik Kg 32,300.00
113 Shadow Line Btg 32,000.00
114 Daun Pintu Aluminium Natural dengan kaca lengkap acesories Unit 1,612,450.00
115 Daun Pintu Aluminium Warna dengan kaca lengkap acesories Unit 1,720,400.00
116 Daun Pintu Frameless Kaca Bening 10 mm lengkap acesories Unit 5,806,350.00
117 Daun Pintu Sliding Aluminium dengan kaca lengkap acesories Unit 2,063,800.00
118 Daun Pintu Kaca Tempered t.12 mm lengkap acesories Unit 6,451,500.00
119 Daun jendela Casement Allumunium Natural dgn kaca + Accs. M2 908,650.00
120 Daun jendela Casement Allumunium Warna dgn kaca + Accs. M2 931,600.00
121 Siku Alumunium M' 32,300.00
122 List Stainless T Btg 42,500.00
123 Lapisan HPL 120 x 240 Cm M2 177,650.00
124 HPL Art Foam Pure Lunch Lbr 256,700.00
125 HPL ex-Himel Lbr 215,050.00
126 HPL ex-Taco (Polos/Biasa) Lbr 322,150.00
127 HPL ex-Taco (Texture) Lbr 273,000.00
128 Edging HPL m' 10,000.00
129 Kusen Aluminium Standar Natural 4" M' 104,550.00
130 Kusen Aluminium Standar Natural 3" M' 84,150.00
131 Kusen Aluminium Warna Doff 4" M' 108,800.00
132 Kusen Aluminium Warna Doff 3" M' 96,900.00
133 Kusen Aluminium Warna 4" M' 118,150.00
134 Kusen Aluminium Warna 3" M' 104,550.00
135 Polycarbonate Sheet / Twin Lite Uk.11,8 x 2,1 t. 5 mm Lbr 2,043,400.00
136 Polycarbonate + kerangka besi M2 472,600.00
137 Polycarbonate + kerangka stainless steel M2 807,500.00
138 Folding Gate (Pintu Lipat) M2 1,021,700.00
139 Fibre Glass ( Acyrlic ) tebal 5 mm Lbr 1,133,900.00
140 Rolling Door / Grille M2 477,700.00
141 Pintu Henderson M2 1,881,900.00
142 Pagar BRC tinggi 120 cm, p.240 cm Lbr 283,050.00
143 Pagar BRC tinggi 60 cm, p.240 cm tbl. 5 mm Lbr 175,950.00
144 Pagar BRC tinggi 90 cm, p.240 cm tbl. 5 mm Lbr 212,500.00
145 Kuda - kuda Baja Ringan Zingallum tbl. 0,75 mm M2 169,150.00
146 Wiremesh M-5 uk. 2,10 x 5,40 m M2 38,000.00
147 Wiremesh M-6 uk. 2,10 x 5,40 m M2 45,050.00
148 Wiremesh M-8 uk. 2,10 x 5,40 m M2 65,450.00
149 Wiremesh M-10 uk. 2,10 x 5,40 m M2 113,050.00
Halaman 6
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
150 Tiang Pancang Kotak Masif 25 x 25 klas A K-500 (P. 6 s/d. 8) M' 278,800.00
151 Tiang Pancang Kotak Masif 25 x 25 klas B K-500 (P. 6 s/d. 8) M' 288,150.00
152 Tiang Pancang Kotak Masif 25 x 25 klas C K-500 (P. 6 s/d. 8) M' 316,200.00
153 Sambungan TP Kotak 25x25 - Kelas A joint 830,500.00
154 Sambungan TP Kotak 25x25 - Kelas B joint 1,057,100.00
155 Sambungan TP Kotak 25x25 - Kelas C joint 1,272,700.00
156 Tiang Pancang Kotak Masif 20 x 20 klas A K-500 (P. 6 s/d. 9) M' 209,100.00
157 Tiang Pancang Segitiga (Triangular ) 22 Kelas A K-500 (P.6) M' 129,200.00
158 Tiang Pancang Segitiga (Triangular ) 24 Kelas A K-500 (P.6) M' 147,050.00
159 Tiang Pancang Segitiga (Triangular ) 26 Kelas A K-500 (P.6) M' 164,050.00
160 Tiang Pancang Segitiga (Triangular ) 28 Kelas A K-500 (P.6 s.d/.8) M' 200,600.00
161 Tiang Pancang Segitiga (Triangular ) 28 Kelas B K-500 (P.6 s.d/.9) M' 224,400.00
162 Tiang Pancang Segitiga (Triangular ) 30 Kelas A K-500 (P.6 s.d/.8) M' 227,800.00
163 Tiang Pancang Segitiga (Triangular ) 30 Kelas B K-500 (P.6 s.d/.9) M' 249,900.00
164 Tiang Pancang Segitiga (Triangular ) 32 Kelas A K-500 (P.6 s.d/.8) M' 233,750.00
165 Tiang Pancang Segitiga (Triangular ) 32 Kelas B K-500 (P.6 s.d/.9) M' 249,050.00
166 Tiang Pancang Beton Bulat d. 300 (p. 6 s/d. 8) Bottom M' 376,550.00
167 Tiang Pancang Beton Bulat d. 300 (p. 6 s/d. 8) Middle M' 405,450.00
168 Tiang Pancang Beton Bulat d. 300 (p. 9 s/d. 11) Bottom M' 355,300.00
169 Tiang Pancang Beton Bulat d. 300 (p. 9 s/d. 11) Middle M' 372,300.00
170 Tiang Pancang Beton Bulat d. 300 (p. 12 s/d. 13) Bottom M' 341,700.00
171 Tiang Pancang Beton Bulat d. 300 (p. 12 s/d. 13) Middle M' 356,150.00
172 Tiang Pancang Beton Bulat d. 350 (p. 6 s/d. 8) Bottom M' 464,100.00
173 Tiang Pancang Beton Bulat d. 350 (p. 6 s/d. 8) Middle M' 507,450.00
174 Tiang Pancang Beton Bulat d. 350 (p. 9 s/d. 11) Bottom M' 437,750.00
175 Tiang Pancang Beton Bulat d. 350 (p. 9 s/d. 11) Middle M' 465,800.00
176 Tiang Pancang Beton Bulat d. 350 (p. 12 s/d. 14) Bottom M' 425,000.00
177 Tiang Pancang Beton Bulat d. 350 (p. 12 s/d. 14) Middle M' 445,400.00
178 Tiang Pancang Beton Bulat d. 350 (p. 15) Bottom M' 447,100.00
179 Tiang Pancang Beton Bulat d. 350 (p. 15) Middle M' 447,100.00
180 Tiang Pancang Beton Bulat d. 400 (p. 6 s/d. 8) Bottom M' 613,700.00
181 Tiang Pancang Beton Bulat d. 400 (p. 6 s/d. 8) Middle M' 668,100.00
182 Tiang Pancang Beton Bulat d. 400 (p. 9 s/d. 11) Bottom M' 581,400.00
183 Tiang Pancang Beton Bulat d. 400 (p. 9 s/d. 11) Middle M' 618,800.00
184 Tiang Pancang Beton Bulat d. 400 (p. 12 s/d. 14) Bottom M' 565,250.00
185 Tiang Pancang Beton Bulat d. 400 (p. 12 s/d. 14) Middle M' 593,300.00
186 Tiang Pancang Beton Bulat d. 400 (p. 15 s/d. 16) Bottom M' 586,500.00
187 Tiang Pancang Beton Bulat d. 400 (p. 15 s/d. 16) Middle M' 586,500.00
188 Tiang Pancang Beton Bulat d. 450 (p. 6 s/d. 8) Bottom M' 735,250.00
189 Tiang Pancang Beton Bulat d. 450 (p. 6 s/d. 8) Middle M' 798,150.00
190 Tiang Pancang Beton Bulat d. 450 (p. 9 s/d. 11) Bottom M' 694,450.00
191 Tiang Pancang Beton Bulat d. 450 (p. 9 s/d. 11) Middle M' 736,950.00
192 Tiang Pancang Beton Bulat d. 450 (p. 12 s/d. 14) Bottom M' 674,050.00
193 Tiang Pancang Beton Bulat d. 450 (p. 12 s/d. 14) Middle M' 706,350.00
194 Tiang Pancang Beton Bulat d. 450 (p. 15 s/d. 16) Bottom M' 732,700.00
195 Tiang Pancang Beton Bulat d. 450 (p. 15 s/d. 16) Middle M' 732,700.00
196 Tiang Pancang Beton Bulat d. 500 (p. 6 s/d. 8) Bottom M' 900,150.00
197 Tiang Pancang Beton Bulat d. 500 (p. 6 s/d. 8) Middle M' 984,300.00
198 Tiang Pancang Beton Bulat d. 500 (p. 9 s/d. 11) Bottom M' 917,150.00
199 Tiang Pancang Beton Bulat d. 500 (p. 9 s/d. 11) Middle M' 917,150.00
200 Tiang Pancang Beton Bulat d. 500 (p. 12 s/d. 14) Bottom M' 888,250.00
201 Tiang Pancang Beton Bulat d. 500 (p. 12 s/d. 14) Middle M' 888,250.00
202 Tiang Pancang Beton Bulat d. 500 (p. 15 s/d. 16) Bottom M' 914,600.00
203 Tiang Pancang Beton Bulat d. 500 (p. 15 s/d. 16) Middle M' 914,600.00
Halaman 7
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
204 Tiang Pancang Beton Bulat d. 600 (p. 6 s/d. 8) Bottom M' 1,271,600.00
205 Tiang Pancang Beton Bulat d. 600 (p. 6 s/d. 8) Middle M' 1,397,400.00
206 Tiang Pancang Beton Bulat d. 600 (p. 9 s/d. 11) Bottom M' 1,195,100.00
207 Tiang Pancang Beton Bulat d. 600 (p. 9 s/d. 11) Middle M' 1,279,250.00
208 Tiang Pancang Beton Bulat d. 600 (p. 12 s/d. 14) Bottom M' 1,157,700.00
209 Tiang Pancang Beton Bulat d. 600 (p. 12 s/d. 14) Middle M' 1,219,750.00
210 Tiang Pancang Beton Bulat d. 600 (p. 15 s/d. 16) Bottom M' 1,134,750.00
211 Tiang Pancang Beton Bulat d. 600 (p. 15 s/d. 16) Middle M' 1,184,050.00
GIRDER H-90 cm
1 PC. I Girder H-90 cm L-12,6m, Ctc-185, K.500 M' 74,306,150.00
2 PC. I Girder H-90 cm L-13,6m, Ctc-185, K.500 M' 79,837,100.00
3 PC. I Girder H-90 cm L-14,6m, Ctc-185, K.500 M' 89,272,100.00
4 PC. I Girder H-90 cm L-15,6m, Ctc-185, K.500 M' 95,885,100.00
5 PC. I Girder H-90 cm L-16,6m, Ctc-185, K.500 M' 102,498,100.00
GIRDER H-125 cm
1 PC. I Girder H-125 cm L-16,6m, Ctc-185, K.500 M' 100,401,150.00
2 PC. I Girder H-125 cm L-17,6m, Ctc-185, K.500 M' 104,030,650.00
3 PC. I Girder H-125 cm L-18,6m, Ctc-185, K.500 M' 109,123,850.00
4 PC. I Girder H-125 cm L-19,6m, Ctc-185, K.500 M' 117,336,550.00
5 PC. I Girder H-125 cm L-20,6m, Ctc-185, K.500 M' 125,804,250.00
6 PC. I Girder H-125 cm L-21,6m, Ctc-185, K.500 M' 134,271,100.00
7 PC. I Girder H-125 cm L-22,6m, Ctc-185, K.600 M' 140,319,700.00
8 PC. I Girder H-125 cm L-23,6m, Ctc-185, K.700 M' 149,996,950.00
GIRDER H-160 cm
1 PC. I Girder H-160 cm L-22,6m, Ctc-185, K.500 M' 175,144,200.00
2 PC. I Girder H-160 cm L-23,6m, Ctc-185, K.500 M' 182,871,550.00
3 PC. I Girder H-160 cm L-24,6m, Ctc-185, K.500 M' 188,823,250.00
4 PC. I Girder H-160 cm L-25,6m, Ctc-185, K.500 M' 196,613,500.00
5 PC. I Girder H-160 cm L-26,6m, Ctc-185, K.500 M' 204,805,800.00
6 PC. I Girder H-160 cm L-27,6m, Ctc-185, K.500 M' 212,203,350.00
7 PC. I Girder H-160 cm L-28,6m, Ctc-185, K.500 M' 222,070,150.00
8 PC. I Girder H-160 cm L-29,6m, Ctc-185, K.500 M' 229,675,100.00
9 PC. I Girder H-160 cm L-30,6m, Ctc-140, K.600 M' 231,328,350.00
10 PC. I Girder H-160 cm L-31,6m, Ctc-140, K.600 M' 240,833,050.00
GIRDER H-170 cm
1 PC. I Girder H-170 cm L-30,8m, Ctc-185, K.500 M' 276,280,600.00
2 PC. I Girder H-170 cm L-31,8m, Ctc-185, K.500 M' 286,984,650.00
3 PC. I Girder H-170 cm L-32,8m, Ctc-185, K.500 M' 297,987,900.00
4 PC. I Girder H-170 cm L-33,8m, Ctc-185, K.500 M' 307,916,750.00
5 PC. I Girder H-170 cm L-34,8m, Ctc-185, K.500 M' 322,184,850.00
6 PC. I Girder H-170 cm L-35,8m, Ctc-185, K.500 M' 343,427,200.00
7 PC. I Girder H-170 cm L-36,8m, Ctc-185, K.700 M' 361,063,000.00
8 PC. I Girder H-170 cm L-37,8m, Ctc-185, K.700 M' 383,483,450.00
9 PC. I Girder H-170 cm L-38,8m, Ctc-185, K.700 M' 399,662,350.00
10 PC. I Girder H-170 cm L-39,8m, Ctc-140, K.700 M' 387,894,950.00
11 PC. I Girder H-170 cm L-40,8m, Ctc-140, K.700 M' 403,206,000.00
12 PC. I Girder H-170 cm L-41,8m, Ctc-140, K.700 M' 419,147,750.00
GIRDER H-210 cm
1 PC. I Girder H-210 cm L-35,8m, Ctc-185, K.500 M' 327,477,800.00
2 PC. I Girder H-210 cm L-36,8m, Ctc-185, K.500 M' 335,606,350.00
3 PC. I Girder H-210 cm L-37,8m, Ctc-185, K.500 M' 393,236,350.00
4 PC. I Girder H-210 cm L-38,8m, Ctc-185, K.500 M' 405,696,500.00
5 PC. I Girder H-210 cm L-39,8m, Ctc-185, K.500 M' 418,445,650.00
6 PC. I Girder H-210 cm L-40,8m, Ctc-185, K.600 M' 436,712,150.00
Halaman 8
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
7 PC. I Girder H-210 cm L-41,8m, Ctc-185, K.600 M' 455,186,050.00
8 PC. I Girder H-210 cm L-42,8m, Ctc-185, K.600 M' 471,954,000.00
9 PC. I Girder H-210 cm L-43,8m, Ctc-185, K.600 M' 489,662,900.00
10 PC. I Girder H-210 cm L-44,8m, Ctc-185, K.700 M' 515,729,850.00
11 PC. I Girder H-210 cm L-45,8m, Ctc-185, K.700 M' 539,461,850.00
12 PC. I Girder H-210 cm L-46,8m, Ctc-140, K.700 M' 527,156,400.00
13 PC. I Girder H-210 cm L-47,8m, Ctc-140, K.700 M' 541,031,800.00
14 PC. I Girder H-210 cm L-48,8m, Ctc-140, K.700 M' 563,565,300.00
15 PC. I Girder H-210 cm L-49,8m, Ctc-140, K.700 M' 588,000,250.00
16 PC. I Girder H-210 cm L-50,8m, Ctc-140, K.700 M' 635,919,000.00
DIAFRAGMA
1 Diafragma PC. I Girder H-90cm, Ctc-185 cm, K.350 M' 2,128,400.00
2 Diafragma PC. I Girder H-90cm, Ctc-140 cm, K.350 M' 1,671,000.00
3 Diafragma PC. I Girder H-125cm, Ctc-185 cm, K.350 M' 2,483,700.00
4 Diafragma PC. I Girder H-125cm, Ctc-140 cm, K.350 M' 2,004,000.00
5 Diafragma PC. I Girder H-160cm, Ctc-185 cm, K.350 M' 2,483,700.00
6 Diafragma PC. I Girder H-160cm, Ctc-140 cm, K.350 M' 1,893,000.00
7 Diafragma PC. I Girder H-170cm, Ctc-185 cm, K.350 M' 2,365,550.00
8 Diafragma PC. I Girder H-170cm, Ctc-140 cm, K.350 M' 1,782,000.00
9 Diafragma PC. I Girder H-210cm, Ctc-185 cm, K.350 M' 15,257,500.00
10 Diafragma PC. I Girder H-210cm, Ctc-140 cm, K.350 M' 2,115,000.00
PLAT DECK
Platdeck Pracetak PC I Garder H-90 cm ; Ctc-185 cm
11 M' 591,600.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-90 cm ; Ctc-140 cm
12 M' 450,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-125 cm ; Ctc-185 cm
13 M' 560,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-125 cm ; Ctc-140 cm
14 M' 450,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-160 cm ; Ctc-185 cm
15 M' 560,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-160 cm ; Ctc-140 cm
16 M' 350,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-170 cm ; Ctc-185 cm
17 M' 450,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-170 cm ; Ctc-140 cm
18 M' 335,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-210 cm ; Ctc-185 cm
19 M' 450,000.00
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-210 cm ; Ctc-140 cm
20 M' 223,000.00
(100cmx160cmx7cm) ; K.350
Halaman 9
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
b = 0,40 , h = 0,50 M' 8,519,550.00
b = 0,40 , h = 1,00 M' 10,860,450.00
9 Pintu Sorong Baja (satu draad) stang
b = 0,50 , h = 0,30 M' 8,097,950.00
b = 0,50, h = 0,50 M' 8,659,800.00
b = 0,50 , h = 1,00 M' 11,701,950.00
10 Pintu Sorong Baja (satu draad) stang
b = 0,60 , h = 0,30 M' 8,426,050.00
b = 0,60 , h = 0,50 M' 8,940,300.00
b = 0,60 , h = 1,00 M' 13,396,000.00
11 Pintu Sorong Baja (satu draad) stang
b = 0,70 , h = 0,30 M' 8,706,550.00
b = 0,70 , h = 0,50 M' 9,866,800.00
b = 0,70 , h =1,00 M' 15,682,500.00
12 Pintu Sorong Baja (satu draad) stang
b = 0,80, h = 0,30 M' 9,175,750.00
b = 0,80, h = 0,50 M' 10,532,350.00
b = 0,80, h =1,00 M' 17,882,300.00
13 Pintu Sorong Baja (satu draad) stang
b = 0,90 , h = 0,30 M' 9,596,500.00
b = 0,90 , h = 0,50 M' 10,999,850.00
b = 0,90, h = 1,00 M' 20,130,550.00
14 Pintu Sorong Baja (satu draad) stang
b =1,00 , h = 0,30 M' 10,299,450.00
b =1,00 , h = 0,50 M' 11,701,950.00
b =1,00 , h = 1,00 M' 22,469,750.00
15 Pintu Sorong Baja (satu draad) stang
b = 1,10, h = 0,50 M' 12,171,150.00
b = 1,10, h = 1,00 M' 24,810,650.00
b = 1,10, h = 1,80 M' 40,352,900.00
16 Pintu Sorong Baja (satu draad) stang
b = 1,20, h = 0,50 M' 13,107,000.00
b = 1,20, h = 1,00 M' 30,428,300.00
b = 1,20, h = 1,80 M' 48,686,300.00
17 Pintu Sorong Baja (satu draad) stang
b = 1,30, h = 1,00 M' 69,847,050.00
b = 1,30, h = 1,50 M' 73,450,200.00
b = 1,30, h = 2.00 M' 77,899,100.00
18 Pintu Sorong Baja (dua draad) stang
b = 1,40, h = 1,00 M' 70,970,750.00
b = 1,40, h = 1,50 M' 76,914,800.00
b = 1,40, h = 2,00 M' 82,658,250.00
19 Pintu Sorong Baja (dua draad) stang
b = 1,50, h = 1,00 M' 72,140,350.00
b = 1,50, h = 1,50 M' 78,319,850.00
b = 1,50, h = 2,00 M' 88,055,750.00
20 Pintu Sorong Baja (dua draad) stang
b = 1,60, h = 1,00 M' 73,264,050.00
b = 1,60, h = 1,50 M' 79,724,050.00
b = 1,60, h = 2,00 M' 89,790,600.00
21 Pintu Sorong Baja (dua draad) stang
b = 1,70, h = 1,00 M' 74,386,900.00
b = 1,70, h = 1,50 M' 78,601,200.00
b = 1,70, h = 2,00 M' 83,937,500.00
Halaman 10
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
22 Pintu Sorong Baja (dua draad) stang
b = 1,80, h = 1,00 M' 75,510,600.00
b = 1,80, h = 1,50 M' 79,958,650.00
b = 1,80, h = 2,00 M' 85,435,200.00
23 Pintu Sorong Baja (dua draad) stang
b = 1,90, h = 1,00 M' 76,635,150.00
b = 1,90, h = 1,50 M' 81,221,750.00
b = 1,90, h = 2,00 M' 86,919,300.00
24 Pintu Sorong Baja (dua draad) stang
b = 2,00, h = 1,00 M' 77,805,600.00
b = 2,00, h = 1,50 M' 98,543,050.00
b = 2,00, h = 2,00 M' 105,659,250.00
Halaman 11
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
41 Water drain besi (floor drain) Bh 76,500.00
42 Water Turn 500 Lt (Penguin) Bh 1,657,500.00
43 Water Turn 1000 Lt (Penguin) Bh 2,461,600.00
44 Kran air Kw. 2 Bh 37,400.00
45 Kran air Kw. 1 Bh 86,700.00
46 Stop kran 3/4" Bh 39,100.00
47 Stop kran 1/2" Bh 34,850.00
48 Stop kran 1" Bh 79,050.00
49 Stop kran 2" Bh 158,950.00
50 Jet Pump 350 watt Bh 1,863,200.00
51 Mesin Pompa Shimizu PS 128 Non Otomatis (Sedot) Bh 425,000.00
52 Mesin Pompa Shimizu PS 135 Otomatis (Sedot) Bh 510,000.00
53 Mesin Pompa Shimizu PS 133 Otomatis (Dorong) Bh 700,000.00
54 Mesin Pompa Shimizu PS 228 Otomatis (Dorong) Bh 775,000.00
55 Mesin Summersible Shimizu 1/3 hp Bh 2,000,000.00
56 Mesin Summersible Shimizu 1/2 hp Bh 2,200,000.00
57 Mesin Summersible Shimizu 3/4 hp Bh 2,500,000.00
58 Mesin Summersible Shimizu 1 hp Bh 2,750,000.00
59 Mesin Summersible Shimizu 1 1/2 hp Bh 3,250,000.00
60 Mesin Summersible Kyodo 2 hp Bh 4,500,000.00
61 Pintu Vynil KM/WC ( 190 x 70 ) Cm kw1 Unit 355,300.00
62 Pintu Vynil serat jati KM/WC ( 190 x 70 ) Cm kw1 Unit 544,850.00
63 Seal tape Bh 3,400.00
64 Floor drain plastik Bh 11,050.00
65 Floor drain alumunium Bh 146,200.00
66 Grefel beton d. 20 cm (Pjg. 1 M) Bh 56,950.00
67 Grefel beton d. 30 cm (Pjg. 1 M) Bh 77,350.00
68 Paving block warna 6 cm ( 50 Bh ) M2 63,750.00
69 Paving block warna 8 cm ( 50 Bh ) M2 72,250.00
70 Paving block natural 6 cm ( 50 Bh ) M2 56,100.00
71 Paving block natural 8 cm ( 50 Bh ) M2 66,300.00
72 Paving Ton natural uk. 20 x 10 t. 6 cm (50 Bh) M2 94,000.00
73 Paving Ton natural uk. 20 x 10 t. 8 cm (50 Bh) M2 105,000.00
74 Paving Ton warna uk. 20 x 10 t. 6 cm (50 Bh) M2 105,000.00
75 Paving Ton warna uk. 20 x 10 t. 8 cm (50 Bh) M2 116,000.00
76 Paving ton Truepave uk. 20 x 10 t. 6 cm (50 Bh) Ex CISANGKAN M2 221,850.00
77 Paving ton Truepave uk. 20 x 10 t. 8 cm (50 Bh) Ex CISANGKAN M2 259,250.00
78 Paving ton Truepave uk. 20 x 10 t. 10 cm (50 Bh) M2 334,900.00
79 Paving ton Halfpave uk. 10 x 10 t. 6 cm (100 Bh) M2 215,900.00
80 Paving ton Halfpave uk. 10 x 10 t. 8 cm (100 Bh) M2 250,750.00
81 Paving ton Fullpave uk. 20 x 20 t. 6 cm (25 Bh) M2 228,650.00
82 Paving ton Fullpave uk. 20 x 20 t. 8 cm (25 Bh) M2 272,850.00
83 Paving ton Topi Uskup uk. 28x20x10 cm t. 6 cm (20 Bh) M2 220,150.00
84 Paving ton Topi Uskup uk. 28x20x10 cm t. 8 cm (20 Bh) M2 250,750.00
85 Paving ton Intepave uk. 20 x 10 cm t. 6 cm (50 Bh) M2 163,200.00
86 Paving ton Intepave uk. 20 x 10 cm t. 8 cm (50 Bh) M2 187,850.00
87 Paving ton Clasic Set t. 6 cm M2 259,250.00
88 Paving ton Clasic Set t. 8 cm M2 296,650.00
89 Paving ton Altstadt Set t. 6 cm M2 259,250.00
90 Paving ton Altstadt Set t. 8 cm M2 296,650.00
91 Paving ton Hexagon t. 6 cm M2 163,200.00
92 Paving ton Hexagon t. 8 cm M2 187,850.00
93 Paving ton Octagon t. 6 cm M2 237,150.00
94 Paving ton Octagon t. 8 cm M2 276,250.00
Halaman 12
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
95 Paving ton Natural t. 10 cm M2 268,600.00
96 Paving ton Kubus uk. 8 x 8 cm t. 6 cm (156 Bh) M2 232,050.00
97 Paving ton Kubus uk. 8 x 8 cm t. 8 cm (156 Bh) M2 277,950.00
98 Paving ton Quatro uk. 10 x 20 cm t. 6 cm (50 Bh) M2 222,700.00
99 Paving ton Quatro uk. 10 x 20 cm t. 8 cm (50 Bh) M2 269,450.00
100 Grassblock ton uk. 45 x 30 cm t. 6 (7,5 Bh) M2 154,700.00
101 Grassblock ton uk. 40 x 40 cm t. 8 (6,25 Bh) M2 177,650.00
102 Grassblock ton uk. 45 x 30 cm t. 10 (7,5 Bh) M2 248,200.00
103 Bataton U 14FS uk. 29 x 14 x 14 cm M' 15,300.00
104 Bataton U 14HS uk. 14 x 14 x 14 cm M' 20,400.00
105 Bataton H 14FS uk. 29 x 14 x 14 cm M2 130,900.00
106 Bataton H 14HS uk. 14 x 14 x 14 cm M2 135,150.00
107 Bataton H 10FS uk. 29 x 10 x 14 cm M2 109,650.00
108 Bataton H 10HS uk. 29 x 10 x 14 cm M2 114,750.00
109 Bataton Kolom uk. 29 x 29 x 14 cm M' 72,250.00
110 Curve Tile uk. 50 x 30 cm M2 72,250.00
111 Kusen Pintu uk. 200 x 90 x 14 cm Bh 375,700.00
112 Kusen Pintu WC uk. 200 x 75 x 14 cm Bh 343,400.00
113 Kusen Jendela uk. 120 x 75 x 14 cm Bh 318,750.00
114 Kusen Jendela Double uk. 150 x 120 x 14 cm Bh 500,650.00
115 Kusen Jendela Minimalis uk. 120 x 60 x 14 Bh 318,750.00
116 Kusen Jendela Minimalis uk. 165 x 60 x 14 Bh 343,400.00
117 Kusen Pintu Double uk. 210 x 160 x 14 cm Bh 563,550.00
118 Support Beam 300 cm (Balok Penyangga) uk. 300x10x6 Bh 532,950.00
119 Support Beam 180 cm (Balok Penyangga) uk. 180x10x6 Bh 517,650.00
120 Support Beam 165 cm (Balok Penyangga) uk. 165x10x6 Bh 328,950.00
121 Support Beam 150 cm (Balok Penyangga) uk. 150x10x6 Bh 306,000.00
122 Kansteen Beton (Uk. 60 x 30 cm) profil Bh 75,650.00
123 Kansteen Beton (Uk. 50 x 25 cm) t. 10 cm Bh 37,400.00
124 Kansteen K.03.1 (15.18.40) Bh 41,650.00
125 Kansteen K.03.2 (15.18.20) Bh 25,500.00
126 Kansteen K.03.3 (15.18.40) Bh 41,650.00
127 Kansteen K.04.2 (15.28.60) Bh 72,250.00
128 Kansteen K.04.2 (15.28.20) Bh 47,600.00
129 Kansteen K.04.3 (15.28.60) Bh 76,500.00
130 U-Ditch 300 x 300 Bh 385,050.00
131 U-Ditch 300 x 400 Bh 428,400.00
132 U-Ditch 400 x 400 Bh 546,550.00
133 U-Ditch 400 x 500 Bh 629,000.00
134 U-Ditch 400 x 600 Bh 670,650.00
135 U-Ditch 500 x 500 Bh 729,300.00
136 U-Ditch 500 x 600 Bh 827,900.00
137 U-Ditch 500 x 700 Bh 959,650.00
138 U-Ditch 600 x 600 Bh 939,250.00
139 U-Ditch 600 x 700 Bh 1,015,750.00
140 U-Ditch 600 x 700 x 1200 Bh 677,000.00
141 U-Ditch 600 x 800 Bh 1,126,250.00
142 U-Ditch 800 x 800 Bh 1,537,650.00
143 U-Ditch 800 x 900 Bh 1,654,950.00
144 U-Ditch 800 x 1000 Bh 1,805,400.00
145 U-Ditch 1000 x 1000 x 1200 Bh 2,584,000.00
146 U-Ditch 2000 x 2000 Bh 8,085,200.00
147 Tutup U-Ditch Light Duty CUD 300 LD Bh 147,900.00
148 Tutup U-Ditch Light Duty CUD 400 LD Bh 183,600.00
Halaman 13
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
149 Tutup U-Ditch Light Duty CUD 500 LD Bh 222,700.00
150 Tutup U-Ditch Light Duty CUD 600 LD Bh 257,550.00
151 Tutup U-Ditch Light Duty CUD 800 LD Bh 328,950.00
152 Tutup U-Ditch Heavy Duty CUD 300 LD Bh 246,500.00
153 Tutup U-Ditch Heavy Duty CUD 400 LD Bh 314,500.00
154 Tutup U-Ditch Heavy Duty CUD 500 LD Bh 375,700.00
155 Tutup U-Ditch Heavy Duty CUD 600 LD Bh 458,150.00
156 Tutup U-Ditch Heavy Duty CUD 800 LD Bh 611,150.00
157 Box Culvert 400 x 400 x 1000 Bh 1,031,900.00
158 Box Culvert 500 x 500 x 1000 Bh 1,320,900.00
159 Box Culvert 600 x 600 x 1000 Bh 1,685,550.00
160 Box Culvert 800 x 800 x 1000 Bh 2,599,300.00
161 Box Culvert 800 x 800 x 1200 Bh 4,516,050.00
162 Box Culvert 1000 x 1000 x 1000 Bh 3,715,350.00
163 Box Culvert 1000 x 1000 x 1200 Bh 5,504,600.00
164 Box Culvert 1200 x 1200 x 1000 Bh 5,247,050.00
165 Box Culvert 1500 x 1500 x 1000 Bh 8,147,250.00
166 Box Culvert 1500 x 1500 x 1200 Bh 12,031,750.00
167 Box Culvert 1800 x 1800 x 1000 Bh 9,793,700.00
168 Box Culvert 2000 x 1000 x 1000 Bh 10,818,800.00
169 Box Culvert 2000 x 2000 x 1000 Bh 13,250,650.00
170 Buis beton D. 20 (Pjg. 1 M, T= 3.5 Cm) Bh 94,350.00
171 Buis beton D. 30 (Pjg. 1 M, T= 3.5 Cm) Bh 130,050.00
172 Buis beton D. 40 (Pjg. 1 M, T= 5 Cm) Bh 195,500.00
173 Buis beton D. 50 (Pjg. 1 M, T= 8 Cm) Bh 231,200.00
174 Buis beton D. 60 (Pjg. 1 M, T= 8 Cm) Bh 311,950.00
175 Buis beton D. 70 (Pjg. 1 M, T= 8 Cm) Bh 193,800.00
176 Buis beton D. 60 (Pjg. 0,5 M, T= 8 Cm) Bh 171,700.00
177 Buis beton D. 80 (Pjg. 0,5 M, T= 8 Cm) Bh 273,700.00
178 Buis beton D. 100 (Pjg. 0,5 M, T=10 Cm) Bh 325,550.00
179 Waterstop PVC 150 mm m' 75,900.00
180 Waterstop PVC 200 mm m' 99,000.00
181 Roof drain plastik 4" Bh 19,800.00
182 Roof drain besi 4" Bh 77,000.00
Halaman 14
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
19 Plafond PVC Shunda Plafon Polos, L. 30 cm M2 90,000.00
20 Plafond PVC Shunda Plafon Motif, L. 30 cm M2 93,300.00
21 Plafond PVC Shunda Plafon Coklat, L. 30 cm M2 96,700.00
22 Plafond PVC Shunda Plafon Coklat Urat Jati, L. 30 cm M2 150,000.00
23 List Plafon PVC, L. 4 cm Putih M' 20,000.00
24 List Plafon PVC, L. 4 cm Coklat M' 22,000.00
25 List Plafon PVC, L. 7 cm M' 23,000.00
26 Asbes gelombang besar 5 mm 105 x 150 Lbr 79,900.00
27 Asbes gelombang besar 5 mm 105 x 300 Lbr 126,650.00
28 Asbes gelombang kecil 4 mm 105 x 150 Lbr 58,650.00
29 Asbes gelombang kecil 4 mm 80 x 150 Lbr 41,650.00
30 Asbes gelombang kecil 4 mm 80 x 180 Lbr 39,100.00
31 Asbes gelombang kecil 4 mm 80 x 210 Lbr 52,700.00
32 Asbes gelombang kecil 4 mm 80 x 240 Lbr 58,650.00
33 Asbes gelombang kecil 4 mm 80 x 360 Lbr 72,250.00
34 Asbes gelombang kecil 4 mm 105 x 210 Lbr 68,850.00
35 Asbes gelombang kecil 4 mm 105 x 240 Lbr 79,900.00
36 Asbes gelombang kecil 4 mm 105 x 300 Lbr 87,550.00
37 Asbes gelombang kecil 4 mm 105 x 360 Lbr 107,950.00
38 Asbes gelombang 5 mm 92 x 250 Lbr 82,450.00
39 Asbes gelombang 4 mm 92 x 250 Lbr 80,750.00
40 Asbes gelombang 5 mm 92 x 225 Lbr 75,650.00
41 Asbes gelombang 4 mm 92 x 225 Lbr 71,400.00
42 Baja Ringan Zincallume t. 0,75 mm M2 173,400.00
43 Baja Ringan Zincallume t. 1,00 mm M2 187,000.00
44 Rangka Baja Ringan Zincallume C70 t. 0,7 mm (6 m) Btg 75,650.00
45 Rangka Baja Ringan Zincallume C70 t. 0,75 mm (6 m) Btg 85,850.00
46 Rangka Baja Ringan Zincallume C70 t. 0,8 mm (6 m) Btg 86,700.00
47 Rangka Baja Ringan Zincallume C75 t. 0,75 mm (6 m) setara Taso Btg 180,000.00
48 Rangka Baja Ringan Zincallume C75 t. 1 mm (6 m) setara Taso Btg 210,000.00
49 Rangka Baja Ringan Zincallume C75 t. 1 mm (6 m) setara Taso Btg 45,050.00
50 Reng Baja Ringan Zincallume t.0,65 mm (6 m) Btg 43,350.00
51 Reng Baja Ringan Zincallume t.0,75 mm (6 m) Btg 48,450.00
52 Genteng plentong kecil (bakar) Bh 1,700.00
53 Genteng plentong super (bakar) Bh 2,550.00
54 Genteng kodok Natural Bh 3,400.00
55 Genteng kodok Glazuur Bh 3,400.00
56 Genteng kodok / Alto transparant (brown) Bh 3,400.00
57 Genteng keramik morando natural Bh 3,400.00
58 Genteng keramik morando transparan Bh 3,400.00
59 Genteng keramik morando warna Bh 4,250.00
60 Genteng beton Natural Bh 5,100.00
61 Genteng beton (setara Cisangkan - Victoria) Bh 12,100.00
62 Genteng metal M2 136,000.00
63 Genteng metal pasir 2 x 4 M2 133,450.00
64 Genteng metal polos 2 x 4 M2 32,300.00
65 Genteng metal Multi Roof t. 0,4 mm M2 146,200.00
66 Genteng metal Multi Roof t. 0,3 mm M2 125,800.00
67 Genteng metal Multi Roof t. 25 mm M2 103,700.00
68 Genteng metal Sakura t. 0,25 mm M2 51,000.00
69 Genteng metal Sakura t. 0,3 mm M2 58,650.00
70 Genteng Tegola M2 345,950.00
71 Genteng Bitumen Gelombang Monolayer Uk.200x97x0.3 cm (Onduline) Lbr 199,000.00
72 Genteng Bitumen Gelombang Monolayer Uk.106x40x0.3 cm (Onduvila) Lbr 65,000.00
Halaman 15
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
73 Nok / Rigde Bitumen Lbr 87,550.00
74 Bubung genteng plentong kecil Bh 3,400.00
75 Bubung genteng plentong super Bh 5,100.00
76 Bubung genteng kodok / Alto natural Bh 5,100.00
77 Bubung genteng kodok / Alto transparan (brown) Bh 6,800.00
78 Bubung genteng morando natural Bh 5,950.00
79 Bubung genteng morando transparan Bh 6,800.00
80 Bubung genteng morando warna Bh 7,650.00
81 Bubung genteng beton natural Bh 5,950.00
82 Bubung genteng beton (setara Cisangkan) Bh 19,200.00
83 Bubung genteng metal (p.90 cm) Bh 56,100.00
84 Bubung genteng metal natural Type U (p.100 cm) Bh 33,150.00
85 Bubung genteng metal natural Type 1/2 Lingkaran (p.100 cm) Bh 54,400.00
86 Bubung genteng metal Warna Kotak (p.100 cm) Bh 28,050.00
87 Bubung genteng metal Warna Type 1/2 Lingkaran (p.100 cm) Bh 43,350.00
88 Genteng decra bond M' 48,450.00
89 Nok stel gelombang M' 45,050.00
90 Seng gelombang BJLS 28 (80 x 180) Lbr 56,100.00
91 Seng gelombang BJLS 30 (80 x 180) Lbr 71,400.00
92 Seng Plat BJLS 28 Lbr 53,550.00
93 Seng Plat BJLS L. 90 Cm M' 37,400.00
94 Seng Plat BJLS L. 75 Cm M' 29,750.00
95 Seng Plat BJLS L. 60 Cm M' 28,050.00
96 Seng Plat BJLS L. 55 Cm M' 22,950.00
97 Seng Plat BJLS L. 45 Cm M' 13,600.00
Halaman 16
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
28 Granit tile 60 x 60 cm (Kasar) (setara indogress) M2 325,550.00
29 Granit tile 60 x 60 cm (Black) M2 442,850.00
30 Granit tile 3D 60 x 60 cm M2 378,250.00
31 Granit tile 80 x 80 cm M2 431,800.00
32 Granit tile 80 x 80 cm (setara indogress) M2 294,950.00
33 Granit tile 80 x 80 cm (setara Marco) M2 282,200.00
34 Granit tile 120 x 60 cm (Halus) M2 784,000.00
35 Granit tile 120 x 60 cm (Halus) (setara indogress) M2 650,000.00
36 Granit tile 120 x 60 cm (Halus) (setara Ex. Cina) M2 350,000.00
37 Granit slab (Batu) DN M2 1,649,850.00
38 Marmer Uk. 1 x 1 m M2 1,517,250.00
39 Stepnose 10 x 30 cm / anti slip Bh 20,400.00
40 Stepnose 10 x 40 cm / anti slip Bh 31,450.00
41 Stepnose 10 x 60 cm / anti slip Bh 52,700.00
42 Kuku Macan Polos M' 7,480.00
43 Kuku Macan Spiral M' 8,415.00
44 Tegel Badak Natural 20 x 20 cm Bh 3,400.00
45 Tegel Badak Natural 30 x 30 cm Bh 4,250.00
46 Tegel Badak Warna 20 x 20 cm Bh 4,250.00
47 Tegel Badak Warna 30 x 30 cm Bh 6,800.00
48 Tegel Cor Beton press warna alami uk. 20 x 20 cm M2 21,250.00
49 Tegel Cor Beton press warna alami uk. 30 x 30 cm M2 26,350.00
50 Parquet jati M2 238,850.00
51 Lantai Vynil Daichi Uk. 15 x 90 cm M2 233,000.00
52 Lantai Vynil Taco Uk. 15 x 90 cm M2 200,000.00
53 Wall paper M2 66,300.00
54 Wall paper Sticker Kertasive (Polos) M2 65,000.00
55 Wall paper Sticker Kertasive (Urat Kayu) M2 67,000.00
56 PVC Penutup Dinding Uk. 0,2 x 3 m M2 200,000.00
57 Roster Terawang 10 x 20 Bh 14,450.00
58 Roster Terawang 20 x 20 Bh 15,300.00
59 Roster Beton 20 x 20 Bh 22,100.00
60 Roster Kayu uk. 15 x 30 Bh 28,900.00
61 Roster Kayu uk. 20 x 20 Bh 28,900.00
62 Roster Genteng uk. 10 x 20 Bh 5,950.00
63 Roster Batu alam uk.15 x 15 Bh 68,850.00
64 Roster Batu alam uk. 30 x 30 Bh 101,150.00
65 Roster Batu alam uk. 20 x 50 Bh 154,700.00
66 Melati Beton Bh 106,250.00
67 Conblock Regular Full 15.01 Bh 14,450.00
68 Bataton U 14FS uk. 29 x 14 x 14 cm M' 12,750.00
69 Bataton U 14HS uk. 14 x 14 x 14 cm M' 16,150.00
70 Bataton H 14FS uk. 29 x 14 x 14 cm M2 124,950.00
Batu Andesit Alur Polos
71 Ukuran 10 x 20 M2 124,950.00
72 Ukuran 10 x 30 M2 127,500.00
73 Ukuran 15 x 30 M2 144,500.00
74 Ukuran 20 x 40 M2 144,500.00
Batu Andesit Alur Motif
75 Ukuran 10 x 20 M2 96,900.00
76 Ukuran 15 x 30 M2 118,150.00
77 Ukuran 20 x 40 M2 161,500.00
Batu Andesit Bakar Polos tebal 1.2 - 1.3 cm
78 Ukuran 10 x 20 M2 121,550.00
Halaman 17
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
79 Ukuran 10 x 30 M2 129,200.00
80 Ukuran 15 x 30 M2 144,500.00
81 Ukuran 15 x 15 M2 142,800.00
82 Ukuran 20 x 30 M2 161,500.00
83 Ukuran 20 x 20 M2 144,500.00
84 Ukuran 20 x 40 M2 101,150.00
85 Ukuran 30 x 30 M2 170,000.00
86 Ukuran 30 x 60 M2 182,750.00
87 Ukuran 40 x 40 M2 123,250.00
Batu Andesit Bakar Bintik
88 Ukuran 10 x 20 M2 79,900.00
89 Ukuran 10 x 30 M2 90,950.00
90 Ukuran 15 x 30 M2 107,100.00
91 Ukuran 15 x 15 M2 107,100.00
92 Ukuran 30 x 30 M2 123,250.00
Batu Andesit Bakar tebal. 5 cm
93 Ukuran 10 x 10 M2 237,150.00
94 Ukuran 15 x 15 M2 334,900.00
95 Ukuran 15 x 30 M2 334,900.00
96 Ukuran 20 x 20 M2 334,900.00
97 Ukuran 20 x 40 M2 353,600.00
98 Ukuran 30 x 30 M2 372,300.00
Batu Andesit Bakar tebal. 3 cm
99 Ukuran 10 x 10 M2 175,950.00
100 Ukuran 15 x 15 M2 249,900.00
101 Ukuran 15 x 30 M2 249,900.00
102 Ukuran 20 x 20 M2 249,900.00
103 Ukuran 30 x 30 M2 273,700.00
Batu Templek
104 Acak Purwakarta M2 90,100.00
105 Ukuran 10 x 20 M2 90,100.00
106 Ukuran 10 x 30 M2 97,750.00
107 Ukuran 15 x 30 M2 103,700.00
108 Ukuran 20 x 40 M2 156,400.00
109 Ukuran 30 x 30 M2 158,950.00
Batu Bobos Palimanan Corak/Palem
110 Ukuran 10 x 20 M2 63,750.00
111 Ukuran 20 x 20 M2 63,750.00
112 Ukuran 20 x 30 M2 75,650.00
113 Ukuran 20 x 40 M2 79,900.00
114 Ukuran 15 x 30 M2 69,700.00
Batu Bobos Palimanan Putih (RTM)
115 Ukuran 10 x 20 M2 104,550.00
116 Ukuran 15 x 30 M2 101,150.00
Batu Andesit Susun Sirih
117 Ukuran 3 x 20 M2 122,400.00
118 Ukuran 3 x 30 M2 133,450.00
119 Ukuran 3 x 40 M2 149,600.00
120 Ukuran 3 x 50 M2 144,500.00
121 Ukuran 5 x 30 M2 69,700.00
122 Ukuran 5 x 40 M2 85,850.00
Batu Alam Profil
123 Ukuran 5 x 30 M2 90,950.00
124 Ukuran 3 x 50 M2 49,300.00
Halaman 18
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
125 Ukuran 4 x 50 M2 49,300.00
126 Ukuran 5 x 50 M2 75,650.00
127 Ukuran 3 x 40 M2 57,800.00
128 Ukuran 4 x 40 M2 70,550.00
129 Ukuran 5 x 40 M2 77,350.00
Batu Candi Muntilan
130 Ukuran 10 x 20 M2 96,900.00
131 Ukuran 15 x 30 M2 103,700.00
132 Ukuran 20 x 40 M2 108,800.00
Koral
133 Koral Pancawarna M2 96,900.00
134 Koral bengkulu hitam M2 96,900.00
135 Koral Flores hijau M2 96,900.00
136 Koral Orange Bali M2 96,900.00
137 Koral Hitam Garut M2 96,900.00
138 Batu Sikat M2 96,900.00
Basaltu Bandung
139 Ukuran 10 x 20 M2 192,950.00
140 Ukuran 10 x 30 M2 204,000.00
141 Ukuran 15 x 30 M2 215,050.00
142 Ukuran 20 x 40 M2 226,100.00
143 Ukuran 30 x 60 M2 247,350.00
Batu Curi Subang
144 Ukuran 10 x 20 M2 96,900.00
145 Ukuran 10 x 30 M2 101,150.00
146 Ukuran 15 x 30 M2 113,050.00
147 Ukuran 20 x 40 M2 118,150.00
148 Ukuran 30 x 30 M2 128,350.00
149 Ukuran 30 x 60 M2 150,450.00
Batu Bilik Gelombang
150 Ukuran 15 x 30 M2 113,050.00
Prasasti
151 Marmer Uk. 30 x 60 cm M2 900,000.00
152 Marmer Uk. 60 x 90 cm M2 1,400,000.00
153 Granite Hitam Uk. 30 x 60 cm M2 1,100,000.00
154 Granite Hitam Uk. 60 x 90 cm M2 1,600,000.00
G BAHAN KACA
1 Kaca polos 3 mm M2 90,950.00
2 Kaca polos 5 mm M2 134,300.00
3 Kaca polos 8 mm M2 135,150.00
4 Kaca polos 10 mm M2 227,800.00
5 Kaca polos 12 mm M2 512,550.00
6 Kaca rayband 3 mm M2 109,650.00
7 Kaca rayband 5 mm M2 163,200.00
8 Kaca Tempered 8 mm M2 514,250.00
9 Kaca Tempered 10 mm M2 703,800.00
10 Kaca Tempered 12 mm M2 810,900.00
11 Kaca Patri M2 2,795,650.00
12 Kaca Es t. 5 mm M2 158,950.00
13 Kaca Es random t. 5 mm M2 193,800.00
14 Kaca Pasta M2 500,650.00
15 Kaca Grafir t. 8 mm M2 1,612,450.00
16 Kaca Grafir corak t. 5 mm M2 1,815,600.00
Halaman 19
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
17 Glass Block 20 x 20 cm Bh 24,650.00
18 Jendela naco + Rangka Daun 57,800.00
19 Pintu besi M2 289,850.00
20 Jendela besi / tralis M2 236,300.00
21 Sekrup Kg 23,800.00
22 Sealant Besar Tube 38,000.00
23 Sealant Kecil Tube 12,750.00
24 Cermin t. 5 mm M2 300,000.00
25 Kaca One way t. 5 mm M2 650,000.00
26 Kaca Bevel t. 3 cm M' 25,000.00
27 Kaca Bevel t. 2 cm M' 20,000.00
28 Sandblast Kaca M2 50,000.00
Halaman 20
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
41 Cat Duco Kg 91,800.00
42 Meni Besi Zingchromate Kg 58,650.00
43 Cat Besi Pollyurethane Kg 85,850.00
Halaman 21
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
11 Lampu TL 2 x 20 watt + kap (setara Phillip ) Bh 376,550.00
12 Lampu TL 2 x 36 watt + kap (setara Phillip ) Inbow Bh 483,650.00
13 Lampu TL 1 x 20 watt + kap (setara Phillip) Bh 125,800.00
14 Lampu TL 2 x 40 watt + kap (setara Phillip) Bh 483,650.00
15 Lampu TL 1 x 40 watt + kap (setara Phillip) Bh 147,900.00
16 Lampu pijar 40 watt (Setara Philip) Bh 12,750.00
17 Lampu tembak 150 watt + kap (Metal Holide) (setara Phillip) Bh 130,900.00
18 Lampu tembak 300 watt + kap (setara Phillip) Bh 215,050.00
19 Lampu tembak 50 watt (LED Putih) (setara Phillip) Bh 323,850.00
20 Lampu tembak 80 watt (LED Putih) (setara Phillip) Bh 376,550.00
21 Lampu tembak 1000 watt (LED Putih) (setara Phillip) Bh 484,500.00
22 Lampu Spiral 5 watt (setara Phillip) Bh 42,500.00
23 Lampu Spiral 8 watt (setara Phillip) Bh 44,200.00
24 Lampu Jari 5 watt (setara Phillip) Bh 29,750.00
25 Lampu Jari 8 watt (setara Phillip) Bh 34,000.00
26 Lampu LED 4 watt (setara Phillip) Bh 35,700.00
27 Lampu LED 5 watt (setara Phillip) Bh 63,750.00
28 Lampu LED 7 watt (setara Phillip) Bh 49,300.00
29 Lampu LED 9 watt (setara Phillip) Bh 60,350.00
30 Lampu LED 10 watt (setara Phillip) Bh 65,450.00
31 Lampu LED 13 watt (setara Phillip) Bh 70,550.00
32 TL. 1 x 40 W Phillip Bh 140,250.00
33 TL. 2 x 40 W Phillip Bh 221,850.00
34 TL. 1 x 20 W Phillip Bh 138,550.00
35 TL. 2 x 20 W Phillip Bh 165,750.00
36 TL. 2 x 20 W RM Bh 322,150.00
37 TL. 2 x 40 W RM Bh 451,350.00
38 Lampu Taman Bh 150,450.00
39 Armatur Lampu Baret Bh 268,600.00
40 Dudukan Downlight Stainlesstell 4" Bh 57,800.00
41 Kabel NYY 3 x 4 mm setara Supreme M' 35,700.00
42 Kabel NYY 4 x 6 mm setara Supreme M' 63,750.00
43 Kabel NYY 3 x 2,5 mm setara Supreme M' 21,250.00
44 Kabel NYY 3 x 1,5 mm setara Supreme M' 15,300.00
45 Kabel NYY 2 x 2,5 mm setara Supreme M' 17,000.00
46 Kabel NYY 2 x 1,5 mm setara Supreme M' 12,750.00
47 Kawat BC 25 mm M' 34,850.00
48 Kawat BC 16 mm M' 26,350.00
49 Kawat BC 6 mm M' 11,050.00
50 Kap Gembreng Bh 32,300.00
51 Down Light 8" Bh 113,050.00
52 Down Light 6" Bh 93,500.00
53 Down Light 4" Bh 72,250.00
54 Down Light 3" Bh 56,950.00
55 Down Light Outbow bulat 3" Bh 88,400.00
56 Down Light Outbow bulat 3,5" Bh 128,350.00
57 Down Light Outbow bulat 4" Bh 161,500.00
58 Down Light Outbow bulat 5" Bh 175,950.00
59 Down Light Outbow kotak 4" Bh 159,800.00
60 Fitting Plafond kotak Bh 15,300.00
61 Photocell 6 A Bh 178,500.00
62 MCB 1 phase 6 A Bh 69,700.00
63 Box MCB Uk. 40 x 50 cm + Dudukan Bh 405,450.00
64 Besi Arde (crum tembaga /2,40 m) Btg 128,350.00
65 Besi Arde (crum tembaga / 2 m) Btg 59,500.00
66 Besi Arde (crum tembaga / 1,5 m) Btg 33,150.00
Halaman 22
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
L ALAT BANTU
1 Cangkul atau sekop Bh 80,750.00
2 Parang Bh 69,700.00
3 Pikulan dan 2 Bakul Bh 48,450.00
4 Palu / Godam Pemecah Batu Bh 48,450.00
5 Stamper 250 Kg Hari 250,000.00
KEPALA DINAS
NAMA JABATAN PARAF TANGGAL
PEKERJAAN UMUM DAN PENATAAN RUANG
M. KRISDIANTORO, ST., M.Si. Kepala Bidang Bangunan KABUPATEN INDRAMAYU
NIP. 19710911 200212 1 003 dan Bina Konstruksi
Halaman 23
PEMERINTAH KABUPATEN INDRAMAYU
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jl. Pahlawan No. 61 Telp. (0234) 274264 Fax (0234) 272741
I N D R A M A Y U - 45212
BIAYA
SEWA
No. URAIAN KODE HP KAP.
ALAT/JAM
(di luar PPN)
KET.
KET.
zona 1
Februari 2022
LA DINAS
DAN PENATAAN RUANG
N INDRAMAYU
22 200501 1 005
PEMERINTAH KABUPATEN INDRAMAYU
DINAS PEKERJAAN UMUM DAN PENATAAN RUA
Jl. Pahlawan No. 61 Telp. (0234) 274264 Fax (0234) 272741
I N D R A M A Y U - 45212
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
A.1 DIBULATKAN 23,759.00
Halaman 28
1 2 3 4 5 6 = (3 x 5)
JUMLAH 36,010.00
OVERHEAD & PROFIT (15 %) 5,401.50
HARGA SATUAN PEKERJAAN 41,411.50
A.2 DIBULATKAN 41,411.50
JUMLAH 521,000.00
OVERHEAD & PROFIT (15 %) 78,150.00
HARGA SATUAN PEKERJAAN 599,150.00
A.3 DIBULATKAN 599,150.00
A.4 1 M' PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER
BAHAN
Seng Gelombang BJLS 28 (80 x 180 cm) 1.2000 Lbr 71,400.00 -
Kayu Dolken d. 8 - 10 P. 4 M 1.2500 Btg 65,450.00 -
Kayu Kaso 5/7 ( Borneo ) 0.0720 M3 4,335,000.00 -
Semen portland 2.5000 Kg 1,275.00 -
Pasir Beton 0.0050 M3 296,650.00 -
Koral Beton 0.0090 M3 292,400.00 -
Meni Besi 0.4500 Kg 58,650.00 -
Paku Biasa 5" - 7" 0.7200 Kg 18,700.00 -
UPAH
Halaman 29
1 2 3 4 5 6 = (3 x 5)
Pekerja 0.2000 OH 79,000.00 15,800.00
Tukang Kayu 0.4000 OH 110,000.00 44,000.00
Kepala Tukang 0.0200 OH 112,000.00 2,240.00
Mandor 0.0200 OH 128,000.00 2,560.00
ALAT
JUMLAH 64,600.00
OVERHEAD & PROFIT (15 %) 9,690.00
HARGA SATUAN PEKERJAAN 74,290.00
A.4 DIBULATKAN 74,290.00
JUMLAH 55,000.00
OVERHEAD & PROFIT (15 %) 8,250.00
HARGA SATUAN PEKERJAAN 63,250.00
A.5 DIBULATKAN 63,250.00
Halaman 30
1 2 3 4 5 6 = (3 x 5)
JUMLAH 327,800.00
OVERHEAD & PROFIT (15 %) 49,170.00
HARGA SATUAN PEKERJAAN 376,970.00
A.7 DIBULATKAN 376,970.00
JUMLAH 101,300.00
OVERHEAD & PROFIT (15 %) 15,195.00
HARGA SATUAN PEKERJAAN 116,495.00
A.8 DIBULATKAN 116,495.00
JUMLAH 36,360.00
OVERHEAD & PROFIT (15 %) 5,454.00
HARGA SATUAN PEKERJAAN 41,814.00
A.9 DIBULATKAN 41,814.00
Halaman 31
1 2 3 4 5 6 = (3 x 5)
JUMLAH 1,152.80
OVERHEAD & PROFIT (15 %) 172.92
HARGA SATUAN PEKERJAAN 1,325.72
A.10 DIBULATKAN 1,325.72
JUMLAH 58,426.00
OVERHEAD & PROFIT (15 %) 8,763.90
HARGA SATUAN PEKERJAAN 67,189.90
A.11 DIBULATKAN 67,189.90
JUMLAH 1,138,634.00
OVERHEAD & PROFIT (15 %) 170,795.10
HARGA SATUAN PEKERJAAN 1,309,429.10
A.12 DIBULATKAN 1,309,429.10
JUMLAH 569,317.00
OVERHEAD & PROFIT (15 %) 85,397.55
HARGA SATUAN PEKERJAAN 654,714.55
A.13 DIBULATKAN 654,714.55
B PEKERJAAN TANAH
Halaman 32
1 2 3 4 5 6 = (3 x 5)
B.1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER
UPAH
Pekerja 0.7500 Org 79,000.00 59,250.00
Mandor 0.0250 Org 128,000.00 3,200.00
ALAT
JUMLAH 62,450.00
OVERHEAD & PROFIT (15 %) 9,367.50
HARGA SATUAN PEKERJAAN 71,817.50
B.1 DIBULATKAN 71,817.50
JUMLAH 76,860.00
OVERHEAD & PROFIT (15 %) 11,529.00
HARGA SATUAN PEKERJAAN 88,389.00
B.2 DIBULATKAN 88,389.00
JUMLAH 67,409.00
OVERHEAD & PROFIT (15 %) 10,111.35
HARGA SATUAN PEKERJAAN 77,520.35
B.3 DIBULATKAN 77,520.35
JUMLAH 83,096.00
OVERHEAD & PROFIT (15 %) 12,464.40
HARGA SATUAN PEKERJAAN 95,560.40
B.4 DIBULATKAN 95,560.40
Halaman 33
1 2 3 4 5 6 = (3 x 5)
Pekerja 1.5000 Org 79,000.00 118,500.00
Mandor 0.0600 Org 128,000.00 7,680.00
ALAT
JUMLAH 126,180.00
OVERHEAD & PROFIT (15 %) 18,927.00
HARGA SATUAN PEKERJAAN 145,107.00
B.5 DIBULATKAN 145,107.00
JUMLAH 100,560.00
OVERHEAD & PROFIT (15 %) 15,084.00
HARGA SATUAN PEKERJAAN 115,644.00
B.6 DIBULATKAN 115,644.00
JUMLAH 4,590.00
OVERHEAD & PROFIT (15 %) 688.50
HARGA SATUAN PEKERJAAN 5,278.50
B.7 DIBULATKAN 5,278.50
JUMLAH 27,350.00
OVERHEAD & PROFIT (15 %) 4,102.50
HARGA SATUAN PEKERJAAN 31,452.50
B.8 DIBULATKAN 31,452.50
Halaman 34
1 2 3 4 5 6 = (3 x 5)
ALAT
JUMLAH 45,900.00
OVERHEAD & PROFIT (15 %) 6,885.00
HARGA SATUAN PEKERJAAN 52,785.00
B.9 DIBULATKAN 52,785.00
JUMLAH 24,980.00
OVERHEAD & PROFIT (15 %) 3,747.00
HARGA SATUAN PEKERJAAN 28,727.00
B.11 DIBULATKAN 28,727.00
JUMLAH 24,980.00
OVERHEAD & PROFIT (15 %) 3,747.00
HARGA SATUAN PEKERJAAN 28,727.00
B.12 DIBULATKAN 28,727.00
Halaman 35
1 2 3 4 5 6 = (3 x 5)
Tanah Merah 1.2000 M3 200,600.00 -
UPAH
Pekerja 0.3000 Org 79,000.00 23,700.00
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
JUMLAH 24,980.00
OVERHEAD & PROFIT (15 %) 3,747.00
HARGA SATUAN PEKERJAAN 28,727.00
B.13 DIBULATKAN 28,727.00
JUMLAH 22,950.00
OVERHEAD & PROFIT (15 %) 3,442.50
HARGA SATUAN PEKERJAAN 26,392.50
B.14 DIBULATKAN 26,392.50
JUMLAH 22,950.00
OVERHEAD & PROFIT (15 %) 3,442.50
HARGA SATUAN PEKERJAAN 26,392.50
B.15 DIBULATKAN 26,392.50
Halaman 36
1 2 3 4 5 6 = (3 x 5)
JUMLAH 79,640.00
OVERHEAD & PROFIT (15 %) 11,946.00
HARGA SATUAN PEKERJAAN 91,586.00
B.16 DIBULATKAN 91,586.00
C PEKERJAAN PONDASI
C.1 1 M3 PASANG PONDASI BATU KALI 1 Pc : 2 Ps
BAHAN
Batu Belah 15 cm / 20 cm 1.2000 M3 286,450.00 -
Semen Portland 267.0000 Kg 1,275.00 -
Pasir Pasang 0.4270 M3 261,800.00 -
UPAH
Pekerja 1.5000 Org 79,000.00 118,500.00
Tukang Batu 0.7500 Org 103,000.00 77,250.00
Kepala Tukang 0.0750 Org 112,000.00 8,400.00
Mandor 0.0750 Org 128,000.00 9,600.00
ALAT
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.1 DIBULATKAN 245,812.50
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.2 DIBULATKAN 245,812.50
Halaman 37
1 2 3 4 5 6 = (3 x 5)
Pasir Pasang 0.5200 M3 261,800.00 -
UPAH
Pekerja 1.5000 Org 79,000.00 118,500.00
Tukang Batu 0.7500 Org 103,000.00 77,250.00
Kepala Tukang 0.0750 Org 112,000.00 8,400.00
Mandor 0.0750 Org 128,000.00 9,600.00
ALAT
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.3 DIBULATKAN 245,812.50
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.4 DIBULATKAN 245,812.50
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.5 DIBULATKAN 245,812.50
Halaman 38
1 2 3 4 5 6 = (3 x 5)
C.6 1 M3 PASANG PONDASI BATU LAMA 1 PC : 3 PS
BAHAN
Semen Portland 202.0000 Kg 1,275.00 -
Pasir Pasang 0.4850 M3 261,800.00 -
UPAH
Pekerja 1.5000 Org 79,000.00 118,500.00
Tukang Batu 0.7500 Org 103,000.00 77,250.00
Kepala Tukang 0.0750 Org 112,000.00 8,400.00
Mandor 0.0750 Org 128,000.00 9,600.00
ALAT
JUMLAH 213,750.00
OVERHEAD & PROFIT (15 %) 32,062.50
HARGA SATUAN PEKERJAAN 245,812.50
C.6 DIBULATKAN 245,812.50
JUMLAH 111,150.00
OVERHEAD & PROFIT (15 %) 16,672.50
HARGA SATUAN PEKERJAAN 127,822.50
C.7 DIBULATKAN 127,822.50
C.8 1 M3 PASANG PONDASI SIKLOP 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR DAN 40% BATU BELAH
BAHAN
Batu Belah 15 cm / 20 cm 0.4800 M3 286,450.00 -
Semen Portland 194.0000 Kg 1,275.00 -
Pasir Beton 0.3120 M3 296,650.00 -
Koral Beton 0.4680 M3 292,400.00 -
Besi Beton 126.0000 Kg 12,750.00 -
Kawat Beton 1.8000 Kg 30,600.00 -
UPAH
Pekerja 3.4000 Org 79,000.00 268,600.00
Tukang Batu 0.8500 Org 103,000.00 87,550.00
Kepala Tukang 0.0850 Org 112,000.00 9,520.00
Mandor 0.1700 Org 128,000.00 21,760.00
ALAT
Halaman 39
1 2 3 4 5 6 = (3 x 5)
JUMLAH 387,430.00
OVERHEAD & PROFIT (15 %) 58,114.50
HARGA SATUAN PEKERJAAN 445,544.50
C.8 DIBULATKAN 445,544.50
C.9 1 M' PENGEBORAN LUBANG BORED PILE DIA-20 CM PADA TANAH BIASA
BAHAN
UPAH
Pekerja 0.1064 Org 79,000.00 8,405.60
Tukang Bor 0.0266 Org 110,000.00 2,926.00
Mandor 0.0106 Org 128,000.00 1,356.80
ALAT
Stang bor, batang bor diameter 1 1/4" 0.0266 Hari 350,000.00 -
Bor Auger diameter 20 cm 0.0266 Hari 350,000.00 -
JUMLAH 12,688.40
OVERHEAD & PROFIT (15 %) 1,903.26
HARGA SATUAN PEKERJAAN 14,591.66
C.9 DIBULATKAN 14,591.66
JUMLAH 6,037.70
OVERHEAD & PROFIT (15 %) 905.66
HARGA SATUAN PEKERJAAN 6,943.36
C.10 DIBULATKAN 6,943.36
C.11 1 M' PENGEBORAN LUBANG BORED PILE DIA-30 CM PADA TANAH BIASA
BAHAN
UPAH
Pekerja 0.2400 Org 79,000.00 18,960.00
Tukang Bor 0.0600 Org 110,000.00 6,600.00
Mandor 0.0240 Org 128,000.00 3,072.00
Halaman 40
1 2 3 4 5 6 = (3 x 5)
ALAT
Stang bor, batang bor diameter 1 1/4" 0.0600 Hari 350,000.00 -
Bor Auger diameter 30 cm 0.0600 Hari 375,000.00 -
JUMLAH 28,632.00
OVERHEAD & PROFIT (15 %) 4,294.80
HARGA SATUAN PEKERJAAN 32,926.80
C.11 DIBULATKAN 32,926.80
JUMLAH 10,885.50
OVERHEAD & PROFIT (15 %) 1,632.83
HARGA SATUAN PEKERJAAN 12,518.33
C.12 DIBULATKAN 12,518.33
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
D.1 DIBULATKAN 42,596.00
Halaman 41
1 2 3 4 5 6 = (3 x 5)
Bata Merah 70.0000 Bh 935.00 -
Semen Portland 11.5000 Kg 1,275.00 -
Pasir Pasang 0.0430 M3 261,800.00 -
UPAH
Pekerja 0.3000 Org 79,000.00 23,700.00
Tukang Batu 0.1000 Org 103,000.00 10,300.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0150 Org 128,000.00 1,920.00
ALAT
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
D.2 DIBULATKAN 42,596.00
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
D.3 DIBULATKAN 42,596.00
JUMLAH 74,080.00
OVERHEAD & PROFIT (15 %) 11,112.00
Halaman 42
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 85,192.00
D.4 DIBULATKAN 85,192.00
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
D.5 DIBULATKAN 42,596.00
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
D.6 DIBULATKAN 42,596.00
Halaman 43
1 2 3 4 5 6 = (3 x 5)
ALAT
Alat Bantu 10.0000 % 137,370.25 -
JUMLAH 68,160.00
OVERHEAD & PROFIT (15 %) 10,224.00
HARGA SATUAN PEKERJAAN 78,384.00
D.7 DIBULATKAN 78,384.00
JUMLAH 68,239.00
OVERHEAD & PROFIT (15 %) 10,235.85
HARGA SATUAN PEKERJAAN 78,474.85
D.8 DIBULATKAN 78,474.85
JUMLAH 54,320.00
OVERHEAD & PROFIT (15 %) 8,148.00
HARGA SATUAN PEKERJAAN 62,468.00
D.9 DIBULATKAN 62,468.00
E PEKERJAAN PLESTERAN
E.1 1 M2 PLESTERAN, 1Pc : 3PP, TEBAL 20 mm
BAHAN
Halaman 44
1 2 3 4 5 6 = (3 x 5)
Semen Portland 10.3680 Kg 1,275.00 -
Pasir Pasang 0.0310 M3 261,800.00 -
UPAH
Pekerja 0.2600 Org 79,000.00 20,540.00
Tukang Batu 0.2000 Org 103,000.00 20,600.00
Kepala Tukang 0.0200 Org 112,000.00 2,240.00
Mandor 0.0130 Org 128,000.00 1,664.00
ALAT
JUMLAH 45,044.00
OVERHEAD & PROFIT (15 %) 6,756.60
HARGA SATUAN PEKERJAAN 51,800.60
E.1 DIBULATKAN 51,800.60
JUMLAH 57,256.00
OVERHEAD & PROFIT (15 %) 8,588.40
HARGA SATUAN PEKERJAAN 65,844.40
E.2 DIBULATKAN 65,844.40
JUMLAH 57,256.00
OVERHEAD & PROFIT (15 %) 8,588.40
HARGA SATUAN PEKERJAAN 65,844.40
E.3 DIBULATKAN 65,844.40
Halaman 45
1 2 3 4 5 6 = (3 x 5)
E.4 1 M2 PLESTERAN DINDING BATA RINGAN
BAHAN
Semen Plesteran (PM-200) Premium Plester 20.0000 Kg 3,230.00 -
UPAH
Pekerja 0.4000 Org 79,000.00 31,600.00
Tukang Batu 0.2000 Org 103,000.00 20,600.00
Kepala Tukang 0.0200 Org 112,000.00 2,240.00
Mandor 0.0220 Org 128,000.00 2,816.00
ALAT
JUMLAH 57,256.00
OVERHEAD & PROFIT (15 %) 8,588.40
HARGA SATUAN PEKERJAAN 65,844.40
E.4 DIBULATKAN 65,844.40
JUMLAH 42,750.00
OVERHEAD & PROFIT (15 %) 6,412.50
HARGA SATUAN PEKERJAAN 49,162.50
E.5 DIBULATKAN 49,162.50
E.6 1 M2 ACIAN
BAHAN
Semen Portland 3.2500 Kg 1,275.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Batu 0.1000 Org 103,000.00 10,300.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
JUMLAH 28,500.00
OVERHEAD & PROFIT (15 %) 4,275.00
HARGA SATUAN PEKERJAAN 32,775.00
E.6 DIBULATKAN 32,775.00
Halaman 46
1 2 3 4 5 6 = (3 x 5)
E.7 1 M2 ACIAN DINDING BATA RINGAN (FINE COAT-PM 300)
BAHAN
Semen Acian (PM-300) Fine Coat 4.0000 Kg 4,930.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Batu 0.1000 Org 103,000.00 10,300.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
JUMLAH 28,500.00
OVERHEAD & PROFIT (15 %) 4,275.00
HARGA SATUAN PEKERJAAN 32,775.00
E.7 DIBULATKAN 32,775.00
JUMLAH 37,040.00
OVERHEAD & PROFIT (15 %) 5,556.00
HARGA SATUAN PEKERJAAN 42,596.00
E.8 DIBULATKAN 42,596.00
JUMLAH 52,512.00
OVERHEAD & PROFIT (15 %) 7,876.80
HARGA SATUAN PEKERJAAN 60,388.80
E.9 DIBULATKAN 60,388.80
Halaman 47
1 2 3 4 5 6 = (3 x 5)
JUMLAH 3,143,000.00
OVERHEAD & PROFIT (15 %) 471,450.00
HARGA SATUAN PEKERJAAN 3,614,450.00
F.1 DIBULATKAN 3,614,450.00
JUMLAH 3,143,000.00
OVERHEAD & PROFIT (15 %) 471,450.00
HARGA SATUAN PEKERJAAN 3,614,450.00
F.2 DIBULATKAN 3,614,450.00
Halaman 48
1 2 3 4 5 6 = (3 x 5)
ALAT
JUMLAH 3,143,000.00
OVERHEAD & PROFIT (15 %) 471,450.00
HARGA SATUAN PEKERJAAN 3,614,450.00
F.3 DIBULATKAN 3,614,450.00
JUMLAH 8,791.40
OVERHEAD & PROFIT (15 %) 1,318.71
HARGA SATUAN PEKERJAAN 10,110.11
F.4 DIBULATKAN 10,110.11
JUMLAH 8,791.40
OVERHEAD & PROFIT (15 %) 1,318.71
HARGA SATUAN PEKERJAAN 10,110.11
F.5 DIBULATKAN 10,110.11
Halaman 49
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.4300 Org 79,000.00 33,970.00
Tukang Aluminium 0.4300 Org 108,000.00 46,440.00
Kepala Tukang 0.0430 Org 112,000.00 4,816.00
Mandor 0.0210 Org 128,000.00 2,688.00
ALAT
JUMLAH 87,914.00
OVERHEAD & PROFIT (15 %) 13,187.10
HARGA SATUAN PEKERJAAN 101,101.10
F.6 DIBULATKAN 101,101.10
JUMLAH 87,914.00
OVERHEAD & PROFIT (15 %) 13,187.10
HARGA SATUAN PEKERJAAN 101,101.10
F.7 DIBULATKAN 101,101.10
JUMLAH 87,914.00
OVERHEAD & PROFIT (15 %) 13,187.10
HARGA SATUAN PEKERJAAN 101,101.10
F.8 DIBULATKAN 101,101.10
Halaman 50
1 2 3 4 5 6 = (3 x 5)
F.9 1 M' PASANG KUSEN ALUMINIUM WARNA DOFT 3"
BAHAN
Kusen Alumunium Warna Doft 3" 1.1000 M' 96,900.00 -
Sealant 1.0000 Tube 38,000.00 -
Skrup fixer 2.0000 Bh 935.00 -
UPAH
Pekerja 0.4300 Org 79,000.00 33,970.00
Tukang Aluminium 0.4300 Org 108,000.00 46,440.00
Kepala Tukang 0.0430 Org 112,000.00 4,816.00
Mandor 0.0210 Org 128,000.00 2,688.00
ALAT
JUMLAH 87,914.00
OVERHEAD & PROFIT (15 %) 13,187.10
HARGA SATUAN PEKERJAAN 101,101.10
F.9 DIBULATKAN 101,101.10
JUMLAH 418,760.00
OVERHEAD & PROFIT (15 %) 62,814.00
HARGA SATUAN PEKERJAAN 481,574.00
F.10 DIBULATKAN 481,574.00
JUMLAH 418,760.00
OVERHEAD & PROFIT (15 %) 62,814.00
Halaman 51
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 481,574.00
F.11 DIBULATKAN 481,574.00
JUMLAH 418,760.00
OVERHEAD & PROFIT (15 %) 62,814.00
HARGA SATUAN PEKERJAAN 481,574.00
F.12 DIBULATKAN 481,574.00
JUMLAH 418,760.00
OVERHEAD & PROFIT (15 %) 62,814.00
HARGA SATUAN PEKERJAAN 481,574.00
F.13 DIBULATKAN 481,574.00
Halaman 52
1 2 3 4 5 6 = (3 x 5)
JUMLAH 418,760.00
OVERHEAD & PROFIT (15 %) 62,814.00
HARGA SATUAN PEKERJAAN 481,574.00
F.14 DIBULATKAN 481,574.00
JUMLAH 338,210.00
OVERHEAD & PROFIT (15 %) 50,731.50
HARGA SATUAN PEKERJAAN 388,941.50
F.15 DIBULATKAN 388,941.50
JUMLAH 338,210.00
OVERHEAD & PROFIT (15 %) 50,731.50
HARGA SATUAN PEKERJAAN 388,941.50
F.16 DIBULATKAN 388,941.50
Halaman 53
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.2100 Org 112,000.00 23,520.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.17 DIBULATKAN 361,445.00
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.18 DIBULATKAN 361,445.00
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.19 DIBULATKAN 361,445.00
Halaman 54
1 2 3 4 5 6 = (3 x 5)
BAHAN
Kayu Kruing, Papan 0.0250 M3 9,151,950.00 -
Paku Biasa 1/2" - 1" 0.0300 Kg 22,100.00 -
Lem Kayu 0.5000 Kg 23,800.00 -
Triplek 3 mm 1.0000 Lbr 62,050.00 -
UPAH
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Kayu 2.1000 Org 110,000.00 231,000.00
Kepala Tukang 0.2100 Org 112,000.00 23,520.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.20 DIBULATKAN 361,445.00
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.21 DIBULATKAN 361,445.00
Halaman 55
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.2100 Org 112,000.00 23,520.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 314,300.00
OVERHEAD & PROFIT (15 %) 47,145.00
HARGA SATUAN PEKERJAAN 361,445.00
F.22 DIBULATKAN 361,445.00
JUMLAH 146,820.00
OVERHEAD & PROFIT (15 %) 22,023.00
HARGA SATUAN PEKERJAAN 168,843.00
F.23 DIBULATKAN 168,843.00
JUMLAH 146,820.00
OVERHEAD & PROFIT (15 %) 22,023.00
HARGA SATUAN PEKERJAAN 168,843.00
F.24 DIBULATKAN 168,843.00
F.25 1 M2 PASANG DINDING ALUMINIUM COMPOSIT PANEL (INDOOR) + RANGKA HOLLOW GALVANIS
BAHAN
Aluminium Composit Panel (Indoor) 1.1000 M2 306,850.00 -
Rangka Holow Galvanis 40x40x2 4.0000 M' 19,975.00 -
Halaman 56
1 2 3 4 5 6 = (3 x 5)
Braket Siku 0.2670 Btg 27,341.67 -
Sealant 0.2500 Tube 38,000.00 -
Skrup 0.1100 Kg 23,800.00 -
Paku Beton 0.0800 Kg 42,500.00 -
UPAH
Pekerja 0.3900 Org 79,000.00 30,810.00
Tukang Besi 0.7000 Org 103,000.00 72,100.00
Kepala Tukang 0.0700 Org 112,000.00 7,840.00
Mandor 0.0070 Org 128,000.00 896.00
ALAT
Alat Bantu 1.00 Ls 20,000.00
JUMLAH 111,646.00
OVERHEAD & PROFIT (15 %) 16,746.90
HARGA SATUAN PEKERJAAN 128,392.90
F.25 DIBULATKAN 128,392.90
F.26 1 M2 PASANG DINDING ALUMINIUM COMPOSIT PANEL (OUTDOOR) + RANGKA HOLLOW GALVANIS
BAHAN
Aluminium Composit Panel (Outdoor) 1.1000 M2 453,050.00 -
Rangka Holow Galvanis 40x40x2 4.0000 M' 19,975.00 -
Braket Siku 0.2670 Btg 27,341.67 -
Sealant 0.2500 Tube 38,000.00 -
Skrup 0.1100 Kg 23,800.00 -
Paku Beton 0.0800 Kg 42,500.00 -
UPAH
Pekerja 0.3900 Org 79,000.00 30,810.00
Tukang Besi 0.7000 Org 103,000.00 72,100.00
Kepala Tukang 0.0700 Org 112,000.00 7,840.00
Mandor 0.0070 Org 128,000.00 896.00
ALAT
Alat Bantu 1.00 Ls 20,000.00
JUMLAH 111,646.00
OVERHEAD & PROFIT (15 %) 16,746.90
HARGA SATUAN PEKERJAAN 128,392.90
F.26 DIBULATKAN 128,392.90
G PEKERJAAN BETON
G.1 1 M3 MEMBUAT BETON TUMBUK, 1Pc : 3Ps : 5Kr
BAHAN
Semen Portland 218.0000 Kg 1,275.00 -
Pasir Beton 0.5200 M3 296,650.00 -
Koral Beton 0.8700 M3 292,400.00 -
UPAH
Pekerja 1.6500 Org 79,000.00 130,350.00
Tukang Batu 0.2500 Org 103,000.00 25,750.00
Kepala Tukang 0.0250 Org 112,000.00 2,800.00
Halaman 57
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0800 Org 128,000.00 10,240.00
ALAT
JUMLAH 169,140.00
OVERHEAD & PROFIT (15 %) 25,371.00
HARGA SATUAN PEKERJAAN 194,511.00
G.1 DIBULATKAN 194,511.00
JUMLAH 176,880.00
OVERHEAD & PROFIT (15 %) 26,532.00
HARGA SATUAN PEKERJAAN 203,412.00
G.2 DIBULATKAN 203,412.00
JUMLAH 176,880.00
OVERHEAD & PROFIT (15 %) 26,532.00
HARGA SATUAN PEKERJAAN 203,412.00
G.3 DIBULATKAN 203,412.00
Halaman 58
1 2 3 4 5 6 = (3 x 5)
Adukan K. 175 Ready Mix 1.0000 M3 963,900.00 -
UPAH
Pekerja 2.5000 Org 79,000.00 197,500.00
Tukang Batu 0.2500 Org 103,000.00 25,750.00
Kepala Tukang 0.1000 Org 112,000.00 11,200.00
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
Alat bantu (Vibrator) 0.0450 Lot 42,700.00 -
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.4 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.5 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.6 DIBULATKAN 271,089.50
Halaman 59
1 2 3 4 5 6 = (3 x 5)
G.7 1 M3 COR BETON K. 300 READY MIX
BAHAN
Adukan K. 300 Ready Mix 1.0000 M3 1,013,200.00 -
UPAH
Pekerja 2.5000 Org 79,000.00 197,500.00
Tukang Batu 0.2500 Org 103,000.00 25,750.00
Kepala Tukang 0.1000 Org 112,000.00 11,200.00
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
Alat bantu (Vibrator) 0.0450 Lot 42,700.00 -
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.7 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.8 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
Halaman 60
1 2 3 4 5 6 = (3 x 5)
G.9 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.10 DIBULATKAN 271,089.50
JUMLAH 235,730.00
OVERHEAD & PROFIT (15 %) 35,359.50
HARGA SATUAN PEKERJAAN 271,089.50
G.11 DIBULATKAN 271,089.50
Halaman 61
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 27,544.80
G.12 DIBULATKAN 27,544.80
JUMLAH 176,880.00
OVERHEAD & PROFIT (15 %) 26,532.00
HARGA SATUAN PEKERJAAN 203,412.00
G.13 DIBULATKAN 203,412.00
JUMLAH 58,780.00
OVERHEAD & PROFIT (15 %) 8,817.00
HARGA SATUAN PEKERJAAN 67,597.00
G.14 DIBULATKAN 67,597.00
Halaman 62
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.1500 Org 110,000.00 16,500.00
Kepala Tukang 0.1500 Org 112,000.00 16,800.00
Pembantu Tukang 0.1200 Org 80,000.00 9,600.00
Mandor 0.0500 Org 128,000.00 6,400.00
ALAT
JUMLAH 58,780.00
OVERHEAD & PROFIT (15 %) 8,817.00
HARGA SATUAN PEKERJAAN 67,597.00
G.15 DIBULATKAN 67,597.00
JUMLAH 75,920.00
OVERHEAD & PROFIT (15 %) 11,388.00
HARGA SATUAN PEKERJAAN 87,308.00
G.16 DIBULATKAN 87,308.00
JUMLAH 75,920.00
OVERHEAD & PROFIT (15 %) 11,388.00
HARGA SATUAN PEKERJAAN 87,308.00
G.17 DIBULATKAN 87,308.00
Halaman 63
1 2 3 4 5 6 = (3 x 5)
BAHAN
Kayu Kelas III (Borneo/dll) 0.0400 M3 4,335,000.00 -
Paku Biasa 2" - 5" 0.4000 Kg 18,700.00 -
Minyak Bekisting 0.2000 Liter 16,150.00 -
Kayu Kelas II (Kamper/Kruing/dll) 0.0150 M3 7,027,800.00 -
Multipleks 9 mm 0.3500 Lbr 157,250.00 -
Kayu Dolken Ø 8-10/400 cm 2.0000 Btg 65,450.00 -
UPAH
Pekerja 0.6600 Org 79,000.00 52,140.00
Tukang Kayu 0.3300 Org 110,000.00 36,300.00
Kepala Tukang 0.0330 Org 112,000.00 3,696.00
Mandor 0.0330 Org 128,000.00 4,224.00
ALAT
JUMLAH 96,360.00
OVERHEAD & PROFIT (15 %) 14,454.00
HARGA SATUAN PEKERJAAN 110,814.00
G.18 DIBULATKAN 110,814.00
JUMLAH 96,360.00
OVERHEAD & PROFIT (15 %) 14,454.00
HARGA SATUAN PEKERJAAN 110,814.00
G.19 DIBULATKAN 110,814.00
Halaman 64
1 2 3 4 5 6 = (3 x 5)
Kayu Dolken Ø 8-10/400 cm 6.0000 Btg 15,300.00 -
UPAH
Pekerja 0.6600 Org 79,000.00 52,140.00
Tukang Kayu 0.3300 Org 110,000.00 36,300.00
Kepala Tukang 0.0330 Org 112,000.00 3,696.00
Mandor 0.0330 Org 128,000.00 4,224.00
ALAT
JUMLAH 96,360.00
OVERHEAD & PROFIT (15 %) 14,454.00
HARGA SATUAN PEKERJAAN 110,814.00
G.20 DIBULATKAN 110,814.00
JUMLAH 96,360.00
OVERHEAD & PROFIT (15 %) 14,454.00
HARGA SATUAN PEKERJAAN 110,814.00
G.21 DIBULATKAN 110,814.00
Halaman 65
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0330 Org 128,000.00 4,224.00
ALAT
JUMLAH 96,360.00
OVERHEAD & PROFIT (15 %) 14,454.00
HARGA SATUAN PEKERJAAN 110,814.00
G.22 DIBULATKAN 110,814.00
JUMLAH 58,780.00
OVERHEAD & PROFIT (15 %) 8,817.00
HARGA SATUAN PEKERJAAN 67,597.00
G.23 DIBULATKAN 67,597.00
JUMLAH 1,403.60
OVERHEAD & PROFIT (15 %) 210.54
HARGA SATUAN PEKERJAAN 1,614.14
G.24 DIBULATKAN 1,614.14
Halaman 66
1 2 3 4 5 6 = (3 x 5)
Kawat Beton 0.0150 Kg 30,600.00 -
UPAH
Pekerja 0.0070 Org 79,000.00 553.00
Tukang Besi 0.0070 Org 103,000.00 721.00
Kepala Tukang 0.0007 Org 112,000.00 78.40
Mandor 0.0004 Org 128,000.00 51.20
ALAT
JUMLAH 1,403.60
OVERHEAD & PROFIT (15 %) 210.54
HARGA SATUAN PEKERJAAN 1,614.14
G.25 DIBULATKAN 1,614.14
JUMLAH 5,880.00
OVERHEAD & PROFIT (15 %) 882.00
HARGA SATUAN PEKERJAAN 6,762.00
G.26 DIBULATKAN 6,762.00
JUMLAH 5,880.00
OVERHEAD & PROFIT (15 %) 882.00
HARGA SATUAN PEKERJAAN 6,762.00
G.27 DIBULATKAN 6,762.00
Halaman 67
1 2 3 4 5 6 = (3 x 5)
BAHAN
Wiramesh M-8 1.0500 M2 65,450.00 -
Kawat Beton 0.0100 Kg 30,600.00 -
UPAH
Tukang Besi 0.0400 Org 103,000.00 4,120.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
Peralatan, spenser 0.0200 Lot 10,000.00 -
JUMLAH 5,880.00
OVERHEAD & PROFIT (15 %) 882.00
HARGA SATUAN PEKERJAAN 6,762.00
G.28 DIBULATKAN 6,762.00
JUMLAH 5,880.00
OVERHEAD & PROFIT (15 %) 882.00
HARGA SATUAN PEKERJAAN 6,762.00
G.29 DIBULATKAN 6,762.00
JUMLAH 8,550.00
OVERHEAD & PROFIT (15 %) 1,282.50
HARGA SATUAN PEKERJAAN 9,832.50
Halaman 68
1 2 3 4 5 6 = (3 x 5)
G.30 DIBULATKAN 9,832.50
JUMLAH 8,550.00
OVERHEAD & PROFIT (15 %) 1,282.50
HARGA SATUAN PEKERJAAN 9,832.50
G.31 DIBULATKAN 9,832.50
JUMLAH 15,240.00
OVERHEAD & PROFIT (15 %) 2,286.00
HARGA SATUAN PEKERJAAN 17,526.00
G.32 DIBULATKAN 17,526.00
Halaman 69
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0040 Org 112,000.00 448.00
Mandor 0.0080 Org 128,000.00 1,024.00
ALAT
JUMLAH 12,192.00
OVERHEAD & PROFIT (15 %) 1,828.80
HARGA SATUAN PEKERJAAN 14,020.80
G.33 DIBULATKAN 14,020.80
Halaman 70
1 2 3 4 5 6 = (3 x 5)
GB.37 PEMBESIAN KOLOM 50/50 176.24 Kg / M3 284,476.03
GB.38 PEMBESIAN KOLOM 35/35 180.25 Kg / M3 290,948.74
GB.39 PEMBESIAN KOLOM 45/45 176.20 Kg / M3 284,411.47
GB.40 PEMBESIAN PLAT LISTPLANK, KANOPI T. 8 CM 83.13 Kg / M3 134,183.46
H PEKERJAAN ATAP
JUMLAH 1,796,000.00
OVERHEAD & PROFIT (15 %) 269,400.00
HARGA SATUAN PEKERJAAN 2,065,400.00
H.1 DIBULATKAN 2,065,400.00
JUMLAH 1,077,600.00
OVERHEAD & PROFIT (15 %) 161,640.00
HARGA SATUAN PEKERJAAN 1,239,240.00
H.2 DIBULATKAN 1,239,240.00
Halaman 71
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 4.0000 Org 79,000.00 316,000.00
Tukang Kayu 12.0000 Org 110,000.00 1,320,000.00
Kepala Tukang 1.2000 Org 112,000.00 134,400.00
Mandor 0.2000 Org 128,000.00 25,600.00
ALAT
JUMLAH 1,796,000.00
OVERHEAD & PROFIT (15 %) 269,400.00
HARGA SATUAN PEKERJAAN 2,065,400.00
H.3 DIBULATKAN 2,065,400.00
JUMLAH 1,077,600.00
OVERHEAD & PROFIT (15 %) 161,640.00
HARGA SATUAN PEKERJAAN 1,239,240.00
H.4 DIBULATKAN 1,239,240.00
JUMLAH 1,796,000.00
OVERHEAD & PROFIT (15 %) 269,400.00
HARGA SATUAN PEKERJAAN 2,065,400.00
H.5 DIBULATKAN 2,065,400.00
Halaman 72
1 2 3 4 5 6 = (3 x 5)
H.6 1 M3 PASANG GORDING KAYU KRUING
BAHAN
Kayu Kruing, Balok 1.1000 M3 8,206,750.00 -
Besi Strip 15.0000 Kg 11,900.00 -
Paku Biasa 2" - 5" 3.0000 Kg 18,700.00 -
UPAH
Pekerja 2.4000 Org 79,000.00 189,600.00
Tukang Kayu 7.2000 Org 110,000.00 792,000.00
Kepala Tukang 0.7200 Org 112,000.00 80,640.00
Mandor 0.1200 Org 128,000.00 15,360.00
ALAT
JUMLAH 1,077,600.00
OVERHEAD & PROFIT (15 %) 161,640.00
HARGA SATUAN PEKERJAAN 1,239,240.00
H.6 DIBULATKAN 1,239,240.00
JUMLAH 1,796,000.00
OVERHEAD & PROFIT (15 %) 269,400.00
HARGA SATUAN PEKERJAAN 2,065,400.00
H.7 DIBULATKAN 2,065,400.00
JUMLAH 20,660.00
Halaman 73
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.8 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.9 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.10 DIBULATKAN 23,759.00
Halaman 74
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.11 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.12 DIBULATKAN 23,759.00
H.13 1 M2 PASANG KASO DOLKEN + RENG KAYU BORNEO untuk GENTENG PALENTONG
BAHAN
Kayu Kaso Dolken 6 cm 1.0000 Btg 16,150.00 -
Kayu Reng 2/3 ( Borneo ) 0.0030 M3 5,473,150.00 -
Paku Biasa 2" - 5" 0.1500 Kg 18,700.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.13 DIBULATKAN 23,759.00
Halaman 75
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.14 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.15 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.16 DIBULATKAN 23,759.00
Halaman 76
1 2 3 4 5 6 = (3 x 5)
H.17 1 M2 PASANG RANGKA ATAP KAYU BORNEO untuk GENTENG TEGOLA
BAHAN
Kayu Kaso 5/7 ( Borneo ) 0.0120 M3 4,335,000.00 -
Paku Biasa 2" - 5" 0.1500 Kg 18,700.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
H.17 DIBULATKAN 23,759.00
H.18 1 M2 PASANG KUDA-KUDA BAJA RINGAN PROFIL C75 + RENG untuk ATAP SPANDEK/ASBES
BAHAN
Baja ringan profil C75 t. 0,75 mm 2.2320 M' 14,308.33 -
Baut (screw driver) 28.0000 bh 297.50 -
Dynabolt 1.6000 bh 6,545.00 -
Reng 2.5000 M' 8,075.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Besi 0.4500 Org 103,000.00 46,350.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0500 Org 128,000.00 6,400.00
ALAT
Aksesories 5.00 % 140,596 -
JUMLAH 69,670.00
OVERHEAD & PROFIT (15 %) 10,450.50
HARGA SATUAN PEKERJAAN 80,120.50
H.18 DIBULATKAN 80,120.50
H.19 1 M2 PASANG KUDA-KUDA BAJA RINGAN PROFIL C75 + RENG untuk ATAP GENTENG BIASA
BAHAN
Baja ringan profil C75 t. 0,75 mm 3.7200 M' 14,308.33 -
Baut (screw driver) 36.0000 bh 297.50 -
Dynabolt 1.6000 bh 6,545.00 -
Reng 3.5000 M' 8,075.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Besi 0.4500 Org 103,000.00 46,350.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Halaman 77
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0500 Org 128,000.00 6,400.00
ALAT
Aksesories 5.00 % 172,342 -
JUMLAH 69,670.00
OVERHEAD & PROFIT (15 %) 10,450.50
HARGA SATUAN PEKERJAAN 80,120.50
H.19 DIBULATKAN 80,120.50
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.20 DIBULATKAN 25,258.60
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.21 DIBULATKAN 25,258.60
Halaman 78
1 2 3 4 5 6 = (3 x 5)
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.22 DIBULATKAN 25,258.60
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.23 DIBULATKAN 25,258.60
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.24 DIBULATKAN 25,258.60
JUMLAH 21,964.00
Halaman 79
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.25 DIBULATKAN 25,258.60
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.26 DIBULATKAN 25,258.60
JUMLAH 21,964.00
OVERHEAD & PROFIT (15 %) 3,294.60
HARGA SATUAN PEKERJAAN 25,258.60
H.27 DIBULATKAN 25,258.60
JUMLAH 29,200.00
Halaman 80
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 4,380.00
HARGA SATUAN PEKERJAAN 33,580.00
H.28 DIBULATKAN 33,580.00
JUMLAH 29,200.00
OVERHEAD & PROFIT (15 %) 4,380.00
HARGA SATUAN PEKERJAAN 33,580.00
H.29 DIBULATKAN 33,580.00
JUMLAH 29,200.00
OVERHEAD & PROFIT (15 %) 4,380.00
HARGA SATUAN PEKERJAAN 33,580.00
H.30 DIBULATKAN 33,580.00
Halaman 81
1 2 3 4 5 6 = (3 x 5)
JUMLAH 21,230.00
OVERHEAD & PROFIT (15 %) 3,184.50
HARGA SATUAN PEKERJAAN 24,414.50
H.31 DIBULATKAN 24,414.50
JUMLAH 21,230.00
OVERHEAD & PROFIT (15 %) 3,184.50
HARGA SATUAN PEKERJAAN 24,414.50
H.32 DIBULATKAN 24,414.50
JUMLAH 21,230.00
OVERHEAD & PROFIT (15 %) 3,184.50
HARGA SATUAN PEKERJAAN 24,414.50
H.33 DIBULATKAN 24,414.50
Halaman 82
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0080 Org 128,000.00 1,024
ALAT
JUMLAH 21,230.00
OVERHEAD & PROFIT (15 %) 3,184.50
HARGA SATUAN PEKERJAAN 24,414.50
H.34 DIBULATKAN 24,414.50
JUMLAH 21,230.00
OVERHEAD & PROFIT (15 %) 3,184.50
HARGA SATUAN PEKERJAAN 24,414.50
H.35 DIBULATKAN 24,414.50
JUMLAH 17,520.00
OVERHEAD & PROFIT (15 %) 2,628.00
HARGA SATUAN PEKERJAAN 20,148.00
H.36 DIBULATKAN 20,148.00
Halaman 83
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.0600 Org 110,000.00 6,600.00
Kepala Tukang 0.0060 Org 112,000.00 672.00
Mandor 0.0060 Org 128,000.00 768
ALAT
JUMLAH 17,520.00
OVERHEAD & PROFIT (15 %) 2,628.00
HARGA SATUAN PEKERJAAN 20,148.00
H.37 DIBULATKAN 20,148.00
JUMLAH 21,162.00
OVERHEAD & PROFIT (15 %) 3,174.30
HARGA SATUAN PEKERJAAN 24,336.30
H.38 DIBULATKAN 24,336.30
JUMLAH 20,440.00
OVERHEAD & PROFIT (15 %) 3,066.00
HARGA SATUAN PEKERJAAN 23,506.00
H.39 DIBULATKAN 23,506.00
Halaman 84
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.1400 Org 79,000.00 11,060.00
Tukang Kayu 0.0700 Org 110,000.00 7,700.00
Kepala Tukang 0.0070 Org 112,000.00 784.00
Mandor 0.0070 Org 128,000.00 896
ALAT
JUMLAH 20,440.00
OVERHEAD & PROFIT (15 %) 3,066.00
HARGA SATUAN PEKERJAAN 23,506.00
H.40 DIBULATKAN 23,506.00
JUMLAH 20,440.00
OVERHEAD & PROFIT (15 %) 3,066.00
HARGA SATUAN PEKERJAAN 23,506.00
H.41 DIBULATKAN 23,506.00
JUMLAH 20,440.00
OVERHEAD & PROFIT (15 %) 3,066.00
HARGA SATUAN PEKERJAAN 23,506.00
H.42 DIBULATKAN 23,506.00
Halaman 85
1 2 3 4 5 6 = (3 x 5)
Genteng Bitumen Gelombang Monolayer 3 mm 3.7100 Lbr 65,000.00 -
Paku Payung Sekrup 16.1290 Bh 1,190.00 0.00
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0100 Org 128,000.00 1,280
ALAT
JUMLAH 29,200.00
OVERHEAD & PROFIT (15 %) 4,380.00
HARGA SATUAN PEKERJAAN 33,580.00
H.43 DIBULATKAN 33,580.00
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.44 DIBULATKAN 64,510.40
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
Halaman 86
1 2 3 4 5 6 = (3 x 5)
H.45 DIBULATKAN 64,510.40
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.46 DIBULATKAN 64,510.40
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.47 DIBULATKAN 64,510.40
Halaman 87
1 2 3 4 5 6 = (3 x 5)
ALAT
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.48 DIBULATKAN 64,510.40
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.49 DIBULATKAN 64,510.40
JUMLAH 56,096.00
OVERHEAD & PROFIT (15 %) 8,414.40
HARGA SATUAN PEKERJAAN 64,510.40
H.50 DIBULATKAN 64,510.40
Halaman 88
1 2 3 4 5 6 = (3 x 5)
Pekerja 0.0840 Org 79,000.00 6,636.00
Tukang Kayu 0.1250 Org 110,000.00 13,750.00
Kepala Tukang 0.0130 Org 112,000.00 1,456.00
Mandor 0.0040 Org 128,000.00 512
ALAT
JUMLAH 22,354.00
OVERHEAD & PROFIT (15 %) 3,353.10
HARGA SATUAN PEKERJAAN 25,707.10
H.51 DIBULATKAN 25,707.10
JUMLAH 58,400.00
OVERHEAD & PROFIT (15 %) 8,760.00
HARGA SATUAN PEKERJAAN 67,160.00
H.52 DIBULATKAN 67,160.00
JUMLAH 58,400.00
OVERHEAD & PROFIT (15 %) 8,760.00
Halaman 89
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 67,160.00
H.53 DIBULATKAN 67,160.00
JUMLAH 39,594.00
OVERHEAD & PROFIT (15 %) 5,939.10
HARGA SATUAN PEKERJAAN 45,533.10
H.54 DIBULATKAN 45,533.10
JUMLAH 21,214.00
OVERHEAD & PROFIT (15 %) 3,182.10
HARGA SATUAN PEKERJAAN 24,396.10
H.55 DIBULATKAN 24,396.10
Halaman 90
1 2 3 4 5 6 = (3 x 5)
JUMLAH 22,354.00
OVERHEAD & PROFIT (15 %) 3,353.10
HARGA SATUAN PEKERJAAN 25,707.10
H.56 DIBULATKAN 25,707.10
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.57 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.58 DIBULATKAN 37,697.00
Halaman 91
1 2 3 4 5 6 = (3 x 5)
ALAT
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.59 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.60 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.61 DIBULATKAN 37,697.00
Halaman 92
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0200 Org 112,000.00 2,240.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.62 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.63 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.64 DIBULATKAN 37,697.00
Halaman 93
1 2 3 4 5 6 = (3 x 5)
Paku Biasa 2" - 5" 0.0600 Kg 18,700.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.2000 Org 110,000.00 22,000.00
Kepala Tukang 0.0200 Org 112,000.00 2,240.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.65 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.66 DIBULATKAN 37,697.00
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.67 DIBULATKAN 37,697.00
Halaman 94
1 2 3 4 5 6 = (3 x 5)
BAHAN
Kayu Kruing, Papan 0.0110 M3 9,151,950.00 -
Paku Biasa 2" - 5" 0.0500 Kg 18,700.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.2000 Org 110,000.00 22,000.00
Kepala Tukang 0.0200 Org 112,000.00 2,240.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 32,780.00
OVERHEAD & PROFIT (15 %) 4,917.00
HARGA SATUAN PEKERJAAN 37,697.00
H.68 DIBULATKAN 37,697.00
JUMLAH 63,880.00
OVERHEAD & PROFIT (15 %) 9,582.00
HARGA SATUAN PEKERJAAN 73,462.00
H.69 DIBULATKAN 73,462.00
JUMLAH 63,880.00
Halaman 95
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 9,582.00
HARGA SATUAN PEKERJAAN 73,462.00
H.70 DIBULATKAN 73,462.00
I PEKERJAAN LANGIT-LANGIT
I.1 1 M2 LANGIT-LANGIT ASBES (1,00 X 1,00) M, TEBAL 5 mm
BAHAN
Plat asbes tebal 5 mm 1.1000 Lbr 68,000.00 -
Paku Biasa 1/2" - 1" 0.0100 Kg 22,100.00 -
UPAH
Pekerja 0.0300 Org 79,000.00 2,370.00
Tukang Kayu 0.0700 Org 110,000.00 7,700.00
Kepala Tukang 0.0070 Org 112,000.00 784.00
Mandor 0.0040 Org 128,000.00 512.00
ALAT
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.1 DIBULATKAN 13,070.90
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.2 DIBULATKAN 13,070.90
Halaman 96
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0040 Org 128,000.00 512.00
ALAT
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.3 DIBULATKAN 13,070.90
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.4 DIBULATKAN 13,070.90
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.5 DIBULATKAN 13,070.90
Halaman 97
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
I.6 DIBULATKAN 23,759.00
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
I.7 DIBULATKAN 23,759.00
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.8 DIBULATKAN 13,070.90
Halaman 98
1 2 3 4 5 6 = (3 x 5)
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.9 DIBULATKAN 13,070.90
JUMLAH 11,366.00
OVERHEAD & PROFIT (15 %) 1,704.90
HARGA SATUAN PEKERJAAN 13,070.90
I.10 DIBULATKAN 13,070.90
Halaman 99
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.0500 Org 110,000.00 5,500.00
Kepala Tukang 0.0050 Org 112,000.00 560.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 14,600.00
OVERHEAD & PROFIT (15 %) 2,190.00
HARGA SATUAN PEKERJAAN 16,790.00
I.11 DIBULATKAN 16,790.00
JUMLAH 54,156.00
OVERHEAD & PROFIT (15 %) 8,123.40
HARGA SATUAN PEKERJAAN 62,279.40
I.12 DIBULATKAN 62,279.40
JUMLAH 54,156.00
Halaman 100
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 8,123.40
HARGA SATUAN PEKERJAAN 62,279.40
I.13 DIBULATKAN 62,279.40
JUMLAH 14,600.00
OVERHEAD & PROFIT (15 %) 2,190.00
HARGA SATUAN PEKERJAAN 16,790.00
I.14 DIBULATKAN 16,790.00
JUMLAH 54,156.00
OVERHEAD & PROFIT (15 %) 8,123.40
HARGA SATUAN PEKERJAAN 62,279.40
I.15 DIBULATKAN 62,279.40
Halaman 101
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0090 Org 128,000.00 1,152.00
ALAT
JUMLAH 54,156.00
OVERHEAD & PROFIT (15 %) 8,123.40
HARGA SATUAN PEKERJAAN 62,279.40
I.16 DIBULATKAN 62,279.40
JUMLAH 54,156.00
OVERHEAD & PROFIT (15 %) 8,123.40
HARGA SATUAN PEKERJAAN 62,279.40
I.17 DIBULATKAN 62,279.40
JUMLAH 20,660.00
OVERHEAD & PROFIT (15 %) 3,099.00
HARGA SATUAN PEKERJAAN 23,759.00
I.18 DIBULATKAN 23,759.00
Halaman 102
1 2 3 4 5 6 = (3 x 5)
Pekerja 0.8000 Org 79,000.00 63,200.00
Tukang Kayu 0.8000 Org 110,000.00 88,000.00
Kepala Tukang 0.0800 Org 112,000.00 8,960.00
Mandor 0.0400 Org 128,000.00 5,120.00
ALAT
JUMLAH 165,280.00
OVERHEAD & PROFIT (15 %) 24,792.00
HARGA SATUAN PEKERJAAN 190,072.00
I.19 DIBULATKAN 190,072.00
JUMLAH 171,251.20
OVERHEAD & PROFIT (15 %) 25,687.68
HARGA SATUAN PEKERJAAN 196,938.88
I.20 DIBULATKAN 196,938.88
JUMLAH 51,750.00
OVERHEAD & PROFIT (15 %) 7,762.50
HARGA SATUAN PEKERJAAN 59,512.50
I.21 DIBULATKAN 59,512.50
Halaman 103
1 2 3 4 5 6 = (3 x 5)
JUMLAH 51,750.00
OVERHEAD & PROFIT (15 %) 7,762.50
HARGA SATUAN PEKERJAAN 59,512.50
I.22 DIBULATKAN 59,512.50
JUMLAH 14,600.00
OVERHEAD & PROFIT (15 %) 2,190.00
HARGA SATUAN PEKERJAAN 16,790.00
I.23 DIBULATKAN 16,790.00
Halaman 104
1 2 3 4 5 6 = (3 x 5)
JUMLAH 10,394.00
OVERHEAD & PROFIT (15 %) 1,559.10
HARGA SATUAN PEKERJAAN 11,953.10
I.24 DIBULATKAN 11,953.10
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.25 DIBULATKAN 14,255.40
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.26 DIBULATKAN 14,255.40
Halaman 105
1 2 3 4 5 6 = (3 x 5)
ALAT
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.27 DIBULATKAN 14,255.40
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.28 DIBULATKAN 14,255.40
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.29 DIBULATKAN 14,255.40
Halaman 106
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0060 Org 112,000.00 672.00
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 12,396.00
OVERHEAD & PROFIT (15 %) 1,859.40
HARGA SATUAN PEKERJAAN 14,255.40
I.30 DIBULATKAN 14,255.40
JUMLAH 5,880.00
OVERHEAD & PROFIT (15 %) 882.00
HARGA SATUAN PEKERJAAN 6,762.00
I.31 DIBULATKAN 6,762.00
I.32 1 M' PASANG DROP CEILING GYPSUM BOARD, RANGKA HOLLOW, TINGGI 30 CM
BAHAN
Hollow 4/4 galvalume 0.4150 Btg 28,050.00 -
Hollow 2/4 galvalume 0.1500 Btg 28,900.00 -
Gypsum Board (120 x 240 x 9) mm 0.2708 Lbr 82,450.00 -
Paku Sekrup gypsum 0.1100 Kg 33,150.00 -
Cotton plaster 0.0720 Bh 21,250.00 -
Compoun 0.1250 Zak 79,050.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.0500 Org 110,000.00 5,500.00
Kepala Tukang 0.0050 Org 112,000.00 560.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 14,600.00
OVERHEAD & PROFIT (15 %) 2,190.00
HARGA SATUAN PEKERJAAN 16,790.00
I.32 DIBULATKAN 16,790.00
J PEKERJAAN SANITASI
Halaman 107
1 2 3 4 5 6 = (3 x 5)
J.1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK (SETARA INA)
BAHAN
Kloset duduk / monoblok 1.0000 Bh 1,676,200.00 -
Perlengkapan (6% Harga Closet duduk) 1.0000 Ls #N/A -
UPAH
Pekerja 3.3000 Org 79,000.00 260,700.00
Tukang Batu 1.1000 Org 103,000.00 113,300.00
Kepala Tukang 0.0010 Org 112,000.00 112.00
Mandor 0.1600 Org 128,000.00 20,480.00
ALAT
JUMLAH 394,592.00
OVERHEAD & PROFIT (15 %) 59,188.80
HARGA SATUAN PEKERJAAN 453,780.80
J.1 DIBULATKAN 453,780.80
JUMLAH 394,592.00
OVERHEAD & PROFIT (15 %) 59,188.80
HARGA SATUAN PEKERJAAN 453,780.80
J.2 DIBULATKAN 453,780.80
JUMLAH 270,780.00
OVERHEAD & PROFIT (15 %) 40,617.00
Halaman 108
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 311,397.00
J.3 DIBULATKAN 311,397.00
JUMLAH 199,600.00
OVERHEAD & PROFIT (15 %) 29,940.00
HARGA SATUAN PEKERJAAN 229,540.00
J.4 DIBULATKAN 229,540.00
JUMLAH 268,630.00
OVERHEAD & PROFIT (15 %) 40,294.50
HARGA SATUAN PEKERJAAN 308,924.50
J.5 DIBULATKAN 308,924.50
Halaman 109
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0750 Org 112,000.00 8,400.00
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 91,959.00
OVERHEAD & PROFIT (15 %) 13,793.85
HARGA SATUAN PEKERJAAN 105,752.85
J.6 DIBULATKAN 105,752.85
J.7 MEMASANG 1 BUAH BAK MANDI BATU BATA LAPIS KERAMIK VOLUME 0,3 M3
BAHAN
Batu Bata 150.0000 Bh 935.00 -
Semen Portland 120.0000 Kg 1,275.00 -
Pasir Pasang 0.3000 M3 261,800.00 -
Keramik Dinding 20 x 25 cm 3.7900 M2 63,750.00 -
Semen Nat 6.0000 Kg 17,391.00 -
UPAH
Pekerja 6.0000 Org 79,000.00 474,000.00
Tukang Batu 3.0000 Org 103,000.00 309,000.00
Kepala Tukang 0.3000 Org 112,000.00 33,600.00
Mandor 0.0300 Org 128,000.00 3,840.00
ALAT
JUMLAH 820,440.00
OVERHEAD & PROFIT (15 %) 123,066.00
HARGA SATUAN PEKERJAAN 943,506.00
J.7 DIBULATKAN 943,506.00
J.8 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (30 x 30) cm, T = 35 cm
BAHAN
Batu Bata 40.0000 Bh 935.00 -
Semen Portland 44.0000 Kg 1,275.00 -
Pasir Pasang 0.0700 M3 261,800.00 -
Batu Kerikil 0.0700 M3 292,400.00 -
Baja Tulangan 1.6000 Kg 12,750.00 -
Pasir Beton 0.0600 M3 296,650.00 -
UPAH
Pekerja 2.1600 Org 79,000.00 170,640.00
Tukang Batu 0.7200 Org 103,000.00 74,160.00
Kepala Tukang 0.0720 Org 112,000.00 8,064.00
Mandor 0.0110 Org 128,000.00 1,408.00
ALAT
JUMLAH 254,272.00
OVERHEAD & PROFIT (15 %) 38,140.80
HARGA SATUAN PEKERJAAN 292,412.80
Halaman 110
1 2 3 4 5 6 = (3 x 5)
J.8 DIBULATKAN 292,412.80
J.9 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45 x 45) cm, T = 50 cm
BAHAN
Batu Bata 70.0000 Bh 935.00 -
Semen Portland 77.0000 Kg 1,275.00 -
Pasir Pasang 0.1300 M3 261,800.00 -
Batu Kerikil 0.0200 M3 292,400.00 -
Baja Tulangan 2.6000 Kg 12,750.00 -
Pasir Beton 0.0900 M3 296,650.00 -
UPAH
Pekerja 3.2000 Org 79,000.00 252,800.00
Tukang Batu 1.1500 Org 103,000.00 118,450.00
Kepala Tukang 0.0110 Org 112,000.00 1,232.00
Mandor 0.0160 Org 128,000.00 2,048.00
ALAT
JUMLAH 374,530.00
OVERHEAD & PROFIT (15 %) 56,179.50
HARGA SATUAN PEKERJAAN 430,709.50
J.9 DIBULATKAN 430,709.50
JUMLAH 18,000.00
OVERHEAD & PROFIT (15 %) 2,700.00
HARGA SATUAN PEKERJAAN 20,700.00
J.10 DIBULATKAN 20,700.00
Halaman 111
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0270 Org 128,000.00 3,456.00
ALAT
JUMLAH 18,000.00
OVERHEAD & PROFIT (15 %) 2,700.00
HARGA SATUAN PEKERJAAN 20,700.00
J.11 DIBULATKAN 20,700.00
JUMLAH 9,952.00
OVERHEAD & PROFIT (15 %) 1,492.80
HARGA SATUAN PEKERJAAN 11,444.80
J.12 DIBULATKAN 11,444.80
JUMLAH 9,952.00
OVERHEAD & PROFIT (15 %) 1,492.80
HARGA SATUAN PEKERJAAN 11,444.80
J.13 DIBULATKAN 11,444.80
Halaman 112
1 2 3 4 5 6 = (3 x 5)
Tukang Batu 0.0600 Org 103,000.00 6,180.00
Kepala Tukang 0.0060 Org 112,000.00 672.00
Mandor 0.0020 Org 128,000.00 256.00
ALAT
JUMLAH 9,952.00
OVERHEAD & PROFIT (15 %) 1,492.80
HARGA SATUAN PEKERJAAN 11,444.80
J.14 DIBULATKAN 11,444.80
JUMLAH 14,928.00
OVERHEAD & PROFIT (15 %) 2,239.20
HARGA SATUAN PEKERJAAN 17,167.20
J.15 DIBULATKAN 17,167.20
JUMLAH 22,328.00
OVERHEAD & PROFIT (15 %) 3,349.20
HARGA SATUAN PEKERJAAN 25,677.20
J.16 DIBULATKAN 25,677.20
Halaman 113
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.0810 Org 79,000.00 6,399.00
Tukang Batu 0.1350 Org 103,000.00 13,905.00
Kepala Tukang 0.0135 Org 112,000.00 1,512.00
Mandor 0.0040 Org 128,000.00 512.00
ALAT
JUMLAH 22,328.00
OVERHEAD & PROFIT (15 %) 3,349.20
HARGA SATUAN PEKERJAAN 25,677.20
J.17 DIBULATKAN 25,677.20
JUMLAH 22,328.00
OVERHEAD & PROFIT (15 %) 3,349.20
HARGA SATUAN PEKERJAAN 25,677.20
J.18 DIBULATKAN 25,677.20
JUMLAH 36,822.00
OVERHEAD & PROFIT (15 %) 5,523.30
HARGA SATUAN PEKERJAAN 42,345.30
J.19 DIBULATKAN 42,345.30
Halaman 114
1 2 3 4 5 6 = (3 x 5)
Kran Air 1.0000 Bh 86,700.00 -
Seal Tape 0.0250 Bh 3,400.00 -
UPAH
Pekerja 0.0100 Org 79,000.00 790.00
Tukang Batu 0.4000 Org 103,000.00 41,200.00
Kepala Tukang 0.0400 Org 112,000.00 4,480.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 47,110.00
OVERHEAD & PROFIT (15 %) 7,066.50
HARGA SATUAN PEKERJAAN 54,176.50
J.20 DIBULATKAN 54,176.50
JUMLAH 12,850.00
OVERHEAD & PROFIT (15 %) 1,927.50
HARGA SATUAN PEKERJAAN 14,777.50
J.21 DIBULATKAN 14,777.50
JUMLAH 12,850.00
OVERHEAD & PROFIT (15 %) 1,927.50
HARGA SATUAN PEKERJAAN 14,777.50
J.22 DIBULATKAN 14,777.50
Halaman 115
1 2 3 4 5 6 = (3 x 5)
Roof Drain Plastik Dia-4" 1.0000 Bh 19,800.00 -
UPAH
Pekerja 0.0100 Org 79,000.00 790.00
Tukang Batu 0.1000 Org 103,000.00 10,300.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 12,850.00
OVERHEAD & PROFIT (15 %) 1,927.50
HARGA SATUAN PEKERJAAN 14,777.50
J.23 DIBULATKAN 14,777.50
JUMLAH 12,850.00
OVERHEAD & PROFIT (15 %) 1,927.50
HARGA SATUAN PEKERJAAN 14,777.50
J.24 DIBULATKAN 14,777.50
J.25 MEMASANG 1 UNIT SEPTIKTANK 2.5 x 1.5 x 2 + REMBESAN (KANTOR TIPE BESAR)
Galian Tanah 7.5000 M3 88,389.00 662,917.50
Pasir Urug 0.3570 M3 297,344.00 10,255.54
Lantai Kerja 3.7500 M3 984,096.00 729,416.25
Pas. Bata 1 : 3 25.0000 M2 150,976.00 1,064,900.00
Plesteran 1 Ps : 3 Pc 25.0000 M2 76,335.00 1,295,015.00
Acian 25.0000 M2 37,540.00 819,375.00
Plat Beton Penutup + Balok 0.5000 M3 2,914,109.21 202,596.23
Pipa PVC 4" + Sambungan 9.0000 M' 146,887.00 231,094.80
Pipa GI. 1 1/2" 2.0000 M' 82,820.00 41,400.00
Galian Tanah untuk rembesan 5.6250 M3 88,389.00 497,188.13
Pasangan ijuk 9.0000 Kg 37,400.00 -
Urugan Kerikil 1.7500 M3 292,400.00 -
Urugan Kembali perataan tanah 1.8750 M3 52,785.00 98,971.88
Tambahan Upah 0.0850 Ls 60,000.00 5,100.00
ALAT
JUMLAH 5,658,230.32
Halaman 116
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 848,734.55
HARGA SATUAN PEKERJAAN 6,506,964.87
J.25 DIBULATKAN 6,506,964.87
J.26 MEMASANG 1 UNIT SEPTIKTANK 2.5 x 1.5 x 1.5 + REMBESAN (KANTOR TIPE KECIL)
Galian Tanah 4.5000 M3 88,389.00 397,750.50
Pasir Urug 0.2140 M3 297,344.00 6,147.58
Lantai Kerja 2.2500 M3 984,096.00 437,649.75
Pas. Bata 1 : 3 15.0000 M2 150,976.00 638,940.00
Plesteran 1 Ps : 3 Pc 15.0000 M2 76,335.00 777,009.00
Acian 15.0000 M2 37,540.00 491,625.00
Plat Beton Penutup + Balok 0.3000 M3 2,914,109.21 121,557.74
Pipa PVC 4" + Sambungan 5.4000 M' 146,887.00 138,656.88
Pipa GI. 1 1/2" 1.2000 M' 82,820.00 24,840.00
Galian Tanah untuk rembesan 3.3750 M3 88,389.00 298,312.88
Pasangan ijuk 5.4000 Kg 37,400.00 -
Urugan Kerikil 1.0500 M3 292,400.00 -
Urugan Kembali perataan tanah 1.1250 M3 52,785.00 59,383.13
Tambahan Upah 0.0920 Ls 60,000.00 5,520.00
ALAT
JUMLAH 3,397,392.45
OVERHEAD & PROFIT (15 %) 509,608.87
HARGA SATUAN PEKERJAAN 3,907,001.31
J.26 DIBULATKAN 3,907,001.31
J.27 MEMASANG 1 UNIT SEPTIKTANK 1.5 x 1 x 1.5 + REMBESAN (RUMAH TIPE KECIL)
Galian Tanah 2.2500 M3 88,389.00 198,875.25
Pasir Urug 0.1070 M3 297,344.00 3,073.79
Lantai Kerja 1.1250 M3 984,096.00 218,824.88
Pas. Bata 1 : 3 7.5000 M2 150,976.00 319,470.00
Plesteran 1 Ps : 3 Pc 7.5000 M2 76,335.00 388,504.50
Acian 7.5000 M2 37,540.00 245,812.50
Plat Beton Penutup + balok 0.1500 M3 2,914,109.21 60,778.87
Pipa PVC 4" + Sambungan 9.0000 M' 146,887.00 231,094.80
Pipa GI. 1 1/2" 0.6000 M' 82,820.00 12,420.00
Galian Tanah untuk rembesan 0.1680 M3 88,389.00 14,849.35
Pasangan ijuk 2.7000 Kg 37,400.00 -
Urugan Kerikil 3.5 cm 0.5250 M3 292,400.00 -
Urugan Kembali perataan tanah 0.5620 M3 52,785.00 29,665.17
Tambahan Upah 0.0650 Ls 60,000.00 3,900.00
ALAT
JUMLAH 1,727,269.10
OVERHEAD & PROFIT (15 %) 259,090.37
HARGA SATUAN PEKERJAAN 1,986,359.47
Halaman 117
1 2 3 4 5 6 = (3 x 5)
J.27 DIBULATKAN 1,986,359.47
JUMLAH 136,839.35
OVERHEAD & PROFIT (15 %) 20,525.90
HARGA SATUAN PEKERJAAN 157,365.25
J.28 DIBULATKAN 157,365.25
JUMLAH 138,478.60
OVERHEAD & PROFIT (15 %) 20,771.79
HARGA SATUAN PEKERJAAN 159,250.39
J.29 DIBULATKAN 159,250.39
UPAH
Pekerja 0.3800 Org 79,000.00 30,020.00
Tukang Batu 0.1900 Org 103,000.00 19,570.00
Kepala Tukang 0.0190 Org 112,000.00 2,128.00
Mandor 0.0190 Org 128,000.00 2,432.00
ALAT
JUMLAH 54,150.00
Halaman 118
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 8,122.50
HARGA SATUAN PEKERJAAN 62,272.50
J.30 DIBULATKAN 62,272.50
UPAH
Pekerja 0.3800 Org 79,000.00 30,020.00
Tukang Batu 0.1900 Org 103,000.00 19,570.00
Kepala Tukang 0.0190 Org 112,000.00 2,128.00
Mandor 0.0190 Org 128,000.00 2,432.00
ALAT
JUMLAH 54,150.00
OVERHEAD & PROFIT (15 %) 8,122.50
HARGA SATUAN PEKERJAAN 62,272.50
J.31 DIBULATKAN 62,272.50
JUMLAH 394,592.00
OVERHEAD & PROFIT (15 %) 59,188.80
HARGA SATUAN PEKERJAAN 453,780.80
J.32 DIBULATKAN 453,780.80
Halaman 119
1 2 3 4 5 6 = (3 x 5)
Tukang Batu 1.1000 Org 103,000.00 113,300.00
Kepala Tukang 0.0010 Org 112,000.00 112.00
Mandor 0.1600 Org 128,000.00 20,480.00
ALAT
JUMLAH 394,592.00
OVERHEAD & PROFIT (15 %) 59,188.80
HARGA SATUAN PEKERJAAN 453,780.80
J.33 DIBULATKAN 453,780.80
Halaman 120
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0000 Org 112,000.00 1.12
Mandor 0.0001 Org 128,000.00 6.40
ALAT
Sewa alat Crane 0.0080 Jam 590,300.00 -
JUMLAH 189.52
OVERHEAD & PROFIT (15 %) 28.43
HARGA SATUAN PEKERJAAN 217.95
K.3 DIBULATKAN 217.95
JUMLAH 584.00
OVERHEAD & PROFIT (15 %) 87.60
HARGA SATUAN PEKERJAAN 671.60
K.4 DIBULATKAN 671.60
JUMLAH 6,614.00
OVERHEAD & PROFIT (15 %) 992.10
HARGA SATUAN PEKERJAAN 7,606.10
K.5 DIBULATKAN 7,606.10
Halaman 121
1 2 3 4 5 6 = (3 x 5)
Pekerja 1.0000 Org 79,000.00 79,000.00
Kepala Tukang 0.1000 Org 112,000.00 11,200.00
Mandor 0.0500 Org 128,000.00 6,400.00
ALAT
JUMLAH 204,600.00
OVERHEAD & PROFIT (15 %) 30,690.00
HARGA SATUAN PEKERJAAN 235,290.00
K.6 DIBULATKAN 235,290.00
JUMLAH 204,600.00
OVERHEAD & PROFIT (15 %) 30,690.00
HARGA SATUAN PEKERJAAN 235,290.00
K.7 DIBULATKAN 235,290.00
JUMLAH 204,600.00
OVERHEAD & PROFIT (15 %) 30,690.00
HARGA SATUAN PEKERJAAN 235,290.00
K.8 DIBULATKAN 235,290.00
Halaman 122
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.1000 Org 112,000.00 11,200.00
Mandor 0.0500 Org 128,000.00 6,400.00
ALAT
JUMLAH 204,600.00
OVERHEAD & PROFIT (15 %) 30,690.00
HARGA SATUAN PEKERJAAN 235,290.00
K.9 DIBULATKAN 235,290.00
K.10 1 M2 PEKERJAAN PINTU BESI PLAT BAJA TEBAL. 2 mm RANGKAP, RANGKA BAJA SIKU
BAHAN
Besi Siku L. 30.30.3 15.0000 Kg 11,900.00 -
Besi Plat Baja 32.8000 Kg 11,900.00 -
Kawat Las 0.0500 Kg 32,300.00 -
UPAH
Tukang Las 1.0500 Org 110,000.00 115,500.00
Pekerja 1.0500 Org 79,000.00 82,950.00
Kepala Tukang 0.1050 Org 112,000.00 11,760.00
Mandor 0.0520 Org 128,000.00 6,656.00
ALAT
JUMLAH 216,866.00
OVERHEAD & PROFIT (15 %) 32,529.90
HARGA SATUAN PEKERJAAN 249,395.90
K.10 DIBULATKAN 249,395.90
JUMLAH 344,958.00
OVERHEAD & PROFIT (15 %) 51,743.70
HARGA SATUAN PEKERJAAN 396,701.70
K.11 DIBULATKAN 396,701.70
Halaman 123
1 2 3 4 5 6 = (3 x 5)
Kayu Kamper, Papan 0.0018 M3 12,364,950.00 -
UPAH
Pekerja 0.1000 Org 79,000.00 7,900.00
Tukang Kayu 0.1000 Org 110,000.00 11,000.00
Kepala Tukang 0.0100 Org 112,000.00 1,120.00
Mandor 0.0005 Org 128,000.00 64.00
ALAT
JUMLAH 20,084.00
OVERHEAD & PROFIT (15 %) 3,012.60
HARGA SATUAN PEKERJAAN 23,096.60
K.12 DIBULATKAN 23,096.60
JUMLAH 20,084.00
OVERHEAD & PROFIT (15 %) 3,012.60
HARGA SATUAN PEKERJAAN 23,096.60
K.13 DIBULATKAN 23,096.60
JUMLAH 20,084.00
OVERHEAD & PROFIT (15 %) 3,012.60
HARGA SATUAN PEKERJAAN 23,096.60
K.14 DIBULATKAN 23,096.60
Halaman 124
1 2 3 4 5 6 = (3 x 5)
JUMLAH 57,550.00
OVERHEAD & PROFIT (15 %) 8,632.50
HARGA SATUAN PEKERJAAN 66,182.50
L.1 DIBULATKAN 66,182.50
JUMLAH 57,550.00
OVERHEAD & PROFIT (15 %) 8,632.50
HARGA SATUAN PEKERJAAN 66,182.50
L.2 DIBULATKAN 66,182.50
JUMLAH 19,461.00
OVERHEAD & PROFIT (15 %) 2,919.15
HARGA SATUAN PEKERJAAN 22,380.15
L.3 DIBULATKAN 22,380.15
Halaman 125
1 2 3 4 5 6 = (3 x 5)
JUMLAH 12,974.00
OVERHEAD & PROFIT (15 %) 1,946.10
HARGA SATUAN PEKERJAAN 14,920.10
L.4 DIBULATKAN 14,920.10
JUMLAH 19,461.00
OVERHEAD & PROFIT (15 %) 2,919.15
HARGA SATUAN PEKERJAAN 22,380.15
L.5 DIBULATKAN 22,380.15
JUMLAH 12,974.00
OVERHEAD & PROFIT (15 %) 1,946.10
HARGA SATUAN PEKERJAAN 14,920.10
L.6 DIBULATKAN 14,920.10
Halaman 126
1 2 3 4 5 6 = (3 x 5)
L.7 1 BH PASANG PEGANGAN PINTU / DOOR HOLDER
BAHAN
Door Holder 1.0000 Bh 168,300.00 -
UPAH
Pekerja 0.0500 Org 79,000.00 3,950.00
Tukang Kayu 0.5000 Org 110,000.00 55,000.00
Kepala Tukang 0.0500 Org 112,000.00 5,600.00
Mandor 0.0025 Org 128,000.00 320.00
ALAT
JUMLAH 64,870.00
OVERHEAD & PROFIT (15 %) 9,730.50
HARGA SATUAN PEKERJAAN 74,600.50
L.7 DIBULATKAN 74,600.50
JUMLAH 19,467.40
OVERHEAD & PROFIT (15 %) 2,920.11
HARGA SATUAN PEKERJAAN 22,387.51
L.8 DIBULATKAN 22,387.51
JUMLAH 19,467.40
OVERHEAD & PROFIT (15 %) 2,920.11
HARGA SATUAN PEKERJAAN 22,387.51
L.9 DIBULATKAN 22,387.51
Halaman 127
1 2 3 4 5 6 = (3 x 5)
BAHAN
Kaca 10 mm 1.1000 M' 227,800.00 -
Sealant 4.0000 M' 38,000.00 -
UPAH
Pekerja 0.0500 Org 79,000.00 3,950.00
Tukang Aluminium 0.4950 Org 108,000.00 53,460.00
Kepala Tukang 0.0500 Org 112,000.00 5,600.00
Mandor 0.0024 Org 128,000.00 307.20
ALAT
JUMLAH 63,317.20
OVERHEAD & PROFIT (15 %) 9,497.58
HARGA SATUAN PEKERJAAN 72,814.78
L.10 DIBULATKAN 72,814.78
JUMLAH 75,866.04
OVERHEAD & PROFIT (15 %) 11,379.91
HARGA SATUAN PEKERJAAN 87,245.95
L.11 DIBULATKAN 87,245.95
Halaman 128
1 2 3 4 5 6 = (3 x 5)
JUMLAH 144,212.00
OVERHEAD & PROFIT (15 %) 21,631.80
HARGA SATUAN PEKERJAAN 165,843.80
L.12 DIBULATKAN 165,843.80
JUMLAH 500,000.00
OVERHEAD & PROFIT (15 %) 75,000.00
HARGA SATUAN PEKERJAAN 575,000.00
L.13 DIBULATKAN 575,000.00
JUMLAH 500,000.00
OVERHEAD & PROFIT (15 %) 75,000.00
HARGA SATUAN PEKERJAAN 575,000.00
L.14 DIBULATKAN 575,000.00
Halaman 129
1 2 3 4 5 6 = (3 x 5)
Bottom straightrap 2.0000 psg 336,600.00 -
Top straighinge 2.0000 psg 431,800.00 -
UPAH
Pemasangan 1.0000 unit 500,000.00 500,000.00
ALAT
JUMLAH 500,000.00
OVERHEAD & PROFIT (15 %) 75,000.00
HARGA SATUAN PEKERJAAN 575,000.00
L.15 DIBULATKAN 575,000.00
JUMLAH 500,000.00
OVERHEAD & PROFIT (15 %) 75,000.00
HARGA SATUAN PEKERJAAN 575,000.00
L.16 DIBULATKAN 575,000.00
JUMLAH 500,000.00
OVERHEAD & PROFIT (15 %) 75,000.00
HARGA SATUAN PEKERJAAN 575,000.00
L.17 DIBULATKAN 575,000.00
Halaman 130
1 2 3 4 5 6 = (3 x 5)
BAHAN
Pintu Aluminium 4.4000 M' 104,550.00 -
Profil Kaca 4.5000 M' 32,300.00 -
Sealant 0.2700 Tube 38,000.00 -
UPAH
Pekerja 0.0850 Org 79,000.00 6,715.00
Tukang Aluminium 0.0850 Org 108,000.00 9,180.00
Kepala Tukang 0.0090 Org 112,000.00 1,008.00
Mandor 0.0050 Org 128,000.00 640.00
ALAT
JUMLAH 17,543.00
OVERHEAD & PROFIT (15 %) 2,631.45
HARGA SATUAN PEKERJAAN 20,174.45
L.18 DIBULATKAN 20,174.45
JUMLAH 37,050.00
Halaman 131
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 5,557.50
HARGA SATUAN PEKERJAAN 42,607.50
M.1 DIBULATKAN 42,607.50
JUMLAH 37,050.00
OVERHEAD & PROFIT (15 %) 5,557.50
HARGA SATUAN PEKERJAAN 42,607.50
M.2 DIBULATKAN 42,607.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.3 DIBULATKAN 114,712.50
Halaman 132
1 2 3 4 5 6 = (3 x 5)
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Batu 0.3500 Org 103,000.00 36,050.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.4 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.5 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.6 DIBULATKAN 114,712.50
Halaman 133
1 2 3 4 5 6 = (3 x 5)
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.7 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.8 DIBULATKAN 114,712.50
Halaman 134
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.9 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.10 DIBULATKAN 114,712.50
JUMLAH 134,750.00
OVERHEAD & PROFIT (15 %) 20,212.50
HARGA SATUAN PEKERJAAN 154,962.50
M.11 DIBULATKAN 154,962.50
Halaman 135
1 2 3 4 5 6 = (3 x 5)
M.12 1 M2 PASANG LANTAI GRANIT TILE UKURAN 60 x 60 cm
BAHAN
Granit Tile 60 x 60 cm (Unpolish/Kasar) 1.1870 M2 325,550.00 -
Semen Portland 10.0000 Kg 1,275.00 -
Pasir Pasang 0.0450 M3 261,800.00 -
Semen Warna 1.5000 Kg 17,391.00 -
UPAH
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Batu 0.3500 Org 103,000.00 36,050.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.12 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.13 DIBULATKAN 114,712.50
Halaman 136
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.14 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.15 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.16 DIBULATKAN 114,712.50
Halaman 137
1 2 3 4 5 6 = (3 x 5)
Granit Tile 80 x 80 cm (setara marco) 1.1870 M2 282,200.00 -
Semen Portland 10.0000 Kg 1,275.00 -
Pasir Pasang 0.0450 M3 261,800.00 -
Semen Warna 1.5000 Kg 17,391.00 -
UPAH
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Batu 0.3500 Org 103,000.00 36,050.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.17 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.18 DIBULATKAN 114,712.50
Halaman 138
1 2 3 4 5 6 = (3 x 5)
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.19 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
M.20 DIBULATKAN 114,712.50
JUMLAH 102,200.00
OVERHEAD & PROFIT (15 %) 15,330.00
HARGA SATUAN PEKERJAAN 117,530.00
M.21 DIBULATKAN 117,530.00
Halaman 139
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.3500 Org 110,000.00 38,500.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 102,200.00
OVERHEAD & PROFIT (15 %) 15,330.00
HARGA SATUAN PEKERJAAN 117,530.00
M.22 DIBULATKAN 117,530.00
JUMLAH 35,186.00
OVERHEAD & PROFIT (15 %) 5,277.90
HARGA SATUAN PEKERJAAN 40,463.90
M.23 DIBULATKAN 40,463.90
JUMLAH 23,952.00
OVERHEAD & PROFIT (15 %) 3,592.80
HARGA SATUAN PEKERJAAN 27,544.80
M.24 DIBULATKAN 27,544.80
Halaman 140
1 2 3 4 5 6 = (3 x 5)
UPAH
Pemasangan Batu Koral 1.0000 Ls 177,000.00 177,000.00
ALAT
JUMLAH 177,000.00
OVERHEAD & PROFIT (15 %) 26,550.00
HARGA SATUAN PEKERJAAN 203,550.00
M.25 DIBULATKAN 203,550.00
JUMLAH 177,000.00
OVERHEAD & PROFIT (15 %) 26,550.00
HARGA SATUAN PEKERJAAN 203,550.00
M.26 DIBULATKAN 203,550.00
JUMLAH 177,000.00
OVERHEAD & PROFIT (15 %) 26,550.00
HARGA SATUAN PEKERJAAN 203,550.00
M.27 DIBULATKAN 203,550.00
Halaman 141
1 2 3 4 5 6 = (3 x 5)
JUMLAH 177,000.00
OVERHEAD & PROFIT (15 %) 26,550.00
HARGA SATUAN PEKERJAAN 203,550.00
M.28 DIBULATKAN 203,550.00
JUMLAH 177,000.00
OVERHEAD & PROFIT (15 %) 26,550.00
HARGA SATUAN PEKERJAAN 203,550.00
M.29 DIBULATKAN 203,550.00
JUMLAH 198,000.00
OVERHEAD & PROFIT (15 %) 29,700.00
HARGA SATUAN PEKERJAAN 227,700.00
M.30 DIBULATKAN 227,700.00
JUMLAH 24,792.00
OVERHEAD & PROFIT (15 %) 3,718.80
Halaman 142
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 28,510.80
M.31 DIBULATKAN 28,510.80
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.1 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.2 DIBULATKAN 114,712.50
Halaman 143
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Batu 0.3500 Org 103,000.00 36,050.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.3 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.4 DIBULATKAN 114,712.50
JUMLAH 99,750.00
Halaman 144
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.5 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.6 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.7 DIBULATKAN 114,712.50
Halaman 145
1 2 3 4 5 6 = (3 x 5)
Pasir Pasang 0.0250 M3 261,800.00 -
Semen Warna 0.6500 Kg 17,391.00 -
Paku 2" - 5" 3.0000 Bh 374.00 -
UPAH
Pekerja 0.7000 Org 79,000.00 55,300.00
Tukang Batu 0.3500 Org 103,000.00 36,050.00
Kepala Tukang 0.0350 Org 112,000.00 3,920.00
Mandor 0.0350 Org 128,000.00 4,480.00
ALAT
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.8 DIBULATKAN 114,712.50
JUMLAH 99,750.00
OVERHEAD & PROFIT (15 %) 14,962.50
HARGA SATUAN PEKERJAAN 114,712.50
N.9 DIBULATKAN 114,712.50
Halaman 146
1 2 3 4 5 6 = (3 x 5)
Alat Bantu 1.0000 Lot 50,000.00 50,000.00
ALAT
JUMLAH 185,590.00
OVERHEAD & PROFIT (15 %) 27,838.50
HARGA SATUAN PEKERJAAN 213,428.50
N.10 DIBULATKAN 213,428.50
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.11 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.12 DIBULATKAN 154,100.00
JUMLAH 134,000.00
Halaman 147
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.13 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.14 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.15 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.16 DIBULATKAN 154,100.00
Halaman 148
1 2 3 4 5 6 = (3 x 5)
N.17 1 M2 PASANG BATU ANDESIT BAKAR POLOS UK. 15 X 15 CM
BAHAN
Batu Andesit Bakar Polos Uk.15x15 cm 1.0100 M2 142,800.00 -
Semen Portland 8.0000 Kg 1,275.00 -
Pasir Pasang 0.0300 M3 261,800.00 -
UPAH
Pemasangan Batu andesit 1.0000 Ls 134,000.00 134,000.00
ALAT
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.17 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.18 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.19 DIBULATKAN 154,100.00
Halaman 149
1 2 3 4 5 6 = (3 x 5)
Pasir Pasang 0.0300 M3 261,800.00 -
UPAH
Pemasangan Batu andesit 1.0000 Ls 134,000.00 134,000.00
ALAT
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.20 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.21 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.22 DIBULATKAN 154,100.00
Halaman 150
1 2 3 4 5 6 = (3 x 5)
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.23 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.24 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.25 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
Halaman 151
1 2 3 4 5 6 = (3 x 5)
N.26 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.27 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.28 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.29 DIBULATKAN 154,100.00
Halaman 152
1 2 3 4 5 6 = (3 x 5)
Batu Andesit Bakar t.3 cm Uk. 30 x 30 cm 1.0100 M2 273,700.00 -
Semen Portland 8.0000 Kg 1,275.00 -
Pasir Pasang 0.0300 M3 261,800.00 -
UPAH
Pemasangan Batu andesit 1.0000 Ls 134,000.00 134,000.00
ALAT
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.30 DIBULATKAN 154,100.00
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.31 DIBULATKAN 147,200.00
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.32 DIBULATKAN 196,650.00
Halaman 153
1 2 3 4 5 6 = (3 x 5)
Pemasangan Batu Templek 1.0000 Ls 128,000.00 128,000.00
ALAT
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.33 DIBULATKAN 147,200.00
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.34 DIBULATKAN 147,200.00
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.35 DIBULATKAN 147,200.00
JUMLAH 128,000.00
Halaman 154
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.36 DIBULATKAN 147,200.00
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.37 DIBULATKAN 147,200.00
JUMLAH 128,000.00
OVERHEAD & PROFIT (15 %) 19,200.00
HARGA SATUAN PEKERJAAN 147,200.00
N.38 DIBULATKAN 147,200.00
JUMLAH 123,000.00
OVERHEAD & PROFIT (15 %) 18,450.00
HARGA SATUAN PEKERJAAN 141,450.00
N.39 DIBULATKAN 141,450.00
Halaman 155
1 2 3 4 5 6 = (3 x 5)
N.40 1 M2 PASANG BATU BOBOS PALIMANAN CORAK UK. 20 X 40 CM
BAHAN
Batu Bobos Palimanan Corak UK. 20 X 40 CM 1.0100 M2 79,900.00 -
Semen Portland 8.0000 Kg 1,275.00 -
Pasir Pasang 0.0300 M3 261,800.00 -
UPAH
Pemasangan 1.0000 Ls 123,000.00 123,000.00
ALAT
JUMLAH 123,000.00
OVERHEAD & PROFIT (15 %) 18,450.00
HARGA SATUAN PEKERJAAN 141,450.00
N.40 DIBULATKAN 141,450.00
JUMLAH 123,000.00
OVERHEAD & PROFIT (15 %) 18,450.00
HARGA SATUAN PEKERJAAN 141,450.00
N.41 DIBULATKAN 141,450.00
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.42 DIBULATKAN 196,650.00
Halaman 156
1 2 3 4 5 6 = (3 x 5)
Pasir Pasang 0.0300 M3 261,800.00 -
UPAH
Pemasangan Batu Andesit Susun Siri 1.0000 Ls 171,000.00 171,000.00
ALAT
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.43 DIBULATKAN 196,650.00
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.44 DIBULATKAN 196,650.00
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.45 DIBULATKAN 196,650.00
Halaman 157
1 2 3 4 5 6 = (3 x 5)
JUMLAH 171,000.00
OVERHEAD & PROFIT (15 %) 25,650.00
HARGA SATUAN PEKERJAAN 196,650.00
N.46 DIBULATKAN 196,650.00
JUMLAH 123,000.00
OVERHEAD & PROFIT (15 %) 18,450.00
HARGA SATUAN PEKERJAAN 141,450.00
N.47 DIBULATKAN 141,450.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.48 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
Halaman 158
1 2 3 4 5 6 = (3 x 5)
N.49 DIBULATKAN 154,100.00
JUMLAH 134,000.00
OVERHEAD & PROFIT (15 %) 20,100.00
HARGA SATUAN PEKERJAAN 154,100.00
N.50 DIBULATKAN 154,100.00
JUMLAH 14,250.00
OVERHEAD & PROFIT (15 %) 2,137.50
HARGA SATUAN PEKERJAAN 16,387.50
N.51 DIBULATKAN 16,387.50
Halaman 159
1 2 3 4 5 6 = (3 x 5)
JUMLAH 269,400.00
OVERHEAD & PROFIT (15 %) 40,410.00
HARGA SATUAN PEKERJAAN 309,810.00
N.52 DIBULATKAN 309,810.00
JUMLAH 11,249.00
OVERHEAD & PROFIT (15 %) 1,687.35
HARGA SATUAN PEKERJAAN 12,936.35
N.53 DIBULATKAN 12,936.35
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.54 DIBULATKAN 77,526.10
Halaman 160
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.4500 Org 110,000.00 49,500.00
Kepala Tukang 0.0450 Org 112,000.00 5,040.00
Mandor 0.0080 Org 128,000.00 1,024.00
ALAT
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.55 DIBULATKAN 77,526.10
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.56 DIBULATKAN 77,526.10
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.57 DIBULATKAN 77,526.10
Halaman 161
1 2 3 4 5 6 = (3 x 5)
N.58 1 M2 PASANG DINDING PARTISI TEAKWOOD RANGKAP, RANGKA KAYU BORNEO
BAHAN
Kayu Borneo, Balok 0.0280 M3 4,838,200.00 -
Kayu Borneo, Papan 0.0070 M3 7,096,650.00 -
Paku Biasa 2" - 5" 0.1500 Kg 18,700.00 -
Lem Kayu 0.5600 Kg 23,800.00 -
Teackwood 4 mm 0.8600 Lbr 140,250.00 -
UPAH
Pekerja 0.1500 Org 79,000.00 11,850.00
Tukang Kayu 0.4500 Org 110,000.00 49,500.00
Kepala Tukang 0.0450 Org 112,000.00 5,040.00
Mandor 0.0080 Org 128,000.00 1,024.00
ALAT
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.58 DIBULATKAN 77,526.10
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.59 DIBULATKAN 77,526.10
N.60 1 M2 PASANG DINDING PARTISI MULTIPLEK 9 MM, RANGKA KAYU KRUING (DUA MUKA)
BAHAN
Kayu Kruing, Balok 0.0280 M3 8,206,750.00 -
Kayu Kruing, Papan 0.0070 M3 9,151,950.00 -
Paku Biasa 2" - 5" 0.1500 Kg 18,700.00 -
Multiplek 9 mm 0.6944 Lbr 157,250.00 -
UPAH
Pekerja 0.1500 Org 79,000.00 11,850.00
Halaman 162
1 2 3 4 5 6 = (3 x 5)
Tukang Kayu 0.4500 Org 110,000.00 49,500.00
Kepala Tukang 0.0450 Org 112,000.00 5,040.00
Mandor 0.0080 Org 128,000.00 1,024.00
ALAT
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.60 DIBULATKAN 77,526.10
N.61 1 M2 PASANG DINDING PARTISI MULTIPLEK 9 MM, RANGKA KAYU KRUING (SATU MUKA)
BAHAN
Kayu Kruing, Balok 0.0280 M3 8,206,750.00 -
Kayu Kruing, Papan 0.0070 M3 9,151,950.00 -
Paku Biasa 2" - 5" 0.1500 Kg 18,700.00 -
Multiplek 9 mm 0.3472 Lbr 157,250.00 -
UPAH
Pekerja 0.1500 Org 79,000.00 11,850.00
Tukang Kayu 0.4500 Org 110,000.00 49,500.00
Kepala Tukang 0.0450 Org 112,000.00 5,040.00
Mandor 0.0080 Org 128,000.00 1,024.00
ALAT
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.61 DIBULATKAN 77,526.10
JUMLAH 67,414.00
OVERHEAD & PROFIT (15 %) 10,112.10
HARGA SATUAN PEKERJAAN 77,526.10
N.62 DIBULATKAN 77,526.10
Halaman 163
1 2 3 4 5 6 = (3 x 5)
N.63 1 M2 PASANG PARTISI RANGKA METAL FURING LAPIS GYPSUM DUA MUKA
BAHAN
Rangka Metal C Stud Lebar 75 mm 1.9500 M' 90,950.00 -
Gypsum 0.6944 Lbr 82,450.00 -
Skrup 0.1700 Kg 23,800.00 -
Cotton Plaster 0.0720 Bh 21,250.00 -
Compoun 0.1250 Zak 79,050.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Kayu 0.6000 Org 110,000.00 66,000.00
Kepala Tukang 0.0600 Org 112,000.00 6,720.00
Mandor 0.0090 Org 128,000.00 1,152.00
ALAT
JUMLAH 89,672.00
OVERHEAD & PROFIT (15 %) 13,450.80
HARGA SATUAN PEKERJAAN 103,122.80
N.63 DIBULATKAN 103,122.80
N.64 1 M2 PASANG PARTISI RANGKA METAL FURING LAPIS GRC DUA MUKA
BAHAN
Rangka Metal C Stud Lebar 75 mm 1.9500 M' 90,950.00 -
GRC 8 mm 0.6944 Lbr 68,000.00 -
Skrup 0.1700 Kg 23,800.00 -
Cotton Plaster 0.0720 Bh 21,250.00 -
Compoun 0.1250 Zak 79,050.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Kayu 0.6000 Org 110,000.00 66,000.00
Kepala Tukang 0.0600 Org 112,000.00 6,720.00
Mandor 0.0090 Org 128,000.00 1,152.00
ALAT
JUMLAH 89,672.00
OVERHEAD & PROFIT (15 %) 13,450.80
HARGA SATUAN PEKERJAAN 103,122.80
N.64 DIBULATKAN 103,122.80
N.65 1 M2 PASANG PARTISI RANGKA BLOCKBOARD DUA MUKA FINISH HPL (POLOS/BIASA)
BAHAN
Rangka Partisi Block Board 18 mm 0.3472 M2 95,329.86 -
Multiplek 9 mm 0.6944 Lbr 157,250.00 -
Lapisan HPL 0.6944 Lbr 322,150.00 -
List Stainless T 4.0000 M' 42,500.00 -
Lem kayu 2.0000 Kg 23,800.00 -
Halaman 164
1 2 3 4 5 6 = (3 x 5)
UPAH
Pekerja 0.7200 Org 79,000.00 56,880.00
Tukang Kayu 1.2800 Org 110,000.00 140,800.00
Kepala Tukang 0.1280 Org 112,000.00 14,336.00
Mandor 0.0360 Org 128,000.00 4,608.00
ALAT
JUMLAH 216,624.00
OVERHEAD & PROFIT (15 %) 32,493.60
HARGA SATUAN PEKERJAAN 249,117.60
N.65 DIBULATKAN 249,117.60
N.66 1 M2 PASANG PARTISI RANGKA BLOCKBOARD SATU MUKA FINISH HPL (POLOS/BIASA)
BAHAN
Rangka Partisi Block Board 18 mm 0.3472 M2 95,329.86 -
Multiplek 9 mm 0.3472 Lbr 157,250.00 -
Lapisan HPL 0.3472 Lbr 322,150.00 -
List Stainless T 2.0000 M' 42,500.00 -
Lem kayu 2.0000 Kg 23,800.00 -
UPAH
Pekerja 0.7200 Org 79,000.00 56,880.00
Tukang Kayu 1.2800 Org 110,000.00 140,800.00
Kepala Tukang 0.1280 Org 112,000.00 14,336.00
Mandor 0.0360 Org 128,000.00 4,608.00
ALAT
JUMLAH 216,624.00
OVERHEAD & PROFIT (15 %) 32,493.60
HARGA SATUAN PEKERJAAN 249,117.60
N.66 DIBULATKAN 249,117.60
N.67 1 M2 PASANG PARTISI RANGKA BLOCKBOARD DUA MUKA FINISH HPL (TEXTURE)
BAHAN
Rangka Partisi Block Board 18 mm 0.3472 M2 95,329.86 -
Multiplek 9 mm 0.6944 Lbr 157,250.00 -
Lapisan HPL 0.6944 Lbr 273,000.00 -
List Stainless T 4.0000 M' 42,500.00 -
Lem kayu 2.0000 Kg 23,800.00 -
UPAH
Pekerja 0.7200 Org 79,000.00 56,880.00
Tukang Kayu 1.2800 Org 110,000.00 140,800.00
Kepala Tukang 0.1280 Org 112,000.00 14,336.00
Mandor 0.0360 Org 128,000.00 4,608.00
ALAT
JUMLAH 216,624.00
Halaman 165
1 2 3 4 5 6 = (3 x 5)
OVERHEAD & PROFIT (15 %) 32,493.60
HARGA SATUAN PEKERJAAN 249,117.60
N.67 DIBULATKAN 249,117.60
N.68 1 M2 PASANG PARTISI RANGKA BLOCKBOARD SATU MUKA FINISH HPL (TEXTURE)
BAHAN
Rangka Partisi Block Board 18 mm 0.3472 M2 95,329.86 -
Multiplek 9 mm 0.3472 Lbr 157,250.00 -
Lapisan HPL 0.3472 Lbr 273,000.00 -
List Stainless T 2.0000 M' 42,500.00 -
Lem kayu 2.0000 Kg 23,800.00 -
UPAH
Pekerja 0.7200 Org 79,000.00 56,880.00
Tukang Kayu 1.2800 Org 110,000.00 140,800.00
Kepala Tukang 0.1280 Org 112,000.00 14,336.00
Mandor 0.0360 Org 128,000.00 4,608.00
ALAT
JUMLAH 216,624.00
OVERHEAD & PROFIT (15 %) 32,493.60
HARGA SATUAN PEKERJAAN 249,117.60
N.68 DIBULATKAN 249,117.60
JUMLAH 24,740.00
OVERHEAD & PROFIT (15 %) 3,711.00
HARGA SATUAN PEKERJAAN 28,451.00
N.69 DIBULATKAN 28,451.00
Halaman 166
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0120 Org 112,000.00 1,344.00
Mandor 0.0190 Org 128,000.00 2,432.00
ALAT
JUMLAH 46,276.00
OVERHEAD & PROFIT (15 %) 6,941.40
HARGA SATUAN PEKERJAAN 53,217.40
O.1 DIBULATKAN 53,217.40
JUMLAH 46,276.00
OVERHEAD & PROFIT (15 %) 6,941.40
HARGA SATUAN PEKERJAAN 53,217.40
O.2 DIBULATKAN 53,217.40
JUMLAH 46,276.00
OVERHEAD & PROFIT (15 %) 6,941.40
HARGA SATUAN PEKERJAAN 53,217.40
O.3 DIBULATKAN 53,217.40
Halaman 167
1 2 3 4 5 6 = (3 x 5)
JUMLAH 82,016.40
OVERHEAD & PROFIT (15 %) 12,302.46
HARGA SATUAN PEKERJAAN 94,318.86
O.4 DIBULATKAN 94,318.86
JUMLAH 82,016.40
OVERHEAD & PROFIT (15 %) 12,302.46
HARGA SATUAN PEKERJAAN 94,318.86
O.5 DIBULATKAN 94,318.86
Halaman 168
1 2 3 4 5 6 = (3 x 5)
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.6 DIBULATKAN 91,349.10
JUMLAH 82,016.40
OVERHEAD & PROFIT (15 %) 12,302.46
HARGA SATUAN PEKERJAAN 94,318.86
O.7 DIBULATKAN 94,318.86
JUMLAH 82,016.40
OVERHEAD & PROFIT (15 %) 12,302.46
HARGA SATUAN PEKERJAAN 94,318.86
O.8 DIBULATKAN 94,318.86
Halaman 169
1 2 3 4 5 6 = (3 x 5)
Kepala Tukang 0.0250 OH 112,000.00 2,800.00
Mandor 0.0030 OH 128,000.00 384.00
Peralatan 1.0000 Lot 5,000.00 5,000.00
ALAT
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.9 DIBULATKAN 91,349.10
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.10 DIBULATKAN 91,349.10
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.11 DIBULATKAN 91,349.10
Halaman 170
1 2 3 4 5 6 = (3 x 5)
Paving Ton Warna 8 cm (Uk. 20 x 10 cm) 1.0100 M2 116,000.00 -
Pasir Urug 0.1000 M3 194,650.00 -
UPAH
Pekerja 0.2500 OH 79,000.00 19,750.00
Tukang Batu 0.5000 OH 103,000.00 51,500.00
Kepala Tukang 0.0250 OH 112,000.00 2,800.00
Mandor 0.0030 OH 128,000.00 384.00
Peralatan 1.0000 Lot 5,000.00 5,000.00
ALAT
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.12 DIBULATKAN 91,349.10
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
HARGA SATUAN PEKERJAAN 91,349.10
O.13 DIBULATKAN 91,349.10
JUMLAH 79,434.00
OVERHEAD & PROFIT (15 %) 11,915.10
Halaman 171
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 91,349.10
O.14 DIBULATKAN 91,349.10
ALAT
JUMLAH 0.00
OVERHEAD & PROFIT (15 %) 0.00
HARGA SATUAN PEKERJAAN 0.00
O.15 DIBULATKAN 0.00
ALAT
JUMLAH 0.00
OVERHEAD & PROFIT (15 %) 0.00
HARGA SATUAN PEKERJAAN 0.00
O.16 DIBULATKAN 0.00
P PEKERJAAN PENGECATAN
P.1 1 M2 MENGIKIS / MENGEROK PERMUKAAN CAT DINDING LAMA
BAHAN
Soda Api 0.0500 Kg 49,300.00 -
UPAH
Pekerja 0.1500 Org 79,000.00 11,850.00
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 12,234.00
OVERHEAD & PROFIT (15 %) 1,835.10
HARGA SATUAN PEKERJAAN 14,069.10
P.1 DIBULATKAN 14,069.10
Halaman 172
1 2 3 4 5 6 = (3 x 5)
Dempul Jadi 0.0800 Kg 58,650.00 -
Minyak Cat 0.0200 Ltr 32,300.00 -
Batu Apung 0.0100 Kg 62,900.00 -
Ampelas 0.5000 Lbr 6,800.00 -
UPAH
Pekerja 0.0400 Org 79,000.00 3,160.00
Tukang Cat 0.0400 Org 103,000.00 4,120.00
Kepala Tukang 0.0040 Org 112,000.00 448.00
Mandor 0.0025 Org 128,000.00 320.00
ALAT
JUMLAH 8,048.00
OVERHEAD & PROFIT (15 %) 1,207.20
HARGA SATUAN PEKERJAAN 9,255.20
P.2 DIBULATKAN 9,255.20
JUMLAH 14,415.00
OVERHEAD & PROFIT (15 %) 2,162.25
HARGA SATUAN PEKERJAAN 16,577.25
P.3 DIBULATKAN 16,577.25
P.4 1 M2 PENGECATAN BID. KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Cat Meni 0.2000 Kg 41,650.00 -
Plamir 0.1500 Kg 47,600.00 -
Cat Dasar 0.1700 Kg 65,450.00 -
Cat Penutup 2 x 0.2600 Kg 65,450.00 -
Ampelas 0.0200 Lbr 6,800.00 -
Minyak Cat 0.0300 Ltr 32,300.00 -
Kuas 0.0100 Bh 11,050.00 -
UPAH
Halaman 173
1 2 3 4 5 6 = (3 x 5)
Pekerja 0.0700 Org 79,000.00 5,530.00
Tukang Cat 0.0090 Org 103,000.00 927.00
Kepala Tukang 0.0060 Org 112,000.00 672.00
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 7,513.00
OVERHEAD & PROFIT (15 %) 1,126.95
HARGA SATUAN PEKERJAAN 8,639.95
P.4 DIBULATKAN 8,639.95
JUMLAH 7,449.00
OVERHEAD & PROFIT (15 %) 1,117.35
HARGA SATUAN PEKERJAAN 8,566.35
P.5 DIBULATKAN 8,566.35
P.6 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP
BAHAN
Cat Meni 0.2000 Kg 41,650.00 -
Plamir 0.1500 Kg 47,600.00 -
Cat Dasar 0.1700 Kg 65,450.00 -
Cat Penutup 3 x 0.3500 Kg 65,450.00 -
Ampelas 0.0200 Lbr 6,800.00 -
Minyak Cat 0.0300 Ltr 32,300.00 -
Kuas 0.0100 Bh 11,050.00 -
UPAH
Pekerja 0.0700 Org 79,000.00 5,530.00
Tukang Cat 0.1050 Org 103,000.00 10,815.00
Kepala Tukang 0.0040 Org 112,000.00 448.00
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 17,177.00
OVERHEAD & PROFIT (15 %) 2,576.55
Halaman 174
1 2 3 4 5 6 = (3 x 5)
HARGA SATUAN PEKERJAAN 19,753.55
P.6 DIBULATKAN 19,753.55
P.7 M' PENGECATAN KUSEN PINTU/JENDELA KAYU, 1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP
BAHAN
Cat Meni 0.1000 Kg 41,650.00 -
Plamir 0.0750 Kg 47,600.00 -
Cat Dasar 0.0850 Kg 65,450.00 -
Cat Penutup 3 x 0.1750 Kg 65,450.00 -
Ampelas 0.0100 Lbr 6,800.00 -
Minyak Cat 0.0150 Ltr 32,300.00 -
Kuas 0.0050 Bh 11,050.00 -
UPAH
Pekerja 0.0350 Org 79,000.00 2,765.00
Tukang Cat 0.0525 Org 103,000.00 5,407.50
Kepala Tukang 0.0020 Org 112,000.00 224.00
Mandor 0.0015 Org 128,000.00 192.00
ALAT
JUMLAH 8,588.50
OVERHEAD & PROFIT (15 %) 1,288.28
HARGA SATUAN PEKERJAAN 9,876.78
P.7 DIBULATKAN 9,876.78
JUMLAH 97,240.00
OVERHEAD & PROFIT (15 %) 14,586.00
HARGA SATUAN PEKERJAAN 111,826.00
P.8 DIBULATKAN 111,826.00
Halaman 175
1 2 3 4 5 6 = (3 x 5)
BAHAN
Wood Filler 0.0750 Kg 49,300.00 -
Woodstain 0.1250 Ltr 84,150.00 -
Sending sealer 0.1750 Ltr 76,500.00 -
Melamic 0.1250 Ltr 84,150.00 -
Ampelas 0.2500 Lbr 6,800.00 -
Minyak Cat / Thiner 0.2500 Ltr 32,300.00 -
Alat Bantu (Alat semprot, dll) 0.5000 Ls 30,000.00 -
UPAH
Pekerja 0.2500 Org 79,000.00 19,750.00
Tukang Cat 0.2500 Org 103,000.00 25,750.00
Kepala Tukang 0.0250 Org 112,000.00 2,800.00
Mandor 0.0025 Org 128,000.00 320.00
ALAT
JUMLAH 48,620.00
OVERHEAD & PROFIT (15 %) 7,293.00
HARGA SATUAN PEKERJAAN 55,913.00
P.9 DIBULATKAN 55,913.00
JUMLAH 11,516.00
OVERHEAD & PROFIT (15 %) 1,727.40
HARGA SATUAN PEKERJAAN 13,243.40
P.10 DIBULATKAN 13,243.40
Halaman 176
1 2 3 4 5 6 = (3 x 5)
JUMLAH 8,668.00
OVERHEAD & PROFIT (15 %) 1,300.20
HARGA SATUAN PEKERJAAN 9,968.20
P.11 DIBULATKAN 9,968.20
P.12 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Plamir 0.1000 Kg 21,250.00 -
Cat Dasar 0.1000 Kg 42,500.00 -
Cat Penutup 2x 0.2600 Kg 42,500.00 -
Roll Cat 0.0100 Bh 31,450.00 -
Ampelas 0.5000 Lbr 6,800.00 -
UPAH
Pekerja 0.0200 Org 79,000.00 1,580.00
Tukang Cat 0.0630 Org 103,000.00 6,489.00
Kepala Tukang 0.0063 Org 112,000.00 705.60
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 9,158.60
OVERHEAD & PROFIT (15 %) 1,373.79
HARGA SATUAN PEKERJAAN 10,532.39
P.12 DIBULATKAN 10,532.39
P.13 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP DULUX
BAHAN
Plamir 0.1000 Kg 21,250.00 -
Cat Dasar Dulux 0.1000 Kg 61,200.00 -
Cat Penutup 2x Dulux 0.2600 Kg 61,200.00 -
Roll Cat 0.0100 Bh 31,450.00 -
Ampelas 0.5000 Lbr 6,800.00 -
UPAH
Pekerja 0.0200 Org 79,000.00 1,580.00
Tukang Cat 0.0630 Org 103,000.00 6,489.00
Kepala Tukang 0.0063 Org 112,000.00 705.60
Mandor 0.0025 Org 128,000.00 320.00
ALAT
JUMLAH 9,094.60
OVERHEAD & PROFIT (15 %) 1,364.19
HARGA SATUAN PEKERJAAN 10,458.79
P.13 DIBULATKAN 10,458.79
P.14 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Halaman 177
1 2 3 4 5 6 = (3 x 5)
Cat Dasar 0.1200 Kg 42,500.00 -
Cat Penutup 2x 0.1800 Kg 42,500.00 -
Roll Cat 0.0100 Bh 31,450.00 -
Ampelas 0.5000 Lbr 6,800.00 -
UPAH
Pekerja 0.0280 Org 79,000.00 2,212.00
Tukang Cat 0.0420 Org 103,000.00 4,326.00
Kepala Tukang 0.0042 Org 112,000.00 470.40
Mandor 0.0030 Org 128,000.00 384.00
ALAT
JUMLAH 7,392.40
OVERHEAD & PROFIT (15 %) 1,108.86
HARGA SATUAN PEKERJAAN 8,501.26
P.14 DIBULATKAN 8,501.26
P.15 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP DULUX
BAHAN
Cat Dasar Dulux 0.1200 Kg 61,200.00 -
Cat Penutup 2x Dulux 0.1800 Kg 61,200.00 -
Roll Cat 0.0100 Bh 31,450.00 -
Ampelas 0.5000 Lbr 6,800.00 -
UPAH
Pekerja 0.0280 Org 79,000.00 2,212.00
Tukang Cat 0.0420 Org 103,000.00 4,326.00
Kepala Tukang 0.0042 Org 112,000.00 470.40
Mandor 0.0025 Org 128,000.00 320.00
ALAT
JUMLAH 7,328.40
OVERHEAD & PROFIT (15 %) 1,099.26
HARGA SATUAN PEKERJAAN 8,427.66
P.15 DIBULATKAN 8,427.66
Halaman 178
1 2 3 4 5 6 = (3 x 5)
JUMLAH 9,158.60
OVERHEAD & PROFIT (15 %) 1,373.79
HARGA SATUAN PEKERJAAN 10,532.39
P.16 DIBULATKAN 10,532.39
JUMLAH 24,740.00
OVERHEAD & PROFIT (15 %) 3,711.00
HARGA SATUAN PEKERJAAN 28,451.00
P.17 DIBULATKAN 28,451.00
JUMLAH 25,700.00
OVERHEAD & PROFIT (15 %) 3,855.00
HARGA SATUAN PEKERJAAN 29,555.00
P.18 DIBULATKAN 29,555.00
Halaman 179
1 2 3 4 5 6 = (3 x 5)
Mandor 0.0100 Org 128,000.00 1,280.00
ALAT
JUMLAH 25,700.00
OVERHEAD & PROFIT (15 %) 3,855.00
HARGA SATUAN PEKERJAAN 29,555.00
P.19 DIBULATKAN 29,555.00
JUMLAH 51,340.00
OVERHEAD & PROFIT (15 %) 7,701.00
HARGA SATUAN PEKERJAAN 59,041.00
P.20 DIBULATKAN 59,041.00
JUMLAH 51,340.00
OVERHEAD & PROFIT (15 %) 7,701.00
HARGA SATUAN PEKERJAAN 59,041.00
P.21 DIBULATKAN 59,041.00
Halaman 180
1 2 3 4 5 6 = (3 x 5)
P.22 1 M2 MENGECAT BESI LAMA ( 3x )
BAHAN
Cat Besi 0.2000 Kg 66,300.00 -
Ampelas Besi 0.4000 Lbr 6,800.00 -
Minyak Cat Thiner 0.1500 Ltr 32,300.00 -
Kuas 0.0500 Bh 11,050.00 -
UPAH
Pekerja 0.2000 Org 79,000.00 15,800.00
Tukang Cat 0.2000 Org 103,000.00 20,600.00
Kepala Tukang 0.0020 Org 112,000.00 224.00
Mandor 0.0020 Org 128,000.00 256.00
ALAT
JUMLAH 36,880.00
OVERHEAD & PROFIT (15 %) 5,532.00
HARGA SATUAN PEKERJAAN 42,412.00
P.22 DIBULATKAN 42,412.00
Indramayu,
Febru
0.00
KEPALA DINA
PEKERJAAN UMUM DAN PE
KABUPATEN INDR
Halaman 181
ATEN INDRAMAYU INDEX :
DAN PENATAAN RUANG RHEAD & PROFIT (15 %) = 15.0%
274264 Fax (0234) 272741 1.0000 LANTAI 1 = 1.000
U - 45212 LANTAI 2 = 1.090
LANTAI 3 = 1.120
LANTAI 4 = 1.135
ERJAAN (AHSP) LANTAI 5 = 1.162
PERUMAHAN
2022
)
AR)
30,324.60 - 30,324.60
374.00 - 374.00
21,818.65 - 21,818.65
- - 1,120.00 0.0100
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 640.00 0.0050
30,324.60 - 30,324.60
374.00 - 374.00
21,818.65 - 21,818.65
- - 23,600.00 0.2000
- - 9,800.00 0.1000
- - 1,030.00 0.0100
- - 1,580.00 0.0200
- 25,000.00 25,000.00
Halaman 182
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
454,869.00 - 454,869.00
81,812.50 - 81,812.50
935.00 - 935.00
1,496.00 - 1,496.00
952.00 - 952.00
8,415.00 - 8,415.00
44,625.00 - 44,625.00
39,270.00 - 39,270.00
29,665.00 - 29,665.00
43,860.00 - 43,860.00
28,050.00 - 28,050.00
11,560.00 - 11,560.00
7,276.00 - 7,276.00
20,145.00 - 20,145.00
- - 158,000.00 2.0000
- - 220,000.00 2.0000
- - 103,000.00 1.0000
- - 33,600.00 0.3000
- - 6,400.00 0.0500
85,680.00 - 85,680.00
81,812.50 - 81,812.50
312,120.00 - 312,120.00
3,187.50 - 3,187.50
1,483.25 - 1,483.25
2,631.60 - 2,631.60
26,392.50 - 26,392.50
13,464.00 - 13,464.00
Halaman 183
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 15,800.00 0.2000
- - 44,000.00 0.4000
- - 2,240.00 0.0200
- - 2,560.00 0.0200
35,000.00 - 35,000.00
42,166.80 - 42,166.80
177,500.40 - 177,500.40
3,740.00 - 3,740.00
- - 30,000.00
- - 25,000.00
- - 7,900.00 0.1000
- - 6,400.00 0.0500
0.00 0.00 14,300.00
0.00 0.00 2,145.00
0.00 0.00 16,445.00
0.00 0.00 16,445.00
26,562.50 - 26,562.50
- - 79,000.00 1.0000
- - 220,000.00 2.0000
- - 22,400.00 0.2000
- - 6,400.00 0.0500
Halaman 184
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
26,562.50 0.00 354,362.50
3,984.38 0.00 53,154.38
30,546.88 0.00 407,516.88
30,546.88 0.00 407,516.00
22,000.00 - 22,000.00
18,000.00 - 18,000.00
20,000.00 - 20,000.00
2,500.00 - 2,500.00
112,210.20 - 112,210.20
1,496.00 - 1,496.00
60,690.00 - 60,690.00
- - 33,000.00 0.3000
- - 3,360.00 0.0300
5,100.00 - 5,100.00
- - 948.00 0.0120
- - 204.80 0.0016
Halaman 185
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
5,100.00 0.00 6,252.80
765.00 0.00 937.92
5,865.00 0.00 7,190.72
5,865.00 0.00 7,190.00
145,350.00 - 145,350.00
49,871.20 - 49,871.20
9,350.00 - 9,350.00
- - 22,000.00 0.2000
- - 22,400.00 0.2000
- - 11,850.00 0.1500
- - 2,176.00 0.0170
- - 1,053,386.00 13.3340
- - 85,248.00 0.6660
- - 526,693.00 6.6670
- - 42,624.00 0.3330
Halaman 186
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 59,250.00 0.7500
- - 3,200.00 0.0250
- - 71,100.00 0.9000
- - 5,760.00 0.0450
- - 58,065.00 1.0570
- - 9,344.00 0.0670
- - 79,000.00 1.0000
- - 4,096.00 0.0320
Halaman 187
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 118,500.00 1.5000
- - 7,680.00 0.0600
- - 94,800.00 1.2000
- - 5,760.00 0.0450
- - 3,950.00 0.0500
- - 640.00 0.0050
- - 26,070.00 0.3300
- - 1,280.00 0.0100
- - 39,500.00 0.5000
- - 6,400.00 0.0500
Halaman 188
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 3,523.40 0.0446
- - 576.00 0.0045
- 5,575.00 5,575.00
0.00 5,575.00 9,674.40
0.00 836.25 1,451.16
0.00 6,411.25 11,125.56
0.00 6,411.25 11,125.00
82,620.00 - 82,620.00
- - 23,700.00 0.3000
- - 1,280.00 0.0100
233,580.00 233,580.00
- - 23,700.00 0.3000
- - 1,280.00 0.0100
Halaman 189
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
240,720.00 240,720.00
- - 23,700.00 0.3000
- - 1,280.00 0.0100
284,580.00 - 284,580.00
- - 19,750.00 0.2500
- - 3,200.00 0.0250
219,300.00 - 219,300.00
- - 19,750.00 0.2500
- - 3,200.00 0.0250
42,967.50 - 42,967.50
35,496.00 - 35,496.00
2,618.00 - 2,618.00
- - 79,000.00 1.0000
- - 640.00 0.0050
Halaman 190
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
343,740.00 - 343,740.00
340,425.00 - 340,425.00
111,788.60 - 111,788.60
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
343,740.00 - 343,740.00
257,550.00 - 257,550.00
126,973.00 - 126,973.00
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
343,740.00 - 343,740.00
207,825.00 - 207,825.00
Halaman 191
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
136,136.00 - 136,136.00
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
343,740.00 - 343,740.00
173,400.00 - 173,400.00
142,419.20 - 142,419.20
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
173,400.00 - 173,400.00
142,419.20 - 142,419.20
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
Halaman 192
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
257,550.00 - 257,550.00
126,973.00 - 126,973.00
- - 118,500.00 1.5000
- - 77,250.00 0.7500
- - 8,400.00 0.0750
- - 9,600.00 0.0750
343,740.00 - 343,740.00
84,088.80 - 84,088.80
- - 61,620.00 0.7800
- - 40,170.00 0.3900
- - 4,368.00 0.0390
- - 4,992.00 0.0390
137,496.00 - 137,496.00
247,350.00 - 247,350.00
92,554.80 - 92,554.80
136,843.20 - 136,843.20
1,606,500.00 - 1,606,500.00
55,080.00 - 55,080.00
- - 268,600.00 3.4000
- - 87,550.00 0.8500
- - 9,520.00 0.0850
- - 21,760.00 0.1700
Halaman 193
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 8,405.60 0.1064
- - 2,926.00 0.0266
- - 1,356.80 0.0106
56,705.88 - 56,705.88
31,712.31 - 31,712.31
- - 3,246.90 0.0411
- - 2,266.00 0.0206
- - 524.80 0.0041
- - 18,960.00 0.2400
- - 6,600.00 0.0600
- - 3,072.00 0.0240
Halaman 194
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
127,586.43 - 127,586.43
70,364.70 - 70,364.70
- - 7,212.70 0.0913
- - 2,508.00 0.0228
- - 1,164.80 0.0091
65,450.00 - 65,450.00
18,321.75 - 18,321.75
10,472.00 - 10,472.00
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
Halaman 195
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
65,450.00 - 65,450.00
14,662.50 - 14,662.50
11,257.40 - 11,257.40
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
65,450.00 - 65,450.00
12,342.00 - 12,342.00
11,781.00 - 11,781.00
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
130,900.00 - 130,900.00
28,305.00 - 28,305.00
26,703.60 - 26,703.60
- - 47,400.00 0.6000
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 3,840.00 0.0300
Halaman 196
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
213,794.89 0.00 298,986.89
213,794.89 0.00 298,986.00
722,500.00 - 722,500.00
17,850.00 - 17,850.00
8,377.60 - 8,377.60
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
397,800.00 - 397,800.00
17,850.00 - 17,850.00
8,377.60 - 8,377.60
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
67,200.00 - 67,200.00
2,010.25 - 2,010.25
- - 52,930.00 0.6700
- - 13,390.00 0.1300
- - 1,456.00 0.0130
- - 384.00 0.0030
Halaman 197
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- 13,737.03 13,737.03
85,680.00 - 85,680.00
2,677.50 - 2,677.50
- - 53,009.00 0.6710
- - 13,390.00 0.1300
- - 1,456.00 0.0130
- - 384.00 0.0030
- 15,659.65 15,659.65
180,625.00 - 180,625.00
15,465.75 - 15,465.75
101,578.40 - 101,578.40
3,570.00 - 3,570.00
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 19,200.00 0.1500
Halaman 198
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
13,219.20 - 13,219.20
8,115.80 - 8,115.80
- - 20,540.00 0.2600
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 1,664.00 0.0130
10,608.00 - 10,608.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 2,816.00 0.0220
8,812.80 - 8,812.80
9,163.00 - 9,163.00
- - 31,600.00 0.4000
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 2,816.00 0.0220
Halaman 199
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
64,600.00 - 64,600.00
- - 31,600.00 0.4000
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 2,816.00 0.0220
8,083.50 - 8,083.50
3,141.60 - 3,141.60
- - 23,700.00 0.3000
- - 15,450.00 0.1500
- - 1,680.00 0.0150
- - 1,920.00 0.0150
4,143.75 - 4,143.75
- - 15,800.00 0.2000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,280.00 0.0100
Halaman 200
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
19,720.00 - 19,720.00
- - 15,800.00 0.2000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,280.00 0.0100
5,508.00 - 5,508.00
1,570.80 - 1,570.80
- - 23,700.00 0.3000
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 1,920.00 0.0150
637.50 - 637.50
3,403.40 - 3,403.40
- - 6,320.00 0.3000
- - 41,200.00 0.1000
- - 4,480.00 0.0100
- - 512.00 0.0150
Halaman 201
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
11,827,750.00 - 11,827,750.00
23,375.00 - 23,375.00
23,800.00 - 23,800.00
- - 553,000.00 7.0000
- - 2,310,000.00 21.0000
- - 235,200.00 2.1000
- - 44,800.00 0.3500
5,322,020.00 - 5,322,020.00
23,375.00 - 23,375.00
23,800.00 - 23,800.00
- - 553,000.00 7.0000
- - 2,310,000.00 21.0000
- - 235,200.00 2.1000
- - 44,800.00 0.3500
9,027,425.00 - 9,027,425.00
23,375.00 - 23,375.00
23,800.00 - 23,800.00
- - 553,000.00 7.0000
- - 2,310,000.00 21.0000
- - 235,200.00 2.1000
- - 44,800.00 0.3500
Halaman 202
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
115,005.00 - 115,005.00
2,280.00 - 2,280.00
1,870.00 - 1,870.00
- - 3,397.00 0.0430
- - 4,644.00 0.0430
- - 481.60 0.0043
- - 268.80 0.0021
92,565.00 - 92,565.00
2,280.00 - 2,280.00
1,870.00 - 1,870.00
- - 3,397.00 0.0430
- - 4,644.00 0.0430
- - 481.60 0.0043
- - 268.80 0.0021
129,965.00 - 129,965.00
38,000.00 - 38,000.00
1,870.00 - 1,870.00
Halaman 203
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 33,970.00 0.4300
- - 46,440.00 0.4300
- - 4,816.00 0.0430
- - 2,688.00 0.0210
115,005.00 - 115,005.00
38,000.00 - 38,000.00
1,870.00 - 1,870.00
- - 33,970.00 0.4300
- - 46,440.00 0.4300
- - 4,816.00 0.0430
- - 2,688.00 0.0210
119,680.00 - 119,680.00
38,000.00 - 38,000.00
1,870.00 - 1,870.00
- - 33,970.00 0.4300
- - 46,440.00 0.4300
- - 4,816.00 0.0430
- - 2,688.00 0.0210
Halaman 204
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
106,590.00 - 106,590.00
38,000.00 - 38,000.00
1,870.00 - 1,870.00
- - 33,970.00 0.4300
- - 46,440.00 0.4300
- - 4,816.00 0.0430
- - 2,688.00 0.0210
494,598.00 - 494,598.00
11,900.00 - 11,900.00
- - 79,000.00 1.0000
- - 330,000.00 3.0000
- - 3,360.00 0.0300
- - 6,400.00 0.0500
366,078.00 - 366,078.00
11,900.00 - 11,900.00
- - 79,000.00 1.0000
- - 330,000.00 3.0000
- - 3,360.00 0.0300
- - 6,400.00 0.0500
Halaman 205
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
434,674.70 0.00 916,248.70
434,674.70 0.00 916,248.00
655,894.00 - 655,894.00
11,900.00 - 11,900.00
- - 79,000.00 1.0000
- - 330,000.00 3.0000
- - 3,360.00 0.0300
- - 6,400.00 0.0500
432,773.25 - 432,773.25
11,900.00 - 11,900.00
- - 79,000.00 1.0000
- - 330,000.00 3.0000
- - 3,360.00 0.0300
- - 6,400.00 0.0500
320,318.25 - 320,318.25
11,900.00 - 11,900.00
- - 79,000.00 1.0000
- - 330,000.00 3.0000
- - 3,360.00 0.0300
- - 6,400.00 0.0500
Halaman 206
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
332,218.25 0.00 750,978.25
49,832.74 0.00 112,646.74
382,050.99 0.00 863,624.99
382,050.99 0.00 863,624.00
741,897.00 - 741,897.00
2,805.00 - 2,805.00
- - 52,930.00 0.6700
- - 220,000.00 2.0000
- - 22,400.00 0.2000
- - 42,880.00 0.3350
549,117.00 - 549,117.00
2,805.00 - 2,805.00
- - 52,930.00 0.6700
- - 220,000.00 2.0000
- - 22,400.00 0.2000
- - 42,880.00 0.3350
309,123.75 - 309,123.75
663.00 - 663.00
11,900.00 - 11,900.00
140,250.00 - 140,250.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
Halaman 207
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 23,520.00 0.2100
- - 4,480.00 0.0350
228,798.75 - 228,798.75
663.00 - 663.00
11,900.00 - 11,900.00
140,250.00 - 140,250.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
- - 23,520.00 0.2100
- - 4,480.00 0.0350
309,123.75 - 309,123.75
663.00 - 663.00
11,900.00 - 11,900.00
157,250.00 - 157,250.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
- - 23,520.00 0.2100
- - 4,480.00 0.0350
Halaman 208
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
228,798.75 - 228,798.75
663.00 - 663.00
11,900.00 - 11,900.00
62,050.00 - 62,050.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
- - 23,520.00 0.2100
- - 4,480.00 0.0350
228,798.75 - 228,798.75
663.00 - 663.00
11,900.00 - 11,900.00
62,050.00 - 62,050.00
104,720.00 - 104,720.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
- - 23,520.00 0.2100
- - 4,480.00 0.0350
79,092.16 - 79,092.16
109,194.40 - 109,194.40
223,700.96 - 223,700.96
31,000.00 - 31,000.00
47,600.00 - 47,600.00
- - 55,300.00 0.7000
- - 231,000.00 2.1000
Halaman 209
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 23,520.00 0.2100
- - 4,480.00 0.0350
29,325.00 - 29,325.00
49,087.50 - 49,087.50
- - 23,700.00 0.3000
- - 110,000.00 1.0000
- - 11,200.00 0.1000
- - 1,920.00 0.0150
6,630.00 - 6,630.00
1,612,875.00 - 1,612,875.00
- - 23,700.00 0.3000
- - 110,000.00 1.0000
- - 11,200.00 0.1000
- - 1,920.00 0.0150
337,535.00 - 337,535.00
79,900.00 - 79,900.00
Halaman 210
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
7,300.23 - 7,300.23
9,500.00 - 9,500.00
2,618.00 - 2,618.00
3,400.00 - 3,400.00
- - 30,810.00 0.3900
- - 72,100.00 0.7000
- - 7,840.00 0.0700
- - 896.00 0.0070
20,000.00 20,000.00
440,253.23 20,000.00 571,899.23
66,037.98 3,000.00 85,784.88
506,291.21 23,000.00 657,684.11
506,291.21 23,000.00 657,684.00
498,355.00 - 498,355.00
79,900.00 - 79,900.00
7,300.23 - 7,300.23
9,500.00 - 9,500.00
2,618.00 - 2,618.00
3,400.00 - 3,400.00
- - 30,810.00 0.3900
- - 72,100.00 0.7000
- - 7,840.00 0.0700
- - 896.00 0.0070
20,000.00 20,000.00
601,073.23 20,000.00 732,719.23
90,160.98 3,000.00 109,907.88
691,234.21 23,000.00 842,627.11
691,234.21 23,000.00 842,627.00
277,950.00 - 277,950.00
154,258.00 - 154,258.00
254,388.00 - 254,388.00
- - 130,350.00 1.6500
- - 25,750.00 0.2500
- - 2,800.00 0.0250
Halaman 211
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 10,240.00 0.0800
433,500.00 - 433,500.00
260,329.50 - 260,329.50
160,191.00 - 160,191.00
- - 118,500.00 1.5000
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 1,280.00 0.0100
502,350.00 - 502,350.00
254,056.50 - 254,056.50
145,358.50 - 145,358.50
- - 118,500.00 1.5000
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 1,280.00 0.0100
Halaman 212
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
963,900.00 - 963,900.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
957,100.00 - 957,100.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
993,650.00 - 993,650.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
Halaman 213
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,013,200.00 - 1,013,200.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
1,082,900.00 - 1,082,900.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
1,122,850.00 - 1,122,850.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
Halaman 214
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,291,277.50 2,209.73 1,564,576.00
1,182,350.00 - 1,182,350.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
1,265,650.00 - 1,265,650.00
- - 197,500.00 2.5000
- - 25,750.00 0.2500
- - 11,200.00 0.1000
- - 1,280.00 0.0100
36,550.00 - 36,550.00
- - 9,480.00 2.5000
- - 12,360.00 0.2500
- - 1,344.00 0.1000
- - 768.00 0.0100
- 20,000 20,000.00
36,550.00 20,000.00 80,502.00
5,482.50 3,000.00 12,075.30
Halaman 215
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
42,032.50 23,000.00 92,577.30
42,032.50 23,000.00 92,577.00
502,350.00 - 502,350.00
263,007.00 - 263,007.00
145,358.50 - 145,358.50
- - 118,500.00 1.5000
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 1,280.00 0.0100
73,695.00 - 73,695.00
54,565.75 - 54,565.75
7,480.00 - 7,480.00
- - 9,480.00 0.1200
- - 16,500.00 0.1500
- - 16,800.00 0.1500
- - 9,600.00 0.1200
- - 6,400.00 0.0500
73,695.00 - 73,695.00
72,262.75 - 72,262.75
7,480.00 - 7,480.00
- - 9,480.00 0.1200
Halaman 216
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 16,500.00 0.1500
- - 16,800.00 0.1500
- - 9,600.00 0.1200
- - 6,400.00 0.0500
173,400.00 - 173,400.00
5,610.00 - 5,610.00
1,615.00 - 1,615.00
- - 41,080.00 0.1200
- - 28,600.00 0.1500
- - 2,912.00 0.1500
- - 3,328.00 0.0500
195,075.00 - 195,075.00
5,610.00 - 5,610.00
1,615.00 - 1,615.00
- - 41,080.00 0.1200
- - 28,600.00 0.1500
- - 2,912.00 0.1500
- - 3,328.00 0.0500
Halaman 217
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
173,400.00 - 173,400.00
7,480.00 - 7,480.00
3,230.00 - 3,230.00
105,417.00 - 105,417.00
55,037.50 - 55,037.50
130,900.00 - 130,900.00
- - 52,140.00 0.1200
- - 36,300.00 0.1500
- - 3,696.00 0.1500
- - 4,224.00 0.0500
173,400.00 - 173,400.00
7,480.00 - 7,480.00
3,230.00 - 3,230.00
1,422.90 - 1,422.90
5,652.50 - 5,652.50
374,000.00 - 374,000.00
- - 52,140.00 0.1200
- - 36,300.00 0.1500
- - 3,696.00 0.1500
- - 4,224.00 0.0500
173,400.00 - 173,400.00
7,480.00 - 7,480.00
3,230.00 - 3,230.00
4,067.25 - 4,067.25
66,937.50 - 66,937.50
Halaman 218
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
91,800.00 - 91,800.00
- - 52,140.00 0.1200
- - 36,300.00 0.1500
- - 3,696.00 0.1500
- - 4,224.00 0.0500
130,050.00 - 130,050.00
7,480.00 - 7,480.00
3,230.00 - 3,230.00
44,523.00 - 44,523.00
92,225.00 - 92,225.00
175,950.00 - 175,950.00
100,000.00 - 100,000.00
- - 52,140.00 0.1200
- - 36,300.00 0.1500
- - 3,696.00 0.1500
- - 4,224.00 0.0500
130,050.00 - 130,050.00
7,480.00 - 7,480.00
2,422.50 - 2,422.50
280.50 - 280.50
171,360.00 - 171,360.00
385,900.00 - 385,900.00
- - 52,140.00 0.1200
- - 36,300.00 0.1500
- - 3,696.00 0.1500
Halaman 219
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 4,224.00 0.0500
Cek Ulang
73,695.00 - 73,695.00
74,806.80 - 74,806.80
7,480.00 - 7,480.00
- - 9,480.00 0.1200
- - 16,500.00 0.1500
- - 16,800.00 0.1500
- - 9,600.00 0.1200
- - 6,400.00 0.0500
13,387.50 - 13,387.50
459.00 - 459.00
- - 553.00 0.0070
- - 721.00 0.0070
- - 78.40 0.0007
- - 51.20 0.0004
13,833.75 - 13,833.75
Halaman 220
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
459.00 - 459.00
- - 553.00 0.0070
- - 721.00 0.0070
- - 78.40 0.0007
- - 51.20 0.0004
39,900.00 - 39,900.00
306.00 - 306.00
- - 4,120.00 0.0400
- - 1,120.00 0.0100
- - 640.00 0.0050
47,302.50 - 47,302.50
306.00 - 306.00
- - 4,120.00 0.0400
- - 1,120.00 0.0100
- - 640.00 0.0050
Halaman 221
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
68,722.50 - 68,722.50
306.00 - 306.00
- - 4,120.00 0.0400
- - 1,120.00 0.0100
- - 640.00 0.0050
118,702.50 - 118,702.50
306.00 - 306.00
- - 4,120.00 0.0400
- - 1,120.00 0.0100
- - 640.00 0.0050
79,695.00 - 79,695.00
306.00 - 306.00
- - 4,740.00 0.0600
- - 3,090.00 0.0300
- - 336.00 0.0030
- - 384.00 0.0030
Halaman 222
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
92,001.15 0.00 101,833.00
103,950.00 - 103,950.00
306.00 - 306.00
- - 4,740.00 0.0600
- - 3,090.00 0.0300
- - 336.00 0.0030
- - 384.00 0.0030
13,005.00 - 13,005.00
32,899.76 - 32,899.76
5,049.00 - 5,049.00
193,698.00 - 193,698.00
- - 7,900.00 0.1000
- - 5,500.00 0.0500
- - 560.00 0.0050
- - 1,280.00 0.0100
6,069.00 - 6,069.00
43,059.98 - 43,059.98
4,301.00 - 4,301.00
193,698.00 - 193,698.00
- - 6,320.00 0.0800
- - 4,400.00 0.0400
Halaman 223
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 448.00 0.0040
- - 1,024.00 0.0080
2,739,498.54 3,008,527.25
2,686,901.22 2,950,764.68
2,307,707.42 2,534,332.67
2,054,582.81 2,256,350.31
3,869,519.09 4,249,519.92
3,287,332.50 3,610,160.50
2,971,748.58 3,263,585.09
3,166,358.66 3,477,306.59
3,296,043.93 3,619,727.43
2,834,338.08 3,112,680.38
2,949,230.35 3,238,855.49
2,966,817.58 3,258,169.85
2,739,498.54 3,008,527.25
2,686,901.22 2,950,764.68
3,301,961.13 3,626,225.71
5,259,732.00 5,776,256.80
2,505,276.10 2,751,303.32
1,957,606.50 2,149,850.58
3,122,965.88 3,429,652.48
3,505,118.28 3,849,333.63
3,168,988.53 3,480,194.72
3,132,170.41 3,439,760.92
1,725,849.56 1,895,334.26
2,728,485.98 2,996,433.22
2,264,972.09 2,487,400.58
3,433,125.70 3,770,271.12
3,578,425.79 3,929,840.21
3,362,941.15 3,693,194.19
3,255,116.64 3,574,780.93
3,078,093.79 3,380,373.78
3,477,340.32 3,818,827.78
3,714,685.73 4,079,481.37
3,076,943.22 3,379,110.23
3,301,961.13 3,626,225.71
3,298,345.06 3,622,254.54
3,024,345.90 3,321,347.66
Halaman 224
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
2,896,797.40 3,181,273.43
2,962,708.42 3,253,657.15
2,896,139.93 3,180,551.40
1,366,379.75 1,500,563.21
11,827,750.00 - 11,827,750.00
178,500.00 - 178,500.00
104,720.00 - 104,720.00
- - 316,000.00 4.0000
- - 1,320,000.00 12.0000
- - 134,400.00 1.2000
- - 25,600.00 0.2000
11,827,750.00 - 11,827,750.00
178,500.00 - 178,500.00
56,100.00 - 56,100.00
- - 189,600.00 2.4000
- - 792,000.00 7.2000
- - 80,640.00 0.7200
- - 15,360.00 0.1200
5,322,020.00 - 5,322,020.00
178,500.00 - 178,500.00
104,720.00 - 104,720.00
Halaman 225
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 316,000.00 4.0000
- - 1,320,000.00 12.0000
- - 134,400.00 1.2000
- - 25,600.00 0.2000
5,322,020.00 - 5,322,020.00
178,500.00 - 178,500.00
56,100.00 - 56,100.00
- - 189,600.00 2.4000
- - 792,000.00 7.2000
- - 80,640.00 0.7200
- - 15,360.00 0.1200
9,027,425.00 - 9,027,425.00
178,500.00 - 178,500.00
104,720.00 - 104,720.00
- - 316,000.00 4.0000
- - 1,320,000.00 12.0000
- - 134,400.00 1.2000
- - 25,600.00 0.2000
Halaman 226
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
9,027,425.00 - 9,027,425.00
178,500.00 - 178,500.00
56,100.00 - 56,100.00
- - 189,600.00 2.4000
- - 792,000.00 7.2000
- - 80,640.00 0.7200
- - 15,360.00 0.1200
178,500.00 - 178,500.00
104,720.00 - 104,720.00
- - 316,000.00 4.0000
- - 1,320,000.00 12.0000
- - 134,400.00 1.2000
- - 25,600.00 0.2000
52,020.00 - 52,020.00
16,419.45 - 16,419.45
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
Halaman 227
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
10,686.67 0.00 13,785.67
81,931.12 0.00 105,690.12
81,931.12 0.00 105,690.00
76,071.60 - 76,071.60
21,083.40 - 21,083.40
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
21,083.40 - 21,083.40
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
16,150.00 - 16,150.00
24,225.00 - 24,225.00
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
Halaman 228
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 640.00 0.0050
16,150.00 - 16,150.00
31,875.00 - 31,875.00
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
16,150.00 - 16,150.00
16,419.45 - 16,419.45
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
16,419.45 - 16,419.45
2,805.00 - 2,805.00
Halaman 229
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
52,020.00 - 52,020.00
16,419.45 - 16,419.45
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
88,750.20 - 88,750.20
21,083.40 - 21,083.40
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
Halaman 230
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
52,020.00 - 52,020.00
2,805.00 - 2,805.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
31,936.20 - 31,936.20
8,330.00 - 8,330.00
10,472.00 - 10,472.00
20,187.50 - 20,187.50
- - 15,800.00 0.2000
- - 46,350.00 0.4500
- - 1,120.00 0.0100
- - 6,400.00 0.0500
- 7,029.79 7,029.79
70,925.70 7,029.79 147,625.49
10,638.86 1,054.47 22,143.82
81,564.56 8,084.25 169,769.31
81,564.56 8,084.25 169,769.00
53,227.00 - 53,227.00
10,710.00 - 10,710.00
10,472.00 - 10,472.00
28,262.50 - 28,262.50
- - 15,800.00 0.2000
- - 46,350.00 0.4500
- - 1,120.00 0.0100
Halaman 231
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 6,400.00 0.0500
- 8,617.08 8,617.08
102,671.50 8,617.08 180,958.58
15,400.73 1,292.56 27,143.79
118,072.23 9,909.64 208,102.36
118,072.23 9,909.64 208,102.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
42,500.00 - 42,500.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
85,000.00 - 85,000.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
Halaman 232
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
85,000.00 0.00 106,964.00
12,750.00 0.00 16,044.60
97,750.00 0.00 123,008.60
97,750.00 0.00 123,008.00
85,000.00 - 85,000.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
61,200.00 - 61,200.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
61,200.00 - 61,200.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
Halaman 233
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
9,180.00 0.00 12,474.60
70,380.00 0.00 95,638.60
70,380.00 0.00 95,638.00
76,500.00 - 76,500.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
30,600.00 - 30,600.00
- - 11,850.00 0.1500
- - 8,250.00 0.0750
- - 840.00 0.0075
- - 1,024.00 0.0080
56,100.00 - 56,100.00
561.00 0.00 561.00
- - 15,800.00 0.2000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
0.00 0.00 1,280.00 0.0100
Halaman 234
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
8,499.15 0.00 12,879.15
65,160.15 0.00 98,740.15
65,160.15 0.00 98,740.00
121,000.00 - 121,000.00
561.00 - 561.00
- - 15,800.00 0.2000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 1,280.00 0.0100
136,119.00 - 136,119.00
374.00 - 374.00
- - 15,800.00 0.2000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 1,280.00 0.0100
42,840.00 - 42,840.00
11,220.00 - 11,220.00
- - 11,060.00 0.1400
- - 8,250.00 0.0750
- - 896.00 0.0080
- - 1,024.00 0.0080
Halaman 235
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
45,390.00 - 45,390.00
11,220.00 0.00 11,220.00
- - 11,060.00 0.1400
- - 8,250.00 0.0750
- - 896.00 0.0080
0.00 0.00 1,024.00 0.0080
45,390.00 - 45,390.00
3,570.00 0.00 3,570.00
- - 11,060.00 0.1400
- - 8,250.00 0.0750
- - 896.00 0.0080
0.00 0.00 1,024.00 0.0080
40,375.00 - 40,375.00
11,220.00 0.00 11,220.00
- - 11,060.00 0.1400
- - 8,250.00 0.0750
- - 896.00 0.0080
Halaman 236
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
0.00 0.00 1,024.00 0.0080
41,225.00 - 41,225.00
11,220.00 0.00 11,220.00
- - 11,060.00 0.1400
- - 8,250.00 0.0750
- - 896.00 0.0080
0.00 0.00 1,024.00 0.0080
39,270.00 - 39,270.00
11,220.00 0.00 11,220.00
- - 9,480.00 0.1200
- - 6,600.00 0.0600
- - 672.00 0.0060
0.00 0.00 768.00 0.0060
39,270.00 - 39,270.00
442.00 0.00 442.00
- - 9,480.00 0.1200
Halaman 237
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 6,600.00 0.0600
- - 672.00 0.0060
0.00 0.00 768.00 0.0060
67,631.67 - 67,631.67
1,785.00 0.00 1,785.00
- - 474.00 0.0060
- - 13,200.00 0.1200
- - 6,720.00 0.0600
0.00 0.00 768.00 0.0060
143,877.00 - 143,877.00
14,000.35 0.00 14,000.35
- - 11,060.00 0.1400
- - 7,700.00 0.0700
- - 784.00 0.0070
0.00 0.00 896.00 0.0070
48,620.00 - 48,620.00
10,888.50 0.00 10,888.50
Halaman 238
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 11,060.00 0.1400
- - 7,700.00 0.0700
- - 784.00 0.0070
0.00 0.00 896.00 0.0070
258,770.60 - 258,770.60
10,888.50 0.00 10,888.50
- - 11,060.00 0.1400
- - 7,700.00 0.0700
- - 784.00 0.0070
0.00 0.00 896.00 0.0070
145,668.00 - 145,668.00
13,643.35 0.00 13,643.35
- - 11,060.00 0.1400
- - 7,700.00 0.0700
- - 784.00 0.0070
0.00 0.00 896.00 0.0070
Halaman 239
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
241,150.00 - 241,150.00
19,193.51 0.00 19,193.51
- - 15,800.00 0.2000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
0.00 0.00 1,280.00 0.0100
25,500.00 - 25,500.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
34,000.00 - 34,000.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
Halaman 240
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
60,464.24 0.00 124,974.00
25,500.00 - 25,500.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
23,800.00 - 23,800.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
27,200.00 - 27,200.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
Halaman 241
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
30,600.00 - 30,600.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
20,400.00 - 20,400.00
10,200.00 - 10,200.00
8,377.60 - 8,377.60
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 256.00 0.0020
108,120.00 - 108,120.00
1,785.00 - 1,785.00
Halaman 242
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 6,636.00 0.0840
- - 13,750.00 0.1250
- - 1,456.00 0.0130
- - 512.00 0.0040
20,825.00 - 20,825.00
935.00 - 935.00
13,770.00 - 13,770.00
8,377.60 - 8,377.60
17,391.00 - 17,391.00
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 2,560.00 0.0200
57,600.00 - 57,600.00
935.00 - 935.00
13,770.00 - 13,770.00
8,377.60 - 8,377.60
17,391.00 - 17,391.00
- - 31,600.00 0.4000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 2,560.00 0.0200
Halaman 243
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
112,784.64 0.00 179,944.64
112,784.64 0.00 179,944.00
53,295.00 - 53,295.00
1,105.00 - 1,105.00
- - 19,750.00 0.2500
- - 16,500.00 0.1500
- - 1,680.00 0.0150
- - 1,664.00 0.0130
16,065.00 - 16,065.00
884.00 - 884.00
- - 11,850.00 0.1500
- - 7,700.00 0.0700
- - 896.00 0.0080
- - 768.00 0.0060
125,896.90 - 125,896.90
11,900.00 - 11,900.00
- - 6,636.00 0.1400
- - 13,750.00 0.0700
- - 1,456.00 0.0070
- - 512.00 0.0070
Halaman 244
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
137,796.90 0.00 160,150.90
20,669.54 0.00 24,022.64
158,466.44 0.00 184,173.54
158,466.44 0.00 184,173.00
133,541.46 - 133,541.46
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
98,841.06 - 98,841.06
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
76,643.82 - 76,643.82
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
Halaman 245
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
136,014.45 - 136,014.45
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
100,671.45 - 100,671.45
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
267,082.92 - 267,082.92
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
Halaman 246
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 2,240.00 0.0200
- - 640.00 0.0050
197,682.12 - 197,682.12
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
28,333.33 - 28,333.33
22,312.50 - 22,312.50
1,122.00 - 1,122.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
39,312.50 - 39,312.50
22,312.50 - 22,312.50
Halaman 247
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,122.00 - 1,122.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
39,312.50 - 39,312.50
1,122.00 - 1,122.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
98,841.06 - 98,841.06
1,870.00 - 1,870.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
Halaman 248
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
100,671.45 - 100,671.45
935.00 - 935.00
- - 7,900.00 0.1000
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 640.00 0.0050
39,270.00 - 39,270.00
331.50 - 331.50
134,836.35 - 134,836.35
- - 15,800.00 0.2000
- - 44,000.00 0.4000
- - 2,800.00 0.0250
- - 1,280.00 0.0100
18,700.00 - 18,700.00
331.50 - 331.50
134,836.35 - 134,836.35
16,320.00 - 16,320.00
- - 15,800.00 0.2000
- - 44,000.00 0.4000
- - 2,800.00 0.0250
- - 1,280.00 0.0100
Halaman 249
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
25,528.18 0.00 35,110.18
195,716.03 0.00 269,178.03
195,716.03 0.00 269,178.00
74,800.00 - 74,800.00
221.00 - 221.00
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
27,115.00 - 27,115.00
221.00 - 221.00
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
58,058.40 - 58,058.40
221.00 - 221.00
27,115.00 - 27,115.00
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
Halaman 250
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 512.00 0.0040
98,481.00 - 98,481.00
1,326.00 - 1,326.00
27,115.00 - 27,115.00
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
1,326.00 - 1,326.00
27,115.00 - 27,115.00
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
58,058.40 - 58,058.40
663.00 - 663.00
39,206.25 - 39,206.25
Halaman 251
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
221.00 - 221.00
1,568.25 - 1,568.25
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
58,058.40 - 58,058.40
1,326.00 - 1,326.00
23,611.11 - 23,611.11
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
Halaman 252
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
98,481.00 - 98,481.00
1,326.00 - 1,326.00
23,611.11 - 23,611.11
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
1,326.00 - 1,326.00
23,611.11 - 23,611.11
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 2,370.00 0.0300
- - 7,700.00 0.0700
- - 784.00 0.0070
- - 512.00 0.0040
23,611.11 - 23,611.11
3,646.50 - 3,646.50
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 7,900.00 0.1000
Halaman 253
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 5,500.00 0.0500
- - 560.00 0.0050
- - 640.00 0.0050
58,058.40 - 58,058.40
1,122.00 - 1,122.00
3,646.50 - 3,646.50
30,011.80 - 30,011.80
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 14,220.00 0.1800
- - 35,200.00 0.3200
- - 3,584.00 0.0320
- - 1,152.00 0.0090
98,481.00 - 98,481.00
1,122.00 - 1,122.00
3,646.50 - 3,646.50
30,011.80 - 30,011.80
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 14,220.00 0.1800
- - 35,200.00 0.3200
- - 3,584.00 0.0320
- - 1,152.00 0.0090
Halaman 254
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
21,700.88 0.00 29,824.28
166,373.43 0.00 228,652.83
166,373.43 0.00 228,652.00
30,011.80 - 30,011.80
3,646.50 - 3,646.50
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 7,900.00 0.1000
- - 5,500.00 0.0500
- - 560.00 0.0050
- - 640.00 0.0050
94,500.00 - 94,500.00
3,646.50 - 3,646.50
- - 14,220.00 0.1800
- - 35,200.00 0.3200
- - 3,584.00 0.0320
- - 1,152.00 0.0090
97,965.00 - 97,965.00
3,646.50 - 3,646.50
- - 14,220.00 0.1800
- - 35,200.00 0.3200
- - 3,584.00 0.0320
Halaman 255
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 1,152.00 0.0090
101,535.00 - 101,535.00
3,646.50 - 3,646.50
- - 14,220.00 0.1800
- - 35,200.00 0.3200
- - 3,584.00 0.0320
- - 1,152.00 0.0090
51,000.00 - 51,000.00
198,900.00 - 198,900.00
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
221.00 - 221.00
1,568.25 - 1,568.25
187,000.00 - 187,000.00
Halaman 256
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 63,200.00 0.8000
- - 88,000.00 0.8000
- - 8,960.00 0.0800
- - 5,120.00 0.0400
baru
112,200.00 - 112,200.00
90,100.00 - 90,100.00
215,900.00 - 215,900.00
64,600.00 - 64,600.00
2,618.00 - 2,618.00
6,000.00 - 6,000.00
- - 45,504.00 0.5760
- - 110,592.00 1.0240
- - 11,468.80 0.1024
- - 3,686.40 0.0288
58,058.40 - 58,058.40
1,870.00 - 1,870.00
- - 11,850.00 0.1500
- - 27,500.00 0.2500
- - 2,800.00 0.0250
- - 9,600.00 0.0750
Halaman 257
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
98,481.00 - 98,481.00
1,870.00 - 1,870.00
- - 11,850.00 0.1500
- - 27,500.00 0.2500
- - 2,800.00 0.0250
- - 9,600.00 0.0750
25,000.00 - 25,000.00
10,000.00 - 10,000.00
3,646.50 - 3,646.50
13,090.00 - 13,090.00
- - 7,900.00 0.1000
- - 5,500.00 0.0500
- - 560.00 0.0050
- - 640.00 0.0050
7,140.00 - 7,140.00
221.00 - 221.00
- - 3,950.00 0.0500
- - 5,500.00 0.0500
- - 560.00 0.0050
- - 384.00 0.0030
Halaman 258
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
7,361.00 0.00 17,755.00
1,104.15 0.00 2,663.25
8,465.15 0.00 20,418.25
8,465.15 0.00 20,418.00
16,065.00 - 16,065.00
701.25 - 701.25
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
19,635.00 - 19,635.00
701.25 - 701.25
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
21,420.00 - 21,420.00
701.25 - 701.25
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
Halaman 259
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
21,000.00 - 21,000.00
1,657.50 - 1,657.50
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
24,150.00 - 24,150.00
1,657.50 - 1,657.50
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
16,800.00 - 16,800.00
1,657.50 - 1,657.50
- - 4,740.00 0.5760
- - 6,600.00 1.0240
Halaman 260
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 672.00 0.1024
- - 384.00 0.0288
13,387.50 - 13,387.50
306.00 - 306.00
- - 4,120.00 0.0400
- - 1,120.00 0.0100
- - 640.00 0.0050
11,640.75 - 11,640.75
4,335.00 - 4,335.00
22,330.21 - 22,330.21
3,646.50 - 3,646.50
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 7,900.00 0.1800
- - 5,500.00 0.3200
- - 560.00 0.0320
- - 640.00 0.0090
Halaman 261
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,676,200.00 - 1,676,200.00
0.00 - 0.00
- - 260,700.00 3.3000
- - 113,300.00 1.1000
- - 112.00 0.0010
- - 20,480.00 0.1600
2,290,750.00 - 2,290,750.00
137,445.00 - 137,445.00
- - 260,700.00 3.3000
- - 113,300.00 1.1000
- - 112.00 0.0010
- - 20,480.00 0.1600
206,550.00 - 206,550.00
7,650.00 - 7,650.00
2,618.00 - 2,618.00
- - 79,000.00 1.0000
- - 154,500.00 1.5000
- - 16,800.00 0.1500
- - 20,480.00 0.1600
Halaman 262
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
249,340.70 0.00 560,737.70
249,340.70 0.00 560,737.00
1,935,450.00 - 1,935,450.00
7,650.00 - 7,650.00
2,618.00 - 2,618.00
580,635.00 - 580,635.00
- - 79,000.00 1.0000
- - 103,000.00 1.0000
- - 11,200.00 0.1000
- - 6,400.00 0.0500
1,250,350.00 - 1,250,350.00
7,650.00 - 7,650.00
26,180.00 - 26,180.00
150,042.00 - 150,042.00
- - 94,800.00 1.2000
- - 149,350.00 1.4500
- - 16,800.00 0.1500
- - 7,680.00 0.0600
3,801,200.00 - 3,801,200.00
760,240.00 - 760,240.00
- - 5,925.00 0.0750
- - 77,250.00 0.7500
Halaman 263
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 8,400.00 0.0750
- - 384.00 0.0030
140,250.00 - 140,250.00
153,000.00 - 153,000.00
78,540.00 - 78,540.00
241,612.50 - 241,612.50
104,346.00 - 104,346.00
- - 474,000.00 6.0000
- - 309,000.00 3.0000
- - 33,600.00 0.3000
- - 3,840.00 0.0300
37,400.00 - 37,400.00
56,100.00 - 56,100.00
18,326.00 - 18,326.00
20,468.00 - 20,468.00
20,400.00 - 20,400.00
17,799.00 - 17,799.00
- - 170,640.00 2.1600
- - 74,160.00 0.7200
- - 8,064.00 0.0720
- - 1,408.00 0.0110
Halaman 264
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
196,066.95 0.00 488,479.00
65,450.00 - 65,450.00
98,175.00 - 98,175.00
34,034.00 - 34,034.00
5,848.00 - 5,848.00
33,150.00 - 33,150.00
26,698.50 - 26,698.50
- - 252,800.00 3.2000
- - 118,450.00 1.1500
- - 1,232.00 0.0110
- - 2,048.00 0.0160
29,580.00 - 29,580.00
8,627.50 - 8,627.50
- - 4,266.00 0.0540
- - 9,270.00 0.0900
- - 1,008.00 0.0090
- - 3,456.00 0.0270
41,820.00 - 41,820.00
12,197.50 - 12,197.50
- - 4,266.00 0.0540
- - 9,270.00 0.0900
- - 1,008.00 0.0090
Halaman 265
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 3,456.00 0.0270
7,140.00 - 7,140.00
2,082.50 - 2,082.50
- - 2,844.00 0.0360
- - 6,180.00 0.0600
- - 672.00 0.0060
- - 256.00 0.0020
9,180.00 - 9,180.00
2,677.50 - 2,677.50
- - 2,844.00 0.0360
- - 6,180.00 0.0600
- - 672.00 0.0060
- - 256.00 0.0020
16,320.00 - 16,320.00
4,760.00 - 4,760.00
- - 2,844.00 0.0360
Halaman 266
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 6,180.00 0.0600
- - 672.00 0.0060
- - 256.00 0.0020
33,660.00 - 33,660.00
9,817.50 - 9,817.50
- - 4,266.00 0.0540
- - 9,270.00 0.0900
- - 1,008.00 0.0090
- - 384.00 0.0030
57,120.00 - 57,120.00
16,660.00 - 16,660.00
- - 6,399.00 0.0810
- - 13,905.00 0.1350
- - 1,512.00 0.0135
- - 512.00 0.0040
81,600.00 - 81,600.00
23,800.00 - 23,800.00
Halaman 267
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 6,399.00 0.0810
- - 13,905.00 0.1350
- - 1,512.00 0.0135
- - 512.00 0.0040
164,220.00 - 164,220.00
47,897.50 - 47,897.50
- - 6,399.00 0.0810
- - 13,905.00 0.1350
- - 1,512.00 0.0135
- - 512.00 0.0040
351,050.00 - 351,050.00
76,500.00 - 76,500.00
- - 2,370.00 0.0300
- - 30,900.00 0.3000
- - 3,360.00 0.0300
- - 192.00 0.0015
Halaman 268
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
86,700.00 - 86,700.00
85.00 - 85.00
- - 790.00 0.0100
- - 41,200.00 0.4000
- - 4,480.00 0.0400
- - 640.00 0.0050
11,050.00 - 11,050.00
- - 790.00 0.0100
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
146,200.00 - 146,200.00
- - 790.00 0.0100
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
Halaman 269
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
19,800.00 - 19,800.00
- - 790.00 0.0100
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
77,000.00 - 77,000.00
- - 790.00 0.0100
- - 10,300.00 0.1000
- - 1,120.00 0.0100
- - 640.00 0.0050
- - 662,917.50 662917.50
95,896.27 - 106,151.81 106151.81
2,960,945.25 - 3,690,361.50 3690360.00
2,709,507.81 - 3,774,407.81 3774400.00
613,381.25 - 1,908,396.25 1908375.00
119,132.81 - 938,507.81 938500.00
1,252,302.60 2,156.25 1,457,055.07 1457054.61
1,090,890.00 - 1,321,984.80 1321983.00
124,240.25 - 165,640.25 165640.00
- - 497,188.13 497188.13
336,600.00 - 336,600.00 336600.00
511,700.00 - 511,700.00 511700.00
- - 98,971.88 98971.88
- - 5,100.00 5100.00
Halaman 270
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,472,189.44 323.44 2,321,247.42 2,321,241.29
11,286,785.68 2,479.69 17,796,230.23 17,796,183.20
11,286,785.68 2,479.69 17,796,230.00 17,796,183.00
- - 397,750.50 397750.50
57,484.04 - 63,631.62 63631.62
1,776,567.15 - 2,214,216.90 2214216.00
1,625,704.69 - 2,264,644.69 2264640.00
368,028.75 - 1,145,037.75 1145025.00
71,479.69 - 563,104.69 563100.00
751,381.56 1,293.75 874,233.04 874232.76
654,534.00 - 793,190.88 793189.80
74,544.15 - 99,384.15 99384.00
- - 298,312.88 298312.88
201,960.00 - 201,960.00 201960.00
307,020.00 - 307,020.00 307020.00
- - 59,383.13 59383.13
- - 5,520.00 5520.00
- - 198,875.25 198875.25
28,742.02 - 31,815.81 31815.81
888,283.58 - 1,107,108.45 1107108.00
812,852.34 - 1,132,322.34 1132320.00
184,014.38 - 572,518.88 572512.50
35,739.84 - 281,552.34 281550.00
375,690.78 646.88 437,116.52 437116.38
1,090,890.00 - 1,321,984.80 1321983.00
37,272.08 - 49,692.08 49692.00
- - 14,849.35 14849.35
100,980.00 - 100,980.00 100980.00
153,510.00 - 153,510.00 153510.00
- - 29,665.17 29665.17
- - 3,900.00 3900.00
Halaman 271
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
4,264,171.26 743.91 6,251,274.00 6,251,259.00
- - 7,917.75
56,950.00 - 56,950.00
108,380.31 - 150,976.31
24,535.25 - 76,335.85
4,765.31 - 37,540.31
- - 1,750.00
- - 10,557.00
77,350.00 - 77,350.00
108,380.31 - 150,976.31
24,535.25 - 76,335.85
4,765.31 - 37,540.31
- - 750.00
143,055.00 - 143,055.00
23,375.00 - 23,375.00
13,132.50 - 13,132.50
15,969.80 - 15,969.80
13,430.85 - 13,430.85
- - 30,020.00 0.3800
- - 19,570.00 0.1900
- - 2,128.00 0.0190
- - 2,432.00 0.0190
Halaman 272
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
31,344.47 0.00 39,466.97
240,307.62 0.00 302,580.12
240,307.62 0.00 302,580.00
188,870.00 - 188,870.00
23,375.00 - 23,375.00
262.65 - 262.65
15,969.80 - 15,969.80
13,430.85 - 13,430.85
- - 30,020.00 0.3800
- - 19,570.00 0.1900
- - 2,128.00 0.0190
- - 2,432.00 0.0190
2,461,600.00 - 2,461,600.00
8,861.76 - 8,861.76
- - 260,700.00 3.3000
- - 113,300.00 1.1000
- - 112.00 0.0010
- - 20,480.00 0.1600
1,657,500.00 - 1,657,500.00
5,967.00 - 5,967.00
- - 260,700.00 3.3000
Halaman 273
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 113,300.00 1.1000
- - 112.00 0.0010
- - 20,480.00 0.1600
18,572.50 - 18,572.50
- - 6,600.00 0.0600
- - 4,740.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
16,617.50 - 16,617.50
- - 4,740.00 0.0600
- - 6,600.00 0.0600
- - 672.00 0.0060
- - 384.00 0.0030
106.25 - 106.25
16.15 - 16.15
Halaman 274
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 1.12 0.0000
- - 6.40 0.0001
- 4,722.40 4,722.40
122.40 4,722.40 5,034.32
18.36 708.36 755.15
140.76 5,430.76 5,789.47
140.76 5,430.76 5,789.00
- - 3,950.00 0.0500
- - 2,200.00 0.0200
- - 336.00 0.0030
- - 128.00 0.0010
477,700.00 - 477,700.00
- - 108,000.00 1.0000
Halaman 275
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 79,000.00 1.0000
- - 11,200.00 0.1000
- - 6,400.00 0.0500
950,000.00 - 950,000.00
- - 108,000.00 1.0000
- - 79,000.00 1.0000
- - 11,200.00 0.1000
- - 6,400.00 0.0500
850,000.00 - 850,000.00
- - 108,000.00 1.0000
- - 79,000.00 1.0000
- - 11,200.00 0.1000
- - 6,400.00 0.0500
480,000.00 - 480,000.00
- - 108,000.00 1.0000
- - 79,000.00 1.0000
Halaman 276
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 11,200.00 0.1000
- - 6,400.00 0.0500
178,500.00 - 178,500.00
390,320.00 - 390,320.00
1,615.00 - 1,615.00
- - 115,500.00 1.0500
- - 82,950.00 1.0500
- - 11,760.00 0.1050
- - 6,656.00 0.0520
73,506.30 - 73,506.30
87,441.32 - 87,441.32
- - 183,700.00 1.6700
- - 131,930.00 1.6700
- - 18,704.00 0.1670
- - 10,624.00 0.0830
34,595.00 - 34,595.00
442.00 - 442.00
Halaman 277
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
22,256.91 - 22,256.91
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 64.00 0.0005
27,115.00 - 27,115.00
442.00 - 442.00
22,256.91 - 22,256.91
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 64.00 0.0005
27,115.00 - 27,115.00
0.00 - 0.00
20,420.40 - 20,420.40
- - 7,900.00 0.1000
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 64.00 0.0005
Halaman 278
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
134,300.00 - 134,300.00
- - 790.00 0.0100
- - 55,000.00 0.5000
- - 1,120.00 0.0100
- - 640.00 0.0050
210,800.00 - 210,800.00
- - 790.00 0.0100
- - 55,000.00 0.5000
- - 1,120.00 0.0100
- - 640.00 0.0050
44,200.00 - 44,200.00
- - 1,185.00 0.0150
- - 16,500.00 0.1500
- - 1,680.00 0.0150
- - 96.00 0.0008
Halaman 279
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
29,750.00 - 29,750.00
- - 790.00 0.0100
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 64.00 0.0005
20,400.00 - 20,400.00
- - 1,185.00 0.0150
- - 16,500.00 0.1500
- - 1,680.00 0.0150
- - 96.00 0.0008
14,450.00 - 14,450.00
- - 790.00 0.0100
- - 11,000.00 0.1000
- - 1,120.00 0.0100
- - 64.00 0.0005
Halaman 280
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
168,300.00 - 168,300.00
- - 3,950.00 0.0500
- - 55,000.00 0.5000
- - 5,600.00 0.0500
- - 320.00 0.0025
147,730.00 - 147,730.00
- - 1,185.00 0.0150
- - 16,500.00 0.1500
- - 1,680.00 0.0150
- - 102.40 0.0008
179,520.00 - 179,520.00
- - 1,185.00 0.0150
- - 16,500.00 0.1500
- - 1,680.00 0.0150
- - 102.40 0.0008
Halaman 281
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
250,580.00 - 250,580.00
152,000.00 - 152,000.00
- - 3,950.00 0.0500
- - 53,460.00 0.4950
- - 5,600.00 0.0500
- - 307.20 0.0024
563,805.00 - 563,805.00
152,000.00 - 152,000.00
- - 4,692.60 0.0594
- - 64,152.00 0.5940
- - 6,652.80 0.0594
- - 368.64 0.0029
57,800.00 - 57,800.00
450,000.00 - 450,000.00
420,000.00 - 420,000.00
135,150.00 - 135,150.00
152,000.00 - 152,000.00
1,190.00 - 1,190.00
30,000.00 - 30,000.00
- - 94,800.00 1.2000
- - 47,300.00 0.4300
- - 1,344.00 0.0120
- - 768.00 0.0060
Halaman 282
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
1,532,601.00 - 1,532,601.00
1,975,400.00 - 1,975,400.00
1,263,100.00 - 1,263,100.00
731,000.00 - 731,000.00
336,600.00 - 336,600.00
431,800.00 - 431,800.00
- - 500,000.00 1.0000
2,919,240.00 - 2,919,240.00
3,950,800.00 - 3,950,800.00
2,526,200.00 - 2,526,200.00
731,000.00 - 731,000.00
673,200.00 - 673,200.00
863,600.00 - 863,600.00
- - 500,000.00 1.0000
2,594,880.00 - 2,594,880.00
3,950,800.00 - 3,950,800.00
2,526,200.00 - 2,526,200.00
731,000.00 - 731,000.00
Halaman 283
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
673,200.00 - 673,200.00
863,600.00 - 863,600.00
- - 500,000.00 1.0000
2,270,520.00 - 2,270,520.00
3,950,800.00 - 3,950,800.00
2,526,200.00 - 2,526,200.00
731,000.00 - 731,000.00
673,200.00 - 673,200.00
863,600.00 - 863,600.00
- - 500,000.00 1.0000
1,946,160.00 - 1,946,160.00
3,950,800.00 - 3,950,800.00
2,526,200.00 - 2,526,200.00
731,000.00 - 731,000.00
673,200.00 - 673,200.00
863,600.00 - 863,600.00
- - 500,000.00 1.0000
Halaman 284
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
460,020.00 - 460,020.00
145,350.00 - 145,350.00
10,260.00 - 10,260.00
- - 6,715.00 0.0850
- - 9,180.00 0.0850
- - 1,008.00 0.0090
- - 640.00 0.0050
52,500.00 - 52,500.00
- - 1,580.00 0.0200
- - 22,000.00 0.2000
- - 2,240.00 0.0200
- - 320.00 0.0025
- 5,000.00 5,000.00
52,500.00 5,000.00 83,640.00
7,875.00 750.00 12,546.00
60,375.00 5,750.00 96,186.00
60,375.00 5,750.00 96,186.00
80,716.00 - 80,716.00
12,750.00 - 12,750.00
11,781.00 - 11,781.00
226.08 - 226.08
- - 20,540.00 0.2600
- - 13,390.00 0.1300
- - 1,456.00 0.0130
- - 1,664.00 0.0130
Halaman 285
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
15,820.96 0.00 21,378.46
121,294.05 0.00 163,901.55
121,294.05 0.00 163,901.00
12,750.00 - 12,750.00
11,781.00 - 11,781.00
226.08 - 226.08
- - 20,540.00 0.2600
- - 13,390.00 0.1300
- - 1,456.00 0.0130
- - 1,664.00 0.0130
58,519.10 - 58,519.10
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
279,479.15 - 279,479.15
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
Halaman 286
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
63,563.85 - 63,563.85
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
136,208.25 - 136,208.25
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
Halaman 287
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
69,617.55 - 69,617.55
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
71,635.45 - 71,635.45
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
113,002.40 - 113,002.40
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
Halaman 288
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 3,920.00 0.0350
- - 4,480.00 0.0350
1,608,285.00 - 1,608,285.00
10,442.25 - 10,442.25
11,781.00 - 11,781.00
11,304.15 - 11,304.15
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
1,958,371.95 - 1,958,371.95
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
- - 35,000.00 1.0000
Halaman 289
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
386,427.85 - 386,427.85
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
172,530.45 - 172,530.45
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
126,118.75 - 126,118.75
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
Halaman 290
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 4,480.00 0.0350
481,269.15 - 481,269.15
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
350,105.65 - 350,105.65
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
Halaman 291
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
334,971.40 - 334,971.40
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
448,982.75 - 448,982.75
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
80,716.00 - 80,716.00
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
Halaman 292
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
89,796.55 - 89,796.55
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
250,792.50 - 250,792.50
44,880.00 - 44,880.00
- - 55,300.00 0.7000
- - 38,500.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
0.00 - 0.00
44,880.00 - 44,880.00
- - 55,300.00 0.7000
Halaman 293
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 38,500.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
0.00 - 0.00
26,180.00 - 26,180.00
- - 13,430.00 0.1700
- - 18,700.00 0.1700
- - 1,904.00 0.0170
- - 1,152.00 0.0090
36,550.00 - 36,550.00
- - 9,480.00 0.1200
- - 12,360.00 0.1200
- - 1,344.00 0.0120
- - 768.00 0.0060
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
Halaman 294
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 177,000.00 1.0000
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 177,000.00 1.0000
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 177,000.00 1.0000
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 177,000.00 1.0000
Halaman 295
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
115,923.00 0.00 292,923.00
17,388.45 0.00 43,938.45
133,311.45 0.00 336,861.45
133,311.45 0.00 336,861.00
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 177,000.00 1.0000
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 198,000.00 1.0000
21,289.95 - 21,289.95
935.00 - 935.00
- - 9,480.00 0.1200
- - 13,200.00 0.1200
- - 1,344.00 0.0120
- - 768.00 0.0060
Halaman 296
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
25,558.69 0.00 54,069.49
25,558.69 0.00 54,069.00
75,671.25 - 75,671.25
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
88,787.60 - 88,787.60
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
95,850.25 - 95,850.25
12,750.00 - 12,750.00
11,781.00 - 11,781.00
26,086.50 - 26,086.50
Halaman 297
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
254,983.00 - 254,983.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
154,071.00 - 154,071.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
Halaman 298
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
28,335.47 0.00 43,297.97
217,238.62 0.00 331,951.12
217,238.62 0.00 331,951.00
112,625.00 - 112,625.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
831,040.00 - 831,040.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
689,000.00 - 689,000.00
15,861.00 - 15,861.00
Halaman 299
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
371,000.00 - 371,000.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 55,300.00 0.7000
- - 36,050.00 0.3500
- - 3,920.00 0.0350
- - 4,480.00 0.0350
1,608,285.00 - 1,608,285.00
15,861.00 - 15,861.00
6,545.00 - 6,545.00
11,304.15 - 11,304.15
1,122.00 - 1,122.00
- - 56,880.00 0.7200
- - 66,950.00 0.6500
- - 7,280.00 0.0650
- - 4,480.00 0.0350
Halaman 300
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 50,000.00 1.0000
126,199.50 - 126,199.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
145,945.00 - 145,945.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
145,945.00 - 145,945.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 301
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
24,599.85 0.00 44,699.85
188,598.85 0.00 342,698.85
188,598.85 0.00 342,698.00
122,765.50 - 122,765.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
130,492.00 - 130,492.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
145,945.00 - 145,945.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 302
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
144,228.00 - 144,228.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
163,115.00 - 163,115.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
145,945.00 - 145,945.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
171,700.00 - 171,700.00
10,200.00 - 10,200.00
Halaman 303
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
7,854.00 - 7,854.00
- - 134,000.00 1.0000
184,577.50 - 184,577.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
80,699.00 - 80,699.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
91,859.50 - 91,859.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 304
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
124,482.50 - 124,482.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
239,521.50 - 239,521.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
338,249.00 - 338,249.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 305
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
409,748.45 0.00 563,848.00
376,023.00 - 376,023.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
177,709.50 - 177,709.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
252,399.00 - 252,399.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 306
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
276,437.00 - 276,437.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
91,001.00 - 91,001.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 128,000.00 1.0000
91,001.00 - 91,001.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 171,000.00 1.0000
91,001.00 - 91,001.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
Halaman 307
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 128,000.00 1.0000
98,727.50 - 98,727.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 128,000.00 1.0000
104,737.00 - 104,737.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 128,000.00 1.0000
157,964.00 - 157,964.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 128,000.00 1.0000
Halaman 308
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
26,402.70 0.00 45,602.70
202,420.70 0.00 349,620.70
202,420.70 0.00 349,620.00
99,110.00 - 99,110.00
14,981.25 - 14,981.25
9,163.00 - 9,163.00
- - 128,000.00 1.0000
64,387.50 - 64,387.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 128,000.00 1.0000
64,387.50 - 64,387.50
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 123,000.00 1.0000
Halaman 309
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
80,699.00 - 80,699.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 123,000.00 1.0000
70,397.00 - 70,397.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 123,000.00 1.0000
123,624.00 - 123,624.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 171,000.00 1.0000
134,784.50 - 134,784.50
10,200.00 - 10,200.00
Halaman 310
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
7,854.00 - 7,854.00
- - 171,000.00 1.0000
151,096.00 - 151,096.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 171,000.00 1.0000
145,945.00 - 145,945.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 171,000.00 1.0000
70,397.00 - 70,397.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 171,000.00 1.0000
Halaman 311
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
49,793.00 - 49,793.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 123,000.00 1.0000
97,869.00 - 97,869.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
104,737.00 - 104,737.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
Halaman 312
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
141,209.65 0.00 295,309.00
109,888.00 - 109,888.00
10,200.00 - 10,200.00
7,854.00 - 7,854.00
- - 134,000.00 1.0000
30,600.00 - 30,600.00
60,690.00 - 60,690.00
224.40 - 224.40
20.40 - 20.40
- - 7,900.00 0.1000
- - 5,150.00 0.0500
- - 560.00 0.0050
- - 640.00 0.0050
49,676.55 - 49,676.55
1,870.00 - 1,870.00
4,462.50 - 4,462.50
- - 47,400.00 0.6000
- - 198,000.00 1.8000
- - 20,160.00 0.1800
- - 3,840.00 0.0300
Halaman 313
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
56,100.00 - 56,100.00
1,105.00 - 1,105.00
- - 1,975.00 0.0250
- - 8,250.00 0.0750
- - 896.00 0.0080
- - 128.00 0.0010
301,070.00 - 301,070.00
86,554.65 - 86,554.65
2,805.00 - 2,805.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
135,469.60 - 135,469.60
49,676.55 - 49,676.55
2,805.00 - 2,805.00
- - 11,850.00 0.1500
Halaman 314
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
229,789.00 - 229,789.00
64,063.65 - 64,063.65
2,805.00 - 2,805.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
301,070.00 - 301,070.00
86,554.65 - 86,554.65
2,805.00 - 2,805.00
13,328.00 - 13,328.00
120,615.00 - 120,615.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
Halaman 315
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
135,469.60 - 135,469.60
49,676.55 - 49,676.55
2,805.00 - 2,805.00
13,328.00 - 13,328.00
120,615.00 - 120,615.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
229,789.00 - 229,789.00
64,063.65 - 64,063.65
2,805.00 - 2,805.00
13,328.00 - 13,328.00
120,615.00 - 120,615.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
229,789.00 - 229,789.00
64,063.65 - 64,063.65
2,805.00 - 2,805.00
109,201.39 - 109,201.39
- - 11,850.00 0.1500
Halaman 316
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
229,789.00 - 229,789.00
64,063.65 - 64,063.65
2,805.00 - 2,805.00
54,600.69 - 54,600.69
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
135,469.60 - 135,469.60
49,676.55 - 49,676.55
2,805.00 - 2,805.00
13,328.00 - 13,328.00
53,363.00 - 53,363.00
- - 11,850.00 0.1500
- - 49,500.00 0.4500
- - 5,040.00 0.0450
- - 1,024.00 0.0080
Halaman 317
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
177,352.50 - 177,352.50
57,256.94 - 57,256.94
4,046.00 - 4,046.00
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 15,800.00 0.1500
- - 66,000.00 0.4500
- - 6,720.00 0.0450
- - 1,152.00 0.0080
177,352.50 - 177,352.50
47,222.22 - 47,222.22
4,046.00 - 4,046.00
1,530.00 - 1,530.00
9,881.25 - 9,881.25
- - 15,800.00 0.1500
- - 66,000.00 0.4500
- - 6,720.00 0.0450
- - 1,152.00 0.0080
33,098.53 - 33,098.53
109,194.40 - 109,194.40
223,700.96 - 223,700.96
170,000.00 - 170,000.00
47,600.00 - 47,600.00
Halaman 318
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 56,880.00 0.7200
- - 140,800.00 1.2800
- - 14,336.00 0.1280
- - 4,608.00 0.0360
33,098.53 - 33,098.53
54,597.20 - 54,597.20
111,850.48 - 111,850.48
85,000.00 - 85,000.00
47,600.00 - 47,600.00
- - 56,880.00 0.7200
- - 140,800.00 1.2800
- - 14,336.00 0.1280
- - 4,608.00 0.0360
33,098.53 - 33,098.53
109,194.40 - 109,194.40
189,571.20 - 189,571.20
170,000.00 - 170,000.00
47,600.00 - 47,600.00
- - 56,880.00 0.7200
- - 140,800.00 1.2800
- - 14,336.00 0.1280
- - 4,608.00 0.0360
Halaman 319
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
82,419.62 0.00 114,913.22
631,883.75 0.00 881,001.35
631,883.75 0.00 881,001.00
33,098.53 - 33,098.53
54,597.20 - 54,597.20
94,785.60 - 94,785.60
85,000.00 - 85,000.00
47,600.00 - 47,600.00
- - 56,880.00 0.7200
- - 140,800.00 1.2800
- - 14,336.00 0.1280
- - 4,608.00 0.0360
79,560.00 - 79,560.00
5,950.00 - 5,950.00
- - 1,580.00 0.0200
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 320.00 0.0025
339,994.56 - 339,994.56
- - 29,625.00 0.3750
- - 12,875.00 0.1250
Halaman 320
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 1,344.00 0.0120
- - 2,432.00 0.0190
462,400.00 - 462,400.00
21,952.10 - 21,952.10
45,792.90 - 45,792.90
57,375.00 - 57,375.00
- - 29,625.00 0.3750
- - 12,875.00 0.1250
- - 1,344.00 0.0120
- - 2,432.00 0.0190
122,843.70 - 122,843.70
197,965.00 - 197,965.00
2,550.00 - 2,550.00
40,375.00 - 40,375.00
1,483.25 - 1,483.25
2,822.85 - 2,822.85
- - 29,625.00 0.3750
- - 12,875.00 0.1250
- - 1,344.00 0.0120
- - 2,432.00 0.0190
Halaman 321
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
64,387.50 - 64,387.50
9,732.50 - 9,732.50
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 166.40 0.0013
- - 5,000.00 1.0000
72,972.50 - 72,972.50
13,625.50 - 13,625.50
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 166.40 0.0013
- - 5,000.00 1.0000
56,661.00 - 56,661.00
9,732.50 - 9,732.50
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0500
- - 384.00 0.0013
- - 5,000.00 1.0000
Halaman 322
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
66,963.00 - 66,963.00
13,625.50 - 13,625.50
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 166.40 0.0013
- - 5,000.00 1.0000
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 166.40 0.0013
- - 5,000.00 1.0000
94,940.00 - 94,940.00
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
Halaman 323
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 2,800.00 0.0250
- - 384.00 0.0030
- - 5,000.00 1.0000
106,050.00 - 106,050.00
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0250
- - 384.00 0.0030
- - 5,000.00 1.0000
106,050.00 - 106,050.00
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0250
- - 384.00 0.0030
- - 5,000.00 1.0000
Halaman 324
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
117,160.00 - 117,160.00
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0250
- - 384.00 0.0030
- - 5,000.00 1.0000
224,068.50 - 224,068.50
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0500
- - 384.00 0.0013
- - 5,000.00 1.0000
261,842.50 - 261,842.50
19,465.00 - 19,465.00
- - 19,750.00 0.2500
- - 51,500.00 0.5000
- - 2,800.00 0.0500
- - 384.00 0.0013
- - 5,000.00 1.0000
Halaman 325
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
323,503.63 0.00 414,852.73
323,503.63 0.00 414,852.00
2,465.00 - 2,465.00
- - 11,850.00 0.1500
- - 384.00 0.0030
Halaman 326
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
4,692.00 - 4,692.00
646.00 - 646.00
629.00 - 629.00
3,400.00 - 3,400.00
- - 3,160.00 0.0400
- - 4,120.00 0.0400
- - 448.00 0.0040
- - 320.00 0.0025
7,140.00 - 7,140.00
11,126.50 - 11,126.50
11,126.50 - 11,126.50
1,813.56 - 1,813.56
3,230.00 - 3,230.00
364.65 - 364.65
- - 5,530.00 0.0700
- - 7,725.00 0.0750
- - 840.00 0.0075
- - 320.00 0.0025
CAT PENUTUP
8,330.00 - 8,330.00
7,140.00 - 7,140.00
11,126.50 - 11,126.50
17,017.00 - 17,017.00
136.00 - 136.00
969.00 - 969.00
110.50 - 110.50
Halaman 327
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 5,530.00 0.0700
- - 927.00 0.0090
- - 672.00 0.0060
- - 384.00 0.0030
17,017.00 - 17,017.00
4,845.00 - 4,845.00
552.50 - 552.50
- - 5,530.00 0.0700
- - 927.00 0.0090
- - 672.00 0.0060
- - 320.00 0.0025
8,330.00 - 8,330.00
7,140.00 - 7,140.00
11,126.50 - 11,126.50
22,907.50 - 22,907.50
136.00 - 136.00
969.00 - 969.00
110.50 - 110.50
- - 5,530.00 0.0700
- - 10,815.00 0.1050
- - 448.00 0.0040
- - 384.00 0.0030
Halaman 328
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
58,327.43 0.00 78,080.98
58,327.43 0.00 78,080.00
4,165.00 - 4,165.00
3,570.00 - 3,570.00
5,563.25 - 5,563.25
11,453.75 - 11,453.75
68.00 - 68.00
484.50 - 484.50
55.25 - 55.25
- - 2,765.00 0.0350
- - 5,407.50 0.0525
- - 224.00 0.0020
- - 192.00 0.0015
7,395.00 - 7,395.00
21,037.50 - 21,037.50
26,775.00 - 26,775.00
21,037.50 - 21,037.50
3,400.00 - 3,400.00
16,150.00 - 16,150.00
30,000.00 - 30,000.00
- - 39,500.00 0.5000
- - 51,500.00 0.5000
- - 5,600.00 0.0500
- - 640.00 0.0050
Halaman 329
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
3,697.50 - 3,697.50
10,518.75 - 10,518.75
13,387.50 - 13,387.50
10,518.75 - 10,518.75
1,700.00 - 1,700.00
8,075.00 - 8,075.00
15,000.00 - 15,000.00
- - 19,750.00 0.2500
- - 25,750.00 0.2500
- - 2,800.00 0.0250
- - 320.00 0.0025
14,025.00 - 14,025.00
12,015.60 - 12,015.60
13,600.00 - 13,600.00
2,550.00 - 2,550.00
110.50 - 110.50
- - 3,160.00 0.0400
- - 6,180.00 0.0600
- - 1,792.00 0.0160
- - 384.00 0.0030
20,527.50 - 20,527.50
- - 7,900.00 0.1000
- - 768.00 0.0060
Halaman 330
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
2,125.00 - 2,125.00
4,250.00 - 4,250.00
11,050.00 - 11,050.00
314.50 - 314.50
3,400.00 - 3,400.00
- - 1,580.00 0.0200
- - 6,489.00 0.0630
- - 705.60 0.0063
- - 384.00 0.0030
T PENUTUP DULUX
2,125.00 - 2,125.00
6,120.00 - 6,120.00
15,912.00 - 15,912.00
314.50 - 314.50
3,400.00 - 3,400.00
- - 1,580.00 0.0200
- - 6,489.00 0.0630
- - 705.60 0.0063
- - 320.00 0.0025
Halaman 331
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
5,100.00 - 5,100.00
7,650.00 - 7,650.00
314.50 - 314.50
3,400.00 - 3,400.00
- - 2,212.00 0.0280
- - 4,326.00 0.0420
- - 470.40 0.0042
- - 384.00 0.0030
7,344.00 - 7,344.00
11,016.00 - 11,016.00
314.50 - 314.50
3,400.00 - 3,400.00
- - 2,212.00 0.0280
- - 4,326.00 0.0420
- - 470.40 0.0042
- - 320.00 0.0025
4,250.00 - 4,250.00
11,050.00 - 11,050.00
314.50 - 314.50
3,400.00 - 3,400.00
- - 1,580.00 0.0200
- - 6,489.00 0.0630
- - 705.60 0.0063
- - 384.00 0.0030
Halaman 332
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
4,165.00 - 4,165.00
110.50 - 110.50
- - 1,580.00 0.0200
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 320.00 0.0025
5,865.00 - 5,865.00
110.50 - 110.50
- - 1,580.00 0.0200
- - 20,600.00 0.2000
- - 2,240.00 0.0200
- - 1,280.00 0.0100
9,180.00 - 9,180.00
110.50 - 110.50
- - 1,580.00 0.0200
- - 20,600.00 0.2000
- - 2,240.00 0.0200
Halaman 333
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
- - 1,280.00 0.0100
6,955.55 - 6,955.55
13,260.00 - 13,260.00
2,720.00 - 2,720.00
4,845.00 - 4,845.00
552.50 - 552.50
- - 15,800.00 0.2000
- - 30,900.00 0.3000
- - 3,360.00 0.0300
- - 1,280.00 0.0100
9,794.55 - 9,794.55
17,170.00 - 17,170.00
2,720.00 - 2,720.00
4,845.00 - 4,845.00
552.50 - 552.50
- - 15,800.00 0.2000
- - 30,900.00 0.3000
- - 3,360.00 0.0300
- - 1,280.00 0.0100
Halaman 334
7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
13,260.00 - 13,260.00
2,720.00 - 2,720.00
4,845.00 - 4,845.00
552.50 - 552.50
- - 15,800.00 0.2000
- - 20,600.00 0.2000
- - 224.00 0.0020
- - 256.00 0.0020
Halaman 335
(KODE) UPAH BAHAN ALAT JUMLAH
TABEL BANTU UTK REKAP
Halaman 336
A.2 41,411.50 60,394.84 28,750.00 130,556.00
Halaman 337
A.4 74,290.00 605,787.05 0.00 680,077.00
Halaman 338
A.7 376,970.00 30,546.88 0.00 407,516.00
Halaman 339
A.10 1,325.72 5,865.00 0.00 7,190.00
Halaman 340
B.1 71,817.50 0.00 0.00 71,817.00
Halaman 341
B.5 145,107.00 0.00 0.00 145,107.00
Halaman 342
B.9 52,785.00 0.00 0.00 52,785.00
Halaman 343
B.13 28,727.00 276,828.00 0.00 305,555.00
Halaman 344
B.16 91,586.00 93,243.73 0.00 184,829.00
Halaman 345
C.3 245,812.50 790,856.15 0.00 1,036,668.00
Halaman 346
C.6 245,812.50 442,201.45 0.00 688,013.00
Halaman 347
C.8 445,544.50 2,617,197.60 0.00 3,062,742.00
Halaman 348
C.11 32,926.80 0.00 50,025.00 82,951.00
Halaman 349
D.2 42,596.00 105,075.39 0.00 147,671.00
Halaman 350
D.4 85,192.00 213,794.89 0.00 298,986.00
Halaman 351
D.7 78,384.00 79,591.79 15,797.58 173,773.00
Halaman 352
E.1 51,800.60 24,535.25 0.00 76,335.00
Halaman 353
E.4 65,844.40 74,290.00 0.00 140,134.00
Halaman 354
E.7 32,775.00 22,678.00 0.00 55,453.00
Halaman 355
F.1 3,614,450.00 ### 0.00 ###
Halaman 356
F.3 3,614,450.00 ### 0.00 ###
Halaman 357
F.6 101,101.10 195,310.25 0.00 296,411.00
Halaman 358
F.9 101,101.10 168,429.00 0.00 269,530.00
Halaman 359
F.11 481,574.00 434,674.70 0.00 916,248.00
Halaman 360
F.14 481,574.00 382,050.99 0.00 863,624.00
Halaman 361
F.17 361,445.00 531,227.26 0.00 892,672.00
Halaman 362
10,625,000
Halaman 363
F.22 361,445.00 564,175.65 0.00 925,620.00
Halaman 364
F.25 128,392.90 506,291.21 23,000.00 657,684.00
Halaman 365
G.1 194,511.00 789,585.40 0.00 984,096.00
Halaman 366
G.4 271,089.50 1,108,485.00 2,209.73 1,381,784.00
Halaman 367
G.7 271,089.50 1,165,180.00 2,209.73 1,438,479.00
Halaman 368
G.9 271,089.50 1,291,277.50 2,209.73 1,564,576.00
Halaman 369
G.12 27,544.80 42,032.50 23,000.00 92,577.00
Halaman 370
G.15 67,597.00 176,453.41 0.00 244,050.00
Halaman 371
G.18 110,814.00 546,784.18 0.00 657,598.00
Halaman 372
G.20 110,814.00 398,951.96 0.00 509,765.00
Halaman 373
G.22 110,814.00 802,116.95 0.00 912,930.00
kode. A.4.1.1.20
Halaman 374
G.25 1,614.14 16,436.66 0.00 18,050.00
Halaman 375
G.28 6,762.00 79,382.78 230.00 86,374.00
Halaman 376
G.30 9,832.50 92,001.15 0.00 101,833.00
Halaman 377
G.33 14,020.80 284,197.18 0.00 298,217.00
Halaman 378
GB.37 284,476.03 2,896,797.40 0.00 3,181,273.43
GB.38 290,948.74 2,962,708.42 0.00 3,253,657.15
GB.39 284,411.47 2,896,139.93 0.00 3,180,551.40
GB.40 134,183.46 1,366,379.75 0.00 1,500,563.21
Halaman 379
H.3 2,065,400.00 6,446,026.00 0.00 8,511,426.00
Halaman 380
H.6 1,239,240.00 ### 0.00 ###
Halaman 381
H.8 23,759.00 81,931.12 0.00 105,690.00
Halaman 382
H.11 23,759.00 49,657.00 0.00 73,416.00
Halaman 383
H.14 23,759.00 22,108.12 0.00 45,867.00
Halaman 384
H.17 23,759.00 63,048.75 0.00 86,807.00
Halaman 385
H.19 80,120.50 118,072.23 9,909.64 208,102.00
Halaman 386
H.22 25,258.60 97,750.00 0.00 123,008.00
Halaman 387
H.25 25,258.60 70,380.00 0.00 95,638.00
Halaman 388
H.28 33,580.00 65,160.15 0.00 98,740.00
Halaman 389
H.31 24,414.50 62,169.00 0.00 86,583.00
Halaman 390
H.34 24,414.50 59,334.25 0.00 83,748.00
Halaman 391
H.37 20,148.00 45,668.80 0.00 65,816.00
Halaman 392
H.40 23,506.00 68,434.78 0.00 91,940.00
Halaman 393
H.43 33,580.00 299,395.04 0.00 332,975.00
Halaman 394
H.45 64,510.40 60,464.24 0.00 124,974.00
Halaman 395
H.48 64,510.40 52,644.24 0.00 117,154.00
Halaman 396
H.51 25,707.10 126,390.75 0.00 152,097.00
Halaman 397
H.53 67,160.00 112,784.64 0.00 179,944.00
Halaman 398
H.56 25,707.10 158,466.44 0.00 184,173.00
Halaman 399
H.59 37,697.00 90,290.89 0.00 127,987.00
Halaman 400
H.62 37,697.00 309,295.86 0.00 346,992.00
Halaman 401
H.65 37,697.00 72,159.05 0.00 109,856.00
Halaman 402
H.68 37,697.00 116,847.42 0.00 154,544.00
Halaman 403
H.70 73,462.00 195,716.03 0.00 269,178.00
Halaman 404
I.3 13,070.90 98,203.56 0.00 111,274.00
Halaman 405
I.6 23,759.00 112,616.80 0.00 136,375.00
Halaman 406
I.9 13,070.90 155,053.77 0.00 168,124.00
Halaman 407
I.11 16,790.00 44,469.19 0.00 61,259.00
Halaman 408
I.13 62,279.40 166,373.43 0.00 228,652.00
Halaman 409
I.16 62,279.40 116,853.23 0.00 179,132.00
Halaman 410
I.19 190,072.00 217,107.64 0.00 407,179.00
Halaman 411
I.22 59,512.50 115,403.65 0.00 174,916.00
Halaman 412
I.24 11,953.10 8,465.15 0.00 20,418.00
Halaman 413
I.27 14,255.40 25,439.44 0.00 39,694.00
Halaman 414
I.30 14,255.40 21,226.13 0.00 35,481.00
Halaman 415
J.1 453,780.80 1,927,630.00 0.00 2,381,410.00
Halaman 416
J.3 311,397.00 249,340.70 0.00 560,737.00
Halaman 417
J.6 105,752.85 5,245,656.00 0.00 5,351,408.00
Halaman 418
J.8 292,412.80 196,066.95 0.00 488,479.00
Halaman 419
J.11 20,700.00 62,120.13 0.00 82,820.00
Halaman 420
J.14 11,444.80 24,242.00 0.00 35,686.00
Halaman 421
J.17 25,677.20 121,210.00 0.00 146,887.00
Halaman 422
J.20 54,176.50 99,802.75 0.00 153,979.00
Halaman 423
J.23 14,777.50 22,770.00 0.00 37,547.00
Halaman 424
J.25 6,506,964.87 ### 2,479.69 ###
Halaman 425
J.27 1,986,359.47 4,264,171.26 743.91 6,251,274.00
Halaman 426
J.30 62,272.50 240,307.62 0.00 302,580.00
Halaman 427
J.33 453,780.80 1,912,987.05 0.00 2,366,767.00
Halaman 428
K.3 217.95 140.76 5,430.76 5,789.00
Halaman 429
K.6 235,290.00 549,355.00 0.00 784,645.00
Halaman 430
K.9 235,290.00 552,000.00 0.00 787,290.00
Halaman 431
K.12 23,096.60 65,888.00 0.00 88,984.00
Halaman 432
L.1 66,182.50 154,445.00 0.00 220,627.00
Halaman 433
L.4 14,920.10 34,212.50 0.00 49,132.00
Halaman 434
L.7 74,600.50 193,545.00 0.00 268,145.00
Halaman 435
L.10 72,814.78 462,967.00 0.00 535,781.00
Halaman 436
L.12 165,843.80 1,433,061.00 0.00 1,598,904.00
Halaman 437
L.15 575,000.00 ### 0.00 ###
Halaman 438
L.18 20,174.45 707,974.50 0.00 728,148.00
Halaman 439
M.1 42,607.50 121,294.05 0.00 163,901.00
Halaman 440
M.4 114,712.50 379,611.15 0.00 494,323.00
Halaman 441
M.7 114,712.50 138,270.31 0.00 252,982.00
Halaman 442
M.9 114,712.50 188,162.89 0.00 302,875.00
Halaman 443
M.12 114,712.50 502,602.15 0.00 617,314.00
Halaman 444
M.14 114,712.50 203,246.69 0.00 317,959.00
Halaman 445
M.17 114,712.50 443,427.24 0.00 558,139.00
Halaman 446
M.19 114,712.50 151,033.53 0.00 265,746.00
Halaman 447
M.22 117,530.00 51,612.00 0.00 169,142.00
Halaman 448
M.25 203,550.00 133,311.45 0.00 336,861.00
Halaman 449
M.28 203,550.00 133,311.45 0.00 336,861.00
Halaman 450
M.31 28,510.80 25,558.69 0.00 54,069.00
Halaman 451
N.3 114,712.50 168,437.91 0.00 283,150.00
Halaman 452
N.5 114,712.50 217,238.62 0.00 331,951.00
Halaman 453
N.8 114,712.50 832,406.97 0.00 947,119.00
Halaman 454
N.10 213,428.50 1,889,584.72 0.00 2,103,013.00
Halaman 455
N.13 154,100.00 188,598.85 0.00 342,698.00
Halaman 456
N.17 154,100.00 186,624.30 0.00 340,724.00
Halaman 457
N.20 154,100.00 218,217.10 0.00 372,317.00
Halaman 458
N.23 154,100.00 126,400.53 0.00 280,500.00
Halaman 459
N.26 154,100.00 409,748.45 0.00 563,848.00
Halaman 460
N.30 154,100.00 338,664.65 0.00 492,764.00
Halaman 461
N.33 147,200.00 125,413.25 0.00 272,613.00
Halaman 462
N.36 147,200.00 202,420.70 0.00 349,620.00
Halaman 463
N.40 141,450.00 113,565.95 0.00 255,015.00
Halaman 464
N.43 196,650.00 175,764.28 0.00 372,414.00
Halaman 465
N.46 196,650.00 101,718.65 0.00 298,368.00
Halaman 466
N.49 154,100.00 141,209.65 0.00 295,309.00
Halaman 467
N.52 309,810.00 64,410.41 0.00 374,220.00
Halaman 468
N.55 77,526.10 216,143.82 0.00 293,669.00
Halaman 469
N.58 77,526.10 370,178.27 0.00 447,704.00
Halaman 470
N.60 77,526.10 466,737.89 0.00 544,263.00
Halaman 471
N.63 103,122.80 287,576.70 0.00 390,699.00
Halaman 472
N.65 249,117.60 671,132.97 0.00 920,250.00
Halaman 473
N.67 249,117.60 631,883.75 0.00 881,001.00
Halaman 474
O.1 53,217.40 390,993.74 0.00 444,211.00
Halaman 475
O.4 94,318.86 85,238.00 0.00 179,556.00
Halaman 476
O.6 91,349.10 76,352.53 0.00 167,701.00
Halaman 477
O.9 91,349.10 131,565.75 0.00 222,914.00
Halaman 478
O.12 91,349.10 157,118.75 0.00 248,467.00
Halaman 479
O.14 91,349.10 323,503.63 0.00 414,852.00
Halaman 480
P.2 9,255.20 10,772.05 0.00 20,027.00
Halaman 481
P.4 8,639.95 51,553.35 0.00 60,193.00
Halaman 482
P.6 19,753.55 58,327.43 0.00 78,080.00
Halaman 483
P.9 55,913.00 72,332.13 0.00 128,245.00
Halaman 484
P.11 9,968.20 23,606.63 0.00 33,574.00
Halaman 485
P.14 8,501.26 18,934.18 0.00 27,435.00
Halaman 486
P.16 10,532.39 21,866.68 0.00 32,399.00
Halaman 487
P.19 29,555.00 10,684.08 0.00 40,239.00
Halaman 488
P.22 42,412.00 24,584.13 0.00 66,996.00
Halaman 489
PEMERINTAH KABUPATEN INDRAMAYU
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jl. Pahlawan No. 61 Telp. (0234) 274264 Fax (0234) 272741
I N D R A M A Y U - 45212
A PEKERJAAN PERSIAPAN A
1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK A.1 23,759.00 60,394.84 0.00 84,153.00
2 1 M' PEMASANGAN DAN PENGUKURAN BOUWPLANK (ALAT UKUR) A.2 41,411.50 60,394.84 28,750.00 130,556.00
3 1 M2 PEMBUATAN KANTOR SEMENTARA (DIREKSI KEET) LANTAI PLESTERAN A.3 599,150.00 888,870.08 0.00 1,488,020.00
4 1 M' PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER A.4 74,290.00 605,787.05 0.00 680,077.00
5 1 M2 PEMBUATAN PAPAN NAMA PROYEK DIGITAL PRINTING A.5 63,250.00 297,168.28 0.00 360,418.00
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN A.6 16,445.00 0.00 0.00 16,445.00
7 1 M2 PEMBUATAN STEGER/PERANCA DARI BAMBU A.7 376,970.00 30,546.88 0.00 407,516.00
8 1 UNIT PEKERJAAN PERANCAH DARI SCAFFOLDING (SEWA per BULAN) A.8 116,495.00 71,875.00 0.00 188,370.00
9 1 BUAH PEMBUATAN KOTAK ADUKAN UKURAN 40 X 50 X 25 CM A.9 41,814.00 200,555.63 0.00 242,369.00
10 1 TITIK CERUCUK BAMBU Ø 8 CM - 10 CM, Uk. P. 1 M - 1,5 M A.10 1,325.72 5,865.00 0.00 7,190.00
11 1 M2 PASANGAN STOOT WERK A.11 67,189.90 235,256.88 0.00 302,446.00
12 1 M3 BONGKARAN BETON BERTULANG A.12 1,309,429.10 0.00 0.00 1,309,429.00
13 1 M3 BONGKARAN DINDING TEMBOK BATA A.13 654,714.55 0.00 0.00 654,714.00
B PEKERJAAN TANAH B
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER B.1 71,817.50 0.00 0.00 71,817.00
2 1 M3 GALIAN TANAH BIASA SEDALAM 2 METER B.2 88,389.00 0.00 0.00 88,389.00
3 1 M3 GALIAN TANAH BIASA SEDALAM 3 METER B.3 77,520.35 0.00 0.00 77,520.00
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 METER B.4 95,560.40 0.00 0.00 95,560.00
5 1 M3 GALIAN TANAH CADAS SEDALAM 1 METER B.5 145,107.00 0.00 0.00 145,107.00
6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 METER B.6 115,644.00 0.00 0.00 115,644.00
7 1 M2 PEKERJAAN STRIPING TANAH TEBING SETINGGI 1 METER B.7 5,278.50 0.00 0.00 5,278.00
8 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER B.8 31,452.50 0.00 0.00 31,452.00
9 1 M3 URUGAN KEMBALI GALIAN TANAH B.9 52,785.00 0.00 0.00 52,785.00
10 1 M3 PEMADATAN TANAH B.10 4,714.31 0.00 6,411.25 11,125.00
11 1 M3 URUGAN TANAH LOKAL B.11 28,727.00 95,013.00 0.00 123,740.00
12 1 M3 URUGAN PASIR B.12 28,727.00 268,617.00 0.00 297,344.00
13 1 M3 URUGAN TANAH MERAH B.13 28,727.00 276,828.00 0.00 305,555.00
14 1 M3 URUGAN SIRTU B.14 26,392.50 327,267.00 0.00 353,659.00
15 1 M3 URUGAN LIMESTONE B.15 26,392.50 252,195.00 0.00 278,587.00
16 1 M2 PEMBUATAN JALAN SEMENTARA B.16 91,586.00 93,243.73 0.00 184,829.00
C PEKERJAAN PONDASI C
1 1 M3 PASANG PONDASI BATU KALI 1 Pc : 2 Ps C.1 245,812.50 915,346.64 0.00 1,161,159.00
2 1 M3 PASANG PONDASI BATU KALI 1 Pc : 3 Ps C.2 245,812.50 837,502.45 0.00 1,083,314.00
3 1 M3 PASANG PONDASI BATU KALI 1 Pc : 4 Ps C.3 245,812.50 790,856.15 0.00 1,036,668.00
4 1 M3 PASANG PONDASI BATU KALI 1 Pc : 5 Ps C.4 245,812.50 758,493.08 0.00 1,004,305.00
5 1 M3 PASANG PONDASI BATU LAMA C.5 245,812.50 363,192.08 0.00 609,004.00
6 1 M3 PASANG PONDASI BATU LAMA 1 PC : 3 PS C.6 245,812.50 442,201.45 0.00 688,013.00
7 1 M3 PASANG BATU KOSONG (AANSTAMPING) C.7 127,822.50 492,003.12 0.00 619,825.00
8 1 M3 PASANG PONDASI SIKLOP 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR DAN 40% BATU BELAH C.8 445,544.50 2,617,197.60 0.00 3,062,742.00
9 1 M' PENGEBORAN LUBANG BORED PILE DIA-20 CM PADA TANAH BIASA C.9 14,591.66 0.00 21,413.00 36,004.00
10 1 M' PENULANGAN+PENGECORAN BORED PILE DIA-20 CM C.10 6,943.36 101,680.92 3,624.92 112,249.00
11 1 M' PENGEBORAN LUBANG BORED PILE DIA-30 CM PADA TANAH BIASA C.11 32,926.80 0.00 50,025.00 82,951.00
12 1 M' PENULANGAN+PENGECORAN BORED PILE DIA-30 CM C.12 12,518.33 227,643.79 3,107.07 243,269.00
E PEKERJAAN PLESTERAN E
1 1 M2 PLESTERAN, 1Pc : 3PP, TEBAL 20 mm E.1 51,800.60 24,535.25 0.00 76,335.00
2 1 M2 PLESTERAN, 1Pc : 4PP, TEBAL 20 mm E.2 65,844.40 21,833.44 0.00 87,677.00
3 1 M2 PLESTERAN, 1Pc : 5PP, TEBAL 20 mm E.3 65,844.40 20,672.17 0.00 86,516.00
4 1 M2 PLESTERAN DINDING BATA RINGAN E.4 65,844.40 74,290.00 0.00 140,134.00
5 1 M2 PLESTERAN SIAR ADUKAN 1Pc : 2PP E.5 49,162.50 12,908.87 0.00 62,071.00
6 1 M2 ACIAN E.6 32,775.00 4,765.31 0.00 37,540.00
Halaman 490
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
7 1 M2 ACIAN DINDING BATA RINGAN (FINE COAT-PM 300) E.7 32,775.00 22,678.00 0.00 55,453.00
8 1 M2 KAMPROTAN 1Pc : 2PP E.8 42,596.00 8,140.62 0.00 50,736.00
9 1 M' SKONING 1Pc : 3PP Lebar 10 cm E.9 60,388.80 4,647.04 0.00 65,035.00
G PEKERJAAN BETON G
1 1 M3 MEMBUAT BETON TUMBUK, 1Pc : 3Ps : 5Kr G.1 194,511.00 789,585.40 0.00 984,096.00
2 1 M3 COR BETON SITE MIX K. 175 G.2 203,412.00 982,123.58 4,312.50 1,189,848.00
3 1 M3 COR BETON SITE MIX K. 225 G.3 203,412.00 1,037,029.75 4,025.00 1,244,466.00
4 1 M3 COR BETON K. 175 READY MIX G.4 271,089.50 1,108,485.00 2,209.73 1,381,784.00
5 1 M3 COR BETON K. 225 READY MIX G.5 271,089.50 1,100,665.00 2,209.73 1,373,964.00
6 1 M3 COR BETON K. 250 READY MIX G.6 271,089.50 1,142,697.50 2,209.73 1,415,996.00
7 1 M3 COR BETON K. 300 READY MIX G.7 271,089.50 1,165,180.00 2,209.73 1,438,479.00
8 1 M3 COR BETON K. 350 READY MIX G.8 271,089.50 1,245,335.00 2,209.73 1,518,634.00
9 1 M3 COR BETON K. 400 READY MIX G.9 271,089.50 1,291,277.50 2,209.73 1,564,576.00
10 1 M3 COR BETON K. 450 READY MIX G.10 271,089.50 1,359,702.50 2,209.73 1,633,001.00
11 1 M3 COR BETON K. 500 READY MIX G.11 271,089.50 1,455,497.50 2,209.73 1,728,796.00
12 1 M2 MEMASANG FLOOR HARDENER G.12 27,544.80 42,032.50 23,000.00 92,577.00
13 1 M3 COR BETON 1 PC : 2 PS : 3 SCREENING G.13 203,412.00 1,047,322.83 4,025.00 1,254,759.00
14 1 M2 BEKISTING MULTIPLEX 9 MM G.14 67,597.00 156,101.86 0.00 223,698.00
15 1 M2 BEKISTING MULTIPLEX 12 MM G.15 67,597.00 176,453.41 0.00 244,050.00
16 1 M2 BEKISTING UNTUK PONDASI G.16 87,308.00 207,718.75 0.00 295,026.00
17 1 M2 BEKISTING UNTUK SLOOF G.17 87,308.00 232,645.00 0.00 319,953.00
18 1 M2 BEKISTING MULTIPLEX 9 MM UNTUK KOLOM G.18 110,814.00 546,784.18 0.00 657,598.00
19 1 M2 BEKISTING MULTIPLEX 9 MM UNTUK BALOK G.19 110,814.00 649,963.21 0.00 760,777.00
20 1 M2 BEKISTING MULTIPLEX 9 MM UNTUK LANTAI G.20 110,814.00 398,951.96 0.00 509,765.00
21 1 M2 BEKISTING MULTIPLEX 9 MM UNTUK DINDING G.21 110,814.00 636,476.70 0.00 747,290.00
22 1 M2 BEKISTING MULTIPLEX 9 MM UNTUK TANGGA G.22 110,814.00 802,116.95 0.00 912,930.00
23 1 M2 PASANG BEKISTING PAPAN G.23 67,597.00 179,379.07 0.00 246,976.00
24 1 KG PEMBESIAN DENGAN BESI POLOS G.24 1,614.14 15,923.48 0.00 17,537.00
25 1 KG PEMBESIAN DENGAN BESI ULIR G.25 1,614.14 16,436.66 0.00 18,050.00
26 1 M2 WIREMESH M-5 G.26 6,762.00 46,236.90 230.00 53,228.00
27 1 M2 WIREMESH M-6 G.27 6,762.00 54,749.78 230.00 61,741.00
28 1 M2 WIREMESH M-8 G.28 6,762.00 79,382.78 230.00 86,374.00
29 1 M2 WIREMESH M-10 G.29 6,762.00 136,859.78 230.00 143,851.00
30 1 M' PASANG PVC WATERSTOP LEBAR 150 G.30 9,832.50 92,001.15 0.00 101,833.00
31 1 M' PASANG PVC WATERSTOP LEBAR 200 G.31 9,832.50 119,894.40 0.00 129,726.00
32 1 M2 BEKISTING LANTAI FLOORDECK / BONDECK TIPE PLAT (JAP ≤ 0,6 M) G.32 17,526.00 281,349.52 0.00 298,875.00
33 1 M2 BEKISTING LANTAI FLOORDECK / BONDECK TIPE PLAT (JAP ≤ 0,8 M) G.33 14,020.80 284,197.18 0.00 298,217.00
Halaman 491
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
8 PEMBESIAN KOLOM 25/25 GB.8 310,947.93 3,166,358.66 3,477,306.59
9 PEMBESIAN KOLOM 25/30 GB.9 323,683.49 3,296,043.93 3,619,727.43
10 PEMBESIAN KOLOM 30/30 GB.10 278,342.30 2,834,338.08 3,112,680.38
11 PEMBESIAN KOLOM 30/35 GB.11 289,625.14 2,949,230.35 3,238,855.49
12 PEMBESIAN KOLOM 40/40 GB.12 291,352.27 2,966,817.58 3,258,169.85
13 PEMBESIAN RINGBALK 15/20 GB.13 269,028.71 2,739,498.54 3,008,527.25
14 PEMBESIAN BALOK 15/25 GB.14 263,863.47 2,686,901.22 2,950,764.68
15 PEMBESIAN BALOK 15/30 GB.15 324,264.58 3,301,961.13 3,626,225.71
16 PEMBESIAN BALOK LATEI 10/10 GB.16 516,524.80 5,259,732.00 5,776,256.80
17 PEMBESIAN PLAT DAK BETON T. 12 CM GB.17 246,027.22 2,505,276.10 2,751,303.32
18 PEMBESIAN PLAT DAK BETON T. 10 CM GB.18 192,244.07 1,957,606.50 2,149,850.58
19 PEMBESIAN BALOK 20/30 GB.19 306,686.60 3,122,965.88 3,429,652.48
20 PEMBESIAN BALOK 20/40 GB.20 344,215.36 3,505,118.28 3,849,333.63
21 PEMBESIAN BALOK 25/50 GB.21 311,206.19 3,168,988.53 3,480,194.72
22 PEMBESIAN BALOK 30/60 GB.22 307,590.52 3,132,170.41 3,439,760.92
23 PEMBESIAN PONDASI POOR GB.23 169,484.70 1,725,849.56 1,895,334.26
24 PEMBESIAN PONDASI FOOT PLAT T.20 CM GB.24 267,947.24 2,728,485.98 2,996,433.22
25 PEMBESIAN PONDASI FOOT PLAT T.25 CM GB.25 222,428.49 2,264,972.09 2,487,400.58
26 PEMBESIAN PONDASI FOOT PLAT T.15 CM GB.26 337,145.42 3,433,125.70 3,770,271.12
27 PEMBESIAN BALOK 20/35 GB.27 351,414.42 3,578,425.79 3,929,840.21
28 PEMBESIAN BALOK 25/40 GB.28 330,253.04 3,362,941.15 3,693,194.19
29 PEMBESIAN BALOK 25/45 GB.29 319,664.29 3,255,116.64 3,574,780.93
30 PEMBESIAN BALOK 30/55 GB.30 302,280.00 3,078,093.79 3,380,373.78
31 PEMBESIAN KOLOM 15/15 GB.31 341,487.46 3,477,340.32 3,818,827.78
32 PEMBESIAN KOLOM 15/20 GB.32 364,795.64 3,714,685.73 4,079,481.37
33 PEMBESIAN KOLOM 15/25 GB.33 302,167.01 3,076,943.22 3,379,110.23
34 PEMBESIAN KOLOM 15/30 GB.34 324,264.58 3,301,961.13 3,626,225.71
35 PEMBESIAN KOLOM 20/30 GB.35 323,909.47 3,298,345.06 3,622,254.54
36 PEMBESIAN KOLOM 30/40 GB.36 297,001.76 3,024,345.90 3,321,347.66
37 PEMBESIAN KOLOM 50/50 GB.37 284,476.03 2,896,797.40 3,181,273.43
38 PEMBESIAN KOLOM 35/35 GB.38 290,948.74 2,962,708.42 3,253,657.15
39 PEMBESIAN KOLOM 45/45 GB.39 284,411.47 2,896,139.93 3,180,551.40
40 PEMBESIAN PLAT LISTPLANK, KANOPI T. 8 CM GB.40 134,183.46 1,366,379.75 1,500,563.21
H PEKERJAAN ATAP H
1 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU KAMPER H.1 2,065,400.00 ### 0.00 15,993,015.00
2 1 M3 PASANG GORDING KAYU KAMPER H.2 1,239,240.00 ### 0.00 15,110,942.00
3 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU BORNEO H.3 2,065,400.00 6,446,026.00 0.00 8,511,426.00
4 1 M3 PASANG GORDING KAYU BORNEO H.4 1,239,240.00 6,390,113.00 0.00 7,629,353.00
5 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU KRUING H.5 2,065,400.00 ### 0.00 12,772,641.00
6 1 M3 PASANG GORDING KAYU KRUING H.6 1,239,240.00 ### 0.00 11,890,568.00
7 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU LAMA H.7 2,065,400.00 325,703.00 0.00 2,391,103.00
8 1 M2 PASANG KASO + RENG KAYU BORNEO untuk GENTENG PALENTONG H.8 23,759.00 81,931.12 0.00 105,690.00
9 1 M3 PASANG KASO + RENG KAYU KRUING untuk GENTENG PALENTONG H.9 23,759.00 114,954.00 0.00 138,713.00
10 1 M3 PASANG RANGKA ATAP KASO LAMA, RENG KAYU KRUING H.10 23,759.00 27,471.66 0.00 51,230.00
11 1 M3 PASANG KASO + RENG KAYU DOLKEN untuk GENTENG PALENTONG H.11 23,759.00 49,657.00 0.00 73,416.00
12 1 M3 PASANG KASO DOLKEN + RENG BAMBU untuk ATAP IJUK H.12 23,759.00 58,454.50 0.00 82,213.00
13 1 M2 PASANG KASO DOLKEN + RENG KAYU BORNEO untuk GENTENG PALENTONG H.13 23,759.00 40,680.62 0.00 64,439.00
14 1 M3 PASANG RANGKA ATAP KASO LAMA + RENG KAYU BORNEO H.14 23,759.00 22,108.12 0.00 45,867.00
15 1 M2 PASANG KASO + RENG KAYU BORNEO untuk GENTENG MORANDO H.15 23,759.00 81,931.12 0.00 105,690.00
16 1 M2 PASANG KASO + RENG KAYU KRUING untuk GENTENG MORANDO H.16 23,759.00 129,534.39 0.00 153,293.00
17 1 M2 PASANG RANGKA ATAP KAYU BORNEO untuk GENTENG TEGOLA H.17 23,759.00 63,048.75 0.00 86,807.00
18 1 M2 PASANG KUDA-KUDA BAJA RINGAN PROFIL C75 + RENG untuk ATAP SPANDEK/ASBES H.18 80,120.50 81,564.56 8,084.25 169,769.00
19 1 M2 PASANG KUDA-KUDA BAJA RINGAN PROFIL C75 + RENG untuk ATAP GENTENG BIASA H.19 80,120.50 118,072.23 9,909.64 208,102.00
20 1 M2 PASANG PENUTUP ATAP GENTENG LAMA H.20 25,258.60 0.00 0.00 25,258.00
21 1 M2 PASANG ATAP GENTENG PALENTONG KECIL H.21 25,258.60 48,875.00 0.00 74,133.00
22 1 M2 PASANG ATAP GENTENG KODOK GLAZUUR H.22 25,258.60 97,750.00 0.00 123,008.00
23 1 M2 PASANG ATAP GENTENG KODOK NATURAL H.23 25,258.60 97,750.00 0.00 123,008.00
24 1 M2 PASANG ATAP GENTENG MORANDO NATURAL H.24 25,258.60 70,380.00 0.00 95,638.00
25 1 M2 PASANG ATAP GENTENG MORANDO TRANSPARANT H.25 25,258.60 70,380.00 0.00 95,638.00
26 1 M2 PASANG ATAP GENTENG MORANDO WARNA H.26 25,258.60 87,975.00 0.00 113,233.00
27 1 M2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR H.27 25,258.60 35,190.00 0.00 60,448.00
28 1 M2 PASANG ATAP GENTENG BETON H.28 33,580.00 65,160.15 0.00 98,740.00
29 1 M2 PASANG ATAP GENTENG BETON (SETARA CISANGKAN) H.29 33,580.00 139,795.15 0.00 173,375.00
30 1 M2 PASANG ATAP GENTENG METAL BERPASIR H.30 33,580.00 156,966.95 0.00 190,546.00
31 1 M2 PASANG ATAP ASBES GELOMBANG (2,25 x 0,92) x 4 mm H.31 24,414.50 62,169.00 0.00 86,583.00
32 1 M2 PASANG ATAP ASBES GELOMBANG (2,25 x 0,92) x 5 mm (GORDING CANAI) H.32 24,414.50 65,101.50 0.00 89,516.00
33 1 M2 PASANG ATAP ASBES GELOMBANG (2,25 x 0,92) x 5 mm (GORDING KAYU) H.33 24,414.50 56,304.00 0.00 80,718.00
34 1 M2 PASANG ATAP ASBES GELOMBANG (2,50 x 0,92) x 4 mm H.34 24,414.50 59,334.25 0.00 83,748.00
35 1 M2 PASANG ATAP ASBES GELOMBANG (2,50 x 0,92) x 5 mm H.35 24,414.50 60,311.75 0.00 84,726.00
36 1 M2 PASANG ATAP SENG GELOMBANG BJLS 28 RANGKA CANAL H.36 20,148.00 58,063.50 0.00 78,211.00
37 1 M2 PASANG ATAP SENG GELOMBANG BJLS 28 RANGKA KAYU H.37 20,148.00 45,668.80 0.00 65,816.00
38 1 M2 PASANG ATAP ZINCALUME (SPANDEK) H.38 24,336.30 79,829.17 0.00 104,165.00
39 1 M2 PASANG ATAP BITUMEN MOTIF GENTENG T. 3 MM H.39 23,506.00 181,558.95 0.00 205,064.00
40 1 M2 PASANG ATAP BITUMEN BERGELOMBANG T. 3 MM H.40 23,506.00 68,434.78 0.00 91,940.00
41 1 M2 PASANG ATAP TEGOLA H.41 23,506.00 310,107.97 0.00 333,613.00
Halaman 492
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
42 1 M2 PASANG ATAP GENTENG BITUMEN (ONDULINE) - Uk.200x97x0.3 cm H.42 23,506.00 183,208.05 0.00 206,714.00
43 1 M2 PASANG ATAP GENTENG BITUMEN (ONDUVILA) - Uk.106x40x0.3 cm H.43 33,580.00 299,395.04 0.00 332,975.00
44 1 M' PASANG BUBUNG GENTENG PALENTONG H.44 64,510.40 50,689.24 0.00 115,199.00
45 1 M' PASANG BUBUNG GENTENG KODOK GLAZUUR H.45 64,510.40 60,464.24 0.00 124,974.00
46 1 M' PASANG BUBUNG GENTENG KODOK / ALTO NATURAL H.46 64,510.40 50,689.24 0.00 115,199.00
47 1 M' PASANG BUBUNG GENTENG MORANDO NATURAL H.47 64,510.40 48,734.24 0.00 113,244.00
48 1 M' PASANG BUBUNG GENTENG MORANDO TRANSPARANT H.48 64,510.40 52,644.24 0.00 117,154.00
49 1 M' PASANG BUBUNG GENTENG MORANDO WARNA H.49 64,510.40 56,554.24 0.00 121,064.00
50 1 M' PASANG BUBUNG GENTENG PALENTONG BESAR H.50 64,510.40 44,824.24 0.00 109,334.00
51 1 M' PASANG BUBUNG STEEL GELOMBANG 0.92 M H.51 25,707.10 126,390.75 0.00 152,097.00
52 1 M' PASANG NOK GENTENG BETON H.52 67,160.00 70,493.39 0.00 137,653.00
53 1 M' PASANG NOK GENTENG BETON (SETARA CISANGKAN) H.53 67,160.00 112,784.64 0.00 179,944.00
54 1 M' PASANG NOK GENTENG METAL H.54 45,533.10 62,560.00 0.00 108,093.00
55 1 M' PASANG NOK SENG H.55 24,396.10 19,491.35 0.00 43,887.00
56 PEMASANGAN 1 M PANJANG NOK BITUMEN H.56 25,707.10 158,466.44 0.00 184,173.00
57 1 M' PASANG LISTPLANK (3 x 20) cm, KAYU KAMPER H.57 37,697.00 155,723.18 0.00 193,420.00
58 1 M' PASANG LISTPLANK (3 x 20) cm, KAYU KRUING H.58 37,697.00 115,817.72 0.00 153,514.00
59 1 M' PASANG LISTPLANK (3 x 5) cm, KAYU BORNEO H.59 37,697.00 90,290.89 0.00 127,987.00
60 1 M' PASANG LISTPLANK (3 x 30) cm, KAYU KAMPER H.60 37,697.00 158,567.12 0.00 196,264.00
61 1 M' PASANG LISTPLANK (3 x 30) cm, KAYU KRUING H.61 37,697.00 117,922.67 0.00 155,619.00
62 1 M' PASANG LISTPLANK 2 (3 x 20) cm, KAYU KAMPER H.62 37,697.00 309,295.86 0.00 346,992.00
63 1 M' PASANG LISTPLANK 2 (3 x 20) cm, KAYU KRUING H.63 37,697.00 229,484.94 0.00 267,181.00
64 1 M' PASANG LISTPLANK GRC TUMPANGSARI (1/20 +1/10) CM H.64 37,697.00 59,533.01 0.00 97,230.00
65 1 M' PASANG LISTPLANK GRC TUMPANGSARI (1/30 +1/10) CM H.65 37,697.00 72,159.05 0.00 109,856.00
66 1 M' PASANG LISTPLANK GRC 1/30 CM H.66 37,697.00 46,499.68 0.00 84,196.00
67 1 M' PASANG LISTPLANK (3 x 20) cm, KAYU KRUING H.67 37,697.00 115,817.72 0.00 153,514.00
68 1 M' PASANG LISTPLANK (3 x 30) cm, KAYU KRUING H.68 37,697.00 116,847.42 0.00 154,544.00
69 1 M2 PASANGAN TALANG DATAR / JUREY SENG BJLS 28 L. 90 cm H.69 73,462.00 200,603.53 0.00 274,065.00
70 1 M' PASANG TALANG MIRING, SENG BJLS 28 H.70 73,462.00 195,716.03 0.00 269,178.00
I PEKERJAAN LANGIT-LANGIT I
1 1 M2 LANGIT-LANGIT ASBES (1,00 X 1,00) M, TEBAL 5 mm I.1 13,070.90 86,274.15 0.00 99,345.00
2 1 M2 LANGIT-LANGIT ASBES (1,00 X 1,00) M, TEBAL 4 mm I.2 13,070.90 31,436.40 0.00 44,507.00
3 1 M2 LANGIT-LANGIT ASBES (1,00x1,00) m, TEBAL 4 mm, RANGKA BORNEO I.3 13,070.90 98,203.56 0.00 111,274.00
4 1 M2 LANGIT-LANGIT ASBES (1,00x1,00) m, TEBAL 4 mm, RANGKA KRUING I.4 13,070.90 145,960.30 0.00 159,031.00
5 1 M2 LANGIT-LANGIT ASBES (1,00x1,00) m, TEBAL 4 mm, RANGKA KAYU LAMA I.5 13,070.90 32,707.15 0.00 45,778.00
6 1 M2 LANGIT-LANGIT TRIPLEK 6 mm, RANGKA BORNEO I.6 23,759.00 112,616.80 0.00 136,375.00
7 1 M2 LANGIT-LANGIT TRIPLEK 6 mm, KAYU LAMA I.7 23,759.00 2,057.64 0.00 25,816.00
8 1 M2 LANGIT-LANGIT GRC, RANGKA KAYU BORNEO I.8 13,070.90 108,567.78 0.00 121,638.00
9 1 M2 LANGIT-LANGIT GRC, RANGKA KAYU KRUING I.9 13,070.90 155,053.77 0.00 168,124.00
10 1 M2 LANGIT-LANGIT GRC, RANGKA KAYU LAMA I.10 13,070.90 41,800.62 0.00 54,871.00
11 1 M2 LANGIT-LANGIT GRC, TANPA RANGKA I.11 16,790.00 44,469.19 0.00 61,259.00
12 1 M2 LANGIT-LANGIT GYPSUM BOARD TEBAL 9 mm, RANGKA BORNEO I.12 62,279.40 119,887.44 0.00 182,166.00
13 1 M2 LANGIT-LANGIT GYPSUM BOARD TEBAL 9 mm, RANGKA KRUING I.13 62,279.40 166,373.43 0.00 228,652.00
14 1 M2 LANGIT-LANGIT GYPSUM BOARD, TEBAL 9 mm, TANPA RANGKA I.14 16,790.00 51,829.98 0.00 68,619.00
15 1 M2 LANGIT-LANGIT PVC (POLOS) I.15 62,279.40 112,868.48 0.00 175,147.00
16 1 M2 LANGIT-LANGIT PVC (MOTIF) I.16 62,279.40 116,853.23 0.00 179,132.00
17 1 M2 LANGIT-LANGIT PVC (URAT JATI) I.17 62,279.40 120,958.73 0.00 183,238.00
18 1 M2 LANGIT-LANGIT AKUSTIK (60 X 120) CM I.18 23,759.00 287,385.00 0.00 311,144.00
19 1 M2 LANGIT-LANGIT LAMBRISERING KAYU 9 CM I.19 190,072.00 217,107.64 0.00 407,179.00
20 1 M2 PLAFOND SPANDRELL I.20 196,938.88 565,130.70 0.00 762,069.00
21 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00 x 1.00) m, KAYU BORNEO I.21 59,512.50 68,917.66 0.00 128,430.00
22 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00 x 1.00) m, KAYU KRUING I.22 59,512.50 115,403.65 0.00 174,916.00
23 1 M2 PASANG RANGKA HOLLOW GALVALUME untuk PLAFON, MODUL 60x60 CM I.23 16,790.00 59,496.98 0.00 76,286.00
24 1 M' PASANG LIST PLAFOND - KAYU PROFIL I.24 11,953.10 8,465.15 0.00 20,418.00
25 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 10 cm I.25 14,255.40 19,281.19 0.00 33,536.00
26 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 12 cm I.26 14,255.40 23,386.69 0.00 37,642.00
27 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 15 cm I.27 14,255.40 25,439.44 0.00 39,694.00
28 1 M' PASANG LIST PLAFON PVC, L.4 cm I.28 14,255.40 26,056.13 0.00 40,311.00
29 1 M' PASANG LIST PLAFON PVC, L.7 cm I.29 14,255.40 29,678.63 0.00 43,934.00
30 1 M' PEKERJAAN SHADOW LINE I.30 14,255.40 21,226.13 0.00 35,481.00
31 1 KG GANTUNGAN PLAFOND BESI D. 10 mm I.31 6,762.00 15,747.53 230.00 22,739.00
32 1 M' PASANG DROP CEILING GYPSUM BOARD, RANGKA HOLLOW, TINGGI 30 CM I.32 16,790.00 61,368.26 0.00 78,158.00
J PEKERJAAN SANITASI J
1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK (SETARA INA) J.1 453,780.80 1,927,630.00 0.00 2,381,410.00
2 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK (SETARA TOTO) J.2 453,780.80 2,792,424.25 0.00 3,246,205.00
3 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN J.3 311,397.00 249,340.70 0.00 560,737.00
4 MEMASANG 1 BUAH URINOIR J.4 229,540.00 2,905,305.95 0.00 3,134,845.00
5 MEMASANG 1 BUAH WASHTAFEL J.5 308,924.50 1,649,355.30 0.00 1,958,279.00
6 MEMASANG 1 BUAH BATHTUB J.6 105,752.85 5,245,656.00 0.00 5,351,408.00
7 MEMASANG 1 BUAH BAK MANDI BATU BATA LAPIS KERAMIK VOLUME 0,3 M3 J.7 943,506.00 825,410.78 0.00 1,768,916.00
8 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (30 x 30) cm, T = 35 cm J.8 292,412.80 196,066.95 0.00 488,479.00
9 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45 x 45) cm, T = 50 cm J.9 430,709.50 302,858.83 0.00 733,568.00
10 MEMASANG 1 M' PIPA GALVANIS DIAMETER 1/2" J.10 20,700.00 43,938.63 0.00 64,638.00
Halaman 493
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
11 MEMASANG 1 M' PIPA GALVANIS DIAMETER 3/4" J.11 20,700.00 62,120.13 0.00 82,820.00
12 MEMASANG 1 M' PIPA PVC TIPE AW d. 1/2" J.12 11,444.80 10,605.88 0.00 22,050.00
13 MEMASANG 1 M' PIPA PVC TIPE AW d. 3/4" J.13 11,444.80 13,636.13 0.00 25,080.00
14 MEMASANG 1 M' PIPA PVC TIPE AW d. 1" J.14 11,444.80 24,242.00 0.00 35,686.00
15 MEMASANG 1 M' PIPA PVC TIPE AW d. 1 1/2" J.15 17,167.20 49,999.13 0.00 67,166.00
16 MEMASANG 1 M' PIPA PVC TIPE AW d. 3" J.16 25,677.20 84,847.00 0.00 110,524.00
17 MEMASANG 1 M' PIPA PVC TIPE AW d. 4" J.17 25,677.20 121,210.00 0.00 146,887.00
18 MEMASANG 1 M' PIPA PVC TIPE AW d. 6" J.18 25,677.20 243,935.13 0.00 269,612.00
19 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS STEEL J.19 42,345.30 491,682.50 0.00 534,027.00
20 MEMASANG 1 BUAH KRAN d. 3/4" ATAU d. 1/2" J.20 54,176.50 99,802.75 0.00 153,979.00
21 MEMASANG 1 BUAH FLOOR DRAIN PLASTIK J.21 14,777.50 12,707.50 0.00 27,485.00
22 MEMASANG 1 BUAH FLOOR DRAIN STAINLESS J.22 14,777.50 168,130.00 0.00 182,907.00
23 MEMASANG 1 BUAH ROOF DRAIN PLASTIK J.23 14,777.50 22,770.00 0.00 37,547.00
24 MEMASANG 1 BUAH ROOF DRAIN BESI/STAINLESS J.24 14,777.50 88,550.00 0.00 103,327.00
25 MEMASANG 1 UNIT SEPTIKTANK 2.5 x 1.5 x 2 + REMBESAN (KANTOR TIPE BESAR) J.25 6,506,964.87 ### 2,479.69 17,796,230.00
26 MEMASANG 1 UNIT SEPTIKTANK 2.5 x 1.5 x 1.5 + REMBESAN (KANTOR TIPE KECIL) J.26 3,907,001.31 6,772,009.62 1,487.81 10,680,498.00
27 MEMASANG 1 UNIT SEPTIKTANK 1.5 x 1 x 1.5 + REMBESAN (RUMAH TIPE KECIL) J.27 1,986,359.47 4,264,171.26 743.91 6,251,274.00
28 1 M' SALURAN GREVEL BETON 1/2 d. 20 CM + PASANGAN J.28 157,365.25 223,825.51 0.00 381,190.00
29 1 M' SALURAN GREVEL BETON 1/2 d. 30 CM + PASANGAN J.29 159,250.39 247,285.51 0.00 406,535.00
30 1 M' SALURAN AIR LIMBAH BUIS BETON D = 30 Cm J.30 62,272.50 240,307.62 0.00 302,580.00
31 1 M' SALURAN AIR LIMBAH BUIS BETON D = 60 Cm J.31 62,272.50 278,194.55 0.00 340,467.00
32 1 BUAH TANGKI AIR FIBREGLASS (TORN) VOLUME 1000 LITER J.32 453,780.80 2,841,031.02 0.00 3,294,811.00
33 1 BUAH TANGKI AIR FIBREGLASS (TORN) VOLUME 500 LITER J.33 453,780.80 1,912,987.05 0.00 2,366,767.00
Halaman 494
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
12 1 M2 PASANG LANTAI GRANIT TILE UKURAN 60 x 60 cm M.12 114,712.50 502,602.15 0.00 617,314.00
13 1 M2 PASANG LANTAI GRANIT TILE UKURAN 60 x 60 cm (setara indogress) M.13 114,712.50 256,620.14 0.00 371,332.00
14 1 M2 PASANG LANTAI GRANIT TILE UKURAN 60 x 60 cm (Ex. Cina) M.14 114,712.50 203,246.69 0.00 317,959.00
15 1 M2 PASANG LANTAI GRANIT TILE UKURAN 80 x 80 cm M.15 114,712.50 611,669.65 0.00 726,382.00
16 1 M2 PASANG LANTAI GRANIT TILE UKURAN 80 x 80 cm (setara Indogress) M.16 114,712.50 460,831.62 0.00 575,544.00
17 1 M2 PASANG LANTAI GRANIT TILE UKURAN 80 x 80 cm (setara marco) M.17 114,712.50 443,427.24 0.00 558,139.00
18 1 M2 PASANG LANTAI GRANIT TILE 3D UKURAN 60 x 60 cm M.18 114,712.50 574,540.29 0.00 689,252.00
19 1 M2 PASANG LANTAI KERAMIK WARNA 20 x 20 cm, ANTI SLIP KM/WC M.19 114,712.50 151,033.53 0.00 265,746.00
20 1 M2 PASANG LANTAI KERAMIK WARNA 30 x 30 cm, ANTI SLIP KM/WC M.20 114,712.50 161,476.16 0.00 276,188.00
21 1 M2 PASANG LANTAI PARQUET JATI M.21 117,530.00 340,023.38 0.00 457,553.00
22 1 M2 PASANG LANTAI KAYU (GYMFLOOR) M.22 117,530.00 51,612.00 0.00 169,142.00
23 1 M2 PASANG LANTAI KARPET M.23 40,463.90 30,107.00 0.00 70,570.00
24 1 M2 PASANG FLOOR HARDENER M.24 27,544.80 42,032.50 0.00 69,577.00
25 1 M2 PASANG BATU KORAL BENGKULU HITAM M.25 203,550.00 133,311.45 0.00 336,861.00
26 1 M2 PASANG BATU KORAL FLORES HIJAU M.26 203,550.00 133,311.45 0.00 336,861.00
27 1 M2 PASANG BATU KORAL ORANGE BALI M.27 203,550.00 133,311.45 0.00 336,861.00
28 1 M2 PASANG BATU KORAL HITAM GARUT M.28 203,550.00 133,311.45 0.00 336,861.00
29 1 M2 PASANG BATU SIKAT M.29 203,550.00 133,311.45 0.00 336,861.00
30 1 M2 PASANG BATU SIKAT MOTIF M.30 227,700.00 133,311.45 0.00 361,011.00
31 1 M' PASANG PLIN KAYU BORNEO T. 2 cm L.10 cm M.31 28,510.80 25,558.69 0.00 54,069.00
Halaman 495
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
55 1 M2 PASANG RANGKA DINDING PARTISI KAYU BORNEO N.55 77,526.10 216,143.82 0.00 293,669.00
56 1 M2 PASANG RANGKA DINDING PARTISI KAYU KRUING N.56 77,526.10 341,156.30 0.00 418,682.00
57 1 M2 PASANG DINDING PARTISI TEAKWOOD RANGKAP, RANGKA KAYU KAMPER N.57 77,526.10 603,028.55 0.00 680,554.00
58 1 M2 PASANG DINDING PARTISI TEAKWOOD RANGKAP, RANGKA KAYU BORNEO N.58 77,526.10 370,178.27 0.00 447,704.00
59 1 M2 PASANG DINDING PARTISI TEAKWOOD RANGKAP, RANGKA KAYU KRUING N.59 77,526.10 495,190.75 0.00 572,716.00
60 1 M2 PASANG DINDING PARTISI MULTIPLEK 9 MM, RANGKA KAYU KRUING (DUA MUKA) N.60 77,526.10 466,737.89 0.00 544,263.00
61 1 M2 PASANG DINDING PARTISI MULTIPLEK 9 MM, RANGKA KAYU KRUING (SATU MUKA) N.61 77,526.10 403,947.10 0.00 481,473.00
62 1 M2 PASANG DINDING PARTISI TRIPLEK 3 MM, RANGKA KAYU BORNEO N.62 77,526.10 292,838.47 0.00 370,364.00
63 1 M2 PASANG PARTISI RANGKA METAL FURING LAPIS GYPSUM DUA MUKA N.63 103,122.80 287,576.70 0.00 390,699.00
64 1 M2 PASANG PARTISI RANGKA METAL FURING LAPIS GRC DUA MUKA N.64 103,122.80 276,036.77 0.00 379,159.00
65 1 M2 PASANG PARTISI RANGKA BLOCKBOARD DUA MUKA FINISH HPL (POLOS/BIASA) N.65 249,117.60 671,132.97 0.00 920,250.00
66 1 M2 PASANG PARTISI RANGKA BLOCKBOARD SATU MUKA FINISH HPL (POLOS/BIASA) N.66 249,117.60 381,968.14 0.00 631,085.00
67 1 M2 PASANG PARTISI RANGKA BLOCKBOARD DUA MUKA FINISH HPL (TEXTURE) N.67 249,117.60 631,883.75 0.00 881,001.00
68 1 M2 PASANG PARTISI RANGKA BLOCKBOARD SATU MUKA FINISH HPL (TEXTURE) N.68 249,117.60 362,343.53 0.00 611,461.00
69 1 M2 PASANG DINDING WALLPAPER L. 50 cm N.69 28,451.00 98,336.50 0.00 126,787.00
P PEKERJAAN PENGECATAN P
1 1 M2 MENGIKIS / MENGEROK PERMUKAAN CAT DINDING LAMA P.1 14,069.10 2,834.75 0.00 16,903.00
2 1 M2 MENDEMPUL DAN MENGGOSOK KAYU P.2 9,255.20 10,772.05 0.00 20,027.00
3 1 M2 PENGECATAN BIDANG KAYU LAMA P.3 16,577.25 40,021.39 0.00 56,598.00
4 1 M2 PENGECATAN BID. KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENU P.4 8,639.95 51,553.35 0.00 60,193.00
5 1 M2 PENGECATAN KANSTIN P.5 8,566.35 25,776.68 0.00 34,343.00
6 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 3 LAPIS CAT P.6 19,753.55 58,327.43 0.00 78,080.00
7 M' PENGECATAN KUSEN PINTU/JENDELA KAYU, 1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP P.7 9,876.78 29,163.71 0.00 39,040.00
8 1 M2 PENGECATAN BIDANG KAYU DENGAN MELAMIK P.8 111,826.00 144,664.25 0.00 256,490.00
9 M' PENGECATAN KUSEN PINTU/JENDELA KAYU DENGAN MELAMIK P.9 55,913.00 72,332.13 0.00 128,245.00
10 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR P.10 13,243.40 48,646.27 0.00 61,889.00
11 1 M2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER P.11 9,968.20 23,606.63 0.00 33,574.00
12 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTU P.12 10,532.39 24,310.43 0.00 34,842.00
13 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTU P.13 10,458.79 32,052.23 0.00 42,511.00
14 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP P.14 8,501.26 18,934.18 0.00 27,435.00
15 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP DULUX P.15 8,427.66 25,385.68 0.00 33,813.00
16 1 M2 PENGECATAN PLAFOND 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP P.16 10,532.39 21,866.68 0.00 32,399.00
17 1 M2 MENGECAT PERMUKAAN BAJA DENGAN MENI BESI P.17 28,451.00 4,916.83 0.00 33,367.00
18 1 M2 MENGECAT PERMUKAAN BAJA DENGAN MENI BESI ZINGCHROMATE P.18 29,555.00 6,871.83 0.00 36,426.00
19 1 M2 MENGECAT DENGAN CAT DUCO P.19 29,555.00 10,684.08 0.00 40,239.00
20 1 M2 MENGECAT BESI ( 3x ) P.20 59,041.00 32,583.01 0.00 91,624.00
21 1 M2 MENGECAT BESI ( 3x ) POLLY URETHANE P.21 59,041.00 40,344.36 0.00 99,385.00
22 1 M2 MENGECAT BESI LAMA ( 3x ) P.22 42,412.00 24,584.13 0.00 66,996.00
KEPALA DINAS
PEKERJAAN UMUM DAN PENATAAN RUANG
KABUPATEN INDRAMAYU