A PEKERJAAN JEMBATAN
1 Pekerjaan Galian Tanah
m 1,00
1.1. Galian Tanah
Bangun 1 Panjang = 4.00 m
Tinggi = 1.50 m
Lebar 1 = 1.80 m
3.75 m 1 1,25
m 1,5
m 1,80
m 1,00
Bangun 2 Panjang = 4.00 m
Tinggi = 3.75 m
Lebar A = 1.50 m
Lebar B = 1.80 m
2 Volume = (((LA+LB)/2) x T ) x P)-C = 24.75 M3
3.75 m
m 1,80
TOTAL GALIAN = 35.55 M3
b. Tembok Pengarah/Lonengan
1,0 m
Panjang = 1.00 m
Lebar = 0.30 m
Tinggi = 1.00 m
1,0 m
Jumlah bangun = 4.00 bh
Volume = (( L x T ) x P ) x Jlh
= (( 0,30 x 1,00 ) x 1,25 ) x 4 = 1.20 M3
volume total pasangan batu kali = 38.60
Propinsi : Jawa Barat Jenis Prasarana : Jembatan
0
Propinsi : Jawa Barat Jenis Prasarana : Jembatan
1,80
BANGUN 1 Panjang 1 = 2.00 m
Panjang 2 = 0.70 m
Tinggi 1 = 1.20 m
Tinggi 2 = 1.20 m
2,00
Jumlah bangun = 2.00 bh
Volume = (((P1+P2)/2)*((T1+T2)/2))*Jlh
= (((2+1,2)/2)*((2,0+1,2)/2)*2 = 3.24 M2
1,2 1,2
1,80
Panjang = 7.00
Lebar Bersih = 3.25 (= 3,5m - ( 3 x lebar balok ) )
4,0 m Tebal = 0.20
0,2 m
Volume = (0.20x2,25)x4,0 = 4.55 M3
7,0 m
0,25
0,80M
L
Tinggi = 1.40 m
Lebar = 0.15 m
Tebal = 0.15 m
Jumlah = 12 bh
Volume = ( 0,15 x 0,15 ) x 1,4 x 12 = 0.38 M3
TOTAL VOLUME COR BETON BERTULANG = 9.81 M2
c
3.2. Pek. Penulangan bc a 2
1 3
a. Penulangan Plat Lantai
O = 12 - 15 Tulangan Memanjang Ø 12
O = 12 - 10 O = 12 - 20 Panjang = 2(a)+b+c = 624 cm = 6.24 m
Jumlah = (300/15)+1 21 Alur
d = (24 x 2) x 6.24 = 262.08 m = 262 / 12 = 21.84 Ujg
1
e h e = 22 Ujg
bf g g 2
Tulangan Melintang Ø 12
a d
3 1 = 3 Panjang = 2(a)+d = 360 cm = 3.6 m
a = 7,5 e = 83 f Jumlah = (400/20)+1 21 Alur
b = 15 = 17 g = = (31 x 2) x 3.6 = 223.2 m = 223 / 12 = 18.60 Ujg
c = 595 48 h = = 19 Ujg
d = 345 71
2 Panjang = 2a+2b+2e+4f+2g+h 446 cm = 4.46 m
Ket : Jumlah = (400/20)+1 31 Alur
= (31 x 1) x 4.5 138 m = 138 /12 = 11.52 Ujg
12 Ujg
4 O 16
6 - O 16
140 140
150
10 40 290 7,00 150
O 8 - 10 8 - O 16 O 8 - 15
Tulangan Memanjang
10 O 590
16
Panjang = (2x10)+(2x140)+(2x40)+290 = 670 cm = 6.7 m
1. Jumlah = 2 Alur 3 Balok = (6,7 x 2)x3 = 40 m
20
2. Panjang = (2x10)+590 = 610 cm = 6.1 m
44 Jumlah = 10 Alur 3 Balok = (6,1 x 10)x3 = 183 m
6 JUMLAH PANJANG = 223.2 M = 18.6 Ujg
3. BEGEL O 10 = 19 Ujg
24 = 18.00 Ujg
6
25
d. Penulangan Balok Tumpuan
345
7,5
20
45 45
45
1. Tulangan Memanjang O 612 Panjang = (2x7,5)+295 = 310 cm = 3.1 m
20
6 Jumlah = 16 Alur 3 Balok = (3,6 x 16)x3 = 148.8 m
45
JUMLAH PANJANG = 148.8 M = 12.4 Ujg
= 13 Ujg
100
120
Panjang = 4.00 m
Tinggi = (0,25+0,5) 0.75 m
Jumlah = 2.00 bh
Luas = 6.00 m2
b. Balok Utama Panjang 7.00 m
Lebar + Tinggi 0.85 m
Jumlah 3.00 bh
Luas = 17.85 m2
5. Pekerjaan Pengecatan
m 0,3
Propinsi : Jawa Barat Jenis Prasarana : Jembatan
2.8 m
1
m 0,8
m 0,8
m 0,9
41.76 M3
m 0,3
1
1,2m
m 1,00
m 1,20
Propinsi : Jawa Barat Jenis Prasarana : Jembatan
4.2 m
160.43 M3
MEMBANGUN INDONESIA
2,0 m 7m
2,0 m
DARI DESA
B PROPINSI
0,3 m
Jawa Barat
KABUPATEN
A A A
Bogor
4,0 m 4m KECAMATAN
Leuwisadeng
DESA
Kalong I
0,3 m JENIS PRASARANA
JEMBATAN
BB LOKASI
Kp. Cikuya
TAMPAK SAMPING JUDUL GAMBAR
Pengaman Jembatan
DENAH
Tembok Pengaman Tiang sandaran
(Pipa Galvanis ) POTONGAN
Dibuat Oleh
C 0,75
M.A.Normal ……………………
Mengetahui
1,0 m Kepala Desa
1,8 m 1,8 m
6m
Nomor Lembar
DETAIL D POTONGAN C-C
POTONGAN B -B TIANG PAGAR JEMBATAN DETAIL PENULANGAN TIANG
MEMBANGUN INDONESIA
Tiang Pagar Jembatan Plat Beton T= 0,20 m 4O - 10 DARI DESA
Beton Cor 1:2:3 (Beton cor 1:2 :3 ) C C PROPINSI
Jawa Barat
Balok Beton (25/50) KABUPATEN
Beton Cor 1:2:3 1,0 m
m m 0,15
D 0,20 m
Bogor
0,30 m KECAMATAN
m 0,15
Leuwisadeng
0.5m 1.25m 1.25m 0.5m 0 8-15
DESA
3,5 m
Kalong I
16 O 12 Dibuat Oleh
0.30 m
O 10 - 12,5
Diperiksa Oleh
E 0
Angkur .
2
5
m m 0.25
0.5 m ……………………
Mengetahui
Kepala Desa
m 0.50
0.5 m 0.25 m
Nomor Lembar
PENULANGAN PLAT & BALOK JEMBATAN
MEMBANGUN INDONESIA
DARI DESA
PROPINSI
Jawa Barat
Plat Lantai (Cor
6 O 16 O 10 -15 O 10 - 10 beton 1:2:3) KABUPATEN
Bogor
0,20m
KECAMATAN
0,50m Leuwisadeng
DESA
6 O 16 Kalong I
0.25m 0,25 m Balok Diafragma 0.25m Balok Utama (Cor
(Cor beton 1:2:3) beton 1:2:3)
JENIS PRASARANA
JEMBATAN
LOKASI
Kp. Cikuya
JUDUL GAMBAR
DENAH
POTONGAN
O 10 - 10
Dibuat Oleh
PONDASI TELAPAK
KOLOM PERKUATAN ABUTMEN
SKALA 1 : 20 Diperiksa Oleh
O 10 - 20
……………………
Mengetahui
O 10 - 20 Kepala Desa
2.75 M KECAMATAN
Leuwisadeng
DESA
L
8 - O 16 Kalong I
O 10- 10
O 10- 15 8 - O 16
A
1.0M JENIS PRASARANA
JEMBATAN
4.00 LOKASI
150
150
1.8 M Kp. Cikuya
JUDUL GAMBAR
DENAH
POTONGAN A - A POTONGAN B - B POTONGAN
PENULANGAN BALOK
DIAFRAGMA Dibuat Oleh
6 O 16 4 - O 16
O 10- 15
0,20 m 0,20 m O 8- 15
Diperiksa Oleh
0.50m
0.25m
8 - O 16
0,30 m 0,30 m
O 8- 10 ……………………
0
0 Mengetahui
8 O 16 8 - 0 16 Kepala Desa
0.25m 0.20m
0.25m
Nomor Lembar
PROGRAM DANA DESA TAHUN 2016
DESA
…………………..
KECAMATAN …………….
KABUPATEN ………………….
PROPINSI ………………
ANALISA HARGA SATUAN
I. Analisa Jembatan
No. Total
Uraian Volume
Volume
2 1 M3 Timbunan
0.4 HOK Pekerja 45 18.00
6 1 M3 Pekerjaan Acian
0.065 Zak Semen PC @50 77.66 5.05
0.1 HOK Pekerja 77.66 7.77
0.07 HOK Tukang 77.66 5.44
0.007 HOK Kepala tukang 77.66 0.54
0.00
7 1 M3 Pekerjaan beton bertulang cor 1:2:3
Ujg besi diameter 8mm 9.00
Ujg besi diameter 10mm 4,997.30 0.00 31.00
Ujg besi diameter 12mm 71.00
Ujg besi diameter 16mm 19.00
6.4 Zak Semen 0.00 9.81 62.80
0.8 M3 Batu Split 0.00 9.81 7.85
0.56 M3 Pasir cor 0.00 9.81 5.50
1.5 kg kawat bendrat 9.81 14.72
2 kg paku biasa 9.81 19.63
0.35 M3 Papan Mal 0.00 9.81 3.43
1.65 Hok pekerja 0.00 9.81 16.19
0.25 Hok Tukang 0.00 9.81 2.45
0.025 Hok Kepala Tukang 0.00 9.81 0.25
0.00
8 1 M3 Pekerjaan pengecatan tiang pagar&kepala jembatan
0.054 kaleng cat tembok @5kg 0.00 47.78 2.58
0.05 Hok Pekerja 0.00 47.78 2.39
0.025 Hok Tukang 0.00 47.78 1.19
0.01 Hok Kepala tukang 47.78 0.48
0.00
Rekap
Bahan
Semen 1,788.73 1,789.00 Sak
Batu 15/20 264.86 265.00 M3
Batu Split 7.85 8.00 M3
Pasir Pasang 125.21 126.00 M3
Pasir Cor 7.36 8.00 M3
Besi dia 8 9.00 9.00 Btg
Besi dia 10 31.00 31.00 Btg
Besi dia 12 71.00 71.00 Btg
Besi dia 16 19.25 20.00 Btg
Pipa Besi dia 2 inchi 6.3 7 Btg
Papan Mal 3.43 4 M3
Bendrat 14.72 15 Kg
VOLUME BIAYA
Kategori Harga Satuan Dana
No. Uraian Dari Dari Dana SAT. Pph+Ppn Swadaya Dana APBD Bobot
Total Biaya. (Rp) Total (Rp)
Swadaya APBD (Rp) (Rp)
(Rp)
I Biaya Persiapan
1 Sosialisasi 1.0 1.0 Ls 1,000,000 50,000 1,050,000.00
2 Pembersihan Lahan 1.0 1.0 Ls 1,500,000 75,000 1,575,000.00
3 Musdes 1.0 1.0 Ls 2,000,000 100,000 2,100,000.00
4 Biaya Survey 1.0 1.0 Ls 2,000,000 100,000 2,100,000.00
5 Biaya Monitoring 1.0 1.0 Ls 2,000,000 100,000 2,100,000.00
6 Biaya Evaluasi 1.0 1.0 Ls 2,000,000 100,000 2,100,000.00
7 Dokumentasi dan Pelaporan 1.0 1.0 Ls 1,000,000 50,000 1,050,000.00
8 OP TPK 1.0 1.0 Ls 11,122,667 556,133 11,678,800.00
Sub Total I) 22,622,667 1,131,133 23,753,800.00 4.8%
II Bahan Material
1 Batu Belah 265.0 - 265.0 M3 295,000 78,175,000 - - 78,175,000.00
2 Pasir Pasang 126.0 - 126.0 M3 295,000 37,170,000 - - 37,170,000.00
3 Pasir Cor 8.0 - 8.0 M3 350,000 2,800,000 322,000 - 3,122,000.00
4 Semen PC @50kg 1,764.0 - 1,764.0 Sak 65,000 114,660,000 13,185,900 - 127,845,900.00
5 Batu Split 10.0 - 10.0 M3 300,000 3,000,000 345,000 - 3,345,000.00
6 Besi diameter 8mm 9.0 - 9.0 btng 55,000 495,000 56,925 - 551,925.00
7 Besi diameter 10mm 45.0 - 45.0 btng 74,000 3,330,000 382,950 - 3,712,950.00
8 Besi diameter 12mm 60.0 - 60.0 btng 95,000 5,700,000 655,500 - 6,355,500.00
9 Besi diameter 16mm 38.0 - 38.0 btng 175,000 6,650,000 764,750 - 7,414,750.00
10 Kayu kls III/mal 2.0 - 2.0 M3 1,800,000 3,600,000 414,000 - 4,014,000.00
11 Kawat bendrat 9.0 - 9.0 kg 25,000 225,000 25,875 - 250,875.00
12 Paku biasa 14.0 - 14.0 kg 25,000 350,000 40,250 - 390,250.00
13 Cat tembok @5kg 4.0 - 4.0 kaleng 175,000 700,000 80,500 - 780,500.00
14 Pipa besi diameter 2 inch p= 6m 6.0 - 6.0 Unit 550,000 3,300,000 379,500 - 3,679,500.00
15 Bambu perancah diameter 10cm 42.0 - 42.0 buah 15,000 630,000 72,450 - 702,450.00
16 Cat minyak @1kg (avian) 16.0 - 16.0 kaleng 85,000 1,360,000 156,400 - 1,516,400.00
Sub Total II) 262,145,000 16,882,000 279,027,000.00 55.8%
III Alat dan Biaya Langsir
1 Ember 30.0 - 30.0 Bh 15,000 450,000 54,000 - 504,000.00
2 Sekop 10.0 - 10.0 Bh 95,000 950,000 114,000 - 1,064,000.00
3 Pacul 3.0 - 3.0 Bh 95,000 285,000 34,200 - 319,200.00
4 Gerobak dorong ARTCO 3.0 - 3.0 Bh 750,000 2,250,000 270,000 - 2,520,000.00
5 Benang 15.0 - 15.0 Roll 10,000 150,000 18,000 - 168,000.00
6 Mobilisasi Pasir Pasang 126.0 - 126.0 Rit 50,000 6,300,000 756,000 - 7,056,000.00
7 Mobilisasi Pasir Cor 8.0 - 8.0 Rit 50,000 400,000 48,000 - 448,000.00
8 Mobilisasi Batu Split 10.0 - 10.0 Rit 50,000 500,000 60,000 - 560,000.00
9 Mobilisasi Batu Kali 15/20 265.0 - 265.0 Rit 100,000 26,500,000 3,180,000 - 29,680,000.00
10 Bambu 28.0 - 28.0 Rit 15,000 420,000 - - 420,000.00
11 Papan Kegiatan 2.0 - 2.0 Rit 250,000 500,000 60,000 - 560,000.00
12 Prasasti 1.0 - 1.0 Rit 500,000 500,000 60,000 - 560,000.00
Sub Total III) 39,205,000 4,654,200 43,859,200.00 8.8%
IV Upah Kerja
1. Pekerja 558.0 - 558.0 HOK 120,000 66,960,000 - - 66,960,000.00
2. Tukang 230.0 - 230.0 HOK 140,000 32,200,000 - - 32,200,000.00
3. Kepala Tukang 21.0 - 21.0 HOK 200,000 4,200,000 - - 4,200,000.00
Sub Total IV) 103,360,000 - - 103,360,000.00 20.7%
V Upah Padat Karya Tunai
1. Pekerja Padat Karya Tunai 500.0 - 500.0 HOK 100,000 50,000,000 - - 50,000,000.00
Sub Total V) 50,000,000 - - 50,000,000.00 10.0%
Dari Dana APBD : 500,000,000.00 100.0%
-Bahan & Tenaga - 0.0%
Dari Swadaya :
-Uang Tunai - 0.0%
Grand Total : 500,000,000.00 100.0%
Kalong I, ......... Desember 2020
Disetujui, Disusun Oleh,
Kepala Desa Kalong I Ketua TPK
S. Yenih ( ......................... )
Diperiksa,
1. PERANGKAT DAERAH TERKAIT ______________
Kegiatan : Jembatan
Ukuran : 7 x 4 t:2 m Bobot
Jumlah : 1 Buah
NO URAIAN No Rab : 002/DBK/2020
DANA BANTUAN
SWADAYA
KABUPATEN
S. Yenih ( ........................... )
Err:509
Err:509
0
RENCANA ANGGARAN BIAYA
Kbupaten : Bogor
I Biaya Persiapan
500,000,000 100.00%
Terbilang Lima ratus juta rupiah
S. Yenih ( ..................................... )
Mengetahui,
Pendamping Desa
Suherman, S.Sg
PROGRAM DANA APBD KABUPATEN BOGOR
RENCANA ANGGARAN BIAYA
S. Yenih ( ......................... )
Mengetahui,
Pendamping Desa
Suherman, S.Ag
Bobot
4.7%
58.6%
7.8%
20.5%
8.4%
100.0%