Anda di halaman 1dari 9

PERHITUNGAN VOLUME

Jenis Pekerjaan : Betonisasi Jalan Desa Kp. Cepak Nangka No. RAB : 002B/DBK/2020
Nama Desa : Wangunjaya Lokasi : Kp. Cepak Nangka
Kecamatan : Leuwisadeng Jns. Keg. : Betonisasi Jalan Desa Kp. Cepak Nangka
Kbupaten : Bogor Ukuran : 100 x 3,5 x 0,15 M
Provinsi : Jawa Barat
Tahun : 2021
Sumber Dana : Dana Bantuan Kabupaten Bogor 2021

ANALISA BETON SITE MIX/MANUAL-K225

NO. URAIAN KOEF SAT. HARGA SAT. JUMLAH JML


PANJANG LEBAR TINGGI JML VOL JML KEBUTUHAN JUMLAH
KEBUTUHAN
1 2 3 4 5 6=(3x5) (M) (M) (M) (M3) BAHAN (Rp)
BAHAN

C003 1 M3 COR BETON SITE MIX K 225 DIBULATKAN

1 Semen PC (50 kg) 7.6000 zak 65,000 494,000 399.0 399.0 25,935,000
2 Split pecah mesin 1/2 0.8100 m³ 275,000 222,750 42.5 43.0 11,825,000
3 Pasir Beton 0.4900 m³ 350,000 171,500 25.7 26.0 9,100,000
4 Pasir Urugan 0.0300 m3 190,000 5,700 10.5 11.0 2,090,000
5 Bescous 0.0200 M3 275,000 5,500 7.0 7.0 1,925,000
6 ADT Additive 0.2500 M3 47,000 11,750 13.1 14.0 658,000
7 Air 2.1500 m3 5,000 10,750 112.9 113.0 565,000
52,098,000
-
1 Pekerja 1.5000 org 110,000 165,000 78.75 79.0 8,690,000
2 Tukang 0.7500 org 130,000 97,500 39.38 40.0 5,200,000
13,890,000
Jumlah 1,184,450 100 3.5 0.15 52.5 65,988,000

Wangunjaya, ......Desember 2020


Disetujui, Disusun Oleh,
Kepala Desa Wangunjaya Ketua TPK

(................................) (...................................)

Mengetahui,
Pendamping Desa

Suherman, S.Ag
HARGA SATUAN BAHAN/MATERIAL - ALAT BANTU KERJA - TENAGA

Jenis Pekerjaan : Betonisasi Jalan Desa Kp. Cepak Nangka


Nama Desa : Wangunjaya
Kecamatan : Leuwisadeng
Kbupaten : Bogor
Provinsi : Jawa Barat
Tahun : 2021
Sumber Dana : Dana Bantuan Kabupaten Bogor 2021

1. Daftar Harga Satuan Bahan Material dan Alat Bantu Kerja

No Jenis Bahan / Material/ Alat Bantu Satuan KLASIFIKASI Harga satuan Keterangan
kerja

1 Batu m3 B 275,000
2 Pasir Urugan m3 B 190,000
3 Pasir Cor m3 A 350,000
4 Pasir Pasang m3 275,000
5 Portland cement (PC) kg A 65,000
6 Split pecah mesin 1/2 m3 A 275,000
7 Ember bh A 15,000
8 Cangkul bh A 95,000
9 Sekop bh A 60,000
10 Pipa PVC btg A 21,000
11 Pengki bh A 25,000
12 Mobilisasi Bahan m3 100,000
13 Mobilisasi Semen Sak 10,000
13 ADT Additive Ltr A 47,000
14 Kawat Tali kg A 15,000
15 Air m3 5,000
16 Plastik Cor m2 A 5,000
17 Paku kg A 17,000
18 Bambu btg 15,000
19 Benang bh A 10,000
20 Papan Bekisting 10 cm btg B 15,000
21 Sewa Mesin Stoom hr A 650,000
22 Mobilisasi Mesin Stoom ls 5,000,000
23 Solar ltr NS 9,000
24 Sewa Molen hr A 350,000
25 Mobilisasi Molen ls 3,000,000
26 Papan Kegiatan bh A 250,000
27 Prasasti bh A 500,000

2. Daftar Harga Satuan Tenaga


No Tenaga Kerja Satuan Harga Satuan Keterangan
1 Pekerja OH 110,000
2 Tukang OH 130,000

Wangunjaya, ......Desember 2020


Diperiksa Oleh Dibuat Oleh:
Kaur Perencanaan Sekretaris Desa

(................................) (...................................)
Disetujui Oleh:
Pendamping Desa

Suherman, S.Ag
PERHITUNGAN KEBUTUHAN BAHAN

Nama Pekerjaan : Betonisasi Jalan Desa Kp. Cepak Nangka


Desa : Wangunjaya
Kecamatan : Leuwisadeng
Kabupaten/Kota : Bogor
Provinsi : Jawa Barat
Tahun : 2020
Sumber Dana : Dana Bantuan Kabupaten Bogor 2021

Volume Harga Satuan Jumlah


No Jenis Material
(M3) (Rp) (Rp)

1 Semen PC (50 kg) 399 65,000 25,935,000


2 Split pecah mesin 1/2 43 275,000 11,825,000
3 Pasir Beton 26 350,000 9,100,000
4 Pasir Urugan 11 190,000 2,090,000
5 Bescous 7 275,000 1,925,000
6 Air 113 5,000 565,000

Jumlah 51,440,000

Wangunjaya, ......Desember 2020


Disetujui, Disusun Oleh,
Kepala Desa Wangunjaya Ketua TPK

(................................) (...................................)
Mengetahui,
Pendamping Desa

Suherman, S.Ag
PERHITUNGAN KEBUTUHAN UPAH

Nama Pekerjaan : Betonisasi Jalan Desa Kp. Cepak Nangka


Desa : Wangunjaya
Kecamatan : Leuwisadeng
Kabupaten/Kota : Bogor
Provinsi : Jawa Barat
Tahun : 2020
Sumber Dana : Dana Bantuan Kabupaten Bogor 2021

Volume Harga Satuan Jumlah


No Jenis Material
(M3) (Rp) (Rp)

1 Pekerja 79 110,000 8,690,000


2 Tukang 40 130,000 5,200,000

Jumlah 13,890,000

Wangunjaya, ......Desember 2020


Disetujui, Disusun Oleh,
Kepala Desa Wangunjaya Ketua TPK

(................................) (...................................)
Mengetahui,
Pendamping Desa

Suherman, S.Ag
RENCANA ANGGARAN BIAYA (RAB)
PROGRAM SAMISADE TAHUN 2021
Provinsi : Jawa Barat
Kabupaten : Bogor No. RAB : 002B/DBK/2020
Kecamatan : Leuwisadeng Lokasi : Kp. Cepak Nangka
Desa : Wangunjaya Jns. Keg. : Betonisasi Jalan Desa Kp. Cepak Nangka
Sumber Dana : Dana Bantuan Kabupaten 2021 Ukuran : 100 x 3,5 x 0,15 M

Volume PPn PPh Sumber Dana


Harga Satuan Pph + Ppn Harga Total Total Pajak Total Harga
URAIAN Dari Dari Sat DPP 21 22 23 Swadaya (Rp)
Total (Rp) 0.10 (11,5%) (Rp.) Dana APBD (Rp) (Rp.) (Rp.)
Swadaya APBD (5%) (1,5%) (2%)

I. BAHAN
1. Semen PC (50) Kg 399.00 - 399.00 Sak 65,000.00 65,000.00 6,500.00 975.00 7,475.00 72,475.00 - 25,935,000.00 2,982,525.00 28,917,525.00
2. Batu Split 1/2 43.00 - 43.00 M3 275,000.00 275,000.00 27,500.00 4,125.00 31,625.00 306,625.00 - 11,825,000.00 1,359,875.00 13,184,875.00
3. Pasir Cor 26.00 - 26.00 M3 350,000.00 350,000.00 35,000.00 5,250.00 40,250.00 390,250.00 - 9,100,000.00 1,046,500.00 10,146,500.00
4. Pasir Urugan 11.00 - 11.00 M3 190,000.00 190,000.00 - 190,000.00 - 2,090,000.00 - 2,090,000.00
5. Bescous 7.00 7.00 M3 275,000.00 275,000.00 27,500.00 4,125.00 31,625.00 306,625.00 - 1,925,000.00 221,375.00 2,146,375.00
6. Air 113.00 - 113.00 M3 5,000.00 5,000.00 - 5,000.00 - 565,000.00 - 565,000.00
Sub Total I) 69,000.00 - 10,350.00 - 79,350.00 - 51,440,000.00 5,610,275.00 57,050,275.00 53%
II. ALAT
1. Ember 30.00 - 30.00 Bh 15,000.00 15,000.00 1,500.00 300.00 1,800.00 16,800.00 - 450,000.00 54,000.00 504,000.00
2. Pengki 10.00 - 10.00 Bh 25,000.00 25,000.00 2,500.00 500.00 3,000.00 28,000.00 - 250,000.00 30,000.00 280,000.00
3. Mobilisasi Semen 399.00 - 399.00 Rit 10,000.00 10,000.00 1,000.00 200.00 1,200.00 11,200.00 - 3,990,000.00 478,800.00 4,468,800.00
4. Mobilisasi Pasir Cor 26.00 - 26.00 Rit 50,000.00 50,000.00 5,000.00 1,000.00 6,000.00 56,000.00 - 1,300,000.00 156,000.00 1,456,000.00
5. Mobilisasi Split 1/2 43.00 - 43.00 Rit 50,000.00 50,000.00 5,000.00 1,000.00 6,000.00 56,000.00 - 2,150,000.00 258,000.00 2,408,000.00
6. Plastik Cor 503.00 - 503.00 Mtr 5,000.00 5,000.00 500.00 100.00 600.00 5,600.00 - 2,515,000.00 301,800.00 2,816,800.00
7. Papan Bekisting 10 Cm 168.00 168.00 Lbr 15,000.00 15,000.00 1,500.00 300.00 1,800.00 16,800.00 - 2,520,000.00 302,400.00 2,822,400.00
8. Paku 2.00 2.00 Kg 17,000.00 17,000.00 1,700.00 340.00 2,040.00 19,040.00 - 34,000.00 4,080.00 38,080.00
9. Benang 5.00 5.00 Bh 10,000.00 10,000.00 1,000.00 200.00 1,200.00 11,200.00 - 50,000.00 6,000.00 56,000.00
10. Bambu 7.00 7.00 Btg 15,000.00 15,000.00 - 15,000.00 - 105,000.00 - 105,000.00
11. Sewa Molen 5.00 5.00 Hr 350,000.00 350,000.00 35,000.00 7,000.00 42,000.00 392,000.00 - 1,750,000.00 210,000.00 1,960,000.00
12. Mobilisasi Molen 1.00 1.00 Ls 3,000,000.00 3,000,000.00 300,000.00 60,000.00 360,000.00 3,360,000.00 - 3,000,000.00 360,000.00 3,360,000.00
13. Solar 24.00 24.00 Ltr 9,000.00 9,000.00 900.00 180.00 1,080.00 10,080.00 - 216,000.00 25,920.00 241,920.00
14. Papan Kegiatan 2.00 - 2.00 Bh 250,000.00 250,000.00 25,000.00 5,000.00 30,000.00 280,000.00 - 500,000.00 60,000.00 560,000.00
15. Prasasti 1.00 - 1.00 Bh 500,000.00 500,000.00 50,000.00 10,000.00 60,000.00 560,000.00 - 500,000.00 60,000.00 560,000.00
Sub Total II) 430,600.00 - - 86,120.00 516,720.00 - 19,330,000.00 2,307,000.00 21,637,000.00 20%
III. UPAH
1. Pekerja 79.00 - 79.00 HOK 110,000.00 - 8,690,000.00 8,690,000.00
2. Tukang 40.00 - 40.00 HOK 130,000.00 5,200,000.00 5,200,000.00
Sub Total III) - - - - - - 13,890,000.00 - 13,890,000.00 13%
IV. UPAH PADAT KARYA TUNAI
1. Pekerja Padat Karya Tunai 108.00 - 108.00 HOK 100,000.00 - 10,800,000.00 10,800,000.00
Sub Total IV) 10,800,000.00 10,800,000.00 10%
V. OPERASIONAL TPK (5%)
1. OP TPK dan Pelaporan (LPJ) 1.00 1.00 Ls 4,938,000.00 246,900.00 246,900.00 5,184,900.00 4,938,000.00 246,900.00 5,184,900.00
Sub Total V) - 246,900.00 - - 246,900.00 4,938,000.00 246,900.00 5,184,900.00 5%
Dari Dana APBD : - 100,398,000.00 8,164,175.00 108,562,175.00
Bahan dan Tenaga -
SUMBER DANA Dari Dana Swadaya :
Uang Tunai -
Grand Total : 108,562,175.00

Wangunjaya, ......Desember 2020


Disetujui, Disusun Oleh,
Kepala Desa Wangunjaya Ketua TPK

(................................) (...................................)
Diperiksa,
1. PERANGKAT DAERAH TERKAIT ______________
2. PDTI/TENAGA AHLI INFRASTRUKTUR KAB ______________
RENCANA ANGGARAN BIAYA (RAB)

Jenis Pekerjaan : Betonisasi Turaf dan Draenase Jalan Desa


Nama Desa : Wangunjaya
Kecamatan : Leuwisadeng
Kbupaten : Bogor

Provinsi : Jawa Barat

Tahun : 2021

Sumber Dana : Dana Bantuan Kabupaten Bogor 2021

Nomor RAB : 002/DBK/2020

: 002A/DBK/2020 Volume : 157 M3

: 002B/DBK/2020 Volume : 100 x 3,5 x 0,15 M

Harga Satuan Jumlah Biaya


No Jenis Pekerjaan Satuan Volume Kode PPH/PPN Bobot (%)
(Rp) (Rp)

I Biaya Persiapan

1. Sosialisasi ls 1.0 380,000 20,000 400,000

2. Pembersihan Lahan ls 1.0 950,000 50,000 1,000,000

3. Musdes ls 1.0 1,900,000 100,000 2,000,000

4. Biaya Survey ls 1.0 1,900,000 100,000 2,000,000

5. Biaya Monitoring ls 1.0 1,900,000 100,000 2,000,000

6. Biaya Evaluasi ls 1.0 1,900,000 100,000 2,000,000

7. Dokumentasi dan Pelaporan ls 1.0 950,000 50,000 1,000,000


8. OP TPK ls 1.0 6,697,956 352,524 7,050,480

17,450,480 5.0%

II Bahan Material

1. Semen PC (50) Kg Sak 890.0 65,000 7,475 64,502,750

2. Batu Split 1/2 M3 43.0 275,000 31,625 13,184,875

3. Pasir Cor M3 26.0 350,000 40,250 10,146,500

4. Pasir urugan M3 11.0 190,000 - 2,090,000

5. Bescous M3 7.0 275,000 31,625 2,146,375

6. Air M3 303.0 5,000 - 1,515,000

7. Pasir Pasang M3 97.0 275,000 - 26,675,000

8. Batu M3 205.0 275,000 - 56,375,000

9. Pipa PVC Btg 28.0 21,000 2,415 655,620

177,291,120 51.3%

III Peralatan
1. Ember Bh 50.0 15,000 1,800 840,000

2. Pengki Bh 17.0 25,000 3,000 476,000

3. Mobilisasi Semen Hr 491.0 10,000 1,200 5,499,200

4. Mobilisasi Pasir Cor Rit 26.0 50,000 6,000 1,456,000

5. Mobilisasi Split 1/2 Ls 43.0 50,000 6,000 2,408,000

6. Mobilisasi Pasir Pasang Rit 97.0 50,000 6,000 5,432,000

7. Mobilisasi batu Rit 205.0 50,000 6,000 11,480,000

8. Plastik Cor Mtr 503.0 5,000 600 2,816,800


9. Papan Bekisting 10 Cm Rit 168.0 15,000 1,800 2,822,400
10. Skup Bh 9.0 60,000 7,200 604,800

11. Paku Rit 9.0 17,000 2,040 171,360

12. Cangkul Bh 5.0 95,000 11,400 532,000

9. Benang Rit 12.0 10,000 1,200 134,400

10. Bambu Rit 37.0 15,000 - 555,000

11. Sewa Molen Rit 5.0 350,000 42,000 1,960,000

12. Mobilisasi Molen Kg 1.0 3,000,000 360,000 3,360,000

13. Solar Bh 24.0 9,000 1,080 241,920

14. Papan Kegiatan Btg 2.0 250,000 30,000 560,000

15. Prasasti Bh 1.0 500,000 60,000 560,000

41,909,880 12.1%

IV Upah Kerja

1. Pekerja HOK 435.0 110,000 - 47,850,000

2. Tukang HOK 202.0 130,000 - 26,260,000

74,110,000 21.4%

V Padat Karya Tunai


1. Upah Padat Karya Tunai HOK 350 100,000 - 35,000,000

35,000,000 10.1%

345,761,480 100.0%

Terbilang Tiga ratus lima puluh juta rupiah

Wangunjaya, ......Desember 2020

Disetujui, Disusun Oleh,

Kepala Desa Wangunjaya Ketua TPK

(................................) (...................................)

Mengetahui,
Pendamping Desa

Suherman, S.Ag

Anda mungkin juga menyukai