REKAPITULASI HARGA PERKIRAAN SENDIRI

KEGIATAN : -

PEKERJAAN :
LOKASI :
TH. ANGGARAN :
SUMBER DANA : -

No. Uraian Sat. HARGA SATUAN HARGA SATUAN (PPN 10%+3% PPH)

BAHAN

1 PC Zak 48,000 54,240


2 Paving Pres K 200 (HOLLAND) 6 cm M2 110,000 124,300
3 Kanstin Trap uk. 15.30.50 Bh 33,000 36,300
4 Pasir Pasang m3 120,000 135,600
5 Pasir Urug m3 110,000 124,300
6 Koral beton 2 - 3 cm m3 270,000 305,100
7 Paku Kg 15,000 16,950
8 Batu Bata Bh 700 791
9 Buis Beton U 20 m 35,000 39,550
ALAT

1 Benang Pasang Bh 3,000 3,300


2 Timba Cor m 10,000 11,300
Gerobak Sorong Bh 575,000 632,500
TENAGA

1 Pekerja HOK 70,000 70,000


2 Tukang HOK 80,000 80,000

Bangunsari 2020

Mengetahui Dibuat oleh :


Kaur Perencanaan

.................................................
JADWAL WAKTU PELAKSANAAN

KEGIATAN : BRONJONG KALI TANI RT.04 RW.01 DSN. JAMBU DESA BANGUNSARI
LOKASI : RT.04 RW.01 DSN. JAMBU DESA BANGUNSARI
TAHUN ANGGARAN : 2020

BOBOT PRESTASI
NO. JENIS KEGIATAN Volume SAT. AGUSTUS SEPTEMBER
% 5 11 10 10 10 %
100

75
I PEKERJAAN BRONJONG
50
1. Pekerjaan Pemasangan Bronjong 84.00 m3 100.00 15.00 20.00 30.00 20.00 10.00

25

0
JUMLAH 100.00

RENCANA MINGGUAN 15.00 20.00 30.00 20.00 15.00


KOMULATIF 15.00 35.00 65.00 85.00 100.00
REALISASI MINGGUAN
KOMULATIF
DAFTAR ANALISA PEKERJAAN

KEGIATAN :

PEKERJAAN : PAVING
LOKASI : -

TH. ANGGARAN : -
SUMBER DANA : -

SNI 7394:2008 6.5 1 m3 Urugan Pasir


a. Bahan
1.2 M3 Pasir Urug @ 124,300.00

b. Tenaga
0.25 Oh Pekerja @ 70,000.00

A.2.3.1.11 1 m2 Pasang paving stone


Permen PU a. Bahan
No. 11 / 2013 1.050 m2 Paving stone Type Holland @ Rp 124,300.00

b. Tenaga
0.250 Oh Pekerja @ Rp 70,000.00
0.250 Oh Tukang batu @ Rp 80,000.00
0.025 Oh Kepala tukang @
0.050 Oh Mandor @

1m Pemasangan Kansteen Ukuran 15 x 30 x 50

0.047 Zak Semen PC @ Rp 54,240.00


0.006 m3 Pasir Pasang @ Rp 135,600.00
2.000 Bh Kanstin Trap uk. 15.35.40 Lokal @ Rp 36,300.00

b. Tenaga
0.200 OH Pekerja @ Rp 70,000.00
0.100 OH Tukang Batu @ Rp 80,000.00
0.026 OH Kepala tukang @
0.026 OH Mandor @

Lantai 1
A.4.4.2.2 1 m2 Plesteran 1 Pc : 2 PP, tebal 15 mm
Permen PU a. Bahan
No. 11 / 2013 0.256 Kg PC @ Rp 54,240.00
0.020 M3 Pasir Pasang @ Rp 135,600.00

b. Tenaga
0.300 Oh Pekerja @ Rp 70,000.00
0.150 Oh Tukang batu @ Rp 80,000.00
0.015 Oh Kepala tukang @
0.015 Oh Mandor @

A.4.4.2.27 1 m2 Acian
Permen PU a. Bahan
No. 11 / 2013 0.081 Zak PC @ 54,240.00

b. Tenaga
0.200 Oh Pekerja @ 70,000.00
0.100 Oh Tukang batu @ 80,000.00

A.4.4.1.7 1 m2 Pasangan bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP
Permen PU a. Bahan
No. 11 / 2013 70.000 Bh Bata merah @ Rp 791.00
0.474 Zak PC @ Rp 54,240.00
DAFTAR ANALISA PEKERJAAN

KEGIATAN :

PEKERJAAN : PAVING
LOKASI : -

TH. ANGGARAN : -
SUMBER DANA : -

0.038 m3 Pasir Pasang @ Rp 135,600.00

b. Tenaga
0.300 Oh Pekerja @ Rp 70,000.00
0.100 Oh Tukang batu @ Rp 80,000.00
0.010 Oh Kepala tukang @
0.015 Oh Mandor @

Lantai 1
-

Pekerja Tukang PC Bata merah

39.05

Rp 149,160.00

Rp 17,500.00 9.76
166,660.00
Rp 258.30

Rp 130,515.00

Rp 17,500.00 64.575
Rp 20,000.00 64.575
Rp -
Rp -
Rp 168,015.00
Rp 199.00

Rp 2,572.80 9.4392864
Rp 837.50
Rp 72,600.00

Rp 14,000.00 39.8
Rp 8,000.00 19.9
Rp -
Rp -
Rp 98,010.30

Rp 13,863.74 -
Rp 2,712.00

Rp 21,000.00 -
Rp 12,000.00 -
Rp -
Rp -
Rp 49,575.74

4,407.00 0

14,000.00 0
8,000.00 0
26,407.00

ampuran spesi 1 PC : 2 PP

Rp 55,370.00 -
Rp 25,696.20 -
-

Pekerja Tukang PC Bata merah

Rp 5,152.80

Rp 21,000.00 -
Rp 8,000.00 -
Rp -
Rp -
Rp 115,219.00
Paving Press
Kanstin Trap uk. K200 6 cm
Pasir Pasang 15.35.40 Lokal Pair Urug Jogja #REF!

46.85

271.215

1.22907375
398

-
Paving Press
Kanstin Trap uk. K200 6 cm
Pasir Pasang 15.35.40 Lokal Pair Urug Jogja #REF!

-
JADWAL WAKTU PELAKSANAAN
PROGRAM :
KEGIATAN :
LOKASI :
TAHUN ANGGARAN :

BOBOT PRESTASI
NO. JENIS KEGIATAN Volume SAT. DESEMBER
% 10 11 10 10 10 %

100
PEKERJAAN PAVING

1. Pek. Pemasangan Paving m2 62.52 15.63 23.45 15.63 7.82


258.30
75
2 Urugan Pasir m3 9.38 4.69 4.69
39.05
3 Kanstin 15.30.50 m 28.10 9.37 9.37 9.37 50
199.00

25

0
JUMLAH 100.00

RENCANA MINGGUAN 9.37 29.69 37.50 15.63 7.82


KOMULATIF 9.37 39.05 76.55 92.18 100.00
REALISASI MINGGUAN
KOMULATIF
KEGIATAN :

PEKERJAAN : PAVING
LOKASI :
TH. ANGGARAN :
SUMBER DANA :

No Uraian Pekerjaan Sat Volume Harga Sat Jumlah Harga

a b c d e f
I PEKERJAAN PAVING
1 Pek. Pemasangan Paving m2 258.3 168,015.00 43,398,274.50
2 Urugan Pasir m3 39.0 166,660.00 6,507,336.21
3 Kanstin 15.30.50 m 199.0 98,010.30 19,504,049.29
Sub Total 1 69,409,660.00
II ALAT BANTU
1 Benang Pasang Bh 6.0 3,300.00 19,800.00

Sub Total 1 19,800.00


II BIAYA PENGELOLAAN Paket 1.0 5,570,000.00 5,570,000.00
A JUMLAH HARGA PEKERJAAN ( KESELURUHAN ) 74,999,460.00

B TOTAL BIAYA PEMBULATAN 75,000,000.00

Bangunsari 2020
Mengetahui Dibuat oleh :
PERHITUNGAN
KEGIATAN : -

PEKERJAAN : PAVING
LOKASI : -
TH. ANGGARAN : -
SUMBER DANA : -

No Gambar Sketsa Perhitungan

1 74,999,460.00 I Paving Pres K 200

Panjang = 34.50

Luas Paving
= 2.4 x 34.5
= 82.8

Urugan Pasir
= 0.15 x 2.4 x 34.5
= 12.42 m3

II Paving Pres K 200

Panjang = 23.00

Luas Paving
= 2.7 x 23
= 62.1

Urugan Pasir
= 0.15 x 2.7 x 23.0
= 9.315 m3

III Paving Pres K 200

Panjang = 42.00

Luas Paving
= 2.7 x 42
= 113.4

Urugan Pasir
= 0.15 x 2.7 x 42.0
= 17.01 m3

TOTAL
1. Luas Paving
= 82.8 + 62.1 + 113.4
= 258.3 m2
2. Volume Urugan
= 12.42 + 9.315 + 17.01
= 38.745 m3
3. Kanstin
= 99.50 x 2
= 199 m
-
DASAR PERHITUNGAN VOLUME

Kegiatan :
Pekerjaan :
Alamat :

No. URAIAN GAMBAR PERHITUNGAN

1 PEKERJAAN GALIAN TANAH Galian Tanah Biasa

0.35 x 0.540 x 24.00

30 12

10
30
45
2 PEKERJAAN PASANGAN BATA
35
Pasangan Batu Bata 1 PC : 2 PSR

0.45 x 24.000 x 2.00


54

3 PEKERJAAN PLASTERAN
Plesteran 1 PC : 2 PSR

1 0.52 x 2 x 24.00

4 PEKERJAAN URUGAN PASIR


0.05 X 0.54 x 24.00
PERHITUNGAN VOLUME SAT

m3

m2

m2

m2

m2

m2
RENCANA PEMBELANJAAN BIAYA PENGELOLAAN
PELAKSANAAN SWAKELOLA

Kegiatan :
Pekerjaan :
Alamat :

Harga Jumlah
No. Jenis Pembelanjaan Sat. Vol. Satuan Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)

1 Honorarium Tim Pengadaan Barang dan jasa Ls 1 3,800,000.00


1 Ketua Org x bln = Ls 1.00 1,000,000.00 1,000,000.00
2 Sekretaris Org x bln = Ls 1.00 850,000.00 850,000.00
3 Anggota Org x bln = Ls 1.00 650,000.00 650,000.00
4 1.00 650,000.00 650,000.00
5 1.00 650,000.00 650,000.00
2 Biaya Alat Tulis Kantor Ls 1 80,000.00
1 Kertas HVS 70 Rim 1.00 50,000.00 50,000.00
2 Map Snail Bh 6.00 5,000.00 30,000.00

3 Biaya Perencanaan Ls 1 173,600.00


1 Biaya jilid Ls 3.00 10,000.00 30,000.00
2 Biaya penggandaan (fotokopi) Lbr 62.00 300.00 18,600.00
3 Biaya Akomodasi Pengukuran ( Minum dan Makan ) Kotak 5.00 25,000.00 125,000.00
4 Biaya Rapat Ls 1 875,000.00
1 Makan Dan Minum Kotak 35.00 25,000.00 875,000.00
5 Biaya Pembuatan Laporan Kegiatan Ls 1 110,500.00
1 Biaya jilid Ls 3.00 10,000.00 30,000.00
2 Biaya penggandaan (fotokopi) Ls 70.00 300.00 21,000.00
3 Materai 6000 Bh 6.00 7,000.00 42,000.00
4 Materai 3000 Bh 5.00 3,500.00 17,500.00
6 Biaya Dokumentasi Ls 1 525,000.00
1 Cetak Foto Kegiatan Lbr 30.00 2,500.00 75,000.00
2 Papan nama Kegiatan Unit 1.00 150,000.00 150,000.00
3 Prasasti Marmer Ukuran 30 x 40 Unit 1.00 300,000.00 300,000.00

JUMLAH HARGA PEKERJAAN ( KESELURUHAN ) 5,564,100.00


Terbilang :
#REF!
Err:509
#REF!
#REF!

POTENSI PEMBAYARAN PAJAK

#REF! : 0
#REF! : PAVING
#REF! : 0

Jumlah Item Kegiatan Yang Potensial Pajak Jenis Pajak


NO Jenis Bahan/Material Material
Tambang/Galian Pengelolaan PPN PPH 23 Alat PPH 23
Pabrikan/Toko PPH 21 (6%) PPH 22 (1,5%) PPH 22 (3%)
(Rp) (Rp) (10%) (2%) Makanan (4%)
(Rp)
I BAHAN MATERIAL
1
PC 40 Kg 271,200 27,120 4,068
2
Pasir Pasang 488,160 14,645
3
Pasir Beton Err:509 Err:509
4
Bambu #REF! #REF! #REF!
6
Besi D 8 - - -
7
Besi D13 19,800 1,980 297
9
Kerikil 2/3 5,842,100 175,263
10
Papan Bekisting 2/20 Err:509 Err:509 Err:509
12
Usuk 5/7 - - -
14
Paku (2" - 5") - - -
15
Bendrat Err:509 Err:509 Err:509
Timba Cor Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
II PENGELOLAAN
1 Makan Minum #NAME? #NAME?
2 Honorarium Panitia Pelaksana 1,000,000 60,000
JUMLAH Err:509 Err:509 #NAME? Err:509 60,000 Err:509 Err:509 - #NAME?
JUMLAH TOTAL POTENSI PAJAK Err:509
RENCANA KEBUTUHAN BAHAN / MATERIAL
PELAKSANAAN SWAKELOLA
KEGIATAN :

PEKERJAAN :
LOKASI :
TH. ANGGARAN :
SUMBER DANA :

Harga Jumlah
No. Jenis Bahan / Material Sat. Vol. Satuan Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)
I Material
1 PC Zak 9.00 54,240.00 488,160.00
3 Pasir Pasang M3 2.00 135,600.00 271,200.00
4 Kanstin Trap uk. 15.30.50 Bh 398.00 36,300.00 14,447,400.00
5 Pair Urug M3 47.00 124,300.00 5,842,100.00
6 Paving Press K200 6 cm Jogja M2 271.00 124,300.00 33,685,300.00

II Alat -
1 Benang Pasang Bh 6.00 3,300.00 19,800.00
-
III Tenaga -
1 Pekerja OH 114 70,000.00 7,961,940.00
2 Tukang OH 84 80,000.00 6,720,000.00

IV BOP 1.00 5,564,100.00 5,564,100.00

(A) JUMLAH HARGA PEKERJAAN ( KESELURUHAN ) 75,000,000.00


(B) TOTAL BIAYA PEMBULATAN
Terbilang :

Bangunsari 2020

Mengetahui Dibuat oleh :


Kepala Desa Bangunsari Kaur Perencanaan

.............................. .................................................

Anda mungkin juga menyukai