OPNAME FISIK

PERENCANAAN, PEMBANGUNAN, PENGAWASAN, DAN PEMANFAATAN BANGUNAN GEDUNG DAERAH KABUPATEN/KOTA


PEMBANGUNAN GEDUNG MALL PELAYANAN PUBLIK
APBD KAB. INDRAMAYU TA. 2021
WILAYAH KECAMATAN INDRAMAYU

PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN


NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

A. PEKERJAAN PERSIAPAN

1 Pek. Pengukuran & bouwplank 188.00 m' 53,068.80 9,976,934.40 0.24 100.00 188.00 9,976,934.40 0.24

2 Sewa direksi keet uk. 18,00 m2 1.00 ls 8,000,000.00 8,000,000.00 0.19 100.00 1.00 8,000,000.00 0.19

3 Sewa pagar pengaman proyek 1.00 ls 15,000,000.00 15,000,000.00 0.36 - - - -

4 Papan nama proyek digital printing uk. 1,50 x 2,00 m 3.00 m2 297,416.00 892,248.00 0.02 100.00 3.00 892,248.00 0.02

5 Biaya administrasi & dokumentasi 1.00 ls 2,500,000.00 2,500,000.00 0.06 - - - -

6 Pengadaan listrik dan air kerja 1.00 ls 5,000,000.00 5,000,000.00 0.12 100.00 1.00 5,000,000.00 0.12

7 Sewa mobil pompa beton 4.00 trip 5,000,000.00 20,000,000.00 0.48 - - - -

8 Sewa scafolding 238.00 m2 11,666.67 2,776,666.67 0.07 - - - -

9 Mobilisasi dan demobilisasi alat berat

Drop Hammer 1.00 ls 5,000,000.00 5,000,000.00 0.12 100.00 1.00 5,000,000.00 0.12

Tandem roller 8 ton 1.00 ls 4,000,000.00 4,000,000.00 0.10 - - - -

10 Biaya Sewa Peralatan dan keselamatan kerja

- Pembuatan kartu identitas pekerja (KIP) 20.00 lbr 10,000.00 200,000.00 0.00 - - - -

- Spanduk (Banner) 3.00 lbr 100,000.00 300,000.00 0.01 100.00 3.00 300,000.00 0.01
PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

- Poster 3.00 lbr 100,000.00 300,000.00 0.01 100.00 3.00 300,000.00 0.01

- Pembatas area (Restricted Area) 1.00 ls 150,000.00 150,000.00 0.00 - - - -

- Pelindung pernafasan dan mulut (masker 100.00 bh 5,000.00 500,000.00 0.01 - - - -

- Sarung tangan (Safety Gloves) 20.00 psg 10,000.00 200,000.00 0.00 - - - -

- Sepatu keselamatan (Safety Shoes) 20.00 psg 85,000.00 1,700,000.00 0.04 - - - -

- Rompi keselamatan (Safety Vest) 20.00 psg 40,000.00 800,000.00 0.02 - - - -

- Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka) 1.00 ls 750,000.00 750,000.00 0.02 - - - -

- Bendera K3 2.00 bh 174,000.00 348,000.00 0.01 100.00 2.00 348,000.00 0.01

- Lampu darurat (Emergency Lamp) 4.00 bh 250,000.00 1,000,000.00 0.02 - - - -

TOTAL A 79,393,849.07 1.92 29,817,182.40 0.72

B. PEKERJAAN TANAH/PASIR & PONDASI BATU

1 Pek. Galian tanah pondasi 43.04 m3 82,500.00 3,550,800.00 0.09 75.00 32.28 2,663,100.00 0.06

2 Pek. Urugan tanah kembali 11.12 m3 60,000.00 667,200.00 0.02 - - - -

3 Pek. Urugan pasir alas pondasi pile cup t. 5 cm 5.51 m3 244,680.00 1,348,186.80 0.03 10.00 0.55 134,818.68 0.00

4 Pek. Urugan tanah merah peninggian lantai t. 75 cm 1,272.30 m3 156,480.00 199,089,504.00 4.81 - - - -

5 Pek. Urugan tanah peninggian site t. 60 cm 1,835.05 m3 156,480.00 287,148,624.00 6.93 - - - -

6 Pek. Aanstamping (batu kosong) 3.84 m3 461,029.80 1,770,354.43 0.04 75.00 2.88 1,327,765.82 0.03

7 Pek. Pondasi batu kali 1 pc : 5 ps (dibawah S1) 30.28 m3 825,102.60 24,984,106.73 0.60 75.00 22.71 18,738,080.05 0.45

8 Pek. Pondasi batu kali 1 pc : 5 ps (area servis) 10.26 m3 825,102.60 8,465,552.68 0.20 - - - -

TOTAL B 527,024,328.64 12.73 22,863,764.55 0.55


PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

C. PEKERJAAN LANTAI BAWAH

C.1 PEKERJAAN STRUKTUR

1 Pek. Lantai kerja pile cup t. 10 cm 11.02 m3 836,714.00 9,220,588.28 0.22 10.00 1.10 922,058.83 0.02

2 Pek. Pemasangan Tiang Pancang

Pekerjaan Tiang Pancang ø 30 cm Bottom P. 6 Meter 624.00 m' 454,000.00 283,296,000.00 6.84 100.00 624.00 283,296,000.00 6.84

Pekerjaan Tiang Pancang ø 30 cm Middle P. 6 Meter 624.00 m' 454,000.00 283,296,000.00 6.84 100.00 624.00 283,296,000.00 6.84

Pekerjaan Tiang Pancang ø 30 cm Middle P. 6 Meter 624.00 m' 454,000.00 283,296,000.00 6.84 100.00 624.00 283,296,000.00 6.84

Pekerjaan Tiang Pancang ø 30 cm Middle P. 3 Meter 312.00 m' 454,000.00 141,648,000.00 3.42 100.00 312.00 141,648,000.00 3.42

Bobok tiang pancang 104.00 ttk 150,000.00 15,600,000.00 0.38 100.00 104.00 15,600,000.00 0.38

Dolly/alat bantu tiang pancang Jack in Pile 104.00 ttk 150,000.00 15,600,000.00 0.38 100.00 104.00 15,600,000.00 0.38

Biaya Pengelasan 208.00 Samb 180,000.00 37,440,000.00 0.90 100.00 208.00 37,440,000.00 0.90

3 Pek. Pile cup t. 40 cm

Pek. Cor beton ready mix K-300 44.10 m3 1,207,150.00 53,235,315.00 1.29 - - - -

Pek. Pembesian 7,803.93 kg 14,336.50 111,881,042.45 2.70 10.00 780.39 11,188,104.24 0.27

Pek. Begisting 2x pakai 58.80 m2 165,468.00 9,729,518.40 0.23 - - - -

4 Pek. Pondasi plat 60/60 cm

Pek. Cor beton ready mix K-300 14.40 m3 1,207,150.00 17,382,960.00 0.42 - - - -

Pek. Pembesian 2,586.19 kg 14,336.50 37,076,912.94 0.90 - - - -

Pek. Begisting 2x pakai 28.80 m2 165,468.00 4,765,478.40 0.12 - - - -


PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

5 Pek. Sloof 20/40 cm (S1)

Pek. Cor beton ready mix K-300 43.04 m3 1,207,150.00 51,955,736.00 1.25 - - - -

Pek. Pembesian 6,642.44 kg 14,336.50 95,229,341.06 2.30 10.00 664.24 9,522,934.11 0.23

Pek. Begisting 2x pakai 215.20 m2 165,468.00 35,608,713.60 0.86 - - - -

6 Pek. Sloof 40/60 cm (S2)

Pek. Cor beton ready mix K-300 11.52 m3 1,207,150.00 13,906,368.00 0.34 - - - -

Pek. Pembesian 2,104.30 kg 14,336.50 30,168,296.95 0.73 - - - -

Pek. Begisting 2x pakai 57.60 m2 165,468.00 9,530,956.80 0.23 - - - -

7 Pek. Sloof 15/20 cm (S3)

Pek. Cor beton ready mix K-300 1.60 m3 1,207,150.00 1,931,440.00 0.05 - - - -

Pek. Pembesian 280.16 kg 14,336.50 4,016,513.84 0.10 - - - -

Pek. Begisting 21.40 m2 165,468.00 3,541,015.20 0.09 - - - -

8 Pek. Sloof 20/30 cm (S4)

Pek. Cor beton ready mix K-300 0.84 m3 1,207,150.00 1,014,006.00 0.02 - - - -

Pek. Pembesian 85.47 kg 14,336.50 1,225,340.66 0.03 - - - -

Pek. Begisting 2x pakai 8.95 m2 165,468.00 1,480,938.60 0.04 - - - -

9 Pek. Plat beton lantai t. 10 cm

Pek. Cor beton ready mix K-300 169.64 m3 1,207,150.00 204,780,926.00 4.94 - - - -
PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

Pek. Pembesian wiremesh M-8 1,696.40 m2 55,250.00 93,726,100.00 2.26 - - - -

Pek. Begisting 2x pakai 184.00 m2 165,468.00 30,446,112.00 0.74 - - - -

10 Pek. Kolom pedestal 45/45 cm

Pek. Cor beton ready mix K-300 10.94 m3 1,207,150.00 13,206,221.00 0.32 - - - -

Pek. Pembesian 1,999.90 kg 14,336.50 28,671,566.35 0.69 - - - -

Pek. Begisting 2x pakai 97.20 m2 165,468.00 16,083,489.60 0.39 - - - -

11 Pek. Kolom 45/45 cm

Pek. Cor beton ready mix K-300 38.45 m3 1,207,150.00 46,414,917.50 1.12 - - - -

Pek. Pembesian 8,329.18 kg 14,336.50 119,411,289.07 2.88 - - - -

Pek. Stek Pembesian P. 80cm 1,288.80 kg 14,336.50 18,476,881.20 0.45 - - - -

Pek. Begisting 2x pakai 340.20 m2 165,468.00 56,292,213.60 1.36 - - - -

12 Pek. Kolom pedestal 60/60 cm

Pek. Cor beton ready mix K-300 1.73 m3 1,178,300.00 2,038,459.00 0.05 - - - -

Pek. Pembesian 325.87 kg 14,336.50 4,671,835.26 0.11 - - - -

Pek. Begisting 2x pakai 11.52 m2 159,378.00 1,836,034.56 0.04 - - - -

13 Pek. Kolom 60/60 cm (K5)

Pek. Cor beton ready mix K-300 6.33 m3 1,207,150.00 7,641,259.50 0.18 - - - -

Pek. Pembesian 1,170.60 kg 14,336.50 16,782,306.90 0.41 - - - -


PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

Pek. Stek Pembesian P. 80cm 190.93 kg 14,336.50 2,737,267.95 0.07 - - - -

Pek. Begisting 2x pakai 42.24 m2 165,468.00 6,989,368.32 0.17 - - - -

14 Pek. Kolom pedestal 20/45 cm

Pek. Cor beton ready mix K-300 1.84 m3 1,207,150.00 2,221,156.00 0.05 - - - -

Pek. Pembesian 527.54 kg 14,336.50 7,563,077.21 0.18 - - - -

Pek. Begisting 2x pakai 26.52 m2 165,468.00 4,388,211.36 0.11 - - - -

15 Pek. Kolom 20/45 cm

Pek. Cor beton ready mix K-300 6.73 m3 1,207,150.00 8,124,119.50 0.20 - - - -

Pek. Pembesian 781.16 kg 14,336.50 11,199,100.34 0.27 - - - -

Pek. Stek Pembesian P. 80cm 72.48 kg 14,336.50 1,039,109.52 0.03 - - - -

Pek. Begisting 2x pakai 48.62 m2 165,468.00 8,045,054.16 0.19 - - - -

16 Pek. Kolom 15/20 cm

Pek. Cor beton site mix K-225 0.26 m3 1,207,150.00 313,859.00 0.01 - - - -

Pek. Pembesian 86.47 kg 14,336.50 1,239,677.16 0.03 - - - -

Pek. Stek Pembesian P. 80cm 5.68 kg 14,336.50 81,431.32 0.00 - - - -

Pek. Begisting 2x pakai 6.16 m2 165,468.00 1,019,282.88 0.02 - - - -

17 Pek. Balok 30/65 cm (B1)

Pek. Cor beton ready mix K-300 49.20 m3 1,207,150.00 59,391,780.00 1.43 - - - -
PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

Pek. Pembesian 18,432.68 kg 14,336.50 264,260,116.82 6.38 - - - -

Pek. Begisting 2x pakai 75.52 m2 165,468.00 12,496,143.36 0.30 - - - -

18 Pek. Balok 30/50 cm (B2)

Pek. Cor beton ready mix K-300 26.35 m3 1,207,150.00 31,808,402.50 0.77 - - - -

Pek. Pembesian 10,558.78 kg 14,336.50 151,375,949.47 3.66 - - - -

Pek. Begisting 2x pakai 125.50 m2 165,468.00 20,766,234.00 0.50 - - - -

19 Pek. Balok 20/40 cm (B3)

Pek. Cor beton ready mix K-300 17.39 m3 1,207,150.00 20,992,338.50 0.51 - - - -

Pek. Pembesian 6,561.57 kg 14,336.50 94,069,948.31 2.27 - - - -

Pek. Begisting 2x pakai 121.77 m2 165,468.00 20,149,038.36 0.49 - - - -

20 Pek. Balok 20/30 cm (B4)

Pek. Cor beton ready mix K-300 0.72 m3 1,207,150.00 869,148.00 0.02 - - - -

Pek. Pembesian 123.57 kg 14,336.50 1,771,561.31 0.04 - - - -

Pek. Begisting 2x pakai 9.00 m2 165,468.00 1,489,212.00 0.04 - - - -

21 Pek. Dak beton t. 13 cm

Pek. Cor beton ready mix K-300 118.00 m3 1,207,150.00 142,443,700.00 3.44 - - - -

Pek. Shear connector 137.50 kg 14,336.50 1,971,268.75 0.05 - - - -

Pek. Pembesian wiremesh M-8 (2 layer) 1,373.15 m2 66,640.00 91,506,716.00 2.21 - - - -


PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

Pek. Begisting 1,373.15 m2 165,468.00 227,212,384.20 5.49 - - - -

22 Pek. Dak beton t. 12 cm (atap musholla)

Pek. Cor beton ready mix K-300 11.52 m3 1,207,150.00 13,906,368.00 0.34 - - - -

Pek. Shear connector 24.00 kg 14,336.50 344,076.00 0.01 - - - -

Pek. Pembesian wiremesh M-8 (1 layer) 96.00 m2 66,640.00 6,397,440.00 0.15 - - - -

Pek. Begisting plat bondex 96.00 m2 160,000.00 15,360,000.00 0.37 - - - -

23 Pek. Tangga utama & area servis

Pek. Pondasi plat

Pek. Cor beton site mix K-225 0.95 m3 1,068,234.00 1,014,822.30 0.02 - - - -

Pek. Pembesian 218.43 kg 14,336.50 3,131,521.70 0.08 - - - -

Pek. Begisting 10.85 m2 165,468.00 1,795,327.80 0.04 - - - -

Pek. Cor beton tangga

Pek. Cor beton site mix K-225 7.94 m3 1,068,234.00 8,481,777.96 0.20 - - - -

Pek. Pembesian 1,865.78 m2 14,336.50 26,748,754.97 0.65 - - - -

Pek. Begisting 2x pakai 31.66 m2 165,468.00 5,238,716.88 0.13 - - - -

24 Pek. Pondasi plat

Pek. Cor beton site mix K-225 5.98 m3 1,068,234.00 6,388,039.32 0.15 - - - -

Pek. Pembesian 74.79 kg 14,336.50 1,072,226.84 0.03 - - - -

Pek. Begisting 39.61 m2 165,468.00 6,554,187.48 0.16 - - - -


PEKERJAAN DALAM KONTRAK PEKERJAAN DALAM LAPANGAN
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH BOBOT JUMLAH BOBOT
PRESTASI VOLUME
SATUAN (Rp) HARGA (Rp.) (%) HARGA (Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11

25 Pek. Base Plat Drop off 812.19 Kg 31,365.00 25,474,339.35 0.62 - - - -

Pek. Baut D16 64.00 Bh 4,500.00 288,000.00 0.01 - - - -

Pek. Angkur D16 64.00 Bh 26,000.00 1,664,000.00 0.04 - - - -

TOTAL C 3,534,950,348.57 85.36 1,081,809,097.18 26.12

JUMLAH II 4,141,368,526.27 100.00 1,134,490,044.13 27.39

JUMLAH TOTAL FISIK 4,141,368,526.27 100.00 1,134,490,044.13 27.39


PPN 10% 414,136,852.63 113,449,004.41
JUMLAH TOTAL 4,555,505,378.90 1,247,939,048.54
DIBULATKAN 4,555,505,000.00 1,247,939,000.00

Terbilang :
Empat milyar lima ratus lima puluh lima juta lima ratus lima ribu rupiah

Indramayu, 14 Agustus 2021


MENYETUJUI ; DISETUJUI ; DIBUAT OLEH ;
PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
PT. Samudra Jaya Konsultan CV. RAJ SOLUSINDO

WIWIK OKTIANI, SE SUNARYO, ST., MT SUNARYO, ST., MT HERSU PANJI PERDANA


NIP. 19841024 201001 2 002 Direktur Pengawas Lapangan Direktur