E. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 975.000 62,526,750.00 - 0.00 975.00 62,526,750.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 3,600.000 224,748,000.00 - 0.00 3,600.00 224,748,000.00
3 Pasangan dinding kerawang M2 117,295.00 230.000 26,977,850.00 - 0.00 230.00 26,977,850.00
4 Pasangan dinding keramik M2 86,500.00 1,503.000 130,009,500.00 - 0.00 1,503.00 130,009,500.00
5 Kolom dan balok praktis M' 59,780.00 3,660.000 218,794,800.00 - 0.00 3,660.00 218,794,800.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 51.200 10,221,363.20 - (22.40) (4,471,846.40) 28.80 5,749,516.80 Dimensi (0,6x4x3) x 4 bh
7 Plesteran dinding 1 : 2 M2 30,836.00 1,950.000 60,130,200.00 - 0.00 1,950.00 60,130,200.00
8 Plesteran dinding 1 : 5 M2 27,546.00 7,200.000 198,331,200.00 - 0.00 7,200.00 198,331,200.00
9 Plesteran kolom beton M2 33,226.00 1,700.000 56,484,200.00 - 0.00 1,700.00 56,484,200.00
F. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 88,810.00 3,446.000 306,039,260.00 - 0.00 3,446.00 306,039,260.00
3 Lantai border plester M2 30,836.00 257.000 7,924,852.00 - 0.00 257.00 7,924,852.00
4 Plint keramik M' 32,780.00 1,520.000 49,825,600.00 - 0.00 1,520.00 49,825,600.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 607.000 49,167,000.00 - 0.00 607.00 49,167,000.00
6 Floor hardener M' 150,000.00 305.000 45,750,000.00 - 0.00 305.00 45,750,000.00
7 Lantai ubin PC M2 57,800.00 5.000 289,000.00 - (5.00) (289,000.00) 0.00 0.00 tidak terpasang
8 Lantai paving blok t = 8 cm M2 181,600.00 174.000 31,598,400.00 - 0.00 174.00 31,598,400.00
9 Keramik motif 30 x 30 cm M2 103,860.00 32.000 3,323,520.00 - 0.00 32.00 3,323,520.00
G. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 530.000 52,684,650.00 - 0.00 530.00 52,684,650.00
2 Plafond ekspose M2 33,226.00 7,336.000 243,745,936.00 - 0.00 7,336.00 243,745,936.00
3 List plafond M' 18,800.00 510.000 9,588,000.00 - 0.00 510.00 9,588,000.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 255.000 26,775,000.00 - 0.00 255.00 26,775,000.00
I. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 16,492.50 7,850.000 129,466,125.00 - 0.00 7,850.00 129,466,125.00
2 Cat plafond gypsum M2 17,367.50 530.000 9,204,775.00 - 0.00 530.00 9,204,775.00
3 Cat plafond beton M2 28,620.00 7,336.000 209,956,320.00 - 0.00 7,336.00 209,956,320.00
4 Cat listplank dan parapet M2 28,620.00 730.000 20,892,600.00 - 0.00 730.00 20,892,600.00
5 Cat dinding kerawang M2 28,620.00 460.000 13,165,200.00 - 0.00 460.00 13,165,200.00
6 Cat kolom beton M2 28,620.00 1,700.000 48,654,000.00 - 0.00 1,700.00 48,654,000.00
J. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 450,000.00 167.000 75,150,000.00 - 0.00 167.00 75,150,000.00
2 Saluran air 30 x 50 cm M' 600,000.00 144.000 86,400,000.00 - 0.00 144.00 86,400,000.00
3 Bak bunga Bh 1,780,800.00 2.000 3,561,600.00 - 0.00 2.00 3,561,600.00
4 Bangunan kanopi M2 4,325,000.00 132.000 570,900,000.00 - 0.00 132.00 570,900,000.00
5 Grill tutup saluran M' 294,000.00 22.000 6,468,000.00 - 0.00 22.00 6,468,000.00
6 Bak kontrol 60 x 60 cm Bh 1,264,071.00 10.000 12,640,710.00 - 0.00 10.00 12,640,710.00
K. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 4,068.000 488,160,000.00 - 0.00 4,068.00 488,160,000.00
5 Plesteran M2 33,226.00 4,068.000 135,163,368.00 - 0.00 4,068.00 135,163,368.00
6 Railing tribune M' 450,000.00 174.000 78,300,000.00 - 0.00 174.00 78,300,000.00
L. PEKERJAAN SANITAIR
1 Closet duduk Toto CWY20J/S516STD Bh 2,250,000.00 73.000 164,250,000.00 - (47.00) (105,750,000.00) 26.00 58,500,000.00 kondisi terpasang
2 Closet jongkok Toto CE6 Bh 521,300.00 37.000 19,288,100.00 - (1.00) (521,300.00) 36.00 18,766,800.00 kondisi terpasang
3 Wastafel Toto L34 Bh 1,038,800.00 24.000 24,931,200.00 10.00 10,388,000.00 0.00 34.00 35,319,200.00 kondisi terpasang
4 Wastafel Toto L521 V1A Bh 1,779,600.00 20.000 35,592,000.00 - (8.00) (14,236,800.00) 12.00 21,355,200.00 kondisi terpasang
5 Urinoir Toto U57M Bh 2,096,300.00 46.000 96,429,800.00 - 0.00 46.00 96,429,800.00
6 Shower Spray TotoTX403SV3P1V Bh 344,100.00 21.000 7,226,100.00 5.00 1,720,500.00 0.00 26.00 8,946,600.00 kondisi terpasang
7 Shower Head Toto TX435S Bh 600,000.00 15.000 9,000,000.00 - (2.00) (1,200,000.00) 13.00 7,800,000.00 kondisi terpasang
8 Soap Holder S156N Bh 92,900.00 15.000 1,393,500.00 - (2.00) (185,800.00) 13.00 1,207,700.00 kondisi terpasang
9 Paper Holder TX720AW Bh 80,100.00 21.000 1,682,100.00 5.00 400,500.00 0.00 26.00 2,082,600.00 kondisi terpasang
10 Floor Drain Bh 139,250.00 76.000 10,583,000.00 58.00 8,076,500.00 0.00 134.00 18,659,500.00 kondisi terpasang
11 Meja wastafel beton berlapis keramik M' 1,415,000.00 21.000 29,715,000.00 - (3.60) (5,094,000.00) 17.40 24,621,000.00 kondisi terpasang
12 Kran Air 0,5" Bh 75,000.00 39.00 2,925,000.00 0.00 39.00 2,925,000.00 kondisi terpasang
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
Sub Jumlah II. L 400,090,800.00 23,510,500.00 (126,987,900.00) 296,613,400.00
M. PEKERJAAN ATAP
4 Pipa talang M' 138,820.00 372.000 51,641,040.00 - 0.00 372.00 51,641,040.00
5 Roof Drain Bh 296,250.00 31.000 9,183,750.00 - 0.00 31.00 9,183,750.00
C. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 522.00 33,475,860.00 - 0.00 522.00 33,475,860.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 2,090.00 130,478,700.00 - 0.00 2,090.00 130,478,700.00
3 Pasangan dinding kerawang M2 117,295.00 240.00 28,150,800.00 - 0.00 240.00 28,150,800.00
4 Pasangan dinding keramik M2 86,500.00 600.00 51,900,000.00 - 0.00 600.00 51,900,000.00
5 Kolom dan balok praktis M' 59,780.00 2,218.00 132,592,040.00 - 0.00 2,218.00 132,592,040.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 51.20 10,221,363.20 - 0.00 51.20 10,221,363.20
7 Plesteran dinding 1 : 2 M2 30,836.00 1,044.00 32,192,784.00 - 0.00 1,044.00 32,192,784.00
8 Plesteran dinding 1 : 5 M2 27,546.00 4,180.00 115,142,280.00 - 0.00 4,180.00 115,142,280.00
9 Plesteran kolom beton M2 33,226.00 765.00 25,417,890.00 - 0.00 765.00 25,417,890.00
D. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 88,810.00 2,710.00 240,675,100.00 - 0.00 2,710.00 240,675,100.00
3 Lantai border plester M2 30,836.00 181.00 5,581,316.00 - 0.00 181.00 5,581,316.00
4 Plint keramik M' 32,780.00 1,100.00 36,058,000.00 - 0.00 1,100.00 36,058,000.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 166.00 13,446,000.00 - 0.00 166.00 13,446,000.00
E. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 273.00 27,137,565.00 - 0.00 273.00 27,137,565.00
2 Plafond ekspose M2 33,226.00 3,530.00 117,287,780.00 - 0.00 3,530.00 117,287,780.00
3 List plafond M' 18,800.00 460.00 8,648,000.00 - 0.00 460.00 8,648,000.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 244.00 25,620,000.00 - 0.00 244.00 25,620,000.00
5 Calsium board t = 6 mm M2 72,050.00 144.00 10,375,200.00 - 0.00 144.00 10,375,200.00
6 List kayu M' 5,500.00 176.00 968,000.00 - 0.00 176.00 968,000.00
G. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 16,492.50 5,220.00 86,090,850.00 - 0.00 5,220.00 86,090,850.00
2 Cat plafond gypsum M2 17,367.50 661.00 11,479,917.50 - 0.00 661.00 11,479,917.50
3 Cat plafond beton M2 28,620.00 3,530.00 101,028,600.00 - 0.00 3,530.00 101,028,600.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
4 Cat listplank dan parapet M2 28,620.00 730.00 20,892,600.00 - 0.00 730.00 20,892,600.00
5 Cat dinding kerawang Kw1 + Kw2 M2 28,620.00 480.00 13,737,600.00 - 0.00 480.00 13,737,600.00
H. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 450,000.00 145.00 65,250,000.00 - 0.00 145.00 65,250,000.00
2 Saluran air 30 x 50 cm M' 600,000.00 138.00 82,800,000.00 - 0.00 138.00 82,800,000.00
3 Bak kontrol Bh 1,264,071.00 10.00 12,640,710.00 - 0.00 10.00 12,640,710.00
4 Trap As 62-63 / A M2 150,000.00 6.00 900,000.00 - 0.00 6.00 900,000.00
I. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 3,650.00 438,000,000.00 - (395.20) (47,424,000.00) 3,254.80 390,576,000.00 Pintu masuk + Pengurangan As
5 Plesteran M2 33,226.00 3,650.00 121,274,900.00 - (395.20) (13,130,915.20) 3,254.80 108,143,984.80 Pintu masuk + Pengurangan As
6 Railing tribune M' 450,000.00 174.00 78,300,000.00 - 0.00 174.00 78,300,000.00
J. PEKERJAAN SANITAIR
1 Closet duduk Toto CWY20J/S516STD Bh 2,250,000.00 13.00 29,250,000.00 - (5.00) (11,250,000.00) 8.00 18,000,000.00
2 Closet jongkok Toto CE6 Bh 521,300.00 6.00 3,127,800.00 9.00 4,691,700.00 0.00 15.00 7,819,500.00
3 Wastafel Toto L34 Bh 1,038,800.00 10.00 10,388,000.00 1.00 1,038,800.00 0.00 11.00 11,426,800.00
4 Wastafel Toto L521 V1A Bh 1,779,600.00 4.00 7,118,400.00 1.00 1,779,600.00 0.00 5.00 8,898,000.00
5 Urinoir Toto U57M Bh 2,096,300.00 11.00 23,059,300.00 5.00 10,481,500.00 0.00 16.00 33,540,800.00
6 Shower Spray Toto TX403SV3P1V Bh 344,100.00 13.00 4,473,300.00 - (5.00) (1,720,500.00) 8.00 2,752,800.00
7 Shower Head Toto TX435S Bh 600,000.00 14.00 8,400,000.00 2.00 1,200,000.00 0.00 16.00 9,600,000.00
8 Soap Holder S156N Bh 92,900.00 - - - 0.00 0.00 0.00
9 Paper Holder TX720AW Bh 80,100.00 37.00 2,963,700.00 - (22.00) (1,762,200.00) 15.00 1,201,500.00
10 Floor Drain Bh 139,250.00 14.00 1,949,500.00 51.00 7,101,750.00 0.00 65.00 9,051,250.00
11 Meja wastafel beton berlapis keramik M' 1,415,000.00 1.00 1,415,000.00 9.00 12,735,000.00 0.00 10.00 14,150,000.00
12 Duropal M2 450,000.00 20.00 9,000,000.00 13.30 5,985,000.00 0.00 33.30 14,985,000.00
16 Penambahan partisi R. Makan dan Rekreasi lt.1 - 0.00 0.00 0.00 Revisi Owner
. Partisi spandrill aluminium M2 250,000.00 10.64 2,660,000.00 0.00 10.64 2,660,000.00
. Kusen pintu dan jendela aluminium M' 120,000.00 113.14 13,576,800.00 0.00 113.14 13,576,800.00
. Kaca polos 5 mm M2 88,000.00 19.27 1,696,112.00 0.00 19.27 1,696,112.00
. Kaca polos 8 mm M2 110,000.00 6.51 716,430.00 0.00 6.51 716,430.00
17 Pembongkaran dinding bata M2 7,500.00 4.92 36,900.00 4.92 36,900.00
18 Penambahan Saluran Air 60 x 70 M' 800,000.00 188.38 150,704,000.00 188.38 150,704,000.00 Revisi Owner
E. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 - - - 0.00 0.00 0.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 453.600 28,318,248.00 - 0.00 453.60 28,318,248.00
3 Pasangan dinding kerawang M2 117,295.00 20.000 2,345,900.00 - 0.00 20.00 2,345,900.00
4 Pasangan dinding keramik M2 86,500.00 141.700 12,257,050.00 - 0.00 141.70 12,257,050.00
5 Kolom dan balok praktis M' 59,780.00 37.800 2,259,684.00 - 0.00 37.80 2,259,684.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 - - - 0.00 0.00 0.00
7 Plesteran dinding 1 : 2 M2 30,836.00 - - - 0 0.00 0.00
8 Plesteran dinding 1 : 5 M2 27,546.00 907.200 24,989,731.20 - 0.00 907.20 24,989,731.20
9 Plesteran kolom beton M2 33,226.00 - - - 0.00 0.00 0.00
F. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 0.00 - - - 0.00 0.00 0.00
3 Lantai border plester M2 0.00 - - - 0.00 0.00 0.00
4 Plint keramik M' 0.00 - - - 0.00 0.00 0.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 28.000 2,268,000.00 - 0.00 28.00 2,268,000.00
6 Floor Hardener M2 0.00 - - - 0.00 0.00 0.00
7 Lantai ubin PC M2 0.00 - - - 0.00 0.00 0.00
8 Lantai paving blok t = 8 cm M2 0.00 - - - 0.00 0.00 0.00
9 Keramik motif 30 x 30 cm M2 0.00 - - - 0.00 0.00 0.00
G. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 - - - 0.00 0.00 0.00
2 Plafond ekspose M2 33,226.00 - - - 0.00 0.00 0.00
3 List plafond M' 18,800.00 - - - 0.00 0.00 0.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 - - - 0.00 0.00 0.00
I. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 14,492.50 - - - 0.00 0.00 0.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
2 Cat plafond gypsum M2 17,367.50 - - - 0.00 0.00 0.00
3 Cat plafond beton M2 26,620.00 - - - 0.00 0.00 0.00
4 Cat listplank dan parapet M2 26,620.00 - - - 0.00 0.00 0.00
5 Cat dinding kerawang Kw1 + Kw2 M2 26,620.00 - - - 0.00 0.00 0.00
6 Cat kolom beton M2 26,620.00 - - - 0.00 0.00 0.00
J. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 441,000.00 - - - 0.00 0.00 0.00
2 Saluran air 30 x 50 cm M' 600,000.00 454.000 272,400,000.00 - 0.00 454.00 272,400,000.00
3 Bak bunga Bh 1,780,800.00 - - - 0.00 0.00 0.00
4 Bangunan kanopi M2 4,325,000.00 - - - 0.00 0.00 0.00
5 Grill tutup saluran Bh 294,000.00 - - - 0.00 0.00 0.00
6 Bak kontrol 60 x 60 cm M2 1,264,071.00 24.000 30,337,704.00 - 0.00 24.00 30,337,704.00
K. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 2,872.990 344,758,800.00 - (274.23) (32,907,600.00) 2,598.76 311,851,200.00 PenguranganAs
5 Plesteran M2 33,226.00 2,872.990 95,457,965.74 - (274.23) (9,111,565.98) 2,598.76 86,346,399.76 PenguranganAs
6 Railing tribune M' 450,000.00 - - - 0.00 0.00 0.00
L. PEKERJAAN SANITAIR
1 Closet jongkok Toto CE6 Bh 521,300.00 4.000 2,085,200.00 - 0.00 4.00 2,085,200.00
2 Wastafel Toto L34 Bh 1,038,800.00 4.000 4,155,200.00 - 0.00 4.00 4,155,200.00
3 Urinoir Toto U57M Bh 2,096,300.00 4.000 8,385,200.00 - 0.00 4.00 8,385,200.00
4 Shower Spray Toto TX403SV3P1V Bh 344,100.00 - - - 0.00 0.00 0.00
5 Floor Drain Bh 139,250.00 4.000 557,000.00 30.00 4,177,500.00 0.00 34.00 4,734,500.00
DENNY ALFIAN NOORSANDHY , ST. Ir. WAGINO HARYS Ir. ANIS J. RAHMAN, MM
NIP. 550 015 296 TEAM LEADER SITE MANAGER
PEKERJAAN TAMBAH KURANG
DINAS PEMUKIMAN DAN PENGEMBANGAN KOTA SAMARINDA NO. CCO PAKET KONTRAK STADION SEGIRI SAMARINDA
KALIMANTAN TIMUR TANGGAL KONTRAKTOR PT. LUHRIBU NAGA JAYA
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12
1 PEKERJAAN PEMANCANGAN
II TRIBUN BARAT STADION SEGIRI 0.00
A PEKERJAAN TIANG PANCANG
1 Pengadaan pancang mini Franki 32 x 32 x 32 cm M' 190,000.00 21,540.000 4,092,600,000.00 - (10,332.000) (1,963,080,000.00) 11,208.00 2,129,520,000.00
2 Penyambungan tiang pancang Bh 7,500.00 2,872.000 21,540,000.00 - (1,615.000) (12,112,500.00) 1,257.00 9,427,500.00
3 Pemancangan M' 33,000.00 21,540.000 710,820,000.00 - (11,321.800) (373,619,400.00) 10,218.20 337,200,600.00
4 Pemotongan kepala tiang pancang Bh 50,000.00 718.000 35,900,000.00 126.00 6,300,000.00 0.000 - 844.00 42,200,000.00
5 Mobilisasi tiang pancang Ls 669,460,000.00 1.000 669,460,000.00 - 0.000 - 1.00 669,460,000.00
Type P6A
- Galian tanah M3 15,570.00 12.90 200,915.28
- Urugan pasir t = 10 cm M3 80,250.00 1.17 94,213.50
- Lantai kerja t = 5 cm M2 29,876.00 11.73 350,445.48
- Beton K.300 M3 926,435.00 4.94 4,572,883.16
- Tulangan D.19 Kg 13,150.00 371.50 4,885,198.70
- Tulangan D.13 Kg 13,150.00 84.30 1,108,492.40
- Bekisting M2 113,500.00 10.42 1,182,216.00
- Urugan tanah kembali M3 11,172.00 6.21 69,366.95
Type P6B
- Galian tanah M3 15,570.00 9.65 150,172.65
- Urugan pasir t = 10 cm M3 80,250.00 0.68 54,168.75
- Lantai kerja t = 5 cm M2 29,876.00 6.43 192,102.68
- Beton K.300 M3 926,435.00 3.17 2,939,578.26
- Tulangan D.19 Kg 13,150.00 238.52 3,136,485.40
- Tulangan D.13 Kg 13,150.00 55.78 733,480.70
- Bekisting M2 113,500.00 6.30 715,050.00
- Urugan tanah kembali M3 11,172.00 5.51 61,535.38
Type P6C
- Galian tanah M3 15,570.00 8.54 132,905.52
- Urugan pasir t = 10 cm M3 80,250.00 0.66 52,724.25
- Lantai kerja t = 5 cm M2 29,876.00 6.57 196,165.82
- Beton K.300 M3 926,435.00 2.09 1,933,469.85
- Tulangan D.19 Kg 13,150.00 167.72 2,205,518.00
- Tulangan D.13 Kg 13,150.00 41.51 545,895.95
- Bekisting M2 113,500.00 4.84 549,794.00
- Urugan tanah kembali M3 11,172.00 5.46 61,043.81
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
Type P7A
- Galian tanah M3 15,570.00 69.44 1,081,102.95
- Urugan pasir t = 10 cm M3 80,250.00 6.31 506,297.25
- Lantai kerja t = 5 cm M2 29,876.00 63.13 1,885,952.38
- Beton K.300 M3 926,435.00 20.28 18,785,322.50
- Tulangan D.19 Kg 13,150.00 2,048.68 26,940,128.85
- Tulangan D.13 Kg 13,150.00 479.56 6,306,161.40
- Bekisting M2 113,500.00 43.22 4,905,243.00
- Urugan tanah kembali M3 11,172.00 39.69 443,405.51
Type P7B
- Galian tanah M3 15,570.00 12.90 200,915.28
- Urugan pasir t = 10 cm M3 80,250.00 1.17 94,213.50
- Lantai kerja t = 5 cm M2 29,876.00 11.73 350,445.48
- Beton K.300 M3 926,435.00 4.94 4,572,883.16
- Tulangan D.19 Kg 13,150.00 371.50 4,885,198.70
- Tulangan D.13 Kg 13,150.00 84.30 1,108,492.40
- Bekisting M2 113,500.00 10.42 1,182,216.00
- Urugan tanah kembali M3 11,172.00 3.28 36,588.30
Type P8B
- Galian tanah M3 15,570.00 74.55 1,160,696.79
- Urugan pasir t = 10 cm M3 80,250.00 7.85 629,802.00
- Lantai kerja t = 5 cm M2 29,876.00 78.47 2,344,399.60
- Beton K.300 M3 926,435.00 29.60 27,423,402.44
- Tulangan D.19 Kg 13,150.00 2,276.18 29,931,780.15
- Tulangan D.13 Kg 13,150.00 529.93 6,968,566.35
- Bekisting M2 113,500.00 51.16 5,806,206.00
- Urugan tanah kembali M3 11,172.00 33.18 370,642.27
Type P9A
- Galian tanah M3 15,570.00 8.55 133,092.36
- Urugan pasir t = 10 cm M3 80,250.00 0.90 72,225.00
- Lantai kerja t = 5 cm M2 29,876.00 9.00 268,824.25
- Beton K.300 M3 926,435.00 3.38 3,129,497.43
- Tulangan D.19 Kg 13,150.00 263.60 3,466,379.45
- Tulangan D.13 Kg 13,150.00 60.51 795,693.35
- Bekisting M2 113,500.00 5.88 667,380.00
- Urugan tanah kembali M3 11,172.00 3.82 42,677.04
Type P9B
- Galian tanah M3 15,570.00 24.98 389,000.88
- Urugan pasir t = 10 cm M3 80,250.00 2.08 167,080.50
- Lantai kerja t = 5 cm M2 29,876.00 20.82 622,018.32
- Beton K.300 M3 926,435.00 5.64 5,225,093.40
- Tulangan D.19 Kg 13,150.00 441.27 5,802,647.90
- Tulangan D.13 Kg 13,150.00 118.68 1,560,642.00
- Bekisting M2 113,500.00 12.18 1,382,430.00
- Urugan tanah kembali M3 11,172.00 16.22 181,221.01
Type P10
- Galian tanah M3 15,570.00 55.89 870,207.30
- Urugan pasir t = 10 cm M3 80,250.00 5.32 427,090.50
- Lantai kerja t = 5 cm M2 29,876.00 53.23 1,590,179.98
- Beton K.300 M3 926,435.00 23.88 22,123,267.80
- Tulangan D.19 Kg 13,150.00 2,022.62 26,597,426.70
- Tulangan D.13 Kg 13,150.00 430.88 5,666,045.70
- Bekisting M2 113,500.00 40.32 4,576,320.00
- Urugan tanah kembali M3 11,172.00 24.02 268,396.13
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
Type P13
- Galian tanah M3 15,570.00 - 37.22 579,437.55 - 37.22 579,437.55
- Urugan pasir t = 10 cm M3 80,250.00 - 3.54 284,325.75 - 3.54 284,325.75
- Lantai kerja t = 5 cm M2 29,876.00 - 35.44 1,058,865.19 - 35.44 1,058,865.19
- Beton K.300 M3 926,435.00 - 16.69 15,461,273.72 - 16.69 15,461,273.72
- Tulangan D.19 Kg 13,150.00 - 1,357.88 17,856,056.25 - 1,357.88 17,856,056.25
- Tulangan D.13 Kg 13,150.00 - 275.92 3,628,374.30 - 275.92 3,628,374.30
- Bekisting M2 113,500.00 - 24.14 2,740,344.00 - 24.14 2,740,344.00
- Urugan tanah kembali M3 11,172.00 - 15.21 169,926.12 - 15.21 169,926.12
Type P13A
- Galian tanah M3 15,570.00 - 20.71 322,439.13 - 20.71 322,439.13
- Urugan pasir t = 10 cm M3 80,250.00 - 1.27 101,516.25 - 1.27 101,516.25
- Lantai kerja t = 5 cm M2 29,876.00 - 12.65 377,931.40 - 12.65 377,931.40
- Beton K.300 M3 926,435.00 - 13.07 12,106,652.58 - 13.07 12,106,652.58
- Tulangan D.19 Kg 13,150.00 - 1,493.15 19,634,922.50 - 1,493.15 19,634,922.50
- Tulangan D.13 Kg 13,150.00 - 223.00 2,932,450.00 - 223.00 2,932,450.00
- Bekisting M2 113,500.00 - 16.72 1,897,720.00 - 16.72 1,897,720.00
- Urugan tanah kembali M3 11,172.00 - 5.74 64,166.38 - 5.74 64,166.38
Type P14
- Galian tanah M3 15,570.00 - 27.10 422,009.28 - 27.10 422,009.28
- Urugan pasir t = 10 cm M3 80,250.00 - 2.46 197,736.00 - 2.46 197,736.00
- Lantai kerja t = 5 cm M2 29,876.00 - 24.64 736,144.64 - 24.64 736,144.64
- Beton K.300 M3 926,435.00 - 9.14 8,467,615.90 - 9.14 8,467,615.90
- Tulangan D.19 Kg 13,150.00 - 708.47 9,316,406.80 - 708.47 9,316,406.80
- Tulangan D.13 Kg 13,150.00 - 169.62 2,230,476.70 - 169.62 2,230,476.70
- Bekisting M2 113,500.00 - 17.92 2,033,920.00 - 17.92 2,033,920.00
- Urugan tanah kembali M3 11,172.00 - 14.27 159,402.10 - 14.27 159,402.10
Sub Jumlah 4 (Pekerjaan Ruang Tiket dan Ruang Sekuriti As 92-01) 0.00 122,333,423.95 0.00 122,333,423.95
Sub Jumlah 5 (Pekerjaan Ground Water Tank, R. Pompa dan R. Tiket As 31 - 33) 0.00 258,087,187.71 0.00 258,087,187.71
Sub Jumlah 6 (Pekerjaan Balok Tribun As 01 - 31/B) 0.00 157,081,455.75 0.00 157,081,455.75
Sub Jumlah 7 (Pekerjaan Perubahan Kolom As 16'/A) 3,072,987.80 0.00 -3,072,987.80 0.00
Sub Jumlah 8 (Pekerjaan Perubahan Kolom As 15' - 16'/A) 3,070,181.14 4,804,537.18 0.00 7,874,718.32
Sub Jumlah 9 (Pekerjaan Jalan Akses Pintu Masuk Utama) 0.00 85,449,987.00 0.00 85,449,987.00
Sub Jumlah 10 (Pekerjaan Tangga Beton VIP As 14 - 18) 0.00 12,778,249.50 0.00 12,778,249.50
Sub Jumlah 11 (Pekerjaan Pagar Tembok As 31 - 33 dan 92 - 01) 0.00 12,189,546.90 0.00 12,189,546.90
Sub Jumlah 12 (Pekerjaan Lantai untuk Koral Sikat) 0.00 23,846,508.00 0.00 23,846,508.00
AS 73 - 75
1 Beton Balok M3 926,435.00 775.00 717,987,125.00 (11.520) (10,672,531.20) 763.48 707,314,593.80
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
2 Besi Balok Kg 13,150.00 124,000.00 1,630,600,000.00 (1,371.610) (18,036,671.50) 122,628.39 1,612,563,328.50
3 Bekisting Balok M2 150,000.00 6,800.00 1,020,000,000.00 (96.440) (14,466,000.00) 6,703.56 1,005,534,000.00
Sub Jumlah 14 (Pekerjaan Balok dan Plat Tribun As 73 - 75/As 50 - 52) 3,368,587,125.00 0.00 -43,175,202.70 3,325,411,922.30
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
Sub Jumlah 17 (Pekerjaan Pondasi Batu Kali As 33 - 48/77 - 92) 0.00 135,050,835.78 0.00 135,050,835.78
Sub Jumlah 18 (Pekerjaan Perubahan Posisi Tie Beam As 62 - 63/A) 0.00 3,694,747.50 0.00 3,694,747.50
Sub Jumlah 19 (Pekerjaan Kanopi Entrance Arah Lapangan As 62 - 63)) - 12,523,109.14 - 12,523,109.14
13 Pintu Spandrell Ruang Makan dan Rekreasi Unit 1.00 - 0.00 0.00 1.00 0.00
G. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 16,492.50 5,220.00 86,090,850.00 - - 0.00 0.00 5,220.00 86,090,850.00
2 Cat plafond gypsum M2 17,367.50 661.00 11,479,917.50 - - 0.00 0.00 661.00 11,479,917.50
3 Cat plafond beton M2 28,620.00 3,530.00 101,028,600.00 - - 0.00 0.00 3,530.00 101,028,600.00
4 Cat listplank dan parapet M2 28,620.00 730.00 20,892,600.00 - - 0.00 0.00 730.00 20,892,600.00
5 Cat dinding kerawang Kw1 + Kw2 M2 28,620.00 480.00 13,737,600.00 - - 0.00 0.00 480.00 13,737,600.00
H. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 450,000.00 145.00 65,250,000.00 - - 0.00 0.00 145.00 65,250,000.00
2 Saluran air 30 x 50 cm M' 600,000.00 138.00 82,800,000.00 - - 0.00 0.00 138.00 82,800,000.00
3 Bak kontrol Bh 1,264,071.00 10.00 12,640,710.00 - - 0.00 0.00 10.00 12,640,710.00
4 Trap As 62-63 / A M2 150,000.00 6.00 900,000.00 - - 0.00 0.00 6.00 900,000.00
I. PEKERJAAN TRIBUNE
1 Beton tribune M3 926,435.00 775.00 717,987,125.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Besi beton Kg 13,150.00 124,000.00 1,630,600,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Bekisting tribune (Plywood Film 12 mm) M2 150,000.00 6,800.00 1,020,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Waterproofing M2 120,000.00 3,650.00 438,000,000.00 - - 0.00 0.00 3,650.00 438,000,000.00
5 Plesteran M2 33,226.00 3,650.00 121,274,900.00 - - (3.32) (110,443.22) 3,646.68 121,164,456.78
6 Railing tribune M' 450,000.00 174.00 78,300,000.00 - - 0.00 0.00 174.00 78,300,000.00
J. PEKERJAAN SANITAIR
1 Closet duduk Toto CWY20J/S516STD Bh 2,250,000.00 13.00 29,250,000.00 - - (5.00) (11,250,000.00) 8.00 18,000,000.00
2 Closet jongkok Toto CE6 Bh 521,300.00 6.00 3,127,800.00 9.000.00 4,691,700.00 0.00 0.00 15.00 7,819,500.00
3 Wastafel Toto L34 Bh 1,038,800.00 10.00 10,388,000.00 1.000.00 1,038,800.00 0.00 0.00 11.00 11,426,800.00
4 Wastafel Toto L521 V1A Bh 1,779,600.00 4.00 7,118,400.00 1.000.00 1,779,600.00 0.00 0.00 5.00 8,898,000.00
5 Urinoir Toto U57M Bh 2,096,300.00 11.00 23,059,300.00 5.000.00 10,481,500.00 0.00 0.00 16.00 33,540,800.00
6 Shower Spray Toto TX403SV3P1V Bh 344,100.00 13.00 4,473,300.00 - - (5.00) (1,720,500.00) 8.00 2,752,800.00
7 Shower Head Toto TX435S Bh 600,000.00 14.00 8,400,000.00 2.000.00 1,200,000.00 0.00 0.00 16.00 9,600,000.00
8 Soap Holder S156N Bh 92,900.00 - - - - 0.00 0.00 0.00 0.00
9 Paper Holder TX720AW Bh 80,100.00 37.00 2,963,700.00 - - (22.00) (1,762,200.00) 15.00 1,201,500.00
10 Floor Drain Bh 139,250.00 14.00 1,949,500.00 51.000.00 7,101,750.00 0.00 0.00 65.00 9,051,250.00
11 Meja wastafel beton berlapis keramik M' 1,415,000.00 1.00 1,415,000.00 9.000.00 12,735,000.00 0.00 0.00 10.00 14,150,000.00
12 Duropal M2 450,000.00 20.00 9,000,000.00 13.300.00 5,985,000.00 0.00 0.00 33.30 14,985,000.00
13 Roof Drain Bh 0.00
2 Type P24
- Galian tanah M3 15,570.00 337.360 5,252,695.20 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan pasir t = 10 cm M3 80,250.00 22.820 1,831,305.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Lantai kerja t = 5 cm M2 29,876.00 239.410 7,152,613.16 #REF! #REF! #REF! #REF! #REF! #REF!
- Beton K.300 M3 926,435.00 261.740 242,485,096.90 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.19 Kg 13,150.00 34,922.000 459,224,300.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.13 Kg 13,150.00 3,332.000 43,815,800.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Bekisting M2 113,500.00 354.840 40,274,340.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan tanah kembali M3 11,172.00 38.100 425,653.20 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.13 Kg 13,150.00 650.000 8,547,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Type P6
- Galian tanah M3 15,570.00 6.000 93,420.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan pasir t = 10 cm M3 80,250.00 0.700 56,175.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Lantai kerja t = 5 cm M2 29,876.00 7.000 209,132.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Beton K.300 M3 926,435.00 4.310 3,992,934.85 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.19 Kg 13,150.00 416.000 5,470,400.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.13 Kg 13,150.00 105.000 1,380,750.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Bekisting M2 113,500.00 10.000 1,135,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan tanah kembali M3 11,172.00 1.160 12,959.52 #REF! #REF! #REF! #REF! #REF! #REF!
4 Type P4
- Galian tanah M3 15,570.00 23.360 363,715.20 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan pasir t = 10 cm M3 80,250.00 4.820 386,805.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Lantai kerja t = 5 cm M2 29,876.00 58.410 1,745,057.16 #REF! #REF! #REF! #REF! #REF! #REF!
- Beton K.300 M3 926,435.00 23.520 21,789,751.20 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.19 Kg 13,150.00 2,412.000 31,717,800.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Tulangan D.13 Kg 13,150.00 558.000 7,337,700.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Bekisting M2 113,500.00 67.840 7,699,840.00 #REF! #REF! #REF! #REF! #REF! #REF!
- Urugan tanah kembali M3 11,172.00 8.100 90,493.20 #REF! #REF! #REF! #REF! #REF! #REF!
D. PEKERJAAN STRUKTUR
1 Beton kolom K1, K2, K3 M3 926,435.00 99.810 92,467,477.35 #REF! #REF! #REF! #REF! #REF! #REF!
2 Besi kolom K1, K2, K3 Kg 13,150.00 26,625.000 350,118,750.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Bekisting kolom K1, K2, K3 (Plywood Film 12 mm) M2 150,000.00 815.640 122,346,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Beton balok M3 926,435.00 109.610 101,546,540.35 #REF! #REF! #REF! #REF! #REF! #REF!
5 Besi balok Kg 13,150.00 20,696.000 272,152,400.00 #REF! #REF! #REF! #REF! #REF! #REF!
6 Bekisting balok (Plywood Film 12 mm) M2 150,000.00 947.000 142,050,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
7 Beton plat M3 926,435.00 177.140 164,108,695.90 #REF! #REF! #REF! #REF! #REF! #REF!
8 Besi plat Kg 13,150.00 22,078.730 290,335,294.24 #REF! #REF! #REF! #REF! #REF! #REF!
9 Bekisting plat (Plywood Film 12 mm) M2 150,000.00 1,139.880 170,982,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
10 Beton tangga M3 926,435.00 120.000 111,172,200.00 #REF! #REF! #REF! #REF! #REF! #REF!
11 Besi tangga Kg 13,150.00 24,000.000 315,600,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
12 Bekisting tangga (Plywood Film 12 mm) M2 150,000.00 901.000 135,150,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
E. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 - - - - 0.00 0.00 0.00 0.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 453.600 28,318,248.00 - - 0.00 0.00 453.60 28,318,248.00
3 Pasangan dinding kerawang M2 117,295.00 20.000 2,345,900.00 - - 0.00 0.00 20.00 2,345,900.00
4 Pasangan dinding keramik M2 86,500.00 141.700 12,257,050.00 - - 0.00 0.00 141.70 12,257,050.00
5 Kolom dan balok praktis M' 59,780.00 37.800 2,259,684.00 - - 0.00 0.00 37.80 2,259,684.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 - - - - 0.00 0.00 0.00 0.00
7 Plesteran dinding 1 : 2 M2 30,836.00 - - - - 0.00 0.00 0.00 0.00
8 Plesteran dinding 1 : 5 M2 27,546.00 907.200 24,989,731.20 - - 0.00 0.00 907.20 24,989,731.20
9 Plesteran kolom beton M2 33,226.00 - - - - 0.00 0.00 0.00 0.00
F. PEKERJAAN LANTAI
1 Cor beton lantai dasar t = 10 cm + wiremesh M2 182,900.00 1,801.800 329,549,220.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Lantai keramik 30 x 30 cm M2 0.00 - - - - 0.00 0.00 0.00 0.00
3 Lantai border plester M2 0.00 - - - - 0.00 0.00 0.00 0.00
4 Plint keramik M' 0.00 - - - - 0.00 0.00 0.00 0.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 28.000 2,268,000.00 - - 0.00 0.00 28.00 2,268,000.00
6 Floor Hardener M2 0.00 - - - - 0.00 0.00 0.00 0.00
7 Lantai ubin PC M2 0.00 - - - - 0.00 0.00 0.00 0.00
8 Lantai paving blok t = 8 cm M2 0.00 - - - - 0.00 0.00 0.00 0.00
9 Keramik motif 30 x 30 cm M2 0.00 - - - - 0.00 0.00 0.00 0.00
G. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 - - - - 0.00 0.00 0.00 0.00
2 Plafond ekspose M2 33,226.00 - - - - 0.00 0.00 0.00 0.00
3 List plafond M' 18,800.00 - - - - 0.00 0.00 0.00 0.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 - - - - 0.00 0.00 0.00 0.00
I. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 14,492.50 - - - - 0.00 0.00 0.00 0.00
2 Cat plafond gypsum M2 17,367.50 - - - - 0.00 0.00 0.00 0.00
3 Cat plafond beton M2 26,620.00 - - - - 0.00 0.00 0.00 0.00
4 Cat listplank dan parapet M2 26,620.00 - - - - 0.00 0.00 0.00 0.00
5 Cat dinding kerawang Kw1 + Kw2 M2 26,620.00 - - - - 0.00 0.00 0.00 0.00
6 Cat kolom beton M2 26,620.00 - - - - 0.00 0.00 0.00 0.00
J. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 441,000.00 - - - - 0.00 0.00 0.00 0.00
2 Saluran air 30 x 50 cm M' 600,000.00 454.000 272,400,000.00 - - 0.00 0.00 454.00 272,400,000.00
3 Bak bunga Bh 1,780,800.00 - - - - 0.00 0.00 0.00 0.00
4 Bangunan kanopi M2 4,325,000.00 - - - - 0.00 0.00 0.00 0.00
5 Grill tutup saluran Bh 294,000.00 - - - - 0.00 0.00 0.00 0.00
6 Bak kontrol 60 x 60 cm M2 1,264,071.00 24.000 30,337,704.00 - - 0.00 0.00 24.00 30,337,704.00
K. PEKERJAAN TRIBUNE
1 Beton tribune M3 926,435.00 656.160 607,889,589.60 #REF! #REF! #REF! #REF! #REF! #REF!
2 Besi beton Kg 13,150.00 104,985.600 1,380,560,640.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Bekisting tribune (Plywood Film 12 mm) M2 150,000.00 4,564.350 684,652,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Waterproofing M2 120,000.00 2,872.990 344,758,800.00 - - 0.00 0.00 2,872.99 344,758,800.00
5 Plesteran M2 33,226.00 2,872.990 95,457,965.74 - - 0.00 0.00 2,872.99 95,457,965.74
6 Railing tribune M' 450,000.00 - - - - 0.00 0.00 0.00 0.00
L. PEKERJAAN SANITAIR
1 Closet jongkok Toto CE6 Bh 521,300.00 4.000 2,085,200.00 - - 0.00 0.00 4.00 2,085,200.00
2 Wastafel Toto L34 Bh 1,038,800.00 4.000 4,155,200.00 - - 0.00 0.00 4.00 4,155,200.00
3 Urinoir Toto U57M Bh 2,096,300.00 4.000 8,385,200.00 - - 0.00 0.00 4.00 8,385,200.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
4 Shower Spray Toto TX403SV3P1V Bh 344,100.00 - - - - 0.00 0.00 0.00 0.00
5 Floor Drain Bh 139,250.00 4.000 557,000.00 30.000 4,177,500.00 0.00 0.00 34.00 4,734,500.00
A.2 Lantai - 2
1 Instalasi Penerangan Kabel NYM 3 x 2,5 mm Titik 256,000.00 22.000 5,632,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Instalasi Stop Kontak Kabel NYM 3 x 2,5 mm Titik 256,000.00 8.000 2,048,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
3 Lampu Exit 10 W + Battery Bh 1,232,000.00 14.000 17,248,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Stop Kontak Bh 71,500.00 8.000 572,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Saklar Double Bh 55,750.00 8.000 446,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
6 TL 2 x 36 W Balk Bh 261,800.00 58.000 15,184,400.00 #REF! #REF! #REF! #REF! #REF! #REF!
7 Kabel Tray 400 M' 200,000.00 146.000 29,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
8 Material Bantu Ls 2,500,000.00 1.000 2,500,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
A.3 Lantai 3 - Tribune
1 Lampu HDK 250 W Bh 1,000,000.00 100.000 100,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Instalasi NYY 3 x 2,5 mm Titik 454,250.00 100.000 45,425,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
B.2 Lantai - 2
1 Instalasi Penerangan Kabel NYM 3 x 2,5 mm Titik 256,000.00 75.000 19,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Instalasi Stop Kontak Kabel NYM 3 x 2,5 mm Titik 256,000.00 5.000 1,280,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
3 Lampu Exit 10 W + Battery Bh 1,232,000.00 9.000 11,088,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Stop Kontak Bh 71,500.00 5.000 357,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Saklar Double Bh 55,750.00 6.000 334,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
6 Saklar Tunggal Bh 44,250.00 6.000 265,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
7 TL 2 x 36 W Balk Bh 261,800.00 38.000 9,948,400.00 #REF! #REF! #REF! #REF! #REF! #REF!
8 TL 2 x 36 W TKI Bh 280,500.00 5.000 1,402,500.00 #REF! #REF! #REF! #REF! #REF! #REF!
9 Baret TL-E 20 W Bh 176,000.00 12.000 2,112,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
10 Down Light SL 18 W Bh 156,200.00 11.000 1,718,200.00 #REF! #REF! #REF! #REF! #REF! #REF!
11 Kabel Tray 400 M' 200,000.00 234.000 46,800,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
12 Material Bantu Ls 3,000,000.00 1.000 3,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
2.7 TESTING COMMISIONING Ls 10,400,000.00 1.000 10,400,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
A.2 Lantai - 2
1 Rate of Rise Detector Bh 95,280.00 14.000 1,333,920.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Smoke Detector Bh 342,615.00 2.000 685,230.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Manual Push Button Bh 204,150.00 2.000 408,300.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Alarm Bell Bh 228,850.00 2.000 457,700.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Indicating Lamp Bh 49,920.00 2.000 99,840.00 #REF! #REF! #REF! #REF! #REF! #REF!
6 Titik Fire Alarm + Telephone Jack NYA 2x 1,5 mm Titik 240,000.00 22.000 5,280,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) PVC 20 mm
7 Terminal Box Fire Alarm (TB-FA) Bh 780,000.00 1.000 780,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
8 Material Bantu Ls 3,600,000.00 1.000 3,600,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
B.2 Lantai - 2
1 Rate of Rise Detector Bh 95,280.00 15.000 1,429,200.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Manual Push Button Bh 204,150.00 1.000 204,150.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Alarm Bell Bh 228,850.00 1.000 228,850.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Indicating Lamp Bh 49,920.00 1.000 49,920.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Titik Fire Alarm + Telephone Jack NYA 2x 1,5 mm Titik 240,000.00 18.000 4,320,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) PVC 20 mm
6 Terminal Box Fire Alarm (TB-FA) Bh 780,000.00 1.000 780,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
7 Material Bantu Ls 3,600,000.00 1.000 3,600,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
C.2 Lantai - 2
1 Rate of Rise Detector Bh 95,280.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
2 Manual Push Button Bh 204,150.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
3 Alarm Bell Bh 228,850.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
4 Indicating Lamp Bh 49,920.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
5 Titik Fire Alarm + Telephone Jack NYA 2x 1,5 mm Titik 240,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
(o) PVC 20 mm - #REF! #REF! #REF! #REF!
6 Terminal Box Fire Alarm (TB-FA) Bh 780,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
7 Material Bantu Ls 3,600,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
D.2 Lantai - 2
1 Rate of Rise Detector Bh 95,280.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
2 Manual Push Button Bh 204,150.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
3 Alarm Bell Bh 228,850.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
4 Indicating Lamp Bh 49,920.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
5 Titik Fire Alarm + Telephone Jack NYA 2x 1,5 mm Titik 240,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
(o) PVC 20 mm - #REF! #REF! #REF! #REF!
6 Terminal Box Fire Alarm (TB-FA) Bh 780,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
7 Material Bantu Ls 3,600,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
3.3 TESTING COMMISIONING Ls 5,100,000.00 1.000 5,100,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5.3 Material Bantu Ls 2,220,000.00 1.000 2,220,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5.4 TESTING COMMISIONING Ls 3,600,000.00 1.000 3,600,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
A.2 Lantai - 2
1 Instalasi Speaker dengan Kabel NYMHY 3 x 1,5 mm2 Titik 258,000.00 16.000 4,128,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Terminal Box Tata Suara Bh 660,000.00 1.000 660,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Ceiling Speaker 6 W Bh 115,200.00 7.000 806,400.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Horn Speaker 15 W Bh 444,000.00 9.000 3,996,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Volume Control Bh 232,800.00 14.000 3,259,200.00 #REF! #REF! #REF! #REF! #REF! #REF!
6 Material Bantu Ls 2,220,000.00 1.000 2,220,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
B.2 Lantai - 2
1 Instalasi Speaker dengan Kabel NYMHY 3 x 1,5 mm2 Titik 258,000.00 11.000 2,838,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Terminal Box Tata Suara Bh 660,000.00 1.000 660,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Ceiling Speaker 6 W Bh 115,200.00 11.000 1,267,200.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Volume Control Bh 232,800.00 2.000 465,600.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 2,220,000.00 1.000 2,220,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
C BLOK UTARA AS 77 s/d 93
C.1 Lantai - 1
1 Instalasi Speaker dengan Kabel NYMHY 3 x 1,5 mm2 Titik 264,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Terminal Box Tata Suara Bh 920,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
3 Ceiling Speaker 6 W Bh 160,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
4 Volume Control Bh 320,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 3,040,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
D.2 Lantai - 2
1 Instalasi Speaker dengan Kabel NYMHY 3 x 1,5 mm2 Titik 264,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
(o) Pipa PVC 20 mm
2 Ceiling Speaker 6 W Bh 160,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
3 Material Bantu Ls 3,040,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
6.4 TESTING COMMISIONING Ls 5,100,000.00 1.000 5,100,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
7.1.4 TESTING COMMISIONING Ls 1,200,000.00 1.000 1,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
E TESTING COMMISIONING Ls 1,200,000.00 1.000 1,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
A.2 Lantai - 2
1 Pipa BSP Sch. 40
a. dia. 2 1/2" M' 85,000.00 15.000 1,275,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Hydrant Box Bh 3,250,000.00 2.000 6,500,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Gate Valve dia. 2 1/2" Bh 1,600,000.00 2.000 3,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Fitting-fitting Ls 550,000.00 1.000 550,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 300,000.00 1.000 300,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
B BLOK BARAT AS 1 s/d 31
B.1 Lantai - 1
1 Indoor Hydrant Box C/W Valve-valve, Pipe Rack, Bh 2,400,000.00 2.000 4,800,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
House Rell & Accessories
2 Pipa BSP Sch. 40
a. dia. 4" M' 210,000.00 18.000 3,780,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
b. dia. 2 1/2" M' 85,000.00 8.000 680,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
c. dia. 1 1/2" M' 50,000.00 4.000 200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Gate Valve dia. 4" Bh 3,000,000.00 2.000 6,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Fitting-fitting Ls 550,000.00 1.000 550,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 1,000,000.00 1.000 1,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
B.2 Lantai - 2
1 Pipa BSP Sch. 40
a. dia. 2 1/2" M' 85,000.00 15.000 1,275,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
2 Hydrant Box Bh 3,250,000.00 2.000 6,500,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Gate Valve dia. 2 1/2" Bh 1,600,000.00 2.000 3,200,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Fitting-fitting Ls 550,000.00 1.000 550,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 300,000.00 1.000 300,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
8.3 TESTING COMMISIONING Ls 2,500,000.00 1.000 2,500,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
B.2 Lantai - 2
1 Pengadaan dan pemasangan unit pendingin (IU/OU-01) Unit 40,000,000.00 2.000 80,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
Kap. 40000 BTUH
Model :Cassete
Lengkap dengan accessories, support, hanger dan
pipa refrigerant alat pendukung dan berfungsi baik
2 Pipa Drain AC PVC + Isolasi Lot 1,000,000.00 1.000 1,000,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
3 Kabel Power NYM 3 x 2,5 mm (o) Pipa PVC 20 mm Lot 2,816,000.00 1.000 2,816,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
4 Ceiling Fan, Cap 100 CFM Unit 700,000.00 9.000 6,300,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
5 Material Bantu Ls 1,500,000.00 1.000 1,500,000.00 #REF! #REF! #REF! #REF! #REF! #REF!
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
NO. URAIAN PEKERJAAN SAT.
(Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.)
C BLOK UTARA AS 78 S/D 93
C.1 Lantai - 1
1 Pengadaan dan pemasangan unit pendingin (IU/OU-01) Unit 11,360,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
Kap. 7100 BTUH
Model : Wall Mounted
Lengkap dengan accessories, support, hanger dan
pipa refrigerant alat pendukung dan berfungsi baik
2 Pengadaan dan pemasangan unit pendingin (IU/OU-01) Unit 12,376,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
Kap. 12000 BTUH
Model : Wall Mounted
Lengkap dengan accessories, support, hanger dan
pipa refrigerant alat pendukung dan berfungsi baik
3 Pipa Drain AC PVC + Isolasi Lot 1,200,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
4 Kabel Power NYM 3 x 2,5 mm (o) Pipa PVC 20 mm Lot 560,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
5 Ceiling Fan, Cap 100 CFM Unit 2,800,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
6 Material Bantu Ls 2,000,000.00 - - #REF! #REF! #REF! #REF! #REF! #REF!
DENNY ALFIAN NOORSANDHY , ST. Ir. WAGINO HARYS Ir. ANIS J. RAHMAN, MM
NIP. 550 015 296 TEAM LEADER SITE MANAGER
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
13
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
-
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
TECHNICAL
JUSTIFICATION
(ALASAN TEKNIS)
KONTRAKTOR PELAKSANA
PT. LUHRIBU NAGA JAYA
E. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 975.000 62,526,750.00 - 0.00 975.00 62,526,750.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 3,600.000 224,748,000.00 - 0.00 3,600.00 224,748,000.00
3 Pasangan dinding kerawang M2 117,295.00 230.000 26,977,850.00 - 0.00 230.00 26,977,850.00
4 Pasangan dinding keramik M2 86,500.00 1,503.000 130,009,500.00 - 0.00 1,503.00 130,009,500.00
5 Kolom dan balok praktis M' 59,780.00 3,660.000 218,794,800.00 - 0.00 3,660.00 218,794,800.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 51.200 10,221,363.20 - (22.40) (4,471,846.40) 28.80 5,749,516.80
7 Plesteran dinding 1 : 2 M2 30,836.00 1,950.000 60,130,200.00 - 0.00 1,950.00 60,130,200.00
8 Plesteran dinding 1 : 5 M2 27,546.00 7,200.000 198,331,200.00 - 0.00 7,200.00 198,331,200.00
9 Plesteran kolom beton M2 33,226.00 1,700.000 56,484,200.00 - 0.00 1,700.00 56,484,200.00
F. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 88,810.00 3,446.000 306,039,260.00 - 0.00 3,446.00 306,039,260.00
3 Lantai border plester M2 30,836.00 257.000 7,924,852.00 - 0.00 257.00 7,924,852.00
4 Plint keramik M' 32,780.00 1,520.000 49,825,600.00 - 0.00 1,520.00 49,825,600.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 607.000 49,167,000.00 - 0.00 607.00 49,167,000.00
6 Floor hardener M' 150,000.00 305.000 45,750,000.00 - 0.00 305.00 45,750,000.00
7 Lantai ubin PC M2 57,800.00 5.000 289,000.00 - (5.00) (289,000.00) 0.00 0.00
8 Lantai paving blok t = 8 cm M2 181,600.00 174.000 31,598,400.00 - (84.40) (15,327,040.00) 89.60 16,271,360.00
9 Keramik motif 30 x 30 cm M2 103,860.00 32.000 3,323,520.00 - 0.00 32.00 3,323,520.00
G. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 530.000 52,684,650.00 - 0.00 530.00 52,684,650.00
2 Plafond ekspose M2 33,226.00 7,336.000 243,745,936.00 - 0.00 7,336.00 243,745,936.00
3 List plafond M' 18,800.00 510.000 9,588,000.00 - 0.00 510.00 9,588,000.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 255.000 26,775,000.00 - 0.00 255.00 26,775,000.00
I. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 16,492.50 7,850.000 129,466,125.00 - 0.00 7,850.00 129,466,125.00
2 Cat plafond gypsum M2 17,367.50 530.000 9,204,775.00 - 0.00 530.00 9,204,775.00
3 Cat plafond beton M2 28,620.00 7,336.000 209,956,320.00 - 0.00 7,336.00 209,956,320.00
4 Cat listplank dan parapet M2 28,620.00 730.000 20,892,600.00 - 0.00 730.00 20,892,600.00
5 Cat dinding kerawang M2 28,620.00 460.000 13,165,200.00 - 0.00 460.00 13,165,200.00
6 Cat kolom beton M2 28,620.00 1,700.000 48,654,000.00 - 0.00 1,700.00 48,654,000.00
J. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 450,000.00 167.000 75,150,000.00 - 0.00 167.00 75,150,000.00
2 Saluran air 30 x 50 cm M' 600,000.00 144.000 86,400,000.00 - 0.00 144.00 86,400,000.00
3 Bak bunga Bh 1,780,800.00 2.000 3,561,600.00 - 0.00 2.00 3,561,600.00
4 Bangunan kanopi M2 4,325,000.00 132.000 570,900,000.00 - 0.00 132.00 570,900,000.00
5 Grill tutup saluran M' 294,000.00 22.000 6,468,000.00 - 0.00 22.00 6,468,000.00
6 Bak kontrol 60 x 60 cm Bh 1,264,071.00 10.000 12,640,710.00 - 0.00 10.00 12,640,710.00
K. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 4,068.000 488,160,000.00 - 0.00 4,068.00 488,160,000.00
5 Plesteran M2 33,226.00 4,068.000 135,163,368.00 - 0.00 4,068.00 135,163,368.00
6 Railing tribune M' 450,000.00 174.000 78,300,000.00 - 0.00 174.00 78,300,000.00
L. PEKERJAAN SANITAIR
1 Closet duduk Toto CWY20J/S516STD Bh 2,250,000.00 73.000 164,250,000.00 - (47.00) (105,750,000.00) 26.00 58,500,000.00
2 Closet jongkok Toto CE6 Bh 521,300.00 37.000 19,288,100.00 - (1.00) (521,300.00) 36.00 18,766,800.00
3 Wastafel Toto L34 Bh 1,038,800.00 24.000 24,931,200.00 10.00 10,388,000.00 0.00 34.00 35,319,200.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
4 Wastafel Toto L521 V1A Bh 1,779,600.00 20.000 35,592,000.00 - (8.00) (14,236,800.00) 12.00 21,355,200.00
5 Urinoir Toto U57M Bh 2,096,300.00 46.000 96,429,800.00 - 0.00 46.00 96,429,800.00
6 Shower Spray TotoTX403SV3P1V Bh 344,100.00 21.000 7,226,100.00 5.00 1,720,500.00 0.00 26.00 8,946,600.00
7 Shower Head Toto TX435S Bh 600,000.00 15.000 9,000,000.00 - (2.00) (1,200,000.00) 13.00 7,800,000.00
8 Soap Holder S156N Bh 92,900.00 15.000 1,393,500.00 - (2.00) (185,800.00) 13.00 1,207,700.00
9 Paper Holder TX720AW Bh 80,100.00 21.000 1,682,100.00 5.00 400,500.00 0.00 26.00 2,082,600.00
10 Floor Drain Bh 139,250.00 76.000 10,583,000.00 58.00 8,076,500.00 0.00 134.00 18,659,500.00
11 Meja wastafel beton berlapis keramik M' 1,415,000.00 21.000 29,715,000.00 - (3.60) (5,094,000.00) 17.40 24,621,000.00
12 Kran Air 0,5" Bh 75,000.00 39.00 2,925,000.00 0.00 39.00 2,925,000.00
M. PEKERJAAN ATAP
4 Pipa talang M' 138,820.00 372.000 51,641,040.00 - 0.00 372.00 51,641,040.00
5 Roof Drain Bh 296,250.00 31.000 9,183,750.00 - 0.00 31.00 9,183,750.00
C. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 522.00 33,475,860.00 - 0.00 522.00 33,475,860.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 2,090.00 130,478,700.00 - 0.00 2,090.00 130,478,700.00
3 Pasangan dinding kerawang M2 117,295.00 240.00 28,150,800.00 - 0.00 240.00 28,150,800.00
4 Pasangan dinding keramik M2 86,500.00 600.00 51,900,000.00 - 0.00 600.00 51,900,000.00
5 Kolom dan balok praktis M' 59,780.00 2,218.00 132,592,040.00 - 0.00 2,218.00 132,592,040.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 51.20 10,221,363.20 - 0.00 51.20 10,221,363.20
7 Plesteran dinding 1 : 2 M2 30,836.00 1,044.00 32,192,784.00 - 0.00 1,044.00 32,192,784.00
8 Plesteran dinding 1 : 5 M2 27,546.00 4,180.00 115,142,280.00 - 0.00 4,180.00 115,142,280.00
9 Plesteran kolom beton M2 33,226.00 765.00 25,417,890.00 - 0.00 765.00 25,417,890.00
D. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 88,810.00 2,710.00 240,675,100.00 - 0.00 2,710.00 240,675,100.00
3 Lantai border plester M2 30,836.00 181.00 5,581,316.00 - 0.00 181.00 5,581,316.00
4 Plint keramik M' 32,780.00 1,100.00 36,058,000.00 - 0.00 1,100.00 36,058,000.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 166.00 13,446,000.00 - 0.00 166.00 13,446,000.00
G. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 16,492.50 5,220.00 86,090,850.00 - 0.00 5,220.00 86,090,850.00
2 Cat plafond gypsum M2 17,367.50 661.00 11,479,917.50 - 0.00 661.00 11,479,917.50
3 Cat plafond beton M2 28,620.00 3,530.00 101,028,600.00 - 0.00 3,530.00 101,028,600.00
4 Cat listplank dan parapet M2 28,620.00 730.00 20,892,600.00 - 0.00 730.00 20,892,600.00
5 Cat dinding kerawang Kw1 + Kw2 M2 28,620.00 480.00 13,737,600.00 - 0.00 480.00 13,737,600.00
H. PEKERJAAN LAIN-LAIN
1 Railing tangga M' 450,000.00 145.00 65,250,000.00 - 0.00 145.00 65,250,000.00
2 Saluran air 30 x 50 cm M' 600,000.00 138.00 82,800,000.00 - 0.00 138.00 82,800,000.00
3 Bak kontrol Bh 1,264,071.00 10.00 12,640,710.00 - 0.00 10.00 12,640,710.00
4 Trap As 62-63 / A M2 150,000.00 6.00 900,000.00 - 0.00 6.00 900,000.00
I. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 3,650.00 438,000,000.00 - 0.00 3,650.00 438,000,000.00
5 Plesteran M2 33,226.00 3,650.00 121,274,900.00 - (3.32) (110,443.22) 3,646.68 121,164,456.78
6 Railing tribune M' 450,000.00 174.00 78,300,000.00 - 0.00 174.00 78,300,000.00
J. PEKERJAAN SANITAIR
1 Closet duduk Toto CWY20J/S516STD Bh 2,250,000.00 13.00 29,250,000.00 - (5.00) (11,250,000.00) 8.00 18,000,000.00
2 Closet jongkok Toto CE6 Bh 521,300.00 6.00 3,127,800.00 9.00 4,691,700.00 0.00 15.00 7,819,500.00
3 Wastafel Toto L34 Bh 1,038,800.00 10.00 10,388,000.00 1.00 1,038,800.00 0.00 11.00 11,426,800.00
4 Wastafel Toto L521 V1A Bh 1,779,600.00 4.00 7,118,400.00 1.00 1,779,600.00 0.00 5.00 8,898,000.00
5 Urinoir Toto U57M Bh 2,096,300.00 11.00 23,059,300.00 5.00 10,481,500.00 0.00 16.00 33,540,800.00
6 Shower Spray Toto TX403SV3P1V Bh 344,100.00 13.00 4,473,300.00 - (5.00) (1,720,500.00) 8.00 2,752,800.00
7 Shower Head Toto TX435S Bh 600,000.00 14.00 8,400,000.00 2.00 1,200,000.00 0.00 16.00 9,600,000.00
8 Soap Holder S156N Bh 92,900.00 - - - 0.00 0.00 0.00
9 Paper Holder TX720AW Bh 80,100.00 37.00 2,963,700.00 - (22.00) (1,762,200.00) 15.00 1,201,500.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
10 Floor Drain Bh 139,250.00 14.00 1,949,500.00 51.00 7,101,750.00 0.00 65.00 9,051,250.00
11 Meja wastafel beton berlapis keramik M' 1,415,000.00 1.00 1,415,000.00 9.00 12,735,000.00 0.00 10.00 14,150,000.00
12 Duropal M2 450,000.00 20.00 9,000,000.00 13.30 5,985,000.00 0.00 33.30 14,985,000.00
E. PEKERJAAN DINDING
1 Pasangan dinding bata 1 : 2 M2 64,130.00 - - - 0.00 0.00 0.00
2 Pasangan dinding bata 1 : 5 M2 62,430.00 453.600 28,318,248.00 - 0.00 453.60 28,318,248.00
3 Pasangan dinding kerawang M2 117,295.00 20.000 2,345,900.00 - 0.00 20.00 2,345,900.00
4 Pasangan dinding keramik M2 86,500.00 141.700 12,257,050.00 - 0.00 141.70 12,257,050.00
5 Kolom dan balok praktis M' 59,780.00 37.800 2,259,684.00 - 0.00 37.80 2,259,684.00
6 Dinding batu alam pada kolom kanopi M2 199,636.00 - - - 0.00 0.00 0.00
7 Plesteran dinding 1 : 2 M2 30,836.00 - - - 0 0.00 0.00
8 Plesteran dinding 1 : 5 M2 27,546.00 907.200 24,989,731.20 - 0.00 907.20 24,989,731.20
9 Plesteran kolom beton M2 33,226.00 - - - 0.00 0.00 0.00
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
F. PEKERJAAN LANTAI
2 Lantai keramik 30 x 30 cm M2 0.00 - - - 0.00 0.00 0.00
3 Lantai border plester M2 0.00 - - - 0.00 0.00 0.00
4 Plint keramik M' 0.00 - - - 0.00 0.00 0.00
5 Lantai keramik 20 x 20 cm M2 81,000.00 28.000 2,268,000.00 - 0.00 28.00 2,268,000.00
6 Floor Hardener M2 0.00 - - - 0.00 0.00 0.00
7 Lantai ubin PC M2 0.00 - - - 0.00 0.00 0.00
8 Lantai paving blok t = 8 cm M2 0.00 - - - 0.00 0.00 0.00
9 Keramik motif 30 x 30 cm M2 0.00 - - - 0.00 0.00 0.00
G. PEKERJAAN PLAFOND
1 Plafond gypsum board t = 9 mm M2 99,405.00 - - - 0.00 0.00 0.00
2 Plafond ekspose M2 33,226.00 - - - 0.00 0.00 0.00
3 List plafond M' 18,800.00 - - - 0.00 0.00 0.00
4 Plafond gypsum tile 60 x 120 cm M2 105,000.00 - - - 0.00 0.00 0.00
I. PEKERJAAN PENGECATAN
1 Cat dinding tembok M2 14,492.50 - - - 0.00 0.00 0.00
2 Cat plafond gypsum M2 17,367.50 - - - 0.00 0.00 0.00
3 Cat plafond beton M2 26,620.00 - - - 0.00 0.00 0.00
4 Cat listplank dan parapet M2 26,620.00 - - - 0.00 0.00 0.00
5 Cat dinding kerawang Kw1 + Kw2 M2 26,620.00 - - - 0.00 0.00 0.00
6 Cat kolom beton M2 26,620.00 - - - 0.00 0.00 0.00
J. PEKERJAAN LAIN-LAIN
PERUBAHAN
HARGA SATUAN KONTRAK AWAL/ASLI PEKERJAAN TAMBAH PEKERJAAN KURANG CONTRACT CHANGE ORDER
TECHNICAL
NO. URAIAN PEKERJAAN SAT.
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUSTIFICATION
(Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) VOLUME (Rp.) (ALASAN TEKNIS)
1 Railing tangga M' 441,000.00 - - - 0.00 0.00 0.00
2 Saluran air 30 x 50 cm M' 600,000.00 454.000 272,400,000.00 - 0.00 454.00 272,400,000.00
3 Bak bunga Bh 1,780,800.00 - - - 0.00 0.00 0.00
4 Bangunan kanopi M2 4,325,000.00 - - - 0.00 0.00 0.00
5 Grill tutup saluran Bh 294,000.00 - - - 0.00 0.00 0.00
6 Bak kontrol 60 x 60 cm M2 1,264,071.00 24.000 30,337,704.00 - 0.00 24.00 30,337,704.00
K. PEKERJAAN TRIBUNE
4 Waterproofing M2 120,000.00 2,872.990 344,758,800.00 - 0.00 2,872.99 344,758,800.00
5 Plesteran M2 33,226.00 2,872.990 95,457,965.74 - 0.00 2,872.99 95,457,965.74
6 Railing tribune M' 450,000.00 - - - 0.00 0.00 0.00
L. PEKERJAAN SANITAIR
1 Closet jongkok Toto CE6 Bh 521,300.00 4.000 2,085,200.00 - 0.00 4.00 2,085,200.00
2 Wastafel Toto L34 Bh 1,038,800.00 4.000 4,155,200.00 - 0.00 4.00 4,155,200.00
3 Urinoir Toto U57M Bh 2,096,300.00 4.000 8,385,200.00 - 0.00 4.00 8,385,200.00
4 Shower Spray Toto TX403SV3P1V Bh 344,100.00 - - - 0.00 0.00 0.00
5 Floor Drain Bh 139,250.00 4.000 557,000.00 30.00 4,177,500.00 0.00 34.00 4,734,500.00
DENNY ALFIAN NOORSANDHY , ST. Ir. WAGINO HARYS Ir. ANIS J. RAHMAN, MM
NIP. 550 015 296 TEAM LEADER SITE MANAGER
BACKUP SAND BAG
PANJANG
130 M'
TINGGI RATA-RATA
1.5