A PEKERJAAN PERSIAPAN
1 Direksi Kit, Bedeng Tukang dan Gudang ls 1.00 2,000,000 - 2,000,000 2,000,000 - 2,000,000
2 Peralatan Kerja dan Alat bantu Lain ls 1.00 2,000,000 - 2,000,000 2,000,000 - 2,000,000
3 Listrik Kerja bl 6.00 500,000 - 500,000 3,000,000 - 3,000,000
4 Air Kerja bl 6.00 100,000 - 100,000 600,000 - 600,000
5 Keamanan bl 6.00 500,000 - 500,000 3,000,000 - 3,000,000
6 Desain Gambar Gudang Workshop 40 x 15m m2 600.00 15,000 - 15,000 9,000,000 - 9,000,000
Total - - -
B PEKERJAAN STRUKTUR TOTAL PEKERJAAN STRUKTUR 247,377,980 118,803,413 366,181,393
C PEKERJAAN ARSITEKTUR
C.I PEKERJAAN LANTAI
1 Pek. Cor Lantai m3 93.67
Tinggi 150 mm + Besi Wermesh M6 + Begisting
Pembesian Besi Wermesh M6 m2 652.48 55,956 22,252 78,208 36,510,314 14,518,920 51,029,234
Bekisting m2 59.04 58,990 47,220 106,210 3,482,770 2,787,869 6,270,638
Cor Beton K-350 m3 93.67 1,474,000 516,750 1,990,750 138,072,528 48,405,006 186,477,534