KECAMATAN DOLOK
KABUPATEN PADANG LAWAS UTARA
1. BAHAN
1.1 Batu Koral/Kali 230,00 M³ 250.000 57.500.000
1.2 Semen @40 Kg 1.338,00 Zak 65.000 86.970.000
1.3 Pasir Pasang 124,00 M³ 200.000 24.800.000
1.3 Kayu Sembarang 3/4 6,00 Btg 45.000 270.000
Sub Total 1) 169.540.000
2. ALAT
2.1 Kereta Sorong 1,00 Bh 600.000 600.000
2.2 Cangkul 2,00 Bh 100.000 200.000
2.3 Sekop 2,00 Bh 100.000 200.000
2.4 Ember Cor 23,00 Bh 10.000 230.000
2.5 Benang 2,00 Glg 15.000 30.000
Sub Total 2) 1.260.000
3. UPAH
3.1 Pekerja 962,00 HOK 75.000 72.150.000
3.2 Tukang 481,00 HOK 85.000 40.885.000
Upah
Tukang = 0,750 x 191,25 = 143,44 ≈ 143 HOK
Pekerja = 1,500 x 191,25 = 286,88 ≈ 287 HOK
0.50 m
4. PEKERJAAN PLESTERAN SALURAN DRAINASE
Plesteran Saluran Drainase = 750,00 m'
0.10m Luas = 0,20 + 0,50 + 0,40 + 0,50 + 0,20 x 750,00
= 1350 m2
Volume 1 sisi jalan = 1350,0 x 1,00 = 1350,00 m3
0.20 m 0.4 0.20 m SNI 2016 A.4.4.2.3. untuk 1 m2 Plesteran tebal 15 mm Camp. 1 : 3
m Bahan
0.9 m Pasir Pasangan = 0,0230 x 1350,00 = 31,05 ≈ 31 m3
Semen PC @ 40 Kg = 0,1944 x 1350,00 = 262,44 ≈ 262 Zak
Upah
Tukang = 0,15 x 1350,00 = 202,50 ≈ 203 HOK
Pekerja = 0,30 x 1350,00 = 405,00 ≈ 405 HOK
Harga Sampai
No Jenis Material / Bahan Satuan Keterangan
dilokasi
1 Batu Kali / Belah M3 250.000
3 Cangkul Bh 100.000
6 Sekop Bh 100.000
KABUPATEN
0,60 m
PADANG LAWAS UTARA
KECAMATAN
0,8 m DOLOK
DESA
0.2 m SIMAMBAL
0.2 m
0,50 m LOKASI
JUDUL GAMBAR
DENAH
0.2 m 0.40 m
0.2 m
( Pihot Pohsn )
Diketahui Oleh :
Kepala Desa