Rincian Pendanaan :
HARGA
NO. U R A I A N VOLUME JUMLAH (Rp)
SATUAN (Rp)
1 2 3 4 5
I. BAHAN (harga hanya contoh)
1. Semen ( 50 Kg ) 216.00 Zak 100,000.00 21,600,000.00
2. Pasir Beton 24.00 M3 200,000.00 4,800,000.00
3. Pasir Urug 9.00 M 3
150,000.00 1,350,000.00
4. Batu pecah 2/3 (maks. 30 mm) 30.00 M3 350,000.00 10,500,000.00
5. Papan Mal uk. 2/18 cm-4m 101.00 Kpg 30,000.00 3,030,000.00
6. Kayu 4/6 101.00 Btg 25,000.00 2,525,000.00
7. Wiremesh M5 (2,1 m x 5,4 m) 19.00 Lbr 250,000.00 4,750,000.00
8. Paku Campur 28.00 Kg 25,000.00 700,000.00
9. Plastik untuk Alas Cor Beton 220.00 M2 5,000.00 1,100,000.00
J U M L A H (Rp.) 71,445,000.00
I Pekerjaan Persiapan
1. Pembersihan Lapangan dan Perataan M2 100.00 x 0.90 x x = 90.00 SNI - 8.11
- Pekerja HOK 0.100 9.00
- Mandor HOK 0.050 4.50
2. Pengukuran dan Pematokan M1 0.00
2. Bekisting M2 100.00 x 0.70 x 4.00 = 280.00 SNI DT-91 0008-2007 poin 6.20 (a)
- Pekerja HOK 0.130 36.40
- Tukang HOK 0.065 18.20
- Kepala Tukang HOK 0.013 3.64
- Mandor HOK 0.013 3.64
- Papan Mal uk. 2/18 cm-4m Kpg 0.360 100.80
- Paku Campuran Kg 0.100 28.00
4. Cor Beton f'c = 9,8 MPa (K-125) M3 = 39.00 SNI 7394-2008 (3.2)
Dengan menggunakan molen
- Pekerja HOK 1.320 51.48
- Tukang Batu HOK 0.205 8.00
- Kepala Tukang HOK 0.020 0.78
- Mandor HOK 0.060 2.34
- Semen ( 50 Kg ) Zak 5.52 215.28
- Pasir Beton M3 0.591 23.05
- Batu pecah 2/3 (maks. 30 mm) M3 0.750 29.25
- Wiremesh M5 (2,1 m x 5,4 m) Lbr 0.100 19.00
- Sewa Molen (Concrete Mixer) Hari 0.200 7.80
A. BAHAN
1. Semen ( 50 Kg ) Zak 215.28 216.00
2. Pasir Beton M3 23.05 24.00
3. Pasir Urug M 3
8.40 9.00
4. Batu pecah 2/3 (maks. 30 mm) M3 29.25 30.00
5 Papan Mal uk. 2/18 cm-4m Kpg 100.80 101.00
6 Kayu 4/6 Btg 100.80 101.00
7 Wiremesh M5 (2,1 m x 5,4 m) Lbr 19.00 19.00
8 Paku Campur Kg 28.00 28.00
9 Plastik untuk Alas Cor Beton M2 220.00 220.00
B. ALAT
1. Sewa Molen (Concrete Mixer) Hari 7.80 8.00
C. UPAH
1. Pekerja HOK 143.98 144.00
2. Tukang HOK 26.20 27.00
3. Kepala Tukang HOK 4.42 5.00
4. Mandor HOK 12.05 13.00