Anda di halaman 1dari 11

DOKUMEN DESAIN DAN RAB

Jalan Rabat Beton

PROVINSI : JAWA BARAT


KABUPATEN : BOGOR
KECAMATAN : CARINGIN
DESA : PASIRBUNCIR
Kabupaten : Bogor Jenis Prasarana : Jalan Rabat Beton
Kecamatan : Caringin Take Of Sheet
Desa : Pasirbuncir Volume : 1200 X 1 x 0.15 m

Bahu Jalan Sirtu 15 cm Rabat Beton Tebal 15 cm

0.25 m 1.00 m 0.25 m

Perhirtungan Volume Bahan

1. Volume Beton

0.15 m

1.00 m
V= 0.15 X 1.00 X 1200 = 180.00 M3

2. Volume Pekerjaan Timbunan Tanah

0.20 m V= ( 0.2 X 0.25 ) X 1200 X 2.0 = 60.00 M3


2
0.25 m V= Volume Timbunan = 60 = 80.00 HOK
Faktor Produktifitas 0.75

3. Volume Pekerjaan Sirtu


0.15 m

1.00 m
V= 0.10 X 1.00 X 1200 = 120.00 M3

ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK BETON CAMPURAN K250 D-07

I. Bahan
1. Pasir Beton = 0.5221 X 180.00 = 93.98 M3 Dibulatkan 94.00 M3
2. Split pecah mesin 2/3 = 0.74786 X 180.00 = 134.61 M3 Dibulatkan 135.00 M3
3. Semen PC (50 Kg) = 7.6800 X 180.00 = 1382.40 Zak Dibulatkan 1383.00 Zak
4. Sirtu = 1.2000 X 120.00 = 144.00 M3 Dibulatkan 144.00 M3
II Upah
1. Pekerja = 1.6500 X 180.00 = 297 x 1.00 = 297 Dibulatkan 297 HOK
2. Tukang = 0.2800 X 180.00 = 50.4 x 1.00 = 50.4 Dibulatkan 50 HOK

2 Upah Timbunan
1. Pekerja = 80.00 HOK Dibulatkan 80.00 HOK

3 Upah Hamparan Pasir Urug Kemampuan kerja penghamparan 2 m3


1. Pekerja = 120.00 / 2 = 60 HOK dibulatkan 60 HOK

Tanggal Survey : Dibuat Oleh :

KUSNADI
Kabupaten Bogor Jenis Prasarana : Jalan Rabat Beton
Kecamatan : Caringin Take Of Sheet 0
Desa : Pasirbuncir Volume : 1200 X 1 x 0.15 m

Perhitungan Papan Begisting

Panjang Rabat = 1200 m


5 m
a
b 1

1200

Va = Panjang Rabat x 2 Sisi x Tinggi


Va = (( 1200 x 2 ) x 0.15 ) = 360.00 m2
Vb = Lebar x Tinggi x Jumlah Dilatasi
Vb = 1 x 0.15 x( 1,200 ) + 1
5
Vb = 1 x 0.15 x 241.00 = 36.15 m 2
V Total = 360.00 + 36.15 = 396.15 m
Untuk papan begisting panjang = 2 x pakai
V = 396.15 / 2 = 198.08 m

Analisa Bekisting dengan Papan 2 x Pakai ( 50% )

I. Bahan
1. Kaso 5/7 2 x pakai = 0.0170 X 198.08 = 3.37 M3 Dibulatkan 4.00 M3
2.Papan Terentang = 0.0100 X 198.08 = 1.98 M3 Dibulatkan 2.00 M3
3 Paku 5 cm = 0.2000 X 198.08 = 39.62 Kg Dibulatkan 40.00 Kg

II Upah
1. Pekerja = 0.1200 X 198.08 = 23.769 HOK Dibulatkan 24 HOK
2. Tukang = 0.1500 X 198.08 = 29.71125 HOK Dibulatkan 30 HOK

Sewa Mesin gilas = 2,850 / 150 = 19 hari

Kebutuhan Mesin Molen

Kemampuan produktifitas mesin = 0.25 m3 / 20 menit


0.75 m3 / 1 Jam
6 m3 / 1 hari

Jadi Kebutuhan Mesin Molen = V beton / 6

= 180.00 / 6 = 30 Dibulatkan 30 hari

Dibuat Oleh TPK

KUSNADI
Propinsi Jawa Barat Jenis Prasarana : Tembok Penahan Tanah
Kabupaten : Bogor Lokasi
Kecamatan : Caringin Take Of Sheet Volume : x x m
Desa : Pasirbuncir

PERHITUNGAN VOLUME GALIAN , PASANGAN BATU KALI DAN PLESTERAN

Panjang 0.0 M Kiri


Plesteran tebal 1,5 cm
0.25 Perhitungan Volume Galian
0.40 X 0.70 X 0.0 X 1.00 = 0.00 m3

V.1 Perhitungan Volume Pasangan Batu Kali


1.60
Adukan camp V.1 : ( 0.25 + 0.70 )X 1.60 X 0.0 X 1.00 = - m3
1:5
2
V.2 : 0.40 X 0.70 X 0.0 X 1.00 = - m3
Vol 1 + 2 : = - + - = - m3
0.40 V.2
Perhitungan Volume Plesteran
0.05 ( 0.35 X 0.0 ) X 1.00 = 0.00 m2
0.70 Perhitungan Volume Pasir urug
0.05 X 0.70 X 0.0 X 1.00 = 0.00 m3
PERHITUNGAN ANALISA KEBUTUHAN BAHAN DAN UPAH
PEKERJAAN GALIAN
I. UPAH
1. Pekerja = 0.750 X 1.00 X 0.00 = 0.00 HOK B-01

PASANGAN BATU KALI CAMPURAN ( 1 : 5 )


I. BAHAN
1. Batu Belah = 1.200 X - = 0.00 M3
2.Pasir pasang = 0.544 X - = 0.00 M3
3.Semen Pc 50 kg = 2.720 X - = 0.00 Zak

II. UPAH
1. Pekerja = 1.500 X 0.75 X - = - HOK
2. Tukang = 0.750 X 0.75 X - = - HOK

PLESTERAN TEBAL 1.5 CM ( 1 :4 ) + Acian


I. BAHAN
1. Pasir Pasang = 0.0240 X 0.0 = 0.00 M3 F-024
2. Semen Pc 50 kg = 0.1248 X 0.0 = 0.00 Zak

II. UPAH
1. Pekerja = 0.300 X 1.00 X 0.0 = 0.00 HOK
2.Tukang = 0.150 X 1.00 X 0.0 = 0.00 HOK

TOTAL KEBUTUHAN BAHAN DAN UPAH

I. BAHAN
1. Batu Belah = 0.00 M3 Dibulatkan 0
2.Pasir pasang = 0.00 + 0.00 = 0.00 M3 Dibulatkan 0
3.Semen Pc 50 kg = 0.00 + 0.00 = 0.00 Zak Dibulatkan 0
4. Pasir Urug = 0.00 0.00 M3 Dibulatkan 0
5. Bambu = 10 10 Btg Dibulatkan 10

II. UPAH
1. Pekerja = - + - + 0.00 = - HOK 0
2.Tukang = - + 0.00 = - HOK 0

Dibuat Oleh;

SUPRIATNA
RENCANA ANGGARAN BIAYA (RAB) PERUBAHAN

Provinsi : Jawa Barat Lokasi : Kp. Baru RW.004


Kabupaten : Bogor Jenis Kegiatan : Betonisasi Jalan dan
Kecamatan : Caringin Bangunan Pelengkap
Desa : Cimande Hilir Ukuran : 800 x 3 x 0,2
Volume Sumber Dana
Kode Harga Satuan
No URAIAN Dari Satuan
Dari Kategori Swadaya APBD
Total Swaday
APBD (Rp) (Rp) (Rp)
a
a b c=d+e d e f g h i=dxh j=exh
I. BETONISASI

1 BAHAN
1 Batu Split 2/3 135.0 - 135.0 M3 290,000 - 39,150,000
2 Pasir Beton 94.0 - 94.0 M3 300,000 - 28,200,000
3 Sirtu 144.0 - 144.0 m3 230,000 - 33,120,000
4 Semen Pc 50 kg 1383.0 - 1383.0 Zak 70,000 - 96,810,000
5 Kaso 5/7 4.0 4.0 m3 1,100,000 - 4,400,000
6 Papan Terentang 2.0 2.0 m3 1,200,000 - 2,400,000
7 Paku 5 cm 40.0 40.0 kg 15,000 - 600,000
10 Plastik 65.0 - 65.0 Kg 25,000 - 1,625,000

Sub Total I) - 206,305,000


2 UPAH
1 Pekerja 486.00 486 hok 100,000 48,600,000
2 Tukang 105.00 105 hok 120,000 12,600,000
3 Mandor hok -

Sub Total II)


TOTAL BIAYA BETONISASI JALAN

B. BANGUNAN PELENGKAP

B.1 TPT Jalan Desa

I BAHAN
1 1. Batu Belah 0.0 - 0.0 m3 270,000 - -
2 2.Pasir pasang 0.0 - 0.0 m3 250,000 - -
3 3.Semen Pc 50 kg 0.0 - 0.0 Zak 70,000 - -
4 Pasir Urug 0.0 - 0.0 m3 220,000 - -
5 Bambu 10.0 10.0 Btg 20,000 - 200,000

Sub Total I) - 200,000


III UPAH
1 Pekerja 0.00 0 hok 100,000 -
2 Tukang 0.00 0 hok 120,000 -
3 Mandor hok -

Sub Total II)


TOTAL BIAYA TPT

B ALAT
1 Solar Molen 104.00 104.00 liter 8,000 - 832,000
2 Molen 30.00 30.00 Hri 500,000 - 15,000,000
3 Mobilisasi dan Demobilisasi 1.00 1.00 Ls 10,000,000 - 10,000,000
6 Ember 31.00 31.00 bh 10,000 310,000
7 Benang 20.00 20.00 bh 5,000 100,000
8 Selang 300.00 300.00 m 7,500 2,250,000
9 Pengki 30.00 30.00 bh 15,000 450,000
10 Cangkul 10.00 10.00 bh 85,000 850,000
11 Sekop 9.00 9.00 bh 55,000 495,000
12 Palu 5.00 5.00 bh 85,000 425,000
13 Gergaji Kayu 5.00 5.00 bh 65,000 325,000
14 Gergaji Besi 4.00 4.00 bh 50,000 200,000
15 Prasasti 1.00 1.00 bh 850,000 850,000
16 Papan proyek 1.00 1.00 bh 250,000 250,000
-
Sub Total Peralatan 32,337,000
Volume Sumber Dana
Kode Harga Satuan
No URAIAN Dari Satuan
Dari Kategori Swadaya APBD
Total Swaday
APBD (Rp) (Rp) (Rp)
a
C BIAYA OPERASIONAL
1 Ketua 1.00 1.00 0rg 5,500,000 5,500,000
2 Sekertaris 1.00 1.00 0rg 4,500,000 4,500,000
3 Anggota 5.00 5.00 0rg 4,100,000 20,500,000
4 Atk 1.00 1.00 Paket 2,000,000 2,000,000
5 Pelaporan Progres 1.00 1.00 Paket 1,000,000 1,000,000
6 Pelaporan Akhir 1.00 1.00 Paket 413,000 413,000
7 Transport TPK 1.00 1.00 ls - -
Sub Total I) 33,913,000
TOTAL BIAYA OPERASIONAL

TOTAL INFRASTRUKTUR (BETONISASI + BANGUNAN PELENGKAP)


TOTAL PERLATAN
TOTAL OPERASIONAL
Dari APBD
SUMBER DANA
Dari Swadaya
GRAND TOTAL

TERBILANG : " SATU MILIYAR RUPIAH "

Dibuat oleh,
Diketahui, TIM PELAKSANA KEGIATAN
KEPALA DESA

( SUPRIATNA )
( OPIK SAHRUDIN )

Diperiksa
1. PERANGKAT DAERAH TERKAIT ________________________

2. PDTI/TENAGA AHLI INFRASTUKTUR KAB ________________________


ANGGARAN BIAYA (RAB) PERUBAHAN

Bangunan Pelengkap

TOTAL (Rp)

(Rp)
k = i+j

39,150,000
28,200,000
33,120,000
96,810,000
4,400,000
2,400,000
600,000
1,625,000

206,305,000

48,600,000
12,600,000
-

61,200,000
267,505,000

-
-
-
-
200,000

200,000

-
-
-

-
200,000

832,000
15,000,000
10,000,000
310,000
100,000
2,250,000
450,000
850,000
495,000
425,000
325,000
200,000
850,000
250,000
-
32,337,000
TOTAL (Rp)

(Rp)

5,500,000
4,500,000
20,500,000
2,000,000
1,000,000
413,000
-
33,913,000
33,913,000

267,705,000
32,337,000
33,913,000
333,955,000
-
333,955,000

Dibuat oleh,
TIM PELAKSANA KEGIATAN

( SUPRIATNA )

________________________

________________________
Form 7.
DOKUMENTASI 0%
TITIK AWAL TITIK TENGAH TITIK AKHIR

PROGRAM BANTUAN KEUANGAN


INFRASTRUKTUR DESA

DOKUMENTASI KEGIATAN
PROPINSI
JAWA BARAT
KABUPATEN
BOGOR
KECAMATAN
CARINGIN
DESA
CIMANDE
JENIS PRASARANA
SARANA DAN PRASARANA
LOKASI

KP.BARU RW.004

Dibuat oleh,
TPK

SUPRIATNA
Disetujui oleh,
Kepala Desa Cimande Hilir

OPIK SAHRUDIN

Lembar 1 dari 1 Lembar


REKAPITULASI RENCANA ANGGARAN BIAYA PRASARANA

PROVINSI : : JAWA BARAT KECAMATAN : CARINGIN


KABUPATEN : : BOGOR DESA : CIMANDE
Kegiatan : Jalan Rabat Beton Kegiatan : Kegiatan : -
Ukuran : 6 x 350 Ukuran : Ukuran : Bobot
Bobot Bobot Bobot JUMLAH TOTAL ( Rp )
No Uraian Jumlah : 1 Jumlah : Jumlah :
(%) (%) (%)
No. RAB : 01 No. RAB : No. RAB : (%)
APBD Swadaya APBD Swadaya APBD Swadaya APBD Swadaya

I BAHAN 206,505,000.00 - 61.84% - - - - 206,505,000.00 - 61.84%

PERALATAN
II 32,337,000.00 - 9.68% - - - - 32,337,000.00 - 9.68%

III UPAH 61,200,000.00 - 18.33% - - - - 61,200,000.00 - 18.33%

300,042,000 - - 300,042,000 -
J u m l a h BAHAN dan - - -
89.85% 0% 89.85%
UPAH
- - 300,042,000

V Operasional 5 % 33,913,000 10.2% 33,913,000 10.15%

0.00%

VII Jumlah Total 333,955,000 333,955,000 100.00%

Jumlah Biaya Upah 61,200,000 - - 61,200,000

Jumlah HOK Konstruksi 2,345 HOK - HOK - 2,345.00 HOK

Kepala Desa Cimande Hilir Cimande , …...Desember 2021


TPK Desa

OPIK SAHRUDIN SUPRIATNA


Ketua
Form 7.
DESAIN GAMBAR RENCANA BETONISASI JALAN DAN BANGUNAN PELENGKAP

PROGRAM BANTUAN KEUANGAN


INFRASTRUKTUR DESA

GAMBAR RENCANA
PROPINSI
JAWA BARAT
KABUPATEN
BOGOR
KECAMATAN
CARINGIN
DESA
CIMANDE
JENIS PRASARANA
TPT
LOKASI

KP.BARU RW.004
JUDUL GAMBAR
POTONGAN MELINTANG
DETAIL POT. MELINTANG

Dibuat oleh,
TPK

SUPRIATNA
Disetujui oleh,
Kepala Desa Cimande

OPIK SAHRUDIN
Diperiksa oleh,

PDTI / TA Infrastruktur
Lembar 1 dari 1 Lembar