RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Bantuan Musholla Kp. Pasir Hihid


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor
Provinsi : Jawa Barat
Tahun : 2020
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I BAHAN MATERIAL
1 Batu Bata 1000 Bh 1,950 1,950,000 9.44%
2 Pasir 15 M3 250,000 3,750,000 18.16%
3 Batu Belah 7 M3 225,000 1,575,000 7.63%
4 Semen 105 Zak 65,000 6,825,000 33.05%
5 Kayu Balok Merahan 2 M3 1,650,000 3,300,000 15.98%
6 Pintu Standar 2 Bh 650,000 1,300,000 6.30%
7 Keramik 40 x 40 30 Mtr 65,000 1,950,000 9.44%

Jumlah 20,650,000 100.00%


PPH+PPN ( 11,5% )
Jumlah Total 20,650,000
Jumlah Dibulatkan 20,650,000
Terbilang : Dua puluh juta tiga ratus ribu rupiah

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan

H. Firdaus Alek
RENCANA ANGGARAN BIAYA
Nama Pekerjaan : Pengadaan Pakaian Kerja Perangkat Desa
Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor :
Provinsi : Jawa Barat
Tahun : 2020 :
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I Pegawai Desa
1 1 Kepala Desa 1 Stel 350,000 350,000
2 2 Sekretaris Desa 1 Stel 350,000 350,000
3 3 Kaur Pemerintahan 1 Stel 350,000 350,000
4 4 Kaur Pelayanan 1 Stel 350,000 350,000
5 5 Kaur Tata Usaha dan Umum 1 Stel 350,000 350,000
6 6 Kasi Perencanaan 1 Stel 350,000 350,000
7 7 Kasi Keuangan 1 Stel 350,000 350,000
8 8 Kasi Kesra 1 Stel 350,000 350,000 2,800,000 10.45%
II Kepala Dusun Stel -
9 1 Kepala Dusun I 1 Stel 300,000 300,000
10 2 Kepala Dusun II 1 Stel 300,000 300,000
11 3 Kepala Dusun III 1 Stel 300,000 300,000
12 4 Kepala Dusun IV 1 Stel 300,000 300,000
13 5 Kepala Dusun V 1 Stel 300,000 300,000 1,500,000 5.60%
III LPM Stel -
14 1 Ketua 1 Stel 300,000 300,000
15 2 Sekretaris Desa 1 Stel 300,000 300,000
16 3 Anggota 1 Stel 300,000 300,000
17 4 Anggota 1 Stel 300,000 300,000
18 5 Anggota 1 Stel 300,000 300,000
19 6 Anggota 1 Stel 300,000 300,000
20 7 Anggota 1 Stel 300,000 300,000 2,100,000 7.84%
IV Satlinmas Stel
21 1 Kepala Satuan 1 Stel 300,000 300,000
22 2 Kepala Satuan Tugas 1 Stel 300,000 300,000
23 3 Komandan Regu I 1 Stel 300,000 300,000
24 4 Komandan Regu II 1 Stel 300,000 300,000
25 5 Komandan Regu III 1 Stel 300,000 300,000
26 6 Komandan Regu IV 1 Stel 300,000 300,000
27 7 Anggota 1 Stel 300,000 300,000
28 8 Anggota 1 Stel 300,000 300,000
29 9 Anggota 1 Stel 300,000 300,000
30 10 Anggota 1 Stel 300,000 300,000
31 11 Anggota 1 Stel 300,000 300,000
32 12 Anggota 1 Stel 300,000 300,000
33 13 Anggota 1 Stel 300,000 300,000
34 14 Anggota 1 Stel 300,000 300,000
35 15 Anggota 1 Stel 300,000 300,000
36 16 Anggota 1 Stel 300,000 300,000
37 17 Anggota 1 Stel 300,000 300,000
38 18 Anggota 1 Stel 300,000 300,000
39 19 Anggota 1 Stel 300,000 300,000
40 20 Anggota 1 Stel 300,000 300,000
41 21 Anggota 1 Stel 300,000 300,000
42 22 Anggota 1 Stel 300,000 300,000
43 23 Anggota 1 Stel 300,000 300,000
44 24 Anggota 1 Stel 300,000 300,000
45 25 Anggota 1 Stel 300,000 300,000
46 26 Anggota 1 Stel 300,000 300,000
47 27 Anggota 1 Stel 300,000 300,000
48 28 Anggota 1 Stel 300,000 300,000
49 29 Anggota 1 Stel 300,000 300,000
50 30 Anggota 1 Stel 300,000 300,000 9,000,000 33.58%
V Ketua Rw Stel -
51 1 Ketua Rw 01 1 Stel 300,000 300,000
52 2 Ketua Rw 02 1 Stel 300,000 300,000
53 3 Ketua Rw 03 1 Stel 300,000 300,000
54 4 Ketua Rw 04 1 Stel 300,000 300,000
55 5 Ketua Rw 05 1 Stel 300,000 300,000
56 6 Ketua Rw 06 1 Stel 300,000 300,000
57 7 Ketua Rw 07 1 Stel 300,000 300,000
58 8 Ketua Rw 08 1 Stel 300,000 300,000
59 9 Ketua Rw 09 1 Stel 300,000 300,000
60 10 Ketua Rw 10 1 Stel 300,000 300,000 3,000,000 11.19%
VI Ketua Rt Stel -
61 1 Ketua Rt. 01/01 1 Stel 300,000 300,000
62 2 Ketua Rt. 02/01 1 Stel 300,000 300,000
63 3 Ketua Rt. 03/01 1 Stel 300,000 300,000
64 4 Ketua Rt.01/02 1 Stel 300,000 300,000
65 5 Ketua Rt.02/02 1 Stel 300,000 300,000
66 6 Ketua Rt.03/02 1 Stel 300,000 300,000
67 7 Ketua Rt.01/03 1 Stel 300,000 300,000
68 8 Ketua Rt.02/03 1 Stel 300,000 300,000
69 9 Ketua Rt.03/03 1 Stel 300,000 300,000
70 10 Ketua Rt.01/04 1 Stel 300,000 300,000
71 11 Ketua Rt.02/04 1 Stel 300,000 300,000
72 12 Ketua Rt.03/04 1 Stel 300,000 300,000
73 13 Ketua Rt.04/04 1 Stel 300,000 300,000
74 14 Ketua Rt.01/05 1 Stel 300,000 300,000
75 15 Ketua Rt.02/05 1 Stel 300,000 300,000
76 16 Ketua Rt.03/05 1 Stel 300,000 300,000
77 17 Ketua Rt.04/05 1 Stel 300,000 300,000
78 18 Ketua Rt.01/06 1 Stel 300,000 300,000
79 19 Ketua Rt.02/06 1 Stel 300,000 300,000
80 20 Ketua Rt.01/07 1 Stel 300,000 300,000
81 21 Ketua Rt.02/07 1 Stel 300,000 300,000
82 22 Ketua Rt.03/07 1 Stel 300,000 300,000
83 23 Ketua Rt.01/08 1 Stel 300,000 300,000
84 24 Ketua Rt.02/08 1 Stel 300,000 300,000
85 25 Ketua Rt.01/09 1 Stel 300,000 300,000
86 26 Ketua Rt.02/09 1 Stel 300,000 300,000
87 27 Ketua Rt.01/10 1 Stel 300,000 300,000
88 28 Ketua Rt.02/10 1 Stel 300,000 300,000 8,400,000 31.34%

Jumlah 88 Stel 26,800,000 26,800,000 100.00%


PPH+PPN ( 11,5% )
Jumlah Total 26,800,000
Jumlah Dibulatkan 26,800,000
Terbilang : Dua puluh enam juta delapan ratus ribu rupiah

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan
H. Firdaus Alek
RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Pembuatan Gedung PAUD RT.03/03


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor :
Provinsi : Jawa Barat
Tahun : 2020 :
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I BAHAN MATERIAL
1 Batu Bata 9858 Bh 950 9,365,100 6.50%
2 Pasir 63 M3 275,000 17,325,000 12.03%
3 Batu Belah 16 M3 225,000 3,600,000 2.50%
4 Batu Split 8 M3 260,000 3,600,000
5 Semen 428 Zak 65,000 27,820,000 19.32%
6 Genteng Pres 1800 Bh 1,850 3,330,000 2.31%
7 Nok Genteng 16 Bh 39,500 632,000
8 Kayu Reng 154 Btg 19,000 2,926,000
9 Kayu Balok Merahan 9 M3 1,650,000 14,850,000 10.31%
10 Besi 10" 35 Btg 59,000 2,065,000
11 Besi 12" 43 Btg 84,500 3,633,500
12 Besi 6" 59 Btg 28,000 1,652,000
13 Cakar Ayam 40x40 10" 13 Bh 115,000 1,495,000
14 Pintu Standar 2 Bh 650,000 1,300,000 0.90%
15 Keramik 40 x 40 72 Mtr 55,000 3,960,000 2.75%
16 Kusen Pintu 2 Bh 350,000 700,000 0.49%
17 Paku Campur 25 Kg 38,500 962,500 0.67%
18 Engsel Pintu 4 Psg 35,500 142,000 0.10%
19 Kusen Jendela 4 Bh 250,000 1,000,000 0.69%
20 Jendela 4 Bh 350,000 1,400,000 0.97%
21 Engsel Jendela 4 Psg 25,000 100,000
22 Plamir tembok 15 Kg 21,500 322,500
23 Kunci Pintu 2 Bh 135,000 270,000 0.19%
24 Cat Tembok @25Kg 6 Pil 595,000 3,570,000 2.48%
25 Cat Kayu @1Kg 5 Kg 67,000 335,000 0.23%
26 Thiner 3 Kg 50,500 151,500 0.11%
27 Internit GRC 1,2 x 2,4 36 Lbr 65,000 2,340,000 1.63%
28 Papan Cor 35 Lbr 8,500 297,500
28 Kaso Jengjing 67 Btg 9,500 636,500 0.44%
109,781,100 76.24%
II UPAH KERJA
29 Tukang 140 HOK 110,000 15,400,000 10.70%
30 Kenet 209 HOK 90,000 18,810,000 13.06%
34,210,000 23.76%
Jumlah 143,991,100 100.00%
PPN+PPH 11,5 %
Jumlah Total 143,991,100
Jumlah Dibulatkan
Terbilang : Seratus empat puluh empat juta delapan puluh dua ribu rupiah 143,992,000

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan
H. Firdaus Alek
RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Pembuatan Kantor BPD dan LPM


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor :
Provinsi : Jawa Barat
Tahun : 2020 :
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I BAHAN MATERIAL
1 Batu Bata 2000 Bh 1,950 3,900,000 11.66%
2 Pasir 15 M3 250,000 3,750,000 11.21%
3 Batu Belah 5 M3 225,000 1,125,000 3.36%
4 Semen 105 Zak 65,000 6,825,000 20.41%
5 Asbes Glbg 1,05 x 3 7 Bh 91,000 637,000 1.90%
6 Kayu Balok Merahan 1 M3 1,650,000 1,650,000 4.93%
7 Pintu Standar 4 Bh 650,000 2,600,000 7.77%
8 Keramik 40 x 40 15 Mtr 55,000 825,000 2.47%
9 Kusen Pintu 3 Bh 350,000 1,050,000 3.14%
10 Paku Campur 5 Kg 38,500 192,500 0.58%
11 Engsel Pintu 4 Psg 36,000 144,000 #DIV/0!
12 Kusen Jendela 2 Bh 250,000 500,000 1.50%
13 Jendela 2 Bh 350,000 700,000 2.09%
14 Kunci Pintu 3 Bh 135,000 405,000 1.21%
15 Cat Tembok @25Kg 1 Pil 595,000 595,000 1.78%
16 Cat Kayu @1Kg 2 Kg 67,000 134,000 0.40%
17 Thiner 2 Kg 50,500 101,000 0.30%
18 Internit GRC 1,2 x 2,4 6 Lbr 65,000 390,000 1.17%
19 Kaso Jengjing 11 Btg 9,500 104,500 0.31%
25,628,000 76.63%
II UPAH KERJA
20 Tukang 30 HOK 115,000 3,450,000 10.32%
21 Kenet 45 HOK 97,000 4,365,000 13.05%
7,815,000 23.37%
Jumlah 33,443,000 100.00%
PPN+PPH 11,5 %
Jumlah Total 33,443,000
Jumlah Dibulatkan
Terbilang : Tiga puluh dua juta sembilan ratus delapan puluh sembilan ribu rupiah

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan

H. Firdaus Alek
RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Pengadaan Leptop dan Printer Kantor Desa


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor :
Provinsi : Jawa Barat
Tahun : 2020 :
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I Komputer
1 Leptop Merk Acer 2 Bh 5,460,000 10,920,000 78.45%
II Printer -
1 Epson Merk L310 2 Bh 1,500,000 3,000,000 21.55%

Jumlah 13,920,000 100.00%


PPH+PPN ( 11,5% )
Jumlah Total 13,920,000
Jumlah Dibulatkan 13,920,000
Terbilang : Tiga belas juta sembilan ratus dua puluh ribu rupiah

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan

H. Firdaus Alek
RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Pengadaan Meja Rapat dan Meja Tamu


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten : Bogor :
Provinsi : Jawa Barat
Tahun : 2020 :
Sumber Dana : CSR PT. Antam TBK

HARGA SATUAN JUMLAH


NO URAIAN VOLUME SATUAN BOBOT
( Rp ) ( Rp )
I Meja Rapat
1 Meja Rapat 1 Set 8,000,000 8,000,000 66.67%
II Printer -
1 Meja Tamu 1 Set 4,000,000 4,000,000 33.33%

Jumlah 12,000,000 100.00%


PPH+PPN ( 11,5% )
Jumlah Total 12,000,000
Jumlah Dibulatkan 12,000,000
Terbilang : Dua belas juta rupiah

Hambaro, Januari 2020


Dibantu, Dibuat Oleh,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi


Diusulkan,
Kepala Desa Ketua
Hambaro Tim Pelaksana Kegiatan

H. Firdaus Alek
RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Pembuatan Jembatan Rt.02/01


Desa : Hambaro
Kecamatan : Nanggung
Kabupaten/Kota : Bogor
Provinsi : Jawa Barat
Tahun : 2020
Sumber Dana : CSR PT. ANTAM TBK

Harga Satuan Biaya Jumlah biaya


No Jenis Pekerjaan Satuan Volume Kode Bobot (%)
(Rp) (Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Honor TPK Is 1 - - - 0.00%
2 Papan Kegiatan+Prasasti ls 1 - - - - 0.00%
3 Pelaporan set 1 - - - - 0.00%
4 Dokumentasi ls 1 - - - - 0.00%
- 0.00%
I Galian Tanah 9.90 60,804 601,960 601,960 1.15%
II Pasangan Sayap dan Klonengan 35.10 945,250 33,178,275.00 33,178,275 63.64%
III Beton Pondasi Dan Jembatan 7.48 1,133,500.00 8,478,580 8,478,580 16.26%
IV Pemasangan Besi WF 2.00 3,337,500 6,675,000 6,675,000 12.80%
VII Pemasangan Besi 12' 12.00 119,000 1,428,000 1,428,000 2.74%
VII Pemasangan Spandek 6.00 120,313 721,875 721,875 1.38%
VII Pemasangan Pagar besi 4.00 207,500 830,000 830,000 1.59%
VIII Pemasangan Pipa PVC 8.40 26,100 219,240 219,240 0.42%
52,132,930 100.00%
Jumlah 52,132,930 100.00%
PPH+PPN ( 11,5 % ) - 0.00%
Jumlah Total 52,132,930 100.00%
Jumlah Total Dibulatkan 52,133,000

Hambaro,…..Januari 2020
Dibantu : Dibuat,
Kaur Pembangunan Tim Perencana

Opik Zulfikor Sonwasi

Diusulkan
Kepala Desa
Hambaro Ketua Tim Pelaksana Kegiatan

H. Firdaus Alek