Harga Harga
Harga
No. Komponen Satuan Bahan Alat Keterangan
Upah (Rp)
(Rp) (Rp)
I. U P A H
1. Pekerja OH 70,000
2. Tukang Batu OH 80,000
3. Tukang Kayu OH 80,000
4. Kepala Tukang OH 90,000
5. Mandor OH 90,000
II. B A H A N
1 Semen Portland zak 60,000 50 kg / sak
2 Pasir Beton m3 313,000
3 Kerikil (Maks. 30mm) m3 296,000
4 Sirtu m3 123,000
5 Papan Bekisting m3 1,800,000
6 Kaso 5/7 m3 1,800,000
7 Paku 5 – 10 cm kg 16,000
8 Minyak bekisting ltr 17,000
9 Aspal drum 1,600,000
10 Pasir Pasang m3 170,000
11 Batu Pecah 5/7 m3 180,000
12 Batu Pecah 3/5 m3 280,000
13 Batu Pecah 2/3 m3 290,000
14 Batu Pecah 1/2 m3 300,000
15 Batu Pecah 0,5/1 m3 310,000
16 Batu Belah m3 170,000
17 Pasir Urug m3 145,000
18 Besi 8 42,500
19 Besi 10 65,000
20 Besi 12 95,000
21 Kawat Beton 20,500
22 Bata merah bh 800
23 Habel 900,000
III. A L A T / PERLENGKAPAN
1. Papan Proyek bh 250,000
2. Prasasti unit 300,000
3. Mobilisasi Molen ls 300,000
4. Sewa Molen hr 250,000
5. Ember Aduk bh 10,000
6. Gerobak Dorong bh 500,000
7. Cangkul bh 70,000
8. Singkup bh 80,000
9. Benang bh 3,000
10. Meteran 50 m bh 80,000
11. Meteran 5 m bh 20,000
Daftar Harga Bahan dan Upah diambil dari Hasil Survey
Peratuaran bersama kepala desa tiap rayon
E015. 1m3 Membuat Kolom Beton Bertulang (300 kg besi + bekisting papan) SNI 2014
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA :
Pekerja L.01 OH 7.050 #REF! #REF!
Tukang Batu L.02 OH 0.275 #REF! #REF!
Tukang Kayu L.03 OH 1.650 #REF!
Tukang Besi L.04 OH 2.100 #REF!
Kepala Tukang L.05 OH 0.403 #REF! #REF!
Mandor L.06 OH 0.353 #REF! #REF!
JML. BIAYA TENAGA KERJA #REF!
B BAHAN :
Kayu m3 0.400 #REF! #REF!
Paku biasa 5 - 7 cm Kg 4.000 #REF!
Minyak bekisting Ltr 2.000 #REF!
Besi beton polos Kg 315.000 #REF!
Kawat beton Kg 4.500 #REF!
Semen Portland Kg 336.000 #REF!
Pasir beton m3 0.540 #REF!
Split m3 0.810 #REF!
Kayu m3 0.150 #REF!
Papan Albasia m3 0.200 #REF!
Bambu Batang dia 7cm Btg 20.000 #REF!
P T LA LB TP V Pemasangan Bowplank Galian Tanah Urugan Pasir Pasangan Batu Kali Plesteran +
NO DATA PATOK
m m m m m m3 Kaso Papan Paku PK TK KT M PK M Psr. Urg PK M Bt.Blh Semen Psr PK TK KT M Semen Psr
P1
1 72 1.60 0.40 0.80 0.50 97.92 0.94 0.50 1.44 7.20 0.72 0.72 0.72 26.73 0.89 3.46 0.86 0.029 117.50 266.34 53.27 146.88 73.44 7.34 7.34 4.77 1.21
P2
2
P3
3
RATA-RATA 1.60 0.40 0.80 0.50
JUMLAH 72 97.92 0.94 0.50 1.44 7.20 0.72 0.72 0.72 26.73 0.89 3.46 0.86 0.03 117.50 266.34 53.27 146.88 73.44 7.34 7.34 4.77 1.21
SATUAN m3 m3 kg OH OH OH OH OH OH m3 OH OH m3 zak m3 OH OH OH OH zak m3
1. Pekerjaan Pengukuran
Panjang = 72 m'
Upah :
Pekerja = 0.020 x 72 = 1.44 OH
Tukang kayu = 0.010 x 72 = 0.72 OH
Bahan :
Kaso 5/7 cm = 0.013 x 72 = 0.94 m3
Papan 3/20 cm = 0.007 x 72 = 0.50 m3
Paku 5-7 cm = 0.020 x 72 = 1.44 kg
Upah :
Pekerja = 0.100 x 72 = 7.20 OH
Tukang kayu = 0.010 x 72 = 0.72 OH
Kepala Tukang = 0.010 x 72 = 0.72 OH
Mandor = 0.010 x 72 = 0.72 OH
3. Galian Tanah
Volume
Panjang = 72 m
Lebar = 0.90 m
Tinggi = 0.55 m
G T1 = P x L x T
G T1 = 72 x 0.9 x 0.55
G T1 = 35.64 m3
Upah :
Pekerja = 0.750 x 35.64 = 26.73 OH
Mandor = 0.025 x 35.64 = 0.89 OH
Upah :
Pekerja = 0.300 x 2.88 = 0.86 OH
Mandor = 0.010 x 2.88 = 0.03 OH
Volume = 97.9 m3
Bahan :
Batu Belah = 1.200 x 97.9 = 117.50 m3
Semen Portland = 2.720 x 97.9 = 266.34 zak
Pasir Pasang = 0.544 x 97.9 = 53.27 m3
Upah :
Pekerja = 1.500 x 97.9 = 146.88 OH
Tukang = 0.750 x 97.9 = 73.44 OH
Kepala Tukang = 0.075 x 97.9 = 7.34 OH
Mandor = 0.075 x 97.9 = 7.34 OH
Bahan :
Kayu = 0.40 x 3.59 = 1.44 m3
Paku biasa 5 -7 = 4.00 x 3.59 = 14.38 Kg
Minyak bekisting= 2.00 x 3.59 = 7.19 Ltr
Besi beton polos = 315.00 x 3.59 = 1132.03 Kg
Kawat beton = 4.50 x 3.59 = 16.17 Kg
Semen Portland = 336.00 x 3.59 = 1207.50 Kg 24.15 zak
Pasir beton = 0.54 x 3.59 = 1.94 m3
Split = 0.81 x 3.59 = 2.91 m3
Papan Bekisting = 0.20 x 3.59 = 0.72 m3
Bambu = 20.00 x 3.59 = 71.88 btg
Upah :
Pekerja = 7.050 x 3.59 = 25.34 OH
Tukang Batu = 0.275 x 3.59 = 0.99 OH
Tukang Kayu = 1.650 x 3.59 = 5.93 OH
Tukang Besi = 2.1 x 3.59 = 7.55 OH
Kepala Tukang = 0.403 x 3.59 = 1.45 OH
Mandor = 0.353 x 3.59 = 1.27 OH
Bahan :
Kayu = 0.40 x 7.50 = 3.00 m3
Paku biasa 5 -7 = 4.00 x 7.50 = 30.00 Kg
Minyak bekisting= 2.00 x 7.50 = 15.00 Ltr
Besi beton polos = 315.00 x 7.50 = 2362.50 Kg
Kawat beton = 4.50 x 7.50 = 33.75 Kg
Semen Portland = 336.00 x 7.50 = 2520.00 Kg 50.4 zak
Pasir beton = 0.54 x 7.50 = 4.05 m3
Split = 0.81 x 7.50 = 6.08 m3
Papan Bekisting = 0.20 x 7.50 = 1.50 m3
Bambu = 20.00 x 7.50 = 150.00 btg
Upah :
Pekerja = 7.050 x 7.50 = 52.88 OH
Tukang Batu = 0.275 x 7.50 = 2.06 OH
Tukang Kayu = 1.650 x 7.50 = 12.38 OH
Tukang Besi = 2.1 x 7.50 = 15.75 OH
Kepala Tukang = 0.403 x 7.50 = 3.02 OH
Mandor = 0.353 x 7.50 = 2.65 OH
I. Bahan
1 Pasir Pasang 54.00 0.00 54.00 zak 170,000 - 9,180,000 9,180,000
2 Pasir Urug 4.00 0.00 4.00 m3 145,000 - 580,000 580,000
3 Batu Belah 118.00 0.00 118.00 m3 170,000 - 20,060,000 20,060,000
4 Pasir Beton 6.00 0.00 6.00 m3 313,000 1,878,000 1,878,000
5 Split 9.00 0.00 9.00 m3 296,000 2,664,000 2,664,000
6 Semen PC 50 kg 341.00 0.00 341.00 m3 60,000 - 20,460,000 20,460,000
7 Kaso 5/7 cm 6.00 0.00 6.00 m3 1,800,000 - 10,800,000 10,800,000
8 Papan Bekisting 3.00 0.00 3.00 m3 1,800,000 - 5,400,000 5,400,000
9 Paku 5-7 cm 46.00 0.00 46.00 kg 16,000 - 736,000 736,000
10 Kawat Beton 50.00 0.00 50.00 kg 20,500 - 1,025,000 1,025,000
11 Minyak bekisting 23.00 0.00 23.00 kg 17,000 - 391,000 391,000
12 Bambu 222.00 0.00 222.00 kg 10,000 - 2,220,000 2,220,000
13 Besi 12 mm 21.00 0.00 21.00 kg 95,000 - 1,995,000 1,995,000
14 Besi 10 mm 121.00 0.00 121.00 kg 65,000 - 7,865,000 7,865,000
15 Besi 8 mm 82.00 0.00 82.00 kg 42,500 - 3,485,000 3,485,000
Sub Total 1) 88,739,000 88,739,000
II. Alat
1 Papan Proyek 1.00 0.00 1.00 bh 250,000 250,000 250,000
2 Prasasti 1.00 0.00 1.00 unit 300,000 - 300,000 300,000
3 Ember Aduk 19.00 0.00 19.00 bh 10,000 - 190,000 190,000
4 Benang 17.00 0.00 17.00 bh 3,000 - 51,000 51,000
5 Meteran 5 m 1.00 0.00 1.00 bh 20,000 - 20,000 20,000
Sub Total 2) 811,000 811,000
III. Upah
1 Pekerja 262.00 0.00 262.00 OH 70,000 - 18,340,000 18,340,000
2 Tukang Batu 121.00 0.00 121.00 OH 80,000 - 9,680,000 9,680,000
3 Kepala Tukang 13.00 0.00 13.00 OH 90,000 - 1,170,000 1,170,000
4 Mandor 14.00 0.00 14.00 OH 90,000 - 1,260,000 1,260,000
Sub Total 3) 30,450,000 30,450,000
TOTAL 120,000,000