Anda di halaman 1dari 4

ENGINEER ESTIMATE

(EE)

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : ........................................................................
PEKERJAAN : .......................................................................
PAGU ANGGARAN : Rp. 21,000,000.00
TAHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )

.......................................................................
1 Pengadaan Pipa PVC Dia. 1½" 15.00 Batang 160,000.00 2,400,000.00
2 Pengadaan Pipa PVC Dia. 1" 40.00 Batang 91,000.00 3,640,000.00
3 Pengadaan Pipa PVC Dia. ½" 15.00 Batang 66,000.00 990,000.00
4 Pengadaan Accessories dan Fitting Pipa 1.00 Ls 2,061,000.00 2,061,000.00
5 Mesin Pompa Air 2.00 Unit 2,500,000.00 5,000,000.00
6 Upah Jasa Pemasangan 1.00 Ls 5,000,000.00 5,000,000.00

Jumlah Rp 19,091,000.00
PPn 10% Rp 1,909,100.00
Jumlah Total Rp 21,000,100.00
Dibulatkan Rp 21,000,000.00

Terbilang : Dua Puluh Satu Juta Rupiah

Rengat, Januari 2021


Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN
(PPK)

...........................................
NIP. ..............................
HARGA PERKIRAAN SENDIRI
(HPS)

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : ........................................................................
PEKERJAAN : .......................................................................
PAGU ANGGARAN : Rp. 21,000,000.00
TAHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )

.......................................................................
1 Pengadaan Pipa PVC Dia. 1½" 15.00 Batang 160,000.00 2,400,000.00
2 Pengadaan Pipa PVC Dia. 1" 40.00 Batang 90,000.00 3,600,000.00
3 Pengadaan Pipa PVC Dia. ½" 15.00 Batang 66,000.00 990,000.00
4 Pengadaan Accessories dan Fitting Pipa 1.00 Ls 2,000,000.00 2,000,000.00
5 Mesin Pompa Air 2.00 Unit 2,500,000.00 5,000,000.00
6 Upah Jasa Pemasangan 1.00 Ls 5,000,000.00 5,000,000.00

Jumlah Rp 18,990,000.00
PPn 10% Rp 1,899,000.00
Jumlah Total Rp 20,889,000.00
Dibulatkan Rp 20,889,000.00

Terbilang : Dua Puluh Juta Delapan Ratus Delapan Puluh Sembilan Ribu Rupiah,-

Rengat, Januari 2021


Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN
(PPK)

...........................................
NIP. ..............................
ANALISA HARGA SATUAN
PEKERJAAN .......................................................................

HARGA SATUAN OVER HEAD TRANSPORTASI HARGA HARGA SATUAN


DAN BONGKAR JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SURVEY 25% MUAT SATUAN DI BULATKAN
( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
a b c d e = d x 25% f g=d+e+f h i=hxc

1 Pengadaan Pipa PVC Dia. 1½" 15.00 Batang 125,000.00 31,250.00 3,000.00 159,250.00 160,000.00 2,400,000.00
2 Pengadaan Pipa PVC Dia. 1" 40.00 Batang 70,000.00 17,500.00 3,000.00 90,500.00 91,000.00 3,640,000.00
3 Pengadaan Pipa PVC Dia. ½" 15.00 Batang 50,000.00 12,500.00 3,000.00 65,500.00 66,000.00 990,000.00
4 Pengadaan Accessories dan Fitting 1.00 Ls 2,061,000.00 2,061,000.00 2,061,000.00 2,061,000.00 2,061,000.00
5 Mesin Pompa Air 2.00 Unit 2,000,000.00 500,000.00 2,500,000.00 2,500,000.00 5,000,000.00
6 Upah Jasa Pemasangan 1.00 Ls 5,000,000.00 5,000,000.00 5,000,000.00 5,000,000.00 5,000,000.00

Jumlah Rp 19,091,000.00
PPn 10% Rp 1,909,100.00
Jumlah Total Rp 21,000,100.00
Dibulatkan Rp 21,000,000.00

Rengat, Januari 2021


Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN
(PPK)

...........................................
NIP. ..............................
SPESIFIKASI TEKNIS

KEGIATAN : ........................................................................
PEKERJAAN : .......................................................................
TAHUN ANGGARAN : 2021

Spesifikasi Teknis barang yang di perlukan sebagai berikut :

Pengadaan Pipa PVC serta Accesorries dan Fitting Pipa


- Bahan : Polyvinil Chloride yang berkualitas baik
- Warna : Warna Disesuaikan dengan merk dan arahan direksi pekerjaan
- Bentuk : Pipa Lurus berpenampang bulat, bidang ujung pipa tegak lurus terhadap sumbu pipa
- Untuk pengadaan Pipa PVC dan Accessories ini dilaksanakan dengan ukuran Diameter Pipa PVC 1½",
1" dan ½" serta Accessories dan Fitting Pipa disesuaikan dengan keperluan saat pemasangan
dilaksanakan.

- Pengadaan Pipa PVC serta Accesorries dan Fitting Pipa ini dilaksanakan lengkap terpasang tanpa
adanya kebocoran pada Pipa serta sambungannya sesuai arahan dari direksi pekerjaan.

Pengadaan Mesin Pompa Air


- Type : Jet Pump Automatic
- Fitur : Thermal Protector
- Voltage/Hz : Min. 220/50
- Output Motor : Min. 250 Kw
- Input Motor : Min. 0,58 Kw
- Pemasangan Dilaksanakan lengkap terpasang sesuai arahan direksi pekerjaan.