REKAPITULASI BIAYA
JUMLAH Rp 400,595,279.52
PPN 10 % Rp 40,059,527.95
TOTAL Rp 440,654,807.47
DIBULATKAN Rp 440,650,000.00
TERBILANG :
HARIYONO, A. Md
Team Leader
ENGINEER'S ESTIMATE (EE)
RENCANA ANGGARAN BIAYA
1 2 3 4 5
1 PEK. PENDAHULUAN
1 Pek. Pas. Papan Bowplank 18.00 M' Rp 64,600.00
2 Pek. Job Mix Design Dan Pengujian Beton 1.00 Ls' Rp 2,000,000.00
SUB JUMLAH
2 PEK. PONDASI
1 Pek. Galian tanah pondasi 3.12 M3 Rp 66,000.00
2 Pek. Urugan pasir bawah pondasi 2.11 M3 Rp 132,000.00
3 Pek. Cor lantai kerja, beton K-100 2.11 M3 Rp 967,900.00
4 Pek. Cor Pondasi Umpak 75x75x25 cm, beton K-225 2.81 M3 Rp 1,962,600.00
5 Pek. Cor kolom pondasi 25/25 cm, beton K-225 0.38 M3 Rp 3,799,100.00
6 Pek. Balok Sloof 20/30 cm, beton K-225 7.94 M3 Rp 4,000,200.00
7 Pek. Urugan tanah kembali 1.56 M3 Rp 79,200.00
SUB JUMLAH
3 PEK. LANTAI
1 Pek. Urugan pasir bawah lantai 19.50 M3 Rp 132,000.00
2 Pek. Pembesian Lantai 2,275.20 Kg Rp 15,600.00
3 Pek. Cor lantai tebal 15 cm beton K-225 65.88 M3 Rp 899,500.00
SUB JUMLAH
4 PEK. STRUKTUR
1 Pek. Kolom Pipa Baja Dia 5" T = 5 Mm 1,002.00 Kg Rp 18,400.00
2 Pek. Reng Pipa Baja Dia 4" T = 5 Mm 1,190.40 Kg Rp 18,400.00
3 Pek. Skor Pipa Baja Dia 2" T = 4 Mm 330.24 Kg Rp 18,400.00
SUB JUMLAH
1 2 3 4 5
3 Pek. Gording Pipa 2" T = 4 Mm 1,328.00 Kg Rp 18,400.00
4 Pek. Pas atap seng Spandek 546.00 M2 Rp 108,200.00
SUB JUMLAH
6 PEK. PENGECATAN
1 Pek. Cat pipa Besi 219.78 M2 Rp 26,700.00
SUB JUMLAH
TOTAL SUB JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN
1 2 3 4 5
1 PEK. PENDAHULUAN
1.1 Pek. Pas. Papan Bowplank 17.00 M' Rp 64,600.00
SUB JUMLAH
1 PEK. PENDAHULUAN
1.1 Pek. Pas. Papan Bowplank 9.40 M' Rp 64,600.00
SUB JUMLAH
2 RABAT BETON
1 Pek. Pembesian Rabat Beton 1,474.67 Kg Rp 15,600.00
2 Pek. Cor Rabat Beton K-225 T = 15 Cm 42.00 M3 Rp 899,500.00
3 Pek. Pas.Papan Mal Cetakan Rabat Beton 5.20 M2 Rp 176,700.00
SUB JUMLAH
TOTAL SUB JUMLAH
NEER'S ESTIMATE (EE)
NCANA ANGGARAN BIAYA
JUMLAH HARGA
6 [3x5]
Rp 1,162,800.00
Rp 2,000,000.00
Rp 3,162,800.00
Rp 205,920.00
Rp 278,520.00
Rp 2,042,269.00
Rp 5,519,812.50
Rp 1,424,662.50
Rp 31,741,587.00
Rp 123,552.00
Rp 41,336,323.00
Rp 2,574,000.00
Rp 35,493,120.00
Rp 59,259,060.00
Rp 97,326,180.00
Rp 18,436,800.00
Rp 21,903,360.00
Rp 6,076,416.00
Rp 46,416,576.00
Rp 24,435,200.00
Rp 10,861,593.60
JUMLAH HARGA
6 [3x5]
Rp 24,435,200.00
Rp 59,077,200.00
Rp 118,809,193.60
Rp 5,868,019.20
Rp 5,868,019.20
Rp 312,919,091.80
JUMLAH HARGA
6 [3x5]
Rp 1,098,200.00
Rp 1,098,200.00
Rp 914,760.00
Rp 304,920.00
Rp 2,235,849.00
Rp 7,933,590.00
Rp 9,336,774.72
Rp 512,715.00
Rp 235,872.00
Rp 2,793,627.00
Rp 24,268,107.72
Rp 25,366,307.72
Rp 607,240.00
Rp 607,240.00
Rp 23,004,800.00
Rp 37,779,000.00
Rp 918,840.00
Rp 61,702,640.00
Rp 62,309,880.00
ANALISA HARGA SATUAN PEKERJAA
A. PEKERJAAN PERSIAPAN
B. PEKERJAAN TANAH
3 1 M3 Urugan pasir
Bahan 1.2000 M3 Pasir urug Rp. 80,000.00 Rp.
Tenaga 0.3000 Oh Pekerja Rp. 75,000.00
0.0100 Oh Mandor Rp. 150,000.00
Rp.
4 1 M3 Urugan tanah
Bahan 1.2000 M3 Tanah timbunan Rp. 40,000.00 Rp.
Tenaga 0.3000 Oh Pekerja Rp. 75,000.00
0.0100 Oh Mandor Rp. 150,000.00
Rp.
C. PEKERJAAN BETON
E. PEKERJAAN PENGECATAN
F. PEKERJAAN BESI
1 1 Kg Fabrikasi baja
Bahan 1.150 Kg Besi Pipa Rp. 12,000.00 Rp.
Tenaga 1.000 Ls Tenga + Mesin Las + Kawat Rp. 3,000.00
Rp.
HARGA SATUAN PEKERJAAN
25,200.00
400.00
14,700.00
Rp. 7,500.00
Rp. 9,000.00
Rp. 1,250.00
Rp. 750.00
40,300.00 Rp. 18,500.00 Rp. 58,800.00
JUMLAH (BELUM PPRp. 58,800.00
JASA 10% 5,880.00
JUMLAH 64,680.00
DIBULATKAN 64,600.00
Rp. 7,500.00
Rp. 7,500.00
Rp. 15,000.00 Rp. 15,000.00
JUMLAH (BELUM PPRp. 15,000.00
JASA 10% 1,500.00
JUMLAH 16,500.00
DIBULATKAN 16,500.00
Rp. 56,250.00
Rp. 3,750.00
- Rp. 60,000.00 Rp. 60,000.00
JUMLAH (BELUM PPRp. 60,000.00
JASA 10% 6,000.00
JUMLAH 66,000.00
DIBULATKAN 66,000.00
Rp. 37,500.00
Rp. 7,500.00
BAHAN TENAGA TOTAL
- Rp. 45,000.00 Rp. 45,000.00
JUMLAH (BELUM PPRp. 45,000.00
JASA 10% 4,500.00
JUMLAH 49,500.00
DIBULATKAN 49,500.00
96,000.00
Rp. 22,500.00
Rp. 1,500.00
96,000.00 Rp. 24,000.00 Rp. 120,000.00
JUMLAH (BELUM PPRp. 120,000.00
JASA 10% 12,000.00
JUMLAH 132,000.00
DIBULATKAN 132,000.00
48,000.00
Rp. 22,500.00
Rp. 1,500.00
48,000.00 Rp. 24,000.00 Rp. 72,000.00
JUMLAH (BELUM PPRp. 72,000.00
JASA 10% 7,200.00
JUMLAH 79,200.00
DIBULATKAN 79,200.00
519,400.00
39,885.71
155,111.11
1,075.00
Rp. 123,750.00
Rp. 24,750.00
Rp. 3,500.00
Rp. 12,450.00
715,471.83 Rp. 164,450.00 Rp. 879,921.83
JUMLAH (BELUM PPRp. 879,921.83
JASA 10% 87,992.18
JUMLAH 967,914.01
DIBULATKAN 967,900.00
BAHAN TENAGA TOTAL
456,400.00
43,428.57
152,444.44
1,075.00
Rp. 123,750.00
Rp. 24,750.00
Rp. 3,500.00
Rp. 12,450.00
653,348.02 Rp. 164,450.00 Rp. 817,798.02
JUMLAH (BELUM PPRp. 817,798.02
JASA 10% 81,779.80
JUMLAH 899,577.82
DIBULATKAN 899,500.00
12,600.00
330.00
Rp. 525.00
Rp. 630.00
Rp. 87.50
Rp. 60.00
12,930.00 Rp. 1,302.50 Rp. 14,232.50
JUMLAH (BELUM PPRp. 14,232.50
JASA 10% 1,423.25
JUMLAH 15,655.75
DIBULATKAN 15,600.00
84,000.00
6,000.00
1,100.00
Rp. 39,000.00
Rp. 23,400.00
Rp. 3,250.00
Rp. 3,900.00
91,100.00 Rp. 69,550.00 Rp. 160,650.00
JUMLAH (BELUM PPRp. 160,650.00
JASA 10% 16,065.00
JUMLAH 176,715.00
DIBULATKAN 176,700.00
BAHAN TENAGA TOTAL
94,500.00
6,000.00
1,100.00
Rp. 39,000.00
Rp. 23,400.00
Rp. 3,250.00
Rp. 3,900.00
101,600.00 Rp. 69,550.00 Rp. 171,150.00
JUMLAH (BELUM PPRp. 171,150.00
JASA 10% 17,115.00
JUMLAH 188,265.00
DIBULATKAN 188,200.00
Rp. 899,500.00
Rp. 354,634.80
Rp. 530,100.00
Rp. 1,784,234.80
JUMLAH (BELUM PPRp. 1,784,234.80
JASA 10% 178,423.48
JUMLAH 1,962,658.28
DIBULATKAN ###
Rp. 899,500.00
Rp. ###
Rp. 941,000.00
Rp. 3,636,574.80
JUMLAH (BELUM PPRp. 3,636,574.80
JASA 10% 363,657.48
JUMLAH 4,000,232.28
DIBULATKAN ###
Rp. 899,500.00
Rp. ###
Rp. 706,800.00
Rp. 3,453,730.00
JUMLAH (BELUM PPRp. 3,453,730.00
JASA 10% 345,373.00
JUMLAH 3,799,103.00
DIBULATKAN ###
BAHAN TENAGA TOTAL
78,225.00
280.00
Rp. 11,250.00
Rp. 6,750.00
Rp. 1,000.00
Rp. 900.00
78,505.00 Rp. 19,900.00 Rp. 98,405.00
JUMLAH (BELUM PPRp. 98,405.00
JASA 10% 9,840.50
JUMLAH 108,245.50
DIBULATKAN 108,200.00
1,960.00
Rp. 1,500.00
Rp. 18,000.00
Rp. 2,500.00
Rp. 375.00
1,960.00 Rp. 22,375.00 Rp. 24,335.00
JUMLAH (BELUM PPRp. 24,335.00
JASA 10% 2,433.50
JUMLAH 26,768.50
DIBULATKAN 26,700.00
13,800.00
Rp. 3,000.00
13,800.00 Rp. 3,000.00 Rp. 16,800.00
JUMLAH (BELUM PPRp. 16,800.00
JASA 10% 1,680.00
JUMLAH 18,480.00
DIBULATKAN 18,400.00
DINAS PEKERJAAN UMUM PERMUKIMAN DAN PRASARANA W
DAFTAR HARGA SATUAN UPAH DAN BAHAN
HARGA
NO. JENIS UPAH DAN BAHAN SATUAN
(Rp.)
1 2 3 4
A. UPAH
1 Pekerja 1 OH 75,000
2 Tukang 1 OH 90,000
3 Kepala tukang 1 OH 125,000
4 Mandor 1 OH 150,000
B. BAHAN
1 Air 1 Liter 5
2 Atap seng spandek 1 M2 74,500
3 Besi Pipa 1 Kg 12,000
4 Besi tulang beton 1 Kg 12,000
5 Cat menie besi 1 Kg 19,600
6 Kawat beton 1 Kg 22,000
7 Kawat las 1 Kg 15,000
8 Kayu kelas III persegi 1 M3 2,100,000
9 Koral beton / kerikil sungai 1 M3 200,000
10 Koral beton / kerikil sungai 1 Kg 148.15
11 Minyak bekisting 1 Ltr 11,000
12 Paku biasa 2" - 5" 1 Kg 20,000
13 Paku hak panjang 1 Kg 14,000
14 Papan kayu klas III 1 M3 2,100,000
15 Pasir pasangan 1 M3 80,000
16 Pasir pasangan 1 Kg 57.14
17 Pasir urug 1 M3 80,000
18 Semen portland 1 Kg 1,400
19 Tanah timbunan 1 M3 40,000
UM PERMUKIMAN DAN PRASARANA WILAYAH
DAFTAR HARGA SATUAN UPAH DAN BAHAN
KETERANGAN
5
JADWAL PELAKSANAAN PEKERJAAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PT.PLN (PERSERO) WILAYAH RIAU DAN KEPULAWAN RIAU
PEKERJAAN : PEMBUATAN SELTER ULPLTD KOTA LAMA
LOKASI : ULPLTD KOTA LAMA PT PLN (Persero) UP3 RENGAT
T.A : 2019
RENCANA MINGGUAN ( % ) 100.00 0.79 3.13 5.43 9.41 10.76 9.70 9.75 10.13
KOMULATIF RENCANA MINGGUAN ( % ) - 0.79 3.92 9.35 18.76 29.52 39.22 48.97 59.10
AKSANAAN PEKERJAAN
100%
50%
0.16
0.15