NO URAIAN PEKERJAAN VOLUME SAT KODE HARGA PAJAK JUMLAH HARGA TOTAL
ANALISA ( Rp ) 10% + PAJAK 10 % ( Rp )
( Rp )
1 2 3 4 5 6 7 = 3x6x10% 8= ( 3 x 6 ) + 7 9
I PEKERJAAN PERSIAPAN
1 Uitzed dan Papan Nama 1.00 LS Taksir 300,000.00 30,000.00 330,000.00
JUMLAH PEKERJAAN PERSIAPAN 330,000.00
II Pek Backdrop
1 Backdrop Kayu jati Ukir 25.03 m2 A.4.5.1.6.a 489,629.80 1,225,298.57 13,478,284.32
2 Stage Kayu Jati 11.05 m2 A.4.5.1.6.b 489,977.40 541,425.03 5,955,675.30
Jumlah Pekerjaan Backdrop 19,433,959.62
III Pek Dinding
1 Papan Kayu Jati Pelapis Dinding 22.40 m2 A.4.5.1.6.a 489,629.80 1,096,770.75 12,064,478.27
Jumlah Pekerjaan Dinding 12,064,478.27
IV Pekerjaan Pintu
1 Kusen Pintu Kayu Jati 6/12 0.14 m3 A.4.6.1.1 16,581,070.00 231,604.39 2,547,648.24
2 Daun Pintu Kayu Jati Ukir 15.75 m2 A.4.6.1.7 1,426,535.00 2,246,792.63 24,714,718.88
3 Papan jati Ukir di atas Pintu 7.00 m2 A.4.5.1.6.a 489,629.80 342,740.86 3,770,149.46
4 rel Pintu 7.20 m' Taksir 355,000.00 255,600.00 2,811,600.00
Jumlah Pekerjaan Pintu 33,844,116.58
V Pekerjaan Finising
1 Politur Melamine 100.00 m2 A.4.7.1.7.a 191,570.50 1,915,609.21 21,071,701.36
86,744,255.83
JUMLAH TOTAL PEKERJAAN 86,744,255.83
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
NO URAIAN PEKERJAAN VOLUME SAT KODE HARGA PAJAK JUMLAH HARGA TOTAL
ANALISA ( Rp ) 10% + PAJAK 10 % ( Rp )
( Rp )
1 2 3 4 5 6 7 = 3x6x10% 8= ( 3 x 6 ) + 7 9
I PEKERJAAN PERSIAPAN
1 Uitzed dan Papan Nama 1.00 LS Taksir 250,000.00 25,000.00 275,000.00
JUMLAH PEKERJAAN PERSIAPAN 275,000.00
II Pek Backdrop
1 Backdrop Kayu jati Ukir 25.03 m2 A.4.5.1.6.a 489,629.80 1,225,298.57 13,478,284.32
2 Stage Kayu Jati 11.05 m2 A.4.5.1.6.b 489,977.40 541,425.03 5,955,675.30
Jumlah Pekerjaan Backdrop 19,433,959.62
III Pek Dinding
1 Papan Kayu Jati Pelapis Dinding 22.40 m2 A.4.5.1.6.a 489,629.80 1,096,770.75 12,064,478.27
Jumlah Pekerjaan Dinding 12,064,478.27
IV Pekerjaan Pintu
1 Kusen Pintu Kayu Jati 6/12 0.14 m3 A.4.6.1.1 16,581,070.00 231,604.39 2,547,648.24
2 Daun Pintu Kayu Jati Ukir 15.75 m2 A.4.6.1.7 1,426,535.00 2,246,792.63 24,714,718.88
3 Papan jati Ukir di atas Pintu 7.00 m2 A.4.5.1.6.a 489,629.80 342,740.86 3,770,149.46
4 rel Pintu 7.20 m' Taksir 355,000.00 255,600.00 2,811,600.00
Jumlah Pekerjaan Pintu 33,844,116.58
V Pekerjaan Finising
1 Politur Melamine 100.00 m2 A.4.7.1.7.a 191,570.50 1,915,609.21 21,071,701.36
86,689,255.83
JUMLAH TOTAL PEKERJAAN 86,689,255.83
DIBULATKAN 86,689,000.00
TERBILANG : Delapan Puluh Enam Juta Enam Ratus Delapan Puluh Sembilan Ribu Rupiah
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
NO URAIAN PEKERJAAN VOLUME SAT KODE HARGA PAJAK JUMLAH HARGA TOTAL
ANALISA ( Rp ) 10% + PAJAK 10 % ( Rp )
( Rp )
1 2 3 4 5 6 7 = 3x6x10% 8= ( 3 x 6 ) + 7 9
I PEKERJAAN PERSIAPAN
1 Uitzed dan Papan Nama 1.00 LS Taksir 200,000.00 20,000.00 220,000.00
JUMLAH PEKERJAAN PERSIAPAN 220,000.00
II Pek Backdrop
1 Backdrop Kayu jati Ukir 25.03 m2 A.4.5.1.6.a 489,629.80 1,225,298.57 13,478,284.32
2 Stage Kayu Jati 11.05 m2 A.4.5.1.6.b 489,977.40 541,425.03 5,955,675.30
Jumlah Pekerjaan Backdrop 19,433,959.62
III Pek Dinding
1 Papan Kayu Jati Pelapis Dinding 22.40 m2 A.4.5.1.6.a 489,629.80 1,096,770.75 12,064,478.27
Jumlah Pekerjaan Dinding 12,064,478.27
IV Pekerjaan Pintu
1 Kusen Pintu Kayu Jati 6/12 0.14 m3 A.4.6.1.1 16,581,070.00 231,604.39 2,547,648.24
2 Daun Pintu Kayu Jati Ukir 15.75 m2 A.4.6.1.7 1,426,535.00 2,246,792.63 24,714,718.88
3 Papan jati Ukir di atas Pintu 7.00 m2 A.4.5.1.6.a 489,629.80 342,740.86 3,770,149.46
4 rel Pintu 7.20 m' Taksir 355,000.00 255,600.00 2,811,600.00
Jumlah Pekerjaan Pintu 33,844,116.58
V Pekerjaan Finising
1 Politur Melamine 100.00 m2 A.4.7.1.7.a 191,570.50 1,915,609.21 21,071,701.36
86,634,255.83
JUMLAH TOTAL PEKERJAAN 86,634,255.83
DIBULATKAN 86,634,000.00
TERBILANG : Delapan Puluh Enam Juta Enam Ratus Tiga Puluh Empat Ribu Rupiah
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
NO URAIAN PEKERJAAN VOLUME SAT KODE HARGA PAJAK JUMLAH HARGA TOTAL
ANALISA ( Rp ) 10% + PAJAK 10 % ( Rp )
( Rp )
1 2 3 4 5 6 7 = 3x6x10% 8= ( 3 x 6 ) + 7 9
I PEKERJAAN PERSIAPAN
1 Uitzed dan Papan Nama 1.00 LS Taksir 150,000.00 15,000.00 165,000.00
JUMLAH PEKERJAAN PERSIAPAN Rp 165,000
II Pek Backdrop
1 Backdrop Kayu jati Ukir 25.03 m2 A.4.5.1.6.a 489,629.80 1,225,298.57 13,478,284.32
2 Stage Kayu Jati 11.05 m2 A.4.5.1.6.b 489,977.40 541,425.03 5,955,675.30
Jumlah Pekerjaan Backdrop Rp 19,433,960
III Pek Dinding
1 Papan Kayu Jati Pelapis Dinding 22.40 m2 A.4.5.1.6.a 489,629.80 1,096,770.75 12,064,478.27
Jumlah Pekerjaan Dinding Rp 12,064,478
IV Pekerjaan Pintu
1 Kusen Pintu Kayu Jati 6/12 0.14 m3 A.4.6.1.1 16,581,070.00 231,604.39 2,547,648.24
2 Daun Pintu Kayu Jati Ukir 15.75 m2 A.4.6.1.7 1,426,535.00 2,246,792.63 24,714,718.88
3 Papan jati Ukir di atas Pintu 7.00 m2 A.4.5.1.6.a 489,629.80 342,740.86 3,770,149.46
4 rel Pintu 7.20 m' Taksir 355,000.00 255,600.00 2,811,600.00
Jumlah Pekerjaan Pintu Rp 33,844,117
V Pekerjaan Finising
1 Politur Melamine 100.00 m2 A.4.7.1.7.a 191,570.50 1,915,609.21 21,071,701.36
Rp 86,579,256
JUMLAH TOTAL PEKERJAAN Rp 86,579,256
DI BULATKAN Rp 86,579,000
TERBILANG : Delapan Puluh Enam Juta Lima Ratus Tujuh Puluh Sembilan Ribu Rupiah
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
Menyetujui Megetahui
Kepala Dinas Perumahan, Permukiman dan Perhubungan Kepala Dinas Pemberdayaan Masyarakat Dan Desa
Kabupaten Blora Kabupaten Blora
selaku
Pengguna Anggran
KECAMATAN : BLORA
KABUPATEN : BLORA
BEAYA : Rp 86,800,000
BACK UP DATA
KEGIATAN : PENGADAAN PERLENGKAPAN DEGUNG KANTOR
LOKASI : DINAS PEMBERDAYAAN MASYARAKAT DAN DESA
SUMBER DANA : APBD KABUPATEN BLORA
TAHUN ANGGARAN : 2019
PENYEDIA JASA : CV. GALANG PRATAMA DESAIN
Pekerjaan Backdrop
Pekerjaan Stage
= 4.5 x 1.6 = 7.200 m2
= 0.500 x 1.600 x 2 = 1.600 m2
= 4.5 x 0.5 = 2.250 m2
11.050 m2
Pekerjaan Pintu
Kusen 6/12
= 0.06 x 0.12 x 2.5 x 2 = 0.036 m3
= 0.06 x 0.12 x 7.200 x 2 = 0.104 m3
0.140 m3
daun Pintu
= 2.25 x 7 = 15.75 m2
DI BUAT
PENYEDIA JASA
CV. GALANG PRATAMA DESIGN
SUPARMAN
DIREKTUR
DAFTAR SEWA P E R A L A T AN
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
HARGA
NO. JENIS PEKERJA SATUAN KET.
(Rp)
1 Pekerja Hr 70,000
2 Mandor Hr 85,000
3 Tukang listrik Hr 80,000
4 Tukang kayu Hr 80,000
5 Kep. tk. kayu Hr 82,000
6 Tukang batu Hr 80,000
7 Kep.tk.batu Hr 85,000
8 Tukang besi Hr 80,000
9 Kep .tk .besi Hr 85,000
10 Tukang cat Hr 80,000
11 Kep. tk. cat Hr 85,000
12 Tukang plitur Hr 80,000
13 Tukang jalan Hr 80,000
14 Tukang gali Hr 80,000
15 Tukang masak aspal Hr 80,000
16 Tk. leideng Hr 80,000
20 Penjaga malam Hr 70,000
21 Sopir Hr 80,000
22 Pembantu Sopir Hr 70,000
23 Operator Hr 80,000
24 Pembantu Operator Alat Berat Hr 60,000
25 Mekanik/Teknisi Alat Berat Hr 80,000
26 Juru Ukur Hr 80,000
Dibuat Oleh :
Konsultan Perencana
CV. GALANG PRATAMA DESAIN
SUPARMAN
Direktur
I BAHAN DASAR
III . B A H A N K A Y U
1 JATI Jati (Papan) m3 21,000,000
Jati (Balok/pesagen) m3 11,500,000
Dibuat Oleh :
Konsultan Perencana
CV. GALANG PRATAMA DESAIN
SUPARMAN
Direktur
Dibuat Oleh :
Konsultan Perencana
CV. GALANG PRATAMA DESAIN
SUPARMAN
Direktur
9 A.4.4.1.9 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP 101,323.09
A Tenaga 31,125.00
L.01 0.30 OH Pekerja 70,000.00 21,000.00
L.02 0.1 OH Tukang Batu 80,000.00 8,000.00
L.03 0.01 OH Kepala Tukang 85,000.00 850.00
L.04 0.015 OH Mandor 85,000.00 1,275.00
B Bahan 60,986.90
70 Buah Bata Merah 5 x 11 x 22 500.00 35,000.00
11.50 Kg Portland Semen 1,350.00 15,525.00
0.043 m3 Pasir Pasang 243,300.00 10,461.90
C PERALATAN
D 0 92,111.90
E Overhead & Profit (contoh 10%) 10% 9,211.19
F Harga Satuan Pekerjaan (D+E) 101,323.09
9 A.4.4.1.9.a 1 m2 Pemasangan Dinding Bata Expose Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP 246,798.09
m2 Tenaga 93,375.00
0 0.90 OH Pekerja 70,000.00 63,000.00
L.01 0.3 OH Tukang Batu 80,000.00 24,000.00
L.02 0.03 OH Kepala Tukang 85,000.00 2,550.00
L.03 0.045 OH Mandor 85,000.00 3,825.00
OH Bahan 130,986.90
70 Buah Bata Expose jatirogo 5 x 11 x 22 1,500.00 105,000.00
11.50 Kg Portland Semen 1,350.00 15,525.00
0.043 m3 Pasir Pasang 243,300.00 10,461.90
C PERALATAN
D PERALATAN 224,361.90
E 0 10% 22,436.19
F Harga Satuan Pekerjaan (D+E) 246,798.09
Tenaga 23,700.00
7 A.4.6.1.7 1 m2 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) 1,426,535.00
A Tenaga 338,850.00
L.01 1 OH Pekerja 70,000.00 70,000.00
L.02 3 OH Tukang Kayu 80,000.00 240,000.00
L.03 0.3 OH Kepala Tukang 82,000.00 24,600.00
L.04 0.05 OH Mandor 85,000.00 4,250.00
B Bahan 958,000.00
0.040 m3 Kayu Klas I (Jati), papan 21,000,000.00 840,000.00
1.200 m2 ukir 85,000.00 102,000.00
0.5 kg Lem Kayu 32,000.00 16,000.00
C PERALATAN
D 0 1,296,850.00
E Overhead & Profit (contoh 10%) 10% 129,685.00
F Harga Satuan Pekerjaan (D+E) 1,426,535.00
1 A.4.1.1.1 1 m3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 926,800.91
A Tenaga 146,935.00
L.01 1.65 OH Pekerja 70,000.00 115,500.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 85,000.00 7,055.00
B Bahan 695,611.29
247 Kg Portland Semen 1,350.00 333,450.00
869 Kg Pasir Beton 193.29 167,965.29
999 Kg Kerikil (maksimum 30 mm) 183.63 183,446.00
215 ltr Air 50.00 10,750.00
C PERALATAN
D 0 842,546.29
E Overhead & Profit (contoh 10%) 10% 84,254.63
F Harga Satuan Pekerjaan (D+E) 926,800.91
Overhead & Profit (contoh 10%) 10%
7 A.4.1.1.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,084,279.52
A Tenaga 146,935.00
L.01 1.650 OH Pekerja 70,000.00 115,500.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 85,000.00 7,055.00
B Bahan 838,773.65
371 Kg Portland Semen 1,350.00 500,850.00
698 Kg Pasir Beton 193.29 134,913.43
1,047 Kg Kerikil (maksimum 30 mm) 183.63 192,260.22
215 ltr Air 50.00 10,750.00
C PERALATAN
D 0 985,708.65
E Overhead & Profit (contoh 10%) 10% 98,570.87
F Harga Satuan Pekerjaan (D+E) 1,084,279.52
8 A.4.1.1.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 1,100,692.89
A Tenaga 146,935.00
L.01 1.650 OH Pekerja 70,000.00 115,500.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 85,000.00 7,055.00
B Bahan 853,694.90
384 Kg Portland Semen 1,350.00 518,400.00
692 Kg Pasir Beton 193.29 133,753.71
1,039 Kg Kerikil (maksimum 30 mm) 183.63 190,791.19
215 ltr Air 50.00 10,750.00
C PERALATAN
D 0 1,000,629.90
E Overhead & Profit (contoh 10%) 10% 100,062.99
F Harga Satuan Pekerjaan (D+E) 1,100,692.89
A Tenaga 16,569.00
L.01 0.14 OH Pekerja 70,000.00 9,800.00
L.02 0.070 OH Tukang Kayu 80,000.00 5,600.00
L.03 0.007 OH Kepala Tukang 82,000.00 574.00
L.04 0.007 OH Mandor 85,000.00 595.00
B Bahan 35,670.00
0.51 Lbr Asbes Gelombang 65,000.00 33,150.00
C PERALATAN
D 0 52,239.00
A Tenaga 23,670.00
L.01 0.2 OH Pekerja 70,000.00 14,000.00
L.02 0.1 OH Tukang Kayu 80,000.00 8,000.00
L.03 0.01 OH Kepala Tukang 82,000.00 820.00
L.04 0.01 OH Mandor 85,000.00 850.00
B Bahan 66,474.00
D 0 90,144.00
A Tenaga 129,960.00
L.01 0.8 OH Pekerja 70,000.00 56,000.00
L.02 0.8 OH Tukang Kayu 80,000.00 64,000.00
L.03 0.08 OH Kepala Tukang 82,000.00 6,560.00
L.04 0.04 OH Mandor 85,000.00 3,400.00
B Bahan 315,158.00
C PERALATAN
D PERALATAN 445,118.00
E 0 10% 44,511.80
A Tenaga 129,960.00
L.01 0.8 OH Pekerja 70,000.00 56,000.00
L.02 0.8 OH Tukang Kayu 80,000.00 64,000.00
L.03 0.08 OH Kepala Tukang 82,000.00 6,560.00
L.04 0.04 OH Mandor 85,000.00 3,400.00
B Bahan 315,474.00
A.4.2.1.19 1 m' Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 72,913.50
A Tenaga 37,640.00
L.01 0.15 OH Pekerja 70,000.00 10,500.00
L.02 0.3 OH Tukang Kayu 80,000.00 24,000.00
L.03 0.03 OH Kepala Tukang 82,000.00 2,460.00
L.04 0.008 OH Mandor 85,000.00 680.00
B Bahan 28,645.00
1.05 Lbr Seng Plaat 20,000.00 21,000.00
D 0 66,285.00
A Tenaga 4,734.00
L.01 0.04 OH Pekerja 70,000.00 2,800.00
L.02 0.02 OH Tukang Besi 80,000.00 1,600.00
L.03 0.002 OH Kepala Tukang 82,000.00 164.00
L.04 0.002 OH Mandor 85,000.00 170.00
B Bahan 14,494.00
0.4 kg Kawat Las 28,000.00 11,200.00
D 0 30,448.00
B Bahan 437,318.50
6.63 Buah Ubin Granito 40x40 cm 0.4 60,000.00 397,800.00
C PERALATAN
D Jumlah A + B + C 466,989.50
Dibuat Oleh :
Konsultan Perencana
CV. GALANG PRATAMA DESAIN
SUPARMAN
Direktur