ANALISIS PRODUKTIVITAS DAN OPERASI ALAT BERAT PEMBUATAN S

1. Pengeboran (pilot hole dan Reaming)Water Jetting

No. UraIan Kode Satuan Drilling Rig Mud Pump

1. Prosentase pemanfaatan *) M % 100% 100%


2.
2. Biaya operasi alat S = (G + P) S Rp/jam 419,564.02 289,025.66
3.
3. Bahan pakai habis K Rp/jam 91,390.00 -
- Drilling Fluid/mud Rp/jam 68,890.00 -
4. - Bit Rp/jam 22,500.00 -
4. Biaya operasi alat+material S+K Rp/jam 510,954.02 289,025.66
5. Biaya operasi total M x (S+K) Rp/jam 510,954.02

6. Pengeboran (Pilot hole dan Produktivitas **) Koefisien Alat Koefisien Tenaga Kerja (OH)
Reaming) (Q) (1/Q) (Pekerja)
a. Borehole ø 8 3/4" 1.85 m/jam 0.5405 0.3089
b. Reaming ø 8 3/4" - 12" 2.00 m/jam 0.5000 0.2857
c. Reaming ø 8 3/4" - 14 3/4" 1.98 m/jam 0.5051 0.2886
d. Reaming ø 8 3/4" - 17" 1.90 m/jam 0.5263 0.3008

2. Bongkar Pasang Temporary Casing

No. UraIan Kode Satuan Drilling Rig Mud Pump

1. Prosentase pemanfaatan *) M % 75% 30%


2.
2. Biaya operasi alat S = (G + P) S Rp/jam 419,564.02 289,025.66
3.
3. Bahan pakai habis K Rp/jam 10,000.00 -
- Wire RB & Ciron Rp/jam 6,500.00 -
4. - Acetelyn & CO2 Rp/jam 3,500.00 -
4. Biaya operasi alat+material S+K Rp/jam 429,564.02 289,025.66
5. Biaya operasi total M x (S+K) Rp/jam 322,173.02

Temporary Casing Produktivitas Koefisien Alat Koefisien Tenaga Kerja (OH)


6.
Diameter (Q) (1/Q) (Pekerja)
a. (ID) 17" 1.75 m/jam 0.5714 0.3265
b. (ID) 12" 1.75 m/jam 0.5714 0.3265

3. Pemasangan Konstruksi Sumur (Pipa Black Steel dan Screen Low Carbon)

No. UraIan Kode Satuan Drilling Rig Mud Pump

1. Prosentase pemanfaatan *) M % 100% 0%


2.
2. Biaya operasi alat S = (G + P) S Rp/jam 419,564.02 289,025.66
3.
3. Bahan pakai habis K Rp/jam -
- Wire RB & Ciron Rp/jam - -
4. - Acetelyn & CO2 Rp/jam - -
4. Biaya operasi alat+material S+K Rp/jam 419,564.02 289,025.66
5. Biaya operasi total M x (S+K) Rp/jam 419,564.02

6. Pemasangan Cassing dan Produktivitas Koefisien Alat Koefisien Tenaga Kerja (OH)
Screen Low Carbon (Q) (1/Q) (Pekerja)
a. BS Cassing or LC Screen 6" 8.00 m/jam 0.1250 0.0714
b. BS Cassing or LC Screen 8" 7.00 m/jam 0.1429 0.0816
c. Pipa sounding PVC 1" 25.00 m/jam 0.0400 0.0229
d. Gravel Pack 0.55 m/jam 1.8182 1.0390

4. Pencucian Sumur (Well Development)

No. UraIan Kode Satuan Drilling Rig Mud Pump

1. Persentase pemanfaatan M % 20% 0%


2.
2. Biaya operasi alat S = (G + P) S Rp./jam
Rp/jam 419,564.02 289,025.66
3. Rp./jam
3. Bahan pakai habis K Rp/jam
Rp./jam
4. - Foam/Detergen Rp/jam
Rp./jam
4. Biaya operasi alat+material S+K Rp/jam 419,564.02 289,025.66
5. Biaya operasi total M x (S+K) Rp/jam 83,912.80

Produktivitas Koefisien Alat Koefisien Tenaga Kerja (OH)


6. Development Methods (Q) (1/Q) (Pekerja)
a. Air Lifting 1.00 jam 1,0000 0.5714
b. Air Jetting 1.00 jam 1,0000
1,0000 0.5714
1,0000
1,0000
c. Blow Up 1.00 jam 1,0000 0.5714
1,0000
1,0000
1,0000

5. Uji Pemompaan (Pumping Test)

No. UraIan Kode Satuan Drilling Rig Mud Pump

1. Persentase pemanfaatan M % 20% 0%


2.
2. Biaya operasi alat S = (G + P) S Rp/jam 419,564.02 289,025.66
3.
3. Bahan pakai habis K Rp/jam
S+K
- Battery, cable lamp, dan lain-
Rp/jam - -
4. lain
4. Biaya operasi alat+material Rp/jam 419,564.02 289,025.66
5. Biaya operasi total M x (S+K) Rp/jam 83,912.80

Pumping Test Produktivitas Koefisien Alat Koefisien Tenaga Kerja (OH)


6. (Q) (1/Q)
Air Lift Methods : (Pekerja)
a. Method "V" Notch 1.00 jam 1.0000 0.5714
b. Method Orifice 1.00 jam 1.0000 0.5714
SI ALAT BERAT PEMBUATAN SUMUR BOR AIR TANAH DALAM

Air Pumping Water


Truck Cargo Pick up Welding set
Compressor Test Jetting
0% 15% 20% 5% 0% 0%
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30
- - - - - -
- - - - - -
- - - - - -
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30

Koefisien Tenaga Kerja (OH)


(Tukang Bor) (Mandor) *) Disesuaikan dengan proporsi pemanfaatan
0.0772 0.0309 **) Produktifitas alat tergantung ukuran pipa dan
0.0714 0.0286 konsistensi tanah, kapasitas ini untuk konsistensi stiff
(sedang), sedangkan untuk tanah lembek kapasitas dikali
0.0722 0.0289
2 - 3 dan untuk tanah keras kapasitas dikali 30 - 50%
0.0752 0.0301

Air Pumping Water


Truck Cargo Pick up Welding set
Compressor Test Jetting
0% 10% 0% 50% 0% 0%
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30
- - - - - -
- - - - - -
- - - - - -
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30

Koefisien Tenaga Kerja (OH)


(Tukang Bor) (Mandor)
0.0816 0.0327
0.0816 0.0327

w Carbon)
Air Pumping Water
Truck Cargo Pick up Welding set
Compressor Test Jetting
0% 10% 10% 100% 0% 100%
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30
12500.00 - - - - -
- - - - - -
12500.00 - - - - -
669,324.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30

Koefisien Tenaga Kerja (OH)


(Tukang Bor) (Mandor)
0.0179 0.0071
0.0204 0.0082
0.0057 0.0023
0.2598 0.1039

Air Pumping Water


Truck Cargo Pick up Welding set
Compressor Test Jetting
100% 10% 10% 5% 0% 0%
656.824,20
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 66.774,46
304,704.30
12.500,00 -
12,500.00
12.500,00 -
12,500.00
669.324,20 66.774,46
669,324.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30

Koefisien Tenaga Kerja (OH)


(Tukang Bor) (Mandor)
0.1429 0.0571
0.1429 0.0571
0.1429 0.0571

Air Pumping Water


Truck Cargo Pick up Welding set
Compressor Test Jetting
0% 0% 5% 5% 100% 10%
656,824.20 80,308.87 66,774.46 108074.23 139165.46 30470430%
9000

- - 9000 -

656,824.20 80,308.87 66,774.46 108,074.23 148,165.46 304,704.30

Koefisien Tenaga Kerja (OH)


(Tukang Bor) (Mandor)
0.1429 0.0571
0.1429 0.0571