6. Pengeboran (Pilot hole dan Produktivitas **) Koefisien Alat Koefisien Tenaga Kerja (OH)
Reaming) (Q) (1/Q) (Pekerja)
a. Borehole ø 8 3/4" 1.85 m/jam 0.5405 0.3089
b. Reaming ø 8 3/4" - 12" 2.00 m/jam 0.5000 0.2857
c. Reaming ø 8 3/4" - 14 3/4" 1.98 m/jam 0.5051 0.2886
d. Reaming ø 8 3/4" - 17" 1.90 m/jam 0.5263 0.3008
3. Pemasangan Konstruksi Sumur (Pipa Black Steel dan Screen Low Carbon)
6. Pemasangan Cassing dan Produktivitas Koefisien Alat Koefisien Tenaga Kerja (OH)
Screen Low Carbon (Q) (1/Q) (Pekerja)
a. BS Cassing or LC Screen 6" 8.00 m/jam 0.1250 0.0714
b. BS Cassing or LC Screen 8" 7.00 m/jam 0.1429 0.0816
c. Pipa sounding PVC 1" 25.00 m/jam 0.0400 0.0229
d. Gravel Pack 0.55 m/jam 1.8182 1.0390
w Carbon)
Air Pumping Water
Truck Cargo Pick up Welding set
Compressor Test Jetting
0% 10% 10% 100% 0% 100%
656,824.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30
12500.00 - - - - -
- - - - - -
12500.00 - - - - -
669,324.20 80,308.87 66,774.46 108,074.23 139,165.46 304,704.30
- - 9000 -