I PEK. PERSIAPAN
II PEK. TANAH
1 Galian Tanah Pondasi 2.86 m3
IV PEK. PEMBESIAN
1 Sloof 0.00 m3
3 Balok 0.09 m3
IX PEKERJAAN PLAFOND
XI PEKERJAAN ELECTRIKAL
Hitungan
Panjang = 13.56 M
Luas = a + b x t
Type 1 2.00
= 1.07 + 0.71 x 0.90
2.00
= 0.89 x 0.90
= 0.80 M2
Luas = a + b x t
Type 2 2.00
= 0.66 + 0.48 x 0.90
2.00
= 0.16 x 0.90
= 0.14 m2
V Total = 2.86 m3
V Total = 0.94 M³
Volume Type 1 = a + b x t
2.00
= 0.25 + 0.50 x 0.65
2.00
= 0.24 m3
Volume Type 2 = a + b x t
2.00
= 0.25 + 0.38 x 0.65
2.00
= 0.20 m3
V Total = 0.45 m3
V Total = 0.01 m3
V Total = 0.59 m3
Volume = Panjang x Lebar x Tebal
= 3.40 x 0.15 x 0.15
= 0.08 x 0.14
= 0.08 x 0.14 bh
= 0.01 m3
V.Total = 101.04 m2
V Total = 46.00 m2
V Total = 0.03 m3
= Panjang x Lebar
= 1.75 x 0.80
= 1.40 m2
V.Total = 13.05 m2
V Total = 39.87 m2
V Total = 13.65 m3
V Total = 13.65 m3
Luas Tampak Depan = L x T
= 6.20 x 3.00
= 18.60 m2
Luas Tampak Belakang = L x T
= 6.20 x 3.00
= 18.60 m2
Luas Tampak Samping Kanan = L x T
= 8.15 x 3.00
= 24.45 m2
Luas Tampak Samping Kiri = L x T
= 9.15 x 3.00
= 27.45 m2
V Total = 89.10 m2
Luas R.Kamar 1 = P x L
Dan Kamar 2 3.00 x 3.00
= 9.00 m2
= 18.00 m2
Luas KM/WC = P x L
= 1.50 x 1.50
= 2.25 m2
Luas Dapur = P x L
= 6.00 x 1.50
= 9.00 m2
V Total = 51.75 m2
Luas Genteng = P x L
= 7.35 x 2.40
= 17.64 m2
Ø8 = 1.67 x 0.54
= 0.90 x B.Jenis Ø8
= 0.90 x 0.39
= 0.35 kg
Total = 0.88 kg