1 GALIAN TANAH
a. Panjang Pondasi
1= 14.00 m V
2= 21.00 m V
Lebar = 0.60 m
Kedalaman galian
rata-rata = 1.00 m
b. Luas lantai
= 62.00 m2
Kedalaman galian
= 0.30 m V
To
2 URUGAN PASIR BAWAH PONDASI
a. Pondasi Utama b = 0.6 m Panjang
a
b
Tebal
To
3 PASANGAN PONDASI
a. Pondasi Utama L = 21.0 m Luas Penampang
A
b. Pondasi lantai A= 65.00 m2 Tebal
t
To
4 PLESTERAN
a. Pondasi Utama L = 21.0 m Keliling Plester
k
b. Pondasi lantai A= 65.00 m2 Tebal
t
To
Perhitungan Volume Satuan
= 8.40 m3
= 12.60 m3
21.00 m3 V= 21.000 m3
= 18.60 m3 V= 18.600 m3
= 8.4 m
= 12.6 m
21.0 m V= 1.26 m3
= 62.0 m2 V= 6.20 m3
= 0.10 m
Luas Penampang
= 1.180 m2 V= 24.78 m3
= 0.30 m V= 19.50 m3
Keliling Plester
= 1.350 m V= 28.35 m2
= 65.00 m V= 65.00 m2
To
2 PASANGAN PONDASI
a. Pondasi Box Luas Penampang
L = 7.2 m A
h = 0.8 m V
b = 0.30 m
A Pintu = 0.450 m
A Lantai = 3.240 m2 V
To
4 PLESTERAN
a. Pondasi Box Luas Penampang
L = 7.2 m A
k = 1.1 m
A Pintu = 0.900 m
A Lantai = 2.250 m2 V
To
Perhitungan Volume Satuan
= 2.50
= 2.50
= 0.60
V= 3.750 m3
Luas Penampang
= 5.310 m2 V= 1.593 m3
= 1.593 m3
= 0.972 m3 V= 0.972 m3
Luas Penampang
= 0.600 m2 V= 1.20 m3
= 1.000 Unit
Luas Penampang
= 7.020 m2 V= 7.02 m2
= 2.250 m3 V= 2.25 m2
Luas Penampang
= 2.000 m1 V= 4.00 m2
= 1.000 Unit
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 2,500,000.00 2,500,000.00
2 Papan Informasi Ls 1.00 500,000.00 500,000.00
3 Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00
4 Pengukuran dan Pemasangan Bowplank Ls 1.00 1,500,000.00 1,500,000.00
JUMLAH I 5,500,000.00
JUMLAH II 251,580,945.15
III. PEKERJAAN BAK BAGI Unit 3.00
JUMLAH IV 53,458,157.10
JUMLAH V 1,600,000.00
JUMLAH I+II+III+IV = (1) 341,100,000.00
DIBULATKAN = 341,100,000.00
-242,900,000.00
REKAP KUANTITAS DAN HARGA
I. PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 2,500,000.00 2,500,000.00
2 Papan Informasi Ls 1.00 500,000.00 500,000.00
3 Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00
4 Pengukuran dan Pemasangan Bowplank Ls 1.00 1,500,000.00 1,500,000.00
JUMLAH I 5,500,000.00
II. BAHAN
a. Semen Zak 1,293.78 55,543.52 71,860,869.19
b. Pasir m3 178.56 218,200.00 38,960,875.56
c. Batu Kali m3 331.29 192,600.00 63,806,454.00
JUMLAH II 174,628,198.75
III. TENAGA
JUMLAH V 21,350,000.00
JUMLAH I+II+III+IV = (1) 341,100,000.00
DIBULATKAN = 341,100,000.00
MENGETAHUI/MENYETUJUI
Ketua Tim Teknis
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 2,500,000.00 2,500,000.00
2 Papan Informasi Ls 1.00 500,000.00 500,000.00
3 Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00
4 Pengukuran dan Pemasangan Bowplank Ls 1.00 1,500,000.00 1,500,000.00
JUMLAH I 5,500,000.00
JUMLAH IV 53,458,157.10
HARGA SATUAN JUMLAH
NO URAIAN JENIS PEKERJAAN SAT. VOL. KET.
(RP) HARGA (RP)
JUMLAH V 1,600,000.00
JUMLAH I+II+III+IV = (1) 341,100,000.00
DIBULATKAN = 341,100,000.00
MENGETAHUI OLEH :
Pejabat Pembuat Komitmen ( PPK )
Dinas Pertanian kabupaten Malaka
Ludovikus Asa, S. Pi
Nip. 19720713 200112 1 006
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
Dibulatkan 341,100,000.00
TERBILANG : Tiga Ratus Empat Puluh Satu Juta SeRatus Ribu Rupiah
Diperiksa :
MENYETUJUIStafOLEH : Sumber Daya Air
Bidang DIBUAT OELH
Ketua Tim Teknis CV. TEPI PANTE CONSULTANT
Dinas PUPR Kab. TTS
JOHANIS I. D. NATONIS
NIP. 19651226 199803 1 006 YAPI PAULUS NDOLU, SST
OKTOVIANUS Y. LAKU MALI, S.PT Direktur
NIP. 19901012 201503 1 001
MENGETAHUI OLEH :
Pejabat Pembuat Komitmen ( PPK )
Dinas Pertanian kabupaten Malaka
Ludovikus Asa, S. Pi
Nip. 19720713 200112 1 006
PEMERINTAH KABUPATEN MALAKA
DINAS TANAMAN PANGAN
HORTIKULTURA DAN PERKEBUNAN
Desa Harekakae, Kecamatan Malaka Tengah, Kabupaten Malaka
ENGINEERING ESTIMATE
(E.E)
Program
Optimalisasi Lahan Kering
Kegiatan
Penyipan Lahan dan Perbaikan Infrastruktur Lahan kering
Pekerjaan
Penyiapan Lahan dan Perbaikan Infrastruktur Lahan Kering ( OPLAH )
Kelompok Tani
Hamparan Sukabihun
Lokasi
Desa Raimataus Kecamatan Malaka Barat Kab. Malaka
KONSULTAN PERENCANA