Back Up Data Jalan Usaha Tani: (Lembar Perhitungan)
Back Up Data Jalan Usaha Tani: (Lembar Perhitungan)
( Lembar Perhitungan )
A. Pekerjaan Persiapan
167,400,000
1.A Galian Tanah
- Panjang = 199.95 m
- STA 00 = 0.100 m2
- STA 50 = 0.181 m2
- STA 100 = 0.655 m2
- STA 150 = 0.440 m2
Total Volume Galian Tanah = 68.78 M³
1 Dinding kiri
- Panjang = 200.0 m
- Lebar Atas = 0.2 m
- Lebar Bawah = 0.4 m
- Tinggi Pasangan = 0.8 m
Volume Dinding Kiri = 47.99 M³
2 Dinding kanan
- Panjang = 20.0 m
- Lebar Atas = 0.2 m
- Lebar Bawah = 0.3 m
- Tinggi Pasangan = 0.4 m
Volume Dinding Kanan = 2.00 M³
3 pondasi Kiri
- Panjang = 200.0 m
- Lebar = 0.4 m
- Tinggi Pas. = 0.2 m
Volume Pondasi kanan = 16.00 M³
4 pondasi Kanan
- Panjang = 20.0 m
- Lebar = 0.3 m
- Tinggi Pas. = 0.2 m
Volume Pondasi kanan = 1.20 M³
Total Volume Pasangan Batu Kali = 67.18 M³
C. Pekerjaan Plesteran
1 Plesteran Kiri
- Panjang = 200.0 m
- Lebar = 1 m
Volume Plasteran Kiri = 199.95 M²
2 Plesteran Kanan
- Panjang = 20.0 m
- Lebar = 0.6 m
Volume Plasteran Kanan = 11.97 M²
Total Volume Plasteran = 211.92 M²
RICKY IKHWAN, ST