A PEKERJAAN PERSIAPAN
3,00 3,00
2,00
4,00
2,00
1,00
1,00
6,00
Volume = 30 m
B PEKERJAAN TANAH
Pondasi Gedung
T = 0.80 m
0.8 m L = 0.60 m
P = 20.00 m
0.6 m Vol I = P x L x T
= 20.0 x 0.6 x 0.8
= 9.6 m3
Pondasi Teras
T = 0.30 m
0.3 m L = 0.30 m
P = 8.00 m
0.3 m Vol II = P x L x T
= 8.0 x 0.3 x 0.3
= 0.7 m3
Volume = 3.4 m3
C PEKERJAAN PONDASI
0.3 m
Pondasi Gedung
T = 0.60 m
0.6 m L = 0.45 m
Batu Belah
P = 20.00 m
Vol I = P x L x T
0.6 m = 20.00 x 0.45 x 0.60
= 5.4 m3
Kabupaten : Bandung Jenis Kegiatan : Gedung Posyandu
Kecamatan : Kecamatan Take off Sheet Lokasi : Rw 08 Kangasari
Desa : Arjasari Volume : 4x6m
0.3 m
Pondasi Teras
T = 0.30 m
Batu Belah 0.3 m L = 0.30 m
P = 8.00 m
0.3 m Vol II = P x L x T
= 8.00 x 0.30 x 0.30
= 0.7 m3
Batu kosong
T = 0.20 m
L = 0.60 m
P = 20.00 m
Anstamping 0.20 m
Volume = P x L x T
0.6 m = 20.0 x 0.60 x 0.20
= 2.4 m3
E PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC :5PP
Vol I = 74.8 m2
0.92 m
F PEKERJAAN PLESTERAN
2 Pemasangan 1 m2 acian
G PEKERJAAN LANTAI
H PEKERJAAN LANGIT-LANGIT
Volume = 30.0 m2
3 3.7 m L = 6.7 m
P = 7.0 m
Volume = 46.9 m2
J PEKERJAAN KAYU
1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
0,92 1,18
0,06 0,30 0,06
0,06 0,30 0,06
0,10
1,48
1,00
2,42
0,10
2,00
0,06
0,10 0,10
Pintu
T = 2.42 m Vol = t x l x Jml
L = 0.92 m x 2xT x 2xL
2.42 m Jml = 1.0 bh Vol = 0.06 x 0.15 x 1.0
t = 0.06 m x 4.84 x 1.84
l = 0.15 m Vol = 0.06 m3
0.92 m
Jendela
T = 1.48 m Vol = t x l x Jml
L = 1.18 m x 3xT x 3xL
1.48 m Jml = 2.0 bh Vol = 0.06 x 0.15 x 2.0
t = 0.06 m x 4.44 x 3.54
1.18 m l = 0.15 m Vol = 0.14 m3
Pintu
T = 2.0 m Vol = T x L x Jml
2.00 m L = 0.8 m Vol = 2.0 x 0.8 x 1.0
Jml = 1.0 bh Vol = 1.6 m2
0.80 m
3 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Jendela
T = 1.0 m Vol = 2xT x 2xL x Jml
1.00 m L = 0.5 m x l
l = 0.1 m Vol = 2.0 x 1.0 x 4.0
Jml = 4.0 bh x 0.1
0.50 m Vol = 1.2 m2
Kabupaten : Bandung Jenis Kegiatan : Gedung Posyandu
Kecamatan : Kecamatan Take off Sheet Lokasi : Rw 08 Kangasari
Desa : Arjasari Volume : 4x6m
4 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
1.2
P = 12.00 m
0.6 2.0 Jml = 4.00 bh
0.8 l = 0.12 m
t = 0.08 m
4.0 Volume = 0.5 m3
Volume = 0.10 m3
Volume = 46.9 m2
8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Volume = 30.0 m2
Pintu = 1 bh Volume = 1 bh
Pintu = 1 bh Volume = 2 bh
Jendela = 4 bh Volume = 8 bh
Jendela = 4 bh Volume = 4 bh
Jendela = 4 bh Volume = 4 bh
Atas Pintu
0.30 m T = 0.3 m Vol = T x L x Jml
L = 0.8 m Vol = 0.3 x 0.8 x 1.0
0.80 m Jml = 1.0 bh Vol = 0.2 m2
Atas Jendela
0.30 m T = 0.3 m Vol = T x L x Jml
L = 0.5 m Vol = 0.3 x 0.5 x 4.0
0.50 m Jml = 4.0 bh Vol = 0.6 m2
Daun Jendela
T = 0.8 m Vol = T x L x Jml
Kabupaten : Bandung Jenis Kegiatan : Gedung Posyandu
Kecamatan : Kecamatan Take off Sheet Lokasi : Rw 08 Kangasari
Desa : Arjasari Volume : 4x6m
L PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kusen Pintu
T = 2.42 m Vol I = 1.94 m2
L = 0.92 m
2.42 m Jml = 1.0 bh
t = 0.06 m
l = 0.15 m
0.92 m
Kusen Jendela
T = 1.48 m Vol II = 5.11 m2
L = 1.18 m
1.48 m Jml = 2.0 bh
t = 0.06 m
1.18 m l = 0.15 m
Daun Pintu
T = 2.0 m Vol III = 3.2 m2
2.00 m L = 0.8 m
Jml = 1.0 bh
0.80 m
Daun Jendela
T = 1.0 m Vol IV = 2.4 m2
1.00 m L = 0.5 m
Jml = 4.0 bh
l = 0.1 m
0.50 m
Listplank
T = 0.2 m Vol V = 11.0 m2
0.20 m L = 27.4 m
27.4 m Jml = 1.0 bh Vol tot = 23.6 m2
2 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Volume = 138.2 m2
Kabupaten : Bandung Jenis Kegiatan : Gedung Posyandu
Kecamatan : Kecamatan Take off Sheet Lokasi : Rw 08 Kangasari
Desa : Arjasari Volume : 4x6m
F
o
RENCANA ANGGARAN BIAYA r
m
.
DESA : No.RAB : 01 Gedung Posyandu 7
KECAMATAN : Bidang : Pembangunan Desa e
KABUPATEN : BANDUNG Kegiatan : Gedung Posyandu
PROVINSI : JAWA BARAT Volume : 4x6m
HARGA
URAIAN VOLUME SATUAN JUMLAH
SATUAN
a b c d e=bxd
1. BAHAN
1 Kaso 5/7 (3m) 143 btg 19,000 2,717,000
2 Paku 5-7 cm 15 kg 15,000 225,000
3 Papan 3/20 (3m) 12 lbr 32,000 384,000
4 Batu Belah 10 m3 200,000 2,000,000
5 Semen PC @50 kg 60 sak 75,000 4,500,000
6 Pasir Pasang 12 m3 250,000 3,000,000
7 Pasir Urug 1 m3 190,000 190,000
8 Bata Merah 4,840 bh 900 4,356,000
9 Ubin Keramik 30 x 30 cm 33 dus 55,000 1,815,000
10 Gypsum Board 11 lbr 52,000 572,000
11 Paku skrup 3 kg 15,000 45,000
12 List Kayu Profil 21 m 3,000 63,000
13 Paku 2-5 cm 0.5 kg 15,000 7,500
14 Genteng Palentong 1,173 bh 2,000 2,346,000
15 Genteng Bubung 35 bh 3,000 105,000
16 Balok 6/15 (4m) 7 btg 72,000 504,000
17 Paku 10 cm 8 kg 15,000 120,000
18 Lem Kayu 1 kg 25,000 25,000
19 Papan 3/30 (4m) 3 lbr 72,000 216,000
20 Balok 8/12 (4m) 23 btg 77,000 1,771,000
21 Besi Strip tebal 5 mm 12 kg 16,000 192,000
22 Paku 12 cm 4 kg 15,000 60,000
23 Balok 6/10 (4m) 4 btg 48,000 192,000
24 Reng 2/3 (3m) 938 btg 4,000 3,752,000
25 Papan 3/20 (4m) 12 lbr 36,000 432,000
26 Kunci tanam biasa 1 bh 100,000 100,000
27 Engsel Pintu 2 bh 20,000 40,000
28 Engsel Jendela 8 bh 15,000 120,000
HARGA
URAIAN VOLUME SATUAN JUMLAH
SATUAN
a b c d e=bxd
29 Kait Angin 4 bh 15,000 60,000
30 Kunci Slot 4 bh 15,000 60,000
31 Kaca 5 mm 2 m2 52,000 104,000
HARGA
URAIAN VOLUME SATUAN JUMLAH
SATUAN
a b c d e=bxd
32 Sealant 0.5 kg 20,000 10,000
33 Cat Menie 5 kg 12,000 60,000
34 Plamuur kayu 4 kg 12,000 48,000
35 Cat Dasar kayu 4 kg 50,000 200,000
36 Cat Penutup kayu 8 kg 50,000 400,000
37 Kuas 1 bh 20,000 20,000
38 Pengencer 1 kg 15,000 15,000
39 Ampelas 5 lbr 15,000 75,000
40 Plamuur tembok 14 kg 12,000 168,000
41 Cat Dasar tembok 14 kg 18,000 252,000
42 Cat Penutup tembok 36 kg 18,000 648,000
43 Glass box 10 bh 25,000 250,000
44 Lampu LED 3 bh 40,000 120,000
45 Dudukan Lampu 3 bh 15,000 45,000
46 Stop kontak 1 bh 15,000 15,000
47 Saklar ganda 1 bh 20,000 20,000
48 Saklar tunggal 1 bh 15,000 15,000
49 MCB 6A 1 bh 60,000 60,000
50 Box Panel PVC 1 bh 200,000 200,000
51 Kabel listrik NYM 30 m 16,000 480,000
52 Isolasi 2 bh 10,000 20,000
E1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 5PP
A Bahan
1 Bata Merah bh 70.000 69.1 4,835.7
2 Semen PC @50 kg sak 0.194 69.1 13.4
3 Pasir Pasang m3 0.045 69.1 3.1
B Tenaga
1 Pekerja oh 0.300 69.1 20.7
2 Tukang oh 0.100 69.1 6.9
F2 Pemasangan 1 m2 acian
A Bahan
1 Semen PC @50 kg sak 0.065 138.2 9.0
B Tenaga
1 Pekerja oh 0.200 138.2 27.6
2 Tukang oh 0.100 138.2 13.8
J1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
No Uraian Satuan Koef Volume Jumlah
A Bahan
1 Balok 6/15 (4m) btg 33.333 0.2 6.8
2 Paku 10 cm kg 1.250 0.2 0.3
3 Lem Kayu kg 1.000 0.2 0.2
B Tenaga
1 Pekerja oh 6.000 0.2 1.2
2 Tukang oh 18.000 0.2 3.7
J3 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
A Bahan
1 Papan 3/30 (4m) btg 0.667 1.2 0.8
2 Lem Kayu kg 0.300 1.2 0.4
B Tenaga
1 Pekerja oh 0.800 1.2 1.0
2 Tukang oh 2.400 1.2 2.9
J4 Pemasangan 1 m3 konstruksi kuda konvensional, kayu kelas I, II dan III bentang 6 meter
A Bahan
1 Balok 8/12 (4m) btg 28.646 0.5 13.2
2 Besi Strip tebal 5 mm kg 15.000 0.5 6.9
3 Paku 12 cm kg 5.600 0.5 2.6
B Tenaga
1 Pekerja oh 4.000 0.5 1.8
2 Tukang oh 12.000 0.5 5.5
J8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
A Bahan
1 Kaso 5/7 (3m) btg 1.552 30.0 46.6
2 Paku 7-10 cm kg 0.250 30.0 7.5
B Tenaga
1 Pekerja oh 0.200 30.0 6.0
2 Tukang oh 0.300 30.0 9.0
L1 Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
A Bahan
1 Cat Menie kg 0.200 23.6 4.7
2 Plamuur kg 0.150 23.6 3.5
3 Cat Dasar kg 0.170 23.6 4.0
4 Cat Penutup kg 0.350 23.6 8.3
5 Kuas bh 0.010 23.6 0.2
6 Pengencer kg 0.030 23.6 0.7
7 Ampelas lbr 0.200 23.6 4.7
B Tenaga
1 Pekerja oh 0.070 23.6 1.7
2 Tukang oh 0.105 23.6 2.5
L2 Pengecatan 1 m2 bidang tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
A Bahan
1 Plamuur kg 0.100 138.2 13.8
2 Cat Dasar kg 0.100 138.2 13.8
3 Cat Penutup kg 0.260 138.2 35.9
B Tenaga
1 Pekerja oh 0.020 138.2 2.8
2 Tukang oh 0.063 138.2 8.7
REKAPITULASI BAHAN, ALAT, DAN UPAH
No Uraian A1 B1 B2 C1 C2 E1 F1 F2 G1 H1 H2 I1 I2 J1 J2 J3 J4 J5 J6 J7 J8 J9 K1 K2
1 Kaso 5/7 (3m) 34 63 47
2 Paku 5-7 cm 1 12 3
3 Papan 3/20 (3m) 12
4 Batu Belah 7 3
5 Semen PC @50 kg 17 13 14 9 6 1
6 Pasir Pasang 3 3 4 1 0
7 Pasir Urug 1
8 Bata Merah 4,836
9 Ubin Keramik 30 x 30 cm 33
10 Gypsum Board 11
11 Paku skrup 3
12 List Kayu Profil 21
13 Paku 2-5 cm 0
14 Genteng Palentong 1,173
15 Genteng Bubung 35
16 Balok 6/15 (4m) 7
17 Paku 10 cm 0 8
18 Lem Kayu 0 1 0
19 Papan 3/30 (4m) 2 1
20 Balok 8/12 (4m) 13 10
21 Besi Strip tebal 5 mm 7 5
22 Paku 12 cm 3 1 0
23 Balok 6/10 (4m) 4
24 Reng 2/3 (3m) 938
25 Papan 3/20 (4m) 12
26 Kunci tanam biasa 1
27 Engsel Pintu 2
28 Engsel Jendela
29 Kait Angin
30 Kunci Slot
31 Kaca 5 mm
32 Sealant
33 Cat Menie
34 Plamuur kayu
35 Cat Dasar kayu
36 Cat Penutup kayu
37 Kuas
38 Pengencer
39 Ampelas
40 Plamuur tembok
41 Cat Dasar tembok
42 Cat Penutup tembok
43 Glass box
44 Lampu LED
45 Dudukan Lampu
46 Stop kontak
47 Saklar ganda
48 Saklar tunggal
49 MCB 6A
50 Box Panel PVC
51 Kabel listrik NYM
52 Isolasi
1 Pekerja 3 8 2 9 2 21 41 28 21 3 1 7 3 1 2 1 2 1 0 5 6 3 0 0
2 Tukang 3 - - 5 1 7 21 14 11 2 1 4 1 4 5 3 6 4 1 5 9 5 1 0
ULASI BAHAN, ALAT, DAN UPAH
0 0 0 0 2 3 2 176 oh 176 oh
1 1 1 0 2 9 2 126 oh 126 oh
GAMBAR RENCANA PRASARANA
3,00 3,00
4,00
1,00
6,00
DENAH
3,00
GAMBAR RENCANA
KABUPATEN
BANDUNG
KECAMATAN
...........................................
2,00
DESA
...........................................
JENIS PRASARANA
GEDUNG POSYANDU
LOKASI
...........................................
2,00
JUDUL GAMBAR
DENAH
Digambar oleh:
Pelaksana Kegiatan
(Kader Teknik)
1,00
…………………………………..
Diperiksa dan Disetujui oleh:
…………………………………..
Lembar…..dari…..Lembar
GAMBAR RENCANA PRASARANA
4,70
3,00 3,00
6,00
TAMPAK DEPAN
GAMBAR RENCANA
1,70
KABUPATEN
BANDUNG
KECAMATAN
...........................................
DESA
...........................................
JENIS PRASARANA
GEDUNG POSYANDU
LOKASI
...........................................
3,00
JUDUL GAMBAR
TAMPAK DEPAN
Digambar oleh:
Pelaksana Kegiatan
(Kader Teknik)
…………………………………..
Diperiksa dan Disetujui oleh:
3,00
Dinas/Instansi terkait dan/atau
Tenaga Profesional
(jika tersedia)
…………………………………..
Lembar…..dari…..Lembar
GAMBAR RENCANA PRASARANA
4,70
TAMPAK SAMPING
GAMBAR RENCANA
KABUPATEN
1,70
BANDUNG
KECAMATAN
...........................................
DESA
...........................................
JENIS PRASARANA
GEDUNG POSYANDU
LOKASI
...........................................
3,00
JUDUL GAMBAR
TAMPAK SAMPING
Digambar oleh:
Pelaksana Kegiatan
(Kader Teknik)
…………………………………..
Diperiksa dan Disetujui oleh:
…………………………………..
Lembar…..dari…..Lembar