Kabupaten : Bandung Jenis Kegiatan : Pembangunan Jembatan

Take off Sheet


Kecamatan : Ibun Lokasi : RW 02-08
Desa : Karyalaksana Volume : TPT = 3 m'
: Jembatan = 6,5 x 1,5 m

PERHITUNGAN PEKERJAAN TPT

La = 0.4 m

Plesteran
Tebal 2 cm
0.10 m

Ta = 2.50 m
Pas. Batu
Camp 1PC : 5PP

Tb = 0.50 m

Lb = 0.6 m P= 3m

1 Penggalian 1 m3 tanah biasa sedalam 1 m

TPT
T = 0.50 m Volume = T x L x P
0.50 m L = 0.60 m = 0.50 x 0.60 x 3
P = 3 m = 0.90 m3

0.60 m

Tenaga Kerja Koef Volume Jumlah Sat


Pekerja 0.750 1 1 Oh
Tukang - 1 - Oh

2 Pemasangan 1 m3 pondasi batu belah campuran 1PC : 5PP

0.40 TPT
Ta = 3.60 m Vol I = 0.40 + 0.60
3.60 3.0
La = 0.40 m 2
2.50 Lb 1 = 0.60 m = 5 m3
Lb = 0.60 m
P = 3 m
0.60
Ta = 3.30 m Vol II = 0.30 + 0.60
3.30 5.0
0.50 La = 0.30 m 2
Lb 1 = 0.60 m = 7 m3
0.60 Lb = 0.60 m
P = 5 m Volume I+II 13.9 m3

0.30
0.9 Lb 1
Ta = 0.90 Vol I = 0.30 + 0.30
0.90 1.0
La = 0.30 2
Lb = 0.30 = 1.08 m3
P = 1
0.30
Bahan Material Koef Volume Jumlah Sat
Batu Belah 1.200 14 17 m3 17
Semen PC @50 kg 2.720 14 38 sak 38
Pasir Pasang 0.544 14 8 m3 8

Tenaga Kerja Koef Volume Jumlah Sat 8 0.2


Pekerja 1.500 14 21 Oh 2 40
Tukang 0.750 14 10 Oh 10

3.1 Pemasangan Besi


Begel Ø 10
P= 16 Bahan Material Koef Volum Jumlah Sat
Ø 10 2
Besi Beton 10.700 16 16 Btg
Kawat Beton 2.520 16 4 Kg
Ø 10 2

Ø 10 2
Tenaga Kerja Koef Volume Jumlah Sat
Ø 10 4 Pekerja 1.250 16 2 HOK
Ø 10 4 Tukang 0.077 16 1 HOK
25
Tul Pokok 8 Ø10

Begel Ø 10

3.2 Pemasangan Bekisting

P= 6.5 Bahan Material Koef Volume Jumlah Sat


L= 1.5 Papan 0.245 0.975 0.239 m3
T= 0.1 Paku 0.150 0.975 0.146 Kg
0.975 Kayu Balok Albasia 0.070 0.975 0.068 m3
Besi WF 1.100 0.975 1.073 Btg

Tenaga Kerja Koef Volume Jumlah Sat


Pekerja 1.250 0.98 1.22 HOK
Tukang 0.077 0.98 0.08 HOK

3.3 Pengecoran Jembatan


P= 6.5 VOLUME
L= 1.5 1.0
1,5 m T= 0.1
0,10 m
Bahan Material Koef Volume Jumlah Sat
6,5 m Semen 6.520 1.0 6.357 Zak
Pasir Beton 0.563 1.0 0.549 m3
Split 0.792 1.0 0.772 m3

Tenaga Kerja Koef Volume Jumlah Sat


Pekerja 1.650 0.98 1.61 HOK
Tukang 0.725 0.98 0.71 HOK

Rekapitulasi:
1 Batu Belah = 17 ~ 17 m3
2 Semen = 44 ~ 44 Zak
3 Pasir Pasang = 8 ~ 8 m3
4 Besi Beton = 16 ~ 16 Btg
5 Kawat Besi = 4 ~ 4 Kg
6 Papan = 0.2 ~ - m3
7 Paku = 0.1 ~ 0.1 Kg
8 Kayu Balok Albasia = 0.1 ~ 0.1 m3
9 Besi WF = 1.1 ~ 1 Btg
10 Pipa Besi dia. 6.0 6 Btg
11 Pasir Beton = 0.549 ~ 1 m3
12 Split = 0.772 ~ 1 m3
13 Pekerja = 26.58 ~ 27 HOK
14 Tukang = 12.44 ~ 12 HOK
Pekerja Angkut Bahan
#REF! = 17 ~ 17
#REF! = 44 ~ 44
#REF! = 8 ~ 8
69 34.50 35
RENCANA ANGGARAN BIAYA F
o
KEGIATAN DANA DESA TA 2024 r
m
.
DESA : KARYALAKSANA Bidang : Pembangunan Desa 7
KECAMATAN : IBUN Kegiatan : Pembangunan Jembatan e
KABUPATEN : BANDUNG Lokasi : RW 02-08
PROVINSI : JAWA BARAT Volume : TPT = 3 m'
: Jembatan = 6,5 x 1,5 m

HARGA
URAIAN VOLUME SATUAN JUMLAH
SATUAN
a b c d e=bxd
1. BAHAN
1 Batu Belah 17 m3 240,000 4,080,000
2 Semen 44 Zak 75,000 3,300,000
3 Pasir Pasang 8 m3 250,000 2,000,000
4 Besi Beton 16 Btg 130,000 2,080,000
5 Kawat Besi 4 Kg 20,000 80,000
6 Papan 1 m3 1,500,000 1,500,000
7 Paku 1.0 Kg 25,000 25,000
8 Kayu Balok Albasia 1.0 m3 1,500,000 1,500,000
9 Besi WF 2 Btg 1,500,000 3,000,000
10 Pipa Besi dia. 12 Btg 450,000 5,400,000
11 Pasir Beton 1 m3 300,000 300,000
12 Split 1 m3 300,000 300,000
13 Bondek 4 Buah 820,000 3,280,000
Sub Total 1) Rp 26,845,000
2. ALAT
3 Papan Proyek 1 Buah 160,000 160,000
4 Prasasti 1 Buah 300,000 300,000
Sub Total 2) Rp 460,000
3. UPAH
1 Pekerja 27 HOK 112,000 3,024,000
2 Tukang 12 HOK 120,000 1,440,000
3 Upah Angkut Bahan 35 HOK 112,000 3,920,000
Sub Total 3) Rp 8,384,000
4. BIAYA UMUM
1 Survey Perencanaan 1 Ls 450,000 450,000
2 ATK Dokumen 1 Ls 250,000 250,000
3 Survey Pelaksanaan 1 Ls 450,000 450,000
4 ATK Pelaporan 1 Ls 250,000 250,000
Sub Total 4) Rp 1,400,000
Total Biaya Rp 37,089,000

Karyalaksana, ………..................…… 2024


Diperiksa Oleh : Pelaksana Kegiatan
Kepala Desa Karyalaksana Kasi Kesejahteraan

...................................... ......................................

Mengetahui : Mengetahui :
Tim Pendamping Desa Tim Teknis/Pendamping Kecamatan

GINGIN GINANJAR, ST ….................................


NIP. …....................................
GAMBAR RENCANA
SUMBER ANGGARAN
DANA DESA
Gambar Jalan Gambar Pondasi DESA KARYALAKSANA KECAMATAN IBUN
0,4 M 0,3 M
KAB. BANDUNG PROV. JABAR
2024
0,1 M
JENIS KEGIATAN
1,5 m
0,10 m PEMBANGUNAN JEMBATAN
LOKASI KEGIATAN
6,5 m I 2,5 M RW 02-08
II PELAKSANA KEGIATAN

III 0,50
M

0,1 M
0,6 M
,1 M
...................................
KEPALA DESA KARYALAKSANA

AEP JULI KARTIKA NUGRAHA

TIM TEKNIS KECAMATAN

….............................................
NIP. …...........................................
TIM TEKNIS KABUPATEN

...............................................................
NIP.
Catatan : Gambar dibuat secara manual