La = 0.3 m
Plesteran
Tebal 1,5 cm
0.10 m
Ta = 1.30 m
Pas. Batu
Camp 1PC : 5PP
Tb = 0.50 m
Lb = 0.6 m P= 113 m
TPT
T = 0.50 m Volume = T x L x P
0.50 m L = 0.60 m = 0.50 x 0.60 x 113.0
P = 113 m = 34 m3
0.60 m
0.30 TPT
Ta = 1.30 m Vol I = 0.30 + 0.60
1.30 113.0
La = 0.30 m 2
1.30 Lb = 0.60 m = 66 m3
P = 113 m
0.3
0.10 L = 0.40 m Volume = L x P
P = 113 m = 0.40 x 113
= 45 m2
4 Pemasangan 1 m2 acian
0.3
0.10 L = 0.40 m Volume = L x P
P = 113 m = 0.40 x 113
= 45 m2
UPAH ANGKUT
Bahan Material Koef Volume Jumlah Sat Jumlah
Batu Belah 0.75 120 90 55,000 4,950,000
Pasir Pasang 0.75 56 42 55,000 2,310,000 pembulatan
Jumlah 132 7,260,000 7,536,000
Sudi, …. ....................2023
Disetujui/Mengesahkan
Kepala Desa Sudi Pelaksana Kegiatan
Mengetahui/Menyetujui
Tim Verifikasi Gambar dan RAB
….....................................
NIP: …....................................
RENCANA ANGGARAN BIAYA (RAB)
DESA SUDI KECAMATAN IBUN
TAHUN ANGGARAN 2023
Bidang : Pembangunan Desa No.RAB :
Kegiatan : TPT Dana : Dana Desa
Waktu : Ukuran : 113x 0,35 x 1,8 m
Pelaksanaan : Lokasi : Jalan Usaha Tani
Sudi, ………...............2023
Disetujui/Mengesahkan
Kepala Desa Sudi Pelaksana Kegiatan
Mengetahui/Menyetujui
Tim Verifikasi Gambar dan RAB
…...........................................
NIP:….........................................
P 17.7 23 48.5 8.7 22.8 13.3 15.4 13
T 2.5 1.5 1 1 2 1.5 2 1.5
17 179.4
1.5 14.5 1.6111111
Dari Swadaya
Rp 34,768,000
Rp 34,768,000