U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 17.40 ) ( 2 x 11.00 ) = 56.80 m' 56.80 m'
0.3
0.5
0.75
0.3
0.5
0.8
Pondasi Utama Pondasi Selasar Depan Pondasi Selasar Belakang/Ram
b. Selasar Depan
Luas Urugan Tanah F= 31.32 m²
Tebal Urugan Tanah T= 55 cm
V2 = 31.32 x 0.55 = 17.226 m3
d. Ram n= 1 buah
Luas Urugan Tanah F= 7.74 m²
Tebal Urugan Tanah T= 40 cm
V4 (1 buah) = 7.74 x 0.40 x 1/2 = 1.548 m3
V4 (n buah) = 1.548 x 1 = 1.548 m3
e. Panggung n= 1 buah
Luas Urugan Tanah F= 5.75 m²
Tebal Urugan Tanah T= 20 cm
V5 (1 buah) = 5.75 x 0.20 = 1.15 m3
V5 (n buah) = 1.15 x 1 = 1.15 m3
30 20 20
90 95 95
80 40 40
Tampang I Tampang II Tampang III
---> Tampang I
Panjang Galian = P = 57.00 m
0.3 + 0.80
V1 = x 0.9 x 57.00 = 28.22 m3
2
---> Tampang II
Panjang Galian = P = 23.40 m
0.2 + 0.40
V2 = x 0.95 x 23.40 = 6.67 m3
2
b. Panggung n= 1 buah
Panjang Pasangan = P = 6.50 m T1 = 30 cm
F1 (1 buah) = 6.50 x 0.3 = 1.95 m²
F1 (n buah) = 1.95 x 1 = 1.95 m²
Total Luas Pasangan Pondasi Batu Bata
F total = F1 + F2 = 4.58 + 1.95 = 6.53 m² = 6.53 m²
0.40 0.40
0.92
1.32 2.16
1.05
0.8
0.69
1.52
Type V 4 Unit
2.8.
Type J4 5 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 0.92 x 2.32 x 3 = 6.4032 m²
Luas Kosen Type P2 F= 01.32 x 2.32 x 1 = 3.0624 m²
Luas Kosen Type J3 F= 2.16 x 1.52 x 2 = 6.5664 m²
Luas Kosen Type J4 F= 2.82 x 1.52 x 5 = 21.432 m²
Luas Kosen Type V1 F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 40.02 m²
Total Luas Pasangan Batu Bata 1 : 4
F total = Fpas. - FKosen = 243.03 - 40.02 = 203.013 m² 203.013 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 203.013 x 2 = 406.03 m² = 406.03 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 28.368 x 2 = 56.74 m² = 56.74 m²
2. Lantai Keramik 40 x 40 cm
Luas Pasangan Keramik 40 x 40 cm Ruang Dalam
Ukuran Bangunan : Jumlah Panjang Lebar Luas
Resume :
a. Kosen Jendela Type P1 = 0.17 m3
b. Kosen Jendela Type P2 = 0.068 m3
c. Kosen Jendela Type J3 = 0.196 m3
d. Kosen Ventilasi Type J4 = 0.626 m3
e. Kosen Ventilasi Type V = 0.109 m3
f. Kosen Lemari meja beton = 0.307 m3
Total Volume Kayu Kosen = 01.477 m3 1.477 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 82 x 210 n = 3 bh 3 bh
b. Type P2 Uk. 82 x 210 n = 1 bh 1 bh
c. Type P2 Uk. 40 x 210 n = 1 bh 1 bh
d. Pintu Meja Beton 60 x 55 n = 20 bh 20 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 17.40 m
Lebar Pasangan L = 6.26 m
F2 = 17.4 x 6.26 = 108.924 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 120.00 + 83.35 = 203.352 m² = 203.352 m²
13
e. Jendela Type J3
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 6 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 6 = 1.07328 m²
f. Jendela Type J4
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 20 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 20 = 3.5776 m²
Resume :
a. Pintu Type P1 = 12.05568 m²
b. Pintu Type P2 ukuran 82 x 210 cm = 3.58176 m²
c. Pintu Type P2 ukuran 40 x 210 cm = 1.7472 m²
d. Pintu Meja Beton = 13.728 m²
e. Jendela Type J3 = 1.07328 m²
f. Jendela Type J4 = 3.5776 m²
g. Jalusi Pintu, Jendela dan Tolak Angin = 23.716 m²
Total Volume Kayu Kosen = 59.47952 m² = 59.48 m²
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 17.40 ) ( 2 x 11.00 ) = 56.80 m' 56.80 m'
0.3
0.5
0.75
0.3
0.5
0.8
Pondasi Utama Pondasi Selasar Depan Pondasi Selasar Belakang/Ram
b. Selasar Depan
Luas Urugan Tanah F= 31.32 m²
Tebal Urugan Tanah T= 55 cm
V2 = 31.32 x 0.55 = 17.226 m3
d. Ram n= 1 buah
Luas Urugan Tanah F= 7.74 m²
Tebal Urugan Tanah T= 40 cm
V4 (1 buah) = 7.74 x 0.40 x 1/2 = 1.548 m3
V4 (n buah) = 1.548 x 1 = 1.548 m3
e. Panggung n= 1 buah
Luas Urugan Tanah F= 5.75 m²
Tebal Urugan Tanah T= 20 cm
V5 (1 buah) = 5.75 x 0.20 = 1.15 m3
V5 (n buah) = 1.15 x 1 = 1.15 m3
30 20 20
90 95 95
80 40 40
Tampang I Tampang II Tampang III
---> Tampang I
Panjang Galian = P = 57.00 m
0.3 + 0.80
V1 = x 0.9 x 57.00 = 28.22 m3
2
---> Tampang II
Panjang Galian = P = 23.40 m
0.2 + 0.40
V2 = x 0.95 x 23.40 = 6.67 m3
2
b. Panggung n= 1 buah
Panjang Pasangan = P = 6.50 m T1 = 30 cm
F1 (1 buah) = 6.50 x 0.3 = 1.95 m²
F1 (n buah) = 1.95 x 1 = 1.95 m²
Total Luas Pasangan Pondasi Batu Bata
F total = F1 + F2 = 4.58 + 1.95 = 6.53 m² = 6.53 m²
0.40 0.40
0.92
1.32 2.16
1.05
0.8
0.69
1.52
Type V 4 Unit
2.8.
Type J4 5 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 0.92 x 2.32 x 3 = 6.4032 m²
Luas Kosen Type P2 F= 01.32 x 2.32 x 1 = 3.0624 m²
Luas Kosen Type J3 F= 2.16 x 1.52 x 2 = 6.5664 m²
Luas Kosen Type J4 F= 2.82 x 1.52 x 5 = 21.432 m²
Luas Kosen Type V1 F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 40.02 m²
Total Luas Pasangan Batu Bata 1 : 4
F total = Fpas. - FKosen = 243.03 - 40.02 = 203.013 m² 203.013 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 203.013 x 2 = 406.03 m² = 406.03 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 33.768 x 2 = 67.54 m² = 67.54 m²
2. Lantai Keramik 40 x 40 cm
Luas Pasangan Keramik 40 x 40 cm Ruang Dalam
Ukuran Bangunan : Jumlah Panjang Lebar Luas
Resume :
a. Kosen Jendela Type P1 = 0.17 m3
b. Kosen Jendela Type P2 = 0.068 m3
c. Kosen Jendela Type J3 = 0.196 m3
d. Kosen Ventilasi Type J4 = 0.626 m3
e. Kosen Ventilasi Type V = 0.109 m3
f. Kosen Lemari meja beton = 0.307 m3
Total Volume Kayu Kosen = 01.477 m3 1.477 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 82 x 210 n = 3 bh 3 bh
b. Type P2 Uk. 82 x 210 n = 1 bh 1 bh
c. Type P2 Uk. 40 x 210 n = 1 bh 1 bh
d. Pintu Meja Beton 60 x 55 n = 20 bh 20 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 17.40 m
Lebar Pasangan L = 6.26 m
F2 = 17.4 x 6.26 = 108.924 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 120.00 + 83.35 = 203.352 m² = 203.352 m²
13
e. Jendela Type J3
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 6 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 6 = 1.07328 m²
f. Jendela Type J4
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 20 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 20 = 3.5776 m²
Resume :
a. Pintu Type P1 = 12.05568 m²
b. Pintu Type P2 ukuran 82 x 210 cm = 3.58176 m²
c. Pintu Type P2 ukuran 40 x 210 cm = 1.7472 m²
d. Pintu Meja Beton = 13.728 m²
e. Jendela Type J3 = 1.07328 m²
f. Jendela Type J4 = 3.5776 m²
g. Jalusi Pintu, Jendela dan Tolak Angin = 23.716 m²
Total Volume Kayu Kosen = 59.47952 m² = 59.48 m²
1 2 3
A. PEKERJAAN PERSIAPAN Rp 7,592,000.00
JUMLAH Rp 425,521,566.71
DIBULATKAN Rp 936,100,000.00
Terbilang : Sembilan Ratus Tiga Puluh Enam Juta Seratus Ribu Rupiah
IQBAL MUNAZAR, ST
Direktur
ENGINEERING ESTIMATE (EE)
1 Instalasi titik penerangan, instalasi termasuk kabel 27.000 Ttk Taksir 220,000.00 5,940,000.00
NYA 3 x 2,5 mm dalam pipa PVC fitting lampu dan
kelengkapan instalasi terpasang. -
2 Instalasi titik kontak, instalasi termasuk kabel NYA 4.000 Ttk Taksir 220,000.00 880,000.00
3 x 2,5 mm dalam pipa PVC, kotak kontak BROCO
dan kelengkapan instalasi terpasang.
3 Box sekring 1.000 bh Taksir 137,300.00 137,300.00
4 Lampu TL 40 watt 6.000 bh Taksir 108,000.00 648,000.00
5 Lampu HE 15 watt 21.000 bh Taksir 40,000.00 840,000.00
6 Saklar tunggal 3.000 bh Taksir 26,800.00 80,400.00
7 Saklar Ganda 6.000 bh Taksir 53,600.00 321,600.00
Jumlah 8,847,300.00
J. PEKERJAAN PENGECATAN
1 Cat dinding tembok (L/D) 509.510 m2 RSNI. T-38-2002-C-B14 26,700.00 13,603,917.00
2 Cat plafond dan list plafond 143.758 m2 RSNI. T-38-2002-C-B8 34,700.00 4,988,385.25
3 Cat mengkilat daun pintu/jendela & jalusi 21.975 m2 RSNI. T-38-2002-C-B8 34,700.00 762,539.44
Jumlah 19,354,841.69
K. PEKERJAAN SANITASI
1 Septictank 1.000 Unit Taksir 3,000,000.00 3,000,000.00
2 Resapan 1.000 Unit Taksir 1,500,000.00 1,500,000.00
3 Kloset Jongkok 2.000 Bh SNI 03-2839-2002-6.3 322,600.00 645,200.00
4 Floor Drain 2.000 Bh SNI 03-2839-2002-6.36 31,400.00 62,800.00
5 Kran Air 3/4" 2.000 Bh SNI 03-2839-2002-6.35 31,400.00 62,800.00
6 Bak mandi Fiberglass 2.000 Bh SNI 03-2839-2002-6.7 938,300.00 1,876,600.00
7 Pemasangan instalasi Pipa PVC 4" 10.000 m' SNI 03-2839-2002-6.24 109,800.00 1,098,000.00
8 Pemasangan instalasi air Kotor Pipa PVC 3" 10.000 m' SNI 03-2839-2002-6.23 59,100.00 591,000.00
9 Pemasangan instalasi air Bersih Pipa PVC 3/4" 15.000 m' SNI 03-2839-2002-6.20 19,400.00 291,000.00
10 Pemasangan Pipa Air hujan dari talang pipa PVC 3 " 20.800 m' SNI 03-2839-2002-6.23 59,100.00 1,229,280.00
11 Box Control 60 x 60 1.000 Bh SNI 03-2839-2002-6.18 338,300.00 338,300.00
Jumlah 10,694,980.00
L. PEKERJAAN LAIN - LAIN
1 Finishing 1.000 Ls Taksir 505,000.00 505,000.00
Jumlah 505,000.00
DAFTAR ANALISA HARGA SATUAN
I PEKERJAAN PERSIAPAN
SNI 03-2835-2002-6.4
1 m' Pengukuran dan pemasangan bouwplank
- Kayu 5/7 0.012 M3 x Rp. 4,400,000.00 = Rp. 52,800.00
- Paku Kayu 2"-5" 0.020 Kg x Rp. 13,000.00 = Rp. 260.00
- Kayu Papan Bouwplank 3/20 0.007 M3 x Rp. 3,840,000.00 = Rp. 26,880.00
- Pekerja 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Tukang 0.100 Oh x Rp. 90,000.00 = Rp. 9,000.00
- Kepala Tukang 0.010 Oh x Rp. 110,000.00 = Rp. 1,100.00
- Mandor 0.005 Oh x Rp. 80,000.00 = Rp. 400.00
Jumlah = Rp. 96,440.00
Dibulatkan = Rp. 96,000.00
SNI 03-2835-2002-6.8
1 m2 Membersihkan Lapangan dan Perataan
- Pekerja 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Mandor 0.050 Oh x Rp. 80,000.00 = Rp. 4,000.00
Jumlah = Rp. 10,000.00
Dibulatkan = Rp. 10,000.00
II PEKERJAAN TANAH
SNI 03-2835-2002-6.1
1 M3 Galian tanah biasa sedalam 1 meter
- Pekerja 0.400 Oh x Rp. 60,000.00 = Rp. 24,000.00
- Mandor 0.040 Oh x Rp. 80,000.00 = Rp. 3,200.00
Jumlah = Rp. 27,200.00
Dibulatkan Rp 27,200.00
SNI 03-2835-2002-6.9
1 M3 Urugan kembali tanah bekas galian
- Pekerja 0.192 Oh x Rp. 60,000.00 = Rp. 11,520.00
- Mandor 0.019 Oh x Rp. 80,000.00 = Rp. 1,520.00
Jumlah = Rp. 13,040.00
Dibulatkan Rp 13,000.00
SNI 03-2835-2002-6.11.b
1 M3 Urugan Tanah bawah lantai
- Tanah Timbun/Urug 1.200 M3 x Rp. 55,000.00 Rp 66,000.00
- Pekerja 0.300 Oh x Rp. 60,000.00 Rp 18,000.00
- Mandor 0.010 Oh x Rp. 80,000.00 Rp 800.00
Jumlah Rp 84,800.00
Dibulatkan Rp 84,800.00
SNI 03-2835-2002-6.11.a
1 M3 Urugan pasir
- Pasir urug 1.200 M3 x Rp. 117,000.00 = Rp. 140,400.00
- Pekerja 0.300 Oh x Rp. 60,000.00 = Rp. 18,000.00
- Mandor 0.010 Oh x Rp. 80,000.00 = Rp. 800.00
Jumlah = Rp. 159,200.00
Dibulatkan = Rp. 159,200.00
IV PEKERJAAN BETON
SNI DT-91-0008-2007-6.5
1 M3 Beton mutu f'c = 14,5 Mpa (K175), slump (12 ± 2) cm, w/c = 0,68
- Pasir Beton 760.000 Kg x Rp. 107.14 = Rp. 81,428.57
- Kerikil Beton (Maximum 30 mm) 1,029.000 Kg x Rp. 74.07 = Rp. 76,222.22
- Semen Portland 326.000 Kg x Rp. 1,050.00 = Rp. 342,300.00
- Air 120.000 Liter x Rp. 120.00 = Rp. 14,400.00
- Pekerja 1.650 OH x Rp. 60,000.00 = Rp. 99,000.00
- Tukang 0.275 OH x Rp. 90,000.00 = Rp. 24,750.00
- Kepala Tukang 0.028 OH x Rp. 110,000.00 = Rp. 3,080.00
- Mandor 0.083 OH x Rp. 80,000.00 = Rp. 6,640.00
Jumlah = Rp. 647,820.79
Dibulatkan = Rp. 647,800.00
SNI DT-91-0008-2007-6.8
1 M3 Beton mutu f'c = 12,7 Mpa (K250), slump (12 ± 2) cm, w/c = 0,56
- Pasir Beton 692.000 Kg x Rp. 107.14 = Rp. 74,142.86
- Kerikil Beton (Maximum 30 mm) 1,039.000 Kg x Rp. 74.07 = Rp. 76,962.96
- Semen Portland 384.000 Kg x Rp. 1,050.00 = Rp. 403,200.00
- Air 120.000 Liter x Rp. 120.00 = Rp. 14,400.00
- Pekerja 1.650 OH x Rp. 60,000.00 = Rp. 99,000.00
- Tukang 0.275 OH x Rp. 90,000.00 = Rp. 24,750.00
- Kepala Tukang 0.028 OH x Rp. 110,000.00 = Rp. 3,080.00
- Mandor 0.083 OH x Rp. 80,000.00 = Rp. 6,640.00
Jumlah = Rp. 702,175.82
Dibulatkan = Rp. 702,100.00
SNI DT-91-0008-2007-6.6
1 M3 Beton mutu f'c = 12,7 Mpa (K200), slump (12 ± 2) cm, w/c = 0,61
- Pasir Beton 731.000 Kg x Rp. 107.14 = Rp. 78,321.43
- Kerikil Beton (Maximum 30 mm) 1,031.000 Kg x Rp. 74.07 = Rp. 76,370.37
- Semen Portland 352.000 Kg x Rp. 1,050.00 = Rp. 369,600.00
- Air 120.000 Liter x Rp. 120.00 = Rp. 14,400.00
- Pekerja 1.650 OH x Rp. 60,000.00 = Rp. 99,000.00
- Tukang 0.275 OH x Rp. 90,000.00 = Rp. 24,750.00
- Kepala Tukang 0.028 OH x Rp. 110,000.00 = Rp. 3,080.00
Mandor 0.083 OH x Rp. 80,000.00 = Rp. 6,640.00
Jumlah = Rp. 672,161.80
Dibulatkan = Rp. 672,100.00
SNI DT-91-0008-2007-6.17
1 Kg Pembesian dengan besi polos
- Besi beton polos 1.050 Kg x Rp. 10,000.00 = Rp. 10,500.00
- Kawat beton 0.050 Kg x Rp. 16,000.00 = Rp. 800.00
- Pekerja 0.007 Oh x Rp. 120.00 = Rp. 0.84
- Tukang 0.007 Oh x Rp. 60,000.00 = Rp. 420.00
- Kepala tukang 0.001 Oh x Rp. 90,000.00 = Rp. 63.00
- Mandor 0.000 Oh x Rp. 110,000.00 = Rp. 44.00
Jumlah = Rp. 11,827.84
Dibulatkan = Rp. 11,800.00
SNI DT-91-0008-2007-6.18
1 Kg Pembesian dengan besi ulir
- Besi beton ulir 1.050 Kg x Rp. 11,000.00 = Rp. 11,550.00
- Kawat beton 0.050 Kg x Rp. 16,000.00 = Rp. 800.00
- Pekerja 0.007 Oh x Rp. 120.00 = Rp. 0.84
- Tukang 0.007 Oh x Rp. 60,000.00 = Rp. 420.00
- Kepala tukang 0.001 Oh x Rp. 90,000.00 = Rp. 63.00
- Mandor 0.000 Oh x Rp. 110,000.00 = Rp. 44.00
Jumlah = Rp. 12,877.84
Dibulatkan = Rp. 12,800.00
SNI DT-91-0008-2007-6.20
1 M² Pasang bekisting untuk pondasi
- Kayu Bekisting 0.040 M³ x Rp. 4,400,000.00 = Rp. 176,000.00
- Paku Kayu 0.300 Kg x Rp. 13,000.00 = Rp. 3,900.00
- Minyak bekisting 0.100 Lt x Rp. 9,400.00 = Rp. 940.00
- Pekerja 0.520 Oh x Rp. 120.00 = Rp. 62.40
- Tukang 0.260 Oh x Rp. 60,000.00 = Rp. 15,600.00
- Kepala tukang 0.026 Oh x Rp. 90,000.00 = Rp. 2,340.00
- Mandor 0.026 Oh x Rp. 110,000.00 = Rp. 2,860.00
Jumlah = Rp. 201,702.40
Digunakan 2 kali pakai 100,851.20
Dibulatkan = Rp. 100,800.00
SNI DT-91-0008-2007-6.21
1 M² Pasang bekisting untuk sloof
- Kayu Bekisting 0.045 M³ x Rp. 4,400,000.00 = Rp. 198,000.00
- Paku Kayu 0.300 Kg x Rp. 13,000.00 = Rp. 3,900.00
- Minyak bekisting 0.100 Lt x Rp. 9,400.00 = Rp. 940.00
- Pekerja 0.520 Oh x Rp. 120.00 = Rp. 62.40
- Tukang 0.260 Oh x Rp. 60,000.00 = Rp. 15,600.00
- Kepala tukang 0.026 Oh x Rp. 90,000.00 = Rp. 2,340.00
- Mandor 0.026 Oh x Rp. 110,000.00 = Rp. 2,860.00
Jumlah = Rp. 223,702.40
Digunakan 2 kali pakai 111,851.20
Dibulatkan = Rp. 111,800.00
SNI DT-91-0008-2007-6.22
1 M² Pasang bekisting untuk kolom
- Kayu Bekisting 0.055 M³ x Rp. 4,400,000.00 = Rp. 242,000.00
- Paku Kayu 0.400 Kg x Rp. 13,000.00 = Rp. 5,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,400.00 = Rp. 1,880.00
- Multiplek tebal 9 mm 0.350 Lbr x Rp. 182,400.00 = Rp. 63,840.00
- Dolken kayu ø 8 - 10 x 4 m 2.000 Btg x Rp. 14,400.00 = Rp. 28,800.00
- Pekerja 0.660 Oh x Rp. 120.00 = Rp. 79.20
- Tukang 0.330 Oh x Rp. 60,000.00 = Rp. 19,800.00
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp. 2,970.00
- Mandor 0.033 Oh x Rp. 110,000.00 = Rp. 3,630.00
Jumlah = Rp. 368,199.20
Digunakan 2 kali pakai 184,099.60
Dibulatkan = Rp. 184,000.00
SNI DT-91-0008-2007-6.23
1 M² Pasang bekisting untuk balok
- Kayu bekisting 0.058 M³ x Rp. 4,400,000.00 = Rp. 255,200.00
- Paku Kayu 0.400 Kg x Rp. 13,000.00 = Rp. 5,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,400.00 = Rp. 1,880.00
- Multiplek tebal 9 mm 0.350 Lbr x Rp. 182,400.00 = Rp. 63,840.00
- Dolken kayu ø 8 - 10 x 4 m 2.000 Btg x Rp. 14,400.00 = Rp. 28,800.00
- Pekerja 0.660 Oh x Rp. 120.00 = Rp. 79.20
- Tukang 0.330 Oh x Rp. 60,000.00 = Rp. 19,800.00
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp. 2,970.00
- Mandor 0.033 Oh x Rp. 110,000.00 = Rp. 3,630.00
Jumlah = Rp. 381,399.20
Digunakan 2 kali pakai 190,699.60
Dibulatkan = Rp. 190,600.00
SNI DT-91-0008-2007-6.24
1 M² Pasang bekisting untuk lantai
- Kayu bekisting 0.055 M³ x Rp. 4,400,000.00 = Rp. 242,000.00
- Paku Kayu 0.400 Kg x Rp. 13,000.00 = Rp. 5,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,400.00 = Rp. 1,880.00
- Multiplek tebal 9 mm 0.350 Lbr x Rp. 182,400.00 = Rp. 63,840.00
- Dolken kayu ø 8 - 10 x 4 m 6.000 Btg x Rp. 14,400.00 = Rp. 86,400.00
- Pekerja 0.660 Oh x Rp. 120.00 = Rp. 79.20
- Tukang 0.330 Oh x Rp. 60,000.00 = Rp. 19,800.00
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp. 2,970.00
- Mandor 0.033 Oh x Rp. 110,000.00 = Rp. 3,630.00
Jumlah = Rp. 425,799.20
Digunakan 2 kali pakai 212,899.60
Dibulatkan = Rp. 212,800.00
SNI DT-91-0008-2007-6.25
1 M² Pasang bekisting untuk tangga
- Kayu bekisting 0.045 M³ x Rp. 4,400,000.00 = Rp. 198,000.00
- Paku Kayu 0.400 Kg x Rp. 13,000.00 = Rp. 5,200.00
- Minyak bekisting 0.150 Lt x Rp. 9,400.00 = Rp. 1,410.00
- Multiplek tebal 9 mm 0.350 Lbr x Rp. 182,400.00 = Rp. 63,840.00
- Dolken kayu ø 8 - 10 x 4 m 2.000 Btg x Rp. 14,400.00 = Rp. 28,800.00
- Pekerja 0.660 Oh x Rp. 120.00 = Rp. 79.20
- Tukang 0.330 Oh x Rp. 60,000.00 = Rp. 19,800.00
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp. 2,970.00
- Mandor 0.033 Oh x Rp. 110,000.00 = Rp. 3,630.00
Jumlah = Rp. 323,729.20
Digunakan 2 kali pakai 161,864.60
Dibulatkan = Rp. 161,800.00
Pekerjaan lain-lain
- Membongkar dan menyiram beton (Pekerja) 1.000 Ls x Rp. 120.00 = Rp. 120.00
Jumlah = Rp. 120.00
Dibulatkan = Rp. 100.00
Suplemen 2
1 m3 Beton bertulang sloof 20 x 25 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 187.300 kg x Rp. 11,800.00 = Rp. 2,210,140.00
- SNI DT-91-0008-2007-6.21 5.000 m2 x Rp. 111,800.00 = Rp. 559,000.00
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 3,471,340.00
Dibulatkan = Rp. 3,471,300.00
Suplemen 3
1 m3 Beton bertulang kolom Pedestal 30 x 30 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 143.600 kg x Rp. 11,800.00 = Rp. 1,694,480.00
- SNI DT-91-0008-2007-6.22 6.667 m2 x Rp. 184,000.00 = Rp. 1,226,666.67
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 3,623,346.67
Dibulatkan = Rp. 3,623,300.00
Suplemen 5
1 m3 Beton bertulang kolom 30 x 30 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 143.600 kg x Rp. 11,800.00 = Rp. 1,694,480.00
- SNI DT-91-0008-2007-6.22 6.667 m2 x Rp. 184,000.00 = Rp. 1,226,666.67
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 3,623,346.67
Dibulatkan = Rp. 3,623,300.00
Suplemen 6
1 m3 Beton bertulang kolom 13 x 13 cm
- SNI DT-91-0008-2007-6.5 1.000 m3 x Rp. 647,800.00 = Rp. 647,800.00
- SNI DT-91-0008-2007-6.17 105.000 kg x Rp. 11,800.00 = Rp. 1,239,000.00
- SNI DT-91-0008-2007-6.22 7.692 m2 x Rp. 184,000.00 = Rp. 1,415,384.62
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 3,302,284.62
Dibulatkan = Rp. 3,302,200.00
Suplemen 7
1 m3 Beton balok latai 13 x 15 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 206.100 kg x Rp. 11,800.00 = Rp. 2,431,980.00
- SNI DT-91-0008-2007-6.23 7.350 m2 x Rp. 190,600.00 = Rp. 1,400,991.45
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 4,535,171.45
Dibulatkan = Rp. 4,535,100.00
Suplemen 8
1 m3 Beton balok latai 15 x 20 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 172.300 kg x Rp. 11,800.00 = Rp. 2,033,140.00
- SNI DT-91-0008-2007-6.23 9.167 m2 x Rp. 190,600.00 = Rp. 1,747,166.67
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 4,482,506.67
Dibulatkan = Rp. 4,482,500.00
Suplemen 9
1 m3 Beton bertulang ring balok 20 x 35 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 216.200 kg x Rp. 11,800.00 = Rp. 2,551,160.00
- SNI DT-91-0008-2007-6.23 6.429 m2 x Rp. 190,600.00 = Rp. 1,225,285.71
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 4,478,645.71
Dibulatkan = Rp. 4,478,600.00
Suplemen 10
1 m3 Beton bertulang plat sunwearing tebal 12 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 105.100 kg x Rp. 11,800.00 = Rp. 1,240,180.00
- SNI DT-91-0008-2007-6.23 8.333 m2 x Rp. 190,600.00 = Rp. 1,588,333.33
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 3,530,713.33
Dibulatkan = Rp. 3,530,700.00
Suplemen 11
1 m3 Beton bertulang plat lantai tebal 15 cm
- SNI DT-91-0008-2007-6.8 1.000 m3 x Rp. 702,100.00 = Rp. 702,100.00
- SNI DT-91-0008-2007-6.17 86.800 kg x Rp. 11,800.00 = Rp. 1,024,240.00
- SNI DT-91-0008-2007-6.23 6.667 m2 x Rp. 190,600.00 = Rp. 1,270,666.67
- Pekerjaan lain-lain 1.000 ls x Rp. 100.00 = Rp. 100.00
Jumlah = Rp. 2,997,106.67
Dibulatkan = Rp. 2,997,100.00
V PEKERJAAN DINDING
SNI 03-2837-2002-6.9
1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps
- Batu bata 70.000 Bh x Rp. 800.00 = Rp. 56,000.00
- Semen portland 18.950 Kg x Rp. 1,050.00 = Rp. 19,897.50
- Pasir pasang 0.038 M3 x Rp. 150,000.00 = Rp. 5,700.00
- Pekerja 0.320 Oh x Rp. 120.00 = Rp. 38.40
- Tukang 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 Oh x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.015 Oh x Rp. 110,000.00 = Rp. 1,650.00
Jumlah = Rp. 90,185.90
Dibulatkan = Rp. 90,100.00
SNI 03-2837-2002-6.11
1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
- Batu bata 70.000 Bh x Rp. 800.00 = Rp. 56,000.00
- Semen portland 11.500 Kg x Rp. 1,050.00 = Rp. 12,075.00
- Pasir pasang 0.043 M3 x Rp. 150,000.00 = Rp. 6,450.00
- Pekerja 0.320 Oh x Rp. 120.00 = Rp. 38.40
- Tukang 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 Oh x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.015 Oh x Rp. 110,000.00 = Rp. 1,650.00
Jumlah = Rp. 83,113.40
Dibulatkan = Rp. 83,100.00
VI PEKERJAAN PLESTERAN
SNI 03-2837-2002-6.2
1 M2 Plesteran 1 Pc : 2 Ps, tebal 15 mm
- Semen portland 8.520 Kg x Rp. 1,050.00 = Rp. 8,946.00
- Pasir pasang 0.017 M3 x Rp. 150,000.00 = Rp. 2,550.00
- Pekerja 0.200 Oh x Rp. 120.00 = Rp. 24.00
- Tukang 0.150 Oh x Rp. 60,000.00 = Rp. 9,000.00
- Kepala Tukang 0.015 Oh x Rp. 90,000.00 = Rp. 1,350.00
- Mandor 0.010 Oh x Rp. 110,000.00 = Rp. 1,100.00
Jumlah = Rp. 22,970.00
Dibulatkan = Rp. 22,900.00
SNI 03-2837-2002-6.4
1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
- Semen portland 5.200 Kg x Rp. 1,050.00 = Rp. 5,460.00
- Pasir pasang 0.020 M3 x Rp. 150,000.00 = Rp. 3,000.00
- Pekerja 0.200 Oh x Rp. 120.00 = Rp. 24.00
- Tukang 0.150 Oh x Rp. 60,000.00 = Rp. 9,000.00
- Kepala Tukang 0.015 Oh x Rp. 90,000.00 = Rp. 1,350.00
- Mandor 0.010 Oh x Rp. 110,000.00 = Rp. 1,100.00
Jumlah = Rp. 19,934.00
Dibulatkan = Rp. 19,900.00
SNI 03-3434-2002-6.8
Membuat dan Memasang 1 M2 Daun Pintu Panel kayu kelas I, atau II
- Papan Kayu 0.040 M3 x Rp. 4,400,000.00 = Rp. 176,000.00
- Pekerja 1.000 OH x Rp. 120.00 = Rp. 120.00
- Tukang 2.500 OH x Rp. 60,000.00 = Rp. 150,000.00
- Kepala Tukang 0.250 OH x Rp. 90,000.00 = Rp. 22,500.00
- Mandor 0.050 OH x Rp. 110,000.00 = Rp. 5,500.00
Jumlah = Rp. 354,120.00
Dibulatkan = Rp. 354,100.00
SNI 03-3434-2002-6.10
Membuat dan memasang 1 m2 jendela kaca
- Kaca 5 mm 1.000 M2 x Rp. 128,400.00 = Rp. 128,400.00
- Papan Kayu 0.035 M3 x Rp. 4,400,000.00 = Rp. 154,000.00
- Pekerja 0.800 OH x Rp. 120.00 = Rp. 96.00
- Tukang 2.000 OH x Rp. 60,000.00 = Rp. 120,000.00
- Kepala Tukang 0.200 OH x Rp. 90,000.00 = Rp. 18,000.00
- Mandor 0.040 OH x Rp. 110,000.00 = Rp. 4,400.00
Jumlah = Rp. 424,896.00
Dibulatkan = Rp. 424,800.00
VIII PEKERJAAN PENUTUP LANTAI
SNI 03-2842-2002-6.44
1 M2 Pasang lantai keramik anti slip 20 x 20 cm
- Keramik 20 x 20 cm 25.000 bh x Rp. 1,800.00 = Rp. 45,000.00
- Semen portland 11.380 Kg x Rp. 1,050.00 = Rp. 11,949.00
- Pasir pasang 0.042 M3 x Rp. 150,000.00 = Rp. 6,300.00
- Semen warna 1.500 Kg x Rp. 2,640.00 = Rp. 3,960.00
- Pekerja 0.620 Oh x Rp. 120.00 = Rp. 74.40
- Tukang 0.350 Oh x Rp. 60,000.00 = Rp. 21,000.00
- Kepala tukang 0.035 Oh x Rp. 90,000.00 = Rp. 3,150.00
- Mandor 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00
Jumlah = Rp. 94,733.40
Dibulatkan = Rp. 94,700.00
SNI 03-2842-2002-6.68
1 M2 Pasang dinding keramik 20 x 25 cm
- Keramik 20 x 25 cm 20.000 bh x Rp. 2,250.00 = Rp. 45,000.00
- Semen portland 9.300 Kg x Rp. 1,050.00 = Rp. 9,765.00
- Pasir pasang 0.018 M3 x Rp. 150,000.00 = Rp. 2,700.00
- Semen warna 1.500 Kg x Rp. 2,640.00 = Rp. 3,960.00
- Pekerja 0.600 Oh x Rp. 120.00 = Rp. 72.00
- Tukang 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Kepala tukang 0.045 Oh x Rp. 90,000.00 = Rp. 4,050.00
- Mandor 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00
Jumlah = Rp. 74,847.00
Dibulatkan = Rp. 74,800.00
SNI 03-2842-2002-6.47
1 M2 Pasang Lantai keramik 40 x 40 cm
- Keramik 40 x 40 cm 6.250 bh x Rp. 10,333.33 = Rp. 64,583.33
- Semen portland 11.380 Kg x Rp. 1,050.00 = Rp. 11,949.00
- Pasir pasang 0.042 M3 x Rp. 150,000.00 = Rp. 6,300.00
- Semen warna 1.500 Kg x Rp. 2,640.00 = Rp. 3,960.00
- Pekerja 0.620 Oh x Rp. 120.00 = Rp. 74.40
- Tukang 0.350 Oh x Rp. 60,000.00 = Rp. 21,000.00
- Kepala tukang 0.035 Oh x Rp. 90,000.00 = Rp. 3,150.00
- Mandor 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00
Jumlah = Rp. 114,316.73
Dibulatkan = Rp. 114,300.00
SNI 03-2842-2002-6.37
Memasang 1 M' Plint Keramik 10 x 40 cm
- Plint Keramik 10 x 40 cm 5.000 bh x Rp. 30,000.00 = Rp. 150,000.00
- Semen portland 1.650 Kg x Rp. 1,050.00 = Rp. 1,732.50
- Pasir pasang 0.003 M3 x Rp. 150,000.00 = Rp. 480.00
- Semen warna 0.100 Kg x Rp. 2,640.00 = Rp. 264.00
- Pekerja 0.090 Oh x Rp. 120.00 = Rp. 10.80
- Tukang 0.090 Oh x Rp. 60,000.00 = Rp. 5,400.00
- Kepala tukang 0.009 Oh x Rp. 90,000.00 = Rp. 810.00
- Mandor 0.0045 Oh x Rp. 110,000.00 = Rp. 495.00
Jumlah = Rp. 159,192.30
Dibulatkan = Rp. 159,100.00
IX PEKERJAAN LANGIT-LANGIT
SNI DT 91-0013-2007-6.5
Memasang 1 M2 Langit-langit Tripleks 4 mm+ rangka
- Paku tripleks 0.060 Kg x Rp. 13,000.00 = Rp. 780.00
- Rangka kayu/kaso-kaso 0.012 M3 x Rp. 4,400,000.00 = Rp. 52,800.00
- Triplek 4 mm 0.375 Lembar x Rp. 108,000.00 = Rp. 40,500.00
- Pekerja 0.100 OH x Rp. 120.00 = Rp. 12.00
- Tukang 0.100 OH x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 OH x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.004 OH x Rp. 110,000.00 = Rp. 440.00
Jumlah = Rp. 101,432.00
Dibulatkan = Rp. 101,400.00
SNI 03-2838-2002-6.19
1 M' Pasang List langit-langit kayu profil
- List Profil kayu 1.100 m' x Rp. 8,000.00 = Rp. 8,800.00
- Paku 0.010 Kg x Rp. 13,000.00 = Rp. 130.00
- Pekerja 0.050 Oh x Rp. 120.00 = Rp. 6.00
- Tukang kayu 0.050 Oh x Rp. 60,000.00 = Rp. 3,000.00
- Kepala tukang 0.005 Oh x Rp. 90,000.00 = Rp. 450.00
- Mandor 0.003 Oh x Rp. 110,000.00 = Rp. 330.00
Jumlah = Rp. 12,716.00
Dibulatkan = Rp. 12,700.00
SNI 03-3436-2002-6.32
1 M² Pasang Atap Seng Genteng Metal
- Atap Seng Genteng Metal 0.30 1.020 Lbr x Rp. 60,000.00 = Rp. 61,200.00
- Baut Reng 11.000 Buah x Rp. 6,000.00 = Rp. 66,000.00
- Pekerja 0.200 Oh x Rp. 120.00 = Rp. 24.00
- Tukang 0.100 Oh x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 Oh x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.001 Oh x Rp. 110,000.00 = Rp. 110.00
Jumlah = Rp. 134,234.00
Dibulatkan = Rp. 134,200.00
SNI 03-3436-2002-6.22
1 M¹ Pasang Rabung Seng Genteng Metal
- Bubungan Seng Genteng 0.35 1.000 Lbr x Rp. 60,000.00 = Rp. 60,000.00
- Baut Reng 6.000 Buah x Rp. 6,000.00 = Rp. 36,000.00
- Pekerja 0.084 Oh x Rp. 120.00 = Rp. 10.08
- Tukang 0.125 Oh x Rp. 60,000.00 = Rp. 7,500.00
- Kepala Tukang 0.013 Oh x Rp. 90,000.00 = Rp. 1,170.00
- Mandor 0.004 Oh x Rp. 110,000.00 = Rp. 440.00
Jumlah = Rp. 105,120.08
Dibulatkan = Rp. 105,100.00
SNI 03-2839-2002-6.20
Memasang 1 M' Pipa PVC tipe AW Ø 3/4"
- Pipa PVC Ø 3/4" 1.200 M' x Rp. 7,750.00 = Rp. 9,300.00
- Harga pipa utk Perlengkapan 35.000 % x Rp. 2,712.50 = Rp. 949.38
- Pekerja 0.054 OH x Rp. 120.00 = Rp. 6.48
- Tukang 0.090 OH x Rp. 60,000.00 = Rp. 5,400.00
- Kepala Tukang 0.009 OH x Rp. 90,000.00 = Rp. 810.00
- Mandor 0.027 OH x Rp. 110,000.00 = Rp. 2,970.00
Jumlah = Rp. 19,435.86
Dibulatkan = Rp. 19,400.00
SNI 03-2839-2002-6.23
Memasang 1 M' Pipa PVC tipe AW Ø 3"
- Pipa PVC tipe AW Ø 3" 1.200 M' x Rp. 34,850.00 = Rp. 41,820.00
- Harga pipa utk Perlengkapan 35.000 % x Rp. 12,197.50 = Rp. 4,269.13
- Pekerja 0.108 OH x Rp. 120.00 = Rp. 12.96
- Tukang 0.180 OH x Rp. 60,000.00 = Rp. 10,800.00
- Kepala Tukang 0.018 OH x Rp. 90,000.00 = Rp. 1,620.00
- Mandor 0.0054 OH x Rp. 110,000.00 = Rp. 594.00
Jumlah = Rp. 59,116.09
Dibulatkan = Rp. 59,100.00
SNI 03-2839-2002-6.24
Memasang 1 M' Pipa PVC tipe AW Ø 4"
- Pipa PVC tipe AW Ø 3" 1.200 M' x Rp. 70,750.00 = Rp. 84,900.00
- Harga pipa utk Perlengkapan 35.000 % x Rp. 24,762.50 = Rp. 8,666.88
- Pekerja 0.135 OH x Rp. 120.00 = Rp. 16.20
- Tukang 0.225 OH x Rp. 60,000.00 = Rp. 13,500.00
- Kepala Tukang 0.023 OH x Rp. 90,000.00 = Rp. 2,025.00
- Mandor 0.007 OH x Rp. 110,000.00 = Rp. 748.00
Jumlah = Rp. 109,856.08
Dibulatkan = Rp. 109,800.00
SNI 03-2839-2002-6.35
Memasang 1 Buah Kran Ø ¾" atau Ø ½"
- Kran Air 1.000 Buah x Rp. 23,700.00 = Rp. 23,700.00
- Seal Tape 0.025 Buah x Rp. 11,000.00 = Rp. 275.00
- Pekerja 0.010 OH x Rp. 120.00 = Rp. 1.20
- Tukang 0.100 OH x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 OH x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.005 OH x Rp. 110,000.00 = Rp. 550.00
Jumlah = Rp. 31,426.20
Dibulatkan = Rp. 31,400.00
SNI 03-2839-2002-6.36
Memasang 1 Buah Floor Drain
- Floor Drain 1.000 Buah x Rp. 24,000.00 = Rp. 24,000.00
- Pekerja 0.010 OH x Rp. 120.00 = Rp. 1.20
- Tukang 0.100 OH x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 OH x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.005 OH x Rp. 110,000.00 = Rp. 550.00
Jumlah = Rp. 31,451.20
Dibulatkan = Rp. 31,400.00
SNI 03-2839-2002-6.18
Memasang 1 Buah Bak Kontrol Batu Bata Ukuran 60 x 60 cm, Tebal = 65 cm
- Batu Bata 108.000 Bh x Rp. 800.00 = Rp. 86,400.00
- Batu Koral 0.033 M³ x Rp. 120,000.00 = Rp. 3,960.00
- Besi Beton 4.850 Kg x Rp. 10,000.00 = Rp. 48,500.00
- Pasir Beton 0.120 M³ x Rp. 150,000.00 = Rp. 18,000.00
- Semend Porland 114.000 Kg x Rp. 1,050.00 = Rp. 119,700.00
- Pekerja 2.160 Oh x Rp. 120.00 = Rp. 259.20
- Tukang 0.720 Oh x Rp. 60,000.00 = Rp. 43,200.00
- Kepala Tukang 0.072 Oh x Rp. 90,000.00 = Rp. 6,480.00
- Mandor 0.108 Oh x Rp. 110,000.00 = Rp. 11,880.00
Jumlah = Rp. 338,379.20
Dibulatkan = Rp. 338,300.00
RSNI T-30-2002-B.5
1 Buah Engsel Pintu
- Engsel Pintu 1.000 Buah x Rp. 42,000.00 = Rp. 42,000.00
- Pekerja 0.015 OH x Rp. 120.00 = Rp. 1.80
- Tukang 0.150 OH x Rp. 60,000.00 = Rp. 9,000.00
- Kepala Tukang 0.015 OH x Rp. 90,000.00 = Rp. 1,350.00
- Mandor 0.001 OH x Rp. 110,000.00 = Rp. 82.50
Jumlah = Rp. 52,434.30
Dibulatkan = Rp. 52,400.00
RSNI T-30-2002-B.6
1 Buah Engsel Jendela Kupu - kupu
- Engsel Jendela 1.000 Buah x Rp. 30,000.00 = Rp. 30,000.00
- Pekerja 0.010 OH x Rp. 120.00 = Rp. 1.20
- Tukang 0.100 OH x Rp. 60,000.00 = Rp. 6,000.00
- Kepala Tukang 0.010 OH x Rp. 90,000.00 = Rp. 900.00
- Mandor 0.001 OH x Rp. 110,000.00 = Rp. 55.00
Jumlah = Rp. 36,956.20
Dibulatkan = Rp. 36,900.00
RSNI T-30-2002-B.9
1 Buah Kait Angin Jendela
- Kait Angin 1.000 Buah x Rp. 7,200.00 = Rp. 7,200.00
- Pekerja 0.015 OH x Rp. 120.00 = Rp. 1.80
- Tukang 0.150 OH x Rp. 60,000.00 = Rp. 9,000.00
- Kepala Tukang 0.015 OH x Rp. 90,000.00 = Rp. 1,350.00
- Mandor 0.001 OH x Rp. 110,000.00 = Rp. 82.50
Jumlah = Rp. 17,634.30
Dibulatkan = Rp. 17,600.00
RSNI T-30-2002-B.26
1 Buah Hak Tarikan Jendela
- Tarikan Jendela 1.000 Buah x Rp. 30,000.00 = Rp. 30,000.00
- Pekerja 0.015 OH x Rp. 120.00 = Rp. 1.80
- Tukang 0.150 OH x Rp. 60,000.00 = Rp. 9,000.00
- Kepala Tukang 0.015 OH x Rp. 90,000.00 = Rp. 1,350.00
- Mandor 0.001 OH x Rp. 110,000.00 = Rp. 82.50
Jumlah = Rp. 40,434.30
Dibulatkan = Rp. 40,400.00
RSNI T-30-2002-B.25
1 Buah Pacok /grendel Jendela
- Pacok Jendela 1.000 Buah x Rp. 9,000.00 = Rp. 9,000.00
- Pekerja 0.020 OH x Rp. 120.00 = Rp. 2.40
- Tukang 0.200 OH x Rp. 60,000.00 = Rp. 12,000.00
- Kepala Tukang 0.020 OH x Rp. 90,000.00 = Rp. 1,800.00
- Mandor 0.001 OH x Rp. 110,000.00 = Rp. 82.50
Jumlah = Rp. 22,884.90
Dibulatkan = Rp. 22,800.00
RSNI. T-38-2002-C-B14
1 M2 Pengecatan Tembok Baru
- Plamir 0.100 Kg x Rp. 11,000.00 = Rp. 1,100.00
- Cat Dasar 0.100 Kg x Rp. 23,000.00 = Rp. 2,300.00
- Cat Tembok 0.260 Kg x Rp. 60,000.00 = Rp. 15,600.00
- Pekerja 0.020 OH x Rp. 60,000.00 = Rp. 1,200.00
- Tukang 0.063 OH x Rp. 90,000.00 = Rp. 5,670.00
- Kepala Tukang 0.006 OH x Rp. 110,000.00 = Rp. 693.00
- Mandor 0.0025 OH x Rp. 80,000.00 = Rp. 200.00
Jumlah = Rp. 26,763.00
Dibulatkan = Rp. 26,700.00
DAFTAR HARGA UPAH DAN BAHAN
2015
HARGA JANGKA BUYA + UPAH KHUSUS
NO URAIAN HARGA B. ACEH HARGA JANGKA BUYA SATUAN
KEUNTUNGAN PEKERJAAN SALURAN
A. UPAH
1 Mandor Rp 80,000.00 Rp 80,000.00 Rp 80,000.00 Rp 90,000.00 Org/ Hari
2 Kepala Tukang Rp 110,000.00 Rp 110,000.00 Rp 110,000.00 Rp 120,000.00 Org/ Hari
3 Tukang Rp 90,000.00 Rp 85,000.00 Rp 85,000.00 Rp 95,000.00 Org/ Hari
4 Pekerja Rp 90,000.00 Rp 75,000.00 Rp 75,000.00 Rp 85,000.00 Org/ Hari
B. BAHAN
1 Atap Genteng Metal Zingcalum Ruby Tile 0,30mm Rp 60,000.00 Rp 46.000,00 / Starof Rp 46.000,00 / Starof m2
2 Air bersih Rp 120.00 Liter
3 Baja Ringan C.100. 100 Rp 25,000.00 m'
4 Reng Baja Ringan U.0,5 Rp 19,000.00 m'
5 Bak Fiberglass Rp 200,000.00 bh
6 Batu bata Rp 800.00 Rp 550.00 Rp 550.00 bh
8 Batu Kali/Batu Belah (Sungai/Gunung) Rp 180,000.00 Rp 12,000.00 Rp 180,000.00 m3
9 Batu Belah 5 - 7 cm Rp 170,000.00 m3
10 Batu Pecah 2 - 3 Cm Rp 325,000.00 m3
11 Baut Angker Dia.1"-30 Rp 10,400.00 bh
12 Baut Truss Rp 6,000.00 Rp 300.00 Rp 300.00 bh
13 Baut Reng Rp 6,000.00 Rp 300.00 Rp 300.00 bh
14 Besi beton polos Rp 10,000.00 Rp 12,000.00 kg
15 Besi beton ulir Rp 11,000.00 kg
16 Bubungan seng Aluminium Rp 60,000.00 m'
Bubungan Genteng Rp 30,000.00 m'
17 Bon bon keramik Rp 15,000.00 m'
18 Cat dasar Rp 23,000.00 kg
19 Cat kayu mengkilat Rp 59,000.00 Rp 55,000.00 Rp 55,000.00 kg
20 Cat Menie Rp 40,000.00 Rp 47,000.00 Rp 47,000.00 kg
21 Cat tembok Rp 60,000.00 Rp 65,000.00 Rp 65,000.00 kg
22 Dempul kayu Rp 24,000.00 Rp 20,000.00 Rp 20,000.00 kg
23 Engsel jendela Rp 30,000.00 Rp 15,000.00 Rp 15,000.00 pasang
24 Engsel pintu Rp 42,000.00 Rp 30,000.00 Rp 30,000.00 pasang
25 Floor drain (tempat keluar Air Kencing Di Kamar Mandi Rp 24,000.00 Rp 15,000.00 Rp 15,000.00 bh
26 Grendel Jendela/pintu Rp 7,200.00 bh
27 Kait jendela Rp 7,200.00 bh
28 Kawat beton / Kawat Ikat Rp 16,000.00 Rp 15,000.00 Rp 18,000.00 kg
29 Kayu Kelas I Rp 5,500,000.00 m3
30 Kayu Kelas II Rp 4,400,000.00 Rp 4,500,000.00 m3
31 Kayu Kelas III Rp 4,000,000.00 Rp 3,800,000.00 m3
32 Kayu Kelas IV Rp 3,840,000.00 m3
33 kayu Dolken Rp 14,400.00 Rp 20,000.00 batang
34 Keramik Keset 20 x 20 cm Rp 45,000.00 Rp 55,000.00 Rp 55,000.00 m2
35 Keramik 10 x 40 cm Rp 30,000.00 m2
36 Keramik Kulit Jeruk Uk. 20 x 25 cm Rp 45,000.00 Rp 65,000.00 Rp 65,000.00 m2
37 Keramik Uk. 30 x 30 cm Rp 50,000.00 m2
38 Keramik Uk. 40 x 40 cm Rp 62,000.00 Rp 57,000.00 Rp 57,000.00 m2
39 Kunci pintu Dua Slaag Rp 175,700.00 bh
40 Kran Air Rp 23,700.00 Rp 25,100.00 Rp 25,100.00 bh
41 Klosed Jongkok Rp 180,000.00 Rp 240,000.00 Rp 240,000.00 unit
42 Lampu TL 40 Watt Rp 108,000.00 bh
43 Lampu TL 24 Watt Rp 108,000.00 bh
12
HARGA JANGKA BUYA + UPAH KHUSUS
NO URAIAN HARGA B. ACEH HARGA JANGKA BUYA SATUAN
KEUNTUNGAN PEKERJAAN SALURAN
44 Lampu HE 15 Watt Rp 40,000.00 bh
45 Lem kayu Rp 46,800.00 Rp 10,000.00 Rp 10,000.00 bh
46 List Eternit kayu Rp 8,000.00 m'
47 Minyak cat Rp 17,840.00 liter
47 Minyak Bekisting Rp 9,400.00 Rp 5,000.00 liter
48 Multipleks 4 mm Rp 108,000.00 Rp 67,000.00 Rp 67,000.00 lbr
49 Tipleks 3 mm Rp 108,000.00 Rp 57,000.00 Rp 57,000.00 lbr
50 Multipleks 6 mm Rp 170,400.00 Rp 90,000.00 Rp 90,000.00 lbr
51 Multipleks 9 mm Rp 182,400.00 Rp 125,000.00 Rp 140,000.00 lbr
52 Nok/Rabung Seng 0.35 /Rabung Ruby Tile Rp 60,200.00 lbr
53 Paku kayu Rp 13,000.00 Rp 15,000.00 Rp 18,000.00 kg
54 Paku seng Rp 18,000.00 Rp 18,000.00 Rp 18,000.00 kg
55 Paku Ulir Primadek Rp 1,200.00 bh
56 Pasir beton Rp 150,000.00 Rp 100,000.00 Rp 100,000.00 m3
57 Kerikil Beton Rp 100,000.00 Rp 100,000.00 Rp 175,000.00 m3
58 Koral Beton 2-3 cm Rp 120,000.00 Rp 100,000.00 Rp 100,000.00 m3
59 Kaca tebal 5 mm Rp 128,400.00 m2
60 Pacok Jendela Rp 9,000.00 Rp 6,000.00 Rp 6,000.00 bh
61 Pasir pasang Rp 150,000.00 Rp 100,000.00 Rp 175,000.00 m3
62 Pasir urug Rp 117,000.00 Rp 100,000.00 Rp 100,000.00 m3
63 Pelumas/Oli Rp 18,000.00 liter
64 Plamur tembok Rp 11,000.00 kg
65 Pipa PVC Dia.3/4 " Rp 7,750.00 Rp 25,000.00 Rp 25,000.00 m
66 Pipa PVC Dia.3 " Rp 34,850.00 Rp 65,000.00 Rp 65,000.00 m
67 Pipa PVC Dia.4 " Rp 70,750.00 Rp 85,000.00 Rp 85,000.00 m
68 Pipa galvanis Dia 2",tebal 3.2 mm Rp 74,125.00 m
69 Pipa galvanis Dia 3",tebal 3.2 mm Rp 128,050.00 m
70 Pipa galvanis Dia 4",tebal 3.2 mm Rp 201,500.00 m
71 Panel Allucobond Rp 200,000.00 m2
72 Seal tape Rp 11,000.00 Rp 4,000.00 Rp 4,000.00 bh
73 Schakelar Rp 26,800.00 bh
74 Semen @ 40 kg Rp 42,000.00 Rp 50,000.00 Zak
75 Semen Putih @ 50 kg Rp 132,000.00 Rp 130,000.00 Rp 130,000.00 Zak
76 Seng BJLS 0.2 Rp 57,900.00 Rp 57,000.00 Rp 57,000.00 Lbr
77 Seng Gelombang BJLS 30 Rp 100,800.00 Lbr
78 Stop kontak lengkap dengan Instalasi Rp 220,000.00 titik
79 Tanah Timbun Rp 55,000.00 Rp 30,000.00 Rp 30,000.00 m3
80 Talang Air Rp 75,000.00 Rp 50,000.00 Rp 50,000.00 m'
81 Tarikan Jendela Rp 30,000.00 Rp 7,000.00 Rp 7,000.00 bh
82 Titik lampu lengkap dengan Instalasi Rp 220,000.00 titik
83 Zekering (kast lokal 2 zekering) Rp 137,300.00 bh
13
ENGINEERING ESTIMATE (EE)
Pekerjaan : Perencanaan Pos Damkar Di 2 Lokasi
Instansi : Badan Penanggulangan Bencana Daerah
Lokasi : Kab. Aceh Besar
Tahun Anggaran : 2014
C. PEKERJAAN BETON
1 Pondasi tapak 120 x 120 cm 4.320 m3 1.20 1.20 0.25 1.00 12.00 4.32
2 Kolom Pedestal 30/30 cm 1.296 m3 1.20 0.3 0.30 1.00 12.00 1.30
3 Sloof 20/25 cm 4.010 m3 80.20 0.2 0.25 1.00 1.00 4.01
4 Kolom 30/30 cm 5.778 m3 5.35 0.3 0.30 1.00 12.00 5.78
5 Kolom Praktis 13/13 cm 0.723 m3 5.35 0.13 0.13 1.00 8.00 0.72
6 Balok latai 13/15 cm 1.014 m3 52.00 0.13 0.15 1.00 1.00 1.01
7 Ring Balok 15/20 cm 0.480 m3 16.00 0.15 0.20 1.00 1.00 0.48
8 Plat Sun Wearing tebal 12 cm 1.270 m3 17.64 0.6 0.12 1.00 1.00 1.27
9 Ring Balk 20/35 cm 6.230 m3 89.00 0.2 0.35 1.00 1.00 6.23
D. PEKERJAAN ATAP
1 Atap seng genteng metal 150.021 m2 11.85 12.66 1.00 1.00 1.00 150.02
2 Rangka kuda - kuda Baja ringan 150.021 m2 11.85 12.66 1.00 1.00 1.00 150.02
3 Rabung seng pada pinggiran atap 11.850 m1 11.85 1 1.00 1.00 1.00 11.85
4 Talang Air Seng 0.3 mm 11.850 m1 11.85 1 1.00 1.00 1.00 11.85
5 Panel Allucobond lengkap Rangka Siku pengaku 71.960 m2 25.70 1.4 1.00 1.00 2.00 71.96
dimensi kubikasi jumlah Vol
NO URAIAN PEKERJAAN VOLUME SAT
panjang lebar tinggi luasan
1 2 3 4
E. PEKERJAAN PASANGAN & PLESTERAN
2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 246.846 m2 53.25 1 5.00 1.00 1.00 246.85
Plesteran 1 Pc : 2 Ps, tebal 15 mm untuk dinding transram
3 46.500 m2
ruangan, kamar mandi dan saluran
4 Plesteran 1 Pc : 4 Ps, tebal 15 mm 493.692 m2
5 Relief papan pada dinding luar 13.828 m2 1.000 1 1.00 13.83 1.00 13.83
G. PEKERJAAN LANTAI
1 Urugan tanah Bawah lantai 67.860 m3 1 1 0.45 150.80 1.00 67.86
2 Urugan pasir bawah lantai 7.540 m3 1.00 1 0.05 150.80 1.00 7.54
3 Cor beton Lantai kerja tebal 7,5 cm' 9.690 m3 1 1 0.075 129.20 1.00 9.69
4 Cor Plat Lantai beton bertulang K 250 tebal 15 cm 13.500 m3 1.000 1 0.15 90.00 1.00 13.50
5 Beton cor K 200 pada selasar tebal 10 cm 3.805 m3 1.000 1 0.10 38.05 1.00 3.81
6 Keramik Ruangan uk. 40 x 40 cm 24.000 m2 1.000 1 1.00 24.00 1.00 24.00
7 Keramik Keset lantai Kamar mandi uk. 20 x 20 cm 6.000 m2 1.000 1 1.00 6.00 1.00 6.00
8 Keramik Keset dinding Kamar mandi uk. 20 x 25 cm, h = 1,5 m 14.100 m2 9.400 1 1.50 1.00 1.00 14.10
9 Pasangan Plint Keramik 10 x 40 cm 9.400 m' 9.400 1 1.00 1.00 1.00 9.40
10 Bonbon keramik dalam kamar mandi 5.400 m' 1.000 1 1.00 1.00 1.00 1.00
11 Urugan pasir Urug lantai Jalan Masuk,tebal 10 cm 7.340 m3 9.175 8 0.10 1.00 1.00 7.34
12 Urugan tanah Urug lantai Jalan Masuk 33.030 m3 9.175 8 0.45 1.00 1.00 33.03
13 Cor Plat Lantai beton bertulang K 250 tebal 15 cm Jalan Masuk 11.010 m3 9.175 8 0.15 1.00 1.00 11.01
dimensi kubikasi jumlah Vol
NO URAIAN PEKERJAAN VOLUME SAT
panjang lebar tinggi luasan
1 2 3 4
H. PEKERJAAN LANGIT-LANGIT
1 Plafond multipleks 4 mm lengkap rangka 153.720 m2 12.600 12.2 1.00 1.00 1.00 153.72
2 List profil kayu pada plafond 169.550 m' 169.550 1 1.00 1.00 1.00 169.55
I. PEKERJAAN ELEKTRIKAL
J. PEKERJAAN PENGECATAN
1 Cat dinding tembok (L/D) 493.692 m2
2 Cat plafond dan list plafond 153.720 m2
3 Cat mengkilat daun pintu/jendela & jalusi 21.975 m2
K. PEKERJAAN SANITASI
1 Septictank 1.000 Unit
2 Resapan 1.000 Unit
3 Kloset Jongkok 2.000 Bh
4 Floor Drain 2.000 Bh
5 Kran Air 3/4" 2.000 Bh
6 Bak mandi Fiberglass 2.000 Bh
7 Pemasangan instalasi Pipa PVC 4" 10.000 m'
8 Pemasangan instalasi air Kotor Pipa PVC 3" 10.000 m'
9 Pemasangan instalasi air Bersih Pipa PVC 3/4" 15.000 m'
10 Pemasangan Pipa Air hujan dari talang pipa PVC 3 " 20.800 m'
11 Box Control 60 x 60 1.000 Bh
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 6.00 ) ( 2 x 6.00 ) = 24.00 m' 24.00 m'
0.3
0.75
0.3
0.8
Pondasi Utama Pondasi Selasar Belakang
b. Teras Depan
Luas Urugan Tanah F= 4.50 m²
Tebal Urugan Tanah T= 55 cm
V2 = 4.50 x 0.55 = 2.475 m3
30 20
90 95
80 40
Tampang I Tampang II
---> Tampang I
Panjang Galian = P = 44.50 m
0.3 + 0.80
V1 = x 0.9 x 44.50 = 22.03 m3
2
---> Tampang II
Panjang Galian = P = .00 m
0.2 + 0.40
V2 = x 0.95 x .00 = .00 m3
2
Total Luas Pasangan Batu Gunung
V total = V1 + V2 = 22.028 + + = 22.03 m3 = 22.028 m3
0.40 0.40
0.92
0.82 1.58
1.05
0.8
0.69
1.68 1.68
Type V 4 Unit
0.57
1.38 0.82
0.72
Type J2 1 Unit Type J3 2 Unit Type J4 1 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 0.92 x 2.22 x 4 = 8.1696 m²
Luas Kosen Type P2 F= 0.82 x 1.76 x 1 = 1.4432 m²
Luas Kosen Type J1 F= 01.58 x 2.38 x 1 = 3.7604 m²
Luas Kosen Type J2 F= 01.38 x 1.68 x 1 = 2.3184 m²
Luas Kosen Type J3 F= .82 x 1.68 x 2 = 2.7552 m²
Luas Kosen Type J4 F= 0.72 x 0.57 x 1 = .4104 m²
Luas Kosen Type V F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 21.41 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 130.904 x 2 = 261.81 m² = 261.81 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 16.00 x 2 = 32.0 m² = 32.0 m²
c. Kosen Jendela J1
Ukuran Kayu yang digunakan : b = 13 cm
h = 6 cm
Jumlah Kosen n = 1 Unit
Panjang Kosen P = 2x 1.58 + 3 x 02.38 = 010.30 m
Volume Untuk 1 Unit V = 10.3 x 0.13 x 0.06 = 0.0803 m3
Volume Untuk n Unit V = 0.0803 x 1 = 0.0803 m3
Resume :
a. Kosen Pintu Type P1 = 0.221 m3
b. Kosen Pintu Type P2 = 0.045 m3
c. Kosen Jendela J1 = 0.08 m3
d. Kosen Jendela Type J2 = 0.048 m3
e. Kosen Jendela Type J3 = 0.065 m3
f. Kosen Jendela Type J4 = 0.02 m3
g. Kosen Ventilasi Type V = 0.109 m3
Total Volume Kayu Kosen = 0.589 m3 .589 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 82 x 210 n = 4 bh 4 bh
b. Type P2 Uk. 72 x 210 n = 1 bh 1 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 8.40 m
Lebar Pasangan L = 4.407 m
F2 = 8.4 x 4.407 = 37.0188 m²
---->> Sisi Miring Bangunan Bagian Depan Depan Belakang (Tampak Samping)
Panjang Sisi Miring m = 4.41 m
Lebar Pasangan L = 1.20 m
Luas Pasangan Plafond F = 4.41 x 1.20 = 5.29 m²
Luas Pasangan Plafond untuk 4 sisi F = 4 x 5.2884 = 21.15 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 36.00 + 46.97 = 82.9656 m² = 82.966 m²
13
b. Jendela Type J1
Ukuran Jendela : P = 1.8 m
L = 0.7 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 1.8 + 2 x 0.7 = 2.52 m
Jumlah Jendela n = 2 Unit
Luas untuk 1 unit F = .504 m²
Luas Untuk n Unit V = 0.504 x 2 = 1.008 m²
c. Jendela Type J2
Ukuran Jendela : P = 1.1 m
L = 0.6 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 1.1 + 2 x 0.6 = 1.32 m
Jumlah Jendela n = 2 Unit
Luas untuk 1 unit F = .264 m²
Luas Untuk n Unit V = 0.264 x 2 = .528 m²
d. Jendela Type J3
Ukuran Jendela : P = 1.1 m
L = 0.7 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 1.1 + 2 x 0.7 = 1.54 m
Jumlah Jendela n = 2 Unit
Luas untuk 1 unit F = .308 m²
Luas Untuk n Unit V = 0.308 x 2 = .616 m²
Resume :
a. Pintu Type P1 = 14.32704 m²
b. Jendela Type J1 = 1.008 m²
c. Jendela Type J2 = .528 m²
d. Jendela Type J3 = .00 m²
e. Ventilasi Jendela dan Pintu = 1.12 m²
f. Jalusi Tolak Angin = 5.796 m²
Total Volume Cat Kayu Kosen = 22.77904 m² = 22.779 m²
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 9.00 ) ( 2 x 5.60 ) = 29.20 m' 29.20 m'
0.3
0.75
0.3
0.8
Pondasi Utama Pondasi Selasar Belakang
b. Teras Depan
Luas Urugan Tanah F= 4.00 m²
Tebal Urugan Tanah T= 55 cm
V2 = 4.00 x 0.55 = 2.20 m3
30 20
90 95
80 40
Tampang I Tampang II
---> Tampang I
Panjang Galian = P = 45.80 m
0.3 + 0.80
V1 = x 0.9 x 45.80 = 22.67 m3
2
---> Tampang II
Panjang Galian = P = .00 m
0.2 + 0.40
V2 = x 0.95 x .00 = .00 m3
2
Total Luas Pasangan Batu Gunung
V total = V1 + V2 = 22.671 + + = 22.67 m3 = 22.671 m3
2.62 2.16
1.75 1.75
0.82
0.82
0.62
0.72
Type JM 10 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 0.82 x .87 x 2 = 1.4268 m²
Luas Kosen Type P2 F= 0.82 x .41 x 7 = 2.3534 m²
Luas Kosen Type JM F= 0.72 x 0.62 x 10 = 4.464 m²
Total Luas Lobang Kosen F total = 8.24 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 93.257 x 2 = 186.51 m² = 186.51 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Bangunan
F1 = 27.20 x 1.75 = 47.6 m² = 47.6 m²
Resume :
a. Kosen Pintu Type P1 = 0.107 m3
b. Kosen Pintu Type P2 = 0.314 m3
c. Kosen Jendela Type JM = 0.209 m3
Total Volume Kayu Kosen = 0.631 m3 .631 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 82 x 210 n = 2 bh 2 bh
b. Type P2 Uk. 72 x 210 n = 7 bh 7 bh
4. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
Panjang Papan Lisplank Untuk Pasangan Memanjang Sisi Depan dan Belakang
Panjang Pasangan P1 = 2 x 11.4 = 22.80 m = 22.80 m
---->> Sisi Miring Bangunan Bagian Depan Depan Belakang (Tampak Samping)
Panjang Sisi Miring m = 4.84 m
Lebar Pasangan L = 1.20 m
Luas Pasangan Plafond F = 4.84 x 1.20 = 5.81 m²
Luas Pasangan Plafond untuk 4 sisi F = 4 x 5.808 = 23.23 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 44.00 + 48.83 = 92.832 m² = 92.832 m²
13
b. Jalusi P1
Jalusi P1 : F = 1.60 m²
Total Luas : F = 1.60 m²
Resume :
a. Pintu Type P1 = 7.16352 m²
b. Jalusi P1 = 1.60 m²
Total Volume Cat Kayu Kosen = 8.76352 m² = 8.764 m²
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 32.40 ) ( 2 x 12.80 ) = 90.40 m' 90.40 m'
0.3
0.5
0.75
0.3
0.5
0.8
Pondasi Utama Pondasi Selasar Depan Pondasi Selasar Belakang/Ram
c. Selasar Samping
Luas Urugan Tanah F= 16.80 m²
Tebal Urugan Tanah T= 40 cm
V3 = 16.80 x 0.40 = 6.72 m3
d. Ram n= 2 buah
Luas Urugan Tanah F= 7.74 m²
Tebal Urugan Tanah T= 40 cm
V4 (1 buah) = 7.74 x 0.40 x 1/2 = 1.548 m3
V4 (n buah) = 1.548 x 2 = 3.096 m3
30 20 20
90 95 95
80 40 40
Tampang I Tampang II Tampang III
---> Tampang I
Panjang Galian = P = 127.50 m
0.3 + 0.80
V1 = x 0.9 x 127.50 = 63.11 m3
2
---> Tampang II
Panjang Galian = P = 48.40 m
0.2 + 0.40
V2 = x 0.95 x 48.40 = 13.79 m3
2
0.40 0.40
1.02
1.42 2.16
1.05
0.8
0.69
2.72 2.16
Type V 4 Unit
0.40 0.4
0.62
1.72 0.82
0.72
Type P4 1 Unit Type P5 2 Unit Type V1 4 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 01.02 x 2.32 x 3 = 7.0992 m²
Luas Kosen Type P2 F= 01.42 x 2.32 x 4 = 13.1776 m²
Luas Kosen Type P3 F= 01.72 x 2.32 x 1 = 3.9904 m²
Luas Kosen Type P4 F= 01.72 x .00 x 1 = .00 m²
Luas Kosen Type P5 F= 0.82 x 1.76 x 2 = 2.8864 m²
Luas Kosen Type PJ3 F= 0.77 x 2.11 x 2 = 3.2494 m²
Luas Kosen Type J3 F= 2.16 x 1.52 x 9 = 29.5488 m²
Luas Kosen Type V1 F= 0.72 x 0.62 x 4 = 1.7856 m²
Luas Kosen Type V F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 64.29 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 448.93 x 2 = 897.86 m² = 897.86 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 47.504 x 2 = 95.01 m² = 95.01 m²
4. Lantai Keramik 40 x 40 cm
Sesuai dengan Gambar :
Total Luas Keramik 40x40 cm untuk Ruangan Dalam = Luas Total Ruang Dalam - Luas KM/WC
Resume :
a. Kosen Pintu Type P1 = 0.175 m3
b. Kosen Pintu Type P2 = 0.278 m3
c. Kosen Pintu Type PJ3 = 0.141 m3
d. Kosen Pintu Type P4 = 0.074 m3
e. Kosen Pintu Type P5 = 0.08 m3
f. Kosen Jendela Type J3 = 0.882 m3
g. Kosen Ventilasi Type V1 = 0.084 m3
h. Kosen Ventilasi Type V = 0.109 m3
Total Volume Kayu Kosen = 01.823 m3 1.823 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 92 x 210 n = 3 bh 3 bh
b. Type P2 Uk. 82 x 210 n = 4 bh 4 bh
c. Type P2 Uk. 52 x 210 n = 4 bh 4 bh
d. Type P3 Uk. 82 x 210 n = 2 bh 2 bh
e. Type P4 Uk. 82 x 210 n = 2 bh 2 bh
f. Type P5 Uk. 72 x 200 n = 2 bh 2 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 32.40 m
Lebar Pasangan L = 7.22 m
F2 = 32.4 x 7.22 = 233.928 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 240.00 + 169.63 = 409.632 m² = 409.632 m²
13
b. Pintu Type P2
Ukuran Pintu : P = 2.1 m
L = 0.82 m
T = 0.04 m
Keliling Pintu K = 2x 2.1 + 2 x 0.82 = 3.444 m
Jumlah Pintu n = 4 Unit
Luas untuk 1 unit F = 3.58176 m²
Luas Untuk n Unit V = 03.5818 x 4 = 14.32704 m²
c. Pintu Type P2
Ukuran Pintu : P = 2.1 m
L = 0.52 m
T = 0.04 m
Keliling Pintu K = 2x 2.1 + 2 x 0.52 = 2.184 m
Jumlah Pintu n = 4 Unit
Luas untuk 1 unit F = 2.27136 m²
Luas Untuk n Unit V = 02.2714 x 4 = 9.08544 m²
e. Jendela Type J3
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 27 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 27 = 4.82976 m²
Resume :
a. Pintu Type P1 = 12.05568 m²
b. Pintu Type P2 = 14.32704 m²
c. Pintu Type P2 = 9.08544 m²
d. Pintu Type P3 dan P4 = 14.32704 m²
e. Jendela Type J3 = 4.82976 m²
f. Jalusi Pintu, Jendela dan Tolak Angin = 38.196 m²
Total Volume Cat Kayu Kosen = 92.82096 m² = 92.821 m²
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 29.40 ) ( 2 x 11.00 ) = 80.80 m' 80.80 m'
0.3
0.5
0.75
0.3
0.5
0.8
Pondasi Utama Pondasi Selasar Depan Pondasi Selasar Belakang/Ram
b. Selasar Depan
Luas Urugan Tanah F= 52.92 m²
Tebal Urugan Tanah T= 55 cm
V2 = 52.92 x 0.55 = 29.106 m3
d. Ram n= 1 buah
Luas Urugan Tanah F= 7.74 m²
Tebal Urugan Tanah T= 40 cm
V4 (1 buah) = 7.74 x 0.40 x 1/2 = 1.548 m3
V4 (n buah) = 1.548 x 1 = 1.548 m3
e. Panggung n= 3 buah
Luas Urugan Tanah F= 7.00 m²
Tebal Urugan Tanah T= 20 cm
V5 (1 buah) = 7.00 x 0.20 = 1.40 m3
V5 (n buah) = 1.40 x 3 = 4.20 m3
b. Panggung n= 3 buah
Panjang Cor P= 6.50 m'
Lebar Cor L= 0.3 m
Tebal Cor T= 5 cm
V5 (1 buah) = 6.50 x 0.30 x 0.05 = 1.95 m3
V4 (n buah) = 1.95 x 3 = 5.85 m3
30 20 20
90 95 95
80 40 40
Tampang I Tampang II Tampang III
---> Tampang I
Panjang Galian = P = 78.00 m
0.3 + 0.80
V1 = x 0.9 x 78.00 = 38.61 m3
2
---> Tampang II
Panjang Galian = P = 35.40 m
0.2 + 0.40
V2 = x 0.95 x 35.40 = 10.09 m3
2
b. Panggung n= 3 buah
Panjang Pasangan = P = 6.50 m T1 = 30 cm
F1 (1 buah) = 6.50 x 0.3 = 1.95 m²
F1 (n buah) = 1.95 x 3 = 5.85 m²
0.40 0.40
1.02
0.92 2.16
1.05
0.8
0.69
1.52
Type V 4 Unit
2.8.
Type J4 6 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 01.02 x 2.32 x 3 = 7.0992 m²
Luas Kosen Type P2 F= 0.92 x 1.70 x 2 = 3.128 m²
Luas Kosen Type J3 F= 2.16 x 1.52 x 9 = 29.5488 m²
Luas Kosen Type J4 F= 2.82 x 1.52 x 6 = 25.7184 m²
Luas Kosen Type V1 F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 68.05 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 250.583 x 2 = 501.17 m² = 501.17 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 29.24 x 2 = 58.48 m² = 58.48 m²
2. Lantai Keramik 40 x 40 cm
Luas Pasangan Keramik 40 x 40 cm Ruang Dalam
Ukuran Bangunan : Jumlah Panjang Lebar Luas
Resume :
a. Kosen Jendela Type P1 = 0.175 m3
b. Kosen Jendela Type P2 = 0.08 m3
c. Kosen Jendela Type J3 = 0.882 m3
d. Kosen Ventilasi Type J4 = 0.752 m3
e. Kosen Ventilasi Type V = 0.109 m3
Total Volume Kayu Kosen = 01.998 m3 1.998 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 92 x 210 n = 3 bh 3 bh
b. Type P2 Uk. 82 x 210 n = 2 bh 2 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 29.40 m
Lebar Pasangan L = 6.26 m
F2 = 29.4 x 6.26 = 184.044 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 216.00 + 124.15 = 340.152 m² = 340.152 m²
13
b. Pintu Type P2
Ukuran Pintu : P = 2.1 m
L = 0.82 m
T = 0.04 m
Keliling Pintu K = 2x 2.1 + 2 x 0.82 = 3.444 m
Jumlah Pintu n = 2 Unit
Luas untuk 1 unit F = 3.58176 m²
Luas Untuk n Unit V = 03.5818 x 2 = 7.16352 m²
c. Jendela Type J3
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 27 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 27 = 4.82976 m²
d. Jendela Type J4
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 24 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 24 = 4.29312 m²
Resume :
a. Pintu Type P1 = 12.05568 m²
b. Pintu Type P2 = 7.16352 m²
c. Jendela Type J3 = 4.82976 m²
d. Jendela Type J4 = 4.29312 m²
e. Jalusi Pintu, Jendela dan Tolak Angin = 35.076 m²
Total Volume Kayu Kosen = 63.41808 m² = 63.418 m²
U R A I A N REKAP.
I. PEKERJAAN PERSIAPAN
Panjang Bouplank yang harus dibuat = ( 2 x 17.40 ) ( 2 x 11.00 ) = 56.80 m' 56.80 m'
0.3
0.5
0.75
0.3
0.5
0.8
Pondasi Utama Pondasi Selasar Depan Pondasi Selasar Belakang/Ram
b. Selasar Depan
Luas Urugan Tanah F= 31.32 m²
Tebal Urugan Tanah T= 55 cm
V2 = 31.32 x 0.55 = 17.226 m3
d. Ram n= 1 buah
Luas Urugan Tanah F= 7.74 m²
Tebal Urugan Tanah T= 40 cm
V4 (1 buah) = 7.74 x 0.40 x 1/2 = 1.548 m3
V4 (n buah) = 1.548 x 1 = 1.548 m3
e. Panggung n= 0 buah
Luas Urugan Tanah F= 5.75 m²
Tebal Urugan Tanah T= 20 cm
V5 (1 buah) = 5.75 x 0.20 = 1.15 m3
V5 (n buah) = 1.15 x 0 = .00 m3
b. Panggung n= 0 buah
Panjang Cor P= 6.50 m'
Lebar Cor L= 0.3 m
Tebal Cor T= 5 cm
V5 (1 buah) = 6.50 x 0.30 x 0.05 = 1.95 m3
V4 (n buah) = 1.95 x 0 = .00 m3
30 20 20
90 95 95
80 40 40
Tampang I Tampang II Tampang III
---> Tampang I
Panjang Galian = P = 53.50 m
0.3 + 0.80
V1 = x 0.9 x 53.50 = 26.48 m3
2
---> Tampang II
Panjang Galian = P = 23.40 m
0.2 + 0.40
V2 = x 0.95 x 23.40 = 6.67 m3
2
b. Panggung n= 0 buah
Panjang Pasangan = P = 6.50 m T1 = 30 cm
F1 (1 buah) = 6.50 x 0.3 = 1.95 m²
F1 (n buah) = 1.95 x 0 = .00 m²
0.40 0.40
0.92
1.32 2.16
1.05
0.8
0.69
1.52
1.52
Type V 4 Unit
2.8.
Type J4 5 Unit
Luas Kosen Sebagaimana berikut ini : Lebar Tinggi Jumlah Luas
Luas Kosen Type P1 F= 0.92 x 2.32 x 1 = 2.1344 m²
Luas Kosen Type P2 F= 01.32 x 2.32 x 1 = 3.0624 m²
Luas Kosen Type J3 F= 2.16 x 1.52 x 4 = 13.1328 m²
Luas Kosen Type J4 F= 2.82 x 1.52 x 5 = 21.432 m²
Luas Kosen Type V1 F= 0.925 x 0.69 x 4 = 2.553 m²
Total Luas Lobang Kosen F total = 42.31 m²
3. Plesteran 1 : 4 ; T = 15 mm
Luas Plesteran 1 : 4 Untuk Dinding Luar Dalam Bangunan
F= 188.115 x 2 = 376.23 m² = 376.23 m²
4. Plesteran 1 : 2 ; T = 15 mm
a. Luas Plesteran 1 : 2 Untuk Dinding Luar Dalam Bangunan
F1 = 20.504 x 2 = 41.01 m² = 41.01 m²
2. Lantai Keramik 40 x 40 cm
Luas Pasangan Keramik 40 x 40 cm Ruang Dalam
Ukuran Bangunan : Jumlah Panjang Lebar Luas
Resume :
a. Kosen Jendela Type P1 = 0.057 m3
b. Kosen Jendela Type P2 = 0.068 m3
c. Kosen Jendela Type J3 = 0.392 m3
d. Kosen Ventilasi Type J4 = 0.626 m3
e. Kosen Ventilasi Type V = 0.109 m3
Total Volume Kayu Kosen = 01.252 m3 1.252 m3
2. Pintu Panel
Jumlah Pintu Panel Yang Digunakan
a. Type P1 Uk. 82 x 210 n = 1 bh 1 bh
b. Type P2 Uk. 82 x 210 n = 1 bh 1 bh
c. Type P2 Uk. 40 x 210 n = 1 bh 1 bh
5. Lisplank Papan
Berdasarkan Gambar Terlampir :
Ukuran Papan Lisplank b = 2.5 cm
h = 30 cm
b. Sisi Belakang
Panjang Pasangan P = 17.40 m
Lebar Pasangan L = 6.26 m
F2 = 17.4 x 6.26 = 108.924 m²
2. Pengecatan Plafond
Luas Pengecatan Plafond Untuk Luar dan Dalam Bangunan
F= Luas Pasangan Plafond Dalam + Luas Pasangan Plafond Luar
F total = 120.00 + 83.35 = 203.352 m² = 203.352 m²
13
d. Jendela Type J3
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 12 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 12 = 2.14656 m²
e. Jendela Type J4
Ukuran Jendela : P = 0.86 m
L = 0.52 m
L. ambang = 0.08 m
T = 0.04 m
Keliling Jendela K = 2x 0.86 + 2 x 0.52 = .8944 m
Jumlah Jendela n = 20 Unit
Luas untuk 1 unit F = .17888 m²
Luas Untuk n Unit V = 0.1789 x 20 = 3.5776 m²
Resume :
a. Pintu Type P1 = 4.01856 m²
b. Pintu Type P2 ukuran 82 x 210 cm = 3.58176 m²
c. Pintu Type P2 ukuran 40 x 210 cm = 1.7472 m²
d. Jendela Type J3 = 2.14656 m²
e. Jendela Type J4 = 3.5776 m²
f. Jalusi Pintu, Jendela dan Tolak Angin = 24.996 m²
Total Volume Kayu Kosen = 40.06768 m² = 40.068 m²
A. UPAH
1 Mandor Orang 80,000.00
2 Kepala Tukang Kayu/Cat Orang 105,000.00
3 Tukang Kayu/Cat Orang 84,000.00
4 Laden Tukang Kayu/Cat Orang 70,200.00
5 Kepala Tukang Batu/Besi Orang 110,000.00
6 Tukang Batu/Besi Orang 86,000.00
7 Laden Tukang Batu/Besi Orang 75,000.00
8 Pekerja Galian Tanah Orang 75,000.00
9 Penjaga malam/Satpam Orang 59,400.00
10 Penyelam Orang 156,600.00
11 Supir Orang 110,000.00
12 Operator Orang 162,000.00
B. HARGA BAHAN
1 Air Liter 120.00
2 Batu Bata Buah 800.00
3 Batu Kali/Batu Belah (Sungai/Gunung) M³ 180,000.00
4 Batu Belah 5 - 7 cm M³ 170,000.00
5 Batu Pecah 2 - 3 Cm M³ 325,000.00
6 Besi Beton Polos Kg 10,000.00
7 Besi Beton Ulir Kg 11,000.00
8 Bubungan Genteng M¹ 30,000.00
10 Cat Dasar Tembok/Sealer Setara Vinilex Kg 23,000.00
11 Cat Kayu Dasar Kg 37,000.00
12 Cat Kayu Mengkilat Kg 59,000.00
13 Cat Menie besi Kg 25,600.00
14 Cat Tembok Setara Vinilex Kg 28,000.00
15 Dempul Kayu Kg 16,400.00
16 Dolken Kayu ø 8 -10/400 cm Batang 62,856.00
17 Door Holder Pasang 120,000.00
18 Engsel Jendela Pasang 22,000.00
19 Engsel Pintu Pasang 22,000.00
20 Floor Drain Buah 20,000.00
21 Gypsum Board tebal 9 mm Lembar 90,000.00
22 Jaring Kawat Baja Kg 25,500.00
23 Hak Angin Pasang 14,000.00
24 Kaca Bening Uk. 2 mm M² 64,500.00
25 Kaca Bening Uk. 3 mm M² 75,000.00
26 Kaca Bening Uk. 5 mm M² 100,000.00
29 Kaso- kaso ( 5 x 7 ) cm M³ 3,000,000.00
30 Kawat Beton Kg 20,000.00
31 Kayu Klas I ( Seumantok / Ulim / dll ) M³ 5,500,000.00
32 Kayu Klas II ( Kamper / Kruing / dll ) M³ 4,500,000.00
33 Kayu Klas III ( Borneo / dll ) M³ 3,800,000.00
34 Kayu Klas IV ( Sengon / dll ) M³ 3,000,000.00
No. Nama Jenis Barang Satuan Harga
ASRIZAL, ST
Direktur