II PEKERJAAN TANAH
a. Galian tanah pondasi dangkal Lebar Galian = 0.55 m
Tinggi Galian = 0.66 m
Panjang Pondasi = 58.8 m
V = 0.8 x 0.8 x 1x 21
= 13.44 M3 13.44 M3
c. Pekerjaan Urugan Pasir Bawah Pondasi dangkal Lebar Pasir Urug = 0.6
Tinggi Pasir Urug = 0.05
Panjang Pondasi = 58.8
Perhitungan Volume
V = 0.6 x 0.05 x 58.8
= 1.764 M3 1.764 M3
V = 0.8 x 0.8 x 0x 21
= 0.134 M3 0.1344 M3
e. Pasangan Batu Kosong Lebar Batu Kosong = 0.66
Tinggi Batu Kosong = 0.1
Panjang Pondasi = 58.8
Perhitungan Volume
V = 0.66 x 0.1 x 58.8
= 3.881 M3 3.8808 M3
V= 13.44 - 3.3235
= 10.12 M3 10.1165 M3
h. Urugan Tanah Bekas Galian Pondasi Dangkal Lebar Dasar Galian = 0.66 m
Lebar Pondasi Permukaan Tanah = 0.33 m
Tinggi Galian = 0.4 m
Panjang Pondasi = 58.8 m
= 0.66 - 0.33 / 2
= 0.165 m
V = 54.5 x 0.13
= 7.085 M3 7.085 M3
V = 54.5 x 0.1
= 5.45 M3 5.45 M3
h. Beton Tumbuk Luasan Bangunan Seluruhnya = 54.5 m2
Tebal Tanah Urug Bawah Lantai = 0.04 m
V = 54.5 x 0.04
= 2.18 M3 2.18 M3
III PEKERJAAN BETON DAN BETON BERTULANG
a. Pekerjaan Sloof 20x20 Lebar Sloof = 0.2 m
Tinggi sloof = 0.2 m
Panjang Pondasi = 58.8 m
V = 0.2 x 0.2 x 65
= 2.592 M3
Volume Total Reng Balok
= 2.352 + 2.592
= 4.944 M3 4.944 M3
c. Pekerjaan Kolom 20x20 Kolom Lantai I
Lebar Kolom = 0.2 m
Panjang Kolom = 0.2 m
Tinggi Kolom = 3 m
Jumlah Kolom = 17 m
V = 0.2 x 0.2 x 3 x 17
= 2.04 M3
Kolom Lantai II
Lebar Kolom = 0.2 m
Panjang Kolom = 0.2 m
Tinggi Kolom = 3 m
Jumlah Kolom = 17 m
V = 0.2 x 0.2 x 3 x 17
= 2.04 M3
= 2.04 + 2.04
= 4.08 M3 4.08 M3
d. Pekerjaan Kolom 15x15 Kolom Lantai I
Lebar Kolom = 0.2 m
Panjang Kolom = 0.2 m
Tinggi Kolom = 3 m
Jumlah Kolom = 3 m
V = 0.2 x 0.2 x 3 x 3
= 0.36 M3
Kolom Lantai II
Lebar Kolom = 0.2 m
Panjang Kolom = 0.2 m
Tinggi Kolom = 3 m
Jumlah Kolom = 1 m
V = 0.2 x 0.2 x 3 x 1
= 0.12 M3
= 0.36 + 0.12
= 0.48 M3 0.48 M3
e. Pekerjaan Pondasi Telapak Segment I
Lebar Bawah Pondasi Segmen I = 0.7 m
Panjang Pondasi Segmen I = 0.7 m
Tinggi Pondasi Segmen I = 0.25 m
Jumlah Pondasi Telapak = 17 Bh
V = 0.7 x 0.7 x 0.25 x 17
V = 2.083 M3
Segment II
Lebar Bawah Pondasi Segmen II = 0.7 m
Lebar Bawah Atas Segmen II = 0.2 m
Tinggi Pondasi Segmen II = 0.05 m
Jumlah Pondasi Telapak = 17 Bh
V = 5.26 x 2 x 0.12
= 1.262 M3
BAGIAN II
Panjang Pelat Lantai = 7.2 m
Lebar Pelat Lantai = 9.2 m
Tebal Pelat Lantai = 0.12 m
BAGIAN III
Panjang Pelat Lantai = 3.2 m
Lebar Pelat Lantai = 2 m
Tebal Pelat Lantai = 0.12 m
V = 3.2 x 2 x 0.12
= 0.768 M3
VOLUME TOTAL
= 9.979 M3 9.9792 M3
g. Pekerjaan Pondasi Telapak Untuk Tangga Bagian I
= 0.10 x 0.10 x 1.24
= 0.0124 M3
Bagian II
= 0.40 x 0.40 x 0.15
= 0.024 M3
Volume Total
= 0.0364 M3 0.0364 M3
Volume Total
= 0.9235 M3 0.92352 M3
i. Perhitungan Kebutuhan Besi Sloof 20x20 Kebutuhan Besi Untuk Sloof 20x20
Volume Sloff = 2.35 m3
Lebar Sloof = 0.2 m
Tinggi sloof = 0.2 m
Panjang Pondasi = 58.8 m
Sengkang = ø8-15 cm
Tulangan Pokok = ø 12
Bj Tualangan Pokok ø 10 = 0.89 kg
Bj Tualangan Pokok ø 8 = 0.39 kg
Tebal Selimut Beton = 0.02 m
Jumlah Tulangan Pokok = 4 Bh
Panjang Tulangan Pokok
= 58.8 x 4
= 235.2 M'
Berat Besi Tulangan Pokok
= 235.2 x 0.888
= 208.86 Kg
Panjang Sengkang
Panjang Sebuah Senkang
= 0.2 - 0.02 + 0.02
= 0.16 M'
= 0.16 x 4 Bagian + 0.05 x 2
= 0.74 M'
Jumlah Sengkang
= Pp / Jarak Sengkang
= 58.8 / 0.15
= 393 Bh
Tiotal Panjang Senkang Selurunya
= 393 x 0.74
= 290.82 M'
Berat Besi Untuk Sengkang
= 290.82 x 0.39
= 113.42 Kg
Kebutuhan Total Untuk Sloff
= Berat Tulanga + Berat Sengkang
= 208.86 + 113.42
= 322.28 Kg 322.277 Kg
j. Perhitungan Kebutuhan Besi Balok 20x20 Kebutuhan Besi Untuk Balok 20x20
Volume Balok = 4.94 m3
Lebar Balok = 0.2 m
Tinggi Balok = 0.2 m
Panjang Balok Lantai I + II = 124 m
Sengkang = ø8-15 cm
Tulangan Pokok = ø 12
Bj Tualangan Pokok ø 10 = 0.89 kg
Bj Tualangan Pokok ø 8 = 0.39 kg
Tebal Selimut Beton = 0.02 m
Jumlah Tulangan Pokok = 4 Bh
Panjang Tulangan Pokok
= 123.6 x 4
= 494.4 M'
Berat Besi Tulangan Pokok
= 494.4 x 0.888
= 439 Kg
Panjang Sengkang
Panjang Sebuah Senkang
= 0.2 - 0.02 + 0.02
= 0.16 M'
= 0.16 x 4 Bagian + 0.05 x 2
= 0.74 M'
Jumlah Sengkang
= Pp / Jarak Sengkang
= 123.6 / 0.15
= 825 Bh
Tiotal Panjang Senkang Selurunya
= 0.74 x 825
= 610.5 M'
Berat Besi Untuk Sengkang
= 610.5 x 0.888
= 542.12 Kg
Kebutuhan Total Untuk Sloff
= Berat Tulanga + Berat Sengkang
= 494.4 + 542.12
= 1037 Kg 1036.52 Kg
k. Perhitungan Kebutuhan Besi Kolom 20x20 Kebutuhan Besi Untuk Kolom 20x20
Volume Kolom = 0.2 M3
Jumlah Kolom Lantai I = 17 Bh
Jumlah Kolom Lantai II = 17 Bh
Lebar kolom = 0.2 m
Panjang Kolom = 0.2 m
Tinggi Bangunan = 3 m
Sengkang = ø8-15 cm
Tulangan Pokok = ø 12
Bj Tualangan Pokok ø 10 = 0.89 kg
Bj Tualangan Pokok ø 8 = 0.39 kg
Tebal Selimut Beton = 0.02 m
Jumlah Tulangan Pokok = 4 Bh
Panjang Tulangan Pokok
= 3 x 4x 34
= 408 M'
Berat Besi Tulangan Pokok
= 408 x 0.888
= 362.3 Kg
Panjang Sengkang
Panjang Sebuah Senkang
= 0.2 - 0.02 + 0.02
= 0.16 M'
= 0.16 x 4 Bagian + 0.05 x 2
= 0.74 M'
Jumlah Sengkang
= Tingga Bangun / Jarak Sengkang
= 3 / 0.15
= 21 x 34 = 715 Bh
Tiotal Panjang Senkang Selurunya
= 715 x 0.74
= 529.1 M'
Berat Besi Untuk Sengkang
= 529.1 x 0.39
= 206.35 Kg 568.653 Kg
l. Perhitungan Kebutuhan Besi Kolom 15x15 Kebutuhan Besi Untuk Kolom 15x15
Volume Kolom = 0.48 M3
Jumlah Kolom Lantai I = 3 Bh
Jumlah Kolom Lantai II = 1 Bh
Lebar kolom = 0.15 m
Panjang Kolom = 0.15 m
Tinggi Bangunan = 3 m
Sengkang = ø8-15 cm
Tulangan Pokok = ø 12
Bj Tualangan Pokok ø 10 = 0.62 kg
Bj Tualangan Pokok ø 8 = 0.39 kg
Tebal Selimut Beton = 0.02 m
Jumlah Tulangan Pokok = 4 Bh
Panjang Tulangan Pokok
= 3 x 4x 4
= 48 M'
Berat Besi Tulangan Pokok
= 48 x 0.617
= 29.616 Kg
Panjang Sengkang
Panjang Sebuah Senkang
= 0.15 - 0.02 + 0.02
= 0.11 M'
= 0.11 x 4 Bagian + 0.05 x 2
= 0.54 M'
Jumlah Sengkang
= Tingga Bangun / Jarak Sengkang
= 3 / 0.15
= 21 x 4 = 85 Bh
Tiotal Panjang Senkang Selurunya
= 85 x 0.54
= 45.9 M'
Berat Besi Untuk Sengkang
= 45.9 x 4
= 183.6 Kg
Kebutuhan Total Untuk Sloff
= Berat Tulanga + Berat Sengkang
= 29.616 + 183.6
= 213.22 Kg 213.216 Kg
Telapak Pondasi
Panjamg Tulangan Utama
= 0.7 x 14 = 9.8 M'
Berat Besi diameter 12
= 9.8 x 0.617 x 17
= 102.79 Kg
Menhitung Sengkang
Panjang Sengkang
= 0.2 - 0.03 + 0.03 x 4
= 0.56 M'
Jumlah Sengkang
= 0.75 / 0.15 x 17
= 85 Bh
Panjang Sengkang Seluruhnya
= 0.56 x 85
= 47.6 M'
Jumlah Seluruhnya
= 247.22 Kg 247.22 Kg
o. Perhitungan Kebutuhan Besi Pondasi Telapak Untuk Tangga Panjang Kolom = 1.24 m
Panjang Tulangan diameter 10
= 1.24 x 4 Bh Tulangan Pokok
= 4.96 M'
Berat Besi
= 4.96 x 0.617
= 3.0603 Kg
Sengkang
= 8.2667 x 0.24
= 1.984 M'
Berat Senkang Diameter 8
= 1.984 x 0.39
= 0.7738 kg 3.83408 kg
p. Perhitungan Kebutuhan Besi Plat Lantai Menghitung Tulangan Bagian I
Panjang = 5.26 m
Lebar = 2.5 m
Tulangan Araha X = Ø 12 - 0.15 cm
Tulangan Araha Y = Ø 10 - 0.15 cm
Bj Untuuk Ø 12 = 0.888
Bj Untuuk Ø 10 = 0.617
Menghitung Kusen P2
Lebar Kusen P2 = 1.8 m
Tinggi Kusen P2 = 2 m
Jumlah Kusen P2 = 3 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 1.8 + 2 x 2
= 5.8 x 3
= 17.4 M'
= 0.06 x 0.12 x 17.4
= 0.12528 M3
Menghitung Kusen P3
Lebar Kusen P3 = 1.06 m
Tinggi Kusen P3 = 2 m
Jumlah Kusen P3 = 2 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 1.06 + 2 x 2
= 5 x 2
= 10.12 M'
= 0.06 x 0.12 x 10.12
= 0.072864 M3
Menghitung Kusen J1
Lebar Kusen J1 = 0.97 m
Tinggi Kusen J1 = 1.5 m
Jumlah Kusen J1 = 2 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 0.97 x 2 + 1.5 x 2
= 4 x 2
= 8.38 M'
= 0.06 x 0.12 x 8.38
= 0.060336 M3
Menghitung Kusen J2
Lebar Kusen J2 = 1.68 m
Tinggi Kusen J2 = 1 m
Jumlah Kusen J2 = 5 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 1.68 x 2 + 1 x 3
= 6.36 x 5
= 31.8 M'
= 0.06 x 0.12 x 31.8
= 0.22896 M3
Menghitung Kusen J3
Lebar Kusen J3 = 2.4 m
Tinggi Kusen J3 = 1.5 m
Jumlah Kusen J3 = 3 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 2.4 x 2 + 1.5 x 4
= 10.8 x 3
= 32.4 M'
= 0.06 x 0.12 x 32.4
= 0.23328 M3
Menghitung Kusen J3a
Lebar Kusen J3a = 2.4 m
Tinggi Kusen J3a = 1 m
Jumlah Kusen J3a = 1 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 2.4 x 2 + 1 x 4
= 8.8 x 1
= 8.8 M'
= 0.06 x 0.12 x 8.8
= 0.06336 M3
Menghitung Kusen V1
Lebar Kusen V1 = 0.96 m
Tinggi Kusen V1 = 0.5 m
Jumlah Kusen V1 = 3 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 0.96 x 2 + 0.5 x 2
= 2.92 x 3
= 8.76 M'
= 0.06 x 0.12 x 8.76
= 0.063072 M3
Menghitung Kusen Hak Angin
Lebar Kusen = 0.3 m
Tinggi Kusen = 0.2 m
Jumlah Kusen = 36 Bh
Kayu Yang Dipakai = 6 x 12 x 3
= 0.3 x 2 + 0.2 x 2
= 1 x 36
= 36 M'
= 0.06 x 0.12 x 36
= 0.2592 M3
Arah Horizontal
= 3 x 2+ 2 x 2+ 3.8 +
5.73
= 19.53 M'
Panjang total
= 44.13 M' 44.13 M'
e. Pekerjaan Kuda-Kuda kayu kelas I Kuda-Kuda I
Jumlah Kuda-Kuda I = 2 Bh
Kayu Rep = 6 cm x12 cm x 3 m
Kaki Kuda-kuda = 1.98 m
Tiang Nok = 0.63 m
Balok Pengunci = 0.4 m
Balok Kuda-Kuda = 2.2 m
P = 3.96 + 0.63 + 0.4 + 2.2
= 14.38
V = 0.06 x 0.12 x 14.38
= 0.104 M3
Kuda-Kuda II
Jumlah Kuda-Kuda II = 2 Bh
Kayu Rep = 6 cm x12 cm x 3 m
Kaki Kuda-kuda = 4.3 m
Tiang Nok = 1.83 m
Penopang = 0.99 m
Balok Kuda-Kuda = 4 m
Jepit = 1.33 m
P = 4.3 + 1.83 + 0.99 + 4
+ 1.33
= 24.9 M'
V = 0.06 x 0.12 x 24.9
= 0.179 M3
Kuda-Kuda III
Jumlah Kuda-Kuda III = 2 Bh
Kayu Rep = 6 cm x12 cm x 3 m
Kaki Kuda-kuda = 3.3 m
Tiang Nok = 1.2 m
Penopang = 0.85 m
Balok Kuda-Kuda = 4.22 m
Kaki-Kaki = 0.8 m
Balok Pengunci = 0.4 m
P = 6.6 + 1.2 + 1.7 + 4.22
+ 1.6 + 0.4
= 31.44 M'
V = 0.06 x 0.12 x 31.44
= 0.226 M3
Kuda-Kuda IV
Jumlah Kuda-Kuda IV = 1 Bh
Kayu Rep = 6 cm x12 cm x 3 m
Kaki Kuda-kuda = 5.05 m
Tiang Nok = 1.83 m
Penopang = 2.6 m
Balok Kuda-Kuda = 3.17 m
Kaki-Kaki = 2.6 m
Balok Pengunci = 0.8 m
P = 5.05 + 1.83 + 2.6 + 3.17
+ 2.6 + 0.8
= 16.05 M'
V = 0.06 x 0.12 x 16.05
= 0.116 M3
Kuda-Kuda V
Jumlah Kuda-Kuda V = 2 Bh
Kayu Rep = 6 cm x12 cm x 3 m
Kaki Kuda-kuda = 5.78 m
Tiang Nok = 1.83 m
Penopang = 2.74 m
Balok Kuda-Kuda = 5 m
Kaki-Kaki = 2.6 m
Balok Pengunci = 0.8 m
Jepit = 1.96 m
P = 5.78 + 1.83 + 2.74 + 5
+ 2.6 + 0.8 + 1.96
= 41.42 M'
V = 0.06 x 0.12 x 41.42
= 0.298 M3
Total Kubikasi
= K1 + K2 + K3 + K4 + K5
= 0.923 M3 0.92297 M3
g. Pekerjaan Rangka Plafond Tripleks 5 mm Plafond Bagian Dalam Lantai I
Kayu Kelas II Teras Muka = 2 x 2.5 = 5 M2
R. Tamu = 5x 3 = 15 M2
R. Tidur 1 = 3x 3 = 9 M2
KM = 1.5 x 2 = 3 M2
WC = 1.5 x 2 = 3 M2
R. Makn = 4x 3 = 12 M2
Dapur = 3x 2 = 6 M2
Teras Blakng = 4x 2 = 8 M2
Jumlah = 61 M2
Plafond Bagian Luar Lantai I
Bagian I = 2.4 M2
Bagian II = 4 M2
Bagian III = 4.8 M2
Bagian IV = 11.2 M2
Bagian V = 3.2 M2
Bagian VI = 3.2 M2
Bagian VII = 4 M2
Jumlah = 32.8 M2
Jumlah Luasan Plafond Lantai I
= Bagian Dalam + Bagian Luar
= 93.8 M2
Plafond Bagian Dalam Lantai II
Teras Muka = 2 x 2.5 = 5 M2
R. Nonton = 5x 3 = 15 M2
R. Tidur 2 = 3x 3 = 9 M2
R. Tidur 3 = 3x 2 = 6 M2
R. Tidur 4 = 3x 2 = 6 M2
R. Keluarga = 4x 3 = 12 M2
Teras Blakng = 4x 2 = 8 M2
Jumlah = 61 M2
Plafond Bagian Luar Lantai II
Bagian I = 2.4 M2
Bagian II = 4 M2
Bagian III = 4.8 M2
Bagian IV = 11.2 M2
Bagian V = 3.2 M2
Bagian VI = 3.2 M2
Bagian VII = 4 M2
Jumlah = 32.8 M2
Jumlah Luasan Plafond Lantai II
= Bagian Dalam + Bagian Luar
= 93.8 M2
= 51.5 M'
Bagian V
P = 4.72 + 4.16 + 3.47 + 2.77
+ 2.08
= 34.4 M'
- Luasan Bagian II
Panjang Atap = 8 M
Lebar Atap = 6 M
Sudut yang dipakai = 30˚
Aroof 2= ( 8x 6 ) / 0.87
= 55.43 M2
Arah Horizontal
= 2 M'
Panjang total
= 33.38 M' 33.38 M'
Arah Horizontal
= 2 M'
Panjang total
= 33.38 M' 33.38 M'
l.Papan Untuk Talang Panjang Seluruhnya
= 5.2 + 8.2
= 13 M' 13.4 M'
V PEMASANGAN
a. Pasangan Dinding Bata Ad 1 : 4 Panjang Pondasi
= 58.8 - 15
= 43.8 M'
Luasan Kusen PJV dan hak Angin
P1
P2 = 13.44 M2
P3 = 9.6 M2
J1 = 3.44 M2
J2 = 2.31 M2
J3 = 7.4 M2
J13a = 6.6 M2
V1 = 2.2 M2
Hak Angin= 0.72 M2
Jumlah = 45.71 M2
Tinggi Dindin= 2.6 M
Luasan Dinding Lantai I Dan Lantai II
= 136.34 M2 136.34 M2
b. Pasangan Tehel 40 x 40 Tegel Putih Licin Tehel Polos Lantai I
Pemasangan Tehel Lantai I R. Tamu = 5x 3 = 15 M2
R. Tidur 1 = 3x 3 = 9 M2
R. Makn = 4x 3 = 12 M2
Jumlah = 36 M2
Tehel Polos Lantai II
R. Nonton = 5x 3 = 15 M2
R. Tidur 2 = 3x 3 = 9 M2
R. Tidur 3 = 3x 2 = 6 M2
R. Tidur 4 = 3x 2 = 6 M2
R. Keluarga = 4x 3 = 12 M2
Jumlah = 48 M2
Luasan Tehel Seluruhnya
= Lantai I+ Lantai II
= 84 M2 84 M2
c. Pasangan Tehel 40 x 40 Tegel Putih Anti Slip
Pemasangan Tehel Lantai II Tehel Anti Slip Lantai I
Teras Muka = 2 x 2.5 = 5 M2
Dapur = 3x 2 = 6 M2
Teras Blakng = 4x 2 = 8 M2
Jumlah = 19 M2
Tehel Anti Slip Lantai II
Teras Muka = 2 x 2.5 = 5 M2
Teras Blakng = 4x 2 = 8 M2
Jumlah = 13 M2
Luasan Tehel Seluruhnya
= Lantai I+ Lantai II
= 32 M2 32 M2
d. Pasangan Tehel 20x20 Tegel Putih Anti Slip Tehel 20x20 Anti Slip
KM = 1.5 x 2 = 3 M2
WC = 1.5 x 2 = 3 M2
Jumlah = 6 M2 6 M2
e. Pasangan Tehel 20x20 Tegel Putih Anti Slip Untuk Tangga Tehel 20x20 Anti Slip
V = 0.8 x 0.7 x 32 + 0.8 x
0.7
= 18.48 M2 18.48 M2
L = 0.25 x 3 x 44.13
= 66.2 M2 66.195 M2
f. Pengecatan Daun Pintu dan Daun Jendela L Pek Daun Pintu = 24.07 M2
L Pek Daun Jendela = 16.49 M2
Bagian yang di cat = 2 Bagian
L = 24.07 + 16.492 x 2
= 81.13 M2 81.1308 M2
g. Pengecatan Kusen PJV Hak Angin Pengecatan Kusen PJV dan Hak Angin
Kusen P1 = 7.6608 M2
Kusen P2 = 4.176 M2
Kusen P1 = 2.4288 M2
Kusen J1 = 2.3712 M2
Kusen J2 = 8.232 M2
Kusen J3 = 8.856 M2
Kusen J3a = 1.92 M2
Kusen V1 = 2.1024 M2
Hak Angin= 8.64 M2
Jumlah = 46.387 M2 46.3872 M2
X Pekerjaan Akhir