Anda di halaman 1dari 9

BACK UP DATA

PEKERJAAN : PERENCANAAN PEMBANGUNAN GEDUNG UJI KENDARAAN DINAS PERHUBUNGAN


LOKASI : TERMINAL DAYA
TAHUN ANGGARAN : 2019

No URAIAN PEKERJAAN DAN SKETSA PERHITUNGAN SATUAN VOLUME


A PEKERJAAN PERSIAPAN
1 PENGUKURAN & PEMASANGAN BOWPLANK m' 48.00
2 DIREKSI KEET ls 1.00
3 PEMBERSIHAN LOKASI PROYEK m2 800.00
4 ALAT BANTU STAGGER m2 360.00
5 PENGURUSAN IMB ls 1.00
6 AIR KERJA bln 6.00
7 LISTRIK KERJA bln 6.00

B PEKERJAAN TANAH
1 Pekerjaan Galian Tanah Pondasi Garis kode PJG x tinggi x lebar
Memanjang A 140.00 x 0.5 x 0.8 = 56 m3 m3 126.08
B 305.00 x 0.2 x 0.8 = 48.8 m3

melintang 1 38.00 x 0.5 x 0.8 = 15.2 m3


2 38.00 x 0.2 x 0.8 = 6.08 m3
521.00 x 0.2 x 0.8 126.08 m3

Pekerjaan Galian Pilecap Jumlah Poer (P1) = 32.00 bh dimensi = 1.2 x 1.2 m3 92.16
Luas x tinggi x jumlah
V (P1) = 1.44 x 2 x 32.00 = 92.16 m3
92.16 m3

2 Urugan Tanah Kembali Volume Galian Pondasi Garis = 126.08 m3 m3 50.43


Volume = 0.40 m3
Volume Urugan = 50.43 m3

Volume Galian Poer Plat = 92.16 m3 m3 64.51


Volume Beton Poer Plat = 27.65 m3
Volume Urugan = 64.51 m3

Luas Bg x t
3 Pekerjaan Timbunan Pasir Bawah Lantai 20 cm V1 = 239.16 x 0.2 = 47.83 m3 m3 70.23
V2 = 111.97 x 0.2 = 22.39 m3
Volume Timb = 70.23 m3

Pekerjaan Timbunan Sirtu Utk Peninggian Lantai V1 = 549.48 x 0.45 = 247.27 m3 m3 484.46
V2 = 70 x 0.73 = 51.10 m3
V3 = 351.13 x 0.53 = 186.10 m3
Volume Timb = 484.46 m3

Pjg x Lebar x tebal


4 Urugan Pasir dibawah Pondasi garis V = 521.00 x 0.6 x 0.1 = 31.26 m3 m3 31.26

Jml x Lebar x tebal


5 Urugan Pasir dibawah Pondasi pilecap V = 32.00 x 2.25 x 0.1 = 7.2 m3 m3 7.2

Luas Bg x t
6 Urugan Pasir Bawah Lantai V1 = 239.16 x 0.10 = 23.92 m3 m3 35.11
V2 = 111.97 x 0.10 = 11.20 m3
Volume = 35.11 m3

Luas Bg x t
7 Pekerjaan Timbunan Tanah Pilihan (Sirtu) V1 = 222 x 0.90 = 199.80 m3 m3 200.22
V2 = 4.2 x 0.10 = 0.42 m3
Volume = 200.22 m3

C PEKERJAAN PONDASI
kode PJG x tinggi x lebar
1 Pasangan Batu Kosong Memanjang A 6.29 x 0.2 x 0.4 = 0.5028 m3 m3 0.75
V = PANJANG DINDING - LEBAR KOLOM B 3.15 x 0.2 x 0.4 = 0.252 m3
9.44 x 0.2 x 0.4 0.75 m3

melintang 1 9.40 x 0.2 x 0.4 = 0.752 m3 m3 3.01


2 9.40 x 0.2 x 0.4 = 0.752 m3
18.80 x 0.2 x 0.4 3.01 m3

Total pas. Batu kosong m2 3.77

Pjg x tinggi x lebar


2 Pasangan Pondasi Batu Kali, 1 : 3 Volume = 9.44 x 2 x 0.45 = 8.4915 m3 m3 8.492
= 18.80 x 0.6 x 0.45 = 5.076 m3 m3 5.076

Total pas. Pondasi batu kali m2 13.57


3 MEMBUAT PONDASI POER PLAT BETON K250

- Pemasangan Bekisting Pondasi Jumlah Poer (F1) = 32.00 bh dimensi = 1.20 x 1.20 m2 43.20

Panjang x tinggi jumlah


V (F1) = 4.8 x 0.3 x 30.00 = 43.20 m2
Volume = 43.20 m2

Total bekisting pondasi Foor plat m2 43.20

- Pembesian Pondasi Plat Pembesian F1


model dia Pjg Jumlah Berat/m Jumlah satuan kg 1247.288
A1 12 2.84 7.73 0.89 19.48888 kg
B1 12 2.84 7.73 0.89 19.48888 kg
Model A1 Jumlah 38.977759 kg
Berat Besi Poer P1 32.00 1247.2883 kg

Model B1

Berat Total Besi Poer Plat = 1247.288 kg

Total Pembesian pondasi Foor plat Kg 1247.288

- Beton mutu K250 Jumlah Poer (F1) = 32.00 bh dimensi = 1.2 x 1.2 m3 13.82

luas x tinggi jumlah


V (F1) = 1.44 x 0.3 x 32.00 = 13.82 m3
Volume = 13.82 m3

Total Beton mutu K250 Foor plat m3 13.824

Lantai Kerja K100 Jumlah Poer (F1) = 32.00 bh dimensi = 1.50 x 1.50 m3 5.04

luas x tinggi jumlah


V (F1) = 2.25 x 0.07 x 32.00 = 5.04 m3
Volume = 5.04 m3

Total Lantai kerja K175 Foor plat m3 5.040

Urugan pasir foor plat Jumlah Poer (F1) = 32.00 bh dimensi = 1.40 x 1.40 m3 3.14

luas x tinggi jumlah


V (F1) = 1.96 x 0.05 x 32.00 = 3.14 m3
Volume = 3.14 m3

Total Urugan pasir Foor plat m3 3.136

4 PEMBUATAN PEDESTAL PONDASI BETON 40/40 K250

Pemasangan Bekisting Kolom Jumlah Poer (F1) = 32.00 bh dimensi = 0.40 x 0.40

Panjang x tinggi jumlah


V (F1) = 1.6 x 2.7 x 32.00 = 138.24 m2
Volume = 138.24 m2
2x pakai 69.12 m2 m2 69.12
Total Bekisting kolom pedestal m2 69.120

Pembesian Kolom pedestal Pembesian F1


model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 1.54 18.00 0.22 6.1494325 kg
B1 12 3.08 4 0.89 10.932324 kg
B2 12 2.93 8 0.89 20.799812 kg
Jumlah 37.881569 kg
Berat Besi Pedestal F1 32.00 1212.2102 kg kg 1212.210
A1

B1 B2
Total Pembesian kolom pedestal Kg 1212.210

Cor beton K250 Kolom pedestal Jumlah Poer (F1) = 32.00 bh dimensi = 0.40 x 0.40

luas x tinggi jumlah


V (F1) = 0.16 x 2.7 x 32.00 = 13.82 m3
Volume = 13.82 m3 m2 13.82

Total Cor K225 kolom pedestal m2 13.824


D PEKERJAAN BETON
1 PEKERJAAN SLOOF BETON 20/40 K250 = (S1) sloof Melintang (S1)
Pemasangan Bekisting sloof Panjang = 140.00 m t = 0.40 cm
V = 140.00 x 0.40 x 2.00 = 112.00 m2

Sloof Memanjang (S1)


Panjang = 64.00 m t = 0.40 cm
V = 64.00 x 0.40 x 2.00 = 51.20 m2
2x pakai = 81.60 m2 M2 81.60
Total Pemasangan Bekisting sloof 20/40 (S1) M2 81.600

Pembesian sloof (S1) Pembesian SLOEF Melintang S1


model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 1.38 933 0.22 285.73121 kg
B1 12 140.00 2 0.89 248.46192 kg
B2 12 140.10 4 0.89 497.27879 kg
Jumlah 1031.4719 kg kg 1031.472

A1 Pembesian SLOEF Memanjang S1


model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 1.30 426.667 0.22 123.04781 kg
B1 B1 12 64.00 2 0.89 113.58259 kg
B2 12 64.10 4 0.89 227.52013 kg
B2
Jumlah 464.15053 kg kg 464.151

Total Pembesian sloof 20/40 (S1) Kg 1495.622

Pemasangan Bekisting sloof PJG x tinngi x lebar m3 16.32


Cor beton sloof 20/40 (S1) Memanjang 140.00 x 0.40 x 0.2 = 11.2 m3

Melintang 64.00 x 0.40 x 0.2 = 5.12 m3


204.00 = 16.32 m3 m3 16.32

1 PEKERJAAN SLOOF BETON 15/20 K250 = (S2) Sloof Melintang (S2)


Panjang = 305.00 m t = 0.20 cm
V = 305.00 x 0.20 x 2.00 = 122.00 m2

Sloof Memanjang (S2)


Panjang = 99.00 m t = 0.20 cm
V = 99.00 x 0.20 x 2.00 = 39.60 m2
2x pakai = 80.80 m2 M2 80.80
Total Pemasangan Bekisting sloof 15/20 (S2) M2 80.800

Pembesian sloof (S2)


Pembesian SLOEF Melintang S2
model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 0.48 2033 0.22 216.51682 kg
B1 12 305.20 4.00 0.89 1083.294 kg
Jumlah 1299.8108 kg kg 1299.811
A1
Pembesian SLOEF Memanjang S2
model dia Pjg Jumlah Berat/m Jumlah satuan
B1 A1 6 0.64 660 0.22 93.705638 kg
B1 12 99.20 4 0.89 352.10604 kg
Jumlah 445.81167 kg kg 445.812

Total Pembesian sloof 15/20 (S2) Kg 1745.622

Cor beton sloof 15/20 (S2) PJG x tinngi x lebar


Memanjang 305.00 x 0.20 x 0.15 = 9.15 m3

Melintang 99.00 x 0.20 x 0.15 = 2.97 m3


404.00 = 12.12 m3 m3 12.12
4 PEKERJAAN KOLOM BETON 15/15 K250 (Kp)
Jml Kolom (Kp) = 25.00 bh dimensi = 0.15 x 0.15
V1 = 5.20 x 25.00 x 0.60 = 78.00 m2
Jml Kolom (Kp) = 26.00 bh dimensi = 0.15 x 0.15
V2 = 3.20 x 26.00 x 0.60 = 49.92 m2
2x pakai = 63.96 m2 M2 63.96
Total Pemasangan Bekisting kolom 15/15 (Kp) M2 63.96
Pembesian Kp
Kp model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 0.24 35 0.22 1.8457171 kg
A1 B1 12 5.30 4 0.89 18.812117 kg
Jumlah 20.657834 kg
B1 Berat Besi K3 25.00 516.44585 kg kg 516.446
Pembesian KP
model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 0.24 21 0.22 1.1358259 kg
B1 10 3.30 4 0.62 8.13417 kg
Jumlah 9.2699959 kg
Berat Besi KP 26.00 241.01989 kg kg 241.020

Total Pembesian kolom 15/15 (Kp) Kg 757.466

Cor Beton mutu K250 (KP) Jml Kolom (KP) = 25.00 bh dimensi = 0.15 x 0.15
V1 = Tinggi x jml x luas
Kp = 5.20 x 25.00 x 0.02 = 2.93 m3 m3 2.93
Jml Kolom (KP) = 26.00 bh dimensi = 0.15 x 0.15
V2 = Tinggi x jml x luas
Kp = 3.20 x 26.00 x 0.02 = 1.87 m3 m3 1.87

Total beton kolom 15/15 (Kp) m3 4.797


5 PEKERJAAN RINGBALK BETON 15/20 K250 (RB)
Memanjang
Pemasangan Bekisting Ringbalk 15/20 PANJANG = 45.00 m dimensi = 0.20 x 0.15
V1 = 45.00 x 0.31 = 13.95 m2
Melintang
PANJANG = 28.00 m dimensi = 0.20 x 0.15
V2 = 28.00 x 0.31 = 8.68 m2
2x pakai = 11.32 m2 m2 11.32
Total Bekisting Balok 15/20 (RB1) m2 11.315

Memanjang
Pembesian Ringbalk Pembesian RB1
model dia Pjg Jumlah Berat/m Jumlah satuan
A1 6 0.660 180.00 0.22 26.3547 kg
B1 12 46.224 1.00 0.89 41.017514 kg
A1 Jumlah 67.372 kg kg 67.37

Melintang
Pembesian RB1
model dia Pjg Jumlah Berat/m Jumlah satuan
B1
A1 6 0.660 112.00 0.22 16.3985 kg
B1 12 46.224 1.00 0.89 41.017514 kg
Jumlah 57.416 kg kg 57.42

Total Pembesian Balok 15/20 (RB) Kg 124.788

Cor beton K250 Ringbalk 15/20 (B1) kode PJG x tinggi x lebar
Memanjang 45.00 x 0.20 x 0.15 = 1.35 m3
Volume = 1.35 m3 m3 1.35

kode PJG x tinggi x lebar


Melintang 28.00 x 0.20 x 0.15 = 0.84 m3
Volume = 0.84 m3 m3 0.84

Total Beton Ringbalk 15/20 (RB1) m3 2.190


PEKERJAAN DINDING BETON PIT KENDARAAN
- Pemasangan Bekisting Pondasi Jumlah dinding 1 = 2.00 bh dimensi = 13.00 m2 24.66
Jumlah dinding 2 = 2.00 bh dimensi = 0.70
Panjang x tinggi jumlah
V (F1) = 13.00 x 1.8 x 1.00 = 23.40 m2
V (F1) = 0.70 x 1.8 x 1.00 = 1.26 m2
Volume = 24.66 m2

Total bekisting pondasi Foor plat m2 24.66


- Pembesian Pondasi Plat Pembesian F1
model dia Pjg Jumlah Berat/m Jumlah satuan kg 1152.636
A1 12 3.94 86.40 0.89 302.0729 kg
B1 12 26.34 11.73 0.89 274.24517 kg
Model A1 Jumlah 576.31807 kg
Berat Besi Dinding 2.00 1152.6361 kg

Model B1 model dia Pjg Jumlah Berat/m Jumlah satuan kg 67.000


A1 12 3.94 4.40 0.89 15.383342 kg
B1 12 1.74 11.73 0.89 18.116423 kg
Jumlah 33.499766 kg
Berat Besi Dinding 2.00 66.999531 kg

Total Pembesian dinding beton Kg 1219.636

- Beton mutu K250 Jumlah Poer (F1) = 2.00 bh dimensi = 13 = 26 m3 9.86


= 2.00 bh dimensi = 0.7 = 1.4
luas x tinggi tebal
V (F1) = 27.4 x 1.8 x 0.20 = 9.86 m3
Volume = 9.86 m3

Total Beton mutu K250 dinding beton m3 9.864


tebal
- Lantai Pit Kendaraan Jumlah Poer (F1) = 0.20 bh dimensi = 0.3 x 12.6 m3 0.76
luas x tebal
V (F1) = 3.78 x 0.20 = 0.76 m3
Volume = 0.76 m3

Total Beton mutu K175 lantai m3 0.756

6 Pekerjaan Kolom Baja Elv. BOC. -10


kolom type 1
PANJANG = 56.00 m berat/btg = 355.20 pjg/btg = 12
V1 = 56.00 x 35.52 = 1989.12 kg kg 1989.12
kolom type 2
PANJANG = 8.00 m berat/btg = 355.20 pjg/btg = 12
V2 = 8.00 x 35.52 = 284.16 kg kg 284.16

Total Kolom Baja kg 2273.280

Footplate
LUASAN = 0.32 m berat/lbr = 2,486.88 luas/lbr = 2.88
30 L1 = 0.32 x 863.50 = 273.56 kg kg 273.557

Stiffener
LUASAN = 0.18 m berat/lbr = 1,440.83 luas/lbr = 2.88
L1 = 0.18 x 500.29 = 91.83 kg kg 91.826
16,5
LUASAN = 0.19 m berat/lbr = 1,507.20 luas/lbr = 2.88
L2 = 0.19 x 523.33 = 100.48 kg kg 100.480

Total Stiffener kg 192.306


Baut Dia. 19
Jumlah baut = 8.00 bh jml. kolom = 32.00 kolom
B1 = 8.00 x 32.00 = 256.00 bh bh 256.000

Cat Zinchromate
JUMLAH = 32.00 kolom
Cat Kolom Baja = 3.92 x 32.00 = 125.57 m2 m2 125.568
10 Cat Foot Plate = 1.12 x 32.00 = 35.71 m2 m2 35.712
Cat Stiffener = 0.17 x 32.00 = 5.59 m2 m2 5.591

Total Cat Zinchromate m2 166.871

10 Pengelasan = 32.00 kolom


= 6.18 x 32.00 = 197.76 cm cm 197.760
7 Pekerjaan Balok Baja Elv. TOC. 2.00 m
balok type 1
PANJANG = 120.00 m berat/btg = 158.40 pjg/btg = 12
V1 = 120.00 x 15.84 = 1900.80 kg kg 1900.80
balok type 2
PANJANG = 8.00 m berat/btg = 158.40 pjg/btg = 12
V2 = 8.00 x 15.84 = 126.72 kg kg 126.72

Total Balok Baja kg 2027.520

Plat penyambung
LUASAN = 0.05 m berat/lbr = 395.64 luas/lbr = 2.88
L1 = 0.05 x 137.38 = 6.92 kg kg 6.924
12,5
Stiffener
LUASAN = 0.13 m berat/lbr = 991.93 luas/lbr = 2.88
L1 = 0.13 x 344.42 = 43.52 kg kg 43.521

6 Baut Dia. 16
Jumlah baut = 4.00 bh jml. kolom = 28.00 kolom
B1 = 4.00 x 28.00 x 2 = 224.00 bh bh 224.000

Cat Zinchromate
JUMLAH = 28.00 balok
Cat Balok Baja = 1.54 x 28.00 = 43.23 m2 m2 43.232
Cat Plat Samb. = 0.37 x 28.00 = 10.37 m2 m2 10.367
Cat Stiffener = 0.06 x 28.00 = 1.77 m2 m2 1.769

Total Cat Zinchromate m2 55.368

Pengelasan = 28.00 balok


= 34.13 x 28.00 = 955.50 cm cm 955.500

8 Pekerjaan Kolom Baja Elv. TOC. +2.00 s/d 6.00 m


kolom type 1
PANJANG = 112.00 m berat/btg = 355.20 pjg/btg = 12
V1 = 112.00 x 35.52 = 3978.24 kg kg 3978.24
kolom type 2
PANJANG = 16.00 m berat/btg = 355.20 pjg/btg = 12
V2 = 16.00 x 35.52 = 568.32 kg kg 568.32

Total Kolom Baja kg 4546.560

Footplate
LUASAN = 0.32 m berat/lbr = 2,486.88 luas/lbr = 2.88
L1 = 0.32 x 863.50 = 273.56 kg kg 273.557

Stiffener
LUASAN = 0.55 m berat/lbr = 4,322.50 luas/lbr = 2.88
L1 = 0.55 x 1500.87 = 826.43 kg kg 826.433

Total Stiffener kg 826.433

Cat Zinchromate
JUMLAH = 32.00 kolom
Cat Kolom Baja = 2.54 x 32.00 = 81.41 m2 m2 81.408
Cat Stiffener = 0.17 x 32.00 = 5.53 m2 m2 5.529

Total Cat Zinchromate m2 86.937

9 Pekerjaan Balok Baja Elv. TOC. 2.00 s/d 6.00 m


balok type 1
PANJANG = 120.00 m berat/btg = 158.40 pjg/btg = 12
V1 = 120.00 x 15.84 = 1900.80 kg kg 1900.80
balok type 2
PANJANG = 8.00 m berat/btg = 158.40 pjg/btg = 12
V2 = 8.00 x 15.84 = 126.72 kg kg 126.72

Total Balok Baja kg 2027.520

Plat penyambung
LUASAN = 0.05 m berat/lbr = 395.64 luas/lbr = 2.88
L1 = 0.05 x 137.38 = 6.92 kg kg 6.924
12,5
Stiffener
LUASAN = 0.13 m berat/lbr = 991.93 luas/lbr = 2.88
L1 = 0.13 x 344.42 = 43.52 kg kg 43.521

6 Baut Dia. 16
Jumlah baut = 4.00 bh jml. kolom = 28.00 kolom
B1 = 4.00 x 28.00 x 2 = 224.00 bh bh 224.000

Cat Zinchromate
JUMLAH = 28.00 balok
Cat Balok Baja = 1.54 x 28.00 = 43.23 m2 m2 43.232
Cat Plat Samb. = 0.37 x 28.00 = 10.37 m2 m2 10.367
Cat Stiffener = 0.06 x 28.00 = 1.77 m2 m2 1.769

Total Cat Zinchromate m2 55.368

Pengelasan = 28.00 balok


= 34.13 x 28.00 = 955.50 cm cm 955.500
10 Pekerjaan Kuda-Kuda Baja Elv. TOC. +6.00 s/d +10.00
Kuda-Kuda 1 IWF 250
PANJANG = 193.26 m berat/btg = 355.20 pjg/btg = 12
V1 = 193.26 x 35.52 = 6864.52 kg kg 6864.52
Rafter IWF 250
PANJANG = 1.57 m berat/lbr = 355.20 pjg/btg = 12
R1 = 1.57 x 35.52 = 55.73 kg kg 55.730

Total Kuda-Kuda Baja IWF 250 kg 6920.255


Kuda-Kuda 2 IWF 125
PANJANG = 31.20 m berat/btg = 158.40 pjg/btg = 12
V2 = 31.20 x 15.84 = 494.21 kg kg 494.21
Rafter IWF 125
PANJANG = 2.37 m berat/lbr = 158.40 pjg/btg = 12
R2 = 2.37 x 15.84 = 37.58 kg kg 37.580

Total Kuda-Kuda Baja IWF 125 kg 531.788

Plat penyambung
LUASAN = 0.21 m berat/lbr = 1,682.65 luas/lbr = 2.88
25 IWF 250 = 0.21 x 584.25 = 125.23 kg kg 125.235

LUASAN = 0.02 m berat/lbr = 183.69 luas/lbr = 2.88


IWF 125 = 0.02 x 63.78 = 1.49 kg kg 1.492

Total Plat Sambungan t. 12 mm kg 126.727


12,5
Stiffener
LUASAN = 0.60 m berat/lbr = 4,682.71 luas/lbr = 2.88
IWF 250 = 0.60 x 1625.94 = 969.91 kg kg 969.911

54 LUASAN = 0.15 m berat/lbr = 1,175.53 luas/lbr = 2.88


IWF 125 = 0.15 x 408.17 = 61.12 kg kg 61.124

Total Stiffener kg 1031.034


Baut Dia. 16
12,5 Jumlah baut = 42.00 bh jml. kuda2 = 13.00 bh
B1 = 42.00 x 13.00 = 546.00 bh bh 546.000

Cat Zinchromate
JUMLAH = 13.00 kuda-kuda
12,5 Cat Kuda-Kuda Baja = 6.42 x 13.00 = 83.43 m2 m2 83.434
Cat plat penyambung = 2.34 x 13.00 = 30.45 m2 m2 30.446
Cat Stiffener = 0.75 x 13.00 = 9.70 m2 m2 9.702

Total Cat Zinchromate m2 123.582


6
Pengelasan = 13.00 kuda-kuda
= 53.61 x 13.00 = 696.98 cm cm 696.982

11 Gording Canal C. 125.50.20.2.3 Gording


PANJANG = 1436.40 m berat/btg = 27.10 pjg/btg = 6
V1 = 1436.40 x 4.52 = 6487.74 kg kg 6487.74

Total Gording kg 6487.740


Plat dudukan
LUASAN = 0.14 m berat/lbr = 1,102.14 pjg/btg = 2.88
V1 = 0.14 x 459.23 = 64.48 kg kg 64.475

Total Gording kg 64.475

Baut Tambat
Jumlah baut = 24.00 bh jml. kuda2 = 13.00 bh
B1 = 24.00 x 13.00 = 312.00 bh bh 312.000

Cat Zinchromate
JUMLAH = 312.00 gording
Cat gording = 0.39 x 312.00 = 123.12 m2 m2 123.115
Cat plat dudukan = 0.02 x 312.00 = 4.68 m2 m2 4.680

Total Cat Zinchromate m2 127.795

Ikatan angin
PANJANG = 192.00 m berat/btg = 0.89
V1 = 192.00 x 0.89 = 170.50 kg kg 170.50

Total Gording kg 170.496

Trekstang
PANJANG = 422.40 m berat/btg = 0.89
V1 = 422.40 x 0.89 = 375.09 kg kg 375.09

Total Gording kg 375.091

Pengelasan = 312.00 gording


= 0.32 x 312.00 = 100.23 cm cm 100.230
12 PASANGAN BATA MERAH 1:4 TEBAL ½ BATA kode PJG x tinggi - luas kusen
GEDUNG UJI Memanjang A 116.04 x 5.22 - 117.32 = 488.409 M2

melintang 1 85.74 = 85.74 M2


201.78 m = 574.15 m2 m2 574.149

kode PJG x tinggi - luas kusen


PASANGAN BATA MERAH Memanjang A 35.80 x 3.2 - 28.88 = 85.6843 M2
RUANG STAFF DAN GENSET B 19.85 x 0.505 = 10.0243 M2
melintang 1 22.20 x 3.2 - 0.72 = 70.32 M2
77.85 m = 166.03 m2 m2 166.03

13 PLESTERAN 1:4 TEBAL 1,5 cm GEDUNG UJI


Memanjang kode PJG x luar/dalam
A 488.41 x 2 = 976.82 M2 M2 1148.30
melintang 1 85.74 x 2 = 171.48 M2

GEDUNG STAF DAN GENSET


Memanjang kode PJG x luar/dalam
A 85.68 x 2 = 171.37 M2 M2 332.06
B 10.02 x 2 = 20.05 M2
melintang 1 70.32 x 2 = 140.64 M2

14 PENUTUP ATAP GEDUNG UJI KENDARAAN


Aluminium foil Panjang lebar
- luas rangka atap 59.85 x 17.552 = 1050.4872 m2 m2 1050.4872
Atap spandeck
- luas penutup atap spandek 0.35 mm Panjang lebar
59.85 x 17.552 = 1050.4872 m2 m2 1050.4872
Nok spandeck
- luas nok atap spandek 0.35 mm Panjang
59.85 = 59.85 m' m' 59.85

15 PEKERJAAN PENUTUP PLAFON RG STAFF DAN GENSET luasan


- PASANG RANGKA PLAFOND HOLLOW 1x40.40.2mm, modul Luasan 45.59 = 45.59
60x60cm 28.55 = 28.55
gypsumboard 9.18 = 9.18
4.48 = 4.48
18.92 = 18.92
106.72

kalsiboard 27.88 = 27.88


Total rangka plafond = 134.60 m2 134.60

- PLAFON = 106.72 m2
gpsumboard 106.72 m2 m2 106.72

kalsiboard = 27.88 m2
27.875 m2 m2 27.875

PENUTUP ATAP GEDUNG STAFF DAN GENSET


16 rangka atap baja ringan
Panjang lebar
- luas rangka atap 22 x 7.15 = 157.3 m2 m2 157.3

- luas penutup atap spandek 0.35 mm Panjang lebar


22 x 7.15 = 157.3 m2 m2 157.3

- panjang listplank Panjang


36.3 x 0.3 = 10.89 m2 m2 10.89

17 Rencana kabel listrik GEDUNG UJI


Panjang turun ke sakelar
37.15 + 20.8 = 57.95 m'
GEDUNG STAFF DAN GENSET
Panjang turun ke sakelar
34.45 + 20.8 = 55.25 m'

Total = 113.20 m' m' 113.20

20 PEKERJAAN PELAPIS LANTAI GEDUNG UJI

Rabat Beton luasan = 230.47 m2


luas x tebal
V (F1) = 230.47 x 0.08 = 18.44 m3
Volume = 18.44 m3

Total Rabat beton m3 18.437

Urugan pasir luasan = 230.47 m2


luas x tebal
V (F1) = 230.47 x 0.10 = 23.05 m3
Volume = 23.05 m3

Total Urugan pasir m3 23.047

Panjang lebar
- PASANG LANTAI Kramik 60 x 60 cm GEDUNG UJI = 59.862 x 1.93 = 115.234
59.862 x 1.93 = 115.234
= 230.469 m2 230.47

21 PEKERJAAN PELAPIS LANTAI GEDUNG STAF DAN GENSET

Rabat Beton luasan = 111.00 m2


luas x tebal
V (F1) = 111.00 x 0.08 = 8.88 m3
Volume = 8.88 m3

Total Rabat beton m3 8.880

Urugan pasir luasan = 111.00 m2


luas x tebal
V (F1) = 111.00 x 0.10 = 11.10 m3
Volume = 11.10 m3

Total Urugan pasir m3 11.100


luasan luasan
- PASANG LANTAI Kramik 60 x 60 cm GEDUNG UJI = A = 45.59 = 45.59
B = 28.55 = 28.55
C = 9.18 = 9.18
D = 4.48 = 4.48
E = 18.92 = 18.92
= 106.72 m2 106.72

KERAMIK WC 30 x 30 = 2.14 x 2.00 = 4.28


= 4.28 m' 4.28

PASANGAN TEGEL KERAMIK DINDING KM. UMUM


RUANG STAFF DAN GENSET Memanjang kode PJG x tinggi luas kusen
A 4.40 x 1.5 = 6.60 M2 m2 16.30
melintang 1 5.55 x 1.5 1.4 = 6.93 M2
T. Wudhu 1.85 x 1.5 = 2.78 M2

22 PASANGAN ACP FASADE DAN KOLOM luasan depan lebar panjang luasan
Penebalan kolom dan balok LUASAN 1 = 23.8835 + 0.50 x 28.61 = 38.19
LUASAN 2 = 8.8 + 0.50 x 5.5 = 11.55
x 2 = 99.48
LUASAN 3 = 5.566 x 0.50 x 20 = 15.57
5.566 x 0.85 x 2 = 7.27
total 122.31
luasan jumlah
Dinding = 43.92 x 2 = 87.84 m2
total 210.15 m2 m2 210.15

atas bawah samping depan luasan


Kanopi LUASAN 1 = 30.75 + 1.50 + 5.125 = 38.44
x 2 = 76.88 m2 76.88

Anda mungkin juga menyukai