PEKERJAAN STRUKTUR
II.1 PEKERJAAN STRUKTUR BAWAH
II.1.1 PEKERJAAN PONDASI
II.1.1.1 Pondasi Bore Pile (P1)
II.1.1.2 Pondasi Bore Pile (P2)
1. Pekerjaan Pengeboran Tanah Diameter 80 cm
Pembesian 14 D 22
Kuantitas = BJ x t x n = 5125.903 Kg
Tinggi (t) = 7.03 m
Jumlah Batang (n') = 14 btg
Jumlah Titik (n) = 33 ttk
Berat Jenis D16 (BJ) = 1.578
Urugan Pasir
Kuantitas = pxlxtxn = 2.376 m2
Panjang (p) = 1.20 m
Lebar (l) = 1.20 m
Tinggi (t) = 0.05 m
Jumlah Titik (n) = 33.00 ttk
Pembesian Poer 6 D 16
Kuantitas = BJ x p x n' x n = 1699.954 Kg
Panjang (p) = 2.72 m
Jumlah Batang (n') = 12.00 btg
Jumlah Titik (n) = 33.00 ttk
Berat Jenis D16 (BJ) = 1.578
Bekisting Poer Beton
Kuantitas = p x l x Jml sisi x n = 1351.680 m2
Panjang (p) = 3.20 m
Lebar (l) = 3.20 m
Jumlah Sisi = 4.00 sisi
Jumlah Titik (n) = 33.00 ttk
Pembesian 14 D 22
Kuantitas = BJ x t x n = 4193.920 Kg
Tinggi (t) = 7.03 m
Jumlah Batang (n') = 14 btg
Jumlah Titik (n) = 27 ttk
Berat Jenis D16 (BJ) = 1.578
Urugan Pasir
Kuantitas = pxlxtxn = 1.944 m2
Panjang (p) = 1.20 m
Lebar (l) = 1.20 m
Tinggi (t) = 0.05 m
Jumlah Titik (n) = 27.00 ttk
w
II.1.2 PEKERJAAN SLOOF
II.1.2.1 Sloof Type S1
Bentang 6 m
Pekerjaan Galian dan Lantai Kerja GALIAN
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
Pekerjaan Besi
T. POKOK 1.6 1.58
URUGAN
Sengkang :
Tumpuan(ɸ10 - 10)
Lapangan(ɸ10 - 15)
Bentang 5 m GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+4,6+40D=5,88
2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+4,5+40D=5,78
2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
Bentang 7 m GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
40D+6,5+40D=7,78
0,2 + 2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
Bentang 3 m GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+2,6+40D=3,88
2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
Bentang 4 m GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+3,6+40D=4,88
2 + 0,2 - 0,08 = 2,32
5d 5d
URUGAN
GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+3,6+40D=4,88
2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
40D+3,55+40D=4,83
0,2 + 2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
40D+4,3+40D=5,58
0,2 + 2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
Bentang 2 m GALIAN
Pekerjaan Beton dan Bekisting
PASIR URUG
L. KERJA K-100
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
0,2 +40D+1,55+40D=2,83
2 + 0,2 - 0,08 = 2,32
5d 5d
Sengkang :
Tumpuan(ɸ10 - 10) T. SENGKANG 1.0 0.62
Lapangan(ɸ10 - 15)
URUGAN
BETON K-225
KAYU 5/7
KAYU 4/6 l
KAYU 4/6 -
Mlt. 9 mm
Pekerjaan Besi
T. POKOK 1 0.617
Tulangan Pokok
(6 D16)
URUGAN
Sengkang :
Tumpuan(ɸ10 - 10)
Lapangan(ɸ10 - 15)
1.08 29 19.31
19 12.43
total =
31.74
TOTAL = 2325.29
4.6 0.45 0.53 19 20.845
1.08 24 15.98
15 10.21
total =
26.19
TOTAL = 1555.52
4.5 0.45 0.53 6 6.440
5.78 6 54.73
TOTAL = 482.20
6.5 0.45 0.53 6 9.302
7.78 6 73.67
TOTAL = 662.42
2.6 0.45 0.53 3 1.860
2.6 0.45 0.05 3 0.1755
3.88 6 36.74
1.08 14 9.32
9 5.77
total =
15.09
TOTAL = 155.50
3.6 0.45 0.53 3 2.576
4.88 6 46.21
1.08 19 12.65
12 7.99
total =
20.64
TOTAL = 200.55
3.6 0.45 0.53 3 2.576
1.08 19 12.65
12 7.99
total =
20.64
TOTAL = 200.55
3.55 0.45 0.53 2 1.693
TOTAL = 132.20
4.3 0.45 0.53 18 18.460
5.58 6 52.84
TOTAL = 1392.55
1.55 0.45 0.53 3 1.109
2.83 6 26.80
TOTAL = 108.19
GALIAN PASIR L. KERJA BESI BETON BEKISTING
96.91448 9.142875 14.6286 7214.98 40.64 271.32
= 0.15 0.2 #VALUE! #VALUE!
### #VALUE!
TOTAL = #VALUE!
BESI BETON BEKISTING
PE S2
#VALUE! #VALUE! #VALUE!
KUANTITAS
URUG (M3)
BEKISTING (M2)
p x t x n x 2sisi G-(P.U+L.K+B)
M2
M3
M3
M3
M3
10.752
M2
M3
M3
M3
M3
6.992
M2
M3
M3
M3
M3
2.16
M2
M3
M3
M3
M3
3.12
M2
M3
M3
M3
M3
0.624
M2
M3
M3
M3
M3
0.864
M2
M3
M3
M3
M3
0.864
M2
M3
M3
M3
M3
0.568
M2
M3
M3
M3
M3
6.192
M2
M3
M3
M3
M3
0.372
URUG
32.508
M2
M3
M3
M3
M3
#REF!
URUG
#REF!
URAIAN PEKERJAAN /
NO.
SKETSA
STRUKTUR
PEKERJAAN KOLOM LT.1
1. Kolom Type K1
1 Beton
2 Pembesian
Sengkang
3 Bekisting
2. Kolom Type KP
1 Beton
2 Pembesian
Sengkang
3 Bekisting
1 Beton
2 Pembesian
Sengkang
3 Bekisting
2. Kolom Type KP
1 Beton
2 Pembesian
Sengkang
Tulangan Pokok (4D12)
3 Bekisting
1 Beton
2 Pembesian
Sengkang
2. Kolom Type KP
1 Beton
2 Pembesian
Sengkang
3 Bekisting
PEKERJAAN KOLOM LT.4
1. Kolom Type K1
1 Beton
2 Pembesian
Sengkang
3 Bekisting
2. Kolom Type KP
1 Beton
2 Pembesian
Sengkang
3 Bekisting
DIMENSI
SAT KUANTITAS SAT
SIMBOL HASIL
Tulangan = 2.50 cm
= 0.025 m
Berat = 3.85 Kg/m
40d = 1.00 m
Panjang = 8.48 m
Jumlah pot = 14 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 457.17 Kg
Tulangan = 1.00 cm
= 0.010 m
Berat = 0.62 Kg/m
Panjang = 4.35 m
Jumlah pot = 4 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 10.73 Kg
Tulangan = 2.50 cm
= 0.025 m
Berat = 3.85 Kg/m
40d = 1.00 m
Panjang = 8.48 m
Jumlah pot = 14 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 457.17 Kg
Tulangan = 2.50 cm
= 0.025 m
Berat = 3.85 Kg/m
40d = 1.00 m
Panjang = 8.48 m
Jumlah pot = 14 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 457.17 Kg
Tulangan = 1.00 cm
= 0.010 m
Berat = 0.62 Kg/m
Panjang = 4.35 m
Jumlah pot = 4 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 10.73 Kg
Tulangan = 2.50 cm
= 0.025 m
Berat = 3.85 Kg/m
40d = 1.00 m
Panjang = 8.48 m
Jumlah pot = 14 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 457.17 Kg
Tulangan = 1.00 cm
= 0.010 m
Berat = 0.62 Kg/m
Panjang = 4.35 m
Jumlah pot = 4 pot
Berat tul,pokok = Berat x Pjg x Jml Pot = 10.73 Kg
BESI
REKAP UNTUK BALOK TYPE B1 DI LT.2
1348.883
II.2.2.2.BalokType B2
= 26.08
II.2.2.3.BalokType B3
II.2.2.4.Balok Type BA
1 Beton
Kuantitas = pxlxtxn
Panjang (p) =
3,01+3,01+3,01+3,01+3,01
1+3,01+3,01+3,01+3,01
= 30.5
Lebar (l) = 0.20
Tinggi (t) = 0.30
2 Pembesian
Sengkang Kuantitas = (Berat Sengkang + Tul.Pokok
Tulangan = 0.1
Berat = 0.39
Panjang = 0.88
Bentang = 30.50
Jumlah tump = 153
Jumlah lap = 117
Tulangan Pokok (4D16) Berat sengkang = Berat x Pjg x (Jml Tump+La
5d 5d = 0.016
Berat = 1.58
Panjang = 30.98
Jumlah pot = 4
Berat tul,pokok = Berat x Pjg x Jml Pot
Tulangan Pokok (1D16)
Tulangan = 1.6
= 0.016
Berat = 1.58
Panjang = 32.10
Jumlah pot = 1
Berat tul,pokok = Berat x Pjg x Jml Pot
3 Bekisting
Kuantitas = Luas x n
Tinggi 1 (t1) = 0.30
Tinggi 2 (t2) = 0.20
Lebar = 0.20
Panjang (p) = 30.50
Luas (L) = (t1 x p)+(t2 x p) +
BESI
REKAP UNTUK BALOK TYPE B3 DI LT.2
339.695
BESI
REKAP UNTUK BALOK TYPE B1 DI LT.2
1348.883
II.2.2.2.BalokType B2
= 26.08
II.2.2.3.BalokType B3
1 Beton Kuantitas = pxlxtxn
4,55+4,55+4,55+4,55+4,55
Panjang (p) = 5+4,55+4,55+4,55+4,65+4,
4,55+4,55+4,55+4,55+4,55
5+4,55+4,55+4,55+4,55+4,
4,55+4,55+4,55+4,55+
+4,65+4,65+4,65+4,65+4,6
= 26.08
II.2.2.4.Balok Type BA
1 Beton
Kuantitas = pxlxtxn
Panjang (p) =
3,01+3,01+3,01+3,01+3,01
1+3,01+3,01+3,01+3,01
= 30.5
Lebar (l) = 0.20
Tinggi (t) = 0.30
2 Pembesian
Sengkang Kuantitas = (Berat Sengkang + Tul.Pokok
Tulangan = 0.1
Berat = 0.39
Panjang = 0.88
Bentang = 30.50
Jumlah tump = 153
Jumlah lap = 117
Tulangan Pokok (4D16) Berat sengkang = Berat x Pjg x (Jml Tump+La
5d 5d = 0.016
Berat = 1.58
Panjang = 30.98
Jumlah pot = 4
Berat tul,pokok = Berat x Pjg x Jml Pot
Tulangan Pokok (1D16)
Tulangan = 1.6
= 0.016
Berat = 1.58
Panjang = 32.10
Jumlah pot = 1
Berat tul,pokok = Berat x Pjg x Jml Pot
3 Bekisting
Kuantitas = Luas x n
Tinggi 1 (t1) = 0.30
Tinggi 2 (t2) = 0.20
Lebar = 0.20
Panjang (p) = 30.50
Luas (L) = (t1 x p)+(t2 x p) +
BESI
REKAP UNTUK BALOK TYPE B3 DI LT.2
339.695
= 54.56
BESI
REKAP UNTUK BALOK TYPE B1 DI LT.4 (elv +12.60)
1348.883
II.2.2.2.BalokType B2
II.2.2.3.BalokType B3
1 Beton Kuantitas = pxlxtxn
4,55+4,55+4,55+4,55+4,55
Panjang (p) = 5+4,55+4,55+4,55+4,65+4,
4,55+4,55+4,55+4,55+4,55
5+4,55+4,55+4,55+4,55+4,
4,55+4,55+4,55+4,55+
+4,65+4,65+4,65+4,65+4,6
= 26.08
II.2.2.4.Balok Type BA
1 Beton
Kuantitas = pxlxtxn
Panjang (p) =
3,01+3,01+3,01+3,01+3,01
1+3,01+3,01+3,01+3,01
= 30.5
Lebar (l) = 0.20
Tinggi (t) = 0.30
2 Pembesian
Sengkang Kuantitas = (Berat Sengkang + Tul.Pokok
Tulangan = 0.1
Berat = 0.39
Panjang = 0.88
Bentang = 30.50
Jumlah tump = 153
Jumlah lap = 117
Tulangan Pokok (4D16) Berat sengkang = Berat x Pjg x (Jml Tump+La
5d 5d = 0.016
Berat = 1.58
Panjang = 30.98
Jumlah pot = 4
Berat tul,pokok = Berat x Pjg x Jml Pot
Tulangan Pokok (1D16)
Tulangan = 1.6
= 0.016
Berat = 1.58
Panjang = 32.10
Jumlah pot = 1
Berat tul,pokok = Berat x Pjg x Jml Pot
3 Bekisting
Kuantitas = Luas x n
Tinggi 1 (t1) = 0.30
Tinggi 2 (t2) = 0.20
Lebar = 0.20
Panjang (p) = 30.50
Luas (L) = (t1 x p)+(t2 x p) +
BESI
REKAP UNTUK BALOK TYPE BA DI LT.4 (elv 12.60)
339.695
SAT KUANTITAS SAT
pxlxtxn = 20.87 M3
0+9,30+9,30+9,30+9,30+9,30+9,30+9,30+9
,30+9,30+9,30+9,30+9,30+9,30+9,30+9,30
+9,30+9,30+9,30+9,30+9,30+9,30+9,30
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 644.69 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 704.19 Kg
= 92.75 M2
m
m
m
= 92.75 M2
BETON BEKISTING
20.869 92.752
pxlxtxn = 3.91 M3
4,30+4,30+4,30+4,30+4,30+4,30+1,27+1,27+1,2
7+1,27+1,27+1,27+1,27+4,74+4,51+4,32+4,32+
4,51+4,74+4,30+4,30+4,30+4,30+4,30+4,30+4,3
0
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 578.45 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 26.08 M2
m
m
m
= 26.08 M2
BETON BEKISTING
3.912 26.08
pxlxtxn = 3.52 M3
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,65+4,65+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+
5+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55
+4,65+4,65+4,65+4,65+4,65+4,65+4,65+4,60+4,
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 578.45 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 23.47 M2
m
m
m
= 23.47 M2
BETON BEKISTING
3.521 23.47
pxlxtxn = 1.83 M3
3,01+3,01+3,01+3,01+3,01+3,01+3,01+3,0
1+3,01+3,01+3,01+3,01+3,01+3,01+
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 93.46 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 195.58 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 50.66 Kg
= 21.350 M2
m
m
m
m
(t1 x p)+(t2 x p) + (l x p) = 21.350 M2
BETON BEKISTING
1.830 21.35
pxlxtxn = 20.87 M3
0+9,30+9,30+9,30+9,30+9,30+9,30+9,30+9
,30+9,30+9,30+9,30+9,30+9,30+9,30+9,30
+9,30+9,30+9,30+9,30+9,30+9,30+9,30
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 644.69 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 704.19 Kg
= 92.75 M2
m
m
m
= 92.75 M2
BETON BEKISTING
20.869 92.752
pxlxtxn = 3.91 M3
4,30+4,30+4,30+4,30+4,30+4,30+1,27+1,27+1,2
7+1,27+1,27+1,27+1,27+4,74+4,51+4,32+4,32+
4,51+4,74+4,30+4,30+4,30+4,30+4,30+4,30+4,3
0
m
m
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 26.08 M2
m
m
m
= 26.08 M2
BETON BEKISTING
3.912 26.08
pxlxtxn = 3.52 M3
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,65+4,65+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55
+4,65+4,65+4,65+4,65+4,65+4,65+4,65+4,60+4,
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 578.45 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 23.47 M2
m
m
m
= 23.47 M2
BETON BEKISTING
3.521 23.47
pxlxtxn = 1.83 M3
3,01+3,01+3,01+3,01+3,01+3,01+3,01+3,0
1+3,01+3,01+3,01+3,01+3,01+3,01+
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 93.46 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 195.58 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 50.66 Kg
= 21.350 M2
m
m
m
m
(t1 x p)+(t2 x p) + (l x p) = 21.350 M2
BETON BEKISTING
1.830 21.35
pxlxtxn = 20.87 M3
9,30+9,30+9,30+9,30+9,30+9,30+9,30+9,3
0+9,30+9,30+9,30+9,30+9,30+9,30+9,30+9
,30+9,30+9,30
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 644.69 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 704.19 Kg
= 92.75 M2
m
m
m
= 92.75 M2
BETON BEKISTING
20.869 92.752
pxlxtxn = 3.91 M3
0+4,30+4,30+4,30+4,74+4,51+4,32+4,32+4,51+
4,74+4,30+4,30+4,30+4,30+4,30+4,30+4,30+4,3
0+4,30+4,30+4,30+4,30+4,30+4,30+4,30+4,30+
4,30+4,30+4,30+4,30+4,30+4,30+4,30+4,30+4,3
0+4,30+4,30+4,30+4,30+4,30+4,30+4,30
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 578.45 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 26.08 M2
m
m
m
= 26.08 M2
BETON BEKISTING
3.912 26.08
pxlxtxn = 3.52 M3
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,65+4,65+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,5
5+4,55+4,55+4,55+4,55+4,55+4,55+4,55+4,55+
4,55+4,55+4,55+4,55+4,55+4,55+4,55
+4,65+4,65+4,65+4,65+4,65+4,65+4,65+4,60+4,
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 578.45 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 75.02 Kg
= 23.47 M2
m
m
m
= 23.47 M2
BETON BEKISTING
3.521 23.47
pxlxtxn = 1.83 M3
3,01+3,01+3,01+3,01+3,01+3,01+3,01+3,0
1+3,01+3,01+3,01+3,01+3,01+3,01+
m
m
m
cm
Kg/m
m
m
pot
pot
Berat x Pjg x (Jml Tump+Lap) = 93.46 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 195.58 Kg
cm
m
Kg/m
m
pot
Berat x Pjg x Jml Pot = 50.66 Kg
= 21.350 M2
m
m
m
m
(t1 x p)+(t2 x p) + (l x p) = 21.350 M2
BETON BEKISTING
1.830 21.35
URAIAN PEKERJAAN / DIMENSI
SKETSA SIMBOL HASIL
II.4 PEKERJAAN STRUKTUR TANGGA
Pekerjaan Beton
LT. 4 As E-F (13-14)
1. Anak Tangga Kuantitas = 1/2 x A x O x Jml anak ta
Antride (A) = 0.30
Optride (O) = 0.15
Lebar (L) = 2.00
Jml anak tangga = 20
Jumlah (n) = 2
0.18+0.075
5d
Bentang = 0.00
5d
Jumlah pot = 1
Jml anak tangga = 11
Berat tul anak tgg = Berat x Pjg x Jml pot x Jm
2. Tul. Pokok pada anak tangga Kuantitas = Berat tul anak tgg x n
2ɸ8 Jumlah (n) = 2
Tulangan = 0.8
Berat = 0.39
1,8+(2 x 5D)-(2
Panjang =
1,8 - 2 x 0,025 + 2 x 5d
5d 5d = 1.83
Jumlah pot = 2
Jml anak tangga = 11
Berat tul anak tgg = Berat x Pjg x Jml pot x Jm
3. Tulangan atas pada plat alas Kuantitas = Berat tul atas plat x n
ɸ12-15 Jumlah (n) = 2
4.30
Tulangan = 1.2
5d
0.29
Berat = 0.89
Panjang = 0,29 + 1,39 +
= 6.12
Bentang = 0.00
Jumlah pot = 13
Berat tul atas plat = Berat x Pjg x Jumlah pot
4. Tulangan bawah pada plat alas Kuantitas = Berat tul bawah plat x n
4.30
0.29
5d
ɸ12-15 Jumlah (n) = 2
4.30
Tulangan = 1.2
Berat = 0.89
0.29
5d
5. Tulangan horizontal pada plat alas Kuantitas = Berat tul bawah plat x n
ɸ8 - 15 Jumlah (n) = 4
Tulangan = 0.8
Berat = 0.39
5d
1,8 - 2 x 0,025 + 2 x 5d
5d
Panjang = 1,8+(2x5D)-(2
= 1.83
Bentang = 2.70
Jumlah pot = 19
Berat tul bwh plat = Berat x Pjg x Jumlah pot x
6. Tulangan Bordes
Tulangan ɸ12 - 15 Kuantitas = Berat tul utama bordes x n
Jumlah (n) = 2
Tulangan = 1.2
Berat = 0.89
Panjang = 1,39 +
= 1.82
Bentang = 1.80
Jumlah pot = 13
Berat tul atas plat = Berat x Pjg x Jumlah pot
1.80
0.35
2. Tul. Pokok pada anak tangga Kuantitas = Berat tul anak tgg x n
2ɸ8 Jumlah (n) = 2
Tulangan = 0.8
Berat = 0.39
1,8+(2 x 5D)-(2
Panjang =
1,8 - 2 x 0,025 + 2 x 5d
5d 5d = 1.83
Jumlah pot = 2
Jml anak tangga = 11
Berat tul anak tgg = Berat x Pjg x Jml pot x Jm
3. Tulangan atas pada plat alas Kuantitas = Berat tul atas plat x n
ɸ12-15 Jumlah (n) = 2
4.30
Tulangan = 1.2
0.29
5d Berat = 0.89
Panjang = 0,29 + 1,39 +
= 6.12
Bentang = 0.00
Jumlah pot = 13
Berat tul atas plat = Berat x Pjg x Jumlah pot
4. Tulangan bawah pada plat alas Kuantitas = Berat tul bawah plat x n
ɸ12-15 Jumlah (n) = 2
4.30
Tulangan = 1.2
Berat = 0.89
0.29
5d
5. Tulangan horizontal pada plat alas Kuantitas = Berat tul bawah plat x n
ɸ8 - 15 Jumlah (n) = 4
Tulangan = 0.8
Berat = 0.39
5d
1,8 - 2 x 0,025 + 2 x 5d
5d
Panjang = 1,8+(2x5D)-(2
= 1.83
Bentang = 2.70
Jumlah pot = 19
Berat tul bwh plat = Berat x Pjg x Jumlah pot x
6. Tulangan Bordes
Tulangan ɸ12 - 15 Kuantitas = Berat tul utama bordes x n
Jumlah (n) = 2
Tulangan = 1.2
Berat = 0.89
Panjang = 1,39 +
= 1.82
Bentang = 1.80
Jumlah pot = 13
Berat tul atas plat = Berat x Pjg x Jumlah pot
PxLxTxn = 1.62 M3
m
m
m
unit
PxLxTxn = 0.39 M3
m
m
m
unit
m
pot
buah
Berat x Pjg x Jml pot x Jml anak = 15.88 Kg
m
pot
Berat x Pjg x Jumlah pot = 70.68 Kg
m
pot
Berat x Pjg x Jumlah pot x 2sisi = 27.44 Kg
m
pot
Berat x Pjg x Jumlah pot = 21.05 Kg
m
pot
Berat x Pjg x Jumlah pot x 2sisi = 28.88 Kg
PxLxTxn = 0.00 M3
m
m
m
unit
PxLxTxn = 0.30 M3
m
m
m
unit
m
pot
buah
Berat x Pjg x Jml pot x Jml anak = 15.88 Kg
m
pot
Berat x Pjg x Jumlah pot = 70.68 Kg
m
pot
Berat x Pjg x Jumlah pot x 2sisi = 27.44 Kg
m
pot
Berat x Pjg x Jumlah pot = 21.05 Kg
m
pot
Berat x Pjg x Jumlah pot x 2sisi = 14.83 Kg
TOTAL KUANTITAS BESI PADA TANGGA = 358.82 Kg