I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi
L = (1+23+1)+(1+18+1)
= 25*20
m 12,85
= 500 m2
m 15,85
L = 3 m *3 m
4m = 9 m2
5m
3 Pemasangan Bowplank
Panjang = 1+23+1 m
Lebar = 1+18+1 m
14,85m
K = 90 m
m 17,85
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Kali
arah x = 12+4+6+2+4+4+4+4+4+10= 54m
arah y = 9+9+9+3,5+3+2+2+1,5 = 39 m
0,8 m K = 46,5 + 39 = 85,5 m
V = 0,39 m2 * 85,5 m
= 33,35 m3
V = 85% Vtot
= 0,85 * 37,8 m3
= 32,13 m3
V = 53,9 m * 0,12 m2
= 11,12 m3
A = 0,1 m * 0,8 m
= 0,08 m2
V = 85,5 m * 0,08 m2
= 6,84 m3
9 Urugan Pasir Bawah Pondasi Telapak
Jumlah pondasi telapak = 18 buah
V 1 pondasi = 1m * 1m* 0,1m
= 0,1 m3
Vtotal = 18 * 0,1 m3
= 1,8 m3
A = 0,1 m * 0,6 m
= 0,06 m2
V = 53,9 m * 0,06 m2
= 3,23 m3
A = 0,8 m * 0,2 m
= 0,16 m2
V = 139,4 m * 0,16 m2
= 22,304 m3
A = ((0,25+0,6)/2 ) * 0,75
= 0,319 m2
V = 85,5 m * 0,319 m2
= 27,27 m3
5 Plesteran Tasram
L = 2 * luas tasram
= 2 * 61,52 m2
= 123,04 m2
IV PEKERJAAN BETON
V 1 pondasi = 0,05 m * 1 m * 1 m
= 0,05 m3
V total = 18 * 0,05 m3
= 0,9 m3
2 Beton Pondasi Telapak jumlah telapak = 18 buah
V1 =( (0,25*0,25)+(1*1)x 0,2 ) / 2
= 0,106 m3
V2 = 1m * 1m * 0,25 m = 0,25 m3
V telapak = 0,106 m3 + 0,25 m3 = 0,356 m3
V kolom pondasi = 0,25 m*0,25 m*1,95 m
= 0,122 m3
V total = 18 * (0,356 + 0,122) = 8,6 m3
9 Beton Listplank
didapat keliling listplank = 33 m
tinggi listplank = 0,3 m
Listplank 2/30 tebal listplank = 0,02 m
A = 33 m * 0 3 m
= 9,9 m2
V = 9,9 m2 * 0,02 m
= 0,198 m3
Lantai 2
jumlah kolom = 18 buah
tinggi kolom = 5,25 m
Tul. Pokok 8f16
konversi = 61,65*0,162*5,25*8 = 66,29 kg
V 18 kolom = 18 * 66,29 kg = 1194,5 kg
8 f 16 Tul. Sengkang f8-150
panjang = 5,25 m * 18 = 94,5 m
jumlah sengkang = 94,5 m / 0,15 m = 630 bh
panjang bukaan begel = 0,82 m
f 8 -150 panjang total = 630* 0,82 m = 516,6 m
konversi = 61,65*0,082*516,6 = 201,47 kg
Balok 2
panjang balok = 15,7 m
Tul. Pokok 5f12
f8-150 5f12 konversi = 61,65*0,122*5 = 4,44 kg
V total = 15,7 m * 4,44 kg = 69,69 kg
Tul. Sengkang f8-150
Tumpuan Lapangan panjang = 15,7 m
jumlah sengkang = 15,7 m / 0,15 m = 105 bh
panjang bukaan begel = 0,62 m
panjang total = 105* 0,62 m = 65,1 m
konversi = 61,65*0,082*65,1 = 25,68 kg
5 Pelat Lantai 2
n = 10 m / 0,2 m = 50 bh
panjang = 3,5 m * 50 bh = 175 m
n = 3,5 m / 0,2 m = 18 bh
panjang = 10 m * 18 bh = 180 m
konversi = 61,65*0,12*355 m = 218,86 kg
n = 6,5 m / 0,2 m = 33 bh
panjang = 2,5 m * 33 bh = 82,5 m
n = 2,5 m / 0,2 m = 13 bh
panjang = 6,5 m * 13 bh = 84,5 m
konversi = 61,65*0,12*167 m = 102,96 kg
n = 10 m / 0,2 m = 50 bh
panjang = 3 m * 50 bh = 150 m
n = 3 m / 0,2 m = 15 bh
panjang = 10 m * 15 bh = 150 m
konversi = 61,65*0,12*300 m = 184,95 kg
n = 3 m / 0,2 m = 15 bh
panjang = 2,5 m * 15 bh = 37,5 m
n = 2,5 m / 0,2 m = 13 bh
panjang = 3 m * 13 bh = 39 m
konversi = 61,65*0,12* 76,5 m = 47,16 kg
Tulangan f8-150
panjang = 1 m * 2 bh * 18 bh = 36 m
konversi = 61,65*0,082*36 m = 14,20 kg
Tulangan f12-200
panjang = 3,3 m
n = 1m / 0,2 m = 5 bh
konversi = 61,65*0,122*3,3 m = 2,93 kg
V total = 2 * 5 bh * 2,93 kg = 29,4 kg
Tulangan f8-150
n = 3,3 m / 0,15 m = 22 bh
panjang = 1 m * 22 bh = 22 m
konversi = 61,65*0,082*22 m = 8,68 kg
V total = 2 * 8,68 kg = 17,36 kg
V = 0,08m*0,12m*15,14m
= 0,145 m3
V = 4 bh * 13,2 m
= 52,8 m
type P1
Panjang = 2(2m) + 0,8 m
= 4,8 m
V = 3 bh * 4,8 m
= 14,4 m
type P2
Panjang kusen = 2(2m) + 0,7 m
= 4,7 m
V = 2 bh * 4,7 m
= 9,4 m
V = 3 bh * 5,6 m
= 16,8 m
type J2
V = 4 bh * 3,6 m
=14,4 m
type J3
V = 3 bh * 3,4 m
= 10,2 m
type J4
V = 2 bh * 5,4 m
= 10,8 m
V = 6 bh * 2 m
= 12 m
type BV2
V = 2 bh * 4,4 m
= 8,8 m
type BV3
V = 1 bh * 6,96 m
= 6,96 m
2 Daun Jendela
3 Daun Bouvenlist
2 Penutup Plafond
Luas = Luas rangka plafond
= 192 m2
10 Tandon Air
L = 12,25+6+7+16,5+10,5+16,5+10,5+5
Lanatai 2 = 84,25 m2
L = 2 m * 1,5 m
= 3 m2
V = 2 KM * 3 m2
2m = 6 m2
1,5 m
V = (2 KM * 14,4m2) - 0,7 m
= 28,1 m2
V = 6,25 m2
5 Wastafel
3 Lampu SL 9 titik
500 m2
9 m2
90 m1
Quantity Satuan
71.82 m3
17.79 m3
37.8 m3
33.35 m3
32.13 m3
11.12 m3
47.25 m3
6.84 m3
1.8 m3
3.23 m3
103.23 m3
Quantity Satuan
22.304 m3
27.27 m3
61.52 m2
558.01 m2
558.01 m2
123.04 m2
1116.02 m2
278.8 m1
Total Satuan
0.9 m3
8.6 m3
3.85 m3
10.03 m3
0.62 m3
7.85 m3
9.81 m3
0.88 m3
0.198 m3
Total Satuan
910.29 kg
2354.74 kg
3
63.92
171.84 kg
1812.62 kg
553.93 kg
71.51 kg
Total Satuan
0.145 m3
0.63 m3
47.5
0.285 m3
157.3 m2
Total Satuan
76.6 m1
52.2 m1
27.76 m1
Total Satuan
18 bh
24 bh
18 bh
Total Satuan
192 m2
192 m2
45 m1
Total Satuan
18 bh
7 bh
9 bh
24 bh
12 bh
Total Satuan
1 bh
1 bh
2 bh
7 titik
2 bh
2 bh
25.35 m
34.55 m
27 m
1 unit
Total Satuan
154.25 m2
6 m2
28.1 m2
6.25 m2
1 unit
Total Satuan
11 titik
10 titik
9 titik
11 titik
11 titik
10 titik
5 titik
Total Satuan
619.53 m2
1239.06 m2
146.68 m
9 bh
12 bh
LAMPIRAN II KEPUTUSAN BUPATI MALANG
NOMOR : 108/524/KEP/421.013/2011
TANGGAL : 23 AGUSTUS 2011
BAHAN BANGUNAN
PERKIRAAN HARGA
TERTINGI
No JENIS BAHAN SATUAN
TAHUN 2012
(Rp.)
1 2 3 4
I BAHAN PENUTUP ATAP DAN PLAFON
1 Asbes datar tebal 4 mm (60x180) lbr 52.700,00
2 Asbes datar tebal 4 mm (120x240) lbr 61.000,00
3 Asbes datar tebal 5 mm (60x180) lbr 49.500,00
4 Asbes datar tebal 6 mm (40x180) lbr 46.300,00
5 Asbes gelombang besar tebal 5 mm (2.50x0.92m) lbr 90.200,00
6 Asbes gelombang besar tebal 5 mm (3.05x1.05m) lbr 91.350,00
7 Asbes gelombang kecil tebal 5 mm (2.25x0.92m) lbr 72.100,00
8 Asbes gelombang kecil tebal 5 mm (2.00x0.92m) lbr 65.650,00
9 Asbes gelombang kecil tebal 5 mm (1.80x0.92m) lbr 65.650,00
10 Asbes gelombang kecil 4 mm (3.05x1.05m) lbr 83.300,00
11 Asbes gelombang kecil 4 mm (2.70x1.05m) lbr 17.800,00
12 Asbes gelombang kecil 4 mm (2.40x1.05) lbr 62.450,00
13 Asbes gelombang kecil 4 mm (2.10x1.05m) lbr 62.450,00
14 Asbes gelombang kecil 4 mm 1.50x1.05m) lbr 39.750,00
15 Asbes wuwung gelombang besar tb. 5mm lbr 56.175,00
16 Asbes wuwung gelombang kecil tb. 4mm lbr 41.200,00
17 Plat asbes tebal 3.5 mm lbr 52.650,00
18 Plat asbes tebal 4 mm lbr 59.150,00
19 Plat asbes tebal 5 mm lbr 55.850,00
20 Plat asbes tebal 6 mm lbr 78.550,00
21 Genteng karang pilang/ wisma bj 6.900,00
22 Genteng wuwung karang pilang/ wisma bj 6.900,00
23 Genteng wuwung galvalum bj 5.500,00
24 Genteng model karang pilang nglayur bj 1.785,00
25 Genteng kodok ex. Bambe bj 5.200,00
26 Genteng kodok ex. Wisma bj 5.200,00
27 Genteng Palentong bj 4.100,00
28 Genteng Palentong Super bh 8.775,00
29 Genteng Nok Palentong bj 7.100,00
30 Genteng Nok Kodok Glazzur bh 10.185,00
31 Genteng bubung kodok bj 5.200,00
32 Genteng beton bj 2.900,00
33 Genteng sirap lbr 121.200,00
34 Nok genteng pinggir bj 4.000,00
35 Nok stel gelombang bj 31.500,00
36 Genteng kodok bj 525.000,00
37 Seng gelombang BKLS 30 ukuran 1.8x0.9 lbr 81.200,00
38 Seng gelombang BJLS 30 ( 0.8x3.00) lbr 130.000,00
39 Seng gelombang BJLS 30 ( 0.8x1.50) lbr 79.600,00
40 Seng plat dasar BJLS 30 (0.45x1.00) lbr 24.400,00
41 Seng plat dasar BJLS 30 (0.60x1.00) lbr 32.445,00
42 Seng plat dasar BJLS 30 (0.90x1.00) lbr 48.750,00
43 Seng plat 3'x6' Bjls 28 lbr 44.950,00
44 Gypsum Board 120x24x9mm lbr 232.900,00
45 Kalsi Board 120x240x4mm lbr 52.550,00
46 Teakwood tebal 4 mm(1.22x2.44) lbr 102.700,00
47 Teakwood tebal 4 mm(1.10x2.10) lbr 67.650,00
48 Plywood tebal 4 mm(1.22x2.44) lbr 85.000,00
49 Plywood tebal 9 mm(1.22x2.44) lbr 152.900,00
50 Plywood tebal 6 mm(0.40x0.80) lbr 89.250,00
51 Triplek tebal 4 mm (1.20x2.40) lbr 69.650,00
52 Triplek tebal 4 mm (0.90x2.00) lbr 49.665,00
53 Triplek tebal 4 mm (1.22x2.44)) lbr 65.600,00
54 Triplek tebal 4 mm (1.10x2.10) lbr 38.500,00
55 Multipleks 12 mm lbr 199.700,00
56 Sirab asbes 4 mm m² 31.500,00
57 Sirab asbes 5 mm m² 34.350,00
58 Tepung gypsum kg 45.900,00
59 Geotextil m² 30.300,00
0.1
RESIKO DAN 0.004
Laba 10 % (Rp) OVERHEAD 0,4% TOTAL (Rp) Pembulatan (Rp)
(Rp)
PERKIRAAN HARGA
No JENIS BAHAN SATUAN TERTINGGI TAHUN 2012
(Rp.)
1 2 3 4
SEWA ALAT
1 Pesawat ukur (Sewa per hari) Bh
2 Meteran (50m) Bh
3 Palu / Bodem Bh
4 Ganco Bh
5 Keranjang Bh
6 Alat pelancip / Pisau besar Bh
7 Kereta dorong Unit
8 Jack Hammer Bh
9 Timbris Unit
10 Ember Bh
11 Cetok Bh
12 Kuas Bh
13 Kasut kayu Bh
14 Kotak adukan Bh
15 Tang pemotong kawat Bh
16 Molen (sewa per hari) Unit
17 Vibrator (sewa per hari) Unit
18 Gergaji Bh
19 Gunting pemotong baja Bh
20 Kunci pembengkok tulangan Bh
21 Tusuk bambu Bh
22 Gerobak Bh
23 Pompa air Unit/hari
24 Vibro roller/stamper Unit/hari
25 Sabit Bh
26 Tampar pemikul kayu Bh
27 Kompresor, blasting, selang dan Nozzle Unit/hari
28 Asphalt Mixing Plant Unit/hari
29 Asphalt Finisher Unit/hari
30 Asphalt Sprayer Unit/hari
31 Buldozer 100-150 HP Unit/hari
32 Compressor 4000-6500 L/M Unit/hari
33 Concrete Mixer 0.3-0.6 M3 Unit/hari
34 Crane 10-15 TON Unit/hari
35 Dump Truck 3.5 TON Unit/hari
36 Dump Truck 10 TON Unit/hari
37 Excavator 80-140 HP Unit/hari
38 Flat Bed Truck 3-4 M3 Unit/hari
39 Generator set Unit/hari
40 Motor Grader >100 HP Unit/hari
41 Track Loader 75-100 HP Unit/hari
42 Wheel Loader 1.0-1.6 M3 Unit/hari
43 Three Whell Roller 6-8 T. Unit/hari
44 Tandem Roller 6-8 T. Unit/hari
45 Tire Roller 8-10 T. Unit/hari
46 Vibratory Roller 5-8 T. Unit/hari
47 Concrete Vibrator Unit/hari
48 Stone Crusher Unit/hari
49 Water Pump 70-100 mm Unit/hari
50 Water Tanker 3000-4500 L. Unit/hari
51 Pedestrian Roller Unit/hari
52 Tamper Unit/hari
53 Jack Hammer Unit/hari
54 Fulvi Mixer Unit/hari
55 Concrete Pump Unit/hari
56 Trailer 20 TON Unit/hari
57 Pile Driver + Hammer Unit/hari
58 Crane On Track 35 TON Unit/hari
59 Welding Set Unit/hari
60 Bore Pile Mechine Unit/hari
61 Asphalt Liquid Mixer Unit/hari
62 Tronton Unit/hari
63 Cold Milling Unit/hari
64 Rock Drill Breaker Unit/hari
65 Cold Recyler Unit/hari
66 Hot Recyler Unit/hari
67 Agregat ( CHIP ) Spreader Unit/hari
68 Asphalt Distributor Unit/hari
69 Slip Form Paver Unit/hari
70 Concrete Pan Mixer Unit/hari
71 Concrete Breaker Unit/hari
72 Asphalt Tanker Unit/hari
73 Cement Tanker Unit/hari
74 Concrete Mixer (350) Unit/hari
75 Vibrating Rammer Unit/hari
76 Truck Mixer (AGITATOR) Unit/hari
77 Bore Pile Mechine Unit/hari
78 Crane On Track 75-100 TON Unit/hari
79 Blending Equipment Unit/hari
80 ASPHALT LIQUID MIXER Unit/hari
UPAH TENAGA KERJA
PERKIRAAN HARGA
No JENIS PEKERJAAN SATUAN TERTINGGI TAHUN 2012
(Rp.)
1 2 3 4
UPAH TENAGA KERJA (HARI)
1 Mandor Orang / hari
2 Kepala Tukang Orang / hari
3 Kepala Tukang Batu Orang / hari
4 Kepala Tukang Besi Orang / hari
5 Kepala Tukang Cat Orang / hari
6 Kepala Tukang Pipa Orang / hari
7 Kepala Tukang Kayu Orang / hari
8 Kepala Tukang Listrik Orang / hari
9 Tukang Batu Orang / hari
10 Tukang Besi Orang / hari
11 Tukang Cat Orang / hari
12 Tukang Kayu Orang / hari
13 Tukang Plitur Orang / hari
14 Tukang Pipa Orang / hari
15 Tukang Listrik Orang / hari
16 Tukang Gali Tanah Orang / hari
17 Pembantu Tukang Batu / Pekerja Orang / hari
18 Pembantu Tukang Kayu / Pekerja Orang / hari
19 Pembantu Tukang Besi / Pekerja Orang / hari
20 Pembantu Tukang Cat / Pekerja Orang / hari
21 Penjaga Orang / hari
22 Sopir Orang / hari
23 Mekanik Terampil Orang / hari
24 Mekanik Semi Terampil Orang / hari
25 Operator terampil Orang / hari
26 Operator semi terampil Orang / hari
27 Pembantu operator Orang / hari
28 Pembantu sopir Orang / hari
29 Pekerja semi terampil Orang / hari
30 Pekerja terampil Orang / hari
31 Pekerja Orang / hari
32 Juru Ukur Orang / hari
33 Ongkos kerja Kontruksi Pintu Air Kg
34 Ongkos Kerja Mesin Kg
35 Ongkos Kerja Kayu Kg
36 Sandblasting dan Cat M2
37 Pengecatan tanpa Sandblasting M2
38 Ongkos Angkut pintu air M2
39 Ongkos Batu Candi M3 Bh
40 Ongkos Angkut beton Precast M2
RESIKO DAN
Laba 10 % TOTAL (Rp) Pembulatan (Rp) 0.1
OVERHEAD 0,4%
0.004
5 6 7 8
Harga Satuan
KODE URAIAN
(Rp)
A PEKERJAAN PERSIAPAN
KODE URAIAN
B PEKERJAAN TANAH
KODE URAIAN
C PEKERJAAN PONDASI
KODE URAIAN
D PEKERJAAN DINDING
1. 1m2 PASANGAN BATU MERAH 1/2 BATA 1 PC : 3 PS
Bahan
70.000 bh Batu merah 5 x 11 x 22 cm
14.370 kg Semen / PC (kg)
0.040 m³ Pasir pasang
Upah
0.015 Oh Mandor
0.010 Oh Kepala tukang batu
0.100 Oh Tukang batu
0.320 Oh Pekerja
Sub Jumlah
KODE URAIAN
E PEKERJAAN PLESTERAN
1. 1m2 PLESTERAN 1 PC : 3 PS , t = 15 mm
Bahan
6.480 kg Semen / PC (kg)
0.019 m³ Pasir pasang
Upah
0.010 Oh Mandor
0.015 Oh Kepala tukang batu
0.150 Oh Tukang batu
0.200 Oh Pekerja
Sub Jumlah
2. 1m 2
PLESTERAN 1 PC : 6 PS, t = 15 mm
Bahan
3.680 kg Semen / PC (kg)
0.023 m³ Pasir pasang
Upah
0.010 Oh Mandor
0.015 Oh Kepala tukang batu
0.150 Oh Tukang batu
0.200 Oh Pekerja
Sub Jumlah
KODE URAIAN
F PEKERJAAN KAYU
KODE URAIAN
G PEKERJAAN BETON
3. kg PEMBESIAN ( POLOS )
Bahan
1.050 kg Besi beton
0.015 kg Kawat beton
Upah
0.000 Oh Mandor
0.001 Oh Kepala tukang besi
0.007 Oh Tukang besi
0.007 Oh Pekerja
Sub Jumlah
KODE URAIAN
H PEKERJAAN ATAP
KODE URAIAN
KODE URAIAN
I PEKERJAAN LANGIT-LANGIT
KODE URAIAN
J PEKERJAAN KERAMIK
KODE URAIAN
KODE URAIAN
KODE URAIAN
M PEKERJAAN SANITASI
2. 1 bh PASANG WASTAFEL Kw A
Bahan
1.000 bh Wastafel Kw A
6.000 kg Semen / PC (kg)
0.010 m³ Pasir pasang
Upah
0.100 Oh Mandor
0.150 Oh Kepala tukang batu
1.450 Oh Tukang batu
1.200 Oh Pekerja
Sub Jumlah
KODE URAIAN
N PEKERJAAN PENGECATAN
1. 1 m2 MENGECAT BIDANG KAYU BARU : 1 lps PLAMIR, 1 lps CAT DASAR, 2 lps CAT PENUTUP
Bahan
0.200 kg Plamir
0.150 kg Cat meni
0.170 kg Cat dasar
0.260 kg Cat penutup 2 kali
Upah
0.003 Oh Mandor
0.006 Oh Kepala tukang cat
0.009 Oh Tukang cat
0.070 Oh Pekerja
Sub Jumlah
3. 1 m2 MENGECAT TEMBOK BARU : 1 lps PLAMIR,1 lps CAT DASAR, 2 lps CAT PENUTUP
Bahan
0.200 kg Plamir
0.230 kg Cat dasar
0.480 kg Cat penutup 2 kali
Upah
0.003 Oh Mandor
0.006 Oh Kepala tukang cat
0.063 Oh Tukang cat
0.020 Oh Pekerja
Sub Jumlah
KODE URAIAN
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 500.000 m2 0.00
2 Pembuatan Direksi Keet 9.000 m2 0.00
3 Pengukuran dan Pemasangan Bowplank 90.000 m 1
0.00
B PEKERJAAN TANAH
1 Galian Tanah sedalam 1 m 89.610 m3 0.00
2 Galian Tanah sedalam 2 m 37.800 m3 0.00
3 Urugan Tanah Kembali 76.600 m 3
0.00
4 Urugan Tanah 47.250 m3 0.00
5 Urugan Pasir 11.870 m 3
0.00
C PEKERJAAN PONDASI
1 Pasangan Batu Kosong 22.304 m3 0.00
2 Pasangan Batu Kali 1 PC : 5 PS 27.270 m3 0.00
D PEKERJAAN DINDING
1 Pasangan Dinding 1 PC : 3 PS 558.010 m2 0.00
2 Pasangan Tasram 1 PC : 6 PS 61.520 m 2
0.00
E PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 PC : 3 PS 1116.020 m2 0.00
2 Plesteran Tasram 1 PC : 6 PS 123.040 m2 0.00
3 Benangan Sudut 278.800 m 1
0.00
F PEKERJAAN KAYU
1 Kusen Pintu & Jendela Kayu Jati m3
2 Pintu & Jendela Kaca Kayu Jati m2
3 Kuda2 Kayu Jati 0.145 m3 0.00
4 Usuk dan Reng 157.300 m2 0.00
5 Listplank 2/30 47.500 m 1
0.00
6 Rangka Hollow 192.000 m2 0.00
G PEKERJAAN BETON
1 Beton Lantai Kerja 0.900 m3 0.00
2 Beton 1 PC : 2 PS : 3 KR 41.838 m 3
0.00
3 Pembesian polos 5874.930 kg 0.00
4 Begesting Pondasi m2
5 Begesting Sloof m2
6 Begesting kolom m2
7 Begesting Balok m2
8 Begesting Dinding m2
9 Begesting lantai m2
10 Begesting Tangga m2
H PEKERJAAN ATAP
1 Pasang Atap Genteng Kodok
2 Pasang Bubung Kodok
I PEKERJAAN LANGIT2
1 Pas. Langit Gypsumboard 192.000 m2 0.00
2 List Langit2 45.000 m1 0.00
J PEKERJAAN KERAMIK
1 Lantai Keramik 30x30 154.250 m2 0.00
2 Lantai Keramik 20x20 6.000 m2 0.00
3 Dinding Keramik 20x25 34.350 m2 0.00
M PEKERJAAN SANITASI
1 Kloset Jongkok 2.000 bh 0.00
2 Wastafel 1.000 bh 0.00
3 Tempat Sabun 2.000 bh 0.00
4 Bak Mandi Batu Bata 2.000 bh 0.00
5 Pipa Galvanish f1/2" 25.350 m1 0.00
6 Pipa PVC f2" 34.550 m1 0.00
7 Pipa PVC f4" 27.000 m1
0.00
8 Kran Air f1/2" 7.000 bh 0.00
9 Kaca Wastafel 1.000 bh 0.00
N PEKERJAAN PENGECATAN
1 Cat Dinding Dalam 619.530 m2 0.00
2 Cat Dinding Luar 1239.060 m 2
0.00
3 Cat Kusen
4 Cat Pintu & Jendela
5 Cat Genteng Dulux
TOTAL KESELURUHAN
PEKERJAAN
JUMLAH TOTAL
Rp Rp
0.00
0.00 0.00
0.00
0.00
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
0.00
L KESELURUHAN
EKERJAAN 0.00
PROSENTASE
NO ITEM PEKERJAAN BIAYA (Rp)
(%)
A PEKERJAAN PERSIAPAN
B PEKERJAAN TANAH
C PEKERJAAN PONDASI
D PEKERJAAN DINDING
E PEKERJAAN PLESTERAN
F PEKERJAAN KAYU
G PEKERJAAN BETON
H PEKERJAAN ATAP
I PEKERJAAN LANGIT-LANGIT
J PEKERJAAN KERAMIK
K PEKERJAAN KUNCI & KACA
L PEKERJAAN BESI & ALUMINIUM
M PEKERJAAN SANITASI
N PEKERJAAN PENGECATAN
O PEKERJAAN INSTANSI LISTRIK
TOTAL BIAYA
LUAS TANAH (M2)
BIAYA PER M2