URAIAN PEKERJAAN

No URAIAN PEKERJAAN VOLUME

I PEKERJAAN PONDASI
I.1 Permulaan
I.1.a Pembersihan lapangan 96 m2

16 m

6m

Panjang = 16 m
lebar =6m
luas = panjang x lebar
= 16 x 6
Volume = 96 m2

I.1.b Pemasangan Bowplank 56 m2

1,5m

16 m

1,5m

Panjang = 19 m
Lebar = 9 m
Keliling = 2 x (panjang + lebar)
= 2 x (19 + 9)
Volume = 56 m2
Panjang tiang =1m
Jarak tiang ke tiang = 2 m
Banyak tiang = 56/2 = 28 Bh.
Ukuran papan = (0,03 x 0,25 x 4) m
Ukuran tiang = (0,05 x 0,07 x 1) m
Volume papan = 56 x 0,03 x 0,25 = 0,42 m3
Volume papan = 28 x 0,05 x 0,07 x 1 = 0,098 m3
Jumlah = 0,518 m3
Kayu terbuang 10% = 0,518 m3
Volume = 0,4662 m3

I.1.c Direksi Keet 12 m2

6x3

4x3

Panjang = 4 m
Lebar = 3 m
Luas = 4 x 3 = 12 m2
Volume = 12 m2

A = Direksi keet
B = Los kerja

I.1.d Los Kerja 18 m2


Panjang = 6 m
Lebar = 3 m
Luas = 6 x 3 = 18 m2
Volume = 18 m2

1.2 Penggalian
1.2.a Galian Tanah Pondasi 60,687 m3
1.2.a.1 Galian Tanah Pondasi Utama 1
Sumbu Tegak
No Sumbu Panjang
1 B–J 3m
2 C–M 11,75 m
Jumlah 14,75 m
Sumbu Datar
No Sumbu Panjang
1 F–A 3m
2 G–A 3m
3 H–C 2m
4 I–A 3m
5 J–A 1,5 m
6 K–A 3m
7 L–C 3m
Jumlah 18,5 m
Panjang sumbu = 14,75 + 18,5 = 33,25 m

1,38 m

0,95 m

1m

Perbandingan 5 : 1
0,95
x = 5 = 0,19 m
Lebar galian = 1 + ( 2 x 0,19) = 1,38 m
1+1,38
Luas penapang = 2 x 0,95 = 1,1305 m2
Volume galian = 33,25 x 1,1305 = 37,589 m3

1.2.a.2 Galian Tanah Pondasi Utama 2


Sumbu Tegak
No Sumbu Panjang
1 A–N 16 m
2 D–N 16 m
Jumlah 32 m
Sumbu Datar
No Sumbu Panjang
1 E–A 6m
Jumlah 6m
Panjang sumbu 32 + 6 = 38 m

0,69m

0,95 m

0,5m
Lebar galian 0,5 + 0,19 = 0,69 m
0,5+0,69
Luas penampang = x 0,95 = 0,56525 m2
2
Volume galian = 38 x 21,4795 m3

1.2.a.3 Galian Tanah Pondasi Teras


Sumbu Datar
No Sumbu Panjang
1 M–C 3m
Jumlah 3m
Panjang sumbu = 3 m

0,96 m

0,65m

0,7 m

0,65
x = 5 = 0,13 m
Lebar galian + 0,7 + (2 x 0,13) = 0,96 m
0,7+0,96
Luas penampang = x 0,65 = 0,5395 m2
2
Volume galian = 3 x 0,5395 = 1,6185 m3

Total volume galian = 37,589 + 21,4795 + 1,6185 = 60,687 m3


I.2.b Urugan Kembali ¼ Galian 15,17 m3

Urugan kembali

Volume galian = 60,687 m3


Urugan kembali ¼ x galian
Volume urugan = ¼ x 60,687 = 15,17175 m3

I.3 Pasangan Pondasi Batu Kali 1,3865 m3


I.3.a Urugan Pasir Bawah Pondasi
I.3.a.1 Urugan Pasir Bawah Pondasi Utama 1

1,02 m

1m

Perbandingan miring 5 : 1 dan tinggi = 5 cm


0,05
x = 5 = 0,01 x 2 = 0,02 m
Lebar atas = 1 + 0,02 = 1,02 m
1+1,02
Penampang = 2 x 0,05 = 0,0255 m2
Volume = panjang x penampang
= 33,25 x 0,0255 = 0,848 m3

I.3.a.2 Urugan Pasir Bawah Pondasi Utama 2


0,51 m

0,5 m

Lebar atas = 0,5 + 0,01 = 0,51 m


0,5+0,01
Penampang = x 0,05 = 0,01275 m2
2
Volume = panjang x penampang
= 38 x 0,01275 = 0,4845 m3

I.3.a.3 Urugan Pasir Bawah Pondasi Utama 3


0,72 m

0,7 m
Luas atas = 0,7 + 0,02 = 0,72 m
0,7+0,02
Penampang = 2 x 0,05 = 0,018 m2
Volume = panjang x penampang
= 3 x 0,018 + 0,054 m3

Total urugan pasir = 0,848 + 0,4845 + 0,054 = 1,3865 m3

1.3.b Anstampang Batu Kali 4,88 m3


1.3.b.1 Anstampang Batu Kali 1

0,1 m

0,9 m
Penampang : 0,1 x 0,9 = 0,09 m2
Volume = 33,25 x 0,09 = 2,99 m3

1.3.b.2 Anstampang Batu Kali 2

0,1 m

0,45m
Penampang = 0,1 x 0,45 = 0,045 m2
Volume = 3 x 0,06 = 0,18 m3

1.3.b.3 Anstampang Batu Kali 3

0,1m

0,6m
Penampang = 0,1 x 0,6 = 0,06 m2
Volume = 3 x 0,06 = 0,18 m3
Total anstampang batu kali = 2,99 + 1,71 + 0,18 = 4,88 m3

1.3.c Pasangan Pondasi Batu kali 23,59 m3


1.3.c.1 Pasangan Pondasi Batu Kali 1
0,3 m

0,8 m

0,8 m

(0,8+0,3)
Penampang = x 0,8 = 0,44 m2
2
Volume = panjang x penampang
= 33,25 x 0,44 = 14,63 m3
1.3.c.2 Pasangan Pondasi Batu Kali 2

0,15 m

0,8 m

0,4 m

(0,4+0,15)
Penampang = x 0,8 = 0,22 m2
2
Volume = panjang x penampang
= 38 x 0,22 = 8,36 m3

1.3.c.3 Pasangan Pondasi Batu Kali 3

0,3m

0,5 m

0,5 m
(0,5+0,3)
Penampang = x 0,5 = 0,2 m2
2
Volume = panjang x penampang
= 3 x 0,2 = 0,6 m3

Total pondasi batu kali = 14,63 + 8,36 + 0,6 = 23,59 m3

II PEKERJAAN BETON & DINDING


II.1 Beton Bertulang
II.1.a Beton Sloof 2,2275 m3
Sumbu Tegak
Sumbu Panjang
B–J 3 m

C–M 11,75 m
A– N 16 m
D–N 16 m
Jumlah 46,75 m

Sumbu Datar
Sumbu Panjang
F – A 3m
G–A 3m
H–C 2m
I–A 3m
J – A 1,5 m
K–A 3m
L–C 3m
E–A 6m
M–C 3m
Jumlah 27,5 m

Panjang sloof = 46,75 m + 27,5 m


= 74,25 m

Penampang sloof = 0,15 m x 0,20 m


= 0,03 m2

Volume sloof = 74,25 m x 0,03 m2


= 2,2275 m3
II.1.b Tiang Praktis 2,2275 m3

II.1.b.1 Tiang Praktis Bangunan


Panjang = 4,00 m
Penampang = 0,15 x 0,15
= 0,0225 m3
Volume = 4,00 x 0,0225
= 0,09 m3
Jumlah Tiang = 21 Buah
Volume 21 Tiang = 21 x 0,9
Volume = 1,89 m3
II.1.b.2 Tiang Praktis Teras
Panjang = 3,90 m
Penampang = 0,15 x 0,30
= 0,045 m2
Volume = 3,90 x 0,045
= 0,1755 m3
Jumlah Tiang = 2 Buah
Volume 2 Tiang = 2 x 0,1755
Volume = 0,351 m3

II.1.b.3 Tiang Praktis Pagar

Panjang = 1,50 m
Penampang = 0,15 x 0,15
= 0,0225 m2
Volume = 1,50 x 0,0225
= 0,03375 m3
Jumlah Tiang = 2 Buah
Volume 2 Tiang = 2 x 0,03375
Volume = 0,0675 m3

Volume Total = 1,89 + 0,351 + 0,0675


= 2,3085 m3
II.1.c Ring Balok 1,8825 m3
Panjang Reng Balok = Panjang Galian Pondasi
= 62,75 m
Penampang Reng Balok = 0,15 x 0,20
= 0,03 m2
Volume = 62,75 x 0,03
= 1,8825 m3

II.1.d Plat Beton 0,146256


m3

Perhatikan gambar diatas


Penjelasan 1
F1 = 1,46 x 0,6 = 0,876 m2
t = 8 cm = 0,08 m
volume= F1 x t = 0,876 m2 x 0,08 m = 0,07008 m3
Penjelasan 2
F2 = (2,0 x 0,63) – (0,96 x 0,50)
= 1,26 – 0,48 = 0,78 m2
t = 8 cm = 0,08 m
volume= F1 x t = 0,78 m2 x 0,08 m = 0,0624 m3

Penjelasan 3
F3 = 1,37 x 0,6 = 0,222 m2
t = 8 cm = 0,08 m
volume= F1 x t = 0,222 m2 x 0,08 m = 0,011776 m3

Penjelasan 4
Perhatikan gambar I.2
Penampang bak = 2 (0,55 x 0,50) x 0,08
= 2 x 1,05 x 0,08
= 0,168 m2
Tinggi = 0,20 m
volume= F1 x t = 0,168 m2 x 0,20 m = 0,0336 m3

F alas bak = 0,50 x 0,50 = 0,25 m2


t alas bak = 8 cm = 0,08 m
Volume = F x t = 0,25 x 0,08 = 0,002 m3

Volume plat beton


Penjelasan 1 = 0,07008 m3
Penjelasan 2 = 0,0624 m3
Penjelasan 3 = 0,011776 m3
Penjelasan 4 = 0,002 m3
Volume (I) = 0,146256 m3

Penjelasan I Plat Beton


Untuk menghitung volume plat beton, tebal plat 8 cm = 0,08

II.1.e Pemasangan Batu Alam 7,02 m2


Volume = Tinggi x Lebar
Volume depan tiang = 3,9 x 0,3 = 1,17 m2
Volume belakang tiang = 3,9 x 0,3 = 1,17 m2
Volume samping kanan tiang = 3,9 x 0,15 = 0,585 m2
Volume samping kiri tiang = 3,9 x 0,15 = 0,585 m2

Volume tiang = 2 buah


Volume 2 buah tiang = 2 x 3,51
Volume = 7,02 m2
II.2 Dinding
Uraian Dinding Sumbu Tegak
1.1 Dinding A – N

A. Luas Dinding A-O


Panjang = 10,5 m
Tinggi = 3,85 m
Luas = 10,5 x 3,85 = 40,425 m2

Panjang = 5,50 m
Tinggi = 1,425 m
Luas = 5,5 x 1,425 = 7,8375 m2

Panjang = 9,4 m
Tinggi = 3,536 m
9,4 𝑥 3,536
Luas = = 16,6192 m2
2

Jumlah Luas Dinding A – O = 40,425+7,8375+16,6192


= 64,8817 m2
B. Luas Bidang Tiang Beton
Tinggi = 3,85 m
Lebar = 5 x 0,15 = 0,75 m
Luas = 3,85 x 0,75 = 2,8875 m2

Tinggi = 1,425 m
Lebar = 1x 0,15 = 0,15 m
Luas = 1,425 x 0,15 = 0,21375 m2
Jumlah Luas Dinding Tiang Beton = 2,8875 + 0,21375
= 3,10125 m2
C. Luas Tembok 1:2
Luas = (1,35 x 1,5) + (1,35 x 1,5) + (1,1+2,85+3,1+5,35) 0,3
= 2,025 + 2,025 + 3,72)
` = 7,77 m2
D. Luas Tembok 1:4
Luas D = A – (B+C)
= 64,8817 – (3,10125+7,77)
= 54,01045 m2

1.2 Dinding B – J

A. Luas Dinding B – J
Panjang = 2,7 m
Tinggi = 3,85 m
Luas = 2,7 x 3,85 = 10,395 m2
B. Luas Bidang Tiang Beton
Tinggi = 3,85 m
Lebar = 2 x 0,15 m
Luas = 3,85 x 0,3 = 1,155 m2
C. Luas Kusen
Luas = 2,2 x 0,8 = 1,76 m2
D. Luas Tembok 1:2
Luas = (1,35 x 1,5) + (0,55 x 1,5)
= 2,025 + 0,825
= 2,85 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 10,395 – (1,155+1,76+2,85)
= 4,63 m2

1.3 Dinding C – L

A. Luas Dinding C – L
Panjang = 13 m
Tinggi = 3,85 m
Luas = 10,25 x 3,85 = 39,4625 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 4 x 0,15 = 0,6 m
Luas = 3,85 x 0,6 = 2,31 m2
C. Luas Kusen
Luas = (2,2 x 0,9) 2 = 3,96 m2
D. Luas Tembok 1:2
Luas = (1,35 x 1,5) + (1,95 x 0,3) + (3,7 x 0,3) + (0,85 x 0,3)
= 2,025 + 0,585 + 1,11 + 0,255
= 3,975 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 39,4625 – (2,31+3,96+3,975)
= 29,2175 m2

1.4 Dinding D – N

A. Luas Dinding D-N


Panjang = 13 m
Tinggi = 3,85 m
Luas = 13 x 3,85 = 50,05 m2

Panjang =3m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2

Panjang = 13,15 m
Tinggi = 3,536 m
13,15 𝑥 3,536
Luas = = 23,2492 m2
2
Jumlah Luas Dinding D – N = 50,05+11,55+23,2492
= 84,8492 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = (4 x 0,15) = 0,6 m
Luas = 3,85 x 0,6 = 2,31 m2

Panjang = 1,425 m
Lebar = (1 x 0,15) = 0,15 m
Luas = 1,425 x 0,15 = 0,21375 m2
Jumlah luas bidang tiang beton = 2,31 x 0,21375 = 2,52375 m2
C. Luas Tembok 1:2
Luas = (4,35+2,85+3,85+1,35+2,85) x 0,3
= 4,575 m2
D. Luas Tembok 1:4
Luas E = A – (B+C)
= 61,6 – (2,52375 +4,575)
= 54,50125 m2

Uraian Dinding Sumbu Datar


2.1 Dinding E-A

A. Luas Dinding E – A
Panjang = 6 m
Tinggi = 3,85 m
Luas = 6 x 3,85 = 23,1 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 2 x 0,15 = 0,3 m
Luas = 3,85 x 0,3 = 1,155 m2
C. Luas Tembok 1:2
Luas = (2,85 x 0,3) x 2
= 1,71 m2
D. Luas Tembok 1:4
Luas D = A – (B+C)
= 23,1 – (1,155+1,71)
= 20,235 m2

2.2 Dinding F – A
A. Luas Dinding F – A
Panjang = 3 m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 2 x 0,15 = 0,3 m
Luas = 3,85 x 0,3 = 1,155 m2
C. Luas Kusen
Luas = (2,2 x 0,8) = 1,76 m2
D. Luas Tembok 1:2
Luas = (1,35 x 1,5) + (0,55 x 1,5)
= 2,025 + 0,825
= 2,85 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 11,55 – (1,155+1,76+2,85)
= 5,785 m2

2.3 Dinding G – A

A. Luas Dinding G – A
Panjang = 3 m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 2 x 0,15 = 0,3 m
Luas = 3,85 x 0,3 = 1,155 m2
C. Luas Kusen
Luas = (2,2 x 0,8) = 1,76 m2
D. Luas Tembok 1:2
Luas = (1,35 x 1,5) + (0,55 x 1,5)
= 2,025 + 0,825
= 2,85 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 11,55 – (1,155+1,76+2,85)
= 5,785 m2
2.4 Dinding H – C

A. Luas Dinding H – C
Panjang = 2 m
Tinggi = 3,85 m
Luas = 2 x 3,85 = 7,7 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 1 x 0,15 = 0,15 m
Luas = 3,85 x 0,15 =0,5775 m2
C. Luas Tembok 1:2
Luas = 1,85 x 0,3
= 0,555 m2
D. Luas Tembok 1:4
Luas D = A – (B+C)
= 7,7 – (0,5775+0,555)
= 6,5675 m2
2.5 Dinding I – A

A. Luas Dinding I – A
Panjang = 3 m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 2 x 0,15 = 0,3 m
Luas = 3,85 x 0,3 = 1,155 m2
C. Luas Tembok 1:2
Luas = (1,35 x 0,3) x 2
= 0,81 m2
D. Luas Tembok 1:4
Luas D = A – (B+C)
= 11,55 – (1,155+0,81)
= 9,585 m2

2.6 Dinding J – A

A. Luas Dinding J – A
Panjang = 1,5 m
Tinggi = 3,85 m
Luas = 1,5 x 3,85 = 5,775 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 1 x 0,15 = 0,15 m
Luas = 3,85 x 0,15 =0,5775 m2
C. Luas Tembok 1:2
Luas = 1,35 x 1,5
= 2,025 m2
D. Luas Tembok 1:4
Luas D = A – (B+C)
= 5,775 – (0,5775+2,025)
= 3,1725 m2

2.7 Dinding K – A

A. Luas Dinding K – A
Panjang = 3 m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 1 x 0,15 = 015 m
Luas = 3,85 x 0,15 = 0,5775 m2
C. Luas Kusen
Luas = (2 x 0,5) x 3 = 3 m2
D. Luas Tembok 1:2
Luas = 2,85 x 0,3
= 0,855 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 11,55 – (0,5775+3+0,855)
= 7,1175 m2
2.8 Dinding L – C

A. Luas Dinding L – C
Panjang = 3 m
Tinggi = 3,85 m
Luas = 3 x 3,85 = 11,55 m2
B. Luas Bidang Tiang Beton
Panjang = 3,85 m
Lebar = 1 x 0,15 = 015 m
Luas = 3,85 x 0,15 = 0,5775 m2
C. Luas Kusen
Luas = (2,6 x 1) x ((2 x 0,5) x 3) = 7,8 m2
D. Luas Tembok 1:2
Luas = 1,85 x 0,3
= 0,555 m2
E. Luas Tembok 1:4
Luas E = A – (B+C+D)
= 11,55 – (0,5775+7,8+0,555)
= 2,6175 m2
Tabel : Luas pasangan tembok menurut sumbu tegak dan sumbu datar
1. Sumbu Tegak

Uraian Jumlah Luas Tembok Tembok Bidang


No.
Sumbu Luas Beton 1:2 1:4 Kusen
1.1 A–N 64,8817 3,10125 7,77 54,01045
1.2 B–J 10,395 1,155 2,85 4,63 1,76
1.3 C–L 39,4625 2,31 3,975 29,2175 3,96
1.4 D–N 84,8492 2,52375 4,575 54,50125
Jumlah 114,7392 9,09 19,17 142,3592 5,72
2. Sumbu Datar

Uraian Jumlah Luas Tembok Tembok Bidang


No.
Sumbu Luas Beton 1:2 1:4 Kusen
2.1 E –A 23,1 1,155 1,71 20,235
2.2 F–A 11,55 1,155 2,85 5,785 1,76
2.3 G–A 11,55 1,155 2,85 5,785 1,76
2.4 H–C 7,7 0,5775 0,555 6,5675
2.5 I–A 11,55 1,155 0,81 9,585
2.6 J–A 5,775 0,5775 2,025 3,1725
2.7 K–A 11,55 0,5775 0,855 7,1175 3
2.8 L–C 11,55 0,5775 0,555 0,555 7,8
Jumlah 94,325 6,93 12,21 58,8025 14,32

II.2.a Pasangan Tembok 1;2 3,77 m3


Sumbu tegak = 19,17 m2
Sumbu datar = 12,21 m2 +
= 31,38 m2
Tebal pasangan tembok = 12 cm = 0,12 cm
Volume = 31,38 x 0,12 = 3,77 m3

II.2.b Pasangan Tembok 1:4 24,14 m3


Sumbu tegak = 142,3592 m2
Sumbu datar = 58,8025 m2 +
= 201,1617 m2
Tebal pasangan tembok = 12 cm = 0,12 cm
Volume = 201,1617 x 0,12 = 24,14 m3

II.3 Kusen
II.3.a Kusen Pintu dan Jendela 1,1264 m3
1. Tipe P1 = 1 buah
Panjang = (2 x 1) + (2 x 2,6) = 7,2 m
2. Tipe P2 = 2 buah
Panjang = (2 x 0,9) + (2 x 2,6) = 7 m

3. Tipe P3 = 3 buah
Panjang = (2 x 0,8) + (2 x 2,6) = 6,8 m

4. Tipe J1 = 6 buah
Panjang = (3 x 0,5) + (2 x 2) = 5,5 m

Panjang Kayu Kusen: Telinga Kusen


1. Tipe P1 = 7,2 m 1 x 2 x 0,15 = 0,3 m
2. Tipe P2 = 14 m 2 x 2 x 0,15 = 0,6 m
3. Tipe P3 = 20,4 m 3 x 2 x 0,15 = 0,9 m
4. Tipe J1 = 33 m + 6 x 4 x 0,15 = 3,6 m +
74,6 m 5,4 m
Panjang = 74,6 + 5,4 = 80 m
10% kayu hilang = 8m +
= 88 m
Volume = 88 x 0,08 x 0,16 = 1,1264 m3
II.3.b Memeni Kayu yang Menyentuh Pasangan 11,44 m2
Luas kusen yang menyentuh pasangan.
Panjang :
1 bh tipe P1 = (2 x 2,6) + 1 = 6,2 m = 6,2 m
2 bh tipe P2 = (2 x 2,6) + 0,9 = 6,1 x 2 = 12,2 m
3 bh tipe P3 = (2 x 2,6) + 0,8 = 6 x 3 = 18 m
6 bh tipe J1 = (2 x 0,5) + (2 x 2) = 5x6 = 30 m +
66,4 m
Luas = 66,4 x 0,15 = 9,96 m2

Luas Telinga Kusen :


Tipe P1 = 1 x 2 x 0,0411= 0,0822 m
Tipe P2 = 2 x 2 x 0,0411= 0,1644 m
Tipe P3 = 3 x 2 x 0,0411= 0,2466 m
Tipe J1 = 6 x 4 x 0,0411= 0,9864 m +
1,48 m
Volume = 9,96 + 1,48 = 11,44 m2

II.3.c Bout-Bout/Angker 33,18 kg

Tipe P1 = 1 x 6 = 6 buah
Tipe P2 = 2 x 6 = 12 buah
Tipe P3 = 3 x 6 = 18 buah
Tipe J1 = 6 x 4 = 24 buah +
60 buah
Berdasarkan daftar baja
d = 16 mm G = 1,58 kg/m
Panjang bout angker = 30 + 5 cm = 0,35 m
Berat 1 buah bout angker = 0,35 x 1,58 = 0,553 kg
Volume = 60 x 0,553 = 33,18 kg

III PEKERJAAN KAP DAN ATAP


III.1 Kap dan Rangka Atap
III.1.a Pekerjaan Kuda Kuda 2,02709
III.1.a.1 Kuda – Kuda Utama m3
Dari ∆ Kuda – Kuda ABC Diketahui
< A = < B = 30o , CC1 = 1/2 BC
CC1 = 1/2 AC = 1/2 BC
AC1 = BC1 = 5,75
AC2 = CC12 + AC12
AC2 = (1/2 AC)2 + (5,75 )2
AC2 = 1/4 AC2 + 33,0625
4 AC2 = AC2 + 132,25
3 AC2 = 132,25
132,25
AC2 = 3
AC2 = 44,0833
AC = √44,0833
AC = 6,6395 m
AC = BC
CC1 = 1/2 AC
CC1 =1/2 (6,6395) m
CC1 = 3,31975 m

Panjang EE1 :
EE1 : CC1 = 2,875 : 5,75
EE1 : 3,31975 = 2,875: 5,75
5,75 x EE1 = 2,875 x 3,31975
EE1 = 9,5443 : 5,75
EE1 = 1,6599 m
EE1 = FF1

Panjang DD1 :
DD1 : CC1 = 1,4375 : 5,75
DD1 : 3,31975 = 1,4375: 5,75
5,75 x DD1 = 1,4375 x 3,31975
DD1 = 4,7721 : 5,75
DD1 = 0,8299 m
DD1 = GG1

Perhatikan ∆ EEC1
Panjang EC1 :
EC12 = EE12 + E1C12
EC12 = (1,6599) 2 + (2,875)2
EC12 = 2,7553 + 8,2656
EC1 = √11,0209
EC1 = 3,3197 m
EC1 = FC1

Perhatikan ∆ DD1E1
Panjang DE1 :
DE12 = DD12 : + D1E12
DE12 = (0,8299)2 + (1,4375)2
DE12 = 0,6887 + 2,0664
DE1 = √2,7551
DE1 = 1,6598 m
DE1 = GF1

Panjang EH :
EH = E1H1
EH = E1C1 +C1H1
EH = 2,875 + 2,875
EH = 5,75 m
EH = AC1 = 5,75 m

1. Ukuran 8/15
Balok Tarik = 2 x 11,50 m = 23 ,00 m
2 bh kuda - kuda = 2 x 23,00 m = 46,00 m
2. Ukuran 8/12
Balok Apit = 2 x 5,75 m = 11,50 m
Balok Skur (EC1 + FC1) = 2 x 3,3197 m = 6,6394 m
Balok Skur (DE1 + GF1 ) = 2 x 1,6598 m = 3,3196 m
Sokong (EE1 + FF1) = 2 x 1,6599 m = 3,3198 m
Sokong (DD1 + GG1) = 2 x 0,8299 m = 1,6598 m
Kaki Kuda – Kuda (AC + BC) = 2 x 6,6395 m = 13,279 m
Tiang Kaki Kuda – Kuda (CC1) = 3,31975 m +
= 43,03735 m
2 bh kuda - kuda = 2 x 43,03735 = 86,0747 m
Nok Gording = 6,00 m +
= 92,0747 m
Uraian Volume :
1. Ukuran 8/15 = 46,00 x 0,08 x 0,15 = 0,55200000 m3
2. Ukuran 8/12 = 92,0747 x 0,08 x 0,12 = 0,88391712 m3+
= 1,43591712 m3
10% kayu hilang = 0,143591712 m3+
Volume = 1,579508832 m3

III.1.a.2 Kuda – Kuda Anak 1


Kuda – Kuda Anak 1
Dari ∆ Kuda – Kuda ABC Diketahui
< A = < B = 30o ,
CC1= 1/2 AC = 1/2 BC
AC1 = BC1 = 5,75
AC2 = CC12 + AC12
AC2 = (1/2 AC)2 + (4,625 )2
AC2 = 1/4 AC2 + 21,3906
4 AC2 = AC2 + 85,5624
3 AC2 = 85,5624
AC2 = 28,5208
AC = 5,3405 m
AC = BC
CC1 = 1/2 AC
CC1 = 1/2 (5,3405) m
CC1 = 2,67025 m

Panjang EE1 :
EE1 : CC1 = 2,3125 : 4,625
EE1 : 2,67025 = 2,3125 : 4,625
4,625 x EE1 = 2,3125 x 2,67025
EE1 = 6,1749 : 4,625
EE1 = 1,3351 m
EE1 = HH1
Perhatikan ∆ EE1C1
Panjang EC1 :
EC12 = EE12 : + E1C12
EC12 = (1,3351)2 + (2,3125)2
EC12 = 1,7825 + 5,3476
EC1 = √7,1301
EC1 = 2,6702 m
EC1= HC1

Panjang EH :
EH = E1H1
EH = E1C1 +C1H1
EH = 2,3125 + 2,3125
EH = 4,625 m
EH = AC1 = 4,625 m

1. Ukuran 8/15
Balok Tarik = 2 x 9,250 m = 18,50 m
2. Ukuran 8/12
Sokong (EE1 + HH1) = 2 x 1,3351 m = 2,6702 m
Balok Skur (EC1 + HC1 ) = 2 x 2,6702 m = 5,3404 m
Kaki Kuda – Kuda (AC + BC) = 2 x 5,3405 m = 10,681 m
Tiang Kaki Kuda – Kuda (CC1) = 2,67025 m +
= 21,36185 m
Uraian Volume :
1. Ukuran 8/15 = 18,50 x 0,08 x 0,15 = 0,22200000 m3
2. Ukuran 8/12 = 21,36185 x 0,08 x 0,12 = 0,20507376 m3
10% kayu hilang = 0,020507376 m3+
Volume = 0,447581136 m3

Volume Total = 1,579508832 m3 + 0,447581136 m3 = 2,027089968 m3


III.1.b Pekerjaan Rangka Atap 75,69048
Dari ∆ ABC Diketahui : m2
< A = < B = 30o , CC1 = 1/2 BC
CC1 = 1/2 AC = 1/2 BC
AC1= BC1= 5,75
BC2 = CC12 + AC12
BC2 = (1/2 AC)2 + (5,75 )2
BC2 = 1/4 AC2 + 33,0625
4 BC2 = AC2 + 132,25
3 BC2 = 132,25
132,25
BC2 = 3
BC2 = 44,0833
BC = √44,0833
BC = 6,6395 m
BC = AC = 6,6395 m
CC1 = 1/2 AC
CC1 =1/2 (6,6395) m
CC1 = 3,31975 m
Jadi panjang sebenarnya :
BC = AC = 6,6395 m
AE = 3,3196 m
BB1 =AA1 = 6 m
Volume atap = 2 x luas BB1CC1 – (AE x 1,20)
= 2 x (6 x 6,6395) – (3,3196 m x 1,20)
= 79,674 – 3,98352
Volume = 75,69048 m2
III.1.c Pekerjaan Lisplank 5,65 m2

Penjelasan Gambar (1)


Panjang = 3,00
Tinggi = 0,30
Luas = 3,00 X 0,30 = 0,90 m2 0,3
1
Panjang = 3,00
Tinggi = 0,30
Luas = 3,00 X 0,30 = 0,90 m2+ 3,00 3,00
= 1,8 m2 6,00

Penjelasan Gambar (2)


Panjang = 3,70
Tinggi = 0,30
Luas = 3,70 X 0,30 = 1,11 m2 2
Panjang = 2,30
Tinggi = 0,30 0,

Luas = 2,30 X 0,30 = 0,69 m2+ 3,70 2,30


= 1,8 m2 6,00
Penjelasan Gambar (3)
Panjang = 6 m
Tinggi = 0,20
Luas = 6 x 0,20 = 1,2 m2

Penjelasan Gambar (4)


Panjang = 4,25 m
Tinggi = 0,20
Luas = 4,25 X 0,20 = 0,85 m2

Pekerjaan listplank papan terdiri dari:


Penjelasan 1 = 1,8 m2
Penjelasan 2 = 1,8 m2
Penjelasan 3 = 1,2 m2
Penjelasan 4 = 0,85 m2
Volume = 5,65 m2

III.1.d Pekerjaan Papan Ruiter 6,00 m


Panjang = 6,00 m
Volume = 6,00 m

III.1.e Memeni Sambungan Kayu 3,4188 m2


Memeni sambungan kayu dan lobang diperkirakan sebagai berikut :
0,12 x 0,12 x 2 = 0,0288 m2
0,08 x 0,12 = 0,0086 m2
0,06 x 0,12 x 2 = 0,0144 m2
0,0518 m2

Untuk 1 buah kuda-kuda ± 22 sambungan


Untuk 3 buah kuda-kuda = 3 x 22 x 0,0518
Volume = 3,4188 m2

III.1.f Residu Kuda – Kuda 44,51 m2


Untuk mencari residu kuda – kuda, perhatikan pekerjaan kuda-kuda
yang telah diuraikan untuk masing –masing ukuran sebagai berikut :
Panjang 8/15... 92,0747 m
Keliling 8/15… 0,4
Luas 92,0747 x 0,4 = 36,82 m2
Panjang 8/12 ... 21,36185 m
Keliing 8/12…. 0,36 m
Luas 21,36185 x 0,36 = 7.69 m2
Volume Residu = 44,51 m2

III.1.g Bout- Bout Angker 34,0084


Penjelasan (1) kg
Berdasarkan Tabellen Staalconstructies
d = 16 mm
G Bout = 1,58 k/m
Panjang Bout = 30 cm = 0,30 M
Berat 1 Buah Bout = 0,30 X 1,58 = 0,474 Kg
Banyak Bout = 2 x 8 = 16 buah
Volume = 16 x 0,474 = 7,584 kg

Penjelasan (2)
Panjang Bout = 30 cm = 0,30 m
Berat 1 Buah Bout = 0,30 X 1,58 = 0,474 kg
Banyak Bout =
Volume =

Panjang Bout = 30 cm = 0,30 m


Berat 1 Buah Bout = 0,30 X 1,58 = 0,474 Kg
Banyak Bout = 8 buah
Volume = 8 x 0,474 = 3,792 kg
Panjang Bout = 15 cm = 0,15 m
d = 16 mm G bout = 1,58 kg/m
Berat 1 Buah Bout = 0,15 X 1,58 = 0,237 Kg
Banyak Bout = 2 buah
Volume = 2 x 0,237 = 0,474 kg

Panjang Plaat Beogol = 25 +100 = 1,25 m


Tebal Plaat = 5 mm
Lebar Plaat = 50 mm
Berat G = 2 kg/m
Volume Plaat = 1,25 x 2 = 2,5 kg
Panjang Reng Plaat= 0,60 m
Ukuran Reng Plaat = 5 mm x 50 mm
Berat 1 Buah Reng Plaat =0,60 x 2 = 1,20 kg
Banyak Reng Plaat= 2 buah
Volume Reng Plaat = 2 x 1,20 = 2,4 kg
12,958 kg

Penjelasan (3)
Panjang beugol = 94 cm = 0,94 m
d = 16 mm G beugol = 1,58 kg/m
berat 1 buah beugol = 0,94 x 1,58 = 1,4852 kg
banyak beugol = 2 buah
volume beugol = 2 x 1,4852 = 2,9704 kg
 Panjang bout = 30 cm = 0,30 m
d = 16 mm G bout = 1,58 kg/m
berat 1 buah bout = 0,30 x 1,58 = 0,474 kg
banyak bout = 4 buah
volume bout = 4 x 0,474 = 1,896 kg
 Panjang reng plaat = 32 cm = 0,32 m
Ukuran reng plaat = 5 mm x 50 mm G = 2 kg/m
berat 1 buah ring bout = 0,30 x 2 = 0,64 kg
banyak reng plaat = 4 buah
volume reng plaat = 4 x 0,64 = 2,56 kg
7,4264 kg
Penjelasan (4)
 Panjang bout = 25 cm = 0,25 m
d = 16 mm G bout = 1,58 kg/m
berat 1 buah bout = 0,25 x 1,58 = 0,395 kg
volume bout = 0,395 kg

penjelasan (5)
 Panjang bout = 25 cm = 0,25 m
d = 16 mm G bout = 1,58 kg/m
berat 1 buah bout = 0,25 x 1,58 = 0,395 kg
banyak bout = 4 buah
volume bout = 4 x 0,395 = 1,58 kg

penjelasan (6)
 Panjang bout = 15 cm = 0,15 m
d = 16 mm G bout = 1,58 kg/m
berat 1 buah bout = 0,15 x 1,58 = 0,237 kg
banyak bout = 5 buah
volume bout = 5 x 0,237 = 1,185 kg

 Panjang reng plaat = 36 cm = 0,36 m


Ukuran reng plaat = 5 mm x 50 mm G = 2 kg/m
berat 1 buah ring bout = 0,36 x 2 = 0,72 kg
banyak reng plaat = 4 buah
volume reng plaat = 4 x 0,72 = 2,88 kg
4,065 kg

Volume bout/angker :
Penjelasan 1 = 7,584 kg
Penjelasan 2 = 12, 958 kg
Penjelasan 3 = 7,4264 kg
Penjelasan 4 = 0,395 kg
Penjelasan 5 = 1,58 kg
Penjelasan 6 = 4,065 kg
Volume = 34,0084 kg

III.2 Atap 75,69048


III.2.a Memasang Atap m2
Luas memasang atap = luas memasang rangka atap
Volume = 75,69048 m2
III.2.b Memasang Perabung 6m
Panjang perabung = panjang papan ruiter
Volume = 6 m
IV PEKERJAAN PLAFOND
IV.1 Balok Plafond
IV.1.a Rangka Plafond Dalam 1,249803
m3

Penjelasan (1)
6/12. . . . . 6,85 x 2 = 13,7 m
5/7 . . . . . 6,73 x 4 = 26,92 m
6/12 . . . . 2,73 x 4 = 10,92 m
5/7 . . . . . 2,73 x 9 = 24,57 m
24,62 m 51,49 m
Penjelasan (2)
6/12. . . . . 4,6 x 1 = 4,6 m
1,56 x 1 = 1,56 m
3,1 x 1 = 3,1 m
5/7 . . . . . 4,48 x 2 = 8,96 m
2,98 x 2 = 5,96 m
6/12 . . . . 1,23 x 1 = 1,23 m
1,44 x 1 = 1,44 m
2,73 x 2 = 5,46 m
5/7 . . . . . 1,23 x 2 = 2,46 m
2,73 x 4 = 10,92 m
17,39 m 28,3 m
Penjelasan (3)
6/12. . . . . 1,35 x 2 = 2,7 m
5/7 . . . . . 1,23 x 2 = 2,46 m
6/12 . . . . 1,23 x 2 = 2,46 m
5/7 . . . . . 1,23 x 2 = 2,46 m
5,16 m 4,92 m

Penjelasan (4)
6/12. . . . . 2,85 x 2 = 5,7 m
5/7 . . . . . 2,73 x 4 = 10,92 m
6/12 . . . . 2,73 x 2 = 5,46 m
5/7 . . . . . 2,73 x 4 = 10,92 m
11,16 m 21,84 m
Penjelasan (5)
6/12. . . . . 4,35 x 2 = 8,7 m
5/7 . . . . . 4,23 x 4 = 16,92 m
6/12 . . . . 2,73 x 3 = 8,19 m
5/7 . . . . . 2,73 x 6 = 16,38 m
16,89 m 33,3 m
Penjelasan (6)
6/12. . . . . 1,35 x 2 = 2,7 m
5/7 . . . . . 1,23 x 2 = 2,46 m
6/12 . . . . 1,23 x 2 = 2,46 m
5/7 . . . . . 1,23 x 2 = 2,46 m
5,16 m 4,92 m
Penjelasan (7)
6/12. . . . . 1,35 x 2 = 2,7 m
5/7 . . . . . 1,23 x 2 = 2,46 m
6/12 . . . . 1,23 x 2 = 2,46 m
5/7 . . . . . 1,23 x 2 = 2,46 m
5,16 m 4,92 m

Daftar Balok Plafond


Penjelasan 6 x 12 5x7
1 24,62 51,49
2 17,39 28,3
3 5,16 4,92
4 11,16 21,84
5 16,89 33,3
6 5,16 4,92
7 5,16 4,92
Jumlah 85,54 m 149,69 m
Volume 6/12 . . . . 85,54 x 0,06 x 0,12 = 0,615888 m3
Volume 5/7 . . . . . 149,69 x 0,05 x 0,07 = 0,523915 m3
1,139803 m3
10% Kayu hilang = 0,11
Volume 1,249803 m3

IV.1.b Rangka Plafond Luar (Overstek) 0,203578


m3

Penjelasan (1)
6/12. . . . . 0,6 x 2 = 1,2 m
5/7 . . . . . 0,48 x 4 = 1,92 m
6/12 . . . . 2,73 x 2 = 5,46 m
6,66 m 1,92 m
Penjelasan (2)
6/12. . . . . 0,6 x 2 = 1,2 m
5/7 . . . . . 0,48 x 4 = 1,92 m
6/12 . . . . 2,73 x 2 = 5,46 m
6,66 m 1,92 m
Penjelasan (3)
6/12. . . . . 1,00 x 2 = 2,00 m
5/7 . . . . . 0,89 x 4 = 3,56 m
6/12 . . . . 2,73 x 2 = 5,46 m
5/7 . . . . . 2,73 x 1 = 2,73 m
7,46 m 6,29 m

Daftar Balok Plafond


Penjelasan 6 x 12 5x7
1 6,66 1,92
2 6,66 1,92
3 7,46 6,29
Jumlah 20,78 10,13
Volume 6/12 . . . . 20,78 x 0,06 x 0,12 = 0,149616 m3
Volume 5/7 . . . . . 10,13 x 0,05 x 0,07 = 0,035455 m3
0,185071 m3
10% Kayu hilang = 0,01
Volume 0,203578 m3

IV.1.c Residu Rangka Plafond 76,632 m2


Plafond Dalam
Panjang 6/12 = 85,54 m Keliling = 0,36 m
Panjang 5/7 = 149,69 m Keliling = 0,24 m
Luas 6/12 = 85,54 x 0,36 = 30,7944 m2
Luas 5/7 = 149,69 x 0,24 = 35,9256 m2
66,72 m2
Plafond Luar
Panjang 6/12 = 20,78 m Keliling = 0,36 m
Panjang 5/7 = 10,13 m Keliling = 0,24 m
Luas 6/12 = 20,78 x 0,36 = 7,4808 m2
Luas 5/7 = 10,13 x 0,24 = 2,4312 m2
9,912 m2
Residu Plafond Dalam = 66,72 m2
Residu Plafond Luar = 9,912 m2
Volume 76,632 m2

IV.2 Memasang Plafond


IV.2.a Memasang Plafond Dalam 62,25 m2

Ruang 1 . . . . Luas = 3,00 x 7,00 = 21,00


Ruang 2 . . . . Luas = (3,00 x 3,25) + (1,50 x 1,50) = 12,00
Ruang 3 . . . . Luas = 1,50 x 1,50 = 2,25
Ruang 4 . . . . Luas = 3,00 x 3,00 = 9,00
Ruang 5 . . . . Luas = 3,00 x 4,50 = 13,5
Ruang 6 . . . . Luas = 1,50 x 1,50 = 2,25
Ruang 7 . . . . Luas = 1,50 x 1,50 = 2,25
Volume 62,25 m2

IV.2.b Memasang Plafond Luar (Overstek) 6,60 m2


Bagian 1 . . . . Luas = 0,60 x 3,00 = 1,8
Bagian 2 . . . . Luas = 0,60 x 3,00 = 1,8
Bagian 3 . . . . Luas = 1,00 x 3,00 = 3,00
Volume 6,60 m2

IV.2.c Les Pinggir Plafond Dalam 76,30 m


Ruang 1
Panjang = 2 x (2,85 + 6,85) = 19,40
Ruang 2
Panjag = 2 x (2,85 + 4,60) = 14,90
Ruang 3
Panjang = 2 x (1,35 + 1,35) = 5,40
Ruang 4
Panjang = 2 x (2,85 + 2,85) = 11,40
Ruang 5
Panjang = 2 x (2,85 + 4,35) = 14,40
Ruang 6
Panjang = 2 x (1,35 + 1,35) = 5,40
Ruang 7
Panjang = 2 x (1,35 + 1,35) = 5,40
Volume 76,30 m

V PEKERJAAN PLESTERAN
VI PEKERJAAN LANTAI
VI.1 Urugan di Bawah Lantai
VI.1.a Urugan Tanah 7, 13 m3
VI.1.a.1 Urugan Tanah di Bawah Lantai Ruangan
Luas ruangan 1 = 4 x 3 = 12
Luas ruangan 2 = 3 x 3 =9
Luas ruangan 3 = 3 x 3,25 = 9,75
Luas ruangan 4 = 3 x 3 =9
Luas ruangan 5 = 3 x 4,60 = 13,8
Luas ruangan 6 = 1,5 x 3 = 4,5
Luas ruangan 7 = 1 x 2 =3
Luas ruangan 8 = 1,5 x 1,5 = 2,25
Luas ruangan 9 = 1,5 x 1,5 = 2,25
Luas ruangan 10 = 1,5 x 1,5 = 2,25
= 66,8 m3
Tebal urugan tanah = 0,10 m
Volume = 66,8 x 0,10 = 6,68 m3
VI.1.a.2 Urugan Tanah di Bawah Lantai Teras
Panjang =3m
Lebar = 1,5 m
Tebal = 0,10 m
Volume = 0,45 m3
Volume urugan tanah Ruangan + Teras = 6,68 + 0,45 = 7, 13 m3

VI.1.b Urugan Pasir 6,7925 m3


VI.1.b.1 Urugan Pasir di Bawah Lantai Ruangan
Luas ruangan 8 s/d 10 = 6,75 m
Tebal urugan pasir = 0,05 m
Volume = 0.3375 m
Luas ruangan 1 s/d 7 = 60,05 m
Tebal urugan pasir = 0,1 m
Volume = 6,005 m
Volume urugan pasir = 0,3375 + 6,005 = 6,3425 m

VI.1.b.1 Urugan Pasir di Bawah Lantai Ruangan


Panjang =3m
Lebar = 1,5 m
Tebal urugan pasir = 0,1
= 0,45m3
Volume urugan pasir Ruangan + Teras = 6,3425 + 0,45 = 6,7925 m3

VI.2 Pasangan Lantai 71, 3 m2


VI.2.a Pasangan Ubin PC Polos
Ruang 1 sd 7 = 60,05
Teras 3 x 1,5 = 4,5
= 64, 55 m2
Luas Ruang 8 s/d 10 = 6,75 m2
Jumlah Seluruhnya = 64, 55 + 6, 75 = 71, 3 m2
VI.2.b Pasangan Ubin PC Petak/Alur 23,85 m2
Untuk 1 kamar Mandi = 3 (1,5 x 1,5) + (1,5 x 1,5) – (1,5 x 0,7)
= 6,75 + (2,25 – 1,05)
= 6,75 + 1,2
= 7,95 m
Untuk 3 kamar mandi = 3 x 7,59 = 23,85 m2
Pasangan PC Petak/ Alur = 23,85 m2

VII PEKERJAAN PERLENGKAPAN DALAM


VII.1 Listrik
VII.1.a Pas Instalasi Dalam 13 Titik
Lampu Pijar = 11 titik
Lampu Downlight = 2 titik
Volume = 13 Titik

VII.1.b Pemasangan Lampu Pijar 11 Titik


Volume = 11 Titik

VII.1.c Pemasangan Lampu Downlight 2 Buah


Volume = 2 Buah

VII.1.d Zekering 1 Buah


Volume = 1 Buah

VII.1.e Stop Kontak 7 Buah


Volume = 7 Buah

VII.1.f Saklar Ganda 4 Buah


Volume = 4 Buah

VII.1.g Saklar Tunggal 3 Buah


Volume = 3 Buah

VII.2 Sanitasi dan Istalasi Air


VII.2.a Kloset Duduk 3 Buah

Volume = 3 Buah
VII.2.b Pemasangan Istalasi Air Bersih 14,2 m
D = ½’
Panjang = 1,5 + 10,3 + 1 + 1,4
Volume = 14,2 m

VII.2.c Pemasangan Istalasi Air Kotor 39,19 m

D = 2’
Panjang = ( 4,61 + 4,39 + 10,79 + 0,69 + 10,72 ) + ( 4,42 + 12,07
+ 1,5 )
Volume = 21,2 + 17,99
= 39,19 m
VII.2.d Kran 4 Buah
Volume = 4 Buah

VII.2.e Flour Drain 3 Buah

Volume = 3 Buah

VIII PEKERJAAN PERLENGKAPAN LUAR


VIII.1 Halaman
VIII.1.a Saluran Keliling Gedung 6m
Saluran Tertutup =6m
Volume =6m

VIII.1.b Rabat Beton 15,675 m2


Luas F.1
Panjang = 2.85 m
Lebar = 5.5 m
Luas = 2,85 x 5,5 = 15,675 m2
Volume = 15,675 m2

VIII.1.c Bak Kontrol 1 buah


Volume
Ukuran 30 x 30 = 1 buah