Take of Sheet

Kegiatan : Bendung
Desa : Sukamaju

I. Pekerjaan Bendung

Panjang = 5 m

Potongan ke 1
a.Luas A1 = 0.48 - 0.04 = 0.02 m2
b.Luas A2 = 2.2 x 0.4 = 0.88 m2
c.Luas A3 = 1.5 - 0.15 = 0.22 m2
Total A 1- 3 = 1.12 m2
Volume 1 = 5.62 m3

Potongan ke 2
d.Luas A4 = 0.4 x 3.3 = 1.32 m2
e.Luas A5 = 1.5 x 1.5 x 0.5 = 1.13 m2
2.45 Total A 4- 7 = 2.45 m3
Volume 2 = 12.23 m3

Potongan ke 3
d.Luas A7 = 8.37 - 1.6 = 13.56 m2
e.Luas A8 = 0.88 + 0.64 - 0.08 = 1.44 m2
Total A 4- 7 = 15.00 m2
Volume 3 = 75.00 m3

Total Volume 1 - 3 = 92.84 m3

Galian Tanah ( analisa K-224 )

Panjang = 5.00 m

a. Luas galian = = 15.57 m2


b. Volume galian = 15.57 x 5.00 = 77.84 m3
b. Pekerja galian = 0.40 x 77.84 = 31.14 HOK
c. Jumlah HOK Pekerja = 75.00 x 31.14 = 106.13 HOK

Analisa bidang pengairan


1 m3 pasangan PC 1:4
a. Batu belah = 1.2 x 92.84 = 111 m3
b. Pasir pasang = 0.5 x 92.84 = 46 m3
c. Semen = 3 x 92.84 = 279 zak
d. Tukang = 1.2 x 92.84 = 111 HOK
e. Pekerja = 3.6 x 92.84 = 334 HOK

1 m2 plesteran PC 1:3
a. Pasir pasang = 0.013 x 92.84 = 1 m3
b. Semen = 0.1 x 92.84 = 9 zak
c. Tukang = 0.15 x 92.84 = 14 HOK
d. Pekerja = 0.4 x 92.84 = 37 HOK

II. Tembok Penahan Tanah

Panjang = 3 m
e.Luas A1 = 0.8 x 2.2 = 1.76 m2
= 0.55 x 1.6 x 0.5 0.17 m2 -
= 1.59 m2
Volume TPT = 4.76 m3

Galian Tanah ( analisa K-224 )

Panjang = 3 m

a. Luas galian = 1.4 x 0.80 = 1.12 m2


b. Volume galian = 1.12 x 3.00 = 3.36 m3
b. Pekerja galian = 0.4 x 3.36 = 1.34 HOK
c. Jumlah HOK Pekerja = 0.17 x 1.34 = 1.52 HOK

Analisa BEP

a. Batu belah = 1.2 x 4.76 = 6 m3


b. Pasir pasang = 0.5 x 4.76 = 2 m3
c. Semen = 2.6 x 4.76 = 12 zak
d. Tukang = 0.8 x 4.76 = 4 HOK
e. Pekerja = 2.4 x 4.76 = 11 HOK

III. Saluran Irigasi

Galian Tanah ( analisa K-224 )

Panjang = 1000 m

a. Luas galian = 0.4 x 0.4 = 0.16 m2


b. Volume galian = 0.16 x 1000 = 160 m3
b. Pekerja galian = 0.4 x 160 = 64 HOK
c. Jumlah HOK Pekerja = 11 x 64 = 75 HOK

Pasangan Saluran
Panjang = 1000 m
Tinggi = 0.8 m
Luas pnp = 0.30 x 0.8 = 0.24 m2
Volume = 240.00 m3

Analisa bidang pengairan


1 m3 pasangan PC 1:4
a. Batu belah = 1.2 x 240 = 288.00 m3
b. Pasir pasang = 0.5 x 240 = 120.00 m3
c. Semen = 3 x 240 = 720.00 zak
d. Tukang = 1.2 x 240 = 288.00 HOK
e. Pekerja = 3.6 x 240 = 864.00 HOK

1 m2 plesteran PC 1:3
Luas = 0.015 m2
Volume = 15 m3
a. Pasir pasang = 0.013 x 15 = 0.19 m3
b. Semen = 0.1 x 15 = 1.50 zak
c. Tukang = 0.15 x 15 = 2.25 HOK
d. Pekerja = 0.4 x 15 = 6.00 HOK

IV. Pekerjaan Beton Bertulang ! : 2 : 3

Volume : 1.30 x 0.70 x 0.10 = 0.09 m3


Analisa BOW Kode G.41
1.Split = 0.82 x 0.09 = 0.07 ˜˜ 0.10 m3
2.Pasir Pasang = 0.54 x 0.09 = 0.05 ˜˜ 0.10 m3
3.Semen = 6.8 x 0.09 = 0.62 ˜˜ 1.00 Zak
4.Tukang = 1 x 0.09 = 0.09 ˜˜ 0.12 HOK
5.Pekerja = 6 x 0.09 = 0.55 ˜˜ 0.73 HOK
6.Tulangan Ø 10 :
- Vertikal = 11.2 + 1.6 = 12.80 m
= 2.00 bt
-Horizontal = 13 + 1 = 14.00 m
= 2.00 bt
Total = 4 bt

Jumlah Bahan dan Upah


BETULIN
a. Batu belah = 405.13 m3
b. Pasir pasang = 170.31 m3
c. Split = 0.10 m3
c. Semen = 1,022.70 Zak
d. Tulangan Ø 10 = 4.00 bt
e. Pekerja = 1,436.62 HOK
d.
e. Tukang
Pekerja = 419.52
1,328 HOK
RENCANA ANGGARAN BIAYA

Propinsi : Jawa Barat No. RAB : 01


Kabupaten : Bogor Program : PNPM MANDIRI PERDESAAN
Kecamatan : Cigudeg Jenis Kegiatan : Bendung
Desa : Sukamaju Ukuran/ Dimensi : Panjang 5 m

VOLUME Harga Jumlah Total


URAIAN Satuan satuan Swadaya PNPM
Total Swadaya PNPM
(Rp) (Rp) (Rp)
BAHAN
1 Papan Nama Proyek 1.00 1.0 Ls 100,000 - 100,000
2 Batu Belah 117.13 35.14 82.0 m3 80,000 2,811,092 6,559,216
3 Pasir Pasang 50.11 50.1 m3 70,000 - 3,507,745
4 Semen 301.20 301.2 zak 52,000 - 15,662,435
5 Besi beton Ø 10 4.00 4.0 kg 70,000 - 280,000
6 Split 0.10 0.1 m3 100,000 - 10,000
7 Kawat Beton 0.50 0.5 bt 50,000 - 25,000
8 Pintu Air 2.00 2.0 Ls 2,000,000 - 4,000,000

Sub Total 1 2,811,092 30,044,396


ALAT
1 Mixer Concreat 0 - jam 50,000 - -
2 Cangkul 2 2 - buah 27,500 55,000 -
3 Sekop 1 1 - buah 32,500 32,500 -
4 Ember 4 4 - buah 5,000 20,000 -

Sub Total 2 107,500 -


UPAH
1 Pekerja 491.18 107.65 383.5 HOK 35,000 3,767,753 13,423,708
2 Tukang 129.27 129.3 HOK 40,000 - 5,170,835

Sub Total 3 3,767,753 18,594,543


TOTAL BIAYA
Dari PNPM 48,638,939
Sumber Dana
Dari Swadaya 6,686,345
RENCANA ANGGARAN BIAYA

Propinsi : Jawa Barat No. RAB : 01


Kabupaten : Bogor Program : PNPM MANDIRI PERDESAAN
Kecamatan : Cigudeg Jenis Kegiatan : Saluran Irigasi
Desa : Sukamaju Ukuran/ Dimensi : Panjang 1.000 m

VOLUME Harga Jumlah Total


URAIAN Satuan satuan Swadaya PNPM
Total Swadaya PNPM
(Rp) (Rp) (Rp)
BAHAN
1 Papan Nama Proyek - Ls 100,000 - -
2 Batu Belah 288.00 86.40 201.6 m3 80,000 6,912,000 16,128,000
3 Pasir Pasang 120.20 120.2 m3 70,000 - 8,413,650
4 Semen 721.5 721.5 zak 52,000 - 37,518,000
5 Besi beton Ø 10 - kg 70,000 - -
6 Split - m3 100,000 - -
7 Kawat Beton - bt 50,000 - -
8 Pintu Air - Ls 2,000,000 - -

Sub Total 1 6,912,000 62,059,650


ALAT
1 Mixer Concreat - jam 50,000 - -
2 Cangkul - buah 27,500 - -
3 Sekop - buah 32,500 - -
4 Ember - buah 5,000 - -

Sub Total 2 - -
UPAH
1 Pekerja 945 75.4 870.0 HOK 35,000 2,640,208 30,450,000
2 Tukang 290 290.3 HOK 40,000 - 11,610,000

Sub Total 3 2,640,208 42,060,000


TOTAL BIAYA
Dari PNPM 104,119,650
Sumber Dana
Dari Swadaya 9,552,208
Dari PNPM - 152,758,589
Dari Swadaya 16,238,553 -