PERHITUNGAN KWANTITAS PEKERJAAN

NO JENIS/GAMBAR PEKERJAAN PERHITUNGAN KWANTITAS SATUAN

I PEKERJAAN PERSIAPAN
1.Pembersihan Lokasi Luas 1 = 13 x 12.8 173.5 m2
= 166,4

Luas 2 = 1,10 x 13/2


= 7,15

Luas total=173,55

2. Pemasangan Bouwplank
Bouwplank = 29 titik 29 m1

3. Pembuatan Jalan Sementara Jalan sementara = 6,2409 m2


Luas 1 = 2 x 2,93
=5,86
Luas 2 = 0,26 x 2,93/2
= 0,3809

Luas total=6,2409

4. Pembuatan Kantor Direksi dan Gudang Kantor Direksi = 10.5 m2

= 1,5 x 1,5 = 2,25

5. Pembuatan Pagar Sementara Pagar sementara = 62 m1

= 13,9+13+12,8+13,05

52.75
II PEKERJAAN TANAH.

1. Galian Tanah Panjang galian = 112,84 m 58.9 m3


Penampang =0,95 x 1
Volume = 0,95x1x112,84=
= 107,198 m

2. Urugan Tanah Kembali Volume = 1/4 galian 15.5 m3


= 1/4x107,198
= 26,7995

3. Urugan Tanah Bawah Lantai 22.34 m3


Luas lantai = (6x5.5)+(6.5x3.85)+(4.7x3.5)=74.48
Tebal urugan = 0.3 m
Volume = (6x5.5)+(6.5x3.85)+(4.7x3.5)x0.3
= 22.34 m3
4. Pekerjaan Urug Pasir Bawah lantai 11.17 m3
Luas lantai = (6x5.5)+(6.5x3.85)+(4.7x3.5)
Tebal urugan = 0.15
Volume = (6x5.5)+(6.5x3.85)+(4.7x3.5)x0.15
= 11.17 m3

III PEKERJAAN PONDASI


1. Pemasangan Batu Kosong Panjang pondasi = 62 m 9.3 m3
Penampang = 0.15x1

Volume =0,15x1x62
= 9.3 m3

2. Pasangan Batu Kali 1Pc : 6 Ps Panjang pondasi = 62m 54.25 m3


Luas penampang =
=(0.25+1)x0.7=0.875

Volume = 0.875x62 =
54.25
IV PEKERJAAN BETON Panjang sloof = 62 m 2,325 m3
1. Pekerjaan Beton sloof Penampang = 0.15x0.25

Volume = 0.15x0.25x62
= 2.325 m3

2. Pekerjaan Pembesian Kebutuhan besi = 25.575


=2.325 x 110 kg
= 183.7 kg
Dalam analisa setiap 10kg.
Maka =255.75:10= 25.575

3. Pekerjaan Pasang Bekesting Panjang = 62 m 24.8 m2


Lebar = 2x0.20= 0.40

Luas=0.40x62=24.8m2

4. Pekerjaan Bongkar Bekesting 24.8 m2

5. Pekerjaan Beton Kolom Jumah kolom = 25 buah 2.8125 m3


Penampang = 0.15x0.25
Tinggi kolom = 3 m
Volume =
25x0.15x0.25x3= 2.8125 m3
6. Pekerjaan Pembesian Kebutuhan besi = 30.9375
=2.8125 x 110 kg
= 309.375 kg
Dalam analisa setiap 10kg.
Maka = 309.375:10= 30.9375

7. Pekerjaan Pasang Bekesting Panjang = 62 m 24.8 m2


Lebar = 2x0.20= 0.40

Luas = 0.40x62=24.8m2

8. Pekerjaan Bongkar Bekesting 24.8 m2

9. Pekerjaan Beton Ring Panjang sloof = 62 m 1.86 m3


Penampang = 0.15x0.20

Volume = 0.15x0.20x62
= 1.86 m3

10. Pekerjaan Pembesian Kebutuhan besi = 20.46


=1.86 x 110 kg
= 204.6 kg
Dalam analisa setiap 10kg.
Maka =204.6:10= 20.46

11. Pekerjaan Pasang Bekesting Panjang = 62 m 24.8 m2


Lebar = 2x0.20= 0.40

Luas = 0.40x62=24.8 m2
12. Pekerjaan Bongkar Bekesting 24.8 m2

V PEKERJAAN DINDING DAN PLESTERAN


1. Pasangan bata 1Pc ; 2 Ps Kamar mandi. 51.909 m2
Tinggi = 1,25 m
Panjang seluruh =16m
Lebar pintu = 0.82m

Panjang bersih =
= 16-0,82 =15.18 m

Luas = 15.18x1.25 =
= 18.975 m2

Diatas lantai 55 cm.


Tinggi = 0.55 m
Panjang seluruh = 67.1m
Lebar pintu =
= 4 x 0.92 = 2.76m
= 3 x 0.82 = 2.46m
=1x2=2m
2.76+2.46+2=7.22
Panjang bersih =
= 67.1 - 7.22 = 59.88 m

Luas = 59.88x0.55=
= 32.934 m2

Jumlah= 18.975 + 32.934 =


= 51.909 m2

2. Pasangan bata 1Pc ; 6 Ps Tinggi dinding = 3.25 m 126.3609 m2


Panjang seluruh = 62.35 m
Luas seluruh = 3.25x62.35
=202,6375 m2

Dikurangi :
1.Tasram = 51.909 m2
2. Pintu/jendela :
a. Pintu Jendela 1
Jumlah = 1 buah.
Luas = 2.06x2-(0.46x1.08)
= 4.12 - 0.4968
= 3.6232 m2

b. Pintu 1
Jumlah = 4 buah.
Luas = 4x2.06x0.92 =
= 7.5808 m

c. Pintu 2
Jumlah = 3 buah.
Luas =
=3x2.06x0.82 =
= 5.0676 m2
d. Jendela 1
Jumlah = 4 buah.
Luas = 4x1.1x1.54 =
= 6.776 m2

e. Jendela 2
Jumlah = 2 buah.
Luas = 2x1.1x0.60 =
= 1.32 m2

e. Bouwvenlick
Jumlah = 3 buah.
Luas = 0.50x0.8 =
= 0.4 m2

Jml. luas pengurangan =


51.909+3.6232+7.5808+
5.0676+6.776+1.32+0.4
= 76.2766 m2

Luas bersih =
= 202.6375 - 76.2766 =
= 126.3609 m2

3. Pekerjaan plesteran 1Pc ; 2 Ps Satu sisi = 51.909 m2 103.818 m2


Dua sisi = 2x51.909 =
= 103.818 m2

4. Pekerjaan plesteran 1Pc ; 6 Ps Luas satu sisi = 126.3609 m2 252.7818 m2


Dua sisi = 2x126.3909
= 252.7818 m2

5. Pekerjaan Pesteran Sudut Jumlah sudut tembok= 10 169.92 m1


Tinggi = 3.25 m
Panjang = 10 x 3.25
= 32.5 m1

Jmlh pintu jendela 1 = 1 buah


Panjang 1 sisi =
= 2.06+2+1.6+2+0.46
= 8.12 m1

Panjang 2 sisi =
= 8.12 x 2
= 16.24 m1

Jmlh pintu 1 = 4 buah.


Panjang 1 sisi =
= (0.92+2.06) x 2 x 4
= 23.84 m1

Panjang 2 sisi =
= 23,84 x 2
= 47.68 m1

Jmlh pintu 2 = 3 buah.


Panjang 1 sisi =
= (0.82+2.06) x 2 x 3
= 17.28 m1
Panjang 2 sisi =
= 17.28 x 2
= 34.56 m1

Jmlh jendela 1 = 4 buah.


Panjang 1 sisi =
= (1.54+1.1) x 2 x 4
= 21.12 m1
Panjang 2 sisi =
= 21.12 x 2
= 42.24 m1

Jmlh jendela 2 = 2 buah.


Panjang 1 sisi =
= (0.6+1.1) x 2 x 2
= 6.8 m1
Panjang 2 sisi =
= 6.8 x 2
= 13.6 m1

Jmlh Bouwvenlick = 3 buah.


Panjang 1 sisi =
= (0.5+0.8) x 2 x 3
= 7.8 m1
Panjang 2 sisi =
= 7.8 x 2
= 15.6 m1
Panjang plesteran sudut=
16.24+47.68+34.56+42.24+
13.6+15.6
= 169.92 m1

6. Pekerjaan Acian Luas acian = plesteran. 37.95 m2


= 18.975 x 2
= 37.95 m2
VI PEKERJAAN KAYU KACA DAN LANGIT-LANGIT
1. Pekerjaan kosen pintu dan jendela
Jumlah kosen = 1 buah 0.6156 m3
Penampang = 0.06x0.12
Panjang kayu kosen =
(1.6x2)+(2.06x2)+2+1.08 =
= 10.4 m

Volume = 10.4x0.0072
= 0,07488 m3

Jumlah kosen = 4 buah


Penampang = 0.06x0.12
Panjang kayu kosen =
(0.92x1)+(2.06x2)x4 =
= 20.16 m

V0lume = 20.16x0.0072
= 0,145152 m3

Jumlah kosen = 3 buah


Penampang = 0.06x0.12
Panjang kayu kosen =
(0.82x1)+(2.06x2)x3 =
= 14.82 m

V0lume = 14.82x0.0072
= 0,106704 m3
Jumlah kosen = 4 buah
Penampang = 0.06x0.12
Panjang kayu kosen =
(1.54x2)+(1.1x3)x4 =
= 25.52 m

V0lume =25.52x0.0072
= 0,183744 m3

Jumlah kosen = 2 buah


Penampang = 0.06x0.12
Panjang kayu kosen =
(0.6x2)+(1.1x2)x2=
= 6.8 m

Volume =6.8x0.0072
= 0,04896 m3

Jumlah kosen = 3 buah


Penampang = 0.06x0.12
Panjang kayu kosen =
(0.8x2)+(0.5x2)x3=
= 7.8 m

Volume = 7.8x0.0072
= 0,05616 m3

Volume seluruh =
0,07488+0,145152+0,106704+
0,183744+0,04896+0,05616
= 0,6156 m3

2. Pekerjaan daun pintu panil


Jumlah pintu panil = 5 bh 8.24 m2
Luas = 2.06x0.80x5
= 8.24 m2
3. Pekerjaan daun jendela kaca
Jumlah daun kaca = 2 bh 8.94 m2
Luas =2x0.5x1.5
= 1.5 m2

Jumlah = 8 bh
Luas = 0.7x1x8
= 5.6 m2

Jumlah = 2 bh
Luas = 0.5x1x2
= 1 m2

Jumlah = 3 bh
Luas = 0.7x0.4x3
= 0.84 m2

Jumlah seluruh =
1.5+5.6+1+0.84
= 8.94 m2

4. Pekerjaan kuda-kuda
Jumlah kuda-kuda =2 bh 0.398784 m3
Penampang = 0.08x0.12
= 0.0096 m2
Panjang 1 buah =
6.45+4.72+4.72+1.39+1.39+2.1
= 20.77 m

Volume 1 bh =
= 20.77x0.0096
= 0.199392 m3
Volume 2 buah =
= 0.199392x2 =
= 0.398784 m3
5. Pekerjaan Gording
Jumlah = 4 batang 0.805632 m3
Panjang = 20.98 m
Penampang = 0.08x0.12
= 0.0096 m2
Volume = 4x20.98x0.0096
= 0.805632 m3
6. Pekerjaan Plapon
Luas plapon dalam = 74.475 m2
= (5.5x6)+(4.7x3.5)+(6.5x3.85)
= 74,475 m2

7. Pekerjaan Lisplang
Panjang listplank = 50.3 m1
= (12.15x2)+12.35+11.5+1.5+0.65
= 50,3 m1
8. Pekerjaan Papan reuter
Panjjang papan reuter = 46.76 m1
(5.48x4)+(3.96x4)+4.12+4.88
= 46.76

9. Pekerjaan Lis Sudut Plapon


List sudut plapon = 91.3 m1
K.mandi = 9.00 m1
Dapur = 7.5 m1
R.kelg = 20 m1
R.tamu = 12.7 m1
K.tidur = 42.1 m1
Jumlah =
= 91.3 m1
10. Pekerjaan Usuk dan reng
Luas genteng = luas usuk 120.2512 m2

(3.88x7.75)+((4.88+12.63)
x3.87)+(1/2x5.6x2.8)+(7.35
x3.05)-(1/2x5.6x2.8)

120.2512

VI 11. Pekerjaan Genteng


Luas enteng = luas usuk 120.2512 m2
=120.2512 m1
12. Pekerjaan Genteng Bubungan
Panjang bubungan = 46.76 m1
= 46.76 m1

1. Pekerjaan Lantai Keramik 30x30


Luas = (5.5x6)+(4.7x3.5)+ 70.225 m2
(3.85x6.5)+(1.5x2.5)
= 78.225 - 8
= 70.225 m2

2. Pekerjaan Lantai Keramik 20x20


Luas = (1.25x2x2)+(1.5x2) 8 m2
= 8 m2
3. Pekerjaan Dinding Keramik
Tinggi = 1.5 m1 20.31 m2
Panjang = 16 - (3x0.82) =
= 13.54 m1

Luas = 1.5 x 13.54 =


= 20.31 m2

VIII PEKERJAAN CAT-CATAN


4. Pekerjaan Plin Keramik 10x30
Panjang = 84.24 m1
List plapon - pintu

Panjang = 91.3 -((5x0.92)+


(3x0.82))
= 84.24 m2
1. Pekerjaan Cat Tembok
Cat tembok = plesteran 37.95 m2
2. Pekerjaan Cat Kosen
Panjang kosen = 85.5 m1 34.2 m2
Dianggap 4 sisi dicat
= (0.12+0.06)x2= 0.4
Luas cat = 85.5x0.4
= 34.2 m2
3. Pekerjaan Cat Daun Pintu/Jendela
Daun pintu = 12.2 m2 21.14 m2
Daun jendela = 8.94 m2
Jumlah= 12.2+8.94
= 21.14 m2
4. Pekerjaan Cat Lisplank
Panjang listplank = 50.3 m1 21.629 m2
Ukuran papan = 0.03x0.20
Luas cat = 50.3x 0.43
= 21.629 m2

5. Pekerjaan Cat Genteng Cat genteng = luas gnteng 120.2512 m2

6. Pekerjaan Cat Plapon Cat plapon = luas plapon 74.475 m2

IX PEKERJAAN PENGGANTUNG , PENGUNCI DAN KACA


1. Pekerjaan Ensel Pintu
Jumlah daun = 8 buah 24 buah
Setiap daun = 3 buah
Jumlah engsel = 8x3
= 24 buah
2. Pekerjaan Ensel Jendela
Jumlah daun jend = 12 bh 24 buah

Setiap daun = 2 buah


Jumlah engsel = 12 x 2
= 24 buah

3. Pekerjaan Kait Angin


Jumlah daun jend = 12 bh 24 buah

Setiap daun = 2 buah


Jumlah = 12 x 2
= 24 buah

4. Pekerjaan Kunci Tanam


Jumlah daun = 8 buah 8 buah
5. Pekerjaan Grendel
Jumlah daun jend = 12 bh 14 buah
Pintu = 2 buah
Jumlah = 14 daun
Setiap daun = 1 buah
Jumlah = 14 x 1
= 14 buah
6. Pekerjaan Handel Jendela
Jumlah daun jend = 12 bh 12 buah
Setiap daun = 1 buah
Jumlah = 12 x 1
= 12 buah

7. Pekerjaan Kaca
Jumlah daun jend = 2 bh 5.2872 m2
Ukuran kaca = 0.17x0.33
= 0.0561 m2
Setiap daun = 8 buah
Luas = 2x0.0561x8
= 0.8976 m2

Jumlah daun jend = 8 bh


Ukuran kaca = 0.26x0.41
= 0.1066 m2
Setiap daun = 4 buah
Luas = 8x0.1066x4
= 3.4112 m2

Jumlah daun jend = 2 bh


Ukuran kaca = 0.16x0.41
= 0.0656 m2
Setiap daun = 4 buah
Luas = 2x0.0656x4
= 0.5248 m2
Jumlah daun jend = 3 bh
Ukuran kaca = 0.54x0.14
= 0.0756 m2
Setiap daun = 2 buah
Luas = 2x0.0756x3
= 0.4536 m2

Jml luas =0.8976+3.4112+


0.5248+0.4536
= 5.2872 m2

X PEKERJAAN SANITAIR
1. Pekerjaan Bak Mandi
Jumlah = 3 buah. 3
Volume = 0.30 m3
2. Pekerjaan Klosed Jongkok
Jumlah = 3 buah. 3 buah
3. Pekerjaan Bak Dapur
Jumlah = 1 buah. 1 buah
4. Pekerjaan Wastapel
Jumlah = 1 buah. 1 buah
5. Pekerjaan Bak Kontrol
Jumlah = 2 buah. 2 buah
6. Pekerjaan Septiktank
Jumlah = 2 buah. 2 buah
7. Pekerjaan Peresapan
Jumlah = 3 buah. 3 buah
8. Pekerjaan Piap Air Bersih 1/2 "
Panjang=datar+vertikal 19 m1

Panjang datar =
=0.3+4+1.55+0.3
= 6.15 m1

Panjang vertikal =
= 4.3+5.5+0.3+2.15
= 12.25 m1
Jumlah = 6.15+12.25
= 18.4 m1
= 19 m2
9. Pekerjaan Pipa Air Kotor 4 "
Panjang =7.62+8.41+1.5 24 m1
2.55+1.57
= 21.65 m1
= 24 m1

10. Pekerjaan Kran


Jumlah kran = 3 buah 3 buah
11. Pekerjaan Flour Drain
Jumlah = 1 buah 1 buah
166.4
7.15
173.55

5.86
0.3809
6.2409
2.25

52.75
51.7 107.198
61.14
112.84

26.7995
250 150
200 200
250 150
200 200
900 700

1000
1020
1000
150
235
350
200 2.76
3955 2.46
2
3955 7.22
385
350
550
370
5610
150
150
5910
150
200
250
200
6710
400
400 200
125 150
125 300
200 400
150 300
225 300
425 300
370 300
350 250 NV
250 300
200 400
200 300
150 300
235 300
350 4500
200
385
370
350
550
250
225
150
6235
51.909
3.6232
7.5808
5.0676
6.776
1.32
76.2766

2.06
2
1.6
2
0.46
8.12
16.24
47.68
34.56
42.24
13.6
15.6
169.92

10.4
20.16
14.82
25.52
6.8
0.92 7.8
4.12 85.5
5.04
3.08
3.3
6.38

1.2
2.2
3.4

1.6
1
2.6

0.07488
0.145152
0.106704
0.183744
0.04896
0.05616
0.6156
1.5
5.6
1
0.84
8.94
33
16.45
25.025
74.475

24.3
12.35
11.5
1.5
0.65
50.3

21.92
15.84
4.12
4.88
46.76

9
7.5
20
12.7
42.1
91.3
30.07
67.7637
7.84
22.4175
128.0912

7.84

33
16.45
25.025
3.75
78.225

5
3
4.6
2.46
7.06
1.5
5.6
1
0.84
8.94
0.8976
3.4112
0.5248
0.4536
5.2872
HARGA SATUAN UPAH
TAHUN 2017

NO URAIAN PEKERJA SATUAN HARGA SATUAN RP

1 Tukang kayu hari 67,500.00


2 Kepala tukang kayu hari 70,000.00
3 Tukang batu hari 65,000.00
4 Kepala tukang batu hari 70,000.00
5 Tukang besi hari 65,000.00
6 Kepala tukang besi hari 70,000.00
9 Tukang cat hari 65,000.00
10 Kepala tukang cat hari 70,000.00
18 Pekerja Batu hari 56,200.00
19 Pekerja Kayu hari 56,200.00
20 Pekerja Besi hari 56,200.00
19 Mandor Kayu hari 72,500.00
20 Mandor Batu hari 72,500.00
21 Mandor Besi hari 72,500.00
22 Pekerja Cat hari 56,200.00
23 Mandor Cat hari 72,500.00

HARGA SATUAN BAHAN


TAHUN 2017

NO URAIAN PEKERJA SATUAN HARGA SATUAN RP

1 Cat kayu se kualitas Emco biasa kg 65,000


2 Cat Tembok Catylac Biasa kg 26,000
3 Cat dasar meni kayu Jago kg 18,500
4 Cat meni kayu, besi dan genteng kg 16,300
6 Plamur tembok acrilyc kg 45,000
10 Kloset jongkok porselin type CE7 standar bh 145,500
11 Wastafel warna (KIA) set 188,000
12 Floordrain bh 60,000
13 Kran air diameter 3/4" atau 1/2" bh 17,000
17 Genteng paris bh 2,000
18 Nok genteng paris bh 5,500
19 Tegel keramik (20 x 20) m2 48,500
20 Tegel keramik (20 x 25) m2 48,500
21 Tegel keramik 30/30 berglasir m2 50,000
24 Konblok m2 58,000.00
25 Plint keramik 10 x 30 bh 4,000
26 List keramik dinding motif 5/20 bh 5,000
27 Kaso kayu kelas I ukuran 5/7 m1 12,500
28 Lem kayu (putih) Fox kg 25,000
29 Kayu kruing balok m3 6,250,000
30 Kayu kruing papan m3 7,750,000
32 Kayu plepet eternit 1/5 cm m1 10,000
33 Kayu Meranti Papan m3 6,250,000
34 Kayu Meranti Balok m3 5,750,000
35 Papan cetakan / begesteng m3 1,500,000
36 Kayu dolken btg 50,000
37 Bambu apus btg 12,000
38 Besi beton polos kg 12,000
39 Besi beton ulir kg 15,000
40 Paku gording 100 x 4,2 mm kg 16,000
41 Paku usuk 80 x 3,8 mm kg 18,000
42 Paku reng 55 x 3,1 mm kg 18,000
43 Paku plepet 40 x 2,1 mm kg 14,000
44 Paku eternit 20 x 1,5 mm kg 18,000
45 Engsel pintu bh 35,000
46 Engsel jendela bh 25,000
47 Grendel bh 15,000
48 Hak angin bh 17,600
49 Handel bh 10,000
52 Kunci tanam biasa bh 85,000
53 Kunci Tanam Besar bh 160,000
54 Kunci Tanam Kecil bh 125,000
55 Batu belah m3 26,200
56 Pasir pasang m3 267,900
57 Agregat kasar/ Krikil m3 134,000
58 Batu merah bj 750
59 Portland Cement (PC) Gresik kg 780
60 Asbes plat ( 100 x 100 x 0,3 ) lbr 18,000
61 Semen warna kg 12,000
62 Semen putih kg 1,700
64 Kaca bening 5 mm m2 90,000
65 Pipa PVC abu-abu dia. 1/2" Wavin btg 14,000
66 Pipa PVC abu-abu dia. 3/4" Wavin btg 27,000
67 Pipa PVC abu-abu dia. 4" Wavin btg 229,000
68 Air ltr 600.00
69 Jendela nako bh 16,000
70 Seng plat 3" x 6" BJLS 24 lbr 35,000
71 Kayu lapis 122x244x0,4 lbr 62,000
72 Besi strip kg 13,500
73 Seng gelombang 2" - 5" BJLS 24 lbr 58,000
74 Cat dasar meni besi Jago kg 28,000
75 Rumput gebalan m2 10,000
76 Kapur pasang m3 125,000
77 Kawat beton / bindrat kg 15,000
78 Kayu lapis. 122x244x0,9 lbr 120,000
79 Ijuk kg 6,000
80 Buis beton D 80 bh 70,000.00
81 Kayu kelas I ukuran 2/3 m1 3,000
82 Kayu plepet eternit 1/5 cm m1 2,000
83 List kayu profil m1 5,500
84 Plamur kayu Jago kg 27,000
85 Cat dasar undercoat / alkali resisiting primer kg 28,700
86 Cat dinding weathershield Dulux kg 100,000
87 Cat genteng air ICI weathershield kg 100,000
88 Urinoir standar TOTO U 57 set 825,000
89 Bak cuci stainless steel bh 575,000
90 Water drain + asesories set 285,000
91 Seal tape bh 3,250
92 Tegel porselin 11/11 bh 55,000
93 Roll door m2 117,500
94 Kaca bening 3 mm m2 60,500
96 Kunci silinder bh 75,000
97 Tanah Urug m3 65,000
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI TAHUN 2010

PEKERJAAN PERSIAPAN

1.00 m1 Pek. Pengukuran & Pemasangan Bowplank


0.0120 m3 Kayu Meranti Balok @ Rp. 5,750,000.00 69,000.00
0.0070 m3 Kayu Meranti Papan @ Rp. 6,250,000.00 43,750.00
0.0200 kg Paku Biasa 2" - 5" @ Rp. 18,000.00 360.00
0.1000 oh Pekerja Batu @ Rp. 56,200.00 5,620.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0050 oh Mandor Batu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM PPN ) 13,182.50 113,110.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Membersihkan Lapangan dan Perataan


0.1000 oh Pekerja batu @ Rp. 56,200.00 5,620.00
0.0500 oh Mandor batu @ Rp. 72,500.00 3,625.00
JUMLAH ( BELUM PPN ) 9,245.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pembuatan jalan sementara, tebal 25 cm


0.2750 m3 Batu belah @ Rp. 26,200.00 7,205.00
0.0300 m3 Agregat kasar/ Krikil @ Rp. 134,000.00 4,020.00
0.0500 m3 Pasir pasang @ Rp. 267,900.00 13,395.00
1.0000 oh Pekerja batu @ Rp. 56,200.00 56,200.00
0.1000 oh Mandor batu @ Rp. 72,500.00 7,250.00
JUMLAH ( BELUM PPN ) 63,450.00 24,620.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pek. Kantor Direksi Keet , dengan lantai plesteran


1.2500 btg Kayu dolken @ Rp. 50,000.00 62,500.00
0.1800 m3 Kayu kruing balok @ Rp. 6,250,000.00 1,125,000.00
0.8500 kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 15,300.00
1.1000 kg Besi Strip @ Rp. 13,500.00 14,850.00
35.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 27,300.00
0.1500 m3 Pasir Pasang @ Rp. 267,900.00 40,185.00
0.1000 m3 Pasir pasang @ Rp. 267,900.00 26,790.00
0.1500 m3 Agregat kasar/ Krikil @ Rp. 134,000.00 20,100.00
30.0000 bh Bata merah @ Rp. 750.00 22,500.00
0.2500 lbr Seng plat 3" x 6" BJLS 24 @ Rp. 35,000.00 8,750.00
0.5000 bh Jendela nako @ Rp. 16,000.00 8,000.00
0.0800 m2 Kaca bening 5 mm @ Rp. 90,000.00 7,200.00
0.1500 bh Kunci tanam biasa @ Rp. 85,000.00 12,750.00
0.0600 lbr Kayu lapis 122x244x0,4 @ Rp. 62,000.00 3,720.00
2.0000 oh Pekerja Batu @ Rp. 56,200.00 112,400.00
2.0000 oh Tukang kayu @ Rp. 67,500.00 135,000.00
1.0000 oh Tukang batu @ Rp. 65,000.00 65,000.00
0.3000 oh Kepala tukang Kayu @ Rp. 70,000.00 21,000.00
0.0500 oh Mandor Kayu @ Rp. 72,500.00 3,625.00
JUMLAH ( BELUM PPN ) 337,025.00 1,394,945.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Pagar Sementara dari Seng Gelombang tinggi 2 m


1.2500 btg Kayu dolken @ Rp. 50,000.00 62,500.00
2.5000 Kg Portland Cement (PC) Gresik @ Rp. 780.00 1,950.00
1.2000 lbr Seng gelombang 2" - 5" BJLS 24 @ Rp. 58,000.00 69,600.00
0.0050 m3 Pasir pasang @ Rp. 267,900.00 1,339.50
0.0090 m3 Agregat kasar/ Krikil @ Rp. 134,000.00 1,206.00
0.0720 m3 Kayu Meranti Balok @ Rp. 5,750,000.00 414,000.00
0.0600 Kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 1,080.00
0.4500 kg Cat dasar meni besi Jago @ Rp. 28,000.00 12,600.00
0.4000 oh Pekerja Kayu @ Rp. 56,200.00 22,480.00
0.2000 oh Tukang kayu @ Rp. 67,500.00 13,500.00
0.0200 oh Kepala tukang Kayu @ Rp. 70,000.00 1,400.00
0.0200 oh Mandor Kayu @ Rp. 72,500.00 1,450.00
JUMLAH ( BELUM PPN ) 38,830.00 564,275.50
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Menggali tanah biasa sedalam 1 meter


0.7500 oh Pekerja Batu @ Rp. 56,200.00 56,200.00
0.0250 oh Mandor Batu @ Rp. 72,500.00 54,375.00
JUMLAH ( BELUM PPN ) 110,575.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Menggali tanah biasa sedalam 2 meter


0.9000 oh Pekerja Batu @ Rp. 56,200.00 56,200.00
0.0450 oh Mandor Batu @ Rp. 72,500.00 65,250.00
JUMLAH ( BELUM PPN ) 121,450.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Urug kembali bekas galian


0.1920 oh Pekerja Batu @ Rp. 56,200.00 10,790.40
0.0190 oh Mandor Batu @ Rp. 72,500.00 1,377.50
JUMLAH ( BELUM PPN ) 12,167.90
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Membuang tanah sejauh 150 meter


0.5160 oh Pekerja Batu @ Rp. 56,200.00 28,999.20
0.0500 oh Mandor Batu @ Rp. 72,500.00 3,625.00
JUMLAH ( BELUM PPN ) 32,624.20
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Mengurug tanh urug


1.2000 m3 Tanah Urug @ Rp. 65,000.00 78,000.00
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.0100 oh Mandor Batu @ Rp. 72,500.00 725.00
JUMLAH ( BELUM PPN ) 17,585.00 78,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Mengurug pasir urug


1.2000 m3 Pasir pasang @ Rp. 267,900.00 321,480.00
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.0100 oh Mandor Batu @ Rp. 72,500.00 725.00
JUMLAH ( BELUM PPN ) 17,585.00 321,480.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Gebalan rumput


0.2000 btg Bambu apus @ Rp. 12,000.00 2,400.00
1.0000 m2 Rumput gebalan @ Rp. 10,000.00 10,000.00
0.5000 oh Pekerja Batu @ Rp. 56,200.00 28,100.00
0.0250 oh Mandor Batu @ Rp. 72,500.00 1,812.50
JUMLAH ( BELUM PPN ) 29,912.50 12,400.00
JASA 10 %
JUMLAH
DIBULATKAN

PEKERJAAN PONDASI

1.00 m3 Memasang pondasi batu belah, campuran 1 PC : 6 PP


1.2000 m3 Batu belah @ Rp. 26,200.00 31,440.00
117.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 91,260.00
0.5610 m3 Pasir Pasang @ Rp. 267,900.00 150,291.90
1.5000 oh Pekerja Batu @ Rp. 72,500.00 108,750.00
0.7500 oh Tukang batu @ Rp. 65,000.00 48,750.00
0.0750 oh Kepala tukang @ Rp. 70,000.00 5,250.00
0.0750 oh Mandor Batu @ Rp. 72,500.00 5,437.50
JUMLAH ( BELUM PPN ) 168,187.50 272,991.90
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Memasang batu kosong (aanstamping)


1.2000 m3 Batu belah @ Rp. 26,200.00 31,440.00
0.4320 m3 Kapur pasang @ Rp. 267,900.00 115,732.80
0.7800 oh Pekerja Batu @ Rp. 56,200.00 43,836.00
0.3900 oh Tukang batu @ Rp. 65,000.00 25,350.00
0.0390 oh Kepala tukang batu @ Rp. 70,000.00 2,730.00
0.0390 oh Mandor Batu @ Rp. 72,500.00 2,827.50
JUMLAH ( BELUM PPN ) 74,743.50 147,172.80
JASA 10 %
JUMLAH
DIBULATKAN

PEKERJAAN DINDING
1.00 m2 Memasang dinding bata merah , campuran spesi 1 PC : 2 PP
70.0000 bh Bata merah @ Rp. 750.00 52,500.00
18.9500 kg Portland Cement (PC) Gresik @ Rp. 780.00 14,781.00
0.0380 m3 Pasir Pasang @ Rp. 267,900.00 10,180.20
0.3000 oh Pekerja @ Rp. 56,200.00 16,860.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0150 oh Mandor Batu @ Rp. 72,500.00 1,087.50
JUMLAH ( BELUM PPN ) 25,147.50 77,461.20
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang dinding bata merah , campuran spesi 1 PC : 6 PP


70.0000 bh Bata merah @ Rp. 750.00 52,500.00
8.3200 kg Portland Cement (PC) Gresik @ Rp. 780.00 6,489.60
0.0490 m3 Pasir Pasang @ Rp. 267,900.00 13,127.10
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0150 oh Mandor Batu @ Rp. 72,500.00 1,087.50
JUMLAH ( BELUM PPN ) 25,147.50 72,116.70
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang dinding bata merah campuran spesi 1 PC : 3 KP : 10 PP


70.0000 bh Bata merah @ Rp. 750.00 52,500.00
4.5000 kg Portland Cement (PC) Gresik @ Rp. 780.00 3,510.00
0.0500 m3 Pasir Pasang @ Rp. 267,900.00 13,395.00
0.0150 m3 Kapur pasang @ Rp. 125,000.00 1,875.00
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0150 oh Mandor Batu @ Rp. 72,500.00 1,087.50
JUMLAH ( BELUM PPN ) 25,147.50 69,405.00
JASA 10 %
JUMLAH
DIBULATKAN

PEKERJAAN BETON
1.00 m3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
326.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 254,280.00
0.5429 m3 Pasir pasang @ Rp. 267,900.00 145,442.91
0.7622 m3 Agregat kasar/ Krikil @ Rp. 134,000.00 102,134.80
215.0000 Ltr Air @ Rp. 600.00 129,000.00
1.6500 oh Pekerja Batu @ Rp. 56,200.00 92,730.00
0.2750 oh Tukang batu @ Rp. 65,000.00 17,875.00
0.0280 oh Kepala tukang batu @ Rp. 70,000.00 1,960.00
0.0830 oh Mandor Batu @ Rp. 72,500.00 6,017.50
JUMLAH ( BELUM PPN ) 118,582.50 630,857.71
JASA 10 %
JUMLAH
DIBULATKAN

10.00 kg Pembesian dengan besi polos


10.5000 kg Besi beton polos @ Rp. 12,000.00 126,000.00
0.1500 kg Kawat beton / bindrat @ Rp. 15,000.00 2,250.00
0.0700 oh Pekerja Besi @ Rp. 56,200.00 3,934.00
0.0700 oh Tukang besi @ Rp. 65,000.00 4,550.00
0.0070 oh Kepala tukang besi @ Rp. 70,000.00 490.00
0.0040 oh Mandor Besi @ Rp. 72,500.00 290.00
JUMLAH ( BELUM PPN ) 9,264.00 128,250.00
JASA 10 %
JUMLAH
HARGA PER KG

1.00 m2 Cetakan beton / begisting memakai papan


0.0170 m3 Kayu Meranti Balok @ Rp. 5,750,000.00 97,750.00
0.0240 m3 Kayu Meranti Papan @ Rp. 6,250,000.00 150,000.00
0.4000 kg Paku usuk 80 x 3,8 mm @ Rp. 18,000.00 7,200.00
0.2000 oh Pekerja Kayu @ Rp. 56,200.00 11,240.00
0.5000 oh Tukang kayu @ Rp. 67,500.00 33,750.00
0.0500 oh Kepala tukang kayu @ Rp. 70,000.00 3,500.00
0.0100 oh Mandor Kayu @ Rp. 72,500.00 725.00
JUMLAH ( BELUM PPN ) 49,215.00 254,950.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Membongkar cetakan


4.0000 oh Pekerja Kayu @ Rp. 56,200.00 224,800.00
JUMLAH ( BELUM PPN ) 224,800.00
JASA 10 %
JUMLAH
DIBULATKAN

PEKERJAAN PLESTERAN
1.00 m2 Memasang plesteran 1 PC : 2 PP, tebal 15 mm
10.2240 kg Portland Cement (PC) Gresik @ Rp. 780.00 7,974.72
0.0200 m3 Pasir Pasang @ Rp. 267,900.00 5,358.00
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.1500 oh Tukang batu @ Rp. 65,000.00 9,750.00
0.0150 oh Kepala tukang batu @ Rp. 70,000.00 1,050.00
0.0150 oh Mandor Batu @ Rp. 72,500.00 1,087.50
JUMLAH ( BELUM TERMASUK PPN ) 28,747.50 13,332.72
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang plesteran 1 PC : 6 PP, tebal 15 mm


4.4160 kg Portland Cement (PC) Gresik @ Rp. 780.00 3,444.48
0.0270 m3 Pasir Pasang @ Rp. 267,900.00 7,233.30
0.3000 oh Pekerja Batu @ Rp. 56,200.00 16,860.00
0.1500 oh Tukang batu @ Rp. 65,000.00 9,750.00
0.0150 oh Kepala tukang batu @ Rp. 70,000.00 1,050.00
0.0150 oh Mandor Batu @ Rp. 72,500.00 1,087.50
JUMLAH ( BELUM PPN ) 28,747.50 10,677.78
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Plesteran skoneng 1 Pc : 2 Ps ( untuk gedung )


0.5000 kg Portland Cement (PC) Gresik @ Rp. 780.00 390.00
0.0020 m3 Pasir pasang @ Rp. 267,900.00 535.80
0.0570 oh Pekerja Batu @ Rp. 56,200.00 3,203.40
0.0380 oh Tukang batu @ Rp. 65,000.00 2,470.00
0.0380 oh Kepala tukang batu @ Rp. 70,000.00 2,660.00
0.0020 oh Mandor Batu @ Rp. 72,500.00 145.00
JUMLAH ( BELUM PPN ) 8,478.40 925.80
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang acian


3.2500 kg Portland Cement (PC) Gresik @ Rp. 780.00 2,535.00
0.2000 oh Pekerja Batu @ Rp. 56,200.00 11,240.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0100 oh Mandor Batu @ Rp. 72,500.00 725.00
JUMLAH ( BELUM PPN ) 7,925.00 13,775.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang lantai keramik ukuran (30 x 30) cm


1.0680 m2 Tegel keramik 30/30 berglasir @ Rp. 50,000.00 53,400.00
10.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 7,800.00
0.0450 m3 Pasir Pasang @ Rp. 267,900.00 12,055.50
1.5000 kg Semen warna @ Rp. 12,000.00 18,000.00
0.7000 oh Pekerja Batu @ Rp. 56,200.00 39,340.00
0.3500 oh Tukang batu @ Rp. 65,000.00 22,750.00
0.0350 oh Kepala tukang batu @ Rp. 70,000.00 2,450.00
0.0350 oh Mandor Batu @ Rp. 72,500.00 2,537.50
JUMLAH ( BELUM PPN ) 67,077.50 91,255.50
JASA 10 %
JUMLAH
DIBULATKAN
1.00 m2 Memasang lantai keramik ukuran (20 x 20) cm
1.0600 m2 Tegel keramik (20 x 20) @ Rp. 48,500.00 51,410.00
10.4000 kg Portland Cement (PC) Gresik @ Rp. 780.00 8,112.00
0.0450 m3 Pasir Pasang @ Rp. 267,900.00 12,055.50
1.6200 kg Semen warna @ Rp. 12,000.00 19,440.00
0.7000 oh Pekerja Batu @ Rp. 56,200.00 39,340.00
0.3500 oh Tukang batu @ Rp. 65,000.00 22,750.00
0.0350 oh Kepala tukang batu @ Rp. 70,000.00 2,450.00
0.0350 oh Mandor Batu @ Rp. 72,500.00 2,537.50
JUMLAH ( BELUM PPN ) 67,077.50 91,017.50
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Pasang plint keramik ukuran 10 x 30 cm


3.5300 bh Plint keramik 10 x 30 @ Rp. 4,000.00 14,120.00
1.6500 kg Portland Cement (PC) Gresik @ Rp. 780.00 1,287.00
0.0032 m3 Pasir pasang @ Rp. 267,900.00 857.28
0.1000 kg Semen warna @ Rp. 267,900.00 26,790.00
0.0900 oh Pekerja Batu @ Rp. 56,200.00 5,058.00
0.0900 oh Tukang batu @ Rp. 65,000.00 5,850.00
0.0090 oh Kepala tukang batu @ Rp. 70,000.00 630.00
0.0050 oh Mandor Batu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM TERMASUK PPN ) 11,900.50 43,054.28
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Pasang keramik dinding ukuran 20 x 25 cm


1.0600 bh Tegel keramik (20 x 25) @ Rp. 48,500.00 51,410.00
9.3000 kg Portland Cement (PC) Gresik @ Rp. 780.00 7,254.00
0.0180 m3 Pasir pasang @ Rp. 100,000.00 1,800.00
1.9400 kg Semen warna @ Rp. 100,000.00 194,000.00
0.9000 oh Pekerja Batu @ Rp. 56,200.00 50,580.00
0.4500 oh Tukang batu @ Rp. 65,000.00 29,250.00
0.0450 oh Kepala tukang batu @ Rp. 70,000.00 3,150.00
0.0450 oh Mandor Batu @ Rp. 3,000.00 135.00
JUMLAH ( BELUM TERMASUK PPN ) 83,115.00 254,464.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400
1.0000 m2 Konblok @ Rp. 58,000.00 58,000.00
0.0500 m3 Pasir urug @ Rp. 267,900.00 13,395.00
0.5000 oh Pekerja Batu @ Rp. 56,200.00 28,100.00
0.2500 oh Tukang batu @ Rp. 65,000.00 16,250.00
0.0250 oh Kepala tukang batu @ Rp. 70,000.00 1,750.00
0.0250 oh Mandor Batu @ Rp. 72,500.00 1,812.50
JUMLAH ( BELUM PPN ) 47,912.50 71,395.00
JASA 10 %
JUMLAH
DIBULATKAN
1.00 m3 Membuat dan memasang kusen pintu dan kusen jendela, kayu kamper
1.2000 m3 Kayu kruing balok @ Rp. 6,250,000.00 7,500,000.00
1.2500 kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 22,500.00
1.0000 kg Lem kayu (putih) Fox @ Rp. 25,000.00 25,000.00
6.0000 oh Pekerja Kayu @ Rp. 56,200.00 337,200.00
18.0000 oh Tukang kayu @ Rp. 67,500.00 1,215,000.00
1.8000 oh Kepala tukang kayu @ Rp. 70,000.00 126,000.00
0.3000 oh Mandor Kayu @ Rp. 72,500.00 21,750.00
JUMLAH ( BELUM PPN ) 1,699,950.00 7,547,500.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Membuat dan memasang daun pintu panel, kayu kamper


0.0400 m3 Kayu kruing papan @ Rp. 7,750,000.00 310,000.00
0.5000 kg Lem kayu (putih) Fox @ Rp. 25,000.00 12,500.00
1.0000 oh Pekerja Kayu @ Rp. 56,200.00 56,200.00
3.0000 oh Tukang kayu @ Rp. 67,500.00 202,500.00
0.3000 oh Kepala tukang kayu @ Rp. 70,000.00 21,000.00
0.0500 oh Mandor Kayu @ Rp. 72,500.00 3,625.00
JUMLAH ( BELUM PPN ) 283,325.00 322,500.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Membuat dan memasang pintu dan jendela kaca, kayu kamper
0.0240 m3 Kayu kruing papan @ Rp. 7,750,000.00 186,000.00
0.3000 kg Lem kayu (putih) Fox @ Rp. 25,000.00 7,500.00
0.8000 oh Pekerja Kayu @ Rp. 56,200.00 44,960.00
2.4000 oh Tukang kayu @ Rp. 67,500.00 162,000.00
0.2400 oh Kepala tukang kayu @ Rp. 70,000.00 16,800.00
0.0400 oh Mandor Kayu @ Rp. 72,500.00 2,900.00
JUMLAH ( BELUM PPN ) 226,660.00 193,500.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Memasang konstruksi kuda-kuda konvensional, kayu kamper bentang 6 meter


1.1000 m3 Kayu kruing balok @ Rp. 6,250,000.00 6,875,000.00
15.0000 kg Besi strip @ Rp. 13,500.00 202,500.00
5.6000 kg Paku gording 100 x 4,2 mm @ Rp. 16,000.00 89,600.00
4.0000 oh Pekerja Kayu @ Rp. 56,200.00 224,800.00
12.0000 oh Tukang kayu @ Rp. 67,500.00 810,000.00
1.2000 oh Kepala tukang kayu @ Rp. 70,000.00 84,000.00
0.2000 oh Mandor Kayu @ Rp. 72,500.00 14,500.00
JUMLAH ( BELUM PPN ) 1,133,300.00 7,167,100.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m3 Memasang konstruksi gordeng, kayu kamper


1.1000 m3 Kayu kruing balok @ Rp. 6,250,000.00 6,875,000.00
15.0000 kg Besi strip @ Rp. 13,500.00 202,500.00
3.0000 kg Paku gording 100 x 4,2 mm @ Rp. 16,000.00 48,000.00
2.4000 oh Pekerja Kayu @ Rp. 56,200.00 134,880.00
7.2000 oh Tukang kayu @ Rp. 67,500.00 486,000.00
0.7200 oh Kepala tukang kayu @ Rp. 70,000.00 50,400.00
0.1200 oh Mandor Kayu @ Rp. 72,500.00 8,700.00
JUMLAH ( BELUM PPN ) 679,980.00 7,125,500.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang usuk kamper 5/7, reng kamper 2/3


2.2000 m1 Kaso kayu kelas I ukuran 5/7 @ Rp. 12,500.00 27,500.00
5.0000 m1 Kayu kelas I ukuran 2/3 @ Rp. 3,000.00 15,000.00
0.1500 kg Paku usuk 80 x 3,8 mm @ Rp. 18,000.00 2,700.00
0.1000 kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 1,800.00
0.1000 oh Pekerja Kayu @ Rp. 56,200.00 5,620.00
0.1000 oh Tukang kayu @ Rp. 67,500.00 6,750.00
0.0100 oh Kepala tukang kayu @ Rp. 70,000.00 700.00
0.0050 oh Mandor Kayu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM PPN ) 13,432.50 47,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Memasang lisplank ukuran (3 x 20) cm, kayu kamper


0.0072 m3 Papan kayu kamper @ Rp. 7,750,000.00 55,800.00
0.0500 kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 900.00
0.1000 oh Pekerja Kayu @ Rp. 56,200.00 5,620.00
0.2000 oh Tukang kayu @ Rp. 67,500.00 13,500.00
0.0250 oh Kepala tukang kayu @ Rp. 70,000.00 1,750.00
0.0050 oh Mandor Kayu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM PPN ) 21,232.50 56,700.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Mengerjakan papan ruiter kayu kamper 2/20


0.0040 m3 Papan kayu kamper @ Rp. 7,750,000.00 31,000.00
0.0200 kg Paku reng 55 x 3,1 mm @ Rp. 18,000.00 360.00
0.0280 oh Pekerja Kayu @ Rp. 56,200.00 1,573.60
0.0800 oh Tukang kayu @ Rp. 67,500.00 5,400.00
0.0080 oh Kepala tukang kayu @ Rp. 70,000.00 560.00
0.0014 oh Mandor Kayu @ Rp. 72,500.00 101.50
JUMLAH 7,635.10 31,360.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kamper memakai plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,250,000.00 75,000.0000
0.0600 kg Paku usuk 80 x 3,8 mm @ Rp. 18,000.00 1,080.0000
1.1000 lbr Asbes plat ( 100 x 100 x 0,3 ) @ Rp. 18,000.00 19,800.0000
2.6000 m1 Kayu plepet eternit 1/5 cm @ Rp. 2,000.00 5,200.0000
0.0100 kg Paku eternit 20 x 1,5 mm @ Rp. 18,000.00 180.0000
0.0100 kg Paku plepet 40 x 2,1 mm @ Rp. 14,000.00 140.0000
0.1800 oh Pekerja Kayu @ Rp. 56,200.00 10,116.0000
0.3200 oh Tukang kayu @ Rp. 67,500.00 21,600.0000
0.0320 oh Kepala tukang kayu @ Rp. 70,000.00 2,240.0000
0.0090 oh Mandor Kayu @ Rp. 72,500.00 652.5000
JUMLAH ( BELUM PPN ) 34,608.50 101,400.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Memasang ist langit-langit kayu profil


1.0500 m1 List kayu profil @ Rp. 5,500.00 5,775.00
0.0100 kg Paku plepet 40 x 2,1 mm @ Rp. 14,000.00 140.00
0.0500 oh Pekerja Kayu @ Rp. 56,200.00 2,810.00
0.0500 oh Tukang kayu @ Rp. 67,500.00 3,375.00
0.0050 oh Kepala tukang kayu @ Rp. 70,000.00 350.00
0.0030 oh Mandor Kayu @ Rp. 72,500.00 217.50
JUMLAH ( BELUM PPN ) 6,752.50 5,915.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pasang genteng paris


25.0000 bh Genteng paris @ Rp. 2,000.00 50,000.00
0.2000 oh Pekerja Batu @ Rp. 56,200.00 11,240.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0100 oh Mandor Batu @ Rp. 72,500.00 725.00
JUMLAH ( BELUM PPN ) 19,165.00 50,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Pasang bubungan genteng paris


5.0000 bh Bubungan genteng paris @ Rp. 5,500.00 27,500.00
0.0152 m3 Kapur pasang @ Rp. 125,000.00 1,900.00
0.0152 m3 Pasir pasang @ Rp. 267,900.00 4,072.08
1.5240 kg Portland Cement (PC) Gresik @ Rp. 780.00 1,188.72
0.4000 oh Pekerja Batu @ Rp. 56,200.00 22,480.00
0.2000 oh Tukang batu @ Rp. 65,000.00 13,000.00
0.0200 oh Kepala tukang batu @ Rp. 70,000.00 1,400.00
0.0200 oh Mandor Batu @ Rp. 72,500.00 1,450.00
JUMLAH ( BELUM PPN ) 38,330.00 34,660.80
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup
0.2000 kg Cat meni kayu, besi dan genteng @ Rp. 16,300.00 3,260.00
0.1500 kg Plamur kayu Jago @ Rp. 27,000.00 4,050.00
0.1700 kg Cat dasar meni kayu Jago @ Rp. 18,500.00 3,145.00
0.3500 kg Cat kayu se kualitas Emco biasa @ Rp. 65,000.00 22,750.00
0.0700 oh Pekerja Cat @ Rp. 56,200.00 3,934.00
0.1050 oh Tukang Cat @ Rp. 65,000.00 6,825.00
0.0040 oh Kepala tukang cat @ Rp. 70,000.00 280.00
0.0025 oh Mandor Cat @ Rp. 72,500.00 181.25
JUMLAH ( BELUM TERMASUK PPN ) 11,220.25 33,205.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Mengecat genteng


0.3600 kg Cat genteng air ICI weathershield @ Rp. 100,000.00 36,000.00
0.0200 oh Pekerja Cat @ Rp. 56,200.00 1,124.00
0.0630 oh Tukang Cat @ Rp. 65,000.00 4,095.00
0.0063 oh Kepala tukang cat @ Rp. 70,000.00 441.00
0.0025 oh Mandor Cat @ Rp. 72,500.00 181.25
JUMLAH ( BELUM PPN ) 5,841.25 36,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pengecatan tembok tidak terlindung dari panas dan hujan


0.1000 kg Cat alkali resisting primer @ Rp. 28,700.00 2,870.00
0.3600 kg Cat ICI Weathershield @ Rp. 100,000.00 36,000.00
0.0630 oh Tukang cat @ Rp. 65,000.00 4,095.00
0.0063 oh Kepala tukang cat @ Rp. 70,000.00 441.00
0.0200 oh Pekerja Cat @ Rp. 56,200.00 1,124.00
0.0025 oh Mandor Cat @ Rp. 72,500.00 181.25
JUMLAH ( BELUM PPN ) 5,841.25 38,870.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang 1Kloset Jongkok Porselen


1.0000 bh Kloset jongkok porselen @ Rp. 145,500.00 145,500.00
6.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 4,680.00
0.0100 m3 Pasir pasang @ Rp. 267,900.00 2,679.00
1.0000 oh Pekerja Batu @ Rp. 56,200.00 56,200.00
1.5000 oh Tukang batu @ Rp. 65,000.00 97,500.00
1.5000 oh Kepala tukang batu @ Rp. 70,000.00 105,000.00
0.1600 oh Mandor Batu @ Rp. 72,500.00 11,600.00
JUMLAH ( BELUM TERMASUK PPN ) 270,300.00 152,859.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang Wastafel


1.0000 bh Wastafel @ Rp. 188,000.00 188,000.00
0.1200 x Harga wastafel (Perlengkapan) @ Rp. 188,000.00 22,560.00
6.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 4,680.00
0.0100 m3 Pasir pasang @ Rp. 267,900.00 2,679.00
1.2000 oh Pekerja Batu @ Rp. 56,200.00 67,440.00
1.4500 oh Tukang batu @ Rp. 65,000.00 94,250.00
0.1500 oh Kepala tukang batu @ Rp. 70,000.00 10,500.00
0.1000 oh Mandor Batu @ Rp. 72,500.00 7,250.00
JUMLAH ( BELUM TERMASUK PPN ) 179,440.00 217,919.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50 cm
150.0000 bh Batu bata @ Rp. 750.00 112,500.00
77.0000 kg Portland Cement (PC) Gresik @ Rp. 780.00 60,060.00
0.1300 m3 Pasir pasang @ Rp. 267,900.00 34,827.00
0.0200 m3 Agregat kasar/ Krikil @ Rp. 134,000.00 2,680.00
2.6000 kg Besi beton polos @ Rp. 12,000.00 31,200.00
0.0900 m3 Pasir beton @ Rp. 267,900.00 24,111.00
1.4200 oh Pekerja Batu @ Rp. 56,200.00 79,804.00
0.4730 oh Tukang batu @ Rp. -
0.0470 oh Kepala tukang batu @ Rp. -
0.0710 oh Mandor Batu @ Rp. -
JUMLAH ( BELUM TERMASUK PPN ) 79,804.00 265,378.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Memasang Pipa PVC tipe AW Ø ½"


1.2000 m1 Pipa PVC abu-abu dia. 1/2" Wavin @ Rp. 14,000.00 16,800.00
0.3500 x Harga pipa (Perlengkapan) @ Rp. 14,000.00 4,900.00
0.0360 oh Pekerja Batu @ Rp. 56,200.00 2,023.20
0.0600 oh Tukang batu @ Rp. 65,000.00 3,900.00
0.0060 oh Kepala tukang batu @ Rp. 70,000.00 420.00
0.0018 oh Mandor Batu @ Rp. 72,500.00 130.50
JUMLAH ( BELUM TERMASUK PPN ) 6,473.70 21,700.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m1 Memasang Pipa PVC tipe AW Ø 4"


1.2000 m1 Pipa PVC abu-abu dia. 4" Wavin @ Rp. 229,000.00 274,800.00
0.3500 x Harga pipa (Perlengkapan) @ Rp. 229,000.00 80,150.00
0.0810 oh Pekerja Batu @ Rp. 56,200.00 4,552.20
0.1350 oh Tukang batu @ Rp. 70,000.00 9,450.00
0.0135 oh Kepala tukang batu @ Rp. 65,000.00 877.50
0.0041 oh Mandor Batu @ Rp. 72,500.00 297.25
JUMLAH ( BELUM TERMASUK PPN ) 15,176.95 354,950.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang Bak Cuci Piring Stainles Steel


1.0000 bh Bak cuci stainless steel @ Rp. 575,000.00 575,000.00
1.0000 set Water drain + asesories @ Rp. 285,000.00 285,000.00
0.0300 oh Pekerja Batu @ Rp. 56,200.00 1,686.00
0.3000 oh Tukang batu @ Rp. 65,000.00 19,500.00
0.0300 oh Kepala tukang batu @ Rp. 70,000.00 2,100.00
0.0015 oh Mandor Batu @ Rp. 72,500.00 108.75
JUMLAH ( BELUM TERMASUK PPN ) 23,394.75 860,000.00
JASA 10 %
JUMLAH
DIBULATKAN
1.00 bh Memasang Kran Ø ¾" atau ½"
1.0000 bh Kran air @ Rp. 17,000.00 17,000.00
0.0250 bh Seal tape @ Rp. 3,250.00 81.25
0.0100 oh Pekerja Batu @ Rp. 56,200.00 562.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0050 oh Mandor Batu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM TERMASUK PPN ) 8,124.50 17,081.25
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang Floor Drain


1.0000 bh Floor drain @ Rp. 60,000.00 60,000.00
0.0100 oh Pekerja Batu @ Rp. 56,200.00 562.00
0.1000 oh Tukang batu @ Rp. 65,000.00 6,500.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0050 oh Mandor Batu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM TERMASUK PPN ) 8,124.50 60,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Memasang bak mandi batu bata volume 0,30 m3


240.0000 bh Batu bata @ Rp. 750.00 180,000.00
120.0000 Kg Portland Cement (PC) Gresik @ Rp. 780.00 93,600.00
0.3000 m3 Pasir pasang @ Rp. 267,900.00 80,370.00
360.0000 bh Porselen (11 x 11) cm @ Rp. 55,000.00 19,800,000.00
6.0000 Kg Semen warna @ Rp. 12,000.00 72,000.00
6.0000 oh Pekerja Batu @ Rp. 56,200.00 337,200.00
3.0000 oh Tukang batu @ Rp. 65,000.00 195,000.00
0.3000 oh Kepala tukang batu @ Rp. 70,000.00 21,000.00
0.3000 oh Mandor Batu @ Rp. 72,500.00 21,750.00
JUMLAH ( BELUM TERMASUK PPN ) 574,950.00 20,225,970.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang kunci Tanam Biasa


1.0000 bh Kunci tanam biasa @ Rp. 85,000.00 85,000.00
0.0100 oh Pekerja Batu @ Rp. 56,200.00 562.00
0.5000 oh Tukang batu @ Rp. 67,500.00 33,750.00
0.0100 oh Kepala tukang batu @ Rp. 70,000.00 700.00
0.0050 oh Mandor Batu @ Rp. 72,500.00 362.50
JUMLAH ( BELUM TERMASUK PPN ) 35,374.50 85,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang kunci Tanam Kamar Mandi


1.0000 bh Kunci Tanam Kecil @ Rp. 125,000.00 125,000.00
0.0050 oh Pekerja Kayu @ Rp. 56,200.00 281.00
0.5000 oh Tukang kayu @ Rp. 67,500.00 33,750.00
0.0050 oh Kepala tukang kayu @ Rp. 70,000.00 350.00
0.0025 oh Mandor Kayu @ Rp. 72,500.00 181.25
JUMLAH ( BELUM TERMASUK PPN ) 34,562.25 125,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang Engsel Pintu


1.0000 bh Engsel pintu @ Rp. 35,000.00 35,000.00
0.0150 oh Pekerja Kayu @ Rp. 56,200.00 843.00
0.1500 oh Tukang kayu @ Rp. 67,500.00 10,125.00
0.0150 oh Kepala tukang kayu @ Rp. 70,000.00 1,050.00
0.0008 oh Mandor Kayu @ Rp. 72,500.00 54.38
JUMLAH ( BELUM TERMASUK PPN ) 12,072.38 35,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang Engsel Jendela Kupu - kupu


1.0000 bh Engsel jendela @ Rp. 25,000.00 25,000.00
0.0100 oh Pekerja Kayu @ Rp. 56,200.00 562.00
0.1000 oh Tukang kayu @ Rp. 67,500.00 6,750.00
0.0100 oh Kepala tukang kayu @ Rp. 70,000.00 700.00
0.0005 oh Mandor Kayu @ Rp. 72,500.00 36.25
JUMLAH ( BELUM TERMASUK PPN ) 8,048.25 25,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang Kait angin


1.0000 bh Hak angin @ Rp. 17,600.00 17,600.00
0.0150 oh Pekerja Kayu @ Rp. 56,200.00 843.00
0.1500 oh Tukang kayu @ Rp. 67,500.00 10,125.00
0.0150 oh Kepala tukang kayu @ Rp. 70,000.00 1,050.00
0.0008 oh Mandor Kayu @ Rp. 72,500.00 54.38
JUMLAH ( BELUM TERMASUK PPN ) 12,072.38 17,600.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 m2 Pasang kaca, tebal 5 mm


1.1000 m2 Kaca bening 3 mm @ Rp. 60,500.00 66,550.00
0.0150 oh Pekerja Kayu @ Rp. 56,200.00 843.00
0.1500 oh Tukang kayu @ Rp. 67,500.00 10,125.00
0.0150 oh Kepala tukang kayu @ Rp. 70,000.00 1,050.00
0.0008 oh Mandor Kayu @ Rp. 72,500.00 54.38
JUMLAH ( BELUM TERMASUK PPN ) 12,072.38 66,550.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang Handel


1.0000 bh Hanndel @ Rp. 10,000.00 10,000.00
0.0150 oh Pekerja Kayu @ Rp. 56,200.00 843.00
0.1500 oh Tukang kayu @ Rp. 67,500.00 10,125.00
0.0150 oh Kepala tukang kayu @ Rp. 70,000.00 1,050.00
0.0008 oh Mandor Kayu @ Rp. 72,500.00 54.38
JUMLAH ( BELUM TERMASUK PPN ) 12,072.38 10,000.00
JASA 10 %
JUMLAH
DIBULATKAN

1.00 bh Pasang Grendel


1.0000 bh Grendel @ Rp. 15,000.00 15,000.00
0.0150 oh Pekerja Kayu @ Rp. 56,200.00 843.00
0.1500 oh Tukang kayu @ Rp. 67,500.00 10,125.00
0.0150 oh Kepala tukang kayu @ Rp. 70,000.00 1,050.00
0.0008 oh Mandor Kayu @ Rp. 72,500.00 54.38
JUMLAH ( BELUM TERMASUK PPN ) 12,072.38 15,000.00
JASA 10 %
JUMLAH
DIBULATKAN
126,292.50
12,629.25
138,921.75

9,245.00
924.50
10,169.50

88,070.00
8,807.00
96,877.00
1,731,970.00
173,197.00
1,905,167.00

603,105.50
60,310.55
663,416.05

110,575.00
11,057.50
121,632.50

121,450.00
12,145.00
133,595.00

12,167.90
1,216.79
13,384.69
32,624.20
3,262.42
35,886.62

95,585.00
9,558.50
105,143.50

339,065.00
33,906.50
372,971.50

42,312.50
4,231.25
46,543.75

441,179.40
44,117.94
485,297.34
221,916.30
22,191.63
244,107.93

102,608.70
10,260.87
112,869.57

97,264.20
9,726.42
106,990.62

94,552.50
9,455.25
104,007.75
749,440.21
74,944.02
824,384.23

137,514.00
13,751.40
151,265.40
15,126.54

304,165.00
30,416.50
334,581.50

224,800.00
22,480.00
247,280.00
42,080.22
4,208.02
46,288.24

39,425.28
3,942.53
43,367.81

9,404.20
940.42
10,344.62

21,700.00
2,170.00
23,870.00

158,333.00
15,833.30
174,166.30
158,095.00
15,809.50
173,904.50

54,954.78
5,495.48
60,450.26
60,450.26

337,579.00
33,757.90
371,336.90
371,336.90

119,307.50
11,930.75
131,238.25
9,247,450.00
924,745.00
10,172,195.00

605,825.00
60,582.50
666,407.50

420,160.00
42,016.00
462,176.00

8,300,400.00
830,040.00
9,130,440.00
7,805,480.00
780,548.00
8,586,028.00

60,432.50
6,043.25
66,475.75

77,932.50
7,793.25
85,725.75

38,995.10
3,899.51
42,894.61
136,008.50
13,600.85
149,609.35

12,667.50
1,266.75
13,934.25

69,165.00
6,916.50
76,081.50

72,990.80
7,299.08
80,289.88
44,425.25
4,442.53
48,867.78

41,841.25
4,184.13
46,025.38

44,711.25
4,471.13
49,182.38

423,159.00
42,315.90
465,474.90

397,359.00
39,735.90
437,094.90

345,182.00
34,518.20
379,700.20

28,173.70
2,817.37
30,991.07

370,126.95
37,012.70
407,139.65

883,394.75
88,339.48
971,734.23
25,205.75
2,520.58
27,726.33

68,124.50
6,812.45
74,936.95

20,800,920.00
2,080,092.00
22,881,012.00

120,374.50
12,037.45
132,411.95
159,562.25
15,956.23
175,518.48

47,072.38
4,707.24
51,779.61

33,048.25
3,304.83
36,353.08

29,672.38
2,967.24
32,639.61

78,622.38
7,862.24
86,484.61
22,072.38
2,207.24
24,279.61

27,072.38
2,707.24
29,779.61
RENCANA ANGGARAN BIAYA TIAP PEKERJAAN

I PEKERJAAN PERSIAPAN
1 173.5 m2 Pembersihan Lokasi @ Rp. 10,169.50 @ Rp. 1,764,408.25
2 29 m1 Pemasangan Bouwplank @ Rp. 138,921.75 @ Rp. 4,028,730.75
3 0 m2 Pembuatan Jalan Sementara @ Rp. 96,877.00 @ Rp. -
4 10.5 m2 Pembuatan Kantor Direksi dan Gudang @ Rp. 1,905,167.00 @ Rp. 20,004,253.50
5 62 m1 Pembuatan Pagar Sementara @ Rp. 663,416.05 @ Rp. 41,131,795.10
JUMLAH @ Rp. 66,929,187.60
DIBLATKAN @ Rp.

II PEKERJAAN TANAH.
1 58.9 m2 Galian Tanah @ Rp. 121,632.50 @ Rp. 7,164,154.25
2 15.5 m1 Urugan Tanah Kembali @ Rp. 13,384.69 @ Rp. 207,462.70
3 22.34 m2 Urugan Tanah Bawah Lantai @ Rp. 105,143.50 @ Rp. 2,348,905.79
4 11.17 m3 Pekerjaan Urug Pasir Bawah lantai @ Rp. 372,971.50 @ Rp. 4,166,091.66
JUMLAH @ Rp. 13,886,614.39
DIBLATKAN @ Rp.

III PEKERJAAN PONDASI


1 9.3 m3 Pemasangan Batu Kosong @ Rp. 244,107.93 @ Rp. 2,270,203.75
2 54.25 m3 Pasangan Batu Kali 1Pc : 6 Ps @ Rp. 485,297.34 @ Rp. 26,327,380.70
JUMLAH @ Rp. 28,597,584.44
DIBLATKAN @ Rp.

IV PEKERJAAN BETON
1 0 m3 Pekerjaan Beton sloof @ Rp. 824,384.23 @ Rp. -
2 25.575 kg Pekerjaan Pembesian @ Rp. 15,126.54 @ Rp. 386,861.26
3 24.8 m2 Pekerjaan Pasang Bekesting @ Rp. 334,581.50 @ Rp. 8,297,621.20
4 24.8 m2 Pekerjaan Bongkar Bekesting @ Rp. 247,280.00 @ Rp. 6,132,544.00
5 2.8125 m3 Pekerjaan Beton Kolom @ Rp. 824,384.23 @ Rp. 2,318,580.65
6 30.9375 kg Pekerjaan Pembesian @ Rp. 15,126.54 @ Rp. 467,977.33
7 24.8 m2 Pekerjaan Pasang Bekesting @ Rp. 334,581.50 @ Rp. 8,297,621.20
8 24.8 m2 Pekerjaan Bongkar Bekesting @ Rp. 247,280.00 @ Rp. 6,132,544.00
9 1.86 m3 Pekerjaan Beton Ring @ Rp. 824,384.23 @ Rp. 1,533,354.67
10 20.46 kg Pekerjaan Pembesian @ Rp. 15,126.54 @ Rp. 309,489.01
11 24.8 m2 Pekerjaan Pasang Bekesting @ Rp. 334,581.50 @ Rp. 8,297,621.20
12 24.8 m2 Pekerjaan Bongkar Bekesting @ Rp. 247,280.00 @ Rp. 6,132,544.00
JUMLAH @ Rp. 48,306,758.52
DIBLATKAN @ Rp.

V PEKERJAAN DINDING DAN PLESTERAN


1 51.909 m3 Pasangan bata 1Pc ; 2 Ps @ Rp. 112,869.57 @ Rp. 5,858,946.51
2 126.3609 m3 Pasangan bata 1Pc ; 6 Ps @ Rp. 106,990.62 @ Rp. 13,519,431.03
3 103.818 m2 Pekerjaan plesteran 1Pc ; 2 Ps @ Rp. 46,288.24 @ Rp. 4,805,552.71
4 252.7818 m2 Pekerjaan plesteran 1Pc ; 6 Ps @ Rp. 43,367.81 @ Rp. 10,962,592.57
5 169.92 m1 Pekerjaan Pesteran Sudut @ Rp. 10,344.62 @ Rp. 1,757,757.83
6 37.95 m2 Pekerjaan Acian @ Rp. 23,870.00 @ Rp. 905,866.50
JUMLAH @ Rp. 37,810,147.15
DIBLATKAN @ Rp.
VI PEKERJAAN KAYU KACA DAN LANGIT-LANGIT
1 0.6156 m3 Pekerjaan kosen pintu dan jendela @ Rp. 10,169,445.00 @ Rp. 6,260,310.34
2 8.24 m2 Pekerjaan daun pintu panil @ Rp. 666,407.50 @ Rp. 5,491,197.80
3 8.94 m2 Pekerjaan daun jendela kaca @ Rp. 462,176.00 @ Rp. 4,131,853.44
4 0.398784 m3 Pekerjaan kuda-kuda @ Rp. 9,130,440.00 @ Rp. 3,641,073.38
5 0.805632 m3 Pekerjaan Gording @ Rp. 8,586,028.00 @ Rp. 6,917,178.91
6 74.475 m2 Pekerjaan Plapon @ Rp. 149,609.35 @ Rp. 11,142,156.34
7 50.3 m1 Pekerjaan Lisplang @ Rp. 85,725.75 @ Rp. 4,312,005.23
8 46.76 m1 Pekerjaan Papan reuter @ Rp. 42,894.61 @ Rp. 2,005,751.96
9 91.3 m2 Pekerjaan Lis Sudut Plapon @ Rp. 13,934.25 @ Rp. 1,272,197.03
10 120.2512 m2 Pekerjaan Usuk dan reng @ Rp. 66,475.75 @ Rp. 7,993,788.71
11 120.2512 m2 Pekerjaan Genteng @ Rp. 76,081.50 @ Rp. 9,148,891.67
12 46.76 m1 Pekerjaan Genteng Bubungan @ Rp. 80,289.88 @ Rp. 3,754,354.79
JUMLAH @ Rp. 66,070,759.60
DIBLATKAN @ Rp.

VII PEKERJAAN KERAMIK


1 70.225 m2 Pekerjaan Lantai Keramik 30x30 @ Rp. 174,166.30 @ Rp. 12,230,828.42
2 8 m2 Pekerjaan Lantai Keramik 20x20 @ Rp. 173,904.50 @ Rp. 1,391,236.00
3 20.31 m2 Pekerjaan Dinding Keramik @ Rp. 371,336.90 @ Rp. 7,541,852.44
4 84.24 m1 Pekerjaan Plin Keramik 10x30 @ Rp. 60,450.26 @ Rp. 5,092,329.73
JUMLAH @ Rp. 26,256,246.59
DIBLATKAN @ Rp.

VIII PEKERJAAN CAT-CATAN


1 37.95 m2 Pekerjaan Cat Tembok @ Rp. 49,182.38 @ Rp. 1,866,471.13
2 34.2 m2 Pekerjaan Cat Kosen @ Rp. 36,206.78 @ Rp. 1,238,271.71
3 21.14 m2 Pekerjaan Cat Daun Pintu/Jendela @ Rp. 36,206.78 @ Rp. 765,411.22
4 21.629 m2 Pekerjaan Cat Lisplank @ Rp. 36,206.78 @ Rp. 783,116.34
5 120.2512 m2 Pekerjaan Cat Genteng @ Rp. 46,025.38 @ Rp. 5,534,606.57
6 74.475 m2 Pekerjaan Cat Plapon @ Rp. 49,182.38 @ Rp. 3,662,857.38
JUMLAH @ Rp. 13,850,734.35
DIBLATKAN @ Rp.

IX PEKERJAAN PENGGANTUNG , PENGUNCI DAN KACA


1 24 bh Pekerjaan Ensel Pintu @ Rp. 51,779.61 @ Rp. 1,242,710.70
2 24 bh Pekerjaan Ensel Jendela @ Rp. 36,353.08 @ Rp. 872,473.80
3 24 bh Pekerjaan Kait Angin @ Rp. 32,639.61 @ Rp. 783,350.70
4 8 bh Pekerjaan Kunci Tanam @ Rp. 132,411.95 @ Rp. 1,059,295.60
5 14 bh Pekerjaan Grendel @ Rp. 29,779.61 @ Rp. 416,914.58
6 12 bh Pekerjaan Handel Jendela @ Rp. 24,279.61 @ Rp. 291,355.35
7 5.2872 m2 Pekerjaan Kaca @ Rp. 86,484.61 @ Rp. 457,261.44
JUMLAH @ Rp. 5,123,362.17
DIBLATKAN @ Rp.

X PEKERJAAN SANITAIR
1 3 bh Pekerjaan Bak Mandi @ Rp. 379,700.20 @ Rp. 1,139,100.60
2 3 bh Pekerjaan Klosed Jongkok @ Rp. 465,474.90 @ Rp. 1,396,424.70
3 1 bh Pekerjaan Bak Dapur @ Rp. 971,734.23 @ Rp. 971,734.23
4 1 bh Pekerjaan Wastapel @ Rp. 437,094.90 @ Rp. 437,094.90
5 2 bh Pekerjaan Bak Kontrol @ Rp. 379,700.20 @ Rp. 759,400.40
6 2 bh Pekerjaan Septiktank @ Rp. @ Rp. -
7 3 bh Pekerjaan Peresapan @ Rp. @ Rp. -
8 19 m1 Pekerjaan Piap Air Bersih 1/2 " @ Rp. 30,991.07 @ Rp. 588,830.33
9 24 m1 Pekerjaan Pipa Air Kotor 4 " @ Rp. 407,139.65 @ Rp. 9,771,351.48
10 3 bh Pekerjaan Kran @ Rp. 27,726.33 @ Rp. 83,178.98
11 1 bh Pekerjaan Flour Drain @ Rp. 74,936.95 @ Rp. 74,936.95
JUMLAH @ Rp. 15,222,052.56
DIBLATKAN @ Rp.
REKAPILTULASI BIAYA

I PEKERJAAN PERSIAPAN RP. 66,929,187.60


II PEKERJAAN TANAH. RP. 13,886,614.39
III PEKERJAAN PONDASI RP. 28,597,584.44
IV PEKERJAAN BETON RP. 48,306,758.52
V PEKERJAAN DINDING DAN PLESTERAN RP. 37,810,147.15
VI PEKERJAAN KAYU KACA DAN LANGIT-LANGIT RP. 66,070,759.60
VII PEKERJAAN KERAMIK RP. 26,256,246.59
VIII PEKERJAAN CAT-CATAN RP. 13,850,734.35
IX PEKERJAAN PENGGANTUNG , PENGUNCI DAN KACA RP. 5,123,362.17
X PEKERJAAN SANITAIR RP. 15,222,052.56
JUMLAH RP. 322,053,447.37
PERHITUNGAN JUMLAH HARI DAN BAHAN

I PEKERJAAN PERSIAPAN
1. Membersihkan Lapangan
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
1 Mandor batu 0.0500 oh 173.5 m2 8.68 6
2 Pekerja batu 0.1000 oh 201.5 m2 20.15 11

2. Pemasangan Bouwplank
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
1 Kayu Meranti Balok 0.0120 m3 0 m1 -
2 Kayu Meranti Papan 0.0070 m3 20 m1 0.14
3 Paku Biasa 2" - 5" 0.0200 kg 20 m1 0.40
4 Pekerja Batu 0.1000 oh 20 m1 2.00
5 Tukang batu 0.1000 oh 20 m1 2.00 2
6 Kepala tukang batu 0.0100 oh 20 m1 0.20 1
7 Mandor Batu 0.0050 oh 20 m1 0.10 1

3. Pembuatan Jalan Sementara


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
1 Batu belah 0.2750 m3 0 m2 -
2 Agregat kasar/ Krikil 0.0300 m3 12 m2 0.36
3 Pasir pasang 0.0500 m3 12 m2 0.60
4 Pekerja batu 1.0000 oh 12 m2 12.00 6
5 Mandor batu 0.1000 oh 12 m2 1.20 1

4. Pembuatan Kantor Direksi dan Gudang


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 3D
TENAGA DAN BAHAN
1 Kayu dolken 1.2500 btg 10.5 m2 13.13
2 Kayu kruing balok 0.1800 m3 10.5 m2 1.89
3 Paku reng 55 x 3,1 mm 0.8500 kg 10.5 m2 8.93
4 Besi Strip 1.1000 kg 10.5 m2 11.55
5 Portland Cement (PC) Gresik 35.0000 kg 10.5 m2 367.50
6 Pasir Pasang 0.1500 m3 10.5 m2 1.58
7 Pasir pasang 0.1000 m3 10.5 m2 1.05
8 Agregat kasar/ Krikil 0.1500 m3 10.5 m2 1.58
9 Bata merah 30.0000 bh 10.5 m2 315.00
10 Seng plat 3" x 6" BJLS 24 0.2500 lbr 10.5 m2 2.63
11 Jendela nako 0.5000 bh 10.5 m2 5.25
12 Kaca bening 5 mm 0.0800 m2 10.5 m2 0.84
13 Kunci tanam biasa 0.1500 bh 10.5 m2 1.58
14 Kayu lapis 122x244x0,4 0.0600 lbr 10.5 m2 0.63
15 Pekerja Batu 2.0000 oh 10.5 m2 21.00 6
16 Tukang kayu 2.0000 oh 10.5 m2 21.00 6
17 Tukang batu 1.0000 oh 10.5 m2 10.50 3
18 Kepala tukang Kayu 0.3000 oh 10.5 m2 3.15 1
19 Mandor Kayu 0.0500 oh 10.5 m2 0.53 1

5. Pembuatan Pagar Sementara


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 4D
TENAGA DAN BAHAN
Kayu dolken 1.2500 btg 62 m1 77.50
Portland Cement (PC) Gresik 2.5000 Kg 57 m1 142.50
Seng gelombang 2" - 5" BJLS 24 1.2000 lbr 57 m1 68.40
Pasir pasang 0.0050 m3 57 m1 0.29
Agregat kasar/ Krikil 0.0090 m3 57 m1 0.51
Kayu Meranti Balok 0.0720 m3 57 m1 4.10
Paku reng 55 x 3,1 mm 0.0600 Kg 57 m1 3.42
Cat dasar meni besi Jago 0.4500 kg 57 m1 25.65
Pekerja Kayu 0.4000 oh 57 m1 22.80 6
Tukang kayu 0.2000 oh 57 m1 11.40 3
Kepala tukang Kayu 0.0200 oh 57 m1 1.14 1
Mandor Kayu 0.0200 oh 57 m1 1.14 1

II PEKERJAAN TANAH. `
1. Galian Tanah
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 3D
TENAGA DAN BAHAN
Pekerja Batu 0.7500 oh 58.9 m3 44.18 8
Mandor Batu 0.0250 oh 28.86 m3 0.72 1

2. Urugan Tanah Kembali


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pekerja Batu 0.1920 oh 15.5 m3 2.98 2
Mandor Batu 0.0190 oh 7.22 m3 0.14 1

3.Urugan Tanah Bawah Lantai


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Tanah Urug 1.2000 m3 22.34 m3 26.81
Pekerja Batu 0.3000 oh 15.75 m3 4.73 5
Mandor Batu 0.0100 oh 15.75 m3 0.16 1
4. Pekerjaan Urug Pasir
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pasir Urug 1.2000 m3 11.17 m3 13.40
Pekerja Batu 0.3000 oh 3.15 m3 0.95 1
Mandor Batu 0.0100 oh 3.15 m3 0.03 1

III PEKERJAAN PONDASI


1. Pemasangan Batu Kosong
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 6D
TENAGA DAN BAHAN
Batu belah 1.2000 m3 9.3 m3 11.16
Kapur pasang 0.4320 m3 66.6 m3 28.77
Pekerja Batu 0.7800 oh 66.6 m3 51.95 9
Tukang batu 0.3900 oh 66.6 m3 25.97 5
Kepala tukang batu 0.0390 oh 66.6 m3 2.60 1
Mandor Batu 0.0390 oh 66.6 m3 2.60 1

2. Pasangan Batu Kali 1Pc : 6 Ps


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 4D
TENAGA DAN BAHAN
Batu belah 1.2000 m3 54.25 m3 65.10
Portland Cement (PC) Gresik 117.0000 kg 23.59 m3 2,760.03
Pasir Pasang 0.5610 m3 23.59 m3 13.23
Pekerja Batu 1.5000 oh 23.59 m3 35.39 9
Tukang batu 0.7500 oh 23.59 m3 17.69 5
Kepala tukang 0.0750 oh 23.59 m3 1.77 1
Mandor Batu 0.0750 oh 23.59 m3 1.77 1

IV PEKERJAAN BETON
1. Pekerjaan Beton sloof
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 326.0000 kg 0 m3 -
Pasir pasang 0.5429 m3 1.67 m3 0.91
Agregat kasar/ Krikil 0.7622 m3 1.67 m3 1.27
Air 215.0000 Liter 1.67 m3 359.05
Pekerja Batu 1.6500 oh 1.67 m3 2.76 3
Tukang batu 0.2750 oh 1.67 m3 0.46 1
Kepala tukang batu 0.0280 oh 1.67 m3 0.05 1
Mandor Batu 0.0830 oh 1.67 m3 0.14 1

2. Pekerjaan Pembesian
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Besi beton polos 10.5000 kg 25.575 kg 268.54
Kawat beton / bindrat 0.1500 kg 18.37 kg 2.76
Pekerja Besi 0.0700 oh 18.37 kg 1.29 2
Tukang besi 0.0700 oh 18.37 kg 1.29 2
Kepala tukang besi 0.0070 oh 18.37 kg 0.13 1
Mandor Besi 0.0040 oh 18.37 kg 0.07 1

3. Pekerjaan Pasang Bekesting


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Kayu Meranti Balok 0.0170 m3 24.8 m2 0.42
Kayu Meranti Papan 0.0240 m3 22.2 m2 0.53
Paku usuk 80 x 3,8 mm 0.4000 kg 22.2 m2 8.88
Pekerja Kayu 0.2000 oh 22.2 m2 4.44 3
Tukang kayu 0.5000 oh 22.2 m2 11.10 6
Kepala tukang kayu 0.0500 oh 22.2 m2 1.11 1
Mandor Kayu 0.0100 oh 22.2 m2 0.22 1

4. Pekerjaan Bongkar Bekesting


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pekerja Kayu 4.0000 oh 24.8 m2 99.20 7

5. Pekerjaan Beton Kolom


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 326.0000 kg 2.8125 m3 916.88
Pasir pasang 0.5429 m3 1.44 m3 0.78
Agregat kasar/ Krikil 0.7622 m3 1.44 m3 1.10
Air 215.0000 Liter 1.44 m3 309.60
Pekerja Batu 1.6500 oh 1.44 m3 2.38 3
Tukang batu 0.2750 oh 1.44 m3 0.40 1
Kepala tukang batu 0.0280 oh 1.44 m3 0.04 1
Mandor Batu 0.0830 oh 1.44 m3 0.12 1

6. Pekerjaan Pembesian
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Besi beton polos 10.5000 kg 30.9375 kg 324.84
Kawat beton / bindrat 0.1500 kg 15.84 kg 2.38
Pekerja Besi 0.0700 oh 15.84 kg 1.11 2
Tukang besi 0.0700 oh 15.84 kg 1.11 2
Kepala tukang besi 0.0070 oh 15.84 kg 0.11 1
Mandor Besi 0.0040 oh 15.84 kg 0.06 1
7. Pekerjaan Pasang Bekesting
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Kayu Meranti Balok 0.0170 m3 24.8 m2 0.42
Kayu Meranti Papan 0.0240 m3 19.2 m2 0.46
Paku usuk 80 x 3,8 mm 0.4000 kg 19.2 m2 7.68
Pekerja Kayu 0.2000 oh 19.2 m2 3.84 2
Tukang kayu 0.5000 oh 19.2 m2 9.60 5
Kepala tukang kayu 0.0500 oh 19.2 m2 0.96 1
Mandor Kayu 0.0100 oh 19.2 m2 0.19 1

8. Pekerjaan Bongkar Bekesting


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pekerja Kayu 4.0000 oh 24.8 m2 99.20 6

9. Pekerjaan Beton Ring


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 326.0000 kg 1.86 m3 606.36
Pasir pasang 0.5429 m3 1.67 m3 0.91
Agregat kasar/ Krikil 0.7622 m3 1.67 m3 1.27
Air 215.0000 Liter 1.67 m3 359.05
Pekerja Batu 1.6500 oh 1.67 m3 2.76 3
Tukang batu 0.2750 oh 1.67 m3 0.46 1
Kepala tukang batu 0.0280 oh 1.67 m3 0.05 1
Mandor Batu 0.0830 oh 1.67 m3 0.14 1

10. Pekerjaan Pembesian


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Besi beton polos 10.5000 kg 20.46 kg 214.83
Kawat beton / bindrat 0.1500 kg 18.37 kg 2.76
Pekerja Besi 0.0700 oh 18.37 kg 1.29
Tukang besi 0.0700 oh 18.37 kg 1.29 2
Kepala tukang besi 0.0070 oh 18.37 kg 0.13 1
Mandor Besi 0.0040 oh 18.37 kg 0.07 1

11. Pekerjaan Pasang Bekesting


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Kayu Meranti Balok 0.0170 m3 24.8 m2 0.42
Kayu Meranti Papan 0.0240 m3 22.2 m2 0.53
Paku usuk 80 x 3,8 mm 0.4000 kg 22.2 m2 8.88
Pekerja Kayu 0.2000 oh 22.2 m2 4.44 3
Tukang kayu 0.5000 oh 22.2 m2 11.10 6
Kepala tukang kayu 0.0500 oh 22.2 m2 1.11 2
Mandor Kayu 0.0100 oh 22.2 m2 0.22 1

12. Pekerjaan Bongkar Bekesting


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
m1 TENAGA DAN BAHAN
Pekerja Kayu 4.0000 oh 24.8 m2 99.20 7

V PEKERJAAN DINDING DAN PLESTERAN


1. Pasangan bata 1Pc ; 2 Ps
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Bata merah 70.0000 bh 51.909 m2 3,633.63
Portland Cement (PC) Gresik 18.9500 kg 16.64 m2 315.33
Pasir Pasang 0.0380 m3 16.64 m2 0.63
Pekerja 0.3000 oh 16.64 m2 4.99 5
Tukang batu 0.1000 oh 16.64 m2 1.66 2
Kepala tukang batu 0.0100 oh 16.64 m2 0.17 1
Mandor Batu 0.0150 oh 16.64 m2 0.25 1

2. Pasangan bata 1Pc ; 6 Ps


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 5D
TENAGA DAN BAHAN
Bata merah 70.0000 bh 126.3609 m2 8,845.26
Portland Cement (PC) Gresik 8.3200 kg 132.1 m2 1,099.07
Pasir Pasang 0.0490 m3 132.1 m2 6.47
Pekerja Batu 0.3000 oh 132.1 m2 39.63 8
Tukang batu 0.1000 oh 132.1 m2 13.21 3
Kepala tukang batu 0.0100 oh 132.1 m2 1.32 1
Mandor Batu 0.0150 oh 132.1 m2 1.98 1

3. Pekerjaan plesteran 1Pc ; 2 Ps


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 5D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 10.2240 kg 103.818 m2 1,061.44
Pasir Pasang 0.0200 m3 33.28 m2 0.67
Pekerja Batu 0.3000 oh 33.28 m2 9.98 2
Tukang batu 0.1500 oh 33.28 m2 4.99 1
Kepala tukang batu 0.0150 oh 33.28 m2 0.50 1
Mandor Batu 0.0150 oh 33.28 m2 0.50 1

4. Pekerjaan plesteran 1Pc ; 6 Ps


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 10D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 4.4160 kg 252.7818 m2 1,116.28
Pasir Pasang 0.0270 m3 264.2 m2 7.13
Pekerja Batu 0.3000 oh 264.2 m2 79.26 8
Tukang batu 0.1500 oh 264.2 m2 39.63 4
Kepala tukang batu 0.0150 oh 264.2 m2 3.96 1
Mandor Batu 0.0150 oh 264.2 m2 3.96 1

5. Pekerjaan Pesteran Sudut


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 0.5000 kg 169.92 m1 84.96
Pasir pasang 0.0020 m3 177.04 m1 0.35
Pekerja Batu 0.0570 oh 177.04 m1 10.09 6
Tukang batu 0.0380 oh 177.04 m1 6.73 4
Kepala tukang batu 0.0380 oh 177.04 m1 6.73 4
Mandor Batu 0.0020 oh 177.04 m1 0.35 1

6. Pekerjaan Acian
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 6D
TENAGA DAN BAHAN
Portland Cement (PC) Gresik 3.2500 kg 37.95 m2 123.34
Pekerja Batu 0.2000 oh 297.48 m2 59.50 10
Tukang batu 0.1000 oh 297.48 m2 29.75 5
Kepala tukang batu 0.0100 oh 297.48 m2 2.97 1
Mandor Batu 0.0100 oh 297.48 m2 2.97 1

VI PEKERJAAN KAYU KACA DAN LANGIT-LANGIT


1. Pekerjaan kosen pintu dan jendela
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Kayu kruing balok 1.2000 m3 0.6156 m3 0.74
Paku reng 55 x 3,1 mm 1.2500 kg 0.712 m3 0.89
Lem kayu (putih) Fox 1.0000 kg 0.712 m3 0.71
Pekerja Kayu 6.0000 oh 0.712 m3 4.27 3
Tukang kayu 18.0000 oh 0.712 m3 12.82 7
Kepala tukang kayu 1.8000 oh 0.712 m3 1.28 1
Mandor Kayu 0.3000 oh 0.712 m3 0.21 1

2. Pekerjaan daun pintu panil


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Kayu kruing papan 0.0400 m3 8.24 m2 0.33
Lem kayu (putih) Fox 0.5000 kg 3.32 m2 1.66
Pekerja Kayu 1.0000 oh 3.32 m2 3.32 2
Tukang kayu 3.0000 oh 3.32 m2 9.96 5
Kepala tukang kayu 0.3000 oh 3.32 m2 1.00 1
Mandor Kayu 0.0500 oh 3.32 m2 0.17 1

3. Pekerjaan daun jendela kaca


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 10D
TENAGA DAN BAHAN
Kayu kruing papan 0.0240 m3 8.94 m2 0.21
Lem kayu (putih) Fox 0.3000 kg 20.26 m2 6.08
Pekerja Kayu 0.8000 oh 20.26 m2 16.21 2
Tukang kayu 2.4000 oh 20.26 m2 48.62 5
Kepala tukang kayu 0.2400 oh 20.26 m2 4.86 1
Mandor Kayu 0.0400 oh 20.26 m2 0.81 1

4. Pekerjaan kuda-kuda
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kayu kruing balok 1.1000 m3 0.398784 m3 0.44
Besi strip 15.0000 kg 0.38 m3 5.70
Paku gording 100 x 4,2 mm 5.6000 kg 0.38 m3 2.13
Pekerja Kayu 4.0000 oh 0.38 m3 1.52 2
Tukang kayu 12.0000 oh 0.38 m3 4.56 5
Kepala tukang kayu 1.2000 oh 0.38 m3 0.46 1
Mandor Kayu 0.2000 oh 0.38 m3 0.08 1

5. Pekerjaan Gording
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kayu kruing balok 1.1000 m3 0.805632 m3 0.89
Besi strip 15.0000 kg 0.51 m3 7.65
Paku gording 100 x 4,2 mm 3.0000 kg 0.51 m3 1.53
Pekerja Kayu 2.4000 oh 0.51 m3 1.22 2
Tukang kayu 7.2000 oh 0.51 m3 3.67 4
Kepala tukang kayu 0.7200 oh 0.51 m3 0.37 1
Mandor Kayu 0.1200 oh 0.51 m3 0.06 1

6. Pekerjaan Plapon
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 6D
TENAGA DAN BAHAN
Kayu kruing balok 0.0120 m3 74.475 m2 0.89
Paku usuk 80 x 3,8 mm 0.0600 kg 92 m2 5.52
Asbes plat ( 100 x 100 x 0,3 ) 1.1000 lbr 92 m2 101.20
Kayu plepet eternit 1/5 cm 2.6000 m1 92 m2 239.20
Paku eternit 20 x 1,5 mm 0.0100 kg 92 m2 0.92
Paku plepet 40 x 2,1 mm 0.0100 kg 92 m2 0.92
Pekerja Kayu 0.1800 oh 92 m2 16.56 3
Tukang kayu 0.3200 oh 92 m2 29.44 5
Kepala tukang kayu 0.0320 oh 92 m2 2.94 1
Mandor Kayu 0.0090 oh 92 m2 0.83 1

7. Pekerjaan Lisplang
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 3D
TENAGA DAN BAHAN
Papan kayu kamper 0.0072 m3 0 m2 -
Paku reng 55 x 3,1 mm 0.0500 kg 41 m2 2.05
Pekerja Kayu 0.1000 oh 41 m2 4.10 2
Tukang kayu 0.2000 oh 41 m2 8.20 3
Kepala tukang kayu 0.0250 oh 41 m2 1.03 1
Mandor Kayu 0.0050 oh 41 m2 0.21 1

8. Pekerjaan Papan reuter


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Papan kayu kamper 0.0040 m3 0 m1 -
Paku reng 55 x 3,1 mm 0.0200 kg 10.5 m1 0.21
Pekerja Kayu 0.0280 oh 10.5 m1 0.29
Tukang kayu 0.0800 oh 10.5 m1 0.84 1
Kepala tukang kayu 0.0080 oh 10.5 m1 0.08 1
Mandor Kayu 0.0014 oh 10.5 m1 0.01 1

9. Pekerjaan Lis Sudut Plapon


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
List kayu profil 1.0500 m1 91.3 m1 95.87
Paku plepet 40 x 2,1 mm 0.0100 kg 55.5 m1 0.56
Pekerja Kayu 0.0500 oh 55.5 m1 2.78 3
Tukang kayu 0.0500 oh 55.5 m1 2.78 3
Kepala tukang kayu 0.0050 oh 55.5 m1 0.28 1
Mandor Kayu 0.0030 oh 55.5 m1 0.17 1

10. Pekerjaan Usuk dan reng


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kaso kayu kelas I ukuran 5/7 2.2000 m1 120.2512 m2 264.55
Kayu kelas I ukuran 2/3 5.0000 m1 105 m2 525.00
Paku usuk 80 x 3,8 mm 0.1500 kg 105 m2 15.75
Paku reng 55 x 3,1 mm 0.1000 kg 105 m2 10.50
Pekerja Kayu 0.1000 oh 105 m2 10.50 11
Tukang kayu 0.1000 oh 105 m2 10.50 11
Kepala tukang kayu 0.0100 oh 105 m2 1.05 2
Mandor Kayu 0.0050 oh 105 m2 0.53 1
11. Pekerjaan Genteng
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 3D
TENAGA DAN BAHAN
Genteng paris 25.0000 bh 120.2512 m2 3,006.28
Pekerja Batu 0.2000 oh 105 m2 21.00 7
Tukang batu 0.1000 oh 105 m2 10.50 4
Kepala tukang batu 0.0100 oh 105 m2 1.05 2
Mandor Batu 0.0100 oh 105 m2 1.05 2

12. Pekerjaan Genteng Bubungan


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Bubungan genteng paris 5.0000 bh 46.76 m1 233.80
Kapur pasang 0.0152 m3 10.5 m1 0.16
Pasir pasang 0.0152 m3 10.5 m1 0.16
Portland Cement (PC) Gresik 1.5240 kg 10.5 m1 16.00
Pekerja Batu 0.4000 oh 10.5 m1 4.20 5
Tukang batu 0.2000 oh 10.5 m1 2.10 3
Kepala tukang batu 0.0200 oh 10.5 m1 0.21 1
Mandor Batu 0.0200 oh 10.5 m1 0.21 1

VII PEKERJAAN KERAMIK


1. Pekerjaan Lantai Keramik 30x30
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 4D
TENAGA DAN BAHAN
Tegel keramik 30/30 berglasir 1.0680 m2 70.225 m2 75.00
Portland Cement (PC) Gresik 10.0000 kg 48 m2 480.00
Pasir Pasang 0.0450 m3 48 m2 2.16
Semen warna 1.5000 kg 48 m2 72.00
Pekerja Batu 0.7000 oh 48 m2 33.60 9
Tukang batu 0.3500 oh 48 m2 16.80 5
Kepala tukang batu 0.0350 oh 48 m2 1.68 2
Mandor Batu 0.0350 oh 48 m2 1.68 2

2. Pekerjaan Lantai Keramik 20x20


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Tegel keramik (20 x 20) 1.0600 m2 8 m2 8.48
Portland Cement (PC) Gresik 10.4000 kg 3 m2 31.20
Pasir Pasang 0.0450 m3 3 m2 0.14
Semen warna 1.6200 kg 3 m2 4.86
Pekerja Batu 0.7000 oh 3 m2 2.10 3
Tukang batu 0.3500 oh 3 m2 1.05 2
Kepala tukang batu 0.0350 oh 3 m2 0.11 1
Mandor Batu 0.0350 oh 3 m2 0.11 1
3. Pekerjaan Dinding Keramik
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Tegel keramik (20 x 20) 1.0600 bh 20.31 m2 21.53
Portland Cement (PC) Gresik 9.3000 kg 9.27 m2 86.21
Pasir pasang 0.0180 m3 9.27 m2 0.17
Semen warna 1.9400 kg 9.27 m2 17.98
Pekerja Batu 0.9000 oh 9.27 m2 8.34 9
Tukang batu 0.4500 oh 9.27 m2 4.17 5
Kepala tukang batu 0.0450 oh 9.27 m2 0.42 1
Mandor Batu 0.0450 oh 9.27 m2 0.42 1

4. Pekerjaan Plin Keramik 10x30


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Plint keramik 10 x 30 3.5300 bh 84.24 m1 297.37
Portland Cement (PC) Gresik 1.6500 kg 51 m1 84.15
Pasir pasang 0.0032 m3 51 m1 0.16
Semen warna 0.1000 kg 51 m1 5.10
Pekerja Batu 0.0900 oh 51 m1 4.59 5
Tukang batu 0.0900 oh 51 m1 4.59 5
Kepala tukang batu 0.0090 oh 51 m1 0.46 1
Mandor Batu 0.0050 oh 51 m1 0.26 1

VIII PEKERJAAN CAT-CATAN


1. Pekerjaan Cat Tembok
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 2D
TENAGA DAN BAHAN
Plamur tembok acrilyc 0.1000 Kg 37.95 m2 3.80
Cat dasar 0.1000 Kg 297.48 m2 29.75
Cat Tembok Catylac Biasa 0.2600 Kg 297.48 m2 77.34
Pekerja Cat 0.0200 oh 297.48 m2 5.95 3
Tukang Cat 0.0630 oh 297.48 m2 18.74 10
Kepala tukang 0.0063 oh 297.48 m2 1.87 2
Mandor Cat 0.0025 oh 297.48 m2 0.74 1

2. Pekerjaan Cat Kosen


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Cat meni kayu, besi dan genteng 0.2000 kg 34.2 m2 6.84
Plamur kayu Jago 0.1500 kg 36.7 m2 5.51
Cat dasar meni kayu Jago 0.1700 kg 36.7 m2 6.24
Cat kayu se kualitas Emco biasa 0.3500 kg 36.7 m2 12.85
Pekerja Cat 0.0700 oh 36.7 m2 2.57 3
Tukang Cat 0.1050 oh 36.7 m2 3.85 4
Kepala tukang cat 0.0040 oh 36.7 m2 0.15 1
Mandor Cat 0.0025 oh 36.7 m2 0.09 1

3. Pekerjaan Cat Daun Pintu/Jendela


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Cat meni kayu, besi dan genteng 0.2000 kg 21.14 m2 4.23
Plamur kayu Jago 0.1500 kg 26.9 m2 4.04
Cat dasar meni kayu Jago 0.1700 kg 26.9 m2 4.57
Cat kayu se kualitas Emco biasa 0.3500 kg 26.9 m2 9.42
Pekerja Cat 0.0700 oh 26.9 m2 1.88 2
Tukang Cat 0.1050 oh 26.9 m2 2.82 3
Kepala tukang cat 0.0040 oh 26.9 m2 0.11 1
Mandor Cat 0.0025 oh 26.9 m2 0.07 1

4. Pekerjaan Cat Lisplank


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Cat meni kayu, besi dan genteng 0.2000 kg 21.629 m2 4.33
Plamur kayu Jago 0.1500 kg 17.63 m2 2.64
Cat dasar meni kayu Jago 0.1700 kg 17.63 m2 3.00
Cat kayu se kualitas Emco biasa 0.3500 kg 17.63 m2 6.17
Pekerja Cat 0.0700 oh 17.63 m2 1.23 2
Tukang Cat 0.1050 oh 17.63 m2 1.85 2
Kepala tukang cat 0.0040 oh 17.63 m2 0.07 1
Mandor Cat 0.0025 oh 17.63 m2 0.04 1

5. Pekerjaan Cat Genteng


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Cat genteng air ICI weathershield 0.3600 kg 120.2512 m2 43.29
Pekerja Cat 0.0200 oh 105 m2 2.10 3
Tukang Cat 0.0630 oh 105 m2 6.62 1
Kepala tukang cat 0.0063 oh 105 m2 0.66 1
Mandor Cat 0.0025 oh 105 m2 0.26 1

6. Pekerjaan Cat Plapon


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Plamur tembok acrilyc 0.1000 Kg 74.475 m2 7.45
Cat dasar 0.1000 Kg 92 m2 9.20
Cat Tembok Catylac Biasa 0.2600 Kg 92 m2 23.92
Pekerja Cat 0.0200 oh 92 m2 1.84 2
Tukang Cat 0.0630 oh 92 m2 5.80 6
Kepala tukang 0.0063 oh 92 m2 0.58 1
Mandor Cat 0.0025 oh 92 m2 0.23 1

IX PEKERJAAN PENGGANTUNG , PENGUNCI DAN KACA


1. Pekerjaan Ensel Pintu
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Engsel pintu 1.0000 bh 24 bh 24.00
Pekerja Kayu 0.0150 oh 9 bh 0.14 1
Tukang kayu 0.1500 oh 9 bh 1.35 2
Kepala tukang kayu 0.0150 oh 9 bh 0.14 1
Mandor Kayu 0.0008 oh 9 bh 0.01 1

2. Pekerjaan Ensel Jendela


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Engsel jendela 1.0000 bh 24 bh 24.00
Pekerja Kayu 0.0100 oh 66 bh 0.66 1
Tukang kayu 0.1000 oh 66 bh 6.60 7
Kepala tukang kayu 0.0100 oh 66 bh 0.66 1
Mandor Kayu 0.0005 oh 66 bh 0.03 1

3. Pekerjaan Kait Angin


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Hak angin 1.0000 bh 24 bh 24.00
Pekerja Kayu 0.0150 oh 33 bh 0.50 1
Tukang kayu 0.1500 oh 33 bh 4.95 5
Kepala tukang kayu 0.0150 oh 33 bh 0.50 1
Mandor Kayu 0.0008 oh 33 bh 0.02 1

4. Pekerjaan Kunci Tanam


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
m1 TENAGA DAN BAHAN
Kunci tanam biasa 1.0000 bh 8 bh 8.00
Pekerja Batu 0.0100 oh 3 bh 0.03 1
Tukang batu 0.5000 oh 3 bh 1.50 2
Kepala tukang batu 0.0100 oh 3 bh 0.03 1
Mandor Batu 0.0050 oh 3 bh 0.02 1

5. Pekerjaan Grendel
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Grendel 1.0000 bh 14 bh 14.00
Pekerja Kayu 0.0150 oh 36 bh 0.54 1
Tukang kayu 0.1500 oh 36 bh 5.40 6
Kepala tukang kayu 0.0150 oh 36 bh 0.54 1
Mandor Kayu 0.0008 oh 36 bh 0.03 1

6. Pekerjaan Handel Jendela


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Handel 1.0000 bh 12 bh 12.00
Pekerja Kayu 0.0150 oh 33 bh 0.50 1
Tukang kayu 0.1500 oh 33 bh 4.95 5
Kepala tukang kayu 0.0150 oh 33 bh 0.50 1
Mandor Kayu 0.0008 oh 33 bh 0.02 1

7. Pekerjaan Kaca
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kaca bening 3 mm 1.1000 m2 5.2872 bh 5.82
Pekerja Kayu 0.0150 oh 12.82 bh 0.19 1
Tukang kayu 0.1500 oh 12.82 bh 1.92 2
Kepala tukang kayu 0.0150 oh 12.82 bh 0.19 1
Mandor Kayu 0.0008 oh 12.82 bh 0.01 1

X PEKERJAAN SANITAIR
1. Pekerjaan Bak Mandi
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Batu bata 240.0000 bh 3 bh 720.00
Portland Cement (PC) Gresik 120.0000 Kg 1 bh 120.00
Pasir pasang 0.3000 m3 1 bh 0.30
Porselen (11 x 11) cm 360.0000 bh 1 bh 360.00
Semen warna 6.0000 Kg 1 bh 6.00
Pekerja Batu 6.0000 oh 1 bh 6.00 6
Tukang batu 3.0000 oh 1 bh 3.00 3
Kepala tukang batu 0.3000 oh 1 bh 0.30 1
Mandor Batu 0.3000 oh 1 bh 0.30 1

2. Pekerjaan Klosed Jongkok


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kloset jongkok porselen 1.0000 bh 3 bh 3.00
Portland Cement (PC) Gresik 6.0000 kg 1 bh 6.00
Pasir pasang 0.0100 m3 1 bh 0.01
Pekerja Batu 1.0000 oh 1 bh 1.00 1
Tukang batu 1.5000 oh 1 bh 1.50 2
Kepala tukang batu 1.5000 oh 1 bh 1.50 2
Mandor Batu 0.1600 oh 1 bh 0.16 1

3. Pekerjaan Bak Dapur


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Bak cuci stainless steel 1.0000 bh 1 bh 1.00
Water drain + asesories 1.0000 set 1 bh 1.00
Pekerja Batu 0.0300 oh 1 bh 0.03 1
Tukang batu 0.3000 oh 1 bh 0.30 1
Kepala tukang batu 0.0300 oh 1 bh 0.03 1
Mandor Batu 0.0015 oh 1 bh 0.00 1

4. Pekerjaan Wastapel
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Wastafel 1.0000 bh 1 bh 1.00
Harga wastafel (Perlengkapan) 0.1200 x 1 bh 0.12
Portland Cement (PC) Gresik 6.0000 kg 1 bh 6.00
Pasir pasang 0.0100 m3 1 bh 0.01
Pekerja Batu 1.2000 oh 1 bh 1.20 2
Tukang batu 1.4500 oh 1 bh 1.45 2
Kepala tukang batu 0.1500 oh 1 bh 0.15 1
Mandor Batu 0.1000 oh 1 bh 0.10 1

5. Pekerjaan Bak Kontrol


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Batu bata 150.0000 bh 2 bh 300.00
Portland Cement (PC) Gresik 77.0000 kg 1 bh 77.00
Pasir pasang 0.1300 m3 1 bh 0.13
Agregat kasar/ Krikil 0.0200 m3 1 bh 0.02
Besi beton polos 2.6000 kg 1 bh 2.60
Pasir beton 0.0900 m3 1 bh 0.09
Pekerja Batu 1.4200 oh 1 bh 1.42 2
Tukang batu 0.4730 oh 1 bh 0.47 1
Kepala tukang batu 0.0470 oh 1 bh 0.05 1
Mandor Batu 0.0710 oh 1 bh 0.07 1

6. Pekerjaan Septiktank
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
2 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -

7. Pekerjaan Peresapan
KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
3 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -
1 bh -

8. Pekerjaan Piap Air Bersih 1/2 "


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pipa PVC . 1/2" Wavin 1.2000 m1 19 m1 22.80
Harga pipa (Perlengkapan) 0.3500 x 36 m1 12.60
Pekerja Batu 0.0360 oh 36 m1 1.30 2
Tukang batu 0.0600 oh 36 m1 2.16 3
Kepala tukang batu 0.0060 oh 36 m1 0.22 1
Mandor Batu 0.0018 oh 36 m1 0.06 1

9. Pekerjaan Pipa Air Kotor 4 "


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Pipa Pvc. 4" Wavin 1.2000 m1 24 m1 28.80
Harga pipa (Perlengkapan) 0.3500 x 24 m1 8.40
Pekerja Batu 0.0810 oh 24 m1 1.94 2
Tukang batu 0.1350 oh 24 m1 3.24 4
Kepala tukang batu 0.0135 oh 24 m1 0.32 1
Mandor Batu 0.0041 oh 24 m1 0.10 1

10. Pekerjaan Kran


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Kran air 1.0000 bh 3 m1 3.00
Seal tape 0.0250 bh 3 m1 0.08
Pekerja Batu 0.0100 oh 3 m1 0.03 1
Tukang batu 0.1000 oh 3 m1 0.30 1
Kepala tukang batu 0.0100 oh 3 m1 0.03 1
Mandor Batu 0.0050 oh 3 m1 0.02 1

11. Pekerjaan Flour Drain


KWANTITAS KEBUTUHAN
NO TENAGA/BAHAN INDEK SATUAN JUMLAH SATUAN DURASI 1D
TENAGA DAN BAHAN
Floor drain 1.0000 bh 1 bh 1.00
Pekerja Batu 0.0100 oh 1 bh 0.01 1
Tukang batu 0.1000 oh 1 bh 0.10 1
Kepala tukang batu 0.0100 oh 1 bh 0.01 1
Mandor Batu 0.0050 oh 1 bh 0.01 1