PERHITUNGAN VOLUME PEKERJAAN

 PEKERJAAN PONDASI
1 Pekerjaan Galian Pondasi

± 0.1 m
0.70 m

Keliling Galian = 2 x 60 = 120 m


Tinggi Galian = 0.80 m
Lebar Galian Bawah = 0.50 m
Perbandingan Miring 4 : 1
χ : 1 = 0.8 : 4
0.80
χ = = 0.2 m
4
Lebar Galian Atas :
= 0.50 + (2 x X)
= 0.5 + (2 x 0.2 )
= 0.9 m
Luas Penampang
0.9 + 0.70
= x 0.80 = 0.64 m²
2
Volume = 0.64 x 120 = 76.8 m³

2 Pekerjaan Urugan Pasir


Panjang Urugan = 120 m
Lebar Urungan = 0.50 m
Tinggi Urungan = 0.1 m
Volume = 120 x 0.50 x 0.1 = 6 m³

3 Pasangan batu kosong


Panjang = 120 m
Lebar = 0.5 m
Tinggi = 0.2 m
Volume = 120 x 0.50 x 0.2 = 12 m³

4 Pasangan Pondasi Batu Kali


Panjang = 120 m
Lebar atas = 0.25 m
Lebar bawah = 0.5 m
Tinggi = 0.75 m
0.25 + 0.5
Volume = x 0.75 x 120
2
= 0.3 x 120
= 33.75 m³

5 Pekerjaan Urugan Tanah Kembali


Volume Galian = 1/4 x Galian
Volume Urugan = 1/4 x 76.8
= 19.2 m³

1
6 Pekerjaan Sloof 20/20
Panjang = 120 m
Volume = 0.20 x 0.20 x 120 = 4.8 m³

7 Pekerjaan Kolom
Jarak Kolom = 4m
Panjang Kolom = 120 m - 8 m = 112 m
Jumlah kolom = 112 : 4 = 28 kolom -1 = 27
Volume = 0.20 x 0.20 x 3.00 x 27 = 3.240 m³

8 Ring Balok 20/20


Panjang Kolom = 120 m - 3 m = 117 m
Volume = 0.20 x 20 x 117 = 468.00 m³

9 Pasangan Batu Bata


Panjang tembok = 117 - 0.2 x 27 = 111.6 m
Volume = 111.6 x 3.00 x 0.12 = 40.176 m³

 PEKERJAAN PLESTERAN TEMBOK


1 Plesteran Tembok
Tebal plesteran = 0.015 m
Tinggi plesteran = 3.00 m
Volume Plesteran Luar Dalam = 4 x 3.00 x 0.015 = 0.18 x 2
= 0.360 m³
Volume 27 Dinding = 0.360 x 27 = 9.72 m³
 PEKERJAAN PEMBESIAN
Untuk 1m³ beton bertulang diperlukan 125 kg besi
Volume Sloof = 4.8 m³
Volume Kolom = 3.240 m³ 476.040 m³
Volume Ring Balk = 468.00 m³
Jadi = 125 x 476.040 = 59505 kg

2
PERHITUNGAN DURASI

Rumus :
V dimana : v = vol. pekerjaan
D =
1/c . N c = Koefisien
N = jumlah tenaga kerja

1 Galian Pondasi (An.A.1)


Volume = 76.8 m³
Dari Analisa SNI untuk 1 m³ galian pondasi biasa dibutuhkan :
0.563 hr Pekerja
0.056 hr Mandor
Penyediaan tenaga kerja rata - rata perhari = 100 orang
76.8
D = = 0.475622 1 hari
1 x 100
0.619
2 Pasangan Pasir Urug (An.A.18)
Volume = 6 m³
Dari Analisa SNI untuk 1 m³ pasir urug dibutuhkan :
1.200 m³ Pasir Urug
0.300 hr Pekerja
0.010 hr Mandor
Penyediaan tenaga kerja rata - rata perhari = 25 orang
6
D = = 0.0744 1 hari
1 x 25
0.310

3 Pasangan Batu Kosong (G.1)


Volume = 12 m³
Dari Analisa SNI untuk 1 m³ pasangan batu dibutuhkan :
0.780 hr Pekerja
0.039 hr Mandor
1.200 m³ Batu Gunung
Penyediaan tenaga kerja rata - rata perhari = 100 orang
12
D = = 0.09828 1 hari
1 x 100
0.819

4 Pasangan Batu Kali


Volume = 33.75 m³
Dari Analisa SNI untuk 1 m³ pasangan batu kali dibutuhkan :
0.750 hr Tukang Batu 1.200 m³ Batu Kali
0.075 hr Kepala Tukang Batu 163.000 zak Semen Potland
1.500 hr Pekerja 0.520 m³ Pasir
0.075 hr Mandor
Penyediaan tenaga kerja rata - rata perhari = 30 orang
33.75
D = = 2.7 3 hari
1 x 30
2.400

3
5 Pekerjaan sloof, kolom, ring balok (An.G.41)
Volume = 476.04 m³
Dari Analisa SNI untuk 1 m³ campuran 1pc : 2psr : 3kr dibutuhkan :
6.000 hr Pekerja 0.820 m³ Kerikil
0.300 hr Mandor 0.520 m³ Pasir
1.000 hr Tukang Batu 6.800 zak Semen Potland
0.100 hr Kepala Tukang
Penyediaan tenaga kerja rata - rata perhari = 50 orang
476.04
D = = 70.45392 71 hari
1 x 50
7.4

6 Pasangan Batu Bata (G.33F)


Volume = 40.18 m³
Dari Analisa SNI untuk 1 m³ pasangan tembok 1/2 bata Camp. 1pc : 1/2 kp : 5ps
1.25 hr Tukang Batu 500 buah Bata
0.125 hr Kepala Tukang 1.972 zak Semen Potland
4.000 hr Pekerja 0.396 m³ Pasir
0.200 hr Mandor 0.040 m³ Kapur
Penyediaan tenaga kerja rata - rata perhari = 30 orang
40.18
D = = 7.46604 8 hari
1 x 30
5.575
7 Pekerjaan Plesteran Tembok (G.50P)
Volume = 9.72 m³
Dari Analisa SNI untuk 1 m³ plesteran Camp. 1pc : 1/2 kp : 5ps
0.120 hr Tukang 0.068 zak Semen Potland
0.012 hr Kepala Tukang 0.014 m³ Pasir
0.300 hr Pekerja
0.015 hr Mandor
Penyediaan tenaga kerja rata - rata perhari = 20 orang
9.72
D = = 0.217242 1 hari
1 x 20
0.447
8 Pekerjaan pembesian (An.spl.V)
Volume = 59505.000 m³
Dari Analis SNI untuk 100 kg/m³ pekerjaan pembesian dibutuhkan :
6.750 hr Tukang Besi 110 kg Besi Beton
2.250 hr Kepala Tukang 2.000 kg Kawat Beton
6.750 hr Pekerja
Penyediaan tenaga kerja rata - rata perhari = 33 orang
59505
D = = 284.0011 285 hari
100 x 33
16
No Kegiatan Jenis Pekerjaan Volume Durasi
1 A Mobilisasi Ls 5 hari
2 A1 Persiapan Ls 5 hari
3 B Pengukuran Ls 5 hari
4 C1 Galian Pondasi 76.8 1 hari
5 C2 Pas.Pasir Urug 6 1 hari
6 D Pas. Batu Kosong 12 1 hari
7 E Pas. Batu Kali 33.75 3 hari
8 F Pas. Sloof/Kolom/Ring Balk 476.04 71 hari
9 G Pas Batu Bata 40.18 8 hari
10 H Plesteran Tembok 9.72 1 hari
11 I Pek Pembesian 59505.000 285 hari
12 J Pengawasan Ls 386 hari
13 A2 Demobilisasi Ls 5 hari

4
5
MENGHITUNG PEMAKAIAN TENAGA KERJA

1 Mobilisasi
Volume = Ls
Durasi = 5 hari
Penyediaan tenaga kerja :
- Pekerja = 5 orang
- Mandor = 1 orang
Jumlah = 6 orang

2 Persiapan
Volume = Ls
Durasi = 2 hari
Penyediaan tenaga kerja :
- Pekerja = 5 orang
- Mandor = 1 orang
Jumlah = 6 orang

3 Galian Pondasi (An.A.1)


Volume = 76.8 m³
Durasi = 1 hari
Kapasitas tenaga kerja
- Pekerja = 1/0.750 Orang = 1.333 m³/org/hari
- Mandor = 1/0.025 Orang = 40 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 76.8 = 57.6 58 orang
1.33 x 1
- Mandor = 76.8 = 1.92 2 orang
40 x 1
Jumlah tenaga kerja 60 orang

4 Pasangan Pasir Urug (An.A.18)


Volume = 6 m³
Durasi = 1 hari
Kapasitas tenaga kerja
- Pekerja = 1/0.300 Orang = 3.333 m³/org/hari
- Mandor = 1/0.001 Orang = 1000 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 6 = 1.8 2 orang
3.33 x 1
- Mandor = 6 = 0.006 1 orang
1000 x 1
Jumlah tenaga kerja 3 orang

5 Pasangan Batu Kosong (G.1)


Volume = 12 m³
Durasi = 1 hari
Kapasitas tenaga kerja
- Pekerja = 1/'5.000 Orang = 0.20 m³/org/hari
- Mandor = 1/0.250 Orang = 4 m³/org/hari

Penyediaan tenaga kerja


- Pekerja = 12 = 60.0 60 orang
0.2 x 1
- Mandor = 12 = 3 3 orang
4 x 1
Jumlah tenaga kerja 63 orang

6
6 Pasangan Batu Kali
Volume = 33.75 m³
Durasi = 3 hari
Kapasitas tenaga kerja
- Pekerja = 1/1.500 Orang = 0.67 m³/org/hari
- Mandor = 1/0.150 Orang = 6.666667 m³/org/hari
- Tukang Batu = 1/0.500 Orang = 2.00 m³/org/hari
- Kepala Tukang. B = 1/0.500 Orang = 2 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 33.75 = 16.875 17 orang
0.67 x 3
- Mandor = 33.75 = 1.688 2 orang
6.67 x 3
- Tukang Batu = 33.75 = 5.6 6 orang
2.00 x 3
- Kepala Tukang = 33.75 = 5.63 6 orang
2 x 3
Jumlah tenaga kerja 31 orang

7 Pekerjaan sloof, kolom, ring balok (An.G.41)


Volume = 476.04 m³
Durasi = 71 hari
Kapasitas tenaga kerja
- Pekerja = 1/6.000 Orang = 0.17 m³/org/hari
- Mandor = 1/0.300 Orang = 3.333333 m³/org/hari
- Kepala Tukang = 1/0.100 Orang = 10.0 m³/org/hari
- Tukang Batu = 1/1.000 Orang = 1 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 476.04 = 40.2 41 orang
0.17 x 71
- Mandor = 476.04 = 2.01 3 orang
3.33 x 71
- Kepala Tukang = 476.04 = 0.67 1 orang
10.0 x 71
- Tukang Batu = 476.04 = 6.70 7 orang
1.0 x 71
Jumlah tenaga kerja 52 orang

8 Pasangan Batu Bata (G.33F)


Volume = 40.18 m³
Durasi = 8 hari
Kapasitas tenaga kerja
- Pekerja = 1/4.000 Orang = 0.250 m³/org/hari
- Mandor = 1/0.200 Orang = 5.000 m³/org/hari
- Kepala Tukang = 1/0.120 Orang = 8.333 m³/org/hari
- Tukang Batu = 1/1.250 Orang = 0.800 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 40.176 = 20.09 21 orang
0.25 x 8
- Mandor = 40.176 = 1.004 2 orang
5 x 8
- Kepala Tukang = 40.176 = 0.603 1 orang
8.3 x 8
- Tukang Batu = 40.176 = 6.28 7 orang
0.8 x 8
Jumlah tenaga kerja 31 orang

7
9 Pekerjaan Plesteran Tembok (G.50P)
Volume = 9.72 m³
Durasi = 1 hari
Kapasitas tenaga kerja
- Pekerja = 1/0.300 Orang = 3.333 m³/org/hari
- Mandor = 1/0.015 Orang = 66.67 m³/org/hari
- Kepala Tukang = 1/0.012 Orang = 83.33 m³/org/hari
- Tukang = 1/0.120 Orang = 8.333 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 9.72 = 2.92 3 orang
3.33 x 1
- Mandor = 9.72 = 0.146 1 orang
67 x 1
- Kepala Tukang = 9.72 = 0.117 1 orang
83.3 x 1
- Tukang = 9.72 = 1.17 2 orang
8.3 x 1
Jumlah tenaga kerja 7 orang
10 Pekerjaan pembesian (An.spl.V))
Volume = 59505.000 kg
Durasi = 285 hari
Kapasitas tenaga kerja
- Pekerja = 100/6.75 Orang = 14.815 m³/org/hari
- Kepala Tukang = 100/2.25 Orang = 44.44 m³/org/hari
- Tukang Besi = 100/6.75 Orang = 14.815 m³/org/hari
Penyediaan tenaga kerja
- Pekerja = 59505 = 14 15 orang
14.8 x 285
- Kepala Tukang = 59505 = 4.70 5 orang
44.4 x 285
- Tukang Besi = 59505 = 14.09328947 15 orang
14.8 x 285
Jumlah tenaga kerja 35 orang

11 Pekerjaan pengawasan
Volume = Ls
Durasi = 386
Penyediaan tenaga kerja
- Pengawas = 10 orang

12 Demobilisasi
Volume = Ls
Durasi = 5 hari
Penyediaan tenaga kerja :
- Pekerja = 20 orang
- Mandor = 1 orang
21 orang
Jumlah tenaga kerja = 21 orang

13 Pengukuran
Volume = Ls
Durasi = 2 hari
Penyediaan tenaga kerja :
- Pekerja = 4 orang
- Mandor = 1 orang
5 orang
Jumlah tenaga kerja = 5 orang

8
URAIAN HARGA SATUAN PEKERJAAN

1 Mobilitas
Harga Satuan ditaksir Rp. 1,000,000.00

2 Persiapan
Harga Satuan ditaksir Rp. 1,000,000.00

3 Pengukuran
Harga Satuan ditaksir Rp. 1,000,000.00

4 Demobilisasi
Harga Satuan ditaksir Rp. 1,000,000.00

5 Galian Pondasi (An.A.1)


Dari Analisa SNI untuk 1 m³ galian pondasi biasa dibutuhkan :
Upah Kerja
0.944 hr Pekerja = Rp 26,400.00 Rp. 24,913.68
0.056 hr Mandor = Rp 36,200.00 Rp. 2,038.06
Rp. 26,951.74

6 Pasangan Pasir Urug (An.A.18)


Dari Analisa SNI untuk 1 m³ pasir urug dibutuhkan :
Upah Kerja
1.200 m³ Pasir Urug = Rp 42,000.00 Rp. 50,400.00
0.300 hr Pekerja = Rp 22,000.00 Rp. 6,600.00
0.010 hr Mandor = Rp 30,000.00 Rp. 300.00
Rp. 57,300.00

7 Pasangan Batu Kosong (G.1)


Dari Analisa SNI untuk 1 m³ pasangan batu dibutuhkan :
Upah Kerja
0.780 hr Pekerja = Rp 22,500.00 Rp. 17,550.00
0.039 hr Mandor = Rp 30,000.00 Rp. 1,170.00
Rp. 18,720.00
Bahan
1.200 m³ Batu Gunung = Rp 39,000.00 Rp. 46,800.00
Rp. 46,800.00

Upah Kerja + Bahan = Rp 18,720.00 + Rp. 46,800.00


= Rp. 65,520.00

9
8 Pasangan Batu Kali
Dari Analisa SNI untuk 1 m³ pasangan batu kali dibutuhkan :
Upah Kerja
0.8 hr Tukang Batu = Rp 35,000.00 Rp. 26,250.00
0.1 hr Kepala Tukang Batu = Rp 40,000.00 Rp. 3,000.00
1.5 hr Pekerja = Rp 22,500.00 Rp. 33,750.00
0.1 hr Mandor = Rp 30,000.00 Rp. 2,250.00
Rp. 65,250.00
Bahan
1.200 m³ Batu Kali = Rp 39,000.00 Rp. 46,800.00
163.000 zakSemen Potland = Rp 31,000.00 Rp. 5,053,000.00
0.520 m³ Pasir = Rp 54,000.00 Rp. 28,080.00
Rp. 5,127,880.00
Upah Kerja + Bahan = Rp 65,250.00 + Rp. 5,127,880.00
= Rp. 5,193,130.00

9 Pekerjaan sloof, kolom, ring balok (An.G.41)


Dari Analisa SNI untuk 1 m³ campuran 1pc : 2psr : 3kr dibutuhkan :
Upah Kerja
6.000 hr Pekerja = Rp 26,400.00 Rp. 158,400.00
0.300 hr Mandor = Rp 36,200.00 Rp. 10,860.00
1.000 hr Tukang Batu = Rp 33,000.00 Rp. 33,000.00
0.100 hr Kepala Tukang = Rp 34,650.00 Rp. 3,465.00
Rp. 205,725.00
Bahan
0.820 m³ Kerikil = Rp 150,000.00 Rp. 123,000.00
0.520 m³ Pasir = Rp 25,000.00 Rp. 13,000.00
6.800 zakSemen Potland = Rp 35,000.00 Rp. 238,000.00
Rp. 374,000.00
Upah Kerja + Bahan = Rp 205,725.00 + Rp. 374,000.00
= Rp. 579,725.00

10 Pasangan Batu Bata (G.33F)


Dari Analisa SNI untuk 1 m³ pasangan tembok 1/2 bata Camp. 1pc : 1/2 kp : 5ps
Upah Kerja
1.3 hr Tukang Batu = Rp 35,000.00 Rp. 43,750.00
0.13 hr Kepala Tukang = Rp 40,000.00 Rp. 5,000.00
4.0 hr Pekerja = Rp 22,500.00 Rp. 90,000.00
0.200 hr Mandor = Rp 30,000.00 Rp. 6,000.00
Rp. 144,750.00
Bahan
500 buah Bata = Rp 300.00 Rp. 150,000.00
1.972 zakSemen Potland = Rp 31,000.00 Rp. 61,132.00
0.396 m³ Pasir = Rp 54,000.00 Rp. 21,384.00
0.040 m³ Kapur = Rp 75,000.00 Rp. 3,000.00
Rp. 235,516.00

Upah Kerja + Bahan = Rp 144,750.00 + Rp. 235,516.00


= Rp. 380,266.00

10
11 Pekerjaan Plesteran Tembok (G.50P)
Dari Analisa SNI untuk 1 m³ plesteran Camp. 1pc : 1/2 kp : 5ps
Upah Kerja
0.120 hr Tukang = Rp 35,000.00 Rp. 4,200.00
0.012 hr Kepala Tukang = Rp 40,000.00 Rp. 480.00
0.300 hr Pekerja = Rp 22,500.00 Rp. 6,750.00
0.015 hr Mandor = Rp 30,000.00 Rp. 450.00
Rp. 11,880.00
Bahan
0.068 zakSemen Potland = Rp 31,000.00 Rp. 2,108.00
0.014 m³ Pasir = Rp 54,000.00 Rp. 756.00
Rp. 2,864.00

Upah Kerja + Bahan = Rp 11,880.00 + Rp. 2,864.00


= Rp. 14,744.00

12 Pekerjaan pembesian (An.spl.V)


Dari Analisa SNI untuk 100 kg/m³ pekerjaan pembesian dibutuhkan :
Upah Kerja
6.750 hr Tukang Besi = Rp 33,000.00 Rp. 222,750.00
2.250 hr Kepala Tukang = Rp 34,650.00 Rp. 77,962.50
6.750 hr Pekerja = Rp 26,400.00 Rp. 178,200.00
Rp. 478,912.50
Bahan
110 kg Besi Beton = Rp 5,000.00 Rp. 550,000.00
2.000 kg Kawat Beton = Rp 13,800.00 Rp. 27,600.00
Rp. 577,600.00

Upah Kerja + Bahan = Rp 478,912.50 + Rp. 577,600.00


= Rp. 1,056,512.50

13 Pembetonan
An.G.41 Untuk 1 m³ Beton Bertulang 1pc : 2Ps : 3kr
Beton Cor
0.820 m³ Kerikil = Rp 80,000.00 Rp. 65,600.00
0.540 m³ Pasir Beton = Rp 90,000.00 Rp. 48,600.00
6.800 zak Semen Pc = Rp 31,000.00 Rp. 210,800.00
(A) ………. Rp. 325,000.00
Upah Kerja
1.000 hr Tukang batu = Rp 35,000.00 Rp. 35,000.00
0.100 hr Kepala tukang = Rp 40,000.00 Rp. 4,000.00
6.000 hr Pekerja = Rp 22,500.00 Rp. 135,000.00
0.300 hr Mandor = Rp 30,000.00 Rp. 9,000.00
(B) ………. Rp. 183,000.00

Upah Kerja + Bahan = Rp 325,000.00 + Rp. 183,000.00


= Rp. 508,000.00

11
Perhitungan RAE, RAM, RAV untuk kondisi BCWS
z Tenaga Kerja Tetap = 200 orang
z Jangka Waktu Proyek = 31 hari
z Sumber Daya yang Tersedia = 31 x 200 = 6200 orang
z Sumber Daya Terjadwal = 18183 orang
z Sumber Daya = 18183 - 200
= 17983 orang
Sehingga
18183
i RAE = 100% = 293.2742
6200 x

17983
i RAM = 100% = 98.9001
18183 x

i RAV = 100% x 54.00% 45.998%

18183
Jadi jumlah tenaga kerja ideal = = 586.5483871 587 orang
31