= 0.5 m² Volume Galian Tanah I PEKERJAAN PERSIAPAN 1.1 Pekerjaan Pembersihan Lapangan Panjang Area = 12.5 m Lebar Area = 8 m Luas Pembersihan = p x l = 12.5 x 8 = 100 m² 1.2 Pekerjaan Pemasangan Bowplank Dimensi Lahan = 12.5 x 8 Panjang Rumah = 7 m Lebar Rumah = 8 m Keliling = 2 x 7 + 8 = 30 m²
II PEKERJAAN TANAH DAN PASANGAN PONDASI
2.1 Pekerjaan Galian Pondasi Menerus Panjang Galian = 105.7 m Lebar Galian = 1 m Tinggi Galian = 1.35 m Volume Galian Pondasi = p x l x t = 105.7 x 1 x 1.35 = 142.6 mᶾ 2.2 Pekerjaan Urugan Pasir Panjang Urugan = 105.7 m Lebar Urugan = 1 m Tinggi Urugan = 0.1 m Volume Urugan Pasir = p x l x t = 105.7 x 1 x 0.1 = 10.57 mᶾ 2.3 Pekerjaan Pasangan Batu Kosong Panjang Pasangan Batu Kosong = 105.7 m Lebar Pasangan Batu Kosong = 1 m Tinggi Pasangan Batu Kosong = 0.2 m Volume Pasangan Batu Kosong = p x l x t = 105.7 x 1 x 0.2 = 21.13 mᶾ 2.4 Pekerjaan Pasangan Batu Kali Panjang Pasangan Batu Kali = 105.7 m Panjang Atas Pasangan Batu kali = 0.25 m Panjang Bawah Pasangan Batu Kali = 0.8 m Tinggi Pasangan Batu kali = 0.95 m Volume Pasangan Batu kali = 52.69 mᶾ
2.5 Pekerjaan Urugan Tanah Kembali
III PEKERJAAN SLOOF 15 X 20 3.1 Pembesian D13 Panjang Sloof = 105.7 m Dimensi Sloof = 0.2 x 0.15 Volume Sloof = 0.2 x 0.15 x 106 = 3.17 mᶾ Volume Bekisting = 0.2 x 105.7 x 2 = 42.26 mᶾ
Volume Pembesian As A (Tulangan Utama)
Panjang Tulangan = Panjang Total D13 = = keliling halaman 39 Keliling bangunan dalam halaman 7.44 keliling luar rumah 37.21 keliling bangunan dalam rumah 22