Anda di halaman 1dari 6

1 Volume Galian Tanah

Luas penampang Galian 0.25 + 0.8 x 0.95 : 2


= 0.5 m²
Volume Galian Tanah
I PEKERJAAN PERSIAPAN
1.1 Pekerjaan Pembersihan Lapangan
Panjang Area = 12.5 m
Lebar Area = 8 m
Luas Pembersihan = p x l
= 12.5 x 8
= 100 m²
1.2 Pekerjaan Pemasangan Bowplank
Dimensi Lahan = 12.5 x 8
Panjang Rumah = 7 m
Lebar Rumah = 8 m
Keliling = 2 x 7 + 8
= 30 m²

II PEKERJAAN TANAH DAN PASANGAN PONDASI


2.1 Pekerjaan Galian Pondasi Menerus
Panjang Galian = 105.7 m
Lebar Galian = 1 m
Tinggi Galian = 1.35 m
Volume Galian Pondasi = p x l x t
= 105.7 x 1 x 1.35
= 142.6 mᶾ
2.2 Pekerjaan Urugan Pasir
Panjang Urugan = 105.7 m
Lebar Urugan = 1 m
Tinggi Urugan = 0.1 m
Volume Urugan Pasir = p x l x t
= 105.7 x 1 x 0.1
= 10.57 mᶾ
2.3 Pekerjaan Pasangan Batu Kosong
Panjang Pasangan Batu Kosong = 105.7 m
Lebar Pasangan Batu Kosong = 1 m
Tinggi Pasangan Batu Kosong = 0.2 m
Volume Pasangan Batu Kosong = p x l x t
= 105.7 x 1 x 0.2
= 21.13 mᶾ
2.4 Pekerjaan Pasangan Batu Kali
Panjang Pasangan Batu Kali = 105.7 m
Panjang Atas Pasangan Batu kali = 0.25 m
Panjang Bawah Pasangan Batu Kali = 0.8 m
Tinggi Pasangan Batu kali = 0.95 m
Volume Pasangan Batu kali = 52.69 mᶾ

2.5 Pekerjaan Urugan Tanah Kembali


III PEKERJAAN SLOOF 15 X 20
3.1 Pembesian D13
Panjang Sloof = 105.7 m
Dimensi Sloof = 0.2 x 0.15
Volume Sloof = 0.2 x 0.15 x 106
= 3.17 mᶾ
Volume Bekisting = 0.2 x 105.7 x 2
= 42.26 mᶾ

Volume Pembesian As A (Tulangan Utama)


Panjang Tulangan =
Panjang Total D13 =
=
keliling halaman 39
Keliling bangunan dalam halaman 7.44
keliling luar rumah 37.21
keliling bangunan dalam rumah 22

105.65