PERHITUNGAN VOLUME PEKERJAAN

PROGRAM : KOTA TANPA KUMUH (KOTAKU)


KEGIATAN : DFAT
LOKASI : KERENG BANGKIRAI
KEGIATAN : JALAN DAN DRAINASE
TAHUN ANGGARAN : 2021

JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase Panjang Lebar Tinggi 40.79 m3
= 111.00 m x 0.70 m x 0.70 m x 75% = 40.79 m3
2 Pek. Dinding Saluran
a. Pek. Pembesian Panjang Berat jenis Jumlah 1,278.42 Kg
Kiri = 111 m x 0.617 kg/m x 5 = 342.44 Kg
Kanan = 111 m x 0.617 kg/m x 5 = 342.44 Kg
= 1.3 m x 0.617 kg/m x 740 = 593.55 Kg

b. Pek, Bekisting Panjang Lebar Sisi 103.60 m2


Kiri = 111.00 m x 0.70 m x 2 m x 1/3 = 51.80 m2
Kanan = 111.00 m x 0.70 m x 2 m x 1/3 = 51.80 m2

c. Cor beton K-225 Panjang Lebar Tebal 15.54 m3


Kiri = 111 m x 0.70 m x 0.10 m = 7.77 m3
Kanan = 111 m x 0.70 m x 0.10 m = 7.77 m3

3 Pek. Lantai saluran


a. Pek. Pembesian Panjang Berat jenis Jumlah 639.21 Kg
= 111 m x 0.617 kg/m x 5 = 342.44 Kg
= 0.65 m x 0.617 kg/m x 740 = 296.78 Kg

b. Plastik Cor Panjang Lebar 77.70 m2


= 111 m x 0.70 = 77.70 m2

c. Cor beton K-225 Panjang Lebar Tebal 7.77 m3


= 111 m x 0.70 m x 0.10 m = 7.77 m3

4 Pek. Penutup saluran


a. Pek. Pembesian Panjang Berat jenis Jumlah 479.41 Kg
= 111 m x 0.617 kg/m x 7 = 479.41 Kg

b. Pek. Bekisting Panjang Lebar 44.40 m2


= 111 m x 1 m x 1/3 = 37.00 m2
Kiri = 111 m x 0.10 m x 1/3 = 3.70 m2
Kanan = 111 m x 0.10 m x 1/3 = 3.70 m2
Vol.
Guiding
c. Cor beton K-225 Panjang Lebar Tebal Block 7.26 m3
= 111 m x 0.70 m x 0.10 m - 0.513 = 7.26 m3

5 Pek. Guiding block di atas cor beton Panjang Lebar 28.50 m2


= 95 m x 0.30 = 28.50 m2

6 Pek. Biopori untuk resapan = 22.00 Bh = 22.00 Bh

7 Pek. Besi untuk handle tutup saluran = 24.00 Bh = 24.00 Bh

II PEKERJAAN JALAN PAVING


A Segmen A Panjang 84 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah Panjang Lebar Sisi 40.30 m2
= 31.00 m x 0.65 m x 2 x = 40.30 m2

2 Pekerjaan Ring Balok 15/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 510.18 Kg
Besi ø 10 = 84.00 m x 0.617 kg/m x 4.00 Bh x 2 = 414.62 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 336.00 Bh x 2 = 95.56 Kg

b. Pek, Bekisting Panjang Lebar Jumlah Bekisting Jumlah sisi 16.80 m2


= 84.00 m x 0.15 m x 2 Bh x 2 x 1/3 = 16.80 m2

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 3.78 m3


= 84.00 m x 0.15 m x 0.15 m x 2 = 3.78 m3

3 Pek. Timbunan Tanah Panjang Lebar Tebal segitiga Jumlah 31.74 m3


= 31.00 m x 2 m x 0.32 m x 2 = 31.74 m3

4 Pek. Kolom praktis 15/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 31.55 Kg
Titik 1 Besi ø 10 = 0.65 m x 0.617 kg/m x 4 Bh x 2 = 3.21 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 4 Bh x 2 = 1.14 Kg
Titik 2 Besi ø 10 = 0.61 m x 0.617 kg/m x 4 Bh x 2 = 3.01 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 4 Bh x 2 = 1.14 Kg
Titik 3 Besi ø 10 = 0.57 m x 0.617 kg/m x 4 Bh x 2 = 2.81 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 4 Besi ø 10 = 0.53 m x 0.617 kg/m x 4 Bh x 2 = 2.62 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 5 Besi ø 10 = 0.49 m x 0.617 kg/m x 4 Bh x 2 = 2.42 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 6 Besi ø 10 = 0.45 m x 0.617 kg/m x 4 Bh x 2 = 2.22 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 7 Besi ø 10 = 0.41 m x 0.617 kg/m x 4 Bh x 2 = 2.02 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 8 Besi ø 10 = 0.37 m x 0.617 kg/m x 4 Bh x 2 = 1.83 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg
Titik 9 Besi ø 10 = 0.34 m x 0.617 kg/m x 4 Bh x 2 = 1.68 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg
Titik 10 Besi ø 10 = 0.30 m x 0.617 kg/m x 4 Bh x 2 = 1.48 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
b Pek, Bekisting Panjang Lebar Jumlah 0.71 m2
Titik 1 = 0.65 m x 0.15 m x 2 Bh x 1/2 = 0.10 m2
Titik 2 = 0.61 m x 0.15 m x 2 Bh x 1/2 = 0.09 m2
Titik 3 = 0.57 m x 0.15 m x 2 Bh x 1/2 = 0.09 m2
Titik 4 = 0.53 m x 0.15 m x 2 Bh x 1/2 = 0.08 m2
Titik 5 = 0.49 m x 0.15 m x 2 Bh x 1/2 = 0.07 m2
Titik 6 = 0.45 m x 0.15 m x 2 Bh x 1/2 = 0.07 m2
Titik 7 = 0.41 m x 0.15 m x 2 Bh x 1/2 = 0.06 m2
Titik 8 = 0.37 m x 0.15 m x 2 Bh x 1/2 = 0.06 m2
Titik 9 = 0.34 m x 0.15 m x 2 Bh x 1/2 = 0.05 m2
Titik 10 = 0.30 m x 0.15 m x 2 Bh x 1/2 = 0.05 m2

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 0.21 m3


Titik 1 = 0.65 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 2 = 0.61 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 3 = 0.57 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 4 = 0.53 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 5 = 0.49 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 6 = 0.45 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 7 = 0.41 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 8 = 0.37 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 9 = 0.34 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 10 = 0.30 m x 0.15 m x 0.15 m x 2 = 0.01 m3

Luas
Guiding
5 Pekerjaan Paving Blok Panjang Lebar Block 141.90 m2
= 84.00 m x 2.00 m - 26.10 = 141.90 m2

6 Pek. Pas Buis Beton 40x100 tebal 5 cm = 2.00 Bh = 2.00 Bh

7 Pek. Guiding Block uk. 30x30 tebal 6 cm Panjang Lebar 25.20 m2


= 84.00 m x 0.30 m = 25.20 m2

B Segmen B Panjang 47 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah Panjang Lebar Sisi 40.30 m2
= 31.00 m x 0.65 m x 2 = 40.30 m2

2 Pekerjaan Ring Balok 15/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 285.46 Kg
Besi ø 10 = 47.00 m x 0.617 kg/m x 4.00 Bh x 2 = 231.99 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 188.00 Bh x 2 = 53.47 Kg

b. Pek, Bekisting Panjang Lebar Jumlah Bekisting Jumlah sisi 9.40 m2


= 47.00 m x 0.15 m x 2 Bh x 2 x 1/3 = 9.40 m2

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 2.12 m3


= 47.00 m x 0.15 m x 0.15 m x 2 = 2.12 m3

3 Pek. Timbunan Tanah Panjang Lebar Tebal segitiga Jumlah 31.74 m3


= 31.00 m x 2 m x 0.32 m x 2 = 31.74 m3

4 Pek. Kolom praktis 15/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 31.55 Kg
Titik 1 Besi ø 10 = 0.65 m x 0.617 kg/m x 4 Bh x 2 = 3.21 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 4 Bh x 2 = 1.14 Kg
Titik 2 Besi ø 10 = 0.61 m x 0.617 kg/m x 4 Bh x 2 = 3.01 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 4 Bh x 2 = 1.14 Kg
Titik 3 Besi ø 10 = 0.57 m x 0.617 kg/m x 4 Bh x 2 = 2.81 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 4 Besi ø 10 = 0.53 m x 0.617 kg/m x 4 Bh x 2 = 2.62 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 5 Besi ø 10 = 0.49 m x 0.617 kg/m x 4 Bh x 2 = 2.42 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 6 Besi ø 10 = 0.45 m x 0.617 kg/m x 4 Bh x 2 = 2.22 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 7 Besi ø 10 = 0.41 m x 0.617 kg/m x 4 Bh x 2 = 2.02 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 3 Bh x 2 = 0.85 Kg
Titik 8 Besi ø 10 = 0.37 m x 0.617 kg/m x 4 Bh x 2 = 1.83 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg
Titik 9 Besi ø 10 = 0.34 m x 0.617 kg/m x 4 Bh x 2 = 1.68 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg
Titik 10 Besi ø 10 = 0.30 m x 0.617 kg/m x 4 Bh x 2 = 1.48 Kg
Besi ø 8 = 0.36 m x 0.395 kg/m x 2 Bh x 2 = 0.57 Kg

b Pek, Bekisting Panjang Lebar Jumlah 0.71 m2


Titik 1 = 0.65 m x 0.15 m x 2 Bh x 1/2 = 0.10 m2
Titik 2 = 0.61 m x 0.15 m x 2 Bh x 1/2 = 0.09 m3
Titik 3 = 0.57 m x 0.15 m x 2 Bh x 1/2 = 0.09 m4
Titik 4 = 0.53 m x 0.15 m x 2 Bh x 1/2 = 0.08 m5
Titik 5 = 0.49 m x 0.15 m x 2 Bh x 1/2 = 0.07 m6
Titik 6 = 0.45 m x 0.15 m x 2 Bh x 1/2 = 0.07 m7
Titik 7 = 0.41 m x 0.15 m x 2 Bh x 1/2 = 0.06 m8
Titik 8 = 0.37 m x 0.15 m x 2 Bh x 1/2 = 0.06 m8
Titik 9 = 0.34 m x 0.15 m x 2 Bh x 1/2 = 0.05 m8
Titik 10 = 0.30 m x 0.15 m x 2 Bh x 1/2 = 0.05 m8

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 0.21 m3


Titik 1 = 0.65 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 2 = 0.61 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 3 = 0.57 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 4 = 0.53 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 5 = 0.49 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 6 = 0.45 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 7 = 0.41 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 8 = 0.37 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 9 = 0.34 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 10 = 0.30 m x 0.15 m x 0.15 m x 2 = 0.01 m3
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
Luas
Guiding
5 Pekerjaan Paving Blok Panjang Lebar Block 79.00 m2
= 47.00 m x 2.00 m - 15.00 = 79.00 m3

6 Pek. Pas Buis Beton 40x100 tebal 5 cm = 4.00 Bh = 4.00 Bh

7 Pek. Guiding Block uk. 30x30 tebal 6 cm Panjang Lebar 14.10 m2


= 47.00 m x 0.30 m = 14.10 m2

C Segmen C Panjang 95 M
1 Pas Dinding Bata Tebal 1/2 Bata pembatas paving Panjang Lebar 33.25 m2
= 95.00 m x 0.35 m = 33.25 m2

2 Pek. Plesteran Panjang Lebar 30.00 m2


= 45.00 m x 0.35 m = 15.75 m2
= 95.00 m x 0.15 m = 14.25 m2

3 Pekerjaan Paving Panjang Lebar 365.75 m2


= 95.00 m x 3.85 m = 365.75 m3

III PEKERJAAN JALAN TITIAN KAYU


1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 Panjang Lebar Tebal Jumlah 1.35 m3
Titian utama (P=71) = 1.30 m x 0.10 m x 0.10 m x 96 Bh = 1.25 m3
Sambungan jln paving (2 Bh) = 1.30 m x 0.10 m x 0.10 m x 8 Bh = 0.10 m3

b Pek Gelagar memanjang Panjang Lebar Tebal Jumlah 1.50 m3


Titian utama (P=71) = 71.00 m x 0.05 m x 0.10 m x 4 Bh = 1.42 m3
Sambungan jln paving (2 Bh) = 2.00 m x 0.05 m x 0.10 m x 8 Bh = 0.08 m3

c Pek. Gelagar melintang Panjang Lebar Tebal Jumlah 0.47 m3


Titian utama (P=71) = 1.80 m x 0.05 m x 0.10 m x 48 Bh = 0.43 m3
Sambungan jln paving (2 Bh) = 1.80 m x 0.05 m x 0.10 m x 4 Bh = 0.04 m3
96
d Pek. Kacapuri Panjang Lebar Tebal Jumlah Jumlah tongkat 0.97 m3
Titian utama (P=71) = 0.50 m x 0.05 m x 0.10 m x 4 x 96 = 0.96 m3
Sambungan jln paving (2 Bh) = 0.50 m x 0.05 m x 0.10 m x 4 x 8 = 0.01 m3

e Pekerjaan sunduk Panjang Lebar Tebal Jumlah Jumlah tongkat 0.24 m3


Titian utama (P=71) = 0.50 m x 0.05 m x 0.10 m x 1 x 96 = 0.24 m3
Sambungan jln paving (2 Bh) = 0.50 m x 0.05 m x 0.10 m x 1 x 8 = 0.00 m3

e Pasangan Mur dan Baut Dia. 10 mm


m10x75mm = 25.00 = 25.00 Kg

2 Pekerjaan Rangka Badan, Lantai dan Railing Panjang Lebar Jumlah 156.80 m2
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Titian utama (P=71) = 2.00 m x 0.20 m x 355.00 keping = 142.00 m2
Klas I, Uk. 2/20 Cm mbungan jln paving (2 Bh) = 2.00 m x 0.20 m x 15.00 keping = 6.00 m2
Tambatan Perahu = 4.00 m x 0.20 m x 9.00 keping = 7.20 m2
= 4.00 m x 0.20 m x 2.00 keping = 1.60 m2

b Pek. Balok Pengunci Lantai Papan uk. 5/7 Panjang Lebar Tebal Jumlah 0.75 m3
Titian utama (P=71) = 71.00 m x 0.05 m x 0.10 m x 2 = 0.71 m3
Sambungan jln paving (2 Bh) = 2.00 m x 0.05 m x 0.10 m x 2 = 0.02 m3
Tambatan Perahu = 2.00 m x 0.05 m x 0.10 m x 2 = 0.02 m3
= 0.35 m x 0.05 m x 0.10 m x 2 = 0.00 m3

c Pekerjaan pagar reling Panjang Lebar Tebal Jumlah 2.74 m3


Tiang pagar uk. 5/10
Titian utama (P=71) 5/10 = 1.20 m x 0.05 m x 0.10 m x 96 = 0.58 m3
Sambungan jln paving (2 Bh) 5/10 = 1.20 m x 0.05 m x 0.10 m x 8 = 0.05 m3
Tambatan Perahu 5/10 = 1.20 m x 0.05 m x 0.10 m x 8 = 0.05 m3

Pagar reling 5/7


Titian utama (P=71) 5/10 = 0.70 m x 0.05 m x 0.10 m x 192 = 0.67 m3
5/10 = 1.15 m x 0.05 m x 0.10 m x 192 = 1.10 m3
Sambungan jln paving (2 Bh) 5/10 = 0.70 m x 0.05 m x 0.10 m x 16 = 0.06 m3
5/10 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3
Tambatan Perahu 5/10 = 0.70 m x 0.05 m x 0.10 m x 16 = 0.06 m3
5/10 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3

3 Pekerjaan Pelitur Reling kayu

a Pek. Pelitur Reling jalan Titian Panjang Lebar Jumlah 138.19 m2


Tiang reling uk. 5/10
Titian utama (P=71) 5/10 = 1.10 m x 0.30 m x x 96 = 31.68 m2
Sambungan jln paving (2 Bh) 5/10 = 1.10 m x 0.30 m x x 8 = 2.64 m2
Tambatan Perahu 5/10 = 1.10 m x 0.30 m x x 8 = 2.64 m2

Pagar reling 5/7


Titian utama (P=71) 5/7 = 0.70 m x 0.24 m x x 192 = 32.26 m2
5/7 = 1.15 m x 0.24 m x x 192 = 52.99 m2
Sambungan jln paving (2 Bh) 5/7 = 0.70 m x 0.24 m x x 16 = 2.69 m2
5/7 = 1.15 m x 0.24 m x x 16 = 4.42 m2
Rest Area 5/7 = 0.70 m x 0.24 m x x 4 = 0.67 m2
5/7 = 1.15 m x 0.24 m x x 4 = 1.10 m2
Tambatan Perahu 5/7 = 0.70 m x 0.24 m x x 16 = 2.69 m2
5/7 = 1.15 m x 0.24 m x x 16 = 4.42 m2
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
4 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 Panjang Lebar Tebal Jumlah 0.16 m3
Tambatan Perahu = 1.30 m x 0.10 m x 0.10 m x 12 Bh = 0.16 m3

b Pek Gelagar memanjang Panjang Lebar Tebal Jumlah 0.05 m3


Tambatan Perahu = 1.80 m x 0.05 m x 0.10 m x 4 Bh = 0.04 m3
= 0.35 m x 0.05 m x 0.10 m x 8 Bh = 0.01 m3

d Pek. Kacapuri Panjang Lebar Tebal Jumlah Jumlah tongkat 0.02 m3


Tambatan Perahu = 0.50 m x 0.05 m x 0.10 m x 4 x 4 = 0.01 m3
= 0.50 m x 0.05 m x 0.10 m x 4 x 8 = 0.01 m3

e Pekerjaan sunduk Panjang Lebar Tebal Jumlah Jumlah tongkat 0.004 m3


Tambatan Perahu = 0.50 m x 0.05 m x 0.07 m x 1 x 4 = 0.002 m3
= 0.50 m x 0.05 m x 0.07 m x 1 x 8 = 0.002 m3

e Pasangan Mur dan Baut Dia. 10 mm


m10x75mm = 1.50 = 1.50 Kg

f Dinding GRC Board rangka balok 5/7 Panjang Lebar 2.81 m2


= 2.55 m x 1.10 = 2.81

g Pengecatan dinding GRC Board Panjang Lebar Sisi 5.61 m2


= 2.55 m x 1.10 m x 2.00 = 5.61 m2

h Pek. Letter huruf timbul = 1.00


= 1.00 Paket

XI KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) = 4.00 4.00 Bh
2 Helm Keselamatan = 20.00 20.00 Bh
3 Rompi Kerja = 20.00 20.00 Bh
4 Sarung Tangan (Safety Glove) = 20.00 20.00 Bh
5 Sepatu Keselamatan (Rubber Shoes) = 20.00 20.00 Bh
6 Kotak P3K = 3.00 3.00 Bh
7 Asuransi Tenaga Kerja = 1.00 1.00 Paket
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) = 2.00 2.00 Bh
2 Vitamin C (1 Box isi 100 tablet) = 25.00 25.00 Bh
3 Tempat Cuci Tangan = 2.00 2.00 Bh
4 Sabun Cuci Tangan (Cair) 200ml/btl = 6.00 6.00 Bh
5 Masker kain = 25.00 25.00 Bh
6 Alat penyemprot desinfektan = 2.00 2.00 Bh
7 Cairan Desinfektan 5L = 5.00 5.00 Bh

XII ADMINISTRASI KEGIATAN


1 Pelaporan KSM = 1.00 1.00 Ls
2 Photo Copy / Penggandaan = 1.00 1.00 Ls
3 Biaya Alat Tulis Kantor (ATK) = 1.00 1.00 Ls
4 Materai = 9.00 9.00 Bh
5 Papan Nama Kegiatan = 1.00 1.00 Paket
Form - RAB1
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT PROGRAM KOTA TANPA KUMUH (KOTAKU)
HASIL KESEPAKATAN HARGA SATUAN UPAH/BAHAN/ALAT
BULAN :
Provinsi : Kalimantan Tengah Kecamatan : Sebangau
Kota : Palangka Raya Kelurahan : Kereng Bangkirai

HARGA SATUAN
SESUAI
No. Uraian Tenaga Kerja Satuan STANDAR
KOTA/KABUPAT
EN

I. TENAGA KERJA
1 Mandor HOK
2 Kepala Tukang HOK 170,000
3 Tukang Batu HOK 155,000
4 Tukang Kayu HOK 150,000
5 Tukang Besi HOK 150,000
6 Tukang Cat HOK 150,000
7 Pekerja HOK 140,000

REKOMENDASI HARGA
HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
HARGA SATUAN UNTUK BULAN INI
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
No. Uraian Tenaga Kerja Satuan STANDAR
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA Almt : Almt : Almt : SATUAN*) Toko/Pemasok
Telp : Telp : Telp :

II. BAHAN/MATERIAL :
1 Cat Plitur Kayu Kg 75,000.00 73,000.00 73,000.00
2 Cat dasar kayu platone Kg 62,400.00 60,000.00 60,000.00
3 Cat penutup kayu platone Kg 62,400.00 60,000.00 60,000.00
4 Cat tembok Jotun Kg 120,000.00 110,000.00 110,000.00
5 Kerikil (Maks 30mm) m3 475,000.00 450,000.00 450,000.00
6 Kwas 4" Bh 45,000.00 45,000.00 45,000.00
7 Paku 5 - 12 cm Kg 22,000.00 22,000.00 22,000.00
8 Pasir beton m3 200,000.00 150,000.00 180,000.00
9 Pasir Pasang m3 190,000.00 130,000.00 150,000.00
10 Semen Portland Kg 1,325.00 1,275.00 1,275.00
11 Semen Portland Gresik 40 Kg/zak 53,000.00 51,000.00 51,000.00
12 Pengencer/Thinner Kg 28,100.00 28,100.00 28,100.00
13 Ampelas Kayu Flexigo Lbr 10,000.00 10,000.00 10,000.00
15 Bata Merah Bh 1,200.00 1,000.00 1,000.00
16 Tanah Urug m3 100,000.00 100,000.00 100,000.00
17 Besi Beton Polos Kg 12,000.00 12,000.00 12,000.00
Besi Beton dia.8 Btg 45,000.00
Besi Beton dia.10 Btg 70,000.00
18 Kawat Beton/Bendrat Kg 25,000.00 25,000.00 25,000.00
19 Plywood Lbr 130,000.00 130,000.00 130,000.00
20 Keramik lantai uk.30x30 Doz 72,100.00 72,100.00 72,100.00
21 Plastik cor/bks Bks 60,000.00 60,000.00 60,000.00
22 Paving blok tebal 8 cm Bh 4,500.00 4,500.00 7,500.00
23 Baut/Mur Kg 35,000.00 35,000.00 35,000.00
24 Buis Beton 40x100 tebal 5 cm Bh 120,000.00 120,000.00 120,000.00
25 Guiding block Bh 38,000.00 38,000.00
27 GRC/KalsiBoard tebal 8 mm Lbr 190,000.00 190,000.00 190,000.00
28 Besi ø 12 untuk handle tutup saluran bh 15,000.00 25,000.00 25,000.00
29 Biopori Bh 75,000.00 75,000.00

REKOMENDASI HARGA
HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
HARGA SATUAN UNTUK BULAN INI
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
No. Uraian Tenaga Kerja Satuan STANDAR
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA Almt : Almt : Almt : SATUAN*) Toko/Pemasok

Telp : Telp : Telp :


1 Balok Kayu Klas II (Lanan) m3 4,000,000.00 4,000,000.00 4,000,000.00
2 Papan Kayu Klas II (Lanan) m3 5,000,000.00 5,000,000.00 5,000,000.00
3 Papan Kayu Klas II (Benuas) m3 6,500,000.00 6,000,000.00 6,000,000.00
4 Balok Kayu Klas II (Benuas) m3 5,500,000.00 5,250,000.00 5,250,000.00
5 Balok Kayu Klas III m3 2,250,000.00 2,200,000.00 2,200,000.00
6 Papan Kayu Klas III m3 2,500,000.00 2,450,000.00 2,450,000.00
7 Kayu Galam diameter 6-10 cm P=4 m (dolken) Batang 30,000.00 30,000.00 30,000.00

REKOMENDASI HARGA
HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
HARGA SATUAN UNTUK BULAN INI
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
No. Uraian Tenaga Kerja Satuan STANDAR
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA SATUAN*) Toko/Pemasok
Almt : Almt : Almt :
Telp : Telp : Telp :

III. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


1 Sosialisasi K3 dan Prokes (Spanduk) Bh 75,000.00
2 Helm Keselamatan Bh 100,000.00
3 Rompi Kerja Bh 60,000.00
4 Sarung Tangan (Safety Glove) Bh 5,000.00
5 Sepatu Keselamatan (Rubber Shoes) Bh 100,000.00
REKOMENDASI HARGA
HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
HARGA SATUAN UNTUK BULAN INI
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
No. Uraian Tenaga Kerja Satuan STANDAR
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA SATUAN*) Toko/Pemasok
Almt : Almt : Almt :
Telp : Telp : Telp :
6 Kotak P3K Bh 40,000.00
7 Asuransi Tenaga Kerja Paket 910,000.00
8 Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 350,000.00
9 Vitamin C (1 Box isi 100 tablet) Bh 25,000.00
10 Tempat Cuci Tangan Bh 250,000.00
11 Sabun Cuci Tangan (Cair) 200ml/btl Bh 25,000.00
12 Masker kain Bh 5,000.00
13 Alat penyemprot desinfektan Bh 65,000.00
14 Cairan Desinfektan 5L Bh 75,000.00
Bh

REKOMENDASI HARGA
HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
HARGA SATUAN UNTUK BULAN INI
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
No. Uraian Tenaga Kerja Satuan STANDAR
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA SATUAN*) Toko/Pemasok
Almt : Almt : Almt :
Telp : Telp : Telp :

XIX ADMINISTRASI KEGIATAN


1 Pelaporan KSM Rp 270,000
2 Photo Copy / Penggandaan Rp 250,000
3 Biaya Alat Tulis Kantor (ATK) Rp 150,000
4 Materai Rp 10,000
5 Pengujian Lab Rp 500,000
6 Papan Nama Kegiatan Rp 250,000

*) Harga Satuan sampai dilokasi Kegiatan (sudah termasuk biaya Transport)


…………., Tgl. …………….20…..

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST


RAB-2

BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT PROGRAM KOTA TANPA KUMUH (KOTAKU)
DAFTAR KUANTITAS PEKERJAAN
PAKET : JALAN DAN DRAINASE

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun

NO. URAIAN PEKERJAAN SATUAN VOLUME

I PEKERJAAN DRAINASE
1. Pek. Galian Drainase m3 40.79
2. Pek. Dinding Saluran
a. Pek. Pembesian Kg 1278.42
b Pek, Bekisting m2 103.60
c. Cor beton K-225 m3 15.54
3. Pek. Lantai saluran
a. Pek. Pembesian Kg 639.21
b Plastik Cor m2 77.70
c. Cor beton K-225 m3 7.77
4. Pek. Penutup saluran
a. Pek. Pembesian Kg 479.41
b Pek. Bekisting m2 44.40
c. Cor beton K-225 m3 7.26
5. Pek. Guiding block di atas cor beton m2 28.50
6. Pek. Biopori untuk resapan Bh 22.00
7. Pek. Besi untuk handle tutup saluran Bh 24.00

II PEKERJAAN JALAN PAVING


A Segmen A Panjang 84 M
1. Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 40.30
2. Pekerjaan Ring Balok 15/15
a Pembesian Kg 510.18
b Pek, Bekisting m2 16.80
c. Cor Beton K.175 m3 3.78
3. Pek. Timbunan Tanah m3 31.74
4. Pek. Kolom praktis 15/15
a Pembesian Kg 31.55
b Pek, Bekisting m2 0.71
c. Cor Beton K.175 m3 0.21
5. Pekerjaan Paving Blok m2 141.90
6. Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 2.00
7. Pek. Guiding Block uk. 30x30 tebal 6 cm m2 25.20
B Segmen B Panjang 47 M
1. Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah
2. Pekerjaan Ring Balok 15/15
a Pembesian Kg 285.46
b Pek, Bekisting m2 9.40
c Cor Beton K.175 m3 2.12
3. Pek. Timbunan Tanah m3 31.74
4. Pek. Kolom praktis 15/15
a Pembesian Kg 31.55
b Pek, Bekisting m2 0.71
NO. URAIAN PEKERJAAN SATUAN VOLUME

c Cor Beton K.175 m3 0.21


5. Pekerjaan Paving Blok m2 79.00
6. Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 4.00
7. Pek. Guiding Block uk. 30x30 tebal 6 cm m2 14.10
C Segmen C Panjang 95 M
1. Pas Dinding Bata Tebal 1/2 Bata pembatas paving m2 33.25
2. Pek. Plesteran m2 30.00
3. Pekerjaan Paving m2 365.75

III PEKERJAAN JALAN TITIAN KAYU


1. Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.35
b Pek Gelagar memanjang m3 1.50
c Pek. Gelagar melintang m3 0.47
d Pek. Kacapuri m3 0.97
e Pekerjaan sunduk m3 0.24
f Pasangan Mur dan Baut Dia. 10 mm Kg 25.00
2. Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 156.80
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.75
c Pekerjaan pagar reling m3 2.74
3. Pekerjaan Pelitur Reling kayu m2 138.19
4. Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 0.16
b Pek Gelagar memanjang m3 0.05
c Pek. Kacapuri m3 0.02
d Pekerjaan sunduk m3 0.00
e Pasangan Mur dan Baut Dia. 10 mm Kg 1.50
f Dinding GRC Board rangka balok 5/7 m2 2.81
g Pengecatan dinding GRC Board m2 5.61
h Pek. Letter huruf timbul Kayu Paket 1.00

IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1. Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00
2. Helm Keselamatan Bh 20.00
3. Rompi Kerja Bh 20.00
4. Sarung Tangan (Safety Glove) Bh 20.00
5. Sepatu Keselamatan (Rubber Shoes) Bh 20.00
6. Kotak P3K Bh 4.00
7. Asuransi Tenaga Kerja Paket 1.00
NO. URAIAN PEKERJAAN SATUAN VOLUME

B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19


1. Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00
2. Vitamin C (1 Box isi 100 tablet) Bh 20.00
3. Tempat Cuci Tangan Bh 3.00
4. Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00
5. Masker kain Bh 22.00
6. Alat penyemprot desinfektan Bh 3.00
7. Cairan Desinfektan 5L Bh 5.00

V ADMINISTRASI KEGIATAN
1. Pelaporan KSM Ls 1.00
2. Photo Copy / Penggandaan Ls 1.00
3. Biaya Alat Tulis Kantor (ATK) Ls 1.00
4. Materai Bh 8.00
6. Papan Nama Kegiatan Paket 1.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


Form - RAB 3
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
FORMAT PEREKAMAN ANALISA HARGA SATUAN

Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 1 m Kode Analisa


Satuan Pembayaran : M3 A. 2.3.1.1

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.7500 140,000.00 105,000.00
Mandor L.04 OH 0.0250 -
Jumlah Tenaga 105,000.00
B. Bahan
Jumlah Bahan
C. Peralatan -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 105,000.00

Pekerjaan : Pembesian 10 kg dengan besi polos atau besi ulir Kode Analisa
Satuan Pembayaran : Kg A.4.1.1.17

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.0700 140,000.00 9,800.00
Tukang Besi L.02 OH 0.0700 150,000.00 10,500.00
Kepala Tukang L.03 OH 0.0070 170,000.00 1,190.00
Mandor L.04 OH 0.0040 -
-
Jumlah Tenaga 21,490.00
B. Bahan
Besi beton Kg 10.5000 12,000.00 126,000.00
Kawat Beton Kg 0.1500 25,000.00 3,750.00
Jumlah Bahan 129,750.00
C. Peralatan
-
Jumlah Peralatan -

D. Harga Satuan Pekerjaan (A+B+C) 151,240.00

Pembesian 1 Kg Besi 15,124.00


Pekerjaan : Membuat 1 m3 beton mutu f’c = 14,5 Mpa (K.175) Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.5.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 1.6500 140,000.00 231,000.00
Tukang batu L.02 OH 0.2750 155,000.00 42,625.00
Kepala tukang L.03 OH 0.0280 170,000.00 4,760.00
Mandor L.04 OH 0.0830 - -
Jumlah Tenaga 278,385.00
B. Bahan
Semen Portland kg 326.0000 1,275.00 415,650.00
Pasir beton kg 760.0000 128.57 97,714.29
Kerikil (Maks 30mm) kg 1,029.0000 250.00 257,250.00
Air Liter 215.0000 -
Jumlah Bahan 770,614.29
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 1,048,999.29

Pekerjaan : Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225) Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.7.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 1.6500 140,000.00 231,000.00
Tukang batu L.02 OH 0.2750 155,000.00 42,625.00
Kepala tukang L.03 OH 0.0280 170,000.00 4,760.00
Mandor L.04 OH 0.0830 - -
Jumlah Tenaga 278,385.00
B. Bahan
Semen Portland kg 352.0000 1,275.00 448,800.00
Pasir beton kg 731.0000 128.57 93,985.71
Kerikil (Maks 30mm) kg 1,031.0000 250.00 257,750.00
Air Liter 215.0000 -
Jumlah Bahan 800,535.71
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 1,078,920.71
Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk kolom Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.22

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0150 4,000,000.00 60,000.00
Plywood tebal 9 mm Lbr 0.3500 - -
Dolken kayu φ 8-10cm Batang 2.0000 30,000.00 60,000.00
Jumlah Bahan 226,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 374,310.00

Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk balok Kode Analisa


Satuan Pembayaran : M3 A.4.1.1.23

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 - -
Balok kayu kelas II m3 0.0180 4,000,000.00 72,000.00
Plywood tebal 9 mm Lbr 0.3500 - -
Dolken kayu φ 8-10cm Batang 2.0000 30,000.00 60,000.00
Jumlah Bahan 238,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 386,310.00
Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk plat Kode Analisa
Satuan Pembayaran : M2 A.4.1.1.24

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0150 4,000,000.00 60,000.00
Plywood tebal 9 mm Lbr 0.3500 130,000.00 45,500.00
Dolken kayu φ 8-10cm Batang 6.0000 30,000.00 180,000.00
Jumlah Bahan 392,300.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 539,810.00

Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk dinding Kode Analisa


Satuan Pembayaran : M2 A.4.1.1.25

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0300 2,450,000.00 73,500.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0200 4,000,000.00 80,000.00
Plywood tebal 9 mm Lbr 0.3500 130,000.00 45,500.00
Dolken kayu φ 8-10cm Batang 3.0000 30,000.00 90,000.00
Jumlah Bahan 297,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 445,310.00
Pekerjaan : 1 m2 Pekerjaan Pelitur Reling Kode Analisa
Satuan Pembayaran : M2 A.4.7.1.4.a

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.0700 140,000.00 9,800.00
Tukang cat L.02 OH 0.0090 150,000.00 1,350.00
Kepala tukang L.03 OH 0.0060 170,000.00 1,020.00
Mandor L.04 OH 0.0030 - -
Jumlah Tenaga 12,170.00
B. Bahan
Cat plitur Kayu Kg 0.2000 73,000.00 14,600.00
Plamuur Kg 0.1500 - -
Cat plitur Kayu Kg 0.1700 73,000.00 12,410.00
Cat penutup Kayu Kg 0.2600 -
Kuas Bh 0.0100 45,000.00 450.00
Pengencer Kg 0.0300 28,100.00 843.00
Ampelas Lbr 0.2000 10,000.00 2,000.00
Jumlah Bahan 30,303.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 42,473.00

Pekerjaan : Pengecatan 1 m2 tembok baru Kode Analisa


Satuan Pembayaran : M2 A.4.7.1.10.

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01.01 OH 0.0200 140,000.00 2,800.00
Tukang cat L.02.08 OH 0.0630 150,000.00 9,450.00
Kepala tukang L.03.01 OH 0.0063 170,000.00 1,071.00
Mandor L.04.01 OH 0.0030 -
Jumlah Tenaga 13,321.00
B. Bahan
Plamuur Kg 0.1000 - -
Cat dasar Tembok Kg 0.1200 110,000.00 13,200.00
Cat Penutup Tembok Kg 0.1800 110,000.00 19,800.00
Jumlah Bahan 33,000.00
C. Peralatan -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 46,321.00
Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm Kode Analisa
Satuan Pembayaran : M2 A.4.4.2.4.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.3000 140,000.00 42,000.00
Tukang batu L.02 OH 0.1500 155,000.00 23,250.00
Kepala tukang L.03 OH 0.0150 170,000.00 2,550.00
Mandor L.04 OH 0.0150 -
Jumlah Tenaga 67,800.00
B. Bahan
Semen Portland Kg 6.240 1,275.00 7,956.00
Pasir pasang m3 0.024 150,000.00 3,600.00
Jumlah Bahan 11,556.00
C. Peralatan -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 79,356.00

Pekerjaan : Pemasangan 1m2 guiding block 30 cm x 30 cm di atas cor beton Kode Analisa
Satuan Pembayaran : M2 A.4.4.3.35.a

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.700 140,000.00 98,000.00
Tukang batu L.02 OH 0.350 155,000.00 54,250.00
Kepala tukang L.03 OH 0.035 170,000.00 5,950.00
Mandor L.04 OH 0.035 -
Jumlah Tenaga 158,200.00
B. Bahan
Guiding block 30x30 Bh 12.000 38,000.00 456,000.00
Semen Portland Kg -
Pasir pasang M3 -
Semen warna Kg -
Jumlah Bahan 456,000.00
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 614,200.00

Pekerjaan : Pemasangan 1m2 guiding block 30 cm x 30 cm Kode Analisa


Satuan Pembayaran : M2 A.4.4.3.35.b

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.700 140,000.00 98,000.00
Tukang batu L.02 OH 0.350 155,000.00 54,250.00
Kepala tukang L.03 OH 0.035 170,000.00 5,950.00
Mandor L.04 OH 0.035 -
Jumlah Tenaga 158,200.00
B. Bahan
Guiding block 30x30 Bh 12.000 38,000.00 456,000.00
Semen Portland Kg 10.000 1,275.00 12,750.00
Pasir pasang M3 0.045 150,000.00 6,750.00
Semen warna Kg -
Jumlah Bahan 475,500.00
C. Peralatan -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 633,700.00
Pekerjaan : Pemasangan 1m2 dinding bata merah Tbl 1 Bata 1PC:4PP Kode Analisa
Satuan Pembayaran : m2 A. 4.4.1.3

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.600 140,000.00 84,000.00
Tukang Batu L.02 OH 0.200 155,000.00 31,000.00
Kepala Tukang L.03 OH 0.020 170,000.00 3,400.00
Mandor L.04 OH 0.030 -
Jumlah Tenaga 118,400.00
B. Bahan
Bata merah Bh 170.000 1,000.00 170,000.00
Semen Portland Kg 26.550 1,275.00 33,851.25
Pasir pasang m3 0.093 150,000.00 13,950.00
Jumlah Bahan 217,801.25
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 336,201.25

Pekerjaan : Pemasangan 1m2 dinding bata merah Tbl 1/2 Bata 1PC:4PP Kode Analisa
Satuan Pembayaran : m2 A.4.4.1.9

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.300 140,000.00 42,000.00
Tukang Batu L.02 OH 0.100 155,000.00 15,500.00
Kepala Tukang L.03 OH 0.010 170,000.00 1,700.00
Mandor L.04 OH 0.015 -
Jumlah Tenaga 59,200.00
B. Bahan
Bata merah Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 11.500 1,275.00 14,662.50
Pasir pasang m3 0.043 150,000.00 6,450.00
Jumlah Bahan 91,112.50
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 150,312.50

Pekerjaan : Pemasangan 1 m2 paving block natural tebal 8 cm Kode Analisa


Satuan Pembayaran : m2 A.4.4.3.65.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.500 140,000.00 70,000.00
Tukang Batu L.02 OH 0.500 155,000.00 77,500.00
Kepala Tukang L.03 OH 0.050 170,000.00 8,500.00
Mandor L.04 OH 0.013 -
Jumlah Tenaga 156,000.00
B. Bahan
Paving Block Hexagonal Bh 27.000 7,500.00 202,500.00
Pasir pasang m3 0.150 150,000.00 22,500.00
Jumlah Bahan 225,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 381,000.00
Pekerjaan : Pekerjaan Rangka Bawah Kayu Klas II (Benuas) Kode Analisa
Satuan Pembayaran : m3 BOW F.1b

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 5.000 140,000.00 700,000.00
Tukang Kayu L.02 OH 7.500 150,000.00 1,125,000.00
Kepala Tukang L.03 OH 0.750 170,000.00 127,500.00
Mandor L.04 OH 0.250 -
Jumlah Tenaga 1,952,500.00
B. Bahan
Balok Kayu Klas II Benuas m3 1.100 5,250,000.00 5,775,000.00
Paku Kg 5.000 22,000.00 110,000.00
Jumlah Bahan 5,885,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 7,837,500.00

Pekerjaan : 1 M2 Pek. Lantai Papan Kayu Klas II Tebal 2 Cm Diserut Rapi Kode Analisa
Satuan Pembayaran : m3 BOW F.38

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6000 140,000.00 84,000.00
Tukang Kayu L.02 OH 1.8000 150,000.00 270,000.00
Kepala Tukang L.03 OH 0.1800 170,000.00 30,600.00
Mandor L.04 OH 0.0300 -
Jumlah Tenaga 384,600.00
B. Bahan
M3 Papan Kayu Klas II Benuas m3 0.0300 6,000,000.00 180,000.00
Paku Kg 0.2000 22,000.00 4,400.00
Jumlah Bahan 184,400.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 569,000.00

Pekerjaan : Mengerjakan Rangka Badan Kayu Klas II Kode Analisa


Satuan Pembayaran : m3 BOW F.22

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 8.0000 140,000.00 1,120,000.00
Tukang Kayu L.02 OH 20.0000 150,000.00 3,000,000.00
Kepala Tukang L.03 OH 2.4000 170,000.00 408,000.00
Mandor L.04 OH 0.4000 -
Jumlah Tenaga 4,528,000.00
B. Bahan
M3 Balok Kayu Klas II Benuas m3 1.1000 5,250,000.00 5,775,000.00
Paku Kg 6.0000 22,000.00 132,000.00
Jumlah Bahan 5,907,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 10,435,000.00
Pekerjaan : Pemasangan 1 m2 dinding pemisah GRC Board rangkap Kode Analisa
Satuan Pembayaran : m3 A.4.6.1.25.a

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.2000 140,000.00 28,000.00
Tukang Kayu L.02 OH 0.6000 150,000.00 90,000.00
Kepala Tukang L.03 OH 0.0600 170,000.00 10,200.00
Mandor L.04 OH 0.0100 -
Jumlah Tenaga 128,200.00
B. Bahan
Balok Kayu Klas II Benuas uk. 5/10 m3 0.0280 5,250,000.00 147,000.00
Paku Kg 0.1500 22,000.00 3,300.00
GRC Board tebal 8 m Lbr 0.8600 190,000.00 163,400.00
Lem Kayu Kg 0.5600
Jumlah Bahan 313,700.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 441,900.00

Pekerjaan : Pengurugan 1 m3 dengan tanah urug Kode Analisa


Satuan Pembayaran : M3 A.2.3.1.11.a

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.2500 140,000.00 35,000.00
Mandor L.04 OH 0.0100 -
Jumlah Tenaga 35,000.00
B. Bahan
Tanah Urug 1.2000 100,000 120,000.00
Jumlah Bahan 120,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 155,000.00

Dibuat oleh : Tim Verifikasi,


UPL Tim Faskel Tim Korkot

Alfiansyah Hengky Pradana, ST Wiwit Whindari, ST


RAB-4

PROGRAM KOTA TANPA KUMUH (KOTAKU)


DAFTAR HARGA SATUAN JADI PEKERJAAN

Kab./Kota : Palangka Raya Nama Paket Pekerjaan : Pembangunan Jalan dan


Drainase
Kecamatan : Sebangau
Kelurahan : Kereng Bangkirai
BKM : Kereng Membangun

HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase m3 Rp 105,000.00
2 Pek. Dinding Saluran
a. Pek. Pembesian Kg Rp 15,124.00
b Pek, Bekisting m2 Rp 445,310.00
c. Cor beton K-225 m3 Rp 1,078,920.71
3 Pek. Lantai saluran
a. Pek. Pembesian Kg Rp 15,124.00
b Plastik Cor m2 Rp 4,000.00
c. Cor beton K-225 m3 Rp 1,078,920.71
4 Pek. Penutup saluran
a. Pek. Pembesian Kg Rp 15,124.00
b Pek. Bekisting m2 Rp 539,810.00
c. Cor beton K-225 m3 Rp 1,078,920.71
5 Pek. Guiding block di atas cor beton m2 Rp 614,200.00
6 Pek. Biopori untuk resapan Bh Rp 75,000.00
7 Pek. Besi untuk handle tutup saluran Bh Rp 25,000.00

II PEKERJAAN JALAN PAVING


A Segmen A Panjang 84 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 Rp 336,201.25
2 Pekerjaan Ring Balok 15/15
a Pembesian Kg Rp 15,124.00
b Pek, Bekisting m2 Rp 386,310.00
c. Cor Beton K.175 m3 Rp 1,048,999.29
3 Pek. Timbunan Tanah m3 Rp 155,000.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg Rp 15,124.00
b Pek, Bekisting m2 Rp 374,310.00
c. Cor Beton K.175 m3 Rp 1,048,999.29
5 Pekerjaan Paving Blok m2 Rp 381,000.00
6 Pek. Pas Buis Beton 40x100 tebal 5 cm Bh Rp 120,000.00
7 Pek. Guiding Block uk. 30x30 tebal 6 cm m2 Rp 633,700.00
HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)
B Segmen B Panjang 47 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah
2 Pekerjaan Ring Balok 15/15
a Pembesian Kg Rp 15,124.00
b Pek, Bekisting m2 Rp 386,310.00
c Cor Beton K.175 m3 Rp 1,048,999.29
3 Pek. Timbunan Tanah m3 Rp 155,000.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg Rp 15,124.00
b Pek, Bekisting m2 Rp 374,310.00
c Cor Beton K.175 m3 Rp 1,048,999.29
5 Pekerjaan Paving Blok m2 Rp 381,000.00
6 Pek. Pas Buis Beton 40x100 tebal 5 cm Bh Rp 120,000.00
7 Pek. Guiding Block uk. 30x30 tebal 6 cm m2 Rp 633,700.00
C Segmen C Panjang 95 M
1 Pas Dinding Bata Tebal 1/2 Bata pembatas paving m2 Rp 150,312.50
2 Pek. Plesteran m2 Rp 79,356.00
3 Pekerjaan Paving m2 Rp 381,000.00

III PEKERJAAN JALAN TITIAN KAYU


1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 Rp 7,837,500.00
b Pek Gelagar memanjang m3 Rp 7,837,500.00
c Pek. Gelagar melintang m3 Rp 7,837,500.00
d Pek. Kacapuri m3 Rp 7,837,500.00
e Pekerjaan sunduk m3 Rp 7,837,500.00
f Pasangan Mur dan Baut Dia. 10 mm Kg Rp 35,000.00
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. m2 Rp 569,000.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 Rp 7,837,500.00
c Pekerjaan pagar reling m3 Rp 10,435,000.00
3 Pekerjaan Pelitur Reling kayu m2 Rp 42,473.00
4 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 Rp 7,837,500.00
b Pek Gelagar memanjang m3 Rp 7,837,500.00
c Pek. Kacapuri m3 Rp 7,837,500.00
d Pekerjaan sunduk m3 Rp 7,837,500.00
e Pasangan Mur dan Baut Dia. 10 mm Kg Rp 35,000.00
f Dinding GRC Board rangka balok 5/7 m2 Rp 441,900.00
g Pengecatan dinding GRC Board m2 Rp 46,321.00
h Pek. Letter huruf timbul Kayu Paket Rp 1,800,000.00
HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)
IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) Bh Rp 75,000.00
2 Helm Keselamatan Bh Rp 100,000.00
3 Rompi Kerja Bh Rp 60,000.00
4 Sarung Tangan (Safety Glove) Bh Rp 5,000.00
5 Sepatu Keselamatan (Rubber Shoes) Bh Rp 100,000.00
6 Kotak P3K Bh Rp 40,000.00
7 Asuransi Tenaga Kerja Paket Rp 1,407,000.00
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) Bh Rp 350,000.00
2 Vitamin C (1 Box isi 100 tablet) Bh Rp 25,000.00
3 Tempat Cuci Tangan Bh Rp 250,000.00
4 Sabun Cuci Tangan (Cair) 200ml/btl Bh Rp 25,000.00
5 Masker kain Bh Rp 5,000.00
6 Alat penyemprot desinfektan Bh Rp 65,000.00
7 Cairan Desinfektan 5L Bh Rp 75,000.00

V ADMINISTRASI KEGIATAN
1 Pelaporan KSM Ls Rp 270,000.00
2 Photo Copy / Penggandaan Ls Rp 250,000.00
3 Biaya Alat Tulis Kantor (ATK) Ls Rp 150,000.00
4 Materai Bh Rp 10,000.00
6 Papan Nama Kegiatan Paket Rp 250,000.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-5
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
RENCANA ANGARAN BIAYA

Kab./Kota : Palangka Raya Nama Paket Pekerjaan : Pembangunan Jalan dan Drainase
Kecamatan : Sebangau
Kelurahan : Kereng Bangkirai
BKM : Kereng Membangun

HARGA SATUAN
NO JENIS PEKERJAAN SATUAN VOLUME ANALISA JUMLAH HARGA (Rp)
(Rp)

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase m3 40.79 A. 2.3.1.1 Rp 105,000.00 Rp 4,283,212.50
2 Pek. Dinding Saluran
a. Pek. Pembesian Kg 1278.42 A.4.1.1.17 Rp 15,124.00 Rp 19,334,884.58
b Pek, Bekisting m2 103.60 A.4.1.1.25 Rp 445,310.00 Rp 46,134,116.00
c. Cor beton K-225 m3 15.54 A.4.1.1.7. Rp 1,078,920.71 Rp 16,766,427.90
3 Pek. Lantai saluran
a. Pek. Pembesian Kg 639.21 A.4.1.1.17 Rp 15,124.00 Rp 9,667,442.29
b Plastik Cor m2 77.70 Ls Rp 4,000.00 Rp 310,800.00
c. Cor beton K-225 m3 7.77 A.4.1.1.7. Rp 1,078,920.71 Rp 8,383,213.95
4 Pek. Penutup saluran
a. Pek. Pembesian Kg 479.41 A.4.1.1.17 Rp 15,124.00 Rp 7,250,581.72
b Pek. Bekisting m2 44.40 A.4.1.1.24 Rp 539,810.00 Rp 23,967,564.00
c. Cor beton K-225 m3 7.26 A.4.1.1.7. Rp 1,078,920.71 Rp 7,829,727.62
5 Pek. Guiding block di atas cor beton m2 28.50 A.4.4.3.35.a Rp 614,200.00 Rp 17,504,700.00
6 Pek. Biopori untuk resapan Bh 22.00 Ls Rp 75,000.00 Rp 1,650,000.00
7 Pek. Besi untuk handle tutup saluran Bh 24.00 Ls Rp 25,000.00 Rp 600,000.00
Jumlah I Rp 163,682,670.55
II PEKERJAAN JALAN PAVING
A Segmen A Panjang 84 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 40.30 A. 4.4.1.3 Rp 336,201.25 Rp 13,548,910.38
2 Pekerjaan Ring Balok 15/15
a Pembesian Kg 510.18 A.4.1.1.17 Rp 15,124.00 Rp 7,715,998.62
b Pek, Bekisting m2 16.80 A.4.1.1.23 Rp 386,310.00 Rp 6,490,008.00
c. Cor Beton K.175 m3 3.78 A.4.1.1.5. Rp 1,048,999.29 Rp 3,965,217.30
3 Pek. Timbunan Tanah m3 31.74 A.2.3.1.11.a Rp 155,000.00 Rp 4,920,320.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg 31.55 A.4.1.1.17 Rp 15,124.00 Rp 477,094.44
b Pek, Bekisting m2 0.71 A.4.1.1.22 Rp 374,310.00 Rp 265,011.48
c. Cor Beton K.175 m3 0.21 A.4.1.1.5. Rp 1,048,999.29 Rp 222,807.45
5 Pekerjaan Paving Blok m2 141.90 A.4.4.3.65. Rp 381,000.00 Rp 54,063,900.00
6 Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 2.00 Ls Rp 120,000.00 Rp 240,000.00
7 Pek. Guiding Block uk. 30x30 tebal 6 cm m2 25.20 A.4.4.3.35.b Rp 633,700.00 Rp 15,969,240.00
Jumlah A Rp 107,878,507.67
B Segmen B Panjang 47 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 40.30 A. 4.4.1.3 Rp 336,201.25 Rp 13,548,910.38
2 Pekerjaan Ring Balok 15/15
a Pembesian Kg 285.46 A.4.1.1.17 Rp 15,124.00 Rp 4,317,284.94
b Pek, Bekisting m2 9.40 A.4.1.1.23 Rp 386,310.00 Rp 3,631,314.00
c Cor Beton K.175 m3 2.12 A.4.1.1.5. Rp 1,048,999.29 Rp 2,218,633.49
3 Pek. Timbunan Tanah m3 31.74 A.2.3.1.11.a Rp 155,000.00 Rp 4,920,320.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg 31.55 A.4.1.1.17 Rp 15,124.00 Rp 477,094.44
b Pek, Bekisting m2 0.71 A.4.1.1.22 Rp 374,310.00 Rp 265,011.48
c Cor Beton K.175 m3 0.21 A.4.1.1.5. Rp 1,048,999.29 Rp 222,807.45
5 Pekerjaan Paving Blok m2 79.00 A.4.4.3.65. Rp 381,000.00 Rp 30,099,000.00
6 Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 4.00 Ls Rp 120,000.00 Rp 480,000.00
7 Pek. Guiding Block uk. 30x30 tebal 6 cm m2 14.10 A.4.4.3.35.b Rp 633,700.00 Rp 8,935,170.00
Jumlah B Rp 69,115,546.18
C Segmen C Panjang 95 M
1 Pas Dinding Bata Tebal 1/2 Bata pembatas paving m2 33.25 A.4.4.1.9 Rp 150,312.50 Rp 4,997,890.63
2 Pek. Plesteran m2 30.00 A.4.4.2.4. Rp 79,356.00 Rp 2,380,680.00
3 Pekerjaan Paving m2 365.75 A.4.4.3.65. Rp 381,000.00 Rp 139,350,750.00
Jumlah C Rp 146,729,320.63
Jumlah II (A+B+C) Rp 323,723,374.47
HARGA SATUAN
NO JENIS PEKERJAAN SATUAN VOLUME ANALISA JUMLAH HARGA (Rp)
(Rp)
III PEKERJAAN JALAN TITIAN KAYU
1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.35 BOW F.1b Rp 7,837,500.00 Rp 10,596,300.00
b Pek Gelagar memanjang m3 1.50 BOW F.1b Rp 7,837,500.00 Rp 11,756,250.00
c Pek. Gelagar melintang m3 0.47 BOW F.1b Rp 7,837,500.00 Rp 3,667,950.00
d Pek. Kacapuri m3 0.97 BOW F.1b Rp 7,837,500.00 Rp 7,602,375.00
e Pekerjaan sunduk m3 0.24 BOW F.1b Rp 7,837,500.00 Rp 1,900,593.75
f Pasangan Mur dan Baut Dia. 10 mm Kg 25.00 Ls Rp 35,000.00 Rp 875,000.00
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 C m2 156.80 BOW F.38 Rp 569,000.00 Rp 89,219,200.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.75 BOW F.1b Rp 7,837,500.00 Rp 5,905,556.25
c Pekerjaan pagar reling m3 2.74 BOW F.22 Rp 10,435,000.00 Rp 28,633,640.00
3 Pekerjaan Pelitur Reling kayu m2 138.19 A.4.7.1.4.a Rp 42,473.00 Rp 5,869,428.82
4 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 0.16 BOW F.1b Rp 7,837,500.00 Rp 1,222,650.00
b Pek Gelagar memanjang m3 0.05 BOW F.1b Rp 7,837,500.00 Rp 391,875.00
c Pek. Kacapuri m3 0.02 BOW F.1b Rp 7,837,500.00 Rp 156,750.00
d Pekerjaan sunduk m3 0.004 BOW F.1b Rp 7,837,500.00 Rp 27,431.25
e Pasangan Mur dan Baut Dia. 10 mm Kg 1.50 Ls Rp 35,000.00 Rp 52,500.00
f Dinding GRC Board rangka balok 5/7 m2 2.81 A.4.6.1.25.a Rp 441,900.00 Rp 1,239,529.50
g Pengecatan dinding GRC Board m2 5.61 A.4.7.1.10. Rp 46,321.00 Rp 259,860.81
h Pek. Letter huruf timbul Kayu Paket 1.00 Ls Rp 1,800,000.00 Rp 1,800,000.00
Jumlah III Rp 171,176,890.38
IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00 Ls Rp 75,000 Rp 300,000
2 Helm Keselamatan Bh 20.00 Ls Rp 100,000 Rp 2,000,000
3 Rompi Kerja Bh 20.00 Ls Rp 60,000 Rp 1,200,000
4 Sarung Tangan (Safety Glove) Bh 20.00 Ls Rp 5,000 Rp 100,000
5 Sepatu Keselamatan (Rubber Shoes) Bh 20.00 Ls Rp 100,000 Rp 2,000,000
6 Kotak P3K Bh 4.00 Ls Rp 40,000 Rp 160,000
7 Asuransi Tenaga Kerja Paket 1.00 Ls Rp 1,407,000 Rp 1,407,000
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00 Ls Rp 350,000 Rp 700,000
2 Vitamin C (1 Box isi 100 tablet) Bh 20.00 Ls Rp 25,000 Rp 500,000
3 Tempat Cuci Tangan Bh 3.00 Ls Rp 250,000 Rp 750,000
4 Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00 Ls Rp 25,000 Rp 125,000
5 Masker kain Bh 22.00 Ls Rp 5,000 Rp 110,000
6 Alat penyemprot desinfektan Bh 3.00 Ls Rp 65,000 Rp 195,000
7 Cairan Desinfektan 5L Bh 5.00 Ls Rp 75,000 Rp 375,000
Jumlah IV Rp 9,922,000.00
V ADMINISTRASI KEGIATAN
1 Pelaporan KSM Ls 1.00 Ls Rp 270,000 Rp 270,000
2 Photo Copy / Penggandaan Ls 1.00 Ls Rp 250,000 Rp 250,000
3 Biaya Alat Tulis Kantor (ATK) Ls 1.00 Ls Rp 150,000 Rp 150,000
4 Materai Bh 8.00 Ls Rp 10,000 Rp 80,000
5 Pengujian Lab Paket 1.00 Ls Rp 500,000 Rp 500,000
6 Papan Nama Kegiatan Paket 1.00 Ls Rp 250,000 Rp 250,000
JumlahV Rp 1,500,000.00

JUMLAH TOTAL Rp 670,004,935.40


DIBULATKAN Rp 670,000,000.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-6
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
REKAPITULASI RENCANA ANGGARAN BIAYA
Kab./Kota : Palangka Raya
Kecamatan : Sebangau
Kelurahan : Kereng Bangkirai
BKM : Kereng Membangun

JUMLAH HARGA
NO. NAMA PAKET PEKERJAAN SATUAN VOLUME
(Rp.)

01. PEKERJAAN DRAINASE Pek. Galian Drainase m3 40.79 Rp 4,283,212.50


Pek. Dinding Saluran
a. Pek. Pembesian Kg 1278.42 Rp 19,334,884.58
b Pek, Bekisting m2 103.60 Rp 46,134,116.00
c. Cor beton K-225 m3 15.54 Rp 16,766,427.90
Pek. Lantai saluran
a. Pek. Pembesian Kg 639.21 Rp 9,667,442.29
b Plastik Cor m2 77.70 Rp 310,800.00
c. Cor beton K-225 m3 7.77 Rp 8,383,213.95
Pek. Penutup saluran
a. Pek. Pembesian Kg 479.41 Rp 7,250,581.72
b Pek. Bekisting m2 44.40 Rp 23,967,564.00
c. Cor beton K-225 m3 7.26 Rp 7,829,727.62
Pek. Guiding block di atas cor beton m2 28.50 Rp 17,504,700.00
Pek. Biopori untuk resapan Bh 22.00 Rp 1,650,000.00
Pek. Besi untuk handle tutup saluran Bh 24.00 Rp 600,000.00
JUMLAH 163,683,000.00
02. PEKERJAAN JALAN Segmen A Panjang 84 M
PAVING Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 40.30 Rp 13,548,910.38
Pekerjaan Ring Balok 15/15
a Pembesian Kg 510.18 Rp 7,715,998.62
b Pek, Bekisting m2 16.80 Rp 6,490,008.00
c. Cor Beton K.175 m3 3.78 Rp 3,965,217.30
Pek. Timbunan Tanah m3 31.74 Rp 4,920,320.00
Pek. Kolom praktis 15/15
a Pembesian Kg 31.55 Rp 477,094.44
b Pek, Bekisting m2 0.71 Rp 265,011.48
c. Cor Beton K.175 m3 0.21 Rp 222,807.45
Pekerjaan Paving Blok m2 141.90 Rp 54,063,900.00
Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 2.00 Rp 240,000.00
Pek. Guiding Block uk. 30x30 tebal 6 cm m2 25.20 Rp 15,969,240.00
Segmen B Panjang 47 M
Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 40.30 Rp 13,548,910.38
Pekerjaan Ring Balok 15/15
a Pembesian Kg 285.46 Rp 4,317,284.94
b Pek, Bekisting m2 9.40 Rp 3,631,314.00
c Cor Beton K.175 m3 2.12 Rp 2,218,633.49
Pek. Timbunan Tanah m3 31.74 Rp 4,920,320.00
Pek. Kolom praktis 15/15
a Pembesian Kg 31.55 Rp 477,094.44
b Pek, Bekisting m2 0.71 Rp 265,011.48
c Cor Beton K.175 m3 0.21 Rp 222,807.45
Pekerjaan Paving Blok m2 79.00 Rp 30,099,000.00
Pek. Pas Buis Beton 40x100 tebal 5 cm Bh 4.00 Rp 480,000.00
Pek. Guiding Block uk. 30x30 tebal 6 cm m2 14.10 Rp 8,935,170.00
Segmen C Panjang 95 M
Pas Dinding Bata Tebal 1/2 Bata pembatas paving m2 33.25 Rp 4,997,890.63
Pek. Plesteran m2 30.00 Rp 2,380,680.00
Pekerjaan Paving m2 365.75 Rp 139,350,750.00
JUMLAH 323,723,000.00
JUMLAH HARGA
NO. NAMA PAKET PEKERJAAN SATUAN VOLUME
(Rp.)

03. PEKERJAAN JALAN Pekerjaan Rangka Bawah


TITIAN KAYU a Pek. Pas Tongkat Kayu 10/10 m3 1.35 Rp 10,596,300.00
b Pek Gelagar memanjang m3 1.50 Rp 11,756,250.00
c Pek. Gelagar melintang m3 0.47 Rp 3,667,950.00
d Pek. Kacapuri m3 0.97 Rp 7,602,375.00
e Pekerjaan sunduk m3 0.24 Rp 1,900,593.75
f Pasangan Mur dan Baut Dia. 10 mm Kg 25.00 Rp 875,000.00
Pekerjaan Rangka Badan, Lantai dan Railing -
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 156.80 Rp 89,219,200.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.75 Rp 5,905,556.25
c Pekerjaan pagar reling m3 2.74 Rp 28,633,640.00
Pekerjaan Pelitur Reling kayu m2 2.74 5,869,428.82
PekerPek. Pas Tongkat Kayu Ulin 10/10
a Pek Gelagar memanjang m3 0.05 Rp 1,222,650.00
b Pek. Kacapuri m3 0.02 Rp 391,875.00
c Pekerjaan sunduk m3 0.00 Rp 156,750.00
d Pasangan Mur dan Baut Dia. 10 mm Kg 1.50 Rp 27,431.25
e Dinding GRC Board rangka balok 5/7 m2 2.81 Rp 52,500.00
f Pengecatan dinding GRC Board m2 5.61 Rp 1,239,529.50
g 259,860.81
h Pek. Letter huruf timbul Kayu Paket 1.00 Rp 1,800,000.00
JUMLAH 171,177,000
04. KEBUTUHAN K3 DAN Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00 Rp 300,000.00
PROKES PENCEGAHAN Helm Keselamatan Bh 20.00 Rp 2,000,000.00
COVID - 19 Rompi Kerja Bh 20.00 Rp 1,200,000.00
Sarung Tangan (Safety Glove) Bh 20.00 Rp 100,000.00
Sepatu Keselamatan (Rubber Shoes) Bh 20.00 Rp 2,000,000.00
Kotak P3K Bh 4.00 Rp 160,000.00
Asuransi Tenaga Kerja Paket 1.00 Rp 1,407,000.00
Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00 Rp 700,000.00
Vitamin C (1 Box isi 100 tablet) Bh 20.00 Rp 500,000.00
Tempat Cuci Tangan Bh 3.00 Rp 750,000.00
Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00 Rp 125,000.00
Masker kain Bh 22.00 Rp 110,000.00
Alat penyemprot desinfektan Bh 3.00 Rp 195,000.00
Cairan Desinfektan 5L Bh 5.00 Rp 375,000.00
JUMLAH 9,922,000
05. ADMINISTRASI Pelaporan KSM Ls 1.00 Rp 270,000.00
KEGIATAN Photo Copy / Penggandaan Ls 1.00 Rp 250,000.00
Biaya Alat Tulis Kantor (ATK) Ls 1.00 Rp 150,000.00
Materai Bh 8.00 Rp 80,000.00
Pengujian Lab Paket 1.00 Rp 500,000.00
Papan Nama Kegiatan Paket 1.00 Rp 250,000.00
JUMLAH 1,500,000
TOTAL 670,000,000

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-7

BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT


PROGRAM KOTA TANPA KUMUH (KOTAKU)
RINCIAN KEBUTUHAN TENAGA KERJA/BAHAN/ALAT
KEGIATAN: DRAINASE

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun
HARGA
SATUAN
JUMLAH BIAYA
NO. URAIAN SATUAN VOLUME
(Rp.)

(1) (2) (3) (4) (5)(Rp.) 6 = (4) X (5)

1. TENAGA KERJA
1. Kepala Tukang HOK 12 170,000 2,040,000.00
2. Tukang Batu HOK 24 155,000 3,720,000.00
3. Tukang Kayu HOK 42 150,000 6,300,000.00
4. Tukang Besi HOK 20 150,000 3,000,000.00
5. Tukang Cat HOK - 150,000 -
6. Pekerja HOK 216 140,000 30,240,000.00
Sub-Total Tenaga Kerja (1) 45,300,000
2. BAHAN
1. Besi Beton
Besi Beton dia.10 btg 490 70,000.00 34,300,000.00
2. Kawat Beton Kg 60 25,000.00 1,500,000.00
3. Semen Portland Kg 340 51,000.00 17,340,000.00
4. Pasir beton m3 16 180,000.00 2,880,000.00
5. Kerikil (maks 30 mm) m3 22 450,000 9,900,000.00
6. Papan Kayu Klas III uk.2/20 Batang 310 39,000 12,090,000.00
7. Paku 5-10 cm Kg 60 22,000 1,320,000.00
8. Balok Kayu Klas II Lanan Uk. 5/7 Batang 200 56,000 11,200,000.00
9. Dolken Kayu ø 8-10 Cm Batang 580 30,000 17,400,000.00
10. Plywood tebal 9 mm Lbr 57 130,000 7,410,000.00
12. Biopori Bh 26 75,000 1,950,000.00
13. Besi untuk handle tutup saluran Bh 30 25,000 750,000.00
14. Plastik Cor Bks 6 60,000 360,000.00
Sub-Total Bahan (2) Sub-Total Bahan 118,400,000
3. A L A T
1.
2.
3.
Sub-Total Alat (3) -

JUMLAH BIAYA (1+2+3) 163,700,000


*)Rincian Kebutauhan Tenaga Kerja/bahan/alat untuk masing-masing Kegiatan
**) Mandor tidak diperhitungkan pada dana BPM, namun dapat diakomodir pada komponen swadaya

Diverifikasi Oleh : Dibuat Oleh:


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-7

BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT


PROGRAM KOTA TANPA KUMUH (KOTAKU)
RINCIAN KEBUTUHAN TENAGA KERJA/BAHAN/ALAT
KEGIATAN: JALAN PAVING

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun
HARGA
SATUAN
JUMLAH BIAYA
NO. URAIAN SATUAN VOLUME
(Rp.)

(1) (2) (3) (4) (5)(Rp.) 6 = (4) X (5)

1. TENAGA KERJA
1. Kepala Tukang HOK 74 170,000 12,580,000.00
2. Tukang Batu HOK 221 155,000 34,255,000.00
3. Tukang Kayu HOK 12 150,000 1,800,000.00
4. Tukang Besi HOK 10 150,000 1,500,000.00
5. Tukang Cat HOK - 150,000 -
6. Pekerja HOK 550 140,000 77,000,000.00
Sub-Total Tenaga Kerja (1) 127,135,000
2. B A H A N
1. Bata merah Bh 16,500 1,000.00 16,500,000.00
2. Semen Portland Kg 225 51,000.00 11,475,000.00
3. Pasir pasang m3 120.0 150,000.00 18,000,000.00
4. Besi beton
Besi beton dia.10 Btg 110 70,000.00 7,700,000.00
Besi beton dia.8 Btg 55 45,000.00 2,475,000.00
5. Kawat Beton Kg 20 25,000 500,000.00
6. Kerikil (Maks 30mm) m3 4.0 450,000 1,800,000.00
7. Papan Kayu Klas III Batang 69 39,000 2,691,000.00
8. Paku 5-10 cm Kg 25 22,000 550,000.00
9. Balok kayu kelas II uk. 5/7 Batang 39 56,000 2,184,000.00
10. Dolken kayu φ 8-10cm Batang 56 30,000 1,680,000.00
11. Pasir Beton m3 4 180,000 720,000.00
12. Guiding block 30x30 M' 438 38,000.00 16,644,000.00
13. Paving Block Hexagonal Bh 14,100 7,500 105,750,000.00
14. Tanah Biasa/Tanah Urug m3 72 100,000 7,200,000.00
15. Buis Beton Bh 6 120,000 720,000.00
Sub-Total Bahan (2) 196,589,000
3. ALAT
1. -
2. -
3.
Sub-Total Alat (3) -

JUMLAH BIAYA (1+2+3) 323,724,000


*)Rincian Kebutauhan Tenaga Kerja/bahan/alat untuk masing-masing Kegiatan
**) Mandor tidak diperhitungkan pada dana BPM, namun dapat diakomodir pada komponen swadaya

Diverifikasi Oleh : Dibuat Oleh:


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-7

BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT


PROGRAM KOTA TANPA KUMUH (KOTAKU)
RINCIAN KEBUTUHAN TENAGA KERJA/BAHAN/ALAT
KEGIATAN: JALAN TITIAN KAYU

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun
HARGA
SATUAN
JUMLAH BIAYA
NO. URAIAN SATUAN VOLUME
(Rp.)

(1) (2) (3) (4) (5)(Rp.) 6 = (4) X (5)

1. TENAGA KERJA
1. Kepala Tukang HOK 40 170,000 6,800,000.00
2. Tukang Batu HOK - 155,000 -
3. Tukang Kayu HOK 378 150,000 56,700,000.00
4. Tukang Besi HOK - 150,000 -
5. Tukang Cat HOK 2 150,000 300,000.00
6. Pekerja HOK 165 140,000 23,100,000.00
Sub-Total Tenaga Kerja (1) 86,900,000
2. B A H A N
1. Balok Kayu Benuas 10/10 Batang 42 210,000.00 8,820,000.00
2. Balok Kayu Benuas 5/10 Batang 207 105,000.00 21,735,000.00
3. Balok Kayu Benuas 5/7 Batang 220 73,000.00 16,060,000.00
4. Paku Kg 76 22,000.00 1,672,000.00
5. Mur dan baut Kg 28 35,000 980,000.00
6. Cat plitur Kayu Kg 51 73,000 3,723,000.00
7. Kuas Bh 2 45,000 90,000.00
8. Pengencer/Thinner Kg 4 28,100 112,400.00
9. Ampelas Lbr 28 10,000 280,000.00
10. Cat Tembok Jotun eksterior Kg 2 110,000 220,000.00
11. Papan Kayu Benuas Batang 294 96,000 28,224,000.00
12. GRC Board tebal 8 m Lembar 3 190,000 570,000.00
13. Letter Huruf timbul kayu Paket 1 1,800,000 1,800,000.00

Sub-Total Bahan (2) 84,286,400


3. ALAT
1. Pedesterian Roller
2. Alat Bantu
3.
Sub-Total Alat (3) -

JUMLAH BIAYA (1+2+3) 171,186,400


*)Rincian Kebutauhan Tenaga Kerja/bahan/alat untuk masing-masing Kegiatan
**) Mandor tidak diperhitungkan pada dana BPM, namun dapat diakomodir pada komponen swadaya

Diverifikasi Oleh : Dibuat Oleh:


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-8
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
REKAPITULASI RINCIAN KEBUTUHAN TENAGA KERJA / BAHAN / ALAT
PAKET : No. 1 dari 3

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun

HARGA SATUAN
JUMLAH BIAYA
NO. URAIAN SATUAN VOLUME
(Rp.)
(Rp.)
(1) (2) (3) (4) (5) 6 = (4) X (5)

1. TENAGA KERJA
1. Kepala Tukang HOK 126 170,000 21,420,000.00
2. Tukang Batu HOK 245 155,000 37,975,000.00
3. Tukang Kayu HOK 432 150,000 64,800,000.00
4. Tukang Besi HOK 30 150,000 4,500,000.00
5. Tukang Cat HOK 2 150,000 300,000.00
6. Pekerja HOK 931 140,000 130,340,000.00
JUMLAH 259,335,000
2. BAHAN
1. Ampelas Lbr 28 10,000 280,000
2. Balok Kayu Benuas 10/10 Batang 42 210,000.00 8,820,000
3. Balok Kayu Benuas 5/10 Batang 207 105,000.00 21,735,000
4. Balok Kayu Benuas 5/7 Batang 220 73,000.00 16,060,000
5. Balok Kayu Klas II Uk. 5/7 Batang 239 56,000 13,384,000
6. Bata merah Bh 16,500 1,000 16,500,000
7. Besi Beton
8. Besi beton dia.10 Btg 600 70,000 42,000,000
9. Besi beton dia.8 Btg 55 45,000 2,475,000
10. Besi untuk handle tutup saluran Bh 30 25,000 750,000
11. Biopori Bh 26 75,000 1,950,000
12. Buis Beton Bh 6 120,000 720,000
13. Cat plitur Kayu Kg 51 73,000 3,723,000
14. Cat Tembok Jotun eksterior Kg 2 110,000 220,000
15. Dolken Kayu ø 8-10 Cm Batang 636 30,000 19,080,000
16. GRC Board tebal 8 m Lembar 3 190,000 570,000
17. Guiding block Bh 438 38,000 16,644,000
18. Kawat Beton Kg 80 25,000 2,000,000
19. Kerikil (maks 30 mm) m3 26 450,000 11,700,000
20. Kuas Bh 2 45,000 90,000
21. Letter Huruf timbul kayu Paket 1 1,800,000 1,800,000
22. Mur dan baut Kg 28 35,000 980,000
23. Paku 5-10 cm Kg 161 22,000 3,542,000
24. Papan Kayu Benuas Batang 294 96,000 28,224,000
25. Papan Kayu Klas III uk.2/20 Batang 379 39,000 14,781,000
26. Pasir beton m3 20 180,000.00 3,600,000
27. Pasir pasang m3 120 150,000 18,000,000
28. Paving Block Hexagonal Bh 14,100 7,500 105,750,000
29. Pengencer/Thinner Kg 4 28,100 112,400
30. Plastik Cor Bks 6 60,000 360,000
31. Plywood tebal 9 mm Lbr 57 130,000 7,410,000
32. Semen Portland Zak 565 51,000 28,815,000
33. Tanah Biasa/Tanah Urug m3 72 100,000 7,200,000

JUMLAH 399,275,400
HARGA SATUAN
JUMLAH BIAYA
NO. URAIAN SATUAN VOLUME
(Rp.)
(Rp.)
3. ALAT
1.
2.
3.
JUMLAH -
4. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
1. Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00 75,000.00 300,000
2. Helm Keselamatan Bh 20.00 100,000.00 2,000,000
3. Rompi Kerja Bh 20.00 60,000.00 1,200,000
4. Sarung Tangan (Safety Glove) Bh 20.00 5,000.00 100,000
5. Sepatu Keselamatan (Rubber Shoes) Bh 20.00 100,000.00 2,000,000
6. Kotak P3K Bh 4.00 40,000.00 160,000
7. Asuransi Tenaga Kerja Paket 1.00 1,407,000.00 1,407,000
8. Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00 350,000.00 700,000
9. Vitamin C (1 Box isi 100 tablet) Bh 20.00 25,000.00 500,000
10. Tempat Cuci Tangan Bh 3.00 250,000.00 750,000
11. Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00 25,000.00 125,000
12. Masker kain Bh 20.00 5,000.00 100,000
13. Alat penyemprot desinfektan Bh 3.00 65,000.00 195,000
14. Cairan Desinfektan 5L Bh 5.00 75,000.00 375,000

JUMLAH 9,912,000
5. ADMINISTRASI KEGIATAN
1. Pelaporan KSM Ls 1 Rp 270,000 270,000
2. Photo Copy / Penggandaan Ls 1 Rp 250,000 250,000
3. Biaya Alat Tulis Kantor (ATK) Ls 1 Rp 150,000 150,000
4. Materai Bh 8 Rp 10,000 80,000
5. Pengujian Lab Paket 1 Rp 500,000 500,000
6. Papan Nama Kegiatan Paket 1 Rp 250,000 250,000

JUMLAH 1,500,000
TOTAL 670,000,000
*)Rincian Kebutauhan Tenaga Kerja/bahan/alat untuk masing-masing Kegiatan
**) Mandor tidak diperhitungkan pada dana BPM, namun dapat diakomodir pada komponen swadaya

Diverifikasi Oleh : Dibuat Oleh:


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


Pekerjaan Rencana Awal

No. Uraian Pekerjaan Volume

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase 40.79 m3
2 Pek. Dinding Saluran
a. Pek. Pembesian 1278.42 Kg
b Pek, Bekisting 103.60 m2
c. Cor beton K-225 15.54 m3
3 Pek. Lantai saluran
a. Pek. Pembesian 639.21 Kg
b Plastik Cor 77.70 m2
c. Cor beton K-225 7.77 m3
4 Pek. Penutup saluran
a. Pek. Pembesian 479.41 Kg
b Pek. Bekisting 44.40 m2
c. Cor beton K-225 7.26 m3
5 Pek. Guiding block di atas cor beton 28.50 m2
6 Pek. Biopori untuk resapan 22.00 Bh
7 Pek. Besi untuk handle tutup saluran 24.00 Bh

II PEKERJAAN JALAN PAVING


A Segmen A Panjang 84 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah 40.30 m2
2 Pekerjaan Ring Balok 15/15
0 a Pembesian 510.18 Kg
0 b Pek, Bekisting 16.80 m2
0 c. Cor Beton K.175 3.78 m3
3 Pek. Timbunan Tanah 31.74 m3
4 Pek. Kolom praktis 15/15
0 a Pembesian 31.55 Kg
0 b Pek, Bekisting 0.71 m2
0 c. Cor Beton K.175 0.21 m3
5 Pekerjaan Paving Blok 141.90 m2
6 Pek. Pas Buis Beton 40x100 tebal 5 cm 2.00 Bh
7 Pek. Guiding Block uk. 30x30 tebal 6 cm 25.20 m2

B Segmen B Panjang 47 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah 40.30 m2
2 Pekerjaan Ring Balok 15/15
a Pembesian 285.46 Kg
b Pek, Bekisting 9.40 m2
c Cor Beton K.175 2.12 m3
3 Pek. Timbunan Tanah 31.74 m3
4 Pek. Kolom praktis 15/15
a Pembesian 31.55 Kg
b Pek, Bekisting 0.71 m2
c Cor Beton K.175 0.21 m3
5 Pekerjaan Paving Blok 79.00 m2
6 Pek. Pas Buis Beton 40x100 tebal 5 cm 4.00 Bh
7 Pek. Guiding Block uk. 30x30 tebal 6 cm 14.10 m2
C Segmen C Panjang 95 M
1 Pas Dinding Bata Tebal 1/2 Bata pembatas paving 33.25 m2
2 Pek. Plesteran 30.00 m2
3 Pekerjaan Paving 365.75 m2

III PEKERJAAN JALAN TITIAN KAYU


A Segmen A, 77 M (Jl. M.Usin)
1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 1.35 m3
b Pek Gelagar memanjang 1.50 m3
c Pek. Gelagar melintang 0.47 m3
d Pek. Kacapuri 0.97 m3
e Pekerjaan sunduk 0.24 m3
f Pasangan Mur dan Baut Dia. 10 mm 25.00 Kg
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm 156.80 m2
b Pek. Balok Pengunci Lantai Papan uk. 5/7 0.75 m3
c Pekerjaan pagar reling 2.74 m3
3 Pekerjaan Pelitur Reling kayu 138.19 m2
4 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 0.16 m3
b Pek Gelagar memanjang 0.05 m3
c Pek. Kacapuri 0.02 m3
d Pekerjaan sunduk 0.00 m3
e Pasangan Mur dan Baut Dia. 10 mm 1.50 Kg
f Dinding GRC Board rangka balok 5/7 2.81 m2
g Pengecatan dinding GRC Board 5.61 m2
h Pek. Letter huruf timbul Kayu 1.00 Paket

B Segmen B (Jl. Hadri Embang)


1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 0.00 m3
b Pek Gelagar memanjang 0.00 m3
c Pek. Gelagar melintang 0.00 m3
d Pek. Kacapuri 0.00 m3
e Pekerjaan sunduk 0.00 m3
f Pekerjaan balok suai 0.00 m3
g Pasangan Mur dan Baut 14/22 0.00 Kg
h. Pas. Ring Baut 0.00 Kg
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm 0.00 m2
b Pek. Balok Pengunci Lantai Papan uk. 5/7 0.00 m3
c Pekerjaan pagar reling 0.00 m3

IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) 4.00 Bh
2 Helm Keselamatan 20.00 Bh
3 Rompi Kerja 20.00 Bh
4 Sarung Tangan (Safety Glove) 20.00 Bh
5 Sepatu Keselamatan (Rubber Shoes) 20.00 Bh
6 Kotak P3K 4.00 Bh
7 Asuransi Tenaga Kerja 1.00 Paket
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) 2.00 Bh
2 Vitamin C (1 Box isi 100 tablet) 20.00 Bh
3 Tempat Cuci Tangan 3.00 Bh
4 Sabun Cuci Tangan (Cair) 200ml/btl 5.00 Bh
5 Masker kain 22.00 Bh
6 Alat penyemprot desinfektan 3.00 Bh
7 Cairan Desinfektan 5L 5.00 Bh

V ADMINISTRASI KEGIATAN
1 Pelaporan KSM 1.00 Ls
2 Photo Copy / Penggandaan 1.00 Ls
3 Biaya Alat Tulis Kantor (ATK) 1.00 Ls
4 Materai 8.00 Bh
5 Pengujian Lab 1.00 Paket
6 Papan Nama Kegiatan 1.00 Paket

TOTAL

DIBULATKAN

Pekerjaan Rencana Awal

No. Uraian Pekerjaan


I PEKERJAAN DRAINASE 111
II PEKERJAAN JALAN PAVING
A Segmen A Panjang 84 M 84
B Segmen B Panjang 47 M 47
C Segmen C Panjang 95 M 95
III PEKERJAAN JALAN TITIAN KAYU
A Segmen A, 77 M (Jl. M.Usin) 77
B Segmen B (Jl. Hadri Embang)
IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
V ADMINISTRASI KEGIATAN
Pekerjaan Tambah K

Harga Satuan Jumlah Harga No. Uraian Pekerjaan

I PEKERJAAN DRAINASE
105,000.00 4,283,212.50 1 Pek. Galian Drainase
2 Pek. Dinding Saluran
15,124.00 19,334,884.58 a.
445,310.00 46,134,116.00 b
1,078,920.71 16,766,427.90 c.
3 Pek. Lantai saluran
15,124.00 9,667,442.29 a.
4,000.00 310,800.00 b
1,078,920.71 8,383,213.95 c.
4 Pek. Penutup saluran
15,124.00 7,250,581.72 a.
539,810.00 23,967,564.00 b
1,078,920.71 7,829,727.62 c.
614,200.00 17,504,700.00 5 Pek. Guiding block di atas cor beton
75,000.00 1,650,000.00 5 Pek. Biopori untuk resapan
25,000.00 600,000.00 6 Pek. Besi untuk handle tutup saluran
7 Pekerjaan Acian
163,682,670.55

II PEKERJAAN JALAN PAVING BLOCK


A Segmen A Panjang 84 M
336,201.25 13,548,910.38 1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah
2 Pekerjaan Ring Balok 15/15
15,124.00 7,715,998.62 a
386,310.00 6,490,008.00 b
1,048,999.29 3,965,217.30 c.
155,000.00 4,920,320.00 3 Pek. Timbunan Tanah
4 Pek. Kolom praktis 15/15
15,124.00 477,094.44 a
374,310.00 265,011.48 b
1,048,999.29 222,807.45 c.
381,000.00 54,063,900.00 5 Pekerjaan Paving Blok
120,000.00 240,000.00 6 Pek. Pas Buis Beton 40x100 tebal 5 cm
633,700.00 15,969,240.00 7 Pek. Guiding Block uk. 30x30 tebal 6 cm
107,878,507.67

A Segmen A Jl. Bara Bere Panjang 42 M


336,201.25 13,548,910.38 1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah
2 Pekerjaan Ring Balok 10/15
15,124.00 4,317,284.94 a
386,310.00 3,631,314.00 b
1,048,999.29 2,218,633.49 c
155,000.00 4,920,320.00 3 Pek. Timbunan/Urugan Tanah
4 Pek. Kolom praktis 15/15
15,124.00 477,094.44 a
374,310.00 265,011.48 b
1,048,999.29 222,807.45 c
381,000.00 30,099,000.00 5 Pekerjaan Paving Block
120,000.00 480,000.00 6 Pek. Pas Buis Beton dia. 50 x 100cm
633,700.00 8,935,170.00 7 Pek. Guiding block dan warning block precast
8 Coating guiding block & warning block
69,115,546.18
C Segmen C Panjang 116 M (Gg Husada)
150,312.50 4,997,890.63 1 Pas Dinding Bata Tebal 1/2 Bata pengunci paving
79,356.00 2,380,680.00 2 Pek. Plesteran Dinding Bata
381,000.00 139,350,750.00 3 Pekerjaan Paving Block
4 Pek. Pipa AW 4" (saluran gorong-gorong)
5 Pek. Guiding block dan warning block precast
6 Coating guiding block & warning block
146,729,320.63
323,723,374.47

III PEKERJAAN JALAN TITIAN KAYU


A Segmen A, 80 M (Jl. M.Usin)
1 Pekerjaan Rangka Bawah
7,837,500.00 10,596,300.00 a
7,837,500.00 11,756,250.00 b
7,837,500.00 3,667,950.00 c
7,837,500.00 7,602,375.00 d
7,837,500.00 1,900,593.75 e
35,000.00 875,000.00 f
2 Pekerjaan Rangka Badan, Lantai dan Railing
569,000.00 89,219,200.00 a
7,837,500.00 5,905,556.25 b
10,435,000.00 28,633,640.00 c
42,473.00 5,869,428.82 3 Pekerjaan Pelitur Reling kayu
3 Pekerjaan tambatan perahu
7,837,500.00 1,222,650.00 a
7,837,500.00 391,875.00 b
7,837,500.00 156,750.00 c
7,837,500.00 27,431.25 d
35,000.00 52,500.00 e
441,900.00 1,239,529.50 f
46,321.00 259,860.81 g
1,800,000.00 1,800,000.00 h
4 Pasangan Mur dan Baut 14/22
5 Pas. Ring Baut
171,176,890.38

B Segmen B 40 M (Jl. Hadri Embang)


1 Pekerjaan Rangka Bawah
7,837,500.00 - a
7,837,500.00 - b
7,837,500.00 - c
7,837,500.00 - d
7,837,500.00 - e
7,837,500.00 - f
45,000.00 - g
19,000.00 - h.
- 2 Pekerjaan Rangka Badan, Lantai dan Railing
569,000.00 - a
7,837,500.00 - b
7,837,500.00 - c
-
171,176,890.38

IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
75,000.00 300,000.00 1 Sosialisasi K3 dan Prokes (Spanduk)
100,000.00 2,000,000.00 2 Helm Keselamatan
60,000.00 1,200,000.00 3 Rompi Kerja
5,000.00 100,000.00 4 Sarung Tangan (Safety Glove)
100,000.00 2,000,000.00 5 Sepatu Keselamatan (Rubber Shoes)
40,000.00 160,000.00 6 Kotak P3K
1,407,000.00 1,407,000.00 7 Asuransi Tenaga Kerja
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
350,000.00 700,000.00 1 Alat ukur suhu badan nir-sentuh (Thermoscan)
25,000.00 500,000.00 2 Vitamin C (1 Box isi 100 tablet)
250,000.00 750,000.00 3 Tempat Cuci Tangan
25,000.00 125,000.00 4 Sabun Cuci Tangan (Cair) 200ml/btl
5,000.00 110,000.00 5 Masker kain
65,000.00 195,000.00 6 Alat penyemprot desinfektan
75,000.00 375,000.00 7 Cairan Desinfektan 5L
9,922,000.00

V ADMINISTRASI KEGIATAN
270,000.00 270,000.00 1 Pelaporan KSM
250,000.00 250,000.00 2 Photo Copy / Penggandaan
150,000.00 150,000.00 3 Biaya Alat Tulis Kantor (ATK)
10,000.00 80,000.00 4 Materai
500,000.00 500,000.00 5 Pengujian Lab
250,000.00 250,000.00 6 Papan Nama Kegiatan
1,500,000.00

670,004,935.40 TOTAL

670,000,000.00 DIBULATKAN

REKAPITULASI PERHITUNGAN TAMBAH KURANG

l Pekerjaan Tambah

Jumlah Harga No. Uraian Pekerjaan


163,682,670.55 I PEKERJAAN DRAINASE
323,723,374.47 II PEKERJAAN JALAN PAVING BLOCK
107,878,507.67 A Segmen A Panjang 84 M
69,115,546.18 A Segmen A Jl. Bara Bere Panjang 42 M
146,729,320.63 C Segmen C Panjang 116 M (Gg Husada)
171,176,890.38 III PEKERJAAN JALAN TITIAN KAYU
171,176,890.38 A Segmen A, 80 M (Jl. M.Usin)
- B Segmen B 40 M (Jl. Hadri Embang)
9,922,000.00 IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
1,500,000.00 V ADMINISTRASI KEGIATAN

670,004,935.40

670,000,000.00
Pekerjaan Tambah Kurang

Uraian Pekerjaan Volume Harga Satuan

PEKERJAAN DRAINASE
Pek. Galian Drainase 42.04 m3 105,000.00
Pek. Dinding Saluran
Pek. Pembesian 1353.82 Kg 14,749.00
Pek, Bekisting 107.35 m2 445,310.00
Cor beton K-175 16.45 m3 1,048,999.29
Pek. Lantai saluran
Pek. Pembesian 671.54 Kg 14,749.00
Plastik Cor 81.00 m2 4,000.00
Cor beton K-175 8.10 m3 1,048,999.29
Pek. Penutup saluran
Pek. Pembesian 614.72 Kg 14,749.00
Pek. Bekisting 32.01 m2 539,810.00
Cor beton K-175 7.47 m3 1,048,999.29
Pek. Guiding block di atas cor beton 0.00 m2 614,200.00
Pek. Biopori untuk resapan 24.00 Bh 70,000.00
Pek. Besi untuk handle tutup saluran 85.00 Bh 10,000.00
Pekerjaan Acian 72.38 m2 49,343.75

PEKERJAAN JALAN PAVING BLOCK


Segmen A Panjang 84 M
Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah 0.00 m2 336,201.25
Pekerjaan Ring Balok 15/15
Pembesian 0.00 Kg 15,124.00
Pek, Bekisting 0.00 m2 386,310.00
Cor Beton K.175 0.00 m3 1,048,999.29
Pek. Timbunan Tanah 0.00 m3 155,000.00
Pek. Kolom praktis 15/15
Pembesian 0.00 Kg 15,124.00
Pek, Bekisting 0.00 m2 374,310.00
Cor Beton K.175 0.00 m3 1,048,999.29
Pekerjaan Paving Blok 0.00 m2 381,000.00
Pek. Pas Buis Beton 40x100 tebal 5 cm 0.00 Bh 120,000.00
Pek. Guiding Block uk. 30x30 tebal 6 cm 0.00 m2 633,700.00

Segmen A Jl. Bara Bere Panjang 42 M


Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah 10.88 m2 336,201.25
Pekerjaan Ring Balok 10/15
Pembesian 256.42 Kg 14,749.00
Pek, Bekisting 8.40 m2 386,310.00
Cor Beton K.175 1.26 m3 1,048,999.29
Pek. Timbunan/Urugan Tanah 17.41 m3 155,000.00
Pek. Kolom praktis 15/15
Pembesian 31.09 Kg 14,749.00
Pek, Bekisting 0.47 m2 374,310.00
Cor Beton K.175 0.21 m3 1,048,999.29
Pekerjaan Paving Block 52.20 m2 381,000.00
Pek. Pas Buis Beton dia. 50 x 100cm 4.00 Bh 120,000.00
Pek. Guiding block dan warning block precast 143.00 m 105,000.00
Coating guiding block & warning block 42.90 m2 35,000.00
Segmen C Panjang 116 M (Gg Husada)
Pas Dinding Bata Tebal 1/2 Bata pengunci paving 81.20 m2 150,312.50
Pek. Plesteran Dinding Bata 28.20 m2 79,356.00
Pekerjaan Paving Block 431.79 m2 381,000.00
Pek. Pipa AW 4" (saluran gorong-gorong) 5.00 m 70,000.00
Pek. Guiding block dan warning block precast 121.50 m 105,000.00
Coating guiding block & warning block 36.45 m2 35,000.00

PEKERJAAN JALAN TITIAN KAYU


Segmen A, 80 M (Jl. M.Usin)
Pekerjaan Rangka Bawah
Pek. Pas Tongkat Kayu 10/10 1.48 m3 7,837,500.00
Pek Gelagar memanjang 1.60 m3 7,837,500.00
Pek. Gelagar melintang 0.49 m3 7,837,500.00
Pek. Kacapuri 0.74 m3 7,837,500.00
Pekerjaan sunduk 0.19 m3 7,837,500.00
Pasangan Mur dan Baut Dia. 10 mm 0.00 Kg 35,000.00
Pekerjaan Rangka Badan, Lantai dan Railing
Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm 168.80 m2 569,000.00
Pek. Balok Pengunci Lantai Papan uk. 5/7 0.58 m3 7,837,500.00
Pekerjaan pagar reling 4.86 m3 7,837,500.00
Pekerjaan Pelitur Reling kayu 0.00 m2 42,473.00
Pekerjaan tambatan perahu
Pek. Pas Tongkat Kayu Ulin 10/10 0.16 m3 7,837,500.00
Pek Gelagar memanjang 0.05 m3 7,837,500.00
Pek. Kacapuri 0.02 m3 7,837,500.00
Pekerjaan sunduk 0.00 m3 7,837,500.00
Pasangan Mur dan Baut Dia. 10 mm 0.00 Kg 35,000.00
Dinding GRC Board rangka balok 5/7 0.00 m2 441,900.00
Pengecatan dinding GRC Board 0.00 m2 46,321.00
Pek. Letter huruf timbul Kayu 0.00 Paket 1,800,000.00
Pasangan Mur dan Baut 14/22 56.00 Kg 45,000.00
Pas. Ring Baut 56.00 Kg 19,000.00

Segmen B 40 M (Jl. Hadri Embang)


Pekerjaan Rangka Bawah
Pek. Pas Tongkat Kayu 10/10 1.08 m3 7,837,500.00
Pek Gelagar memanjang (sloof) 0.80 m3 7,837,500.00
Pek. Gelagar melintang 0.40 m3 7,837,500.00
Pek. Kacapuri 0.38 m3 7,837,500.00
Pekerjaan sunduk 0.09 m3 7,837,500.00
Pekerjaan balok suai 0.51 m3 7,837,500.00
Pasangan Mur dan Baut 14/22 28.70 Kg 45,000.00
Pas. Ring Baut 28.70 Kg 19,000.00
Pekerjaan Rangka Badan, Lantai dan Railing
Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm 80.00 m2 569,000.00
Pek. Balok Pengunci Lantai Papan uk. 5/7 0.28 m3 7,837,500.00
Pekerjaan pagar reling 1.27 m3 7,837,500.00

KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
Sosialisasi K3 dan Prokes (Spanduk) 4.00 Bh 75,000.00
Helm Keselamatan 20.00 Bh 100,000.00
Rompi Kerja 20.00 Bh 60,000.00
Sarung Tangan (Safety Glove) 20.00 Bh 5,000.00
Sepatu Keselamatan (Rubber Shoes) 20.00 Bh 100,000.00
Kotak P3K 4.00 Bh 40,000.00
Asuransi Tenaga Kerja 1.00 Paket 1,407,000.00
KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
Alat ukur suhu badan nir-sentuh (Thermoscan) 2.00 Bh 350,000.00
Vitamin C (1 Box isi 100 tablet) 20.00 Bh 25,000.00
Tempat Cuci Tangan 3.00 Bh 250,000.00
Sabun Cuci Tangan (Cair) 200ml/btl 5.00 Bh 25,000.00
Masker kain 20.00 Bh 5,000.00
Alat penyemprot desinfektan 3.00 Bh 65,000.00
Cairan Desinfektan 5L 5.00 Bh 75,000.00

ADMINISTRASI KEGIATAN
Pelaporan KSM 1.00 Ls 270,000.00
Photo Copy / Penggandaan 1.00 Ls 250,000.00
Biaya Alat Tulis Kantor (ATK) 1.00 Ls 150,000.00
Materai 8.00 Bh 10,000.00
Pengujian Lab 1.00 Paket 500,000.00
Papan Nama Kegiatan 1.00 Paket 250,000.00

TOTAL

DIBULATKAN

HITUNGAN TAMBAH KURANG

Pekerjaan Tambah Kurang

Uraian Pekerjaan Jumlah Harga


PEKERJAAN DRAINASE 118.8
PEKERJAAN JALAN PAVING BLOCK
Segmen A Panjang 84 M 84
Segmen A Jl. Bara Bere Panjang 42 M 42
Segmen C Panjang 116 M (Gg Husada) 116
PEKERJAAN JALAN TITIAN KAYU
Segmen A, 80 M (Jl. M.Usin) 80
Segmen B 40 M (Jl. Hadri Embang) 40
KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
ADMINISTRASI KEGIATAN
Pekerjaan tambah kurang
Jumlah Harga

4,413,740.63 130,528.13 0.66% 100 0.66% 0.00%

19,967,511.83 632,627.25 2.98% 100 2.98% 0.00%


47,802,544.13 1,668,428.13 7.13% 100 7.13% 0.00%
17,256,038.25 489,610.35 2.58% 100 2.58% 0.00%

9,904,584.76 237,142.47 1.48% 100 1.48% 0.00%


324,000.00 13,200.00 0.05% 100 0.05% 0.00%
8,496,894.21 113,680.26 1.27% 100 1.27% 0.00%

9,066,462.51 1,815,880.79 1.35% 100 1.35% 0.00%


17,279,318.10 (6,688,245.90) 2.58% 100 2.58% 0.00%
7,834,975.67 5,248.04 1.17% 100 1.17% 0.00%
- (17,504,700.00) 0.00% 100 0.00% 0.00%
1,680,000.00 30,000.00 0.25% 100 0.25% 0.00%
850,000.00 250,000.00 0.13% 100 0.13% 0.00%
3,571,500.63 3,571,500.63 0.53% 100 0.53% 0.00%
148,447,570.71 (15,235,099.85) 22.16% 22.16% 0.00%
- (13,548,910.38) 0.00%

- (7,715,998.62) 0.00%
- (6,490,008.00) 0.00%
- (3,965,217.30) 0.00%
- (4,920,320.00) 0.00%

- (477,094.44) 0.00%
- (265,011.48) 0.00%
- (222,807.45) 0.00%
- (54,063,900.00) 0.00%
- (240,000.00) 0.00%
- (15,969,240.00) 0.00%
- (107,878,508) 0.00% 0.00% 0.00%

3,657,869.60 (9,891,040.78) 0.55% 100 0.55% 0.00%

3,781,914.98 (535,369.96) 0.56% 100 0.56% 0.00%


3,245,004.00 (386,310.00) 0.48% 100 0.48% 0.00%
1,321,739.10 (896,894.39) 0.20% 100 0.20% 0.00%
2,698,240.00 (2,222,080.00) 0.40% 100 0.40% 0.00%

458,506.88 (18,587.56) 0.07% 100 0.07% 0.00%


176,674.32 (88,337.16) 0.03% 100 0.03% 0.00%
222,807.45 - 0.03% 100 0.03% 0.00%
19,888,200.00 (10,210,800.00) 2.97% 100 2.97% 0.00%
480,000.00 - 0.07% 100 0.07% 0.00%
15,015,000.00 6,079,830.00 2.24% 100 2.24% 0.00%
1,501,500.00 1,501,500.00 0.22% 0.00% 0.22%
52,447,456.33 (16,668,090) 7.83% 7.60% 0.22%
12,205,375.00 7,207,484.38 1.82% 100 1.82% 0.00%
2,237,839.20 (142,840.80) 0.33% 90 0.30% 0.03%
164,511,990.00 25,161,240.00 24.55% 90 22.10% 2.46%
350,000.00 350,000.00 0.05% 100 0.05% 0.00%
12,757,500.00 12,757,500.00 1.90% 70 1.33% 0.57%
1,275,750.00 1,275,750.00 0.19% 50 0.10% 0.10%
193,338,454.20 46,609,133.58 28.86% 20 25.70% 3.16%
245,785,910.53 (77,937,463.94) 36.68% 33.30% 3.38%

11,630,850.00 1,034,550.00 1.74% 100 1.74% 0.00%


12,540,000.00 783,750.00 1.87% 100 1.87% 0.00%
3,809,025.00 141,075.00 0.57% 100 0.57% 0.00%
5,815,425.00 (1,786,950.00) 0.87% 100 0.87% 0.00%
1,453,856.25 (446,737.50) 0.22% 100 0.22% 0.00%
- (875,000.00) 0.00% 100 0.00% 0.00%

96,047,200.00 6,828,000.00 14.33% 100 14.33% 0.00%


4,517,926.88 (1,387,629.38) 0.67% 100 0.67% 0.00%
38,117,681.25 9,484,041.25 5.69% 100 5.69% 0.00%
- (5,869,428.82) 0.00% 100 0.00% 0.00%

1,222,650.00 - 0.18% 100 0.18% 0.00%


391,875.00 - 0.06% 100 0.06% 0.00%
156,750.00 - 0.02% 100 0.02% 0.00%
27,431.25 - 0.00% 100 0.00% 0.00%
- (52,500.00) 0.00% 100 0.00% 0.00%
- (1,239,529.50) 0.00% 100 0.00% 0.00%
- (259,860.81) 0.00% 100 0.00% 0.00%
- (1,800,000.00) 0.00% 100 0.00% 0.00%
2,520,000.00 2,520,000.00 0.38% 100 0.38% 0.00%
1,064,000.00 1,064,000.00 0.16% 100 0.16% 0.00%
179,314,670.63 8,137,780.25 26.76% 26.76% 0.00%

8,464,500.00 8,464,500.00 1.26% 85 1.07% 0.19%


6,270,000.00 6,270,000.00 0.94% 10 0.09% 0.84%
3,135,000.00 3,135,000.00 0.47% 0.00% 0.47%
2,962,575.00 2,962,575.00 0.44% 0.00% 0.44%
740,643.75 740,643.75 0.11% 0.00% 0.11%
3,993,990.00 3,993,990.00 0.60% 0.00% 0.60%
1,291,500.00 1,291,500.00 0.19% 0.00% 0.19%
545,300.00 545,300.00 0.08% 0.00% 0.08%

45,520,000.00 45,520,000.00 6.79% 0.00% 6.79%


2,194,500.00 2,194,500.00 0.33% 0.00% 0.33%
9,945,787.50 9,945,787.50 1.48% 0.00% 1.48%
85,063,796.25 85,063,796.25 12.70% 1.17% 11.53%
264,378,466.88 93,201,576.50 39.46% 27.93% 11.53%

300,000.00 - 0.04% 100 0.04% 0.00%


2,000,000.00 - 0.30% 100 0.30% 0.00%
1,200,000.00 - 0.18% 100 0.18% 0.00%
100,000.00 - 0.01% 100 0.01% 0.00%
2,000,000.00 - 0.30% 100 0.30% 0.00%
160,000.00 - 0.02% 100 0.02% 0.00%
1,407,000.00 - 0.21% 100 0.21% 0.00%

700,000.00 - 0.10% 100 0.10% 0.00%


500,000.00 - 0.07% 100 0.07% 0.00%
750,000.00 - 0.11% 100 0.11% 0.00%
125,000.00 - 0.02% 100 0.02% 0.00%
100,000.00 (10,000) 0.01% 100 0.01% 0.00%
195,000.00 - 0.03% 100 0.03% 0.00%
375,000.00 - 0.06% 100 0.06% 0.00%
9,912,000.00 (10,000) 1.48% 1.48% 0.00%

270,000.00 - 0.04% - 0.00% 0.04%


250,000.00 - 0.04% - 0.00% 0.04%
150,000.00 - 0.02% 100.00 0.02% 0.00%
80,000.00 - 0.01% 100.00 0.01% 0.00%
500,000.00 - 0.07% - 0.00% 0.07%
250,000.00 - 0.04% 100.00 0.04% 0.00%
1,500,000.00 - 0.22% 0.07% 0.15%

670,023,948 19,013 100% 84.94% 15.06%

670,000,000 -

Pekerjaan tambah kurang


Jumlah Harga
148,447,570.71 (15,235,099.85) 22.16%
245,785,910.53 33.30%
- (107,878,507.67) 0.00%
52,447,456.33 (16,668,089.85) 7.60%
193,338,454.20 46,609,133.58 25.70%
264,378,466.88 27.93%
179,314,670.63 8,137,780.25 26.76%
85,063,796.25 85,063,796.25 1.17%
9,912,000.00 (10,000.00) 1.48%
1,500,000.00 - 0.07%

670,023,948.11 19,012.72

670,000,000.00 -
148,440,000
245,780,000

264,370,000

9,910,000
1,500,000

670,000,000
PERHITUNGAN VOLUME PEKERJAAN TAMBAH KURANG

PROGRAM : KOTA TANPA KUMUH (KOTAKU)


KEGIATAN : DFAT
LOKASI : KERENG BANGKIRAI
KEGIATAN : Jalan dan Drainase
TAHUN ANGGARAN : 2021

JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase Panjang Lebar Tinggi 42.04 m3
D. Tertutup = 103.40 m x 0.70 m x 0.70 m x 75% = 38.00 m3
D.Terbuka I = 2.80 m x 0.70 m x 0.70 m x 75% = 1.03 m3
D. Bwh Paving = 3.30 m x 0.70 m x 0.70 m x 75% = 1.21 m3
D. Terbuka II = 8.70 m x 0.50 m x 0.55 m x 75% = 1.79 m3
2 Pek. Dinding Saluran
a. Pek. Pembesian Panjang Berat jenis Jumlah 1,353.82 Kg
- Besi ø 10 D. Tertutup Kiri memanjang = 103.40 m x 0.617 kg/m x 5 = 318.99 Kg
Kanan memanjang = 103.40 m x 0.617 kg/m x 5 = 318.99 Kg
Melintang = 1.3 m x 0.617 kg/m x 690 = 553.45 Kg

D.Terbuka I Kiri memanjang = 2.80 m x 0.617 kg/m x 5 = 8.64 Kg


Kanan memanjang = 1.40 m x 0.617 kg/m x 5 = 4.32 Kg
Melintang = 1.3 m x 0.617 kg/m x 14 = 11.23 Kg

D. Bwh Paving Kiri memanjang = 3.30 m x 0.617 kg/m x 5 = 10.18 Kg


Kanan memanjang = 3.30 m x 0.617 kg/m x 5 = 10.18 Kg
Melintang = 1.3 m x 0.617 kg/m x 22 = 17.65 Kg

D. Terbuka II Kiri memanjang = 8.70 m x 0.617 kg/m x 5 = 26.84 Kg


Kanan memanjang = 8.70 m x 0.617 kg/m x 5 = 26.84 Kg
Melintang = 1.3 m x 0.617 kg/m x 58 = 46.52 Kg

b. Pek, Bekisting Panjang Lebar Sisi 107.35 m2


D. Tertutup Kiri = 103.40 m x 0.70 m x 2 m x 1/3 = 48.25 m2
Kanan = 103.40 m x 0.70 m x 2 m x 1/3 = 48.25 m2

D.Terbuka I Kiri = 2.80 m x 0.70 m x 2 m x 1/3 = 1.31 m2


Kanan = 1.40 m x 0.70 m x 2 m x 1/3 = 0.65 m2

D. Bwh Paving Kiri = 3.30 m x 0.70 m x 2 m x 1/3 = 1.54 m2


Kanan = 3.30 m x 0.70 m x 2 m x 1/3 = 1.54 m2

D. Terbuka II Kiri = 8.70 m x 0.50 m x 2 m x 1/3 = 2.90 m2


Kanan = 8.70 m x 0.50 m x 2 m x 1/3 = 2.90 m2

c. Cor beton K-175 Panjang Lebar Tebal 16.45 m3


D. Tertutup Kiri = 103.40 m x 0.70 m x 0.10 m = 7.24 m3
Kanan = 103.40 m x 0.70 m x 0.10 m = 7.24 m3

D.Terbuka I Kiri = 2.80 m x 0.70 m x 0.10 m = 0.20 m3


Kanan = 1.40 m x 0.70 m x 0.10 m = 0.10 m3

D. Bwh Paving Kiri = 3.30 m x 0.70 m x 0.10 m = 0.23 m3


Kanan = 3.30 m x 0.70 m x 0.10 m = 0.23 m3

D. Terbuka II Kiri = 8.70 m x 0.70 m x 0.10 m = 0.61 m3


Kanan = 8.70 m x 0.70 m x 0.10 m = 0.61 m3

3 Pek. Lantai saluran


a. Pek. Pembesian Panjang Berat jenis Jumlah 671.54 Kg
- Besi ø 10 D. Tertutup Memanjang = 103.40 m x 0.617 kg/m x 5 = 318.99 Kg
Melintang = 0.65 m x 0.617 kg/m x 690 = 276.72 Kg

D.Terbuka I Memanjang = 2.10 m x 0.617 kg/m x 5 = 6.48 Kg


Melintang = 0.65 m x 0.617 kg/m x 14 = 5.61 Kg

D. Bwh Paving Memanjang = 3.30 m x 0.617 kg/m x 5 = 10.18 Kg


Melintang = 0.65 m x 0.617 kg/m x 22 = 8.82 Kg

D. Terbuka II Memanjang = 8.70 m x 0.617 kg/m x 5 = 26.84 Kg


Melintang = 0.5 m x 0.617 kg/m x 58 = 17.89 Kg

b. Plastik Cor Panjang Lebar 81.00 m2


D. Tertutup = 103.40 m x 0.70 = 72.38 m2
D.Terbuka I = 2.80 m x 0.70 = 1.96 m2
D. Bwh Paving = 3.30 m x 0.70 = 2.31 m2
D. Terbuka II = 8.70 m x 0.50 = 4.35 m2

c. Cor beton K-175 Panjang Lebar Tebal 8.10 m3


D. Tertutup = 103.40 m x 0.70 m x 0.10 m = 7.24 m3
D.Terbuka I = 2.80 m x 0.70 m x 0.10 m = 0.20 m3
D. Bwh Paving = 3.30 m x 0.70 m x 0.10 m = 0.23 m3
D. Terbuka II = 8.70 m x 0.50 m x 0.10 m = 0.44 m3

4 Pek. Penutup saluran


a. Pek. Pembesian Panjang Berat jenis Jumlah 614.72 Kg
- Besi ø 10 D. Tertutup Memanjang = 103.40 m x 0.617 kg/m x 5 = 318.99 Kg
Melintang = 0.65 m x 0.617 kg/m x 690 = 276.72 Kg

D. Bwh Paving Memanjang = 3.30 m x 0.617 kg/m x 5 = 10.18 Kg


Melintang = 0.65 m x 0.617 kg/m x 22 = 8.82 Kg

b. Pek. Bekisting Panjang Lebar 32.01 m2


D. Tertutup Memanjang = 103.40 m x 0.70 m x 1/3 = 24.13 m2
Kiri = 103.40 m x 0.10 m x 1/3 = 3.45 m2
Kanan = 103.40 m x 0.10 m x 1/3 = 3.45 m2
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
D. Bwh Paving Memanjang = 3.30 m x 0.70 m x 1/3 = 0.77 m2
Kiri = 3.30 m x 0.10 m x 1/3 = 0.11 m2
Kanan = 3.30 m x 0.10 m x 1/3 = 0.11 m2

c. Cor beton K-175 Panjang Lebar Tebal 7.47 m3


D. Tertutup = 103.40 m x 0.70 m x 0.10 m = 7.24 m3

D. Bwh Paving = 3.30 m x 0.70 m x 0.10 m = 0.23 m3

6 Pek. Biopori untuk resapan = 24.00 Bh = 24.00 Bh

7 Pek. Besi untuk handle tutup saluran Pasang Kiri-kanan = 85.00 Bh / 2.00 Bh = 42.50 Bh

8 Pekerjaan Acian Panjang Lebar 72.38 m2


= 89.40 m x 0.70 m = 62.58 m2
= 14.00 m x 0.70 m = 9.80 m2
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
II PEKERJAAN JALAN PAVING BLOCK
A Segmen A Jl. Bara Bere Panjang 42 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah Panjang Lebar Sisi 10.88 m2
= 34.00 m x 0.16 m x 2 = 10.88 m2

2 Pekerjaan Ring Balok 10/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 256.42 Kg
- Besi ø 10 Besi ø 10 = 42.00 m x 0.617 kg/m x 4.00 Bh x 2 = 207.31 Kg
- Besi ø 8 Besi ø 8 = 0.37 m x 0.395 kg/m x 168.00 Bh x 2 = 49.11 Kg

b. Pek, Bekisting Panjang Lebar Jumlah Bekisting Jumlah sisi 8.40 m2


= 42.00 m x 0.15 m x 2 Bh x 2 x 1/3 = 8.40 m2

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 1.26 m3


= 42.00 m x 0.10 m x 0.15 m x 2 = 1.26 m3

3 Pek. Timbunan/Urugan Tanah Panjang Lebar Tebal segitiga Jumlah 17.41 m3


= 34.00 m x 2 m x 0.16 m x 2 = 17.41 m3

4 Pek. Kolom praktis 15/15


a. Pembesian Panjang Berat Jenis Jumlah besi Jumlah 31.09 Kg
Titik 1 Besi ø 10 = 0.65 m x 0.617 kg/m x 4 Bh x 2 = 3.21 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 4 Bh x 2 = 1.07 Kg
Titik 2 Besi ø 10 = 0.61 m x 0.617 kg/m x 4 Bh x 2 = 3.01 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 4 Bh x 2 = 1.07 Kg
Titik 3 Besi ø 10 = 0.57 m x 0.617 kg/m x 4 Bh x 2 = 2.81 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 3 Bh x 2 = 0.81 Kg
Titik 4 Besi ø 10 = 0.53 m x 0.617 kg/m x 4 Bh x 2 = 2.62 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 3 Bh x 2 = 0.81 Kg
Titik 5 Besi ø 10 = 0.49 m x 0.617 kg/m x 4 Bh x 2 = 2.42 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 3 Bh x 2 = 0.81 Kg
Titik 6 Besi ø 10 = 0.45 m x 0.617 kg/m x 4 Bh x 2 = 2.22 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 3 Bh x 2 = 0.81 Kg
Titik 7 Besi ø 10 = 0.41 m x 0.617 kg/m x 4 Bh x 2 = 2.02 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 3 Bh x 2 = 0.81 Kg
Titik 8 Besi ø 10 = 0.37 m x 0.617 kg/m x 4 Bh x 2 = 1.83 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 2 Bh x 2 = 0.54 Kg
Titik 9 Besi ø 10 = 0.34 m x 0.617 kg/m x 4 Bh x 2 = 1.68 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 2 Bh x 2 = 0.54 Kg
Titik 10 Besi ø 10 = 0.30 m x 0.617 kg/m x 4 Bh x 2 = 1.48 Kg
Besi ø 8 = 0.34 m x 0.395 kg/m x 2 Bh x 2 = 0.54 Kg
- Besi ø 10 23.30 Kg
- Besi ø 8 7.79 Kg

b Pek, Bekisting Panjang Lebar Jumlah 0.47 m2


Titik 1 = 0.65 m x 0.10 m x 2 Bh x 1/2 = 0.07 m2
Titik 2 = 0.61 m x 0.10 m x 2 Bh x 1/2 = 0.06 m3
Titik 3 = 0.57 m x 0.10 m x 2 Bh x 1/2 = 0.06 m4
Titik 4 = 0.53 m x 0.10 m x 2 Bh x 1/2 = 0.05 m5
Titik 5 = 0.49 m x 0.10 m x 2 Bh x 1/2 = 0.05 m6
Titik 6 = 0.45 m x 0.10 m x 2 Bh x 1/2 = 0.05 m7
Titik 7 = 0.41 m x 0.10 m x 2 Bh x 1/2 = 0.04 m8
Titik 8 = 0.37 m x 0.10 m x 2 Bh x 1/2 = 0.04 m8
Titik 9 = 0.34 m x 0.10 m x 2 Bh x 1/2 = 0.03 m8
Titik 10 = 0.30 m x 0.10 m x 2 Bh x 1/2 = 0.03 m8

c Cor Beton K.175 Panjang Lebar Tebal Jumlah 0.21 m3


Titik 1 = 0.65 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 2 = 0.61 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 3 = 0.57 m x 0.15 m x 0.15 m x 2 = 0.03 m3
Titik 4 = 0.53 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 5 = 0.49 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 6 = 0.45 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 7 = 0.41 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 8 = 0.37 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 9 = 0.34 m x 0.15 m x 0.15 m x 2 = 0.02 m3
Titik 10 = 0.30 m x 0.15 m x 0.15 m x 2 = 0.01 m3

Luas
Guiding
5 Pekerjaan Paving Block Panjang Lebar Block 52.20 m2
= 42.00 m x 1.60 m - 15.00 = 52.20 m3

6 Pek. Pas Buis Beton dia. 50 x 100cm = 4.00 Bh = 4.00 Bh

7 Pek. Guiding block dan warning block precast Panjang 143.00 m


=( 137 bh + 6.00 bh ) = 143.00 m

8 Coating epoxy resin untuk guiding block = 143.00 x 0.30 = 42.90 M2


###
C Segmen C Panjang 116 M (Gg Husada)
1 Pas Dinding Bata Tebal 1/2 Bata pengunci paving Panjang Tinggi 81.20 m2
Panjang 95 m Kiri = 91.00 m x 0.35 m = 31.85 m2
Kanan = 91.00 m x 0.35 m = 31.85 m2

Tikungan Kiri = 17.00 m x 0.35 m = 5.95 m2


Kanan = 17.00 m x 0.35 m = 5.95 m2

Lanjutan paving Kiri = 8.00 m x 0.35 m = 2.80 m2


Kanan = 8.00 m x 0.35 m = 2.80 m2

2 Pek. Plesteran Dinding Bata Panjang Lebar 28.20 m2


Panjang 95 m Kiri = 91.00 m x 0.10 m = 9.10 m2
Kanan = 91.00 m x 0.10 m = 9.10 m2

Tikungan Kiri = 17.00 m x 0.20 m = 3.40 m2


Kanan = 17.00 m x 0.20 m = 3.40 m2

Lanjutan paving Kiri = 8.00 m x 0.20 m = 1.60 m2


Kanan = 8.00 m x 0.20 m = 1.60 m2
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
3 Pekerjaan Paving Block Panjang Lebar 431.79 m2
= 10.70 m x 3.70 m = 39.59 m3
= 80.30 m x 3.70 m = 297.11 m3
= 0.70 m x 3.70 m = 2.59 m3
= 17.00 m x 3.70 m = 62.90 m3
= 8.00 m x 3.70 m = 29.60 m3

6 Pek. Pipa AW 4" (saluran gorong-gorong) = 5 m = 5.00 m

5 Pek. Guiding block dan warning block precast Panjang 121.50 m


=( 360 bh + 45.00 bh )x 0.30 = 121.50 m

6 Coating epoxy resin untuk guiding block = 121.50 m x 0.30 = 36.45 m2

III PEKERJAAN JALAN TITIAN KAYU


A Segmen A, 80 M (Jl. M.Usin)
1 Pekerjaan Rangka Bawah III PEKERJAAN JALAN TITIAN
a Pek. Pas Tongkat Kayu 10/10 Titian Panjang Lebar Tebal Jumlah Ki-Ka 1.48 m3 1 Pekerjaan Rangka Bawah
12.5 = 1.40 m x 0.10 m x 0.10 m x 16 Bh = 0.22 m3 a Pek. Pas Tongkat Kayu
5= 1.40 m x 0.10 m x 0.10 m x 6 Bh = 0.08 m3
56.5 = 1.40 m x 0.10 m x 0.10 m x 76 Bh = 1.06 m3
3= 1.40 m x 0.10 m x 0.10 m x 4 Bh = 0.06 m3
3= 1.40 m x 0.10 m x 0.10 m x 4 Bh = 0.06 m3 b Pek Gelagar memanjang

b Pek Gelagar memanjang Titian Panjang Lebar Tebal Jumlah 1.60 m3


12.5 = 12.50 m x 0.05 m x 0.10 m x 4 Bh = 0.25 m3
5= 5.00 m x 0.05 m x 0.10 m x 4 Bh = 0.10 m3 c Pek. Gelagar melintang
56.5 = 56.50 m x 0.05 m x 0.10 m x 4 Bh = 1.13 m3
3= 3.00 m x 0.05 m x 0.10 m x 4 Bh = 0.06 m3
3= 3.00 m x 0.05 m x 0.10 m x 4 Bh = 0.06 m3
d Pek. Kacapuri

e Pekerjaan sunduk

e Pasangan Mur dan Baut


b Pek Gelagar memanjang

c Pek. Gelagar melintang

JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5 d Pek. Kacapuri
c Pek. Gelagar melintang Titian Panjang Lebar Tebal Jumlah 0.49 m3
12.5 = 1.80 m x 0.05 m x 0.10 m x 8 Bh = 0.07 m3
5= 1.80 m x 0.05 m x 0.10 m x 4 Bh = 0.04 m3
56.5 = 1.80 m x 0.05 m x 0.10 m x 38 Bh = 0.34 m3 e Pekerjaan sunduk
3= 1.80 m x 0.05 m x 0.10 m x 2 Bh = 0.02 m3
3= 1.80 m x 0.05 m x 0.10 m x 2 Bh = 0.02 m3

d Pek. Kacapuri Titian Panjang Lebar Tebal Jumlah Jumlah tongkat 0.74 m3 e Pasangan Mur dan Baut
12.5 = 0.50 m x 0.05 m x 0.07 m x 4 x 16 = 0.11 m3
5= 0.50 m x 0.05 m x 0.07 m x 4 x 6 = 0.04 m3
56.5 = 0.50 m x 0.05 m x 0.07 m x 4 x 76 = 0.53 m3
3= 0.50 m x 0.05 m x 0.07 m x 4 x 4 = 0.03 m3
3= 0.50 m x 0.05 m x 0.07 m x 4 x 4 = 0.03 m3

e Pekerjaan sunduk Titian Panjang Lebar Tebal Jumlah Jumlah tongkat 0.19 m3
12.5 = 0.50 m x 0.05 m x 0.07 m x 1 x 16 = 0.03 m3
5= 0.50 m x 0.05 m x 0.07 m x 1 x 6 = 0.01 m3
56.5 = 0.50 m x 0.05 m x 0.07 m x 1 x 76 = 0.13 m3
3= 0.50 m x 0.05 m x 0.07 m x 1 x 4 = 0.01 m3
3= 0.50 m x 0.05 m x 0.07 m x 1 x 4 = 0.01 m3

2 Pekerjaan Rangka Badan, Lantai dan Railing Titian Panjang Lebar Panjang 168.80 m2
a Pek. Pas. Lantai Papan Tebal 2 Cm 12.5 = 12.50 m x 2.00 m x 63.00 = 25.00 m2
Kayu Klas I, Uk. 2/20 Cm 5= 5.00 m x 2.00 m x 26.00 = 10.00 m2
56.5 = 56.50 m x 2.00 m x 281.00 = 113.00 m2
3= 3.00 m x 2.00 m x 15.00 = 6.00 m2
3= 3.00 m x 2.00 m x 15.00 = 6.00 m2

Tambatan Perahu = 4.00 m x 0.20 m x 9.00 keping = 7.20 m2


= 4.00 m x 0.20 m x 2.00 keping = 1.60 m2

b Pek. Balok Pengunci Lantai Papan uk. 5/7 Titian Panjang Lebar Tebal Jumlah 0.58 m3
12.5 = 12.50 m x 0.05 m x 0.07 m x 2 = 0.09 m3
5= 5.00 m x 0.05 m x 0.07 m x 2 = 0.04 m3
56.5 = 56.50 m x 0.05 m x 0.07 m x 2 = 0.40 m3
3= 3.00 m x 0.05 m x 0.07 m x 2 = 0.02 m3
3= 3.00 m x 0.05 m x 0.07 m x 2 = 0.02 m3

Tambatan Perahu = 2.00 m x 0.05 m x 0.07 m x 2 = 0.01 m3


= 0.35 m x 0.05 m x 0.07 m x 2 = 0.00 m3

c Pekerjaan pagar reling Panjang Lebar Tebal Jumlah 4.86 m3


Titian Tiang pagar uk. 5/10
12.5 5/10 = 1.25 m x 0.05 m x 0.10 m x 18 = 0.11 m3
5 5/10 = 1.25 m x 0.05 m x 0.10 m x 8 = 0.05 m3
56.5 5/10 = 1.25 m x 0.05 m x 0.10 m x 76 = 0.48 m3
3 5/10 = 1.25 m x 0.05 m x 0.10 m x 4 = 0.03 m3
3 5/10 = 1.25 m x 0.05 m x 0.10 m x 4 = 0.03 m3

Tambatan Perahu 5/10 = 1.25 m x 0.05 m x 0.10 m x 8 = 0.05 m3

Titian Pagar reling 5/7


12.5 5/7 = 0.70 m x 0.05 m x 0.10 m x 72 = 0.25 m3
12.5 5/7 = 1.15 m x 0.05 m x 0.10 m x 72 = 0.41 m3
5 5/7 = 0.70 m x 0.05 m x 0.10 m x 32 = 0.11 m3
5 5/7 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3
56.5 5/7 = 0.70 m x 0.05 m x 0.10 m x 304 = 1.06 m3
56.5 5/7 = 1.15 m x 0.05 m x 0.10 m x 304 = 1.75 m3
3 5/7 = 0.70 m x 0.05 m x 0.10 m x 16 = 0.06 m3
3 5/7 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3
3 5/7 = 0.70 m x 0.05 m x 0.10 m x 16 = 0.06 m3
3 5/7 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3

Tambatan Perahu 5/7 = 0.70 m x 0.05 m x 0.10 m x 16 = 0.06 m3


5/7 = 1.15 m x 0.05 m x 0.10 m x 16 = 0.09 m3

4 Pekerjaan tambatan perahu


a Pek. Pas Tongkat Kayu Ulin 10/10 Panjang Lebar Tebal Jumlah 0.16 m3
Tambatan Perahu = 1.30 m x 0.10 m x 0.10 m x 12 Bh = 0.16 m3

b Pek Gelagar memanjang Panjang Lebar Tebal Jumlah 0.05 m3


Tambatan Perahu = 1.80 m x 0.05 m x 0.10 m x 4 Bh = 0.04 m3
= 0.35 m x 0.05 m x 0.10 m x 8 Bh = 0.01 m3

d Pek. Kacapuri Panjang Lebar Tebal Jumlah Jumlah tongkat 0.02 m3


Tambatan Perahu = 0.50 m x 0.05 m x 0.10 m x 4 x 4 = 0.01 m3
= 0.50 m x 0.05 m x 0.10 m x 4 x 8 = 0.01 m3

e Pekerjaan sunduk Panjang Lebar Tebal Jumlah Jumlah tongkat 0.004 m3


Tambatan Perahu = 0.50 m x 0.05 m x 0.07 m x 1 x 4 = 0.002 m3
= 0.50 m x 0.05 m x 0.07 m x 1 x 8 = 0.002 m3

5 Pasangan Mur dan Baut 14/22


= 80.00 x 0.70 = 56.00 Kg
6 Pas. Ring Baut
= 56.00 = 56.00 Kg

A Segmen B 40 M (Jl. Hadri Embang)


1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 P. Titian Panjang pancang Lebar Tebal Jumlah Ki-Ka 1.08 m3
30 = 2.00 m x 0.10 m x 0.10 m x 40 Bh = 0.80 m3
10 = 2.00 m x 0.10 m x 0.10 m x 14 Bh = 0.28 m3

b Pek Gelagar memanjang (sloof) P. Titian Panjang Lebar Tebal Jumlah 0.80 m3
40 = 40.00 m x 0.05 m x 0.10 m x 4 Bh = 0.80 m3

c Pek. Gelagar melintang P. Titian Panjang Lebar Tebal Jumlah 0.40 m3


40 = 2.00 m x 0.05 m x 0.10 m x 40 Bh = 0.40 m3
JUMLAH
NO URAIAN PEKERJAAN PERHITUNGAN VOLUME SATUAN

1 2 3 4 5
d Pek. Kacapuri P. Titian Panjang Lebar Tebal Jumlah Jumlah tongkat 0.38 m3
40 = 0.50 m x 0.05 m x 0.07 m x 4 x 54 = 0.38 m3

e Pekerjaan sunduk P. Titian Panjang Lebar Tebal Jumlah Jumlah tongkat 0.09 m3
40 = 0.50 m x 0.05 m x 0.07 m x 1 x 54 = 0.09 m3

f Pekerjaan balok suai Panjang Lebar Tebal Jumlah Jumlah ruas 0.51 m3
Memanjang 40 = 3.50 m x 0.05 m x 0.07 m x 2 x 13 = 0.32 m3
= 1.84 m x 0.05 m x 0.07 m x 2 x = - m3
Melintang 40 = 2.10 m x 0.05 m x 0.07 m x 2 x 13 = 0.19 m3
g Pasangan Mur dan Baut 14/22
= 41.00 x 0.70 = 28.70 Kg

h Pas. Ring Baut


= 28.70 = 28.70 Kg

2 Pekerjaan Rangka Badan, Lantai dan Railing Panjang Lebar 80.00 m2


a Pek. Pas. Lantai Papan Tebal 2 Cm 40 = 40.00 m x 2.00 m = 80.00 m2
Kayu Klas I, Uk. 2/20 Cm =

b Pek. Balok Pengunci Lantai Papan uk. 5/7 Panjang Lebar Tebal Jumlah 0.28 m3
40 = 40.00 m x 0.05 m x 0.07 m x 2 = 0.28 m3

c Pekerjaan pagar reling Panjang Lebar Tebal Jumlah 1.27 m3


Tiang & Railing Pagar uk. 5/10 ki-ka
40 = 2.70 m x 0.05 m x 0.10 m x 54 = 0.73 m3

Pagar dalam reling 5/5


40 = 1.40 m x 0.05 m x 0.05 m x 54 = 0.19 m3
40 = 2.60 m x 0.05 m x 0.05 m x 54 = 0.35 m3

XI KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) = 4.00 4.00 Bh
2 Helm Keselamatan = 20.00 20.00 Bh
3 Rompi Kerja = 20.00 20.00 Bh
4 Sarung Tangan (Safety Glove) = 20.00 20.00 Bh
5 Sepatu Keselamatan (Rubber Shoes) = 20.00 20.00 Bh
6 Kotak P3K = 3.00 3.00 Bh
7 Asuransi Tenaga Kerja = 1.00 1.00 Paket
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) = 2.00 2.00 Bh
2 Vitamin C (1 Box isi 100 tablet) = 25.00 25.00 Bh
3 Tempat Cuci Tangan = 2.00 2.00 Bh
4 Sabun Cuci Tangan (Cair) 200ml/btl = 6.00 6.00 Bh
5 Masker kain = 25.00 25.00 Bh
6 Alat penyemprot desinfektan = 2.00 2.00 Bh
7 Cairan Desinfektan 5L = 5.00 5.00 Bh

XII ADMINISTRASI KEGIATAN


1 Pelaporan KSM = 1.00 1.00 Ls
2 Photo Copy / Penggandaan = 1.00 1.00 Ls
3 Biaya Alat Tulis Kantor (ATK) = 1.00 1.00 Ls
4 Materai = 9.00 9.00 Bh
5 Papan Nama Kegiatan = 1.00 1.00 Paket
Form - RAB1
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT PROGRAM KOTA TANPA KUMUH (KOTAKU)
HASIL KESEPAKATAN HARGA SATUAN UPAH/BAHAN/ALAT
BULAN :
Provinsi : Kalimantan Tengah Kecamatan : Sebangau
Kota : Palangka Raya Kelurahan : Kereng Bangkirai

HARGA SATUAN
SESUAI
No. Uraian Tenaga Kerja Satuan STANDAR
KOTA/KABUPAT
EN
I. TENAGA KERJA
1 Mandor HOK 225,000
2 Kepala Tukang HOK 170,000
3 Tukang Batu HOK 155,000
4 Tukang Kayu HOK 150,000
5 Tukang Besi HOK 150,000
6 Tukang Cat HOK 150,000
7 Pekerja HOK 140,000

REKOMENDASI HARGA
HARGA SATUAN HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
SESUAI UNTUK BULAN INI
No. Uraian Tenaga Kerja Satuan STANDAR Toko/Pemasok -1 Toko/Pemasok - 2 Toko/Pemasok - 3
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA Almt : Almt : Almt : SATUAN*) Toko/Pemasok
Telp : Telp : Telp :

II. BAHAN/MATERIAL :
1 Cat Plitur Kayu Kg 75,000.00 73,000.00
2 Cat dasar kayu platone Kg 62,400.00 60,000.00
3 Cat penutup kayu platone Kg 62,400.00 60,000.00
4 Cat tembok Jotun Kg 120,000.00 110,000.00
5 Kerikil (Maks 30mm) m3 475,000.00 450,000.00
6 Kwas 4" Bh 45,000.00 45,000.00
7 Paku 5 - 12 cm Kg 22,000.00 22,000.00
8 Pasir beton m3 200,000.00 180,000.00
9 Pasir Pasang m3 190,000.00 150,000.00
10 Semen Portland Kg 1,325.00 1,275.00
11 Semen Portland Gresik 40 Kg/zak 53,000.00 51,000.00
12 Minyak Cat/Thinner Cemerlang Kg 28,100.00 28,100.00
13 Ampelas Kayu Flexigo Lbr 10,000.00 10,000.00
14 Papan Informasi Kegiatan Lbr 200,000.00 200,000.00
15 Bata Merah Bh 1,200.00 1,000.00
16 Tanah Urug m3 100,000.00 100,000.00
17 Besi Beton Polos Kg 12,000.00 12,000.00
Besi Beton Polos d.10 P= 12m Btg/12m 70,500.00 -
Besi Beton Polos d.8 P= 12m Btg/12m 47,000.00 -
18 Besi Beton Polos d.6 P= 12m Btg/12m 30,000.00 -
19 Plywood Lbr 130,000.00 130,000.00
20 Keramik lantai uk.30x30 Doz 72,100.00 72,100.00
21 Plastik cor/bks Bks 60,000.00 60,000.00
22 Paving blok tebal 8 cm Bh 7,650.00 7,500.00
23 Baut/Mur Kg 45,000.00
Ring Baut Kg 19,000.00
24 Buis Beton 40x100 tebal 5 cm Bh 120,000.00 120,000.00
25 Guiding block Bh 38,000.00
26 pipa + tutup Biopori 4 inchi Bh 50,000.00 50,000.00
27 GRC Board tebal 8 mm Lbr 190,000.00 190,000.00
28 Besi ø 12 untuk handle tutup saluran bh 15,000.00 25,000.00
29 Biopori Bh 70,000.00
30

REKOMENDASI HARGA
HARGA SATUAN HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
SESUAI UNTUK BULAN INI
No. Uraian Tenaga Kerja Satuan STANDAR Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3
KABUPATEN/KO Nama: Nama: Nama: HARGA Nama
TA Almt : Almt : Almt : SATUAN*) Toko/Pemasok
Telp : Telp : Telp :
1 Balok Kayu Klas II (Lanan) m3 4,000,000.00 4,000,000.00 4,000,000.00
2 Papan Kayu Klas II (Lanan) m3 5,000,000.00 5,000,000.00 5,000,000.00
3 Papan Kayu Klas II (Benuas) m3 6,500,000.00 6,000,000.00 6,000,000.00
4 Balok Kayu Klas II (Benuas) m3 5,500,000.00 5,250,000.00 5,250,000.00
5 Balok Kayu Klas III m3 2,250,000.00 2,200,000.00 2,200,000.00
6 Papan Kayu Klas III m3 2,500,000.00 2,450,000.00 2,450,000.00
7 Kayu Galam diameter 6-10 cm P=4 m Batang 30,000.00 30,000.00 30,000.00
REKOMENDASI HARGA
HARGA SATUAN HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3 UNTUK BULAN INI
No. Uraian Tenaga Kerja Satuan STANDAR Nama: Nama: Nama: HARGA Nama
KABUPATEN/KO Almt : Almt : Almt : SATUAN*) Toko/Pemasok
TA Telp : Telp : Telp :

III. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


1 Sosialisasi K3 dan Prokes (Spanduk) 75,000.00
2 Helm Keselamatan 100,000.00
3 Rompi Kerja 60,000.00
4 Sarung Tangan (Safety Glove) 5,000.00
5 Sepatu Keselamatan (Rubber Shoes) 100,000.00
6 Kotak P3K 40,000.00
7 Asuransi Tenaga Kerja 673,500.00
8 Alat ukur suhu badan nir-sentuh (Thermoscan) 350,000.00
9 Vitamin C (1 Box isi 100 tablet) 25,000.00
10 Tempat Cuci Tangan 250,000.00
11 Sabun Cuci Tangan (Cair) 200ml/btl 25,000.00
12 Masker kain 5,000.00
13 Alat penyemprot desinfektan 65,000.00
14 Cairan Desinfektan 5L 75,000.00

REKOMENDASI HARGA
HARGA SATUAN HARGA SATUAN HASIL SURVEY*) TERENDAH YANG DIPILIH
SESUAI Toko/Pemasok - 1 Toko/Pemasok - 2 Toko/Pemasok - 3 UNTUK BULAN INI
No. Uraian Tenaga Kerja Satuan STANDAR Nama: Nama: Nama: HARGA Nama
KABUPATEN/KO Almt : Almt : Almt : SATUAN*) Toko/Pemasok
TA Telp : Telp : Telp :

XIX ADMINISTRASI KEGIATAN


1 Pelaporan KSM Rp 270,000
2 Photo Copy / Penggandaan Rp 250,000
3 Biaya Alat Tulis Kantor (ATK) Rp 150,000
4 Materai Rp 10,000
5 Pengujian Lab Rp 500,000
6 Papan Nama Kegiatan Rp 250,000

*) Harga Satuan sampai dilokasi Kegiatan (sudah termasuk biaya Transport)


…………., Tgl. …………….20…..

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-2

BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT PROGRAM KOTA TANPA KUMUH (KOTA
DAFTAR KUANTITAS PEKERJAAN
PAKET : JALAN DAN DRAINASE

Kab./Kota : Palangka Raya Kelurahan : Kereng Bangkirai


Kecamatan : Sebangau BKM : Kereng Membangun

NO. URAIAN PEKERJAAN SATUAN VOLUME

I PEKERJAAN DRAINASE
1. Pek. Galian Drainase m3 42.04
2. Pek. Dinding Saluran
a. Pek. Pembesian Kg 1353.82
b Pek, Bekisting m2 107.35
c. Cor beton K-175 m3 16.45
3. Pek. Lantai saluran
a. Pek. Pembesian Kg 671.54
b Plastik Cor m2 81.00
c. Cor beton K-175 m3 8.10
4. Pek. Penutup saluran
a. Pek. Pembesian Kg 614.72
b Pek. Bekisting m2 32.01
c. Cor beton K-175 m3 7.47
5. Pek. Biopori untuk resapan Bh 24.00
6. Pek. Besi untuk handle tutup saluran Bh 85.00
7. Pekerjaan Acian m2 72.38

II PEKERJAAN JALAN PAVING BLOCK


A Segmen A Jl. Bara Bere Panjang 42 M
1. Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 10.88
2. Pekerjaan Ring Balok 10/15
a Pembesian Kg 256.42
b Pek, Bekisting m2 8.40
c Cor Beton K.175 m3 1.26
3. Pek. Timbunan/Urugan Tanah m3 17.41
4. Pek. Kolom praktis 15/15
a Pembesian Kg 31.09
b Pek, Bekisting m2 0.47
c Cor Beton K.175 m3 0.21
5. Pekerjaan Paving Block m2 52.20
6. Pek. Pas Buis Beton dia. 50 x 100cm Bh 4.00
7. Pek. Guiding block dan warning block precast m 143.00
8. Coating guiding block & warning block m2 42.90
NO. URAIAN PEKERJAAN SATUAN VOLUME

C Segmen C Panjang 116 M (Gg Husada)


1. Pas Dinding Bata Tebal 1/2 Bata pengunci paving m2 81.20
2. Pek. Plesteran Dinding Bata m2 28.20
3. Pekerjaan Paving Block m2 431.79
4. Pek. Pipa AW 4" (saluran gorong-gorong) m 5.00
5. Pek. Guiding block dan warning block precast m 121.50
6. Coating guiding block & warning block m2 36.45

III PEKERJAAN JALAN TITIAN KAYU


A Segmen A, 80 M (Jl. M.Usin)
1. Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.48
b Pek Gelagar memanjang m3 1.60
c Pek. Gelagar melintang m3 0.49
d Pek. Kacapuri m3 0.74
e Pekerjaan sunduk m3 0.19
2. Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 168.80
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.58
c Pekerjaan pagar reling m3 4.86
3. Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 0.16
b Pek Gelagar memanjang m3 0.05
c Pek. Kacapuri m3 0.02
d Pekerjaan sunduk m3 0.00
4. Pasangan Mur dan Baut 14/22 Kg 56.00
5. Pas. Ring Baut Kg 56.00

B Segmen B 40 M (Jl. Hadri Embang)


1. Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.08
b Pek Gelagar memanjang (sloof) m3 0.80
c Pek. Gelagar melintang m3 0.40
d Pek. Kacapuri m3 0.38
e Pekerjaan sunduk m3 0.09
f Pekerjaan balok suai m3 0.51
g Pasangan Mur dan Baut 14/22 Kg 28.70
h. Pas. Ring Baut Kg 28.70
2. Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 80.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.28
c Pekerjaan pagar reling m3 1.27
NO. URAIAN PEKERJAAN SATUAN VOLUME

IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1. Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00
2. Helm Keselamatan Bh 20.00
3. Rompi Kerja Bh 20.00
4. Sarung Tangan (Safety Glove) Bh 20.00
5. Sepatu Keselamatan (Rubber Shoes) Bh 20.00
6. Kotak P3K Bh 4.00
7. Asuransi Tenaga Kerja Paket 1.00
A KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1. Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00
2. Vitamin C (1 Box isi 100 tablet) Bh 20.00
3. Tempat Cuci Tangan Bh 3.00
4. Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00
5. Masker kain Bh 20.00
6. Alat penyemprot desinfektan Bh 3.00
7. Cairan Desinfektan 5L Bh 5.00

A ADMINISTRASI KEGIATAN
18. Pelaporan KSM Ls 1.00
2. Photo Copy / Penggandaan Ls 1.00
3. Biaya Alat Tulis Kantor (ATK) Ls 1.00
4. Materai Bh 8.00
5. Pengujian Lab Paket 1.00
6. Papan Nama Kegiatan Paket 1.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


Form - RAB 3
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
FORMAT PEREKAMAN ANALISA HARGA SATUAN

Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 1 m Kode Analisa


Satuan Pembayaran : M3 A. 2.3.1.1

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.7500 140,000.00 105,000.00
Mandor L.04 OH 0.0250 -
Jumlah Tenaga 105,000.00
B. Bahan
Jumlah Bahan
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 105,000.00

Pekerjaan : Pengurugan 1 m3 dengan tanah urug Kode Analisa


Satuan Pembayaran : M3 A.2.3.1.11.a

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.2500 140,000.00 35,000.00
Mandor L.04 OH 0.0100 -
Jumlah Tenaga 35,000.00
B. Bahan
Tanah Urug 1.2000 100,000 120,000.00
Jumlah Bahan 120,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 155,000.00

Pekerjaan : Pembesian 10 kg dengan besi polos atau besi ulir Kode Analisa
Satuan Pembayaran : Kg A.4.1.1.17

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.0700 140,000.00 9,800.00
Tukang Besi L.02 OH 0.0700 150,000.00 10,500.00
Kepala Tukang L.03 OH 0.0070 170,000.00 1,190.00
Mandor L.04 OH 0.0040 - -
-
Jumlah Tenaga 21,490.00
B. Bahan
Besi beton Kg 10.5000 12,000.00 126,000.00
Kawat Beton Kg 0.1500 - -
Jumlah Bahan 126,000.00
C. Peralatan

Jumlah Peralatan -

D. Harga Satuan Pekerjaan (A+B+C) 147,490.00

Pembesian 1 Kg Besi 14,749.00


Pekerjaan : Membuat 1 m3 beton mutu f’c = 14,5 Mpa (K.175) Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.5.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 1.6500 140,000.00 231,000.00
Tukang batu L.02 OH 0.2750 155,000.00 42,625.00
Kepala tukang L.03 OH 0.0280 170,000.00 4,760.00
Mandor L.04 OH 0.0830 - -
Jumlah Tenaga 278,385.00
B. Bahan
Semen Portland kg 326.0000 1,275.00 415,650.00
Pasir beton kg 760.0000 128.57 97,714.29
Kerikil /Split (Maks 30mm) kg 1,029.0000 250.00 257,250.00
Air Liter 215.0000 -
Jumlah Bahan 770,614.29
C. Peralatan

Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 1,048,999.29

Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk pondasi Kode Analisa


Satuan Pembayaran : M3 A.4.1.1.20

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.5200 140,000.00 72,800.00
Tukang kayu L.02 OH 0.2600 150,000.00 39,000.00
Kepala tukang L.03 OH 0.0260 170,000.00 4,420.00
Mandor L.04 OH 0.0260 - -
Jumlah Tenaga 116,220.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.3000 22,000.00 6,600.00
Minyak Bekisting kg 0.1000 -
Jumlah Bahan 104,600.00
C. Peralatan
Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk kolom Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.22

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0150 4,000,000.00 60,000.00
Plywood tebal 9 mm Lbr 0.3500 - -
Dolken kayu φ 8-10cm Batang 2.0000 30,000.00 60,000.00
Jumlah Bahan 226,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 374,310.00
Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk balok Kode Analisa
Satuan Pembayaran : M3 A.4.1.1.23

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 - -
Balok kayu kelas II m3 0.0180 4,000,000.00 72,000.00
Plywood tebal 9 mm Lbr 0.3500 - -
Dolken kayu φ 8-10cm Batang 2.0000 30,000.00 60,000.00
Jumlah Bahan 238,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 386,310.00

Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk plat Kode Analisa


Satuan Pembayaran : M2 A.4.1.1.24

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0400 2,450,000.00 98,000.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0150 4,000,000.00 60,000.00
Plywood tebal 9 mm Lbr 0.3500 130,000.00 45,500.00
Dolken kayu φ 8-10cm Batang 6.0000 30,000.00 180,000.00
Jumlah Bahan 392,300.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 539,810.00
Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk dinding Kode Analisa
Satuan Pembayaran : M2 A.4.1.1.25

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6600 140,000.00 92,400.00
Tukang kayu L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 170,000.00 5,610.00
Mandor L.04 OH 0.0330 - -
Jumlah Tenaga 147,510.00
B. Bahan
Kayu Klas III m3 0.0300 2,450,000.00 73,500.00
Paku 5-10 cm kg 0.4000 22,000.00 8,800.00
Minyak Bekisting kg 0.2000 -
Balok kayu kelas II m3 0.0200 4,000,000.00 80,000.00
Plywood tebal 9 mm Lbr 0.3500 130,000.00 45,500.00
Dolken kayu φ 8-10cm Batang 3.0000 30,000.00 90,000.00
Jumlah Bahan 297,800.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 445,310.00

Pekerjaan : 1 m2 Pekerjaan Pelitur Reling Kode Analisa


Satuan Pembayaran : M2 A.4.7.1.4.a

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.0700 140,000.00 9,800.00
Tukang cat L.02 OH 0.0090 150,000.00 1,350.00
Kepala tukang L.03 OH 0.0060 170,000.00 1,020.00
Mandor L.04 OH 0.0030 - -
Jumlah Tenaga 12,170.00
B. Bahan
Cat plitur Kayu Kg 0.2000 73,000.00 14,600.00
Plamuur Kg 0.1500 - -
Cat plitur Kayu Kg 0.1700 73,000.00 12,410.00
Cat penutup Kayu Kg 0.2600 -
Kuas Bh 0.0100 45,000.00 450.00
Pengencer Kg 0.0300 28,100.00 843.00
Ampelas Lbr 0.2000 10,000.00 2,000.00
Jumlah Bahan 30,303.00
C. Peralatan
-
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 42,473.00
Pekerjaan : Pengecatan 1 m2 tembok baru Kode Analisa
Satuan Pembayaran : M2 A.4.7.1.10.

Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien
(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01.01 OH 0.0200 140,000.00 2,800.00
Tukang cat L.02.08 OH 0.0630 150,000.00 9,450.00
Kepala tukang L.03.01 OH 0.0063 170,000.00 1,071.00
Mandor L.04.01 OH 0.0030 -
Jumlah Tenaga 13,321.00
B. Bahan
Plamuur Kg 0.1000 - -
Cat dasar Tembok Kg 0.1200 110,000.00 13,200.00
Cat Penutup Tembok Kg 0.1800 110,000.00 19,800.00
Jumlah Bahan 33,000.00
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 46,321.00

Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm Kode Analisa


Satuan Pembayaran : M2 A.4.4.2.4.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.3000 140,000.00 42,000.00
Tukang batu L.02 OH 0.1500 155,000.00 23,250.00
Kepala tukang L.03 OH 0.0150 170,000.00 2,550.00
Mandor L.04 OH 0.0150 -
Jumlah Tenaga 67,800.00
B. Bahan
Semen Portland Kg 6.240 1,275.00 7,956.00
Pasir pasang m3 0.024 150,000.00 3,600.00
Jumlah Bahan 11,556.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 79,356.00

Pekerjaan : Pemasangan 1 m2 acian Kode Analisa


Satuan Pembayaran : M2 A.4.4.2.27.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.2000 140,000.00 28,000.00
Tukang batu L.02 OH 0.1000 155,000.00 15,500.00
Kepala tukang L.03 OH 0.0100 170,000.00 1,700.00
Mandor L.04 OH 0.0100 -
Jumlah Tenaga 45,200.00
B. Bahan
Semen Portland Kg 3.250 1,275.00 4,143.75
Jumlah Bahan 4,143.75
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 49,343.75
Pekerjaan : Pemasangan 1m2 guiding block 30 cm x 30 cm di atas cor beton Kode Analisa
Satuan Pembayaran : M2 A.4.4.3.35.a

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.700 140,000.00 98,000.00
Tukang batu L.02 OH 0.350 155,000.00 54,250.00
Kepala tukang L.03 OH 0.035 170,000.00 5,950.00
Mandor L.04 OH 0.035 -
Jumlah Tenaga 158,200.00
B. Bahan
Guiding block 30x30 Bh 12.000 38,000.00 456,000.00
Semen Portland Kg -
Pasir pasang M3 -
Semen warna Kg -
Jumlah Bahan 456,000.00
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 614,200.00

Pekerjaan : Pemasangan 1m2 guiding block 30 cm x 30 cm Kode Analisa


Satuan Pembayaran : M2 A.4.4.3.35.b

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.700 140,000.00 98,000.00
Tukang batu L.02 OH 0.350 155,000.00 54,250.00
Kepala tukang L.03 OH 0.035 170,000.00 5,950.00
Mandor L.04 OH 0.035 -
Jumlah Tenaga 158,200.00
B. Bahan
Guiding block 30x30 Bh 12.000 38,000.00 456,000.00
Semen Portland Kg 10.000 1,275.00 12,750.00
Pasir pasang M3 0.045 150,000.00 6,750.00
Semen warna Kg -
Jumlah Bahan 475,500.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 633,700.00

Pekerjaan : Pemasangan 1m2 dinding bata merah Tbl 1 Bata 1PC:4PP Kode Analisa
Satuan Pembayaran : m2 A. 4.4.1.3

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.600 140,000.00 84,000.00
Tukang Batu L.02 OH 0.200 155,000.00 31,000.00
Kepala Tukang L.03 OH 0.020 170,000.00 3,400.00
Mandor L.04 OH 0.030 -
Jumlah Tenaga 118,400.00
B. Bahan
Bata merah Bh 170.000 1,000.00 170,000.00
Semen Portland Kg 26.550 1,275.00 33,851.25
Pasir pasang m3 0.093 150,000.00 13,950.00
Jumlah Bahan 217,801.25
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 336,201.25
Pekerjaan : Pemasangan 1m2 dinding bata merah Tbl 1/2 Bata 1PC:4PP Kode Analisa
Satuan Pembayaran : m2 A.4.4.1.9

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.300 140,000.00 42,000.00
Tukang Batu L.02 OH 0.100 155,000.00 15,500.00
Kepala Tukang L.03 OH 0.010 170,000.00 1,700.00
Mandor L.04 OH 0.015 -
Jumlah Tenaga 59,200.00
B. Bahan
Bata merah Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 11.500 1,275.00 14,662.50
Pasir pasang m3 0.043 150,000.00 6,450.00
Jumlah Bahan 91,112.50
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 150,312.50

Pekerjaan : Pemasangan 1 m2 paving block natural tebal 8 cm Kode Analisa


Satuan Pembayaran : m2 A.4.4.3.65.

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.500 140,000.00 70,000.00
Tukang Batu L.02 OH 0.500 155,000.00 77,500.00
Kepala Tukang L.03 OH 0.050 170,000.00 8,500.00
Mandor L.04 OH 0.013 -
Jumlah Tenaga 156,000.00
B. Bahan
Paving Block Hexagonal Bh 27.000 7,500.00 202,500.00
Pasir pasang m3 0.150 150,000.00 22,500.00
Jumlah Bahan 225,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 381,000.00

Pekerjaan : Pekerjaan Rangka Bawah Kayu Klas II (Benuas) Kode Analisa


Satuan Pembayaran : m3 BOW F.1b

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 5.000 140,000.00 700,000.00
Tukang Kayu L.02 OH 7.500 150,000.00 1,125,000.00
Kepala Tukang L.03 OH 0.750 170,000.00 127,500.00
Mandor L.04 OH 0.250 -
Jumlah Tenaga 1,952,500.00
B. Bahan
Balok Kayu Klas II Benuas m3 1.100 5,250,000.00 5,775,000.00
Paku Kg 5.000 22,000.00 110,000.00
Jumlah Bahan 5,885,000.00
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 7,837,500.00
Pekerjaan : 1 M2 Pek. Lantai Papan Kayu Klas II Tebal 2 Cm Diserut Rapi Kode Analisa
Satuan Pembayaran : m3 BOW F.38

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.6000 140,000.00 84,000.00
Tukang Kayu L.02 OH 1.8000 150,000.00 270,000.00
Kepala Tukang L.03 OH 0.1800 170,000.00 30,600.00
Mandor L.04 OH 0.0300 -
Jumlah Tenaga 384,600.00
B. Bahan
M3 Papan Kayu Klas II Benuas m3 0.0300 6,000,000.00 180,000.00
Paku Kg 0.2000 22,000.00 4,400.00
Jumlah Bahan 184,400.00
C. Peralatan - -
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 569,000.00

Pekerjaan : Mengerjakan Rangka Badan Kayu Klas II Kode Analisa


Satuan Pembayaran : m3 BOW F.22

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 5.0000 140,000.00 700,000.00
Tukang Kayu L.02 OH 15.0000 150,000.00 2,250,000.00
Kepala Tukang L.03 OH 1.5000 170,000.00 255,000.00
Mandor L.04 OH 0.4000 -
Jumlah Tenaga 3,205,000.00
B. Bahan
M3 Balok Kayu Klas II Benuas m3 1.1000 5,250,000.00 5,775,000.00
Paku Kg 3.0000 22,000.00 66,000.00
Jumlah Bahan 5,841,000.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 9,046,000.00

Pekerjaan : Pemasangan 1 m2 dinding pemisah GRC Board rangkap Kode Analisa


Satuan Pembayaran : m3 A.4.6.1.25.a

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 OH 0.2000 140,000.00 28,000.00
Tukang Kayu L.02 OH 0.6000 150,000.00 90,000.00
Kepala Tukang L.03 OH 0.0600 170,000.00 10,200.00
Mandor L.04 OH 0.0100 -
Jumlah Tenaga 128,200.00
B. Bahan
Balok Kayu Klas II Benuas uk. 5/10 m3 0.0280 5,250,000.00 147,000.00
Paku Kg 0.1500 22,000.00 3,300.00
GRC Board tebal 8 m Lbr 0.8600 190,000.00 163,400.00
Lem Kayu Kg 0.5600
Jumlah Bahan 313,700.00
C. Peralatan
Jumlah Peralatan -
D. Harga Satuan Pekerjaan (A+B+C) 441,900.00
Pekerjaan : Timbunan Biasa Kode Analisa
Satuan Pembayaran : m3 Analisa EI-322

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp)
A. Tenaga Kerja
Pekerja L.01 Jam 0.2275 140,000.00 31,847.13
Mandor L.04 Jam 0.0455
Jumlah Tenaga 31,847.13
B. Bahan
Tanah Biasa m3 1.2000 100,000.00 120,000.00
Jumlah Bahan 120,000.00
C. Peralatan
Pick Up E39 jam 0.3185 - -
Pedesterian Roller E34 jam 0.0361 88,625.54 3,199.38
Alat Bantu Ls 1.0000 800.00 800.00

Jumlah Peralatan 3,999.38


D. Harga Satuan Pekerjaan (A+B+C) 155,846.52

Dibuat oleh : Tim Verifikasi,


Ketua KSM Tim Faskel Tim Korkot

................................. Hengky Pradana, ST Wiwit Whindari, ST


RAB-4

PROGRAM KOTA TANPA KUMUH (KOTAKU)


DAFTAR HARGA SATUAN JADI PEKERJAAN

Kab./Kota : Palangka Raya Nama Paket Pekerjaan : Pembangunan Jalan dan


Drainase
Kecamatan : Sebangau
Kelurahan : Kereng Bangkirai
BKM : Kereng Membangun

HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase m3 Rp 105,000.00
2 Pek. Dinding Saluran
a. Pek. Pembesian Kg Rp 14,749.00
b Pek, Bekisting m2 Rp 445,310.00
c. Cor beton K-175 m3 Rp 1,048,999.29
3 Pek. Lantai saluran
a. Pek. Pembesian Kg Rp 14,749.00
b Plastik Cor m2 Rp 4,000.00
c. Cor beton K-175 m3 Rp 1,048,999.29
4 Pek. Penutup saluran
a. Pek. Pembesian Kg Rp 14,749.00
b Pek. Bekisting m2 Rp 539,810.00
c. Cor beton K-175 m3 Rp 1,048,999.29
5 Pek. Biopori untuk resapan Bh Rp 70,000.00
6 Pek. Besi untuk handle tutup saluran Bh Rp 10,000.00
7 Pekerjaan Acian m2 Rp 49,343.75

II PEKERJAAN JALAN PAVING BLOCK


A Segmen A Jl. Bara Bere Panjang 42 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 Rp 336,201.25
2 Pekerjaan Ring Balok 10/15
a Pembesian Kg Rp 14,749.00
b Pek, Bekisting m2 Rp 386,310.00
c Cor Beton K.175 m3 Rp 1,048,999.29
3 Pek. Timbunan/Urugan Tanah m3 Rp 155,000.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg Rp 14,749.00
b Pek, Bekisting m2 Rp 374,310.00
c Cor Beton K.175 m3 Rp 1,048,999.29
5 Pekerjaan Paving Block m2 Rp 381,000.00
6 Pek. Pas Buis Beton dia. 50 x 100cm Bh Rp 120,000.00
7 Pek. Guiding block dan warning block precast m Rp 105,000.00
8 Coating guiding block & warning block m2 Rp 35,000.00

C Segmen C Panjang 116 M (Gg Husada)


1 Pas Dinding Bata Tebal 1/2 Bata pengunci paving m2 Rp 150,312.50
2 Pek. Plesteran Dinding Bata m2 Rp 79,356.00
3 Pekerjaan Paving Block m2 Rp 381,000.00
4 Pek. Pipa AW 4" (saluran gorong-gorong) m Rp 70,000.00
5 Pek. Guiding block dan warning block precast m Rp 105,000.00
6 Coating guiding block & warning block m2 Rp 35,000.00
HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)

III PEKERJAAN JALAN TITIAN KAYU


A Segmen A, 80 M (Jl. M.Usin)
1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 Rp 7,837,500.00
b Pek Gelagar memanjang m3 Rp 7,837,500.00
c Pek. Gelagar melintang m3 Rp 7,837,500.00
d Pek. Kacapuri m3 Rp 7,837,500.00
e Pekerjaan sunduk m3 Rp 7,837,500.00
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 Rp 569,000.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 Rp 7,837,500.00
c Pekerjaan pagar reling m3 Rp 7,837,500.00
3 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 Rp 7,837,500.00
b Pek Gelagar memanjang m3 Rp 7,837,500.00
c Pek. Kacapuri m3 Rp 7,837,500.00
d Pekerjaan sunduk m3 Rp 7,837,500.00
4 Pasangan Mur dan Baut 14/22 Kg Rp 45,000.00
5 Pas. Ring Baut Kg Rp 19,000.00

B Segmen B 40 M (Jl. Hadri Embang)


1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 Rp 7,837,500.00
b Pek Gelagar memanjang (sloof) m3 Rp 7,837,500.00
c Pek. Gelagar melintang m3 Rp 7,837,500.00
d Pek. Kacapuri m3 Rp 7,837,500.00
e Pekerjaan sunduk m3 Rp 7,837,500.00
f Pekerjaan balok suai m3 Rp 7,837,500.00
g Pasangan Mur dan Baut 14/22 Kg Rp 45,000.00
h. Pas. Ring Baut Kg Rp 19,000.00
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 Rp 569,000.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 Rp 7,837,500.00
c Pekerjaan pagar reling m3 Rp 7,837,500.00

IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19


A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) Bh Rp 75,000.00
2 Helm Keselamatan Bh Rp 100,000.00
3 Rompi Kerja Bh Rp 60,000.00
4 Sarung Tangan (Safety Glove) Bh Rp 5,000.00
5 Sepatu Keselamatan (Rubber Shoes) Bh Rp 100,000.00
6 Kotak P3K Bh Rp 40,000.00
7 Asuransi Tenaga Kerja Paket Rp 1,407,000.00
HARGA
NO. JENIS PEKERJAAN SATUAN
(Rp.)
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) Bh Rp 350,000.00
2 Vitamin C (1 Box isi 100 tablet) Bh Rp 25,000.00
3 Tempat Cuci Tangan Bh Rp 250,000.00
4 Sabun Cuci Tangan (Cair) 200ml/btl Bh Rp 25,000.00
5 Masker kain Bh Rp 5,000.00
6 Alat penyemprot desinfektan Bh Rp 65,000.00
7 Cairan Desinfektan 5L Bh Rp 75,000.00

V ADMINISTRASI KEGIATAN
1 Pelaporan KSM Ls Rp 270,000.00
2 Photo Copy / Penggandaan Ls Rp 250,000.00
3 Biaya Alat Tulis Kantor (ATK) Ls Rp 150,000.00
4 Materai Bh Rp 10,000.00
5 Pengujian Lab Paket Rp 500,000.00
6 Papan Nama Kegiatan Paket Rp 250,000.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur, Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST Alfiansyah


RAB-5
BANTUAN PEMERINTAH UNTUK MASYARAKAT ( BPM ) DFAT
PROGRAM KOTA TANPA KUMUH (KOTAKU)
RENCANA ANGARAN BIAYA

Kab./Kota : Palangka Raya Nama Paket Pekerjaan : Pembangunan Jalan dan Drainase
Kecamatan : Sebangau
Kelurahan : Kereng Bangkirai
BKM : Kereng Membangun

HARGA SATUAN
NO JENIS PEKERJAAN SATUAN VOLUME ANALISA JUMLAH HARGA (Rp)
(Rp)

I PEKERJAAN DRAINASE
1 Pek. Galian Drainase m3 42.04 A. 2.3.1.1 Rp 105,000.00 Rp 4,413,740.63
2 Pek. Dinding Saluran
a. Pek. Pembesian Kg 1353.82 A.4.1.1.17 Rp 14,749.00 Rp 19,967,511.83
b Pek, Bekisting m2 107.35 A.4.1.1.25 Rp 445,310.00 Rp 47,802,544.13
c. Cor beton K-175 m3 16.45 A.4.1.1.5. Rp 1,048,999.29 Rp 17,256,038.25
3 Pek. Lantai saluran
a. Pek. Pembesian Kg 671.54 A.4.1.1.17 Rp 14,749.00 Rp 9,904,584.76
b Plastik Cor m2 81.00 Ls Rp 4,000.00 Rp 324,000.00
c. Cor beton K-175 m3 8.10 A.4.1.1.5. Rp 1,048,999.29 Rp 8,496,894.21
4 Pek. Penutup saluran
a. Pek. Pembesian Kg 614.72 A.4.1.1.17 Rp 14,749.00 Rp 9,066,462.51
b Pek. Bekisting m2 32.01 A.4.1.1.24 Rp 539,810.00 Rp 17,279,318.10
c. Cor beton K-175 m3 7.47 A.4.1.1.5. Rp 1,048,999.29 Rp 7,834,975.67
5 Pek. Biopori untuk resapan Bh 24.00 Ls Rp 70,000.00 Rp 1,680,000.00
6 Pek. Besi untuk handle tutup saluran Bh 85.00 Ls Rp 10,000.00 Rp 850,000.00
7 Pekerjaan Acian m2 72.38 A.4.4.2.27. Rp 49,343.75 Rp 3,571,500.63
Jumlah I Rp 148,447,570.71
II PEKERJAAN JALAN PAVING BLOCK
A Segmen A Jl. Bara Bere Panjang 42 M
1 Pas Dinding Bata Tebal 1 Bata Dinding Penahan Tanah m2 10.88 A. 4.4.1.3 Rp 336,201.25 Rp 3,657,869.60
2 Pekerjaan Ring Balok 10/15
a Pembesian Kg 256.42 A.4.1.1.17 Rp 14,749.00 Rp 3,781,914.98
b Pek, Bekisting m2 8.40 A.4.1.1.23 Rp 386,310.00 Rp 3,245,004.00
c Cor Beton K.175 m3 1.26 A.4.1.1.5. Rp 1,048,999.29 Rp 1,321,739.10
3 Pek. Timbunan/Urugan Tanah m3 17.41 A.2.3.1.11.a Rp 155,000.00 Rp 2,698,240.00
4 Pek. Kolom praktis 15/15
a Pembesian Kg 31.09 A.4.1.1.17 Rp 14,749.00 Rp 458,506.88
b Pek, Bekisting m2 0.47 A.4.1.1.22 Rp 374,310.00 Rp 176,674.32
c Cor Beton K.175 m3 0.21 A.4.1.1.5. Rp 1,048,999.29 Rp 222,807.45
5 Pekerjaan Paving Block m2 52.20 A.4.4.3.65. Rp 381,000.00 Rp 19,888,200.00
6 Pek. Pas Buis Beton dia. 50 x 100cm Bh 4.00 Ls Rp 120,000.00 Rp 480,000.00
7 Pek. Guiding block dan warning block precast m 143.00 Ls Rp 105,000.00 Rp 15,015,000.00
8 Coating guiding block & warning block m2 42.90 Ls Rp 35,000.00 Rp 1,501,500.00
Jumlah B Rp 52,447,456.33
C Segmen C Panjang 116 M (Gg Husada)
1 Pas Dinding Bata Tebal 1/2 Bata pengunci paving m2 81.20 A.4.4.1.9 Rp 150,312.50 Rp 12,205,375.00
2 Pek. Plesteran Dinding Bata m2 28.20 A.4.4.2.4. Rp 79,356.00 Rp 2,237,839.20
3 Pekerjaan Paving Block m2 431.79 A.4.4.3.65. Rp 381,000.00 Rp 164,511,990.00
4 Pek. Pipa AW 4" (saluran gorong-gorong) m 5.00 Ls Rp 70,000.00 Rp 350,000.00
5 Pek. Guiding block dan warning block precast m 121.50 Ls Rp 105,000.00 Rp 12,757,500.00
6 Coating guiding block & warning block m2 36.45 Ls Rp 35,000.00 Rp 1,275,750.00
Jumlah C Rp 193,338,454.20
Jumlah II (A+B+C) Rp 245,785,910.53
III PEKERJAAN JALAN TITIAN KAYU
A Segmen A, 80 M (Jl. M.Usin)
1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.48 BOW F.1b Rp 7,837,500.00 Rp 11,630,850.00
b Pek Gelagar memanjang m3 1.60 BOW F.1b Rp 7,837,500.00 Rp 12,540,000.00
c Pek. Gelagar melintang m3 0.49 BOW F.1b Rp 7,837,500.00 Rp 3,809,025.00
d Pek. Kacapuri m3 0.74 BOW F.1b Rp 7,837,500.00 Rp 5,815,425.00
e Pekerjaan sunduk m3 0.19 BOW F.1b Rp 7,837,500.00 Rp 1,453,856.25
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 168.80 BOW F.38 Rp 569,000.00 Rp 96,047,200.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.58 BOW F.1b Rp 7,837,500.00 Rp 4,517,926.88
c Pekerjaan pagar reling m3 4.86 BOW F.1b Rp 7,837,500.00 Rp 38,117,681.25
3 Pekerjaan tambatan perahu
a Pek. Pas Tongkat Kayu Ulin 10/10 m3 0.16 BOW F.1b Rp 7,837,500.00 Rp 1,222,650.00
b Pek Gelagar memanjang m3 0.05 BOW F.1b Rp 7,837,500.00 Rp 391,875.00
c Pek. Kacapuri m3 0.02 BOW F.1b Rp 7,837,500.00 Rp 156,750.00
d Pekerjaan sunduk m3 0.004 BOW F.1b Rp 7,837,500.00 Rp 27,431.25
4 Pasangan Mur dan Baut 14/22 Kg 56.00 Ls Rp 45,000.00 Rp 2,520,000.00
5 Pas. Ring Baut Kg 56.00 Ls Rp 19,000.00 Rp 1,064,000.00
Jumlah III Rp 179,314,670.63
HARGA SATUAN
NO JENIS PEKERJAAN SATUAN VOLUME ANALISA JUMLAH HARGA (Rp)
(Rp)
B Segmen B 40 M (Jl. Hadri Embang)
1 Pekerjaan Rangka Bawah
a Pek. Pas Tongkat Kayu 10/10 m3 1.08 BOW F.1b Rp 7,837,500.00 Rp 8,464,500.00
b Pek Gelagar memanjang (sloof) m3 0.80 BOW F.1b Rp 7,837,500.00 Rp 6,270,000.00
c Pek. Gelagar melintang m3 0.40 BOW F.1b Rp 7,837,500.00 Rp 3,135,000.00
d Pek. Kacapuri m3 0.38 BOW F.1b Rp 7,837,500.00 Rp 2,962,575.00
e Pekerjaan sunduk m3 0.09 BOW F.1b Rp 7,837,500.00 Rp 740,643.75
f Pekerjaan balok suai m3 0.51 BOW F.1b Rp 7,837,500.00 Rp 3,993,990.00
g Pasangan Mur dan Baut 14/22 Kg 28.70 Ls Rp 45,000.00 Rp 1,291,500.00
h. Pas. Ring Baut Kg 28.70 Ls Rp 19,000.00 Rp 545,300.00
2 Pekerjaan Rangka Badan, Lantai dan Railing
a Pek. Pas. Lantai Papan Tebal 2 Cm Kayu Klas I, Uk. 2/20 Cm m2 80.00 BOW F.38 Rp 569,000.00 Rp 45,520,000.00
b Pek. Balok Pengunci Lantai Papan uk. 5/7 m3 0.28 BOW F.1b Rp 7,837,500.00 Rp 2,194,500.00
c Pekerjaan pagar reling m3 1.27 BOW F.1b Rp 7,837,500.00 Rp 9,945,787.50
Jumlah III Rp 85,063,796.25
Jumlah III (A+B) Rp 264,378,466.88
IV KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
A KEBUTUHAN KESEHATAN DAN KESELAMATAN KERJA
1 Sosialisasi K3 dan Prokes (Spanduk) Bh 4.00 Ls Rp 75,000 Rp 300,000
2 Helm Keselamatan Bh 20.00 Ls Rp 100,000 Rp 2,000,000
3 Rompi Kerja Bh 20.00 Ls Rp 60,000 Rp 1,200,000
4 Sarung Tangan (Safety Glove) Bh 20.00 Ls Rp 5,000 Rp 100,000
5 Sepatu Keselamatan (Rubber Shoes) Bh 20.00 Ls Rp 100,000 Rp 2,000,000
6 Kotak P3K Bh 4.00 Ls Rp 40,000 Rp 160,000
7 Asuransi Tenaga Kerja Paket 1.00 Ls Rp 1,407,000 Rp 1,407,000
B KEBUTUHAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
1 Alat ukur suhu badan nir-sentuh (Thermoscan) Bh 2.00 Ls Rp 350,000 Rp 700,000
2 Vitamin C (1 Box isi 100 tablet) Bh 20.00 Ls Rp 25,000 Rp 500,000
3 Tempat Cuci Tangan Bh 3.00 Ls Rp 250,000 Rp 750,000
4 Sabun Cuci Tangan (Cair) 200ml/btl Bh 5.00 Ls Rp 25,000 Rp 125,000
5 Masker kain Bh 20.00 Ls Rp 5,000 Rp 100,000
6 Alat penyemprot desinfektan Bh 3.00 Ls Rp 65,000 Rp 195,000
7 Cairan Desinfektan 5L Bh 5.00 Ls Rp 75,000 Rp 375,000
Jumlah IV Rp 9,912,000.00
V ADMINISTRASI KEGIATAN
1 Pelaporan KSM Ls 1.00 Ls Rp 270,000 Rp 270,000
2 Photo Copy / Penggandaan Ls 1.00 Ls Rp 250,000 Rp 250,000
3 Biaya Alat Tulis Kantor (ATK) Ls 1.00 Ls Rp 150,000 Rp 150,000
4 Materai Bh 8.00 Ls Rp 10,000 Rp 80,000
5 Pengujian Lab Paket 1.00 Ls Rp 500,000 Rp 500,000
6 Papan Nama Kegiatan Paket 1.00 Ls Rp 250,000 Rp 250,000
JumlahV Rp 1,500,000.00

JUMLAH TOTAL Rp 670,023,948.11


DIBULATKAN Rp 670,000,000.00

Diverifikasi Oleh : Dibuat Oleh :


Askot Infrastruktur Fasilitator Teknik, UPL

Wiwit Whindari, ST. Hengky Pradana, ST


FORM - RPD

RENCANA PENGGUNAAN DANA (RPD)


KSM/PANITIA

Kab./Kota : Palangka Raya


Kecamatan : Sebangau Nama Paket : Jalan & Drainase
Kel/Desa : Kereng Bangkirai
KSM/Panitia : Kereng Membangun 1

JUMLAH HARGA
RPD TAHAP-I RPD TAHAP-II
NO. URAIAN SESUAI SPPD-L
(70%) (30%)
(Rp.)
(1) (2) (3) (4) (4)
1. TENAGA KERJA
1. Kepala Tukang 21,420,000 14,994,000.00 6,426,000
2. Tukang Batu 37,975,000 26,582,500.00 11,392,500
3. Tukang Kayu 64,800,000 45,360,000.00 19,440,000
4. Tukang Besi 4,500,000 3,150,000.00 1,350,000
5. Tukang Cat 300,000 210,000.00 90,000
6. Pekerja 130,340,000 91,238,000.00 39,102,000
JUMLAH 259,335,000 181,534,500 77,800,500
2. B A H A N
1. Ampelas 280,000 196,000.00 84,000
2. Balok Kayu Benuas 10/10 8,820,000 6,174,000.00 2,646,000
3. Balok Kayu Benuas 5/10 21,735,000 15,214,500.00 6,520,500
4. Balok Kayu Benuas 5/7 16,060,000 11,242,000.00 4,818,000
5. Balok Kayu Klas II Uk. 5/7 13,384,000 9,368,800.00 4,015,200
6. Bata merah 16,500,000 11,550,000.00 4,950,000
7. Besi Beton
8. Besi beton dia.10 42,000,000 29,400,000.00 12,600,000
9. Besi beton dia.8 2,475,000 1,732,500.00 742,500
10. Besi untuk handle tutup saluran 750,000 525,000.00 225,000
11. Biopori 1,950,000 1,365,000.00 585,000
12. Buis Beton 720,000 504,000.00 216,000
13. Cat plitur Kayu 3,723,000 2,606,100.00 1,116,900
14. Cat Tembok Jotun eksterior 220,000 154,000.00 66,000
15. Dolken Kayu ø 8-10 Cm 19,080,000 13,356,000.00 5,724,000
16. GRC Board tebal 8 m 570,000 399,000.00 171,000
17. Guiding block 16,644,000 11,650,800.00 4,993,200
18. Kawat Beton 2,000,000 1,400,000.00 600,000
19. Kerikil (maks 30 mm) 11,700,000 8,190,000.00 3,510,000
20. Kuas 90,000 63,000.00 27,000
21. Letter Huruf timbul kayu 1,800,000 1,260,000.00 540,000
22. Mur dan baut 980,000 686,000.00 294,000
JUMLAH HARGA
RPD TAHAP-I RPD TAHAP-II
NO. URAIAN SESUAI SPPD-L
(70%) (30%)
(Rp.)

23. Paku 5-10 cm 3,542,000 2,479,400.00 1,062,600


24. Papan Kayu Benuas 28,224,000 19,756,800.00 8,467,200
25. Papan Kayu Klas III uk.2/20 14,781,000 10,346,700.00 4,434,300
26. Pasir beton 3,600,000 2,520,000.00 1,080,000
27. Pasir pasang 18,000,000 12,600,000.00 5,400,000
28. Paving Block Hexagonal 105,750,000 74,025,000.00 31,725,000
29. Pengencer/Thinner 112,400 78,680.00 33,720
30. Plastik Cor 360,000 252,000.00 108,000
31. Plywood tebal 9 mm 7,410,000 5,187,000.00 2,223,000
32. Semen Portland 28,815,000 20,170,500.00 8,644,500
33. Tanah Biasa/Tanah Urug 7,200,000 5,040,000.00 2,160,000

JUMLAH 399,275,400 279,492,780 119,782,620


3. A L A T
1.
2.
3.
JUMLAH
4. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
1. Sosialisasi K3 dan Prokes (Spanduk) 300,000 210,000.00 90,000
2. Helm Keselamatan 2,000,000 1,400,000.00 600,000
3. Rompi Kerja 1,200,000 840,000.00 360,000
4. Sarung Tangan (Safety Glove) 100,000 70,000.00 30,000
5. Sepatu Keselamatan (Rubber Shoes) 2,000,000 1,400,000.00 600,000
6. Kotak P3K 160,000 112,000.00 48,000
7. Asuransi Tenaga Kerja 1,407,000 984,900.00 422,100
8. Alat ukur suhu badan nir-sentuh (Thermoscan) 700,000 490,000.00 210,000
9. Vitamin C (1 Box isi 100 tablet) 500,000 350,000.00 150,000
10. Tempat Cuci Tangan 750,000 525,000.00 225,000
11. Sabun Cuci Tangan (Cair) 200ml/btl 125,000 87,500.00 37,500
12. Masker kain 100,000 70,000.00 30,000
13. Alat penyemprot desinfektan 195,000 136,500.00 58,500
14. Cairan Desinfektan 5L 375,000 262,500.00 112,500

JUMLAH 9,912,000 6,938,400 2,973,600


JUMLAH HARGA
RPD TAHAP-I RPD TAHAP-II
NO. URAIAN SESUAI SPPD-L
(70%) (30%)
(Rp.)

5. ADMINISTRASI KEGIATAN
1. Pelaporan KSM 270,000 189,000.00 81,000
2. Photo Copy / Penggandaan 250,000 175,000.00 75,000
3. Biaya Alat Tulis Kantor (ATK) 150,000 105,000.00 45,000
4. Materai 80,000 56,000.00 24,000
5. Pengujian Lab 500,000 350,000.00 150,000
6. Papan Nama Kegiatan 250,000 175,000.00 75,000

1,500,000 1,050,000 450,000


JUMLAH (1+2+3+4+5) 670,022,400 469,015,680 201,006,720

PEMBULATAN 670,000,000 469,000,000 201,000,000

Diverifikasi Oleh : Dibuat Oleh


Fasilitator Teknik, KSM Kereng Membangun 1

Hengky Pradana, ST Syahrijal


FORM - LPD

LAPORAN PENGGUNAAN DANA (LPD)


KSM/PANITIA

Kab./Kota : Palangka Raya


Kecamatan : Sebangau Nama Paket : Jalan & Drainase
Kel/Desa : Kereng Bangkirai
KSM/Panitia : Kereng Membangun 1

JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

1. TENAGA KERJA
1. Kepala Tukang 21,420,000 4,930,000.00 16,490,000
2. Tukang Batu 37,975,000 18,135,000.00 19,840,000
3. Tukang Kayu 64,800,000 39,300,000.00 25,500,000
4. Tukang Besi 4,500,000 2,700,000.00 1,800,000
5. Tukang Cat 300,000 - 300,000
6. Pekerja 130,340,000 59,920,000.00 70,420,000

JUMLAH 259,335,000 124,985,000 134,350,000


2. B A H A N
1. Ampelas 280,000 270,000.00 10,000
2. Balok Kayu Benuas 10/10 8,820,000 8,820,000.00 -
3. Balok Kayu Benuas 5/10 21,735,000 21,735,000.00 -
4. Balok Kayu Benuas 5/7 16,060,000 16,060,000.00 -
5. Balok kayu kelas II uk. 5/7 13,384,000 12,544,000.00 840,000
6. Bata merah 16,500,000 10,000,000.00 6,500,000
7. Besi Beton -
Besi beton dia.10 42,000,000 35,770,000.00 6,230,000
Besi beton dia.8 2,475,000 1,800,000.00 675,000
8. Besi untuk handle tutup saluran 750,000 600,000.00 150,000
9. Biopori 1,950,000 1,650,000.00 300,000
10. Buis Beton 720,000 480,000.00 240,000
11. Cat plitur Kayu 3,723,000 - 3,723,000
12. Cat Tembok Jotun eksterior 220,000 - 220,000
13. Dolken Kayu ø 8-10 Cm 19,080,000 18,330,000.00 750,000
14. GRC Board tebal 8 m 570,000 - 570,000
15. Guiding block 16,644,000 30,870,000.00 - 14,226,000
16. Kawat Beton 2,000,000 1,225,000.00 775,000
17. Kerikil (maks 30 mm) 11,700,000 9,000,000.00 2,700,000
18. Kuas 90,000 - 90,000
JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

19. Letter Huruf timbul kayu 1,800,000 - 1,800,000


20. Mur dan baut 980,000 315,000.00 665,000
21. Paku 3,542,000 3,124,000.00 418,000
22. Papan Kayu Benuas 28,224,000 28,224,000.00 -
23. Papan Kayu Klas III uk.2/20 14,781,000 13,845,000.00 936,000
24. Pasir beton 3,600,000 2,880,000.00 720,000
25. Pasir pasang 18,000,000 10,800,000.00 7,200,000
26. Paving Block Hexagonal 105,750,000 72,675,000.00 33,075,000
27. Pengencer/Thinner 112,400 - 112,400
28. Plastik Cor 360,000 300,000.00 60,000
29. Plywood tebal 9 mm 7,410,000 6,760,000.00 650,000
30. Semen Portland 28,815,000 18,105,000.00 10,710,000
31. Tanah Biasa 7,200,000 6,400,000.00 800,000
32. Benang Roll - 5,000.00 - 5,000

JUMLAH 399,275,400 332,587,000 66,688,400


3. A L A T
1.
2.
3.

JUMLAH
4. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
1. Sosialisasi K3 dan Prokes (Spanduk) 300,000 300,000.00 -
2. Helm Keselamatan 2,000,000 2,000,000.00 -
3. Rompi Kerja 1,200,000 1,200,000.00 -
4. Sarung Tangan (Safety Glove) 100,000 100,000.00 -
5. Sepatu Keselamatan (Rubber Shoes) 2,000,000 2,000,000.00 -
6. Kotak P3K 160,000 280,000.00 - 120,000
7. Asuransi Tenaga Kerja 1,407,000 910,000.00 497,000
8. Alat ukur suhu badan nir-sentuh (Thermoscan) 700,000 700,000.00 -
9. Vitamin C (1 Box isi 100 tablet) 500,000 600,000.00 - 100,000
10. Tempat Cuci Tangan 750,000 750,000.00 -
11. Sabun Cuci Tangan (Cair) 200ml/btl 125,000 175,000.00 - 50,000
12. Masker kain 100,000 100,000.00 -
13. Alat penyemprot desinfektan 195,000 260,000.00 - 65,000
14. Cairan Desinfektan 5L 375,000 525,000.00 - 150,000
15. Tisu - 12,000.00 - 12,000

JUMLAH 9,912,000 9,912,000 12,000


JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

5. ADMINISTRASI KEGIATAN
1. Pelaporan KSM 270,000 - 270,000
2. Photo Copy / Penggandaan 250,000 - 250,000
3. Biaya Alat Tulis Kantor (ATK) 150,000 150,000.00 -
4. Materai 80,000 80,000.00 -
5. Pengujian Lab 500,000 - 500,000
6. Papan Nama Kegiatan 250,000 250,000.00 -
7. Biaya transfer - 43,500.00 - 43,500

1,500,000 523,500 976,500

JUMLAH 670,022,400 468,007,500 202,026,900

Palangka Raya, 17 September 2021


Diverifikasi Oleh : Dibuat Oleh
Fasilitator Teknik, KSM Kereng Membangun 1

Hengky Pradana, ST Syahrijal


FORM - LPD

LAPORAN PENGGUNAAN DANA (LPD)


KSM/PANITIA

Kab./Kota : Palangka Raya


Kecamatan : Sebangau Nama Paket : Jalan & Drainase
Kel/Desa : Kereng Bangkirai
KSM/Panitia : Kereng Membangun 1

JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

1. TENAGA KERJA
1. Kepala Tukang 21,420,000 11,050,000.00 10,370,000
2. Tukang Batu 37,975,000 79,875,000.00 - 41,900,000
3. Tukang Kayu 64,800,000 45,035,000.00 19,765,000
4. Tukang Besi 4,500,000 2,850,000.00 1,650,000
5. Tukang Cat 300,000 - 300,000
6. Pekerja 130,340,000 87,970,000.00 42,370,000

JUMLAH 259,335,000 226,780,000 32,555,000


2. B A H A N
1. Ampelas 280,000 280,000.00 -
2. Balok Kayu Benuas 10/10 8,820,000 16,380,000.00 - 7,560,000
3. Balok Kayu Benuas 5/10 21,735,000 28,035,000.00 - 6,300,000
4. Balok Kayu Benuas 5/5 - 8,060,000.00 - 8,060,000
5. Balok Kayu Benuas 5/7 16,060,000 32,193,000.00 - 16,133,000
6. Balok Kayu Klas II Lanan Uk. 5/7 13,384,000 12,880,000.00 504,000
7. Bata merah 16,500,000 12,000,000.00 4,500,000
8. Besi Beton -
Besi beton dia.10 42,000,000 35,770,000.00 6,230,000
Besi beton dia.8 2,475,000 1,800,000.00 675,000
9. Besi untuk handle tutup saluran 750,000 600,000.00 150,000
10. Biopori 1,950,000 1,650,000.00 300,000
11. Buis Beton 720,000 480,000.00 240,000
12. Cat plitur Kayu 3,723,000 - 3,723,000
13. Cat Tembok Jotun eksterior 220,000 - 220,000
14. Dolken Kayu ø 8-10 Cm 19,080,000 18,330,000.00 750,000
15. GRC Board tebal 8 m 570,000 - 570,000
16. Guiding block 16,644,000 39,795,000.00 - 23,151,000
17. Kawat Beton 2,000,000 1,225,000.00 775,000
18. Kerikil (maks 30 mm) 11,700,000 9,000,000.00 2,700,000
19. Kuas 90,000 - 90,000
JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

20. Letter Huruf timbul kayu 1,800,000 - 1,800,000


21. Mur dan baut 980,000 6,335,000.00 - 5,355,000
22. Paku 3,542,000 3,960,000.00 - 418,000
23. Papan Kayu Benuas 28,224,000 40,704,000.00 - 12,480,000
24. Papan Kayu Klas III uk.2/20 14,781,000 14,235,000.00 546,000
25. Pasir beton 3,600,000 2,880,000.00 720,000
26. Pasir pasang 18,000,000 12,600,000.00 5,400,000
27. Paving Block Hexagonal 105,750,000 96,675,000.00 9,075,000
28. Pengencer/Thinner 112,400 - 112,400
29. Plastik Cor 360,000 300,000.00 60,000
30. Plywood tebal 9 mm 7,410,000 6,760,000.00 650,000
31. Semen Portland 28,815,000 21,420,000.00 7,395,000
32. Tanah Biasa 7,200,000 6,800,000.00 400,000
33. Benang Roll - 5,000.00 - 5,000
34. Pipa 4" - 590,000.00 - 590,000

JUMLAH 399,275,400 431,742,000 (32,466,600)


3. A L A T
1.
2.
3.

JUMLAH
4. KEBUTUHAN K3 DAN PROKES PENCEGAHAN COVID - 19
1. Sosialisasi K3 dan Prokes (Spanduk) 300,000 300,000.00 -
2. Helm Keselamatan 2,000,000 2,000,000.00 -
3. Rompi Kerja 1,200,000 1,200,000.00 -
4. Sarung Tangan (Safety Glove) 100,000 100,000.00 -
5. Sepatu Keselamatan (Rubber Shoes) 2,000,000 2,000,000.00 -
6. Kotak P3K 160,000 280,000.00 - 120,000
7. Asuransi Tenaga Kerja 1,407,000 910,000.00 497,000
8. Alat ukur suhu badan nir-sentuh (Thermoscan) 700,000 700,000.00 -
9. Vitamin C (1 Box isi 100 tablet) 500,000 600,000.00 - 100,000
10. Tempat Cuci Tangan 750,000 750,000.00 -
11. Sabun Cuci Tangan (Cair) 200ml/btl 125,000 175,000.00 - 50,000
12. Masker kain 100,000 100,000.00 -
13. Alat penyemprot desinfektan 195,000 260,000.00 - 65,000
14. Cairan Desinfektan 5L 375,000 525,000.00 - 150,000
15. Tisu - 12,000.00 - 12,000

JUMLAH 9,912,000 9,912,000 12,000


JUMLAH HARGA
REALISASI s/d SAAT INI SISA s/d SAAT INI
NO. URAIAN SESUAI SPPD-L
(Rp.) (Rp.)
(Rp.)

5. ADMINISTRASI KEGIATAN
1. Pelaporan KSM 270,000 270,000.00 -
2. Photo Copy / Penggandaan 250,000 250,000.00 -
3. Biaya Alat Tulis Kantor (ATK) 150,000 150,000.00 -
4. Materai 80,000 80,000.00 -
5. Pengujian Lab 500,000 500,000.00 -
6. Papan Nama Kegiatan 250,000 250,000.00 -
7. Biaya transfer - 95,000.00 - 95,000

1,500,000 1,595,000 -

JUMLAH 670,022,400 670,029,000 100,400

Palangka Raya, 18 Desember 2021


Diverifikasi Oleh : Dibuat Oleh
Fasilitator Teknik, KSM Kereng Membangun 1

Hengky Pradana, ST Syahrijal