Anda di halaman 1dari 31

No Uraian Pekerjaan Volume Satuan

I PEKERJAAN PONDASI
PEKERJAAN PERSIAPAN
1 Pembersihan lapangan

Ukuran = 7.5 x 12 m

Lebar = 7.5 m
Panjang = 12 m

Luas = 90 m2 90.00 m2

2 Pemasangan Bowplank

Pasangan Bowplank
Panjang = 7.5 m
Lebar = 12 m
Keliling = 39 m 39.00 m

3 Pembuatan direksi keet

Direksi
Keet

Panjang = 3m
Lebar = 2m

Luas = 6 m2 6.00 m2

4 Los Kerja
Panjang = 4m
Lebar = 2m
Luas = 8 m2 8 m2

PEKERJAAN GALIAN

1 Galian Tanah Pondasi


Type I
1m

0.8 m

0.8 m

Panjang Pondasi:
Meter lari pondasi type I = 97 95 m

Jadi, Panjang Pondasi = 95 m


Volume = 68.4 m3

Type II
1 m

0.8 m

0.5 m

Panjang Pondasi:
Meter lari pondasi type II = 76 m
Panjang Pondasi = 76 m
Volume = 45.6 m3

Total Galian Pondasi = 114.00 m3 114.00 m3

2 Timbunan Tanah Kembali

Volume Galian = 114.00 m3


Volume Timbunan = 1/4 x Vol. Galian
= 28.5 m3 28.50 m3

3 Timbunan Tanah Bawah Lantai T L


Carport 3 x 2.5 = 7.5

7.5 x 0.05 = 0.375 m3

Ruang Makan 2.43 x 3.43 = 8.335


Mushollah 0 x 0 = 0.000
Dapur 2.43 x 2.43 = 5.905
Ruang Tamu 2.43 x 3.42 = 8.311
Ruang Keluarga 1.50 x 3.42 = 5.130
Kamar Utama 2.50 x 2.43 = 6.075
Kamar Tidur Tamu 2.43 x 2.43 = 5.905

39.660 x 0.15 = 5.94905 m3

WC I 1 x 1.43 = 1.430
WC II 1.58 x 1.50 = 2.370
3.800 x 0.10 = 0.38 m3

Teras Depan 2 x 2.28 = 4.560


Teras Belakang 4.43 x 4.3 = 19.049
23.609 x 0.10 = 2.3609 m3

Volume Timbunan = 9.065 m3

9.064945 m3

4 Urugan Pasir Dibawah Pondasi

Type I 0.86 m

0.10 m
0.80 m

Panjang Pondasi = 95 m
Volume = 7.885 m3

Type II
0.52 m

0.10 m
0.5 m

Panjang Pondasi = 76 m
Volume = 3.876 m3

Total Urugan Pasir Bawah Pondasi = 11.761 m3 11.761 m3

5 Urugan Pasir Di Bawah Lantai

Carport 3 x 2.5 = 7.5 m2


Ruang Makan 2.43 x 3.43 = 8.3349 m2
Mushollah 0 x 0 = 0 m3
Ruang Tamu 2.43 x 3.42 = 8.3106 m3
Ruang Keluarga 1.50 x 3.42 = 5.13 m2
Gudang 0 x 0 = 0 m3
Dapur 2.43 x 2.43 = 5.9049 m4
Kamar Utama 2.50 x 2.43 = 6.075 m2
Kamar Tidur Tamu 2.43 x 2.43 = 5.9049 m2
Kamar Tidur II 0 x 0 = 0 m2
WC I 1 x 1.43 = 1.43 m2
WC II 1.58 x 1.50 = 2.37 m2
Teras Depan 2 x 2.28 = 4.56 m2
Teras Belakang 4.43 x 4.3 = 19.049 m2
74.5693 m2

Luas Lantai = 74.5693 m2


Tebal pasir = 0.1 m
Volume = 7.45693 m3

Total Urugan Pasir Bawah Pondasi = 7.45693 m3 7.45693 m3

1 Pas. Pondasi Batu Gunung 1:5


Type I
0.30 m

0.60 m

0.60 m
Panjang Pondasi = 95 m
Volume = 25.65 m3

Type II
0.3 m

0.60 m

0.6 m
Panjang Pondasi = 76 m
Volume = 20.52 m3

Total Volume Pondasi = 46.17 m3 46.17 m3

2 Pas. Batu Kosong


Type I

0.92

0.2 m

0.84

Panjang Pondasi = 95 m
Volume = 16.72 m3

Type II

0.7

0.2 m

0.62

Panjang Pondasi = 76 m
Volume = 10.032 m3

Total Pas. Batu Kosong = 26.75 m3 26.75 m3

IV PEKERJAAN BETON
1 Pek. Sloef

0.2 m

0.15 m

Panjang Sloef = 173.3 m


Volume = 5.199 m3 5.199 m3

2 Pek. Kolom
15 x 15

0.15 m
0.15 m

0.2 m

Volume Kolom
0.15 x 0.20 x 4.00 x 38 = 4.56 m3

Total Volume Kolom = 4.56

4.56 m3

3 Pek. Ring Balk

0.2 m

0.15 m
Panjang Ring Balk = 88 m
Volume = 0.2 x 0.15 x 88
= 2.64 m3 2.64 m3

4 Pek. Rabat Beton Bawah Lantai


Luas Lantai Rumah = 67.0693 m2
Tebal Rabat Beton = 0.05 m
Volume Rabat Beton = 67.0693 x 0.05
= 3.353465 m3 3.35 m3

5 Pek. Rabat Beton Carport

Luas Lantai Carport = 7.5 m2


Tebal Rabat Beton = 0.05 m
Volume Rabat Beton = 7.5 x 0.05
= 0.38 m3 0.38 m3

V PEKERJAAN TEMBOK & LANTAI


1 Pek. Dinding

Luas Dinding Tanpa Pintu dan Jendela = 684 m2


Luas Pintu dan Jendela
Type P1
1.1

1.9 jumlah 1 Bh

= 1.1 x 1.90 x 1
= 2.0900 m2

Type P2
1.7

1.9 jumlah 3 Bh

= 1.1 x 1.90 x 3
= 6.27 m2

Type P3
0.82

2.05
jumlah 1 Bh

= 0.82 x 2.05 x 1
= 1.681 m2

Type J1
1.58
1.32 jumlah 2 Bh

= 1.58 x 1.32 x 2
= 4.17 m2

Type J2
0.92

1.32 jumlah 3 Bh

= 0.92 x 1.32 x 3
= 3.64 m2

Luas Pintu dan Jendela Keseluruhan


= p1 p2 p3 j1 j2
= 2.09 6.27 1.681 4.17 3.64
= 17.86

Volume = 17.86 x 0.15


= 2.67831 m3
Volume dinding utuh = 684 x 0.15
102.6
Volume pek. Dinding 1:5 = Volume dinding utuh - Volume pimtu dan jendela
= 102.6 - 2.67831
= 99.9217 99.92 m3

2 Plesteran
Tebal Plesteran = 0.02 m
Volume Plesteran = 26.6458 m3 26.64578 m3

3 Acian
Volume Plesteran = 13.3229 m3 13.3 m3

4 Pek. Dinding Keramik WC dan Jemuran (20 x 20) (2 Kamar Mandi)

Luas Wc/ KM 1 = 1 x 1.43


= 1.43 m2 x

2 = 1.58 x 1.50
= 2.37 m2 x

Total = 3.8 m2

Luas Jemuran = 0 x 3 - 0 * 2.6


= 0 m2 - 0
= 0 m3

TOTAL = 3.8 3.8 m3

5 Pek. Lantai Keramik 40 x 40 cm


Ruang Makan 2.43 x 3.43 = 8.3349
Ruang Keluarga 1.50 x 3.42 = 5.13
Ruang Tamu 2.43 x 3.42 = 8.3106
Kamar Utama 2.50 x 2.43 = 6.075
Kamar Tidur Tamu 2.43 x 2.43 = 5.9049

Jadi Luas Secara Keseluruhan Lantai Keramik


= 8.3349 + 5.13 + 8.3106 + 6.075 + 5.9
= 33.76 m2 33.76 m2

6 Luas lantai teras 30 x 30 cm


Luas teras depan = 2 x 2.28
= 4.56 m2
Luas teras belakang = 4.43 x 4.3
= 19.049 m2
Luas total = 4.56 + 19.049
= 23.609 m2 23.61 m2

VI PEKERJAAN PINTU DAN JENDELA


1 Pek. Kusen Pintu dan Jendela
P1 5 / 15 ( 1 Buah )
Panjang Balok = 4.6 m
Luas = 0.05 x 0.15 = 0.0075 m2
Volume = 4.6 x 0.0075 = 0.0345 m3
= 0.0345 m3

P2 5 / 15 ( 3 Buah )
Panjang Balok = 4.5 m
Luas = 0.05 x 0.15 = 0.0075 m2
Volume = 4.5 x 0.0075 = 0.03375 m 3

= 0.10125 m3

P3 5 / 15 ( 2 Buah )
Panjang Balok = 4.50 m
Luas = 0.05 x 0.15 = 0.0075 m2
Volume = 4.50 x 0.0075 = 0.03375 m3
= 0.0675 m3

J1 5/15 ( 6 Buah )
Panjang Balok = 9.20 m
Luas = 0.05 x 0.15 = 0.0075 m2
Volume = 9.20 x 0.0075 = 0.069 m 3

= 0.414 m3

J2 5 / 15 ( 2 Buah )
Panjang Balok = 5.90 m
Luas = 0.05 x 0.15 = 0.0075 m2
Volume = 5.90 x 0.0075 = 0.044 m3
= 0.0885 m3

Jadi Total Volume


= P1 + P2 + P3 + J1 + J2
= 0.0345 + 0.10125 + 0.0675 + 0.414 + 0.0885
= 0.71 m3 0.706 m3

2 Pek. Daun Pintu


P1 ( 4 Buah )
Tebal = 3 cm
Lebar = 0.7 m
Panjang = 1.96 m
Luas = 0.7 x 1.96 = 1.372 m2
= 5.488 m2

P2 ( 3 Buah )
Tebal = 3 cm
Lebar = 0.72 m
Panjang = 1.96 m
Luas = 0.72 x 1.96 = 1.411 m2
= 4.234 m2

P3 ( 2 Buah )
Tebal = 3 cm
Lebar = 0.72 m
Panjang = 1.96 m
Luas = 0.72 x 1.96 = 1.411 m2
= 2.822 m2
Jadi Total Luas
= 5.488 + 4.234 + 2.822
= 12.544 m2 12.544 m2

3 Pek. Kaca Mati


J1
Tebal = 5 mm Jumlah 4 Bh
Luas = 2.592 m2

J2
Tebal = 5 mm Jumlah 3 Bh
Luas = 1.530 m2

Jadi Total Volume


= J1 + J2
= 2.592 + 1.530
= 4.122 m2 4.122 m2

5 Pas. Kunci Tanam


= 5 Bh 11 Bh

6 Pas. Engsel Pintu


= 12 Bh 12 Bh

7 Pas. Grendel Pintu


= 5 Bh 9 Bh

8 Pas. Engsel Jendela


= 15 Bh 15 Bh

9 Pas. Grendel Jendela


= 5 Bh 5 Bh

10 Hak Angin
= 12 Bh 12 Bh

VII PEKERJAAN ATAP DAN PLAFOND


1 Pek. Kuda-Kuda 6/12

Panjang Balok Kuda-Kuda

= 4.18+1.62+6.86+2.1+1.04+1.51+1.71+1.51+1.04+1.04 = 23 m

Volume
= 0.06 x 0.12 x 23
= 0.162792 m3 x 3 Bh
= 0.488376 m3
0.4884 m3

2 Pek. Balok Nok 8/12


Panjang Balok = 16.5 m
Volume = 0.08 x 0.12 x 16.5
= 0.1584 m3 0.1584 m3

3 Pek. Skor Angin 8/10


Panjang Balok = 1.500 m
Volume = 0.08 x 0.10 x 1.500
= 0.012 m3 x 6 Bh
= 0.072 m3 0.072 m3

4 Pek. Gording 5/7


Panjang Balok = 16.5

Volume = 0.06 x 0.12 x 16.5


= 0.1188 m3 0.1188 m3

5 Pek. Kasau 5/7


Panjang balok = 18.5

Volume = 0.05 x 0.07 x 18.5


= 0.0648 m3 0.06475 m3

6 Pek.Reng 2/3
Panjang Balok = 16.5

Volume = 0.03 x 0.04 x 16.5


= 0.0198 m3 0.0198 m3

7 Pek. Atap Genteng


Luas = 149.600 m2 149.600 m2

8 Pek. Bubungan / Nok Atap


Luas = 16 m1 16 m1

1
9 Pek. Rangka Plafond 5/7

Carport 3 x 2.5 = 7.5


Ruang Makan 2.43 x 3.43 = 8.3349
Mushollah 0 x 0 = 0
Ruang Tamu 2.43 x 3.42 = 8.3106
Ruang Keluarga 1.5 x 3.42 = 5.13
Gudang 0 x 0 = 0
Dapur 2.43 x 2.43 = 5.9049
Kamar Utama 2.5 x 2.43 = 6.075
Kamar Tidur Tamu 2.43 x 2.43 = 5.9049
Kamar Tidur II 0 x 0 = 0
WC I 1 x 1.43 = 1.43
WC II 1.58 x 1.5 = 2.37
Teras Depan 2 x 2.28 = 4.56
Teras Belakang 4.43 x 4.3 = 19.049
74.5693

Rangka Plafond = Luas : ukuran plafond


= 74.5693 : (1,2*1,2)
= 74.5693 : 1.44
= 51.78424

Volume = 0.05 x 0.07 x 51.784


= 0.18124 m3 0.181245 m3

10 Pek. Plafond

Carport 3 x 2.5 = 7.5


Ruang Makan 2.43 x 3.43 = 8.3349
Mushollah 0 x 0 = 0
Ruang Tamu 2.43 x 3.42 = 8.3106
Ruang Keluarga 1.5 x 3.42 = 5.13
Gudang 0 x 0 = 0
Dapur 2.43 x 2.43 = 5.9049
Kamar Utama 2.5 x 2.43 = 6.075
Kamar Tidur Tamu 2.43 x 2.43 = 5.9049
Kamar Tidur II 0 x 0 = 0
WC I 1 x 1.43 = 1.43
WC II 1.58 x 1.5 = 2.37
Teras Depan 2 x 2.28 = 4.56
Teras Belakang 4.43 x 4.3 = 19.049
74.5693 m2

Luas Total Plafond = 74.57 m2 74.57 m2

11 Pek. Lisplank
Panjang Total Lisplank = (0,2*16,5) x 2 x 2
= 13.2 m2 13.2 m2

VIII PEKERJAAN PENGECETAN


1 Pek. Pengecetan Tembok
Luas Total Dinding Yang Di Cet = 13 m2 13.3 m2

2 Pek. Kusen, Pintu dan Jendela


Luas = P1 + P2 + P3 + J1 + J2
= 2.1 + 6.27 + 1.681 + 4.17 + 3.64
= 17.855 m2 17.855 m2

3 Pek. Pengecetan Plafond


Luas Pengecetan Plafond = 75 m2 75 m2

4 Pek. Pengecetan Lisplank


Luas Pengecetan Lisplank = 13 m 13 m

5 Pek. Pengecetan Atap


Luas Pengecetan Atap = 0.000 m2 0.000 m2

IX PEKERJAAN INSTALASI LISTRIK

1 Pas. Saklar Ganda


Volume Saklar Ganda = 2 Bh 2 Bh

2 Pas. Saklar Tunggal


Volume Saklar Tunggal = 5 Bh 5 Bh

3 Pas. Stop Kontak


Volume Stop Kontak = 7 Bh 7 Bh

4 Pas. Lampu Hias


Volume Lampu Hias = 1 Bh 1 Bh

5 Pas. Lampu Pijar 20 watt


Volume Lampu Pijar 18 watt = 1 Bh 1 Bh

6 Pas. Lampu Pijar 40 watt


Volume Lampu Pijar 40 watt = 4 Bh 4 Bh

X PEKERJAAN SANITASI
1 Pek. Stop kran
Volume Stop Kran = 6 Unit 6 Unit

2 Pek. Pipa 3/4'


Panjang Pipa 3/4' = 40 m 40 m

3 Pek. Pipa PVC 4'


Panjang Pipa PVC 4' = 20 m 20 m

4 Pas. Klosed Duduk


Volume Klosed Duduk = 2 Pas 2 Pas

5 Pek. Bak Cuci Piring


Volume Bak Cuci Piring = 1 Pas 1 Pas

6 Bak Air Viber


Volume Bak Air Viber = 2 Pas 2 Pas
7 Floor Drain = 3 pas 3 pas
STANDAR HARGA SATUAN BAHAN BANGUNAN DAN UPAH KERJA
PEMERINTAH PROVINSI SULAWESI SELATAN
KOTA MAKASSAR
TAHUN 2018
Dalam Rupiah (Rp)
NO BAHAN DASAR SPESIFIKASI SATUAN HARGA HARGA + 10%
1 2 3 4 5 5
BAHAN KAYU

1 Kayu Kelas 1 bayam (balok) chain saw m3 Rp 9,980,500 10,978,550

2 Kayu kelas 1 bayam (balok) sawmill m3 Rp 9,980,500 10,978,550

3 Kayu kelas 1 Ulin (papan) m 3


Rp 20,500,000 22,550,000
4 Kayu Kelas 1 ulin (tiang) m3 Rp 20,000,000 22,000,000

5 Kayu Kelas 1 bayam ( Papan) shain saw m3 Rp 17,000,000 18,700,000

6 Kayu Kelas 1 bayam ( Papan) sawmill m3 Rp 17,000,000 18,700,000

7 Kayu kelas II samarinda (balok)/lokal m3 Rp 5,857,000 6,442,700

8 Kayu kelas II samarinda (papan)/lokal m3 Rp 5,535,000 6,088,500

9 Kayu Kelas III kapur (balok)/kemiri m3 Rp 4,980,000 5,478,000

10 Kayu kelas III (papan) m3 Rp 6,940,000 7,634,000


11 Kayu Perancah m3 Rp 6,657,000 7,322,700
12 Kayu Mangga/Kemiri papan m 3
Rp 6,990,000 7,689,000
13 Kayu kumea balok m3 Rp 6,807,000 7,487,700
14 Kayu kumea papan m3 Rp 6,770,000 7,447,000
15 Papan kelas 1 m3 Rp 20,000,000 22,000,000
16 papan kelas 11 m3 Rp 4,657,500 5,123,250

17 Kayu lapis Tripleks Lapis Kayu lainnya Lembar Rp 65,700 72,270

18 Kayu lapis Tripleks Lapis Kayu lainnya Lembar Rp 60,250 66,275

19 Kayu lapis Tripleks Lapis Kayu lainnya Lembar Rp 90,400 99,440

20 Dolken Kayu Ø 8-10/400 cm Btg Rp 25,500 28,050


21 Minyak Bekisting ltr Rp 25,000 27,500
Bahan Besi
22 Paku Campuran 5-10 cm kg Rp 30,700 33,770
23 Paku asbes dan karet kg Rp 25,000 27,500
24 Paku kg Rp 26,700 29,370
25 Paku 1 1/2 - 2 1/2 cm 2-3 cm kg Rp 18,000 19,800
26 Paku 4 cm kg Rp 18,700 20,570
27 paku 2-3 cm kg Rp 17,000 18,700
28 Paku sirap 2-3 cm kg Rp 17,000 18,700
29 Paku seng 1kg/dos kg Rp 17,000 18,700
30 Paku skrup Biji Rp 2,000 2,200
Bariling 450 bj =
31 Paku skrup besi hollow 1000 biji per d 4,5 cm Dos/bungkus Rp 60,000 66,000

32 Paku skrup gypsum-500 biji perbungkus Dos/bungkus Rp 50,000 55,000

33 Paku jembatan kg Rp 50,000 55,000


34 Paku Beton 5 cm Dos Rp 20,000 22,000
35 Paku Beton 6 cm Dos Rp 50,000 55,000
36 Paku Beton 7-10 cm Dos Rp 50,000 55,000
37 Paku Payung Berulir 1 kg/ dos kg Rp 30,000 33,000
38 Paku asbes berulir dos Rp 30,000 33,000
39 Paku asbes biasa dos Rp 20,000 22,000
setara paku 2-3
40 Paku Triplex kh Rp 15,000 16,500
cm
setara paku 2-3
41 Paku eternit kg Rp 15,000 16,500
cm
42 Paku ripet Biji Rp 20,000 22,000
43 Besi Streep 30 x 3 mm m' Rp 60,000 66,000
44 Kawat ikat beton kg Rp 20,900 22,990
akustik 120 x 60 cm lmbr Rp 51,000 56,100
Polos
Besi Beton kg Rp 20,800 22,880
45 ( campuran)
Bahan Dasar -
46 Agregat Kasar m3 Rp 130,000.00 143,000
47 Agregat Halus m3 Rp 200,000.00 220,000
48 Batu kali m3 Rp 240,000.00 264,000
49 Batu Kali Bela m3 Rp 265,000.00 291,500
50 Batu Gunung m3 Rp 365,700.00 402,270
51 Batu Belah 10-15 cm m3 Rp 340,800.00 374,880
52 Batu Pecah 7-10 cm m3 Rp 318,200.00 350,020
53 Batu Pecah 5-7 cm m3 Rp 380,200.00 418,220
54 Batu Pecah 3-5 cm m3 Rp 350,000.00 385,000
55 Batu Pecah 2-3 cm m3 Rp 345,000.00 379,500
56 Batu Pecah 1- 2 cm m3 Rp 345,000.00 379,500
57 Batu Pecah 0,5 - 1 cm m3 Rp 480,900.00 528,990
58 Batu merah standar BIji Rp 900.00 990
59 Bata Ringan m3 Rp 2,180,200.00 2,398,220
21x10,5x6cm -
60 Bata block m3 Rp 35,400.00 38,940
60 Bh/M2
21x10,5x6cm -
61 Bata block Buah Rp 38,900.00 42,790
60 Bh/M3
21x10,5x6cm -
62 Batako 60 Bh/M4 m3 Rp 70,600.00 77,660

63 Roster 15 x 30 cm m3 Rp 55,800.00 61,380


64 Glass Block m3 Rp 28,200.00 31,020
65 Gravel m3 Rp 150,400.00 165,440
66 Material Pilihan m3 Rp 196,600.00 216,260
67 Urugan Pilihan m3 Rp 235,200.00 258,720

68 Pasirkasar/pasir beton/pasir pasangan m 3


Rp 230,000.00 253,000

69 Sirtu A m3 Rp 235,000.00 258,500


70 Sirtu B m3 Rp 220,000.00 242,000
71 Sirtu C m3 Rp 287,000.00 315,700
72 Pasir Timbunan m3 Rp 271,600.00 298,760
73 Tanah timbunan m3 Rp 199,500.00 219,450
74 Kerikil Sungai m3 Rp 240,400.00 264,440

75 Semen
50 kg P,C sak Rp 90,300.00 99,330
(Tonasa)

76 Semen 40 kg P,C sak Rp 95,700.00 105,270


(Tonasa)

77 Semen
Putih 40 Kg per sak Rp 130,700.00 143,770
sak
78 Semen tonasa kg Rp 1,806.00 1,987
79 Pigmen warana kg Rp 150,000.00 165,000
80 Semen nat tegel sak Rp 25,900.00 28,490
Bahan Atap -
genteng beton bh bh Rp 43,000.00 47,300
BWG 33 BJLS
81 Seng BWG Kaki Rp 65,000.00 71,500
0,20 MM

82 Seng BWG BWG 28 BJLS Lembar Rp 80,000.00 88,000


0,35 MM

Gelombang bjls
83 Seng Lembar Rp 88,500.00 97,350
0,35 (6 Kaki)

Gelombang bjls
84 Seng Lembar Rp 85,000.00 93,500
0,25 (6 Kaki)

Gelombang bjls
85 Seng Lembar Rp 85,000.00 93,500
0,20 (7 Kaki)

86 Seng Gelombang bjls Lembar Rp 50,000.00 55,000


0,20 (10 Kaki)

87 Seng Gelombang bjls Lembar Rp 58,000.00 63,800


0,20
Plat bjls 0,35 (6
88 Seng plat bjls KK) Lembar Rp 85,000.00 93,500

89 Seng plat bjls Plat bjls 0,30 (6 Lembar Rp 85,200.00 93,720


KK)

90 Seng plat bjls Plat bjls 0,20 (6 Lembar Rp 58,100.00 63,910


KK)
91 Seng Fiber Fiber Lembar Rp 20,500.00 22,550
Bahan Kaca -
92 Kaca bening 3 mm m2 Rp 155,800.00 171,380
93 Kaca bening 5 mm m2 Rp 140,400.00 154,440
94 Kaca bening 6 mm m2 Rp 280,900.00 308,990
95 Kaca bening 8 mm m2 Rp 323,500.00 355,850
96 Kaca bening 10 mm m2 Rp 440,900.00 484,990
Bahan Penggantung -
97 Engsel Baja Biji Rp 35,800.00 39,380
98 Engsel Kuningan pasang Rp 80,400.00 88,440
99 Engsel Stainless steel pasang Rp 18,000.00 19,800
100 Engsel H-3 lubang pasang Rp 69,800.00 76,780
101 Engsel Kupu-Kupu pasang Rp 27,200.00 29,920
102 Engsel antik jendela pasang Rp 221,700.00 243,870
103 Engsel pintu Biasa merk 777 pasang Rp 63,300.00 69,630
104 Engsel pintu lemari biasa pasang Rp 18,450.00 20,295
105 Engsel jendela biasa merk 777 pasang Rp 36,600.00 40,260
106 Engsel Jendela Kuningan pasang Rp 31,350.00 34,485
107 Engsel Pintu 4" (SES) Bh Rp 30,000.00 33,000
108 Engsel Jendela 5" (SES) Bh Rp 45,000.00 49,500
109 Engsel pintu kuningan SES Pasang Rp 45,000.00 49,500
110 Gagang Pintu lemari Bh Rp 45,000.00 49,500
111 Grendel jendela kuningan Bh Rp 45,000.00 49,500
112 Grendel Pintu biasa Royalty Bh Rp 45,000.00 49,500
113 Grendel pintu kuningan/vertikal Bh Rp 45,000.00 49,500
114 Grendel pintu besar Buah Rp 45,000.00 49,500
115 Grendel pintu tanam ( expanyolet) Buah Rp 45,000.00 49,500
116 Kunci tanam yale 1xputar Buah Rp 45,000.00 49,500
117 Kunci tanam yale 2xputqr Buah Rp 45,000.00 49,500
2xputar besar
118 Kunci tanam pintu biasa Buah Rp 45,000.00 49,500

119 Kunci tanam pintu 2 x putar kecil Buah Rp 45,000.00 49,500


biasa
120 Kunci tanam pintu 2 x putas SES Buah Rp 45,000.00 49,500
121 Hak angin kecil antik Buah Rp 45,000.00 49,500
122 Hak angin besar Buah Rp 45,000.00 49,500
handle jendela Buah Rp 45,000.00 49,500
123 Hak angin kecil Buah Rp 45,000.00 49,500
Bahan langit-langit Rp 45,000.00 49,500
124 Pinyu fiberglass KM/WC Lembar Rp 45,000.00 49,500
Pintu KM/WCBahan PVC Lengkap
125 asesoris ex MASPION Unit Rp 45,000.00 49,500

126 Teakwood 120 x 240 cm Lembar Rp 45,000.00 49,500


t. 3mm
3 mm 120 x
127 Triplex Lembar Rp 55,000.00 60,500
240 cm
128 4 mm 120 x Lembar
Triplex Rp 68,000.00 74,800
240 cm
129 Triplex 5 mm Lembar Rp 55,000.00 60,500

130 6 mm 120 x Lembar Rp 65,000.00 71,500


Triplex
240 cm
131 Triplex 7 mm Lembar Rp 75,000.00 82,500
132 Triplex 9 mm Lembar Rp 75,000.00 82,500
133 Triplex 10 mm Lembar Rp 75,000.00 82,500
134 Triplex 15 mm Lembar Rp 75,000.00 82,500
135 Triplex 20 mm Lembar Rp 75,000.00 82,500
136 Triplex ukuran pintu Lembar Rp 75,000.00 82,500
120 x 240 cm Lembar
137 Triplex melamin 3 mm
Rp 75,000.00 82,500

120 x 240 cm Lembar Rp 75,000.00 82,500


138 Teakwood
4 mm
120 x 240 cm Lembar
139 Multiplex Rp 75,000.00 82,500
6 mm
120 x 240 cm Lembar
140 Multiplex Rp 75,000.00 82,500
9 mm
120 x 240 cm Lembar
141 Multiplex Rp 75,000.00 82,500
12 mm
120 x 240 cm Lembar
142 Multiplex 18 mm
Rp 75,000.00 82,500

122 x 244 cm Lembar Rp 75,000.00 82,500


143 Gypsum board
9 mm
144 Kalsiboard 4 m' Lembar Rp 75,000.00 82,500
145 Lambrizing Lembar Rp 75,000.00 82,500
Lebar 5 cm ( 4 Lembar
146 HPL Rp 75,000.00 82,500
m')
Lebar 3 cm ( 4
147 Les kayu Profil batang Rp 75,000.00 82,500
m')
Lebar 1 1/2 cm
148 Les kayu Profil batang Rp 75,000.00 82,500
( 4 m')
1 x 10 x 400 Rp 75,000.00 82,500
149 Les kayu Profil batang
cm
150 Les kayu 4 x 4 x 400 cm batang Rp 75,000.00 82,500

151 Les Kayu Profil 0,5 x 3 cm batang Rp 75,000.00 82,500


152 Les kayu Biasa batang Rp 75,000.00 82,500
Bahan lantai Rp 75,000.00 82,500
153 Tegel pc 30 x 30 cm Dos Rp 75,000.00 82,500
154 tegel motif 30 x 30 cm Dos Rp 75,000.00 82,500
155 Tegel keramik putih 10 x 20 cm Dos Rp 75,000.00 82,500
156 Tegel keramik putih 20 x 20 cm Dos Rp 75,000.00 82,500
157 Tegel keramik putih 20 x 25 cm Dos Rp 75,000.00 82,500
158 Tegel keramik putih 30 x 30 cm Dos Rp 75,000.00 82,500
159 Tegel keramik putih 40 x 40 cm Dos Rp 75,000.00 82,500
160 Tegel keramik putih 50 x 50 cm Dos Rp 75,000.00 82,500
60 x 60 cm Ex Rp 75,000.00 82,500
161 Tegel keramik putih Dos
granito
60 x 60 cm Ex
162 Tegel keramik putih Dos Rp 230,000.00 253,000
garuda
30 x 60 cm Ex
163 Tegel keramik putih granito Dos Rp 230,000.00 253,000

60 x 60 cm Ex
164 Tegel keramik putih granito Dos Rp 230,000.00 253,000

60 x 60 cm Ex
165 Tegel Keramik Warna Dos Rp 172,000.00 189,200
garuda
30 x 60 cm Ex Rp 294,000.00 323,400
166 Tegel Keramik Warna Dos
garuda
167 Tegel keramik putih 30 x 60 cm Dos Rp 107,900.00 118,690
168 Tegel Keramik Warna 20 x 20 cm Dos Rp 60,000.00 66,000
169 Tegel Keramik Warna 30 x 30 cm Dos Rp 60,000.00 66,000
170 Tegel Keramik Warna 20 x 25 cm m2 Rp 60,000.00 66,000
171 Tegel Keramik Warna 40 x 40 cm m 2 Rp 60,000.00 66,000
50 x 50 cm
172 Tegel Keramik Warna Dos Rp 60,000.00 66,000
(Platinum)
60 x 60 cm
173 Tegel Keramik Warna Dos Rp 60,000.00 66,000
(Enem polos)
174 Tegel Keramik Warna 30 x 60 cm Dos Rp 60,000.00 66,000
175 Keramik WC 20 x 20 cm Dos Rp 60,000.00 66,000
176 Keramik WC 20 x 25 cm Dos Rp 60,000.00 66,000
177 Keramik WC 30 x 30 cm Dos Rp 60,000.00 66,000
178 Keramik 30 x 30 cm Dos Rp 60,000.00 66,000
179 Keramik 40 x 40 cm Dos Rp 60,000.00 66,000
Bahan Finishing Rp 60,000.00 66,000
180 Cat dasar 3,5 kg /kaleng kaleng Rp 60,000.00 66,000
181 Cat Dasar meni 3,5 kg /kaleng kaleng Rp 45,000.00 49,500
182 Cat meni glatik 3,5 kg /kaleng kaleng Rp 45,000.00 49,500
183 Cat meni kg Rp 45,000.00 49,500
184 Plamur tembok Boyo dan setara 5kg Kaleng Rp 45,000.00 49,500
185 Palmur Kg Rp 45,000.00 49,500
186 Cat dasar Tembok Kg Rp 45,000.00 49,500
187 Cat tembok dulux 2,5 kg kaleng Rp 45,000.00 49,500
188 Cat tembok dulux Kg Rp 45,000.00 49,500
189 Cat seng Nippon 2,5 kg kaleng Rp 45,000.00 49,500
batu tempel m2 Rp 45,000.00 49,500
kapur pasang zak Rp 45,000.00 49,500
190 Cat seng Nippon kg Rp 45,000.00 49,500
Bahan instalasi listrik -
Eterna 3 x 2,5
191 Kabel NYM M Rp 8,540.00 9,394
mm
192 Saklar Tunggal Panasonic buah Rp 9,500.00 10,450
193 Saklar Ganda Panasonic Buah Rp 25,000.00 27,500
194 Stop kontak Broco Bh Rp 15,500.00 17,050
195 Stop kontak Clipsal Bh Rp 35,400.00 38,940
IKEA
196 lampu Hias buah Rp 100,000.00 110,000
HEMMA
Bohlam (lampu penerangan) PCC 23 Rp 35,500.00 39,050
197 Watt Ecuat pcs
Bohlam (lampu penerangan) Philips
198 buah Rp 9,500.00 10,450
pijar 40 watt
Bahan pipa -
199 tee 4'' bh Rp 120,000.00 132,000
keni 4'' bh Rp 120,000.00 132,000
pipa gip 1 1/2'' 1 1/2'' m Rp 53,550.00 58,905
200 Pipa jenis C untuk instalasi listrik 5/8" m Rp 5,125.00 5,638
201 Pipa PVC 3/4" - 4 m Batang Rp 41,400.00 45,540
202 Pipa PVC 3/4" m Rp 10,350.00 11,385
203 Pipa PVC 4" - 4 m batang Rp 156,300.00 171,930
204 Pipa PVC 4" m Rp 39,075.00 42,983
205 tee 3/4'' bh Rp 65,900.00 72,490
206 keni 3/4'' bh Rp 15,500.00 17,050
Bahan saniter/saluran air -
Kloset Duduk Ex KIA lengkap (putih)
207 unit Rp 800,000.00 880,000
tangki batu
Kloset Duduk Ex KIA lengkap
208 unit Rp 800,000.00 880,000
(warna) tangki batu
Kloset duduk ex Toto lengkap Rp 800,000.00 880,000
209 accessories warna putih unit
Kloset duduk ex Toto lengkap
210 accessories warna gelap unit Rp 600,000.00 660,000

211 Kloset jongkok ex KIA Buah Rp 285,500.00 314,050


212 Kloset jongkok biasa Buah Rp 90,000.00 99,000
213 Kran air kuningan DIA 3/4 Biasa Buah Rp 47,100.00 51,810
214 Kran air vernekel DIA 1/2 biasa DIA 1/2 Biasa Buah Rp 41,400.00 45,540
215 Kran air vernekel DIA 3/4 biasa DIA 3/4 Biasa Buah Rp 41,800.00 45,980
216 Kran air antik DIA 1/2 DIA 1/2 Biasa Buah Rp 120,700.00 132,770
217 Seal tape Buah Rp 2,500.00 2,750
218 Bak Cuci Piring Stain Steel Buah Rp 683,800.00 752,180
219 Bak tube fiber biasa Buah Rp 579,300.00 637,230
220 Bak tube fiber ex toto Buah Rp 861,400.00 947,540
Saringan kotoran Kamar Mandi Rp 34,000.00 37,400
221 Buah
Bahan Besi/Kuningan (Floor Drain)
222 Saringan kotoran Kamar Mandi Buah Rp 20,000.00 22,000
Bahan Plastik (Floor Drain)
224 septicktanck ls Rp 1,800,000.00 2,000,000
223 ijuk resapan kg Rp 4,200.00 4,620
UPAH KERJA -
1 Mandor Lapangan Orang/Hari Rp 240,000.00 264,000
2 Kepala Tukang Orang/Hari Rp 220,000.00 242,000
3 Kepala Tukang Listrik Orang/Hari Rp 155,000.00 170,500
4 Tukang Batu / Cat Orang/Hari Rp 145,000.00 159,500
5 Tukang Kayu / Besi Orang/Hari Rp 155,000.00 170,500
6 Tukang Pasang Paving Orang/Hari Rp 130,000.00 143,000
7 Pembantu Sopir Orang/Hari Rp 125,000.00 137,500
8 Pembantu Mekanik Orang/Hari Rp 140,000.00 154,000
9 Pembantu Tukang Listrik Orang/Hari Rp 140,000.00 154,000
10 Pembantu Operator Orang/Hari Rp 130,000.00 143,000
11 Mekanik Orang/Hari Rp 125,000.00 137,500
12 Operator Terlatih Orang/Hari Rp 155,000.00 170,500
13 Pekerja Orang/Hari Rp 230,000.00 253,000
14 Sopir Terampil Orang/Hari Rp 135,000.00 148,500
15 Biaya pasang Canstein /M' Rp 125,000.00 137,500
16 Biaya pasang Paving /M2 Rp 125,000.00 137,500
DAFTAR ANALISA BIAYA
PERENCANAAAN PEMBANGUNAN PERUMAHAN "GRIYA OURHOUSE"
TYPE 45
Kota MakassarTahun 2018

No Uraian Koef Sat Harga Satuan Jumlah

1 An. 1. 1 M2 Membersihkan Lapangan dan P eralatan


Upah :
Pekerja 0.050 Hr @ Rp. 253,000.00 Rp. 12,650.00
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.00
Harga Satuan Rp. 20,570.00

An. . 1 M' Pengukuran & Pemasangan Bowplank


Upah :
Kayu 5/7 Klas III 0.001 M³ @ Rp. 5,478,000.00 Rp. 5,478.00
Paku Biasa 2"-5" 0.020 Kg @ Rp. 33,770.00 Rp. 675.40
Kayu papan 3/20 0.004 M³ @ Rp. 7,634,000.00 Rp. 30,536.00
Tenaga :
Tukang Kayu 0.100 Hr @ Rp. 170,500.00 Rp. 17,050.00
Pekerja 0.100 Hr @ Rp. 253,000.00 Rp. 25,300.00
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.00
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.00
Harga Satuan Rp. 82,779.40

Pembuatan direksi keet dan los kerja


Upah :
Kayu 5/7 Klas II 0.001 M³ @ Rp. 6,442,700.00 Rp. 6,442.70
Paku Biasa 2"-5" 0.020 Kg @ Rp. 33,770.00 Rp. 675.40
Kayu papan 3/20 0.004 M³ @ Rp. 6,088,500.00 Rp. 24,354.00
Tenaga :
Tukang Kayu 0.100 Hr @ Rp. 170,500.00 Rp. 17,050.00
Pekerja 0.100 Hr @ Rp. 253,000.00 Rp. 25,300.00
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.00
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.00
Harga Satuan Rp. 77,562.10

2 An. 2. 1 M3 Galian Tanah biasa


Upah :
Pekerja 0.550 Hr @ Rp. 253,000.00 Rp. 139,150.00
Mandor 0.015 Hr @ Rp. 264,000.00 Rp. 3,960.00
Harga Satuan Rp. 143,110.00

3 An. 3. 1 M3 Urugan Kembali


Upah :
Pekerja 0.102 Hr @ Rp. 253,000.00 Rp. 25,806.00
Mandor 0.015 Hr @ Rp. 264,000.00 Rp. 3,960.00
Harga Satuan Rp. 29,766.00

4 An. 4. 1 M3 Pemadatan Tanah


Upah :
Pekerja 0.300 Hr @ Rp. 253,000.00 Rp. 75,900.00
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.00
Harga Satuan Rp. 83,820.00

5 An. 5. 1 M3 Urugan Pasir


Bahan :
Pasir Urug 1.100 M3 @ Rp. 258,500.00 Rp. 284,350.00
Upah :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.00
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.00
Harga Satuan Rp. 337,590.00

6 An. 6. 1 M3 Urugan Si rt u
Bahan :
Sirtu 1.100 M3 @ Rp. 242,000.00 Rp. 266,200.00
Upah :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.00
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.00
Harga Satuan Rp. 319,440.00

7 An. 7. 1 M3 Urugan Tanah


Bahan :
Tanah Urug 1.100 M3 @ Rp. 258,720.00 Rp. 284,592.00
Upah :
Pekerja 0.100 Hr @ Rp. 253,000.00 Rp. 25,300.00
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.00
Harga Satuan Rp. 312,532.00

8 An. 8. 1 M3 Pasang Pondasi Batu Kosong


Bahan :
Batu Gunung 15/20 cm 1.200 M3 @ Rp. 374,880.00 Rp. 449,856.00
Pasir Urug 0.300 M3 @ Rp. 258,500.00 Rp. 77,550.00
Upah :
Pekerja 0.780 Hr @ Rp. 253,000.00 Rp. 197,340.00
Tukang Batu 0.390 Hr @ Rp. 159,500.00 Rp. 62,205.00
Kepala Tukang 0.039 Hr @ Rp. 242,000.00 Rp. 9,438.00
Mandor 0.039 Hr @ Rp. 264,000.00 Rp. 10,296.00
Harga Satuan Rp. 806,685.00

9 An. 9. 1 M3 Pasang Pondasi Batu Gunung 1 Pc : 3 Ps


Bahan :
Batu Gunung 1.100 M3 @ Rp. 374,880.00 Rp. 412,368.00
Semen Portland 350.000 Kg @ Rp. 2,631.75 Rp. 921,112.50
Pasir Pasangan 0.314 M3 @ Rp. 253,000.00 Rp. 79,442.00
Upah :
Pekerja 1.100 Hr @ Rp. 253,000.00 Rp. 278,300.00
Tukang Batu 0.300 Hr @ Rp. 159,500.00 Rp. 47,850.00
Kepala Tukang 0.050 Hr @ Rp. 242,000.00 Rp. 12,100.00
Mandor 0.055 Hr @ Rp. 264,000.00 Rp. 14,520.00
Harga Satuan Rp. 1,765,692.50

10 An. 10. 1 M3 Pasang Pondasi Batu Kali 1 P c : 5 P s


Bahan :
Batu Kali 1.000 M3 @ Rp. 264,000.00 Rp. 264,000.00
Semen Portland 99.000 Kg @ Rp. 2,631.75 Rp. 260,543.25
Pasir Pasangan 0.520 M3 @ Rp. 253,000.00 Rp. 131,560.00
Upah :
Pekerja 2.000 Hr @ Rp. 253,000.00 Rp. 506,000.00
Tukang Batu 1.000 Hr @ Rp. 159,500.00 Rp. 159,500.00
Kepala Tukang 0.050 Hr @ Rp. 242,000.00 Rp. 12,100.00
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.00
Harga Satuan Rp. 1,341,623.25

11 An. 11. 1 M2 Pasang Bata Merah 1/ 2 Bata, 1 Pc : 3 Ps


Bahan :
Bata Merah 5x11x22 140.000 Bh @ Rp. 990.00 Rp. 138,600.00
Semen Portland 40.500 Kg @ Rp. 2,631.75 Rp. 106,585.88
Pasir Pasangan 0.080 M3 @ Rp. 253,000.00 Rp. 20,240.00
Upah :
Pekerja 0.650 Hr @ Rp. 253,000.00 Rp. 164,450.00
Tukang Batu 0.200 Hr @ Rp. 159,500.00 Rp. 31,900.00
Kepala Tukang 0.020 Hr @ Rp. 242,000.00 Rp. 4,840.00
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.00
Harga Satuan Rp. 474,535.88

12 An. 12. 1 M3 Pasang Bata Merah 1/ 2 Bata, 1 Pc : 5 Ps


Bahan :
Bata Merah 5x11x22 70.000 Bh @ Rp. 990.00 Rp. 69,300.00
Semen Portland 9.680 Kg @ Rp. 2,631.75 Rp. 25,475.34
Pasir Pasangan 0.045 M3 @ Rp. 253,000.00 Rp. 11,385.00
Upah :
Pekerja 0.320 Hr @ Rp. 253,000.00 Rp. 80,960.00
Tukang Batu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.00
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.00
Mandor 0.015 Hr @ Rp. 264,000.00 Rp. 3,960.00
Harga Satuan Rp. 209,450.34

13 An. 13. 1 M2 Pasang Lantai Bata Merah 1/ 4 Bata , 1 P c : 5 P s


Bahan :
Bata Merah 5x11x22 30.000 Bh @ Rp. 990.00 Rp. 29,700.00
Semen Portland 3.840 Kg @ Rp. 2,631.75 Rp. 10,105.92
Pasir Pasangan 0.023 M3 @ Rp. 253,000.00 Rp. 5,692.50
Upah :
Pekerja 0.160 Hr @ Rp. 253,000.00 Rp. 40,480.00
Tukang Batu 0.050 Hr @ Rp. 159,500.00 Rp. 7,975.00
Kepala Tukang 0.005 Hr @ Rp. 242,000.00 Rp. 1,210.00
Mandor 0.008 Hr @ Rp. 264,000.00 Rp. 1,980.00
Harga Satuan Rp. 97,143.42

14 An. 14. 1 M2 Plest eran 1 Pc : 3 Ps, tebal 1, 5 cm


Bahan :
Semen Portland 3.480 Kg @ Rp. 2,631.75 Rp. 9,158.49
Pasir Pasangan 0.019 M3 @ Rp. 253,000.00 Rp. 4,807.00
Upah :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.00
Tukang Batu 0.150 Hr @ Rp. 159,500.00 Rp. 23,925.00
Kepala Tukang 0.015 Hr @ Rp. 242,000.00 Rp. 3,630.00
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.00
Harga Satuan Rp. 94,760.49

15 An. 15. 1 M2 Plest eran 1 Pc : 5 Ps, tebal 1, 5 cm


Bahan :
Semen Portland 2.320 Kg @ Rp. 2,631.75 Rp. 6,105.66
Pasir Pasangan 0.022 M3 @ Rp. 253,000.00 Rp. 5,566.00
Upah :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.00
Tukang Batu 0.150 Hr @ Rp. 159,500.00 Rp. 23,925.00
Kepala Tukang 0.015 Hr @ Rp. 242,000.00 Rp. 3,630.00
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.00
Harga Satuan Rp. 92,466.66

16 An. 16. 1 M2 Plest eran 1 Pc : 3 Ps, tebal 2 cm


Bahan :
Semen Portland 8.800 Kg @ Rp. 2,631.75 Rp. 23,159.40
Pasir Pasangan 0.026 M3 @ Rp. 253,000.00 Rp. 6,578.00
Upah :
Pekerja 0.250 Hr @ Rp. 253,000.00 Rp. 63,250.00
Tukang Batu 0.200 Hr @ Rp. 159,500.00 Rp. 31,900.00
Kepala Tukang 0.020 Hr @ Rp. 242,000.00 Rp. 4,840.00
Mandor 0.013 Hr @ Rp. 264,000.00 Rp. 3,300.00
Harga Satuan Rp. 133,027.40

17 An. 17. 1 M2 Plest eran 1 Pc : 5 Ps, tebal 2 cm


Bahan :
Semen Portland 5.290 Kg @ Rp. 2,631.75 Rp. 13,921.96
Pasir Pasangan 0.028 M3 @ Rp. 253,000.00 Rp. 7,084.00
Upah :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.00
Tukang Batu 0.200 Hr @ Rp. 159,500.00 Rp. 31,900.00
Kepala Tukang 0.020 Hr @ Rp. 242,000.00 Rp. 4,840.00
Mandor 0.012 Hr @ Rp. 264,000.00 Rp. 3,168.00
Harga Satuan Rp. 111,513.96

18 An. 18. 1 M2 Acian P lesteran


Bahan :
Semen Portland 3.000 Kg @ Rp. 2,631.75 Rp. 7,895.25
Kapur Pasangan 0.030 Kg @ Rp. 65,000.00 Rp. 1,950.00
Upah :
Pekerja 1.000 Hr @ Rp. 253,000.00 Rp. 253,000.00
Tukang Batu 1.000 Hr @ Rp. 159,500.00 Rp. 159,500.00
Kepala Tukang 0.100 Hr @ Rp. 242,000.00 Rp. 24,200.00
Mandor 0.050 Hr @ Rp. 264,000.00 Rp. 13,200.00
Harga Satuan Rp. 459,745.25

19 An. 19. 1 M3 Membuat Beton Tumbuk 1 P c : 3 P s : 6 K r


Bahan :
Semen Portland 150.000 Kg @ Rp. 2,631.75 Rp. 394,762.50
Pasir Beton 0.470 M3 @ Rp. 253,000.00 Rp. 118,910.00
Koral Beton 0.940 M3 @ Rp. 376,200.00 Rp. 353,628.00
Air 150.000 L @ Rp. 250.00 Rp. 37,500.00
Tenaga :
Pekerja 1.200 Hr @ Rp. 253,000.00 Rp. 303,600.00
Tukang Batu 0.250 Hr @ Rp. 159,500.00 Rp. 39,875.00
Kepala Tukang 0.025 Hr @ Rp. 242,000.00 Rp. 6,050.00
Mandor 0.080 Hr @ Rp. 264,000.00 Rp. 21,120.00
Harga Satuan Rp. 1,275,445.50

20 An. 20. 1 M3 Membuat Beton Bertulang, 1 Pc : 2 Ps : 3 Kr


Bahan :
Semen Portland 225.000 Kg @ Rp. 2,631.75 Rp. 592,143.75
Pasir Beton 0.540 M3 @ Rp. 253,000.00 Rp. 136,620.00
Koral Beton 0.820 M3 @ Rp. 376,200.00 Rp. 308,484.00
Air 125.000 L @ Rp. 250.00 Rp. 31,250.00
Tenaga :
Pekerja 13.000 Hr @ Rp. 253,000.00 Rp. 3,289,000.00
Tukang Batu 1.000 Hr @ Rp. 159,500.00 Rp. 159,500.00
Kepala Tukang 1.250 Hr @ Rp. 242,000.00 Rp. 302,500.00
Mandor 0.400 Hr @ Rp. 264,000.00 Rp. 105,600.00
Harga Satuan Rp. 4,925,097.75

21 An. 22 1 Kg Pembesian dengan Besi Polos atau Besi Ulir


Bahan :
Besi Beton ( Polos/ulir ) 1.050 Kg @ Rp. 22,880.00 Rp. 24,024.000
Kawat Beton 0.015 Kg @ Rp. 22,990.00 Rp. 344.850
Tenaga :
Pekerja 0.007 Hr @ Rp. 253,000.00 Rp. 1,771.000
Tukang Besi 0.007 Hr @ Rp. 159,500.00 Rp. 1,116.500
Kepala Tukang 0.001 Hr @ Rp. 242,000.00 Rp. 169.400
Mandor 0.000 Hr @ Rp. 264,000.00 Rp. 79.200
Harga Satuan Rp. 27,504.95

22 An. 22. 1 M2 Pasangan Bekisting


Bahan :
Papan Kayu Klas III 0.045 M3 @ Rp. 7,634,000.00 Rp. 343,530.000
Paku Biasa 2" - 5" 0.300 Kg @ Rp. 33,770.00 Rp. 10,131.000
Minyak Bekisting 0.100 Ltr @ Rp. 27,500.00 Rp. 2,750.000
Tenaga :
Pekerja 0.300 Hr @ Rp. 253,000.00 Rp. 75,900.000
Tukang Kayu 0.260 Hr @ Rp. 159,500.00 Rp. 41,470.000
Kepala Tukang 0.026 Hr @ Rp. 242,000.00 Rp. 6,292.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Harga Satuan Rp. 481,393.00

23 An. 23. 1 M3 Membuat Bet on B ert ulang


Analisa :
An. 20. Beton segar 1.000 M3 @ Rp. 4,925,097.75 Rp. 4,925,097.750
An. 22 Pembesian Beton 125.000 Kg @ Rp. 27,504.95 Rp. 3,438,118.750
An. 22. Bekisting 6.000 M2 @ Rp. 481,393.00 Rp. 2,888,358.000
Harga Satuan Rp. 11,251,574.50

24 An. 24. 1 M3 Pasang K onstruksi Kuda-kuda


Bahan :
Balok Kayu Klas I 1.100 M3 @ Rp. 10,978,550.00 Rp. 12,076,405.000
Balok Kayu Klas II 1.100 M3 @ Rp. 6,442,700.00 Rp. 7,086,970.000
Balok Kayu Klas III 1.100 M3 @ Rp. 5,478,000.00 Rp. 6,025,800.000
Besi Strip 15.000 Kg @ Rp. 66,000.00 Rp. 990,000.000
Paku Biasa 2" - 5" 0.800 Kg @ Rp. 33,770.00 Rp. 27,016.000
Tenaga :
Pekerja 4.000 Hr @ Rp. 253,000.00 Rp. 1,012,000.000
Tukang Kayu 12.000 Hr @ Rp. 159,500.00 Rp. 1,914,000.000
Kepala Tukang 1.200 Hr @ Rp. 242,000.00 Rp. 290,400.000
Mandor 0.200 Hr @ Rp. 264,000.00 Rp. 52,800.000
Balok Kayu Klas I Rp. 16,362,621.00
Balok Kayu Klas II Rp. 11,373,186.00

Balok Kayu Klas III Rp. 10,312,016.00

25 An. 25. 1 M3 Pasang Gurding


Bahan :
Balok Kayu Klas I 1.100 M3 @ Rp. 10,978,550.00 Rp. 12,076,405.000
Balok Kayu Klas II 1.100 M3 @ Rp. 6,442,700.00 Rp. 7,086,970.000
Balok Kayu Klas III 1.100 M3 @ Rp. 5,478,000.00 Rp. 6,025,800.000
Paku Biasa 2" - 5" 0.800 Kg @ Rp. 33,770.00 Rp. 27,016.000
Tenaga :
Pekerja 6.000 Hr @ Rp. 253,000.00 Rp. 1,518,000.000
Tukang Kayu 12.000 Hr @ Rp. 159,500.00 Rp. 1,914,000.000
Kepala Tukang 1.800 Hr @ Rp. 242,000.00 Rp. 435,600.000
Mandor 0.300 Hr @ Rp. 264,000.00 Rp. 79,200.000
Balok Kayu Klas I Rp. 16,050,221.00
Balok Kayu Klas II Rp. 11,060,786.00
Balok Kayu Klas III Rp. 9,999,616.00

26 An. 26. 1 M2 Pasang K aso + Reng A tap Gent eng


Bahan :
Balok Kayu Klas I 0.012 M @ Rp.
3
10,978,550.00 Rp. 131,742.600
Balok Kayu Klas II 0.012 M3 @ Rp. 6,442,700.00 Rp. 77,312.400
Balok Kayu Klas III 0.014 M3 @ Rp. 5,478,000.00 Rp. 76,692.000
Paku Biasa 2" - 5" 0.150 Kg @ Rp. 33,770.00 Rp. 5,065.500
Tenaga :
Pekerja 0.100 Hr @ Rp. 253,000.00 Rp. 25,300.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Balok Kayu Klas I Rp. 181,798.10
Balok Kayu Klas II Rp. 127,367.90
Balok Kayu Klas III Rp. 126,747.50

27 An. 27. 1 M2 Pasang K aret Pelapis At ap Genteng


Bahan :
Karet Pelapis 1.200 M2 @ Rp. 15,000.00 Rp. 18,000.000
Paku Biasa 2" - 5" 0.500 Kg @ Rp. 33,770.00 Rp. 16,885.000
Tenaga :
Pekerja 0.150 Hr @ Rp. 253,000.00 Rp. 37,950.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.000
Harga Satuan Rp. 93,845.00

28 An. 28. 1 M2 Pasang A tap Gent eng


Bahan :
Genteng 8.000 Lbr @ Rp. 36,300.00 Rp. 290,400.000
Paku Biasa 2" - 5" 0.030 Kg @ Rp. 33,770.00 Rp. 1,013.100
Tenaga :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.000
Harga Satuan Rp. 363,023.10

29 An. 29. 1 M1 Pasang Nok A tap Gent eng


Bahan :
Nok Genteng Beton 2.000 Lbr @ Rp. 16,500.00 Rp. 33,000.000
Semen Portland 2.000 Kg @ Rp. 2,631.75 Rp. 5,263.500
Pasir Pasangan 0.020 M3 @ Rp. 253,000.00 Rp. 5,060.000
Tenaga :
Pekerja 0.150 Hr @ Rp. 253,000.00 Rp. 37,950.000
Tukang Kayu 0.075 Hr @ Rp. 159,500.00 Rp. 11,962.500
Kepala Tukang 0.008 Hr @ Rp. 242,000.00 Rp. 1,815.000
Mandor 0.008 Hr @ Rp. 264,000.00 Rp. 1,980.000
Harga Satuan Rp. 97,031.00

30 An. 30. 1 M2 Pasang Listplank 3/20


Bahan :
Balok Kayu Klas I 0.011 M3 @ Rp. 10,978,550.00 Rp. 120,764.050
Balok Kayu Klas II 0.011 M3 @ Rp. 6,442,700.00 Rp. 70,869.700
Balok Kayu Klas III 0.011 M3 @ Rp. 5,478,000.00 Rp. 60,258.000
Paku Biasa 2" - 5" 0.050 Kg @ Rp. 33,770.00 Rp. 1,688.500
Tenaga :
Pekerja 0.110 Hr @ Rp. 253,000.00 Rp. 27,830.000
Tukang Kayu 0.220 Hr @ Rp. 159,500.00 Rp. 35,090.000
Kepala Tukang 0.022 Hr @ Rp. 242,000.00 Rp. 5,324.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Balok Kayu Klas I Rp. 192,016.55
Balok Kayu Klas II Rp. 142,122.20
Balok Kayu Klas III Rp. 131,510.50

31 An. 31. 1 M2 Pasang Listplank 3/30


Bahan :
Balok Kayu Klas I 0.011 M3 @ Rp. 10,978,550.00 Rp. 120,764.050
Balok Kayu Klas II 0.011 M3 @ Rp. 6,442,700.00 Rp. 70,869.700
Balok Kayu Klas III 0.011 M3 @ Rp. 5,478,000.00 Rp. 60,258.000
Paku Biasa 2" - 5" 0.050 Kg @ Rp. 33,770.00 Rp. 1,688.500
Tenaga :
Pekerja 0.110 Hr @ Rp. 253,000.00 Rp. 27,830.000
Tukang Kayu 0.220 Hr @ Rp. 159,500.00 Rp. 35,090.000
Kepala Tukang 0.022 Hr @ Rp. 242,000.00 Rp. 5,324.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Balok Kayu Klas I Rp. 192,016.55
Balok Kayu Klas II Rp. 142,122.20
Balok Kayu Klas III Rp. 131,510.50

32 An. 32. 1 M2 Pasang Listplank 2x3/ 20


Bahan :
Balok Kayu Klas I 0.011 M3 @ Rp. 10,978,550.00 Rp. 120,764.050
Balok Kayu Klas II 0.011 M3 @ Rp. 6,442,700.00 Rp. 70,869.700
Balok Kayu Klas III 0.011 M3 @ Rp. 5,478,000.00 Rp. 60,258.000
Paku Biasa 2" - 5" 0.050 Kg @ Rp. 33,770.00 Rp. 1,688.500
Tenaga :
Pekerja 0.110 Hr @ Rp. 253,000.00 Rp. 27,830.000
Tukang Kayu 0.220 Hr @ Rp. 159,500.00 Rp. 35,090.000
Kepala Tukang 0.022 Hr @ Rp. 242,000.00 Rp. 5,324.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Balok Kayu Klas I Rp. 192,016.55
Balok Kayu Klas II Rp. 142,122.20
Balok Kayu Klas III Rp. 131,510.50

33 An. 33. 1 M1 Pasang Listplank 2x2/ 20


Bahan :
Balok Kayu Klas I 0.011 M3 @ Rp. 10,978,550.00 Rp. 120,764.050
Balok Kayu Klas II 0.011 M3 @ Rp. 6,442,700.00 Rp. 70,869.700
Balok Kayu Klas III 0.011 M3 @ Rp. 5,478,000.00 Rp. 60,258.000
Paku Biasa 2" - 5" 0.050 Kg @ Rp. 33,770.00 Rp. 1,688.500
Tenaga :
Pekerja 0.110 Hr @ Rp. 253,000.00 Rp. 27,830.000
Tukang Kayu 0.220 Hr @ Rp. 159,500.00 Rp. 35,090.000
Kepala Tukang 0.022 Hr @ Rp. 242,000.00 Rp. 5,324.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Balok Kayu Klas I Rp. 192,016.55
Balok Kayu Klas II Rp. 142,122.20
Balok Kayu Klas III Rp. 131,510.50

34 An. 34. 1 M2 Pasang A tap Gent eng


Bahan :
Genteng 8.000 Lbr @ Rp. 36,300.00 Rp. 290,400.000
Paku 0.030 Kg @ Rp. 33,770.00 Rp. 1,013.100
Tenaga :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.000
Harga Satuan Rp. 363,023.10

35 An. 35. 1 M2 Pasang Nok Genteng


Bahan :
Nok Genteng 2.000 Lbr @ Rp. 16,500.00 Rp. 33,000.000
Paku 0.050 Kg @ Rp. 33,770.00 Rp. 1,688.500
Tenaga :
Pekerja 0.400 Hr @ Rp. 253,000.00 Rp. 101,200.000
Tukang Kayu 0.200 Hr @ Rp. 159,500.00 Rp. 31,900.000
Kepala Tukang 0.020 Hr @ Rp. 242,000.00 Rp. 4,840.000
Mandor 0.020 Hr @ Rp. 264,000.00 Rp. 5,280.000
Harga Satuan Rp. 177,908.50

36 An. 36. 1 M2 Pasang Rangka Langit-langit 100x100 cm


Bahan :
Balok Kayu Klas I 0.012 M3 @ Rp. 10,978,550.00 Rp. 131,742.600
Balok Kayu Klas II 0.012 M3 @ Rp. 6,442,700.00 Rp. 77,312.400
Balok Kayu Klas III 0.012 M3 @ Rp. 5,478,000.00 Rp. 65,736.000
Paku Biasa 2" - 5" 2.000 Kg @ Rp. 33,770.00 Rp. 67,540.000
Tenaga :
Pekerja 0.600 Hr @ Rp. 253,000.00 Rp. 151,800.000
Tukang Kayu 1.800 Hr @ Rp. 159,500.00 Rp. 287,100.000
Kepala Tukang 0.180 Hr @ Rp. 242,000.00 Rp. 43,560.000
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.000
Balok Kayu Klas I Rp. 689,662.60
Balok Kayu Klas II Rp. 635,232.40
Balok Kayu Klas III Rp. 623,656.00

37 An. 37. 1 M2 Pasang Langit -l angit 100x100 cm


Bahan :
Etermit 1.000 Lbr @ Rp. ### Rp. 5,166,983,185.089
Tripleks 0.390 Lbr @ Rp. 60,500.00 Rp. 23,595.000
Paku 0.020 Kg @ Rp. 33,770.00 Rp. 675.400
Tenaga :
Pekerja 0.300 Hr @ Rp. 253,000.00 Rp. 75,900.000
Tukang Kayu 0.500 Hr @ Rp. 159,500.00 Rp. 79,750.000
Kepala Tukang 0.050 Hr @ Rp. 242,000.00 Rp. 12,100.000
Mandor 0.020 Hr @ Rp. 264,000.00 Rp. 5,280.000
Plafond Eternit Rp. 5,167,094,190.49
Plafond Tripleks Rp. 197,300.40

38 An. 38. 1 M1 Pasang List P lafound K ayu Profil


Bahan :
Kayu Profil 1.100 M1 @ Rp. 82,500.00 Rp. 90,750.000
Tenaga :
Pekerja 0.050 Hr @ Rp. 253,000.00 Rp. 12,650.000
Tukang Kayu 0.050 Hr @ Rp. 159,500.00 Rp. 7,975.000
Kepala Tukang 0.005 Hr @ Rp. 242,000.00 Rp. 1,210.000
Mandor 0.003 Hr @ Rp. 264,000.00 Rp. 792.000
Harga Satuan Rp. 113,377.00

39 An. 39. 1 M3 Pasang K usen Pintu dan Jendela Klas I


Bahan :
Balok Kayu Klas I 1.100 M3 @ Rp. 10,978,550.00 Rp. 12,076,405.000
Tenaga :
Pekerja 6.000 Hr @ Rp. 253,000.00 Rp. 1,518,000.000
Tukang Kayu 20.000 Hr @ Rp. 159,500.00 Rp. 3,190,000.000
Kepala Tukang 2.000 Hr @ Rp. 242,000.00 Rp. 484,000.000
Mandor 0.300 Hr @ Rp. 264,000.00 Rp. 79,200.000
Harga Satuan Rp. 17,347,605.00

40 An. 40. 1 M2 Pasang Jalusi P int u dan Jendela K ayu Klas I


Bahan :
Papan Kayu Klas I (kayu bangkirei) 0.064 M3 @ Rp. 25,500,000.00 Rp. 1,632,000.000
Tenaga :
Pekerja 1.000 Hr @ Rp. 253,000.00 Rp. 253,000.000
Tukang Kayu 3.000 Hr @ Rp. 159,500.00 Rp. 478,500.000
Kepala Tukang 0.300 Hr @ Rp. 242,000.00 Rp. 72,600.000
Mandor 0.300 Hr @ Rp. 264,000.00 Rp. 79,200.000
Harga Satuan Rp. 2,515,300.00

41 An. 41. 1 M2 Pasang Jalusi Mat i Kusen K ayu Klas I


Bahan :
Papan Kayu Klas I (kayu bangkirei) 0.060 M3 @ Rp. 10,978,550.00 Rp. 658,713.000
Paku Biasa 1/2"-1" 0.150 Kg @ Rp. 20,570.00 Rp. 3,085.500
Tenaga :
Pekerja 0.500 Hr @ Rp. 253,000.00 Rp. 126,500.000
Tukang Kayu 2.000 Hr @ Rp. 159,500.00 Rp. 319,000.000
Kepala Tukang 0.200 Hr @ Rp. 242,000.00 Rp. 48,400.000
Mandor 0.025 Hr @ Rp. 264,000.00 Rp. 6,600.000
Harga Satuan Rp. 1,162,298.50

42 An. 42. 1 M2 Pasang P int u dan Jendela P anil Kayu K las I


Bahan :
Papan Kayu Klas I (kayu bangkirei) 0.040 M3 @ Rp. 10,978,550.00 Rp. 439,142.000
Tenaga :
Pekerja 1.544 Hr @ Rp. 253,000.00 Rp. 390,632.000
Tukang Kayu 4.633 Hr @ Rp. 159,500.00 Rp. 738,963.500
Kepala Tukang 0.463 Hr @ Rp. 242,000.00 Rp. 112,046.000
Mandor 0.463 Hr @ Rp. 264,000.00 Rp. 122,232.000
Harga Satuan Rp. 1,803,015.50

43 An. 43. 1 M2 Pasang P int u dan Jendela P anil Kaca K las I


Bahan :
Papan Kayu Klas I (kayu bangkirei) 0.035 M3 @ Rp. 10,978,550.00 Rp. 384,249.250
Kaca Bening 6 mm 1.100 M2 @ Rp. 308,990.00 Rp. 339,889.000
Tenaga :
Pekerja 0.800 Hr @ Rp. 253,000.00 Rp. 202,400.000
Tukang Kayu 2.000 Hr @ Rp. 159,500.00 Rp. 319,000.000
Kepala Tukang 0.200 Hr @ Rp. 242,000.00 Rp. 48,400.000
Mandor 0.040 Hr @ Rp. 264,000.00 Rp. 10,560.000
Harga Satuan Rp. 1,304,498.25
44 An. 44. 1 M2 Pasang K aca Mati
Bahan :
Kaca Bening 6 mm 1.000 M2 @ Rp. 154,440.00 Rp. 154,440.000
Kayu Les Klas II 0.005 M3 @ Rp. 82,500.00 Rp. 412.500
Tenaga :
Pekerja 0.150 Hr @ Rp. 253,000.00 Rp. 37,950.000
Tukang Kayu 0.500 Hr @ Rp. 159,500.00 Rp. 79,750.000
Kepala Tukang 0.050 Hr @ Rp. 242,000.00 Rp. 12,100.000
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.000
Harga Satuan Rp. 287,292.50

45 An. 45. 1 M2 Pasang Lantai K eramik


Bahan :
Keramik 20x20 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Keramik 20x25 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Keramik 30x30 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Keramik 40x40 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Semen Portland 11.380 Kg @ Rp. 1,986.60 Rp. 22,607.508
Pasir Pasangan 0.042 M3 @ Rp. 253,000.00 Rp. 10,626.000
Semen Warna 1.500 Kg @ Rp. 28,490.00 Rp. 42,735.000
Tenaga :
Pekerja 0.620 Hr @ Rp. 253,000.00 Rp. 156,860.000
Tukang Batu 0.350 Hr @ Rp. 159,500.00 Rp. 55,825.000
Kepala Tukang 0.035 Hr @ Rp. 242,000.00 Rp. 8,470.000
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.000
Keramik 20x20 Rp. 371,043.51
Keramik 20x25 Rp. -
Keramik 30x30 Rp. 371,043.51
Keramik 40x40 Rp. 371,043.51

46 An. 46. 1 M Pasang Dindi ng K eramik


2

Bahan :
Keramik 10/20 1.000 M2 @ Rp. 62,920.00 Rp. 62,920.000
Keramik 20x20 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Keramik 20x25 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Keramik 30x30 1.000 M2 @ Rp. 66,000.00 Rp. 66,000.000
Batu Tempel 1.000 M2 @ Rp. 163,350.00 Rp. 163,350.000
Semen Portland 9.300 Kg @ Rp. 1,986.60 Rp. 18,475.380
Pasir Pasangan 0.018 M3 @ Rp. 253,000.00 Rp. 4,554.000
Semen Warna 1.500 Kg @ Rp. 28,490.00 Rp. 42,735.000
Tenaga :
Pekerja 0.600 Hr @ Rp. 253,000.00 Rp. 151,800.000
Tukang Batu 0.450 Hr @ Rp. 159,500.00 Rp. 71,775.000
Kepala Tukang 0.045 Hr @ Rp. 242,000.00 Rp. 10,890.000
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.000
Keramik 10/20 Rp. 371,069.38
Keramik 20x20 Rp. 374,149.38
Keramik 20x25 Rp. 374,149.38
Keramik 30x30 Rp. 374,149.38
Batu Tempel Rp. 471,499.38

47 An. 47. 1 M2 Pengecatan Tembok/Et ernit Baru


( 1 Lps Plamir, 1 Lps Cat Dasar, 2 Lps Cat Penutup )
Bahan :
Plamir 1 x 0.100 Kg @ Rp. 49,500.00 Rp. 4,950.000
Cat Dasar 1 x 0.100 Kg @ Rp. 49,500.00 Rp. 4,950.000
Cat Penutup 2 x 0.200 Kg @ Rp. 49,500.00 Rp. 9,900.000
Tenaga :
Pekerja 0.200 Hr @ Rp. 253,000.00 Rp. 50,600.000
Tukang Cat 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.009 Hr @ Rp. 242,000.00 Rp. 2,178.000
Mandor 0.030 Hr @ Rp. 264,000.00 Rp. 7,920.000
Harga Satuan Rp. 96,448.00

48 An. 48. 1 M2 Pengecatan Kayu Baru ( 1 Lps Plamir, 1 Lps Cat Dasar, 2 Lps Cat Penut up )
Bahan :
Cat Meni 0.200 Kg @ Rp. 49,500.00 Rp. 9,900.000
Plamir 1 x 0.150 Kg @ Rp. 49,500.00 Rp. 7,425.000
Cat Dasar 1 x 0.170 Kg @ Rp. 14,142.86 Rp. 2,404.286
Cat Penutup 2 x 0.350 Kg @ Rp. 15,000.00 Rp. 5,250.000
Tenaga :
Pekerja 0.070 Hr @ Rp. 253,000.00 Rp. 17,710.000
Tukang Cat 0.105 Hr @ Rp. 159,500.00 Rp. 16,747.500
Kepala Tukang 0.004 Hr @ Rp. 242,000.00 Rp. 968.000
Mandor 0.003 Hr @ Rp. 264,000.00 Rp. 660.000
Harga Satuan Rp. 51,164.79

49 An. 49. 1 M2 Pengecatan At ap Seng Baru ( 1 Lps Cat Dasar, 2 Lps Cat P enutup )
Bahan :
Cat Dasar 1 x 0.170 Kg @ Rp. 49,500.00 Rp. 8,415.000
Cat Penutup 2 x 0.260 Kg @ Rp. 19,800.00 Rp. 5,148.000
Tenaga :
Pekerja 0.070 Hr @ Rp. 253,000.00 Rp. 17,710.000
Tukang Cat 0.009 Hr @ Rp. 159,500.00 Rp. 1,435.500
Kepala Tukang 0.006 Hr @ Rp. 242,000.00 Rp. 1,452.000
Mandor 0.003 Hr @ Rp. 264,000.00 Rp. 660.000
Harga Satuan Rp. 34,820.50

50 An. 50. 1 Bh Kunci Tanam 2 x Putar


Bahan :
Kunci Tanam 2 x Putar 1.000 Bh @ Rp. 49,500.00 Rp. 49,500.000
Tenaga :
Pekerja 0.010 Hr @ Rp. 253,000.00 Rp. 2,530.000
Tukang Kayu 0.500 Hr @ Rp. 159,500.00 Rp. 79,750.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Harga Satuan Rp. 135,520.00

51 An. 51. 1 Bh Engsel Pintu Kuningan


Bahan :
Engsel Pintu Kuningan 1.000 Bh @ Rp. 49,500.00 Rp. 49,500.000
Tenaga :
Pekerja 0.015 Hr @ Rp. 253,000.00 Rp. 3,795.000
Tukang Kayu 0.150 Hr @ Rp. 159,500.00 Rp. 23,925.000
Kepala Tukang 0.015 Hr @ Rp. 242,000.00 Rp. 3,630.000
Mandor 0.001 Hr @ Rp. 264,000.00 Rp. 198.000
Harga Satuan Rp. 81,048.00

52 An. 52. 1 Bh Engsel Jendela Kuningan


Bahan :
Engsel Jendela Kuningan 1.000 Bh @ Rp. 34,485.00 Rp. 34,485.000
Tenaga :
Pekerja 0.020 Hr @ Rp. 253,000.00 Rp. 5,060.000
Tukang Kayu 0.200 Hr @ Rp. 159,500.00 Rp. 31,900.000
Kepala Tukang 0.020 Hr @ Rp. 242,000.00 Rp. 4,840.000
Mandor 0.010 Hr @ Rp. 264,000.00 Rp. 2,640.000
Harga Satuan Rp. 78,925.00

53 An. 53. 1 Bh Grendel Pintu


Bahan :
Grendel Pintu 1.000 Bh @ Rp. 49,500.00 Rp. 49,500.000
Tenaga :
Pekerja 0.010 Hr @ Rp. 253,000.00 Rp. 2,530.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.010 Hr @ Rp. 242,000.00 Rp. 2,420.000
Mandor 0.005 Hr @ Rp. 264,000.00 Rp. 1,320.000
Harga Satuan Rp. 71,720.00

54 An. 54. 1 Bh Grendel Jendela


Bahan :
Grendel Jendela 1.000 Bh @ Rp. 49,500.00 Rp. 49,500.000
Tenaga :
Pekerja 0.012 Hr @ Rp. 253,000.00 Rp. 3,036.000
Tukang Kayu 0.120 Hr @ Rp. 159,500.00 Rp. 19,140.000
Kepala Tukang 0.012 Hr @ Rp. 242,000.00 Rp. 2,904.000
Mandor 0.006 Hr @ Rp. 264,000.00 Rp. 1,584.000
Harga Satuan Rp. 76,164.00

55 An. 55. 1 Bh Kait Angin Jendela


Bahan :
Kair Angin 1.000 Bh @ Rp. 49,500.00 Rp. 49,500.000
Tenaga :
Pekerja 0.015 Hr @ Rp. 253,000.00 Rp. 3,795.000
Tukang Kayu 0.100 Hr @ Rp. 159,500.00 Rp. 15,950.000
Kepala Tukang 0.015 Hr @ Rp. 242,000.00 Rp. 3,630.000
Mandor 0.001 Hr @ Rp. 264,000.00 Rp. 198.000
Harga Satuan Rp. 73,073.00

56 An. 56. 1 Bh Kloset Jongkok Porselain


Bahan :
Kloset Jongkok 1.000 Bh @ Rp. 314,050.00 Rp. 314,050.000
Semen Portland 6.000 Kg @ Rp. 1,986.60 Rp. 11,919.600
Pasir Pasangan 0.010 M3 @ Rp. 253,000.00 Rp. 2,530.000
Tenaga :
Pekerja 1.000 Hr @ Rp. 253,000.00 Rp. 253,000.000
Tukang Batu 1.500 Hr @ Rp. 159,500.00 Rp. 239,250.000
Kepala Tukang 1.500 Hr @ Rp. 242,000.00 Rp. 363,000.000
Mandor 0.160 Hr @ Rp. 264,000.00 Rp. 42,240.000
Harga Satuan Rp. 1,225,989.60

57 An. 57. 1 Bh Kloset Duduk


Bahan :
Kloset Duduk Lengkap 1.000 Bh @ Rp. 660,000.00 Rp. 660,000.000
Perlengkapan Rp. -
Tenaga :
Pekerja 3.300 Hr @ Rp. 253,000.00 Rp. 834,900.000
Tukang Batu 1.100 Hr @ Rp. 159,500.00 Rp. 175,450.000
Kepala Tukang 0.001 Hr @ Rp. 242,000.00 Rp. 242.000
Mandor 0.160 Hr @ Rp. 264,000.00 Rp. 42,240.000
Harga Satuan Rp. 1,712,832.00

58 An. 58. 1 Bh Urinoir


Bahan :
Urinoir 1.000 Bh @ Rp. 2,090,000.00 Rp. 2,090,000.000
Perlengkapan Rp. 627,000.000
Semen Portland 6.000 Kg @ Rp. 1,986.60 Rp. 11,919.600
Pasir Pasangan 0.010 M3 @ Rp. 253,000.00 Rp. 2,530.000
Tenaga :
Pekerja 1.000 Hr @ Rp. 253,000.00 Rp. 253,000.000
Tukang Batu 1.000 Hr @ Rp. 159,500.00 Rp. 159,500.000
Kepala Tukang 0.100 Hr @ Rp. 242,000.00 Rp. 24,200.000
Mandor 0.100 Hr @ Rp. 264,000.00 Rp. 26,400.000
Harga Satuan Rp. 3,194,549.60

59 An. 59. 1 Bh Wastafel


Bahan :
Wastafel 1.000 Bh @ Rp. 752,180.00 Rp. 752,180.000
Perlengkapan Rp. 90,261.600
Semen Portland 6.000 Kg @ Rp. 1,986.60 Rp. 11,919.600
Pasir Pasangan 0.010 M3 @ Rp. 253,000.00 Rp. 2,530.000
Tenaga :
Pekerja 1.200 Hr @ Rp. 253,000.00 Rp. 303,600.000
Tukang Batu 1.450 Hr @ Rp. 159,500.00 Rp. 231,275.000
Kepala Tukang 0.150 Hr @ Rp. 242,000.00 Rp. 36,300.000
Mandor 0.100 Hr @ Rp. 264,000.00 Rp. 26,400.000
Harga Satuan Rp. 1,454,466.20
RENCANA ANGGARAN BIAYA
PERENCANAAN PEMBANGUNAN PERUMAHAN GRIYA OURHOUSE TYPE 45

NO. JENIS PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA

a b c d e f

I PONDASI

A PEKERJAAN PERSIAPAN

1 Pek. Pembersihan Lokasi 90.00 M2 Rp. 20,000.00 Rp. 1,800,000.00


1 Pek. Pengukuran/Pasangan Bowuplank 39.00 M' Rp. 20,000.00 Rp. 780,000.00

Jumlah Untuk Pekerjaan Persiapan Rp. 2,580,000.00

B PEKERJAAN TANAH DAN PASIR

1 Pek. Galian Tanah Pondasi 114.00 M3 Rp. 143,110.00 Rp. 16,314,540.00


2 Pek. Timbunan Tanah Kembali 28.50 M3 Rp. 29,766.00 Rp. 848,331.00
3 Pek. Timbunan Tanah Bawah Lantai 9.06 M3 Rp. 312,532.00 Rp. 2,833,085.39
4 Urugan Pasir bawah lantai 7.46 M3 Rp. 319,440.00 Rp. 2,382,041.72
5 Pek. Pasir Urug Bawah Pondasi 11.76 M3 Rp. 337,590.00 Rp. 3,970,395.99

Jumlah Untuk Pekerjaan Tanah dan Pasir Rp. 26,348,394.10

C PEKERJAAN PONDASI

1 Pas. Pondasi Batu Gunung /Batu kali 1:5 20.00 M3 Rp. 1,341,623.25 Rp. 26,832,465.00
2 Pek. Pas Batu Kosong 10.00 M3 Rp. 488,687.00 Rp. 4,886,870.00

Jumlah Untuk Pekerjaan Pondasi Rp. 31,719,335.00

II PEKERJAAN BETON

1 Pek. Sloef 2.00 M3 Rp. 3,917,325.00 Rp. 7,834,650.00


2 pek. Kolom 2.00 M3 Rp. 3,917,325.00 Rp. 7,834,650.00
3 Pek. Ring Balk 2.30 M3 Rp. 3,917,325.00 Rp. 9,009,847.50
4 Pek. Rabat Beton Bawah Lantai 3.30 M3 Rp. 1,275,445.50 Rp. 4,208,970.15
5 Pek. Rabat Beton Carport 0.30 M3 Rp. 1,275,445.50 Rp. 382,633.65

Jumlah Untuk Pekerjaan Beton Rp. 29,270,751.30

III PEKERJAAN TEMBOK DAN LANTAI

1 Pek. Dinding 1 : 3 20.00 M2 Rp. 474,535.88 Rp. 9,490,717.50


2 Pek. Plesteran 1 : 3 10.00 M2 Rp. 133,027.40 Rp. 1,330,274.00
3 Pek. Acian 10.00 M2 Rp. 459,745.25 Rp. 4,597,452.50
4 Pek. Dinding Keramik Wc 20x20 2.00 M2 Rp. 374,149.38 Rp. 919,490.50
5 Pek. Lantai Keramik 40 x 40 10.00 M2 Rp. 371,043.51 Rp. 3,741,493.80
6 Pek. Lantai Keramik 30 x 30 10.00 M2 Rp. 371,043.51 Rp. 3,710,435.08

Jumlah Untuk Pekerjaan Tembok dan Lantai Rp. 23,789,863.38

IV PEKERJAAN PINTU DAN JENDELA

1 Pek. Kusen Pintu dan Jendela Kls 1 0.71 M3 Rp. 17,347,605.00 Rp. 12,243,072.23
2 Pek. Daun Pintu Kls 1 5.00 M2 Rp. 1,803,015.50 Rp. 9,015,077.50
3 Pek. Kaca Mati 2.00 M2 Rp. 287,292.50 Rp. 574,585.00
4 Pas. Kunci Tanam 5.00 buah Rp. 135,520.00 Rp. 677,600.00
5 Pas. Engsel Pintu 10.00 Pas Rp. 81,048.00 Rp. 810,480.00

Jumlah Untuk Pekerjaan Pintu dan Jendela Rp. 23,320,814.73

V PEKERJAAN ATAP DAN PLAFOND

1 Pek. Kuda-kuda 0.49 M3 Rp. 16,362,621.00 Rp. 7,991,111.39


2 Pek. Balok Nok 0.16 M3 Rp. 9,999,616.00 Rp. 1,583,939.17
3 Pek. Skor Angin 0.07 M3 Rp. 9,999,616.00 Rp. 719,972.35
4 Pek. Gording 0.12 M3 Rp. 9,999,616.00 Rp. 1,187,954.38
5 Pek. Kaso + Reng 0.08 M2 Rp. 181,798.10 Rp. 15,371.03
6 Pek. Atap Genteng 7.50 M2 Rp. 363,023.10 Rp. 2,722,673.25
7 Pek. Nok Atap Genteng 16.00 M Rp. 177,908.50 Rp. 2,846,536.00
8 Pek. Rangka Plafond 0.18 M3 Rp. 689,662.60 Rp. 124,997.78
9 Pek. Plafond 6.98 M2 Rp. 197,300.40 Rp. 1,376,170.29
10 Pek. Listplank 13.20 M Rp. 113,377.00 Rp. 1,496,576.40

Jumlah Untuk Pekerjaan Atap dan Plafond Rp. 20,065,302.05

VII PEKERJAAN PENGECATAN

1 Pek. Pengecatan Tembok 10.00 M2 Rp. 96,448.00 Rp. 964,480.00


2 Pek. Cat Kusen, Pintu & Jendela 17.86 M2 Rp. 51,164.79 Rp. 913,567.71
3 Pek. Pengecatan Plafond 36.00 M2 Rp. 96,448.00 Rp. 3,472,128.00
4 Pek. Pengecatan Atap 36.00 M2 34,820.50 Rp. 1,253,538.00
5 Pek. Pengecatan Listplank 10.00 M Rp. 51,164.79 Rp. 511,647.86

Jumlah Untuk Pekerjaan Pengecatan Rp. 7,115,361.57

VIII PEKERJAAN INSTALASI LISTRIK

1 ######
Pas. Saklar Ganda 2.00 bh Rp. 27,500.00 Rp. 55,000.00
2 Pas. Saklar Tunggal 3.00 bh Rp. 10,450.00 Rp. 31,350.00
3 Pas. Stop Kontak 5.00 bh Rp. 38,940.00 Rp. 194,700.00
4 Pas. Lampu Pijar 40 Watt 1.00 bh Rp. 10,450.00 Rp. 10,450.00

Jumlah Untuk Pekerjaan Instalasi Listrik Rp. 291,500.00

IX PEKERJAAN SANITASI

1 Pek. Stop Kran 2.00 Unit Rp. 28,000.00 Rp. 56,000.00


2 Pek. Pipa 3/4 ' 2.00 btg Rp. 45,540.00 Rp. 91,080.00
3 Pek. Pipa PVC 4" 3.00 btg Rp. 171,930.00 Rp. 515,790.00
4 Pas. Kloset Duduk 1.00 Pas Rp. 1,712,832.00 Rp. 1,712,832.00
5 Pek. Bak Cuci Piring 1.00 Pas Rp. 1,454,466.20 Rp. 1,454,466.20
6 Bak Air Fiber 2.00 Pas Rp. 637,230.00 Rp. 1,274,460.00
8 Pek. Septiktank 1.00 Pas Rp. 2,500,000.00 Rp. 2,500,000.00

Jumlah Untuk Pekerjaan Sanitasi Rp. 7,604,628.20


` Rp. 172,105,950.33
3,187,147
YPE 45

JUMLAH HARGA

f
Balai Pengembangan sumber Daya Lokal UPT Dinas Tarkim
Daftar Harga bahan bangunan dan Upah Kerja
Standar Harga Pemerintah Prov. Sul- Sel, Januari - Maret Tahun 2009

a. Kabupaten/Kota : MAKASSAR
JENIS BAHAN Sat HARGA
BAHAN DASAR
1 Batu Kali
Utuh M3 Rp 135,000
Batu pecah 7-10 cm M3 Rp 160,000
Batu pecah 5-7 cm M3 Rp 170,000
Batu pecah 3-5 cm M3 Rp 190,000
Batu pecah 2-3 cm M3 Rp 230,000
Batu pecah 1-2 cm M3 Rp 250,000
Batu pecah 0.51-1 cm M3 Rp 275,000
2 Batu Gunung M2 Rp 150,000
Batu alam
Andesit Biasa M2 Rp 145,000
Andesit Susun Sirih M2 Rp 140,000
Andesit Halus M2 Rp 185,000
Andesit Gelombang M2 Rp 185,000
Batu Candi Permukaan Rata M2 Rp 140,000
Batu Palimanan Kuning M2 Rp 85,000
Batu Hijau Sukabumi M2 Rp 100,000
Batu Bali Green M2 Rp 185,000
Batu Bali Napoli M2 Rp 185,000
Paras Jokja Besar M2 Rp 120,000
Batu Cirebon Beraturan M2 Rp 120,000
Batu Cirebon Tidak Beraturan M2 Rp 90,000
3 Tanah Timbunan M3 Rp 80,000
4 Pasir
Timbunan / Urug M3 Rp 80,000
Pasangan M3 Rp 100,000
Beton M3 Rp 120,000
5 Kerikil M3 Rp 115,000
6 Sirtu M3 Rp 122,000
7 Kapur Pasangan Zak Rp 78,000
8 Semen PC (40 kg) Zak Rp 39,500
9 Semen Putih (50 kg) Zak Rp 48,000
10 Semen warna (5 kg) Zak Rp 15,000
11 Batu Merah Buah Rp 500
12 Paving Blok Mutu (K 175)
Tebal 6 cm M2 Rp 38,000
Tebal 8 cm M2 Rp 42,000
Berlian M2 Rp 45,000
13 Paving Blok Mutu (K 225)
Tebal 6 cm M2 Rp 44,500
Tebal 8 cm M2 Rp 46,000
14 Paving Blok Mutu (K 300)
Tebal 6 cm M2 Rp 48,000
Tebal 8 cm M2 Rp 50,000
15 Paving Blok Mutu (K 400) M2 Rp 60,000
Toppluskup (K 225) Biji Rp 3,500
Kanstin 10 x 25 x 50 Biji Rp 18,500
16 Buis Beton
d = 20 cm Biji Rp 50,000
d = 30 cm Biji Rp 75,000
d = 40 cm Biji Rp 150,000
d = 50 cm Biji Rp 200,000
d = 60 cm Biji Rp 250,000
BAHAN KAYU
Kayu Kelas I
Balok Gergaji Sawmil M3 Rp 7,300,000
Papan Gergaji Sawmil M3 Rp 7,400,000
Balok Gergaji Sansaw M3 Rp 6,300,000
Papan Gergaji Sansaw M3 Rp 6,400,000
Kayu Kelas II
Balok M3 Rp 3,300,000
Papan M3 Rp 3,600,000
Kayu Kelas III
Balok M3 Rp 1,850,000
Dolken/balok 5/7,4m btg Rp 28,000
Papan M3 Rp 2,100,000
BAHAN LANTAI
1 Tegel PC
PC abu-abu 20 x 20 cm Buah Rp 1,400
PC abu-abu 30 x 30 cm Buah Rp 2,500
PC warna 20 x 20 cm Buah Rp 2,600
PC Badak 20 x 20 cm Buah Rp 2,100
PC badak 30 x 30 cm Buah Rp 2,400
PC Wafel 20 x 20 cm Buah Rp 2,600
PC Wafel 30 x 30 cm Buah Rp 2,700
Plint PC 15 x 20 cm Buah Rp 2,000
Plint PC 15 x 30 cm Buah Rp 2,300
Tegel Mozaik 30 x 30 cm Buah Rp 3,200
2 Tegel Keramik
Putih 10 x 20 cm Dos Rp 42,000
Warna 10 x 20 cm Dos Rp 45,000
Putih 20 x 20 cm Dos Rp 42,500
Warna 20 x 20 cm Dos Rp 47,500
Putih 20 x 25 cm Dos Rp 43,000
Warna 20 x 25 cm Dos Rp 48,000
Putih 30 x 30 cm Dos Rp 45,000
Warna 30 x 30 cm Dos Rp 50,000
Putih 40 x 40 cm Dos Rp 48,000
Warna 40 x 40 cm Dos Rp 51,000
Warna 50 x 50 cm Dos Rp 53,000
Warna 60 x 50 cm Dos Rp 140,000
BAHAN KACA
Kaca Bening 3 mm M2 Rp 63,000
Kaca Buram 3 mm M2 Rp 130,000
Kaca Buram 5 mm M2 Rp 160,000
Kaca Ryben 3 mm M2 Rp 100,000
Kaca Ryben 5 mm M2 Rp 130,000
Rangka Nako Lengkap Terali Set / Daun Rp 52,000
BAHAN BESI
1 Besi Beton
d = 4 mm Btg Rp 16,300
d = 6 mm Btg Rp 20,900
d = 8 mm Btg Rp 38,000
d = 10 mm Btg Rp 57,500
d = 12 mm Btg Rp 77,000
d = 14 mm Btg Rp 105,000
d = 16 mm Btg Rp 138,000
d = 19 mm Btg Rp 195,000
d = 20 mm Btg Rp 224,000
2 Besi Ulir
d = 12 mm Btg Rp 75,000
d = 16 mm Btg Rp 135,000
d = 19 mm Btg Rp 275,000
3 Paku
Paku biasa Kg Rp 17,000
Paku Asbes Kg Rp 20,000
Paku Seng ( Payung ) RRT Kg Rp 18,000
Paku Scrub 3 1/2 inchi Kg Rp 17,000
Paku Scrub 4 inchi Kg Rp 19,000
Paku Payung Berulir 75 mm Kg Rp 25,000
Paku Sirap Kg Rp 18,500
Paku Beton Hitam Dos Rp 24,000
Paku Beton Putih Dos Rp 15,000
4 Kawat
Beton Kg Rp 19,000
Nyamuk M Rp 8,000
Ayakan Kecil M Rp 9,500
Duri Roll Rp 110,000
5 Besi Plat
2 mm = 120 x 240 mm Lmbr Rp 690,000
3 mm = 120 x 240 mm Lmbr Rp 750,000
Besi H 15 cm Panjang 12 m Btg Rp 3,700,000
6 Besi Strep
30.3 mm Btg Rp 17,500
35.4 mm Btg Rp 25,800
46.4 mm Btg Rp 27,800
40.6 mm Btg Rp 29,000
50.6 mm Btg Rp 37,000
7 Besi Siku
30. 30 .3 Btg Rp 43,000
40. 40. 4 Btg Rp 135,000
40. 40. 3 Btg Rp 60,000
50. 50. 4 Btg Rp 83,000
50. 50. 5 Btg Rp 95,000
60. 60. 6 Btg Rp 100,000
70. 70. 7 Btg Rp 140,000
8 Besi 6 mm M Rp 20,000
9 Besi type C (Rangka Baja Ringan
6 Meter)
Lebar 10, Tebal 1.8-2.00 mm Btg Rp 156,000
Lebar 12.5, Tebal 1.8-2.00 mm Btg Rp 131,000
Lebar 15, Tebal 1.8-2.00 mm Btg Rp 210,000
BAHAN PIPA
1 Pipa Besi GIP
∅ 1/2 inci - 6 m Btg Rp 95,000
∅ 3/4 inci - 6 m Btg Rp 120,000
∅ 1 inci - 6 m Btg Rp 185,000
∅ 2 inci - 6 m Btg Rp 395,000
∅ 2 1/2 inci - 6 m Btg Rp 475,000
∅ 3 inci - 6 m Btg Rp 575,000
2 Pipa PVC Air Bersih
∅ 1/2 inci - 4 m Btg Rp 11,500
∅ 3/4 inci - 6 m Btg Rp 22,500
∅ 1 inci - 6 m Btg Rp 28,900
∅ 1 1/2 inci - 6 m Btg Rp 59,500
∅ 2 inci - 6 m Btg Rp 95,000
∅ 2 1/2 inci - 6 m Btg Rp 130,000
∅ 3 inci - 6 m Btg Rp 190,000
∅ 4 inci - 6 m Btg Rp 245,000
∅ 6 inci - 6 m Btg Rp 595,000
∅ 8 inci - 6 m Btg Rp 900,000
∅ 10 inci - 6 m Btg Rp 1,400,000
3 Pipa Untuk Saluran Pembuangan Air
∅ 1/2 inci - 4 m Btg Rp 8,500
∅ 3/4 inci - 4 m Btg Rp 13,000
∅ 1 inci - 4 m Btg Rp 18,500
∅ 1 1/2 inci - 4 m Btg Rp 22,500
∅ 2 inci - 4 m Btg Rp 27,500
∅ 2 1/2 inci - 4 m Btg Rp 36,000
∅ 3 inci - 4 m Btg Rp 45,000
∅ 4 inci - 4 m Btg Rp 68,500
∅ 5 inci - 4 m Btg Rp 110,000
∅ 6 inci - 4 m Btg Rp 160,000
∅ 10 inci - 4 m Btg Rp 450,000
4 Pipa Untuk Instalasi Listrik
∅ 5/8 inci - 4 m Btg Rp 7,000
Ø3/4 inci - 4 m Btg Rp 22,000
Ø1 inci - 4 m Btg Rp 25,000
Ø1 1/2 inci - 4 m Btg Rp 44,500
BAHAN LANGIT-LANGIT
1 Eternit 100×100 Set Rp 15,000
2 Tripleks
122 × 244 ×0.2 cm Lmbr Rp 37,500
122 × 244 ×0.3 cm Lmbr Rp 47,500
122 × 244 ×0.6 cm Lmbr Rp 80,000
122 × 244 ×0.9 cm Lmbr Rp 125,000
3 Tripleks Melamin
122 × 244 ×0.3 cm Lmbr Rp 78,000
4 Accoustic 40 × 60 Lmbr Rp 45,000
5 Teakwood
80 × 224 × 0.3 cm Lmbr Rp 96,000
122 × 224 × 0.3 cm Lmbr Rp 80,000
6 Karsiboard Lmbr Rp 49,000
7 Gypsum Lmbr Rp 54,000
Les Gipsum Lmbr Rp 15,000
8 Hard Board 122 × 224 cm Lmbr Rp 75,000
9 Asbes Plat Harfeks
200 × 100 × 0.3 Lmbr Rp 42,000
10 List Profil
2 × 3 cm M' Rp 9,000
3 × 3 cm M' Rp 12,000
4 × 4 cm M' Rp 16,000
4 × 5 cm M' Rp 20,000
BAHAN ATAP
1 Genteng
Beton Biji Rp 2,700
Keramik Buah Rp 9,000
Asbes Gelombang 7 kaki Lmbr Rp 43,000
Harfles (115 × 85 × 0.5 cm) Lmbr Rp 51,000
2 Atap Metal Lmbr Rp 72,300
3 Asbes Genteng Lmbr Rp 19,000
4 Sirap Ikat Rp 24,000
5 Seng Gelombang kecil
BJLS 0.20 mm Kaki Rp 5,200
BJLS 0.22 mm Kaki Rp 5,300
BJLS 0.30 mm Kaki Rp 11,000
BJLS 0.35 mm Kaki Rp 12,000
6 Bitumen Gelombang (200 × 95 × 0.3 cm) Lmbr Rp 134,000
Bitumen Genteng (106 × 40 × 0.3 cm) Lmbr Rp 64,200
Nok Bitumen (50x90x0.3 cm) Lmbr Rp 81,200
7 Seng Plat
BJLS 0.30 mm Lmbr Rp 40,000
BJLS 0.35 mm Lmbr Rp 52,000
8 Seng Super Deck
180 x 70 cm - 10 kaki Kaki Rp 12,000
9 Seng Alumunium Gelombang
SWG 32" 0.27 mm Kaki Rp 7,000
SWG 30" 0.31 mm Kaki Rp 8,000
SWG 28" 0.38 mm Kaki Rp 9,000
10 Seng Plastik (Fiber) Kaki Rp 7,500
11 Fiber Semen (Harflex)
Super 240 x 108 x 0.6 cm Kaki Rp 63,000
Super 180 x 108 x 0.6 cm Kaki Rp 44,000
Ekonomi 240 x 92 x 0.5 cm Kaki Rp 49,000
Ekonomi 180 x 92 x 0.4 cm Kaki Rp 42,700
Mini 240 x 105 x 0.4 cm Kaki Rp 42,000
Mini 180 x 92 x 0.5 cm Kaki Rp 40,000
Super 240 x 105 x 0.4 cm Kaki Rp 50,500
Super 180 x 105 x 0.4 cm Kaki Rp 44,500
12 Nok/Bubungan
Genteng Beton Buah Rp 18,000
Genteng Asbes Buah Rp 20,000
Genteng Keramik Buah Rp 19,000
Alm. SWG 28" - 180 cm Lmbr Rp 46,500
Alm. SWG 28" - 105 cm Lmbr Rp 38,000
13 Nok Steel Gelombang
Super - 180 cm Buah Rp 32,000
Mini - 105 cm Buah Rp 24,000
Ekonomi - 95 cm Buah Rp 18,000
14 Nok Steel Gelombangteel Rata
Super - 180 cm Buah Rp 27,000
Mini - 105 cm Buah Rp 22,500
Ekonomi - 95 cm Buah Rp 22,500
15 Nok 1/2 Lingkaran Buah Rp 38,500
16 Karet Pelapis Genteng
Ukuran 55 M Rp 4,500
Ukuran 90 M Rp 6,500
BAHAN PENGGANTUNG
1 Kunci Tanam
1 Slag Buah Rp 126,500
Double Slag Buah Rp 227,000
2 Penggantung
Hak angin Kecil Buah Rp 9,000
Hak Angin Besar Buah Rp 14,000
Grendel Kecil Buah Rp 21,000
Grendel Besar Buah Rp 28,000
Engsel Pintu Buah Rp 28,000
Engsel Jendela Buah Rp 25,000
Expanyolet Buah Rp 110,000
BAHAN SANTER
1 Closet duduk Buah Rp 230,000
2 Closet Jongkok Buah Rp 429,000
3 Wasthafel Warna Buah Rp 260,000
4 Wasthafel CucI Piring Logam Buah Rp 180,000
5 Pompa Mesin Buah Rp 1,300,000
6 Urinoir Lengkap Buah Rp 1,900,000
7 Bak Mandi Fiber Buah Rp 260,000
8 Reservoir Fiber = 1 m3 Buah Rp 900,000
9 Reservoir Stainless stell = 1 m3 Buah Rp 2,750,000
10 Stop Kran Buah Rp 45,000
11 Kran Air Buah Rp 35,000
12 Seal Tape Buah Rp 2,500
BAHAN FINISHING/CAT
1 Cat Tembok
Cat Dasar ( kimex ) 5 kg Rp 35,000
plamur 5 kg Rp 26,000
Cat Kilap 5 kg Rp 75,000
2 Cat Kayu
Cat Dasar Kg Rp 30,000
Cat Kilap Kg Rp 33,000
Palatone Kg Rp 32,000
ICI Kg Rp 30,000
Politur Kg Rp 31,000
Meni 4 kg Rp 36,000
Minyak Cat Ltr Rp 18,000
3 Cat Atap
Cat Dasar Kg Rp 70,000
Cat Kilap
Lem Seng M Rp 13,000
Amplas/ Kertas Gosok Lmbr Rp 2,500
Dempul Kg Rp 20,000
Residu 10 ltr Rp 43,000
BAHAN INSTALASI LISTRIK
1 Kabel Listrik
Type NYA (full)
1 1/2 mm Roll Rp 220,000
2 1/2 mm Roll Rp 350,000
Type NYY
2x 1 1/2 mm Roll Rp 473,000
2x 2 1/2 mm Roll Rp 717,000
2x 4 mm Roll Rp 110,000
2 Lampu TL
1x20W Buah Rp 70,000
2x20W Buah Rp 85,000
1x40W Buah Rp 93,000
2x40W Buah Rp 120,000
3 Lampu pijar
25W Buah Rp 5,000
40W Buah Rp 6,000
60W Buah Rp 9,000
100W Buah Rp 9,500
4 Lampu Taman Mercury Buah Rp 320,000
5 Saklar Phase
Tunggal Putih Buah Rp 20,000
Tunggal Hitam Buah Rp 15,000
Double putih Buah Rp 13,000
Double Hitam Buah Rp 20,000
6 Stop kontak
Hitam Buah Rp 25,000
Putih Buah Rp 27,000
7 Zekering Kast Lokal Biasa
Lokal 2 Group Automat Buah Rp 75,000
Lokal 3 Group Biasa Buah Rp 85,000
Fitting Buah Rp 10,000
BAHAN JALAN
Aspal Kg Rp 10,000
1 Minyak Tanah Ltr Rp 4,500
2 Minyak Solar Ltr Rp 5,500
3 Minyak Pelumas Ltr Rp 25,000
UPAH KERJA
Pekerja Org/hr Rp 35,000
Buruh Org/hr Rp 35,000
1 Pembantu Masinis Org/hr Rp 35,000
2 Penjaga Gudang Org/hr Rp 35,000
3 Penjaga Malam Org/hr Rp 35,000
Tukang :
1 Tukang Kayu Org/hr Rp 50,000
2 Tukang Batu Org/hr Rp 50,000
3 Tukang Cat Org/hr Rp 50,000
4 Tukang Listrik Org/hr Rp 50,000
5 Tukang Pipa Org/hr Rp 50,000
6 Tukang Besi Org/hr Rp 50,000
Kepala Tukang
1 Kepala Tukang Kayu Org/hr Rp 55,000
2 Kepala Tukang Batu Org/hr Rp 55,000
3 Kepala Tukang Listrik Org/hr Rp 55,000
4 Kepala Tukang Cat Org/hr Rp 55,000
5 Kepala Tukang Pipa Org/hr Rp 55,000
6 Kepala Tukang Besi Org/hr Rp 55,000
7 Mandor Org/hr Rp 60,000
Bobot
Kegiatan pekerjaan bagian sub. Bagian
1 Pekerjaan Persiapan
a 1 Pembersihan lapangan 1.0459
2 Memasang bouwplank 1.50 0.4532

1 Galian tanah pondasi 9.4794


Pekerjaan Tanah dan pasir 2 Urugan Kembali galian 35.24 15.31 0.4929
b 3 timbunan tanah bawah lantai 1.6461
4 Pasir urug bawah lantai 1.3841
5 Pasir urug bawah pondasi 2.3069

1 Pas.pondasi batu kali 18.43 15.5907


Pasangan Pondasi Batu kali 2 pek.pas batu kosong 2.8395
c
1 Beton sloef 4.5522
2 Pekerjaan Beton 3 pek.kolom 17.01 4.5522
a 4 pek. Ring balk 5.2351
5 pek. Rabat beton bawah lantai 2.4456
6 pek. Rabat beton carport 0.2223

1 Pek. Dinding 1 : 5 5.5145


3 Pekerjaan Tembok dan lantai 2 pek. Plesteran 1 : 3 0.7729
a 3 pek. Acian 13.82 2.6713
4 pek. Dinding keramik wc 20X20 0.5343
5 pek. Lantai keramik 40x 40 2.1739
6 pek. Lantai keramik 30x30 2.1559

1 pek. Kusen pintu dan jendela 7.1137


4 pekerjaan Pintu Dan Jendela 2 pek. Daun pintu 5.2381
a 3 pek. Kaca mati 0.3339
5 pas. Kunci tanam 13.55 0.3937
6 pas. Engsel pintu 0.4709

1 pek. Kuda-kuda 4.6431


5 Pekerjaan Atap dan plafon 2 pek. Gording dan Balok nok 3.2211
a 3 pek. Skor angin 0.4183
4 pek. Kaso + reng 0.0089
5 pek. Atap genteng 11.66 1.5820
6 pek. Nok atap genteng 1.6539
7 pek. Rangka plafond 0.0726
8 pek. Plafond 0.7996
9 pek. Listplank 0.8696

1 pek.pengecetan tembok 0.5604


6 Pekerjaan Pengecetan 2 pek. Cat kusen, pintu dan jendela 0.5308
a 3 pek. Pengecetan plafond 3.41 2.0174
4 pek. Pengecetan listplank 0.2973

1 Pas. Saklar Ganda 0.0320


7 Pekerjaan instalasi listrik 2 Pas. Saklar Tunggal 0.0182
a 3 Pas. Stop Kontak 0.18 0.1131
4 Pas. Lampu Hias 0.0050
5 Pas. Lampu Pijar 40 Watt 0.0100
6 Pas.Lampu Pijar 20 watt 0.0061

1 Pek. Stop Kran 0.0325


8 Pekerjaan Sanitasi 2 Pek. Pipa 3/4 ' 0.0529
a 3 Pek. Pipa PVC 4" 0.2997
4 Pas. Kloset Duduk 4.46 0.9952
5 Pek. Bak Cuci Piring 0.8451
6 Bak Air Fiber 0.7405
7 Floor Drain 0.0400
8 Pek. Septiktank 1.4526
JUMLAH 99.33
PERHITUNGAN BOBOT PEKERJAAN

Persentase
No. URAIAN
Bobot Pekerjaan (%)
I.1a Pembersihan Lapangan
Volume = 90.00 m3
Harga Satuan = 20,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan


x 100%
Harga Bangunan
= 90.00 x 20,000
x 100%
172105950.33
= 0.01045867 x 100 % = 1.046

1b Memasang Bowplank
Volume = 39.00 m3
Harga Satuan = 20,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan


x 100%
Harga Bangunan
= 39.0 x 20,000
x 100%
172105950.33
= 0.00453209 x 100 % = 0.453209

2a Galian Tanah Pondasi


Volume = 114.00 m3
Harga Satuan = 143,110.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan


x 100%
Harga Bangunan
= 114.000 x 143,110
x 100%
172105950.33
= 0.09479358 x 100 % = 9.48

2b Urugan Kembali 1/4 galian


Volume = 28.500 m3
Harga Satuan = 29,766.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 28.500 x 29,766 x 100%
172105950.33
= 0.00492912 x 100 % = 0.49

2c Timbunan Tanah Bawah Lantai


Volume = 9.065 m3
Harga Satuan = 312,532.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 9.065 x 312,532 x 100%
172105950.33
= 0.01646129 x 100 % = 1.65

2d Urugan Pasir bawah lantai


Volume = 7.457 m3
Harga Satuan = 319,440.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 7.457 x 319,440 x 100%
172105950.33
= 0.01384055 x 100 % = 1.38

2d Urugan Pasir bawah Pondasi


Volume = 11.761 m3
Harga Satuan = 337,590.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 11.761 x 337,590 x 100%
172105950.33
= 0.02306949 x 100 % = 2.31

3c Pasangan Pondasi Batu Kali 1:5


Volume = 20.000 m3
Harga Satuan = 1,341,623.25
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 20.000 x 1,341,623 x 100%
172105950.33
= 0.15591 x 100 % = 15.59
3a Pasangan Batu Kosong
Volume = 10.000 m3
Harga Satuan = 488,687.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 488,687 x 100%
172105950.33
= 0.02839454 x 100 % = 2.84

35.24

II.1a Beton Sloof


Volume = 2.000 m3
Harga Satuan = 3,917,325
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan

= 2.000 x 3,917,325 x 100%


172105950.33
= 0.04552225 x 100 % = 4.55

1b Kolom
Volume = 2.000 m3
Harga Satuan = 3,917,325.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 3,917,325 x 100%
172105950.33
= 0.04552225 x 100 % = 4.55

1c Ring Balk
Volume = 2.300 m3
Harga Satuan = 3,917,325.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.300 x 3,917,325 x 100%
172105950.33
= 0.05235059 x 100 % = 5.24

1d Rabat Beton Bawah Lantai


Volume = 3.300 m3
Harga Satuan = 1,275,446
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 3.300 x 1,275,446 x 100%
172105950.33 ---------
= 0.02445569 x 100 % = 2.446

1e Rabat Beton Carport


Volume = 0.300 m3
Harga Satuan = 1,275,446
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.300 x 1,275,446 x 100%
172105950.33
= 0.00222324 x 100 % = 0.222

2b Pas. Dinding 1:5


Volume = 20.000 m3
Harga Satuan = 474,536
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 20.000 x 474,536 x 100%
172105950.33
= 0.05514462 x 100 % = 5.51

2a Pas. Dinding 1:3


Volume = 10.000 m3
Harga Satuan = 133,027
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 133,027 x 100%
172105950.33
= 0.00772939 x 100 % = 0.773

2c pek. Acian
Volume = 10.000 m3
Harga Satuan = 459,745
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 459,745 x 100%
172105950.33
= 0.02671292 x 100 % = 2.67

2f Pas.Dinding Keramik 20 X 20 cm (KM/WC)


Volume = 2.00 m3
Harga Satuan = 459,745
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 459,745 x 100%
172105950.33
= 0.00534258 x 100 % = 0.53

2d Pas.Lantai Keramik 40X40 cm


Volume = 10.00 m3
Harga Satuan = 374,149
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 374,149 x 100%
172105950.33
= 0.02173948 x 100 % = 2.17

2e Pas.Lantai Keramik 30 X 30 cm
Volume = 10.00 m3
Harga Satuan = 371,044
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 371,044 x 100%
172105950.33
= 0.02155902 x 100 % = 2.16

30.83

III.1a Kusen Pintu dan Jendela


Volume = 0.706 m3
Harga Satuan = 17,347,605
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.706 x 17,347,605 x 100%
172105950.33
= 0.07113683 x 100 % = 7.114
1b Daun Pintu kls 1
Volume = 5.00 m3
Harga Satuan = 1,803,016
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 5.000 x 1,803,016 x 100%
172105950.33
= 0.05238098 x 100 % = 5.24

1c Pas. Kaca Mati


Volume = 2.00 m3
Harga Satuan = 287,293
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 287,293 x 100%
172105950.33
= 0.00333855 x 100 % = 0.333855

1d Pas. Kunci tanam


Volume = 5 buah
Harga Satuan = 135,520
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 5.000 x 135,520 x 100%
172105950.33
= 0.00393711 x 100 % = 0.394

1f Pas. Engsel Pintu Standar 4 inci


Volume = 10 buah
Harga Satuan = 81,048
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 81,048 x 100%
172105950.33
= 0.00470919 x 100 % = 0.47092

IV.1a Pas. Kuda-kuda


Volume = 0.488 m3
Harga Satuan = 16,362,621
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.488 x 16,362,621 x 100%
172105950.33
= 0.04643135 x 100 % = 4.64

1b Pas. Gording dan Balok Nok


Volume = 0.277 m3
Harga Satuan = 19,999,232
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.277 x 19,999,232 x 100%
172105950.33
= 0.03221148 x 100 % = 3.22

1c Pek. Skor angin


Volume = 0.072 m3
Harga Satuan = 9,999,616
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.072 x 9,999,616 x 100%
172105950.33
= 0.00418331 x 100 % = 0.42

1d Pas. Rangka Atap Kaso 5/7 dan Reng 3/4


Volume = 0.085 m3
Harga Satuan = 181,798
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.085 x 181,798 x 100%
172105950.33
= 0.00008931 x 100 % = 0.008931

1e Pas. Atap Genteng


Volume = 7.500 m3
Harga Satuan = 363,023
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 7.500 x 363,023 x 100%
172105950.33
= 0.01581975 x 100 % = 1.58

1f Pas. Nok Genteng


Volume = 16.0 m3
Harga Satuan = 177,909
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 16.000 x 177,909 x 100%
172105950.33
= 0.01653944 x 100 % = 1.65

1g Rangka Plafond Dalam


Volume = 0.18 m3
Harga Satuan = 689,663
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 0.181 x 689,663 x 100%
172105950.33
= 0.00072628 x 100 % = 0.07

1h Pas. Plafond
Volume = 6.98 m2
Harga Satuan = 197,300
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 6.975 x 197,300 x 100%
172105950.33
= 0.00799606 x 100 % = 0.80

1i pek. Listplank
Volume = 13.200 m2
Harga Satuan = 113,377
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 13.200 x 113,377 x 100%
172105950.33
= 0.00869567 x 100 % = 0.87
13.269
1a Pengecetan Dinding Dengan Cat Tembok
Volume = 10.000 m2
Harga Satuan = 96,448
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 96,448 x 100%
172105950.33
= 0.00560399 x 100 % = 0.560399

1b PengecetanPlafond
Volume = 36.000 m3
Harga Satuan = 96,448
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 36.000 x 96,448 x 100%
172105950.33
= 0.02017436 x 100 % = 2.02

1c Pengecetan Lisplank Dengan Cat Minyak


Volume = 10.000 m3
Harga Satuan = 51,165
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 10.000 x 51,165 x 100%
172105950.33
= 0.00297287 x 100 % = 0.29729

1d Pengecetan Kusen,pintu dan jendela Dengan Cat Minyak


Volume = 17.855 m3
Harga Satuan = 51,165
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 17.855 x 51,165 x 100%
172105950.33
= 0.00530817 x 100 % = 0.530817

3.41

1e Sakelar ganda
Volume = 2 ttk
Harga Satuan = 27,500.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 27,500 x 100%
172105950.33
= 0.00031957 x 100 % = 0.03

1h Sakelar tunggal
Volume = 3 ttk
Harga Satuan = 10,450.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 3.000 x 10,450 x 100%
172105950.33
= 0.00018216 x 100 % = 0.02

1d Stop Kontak
Volume = 5 ttk
Harga Satuan = 38,940
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 5.000 x 38,940 x 100%
172105950.33
= 0.00113128 x 100 % = 0.11

1c Pas. Lampu Hias


Volume = 1 ttk
Harga Satuan = 100,000
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 1.000 x 100,000 x 100%
172105950.33
= 0.00058104 x 100 % = 0.06

1f Pas.lampu Pijar 40 watt


Volume = 6 ttk
Harga Satuan = 45,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 6.000 x 45,000 x 100%
172105950.33
= 0.00156880 x 100 % = 0.16
1g Pas.lampu Pijar 20 watt
Volume = 1 ttk
Harga Satuan = 10,450.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 1.000 x 10,450 x 100%
172105950.33
= 0.00006072 x 100 % = 0.01
0.38

2e Kran
Volume = 2 bh
Harga Satuan = 28,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 28,000 x 100%
172105950.33
= 0.00032538 x 100 % = 0.03

2c Pemasangan Instalasi Air Bersih (pipa galvanis)


Volume = 2.000 m3
Harga Satuan = 45,540.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 45,540 x 100%
172105950.33
= 0.00052921 x 100 % = 0.05

2d Pemasangan Instalasi Air Kotor (pvc)


Volume = 3.000 m3
Harga Satuan = 171,930.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 3.000 x 171,930 x 100%
172105950.33
= 0.00299693 x 100 % = 0.30

2b Kloset Duduk
Volume = 1 bh
Harga Satuan = 1,712,832.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 1.000 x 1,712,832 x 100%
172105950.33
= 0.00995220 x 100 % = 1.00

2f Pek.bak Cuci piring


Volume = 1 bh
Harga Satuan = 1,454,466.20
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 1.000 x 1,454,466 x 100%
172105950.33
= 0.00845099 x 100 % = 0.85

2a Bak Mandi Fiber


Volume = 2 bh
Harga Satuan = 637,230.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 2.000 x 637,230 x 100%
172105950.33
= 0.00740509 x 100 % = 0.74

2f Flour Drain
Volume = 5 bh
Harga Satuan = 30,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 5.000 x 30,000 x 100%
172105950.33
= 0.00087156 x 100 % = 0.087156

1d Septick Tank
Volume = 1 bh
Harga Satuan = 2,500,000.00
Harga Bangunan = 172,105,950.33

PBP = Volume x Harga satuan x 100%


Harga Bangunan
= 1.000 x 2,500,000 x 100%
172105950.33
= 0.01452594 x 100 % = 1.45
4.51

35.24
JADWAL WAKTU PELAKSANAAN ( TIME SCHEDULE )

NILAI WAKTU PELAKSANAAN NILAI


NO. URAIAN PEKERJAAN BOBOT BULAN I BULAN II BULAN III BULAN IV KURVA KET.
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 (%)

I. PEKERJAAN PERSIAPAN 1.50 1.50 100% 112 Hari


Masa Pelaksanaan
II. PEKERJAAN TANAH DAN PASIR 15.31 5.10 5.10 5.10 10.21
120 Hari
III. PEKERJAAN PONDASI 18.43 3.69 3.69 3.69 3.69 3.69 Masa Pemeliharaan
75%
IV. PEKERJAAN BETON 17.01 2.83 2.83 2.83 2.83 2.83 2.83

V. PEKERJAAN TEMBOK DAN LANTAI 13.82 2.76 2.76 2.76 2.76 2.76

VI. PEKERJAAN PINTU DAN JENDELA 13.55 4.52 4.52 4.52 50%

VII. PEKERJAAN ATAP DAN PLAFOND 11.66 3.89 3.89 3.89

VIII. PEKERJAAN PENGECATAN 4.13 2.07 2.07 25%

IX. PEKERJAAN INSTALASI LISTRIK 0.17 0.08 0.08

X. PEKERJAAN SANITASI 4.42 2.21 2.21 0%

JUMLAH BOBOT 100.00


RENCANA KEMAJUAN PEKERJAAN (%) 1.50 5.10 5.10 8.79 6.52 6.52 9.29 9.29 5.60 10.12 11.17 8.40 5.95 2.15 2.29 2.21
KOMULATIF KEMAJUAN PEKERJAAN (%) 1.50 6.60 11.71 20.49 27.02 33.54 42.82 52.11 57.71 67.82 78.99 87.39 93.34 95.50 97.79 100.00
RENCANA KEMAJUAN PEKERJAAN
KOMULATIF KEMAJUAN PEKERJAAN
DEVIASI

langkah2 membuat kurva S bobot = harga per item pek.


1 menghitung bobot pekerjaan harga total x 100%

2 membagi bobot trhdp durasi pelaksanaan pekerjaan


3 menjumlahkan kemajuan pkrjaan per minggu
4 menghitung kumulatif
REKAPITULASI RENCANA ANGGARAN BIAYA
PERUMAHAN MARIO RESIDENCE TYPE 45

NO. URAIAN JENIS PEKERJAAN JUMLAH HARGA


(a) (b) (c)

I PEKERJAAN PERSIAPAN Rp 2,580,000.00


II PEKERJAAN TANAH DAN PASIR Rp 26,348,394.10
III PEKERJAAN PONDASI Rp 31,719,335.00
IV PEKERJAAN BETON Rp 29,270,751.30
V PEKERJAAN TEMBOK DAN LANTAI Rp 23,789,863.38
VI PEKERJAAN PINTU DAN JENDELA Rp 23,320,814.73
VII PEKERJAAN ATAP DAN PLAFOND Rp 20,065,302.05
VIII PEKERJAAN PENGECATAN Rp 7,115,361.57
IX PEKERJAAN INSTALASI LISTRIK Rp 291,500.00
X PEKERJAAN SANITASI Rp 7,604,628.20

REAL COST Rp 172,105,950.33


PPN 10% Rp 17,210,595.03
JUMLAH Rp 189,316,545.36
DIBULATKAN Rp 217,124,000.00
jadi, harga per- m2 = Real Cost : 45 Luas bangunan) = Rp 3,824,576.67
Terbilang :

DUA RATUS TUJUH BELAS JUTA SERATUS DUA PULUH EMPAT RIBU RUPIAH

Anda mungkin juga menyukai